Sheridan Transportation v. Gsa , 651 F. App'x 987 ( 2016 )


Menu:
  •        NOTE: This disposition is nonprecedential.
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    SHERIDAN TRANSPORTATION SYSTEMS, INC.,
    Appellant
    v.
    GENERAL SERVICES ADMINISTRATION, ERIC K.
    FANNING, SECRETARY OF THE ARMY,
    Appellees
    ______________________
    2015-1858
    ______________________
    Appeal from the Civilian Board of Contract Appeals in
    No. 4071-RATE, Administrative Judge Stephen M. Dan-
    iels.
    ______________________
    Decided: June 9, 2016
    ______________________
    EARL E. CLOUD, Huntsville, AL, argued for appellant.
    Also represented by JOHN ELGIN MCCULLEY, John E.
    McCulley, P.C., Tuscaloosa, AL.
    MARK E. PORADA, Commercial Litigation Branch, Civil
    Division, United States Department of Justice, Washing-
    ton, DC, argued for appellees. Also represented by
    DEBORAH A. BYNUM, ROBERT E. KIRSCHMAN, JR.,
    BENJAMIN C. MIZER.
    2                          SHERIDAN TRANSPORTATION     v. GSA
    ______________________
    Before DYK, PLAGER, and TARANTO, Circuit Judges.
    PER CURIAM.
    This case involves a contract dispute between the gov-
    ernment and Sheridan Transportation Systems, Inc., a
    private trucking company the government hired to
    transport emergency supplies to potential hurricane
    areas. As relevant here, Sheridan delivered supplies to
    the government in two trailers in September 2008. Not
    until July 6, 2012, however, did the government notify
    Sheridan that the trailers were available to be picked up.
    In May 2013, Sheridan submitted invoices for payment
    for that entire period based on the daily rate specified in a
    contract provision addressing “detention” for a period
    needed for the government to unload the trailers. Sheri-
    dan and the government have consistently treated the
    claims as filed under a provision of the Transportation
    Act, 31 U.S.C. § 3726. The government—both the agency
    contracting officer and a dispute-resolutions officer of the
    General Services Administration—rejected Sheridan’s
    claims as untimely under § 3726(c)(2), which required this
    claim to be received by the government no more than 3
    years after the claim accrued.
    Sheridan appealed to the Civilian Board of Contract
    Appeals pursuant to 31 U.S.C. § 3726(i)(1) and a regulato-
    ry delegation to the Board by the Administrator of Gen-
    eral Services, 41 C.F.R. § 102-118.490(a). See 31 U.S.C.
    § 3726(g) (authorizing such delegation). Before the Board,
    Sheridan presented no claim except the claim for payment
    of the contract “detention” rate, and Sheridan did not
    dispute that the claim was a Transportation Act claim
    subject to 31 U.S.C. § 3726. The Board held the claim to
    be untimely. J.A. 1–8.
    Sheridan appealed to this court, invoking our jurisdic-
    tion under 28 U.S.C. § 1295(a)(10) to hear “an appeal from
    SHERIDAN TRANSPORTATION   v. GSA                          3
    a final decision of an agency board of contract appeals
    pursuant to” 41 U.S.C. § 7107(a)(1), a provision of the
    Contract Disputes Act. The government did not contest
    this court’s jurisdiction until after briefing and argument.
    It has now done so. We agree that we lack jurisdiction.
    Under an earlier codification of the Contract Disputes
    Act, we held that not all Board decisions, but only Board
    decisions on contract claims covered by the Contract
    Disputes Act, are within (what is now) section 7107(a)(1)’s
    reference to a “decision of an agency board.” See G.E.
    Boggs & Assocs. v. Roskens, 
    969 F.2d 1023
    , 1026 (Fed.
    Cir. 1992); see also Roberta B. v. Tenet, 71 F. App’x 45, 46
    (Fed. Cir. 2003); Corrigan v. Dollar, 89 F. App’x 238, 239
    (Fed. Cir. 2003). At the same time, in Inter-Coastal
    Xpress, Inc. v. United States, 
    296 F.3d 1357
    , 1366–70
    (Fed. Cir. 2002), we held that a claim for a payment
    specified in a transportation contract with the govern-
    ment like the one at issue here is covered by the Trans-
    portation Act and not by the Contract Disputes Act. See
    also 
    id. at 1366
    (“Congress intended to have the [Trans-
    portation Act] govern all actions seeking the payment of
    money for the charges owed on contracts for transporta-
    tion services between common carriers and the govern-
    ment.”). Those principles together mean that the Board’s
    decision on the current claim for payment under the
    transportation contract at issue is not a decision within
    41 U.S.C. § 7107(a)(1) subject to appeal to this court
    under 28 U.S.C. § 1295(a)(10).
    A claim for a contract-specified payment under a
    transportation contract like this one can be pursued
    directly in court, subject to timeliness and other condi-
    tions. Thus, separately from permitting a claim for
    agency relief in 31 U.S.C. § 3726, the Transportation Act
    provides for a “civil action to recover charges” in a trans-
    portation contract, 49 U.S.C. § 14705(a), including against
    the federal government, § 14705(f). That action is not for
    review of the agency decision, but a direct action for
    4                           SHERIDAN TRANSPORTATION     v. GSA
    judicial relief. InterCoastal Xpress, after separately and
    unsuccessfully pursuing agency relief, filed such an action
    in the Court of Federal 
    Claims, 296 F.3d at 1361
    –62—
    though it encountered a timeliness problem as to many of
    its claims, because the judicial remedy carries a three-
    year limitations period of its own, 
    id. at 1366
    –67; see 49
    U.S.C. § 14705(f). Sheridan, in contrast, did not file such
    an action.
