Parsons Evergreene, LLC v. Secretary of the Air Force ( 2020 )


Menu:
  • Case: 19-1931    Document: 58     Page: 1   Filed: 08/07/2020
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    PARSONS EVERGREENE, LLC,
    Appellant
    v.
    SECRETARY OF THE AIR FORCE,
    Cross-Appellant
    ______________________
    2019-1931, 2019-1975
    ______________________
    Appeals from the Armed Services Board of Contract
    Appeals in Nos. 58634, 61784, Administrative Judge J.
    Reid Prouty, Administrative Judge Craig S. Clarke, Ad-
    ministrative Judge Richard Shackleford.
    ______________________
    Decided: August 7, 2020
    ______________________
    CAMERON HAMRICK, Miles & Stockbridge PC, Washing-
    ton, DC, argued for appellant. Also represented by
    RAYMOND MONROE.
    ROBERT R. KIEPURA, Commercial Litigation Branch,
    Civil Division, United States Department of Justice, Wash-
    ington, DC, argued for cross-appellant. Also represented
    by ETHAN P. DAVIS, STEVEN JOHN GILLINGHAM, ROBERT
    EDWARD KIRSCHMAN, JR.; LORI R. SHAPIRO, Office of Gen-
    eral Counsel, United States General Services Administra-
    tion, Washington, DC.
    Case: 19-1931     Document: 58      Page: 2    Filed: 08/07/2020
    2    PARSONS EVERGREENE, LLC   v. SECRETARY OF THE AIR FORCE
    ______________________
    Before DYK, CLEVENGER, and HUGHES, Circuit Judges.
    DYK, Circuit Judge.
    Parsons Evergreene, LLC (“Parsons”) appeals from two
    decisions by the Armed Services Board of Contract Appeals
    (“Board”). The Board granted in part and denied in part
    Parsons’ claims for equitable adjustment on a contract for
    the design and construction of two buildings at McGuire
    Air Force Base. The government cross-appeals, contending
    that the Board lacked jurisdiction; that we lack jurisdiction
    in part; and, on the merits, that the Board erroneously re-
    quired it to disprove the reasonableness of Parsons’
    claimed costs. We affirm in part, reverse in part, dismiss
    in part, and remand.
    BACKGROUND
    On December 12, 2003, the government awarded Par-
    sons a $2.1 billion indefinite-delivery, indefinite-quantity
    contract (“Contract”) for planning and construction work. 1
    The work was to be described in subsequent task orders.
    On July 13, 2005, the government issued a $34 million task
    order (“Task Order”) under the Contract to complete an ex-
    isting, concept-level design and construct two facilities,
    known as the Temporary Lodging Facility and the Visiting
    Quarters, at the McGuire Air Force Base in New Jersey.
    The Temporary Lodging Facility was to be a 50-unit tran-
    sitional housing facility for use by military and civilian per-
    sonnel. The Visiting Quarters was to be a 175-unit facility
    similar to a hotel with individual rooms and private bath-
    rooms. Design and construction were completed, and the
    1  The contract was originally awarded to Parsons In-
    frastructure and Technology Group Inc. The contract was
    transferred to Parsons via novation on September 7, 2004.
    Case: 19-1931    Document: 58      Page: 3    Filed: 08/07/2020
    PARSONS EVERGREENE, LLC   v. SECRETARY OF THE AIR FORCE    3
    U.S. Department of the Air Force (“Air Force”) accepted the
    completed facilities for “beneficial use” on September 11,
    2008. J.A. 96.
    On June 29, 2012, Parsons submitted a claim to the Air
    Force seeking approximately $34 million in additional
    costs that Parsons allegedly incurred in the design and con-
    struction process. The contracting officer issued a final de-
    cision on March 27, 2013 almost entirely denying Parsons’
    claim, which Parsons appealed to the Board under the Con-
    tract Disputes Act (“CDA”). In separate decisions in
    ASBCA Nos. 58634 and 61784, the Board denied in part
    and sustained in part Parsons’ claim, awarding Parsons
    about $10.5 million plus interest.
