Vermont Yankee Nuclear Power Corp. v. Entergy Nuclear Vermont Yankee, LLC , 683 F.3d 1330 ( 2012 )


Menu:
  •   United States Court of Appeals
    for the Federal Circuit
    __________________________
    VERMONT YANKEE NUCLEAR POWER
    CORPORATION,
    Plaintiff-Cross Appellant,
    v.
    ENTERGY NUCLEAR VERMONT YANKEE, LLC,
    AND ENTERGY NUCLEAR OPERATIONS, INC.,
    Plaintiffs-Cross Appellants,
    v.
    UNITED STATES,
    Defendant-Appellant.
    __________________________
    2011-5033, -5034, -5042
    __________________________
    Appeals from the United States Court of Federal
    Claims in consolidated case nos. 02-CV-898 and 03-CV-
    2663, Judge Thomas C. Wheeler.
    __________________________
    Decided: June 13, 2012
    ___________________________
    RICHARD J. CONWAY, Dickstein Shapiro LLP, of Wash-
    ington, DC, argued for plaintiff-cross appellant, Vermont
    Yankee Nuclear Power Corporation, of Washington, DC.
    VERMONT YANKEE NUCLEAR POWER     v. US                    2
    BRAD FAGG, Morgan, Lewis & Bockius LLP, of Wash-
    ington, DC, argued for plaintiffs cross appellants Entergy
    Nuclear Operations, Inc., et al. Of counsel on the brief
    was L. JAGER SMITH, Wise, Carter, Child & Caraway,
    P.A., of Jackson, Mississippi.
    ANDREW P. AVERBACH, Trial Attorney, United States
    Department of Justice, of Washington, DC, argued for
    defendant-appellant. With him on the brief were TONY
    WEST, Assistant Attorney General, JEANNE E. DAVIDSON,
    Director, and HAROLD D. LESTER, JR., Assistant Director
    Of counsel on the brief were MARIAN E. SULLIVAN,
    JEREMIAH M. LUONGO, MARIANA T. ACEVEDO, SETH W.
    GREENE, JOSEPH D. KELLER, and DANIEL G. KIM, Trial
    Attorneys; and JANE K. TAYLOR, Office of General Coun-
    sel, United States Department of Energy, of Washington,
    DC.
    KYLE H. LANDIS-MARINELLO, Assistant Attorney Gen-
    eral, Office of the Attorney General, State of Vermont,
    Montpelier, Vermont, for amicus curiae. With him on the
    brief was GAVIN J. BOYLES, Assistant Attorney General.
    __________________________
    Before BRYSON, MAYER, and DYK, Circuit Judges.
    Opinion for the court filed by Circuit Judge DYK, in which
    Circuit Judge MAYER joins except for Part I(C), and in
    which Circuit Judge BRYSON joins except for Part III (B),
    (D), and (F). Opinions dissenting in part filed by Circuit
    Judges MAYER and BRYSON.
    DYK, Circuit Judge.
    This case involves the federal government’s breach of
    a contract requiring it to accept for disposal spent nuclear
    fuel generated at the Vermont Yankee Nuclear Power
    3                     VERMONT YANKEE NUCLEAR POWER     v. US
    Station (“VYNPS”). The government, the current owner
    of VYNPS, Entergy Nuclear Vermont Yankee, LLC
    (“ENVY”), 1 and the former owner of VYNPS, Vermont
    Yankee Nuclear Power Corporation (“Vermont Yankee”),
    each appeal from a judgment of the Court of Federal
    Claims (“Claims Court”) awarding damages to ENVY for
    breach of the contract. Because the government agrees
    that it breached the contract, all issues on appeal concern
    either the assignment of the contract (or contract claims)
    from Vermont Yankee to ENVY or the measure of dam-
    ages.
    In Part I of this opinion, we hold that Vermont Yan-
    kee validly assigned to ENVY pre-existing claims against
    the government under the Standard Contract for Disposal
    of Spend Nuclear Fuel and/or High-Level Radioactive
    Waste, 
    10 C.F.R. § 961.11
     (1984) (hereinafter “Standard
    Contract”). We also hold that while the partial assign-
    ment of rights and duties under the Standard Contract
    from Vermont Yankee to ENVY was not valid, the gov-
    ernment nonetheless waived its right to object to the
    partial assignment.
    In Part II, we hold that the scope of the assignment
    from Vermont Yankee to ENVY encompassed the claims
    Vermont Yankee asserted against the government, in-
    cluding the claim for pre-sale mitigation costs and the
    claim for the diminution in value of VYNPS.
    In Part III, we hold that legal and lobbying fees in-
    curred by ENVY to secure approval from the State of
    Vermont for a dry storage facility were foreseeable. We
    hold, however, that other state-imposed requirements
    were not foreseeable, and hence not recoverable, including
    1    ENVY’s sister company, Entergy Nuclear Opera-
    tions, Inc., also joins ENVY as a Plaintiff-Cross Appellant.
    For simplicity, we refer only to ENVY in this opinion.
    VERMONT YANKEE NUCLEAR POWER       v. US                     4
    payments into Vermont’s Clean Energy Development
    Fund, performance of a flood analysis, and construction of
    a visual barrier to the dry storage facility.
    In Part IV, we hold that ENVY did not meet its bur-
    den of proof with respect to its claimed damages for the
    costs of disposing of contaminated material discovered
    due to the breach and the characterization of spent fuel
    moved to dry storage.
    In Part V, we discuss the remaining issues, which are
    for the most part controlled by our recent precedents. In
    accordance with those precedents, we hold that ENVY is
    not entitled to recover its cost of capital to fund its mitiga-
    tion activities. And while we hold that ENVY is entitled
    to recover its capital suspense loader overhead costs, we
    hold that, due to insufficient argument on appeal, ENVY
    is not entitled to recover its Resource Code 19 payroll
    loader overhead costs.
    BACKGROUND
    This is another in a long series of cases in which the
    government breached a commitment for the disposal of
    spent nuclear fuel (“SNF”) and high-level radioactive
    waste (“HLW”). Briefly, the background is as follows. In
    1983, Congress enacted the Nuclear Waste Policy Act of
    1982 (“NWPA”), Pub. L. No. 97-425, 
    96 Stat. 2201
     (1983)
    (codified as amended at 
    42 U.S.C. §§ 10101-10270
     (2006)).
    The NWPA authorized the Department of Energy (“DOE”)
    to enter into contracts with nuclear facilities for the
    disposal of SNF and HLW. 
    42 U.S.C. § 10222
    . Congress
    expressly mandated that, under the terms of the con-
    tracts, DOE accept SNF and HLW “beginning not later
    than January 31, 1998.” 
    Id.
     § 10222(a)(5)(B). Contem-
    plating the potential sale of nuclear facilities, the NWPA
    also provided that “[t]he rights and duties of a party to a
    contract entered into under this [Act] may be assignable
    5                    VERMONT YANKEE NUCLEAR POWER     v. US
    with transfer of title to the spent nuclear fuel . . . in-
    volved.” Id. § 10222(b)(3).
    Pursuant to its authority under the NWPA, DOE
    promulgated regulations defining the terms of the Stan-
    dard Contract to be executed with nuclear facilities. See
    
