Kellogg Brown & Root Services v. Secretary of the Army ( 2020 )


Menu:
  • Case: 19-1683     Document: 52    Page: 1   Filed: 09/01/2020
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    KELLOGG BROWN & ROOT SERVICES, INC.,
    Appellant
    v.
    SECRETARY OF THE ARMY,
    Appellee
    ______________________
    2019-1683
    ______________________
    Appeal from the Armed Services Board of Contract Ap-
    peals in Nos. 57530, 58161, Administrative Judge Mark A.
    Melnick, Administrative Judge Owen C. Wilson, Adminis-
    trative Judge Richard Shackleford.
    ______________________
    Decided: September 1, 2020
    ______________________
    EDWARD SANDERSON HOE, Covington & Burling LLP,
    Washington, DC, argued for appellant. Also represented
    by RAYMOND B. BIAGINI, HERBERT L. FENSTER; ALEJANDRO
    LUIS SARRIA, JASON NICHOLAS WORKMASTER, Miller &
    Chevalier Chartered, Washington, DC.
    DAVID W. TYLER, Commercial Litigation Branch, Civil
    Division, United States Department of Justice, Washing-
    ton, DC, argued for appellee. Also represented by ETHAN
    P. DAVIS, RUSSELL B. KINNER, WILLIAM JAMES GRIMALDI,
    ROBERT EDWARD KIRSCHMAN, JR., PATRICIA M. MCCARTHY,
    Case: 19-1683     Document: 52     Page: 2    Filed: 09/01/2020
    2      KELLOGG BROWN & ROOT SERVICES     v. SECRETARY OF THE
    ARMY
    MICHAL L. TINGLE, ANDY J. MAO, PATRICK KLEIN, II; CAROL
    MATSUNAGA, Defense Contract Management Agency, Car-
    son, CA; KARA KLAAS, Chantilly, VA.
    ______________________
    Before NEWMAN, DYK, and WALLACH, Circuit Judges.
    Opinion for the court filed by Circuit Judge DYK.
    Dissenting opinion filed by Circuit Judge NEWMAN.
    DYK, Circuit Judge.
    Kellogg Brown and Root Services, Inc. (“KBR”) con-
    tracted with the government to provide trailers to house
    coalition personnel at military camps in Iraq. KBR claimed
    that the government breached the contract by failing to
    provide “force protection” to the trucks delivering the trail-
    ers to the military camps. KBR sought to recover payments
    made to its subcontractor, First Kuwaiti Co. of Kuwait
    (“Kuwaiti”), for costs caused by the government’s alleged
    breach. The administrative contracting officer in large
    part denied the claim, and KBR appealed to the Armed Ser-
    vices Board of Contract Appeals (“Board”). The Board
    found that KBR was not entitled to any additional recovery
    and denied its appeal.
    We affirm the Board’s decision on the ground that the
    Board properly determined that KBR’s costs had not been
    shown to be reasonable, and we do not reach the question
    whether the government breached the “force protection”
    provision of the contract.
    BACKGROUND
    In 2001, the United States Army awarded Contract No.
    DAAA09-02-D-0007 (“Contract 0007”) in the U.S. Army’s
    Logistics Civil Augmentation Program (“LOGCAP III”) to
    KBR. Among other things, the contract required KBR to
    provide logistical support in the form of goods (such as
    trailers used for temporary housing) for the government
    Case: 19-1683     Document: 52     Page: 3    Filed: 09/01/2020
    KELLOGG BROWN & ROOT SERVICES     v. SECRETARY OF THE       3
    ARMY
    pursuant to a series of task orders. LOGCAP III contained
    a provision (“the Force Protection Clause”) requiring that
    the Army provide “force protection” for the contractor’s con-
    voys for providing these goods and services. It stated:
    H-16 Force Protection
    While performing duties [in accordance with] the
    terms and conditions of the contract, the Service
    Theatre Commander will provide force protection
    to contractor employees commensurate with that
    given to Service/Agency (e.g. Army, Navy, Air
    Force, Marine, DLA) civilians in the operations
    area unless otherwise stated in each task order.
    J.A. 242.
    In June 2003, the government executed Task Order 59,
    a cost-plus-fixed-fee order for KBR to provide support to
    operations in Iraq. This case concerns the government’s
    October 10, 2003, modification to Task Order 59 (“Change
    5”), which required KBR to “provide accommodations and
    life support services to [Command Joint Task Force 7
    (“CJTF7”)] and coalition forces in various locations in Iraq.”
    J.A. 291. The “accommodations and life support services”
    were trailers for temporary housing of Army personnel.
    Change 5 states that “[i]t is the Commander’s intent to rap-
    idly bed down the remainder of CJTF soldiers, building
    within battalion sets, simultaneously as opposed to sequen-
    tially, in accordance with established and provided priori-
    ties.”
    Id. KBR was originally
    required to furnish the
    trailers by December 15, 2003.
    The trailers were to be manufactured in Kuwait and
    then transported to Iraq by Kuwaiti in truck convoys. Sec-
    tion 1.10 of Change 5 again addressed the issue of force
    protection, stating that “[t]he government will provide for
    the security of contractor personnel in convoys and on site,
    commensurate with the threat, and [in accordance with]
    Case: 19-1683    Document: 52      Page: 4    Filed: 09/01/2020
    4      KELLOGG BROWN & ROOT SERVICES    v. SECRETARY OF THE
    ARMY
    the applicable Theater Anti-Terrorism/Force Protection
    guidelines.” J.A. 292.
    On October 17, 2003, KBR and Kuwaiti entered into a
    firm-fixed-price subcontract (“the Subcontract”) for the pro-
    curement and delivery of 2,252 trailers to Camp Anaconda
    in fulfillment of part of KBR’s obligations under Change 5.