    Nor did Sheridan present to the board in this case a
    claim for general contract damages for breach of a gov-
    ernment obligation to return the trailers. Whatever the
    reason—simplicity; the magnitude of the amount pro-
    duced by multiplying the contract-specified daily rate by
    the three-plus years of government retention of the trail-
    ers; a much lower estimate of likely damages from breach
    in the circumstances—Sheridan presented only a claim
    for payment of contract-specified “detention” charges.
    That claim comes squarely within 31 U.S.C. § 3726 and
    Inter-Coastal and therefore is outside the Contract Dis-
    putes Act.
    After Inter-Coastal was decided, the Contract Dis-
    putes Act was recodified and amended, but we see no
    basis in those changes for reaching a different result.
    Effective January 2007, Congress created the Civilian
    Board of Contract Appeals to consolidate some agency-
    specific boards, allowing the new board to be assigned
    functions that had been assigned to the predecessor
    boards. See 41 U.S.C. § 438 (in effect from January 2007
    to January 2011); Pub. L. No. 109-163, § 847, 119 Stat.
    3136, 3391–95 (2006); H.R. Rep. No. 109-360, at 762
    (2005) (Conf. Rep.). Then, in 2011, Congress recodified
    the Contract Disputes Act, with the foregoing provision
    now appearing at 41 U.S.C. § 7105(b). Public Contracts
    Act of Jan. 4, 2011, Pub. L. No. 111-350, § 3, 124 Stat.
    3677, 3821 (2011). Congress expressly declared its intent
    to restate, not significantly alter, existing law. 
    Id. § 2(b),
    SHERIDAN TRANSPORTATION    v. GSA                          5
    124 Stat. at 3677 (“In the codification of laws by this Act,
    the intent is to conform to the understood policy, intent,
    and purpose of Congress in the original enactments, with
    such amendments and corrections as will remove ambigu-
    ities, contradictions, and other imperfections . . . .”); see
    H.R. Rep. 111-42, at 2 (2009) (same).
    It was before those congressional actions that we had
    held our 28 U.S.C. § 1295(a)(10) jurisdiction limited to
    agency board decisions made on Contract Disputes Act
    claims and, in Inter-Coastal, recognized the parallel
    availability of the agency and judicial remedies for claims
    seeking payment under transportation contracts and held
    that the Transportation Act governs such claims to the
    exclusion of the Contract Disputes Act. We discern no
    alteration either of the Inter-Coastal holding that a claim
    like Sheridan’s is outside the Contract Disputes Act, and
    covered only by the Transportation Act, or of the limita-
    tion of our appellate jurisdiction to those Board “deci-
    sions” which rule on claims covered by the Contract
    Disputes Act itself, excluding other decisions the Board
    may be assigned to make. For those reasons, we conclude
    that we lack jurisdiction over this appeal under the exist-
    ing statutory regime and our precedent.
    We also conclude that, unlike G.E. Boggs, this is not
    an appropriate case to transfer to the Court of Federal
    Claims. For such a transfer to be justified, not only would
    the Court of Federal Claims have to possess jurisdiction
    over the matter, but transfer would have to be in the
    interest of justice. 28 U.S.C. § 1631. Here, however,
    Sheridan has a timeliness problem even under its broad
    view of “detention” as covering the government’s holding
    of the trailers until it gave Sheridan notice of their avail-
    ability to be picked up.
    That notice came in early July 2012, and both trailers
    were retrieved by July 13, 2012. J.A. 6. Under the stat-
    ute governing transportation claims in the Court of Fed-
    6                          SHERIDAN TRANSPORTATION    v. GSA
    eral Claims, Sheridan’s claim accrued “on delivery or
    tender of delivery by the carrier,” 49 U.S.C. § 14705(g),
    and Sheridan has asserted that its claim accrued by the
    time it picked up the trailers (by July 13, 2012), Appel-
    lant’s Br. at 15, 19, 20, 21–22. Sheridan initiated the
    present judicial proceeding by filing a petition for review
    on July 15, 2015. ECF No. 1. That is past the three years
    after accrual allowed by 49 U.S.C. § 14705(f).
    When a case is transferred under 28 U.S.C. § 1631,
    the date of filing in the transferor court is used as the
    date of filing in the transferee court. See 28 U.S.C. § 1631
    (“the [transferred] action or appeal shall proceed as if it
    had been filed in or noticed for the court to which it is
    transferred on the date upon which it was actually filed in
    or noticed for the court from which it is transferred.”).
    Thus, were we to transfer this case to the Court of Federal
    Claims, that court would proceed as if Sheridan had filed
    its petition on July 15, 2015, more than three years past
    the accrual date. We see no basis for equitable tolling of
    the three-year time limit of 49 U.S.C. § 14705(f), at least
    in this case. Cf. John R. Sand & Gravel Co. v. United
    States, 
    552 U.S. 130
    , 136–39 (2008) (no equitable tolling
    of 28 U.S.C. § 2501); Air Express Int’l Corp. v. United
    States, 
    439 F.2d 157
    , 159 (Ct. Cl. 1971) (limitations period
    for Transportation Act lawsuit is not tolled by pursuit of
    agency relief); Iran Nat’l Airlines Corp. v. United States,
    
    360 F.2d 640
    , 642 (Ct. Cl. 1966). In Inter-Coastal, we
    treated that time limit as 
    jurisdictional. 269 F.3d at 1375
    . At a minimum, it does not seem to us to be in the
    interest of justice to transfer this matter, given all the
    facts, once we decide, as we have, that we lack jurisdiction
    to review the Board’s decision.
    The appeal is therefore dismissed.
    No costs.
    DISMISSED