Rockies Express Pipeline LLC v. Interior , 730 F.3d 1330 ( 2013 )


Menu:
  •   United States Court of Appeals
    for the Federal Circuit
    ______________________
    ROCKIES EXPRESS PIPELINE LLC,
    Appellant,
    v.
    KEN SALAZAR, Secretary of the Interior,
    Appellee.
    ----------------------
    KEN SALAZAR, Secretary of the Interior
    Appellant,
    v.
    ROCKIES EXPRESS PIPELINE LLC,
    Appellee.
    ______________________
    2012-1055, -1174
    ______________________
    Appeals from the Civilian Board of Contract Appeals
    in No. 1821, Administrative Judge Allan H. Goodman.
    ______________________
    Decided: September 13, 2013
    ______________________
    L. POE LEGGETTE, Fulbright & Jaworski, L.L.P., of
    Denver, Colorado, argued for Rockies Express Pipeline
    2                   ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR
    LLC. With him on the brief were OSBORNE J. DYKES, III,
    BENJAMIN M. VETTER and LUCY D. ARNOLD.
    DOMENIQUE KIRCHNER, Senior Trial Counsel, Com-
    mercial Litigation Branch, Civil Division, United States
    Department of Justice, of Washington, DC, argued for
    KEN SALAZAR, Secretary of the Interior. With her on the
    brief were STUART F. DELERY, Acting Assistant Attorney
    General, JEANNE E. DAVIDSON, Director, and HAROLD D.
    LESTER, JR., Assistant Director.
    ______________________
    Before RADER, Chief Judge, REYNA, Circuit Judge, and
    DAVIS ∗, Chief Judge.
    REYNA, Circuit Judge.
    This case involves a dispute over the interpretation of
    a series of contracts entered into by Rockies Express
    Pipeline LLC (“Rockies Express”) and Minerals Manage-
    ment Service, a unit of the Department of the Interior
    (collectively “Interior”). The dispute centers on the Royal-
    ty-in-Kind (RIK) provisions found in the contracts. The
    Civilian Board of Contract Appeals (“Board”) determined
    that Interior had materially breached the contract, but
    that Rockies Express was only entitled to damages that
    had accrued before the Secretary of the Interior an-
    nounced a decision to phase-out RIK contracts. We agree
    that Interior materially breached the contract, but we
    reverse the Board’s decision to limit damages. According-
    ly, we affirm-in-part, reverse-in-part, and remand.
    ∗
    The Honorable Leonard Davis, Chief Judge of the
    United States District Court for the Eastern District of
    Texas, sitting by designation.
    ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR                  3
    I. BACKGROUND
    In 2005, Rockies Express set out to build a $6.8 billion
    pipeline to ship natural gas from Wyoming to Eastern
    Ohio. The pipeline was to be built in two phases. The
    first phase, Rockies Express West, would be completed
    first and would stretch from Wyoming to Missouri. The
    second phase, Rockies Express East, would connect to
    Rockies Express West and continue from Missouri to
    Ohio. In exchange for building the pipeline, Interior
    agreed to pay Rockies Express a reservation charge for at
    least ten years per section, reserving 2.5% of the gas
    shipped on the pipeline. 1 Interior would receive the
    natural gas as a royalty-in-kind for gas Rockies Express
    extracted from federal land. 2 Interior agreed to pay the
    reservation charge regardless of whether or not it shipped
    gas on the pipeline and Rockies Express agreed to main-
    tain shipping capacity for Interior. Interior also agreed to
    initial reservation charges for Rockies Express West of
    $1,207,540/month. Upon completion of Rockies Express
    East, Interior promised to pay reservation charges of
    1   In addition to reservation charges, Interior was
    obligated to pay commodity charges, which included usage
    charges, fuel-burn charges, lost and unaccounted for gas
    charges, and annual cost of gas adjustment charges.
    2   Under the RIK program, the government receives
    its royalty for mineral resources extracted pursuant to
    federal leases “in kind,” i.e., in natural gas, rather than in
    value, or cash. See 
    30 U.S.C. § 192
    ; 
    42 U.S.C. § 15902
    (b).
    In exchange, the government makes monthly payments to
    ensure that a certain quantity of the mineral resources is
    made available for its purposes. The government then
    enters into processing and transportation contracts to sell
    the mineral royalties, often at a substantial profit over
    royalties received in value.
    4                 ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR
    $1,663,800/month. For Interior, the reservation charges
    created firm transportation capacity for its reserved
    natural gas. For Rockies Express, the reservation charges
    enabled it to recoup the massive capital investment it
    incurred in building the pipeline. The parties unques-
    tionably intended for the relationship to continue for at
    least ten years following the completion of Rockies Ex-
    press East. The terms guiding the relationship were
    considered and agreed upon prior to construction begin-
    ning on the pipelines.
    As required by the Federal Energy Regulatory Com-
    mission, before construction could begin, Rockies Express
    and Interior entered into a Precedent Agreement in order
    to memorialize the parties’ agreement. The Precedent
    Agreement is a primary agreement that obligated the
    parties to enter into follow-on agreements. During nego-
    tiations on the Precedent Agreement, Interior requested a
    termination for convenience clause or a clause that would
    allow it to terminate the agreements if Interior later
    abandoned the RIK program, but Rockies Express refused
    to agree to either clause. As a result, the parties agreed
    that under Provision 3(b) of the Precedent Agreement,
    Interior could terminate the agreement only if it was
    “directed by Legislative Action or required by a change in
    the Federal or State policy to discontinue taking gas in
    kind . . . upon (30) thirty days written notice to [Rockies
    Express].” Joint App’x 273 (emphasis added). Converse-
    ly, Rockies Express could be excused from liability to
    Interior upon the occurrence of certain events listed in
    Section 9(b) provided that it gave Interior a five-day
    notice. Most notably, Section 9(b)(v) provided that