    Parsons appeals. The government cross-appeals, con-
    tending that the Board lacked jurisdiction; that we lack ju-
    risdiction in ASBCA No. 61784; and that on the merits the
    Board erroneously required it to disprove the reasonable-
    ness of Parsons’ claimed costs. We review the Board’s legal
    conclusions de novo and its factfinding for substantial evi-
    dence. 41 U.S.C. § 7107(b).
    DISCUSSION
    I
    At the outset, we must resolve a jurisdictional chal-
    lenge. The government contends that the Board lacked
    CDA jurisdiction over this case. We disagree.
    The CDA provides a process for dispute resolution of
    certain contract claims against the government. As rele-
    vant here, the CDA applies to contracts “made by an exec-
    utive agency” for “the procurement of services” or “the
    procurement of construction . . . of real property.” 41
    U.S.C. § 7102(a)(1), (3). Claims by contractors are first
    submitted to a contracting officer, who issues a decision on
    the claim. 41 U.S.C. § 7103(a)(1), (d). The contractor may
    appeal the contracting officer’s decision to a Board of
    Case: 19-1931    Document: 58      Page: 4    Filed: 08/07/2020
    4   PARSONS EVERGREENE, LLC   v. SECRETARY OF THE AIR FORCE
    Contract Appeals.
    Id. § 7104(a). The
    Board’s decision may,
    in turn, be appealed to this court.
    Id. § 7107(a)(1). A
         The government first contends that the Board lacked
    jurisdiction under the so-called “NAFI doctrine.” The
    Board concluded that it had jurisdiction because the NAFI
    doctrine had been abrogated by this court’s decision in
    Slattery v. United States, 
    635 F.3d 1298
    (Fed. Cir. 2011) (en
    banc).
    Beginning in the late 1960s, our predecessor court held
    in a line of cases that neither the Court of Federal Claims
    (“Claims Court”) nor the Boards of Contract Appeals had
    jurisdiction over contract disputes with nonappropriated
    fund instrumentalities (“NAFIs”). Kyer v. United States,
    
    369 F.2d 714
    (Ct. Cl. 1966). “A ‘nonappropriated fund in-
    strumentality’ is one which does not receive its monies by
    congressional appropriation.” United States v. Hopkins,
    
    427 U.S. 123
    , 125 n.2 (1976). As relevant to Board juris-
    diction, these cases construed the phrase “executive
    agency” in the CDA to exclude contracts made by NAFIs.
    See, e.g., Furash & Co. v. United States, 
    252 F.3d 1336
    ,
    1343 (Fed. Cir. 2001); Strand Hunt Const., Inc. v. West, 
    111 F.3d 142
    (Fed. Cir. 1997) (unpublished table decision). As
    to Claims Court jurisdiction, these cases construe the
    Tucker Act’s authorization of suits against “the United
    States” to exclude NAFIs. See 28 U.S.C. § 1491(a)(1); 
    Kyer, 369 F.2d at 719
    .
    In 2011, in our en banc decision in Slattery, we held
    that the Claims Court had Tucker Act jurisdiction over a
    dispute between a contractor and the Federal Deposit In-
    surance Corporation (“FIDC”), even though the FDIC was
    a 
    NAFI. 635 F.3d at 1310
    , 1314. In so holding, we abro-
    gated the NAFI doctrine for Tucker Act claims.
    Id. at 1321.
     We have not yet decided whether Slattery also abrogated
    the NAFI doctrine for CDA disputes appealed to a Board of
    Case: 19-1931    Document: 58     Page: 5   Filed: 08/07/2020
    PARSONS EVERGREENE, LLC   v. SECRETARY OF THE AIR FORCE   5
    Contract Appeals. We expressly reserved that the question
    in one later case. See Minesen Co. v. McHugh, 
    671 F.3d 1332
    , 1337 (Fed. Cir. 2012).
    The government asserts that the Board lacked CDA ju-
    risdiction under the NAFI doctrine. It points out that the
    Board found that the Task Order was made by the Air
    Force Services Agency (“AFSVA”), a NAFI. We need not
    decide the current status of the NAFI doctrine as applied
    to the Boards of Contract Appeals because, even under pre-
    Slattery precedent, the dispute here would not be barred.