    42 U.S.C. § 10222
    (a)(1); 
    48 Fed. Reg. 5,458
     (Feb. 4, 1983)
    (proposed rule); 
    48 Fed. Reg. 16,590
     (Apr. 18, 1983) (final
    rule). Consistent with section 10222(b)(3), the Standard
    Contract provided: “The rights and duties of the Pur-
    chaser may be assignable with transfer of title to the
    SNF . . . involved; provided, however, that notice of any
    such transfer shall be made to DOE within ninety (90)
    days of transfer.” 
    10 C.F.R. § 961.11
    , art. XIV; see also
    J.A. 120.
    In June 1983, DOE entered into a Standard Contract
    with Vermont Yankee for the disposal of SNF stored at
    the VYNPS facility. In consideration for DOE’s commit-
    ment to dispose of SNF, the Standard Contract required
    the utilities to pay fees to DOE. First is a one-time fee
    that is based on any SNF generated prior to April 1983.
    Payment of this one-time fee may be deferred with inter-
    est until anytime prior to the beginning of DOE’s per-
    formance. Vermont Yankee had been producing SNF
    since 1972, and was thus obligated to pay the one-time fee
    for disposal of its pre-1983 SNF. Vermont Yankee elected
    to defer the payment of the one-time fee, which at the
    time of this action, has not yet been paid. Second, con-
    tract holders must pay a continuing quarterly fee based
    on the amount of electricity generated and sold during
    that quarter by the utility. This fee has been paid by
    Vermont Yankee and ENVY during the period of their
    ownership of VYNPS and accepted by the government.
    DOE failed to begin accepting and disposing of SNF
    from Vermont Yankee and other utilities in the nuclear
    VERMONT YANKEE NUCLEAR POWER      v. US                     6
    industry by January 31, 1998. On August 15, 2001,
    Vermont Yankee entered into a Purchase and Sale
    Agreement (“PSA”) with ENVY. On July 31, 2002, the
    parties completed the sale of VYNPS, including title to all
    of the SNF generated and stored at VYNPS. The PSA
    expressly provided that “[Vermont Yankee] shall assign to
    [ENVY] the DOE Standard Contract, except for the
    obligation to pay the one time fee.” J.A. 241. The PSA
    further provided that Vermont Yankee transferred to
    ENVY “any claims of [Vermont Yankee] related to
    [DOE]’s defaults under the DOE Standard Contract
    accrued as of the Closing, whether relating to periods
    prior to or following the Closing.” J.A. 197. The assign-
    ment excluded “claims as may relate to the one-time fee
    with respect to fuel used to generate electricity prior to
    April 7, 1983.” J.A. 197.
    In a letter dated July 31, 2002, ENVY notified DOE
    “that Vermont Yankee ha[d] . . . assigned its right, title,
    and interest” under the Standard Contract to ENVY, and
    that ENVY would “assume and discharge the obligations
    of Vermont Yankee under the [Standard] Contract in lieu
    of Vermont Yankee.” J.A. 268. In a letter dated August
    21, 2002, Vermont Yankee similarly notified DOE that it
    had transferred to ENVY “its title to Spent Nuclear Fuel”
    at VYNPS along with “its rights and duties under the
    [Standard] Contract.” J.A. 269. The Vermont Yankee
    letter also notified DOE that it had “retained the rights to
    any and all damages and other remedies that might
    accrue under from [DOE]’s breach of its obligations under
    the [Standard] Contract to the extent of the one-time fee
    for fuel used to generate electricity prior to April 7, 1983.”
    J.A. 269. However, neither letter notified DOE that
    Vermont Yankee had also retained the obligation to pay
    the one-time fee prior to DOE’s performance. This reser-
    vation was not discovered by the government until it
    7                     VERMONT YANKEE NUCLEAR POWER      v. US
    obtained a copy of the PSA during document production in
    this case in 2006.
    As a result of DOE’s breach, and as mitigation, ENVY
    concluded that it should construct an on-site dry-storage
    facility to provide for the interim storage of SNF at
    VYNPS. Pursuant to federal regulations and ENVY’s pre-
    existing license with the Nuclear Regulatory Commission
    (“NRC”), ENVY was permitted to construct a dry-storage
    facility implementing a system that had been previously
    approved by the NRC. However, as discussed below,
    ENVY claims that it incurred other expenses in order to
    obtain approval from the State of Vermont to construct
    the facility, including: (1) legal and lobbying fees;
    (2) payments into Vermont’s Clean Energy Development
    Fund; (3) the cost of performing a flood analysis; and
    (4) the cost of constructing a visual barrier.
    On November 12, 2003, ENVY filed an action in the
    Claims Court for damages caused by DOE’s breach of
    contract. The Claims Court consolidated ENVY’s action
    with a separate action brought by Vermont Yankee as-
    serting claims arising out of its pre-sale ownership and
    operation of VYNPS. See Entergy Nuclear Vt. Yankee,
    LLC v. United States, 
    95 Fed. Cl. 160
    , 167 (2010).
    We have previously held that DOE’s failure to begin
    collecting SNF constituted a partial breach of the Stan-
    dard Contract. Me. Yankee Atomic Power Co. v. United
    States, 
    225 F.3d 1336
    , 1342 (Fed. Cir. 2000) (“The breach
    involved all the utilities that had signed the contract—the
    entire nuclear electric industry.”); see also N. States Power
    Co. v. United States, 
    224 F.3d 1361
    , 1367 (Fed. Cir. 2000).
    The government admitted liability for its breach of
    the Standard Contract, and the Claims Court awarded
    ENVY $34,895,467 in undisputed damages, the largest
    portion of which was for the construction of the dry stor-
    VERMONT YANKEE NUCLEAR POWER    v. US                   8
    age facility. However, the government, ENVY, and Ver-
    mont Yankee disputed the government’s liability for
    various categories of damages, and this dispute continues
    on appeal. 2
    Through determinations at summary judgment and
    after trial, the Claims Court resolved the disputed claims
    as follows. 3 The Claims Court held at summary judgment
    that the assignment from Vermont Yankee to ENVY of
    pre-existing claims against the government was valid,
    and that, contrary to the government’s position, the
    partial assignment from Vermont Yankee to ENVY of the
    rights and duties under the Standard Contract was also
    valid. Vt. Yankee Nuclear Power Corp. v. United States
    (“Vermont Yankee I”), 
    73 Fed. Cl. 236
    , 240-42 (2006). The
    Claims Court also held at summary judgment that Ver-
    mont Yankee had unambiguously assigned to ENVY the
    claims it asserted against the government for the cost of
    its pre-sale mitigation activities and the diminution in
    value of VYNPS. Vt. Yankee Nuclear Power Corp. v.
    United States (“Vermont Yankee II”), 
    84 Fed. Cl. 339
    , 346-
    47 (2008).
    2   The government also disputed four categories of
    damages before the Claims Court that are not involved in
    this appeal.
    3   Prior to the trial, Claims Court also entered a
    Rule 54(b) final judgment dismissing Vermont Yankee’s
    claims. In an initial appeal, we determined that because
    “Vermont Yankee and ENVY have each claimed relief for
    the same alleged wrong, and . . . that pursuant to the
    [PSA] only one of them can recover,” “the claims [were]
    too intertwined for entry of judgment pursuant to Rule
    54(b) as to only one party.” Vt. Yankee Nuclear Power
    Corp. v. United States, 346 F. App’x 589, 591 (Fed. Cir.
    2009). Accordingly, we ordered the Claims Court to
    vacate the Rule 54(b) judgment. 
    Id.
    9                     VERMONT YANKEE NUCLEAR POWER     v. US
    In addition to the undisputed portion of ENVY’s dam-
    ages claim, the Claims Court awarded ENVY its claimed
    costs of securing state approval for the dry storage facil-
    ity, including: (1) legal and lobbying fees; (2) payments
    into the Vermont Clean Energy Development fund;
    (3) performance of a river flood analysis; and
    (4) construction of a visual barrier to the dry-storage
    facility. Entergy Nuclear, 95 Fed. Cl. at 184, 190. The
    Claims Court also awarded ENVY damages for its
    claimed costs of (1) disposing of contaminated material
    discovered due to the breach; and (2) characterizing the
    SNF moved into on-site dry storage. Id. at 190-92.
    Finally, the Claims Court decided two issues that
    have since been determined by our recent precedent. The
    Claims Court denied damages for ENVY’s cost of capital
    to fund its mitigation activities (consistent with our
    precedent) and denied ENVY’s overhead costs calculated
    via its capital suspense loader (contrary to our precedent).
    Id. at 194-97. In addition, the Claims Court denied
    damages for ENVY’s overhead costs calculated via its
    Resource Code 19 payroll loader. Id. at 195-96.
    The parties timely appealed. We have jurisdiction
    under 
    28 U.S.C. § 1295
    (a)(3). We review legal conclusions
    of the Claims Court de novo. Ind. Mich. Power Co. v.
    United States, 
    422 F.3d 1369
    , 1373 (Fed. Cir. 2005).
    Factual findings are reviewed for “clear error.” 
    Id.
    DISCUSSION
    I Assignment
    The government argues that the NWPA’s assignment
    provision does not allow for either the assignment of
    claims under the Standard Contract or a partial assign-
    ment of the contract itself from Vermont Yankee to
    ENVY.
    VERMONT YANKEE NUCLEAR POWER    v. US                   10
    A
    The government first argues that the NWPA’s as-
    signment provision does not allow for the assignment to
    ENVY of claims against the government previously ac-
    crued by Vermont Yankee under the Standard Contract.
    In general, the Assignment of Claims Act (“Claims Act”)
    bars the assignment of claims against the United States
    government unless the assignment is made “after [the]
    claim is allowed, the amount of the claim is decided, and a
    warrant for payment of the claim has been issued.” 
    31 U.S.C. § 3727
    (b). However, the restrictions of the Claims
    Act may be waived by the government either by an ex-
    press contractual provision or otherwise. See, e.g., Del-
    marva Power & Light Co. v. United States, 
    542 F.3d 889
    ,
    891-93 (Fed. Cir. 2008). With respect to the assignment
    provisions in the NWPA and the Standard Contract, we
    recently held that “Congress’ intent is manifest in the
    plain language of the NWPA: a party to the Standard
    Contract may assign its rights,” including “the party’s
    right to collect damages incurred due to an existing,
    ongoing breach.” Dominion Res., Inc. v. United States,
    
    641 F.3d 1359
    , 1363 (Fed. Cir. 2011). The government
    now concedes that our decision in Dominion Resources
    “disposes of the claim assignment issue.” Appellant’s
    Reply Br. 16. Accordingly, we affirm the Claims Court’s
    holding that the assignment of pre-existing claims from
    Vermont Yankee to ENVY was valid. 4
    B
    The government also argues that the NWPA’s as-
    signment provision does not allow for the partial assign-
    4   The assignability of claims has no bearing on the
    assignability of continuing rights and obligations of a
    government contract, which, as discussed below, is gov-
    erned by the Assignment of Contracts Act.
    11                     VERMONT YANKEE NUCLEAR POWER     v. US
    ment of the rights and obligations designated in the
    Standard Contract, and in particular does not allow a
    partial assignment where Vermont Yankee retained the
    obligation to pay the one-time fee.
    For contracts with the federal government, the As-
    signment of Contracts Act (“Contracts Act”) provides:
    No contract or order, or any interest therein, shall
    be transferred by the party to whom such contract
    or order is given to any other party, and any such
    transfer shall cause the annulment of the contract
    or order transferred, so far as the United States is
    concerned. All rights of action, however, for any
    breach of such contract by the contracting parties,
    are reserved to the United States.
    