    Transporter [i.e., Rockies Express] shall have the
    right to terminate this Precedent Agreement with
    no liability to Shipper [i.e., Interior] by giving
    Shipper five (5) days advance written notice
    (which notice must be given, if at all, within ten
    (10) days after the occurrence or nonoccurrence of
    ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR                    5
    the relied upon-event) . . . , in the event: . . . Ship-
    per fails to comply with any of its material obliga-
    tions hereunder or under any FTSA then in effect
    ....
    Joint App’x 279.
    The Federal Energy Regulatory Commission reviewed
    the Precedent Agreement between Rockies Express and
    Interior, as well as the precedent agreements that Rockies
    Express entered into with eleven other shippers of natu-
    ral gas, to determine if approval of the pipeline project
    was in the public interest. After reviewing the precedent
    agreements, the commission found that construction of
    the pipeline was in the public interest and treated all the
    precedent agreements as binding.
    Section 8(a) of the Precedent Agreement obligated In-
    terior to enter into Firm Transportation Service Agree-
    ments (FTSA) and Negotiated Rate Agreements, which
    would govern the shipment of gas over each segment of
    the pipeline:
    Shipper agrees that it will execute a minimum of
    three[ 3] Firm Transportation Service Agreements
    consistent with the form of Service Agreement as
    contained in Appendix B hereto, as finally ap-
    proved by [the Federal Energy Regulatory Com-
    mission] which, if Shipper shall have elected the
    Negotiated Reservation Rate Option, shall reflect
    the fixed nature of the reservation rate as de-
    scribed in Section 4, within five (5) business days
    after tender by Transporter.
    Joint App’x 277. Pursuant to Section 8(a), an unexecuted,
    but agreed-upon, FTSA for Rockies Express West and
    3   Three FTSAs were required because Rockies Ex-
    press East actually consisted of two segments initially.
    6                  ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR
    Rockies Express East was attached as Appendix B to the
    Precedent Agreement.
    Based on the foregoing contracts, construction on the
    Rockies Express West pipeline commenced in 2006. Once
    construction concluded, Interior executed an FTSA on
    April 24, 2007, and the Rockies Express West pipeline
    went into service. Interior shipped gas on Rockies Ex-
    press West for over a year without incident, including
    during the time construction was progressing on Rockies
    Express East. On May 16, 2008, shortly before Rockies
    Express East was completed, Rockies Express sent Interi-
    or the FTSAs for Rockies Express East, which had been
    drawn up from Appendix B of the Precedent Agreement.
    Rather than executing the FTSAs as required under the
    Precedent Agreement, Interior decided that the FTSA
    required Federal Acquisition Regulations (FAR) provi-
    sions, basing that decision on a non-binding memorandum
    from Interior’s Office of Solicitor. 4 The parties negotiated
    FAR provisions, but failed to reach an agreement, and
    Interior ultimately refused to sign the Rockies Express
    East FTSA that Rockies Express tendered on November
    25, 2008. On December 11, 2008, Rockies Express termi-
    nated the Precedent Agreement on the grounds that
    Interior was in material breach. Interior also stopped
    shipping gas on Rockies Express West on March 31, 2009,
    even though the Precedent Agreement obligated it to do
    so until Rockies Express East entered service. When
    Rockies Express East entered interim service on June 29,
    2009, Interior refused to ship gas on it based on the
    parties’ failure to execute an FTSA for Rockies Express
    East.
    4    We note that Interior did not insist on a similar
    requirement prior to executing the FTSA associated with
    Rockies Express West, which was for all purposes identi-
    cal to the Rockies Express East FTSA.
    ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR                 7
    On June 30, 2009, Rockies Express filed claims with
    the contracting officer for Interior’s breach, citing Interi-
    or’s refusal to execute the Rockies Express East FTSA
    and its failure to pay reservation charges on Rockies
    Express West from April 1 through June 28, 2009. On
    September 16, 2009, the Secretary of the Interior an-
    nounced the agency’s intention to phase-out RIK contracts
    and, on December 8, 2009, issued a memorandum in-
    structing the Assistant Secretary of Land and Minerals
    Management to “proceed with the termination of the RIK
    program.” Joint App’x 1268. Termination was to proceed
    according to a list of “guiding principles,” including honor-
    ing all existing RIK sales contracts. Consequently, Inte-
    rior allowed its RIK sales contract related to natural gas
    from Wyoming to expire on October 31, 2009, when the
    Rockies Express West FTSA was scheduled to conclude.
    On November 30, 2009, Interior’s contracting officer
    issued a Final Decision, concluding that Interior was not
    in breach for failing to enter into the Rockies Express
    East FTSA because the Precedent Agreement was not a
    binding contract and, in any event, Rockies Express
    committed the first material breach by terminating the
    agreement without a five-day notice.
    Rockies Express appealed the decision of the contract-
    ing officer to the Board and argued that the Precedent
    Agreement was a binding contract that Interior breached
    by not signing the Rockies Express East FTSA. The
    Board held that the Precedent Agreement was a contract
    for procurement of services, thereby vesting it with juris-
    diction, and that Interior breached the agreement by
    refusing to pay reservation charges on Rockies Express
    West and refusing to execute the Rockies Express East
    FTSA. The Board also found that Interior would have
    exercised the termination option pursuant to the agency’s
    announced policy decision to stop taking RIK payments.
    As a result, the Board concluded that Interior was only
    liable for the reservation charges on Rockies Express
    8                  ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR
    West ($3,542,121) and reservation charges on Rockies
    Express East through October 2009 ($3,319,104), not the
    ten-years-worth of reservation charges ($173,230,601), to
    which Rockies Express argued it was entitled.
    In its appeal to this court, Rockies Express challenges
    the Board’s conclusion that damages were limited by
    Interior’s subsequent “policy” change. Interior cross-
    appeals the Board’s exercise of jurisdiction over the
    Precedent Agreement and its liability under it. We have
    jurisdiction pursuant to 
    28 U.S.C. § 1295
    (a)(10).
    II. STANDARD OF REVIEW
    The Board’s factual determinations shall be set aside
    if they are arbitrary, capricious, or unsupported by sub-
    stantial evidence. 
    41 U.S.C. § 7107
    (b)(2); see TipTop
    Constr. Inc. v. Donahoe, 
    695 F.3d 1276
    , 1281 (Fed. Cir.
    2012). Its determinations on questions of law, including
    jurisdiction and interpretations of contracts, statutes, and
    regulations, are reviewed de novo. Parsons Global Servs.
    Inc. v. McHugh, 
    677 F.3d 1166
    , 1170 (Fed. Cir. 2012);
    Brownlee v. DynCorp, 
    349 F.3d 1343
    , 1349 (Fed. Cir.
    2003).
    III. JURISDICTION
    Under the Contract Disputes Act, the Board possesses
    jurisdiction to hear suits over any express or implied
    contract made by an Executive agency, including con-
    tracts for the “procurement of services.” 
    41 U.S.C. §§ 7102
    (a)(2), 7105(e)(1)(B). Interior argues that the Board
    lacks jurisdiction in this case because the Precedent
    Agreement was not a procurement contract within the
    terms of the Contract Disputes Act because no services
    were procured under it. While the Contract Disputes Act
    does not define “procurement,” Interior notes that this
    court has previously characterized procurement as “the
    acquisition . . . of property or services for the direct bene-
    fit or use of the Federal Government.” New Era Constr. v.
    ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR                9
    United States, 
    890 F.2d 1152
    , 1157 (Fed. Cir. 1989) (em-
    phasis omitted). In Interior’s view, for a procurement
    contract to exist, there must be a buyer-seller relationship
    and the expenditure of government funds. Interior main-
    tains that the Precedent Agreement is an agreement to
    agree in the future and that Interior would not “acquire
    any transportation service” until after execution of the
    FTSAs. As a result, there was no buyer-seller relation-
    ship or expenditure of government funds under the Prece-
    dent Agreement. We are not persuaded by Interior’s
    arguments.
    Congress defined “procurement” when it established
    the Office of Federal Procurement Policy, which oversees
    the direction of federal procurement policies, regulations,
    and procedures. Distributed Solutions Inc. v. United
    States, 
    539 F.3d 1340
    , 1345 (Fed. Cir. 2008) (citing 
    41 U.S.C. §§ 401-20
    ). Specifically, 
    41 U.S.C. § 403
    (2) states
    that “‘procurement’ includes all stages of the process of
    acquiring property or services, beginning with the process
    of determining a need for property or services and ending
    with contract completion and closeout.” 
    41 U.S.C. § 403
    (2). This court has relied on this definition for pro-
    curement on multiple occasions. See Res. Conservation
    Grp. LLC v. United States, 
    597 F.3d 1238
    , 1244 (Fed. Cir.
    2010); Distributed Solutions, 
    539 F.3d at 1345
    . While
    those cases involved defining the term, “procurement,” in
    the context of the Court of Federal Claims’ jurisdictional
    statute, the Tucker Act, we discern no reason that un-
    dermines the applicability of the definition to the portion
    of the Contract Disputes Act that defines the Board’s
    jurisdiction. It follows that this definition of “procure-
    ment” is not limited to situations where money has
    changed hands or there is a buyer-seller relationship;
    rather, “procurement” covers “all stages of the process of
    acquiring property or services.”
    The Board’s carefully-reasoned opinion recognizes
    that the Precedent Agreement bears all the hallmarks of
    10                 ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR
    a traditional contract. It contains the essential terms and
    conditions, it was negotiated and approved by an author-
    ized official, it is supported by consideration, and it con-
    tains an expressed statement of an intention to be bound.
    See Rockies Express Pipeline LLC v. Dep’t of the Interior,
    CBCA 1821, 
    10-2 BCA ¶ 34,542
    , at 170,356–57. Fur-
    thermore, upon fulfillment of certain conditions prece-
    dent, the Precedent Agreement obligated the parties to
    enter into an agreed-upon FTSA, which was incorporated
    as an appendix to the agreement. 
    Id. at 170,357
    . Unlike
    the independent contracts at issue in Wesleyan Co. v.
    Harvey, 
    454 F.3d 1375
     (Fed. Cir. 2006), the principal case
    on which Interior relies, the Precedent Agreement is part
    of an interlocking set of agreements through which both
    parties were bound. We refuse to convert the Precedent
    Agreement into a mere options contract from which
    Interior could withdraw at its leisure, thereby causing
    Rockies Express to bear an unanticipated share of the
    expense involved in constructing a $6.8 billion pipeline.
    Therefore, we hold that the Precedent Agreement is a
    contract for the procurement of transportation services
    justiciable under the Contract Disputes Act. Having
    determined that the Board and this court have jurisdic-
    tion, we now turn to the merits of the dispute.
    IV. DISCUSSION
    We must decide whether Interior breached the Prece-
    dent Agreement and, if so, the amount of damages, if any,
    to which Rockies Express is entitled. The Board held that
    Interior’s refusal to sign the Rockies Express East FTSA
    breached the Precedent Agreement. As a defense to its
    alleged breach, Interior contends that the Rockies Ex-
    press East FTSA would have been an illegal contract for
    three reasons. First, Interior argues that a ten-year
    contract term “is contrary to statute and no government
    official could have agreed to it.” Interior’s Br. 26 (citing
    