    Contrary to the Board’s finding, the contract is not a NAFI
    contract.
    The contracting documents show that the Task Order
    was made by the Air Force and not by the AFSVA. The
    Contract on which the Task Order is based was “Issued By”
    the “Air Force Materiel Command” (“AFMC”), a part of the
    Air Force that the government admits is not a NAFI, and
    was to be “Administered By” the “Department of the Air
    Force.” J.A. 733. The request for proposal (“RFP”) that led
    to the Task Order uses “Department of the Air Force” let-
    terhead and states that “[t]he USAF intends to issue a com-
    petitive [Task Order].” J.A. 4823 (emphasis added). The
    Task Order, like the Contract, was “Issued By” the “Air
    Force Materiel Command” and “Administered By” the “De-
    partment of The Air Force.” J.A. 798. The contracting of-
    ficer who signed the Task Order was from the AFMC. The
    government has not identified any mention of the AFSVA
    or any other NAFI in either the Contract or the Task Order.
    The contractual terms further support the conclusion
    that this was not a NAFI contract. Air Force Manual 64-
    302, which “provid[es] guidance and procedures for Air
    Force NAF contracting,” states that “when FAR clauses are
    used in NAFI contracts, the contracting officer will delete
    references to ‘Government’ and substitute ‘NAFI.’” Depart-
    ment of the Air Force, Manual 64-302, Nonappropriated
    Case: 19-1931     Document: 58      Page: 6     Filed: 08/07/2020
    6   PARSONS EVERGREENE, LLC     v. SECRETARY OF THE AIR FORCE
    Fund (NAF) Contracting Procedures, at 1, 15 (Nov. 3,
    2000), http://afpubs.hq.af.mil. Yet the Contract includes
    many FAR clauses referring to “Government” and no refer-
    ences to the contracting entity’s being a “NAFI.”
    The government contends that the Task Order is a
    NAFI contract because the Air Force did not and could not
    have lawfully funded it with appropriations. The govern-
    ment points out that the funds used for the Task Order
    were “non-appropriated funds.” Cross-Appellant’s Reply 4
    (citing J.A. 804). The government contends that “a military
    department must make a specific request to Congress for
    funding for a specified building project, and Congress must
    grant funding authority for that project, in order for a mil-
    itary department to be allowed to expend appropriated
    funds for a military construction project.”
    Id. at 11. 2 2
        For this proposition, the government relies on 10
    U.S.C. § 2802(a), which provides that “the Secretaries of
    the military departments may carry out such military con-
    struction projects . . . as are authorized by law.” See also
    10 U.S.C. § 114(a) (“No funds may be appropriated . . . to
    or for the use of any armed force or obligated or expended
    for . . . military construction . . . unless funds therefor have
    been specifically authorized by law.”); G. James Herrera,
    Cong. Rsch. Serv., R44710, Military Construction: Author-
    ities, Process, and Frequently Asked Questions 2 (2019)
    (“In practical application of [sections 2802 and 114], Con-
    gress has required project-by-project authorization and ap-
    propriation for military construction projects.”).
    The government also cites to the 2005 National De-
    fense Authorization Act, Pub. L. 108–375, 118 Stat. 1811,
    2108–11 (2004) (“Authorization Act”). The Authorization
    Act listed and provided appropriations for construction at
    dozens of Air Force bases, but did not authorize construc-
    tion at McGuire Air Force Base, where the Visiting
    Case: 19-1931    Document: 58     Page: 7    Filed: 08/07/2020
    PARSONS EVERGREENE, LLC   v. SECRETARY OF THE AIR FORCE   7
    Congress did not provide the Air Force with the required
    authorization here, the government asserts, so the Task
    Order must have been a NAFI contract.
    Even assuming arguendo that the Air Force could not
    have used appropriated funds for the Task Order, the gov-
    ernment’s argument fails. The government relies on Hop-
    kins and Furash to suggest that a contract paid from
    nonappropriated funds is a NAFI contract. Despite some
    language in prior cases suggesting that the NAFI exclusion
    turns on the “activity” at issue, the exclusion did not de-
    pend on whether the contract itself was to be funded with
    appropriations. See United States v. Gen. Elec., 
    727 F.2d 1567
    , 1570 (Fed. Cir. 1984). Instead, the nature of the con-
    tracting entity governed: namely, whether the contract was
    “made by” a NAFI. And an agency is only a NAFI where
    there is “a clear expression by Congress that it intended to
    separate the agency from general federal revenues.”