    In accordance with Change 5, the Subcontract required Ku-
    waiti to complete performance by December 15, 2003, with
    “[a]llowances” in the event of “delays in KBR convoy coor-
    dination and support.” J.A. 1153. The Subcontract pro-
    vided that if KBR ordered any changes to performance that
    resulted in an increased cost of performance to Kuwaiti,
    Kuwaiti would be entitled to request an equitable adjust-
    ment. On December 13, 2003, KBR issued another change
    order, directing Kuwaiti to deliver and install an additional
    1,760 trailers to a second Army camp in Iraq, Camp Vic-
    tory.
    The Army’s failure to provide force protection in Iraq
    became an issue between the government and KBR, and
    another such dispute resulted in a previous Board decision
    finding that the Army failed to meet its force protection ob-
    ligations. See Sec’y of the Army v. Kellogg Brown & Root
    Servs., Inc., 779 F. App’x 716, 718 (Fed. Cir. 2019). As rel-
    evant here, the Board found that by late November of 2003,
    “dangerous conditions in Iraq” and “limitations upon the
    military’s resources to escort convoys” and the prioritiza-
    tion of other Army needs resulted in the failure to provide
    necessary force protection and convoy delays. J.A. 7.
    Kuwaiti alleged that the delays resulted in delivery de-
    lays and a backup of trailers at the Kuwait/Iraq border. It
    alleged that it was eventually required to store the trailers
    on rented land (a “laydown yard”) in Kuwait and incurred
    Case: 19-1683     Document: 52     Page: 5    Filed: 09/01/2020
    KELLOGG BROWN & ROOT SERVICES     v. SECRETARY OF THE       5
    ARMY
    costs for double handling, i.e., unloading and then reload-
    ing the trailers onto its trucks. 1 J.A. 7.
    On August 1, 2004, and August 4, 2004, KBR and Ku-
    waiti executed two change orders adding a total of
    $48,754,547.25 in equitable adjustments for idle truck
    costs due to the backup of trailers at the border and double-
    handling costs.
    As would be expected, KBR, as the prime contractor,
    then filed two requests for equitable adjustments with the
    government, asserting that it was entitled to recover the
    payment to Kuwaiti because the delay and double-han-
    dling costs were due to the government’s failure to provide
    the required force protection. The final amount sought by
    KBR, which included the $48,754,547.25 paid to Kuwaiti
    as well as indirect costs and the award fee, 2 totaled
    $51,273,482.
    On July 29, 2011, the administrative contracting of-
    ficer issued a final decision allowing $3,783,005 in costs as-
    sociated with the land leased to store the trailers (including
    indirect costs and award fees) but rejecting the remainder
    of KBR’s requested costs for delay and double handling.
    KBR timely appealed to the Board, arguing that it was
    entitled to recover the rejected delay costs and double-han-
    dling costs because the government violated the contract
    by failing to provide the required force protection. It
    1   “The term ‘double handling’ . . . refer[red] to both
    the transfer on and off trucks at the camps [due to delays
    in site preparation], as well as onto and off the [laydown
    yard].” J.A. 8.
    2   Under the Federal Acquisition Regulation (“FAR”),
    an “award fee” is “an award amount, based upon a judg-
    mental evaluation by the Government, sufficient to provide
    motivation for excellence in contract performance.” 48
    C.F.R. § 16.305.
    Case: 19-1683     Document: 52      Page: 6    Filed: 09/01/2020
    6      KELLOGG BROWN & ROOT SERVICES      v. SECRETARY OF THE
    ARMY
    argued that it was entitled to recover the disallowed costs
    ($47,490,477) and that these costs were reasonable.
    The Board found that KBR was not entitled to reim-
    bursement on the ground that the government had not
    breached the Force Protection Clause because “nothing in
    Change 5 required the government to place [Kuwaiti]’s
    trailers into convoys without delay.” J.A. 16. The Board
    further concluded that even if the government had
    breached the contract by failing to meet its force protection
    obligations, KBR had not shown that its settlement costs
    with Kuwaiti were reasonable. The Board concluded that
    (1) “KBR ha[d] not shown that a prudent person conducting
    a competitive business would have resolved [Kuwaiti]’s de-
    lay [equitable adjustment] based upon the model submit-
    ted by [Kuwaiti],” J.A. 21, and (2) for similar reasons, “KBR
    ha[d] not shown that its settlement of the double[-]han-
    dling [equitable adjustment] . . . was reasonable,” J.A. 22.
    The Board stated that KBR had failed to provide the actual
    costs incurred by Kuwaiti, as is typical in claims for equi-
    table adjustments in other contracts. Instead, KBR’s
    claimed costs were based solely on Kuwaiti’s estimates.
    The Board found that the damages models were “unrealis-
    tic,” “inconsistent,” “flaw[ed],” “unreasonable” and as-
    sumed a “perfect world.” J.A. 10, 17–18, 21. The Board
    concluded that “KBR [was] not entitled to any recovery.”
    J.A. 22.
    KBR appeals, and we have jurisdiction under 41 U.S.C.
    § 7107(a)(1)(A) and 28 U.S.C. § 1295(a)(10).
    DISCUSSION
    Our review of the Board’s decision is limited by statute.
    See 41 U.S.C. § 7107. We review the Board’s legal conclu-
    sions de novo, but we may only set aside a factual finding
    if it is “(A) fraudulent, arbitrary, capricious; (B) so grossly
    erroneous as to necessarily imply bad faith; or (C) not sup-
    ported by substantial evidence.”
    Id. § 7107(b). Contract
     interpretation is a question of law. Agility Logistics Servs.