    41 U.S.C. § 3903
    ). At bottom, Interior argues that its
    promise to enter into the Rockies Express East FTSA was
    ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR               11
    an illegal promise and thus unenforceable. Second,
    Interior claims that the Rockies Express East FTSA did
    not include a termination for convenience clause and that
    this clause was required by our predecessor court’s hold-
    ing in G.L. Christian & Associates v. United States, 
    312 F.2d 418
    , 426 (Ct. Cl. 1963). According to Interior, its
    refusal to sign the Rockies Express East FTSA without
    this clause was not a breach of the Precedent Agreement.
    Third, Interior argues that while an agency head can
    authorize deviations from the FAR, the contracting officer
    lacked authority to bind the government to a promise to
    sign future FTSAs because no deviation eliminating the
    need for a termination for convenience clause was ob-
    tained prior to the Precedent Agreement’s execution. We
    are not convinced by Interior’s contract-based defenses.
    We first address whether the Rockies Express East
    FTSA would have been unenforceable because of its ten-
    year term. We note that Interior has not established that
    FAR provisions contained in the procurement statutes are
    applicable to the Precedent Agreement. Where there is a
    question over the applicability of the procurement stat-
    utes, a contract is unenforceable only when the contractor
    caused the illegal award, or the illegality was so obvious
    that the contractor should have recognized it. United
    States v. Ahmdal Corp., 
    786 F.2d 387
    , 395 (Fed. Cir.
    1986). When an illegality is not obvious, a contractor
    should be accorded the benefit of all reasonable doubts
    and the award upheld. John Reiner & Co. v. United
    States, 
    325 F.2d 438
    , 440 (Ct. Cl. 1963).
    The Energy Policy Act of 2005 governs RIK transpor-
    tation contracts “[n]otwithstanding any other provisions
    of law.” 
    42 U.S.C. § 15902
    ; see also Cisneros v. Alpine
    Ridge Grp., 
    508 U.S. 10
    , 18 (1993) (noting that the use of
    a “notwithstanding” clause signals the drafter’s intention
    that the section override conflicting provisions elsewhere).
    While traditional procurement contracts are subject to
    appropriations regulations requiring shorter contract
    12                ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR
    terms than the ten years specified in the FTSAs in this
    case, RIK contracts specifically are governed by the
    provisions contained in § 15902, which contain no such
    limitation. The statute is clear that RIK transportation
    contracts are removed from the scope of traditional pro-
    curement rules.
    We agree with the government that it may cancel as
    illegal a contract that violates procurement statues or
    regulations, see Schoenbrod v. United States, 
    410 F.2d 400
    , 403–04 (Ct. Cl. 1969), but Interior has conceded that
    the FTSAs are not illegal contracts. Specifically, Interior
    is not contesting its liability under the Rockies Express
    West FTSA, which in all material respects is the same as
    the Rockies Express East FTSA. The Board concluded
    that Interior owes Rockies Express over $3 million for
    breaching the Rockies Express West FTSA, and Interior
    does not dispute this finding on appeal. Interior cannot
    escape liability on the grounds that the same contract
    provisions in Rockies Express West for which it assumed
    liability are illegal in Rockies Express East. It follows
    that if Rockies Express can recover under the Rockies
    Express West FTSA, it should also have a remedy for
    Interior’s breach related to the Rockies Express East
    FTSA. See Maxima Corp. v. United States, 
    847 F.2d 1549
    ,
    1556 (Fed. Cir. 1988); see also Brandt v. Hickel, 
    427 F.2d 53
    , 57 (9th Cir. 1970) (“To say to these appellants, ‘The
    joke is on you. You shouldn't have trusted us,’ is hardly
    worthy of our great government.”).
    Finally, the Board observed that Rockies Express does
    not have a history of contracting with the government.
    Thus, it was presumably unaware of whether a particular
    FAR provision might be applicable. In any event, there is
    no evidence that Rockies Express created or overlooked an
    obvious illegality, assuming one existed. As such, we
    accord Rockies Express the benefit of all reasonable
    doubts and uphold the Board’s determination that the
    Precedent Agreement was a legally binding contract. See
    ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR                13
    John Reiner & Co., 
    325 F.2d at 440
     (“It is therefore just to
    the contractor, as well as to the Government, to give him
    the benefit of reasonable doubts [when the issue of legali-
    ty is very close] and to uphold the award unless its inva-
    lidity is clear.”).
    We now turn to Interior’s second argument that the
    absence of a termination for convenience clause in the
    Precedent Agreement excuses its refusal to sign the
    Rockies Express East FTSA. This argument incorrectly
