Higgins v. United States , 589 F. App'x 977 ( 2014 )


Menu:
  •        NOTE: This disposition is nonprecedential.
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    CHERYL HIGGINS,
    Plaintiff-Appellant,
    v.
    UNITED STATES,
    Defendant-Appellee.
    ______________________
    2014-5025
    ______________________
    Appeal from the United States Court of Federal
    Claims in No. 1:12-cv-00922-EJD, Judge Edward J.
    Damich.
    ______________________
    Decided: October 14, 2014
    ______________________
    CHERYL HIGGINS, of Bowie, Maryland, pro se.
    DOUGLAS T. HOFFMAN, Trial Attorney, Commercial
    Litigation Branch, Civil Division, United States Depart-
    ment of Justice, of Washington, DC, for defendant-
    appellee. With him on the brief were STUART F. DELERY,
    Assistant Attorney General, ROBERT E. KIRSCHMAN, JR.,
    Director, and MARTIN F. HOCKEY, JR., Assistant Director.
    ______________________
    2                                             HIGGINS   v. US
    Before LOURIE, PLAGER, and WALLACH, Circuit Judges.
    PER CURIAM.
    Cheryl Higgins (“Higgins”) appeals from the decision
    of the United States Court of Federal Claims (the “Claims
    Court”) dismissing two of her claims as beyond the six-
    year statute of limitations and granting summary judg-
    ment in favor of the government on the third and remain-
    ing claim. See Higgins v. United States, No. 12-922C
    (Fed. Cl. Oct. 9, 2013) (“Opinion”). Because the Claims
    Court did not err in holding that it lacked jurisdiction
    over Higgins’ first two claims and in granting summary
    judgment on the third claim, we affirm.
    BACKGROUND
    The United States Department of Labor (“DOL”)
    awarded a grant in September 1999 to Devereaux Corpo-
    ration (“Devereaux”), of which Higgins was the executive
    director. Id. at 2. The grant was for about $3 million, to
    be paid over a period of three years. Id. Months later, a
    DOL grant officer submitted a proposal to terminate the
    grant for “material failure to comply with the terms and
    conditions of a grant award” under 
    29 C.F.R. § 95.61
    (a)(1).
    
    Id.
     After considering Devereaux’s response, DOL issued a
    Final Determination to terminate the grant. 
    Id.
    Devereaux submitted to the DOL Office of Adminis-
    trative Law Judges (“ALJ Office”) a request for a hearing
    to review the Final Determination. 
    Id. at 3
    . The ALJ
    Office issued a prehearing order requesting information
    from both parties. 
    Id.
     Devereaux failed to comply, de-
    spite a show cause order, and the ALJ Office entered a
    default judgment in May 2001. 
    Id.
    After negotiations with Higgins, DOL prepared a
    Modification of the grant award to effectuate the termina-
    tion by reducing the award amount and changing the
    expiration date to September 2000. 
    Id.
     On October 24,
    2001, Higgins and DOL signed the Modification, which
    HIGGINS   v. US                                        3
    was effective at execution, and the remainder of the
    negotiated amount was paid to Devereaux. Appellee’s
    App. 28, 38, 42. In May 2002, DOL officially closed the
    grant based on that settlement and payment. 
    Id. at 42
    .
    DOL subsequently sent closeout documents to
    Devereaux, but they were returned in the mail as unde-
    liverable. Opinion at 3. After being notified that the
    corporation was defunct, DOL executed a unilateral
    closeout on May 12, 2004, adopting the terms of the
    Modification. DOL then sent a preliminary settlement
    notice to Higgins on May 26, 2004 (“Settlement Notice”).
    
    Id.
     The Settlement Notice contained a paragraph that
    described certain situations in which further payment
    adjustments might be made for an amended settlement,
    including “[u]nresolved disputes or claims identified on
    the Grantee’s Release.” 
    Id.
    In November 2005, Higgins sent a letter requesting
    over $1.5 million from the grant for reimbursement of
    various outstanding claims incurred by Devereaux.
    Opinion at 3. In February 2006, DOL responded with a
    letter stating that the grant had been closed out and no
    further funds were owed to Devereaux. Appellee’s App.
    36–38. That letter noted the various documents and
    events concerning the grant termination and closure,
    including the Final Determination, the ALJ Office’s
    default judgment, and the Modification signed by both
    parties in October 2001. Moreover, the letter elaborated
    that the legislative authorization for the grant program
    had lapsed and that no additional funding was available.