    41 U.S.C. § 15
    (a) (2006). 5 Our precedents have estab-
    lished that the government may consent to or waive any
    objections it may have to assignments that would other-
    wise be in violation of the Contracts Act. See Tuftco Corp.
    v. United States, 
    614 F.2d 740
    , 745-46 (Ct. Cl. 1980).
    Specifically, our predecessor court noted that the govern-
    ment may recognize the validity of an assignment outside
    the bounds of the Contracts Act by its “course of conduct,
    its statements to the parties and its dealings with the
    assignee.” 
    Id. at 745
    .
    Here, the Standard Contract allows for the assign-
    ment of the rights and duties of the Standard Contract,
    but says nothing about the validity of partial assign-
    ments. Further, the Standard Contract expressly re-
    5  
    41 U.S.C. § 15
     was recodified on January 4, 2011,
    in substantially similar form, at 
    41 U.S.C. § 6305
    . Be-
    cause section 15 was still in effect at the time of the
    disputed assignment, we will refer to that section for the
    purposes of this appeal.
    VERMONT YANKEE NUCLEAR POWER      v. US                    12
    quires a “transfer of title to the [SNF] . . . involved” along
    with an assignment of the “rights and duties” of the
    contract holder. J.A. 120; see also 
    10 C.F.R. § 961.11
    , art.
    XIV. Indeed, we have recognized that “[a] party to a
    standard contract cannot transfer its rights and duties to
    another party without also transferring title to the SNF.”
    Dominion Res., 
    641 F.3d at 1363
    . This requirement that
    the rights and duties of the Standard Contract must be
    tied to the title of the involved SNF suggests that all of
    the rights and duties under the Standard Contract must
    be assigned together.
    Moreover, under standard contract law, assignments
    are generally not permitted in situations where they
    would disadvantage the obligor. “A contractual right can
    be assigned unless (a) the substitution of a right of the
    assignee for the right of the assignor would . . . materially
    increase the burden or risk imposed on him by his con-
    tract, or materially impair his chance of obtaining return
    performance . . . .” Restatement (Second) of Contracts
    § 317(2) (1981). “What is . . . an increase in burden or
    risk . . . depends on the nature of the contract and on the
    circumstances.” Id. cmt. d. But at the least, “if the obli-
    gor is to perform in exchange for the promise of one
    person to render a return performance at a future time,
    substitution of the return promise of another impairs the
    obligor’s expectation of counter-performance.” Id. Here,
    the government has a strong interest in having all of the
    rights and duties under the Standard Contract, including
    the obligation to pay the one-time fee, reside in the same
    party. Requiring any assignments of the Standard Con-
    tract to be complete would ensure that the government
    would only have to deal with a single party in order to
    secure return performance or to resolve potential dis-
    putes.
    13                    VERMONT YANKEE NUCLEAR POWER     v. US
    Vermont Yankee nonetheless argues that its retention
    of the obligation to pay the one-time fee puts the govern-
    ment at no greater risk than would exist without the
    partial assignment. According to Vermont Yankee, this is
    because DOE does not have to perform under the Stan-
    dard Contract until after the one-time fee is paid, assum-
    ing that, unlike the present situation, the government
    were otherwise willing to perform. 6 But DOE has an
    overarching interest in the goals of the NWPA, that is, to
    establish a federal program “for the disposal of . . . spent
    nuclear fuel.” 
    42 U.S.C. § 10131
    (b)(2). Thus, any addi-
    tional risk that the SNF could not be properly disposed of
    (because of a non-payment or a delayed payment of the
    one-time fee) would disadvantage the government.
    For these reasons, we disagree with the Claims
    Court’s conclusion that “[t]he range of assignments per-
    mitted under the NWPA . . . extends to the ‘partial’ as-
    signment of rights and duties created by the Standard
    Contract.” Vermont Yankee I, 73 Fed. Cl. at 240.
    C
    However, an improper assignment does not automati-
    cally nullify the contract; rather it gives the government
    the option to nullify the contract. See Tuftco Corp., 614
    F.2d at 745. As described above, the government’s right
    to void an assignment under the Contracts Act can be
    waived. See id. at 745-46. Here, the government became
    6  The government argued below that it had no duty
    to perform, and thus could not be held liable for partially
    breaching the Standard Contract until after the one-time
    fee was paid. See Vermont Yankee I, 73 Fed. Cl. at 243.
    However, the Claims Court held that payment of the one-
    time fee was not yet due, and thus Vermont Yankee’s
    deferral of the one-time fee did not excuse the govern-
    ment’s failure to perform. Id. at 244. The government
    does not raise that issue on appeal.
    VERMONT YANKEE NUCLEAR POWER     v. US                   14
    aware of the assignment and continued to accept post-
    assignment payments of the quarterly fee from ENVY for
    six years from 2006 (when it discovered the partial nature
    of the assignment) up to the present. At the same time,
    the government sought to invalidate the assignment at
    summary judgment, arguing that “[b]ecause the contract
    assignment to ENVY [was] defective, ENVY does not have
    any privity of contract with DOE.” Defendant’s Motion
    for Summary Judgment Regarding the Invalid Assign-
    ment of Plaintiff’s Standard Contract at 2, Vermont
    Yankee I, 
    73 Fed. Cl. 236
     (No. 03-2663C). While, as the
    dissent points out, this course of conduct would not neces-
    sarily waive the government’s right to sue for damages for
    breach of contract, it most assuredly prevents the gov-
    ernment from seeking to undo (or to refuse to recognize)
    the assignment of the Standard Contract from Vermont
    Yankee to ENVY. The receipt of benefits is directly
    inconsistent with the refusal to recognize the validity of
    the assignment.
    In comparable situations, it is well established that
    the continued receipt of benefits under a contract bars the
    non-breaching party from seeking to rescind the contract
    and secure restitution. As the Supreme Court stated in
    Mobil Oil Exploration & Producing Southeast, Inc. v.
    United States, 
    530 U.S. 604
    , 622 (2000), “acceptance of
    performance under a once-repudiated contract can consti-
    tute a waiver of the right to restitution that repudiation
    would otherwise create.” Following Mobil Oil, we have
    held that it “is clear that the receipt of partial perform-
    ance by the plaintiff will bar restitution.” Old Stone Corp.
    v. United States, 
    450 F.3d 1360
    , 1371-74 (Fed. Cir. 2006)
    (finding that plaintiff’s continued receipt of benefits
    waived the right to restitution, but not the right to re-
    15                    VERMONT YANKEE NUCLEAR POWER       v. US
    cover damages). 7 The cases cited by the dissent are not to
    the contrary. Each involved a situation in which the non-
    breaching party was held entitled to sue for partial
    breach, despite the continued receipt of benefits because
    the non-breaching party supplied timely notice of the
    breach. There is no inconsistency between the receipt of
    benefits and a suit for partial breach. None of those cases
    involved a situation in which the non-breaching party
    sought to undo the contract in its entirety. 8
    Accordingly, we hold that the partial assignment of
    the Standard Contract from Vermont Yankee to ENVY is
    effective.
    7  See also Richard A. Lord, Williston on Contracts
    § 39:32 (4th ed. 2000) (“When one party commits a mate-
    rial breach of contract, the other party has a choice be-
    tween two inconsistent rights—he or she can either elect
    to allege a total breach, terminate the contract and bring
    an action, or, instead, elect to keep the contract in force,
    declare the default only a partial breach, and recover
    those damages caused by that partial breach—but the
    nonbreaching party, by electing to continue receiving
    benefits pursuant to the agreement, cannot then refuse to
    perform his or her part of the bargain.”); id. § 40:1 (“[I]f a
    party in default under a contract is allowed to continue to
    perform, this precludes any right of the other party to
    rescind the contract or declare a material breach and
    refuse to further perform . . . .”).
    8   See Westfed Holdings, Inc. v. United States, 
    407 F.3d 1352
    , 1356 (Fed. Cir. 2005) (plaintiff seeking reliance
    damages); N. Helex Co. v. United States, 
    455 F.2d 546
    ,
    555 (Ct. Cl. 1972) (plaintiff seeking remainder of full
    payment after the acceptance of partial payment); Inland
    Trucking Corp. v. United States, 
    281 F.2d 457
    , 458 (Ct. Cl.
    1960) (plaintiff seeking withheld portions of final pay-
    ment).
    VERMONT YANKEE NUCLEAR POWER     v. US                     16
    II Scope of the Partial Assignment
    Vermont Yankee challenges the Claims Court’s hold-
    ing that it had transferred to ENVY each of the claims it
    brought against DOE in this case. Vermont Yankee
    argues that it retained its pre-closing mitigation costs
    claims and its diminution-in-value claim.
    Under the section entitled “Transfer of Assets,” the
    PSA provided:
    Upon the terms . . . contained in this Agreement,
    at the Closing [Vermont Yankee] will sell, assign,
    convey, transfer and deliver to [ENVY], and
    [ENVY] will purchase, assume and acquire from
    [Vermont Yankee], . . . all of [Vermont Yankee]’s
    right, title and interest immediately prior to the
    Closing in and to all of the properties and assets
    constituting or used in the operation of the
    [VYNPS] Facility . . . .
    J.A. 195-96 (PSA § 2.1). Specifically listed amongst the
    transfer of assets were the following:
    (n) Subject to Section 6.11(b), any claims of [Ver-