    Case: 19-1683     Document: 52      Page: 7    Filed: 09/01/2020
    KELLOGG BROWN & ROOT SERVICES      v. SECRETARY OF THE       7
    ARMY
    Co. KSC v. Mattis, 
    887 F.3d 1143
    , 1148 (Fed. Cir. 2018).
    The reasonableness of a cost is a question of fact based on
    applicable legal principles. Kellogg Brown & Root Servs.,
    Inc. v. United States, 
    728 F.3d 1348
    , 1360 (Fed. Cir. 2013).
    I
    KBR argues that, under Change 5, the government was
    obligated to “furnish convoy escorts well before the
    [Change 5] deadlines,” Appellant’s Br. 19, and that but for
    the government’s breach, KBR would have been able to
    “meet the express dates for trailer installation,” Reply
    Br. 12. We need not reach the issue of whether the govern-
    ment breached the contract by failing to provide adequate
    force protection because the Board did not err in concluding
    that KBR’s claimed costs were not shown to be reasonable
    (a prerequisite to its requested relief). See Castle v. United
    States, 
    301 F.3d 1328
    , 1341 (Fed. Cir. 2002) (“[W]e find that
    [the plaintiffs] have not established their entitlement to
    damages . . . . Accordingly, . . . we expressly decline to con-
    sider the liability issue.”). In addressing the issue of cost
    reasonableness, we assume that the government was re-
    quired to provide reasonable force protection to enable
    KBR to timely perform under the contract. 3
    Before addressing the reasonableness issue, we note
    that the government argues on appeal that KBR was re-
    quired to submit not only the actual costs that KBR in-
    curred, but the actual costs incurred by its subcontractor,
    Kuwaiti. It argues that under the Subcontract, Kuwaiti
    was required to maintain “‘records [that] relate to cost re-
    imbursement,’ and provide to KBR ‘[c]opies of documents
    3   However, as the Board found, nothing in Change 5,
    including the Force Protection Clause, “constituted a guar-
    antee by the government that its convoy security would en-
    able KBR to comply” with the December 15, 2003,
    completion date. J.A 16.
    Case: 19-1683     Document: 52     Page: 8    Filed: 09/01/2020
    8      KELLOGG BROWN & ROOT SERVICES     v. SECRETARY OF THE
    ARMY
    and records supporting requests for payment.’” Appellee’s
    Br. 53 (alterations in original) (quoting J.A. 1166). The
    government’s reliance on the Subcontract is misplaced. As
    the government conceded at oral argument, the amounts
    paid by KBR to Kuwaiti were “costs” under the prime con-
    tract, and there is no provision in the prime contract that
    required KBR to submit the actual costs incurred by its
    subcontractor. KBR’s obligation was to show that the pay-
    ments to Kuwaiti were “reasonable.” See 48 C.F.R.
    § 31.201-2(a)(1). While the failure to collect and submit
    Kuwaiti’s costs bears on the reasonableness of the pay-
    ments, submission of the subcontractor’s costs is not a sep-
    arate requirement.
    The FAR provides:
    A cost is allowable only when the cost complies
    with all of the following requirements: (1) Reason-
    ableness . . . .
    Id. § 31.201-2(a). (a)
    A cost is reasonable if, in its nature and amount,
    it does not exceed that which would be incurred by
    a prudent person in the conduct of competitive
    business. Reasonableness of specific costs must be
    examined with particular care in connection with
    firms or their separate divisions that may not be
    subject to effective competitive restraints. No pre-
    sumption of reasonableness shall be attached to
    the incurrence of costs by a contractor. If an initial
    review of the facts results in a challenge of a spe-
    cific cost by the contracting officer or the contract-
    ing officer’s representative, the burden of proof
    shall be upon the contractor to establish that such
    cost is reasonable.
    (b) What is reasonable depends on a variety of con-
    siderations, including . . . [g]enerally accepted
    sound business practices, arm’s length bargaining,
    Case: 19-1683    Document: 52       Page: 9   Filed: 09/01/2020
    KELLOGG BROWN & ROOT SERVICES    v. SECRETARY OF THE       9
    ARMY
    and . . . [a]ny significant deviations from the con-
    tractor’s established practices.
    Id. § 31.201-3 (emphasis
    added).
    The FAR thus makes clear that the burden is on the
    contractor to establish the reasonableness of its costs and
    that there is no presumption of reasonableness. We have
    similarly explained that there is no presumption that a
    contractor is entitled to reimbursement “simply because it
    incurred . . . costs.” 
    Kellogg, 728 F.3d at 1363
    .
    A
    KBR only devotes two pages of its brief to defending the
    reasonableness of its costs and fails to describe in any de-
    tail KBR’s cost calculation methodology or why its method-
    ology was reasonable. This alone would justify affirmance,
    since KBR has not meaningfully briefed the issue. See
    SmithKline Beecham Corp. v. Apotex Corp., 
    439 F.3d 1312
    ,
    1320 (Fed. Cir. 2006). We nevertheless have looked to
    KBR’s justifications for its claimed costs (as argued to the
    Board) to determine whether the costs were reasonable.
    We begin with KBR’s arguments directed to the alleged de-
    lays at the Iraq/Kuwait border.
    KBR stated that the claimed costs related to delays
    were not based on documented costs incurred by Kuwaiti,
    but were instead estimated “based upon 83,078 days of idle
    truck time and a truck and driver daily cost rate of $300.”
    J.A. 2928. We briefly describe how KBR arrived at those
    numbers. 4
    Under Change 5, KBR was required to deliver 2,252
    trailers to Camp Anaconda and 1,760 trailers to Camp
    4  In its certified claim, KBR used the same estimates
    that Kuwaiti used in its original request for equitable ad-
    justments. For convenience, we refer to these as KBR’s es-
    timates.