    assumes that the Precedent Agreement required a termi-
    nation clause in the first place. Christian stands for the
    proposition that if the parties to a government contract
    neglect to include a clause in the contract that is otherwise
    required by regulation (e.g., a termination for convenience
    clause), courts will read the clause into the contract as a
    matter of law. 
    312 F.2d at
    426–27. Here, Interior has not
    shown that the Precedent Agreement was necessarily
    covered by the FAR, or that the termination for conven-
    ience clause was necessarily required. Nor has Interior
    established that a termination for convenience clause is
    required in RIK contracts by law or regulation such that
    the parties neglected to include one. As we have previous-
    ly observed, the “[n]otwithstanding any other provisions
    of law” provision in § 15902 excepts RIK contracts from
    provisions normally required by the procurement stat-
    utes. Consistent with this exception, the Director of the
    Minerals Management Service instructed the RIK pro-
    gram to use standard industry contracts. As the contract-
    ing officer noted, a termination for convenience clause is
    the antithesis of an industry practice and would “totally
    run counter to [Interior’s] approach in royalty in kind.”
    Rockies Express, 
    11-2 BCA ¶ 34,847
    , at 171,414. In any
    event, violation of the Christian doctrine does not render
    a contract illegal; it permits the court to cure the defect
    and include the clause after the fact. 
    312 F.2d at 427
    .
    Interior’s third argument is also without merit. In
    pressing it, Interior essentially contends that the con-
    14                 ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR
    tracting officer lacked authority to enter into the Prece-
    dent Agreement, which obligated Interior to sign future
    FTSAs, because he had not sought a deviation from the
    required termination for convenience clause. This argu-
    ment essentially repackages Interior’s second argument,
    which we rejected above. Additionally, Interior concedes
    that it could have sought a deviation from any FAR
    provision it believed applied, which it did not do. Accord-
    ingly, we affirm the Board’s conclusion that even assum-
    ing FAR provisions were required, Interior breached the
    Precedent Agreement by refusing to seek a deviation from
    the FAR provisions when negotiating the Rockies Express
    East FTSA. Cf. Rockies Express, 
    11-2 BCA ¶ 34,847
    , at
    171,421–22 (citing 
    48 C.F.R. § 1.401
    ); see also 
    48 C.F.R. § 1.402
    . In particular, we affirm the Board’s conclusions
    that Interior breached the following provisions of the
    Precedent Agreement: Section 12, which states that the
    Precedent Agreement is a “legal, valid, binding and
    enforceable obligation” of the parties; Section 10, which
    authorizes modifications only when ordered or required by
    a “law, order, decision, rule, or regulation”; and Section
    8(a), which states that Interior “agrees it will execute a
    minimum of three [FTSAs]” consistent with the form
    agreement attached to the Precedent Agreement. Rockies
    Express, 
    11-2 BCA ¶ 34,847
    , at 171,421–22. Interior
    breached Section 12 by insisting that the Precedent
    Agreement was illegal and unenforceable instead of
    treating it as legal, valid, binding and enforceable obliga-
    tion. It breached Section 10 by requiring a modification
    in the form of a termination for convenience clause that
    was not required by any law, order, decision, rule or
    regulation. And it breached Section 8(a) by refusing to
    seek a deviation that would have allowed it to execute the
    Rockies Express East FTSA without the additional FAR
    provisions. Accordingly, we hold that Interior materially
    breached the Precedent Agreement upon its refusal to
    enter into the Rockies Express East FTSA.
    ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR                  15
    Interior contends alternatively that Rockies Express
    breached the Precedent Agreement first by prematurely
    terminating it. Interior argues that under Provision 9(b)
    of the Precedent Agreement, Rockies Express was re-
    quired to provide a five-day notice before terminating the
    Precedent Agreement. Interior misreads Provision 9(b).
    Provision 9(b) sets out the procedure under which Rockies
    Express may terminate the Precedent Agreement so as to
    relieve itself of liability upon the occurrence of certain
    events, including “[Interior’s] fail[ure] to comply with any
    of its material obligations [under the Precedent Agree-
    ment].” Joint App’x 279. By declaring the Precedent
    Agreement breached and terminating it, Rockies Express
    did not seek to relieve itself of liability, but instead sought
    to establish Interior’s culpability for the breach. Conse-
    quently, the five-day notice requirement of Provision 9(b)
    does not apply.
    The remaining issue is the quantum of the damages
    owed to Rockies Express. The Board relied on a double