    
    Furash, 252 F.3d at 1339
    .
    Thus, our predecessor held that a contract made by the
    Agency for International Development (“AID”) did not im-
    plicate the NAFI doctrine—even though the program im-
    plemented by the contract was to be run without
    appropriated funds—because AID (as a whole) received ap-
    propriated funds. McCarthy v. United States, 
    670 F.2d 996
    ,
    1002 (Ct. Cl. 1982). The court explained that “the nonap-
    propriated funds exclusion is limited to instances when, by
    law, appropriated funds not only are not used to fund the
    agency, but could not be.” Id.; see also L’Enfant Plaza
    Props., Inc. v. United States, 
    668 F.2d 1211
    , 1212 (Ct. Cl.
    1982) (explaining that, to implicate the NAFI doctrine,
    “there must be a clear expression by Congress that the
    agency was to be separated from general federal
    Quarters and Temporary Lodging Facility were built. See
    Authorization Act §§ 2301–02.
    Case: 19-1931    Document: 58      Page: 8    Filed: 08/07/2020
    8   PARSONS EVERGREENE, LLC   v. SECRETARY OF THE AIR FORCE
    revenues”). Here, there is no question that the Air Force
    “has authority to use appropriated funds if and to the ex-
    tent appropriated, and that is sufficient to avoid the non-
    appropriated funds exclusion.” See 
    McCarthy, 670 F.2d at 1002
    . 3
    The Task Order was made by the Air Force, and not the
    AFSVA. The NAFI doctrine, even if it survives under the
    CDA, is inapplicable.
    B
    The government argues alternatively that the CDA is
    limited to contracts for “the procurement of services” or
    “the procurement of construction . . . of real property,” and
    the contract here does not qualify. Cross-Appellant’s Br.
    29–30 (citing 41 U.S.C. § 7102(a)). The contract here was
    for the design and construction of two buildings, the Tem-
    porary Lodging Facility and the Visiting Quarters. The
    Task Order falls neatly within the CDA’s “procurement”
    language.
    The government nevertheless contends that this was
    not a “procurement,” relying principally on 31 U.S.C.
    § 6303. Section 6303 provides that:
    An executive agency shall use a procurement con-
    tract . . . when—(1) the principal purpose of the in-
    strument is to acquire . . . property or services for
    the direct benefit or use of the United States Gov-
    ernment; or (2) the agency decides in a specific
    3   Our decision in General Electric supports this con-
    clusion. There, as here, the fact that the governmental
    counterparty to the contract was the Air Force was suffi-
    cient to place the dispute outside the NAFI 
    doctrine. 727 F.2d at 1570
    .
    Case: 19-1931    Document: 58      Page: 9    Filed: 08/07/2020
    PARSONS EVERGREENE, LLC   v. SECRETARY OF THE AIR FORCE    9
    instance that the use of a procurement contract is
    appropriate.
    The government asserts that the buildings at issue here
    were built for the purpose of “support[ing] the morale, wel-
    fare, and recreation of the service member[s] or other
    guests,” which the government contends is “a distinct pur-
    pose from that of the Air Force, whose primary function is
    national defense.” Cross-Appellant’s Br. 36. Thus, to the
    government, the Task Order is not “for the direct benefit or
    use of the United States Government,” under the meaning
    of 31 U.S.C. § 6303.
    The government’s argument lacks merit. Section 6303
    is not part of a statutory definition of CDA jurisdiction. It
    is in a separate title of the United States Code. It does not
    control the interpretation of the term “procurement” as
    used in the CDA. In any event, the government’s position
    that a project supporting the morale and welfare of service-
    members is not for the “direct benefit” of the government is
    at odds with the Supreme Court’s holding in Standard Oil
    Co. of California v. Johnson, 
    316 U.S. 481
    (1942), which
    held that military post exchanges were “essential for the
    performance of governmental functions.”