    Case: 19-1683    Document: 52     Page: 10    Filed: 09/01/2020
    10     KELLOGG BROWN & ROOT SERVICES    v. SECRETARY OF THE
    ARMY
    Victory by December 15, 2003. It was understood as a prac-
    tical matter that the delivery of the trailers would occur
    over the entire period of performance. KBR began with the
    assumption that, if the government had provided adequate
    force protection, Kuwaiti would have delivered a uniform
    number of trailers each day to each camp. Under this as-
    sumption, KBR estimated that it would have delivered 135
    and 58 trailers per day for Camp Victory and Camp Ana-
    conda, respectively, to complete the deliveries in accord-
    ance with the December 15, 2003, deadline in Change 5.
    This translated to an assumption that 193 trucks would
    have crossed the Iraq/Kuwait border each day during the
    original period of performance. We refer to this as the “uni-
    form rate assumption.”
    KBR then assumed that any deviation from the uni-
    form rate assumption was attributable to government-
    caused delay. To calculate the number of supposedly idle
    trucks on a particular day, KBR subtracted the total num-
    ber of trucks that had crossed the border (from the start
    date of the Subcontract up to that day) from the total num-
    ber of trucks that would have crossed the border under the
    uniform rate assumption. For example, if, on a particular
    day, Kuwaiti’s records showed that a total of 100 trucks
    had crossed the border, but 193 trucks would have crossed
    the border under the uniform rate assumption, KBR’s
    model would claim 93 idle truck days. KBR then multiplied
    the total number of idle truck days by $300, which it
    adopted as a “reasonable market price for idle trucks based
    upon a review of other business KBR conducted.” J.A. 17.
    There are several reasons why KBR’s model is not a
    reasonable cost calculation—each of which, standing alone,
    is sufficient to defeat its claims.
    First, contrary to KBR’s model, the Board found that
    Kuwaiti “did not always have the number of trucks availa-
    ble at the border dictated by the model or have access to
    the model’s required number of trucks.” J.A. 10. “In fact,
    Case: 19-1683    Document: 52     Page: 11    Filed: 09/01/2020
    KELLOGG BROWN & ROOT SERVICES    v. SECRETARY OF THE      11
    ARMY
    it was not known where all the trucks were at any given
    time.”
    Id. A December 15,
    2003, email from the Operations
    Manager at Camp Anaconda stated that Kuwaiti did not
    have trailers ready at the border, and that, “[w]hile [Ku-
    waiti] may have [had] hundreds of trailers waiting at the
    border, they apparently [were] not bound for [Camp] Ana-
    conda.” J.A. 4065. KBR assumed “perfect performance
    where everything worked flawlessly” on the part of Kuwaiti
    (despite records showing the contrary). J.A. 10. As the
    Board found, “KBR has not demonstrated that [the] model
    approximates the actual events that occurred.” J.A. 18.
    Indeed, the Board found that KBR’s estimates as to the
    number of trucks at the border were inconsistent with the
    only evidence that KBR did submit. For example, “[Ku-
    waiti] reported on December 2, 2003, that it had 150 trucks
    waiting, but the model charged for 403 [idle truck days].”
    J.A. 10. The Board noted that “[Kuwaiti] and KBR also
    maintained status reports showing the number of trailers
    waiting at the border on specific days, and a Delivery Re-
    port for particular days showing the number of trailers
    waiting on trucks,” and that “[t]hese reports generally
    showed lower numbers than” KBR’s estimates.
    Id. Finally, the Board
    cited “numerous communications” attached to
    the request for equitable adjustment “discussing signifi-
    cantly different numbers of trucks and trailers available at
    the border than shown in the [KBR] model.”
    Id. KBR pro- vided
    no explanation for why its model could be reliable
    when it was “inconsistent” with the records that Kuwaiti
    did maintain. J.A. 9.
    Second, KBR’s model “assumed [that] every truck ar-
    riving at the [Iraq/Kuwait] border would be placed into a
    convoy for Iraq the very next day” and that all delays at the
    border were the result of inadequate government force pro-
    tection. J.A. 10. In fact, substantial evidence supported
    the Board’s findings that other factors outside of the gov-
    ernment’s control (in addition to KBR’s delay in providing
    trucks at the border) contributed to delays. See Sauer Inc.
    Case: 19-1683    Document: 52     Page: 12    Filed: 09/01/2020
    12     KELLOGG BROWN & ROOT SERVICES    v. SECRETARY OF THE
    ARMY
    v. Danzig, 
    224 F.3d 1340
    , 1348 (Fed. Cir. 2000) (“[T]o es-
    tablish a compensable delay, a contractor must separate
    government-caused delays from its own delays.”). Even
    with “unlimited force protection assets, security threats
    and other constraints, such as the status of communication
    lines,” “intelligence [reported] that the roads were too dan-
    gerous for travel at all,” and insurgent attacks could delay
    the delivery of the trailers. J.A. 6. Yet KBR assigned every
    delay at the border to the lack of force protection without
    attempting to disaggregate the causes of those delays.
    KBR’s assumption was simply “not realistic.” J.A. 10.