    mont Yankee] related to the Department of En-
    ergy's defaults under the DOE Standard Contract
    accrued as of the Closing, whether relating to pe-
    riods prior to or following the Closing, excluding
    such claims as may relate to the one-time fee with
    respect to fuel used to generate electricity prior to
    April 7, 1983[.]
    J.A. 197 (emphasis added) (PSA § 2.1(n)). As noted in
    section 2.1(n) of the PSA, the transfer of claims was
    subject to section 6.11(b). That section, under the title of
    “Spent Nuclear Fuel Fees,” provided:
    17                     VERMONT YANKEE NUCLEAR POWER     v. US
    (b) [Vermont Yankee] agrees, upon receipt of at
    least 30 days advance written notice from [ENVY]
    of the date on which the one-time fee for fuel
    burned prior to April 7, 1983 under the DOE
    Standard Contract will become due and payable in
    accordance with the terms of the DOE Standard
    Contract, to cause such fee to be duly paid when
    due, subject to any rights of set-off to which [Ver-
    mont Yankee] may be entitled by reason of the De-
    partment of Energy’s defaults under said DOE
    Standard Contract.
    J.A. 241 (emphasis added) (PSA § 6.11(b)). Under “Ex-
    cluded Assets,” the PSA similarly listed the following:
    (i) The Vermont Yankee Spent Fuel Disposal
    Trust and claims of [Vermont Yankee] related or
    pertaining to [DOE]’s defaults under the DOE
    Standard Contract to the extent applicable to the
    one-time fee with respect to fuel used to generate
    electricity prior to April 7, 1983[.]
    J.A. 198 (PSA § 2.2(i)).
    The Claims Court found that while Vermont Yankee’s
    claims “may stem from the pre-1983 fuel, they are unre-
    lated to the one-time fee,” and were thus not retained by
    Vermont Yankee under the terms of the PSA. Vermont
    Yankee II, 84 Fed. Cl. at 347. It is not perfectly clear
    what exactly is included in the “set-off” referred to in the
    “Spent Nuclear Fuel Fees” section. But Vermont Yankee
    does not argue that the claims in question are related to
    the one-time fee. Rather, Vermont Yankee argues that
    the “set-off” encompassed in 6.11(b) is not limited to items
    related to the one-time fee, but instead covers claims for
    costs “related to DOE’s breach of and default on its duty
    to pick up the pre-April 7, 1983 SNF for which Vermont
    Yankee agreed to pay the one-time fee.” Vermont Yankee
    VERMONT YANKEE NUCLEAR POWER     v. US                   18
    Br. 21. Vermont Yankee’s interpretation of the PSA is not
    plausible, and the PSA is clear that claims not related to
    the one-time fee are not excluded from the transfer to
    ENVY.
    Thus, we affirm the Claims Court’s holding that Ver-
    mont Yankee transferred to ENVY its claims for pre-
    closing mitigation costs and diminution in value, and that
    Vermont Yankee could not assert those claims in this
    litigation.
    III Vermont Legislation-Related Costs
    The government challenges the Claims Court’s award
    of $9,608,189 in damages for the costs incurred to obtain
    approval from the State of Vermont to build an on-site dry
    storage facility.
    A
    At the time Vermont Yankee signed the Standard
    Contract in 1983, Vermont required that utilities obtain
    legislative approval prior to constructing a “facility for
    deposit, storage, reprocessing or disposal of spent nuclear
    fuel.” 
    Vt. Stat. Ann. tit. 10, § 6501
     (1982). Vermont
    Yankee enjoyed a company-specific statutory exemption
    for the “temporary storage . . . of spent nuclear fuel.” 
    Id.
    § 6505. But after the 2002 sale of VYNPS to ENVY, the
    Attorney General of Vermont rendered an opinion in 2004
    stating that the statutory exemption did not extend to
    ENVY as the successor of Vermont Yankee. After unsuc-
    cessfully lobbying the Vermont general assembly to
    extend the exemption, ENVY commenced negotiations
    with the state to gain separate legislative approval.
    On June 3, 2005, the Vermont state legislature en-
    acted the Dry Cask Storage Authorization Act (“Dry
    Storage Act”). The Dry Storage Act approved the con-
    struction of a dry storage facility contingent on ENVY’s:
    19                    VERMONT YANKEE NUCLEAR POWER      v. US
    (1) obtaining a Certificate of Public Good (“Certificate”)
    from the Vermont Public Service Board (“Board”) pursu-
    ant to 
    Vt. Stat. Ann. tit. 30, § 248
    ; and (2) complying with
    the terms of a spent fuel storage Memorandum of Under-
    standing, which had been negotiated with the Vermont
    Department of Public Service and was also signed on
    June 21, 2005. See 
    Vt. Stat. Ann. tit. 10, § 6522
     (2012);
    see also Entergy Nuclear, 95 Fed. Cl. at 176. ENVY
    received the required Certificate from the Board and
    entered into the Memorandum of Understanding (“Memo-
    randum”). The Memorandum and the Certificate, how-
    ever, imposed multiple requirements on ENVY. The
    Memorandum required ENVY to pay, over the course of
    several years, a total of $15,625,000 into the Clean En-
    ergy Development Fund, which was also established by
    the Dry Storage Act. See 
    Vt. Stat. Ann. tit. 10, § 6523
    (2010) (recodified at 
    Vt. Stat. Ann. tit. 30, § 8015
     (2012)).
    Due to the perceived inadequacy of an NRC-required flood
    analysis relating to storage safety, the Certificate re-
    quired ENVY to conduct an additional flood analysis to
    demonstrate that the dry storage facility was not vulner-
    able to potential flooding. The Memorandum also re-
    quired ENVY to construct a visual barrier on two sides of
    the dry storage facility.
    ENVY seeks: (1) $3,385,783 for legal and lobbying
    costs; (2) $5,625,000 for contributions made to the Ver-
    mont Clean Energy Development Fund during the period
    in question here; (3) $184,552 for the performance of a
    river flood analysis; and (4) $412,854 for the construction
    of a visual barrier to the dry-storage facility. Though we
    affirm the award of damages for ENVY’s legal and lobby-
    ing fees, we hold that the Claims Court clearly erred in
    awarding damages to ENVY for payments made into the
    Vermont Clean Energy Development fund, performance of
    a flood analysis, and construction of a visual barrier.
    VERMONT YANKEE NUCLEAR POWER     v. US                    20
    B
    The government challenges that these costs were not
    foreseeable at the time of contracting in 1983. As we held
    in Indiana Michigan, 
    422 F.3d at 1373
    , damages must be
    “reasonably foreseeable by the breaching party at the
    time of contracting.” See also Williston on Contracts
    § 64:29 (“[T]he defendant [must have] had reason to
    foresee [the damages] as a probable result of the defen-
    dant’s breach when the contract was made.”). ENVY
    contends that the foreseeability requirement for each of
    the above listed categories is satisfied because the need to
    construct additional on-site facilities was foreseeable.
    There is no need, ENVY argues, to establish foreseeability
    of each particular type of cost incurred. This is incorrect.
    The Restatement and relevant treatises have uni-
    formly set forth the relevant standard and make clear
    that a plaintiff must show that the type of damages are
    foreseeable as well as the fact of damage. “[D]amages are
    not recoverable for loss that the party in breach did not
    have reason to foresee as a probable result of the breach
    when the contract was made.” Restatement (Second) of
    Contracts § 351. Although this does not require “actual
    foresight” that the breach will cause a “specific injury or a
    particular amount in money[,] . . . the injury actually
    suffered [still] must be one of a kind that the defendant
    had reason to foresee and of an amount that is not beyond
    the bounds of reasonable prediction.” Joseph M. Perillo,
    11 Corbin on Contracts § 56.7, at 108 (rev. ed. 2005)
    (emphasis added). “[R]emoteness in space and time and
    the number of intervening events have obvious bearing on
    foreseeability.” Williston on Contracts § 64:13.
    These principles have been adopted in our cases.
    While a “specific loss” need not be foreseeable, Anchor
    Sav. Bank, FSB v. United States, 
    597 F.3d 1356
    , 1364
    21                    VERMONT YANKEE NUCLEAR POWER    v. US
    (Fed. Cir. 2010), it is well-established that “a plaintiff
    must prove that . . . [the] type of damages were foresee-
    able,” Landmark Land Co. v. FDIC, 
    256 F.3d 1365
    , 1378
    (Fed. Cir. 2001) (emphasis added). Similarly, our prede-
    cessor court in Gardner Displays Co. v. United States, 
    346 F.2d 585
    , 589 (Ct. Cl. 1965), held that “consequential
    damages involves consideration of the type of loss fore-
    seeable by the contracting parties at the time of their
    agreement.” Unquestionably, “the foreseeability prong
    applies to the type of loss.” Sacramento Mun. Util. Dist.
    v. United States, 293 F. App’x 766, 771 (Fed. Cir. 2008).
    In keeping with this general rule, we have held that
    plaintiffs cannot recover breach of contract damages
    where the type of loss was not foreseeable. For example,
    in Old Stone, 
    450 F.3d 1360
    , a Winstar case, the plaintiff
    holding company was forced to sell valuable subsidiary
    entities in order to mitigate the government’s breach and
    did not have those assets available to help it solve other
    problems not caused by the breach. This resulted in
    seizure of the thrift. We held that damages resulting
    from the seizure were not foreseeable because the plaintiff
    did not establish that “this extended chain of causation
    was foreseeable.” 
    Id. at 1376
    . We explained:
    [E]ven if the need for replacement capital was
    foreseeable [as a result of the government’s
    breach], that hardly establishes that the adverse
    consequences alleged to flow from the need to
    make [capital] infusions were foreseeable . . . .
    “[T]he mere circumstance that some loss was fore-
    seeable, or even that some loss of the same gen-
    eral kind was foreseeable, will not suffice if the
    loss that actually occurred was not foreseeable.”
    