    inference to limit damages as of October 31, 2009. Specif-
    ically, the Board reasoned that had Interior executed the
    Rockies Express East FTSA, Interior would have termi-
    nated the Rockies Express East FTSA under Provision
    3(b) following the Secretary’s announcement of the agen-
    cy’s “policy” change with respect to the RIK program.
    Provision 3(b) of the Precedent Agreement provides that
    interior may terminate the Precedent Agreement when it
    is “directed by Legislative Action or required by a change
    in Federal . . . policy.” Joint App’x 273 (emphasis added).
    It follows that Interior could have terminated the Prece-
    dent Agreement if one of the two following scenarios had
    occurred: Congress enacted legislation that specifically
    directed Interior to stop accepting RIK payments or that
    declared existing RIK contracts null and void, or a change
    in Federal policy was implemented that required Interior
    to terminate the RIK program. It is undisputed that
    there was no legislative action directing Interior to stop
    16                ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR
    taking gas-in-kind. The Board, however, concluded that
    the Secretary initiated a change in Federal policy that
    required Interior to terminate the RIK program and
    withdraw from the Rockies Express East FTSA.
    We note at the outset that some members of Congress,
    most notably the chair of the House Committee on Natu-
    ral Resources, Congressman Rahall, had attempted to
    terminate the RIK program through legislative action for
    several years without success. Indeed, it was during a
    hearing on Chairman Rahall’s proposed legislation for
    terminating the program that the Secretary of Interior
    announced the agency’s intention to phase out the RIK
    program. Almost three months later, the Secretary
    followed up on the announced intention by issuing a
    memorandum in which he directed the Assistant Secre-
    tary of Land and Minerals Management to proceed with
    the termination of the RIK program. The Secretary,
    however, instructed that the termination was to proceed
    according to a list of “guiding principles.” One of the
    principles listed was that all existing RIK sales contracts
    would be honored.
    The Board’s conclusion that the Secretary’s actions
    amount to a change in Federal policy overlooks the Secre-
    tary’s guiding principle that all existing RIK sales con-
    tracts would be honored. Assuming that the Rockies
    Express East FTSA had been executed by Interior in 2008
    as it was obligated to do, there is no question that the
    FTSA would constitute an “existing RIK sales contract”
    when the Secretary’s memorandum issued in December
    2009. Accordingly, even under the Secretary’s RIK pro-
    gram phase-out, Interior was obligated to honor the
    Rockies Express East FTSA for the full ten-year duration
    of that agreement. This means that there was no change
    in Federal policy that would have affected the Rockies
    Express East FTSA.
    ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR               17
    The language contained in Provision 3(b) further con-
    vinces us that the Secretary’s statements did not create a
    change in Federal policy even in a broader sense. Under
    traditional contract principles, “a change in Federal
    policy” and “Legislative Action” from Provision 3(b) should
    be interpreted ejusdem generis, or “of the same kinds,
    class, or nature.” Cf. Avenues in Leather, Inc. v. United
    States, 
    178 F.3d 1241
    , 1243 & n.1 (Fed. Cir. 1999) (quot-
    ing Black’s Law Dictionary (6th ed. 1990)). Thus, any
    policy change recognized by Provision 3(b) must carry the
    same significance as Legislative Action. Under the Ad-
    ministrative Procedure Act, there is no effective “change”
    in Federal policy until various requirements are met, such
    as publication in the Federal Register and opportunity for
    public comment. 
    5 U.S.C. § 552
    (a)(1)(D)-(E); see Metric
    Constructors, Inc. v. NASA, 
    169 F.3d 747
    , 752 (Fed. Cir.
    1999); cf. Termination of the Royalty-in-Kind (RIK) Eligi-
    ble Refiner Program, 
    75 Fed. Reg. 15,725
     (Mar. 30, 2010).
    There was no publication in this case and, consequently,
    the Board erroneously concluded that the Secretary’s
    announced intention resulted in the type of change in
    Federal policy that would result in the vitiation of valid
    contracts.
    Furthermore, the Board erred when it relied on a dic-
    tionary definition for “policy” that was divorced from the
    Precedent Agreement. See Rockies Express, 
    11-2 BCA ¶ 34,847
    , at 171,423 (quoting Webster’s New Collegiate
    Dictionary 882 (1979)). In particular, the Board defined
    “policy” as
    a definite course of action or method of action se-
    lected among alternatives in light of given condi-
    tions to guide and determine present and future
    decisions; a high-level plan embracing the general
    goals and acceptable procedures, especially of a
    governmental body.
    18                  ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR
    