    DOL and Higgins later had an in-person meeting and
    further written correspondence, in which DOL reiterated
    that the grant had been terminated, the Modification
    signed by Higgins reflected a negotiated settlement, the
    grant had been officially closed based on that settlement
    and payment of agreed costs, and no additional funds
    were available. Opinion at 3; Appellee’s App. 42.
    4                                             HIGGINS   v. US
    In October 2008, in response to another inquiry from
    Higgins, DOL sent a letter stating that the grant was
    terminated in accordance with 
    29 C.F.R. § 95.61
    (a)(2).
    Opinion at 3.
    On December 28, 2012, Higgins filed suit against the
    government in the Claims Court alleging a breach of
    contract or, alternatively, entitlement to an amended
    settlement according to the Settlement Notice or a final
    settlement under § 95.61(a)(2). The court found that the
    breach of contract claim accrued on May 12, 2004, when
    DOL unilaterally closed out the grant. Id. at 4. Similar-
    ly, the court found that the amended-settlement claim
    accrued on May 26, 2004, when DOL sent the Settlement
    Notice. Id. at 6. The court also found that the termina-
    tion occurred under § 95.61(a)(1) instead of § 95.61(a)(2).
    Id. at 5–6. The court thus dismissed the breach of con-
    tract claim and the amended-settlement claim as beyond
    the six-year statute of limitations, and granted summary
    judgment in favor of the government on the final-
    settlement claim as arising under an inapplicable statuto-
    ry provision. Id. at 7.
    Higgins appealed to this court. We have jurisdiction
    pursuant to 
    28 U.S.C. § 1295
    (a)(3).
    DISCUSSION
    We review the Claims Court’s dismissal for lack of ju-
    risdiction de novo. FloorPro, Inc. v. United States, 
    680 F.3d 1377
    , 1380 (Fed. Cir. 2012). We also review the
    grant of summary judgment de novo. Holland v. United
    States, 
    621 F.3d 1366
    , 1374 (Fed. Cir. 2010).
    I. Claims Dismissed for Lack of Jurisdiction
    A claim against the government must be filed within
    six years after the claim first accrues. 
    28 U.S.C. § 2501
    ;
    Martinez v. United States, 
    333 F.3d 1295
    , 1304 (Fed. Cir.
    2003) (en banc). A claim accrues for purposes of the
    statute of limitations “when all the events have occurred
    HIGGINS   v. US                                          5
    which fix the liability of the Government and entitle the
    claimant to institute an action.” FloorPro, 
    680 F.3d at 1381
     (citation omitted). “The question of whether the
    pertinent events have occurred is determined under an
    objective standard; a plaintiff does not have to possess
    actual knowledge of all the relevant facts in order for the
    cause of action to accrue.” Fallini v. United States, 
    56 F.3d 1378
    , 1380 (Fed. Cir. 1995). The six-year statute of
    limitations is “jurisdictional” and thus is not subject to
    equitable tolling. John R. Sand & Gravel Co. v. United
    States, 
    552 U.S. 130
    , 134–39 (2008).
    A. The Breach of Contract Claim
    Higgins argues that her breach of contract claim did
    not accrue until 2012, when “a certain federal official”
    revealed to her that the grant termination “was not a true
    termination,” or until 2013, when she learned about the
    undelivered closeout documents. Appellant’s Br. 4–5.
    She also asserts that equitable tolling should apply be-
    cause she has pursued several remedies in good faith.
    The government responds that the events in 2012 and
    2013 are irrelevant to a determination whether Higgins
    had filed her complaint within the statute of limitations
    period. The government asserts that “all events required
    to assert a claim for unpaid, but due and owing grant
    money” had occurred when the Modification was signed in
    2001. Appellee’s Br. 9. The government contends that
    even if Higgins’ reimbursement request in November
    2005 were considered an event necessary to assert the
    claim, the February 2006 letter rejecting the request
    would be the latest event to start the clock, which still
    puts the claim beyond the six-year period. The govern-
    ment argues that Higgins’ pursuit of other remedies does
    not affect when the events necessary to assert the claim
    all occurred.
    We agree with the government that the Claims Court
    lacked jurisdiction over the breach of contract claim
    6                                             HIGGINS   v. US
    because the claim first accrued more than six years before
    Higgins filed her complaint.
    The breach of contract claim arises from the grant
    award from DOL to Devereaux. The Claims Court found
    that May 12, 2004, the date when DOL executed the
    unilateral closeout, was the “latest date upon which a
    contractual claim could conceivably be seen to arise.”