    Id. at 485.
    The
    government’s position is also inconsistent with the Secre-
    tary of the Air Force’s responsibility for “the morale and
    welfare of [Air Force] personnel.” 10 U.S.C. § 9013(b)(9).
    Finally, section 6303 does not require that procurement
    contracts be for the “direct benefit or use” of the govern-
    ment. It states that agencies “shall use” procurement con-
    tracts in certain circumstances, but does not otherwise
    foreclose their use. Section 6303 contemplates procure-
    ment contracts even when not for the government’s direct
    benefit so long as “the agency decides” that a procurement
    contract “is appropriate.” The Task Order is a “procure-
    ment” contract under the CDA.
    Case: 19-1931    Document: 58       Page: 10    Filed: 08/07/2020
    10 PARSONS EVERGREENE, LLC v. SECRETARY OF THE AIR FORCE
    The government’s reliance on G.E. Boggs & Assocs.,
    Inc. v. Roskens, 
    969 F.2d 1023
    (Fed. Cir. 1992), and New
    Era Construction v. United States, 
    890 F.2d 1152
    (Fed Cir.
    1989), is similarly unavailing. In each of those cases, we
    held the contractual dispute to be not subject to the CDA.
    But G.E. Boggs and New Era, unlike this case, involved
    contracts with entities—the Syrian Arab Republic and the
    Sac and Fox Tribe of Missouri, respectively—that were not
    executive agencies. G.E. 
    Boggs, 969 F.2d at 1024
    ; New 
    Era, 890 F.2d at 1153
    .
    We conclude that the Board had CDA jurisdiction.
    II
    We next consider the timeliness of Parsons’ appeal
    from ASBCA No. 61784 as it relates to our own jurisdiction.
    Parsons contends that the Board erred in denying recovery
    for costs Parsons allegedly incurred as a result of delays
    caused by a payroll review by the Air Force to determine
    Parson’s compliance with the Davis-Bacon Act. The Act re-
    quires federal construction contractors to pay laborers and
    mechanics at least the prevailing wage for their work. 40
    U.S.C. § 3142(a). Under FAR § 22.406–8, the government
    was authorized to ensure Davis-Bacon Act compliance by
    “[c]onduct[ing] labor standards investigations when avail-
    able information indicates such action is warranted.” Par-
    sons asserts that it is entitled to compensation because the
    Air Force unreasonably delayed initiating and conducting
    such a review. We do not reach the merits of Parsons’ pay-
    roll claim because we lack jurisdiction to consider it.
    The procedural history of Parsons’ payroll claim is as
    follows. On June 29, 2012, Parsons submitted the claims
    at issue here to the contracting officer, including its payroll
    claim. The contracting officer denied recovery and, on
    April 22, 2013, Parsons appealed to the Board. Parsons’
    appeal was initially docketed as ASBCA No. 58634. Liti-
    gation continued and, on September 5, 2018, the Board
    Case: 19-1931    Document: 58      Page: 11     Filed: 08/07/2020
    PARSONS EVERGREENE, LLC    v. SECRETARY OF THE AIR FORCE 11
    issued its decisions on the merits of Parsons’ claims, includ-
    ing the payroll claim. For all claims except the payroll
    claim, the Board issued its decision in the original case,
    ASBCA No. 58634. For the payroll claim, “[f]or reasons of
    judicial efficiency and clarity,” the Board issued a separate
    opinion under a new appeal number, ASBCA No. 61784.
    J.A. 1 n.1. Parsons received the Board’s decisions on Sep-
    tember 10, 2018. On October 10, 2018, Parsons moved for
    reconsideration of the Board’s decision on several claims in
    ASBCA No. 58634. Parsons did not seek reconsideration of
    the payroll claim in ASBCA No. 61784. The Board issued
    its decision denying Parsons’ reconsideration request in
    ASBCA No. 58634 on January 23, 2019, which Parsons re-
    ceived on January 28, 2019. Parsons appealed the Board’s
    decisions on its claims, including the payroll claim, to this
    court on May 23, 2019.
    Parsons’ appeal of its payroll claim was not timely filed.