    Id.
     This general dictionary definition of “policy” overlooks
    the context in which the term arose and the intention of
    the parties—most notably, the initial negotiations by the
    parties on the Precedent Agreement and Rockies Ex-
    press’s unwillingness to agree to a termination for conven-
    ience clause. See Metric, 
    169 F.3d at 752
     (“[T]o interpret
    disputed contract terms, the context and intention of the
    contracting parties are more meaningful than the diction-
    ary definition.”). We therefore conclude that the Secre-
    tary’s announced intention did not constitute a “change in
    Federal . . . policy” that would have limited Interior’s
    liability for refusing to sign the Rockies Express East
    FTSA.
    Finally, we address whether Interior may escape
    damages through post-termination actions such as its
    attempt to terminate the Precedent Agreement under
    Provision 3(b), which occurred after it had breached the
    Precedent Agreement. Relying on Northern Helex Co. v.
    United States (Helex III), 
    524 F.2d 707
     (Ct. Cl. 1975),
    Rockies Express argues that Interior cannot rely on post-
    breach events to limit damages. Rockies Express main-
    tains that upon termination for Interior’s material breach,
    the balance owed on the contract immediately became due
    so it is entitled to damages equal to the full value of the
    contract.
    As our predecessor court has recognized,
    [a] material breach does not automatically and ip-
    so facto end a contract. It merely gives the injured
    party the right to end the agreement; the injured
    party can choose between canceling the contract
    and continuing it. If he decides to close the con-
    tract and so conducts himself, both parties are re-
    lieved of their further obligations and the injured
    party is entitled to damages to the end of the con-
    tract term (to put him in the position he would
    have occupied if the contract had been completed).
    ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR               19
    Cities Serv. Helex, Inc. v. United States, 
    543 F.2d 1306
    ,
    1313 (Ct. Cl. 1976). In this case, Rockies Express chose to
    terminate the contract upon Interior’s material breach.
    As a result, under Helex III, Rockies Express is entitled to
    damages through the end of the contract period regardless
    of any post-termination actions performed by Interior. In
    particular, Interior’s attempted termination of the con-
    tract following its material breach was ineffective to limit
    damages because Interior could not terminate a non-
    existing contract. Helex III, 524 F.2d at 716. It follows
    that Rockies Express is entitled to compensatory damages
    designed “to put [it] in as good a position as that in which
    [it] would have been put by full performance of the con-
    tract.” Id. at 713. We conclude that it was improper for
    the Board to limit damages as of October 31, 2009.
    The burden to determine the quantum of Rockies Ex-
    press’s compensatory damages rests on the Board. We
    observe that by claiming two alternative entitlements to
    the balance due on the contract ($173,230,601 or
    $130,975,417), Rockies Express is requesting not only its
    profits throughout the full term of the Precedent Agree-
    ment, but also the costs it avoided having never shipped
    natural gas to Interior on Rockies Express East. Recovery
    of the full contract price presumes that Rockies Express
    was unable to find another shipper willing to assume
    Interior’s 2.5% reservation after undertaking reasonable
    efforts. This decision is not for this court to make and we
    instruct the Board to make this determination on remand.
    Nevertheless, we hold that Rockies Express is only enti-
    tled to “recover its pecuniary loss of anticipated and
    unearned profits” for the contract term, not the entire
    value of the contract when it includes costs avoided or
    offsets gained through mitigation. Helex III, 524 F.2d at
    721.
    20                 ROCKIES EXPRESS PIPELINE LLC   v. INTERIOR
    V. CONCLUSION
    In sum, we conclude that review of the Precedent
    Agreement fell within the Board’s jurisdiction, and we
    affirm that Interior materially breached that agreement.
    We reverse the Board’s decision that limited liability due
    to a purported change in policy by Interior. Accordingly,
    for the reasons set forth in this opinion, we affirm-in-part,
    reverse-in-part, and remand for the purpose of calculating
    Rockies Express’s damages.
    AFFIRMED-IN-PART, REVERSED-IN-PART, AND
    REMANDED
    COSTS
    Costs to Rockies Express.
    