    Opinion at 4. Higgins fails to identify a date subsequent
    to that date that would have given rise to a breach of
    contract claim, considering the contract in question had
    been terminated, amended to expire, officially closed, and
    then finally processed for closeout. Because the six-year
    statute of limitations is jurisdictional, equitable tolling
    exceptions do not apply. We therefore hold that the
    Claims Court did not err in finding that May 12, 2004,
    was objectively the latest possible date that the breach of
    contract claim first accrued.
    B. The Amended-Settlement Claim
    Higgins argues that because a grantee’s release was
    never executed, she was unable to formally communicate
    the disputed claim. She asserts that she thus is entitled
    to an amended settlement. The government responds
    that regardless whether a grantee’s release was executed,
    the amended-settlement claim accrued on May 26, 2004,
    because the claim arose from the Settlement Notice.
    We agree with the government that the Claims Court
    also lacked jurisdiction over the amended-settlement
    claim because that claim first accrued more than six years
    before Higgins filed her complaint.
    The amended-settlement claim stems from the Set-
    tlement Notice dated May 26, 2004. The only contingency
    that Higgins claims to apply in her case is for
    “[u]nresolved disputes or claims identified on the Grant-
    ee’s Release.” Appellant’s Br. 9–10; Opinion at 6. While
    Higgins repeatedly insists that every grantee is entitled
    HIGGINS   v. US                                           7
    to a release, she has provided no statutory or regulatory
    basis for that entitlement. Regardless whether a release
    would have been procedurally proper for a closeout,
    Higgins was on notice of that contingency through the
    Settlement Notice and she knew that she did not possess
    a grantee’s release. We therefore hold that the Claims
    Court did not err in finding that the amended-settlement
    claim first accrued on May 26, 2004.
    For the Claims Court to have jurisdiction, Higgins’
    claims must have first accrued by December 28, 2006: six
    years before she filed her complaint. Martinez, 
    333 F.3d at 1304
    . To challenge the grant termination or the avail-
    ability of an amended settlement, Higgins should have
    filed suit before the statute of limitations expired. Be-
    cause we agree with the Claims Court’s findings that the
    clock began running no later than May 2004 for both the
    breach of contract and amended-settlement claims, we
    hold that the Claims Court did not err in dismissing those
    claims for lack of jurisdiction.
    II. The Summary Judgment
    “The court shall grant summary judgment if the mo-
    vant shows that there is no genuine dispute as to any
    material fact and the movant is entitled to judgment as a
    matter of law.” RCFC 56(a). In determining whether
    there are genuine issues of material fact, “[t]he evidence
    of the nonmovant is to be believed, and all justifiable
    inferences are to be drawn in his favor.” Anderson v.
    Liberty Lobby, Inc., 
    477 U.S. 242
    , 255 (1986).
    Higgins argues that she is entitled to a final settle-
    ment because DOL converted the unilateral termination
    under § 95.61(a)(1) to a mutual termination under
    § 95.61(a)(2), as evidenced by the October 2008 letter.
    The government responds that the Claims Court explicitly
    considered the October 2008 letter when finding no genu-
    ine issue of material fact because the letter did not change
    the original basis for the termination. The government
    8                                              HIGGINS   v. US
    also argues that the Claims Court found that both the
    Final Determination and the ALJ Office’s default judg-
    ment specifically referenced § 95.61(a)(1).
    We agree with the government that the October 2008
    letter did not change the original basis for the termina-
    tion of the grant. The documents contemporaneous with
    the termination refer specifically to § 95.61(a)(1). The
    October 2008 letter was sent more than seven years after
    the grant was terminated. It does not state that DOL
    converted the termination, much less imply that a final
    settlement was to follow. While the two letters that
    Higgins submitted in support of such an interpretation do
    in fact reference conversations with DOL about changing
    the basis for the termination to “for convenience” instead
    of “from default” (i.e., under § 95.61(a)(2) instead of
    § 95.61(a)(1)), neither of those letters refers to her claim
    for a final settlement. See Reply App. A. Instead, she
    stated that a DOL letter reflecting the change “will great-
    ly assist [her] in responding to future RFP’s.” Id. The
    justifiable inference is, at best, that the October 2008
    letter nominally changed the termination to one under
    § 95.61(a)(2) such that Higgins could more easily submit
    future grant proposals. Even believing Higgins’ evidence,
    that letter does not change the original basis for the grant
    termination, and Higgins thus is not entitled to a final
    settlement. We therefore agree with the Claims Court’s
    holding that the government was entitled to summary
    judgment on the final-settlement claim.
    CONCLUSION
    We have considered Higgins’ remaining arguments
    and conclude that they are without merit. For the forego-
    ing reasons, the decision of the Claims Court is affirmed.
    AFFIRMED