    The statute governing appeals from the Board to this court
    provides that “a contractor may appeal the decision [of an
    agency board] within 120 days from the date the contractor
    receives a copy of the decision.” 41 U.S.C. § 7107(a)(1)(A).
    The 120-day appeal period runs from contractor’s receipt of
    the Board’s decision on reconsideration, if reconsideration
    is sought. Although Parsons sought reconsideration of the
    Board’s decision in ASBCA No. 58634 (and its appeal in
    that case is timely), Parsons did not seek reconsideration
    in ASBCA No. 61784. Parsons’ appeal in ASBCA No. 61784
    was filed 255 days after it received a copy of the final deci-
    sion in that action. The 120-day deadline was not tolled by
    the request for reconsideration in ASBCA No. 58634.
    Therefore, we lack jurisdiction to review the Board’s deci-
    sion in ASBCA No. 61784. See Placeway Const. Corp. v.
    United States, 
    713 F.2d 726
    , 728 (Fed. Cir. 1983) (dismiss-
    ing for lack of jurisdiction an appeal from the Board filed
    after the 120-day deadline).
    We dismiss Parsons’ appeal as to its payroll claim.
    Case: 19-1931    Document: 58       Page: 12   Filed: 08/07/2020
    12 PARSONS EVERGREENE, LLC v. SECRETARY OF THE AIR FORCE
    III
    We turn to the merits of Parsons’ appeal in ASBCA No.
    58634. Parsons argues that the Board erred in denying re-
    covery on Parsons’ claim that it was not required to apply
    wall coatings from Duroplex-Triarch Industries and Plex-
    ture-Triarch Industries (collectively, “Triarch”) to the Vis-
    iting Quarters. Triarch is not “paint” in the conventional
    sense, though it is a paint-like substance.
    The Board rejected Parsons’ theory that it was required
    to apply Sherwin-Williams instead of Triarch, holding that
    Parsons was required to apply Triarch. The Board found
    dispositive the terms of Request for Proposal No. FA8903-
    05-R-8234 (“RFP”), on which the Task Order was based.
    The RFP “required ‘Duroplex – Triarch Industries’ and
    ‘Plexture – Triarch Industries’ for interior paints.”
    J.A. 132 (quoting RFP § 09911). Parsons does not now
    challenge the determination that it was required to apply
    Triarch.
    The Board, however, introduced a new theory of liabil-
    ity, finding the government liable for Parsons’ costs in ap-
    plying Sherwin Williams paint due to the Air Force’s
    “indecision on what wall coating it wanted, causing [Par-
    sons] to start applying Sherwin Williams paint in the [Vis-
    iting Quarters].” J.A. 132. But because Parsons did not
    argue this theory before the Board and did not quantify its
    cost in using Sherwin Williams, the Board denied Parsons
    recovery. On appeal, Parsons argues that the Board erred
    in denying Parsons recovery under the Board’s theory. We
    disagree.
    A required element of a claim for equitable adjustment
    is proof of damages. The contractor has the “obligation . . .
    to provide a basis for making a reasonably correct approx-
    imation of the damages” for which the government is liable.
    Wunderlich Contracting Co. v. United States, 
    351 F.2d 956
    ,
    969 (Ct. Cl. 1965). It was Parsons’ burden to prove its
    Case: 19-1931    Document: 58     Page: 13    Filed: 08/07/2020
    PARSONS EVERGREENE, LLC   v. SECRETARY OF THE AIR FORCE 13
    damages, i.e., the costs incurred in applying Sherwin Wil-
    liams paint. The Board did not err in concluding that Par-
    sons did not meet its burden.
    Parsons contends that the record at the time of the
    Board decision included sufficient evidence to calculate
    Parsons’ cost in using Sherwin Williams. But Parsons
    failed to include an alternative argument concerning the
    Air Force’s erroneous direction to apply Sherwin Williams
    in the Visiting Quarters, and did not identify its costs in
    doing so. Nothing in Southwest Electronics & Manufactur-
    ing Corporation v. United States, 
    655 F.2d 1078
    (Ct. Cl.