    Id.
     (quoting Restatement (Second) of Contracts § 351 cmt.
    a). Similarly, in Landmark Land, the plaintiff land
    VERMONT YANKEE NUCLEAR POWER     v. US                   22
    holding company, which had acquired a struggling thrift
    pursuant to a contract with the government, later trans-
    ferred almost all of its land holdings to that struggling
    thrift in order to receive favorable tax treatment. 
    256 F.3d at 1369-71
    . When the thrift was later seized as a
    result of the government’s breach, we held that it was not
    foreseeable at the time of contracting that the plaintiff
    would have transferred essentially all of its assets to the
    struggling thrift, and we therefore denied plaintiff’s
    damage claim for the value of those assets. 
    Id.
     at 1378-
    79; see also Anchor Savings, 
    597 F.3d at 1364
     (explaining
    that “the mere circumstance that some loss was foresee-
    able may not suffice to impose liability for a particular
    type of loss that was so unusual as not to be foreseeable”
    (quoting E. Allan Farnsworth, Farnsworth on Contracts
    § 12.14, at 262 (3d ed. 2004))); Prudential Ins. Co. of Am.
    v. United States, 
    801 F.2d 1295
    , 1301 (Fed. Cir. 1986)
    (finding government could not have foreseen that holding
    over on its lease would cause the landlord to lose a tenant
    for “other property in excess of that occupied by the
    government”). This foreseeability standard has also been
    applied in SNF cases. In Indiana Michigan, we held that
    the utility’s “high cost” and “speculative” investment in an
    alternative out-of-state private storage facility, was
    unforeseeable even though we also determined that “DOE
    should have foreseen that its breach would force Indiana
    Michigan to find alternate storage for its SNF.” 
    422 F.3d at 1376
    .
    This is not a case like Citizens Federal Bank v. United
    States, 
    474 F.3d 1314
     (Fed. Cir. 2007), another Winstar
    case where the adverse tax consequences of the plaintiffs’
    mitigation activities were foreseeable because they ex-
    isted in the code at the time of the transaction. Nor is
    this case like Anchor Savings, where it was foreseeable
    that acquiring thrifts would have to sell investments to
    23                    VERMONT YANKEE NUCLEAR POWER     v. US
    raise regulatory capital because the government previ-
    ously “needed and expected” acquiring thrifts like Anchor
    Savings “to leverage its [later disallowed] goodwill into
    [those] profitable investments.” 
    597 F.3d at 1362
    .
    C
    The question is whether ENVY has established the
    foreseeability of the costs incurred to secure approval for
    the dry storage facility from the State of Vermont. With
    respect to the legal and lobbying expenses incurred by
    ENVY to secure state approval of the dry storage facility,
    we agree that ENVY has established foreseeability.
    At the time the Standard Contract was signed in
    1983, it was foreseeable that at least some form of ap-
    proval was required by the State of Vermont for the
    construction of a dry storage facility at VYNPS. For
    example, a Vermont statute, enacted in 1977, provided
    that:
    No facility for deposit, storage, reprocessing or
    disposal of spent nuclear fuel elements or radioac-
    tive waste material shall be constructed or estab-
    lished in the state of Vermont unless the general
    assembly first finds that it promotes the general
    good of the state and approves, through either bill
    or joint resolution, a petition for approval of the
    facility.
    
