Office Design Group v. United States ( 2020 )


Menu:
  • Case: 19-1337    Document: 70     Page: 1   Filed: 03/06/2020
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    OFFICE DESIGN GROUP,
    Plaintiff-Appellant
    v.
    UNITED STATES, CUNA SUPPLY, LLC,
    Defendants-Appellees
    GOVSOLUTIONS, INC.,
    Defendant
    ______________________
    2019-1337
    ______________________
    Appeal from the United States Court of Federal Claims
    in No. 1:18-cv-01147-RHH, Senior Judge Robert H.
    Hodges, Jr.
    ______________________
    Decided: March 6, 2020
    ______________________
    JOSEPH ANTHONY WHITCOMB, Whitcomb, Selinsky, PC,
    Denver, CO, argued for plaintiff-appellant. Also repre-
    sented by TIMOTHY TURNER.
    TANYA KOENIG, Commercial Litigation Branch, Civil
    Division, United States Department of Justice, Washing-
    ton, DC, argued for defendant-appellee United States. Also
    represented by JOSEPH H. HUNT, ROBERT EDWARD
    KIRSCHMAN, JR., DOUGLAS K. MICKLE.
    Case: 19-1337    Document: 70      Page: 2    Filed: 03/06/2020
    2                        OFFICE DESIGN GRP. v. UNITED STATES
    MATTHEW THOMAS SCHOONOVER, Koprince Law LLC,
    Lawrence, KS, for defendant-appellee Cuna Supply, LLC.
    ______________________
    Before LOURIE, REYNA, and HUGHES, Circuit Judges.
    REYNA, Circuit Judge.
    Office Design Group appeals from an order of the
    United States Court of Federal Claims granting judgment
    on the administrative record for the government and Cuna
    Supply, LLC. Because Office Design Group fails to estab-
    lish that the government’s evaluation of its proposal was
    arbitrary, capricious, an abuse of discretion, or otherwise
    not in accordance with law, we affirm.
    I.
    On May 5, 2017, the United States Department of Vet-
    erans Affairs (“VA”) issued five Requests for Proposals
    (“RFP”) for the provision of healthcare furniture and re-
    lated services for VA facilities. The five RFPs were essen-
    tially identical, except that each related to a separate
    geographic region. Each RFP contemplated awarding
    three to five contracts for indefinite delivery, indefinite
    quantity, with each contract having a five-year base period
    and one five-year option period.
    The RFP 1 established that the VA would award con-
    tracts based on a best-value trade off selection process that
    considered three primary evaluation factors: Technical Ca-
    pability, Past Performance, and Price. The VA deemed
    1  To simplify, this opinion will refer to RFP in the
    singular when discussing the RFPs’ requirements and
    evaluation criteria.
    Case: 19-1337      Document: 70      Page: 3     Filed: 03/06/2020
    OFFICE DESIGN GRP. v. UNITED STATES                            3
    Technical Capability more important than Past Perfor-
    mance, and Past Performance more important than Price.
    Central to this appeal is Technical Capability subfac-
    tor 3. Subfactor 3 specified that an offeror’s technical pro-
    posal must include a narrative “addressing each of the
    items listed under SV1, SV2, SV3, and SV4 as defined” in
    the Statement of Work (“SOW”). J.A. 128. SV1, SV2, SV3,
    and SV4 are codes corresponding to the specific services
    and products sought by the RFP. Subfactor 3 also required
    an offeror to address eight “key” elements, which included
    an offeror’s staffing plan, inventory and cataloging process,
    personnel experience and qualifications, and process used
    for warranty repairs.
    Subfactor 3 also provided that the VA would evaluate
    each offeror’s technical volume of its proposal, i.e., its “tech-
    nical proposal,” based on the offeror’s ability “to meet all
    services as defined in the Statement of Work.” The RFP
    noted that an “unacceptable” rating for any technical sub-
    factor would result in an overall “unacceptable” technical
    proposal. An offeror with an unacceptable Technical Capa-
    bility subfactor was ineligible for a contract award.
    The RFP also included “Attachment 15,” an evaluation
    questionnaire containing thirty-three yes or no questions
    regarding the service requirements from the SOW and the
    eight key elements listed under subfactor 3. The question-
    naire was divided into four sections, each corresponding to
    the four SOW sections—SV1, SV2, SV3, SV4. Reproduced
    below are the first seven questions of Attachment 15, which
    correspond to SV1 of the SOW.
    Case: 19-1337     Document: 70     Page: 4    Filed: 03/06/2020
    4                        OFFICE DESIGN GRP. v. UNITED STATES
    J.A. 166
    In an amendment to the RFP, the VA clarified that At-
    tachment 15 was to be used by the agency as a checklist to
    evaluate offerors’ technical proposals. The amendment pro-
    vided that “Attachment 8 Sample Project Tech Evaluation
    and Attachment 15 Service Technical Questions are infor-
    mational only. They are the checklists that will be used to
    evaluate the technical proposals.” J.A. 141 (emphasis
    added).