    1981), or any other authority cited by Parsons suggests
    that the Board was required to scour the tens of thousands
    of pages of record evidence in this case, without any guid-
    ance, to determine the amount of an award. 4
    Parsons also asserts that the Board erred by failing “to
    seek the parties’ input as to whether the record supported
    recovery under the Board’s new theory prior to deciding the
    issue.” Appellant’s Br. 34. “The [Administrative Procedure
    Act] does not require the Board to alert a [claimant] that it
    may find the asserted theory,” or any other theory that the
    4    In Southwest Electronics, the Board overturned the
    contracting officer’s award, on the basis that the contractor
    did not establish the exact amount of its 
    damages. 655 F.2d at 1088
    . In reinstating the contracting officer’s
    award, our predecessor reasoned that the contractor “[did]
    supply some evidence of the damages for which [the gov-
    ernment] is liable, and the contracting officer’s award is a
    reasonable approximation of the damages which [the con-
    tractor] has proven.”
    Id. Here, by contrast,
    there is noth-
    ing to indicate that the contracting officer awarded Parsons
    the cost of using Sherwin Williams, nor did Parsons pro-
    vide the Board with evidence from which “a reasonable ap-
    proximation” of that cost could be determined. See
    id. Case: 19-1931 Document:
    58      Page: 14    Filed: 08/07/2020
    14 PARSONS EVERGREENE, LLC v. SECRETARY OF THE AIR FORCE
    claimant could have argued, “lacking in evidence before it
    actually does so in [an opinion]. Nor is a [claimant] entitled
    to a pre-decision opportunity to disagree with the Board’s
    assessment of its arguments.” Fanduel, Inc. v. Interactive
    Games LLC, No. 2019-1393, 
    2020 WL 4342681
    (Fed. Cir.
    July 29, 2020). While Parsons directed the Board to this
    evidence on reconsideration, this was simply too late. See
    Exxon Shipping Co. v. Baker, 
    554 U.S. 471
    , 485 n.5 (2008)
    (a motion for reconsideration “may not be used to . . . pre-
    sent evidence that could have been raised prior to the entry
    of judgment”).
    IV
    We next turn to Parsons’ contention that the Board
    erred in denying Parsons recovery for the added cost of us-
    ing the “Baker design” rather than the “structural-brick”
    design for the Visiting Quarters.
    The Board held that under the contract Parsons was
    entitled to use a structural-brick design to construct the
    Visiting Quarters. The Board also found that the govern-
    ment improperly denied Parsons the use of the structural
    brick design, and instead required Parsons to use what was
    called the “Baker design.” The structural-brick design
    used a single wall made of closure face brick. The Baker
    design used two walls: a first wall of concrete masonry
    units and a second wall of brick veneer. After the award,
    the government directed Parsons to use the Baker design
    and to modify the original Baker design to address prob-
    lems of progressive collapse, 5 a design choice that made
    construction more expensive.
    5  Progressive collapse is a phenomenon that occurs
    when certain structural members of a building are dam-
    aged and weight is transferred to other members that
    Case: 19-1931    Document: 58      Page: 15    Filed: 08/07/2020
    PARSONS EVERGREENE, LLC   v. SECRETARY OF THE AIR FORCE 15
    Parsons sought an equitable adjustment for the in-
    creased design and construction costs of the Baker design
    over that of the structural-brick design. The Board
    awarded Parsons a lesser amount for added construction
    costs: “the additional cost . . . required to make the
    Baker . . . design resist progressive collapse.” J.A. 120–21.
    The Board awarded Parsons $722,176 in design costs.
    The Board erred in not also awarding the full amount
    of Parsons’ additional construction costs for using the
    Baker design over the structural-brick design. The amount
    of an award for an equitable adjustment is “the difference
    between the reasonable cost of performing without the
    change . . . and the reasonable cost of performing with the
    change.” Morrison Knudsen Corp. v. Fireman's Fund Ins.
    Co., 
    175 F.3d 1221
    , 1244 (10th Cir. 1999) (quoting Celesco
    Indus., Inc., ASBCA No. 22251, 79–1 B.C.A. (CCH) ¶
    13,604, at 66,683 (1978)). Here, the “cost of performing
    without the change” is the cost of construction using struc-
    tural brick. The “cost of performing with the change” is the
    actual cost of construction (i.e., the cost of using the modi-
    fied double-wall design). Parsons was entitled to the dif-
    ference between these two amounts.