    Third, KBR’s spreadsheets calculating idle truck days,
    “without substantiating data or records,” were insufficient
    to establish the reasonableness of its costs. J.A. 9. KBR
    offered no fact or expert witnesses to support the reasona-
    bleness of its estimated number of idle truck days. Alt-
    hough Change 5 did not require KBR to provide actual
    costs to support its claim, the Board properly determined
    that KBR’s failure to provide any supporting data was fatal
    to its claim. Under KBR’s contract with Kuwaiti, Kuwaiti
    was obligated to “maintain books and records” reflecting
    actual costs, and KBR had the right to “inspect and audit”
    those records. J.A. 1166. As the Board found, it was simply
    not plausible that Kuwaiti did not record “how long trucks
    actually waited” at the border, J.A. 18, and KBR made no
    attempt to access or utilize these records. At bare mini-
    mum, KBR was required to support its estimates with rep-
    resentative data as to the number of trucks actually
    delayed. In fact, KBR supplied no representative data
    whatsoever. Without further evidence demonstrating the
    reliability of KBR’s estimates, the Board properly found
    that KBR’s claimed costs were not reasonable.
    Fourth, KBR only offered conclusory testimony, unsup-
    ported by any data or evidence in the record, that the daily
    rate of $300 was a reasonable “composite rate” for each
    truck, trailer, and driver, “based on [KBR’s] market re-
    search and . . . pricing data available . . . at the time.”
    Case: 19-1683    Document: 52      Page: 13     Filed: 09/01/2020
    KELLOGG BROWN & ROOT SERVICES     v. SECRETARY OF THE       13
    ARMY
    J.A. 3002. In fact, KBR knew (from the redacted truck
    leases submitted by Kuwaiti) that Kuwaiti had records
    showing more precise daily costs for its idle trucks. The
    Board found that “[i]t simply strain[ed] credulity” that Ku-
    waiti, a “sophisticated company” having “over 70 subcon-
    tracts with KBR alone,” would “not record how much it
    actually paid its drivers while they waited at the bor-
    der . . . , especially given that it would ultimately seek mil-
    lions of dollars in additional compensation for these
    events.” J.A. 18. At oral argument, the only reason KBR
    gave for its failure to inquire into the costs charged by Ku-
    waiti was that it “wanted to move this matter along.” Oral
    Arg. at 40:08–12. The Board properly concluded that
    KBR’s testimony did not establish what Kuwaiti “actually
    paid to lease the trucks (which [Kuwaiti] knew but did not
    disclose) and how much it actually paid its drivers.”
    J.A. 18.
    Finally, KBR charged a $300 rate for all claimed delay
    days, implicitly assuming that each trailer was always at-
    tached to a truck with a driver. This was despite the fact
    that Kuwaiti was also claiming double-handling costs for
    the trailers, which it claimed were offloaded and stored—
    unattached to any trucks—in its laydown yard. The basis
    for claiming additional delay costs related to drivers and
    trucks for such stored trailers was not explained and, as
    the Board found, “ignored the fact that, once [Kuwaiti] pro-
    cured land for a laydown yard at the border, it removed the
    trailers from trucks and placed them in the yard, relieving
    at least some trucks and drivers from having to remain idle
    the entire time the trailers were delayed.” J.A. 18.
    In Kellogg, another case between the same parties,
    KBR “declined to present independent evidence of the rea-
    sonableness of . . . [its] costs.” 
    Kellogg, 728 F.3d at 1363
    .
    We held that KBR failed to satisfy its burden of proving the
    reasonableness of its costs.
    Id. The record in
    this case
    leads to the same result. Despite having ample oppor-
    tunity to do so, KBR supplied no meaningful evidence to
    Case: 19-1683     Document: 52    Page: 14    Filed: 09/01/2020
    14       KELLOGG BROWN & ROOT SERVICES   v. SECRETARY OF THE
    ARMY
    the Board showing the reasonableness of its costs, nor has
    it explained the inconsistencies between its proposed cost
    model and the factual record.
    We conclude that the Board’s determination that KBR
    had failed to demonstrate that its delay costs were reason-
    able was supported by substantial evidence.
    B
    We turn to KBR’s costs related to double handling.
    Here, KBR sought reimbursement for the cost of the entire
    facility used to store the trailers, apparently on the theory
    that every cost related to the facility was attributable to
    the alleged government delay. 5 In this respect, KBR’s dou-
    ble-handling claim suffered from many of the same defi-
    ciencies as its delay claim. There were, in addition, other
    deficiencies.
    KBR failed to support the reasonableness of its claimed
    costs with any record evidence. Although KBR stated that
    it “engaged . . . procurement personnel to obtain pricing
    from sources other than [Kuwaiti] to negotiate the double[-
    ]handling claim,” J.A. 2927, its certified claim for double-
    handling costs contained only spreadsheets summarizing
    monthly costs. KBR never submitted pricing data from its
    other sources.
    Not only was the pricing not supported—the descrip-
    tion of the work performed was lacking in necessary detail
    or described work unrelated to any government-caused de-
    lay. Kuwaiti had claimed costs related to “skilled workers,”
    at various rates (ranging from $2,000 to $3,500 per person
    per month) without explaining what these workers did, or
    5   KBR also sought costs related to double handling
    due to “late site preparation.” J.A. 21. As with KBR’s other
    double-handling costs, it failed to support these claimed
    costs with adequate data.
    Case: 19-1683    Document: 52       Page: 15   Filed: 09/01/2020
    KELLOGG BROWN & ROOT SERVICES      v. SECRETARY OF THE     15
    ARMY
    even what their “skills” were. J.A. 8. Kuwaiti also charged
    $3,090,750 in “Repair Cost Consequent on Double Han-
    dling [sic].” J.A. 4798. The administrative contracting of-
    ficer noted that, while “some damage [to the trailers] will
    occur during double handling,” “some of the damage
    charged [for] in the [equitable adjustment] was also appar-
    ently attributed to vandalism.” J.A. 1892. KBR’s submis-
    sions to the Board “did not describe any [double-handling]
    repairs, or what might have happened to require any [re-
    pairs].” J.A. 8. KBR simply made no effort to “field verify
    any additional equipment, manpower, protection, land
    preparation, repairs, and double installations” from the
    double handling. J.A. 12.