    During contract evaluation, the VA assigned an offeror
    2 points for each question in Attachment 15 that the offeror
    sufficiently addressed in its technical proposal. To receive
    a passing score for its technical proposal, an offeror needed
    to receive a minimum of 40 points, i.e., a “yes” for twenty
    of the thirty-three questions in Attachment 15.
    Office Design Group (“ODG”) submitted a proposal for
    all five regions. The VA assigned ODG an unacceptable
    rating for its technical proposal, rendering ODG’s overall
    proposal ineligible for award. The VA noted in its evalua-
    tion report that it was only able to locate responses to six
    of the thirty-three questions in Attachment 15 in ODG’s
    technical proposal, resulting in a failing score of 12 points.
    The VA explained that ODG’s technical proposal “lacked
    detail” and contained “vague info.” J.A. 120. The VA also
    Case: 19-1337    Document: 70     Page: 5   Filed: 03/06/2020
    OFFICE DESIGN GRP. v. UNITED STATES                      5
    noted that ODG’s technical proposal failed to address the
    following seven SOW service requirements: (1) a staffing
    plan, (2) information regarding inventory, cataloging, and
    protecting VA property information, (3) information about
    protecting furniture from damage and loss, (4) information
    about executing a warranty, (5) information about provid-
    ing AUTOCAD or PDF files, (6) information about its team
    members’ experience in the healthcare and federal indus-
    tries, and (7) information about whether its personnel had
    knowledge about life safety, infection control, and patient
    privacy standards.
    The VA awarded contracts to nine offerors under each
    of the five RFPs. Each of the awardees earned at least
    40 points for its technical proposal.
    ODG filed a bid protest before the Government
    Accountability Office (“GAO”), alleging that the VA
    (1) unreasonably and disparately evaluated its technical
    proposal in comparison to the awardees’ technical
    proposals and (2) improperly relied on Attachment 15 to
    evaluate its technical proposal. The GAO denied ODG’s
    protest on both grounds. ODG then filed a bid protest
    before the Claims Court, alleging the same two grounds. 2
    The Claims Court determined that the VA’s use of
    Attachment 15 was proper and that ODG had not shown
    that the VA’s alleged disparate treatment was prejudicial
    error.   The Claims Court denied ODG’s motion for
    judgment on the administrative record and granted the
    government’s and the defendant-intervenor’s cross-motion
    for judgment on the administrative record. ODG timely
    appeals. We have jurisdiction under 
    28 U.S.C. § 1295
    (a)(3).
    2    ODG also alleged in the Claims Court that four of
    these offerors colluded and provided substantially the
    same technical proposal. ODG, however, does not raise the
    collusion issue on appeal.
    Case: 19-1337     Document: 70      Page: 6    Filed: 03/06/2020
    6                        OFFICE DESIGN GRP. v. UNITED STATES
    DISCUSSION
    We review the grant of a motion for judgment on the
    administrative record in a bid protest action de novo. Glenn
    Defense Marine (ASIA), PTE Ltd. v. United States, 
    720 F.3d 901
    , 907 (Fed. Cir. 2013). In a bid protest case, the inquiry
    is whether the agency’s actions were “arbitrary, capricious,
    an abuse of discretion, or otherwise not in accordance with
    law, and if so whether the error is prejudicial.” Id.; see also
    Alabama Aircraft Indus., Inc. Birmingham v. United
    States, 
    586 F.3d 1372
    , 1375 (Fed. Cir. 2009). “The court’s
    task is to determine whether ‘(1) the procurement official’s
    decision lacked a rational basis; or (2) the procurement pro-
    cedure involved a violation of regulation or procedure.’”
    Savantage Fin. Servs., Inc. v. United States, 
    595 F.3d 1282
    ,
    1285–86 (Fed. Cir. 2010) (quoting Weeks Marine, Inc. v.
    United States, 
    575 F.3d 1352
    , 1358 (Fed. Cir. 2009)).
    On appeal, ODG raises the same two challenges it
    raised before the GAO and the Claims Court. First, ODG
    argues that the VA’s reliance on Attachment 15 during the
    evaluation process was inconsistent with the terms of the
    RFP. Second, ODG argues that the VA disparately evalu-
    ated its technical proposal in comparison to those of vari-
    ous awardees. We address each argument in turn.
    I.
    ODG argues that the VA unreasonably strayed from
    the terms of the RFP by relying on Attachment 15 to eval-
    uate its technical proposal. According to ODG, “the prob-
    lem for the VA, is that it never announced . . . that it
    planned to use responses to Attachment 15 . . . as the ru-
    bric against which proposals were scored and evaluated.”