Document Info

Docket Number: 2012-1055, 2012-1174

Citation Numbers: 730 F.3d 1330

Judges: Davis, Rader, Reyna

Filed Date: 9/13/2013

Precedential Status: Precedential

Modified Date: 8/7/2023

Authorities (14)

Mary L. Brandt and Natalie Z. Shell v. Walter J. Hickel, ... , 427 F.2d 53 ( 1970 )

Les Brownlee, Acting Secretary of the Army v. Dyncorp , 349 F.3d 1343 ( 2003 )

Metric Constructors, Inc. v. National Aeronautics and Space ... , 169 F.3d 747 ( 1999 )

Maxima Corporation v. The United States , 847 F.2d 1549 ( 1988 )

Avenues in Leather, Inc. v. United States , 178 F.3d 1241 ( 1999 )

Wesleyan Company, Inc. v. Francis J. Harvey, Secretary of ... , 454 F.3d 1375 ( 2006 )

G. L. Christian and Associates v. The United States , 312 F.2d 418 ( 1963 )

The United States v. Amdahl Corporation , 786 F.2d 387 ( 1986 )

PARSONS GLOBAL EX REL. ODELL INTERN. v. McHugh , 677 F.3d 1166 ( 2012 )

Resource Conservation Group, LLC v. United States , 597 F.3d 1238 ( 2010 )

Herbert Schoenbrod, as Trustee, Etc. v. The United States , 410 F.2d 400 ( 1969 )

John Reiner & Company, Individually and to the Use of Kurz &... , 325 F.2d 438 ( 1963 )

Distributed Solutions, Inc. v. United States , 539 F.3d 1340 ( 2008 )

Cisneros v. Alpine Ridge Group , 113 S. Ct. 1898 ( 1993 )

View All Authorities »