    KBR itself expressed concern with the reasonableness
    of Kuwaiti’s proposed double-handling costs, stating that
    Kuwaiti’s quoted prices were “too high” and that “if this
    was a claim and if this was being assessed as per the
    FAR[] . . . there would be a very high possibility that this
    would be dismissed.” J.A. 4800. KBR also noted during its
    negotiations with Kuwaiti that “the numbers [of trailers]
    that were said to have been repaired daily . . . [did] not add
    up.” J.A. 4801.
    Under these circumstances, we conclude that the
    Board did not err in finding that KBR had failed to prove
    the reasonableness of its double-handling costs.
    II
    KBR finally argues on appeal that the Board failed to
    apply the “jury verdict” method. The jury verdict method
    is “not favored and may be used only when other, more ex-
    act, methods cannot be applied.” Dawco Const., Inc. v.
    United States, 
    930 F.2d 872
    , 880 (Fed. Cir. 1991), overruled
    on other grounds by Reflectone, Inc. v. Dalton, 
    60 F.3d 1572
     (Fed. Cir. 1995). As previously discussed, KBR has not
    shown that other, more exact, methods were unavailable.
    We affirm the Board’s holding that “[t]he jury verdict
    Case: 19-1683   Document: 52    Page: 16    Filed: 09/01/2020
    16     KELLOGG BROWN & ROOT SERVICES   v. SECRETARY OF THE
    ARMY
    method does not relieve KBR from FAR Part 31’s limitation
    of its recovery to costs that are reasonable.” J.A. 21.
    AFFIRMED
    Case: 19-1683     Document: 52     Page: 17   Filed: 09/01/2020
    United States Court of Appeals
    for the Federal Circuit
    ______________________
    KELLOGG BROWN & ROOT SERVICES, INC.,
    Appellant
    v.
    SECRETARY OF THE ARMY,
    Appellee
    ______________________
    2019-1683
    ______________________
    Appeal from the Armed Services Board of Contract Ap-
    peals in Nos. 57530, 58161, Administrative Judge Mark A.
    Melnick, Administrative Judge Owen C. Wilson, Adminis-
    trative Judge Richard Shackleford.
    ______________________
    NEWMAN, Circuit Judge, dissenting.
    With the expedition of United States forces to Iraq, the
    Army contracted with Kellogg Brown & Root Services, Inc.
    (“KBR”) for various services including the provision of pre-
    fabricated housing for thousands of troops. As described
    by the Armed Services Board of Contract Appeals
    (“ASBCA”), 1 “soldiers slept wherever they could
    1   Kellogg Brown & Root Servs., Inc., ASBCA No.
    57530, 19-1 BCA ¶ 37,205, 
    2018 WL 6431434
    (Nov. 19,
    2018) (“ASBCA Op.”).
    Case: 19-1683    Document: 52      Page: 18    Filed: 09/01/2020
    2      KELLOGG BROWN & ROOT SERVICES     v. SECRETARY OF THE
    ARMY
    in . . . abandoned schools, . . . tents, vehicles, the ground,
    or any other place soldiers could put a sleeping bag.”
    ASBCA Op. at 2. By contract LOGCAP III, KBR would
    “provide accommodations and life support services to [the
    soldiers] and coalition forces in various locations in
    Iraq . . . to rapidly bed down the remainder of [the sol-
    diers].” J.A. 291. This “Bed Down Mission” was a priority
    Army activity, scheduled to be completed before Christmas
    2003, for reasons of both morale and military prepared-
    ness. The ASBCA reports that over 18,000 such living
    trailers were included, for multiple military locations.
    ASBCA Op. at 2.
    KBR and subcontractor First Kuwaiti Trading Com-
    pany (“FKTC”) designed, furnished, equipped, and brought
    to the Kuwait-Iraq border the contracted living trailers.
    However, delivery was often delayed due to unavailability
    of military force protection for convoys and installation.
    KBR paid an equitable adjustment to FKTC for this delay,
    but the ASBCA denied reimbursement to KBR, on the
    grounds that the government had not breached its obliga-
    tion to provide force protection, and also that KBR had em-
    ployed an incorrect methodology for calculating the
    equitable adjustment.
    On KBR’s appeal, my colleagues on this panel, while
    correctly rejecting the ASBCA’s reasons for denying com-
    pensation as contrary to the contract, nonetheless err in
    implementing the correct standard. My colleagues hold
    that the correct standard is “reasonableness,” and while
    complaining about the absence of evidence and witnesses
    and argument on this standard, my colleagues make exten-
    sive findings on information that has not been presented,
    and decide the issue of reasonableness without participa-
    tion of the parties.
    Thus the panel majority now finds that our new stand-
    ard is not met, and denies all reimbursement. From this
    Case: 19-1683    Document: 52      Page: 19     Filed: 09/01/2020
    KELLOGG BROWN & ROOT SERVICES     v. SECRETARY OF THE         3
    ARMY
    flawed procedure and incorrect result, I respectfully dis-
    sent.
    DISCUSSION
    At issue in this appeal is the measure of damages for
    government-caused delay in performance of the contract to
    provide 2,252 living trailers for installation at Camp Ana-
    conda by December 15, 2003, and 1,760 trailers for Camp
    Victory with completion extended to January 1, 2004. KBR
    and its subcontractors designed, obtained, furnished,
    equipped, and trucked the trailers to the Kuwait-Iraq bor-
    der. The war was active, and transport along the main sup-
    ply route from Kuwait was under attack, as the ASBCA
    reported:
    Because there was a war on, MSR [Main Supply
    Route] Tampa was extremely dangerous. Insur-
    gent attacks began in the spring of 2003 and people
    were shot and killed. Among those who frequently
    lost their lives were KBR affiliate personnel. . . . In
    June 2003, the military imposed movement re-
    strictions, requiring military control and escorts
    into Iraq of all assets, including contractors.