    Vt. Stat. Ann. tit. 10, § 6501
    (a). Although an exception to
    the statute was adopted in 1979 specifically for Vermont
    Yankee, see 
    id.
     § 6505, and even though ENVY may have
    itself believed that this exception was transferable, it was
    still foreseeable that approval from the Vermont legisla-
    ture might have been required for ENVY. The assign-
    ment provision in the Standard Contract shows that the
    sale of VYNPS and the assignment of the Standard Con-
    VERMONT YANKEE NUCLEAR POWER      v. US                    24
    tract was foreseeable. And the fact that the legislature
    had gone so far as to create an exemption that applied
    only to Vermont Yankee suggested that there may be
    further legislative action in the future related to that
    exemption or that the exemption would not extend to a
    potential successor.
    The statute required approval from the state legisla-
    ture based on its finding that the dry storage facility
    “promote[d] the general good of the state.” While the
    specific amount of legal and lobbying fees may not have
    been foreseeable, the payment of at least some legal and
    lobbying fees was foreseeable. And because the govern-
    ment only challenges the payment of legal and lobbying
    fees in general, we have no occasion to determine whether
    specific portions of those fees might have been unforesee-
    able (and hence not recoverable). 9 Accordingly, we affirm
    the Claims Court’s award of $3,385,783 for ENVY’s legal
    and lobbying fees.
    D
    We hold, however, that ENVY has not established
    that the government could have foreseen the unprece-
    dented requirement that ENVY contribute money into
    Vermont’s Clean Energy Development Fund. The Clean
    Energy Development Fund was established in 2005 as
    part of the Dry Storage Act. See 
    Vt. Stat. Ann. tit. 30, § 8015
    . The imposed fees bear no relationship to any
    costs incurred by the state or its citizens as a result of the
    construction of the dry storage facility. It would not be
    9   Thus we need not determine, for example,
    whether it was foreseeable that 
    Vt. Stat. Ann. tit. 30, § 248
    (a)(2) would apply to the construction of a dry stor-
    age facility and would require ENVY to obtain a Certifi-
    cate of Public Good from the Vermont Public Service
    Board.
    25                    VERMONT YANKEE NUCLEAR POWER      v. US
    inaccurate to characterize the fee as a form of blackmail
    for the state approval of the construction. ENVY con-
    ceded at oral argument that, at the time the Standard
    Contract was signed in 1983, neither Vermont nor any
    other state had imposed payments similar those into the
    Clean Energy Development Fund while licensing a nu-
    clear utility. Moreover, ENVY conceded in another case
    that the Clean Energy Development Fund had “nothing to
    do with dry cask storage.” J.A. 749. 10
    It was particularly unforeseeable that Vermont would
    require payments into the Clean Energy Development
    Fund because such a requirement raised a substantial
    question of preemption and was likely unconstitutional. 11
    10  The only testimony at trial regarding the foresee-
    ability of potential state-imposed costs was the testimony
    of an Entergy Services (a sister company of ENVY) em-
    ployee who stated that there may be some “hidden costs
    and surprises regulatory-wise” if ENVY needed to trans-
    port SNF to other sites. J.A. 1059. Such testimony,
    referring generally to “hidden costs and surprises,” and
    only applying to situations where ENVY would need to
    transport SNF generated at VYNPS off site, does not
    speak to the foreseeability of the costs actually imposed
    by the state.
    11  The State of Vermont alleges that the government
    waived its preemption argument by failing to timely
    notify the state of the preemption challenge pursuant to
    the notice requirements of 
    28 U.S.C. § 2403
    (b). Section
    2403(b) applies to certain challenges to state statutes in a
    “court of the United States,” which the Historical and
    Statutory Notes explain “is defined in section 451 of this
    title.” 
    Id.
     The definition of “court of the United States” in
    