    Appellant’s Br. 13. We reject this argument.
    The VA informed all offerors, including ODG, that At-
    tachment 15 would be used to evaluate technical proposals.
    An amendment to the RFP noted that Attachment 15 was
    to be used as a “checklist[]” that “will be used to evaluate
    Case: 19-1337     Document: 70      Page: 7    Filed: 03/06/2020
    OFFICE DESIGN GRP. v. UNITED STATES                          7
    the technical proposals.” J.A. 141. Thus, contrary to
    ODG’s contention, the record establishes that the VA pro-
    vided clear, reasonable notice that the VA planned to use
    Attachment 15 to evaluate proposals.
    II.
    ODG argues that the VA disparately evaluated its
    technical proposal. According to ODG, although its tech-
    nical proposal was sufficiently similar to the awardees’ pro-
    posals, the VA improperly assigned ODG’s technical
    proposal a failing score. ODG provides seven examples of
    the VA’s alleged disparate treatment of its technical pro-
    posal.
    The Federal Acquisition Regulation requires an agency
    to treat offerors fairly and impartially. 
    48 C.F.R. § 1.602
    –
    2(b) (“Contracting officers shall . . . ensure that contractors
    receive impartial, fair, and equitable treatment.”). This ob-
    ligation necessarily encompasses an agency’s obligation to
    fairly and impartially evaluate all proposals. Equal evalu-
    ation of proposals, however, does not translate into identi-
    cal evaluations. An agency is under no obligation to assign
    dissimilar proposals the same evaluation rating. 
    48 C.F.R. § 1.102
    –2(c)(3) (“All contractors and prospective contrac-
    tors shall be treated fairly and impartially but need not be
    treated the same.” (emphasis added)).
    Upon review, it appears that this court has not yet ar-
    ticulated a standard for evaluating disparate evaluation
    claims. The Claims Court, however, has done so, having
    adjudicated numerous disparate evaluation claims. To
    prevail at the Claims Court, a protestor must show that the
    agency unreasonably downgraded its proposal for deficien-
    cies that were “substantively indistinguishable” or nearly
    identical from those contained in other proposals. See En-
    hanced Veterans Solutions, Inc. v. United States, 
    131 Fed. Cl. 565
    , 588 (2017); see also Red River Comput. Co. v.
    United States, 
    120 Fed. Cl. 227
    , 238 (2015); Sci. Applica-
    tions Int’l Corp. v. United States, 
    108 Fed. Cl. 235
    , 272
    Case: 19-1337    Document: 70      Page: 8    Filed: 03/06/2020
    8                        OFFICE DESIGN GRP. v. UNITED STATES
    (2012); Chenega Mgmt., LLC v. United States, 
    96 Fed. Cl. 556
    , 585 (2010); Hamilton Sundstrand Power Sys. v.
    United States, 
    75 Fed. Cl. 512
    , 516 (2007). 3 A protestor
    may also prevail by showing that the agency inconsistently
    applied objective solicitation requirements between it and
    other offerors, such as proposal page limits, formatting re-
    quirements, or submission deadlines. See Sci. Applications
    Int’l Corp., 108 Fed. Cl. at 272 (citing BayFirst Sols., LLC
    v. United States, 
    102 Fed. Cl. 677
     (2012)).
    We see no reason to depart from the Claims Court’s
    “substantively indistinguishable” standard. If a protestor
    meets this threshold, a reviewing court can then compara-
    tively and appropriately analyze the agency’s treatment of
    proposals without interfering with the agency’s broad dis-
    cretion in these matters. See, e.g., COMINT Sys. Corp. v.
    United States, 
    700 F.3d 1377
    , 1384 (Fed. Cir. 2012). If a
    protestor does not, then the court should dismiss the claim.
    To allow otherwise would give a court free reign to second-
    guess the agency’s discretionary determinations underly-
    ing its technical ratings. This is not the court’s role. E.W.
    Bliss Co. v. United States, 
    77 F.3d 445
    , 440 (Fed. Cir. 1996)
    3   Several of the above-cited Claims Court cases ad-
    dress disparate evaluation claims in the context of compet-
    itive range determinations. An agency may select a
    competitive range of proposals that have been more highly
    ranked to continue in the competition. 
    48 C.F.R. § 15.306
    (c)(1). Proposals that have not met the competitive
    range threshold are eliminated from the competition. 
    48 C.F.R. § 15.306
    (c)(4). We see no relevant difference for pur-
    poses of disparate evaluation claims whether the alleged
    disparate evaluation occurred at the threshold competitive
    range determination or at the ultimate award decision. An
    agency is obligated to fairly evaluate proposals at both
    stages. See 
    48 C.F.R. § 1.102
    –2(c)(3); 
    48 C.F.R. § 1.602
    –
    2(b).