    ASBCA Op. at 4–5 (internal citations omitted). The KBR
    contract and subcontracts required the government to pro-
    vide force protection for delivery and installation of the
    trailers:
    H-16 Contractor Force Protection
    While performing duties [in accordance with] the
    terms and conditions of the contract, the Service
    Theater Commander will provide force protection
    to contractor employees commensurate with that
    given to Service/Agency (e.g. Army, Navy, Air
    Force, Marine, DLA) civilians in the operations
    area unless otherwise stated in each task order.
    Case: 19-1683    Document: 52      Page: 20     Filed: 09/01/2020
    4      KELLOGG BROWN & ROOT SERVICES      v. SECRETARY OF THE
    ARMY
    J.A. 242; see also J.A. 1157 (Subcontract 11, Prime Con-
    tract). The ASBCA found that “[b]ecause of the dangerous
    conditions in Iraq, and the limitations upon the military’s
    resources to escort convoys, trailers backed up at the Ku-
    wait/Iraq border waiting for escorts.” ASBCA Op. at 6. De-
    spite the priority of the Bed Down Mission, due to delays
    in military force protection the delivery of living trailers to
    Camp Victory was not completed until May 10, 2004, and
    to Camp Anaconda on June 28, 2004.
    By its subcontract, FKTC was entitled to an equitable
    adjustment if government or KBR delay caused substan-
    tially increased cost or time of performance:
    § 3.2.5. If [FKTC’s] performance of the Sublet
    Work is delayed by [the government or KBR’s] fail-
    ure to perform their obligations hereunder, or by
    orders of [KBR] delaying or suspending the work,
    [FKTC] shall be entitled to an equitable adjust-
    ment in the compensation or time of performance,
    or both, if the delay substantially increases the cost
    to [FKTC] of the Sublet Work or the time that
    [FKTC’s] equipment and forces are required at the
    site.
    J.A. 1162 (LOGCAP III); see also J.A. 1176–77 (Subcon-
    tract 11, Special Provisions, §§ 4.2, 4.4).
    The ASBCA acknowledged that “Under the subcon-
    tract, KBR was responsible for paying an ‘equitable adjust-
    ment’ to FKTC in the event of a government performance
    failure causing delay.” ASBCA Op. at 16. KBR and FKTC
    negotiated this adjustment, and KBR paid the negotiated
    amount. However, the ASBCA refused to reimburse KBR
    for this payment, or any portion thereof. That is the subject
    of this appeal.
    A
    It is not disputed that five to eight months of delays in
    delivery occurred due to the unavailability of force
    Case: 19-1683   Document: 52     Page: 21    Filed: 09/01/2020
    KELLOGG BROWN & ROOT SERVICES   v. SECRETARY OF THE      5
    ARMY
    protection, and that trailers “piled up” at the Kuwait-Iraq
    border. It is not disputed that heavy costs were incurred:
    costs of storage, handling, maintenance, repairs, person-
    nel, and vandalism. KBR and FKTC agreed to the adjust-
    ment methodology of a fixed sum of $300 per delay day per
    trailer. The ASBCA disapproved of this methodology as
    not in conformity with the Federal Acquisition Regulation
    (“FAR”), and held that none of the equitable adjustment
    would be reimbursed.
    I agree with my colleagues that the ASBCA applied an
    incorrect standard for measuring delay damages. As the
    majority reports, at the oral argument of this appeal the
    government conceded that “there is no provision in the
    prime contract that required KBR to submit the actual
    costs incurred by its subcontractor.” Maj. Op. at 8. Thus I
    agree that the ASBCA’s decision must be vacated.
    I also agree that the correct standard is “reasonable-
    ness.” However, my colleagues do not remand for applica-
    tion by the ASBCA of this standard; they do not discuss
    whether the methodology used by KBR was reasonable, alt-
    hough this aspect was the subject of testimony at the
    ASBCA; and they do not consider whether any of the costs
    of delay were reasonable in the circumstances that existed.
    Instead, my colleagues extract isolated costs from un-
    briefed documents, and rule, with no briefing and no argu-
    ment, that reasonableness was not shown.
    Although KBR requested remand to the ASBCA if this
    court agrees that the ASBCA’s decision should be reversed,
    remand is not provided. KBR has no opportunity to meet
    this court’s new standard. Instead, my colleagues scavenge
    among assorted materials that were provided in other con-
    texts, and complain about the absence of evidence and ex-
    pert testimony related to the court’s new standard.
    B
    The ASBCA also held that “nothing in Change 5 re-
    quired the government to place FKTC’s trailers into
    Case: 19-1683    Document: 52     Page: 22    Filed: 09/01/2020
    6      KELLOGG BROWN & ROOT SERVICES    v. SECRETARY OF THE
    ARMY
    convoys without delay.” ASBCA Op. at 15. The govern-
    ment argues that FKTC “assumed the risk” of delay, and
    that the government had not breached its contractual obli-
    gation to provide force protection. That is incorrect, and in
    a related case concerning the same contract, the ASBCA
    held that the government’s failure to provide force protec-
    tion was indeed a breach of contract.
    In companion litigation on the same contract require-
    ment, the ASBCA found that the government breached its
    contract obligation, when the Army “did not have sufficient
    resources to provide . . . protection to KBR[ ].” Kellogg
    Brown & Root Servs., Inc., ASBCA No. 56358, 17-1 BCA ¶
    36,779, 
    2017 WL 2676674
    (June 8, 2017).