    28 U.S.C. § 451
     includes Article III courts, but as we
    recognized in Essex Electro Engineers, Inc. v. United
    States, 
    757 F.2d 247
    , 251 n.1 (Fed. Cir. 1985), the Claims
    Court, as an Article I court, is not included within section
    451’s definition of “court of the United States.” Accord-
    ingly, the notice provisions of section 2403 did not apply
    to this case in the Claims Court.
    VERMONT YANKEE NUCLEAR POWER      v. US                    26
    Through a trilogy of cases, the Supreme Court has estab-
    lished a test evaluating when a state law involving nu-
    clear power is preempted by the United States
    government’s authority over nuclear safety. See English
    v. Gen. Elec. Co., 
    496 U.S. 72
     (1990); Silkwood v. Kerr-
    McGee Corp., 
    464 U.S. 238
     (1984); Pac. Gas & Elec. Co. v.
    State Energy Res. Conservation & Dev. Comm’n, 
    461 U.S. 190
     (1983). “[T]he Federal Government has occupied the
    entire field of nuclear safety concerns, except the limited
    powers expressly ceded to the States.” Pac. Gas, 
    461 U.S. at 212
    . These limited powers include the states’ “tradi-
    tional responsibility in the field of regulating electrical
    utilities for determining questions of need, reliability, cost
    and other related state concerns.” 
    Id. at 205
    . In Pacific
    Gas, the Court upheld California’s moratorium only
    because the law was based on a non-safety (i.e., economic)
    rationale. 
    Id. at 215-16
    . Under the Supreme Court’s test,
    a state law related to nuclear power is preempted if it: (1)
    is motivated by safety concerns, 
    id. at 213
    , or (2) “ha[s]
    some direct and substantial effect on the decisions made
    by those who build or operate nuclear facilities concerning
    radiological safety levels,” English, 
    496 U.S. at 85
    .
    Here, the required payments into the Clean Energy
    Development Fund totaled $15,625,000. This extraction
    of money is significant in amount, and, as a condition of
    constructing a dry storage facility, could easily deter a
    utility from constructing such a facility whose construc-
    tion is encouraged if not mandated by federal law. See 
    42 U.S.C. § 10151
    (a). 12 In Skull Valley Band of Goshute
    12   
    42 U.S.C. § 10151
    (a) states: “(1) the persons own-
    ing and operating civilian nuclear power reactors have the
    primary responsibility for providing interim storage of
    spent nuclear fuel from such reactors, by maximizing, to
    the extent practical, the effective use of existing storage
    facilities at the site of each civilian nuclear power reactor,
    27                   VERMONT YANKEE NUCLEAR POWER     v. US
    Indians v. Nielson, 
    376 F.3d 1223
    , 1248-50 (10th Cir.
    2004), the Tenth Circuit held that state provisions requir-
    ing payments to cover the “unfunded potential liability” of
    the site were preempted because “it is not the states but
    rather the NRC that is vested with the authority to decide
    under what conditions to license an SNF storage facility.”
    Unlike the non-preempted state tort claims in English
    that only had “some effect” on radiological safety deci-
    sions, the requirement to pay money into the Clean
    Energy Development Fund could have a “direct and
    substantial effect” on decisions concerning radiological
    safety. English, 
    496 U.S. at 85
    . Such a regulation of
    “matters directly affecting the radiological safety of nu-
    clear-plant construction and operation” is likely pre-
    empted, “‘even if [it was] enacted out of nonsafety
    concerns.’” 
    Id. at 84
     (quoting Pac. Gas, 
    461 U.S. at 212
    ).
    Notably, ENVY itself challenged the payments to the
    Clean Energy Development Fund on preemption grounds
    in a separate action before a federal district court (aban-
    doning that challenge only after the Claims Court
    awarded those fees as damages), see Entergy Nuclear Vt.
    Yankee, LLC v. Shumlin, No 1:11-cv-99, 
    2012 WL 162400
    (D. Vt. Jan. 19, 2012), and even now does not argue that
    the Vermont law can escape preemption under federal
    law.
    ENVY argues that “[d]isputing the state’s authority to
    require the payments was not viewed as being in the best
    interests of the company” because “the company needed to
    continue to operate and do additional business in the
    and by adding new onsite storage capacity in a timely
    manner where practical; [and] (2) the Federal Government
    has the responsibility to encourage and expedite the effec-
    tive use of existing storage facilities and the addition of
    needed new storage capacity at the site of each civilian
    nuclear power reactor . . . .” (emphasis added).
    VERMONT YANKEE NUCLEAR POWER      v. US                      28
    state.” ENVY Br. 52. Thus, they argue, their choice to
    acquiesce to the monetary demands of the state was
    reasonable. But whether or not ENVY’s choice to acqui-
    esce to the likely preempted state requirements was
    reasonable as a business proposition does not reflect on
    whether the costs incurred in complying with those re-
    quirements were foreseeable at the time the Standard
    Contract was signed. A leading treatise makes clear that
    reasonableness and foreseeability are separate require-
    ments in the context of mitigation damages:
    If the attempt [to mitigate] is reasonable . . . the
    injured party can recover . . . [but] [t]his is sub-
    ject . . . to the qualification applicable to the right
    to recover consequential damages of any kind,
    namely, that the defendant had reason to foresee
    them as a probable result of the defendant’s
    breach when the contract was made.
    Williston on Contracts § 64:29. Just because it may have
    been in ENVY’s best interest to maintain good relations
    with the state and to agree to pay a fee that was likely
    preempted by federal law does not render the fee recover-
    able. ENVY’s acquiescence to the state of Vermont went
    so far as to agree not to challenge the requirements of the
    Memorandum on preemption grounds. But ENVY cannot
    agree to improper state requirements, agree not to chal-
    lenge those improper requirements on preemption
    grounds, and then pass the expense of complying with
    those requirements to the federal government. As we
    held in Hercules Inc. v. United States, a plaintiff cannot
    voluntarily forego defending itself against third-party
    claims that are barred as a matter of law, and then re-
    cover those costs from the government. 
    24 F.3d 188
    , 200
    (Fed. Cir. 1994), aff’d on other grounds, 
    516 U.S. 417
    (1996).
    29                   VERMONT YANKEE NUCLEAR POWER     v. US
    For these reasons, we reverse the Claims Court’s
    award to ENVY of $5,625,000 in damages for payments
    made into the Clean Energy Development Fund.
    E
    It was similarly unforeseeable that Vermont would
    require the performance of a flood analysis, which also
    raises a substantial question of preemption. Here, the
    flood analysis was required due to the perceived inade-
    quacies of a previously performed NRC-required flood
    analysis that “took into account a ‘probable maximum
    flood’ at the site to ensure that such flooding would not
    create safety issues at the plant.” Entergy Nuclear, 95
    Fed. Cl. at 179 (emphasis added). ENVY has failed to
    point to any evidence that, as of 1983, Vermont or any
    other state had required utilities to perform additional
    flood control analyses beyond those already performed
    under federal regulations. In any event, because the
    requirement to perform an additional analysis was di-
    rectly motivated by safety concerns, it is clear that the
    flood analysis requirement was likely preempted under
    Pacific Gas, 
    461 U.S. at 215
    ; see also ANR Pipeline Co. v.
    Iowa State Commerce Comm’n, 
    828 F.2d 465
    , 471-72 (8th
    Cir. 1987) (finding state safety regulations to be pre-
    empted by the federal regulation of gas pipelines). The
    required flood analysis was thus not foreseeable. Accord-
    ingly, we reverse the Claims Court’s award of $184,552 in
    damages for the performance of the river flood analysis.
    F
    ENVY has also failed to meet its burden of establish-
    ing that the requirement to build a visual barrier on two
    sides of the dry storage facility was foreseeable. Notably,
    the Public Service Board commented that “[VYNPS] is an
    industrial site, and from an aesthetic perspective, the
    addition of a limited number of concrete and metal con-
    VERMONT YANKEE NUCLEAR POWER     v. US                    30
    tainers results in little change to the overall aesthetics of
    the site.” Entergy Nuclear, 95 Fed. Cl. at 178. The lack of
    an impact that dry storage would have on the overall
    aesthetics of a site suggests that the imposition of aes-
    thetic requirements for a dry storage facility in particular
    was not foreseeable. Moreover, ENVY has failed to point
    to any evidence that, as of 1983, Vermont or any other
    state had imposed such aesthetic requirements as a
    prerequisite for licensing a utility. Accordingly, we re-
    verse the Claims Court’s award of $412,854 for the con-
    struction of the visual barrier.
    IV Disposal of Contaminated Material and
    Characterization of Spent Fuel
    The government challenges the Claims Court’s award
    of $276,980 to ENVY for the costs of disposing contami-
    nated soil and asphalt, and $156,000 for the costs of
    performing a characterization on SNF moved into on-site
    dry storage. We hold that the Claims Court clearly erred
    in awarding damages to ENVY for the costs of disposing
    contaminated material and for the costs of characterizing
    SNF moved into on-site dry storage.
    In Yankee Atomic Electric Co. v. United States, we ex-
    plained that “damages for breach of contract require a
    showing of causation,” which in turn necessitates a “com-
    parison between the breach and non-breach worlds.” 
    536 F.3d 1268
    , 1273 (Fed. Cir. 2008). As we further explained
    in Energy Northwest v. United States, it is the plaintiff
    who “must prove the extent to which his incurred costs
    differ from the costs he would have incurred in the non-
    breach world.” 
    641 F.3d 1300
    , 1306 (Fed. Cir. 2011).
    Thus, a plaintiff is entitled to recover costs “only to the
    extent it can prove, to a reasonable certainty, that but for
    the government’s breach they would not have been in-
    curred.” 
    Id. at 1307
    .
    31                   VERMONT YANKEE NUCLEAR POWER    v. US
    A
    During the construction of the dry-storage facility at
    VYNPS, ENVY discovered contaminated soil and asphalt
    and incurred $276,980 in costs having that contaminated
    material disposed. The Claims Court did not find that
    DOE’s breach caused the contamination, but rather found
    that DOE’s breach caused ENVY to discover the contami-
    nation. The government challenges these costs on the
    grounds that they would have been incurred in a non-
    breach world when the site was eventually decommis-
    sioned. Without the benefit of our decision in Energy
    Northwest, the Claims Court held that “it [was] the Gov-
    ernment, not ENVY, that [bore] the burden of demon-
    strating that these future costs at decommissioning would
    be identical.” Entergy Nuclear, 95 Fed. Cl. at 191. How-
    ever, Energy Northwest clearly dictates that it was
    ENVY’s burden to “submit a hypothetical model establish-
    ing what its costs would have been in the absence of
    breach.” 
    641 F.3d at 1305
    . Because ENVY failed to prove
    the amount by which its actual removal costs were differ-
    ent from what its removal costs would have been at
    decommissioning in a non-breach world, we reverse the
    Claims Court’s award of $276,980 for the disposal of the
    contaminated material.
    B
    In preparing SNF for on-site dry storage, ENVY in-
    curred $156,000 in costs to characterize the SNF. Such a
    characterization is required for storage in any NRC-
    approved cask. ENVY’s theory is “that the fuel charac-
    terization may well be required a second time” for DOE-
    supplied casks, “when and if DOE performs.” ENVY Br.
    57. Thus, ENVY argues that it may have to pay for two
    characterizations, whereas in a non-breach world, it
    would have had to pay for only a single characterization
    VERMONT YANKEE NUCLEAR POWER    v. US                   32
    for the DOE-supplied casks. However, ENVY has not
    established the likelihood that DOE will require ENVY to
    incur further characterization costs upon performance. In
    fact, the Claims Court noted that “ENVY [itself] believes
    that DOE will accept” the previously performed charac-
    terization before finding that it is “possible that another
    review of the spent fuel condition will be required.”
    Entergy Nuclear, 95 Fed. Cl. at 182. Further, ENVY has
    failed to “submit a hypothetical model” comparing what
    its costs would be in breach versus non-breach worlds in
    the event that DOE does eventually require further
    characterization. Energy Nw., 
    641 F.3d at 1305
    . Accord-
    ingly, we reverse the Claims Court’s award to ENVY of
    $156,000 in costs incurred for the spent fuel characteriza-
    tion.
    V Issues Resolved By Our Recent Precedent
    A Cost of Capital
    ENVY challenges the Claims Court’s denial of
    $7,472,866 in damages for the cost of capital to fund
    ENVY’s mitigation activities. In Energy Northwest, we
    held that the no-interest rule barred parties to the Stan-
    dard Contract from recovering the costs of financing
    mitigation projects. 
    641 F.3d at
    1310-13 (citing 
    28 U.S.C. § 2516
    (a)); see also Sys. Fuels, Inc. v. United States, 
    666 F.3d 1306
    , 1310-11 (Fed. Cir. 2012). We further explained
    in Boston Edison Co. v. United States that the “commer-
    cial enterprise exception” to the no-interest rule did not
    apply in the context of the NWPA. 
    658 F.3d 1361
    , 1371
    (Fed. Cir. 2011).
    Consistent with our decisions in Energy Northwest
    and Boston Edison, we affirm the Claims Court’s denial of
    ENVY’s cost of capital claims.
    33                    VERMONT YANKEE NUCLEAR POWER      v. US
    B Overhead Costs
    ENVY also challenges the Claims Court’s denial of
    $788,414 in damages for its capital suspense loader
    overhead costs. Without the benefit of our recent SNF-
    related decisions, the Claims Court denied ENVY’s capital
    suspense loader overhead claims despite acknowledging
    that “[ENVY]’s accounting practices follow Generally
    Accepted Accounting Principles [GAAP] and FERC Guide-
    lines.” Entergy Nuclear, 95 Fed. Cl. at 195. In System
    Fuels, where the “Plaintiffs used accounting procedures as
    mandated by FERC and consistent with [GAAP],” we held
    that the plaintiff’s accounting records sufficiently “demon-
    strate[d] the effect of the mitigation project on the capital
    pools entitlement with reasonable particularity.” 
    666 F.3d at 1312
     (internal quotation marks omitted); see also
    Energy Nw., 
    641 F.3d at 1309
     (allowing recovery for the
    “portion of [the plaintiff’s] overhead costs fairly allocated
    to support of the mitigation via generally accepted ac-
    counting practices”); Bos. Edison, 
    658 F.3d at 1370
     (allow-
    ing recovery of “the portion of overhead costs (calculated
    using GAAP) that was attributable to mitigation pro-
    jects”).
    Consistent with our recent decisions, we reverse the
    Claims Court’s denial of $788,414 in damages for over-
    head costs allocated to ENVY’s mitigation activities via
    the capital suspense loader.
    However, we decline to review the Claims Court’s
    holding with respect to the Resource Code 19 payroll
    loader based on ENVY’s limited arguments on appeal.
    The Claims Court found that Resource Code 19 payroll
    loader included, among other items, pension costs for
    retired employees that could not be attributed to mitiga-
    tion activity and were thus not recoverable. Entergy
    Nuclear, 95 Fed. Cl. at 195-96. On appeal, ENVY has
    VERMONT YANKEE NUCLEAR POWER     v. US                 34
    failed to develop an argument as to why Resource Code 19
    payroll loader overhead costs should be considered analo-
    gous to other overhead costs that we have deemed to be
    sufficiently attributed to mitigation activities and thus
    recoverable. Because ENVY has not adequately briefed
    its claim with respect to the Resource Code 19 payroll
    loader, we affirm the Claim’s Court’s denial of $10,013 in
    damages for that particular overhead cost.
    AFFIRMED IN PART, REVERSED IN PART, and
    REMANDED
    COSTS
    No costs.
    United States Court of Appeals
    for the Federal Circuit
    __________________________
    VERMONT YANKEE NUCLEAR POWER
    CORPORATION
    Plaintiff-Cross Appellant,
    v.
    ENTERGY NUCLEAR VERMONT YANKEE, LLC,
    AND ENTERGY NUCLEAR OPERATIONS, INC.,
    Plaintiffs-Cross Appellants,
    v.
    UNITED STATES,
    Defendant-Appellant.
    __________________________
    2011-5033, -5034, -5042
    __________________________
    Appeals from the United States Court of Federal
    Claims in consolidated case nos. 02-CV-898 and 03-CV-
    2664, Judge Thomas C. Wheeler.
    __________________________
    MAYER, Circuit Judge, dissenting-in-part.
    I join the court’s opinion, except for Part I-C, which
    concludes that the government waived the right to chal-
    lenge the partial assignment by Vermont Yankee Nuclear
    Power Corporation (“Vermont Yankee”) of its rights and
    obligations under the Department of Energy’s Standard
    Contract. There was no waiver because the government
    VERMONT YANKEE NUCLEAR POWER     v. US                    2
    promptly and unequivocally objected to the partial as-
    signment.
    “‘Waiver’ is a vague term used for a great variety of
    purposes, good and bad, in the law. In any normal sense,
    however, it connotes some kind of voluntary knowing
    relinquishment of a right.” Green v. United States, 
    355 U.S. 184
    , 191 (1957). The government never relinquished
    its right to challenge Vermont Yankee’s partial assign-
    ment of its rights and obligations under the Standard
    Contract. It was not until 2006 that the government
    learned, during discovery, that Vermont Yankee breached
    the Standard Contract when it assigned its right to have
    the government accept spent nuclear fuel (“SNF”), but
    failed to assign the obligation to pay the substantial one-
    time fee for SNF generated prior to April 1983. Upon
    learning of the breach, the government promptly filed a
    motion for summary judgment in the Court of Federal
    Claims, arguing that the partial assignment violated the
    Assignment of Contracts Act, 
    41 U.S.C. § 15
    (a), and was
    therefore invalid. See Vt. Yankee Nuclear Power Corp. v.
    United States, 
    73 Fed. Cl. 236
    , 240 (Fed. Cl. 2006).
    The fact that the government continued to accept
    payments under the Standard Contract after learning of
    the breach is insufficient to establish waiver. When a
    party timely and unambiguously objects to a breach, he
    does not forfeit his claim by continuing to accept pay-
    ments under a contract. See N. Helex Co. v. United
    States, 
    455 F.2d 546
    , 555 (Ct. Cl. 1972) (explaining that a
    contractor’s “acceptance of partial payment, even without
    notation on the check, does not waive his claim”); Inland
    Trucking Corp. v. United States, 
    150 Ct. Cl. 642
    , 654 (Ct.
    Cl. 1960) (emphasizing that a contractor did not waive his
    right to sue for breach by accepting “final payment” under
    a contract). In Westfed Holdings, Inc. v. United States, for
    example, we concluded that a bank had not waived its
    3                     VERMONT YANKEE NUCLEAR POWER     v. US
    right to seek damages notwithstanding the fact that it
    had continued to accept “hundreds of millions of dollars
    from the government” following the government’s breach.
    