    We reverse the Board’s denial of recovery to Parsons
    for its claim to construction costs. On remand, the Board
    must award Parsons the difference between its cost in con-
    structing the Baker design compared to the cost Parsons
    would have incurred in constructing the structural brick
    design.
    V
    We turn finally to the government’s cross-appeal chal-
    lenging the Board’s reasonable-costs analysis.
    cannot handle the additional weight. As a result, the build-
    ing collapses.
    Case: 19-1931    Document: 58     Page: 16    Filed: 08/07/2020
    16 PARSONS EVERGREENE, LLC v. SECRETARY OF THE AIR FORCE
    The government contends that the Board erroneously
    shifted the burden as to reasonableness to the government,
    when the burden should have been on Parsons to prove rea-
    sonableness. The government points to Judge Clarke’s
    opinion for the Board, which concluded that Parsons’ costs
    were reasonable in part because the Air Force’s did not pro-
    vide “specific, individualized challenges to each of Parsons’
    claimed costs.” Cross-Appellant’s Br. 38. The government
    contends that this improperly saddled the government
    with the burden of proof. But Administrative Judge
    Clarke’s analysis on this issue was expressly disclaimed by
    the other two panel judges in a concurring opinion written
    by Administrative Judge Shackleford and joined by Admin-
    istrative Judge Prouty. Thus, Judge Shackleford’s opinion,
    not Judge Clarke’s opinion, is the Board’s controlling opin-
    ion on the reasonable-costs issue.
    The government does not contend that Judge Shackle-
    ford’s opinion commits the same purported burden-shifting
    error as Judge Clarke’s opinion. Instead, the government
    asserts that Judge Shackleford’s opinion is “so devoid of
    any analysis that it cannot be plausibly reviewed for legal
    sufficiency on appeal.” Cross-Appellant’s Br. 44. We disa-
    gree. Judge Shackleford clearly stated the governing law
    and its application to this case. The government has not
    shown error in the Board’s reasonable-costs analysis.
    The government’s challenge also fails because it has ar-
    ticulated no prejudice resulting from of the Board’s pur-
    ported error. “[T]he party that ‘seeks to have a judgment
    set aside because of an erroneous ruling carries the burden
    of showing that prejudice resulted.’” Shinseki v. Sanders,
    
    556 U.S. 396
    , 409 (2009) (quoting Palmer v. Hoffman, 
    318 U.S. 109
    , 116 (1943)); see also SolarWorld Ams., Inc v.
    United States, No. 2019-1591, 
    2020 WL 3443470
    , at *4–*5
    (Fed. Cir. June 24, 2020) (rejecting an appellant’s challenge
    to a purportedly unlawful agency action because the appel-
    lant did not establish that the action was prejudicial).
    Case: 19-1931    Document: 58    Page: 17    Filed: 08/07/2020
    PARSONS EVERGREENE, LLC   v. SECRETARY OF THE AIR FORCE 17
    Here, the government has not explained which, if any, of
    the costs awarded to Parsons would have been affected by
    the Board’s purported error or how they would have been
    affected. We conclude that the Board’s purported errors, if
    any, were harmless.
    We affirm the Board’s conclusion that Parsons’ costs
    awarded by the Board were reasonable.
    CONCLUSION
    We conclude that the Board had CDA jurisdiction over
    ASBCA No. 58634. We dismiss Parsons’ appeal as to its
    claim for costs associated with its payroll review (ASBCA
    No. 61784) as untimely. We affirm the Board’s decision de-
    clining to award Parsons its costs in using Triarch wall
    coatings. We reverse the Board’s decision declining to
    award Parsons its full costs in constructing the Baker de-
    sign over the costs of the structural-brick design. We af-
    firm the Board’s conclusion that Parsons’ claimed costs
    were reasonable. We remand for further proceedings con-
    sistent with this opinion.
    AFFIRMED IN PART, REVERSED IN PART,
    DISMISSED IN PART, AND REMANDED
    COSTS
    No costs.