    The Federal Circuit affirmed that the contract was
    breached by the Army’s insufficiency “to provide military
    escorts for its contractors and several KBR employees and
    subcontractors were killed in the attacks,” stating that the
    breach “eviscerated the promise at the heart” of the con-
    tract. Sec’y of the Army v. Kellogg Brown & Root Servs.,
    Inc., 779 F. Appx 716, 717, 719 (Fed. Cir. 2019).
    That final decision estops the government’s present ar-
    gument that the failure to provide force protection did not
    breach the contract. My colleagues state that they do not
    reach the question of breach, but they nonetheless appear
    to give weight to the government’s argument that it was
    the war, not the government, that caused the Army’s de-
    lays in providing force security. The government states
    that the delays were due to “efforts to militarily secure the
    country, discovery of explosives on the roads, and other rea-
    sons that inevitably occur while performing such opera-
    tions over the extended distances in a warzone,” Govt. Br.
    19 (internal quotation marks omitted).
    The panel majority agrees that “factors outside of the
    government’s control” contributed to the delays, and ap-
    pears to deem such factors to weigh on the side of withhold-
    ing the contract-mandated adjustment for delays in
    delivery and installation of the living trailers. Maj. Op. at
    Case: 19-1683   Document: 52     Page: 23   Filed: 09/01/2020
    KELLOGG BROWN & ROOT SERVICES   v. SECRETARY OF THE     7
    ARMY
    11. However, an equitable adjustment is required by con-
    tract, and reinforced by the breach.
    C
    The issue before the ASBCA was the reasonableness of
    the methodology used to measure the equitable adjustment
    that KBR paid. The ASBCA held that the FAR requires
    actual costs and payments, and rejected the KBR method-
    ology of negotiating a daily lump sum.
    KBR summarized that costs arose from the delay-re-
    quired storage, maintenance, handling, and repairs of
    trailers and trucks, as well as personnel costs and site
    preparation and installation. KBR argued to the ASBCA
    that its methodology was reasonable. Although my col-
    leagues reject the ASBCA’s requirement of detailed cost
    and payment records, my colleagues criticize the pieces of
    cost data that they can scour from various documents, and
    summarily deny all recovery. The court complains about
    the absence of evidence and expert testimony 2—although
    the court does not remand for evidence and expert testi-
    mony.
    The court denies KBR the opportunity to demonstrate
    reasonableness, and appears to require the same degree of
    detail for which the court has reversed the ASBCA. The
    court criticizes the absence of detailed evidence, stating
    that “KBR only devotes two pages of its brief to defending
    the reasonableness of its costs.” Maj. Op. at 9. The court
    ignores that KBR’s action in the ASBCA was to support the
    methodology by which it settled the equitable adjustment
    2   The panel majority complains that “KBR offered no
    fact or expert witnesses to support the reasonableness of
    its estimated number of idle truck days,” Maj. Op. at 12.
    There indeed were expert witnesses, arguing for the rea-
    sonableness of the settlement methodology based on a fixed
    daily cost and the number of delay-days. KBR Br. 36.
    Case: 19-1683    Document: 52      Page: 24     Filed: 09/01/2020
    8      KELLOGG BROWN & ROOT SERVICES      v. SECRETARY OF THE
    ARMY
    owed to FKTC, not to meet this court’s new and undefined
    reasonableness standard.
    The panel majority concludes that KBR is entitled to
    no recovery at all, although there was no hearing, no testi-
    mony, no briefing, and no argument on the court’s new
    standard—either to clarify this standard, or to provide ev-
    idence to which the standard is applied.
    Instead, my colleagues cite records not presented for
    this purpose, and complain of their inadequacy. The vari-
    ous spreadsheets were presented to the ASBCA to support
    the argument that the methodology that was used was rea-
    sonable. There is no record for whatever standard of rea-
    sonableness the court now intends.
    For example, in the criticized “two pages” on reasona-
    bleness in KBR’s brief, KBR states that “the record at the
    ASBCA contained ample evidence upon which it could have
    calculated a ‘fair, equitable and reasonable amount’ of com-
    pensation” by the jury verdict method. KBR Br. 36. The
    majority does not mention KBR’s evidence “including five
    delay day models, reports and testimony from multiple ex-
    pert witnesses and the [Administrative Contracting Of-
    ficer’s] initial, unbridled conclusion that KBR was entitled
    to recover at least $25.5 million.”
    Id. The Administrative Contracting
    Officer had found that the methodology that
    was used reflected “commercial procedures” and that “ade-
    quate price analysis was provided.” ASBCA Op. at 10 (al-
    terations omitted).
    Precedent illustrates that when there is question con-
    cerning the method of determining compensable costs, this
    “[does not] mandate that Delco recover nothing.” Delco El-
    ecs. Corp. v. United States, 
    17 Cl. Ct. 302
    , 324 (1989), aff’d,
    
    909 F.2d 1495
    (Fed. Cir. 1990). The jury verdict method
    has served to determine an “appropriate amount for a rea-
    sonable recovery” that is a fair approximation of damages
    “in light of all the facts.”
    Id. at 323–24.
    In Delco this
    method was invoked to determine damages in the absence
    Case: 19-1683    Document: 52     Page: 25    Filed: 09/01/2020
    KELLOGG BROWN & ROOT SERVICES    v. SECRETARY OF THE       9
    ARMY
    of adequate cost and pricing data—the issue on which my
    colleagues now focus.
    KBR has requested remand, to provide the opportunity
    to establish “fair, equitable, and reasonable” compensation.
    At issue is not only the resolution of this case; at issue is
    the public’s confidence in fair, equitable, and reasonable
    government dealings with those who are willing to provide
    their expertise and resources to the nation.
    I respectfully dissent.