    407 F.3d 1352
    , 1360 (Fed. Cir. 2005). We explained that
    because the government knew of the bank’s “timely
    reservation of rights in protest to the breach,” the contin-
    ued acceptance of payments under the contract did not act
    as a waiver. 
    Id.
    A similar analysis applies here. Although the gov-
    ernment continued to accept payments as required by the
    Standard Contract after learning of Vermont Yankee’s
    breach, it preserved its right to challenge the partial
    assignment by filing a timely motion to have that assign-
    ment invalidated. See All-Ways Logistics, Inc. v. USA
    Truck, Inc., 
    583 F.3d 511
    , 517 (8th Cir. 2009) (emphasiz-
    ing that “there can be no waiver when the injured party
    does not manifest an intent to waive the breach”). “A
    party to a contract may waive the breach of an agreement
    by the continued acceptance of performance by the
    breaching party without reservation of rights.” Westfed,
    
    407 F.3d at 1360
    ; see also Ling-Temco-Vought, Inc. v.
    United States, 
    475 F.2d 630
    , 637 (Ct. Cl. 1973) (applying
    the waiver doctrine where a contractor continued to
    perform under a contract and “no reservation of rights
    was made known”). Conversely, however, the waiver
    doctrine has no application where, as here, the non-
    breaching party promptly and vociferously protests a
    breach. See Cole Taylor Bank v. Truck Ins. Exch., 
    51 F.3d 736
    , 740 (7th Cir. 1995) (explaining that while a victim of
    breach of contract must take some action to protect his
    contractual rights, he “is not required upon learning of
    the breach to wail and tear his hair”).
    Tuftco Corp. v. United States, 
    614 F.2d 740
     (Ct. Cl.
    1980), upon which the court relies, is inapposite. There,
    we concluded that the government waived its right to
    VERMONT YANKEE NUCLEAR POWER    v. US                   4
    object to contract assignments where the contracting
    officer had assured the contractor “that despite the Anti-
    Assignment Act, the assignments were proper and would
    be recognized by [the government].” 
    Id. at 745
    . Here, by
    contrast, the government never approved of, or acquiesced
    in, the partial assignment, but instead immediately
    sought redress by seeking to have that assignment invali-
    dated.
    “Waiver is an affirmative defense, as to which the
    breaching party bears the burden of proof.” Westfed, 
    407 F.3d at 1360
    . Mere assertions are not enough.
    United States Court of Appeals
    for the Federal Circuit
    __________________________
    VERMONT YANKEE NUCLEAR POWER
    CORPORATION,
    Plaintiff-Cross Appellant,
    v.
    ENTERGY NUCLEAR VERMONT YANKEE, LLC,
    AND ENTERGY NUCLEAR OPERATIONS, INC.,
    Plaintiffs-Cross Appellants,
    v.
    UNITED STATES,
    Defendant-Appellant.
    __________________________
    2011-5033, -5034, -5042
    __________________________
    Appeals from the United States Court of Federal
    Claims in consolidated Case Nos. 02-CV-898 and 03-CV-
    2663, Judge Thomas C. Wheeler.
    __________________________
    BRYSON, Circuit Judge, concurring in part and dissenting
    in part.
    I join the court’s opinion on all issues but one: the ma-
    jority’s conclusion that payments to the Vermont Clean
    Energy Development Fund and the requirement to put up
    a visual barrier at the power plant were unforeseeable
    2
    and therefore cannot be included in the calculation of
    ENVY’s damages.
    With respect to ENVY’s payments into the Clean En-
    ergy Development Fund, I would uphold the trial court’s
    finding that it was reasonably foreseeable at the time of
    contract formation that a nuclear operator would be faced
    with expenses of that type if the government’s breach
    forced the operator to build a dry storage facility. The
    costs of dealing with state regulatory efforts were clearly
    foreseeable. While the precise identity of those expenses
    may not have been predictable, all that is required is that
    “the injury actually suffered must be one of a kind that
    the defendant had reason to foresee.” 11 Joseph M.
    Perillo, Corbin on Contracts § 56.7, at 108 (rev. ed. 2005);
    see also Anchor Sav. Bank, FSB v. United States, 
    597 F.3d 1356
    , 1364 (Fed. Cir. 2010); Citizens Fed. Bank v. United
    States, 
    474 F.3d 1314
    , 1321 (Fed. Cir. 2007). The trial
    court reasonably found that the Clean Energy Develop-
    ment Fund payments met that test.
    “Foreseeability is a question of fact reviewed for clear
    error.” Pac. Gas & Elec. Co. v. United States, 
    668 F.3d 1346
    , 1352 (Fed. Cir. 2012), quoting Bluebonnet Sav.
    Bank, F.S.B. v. United States, 
    266 F.3d 1348
    , 1355 (Fed.
    Cir. 2001). The government has failed to show that the
    trial court’s findings on the issue of foreseeability were
    clearly erroneous. The majority accepts the government’s
    assertion that the payments in question were unforesee-
    able because the State’s regulatory efforts would likely
    have been preempted by federal law. But that is far from
    clear. As the majority itself points out, states are permit-
    ted certain regulatory powers over nuclear energy facili-
    ties if those powers are directed at non-safety issues, such
    as economic or other concerns. The majority relies on
    English v. General Electric Co. for the proposition that
    3
    state law is preempted if it “ha[s] some direct and sub-
    stantial effect on the decisions made by those who build or
    operate nuclear facilities concerning radiological safety
    levels.” 
    496 U.S. 72
    , 85 (1990). In fact, however, the
    Court in English concluded that even though claims for
    emotional distress stemming from whistleblowing activity
    relating to safety at a nuclear facility “may have some
    effect on these decisions,” the effect was “neither direct
    nor substantial enough to place petitioner’s claim in the
    pre-empted field.” 
    Id.
     Similarly, state tort law is not
    preempted for damages awards for radiation-based inju-
    ries—including punitive damages—even though the
    “prospect of compensatory and punitive damages for
    [these] injuries will undoubtedly affect nuclear employers’
    primary decisions about radiological safety in the con-
    struction and operation of nuclear power facilities.” 
    Id. at 86
    ; see Silkwood v. Kerr-McGee Corp., 
    464 U.S. 238
    , 256
    (1984).
    As the Supreme Court cases cited by the majority
    demonstrate, in 1983 it was foreseeable to the govern-
    ment that a state would try to regulate aspects of nuclear
    power facilities. In fact, the government was intimately
    involved in the litigation of nuclear power preemption
    cases, with varying degrees of success. See English, 
    496 U.S. 72
     (1990) (United States as amicus); Silkwood, 
    464 U.S. 238
     (1984) (same); Pac. Gas & Elec. Co. v. State
    Energy Res. Conservation & Dev. Comm’n, 
    461 U.S. 211
    (1983) (same). Attempted state regulation of nuclear
    waste storage facilities was at that time—and continued
    to be for years—a contested area of overlapping state and
    federal regulation. 1 E.g., In re Indep. Spent Fuel Storage
    1  The State of Vermont, as amicus curiae, asserts
    that the government cannot raise its preemption argu-
    ment because it failed to give notice of that argument to
    4
    Installation, 
    501 N.W.2d 638
    , 648 (Minn. App. 1993)
    (concluding that “proposed facility must be classified as a
    radioactive waste management facility [and] must obtain
    legislative authorization” pursuant to state law); cf.
    Citizens’ Util. Bd. v. Pub. Serv. Comm'n, 
    565 N.W.2d 554
    ,
    564 (Wis. App. 1997) (approving state commission’s
    determination that environmental impact statement
    prepared for dry fuel storage was adequate).
    Given such attempts to regulate nuclear power facili-
    ties by the states, it is reasonable to conclude that it was
    foreseeable that an injured party attempting to procure
    alternative storage for its SNF—and forced to do so
    quickly due to the government’s breach—would acquiesce
    in state demands, even demands that might be regarded
    as excessive. “The reasonably foreseeable consequences of
    a breach of contract are compensable, whether they were
    actually foreseen or not, or even if the criminal act of a
    third person intervened.” 24 Richard A. Lord, Williston
    on Contracts § 64:13, at 138-39 (4th ed. 2002). Because
    the issue of foreseeability in this case is at least debat-
    able, we should defer to the trial court’s findings.
    Given the pressure—due to the government’s
    breach—on ENVY to build SNF storage facilities quickly,
    it was also foreseeable that ENVY would elect not to
    engage in prolonged, costly, and complex litigation with
    the State pursuant to 
    28 U.S.C. § 2403
    (b). Setting aside
    whether section 2403 applies to the Court of Federal
    Claims, the statute is directed to the court, not the gov-
    ernment. Moreover, the preemption issue is not directly
    presented by this case; it is raised only indirectly, in
    support of the government’s contention that in light of the
    preemption doctrine among other reasons, it would not
    have been foreseeable for a nuclear operator to have to
    make mitigation payments in response to state regulatory
    efforts.
    5
    the State of Vermont over the preemption issue. See
    Restatement (Second) of Contracts § 351, cmt. c, illus. 9
    (explaining that payment of settlement by injured party
    to avoid litigation with a third party is foreseeable and
    therefore recoverable); cf. N.Y. Marine & Gen. Ins. Co. v.
    Lafarge N. Am., Inc., 
    599 F.3d 102
    , 122 (2d Cir. 2010)
    (concluding that in light of exceptional circumstances, it
    was reasonable for the insured to act quickly to minimize
    damages, even if its actions were not in strict compliance
    with those recommended by the insurer).
    In an analogous case, the Court of Federal Claims re-
    jected a similar argument by the government, stating that
    it “simply cannot be the case that plaintiff should be
    required to mitigate the damages caused by defendant’s
    breach . . . , be compelled to pursue that mitigation
    through the state legislature . . . , and then in the final
    analysis be forced to absorb the economic cost of legisla-
    tive mandates it had no power to avoid.” N. States Power
    Co. v. United States, 
    78 Fed. Cl. 449
    , 463, 464 (2007); see
    also Valladares v. DMJ, Inc., 
    885 P.2d 580
    , 582 (Nev.
    1994) (“[I]t would be inequitable for [the injured party] to
    be forced to pay for the results of [the breaching party’s]
    extreme lack of diligence in completing the contract.”). In
    this setting, as in other similar instances involving the
    question of which party should bear the costs of mitiga-
    tion, “the risks incident to [efforts to minimize losses from
    a breach] should be carried by the party whose wrongful
    conduct makes them necessary.” 11 Joseph M. Perillo,
    Corbin on Contracts § 57.16, at 349.
    The same arguments apply with perhaps even greater
    force to the costs for constructing the visual barrier. The
    government’s preemption rationale is attenuated in that
    setting because it is beyond dispute that states are per-
    mitted to regulate certain environmental aspects of
    6
    nuclear power plants as long as those aspects are unre-
    lated to radiological safety. Silkwood, 
    464 U.S. at 249
    ; N.
    States Power Co. v. Minnesota, 
    447 F.2d 1143
    , 1151 (8th
    Cir. 1971) (explaining that Atomic Energy Act “does not
    impair State authority to regulate activities of [nuclear
    plant operators] for the manifold health, safety, and
    economic purposes other than radiation protection”);
    Pennsylvania v. Lockheed Martin Corp., 
    684 F. Supp. 2d 564
    , 588 (M.D. Pa. 2010) (state statute permitting recov-
    ery of cleanup costs for radioactive material does not
    “cause a direct or substantial effect on the decisions made
    by [operators of] nuclear facilities concerning radiological
    safety levels”); Me. Yankee Atomic Power Co. v. Bonsey,
    
    107 F. Supp. 2d 47
    , 54 (D. Me. 2000) (“Nonradiological
    aspects of spent fuel storage, however, are still subject to
    some regulation by the states . . . .”); Conn. Coal. Against
    Millstone v. Conn. Siting Council, 
    942 A.2d 345
    , 359
    (Conn. 2008) (state council’s findings with respect to
    factors such as “distance of [nuclear] facility from residen-
    tial areas, the flood zone, and tidal and inland wetlands;
    the impact of the facility on groundwater; [and] the design
    of the facility” are not preempted by federal law).
    Because a visual barrier cannot be said to relate to
    radiological safety concerns, it likely lies outside the zone
    of federal preemption. It is therefore foreseeable that a
    state would respond to a proposed dry storage facility by
    requiring the construction of a visual barrier for aesthetic
    reasons and that such a requirement would not be subject
    to challenge on preemption grounds. See Me. Yankee, 
    107 F. Supp. 2d at 55
     (state may insist that nuclear operator
    “comply with state requirements that do not impermissi-
    bly infringe on radiological, operational, construction, or
    safety issues, such as, for example, aesthetic landscaping
    requirements”).
    7
    I therefore respectfully dissent from the majority’s de-
    cision to reverse the trial court on those two disputed
    items of mitigation expenses.
    

Document Info

Docket Number: 2011-5033, 2011-5034, 2011-5042

Citation Numbers: 683 F.3d 1330

Judges: Bryson, Dyk, Mayer

Filed Date: 6/13/2012

Precedential Status: Precedential

Modified Date: 8/5/2023

Authorities (36)

Skull Valley Band of Goshute Indians v. Nielson Ex Rel. ... , 376 F.3d 1223 ( 2004 )

New York Marine & General Insurance v. Lafarge North ... , 599 F.3d 102 ( 2010 )

Northern States Power Company v. The State of Minnesota, ... , 447 F.2d 1143 ( 1971 )

All-Ways Logistics, Inc. v. USA Truck, Inc. , 583 F.3d 511 ( 2009 )

Cole Taylor Bank v. Truck Insurance Exchange , 51 F.3d 736 ( 1995 )

anr-pipeline-company-v-iowa-state-commerce-commission-andrew-varley , 828 F.2d 465 ( 1987 )

Bluebonnet Savings Bank, F.S.B., Stone Capital, Inc. (... , 266 F.3d 1348 ( 2001 )

Yankee Atomic Electric Co. v. United States , 536 F.3d 1268 ( 2008 )

Indiana Michigan Power Company v. United States , 422 F.3d 1369 ( 2005 )

Dominion Resources, Inc. v. United States , 641 F.3d 1359 ( 2011 )

Westfed Holdings, Inc. v. United States , 407 F.3d 1352 ( 2005 )

Pacific Gas & Electric Co. v. United States , 668 F.3d 1346 ( 2012 )

Essex Electro Engineers, Inc. v. The United States , 757 F.2d 247 ( 1985 )

Delmarva Power & Light Co. v. United States , 542 F.3d 889 ( 2008 )

The Prudential Insurance Company of America v. The United ... , 801 F.2d 1295 ( 1986 )

System Fuels, Inc. v. United States , 666 F.3d 1306 ( 2012 )

Citizens Federal Bank v. United States , 474 F.3d 1314 ( 2007 )

Hercules Incorporated v. The United States, Wm. T. Thompson ... , 24 F.3d 188 ( 1994 )

Boston Edison Co. v. United States , 658 F.3d 1361 ( 2011 )

Anchor Sav. Bank, FSB v. United States , 597 F.3d 1356 ( 2010 )

View All Authorities »