    Case: 19-1337     Document: 70     Page: 9    Filed: 03/06/2020
    OFFICE DESIGN GRP. v. UNITED STATES                         9
    (noting that the court “will not second guess” the “minutiae
    of the procurement process in such matters as technical
    ratings . . . , which involve discretionary determinations of
    procurement officials”).
    The record indicates that ODG’s proposal was substan-
    tively distinguishable from other proposals in various re-
    spects. 4 The RFP required offerors to provide a description
    of their interior designer’s “experience and qualifications
    working on healthcare facilities and what hardware and
    software that will be used to produce digital and hard copy
    drawings.” J.A. 131. Unlike the awardees’ proposals,
    ODG’s proposal did not address the hardware and software
    requirements. Compare J.A. 94-100, with J.A. 32.
    The RFP also required an offeror to describe the “expe-
    rience of the installation staff and Interior Design staff” as
    well as their “knowledge regarding life safety codes, infec-
    tion control standards and patient privacy standards.”
    J.A. 131. Unlike the awardees’ proposals, ODG’s proposal
    did not address whether its staff had experience with life
    safety codes, infection control standards, and patient pri-
    vacy standards. Compare J.A. 94-100, with J.A. 25-26, 55,
    88.
    The RFP required offerors to provide a staffing plan
    that included its key personnel’s qualifications and experi-
    ence in a healthcare environment. But, as the Claims
    Court found, ODG submitted a staffing plan “that could not
    be compared to others.” J.A. 7. The Claims Court also
    noted that ODG’s proposal said “little of the staff’s qualifi-
    cations in healthcare,” and that the comparators’ proposals
    were “more responsive and descriptive.” 
    Id.
    The RFP required offerors to describe the “technical ca-
    pabilities of staff producing AutoCAD and/or PDF
    4   ODG makes no allegation that the VA inconsist-
    ently applied objective solicitation requirements.
    Case: 19-1337    Document: 70     Page: 10    Filed: 03/06/2020
    10                       OFFICE DESIGN GRP. v. UNITED STATES
    drawings of the as-built furniture installation.” J.A. 131.
    Unlike the awardees’ proposals, ODG did not address
    whether its staff will use AutoCAD or PDF to produce
    drawings. Compare J.A. 94-100, with J.A. 30, 55, 71, 88.
    In light of these substantive differences, ODG cannot
    prevail on most of its claims of disparate treatment. ODG,
    however, has sufficiently established that the VA dispar-
    ately evaluated its technical proposal in two instances.
    Both ODG and awardee A. Pomerantz failed to provide a
    (1) description of the process of inventory, cataloging and
    protecting VA property and (2) description of materials
    used and how they are applied to protect VA property dur-
    ing installation. The VA assigned 6 points to this awardee
    as if it had provided this information yet did not assign
    ODG any points.
    To prevail, ODG must show that this instance of une-
    qual treatment was prejudicial. Glenn Def. Marine (ASIA),
    720 F.3d at 907. To establish prejudicial error, a protestor
    must show that but for that error, the protestor had a sub-
    stantial chance of receiving a contract award. Alfa Laval
    Separation, Inc. v. United States, 
    175 F.3d 1365
    , 1367 (Fed.
    Cir. 1999). De minimis errors in the procurement process
    do not justify relief. Grumman Data Sys. Corp. v. Dalton,
    
    88 F.3d 990
    , 1000 (Fed. Cir. 1996); Lockheed Missiles &
    Space Co. v. Bentsen, 
    4 F.3d 955
    , 960 (Fed. Cir. 1993). Prej-
    udice is a question of fact that we review for clear error.
    CliniComp Int’l, Inc. v. United States, 
    904 F.3d 1353
    , 1359
    (Fed. Cir. 2018).
    The Claims Court found that ODG was not prejudiced
    by the VA’s disparate treatment. We see no error in this
    finding. Even if the VA awarded ODG the additional
    6 points it afforded to the awardee, ODG’s technical score
    would only increase to 18 points, well below the acceptable
    40-point threshold for award.
    In sum, many of ODG’s various claims of disparate
    treatment amount to a request for this court to reevaluate
    Case: 19-1337    Document: 70    Page: 11   Filed: 03/06/2020
    OFFICE DESIGN GRP. v. UNITED STATES                    11
    its technical proposal and those of the various awardees.
    We are in no position to do so. For the few instances in
    which the VA did engage in disparate treatment, ODG has
    failed to establish that such error was prejudicial.
    CONCLUSION
    We have considered ODG’s other arguments and find
    them unpersuasive. We affirm.
    AFFIRMED
    COSTS
    No costs.