Pseg Nuclear, l.l.c. v. United States , 465 F.3d 1343 ( 2006 )


Menu:
  • Error: Bad annotation destination
    United States Court of Appeals for the Federal Circuit
    05-5162
    PSEG NUCLEAR, L.L.C.,
    and PUBLIC SERVICE ELECTRIC AND GAS COMPANY,
    Plaintiffs-Appellants,
    v.
    UNITED STATES,
    Defendant-Appellee.
    Jay E. Silberg, Pillsbury Winthrop Shaw Pittman LLP, of Washington, DC, argued for
    plaintiffs-appellants. With him on the brief were Alex D. Tomaszczuk, Daniel S. Herzfeld,
    and Jack Y. Chu, of McLean, Virginia.
    Harold D. Lester, Jr., Assistant Director, Commercial Litigation Branch, Civil Division,
    United States Department of Justice, of Washington, DC, argued for defendant-appellee.
    With him on the brief were Peter D. Keisler, Assistant Attorney General; David M. Cohen,
    Director; Alan J. Lo Re, Senior Trial Counsel; and Heide L. Herrmann, Trial Attorney. Of
    counsel was Jane K. Taylor, United States Department of Energy, of Washington, DC.
    Jerry Stouck, Greenberg Traurig, LLP, of Washington, DC, for amici curiae. With him
    on the brief was Robert L. Shapiro.
    Appealed from: United States Court of Federal Claims
    Senior Judge Bohdan A. Futey
    United States Court of Appeals for the Federal Circuit
    05-5162
    PSEG NUCLEAR, L.L.C.,
    and PUBLIC SERVICE ELECTRIC AND GAS COMPANY,
    Plaintiffs-Appellants,
    v.
    UNITED STATES,
    Defendant-Appellee.
    __________________________
    DECIDED: September 29, 2006
    __________________________
    Before LOURIE, RADER, and PROST, Circuit Judges.
    PROST, Circuit Judge.
    PSEG Nuclear, L.L.C. and Public Service Electric and Gas Company (collectively
    “PSEG”) appeal the decision of the United States Court of Federal Claims holding that
    the court lacked subject matter jurisdiction over PSEG’s breach of contract claims. Fla.
    Power & Light Co. v. United States, 
    64 Fed. Cl. 37
    , 44 (2005) (“Florida Power I”).
    Because we hold that the Court of Federal Claims possesses subject matter jurisdiction
    over the claims under the Tucker Act, 
    28 U.S.C. § 1491
    (a)(1), we reverse.
    BACKGROUND
    I.
    The breach of contract claims asserted in this case stem from contracts entered
    into between PSEG and the Department of Energy (“DOE”) under the Nuclear Waste
    Policy Act of 1982 (“NWPA” or “the Act”), 
    42 U.S.C. §§ 10101-10270
    .              Congress
    enacted the NWPA in January 1983 in order to provide for collection and storage of
    radioactive waste and spent nuclear fuel (collectively “SNF”) by the DOE. Under its
    scheme, section 302 of the Act authorized the DOE to enter into contracts with
    companies who generate or hold SNF provided that the companies pay into a fund used
    to pay for SNF collection and storage. 
    42 U.S.C. § 10222
     (2000). The Act states in
    pertinent part:
    (a) Contracts
    (1) In the performance of his functions under this chapter, the Secretary
    [of Energy] is authorized to enter into contracts with any person who
    generates or holds title to high-level radioactive waste, or spent nuclear
    fuel, of domestic origin for the acceptance of title, subsequent
    transportation, and disposal of such waste or spent fuel. Such contracts
    shall provide for payment to the Secretary of fees pursuant to paragraphs
    (2) and (3) sufficient to offset expenditures described in subsection
    (d) . . . .
    ...
    (5) Contracts entered into under this section shall provide that--
    (A) following commencement of operation of a repository, the Secretary
    shall take title to the high-level radioactive waste or spent nuclear fuel
    involved as expeditiously as practicable upon the request of the generator
    or owner of such waste or spent fuel; and
    (B) in return for the payment of fees established by this section, the
    Secretary, beginning not later than January 31, 1998, will dispose of the
    high-level radioactive waste or spent nuclear fuel involved as provided in
    this subchapter.
    
    Id.
     (emphases added).
    The DOE engaged in an administrative hearing process to create a single
    contract with identical terms (“the Standard Contract”) for use with all parties contraction
    under section 302. The contract included the terms required by the NWPA and also
    05-5162                                      2
    many additional terms. In general, the contract required companies with SNF to pay a
    fee that the DOE would use to develop an SNF storage facility and to collect and
    maintain the SNF at the facility.1 Beginning in 1983, utility companies with SNF entered
    into contracts based on the Standard Contract and started paying into the fund while the
    DOE, presumably, began preparations to start collecting and disposing of the
    companies’ SNF.2
    Once it became clear that the DOE would not be prepared to begin SNF
    collection by the January 31, 1998 date in the Standard Contract, the contracting utility
    companies, including PSEG, brought suit for breach of the Standard Contract. To date,
    the government asserts that sixty-six such claims have been filed.
    II.
    One provision of the NWPA discusses judicial review of DOE actions taken
    pursuant to the NWPA. This provision, section 119, states:
    (a) Jurisdiction of United States courts of appeals
    (1) Except for review in the Supreme Court of the United States, the
    United States courts of appeals shall have original and exclusive
    jurisdiction over any civil action--
    (A) for review of any final decision or action of the Secretary, the
    President, or the Commission under this part; . . . .
    
    42 U.S.C. § 10139
     (2000) (emphasis added).
    1
    The facility, still under development by the DOE, is commonly known as
    Yucca Mountain.
    2
    PSEG entered into a contract based on the Standard Contract on June 13,
    1983 and it alleges that it has paid at least $540 million into the SNF fund pursuant to its
    obligations under the contract.
    05-5162                                      3
    In several cases, courts of appeals have asserted jurisdiction under section 119
    over claims brought challenging DOE actions under the NWPA. The first of these cases
    was General Electric Uranium v. United States Department of Energy, 
    764 F.2d 896
    ,
    901 (D.C. Cir. 1985).    In that case, the plaintiff alleged that the DOE abused its
    discretion when setting one-time fees under its authority under section 302(a)(3) of the
    NWPA. Although section 302(a)(3) fell within Title III of the Act and section 119 was in
    Title I and only conferred the courts of appeals with jurisdiction over agency actions
    “under this part,” the D.C. Circuit held that it possessed jurisdiction over the case. The
    court reasoned that DOE’s rule setting the one-time fee under section 302(a)(3) was
    “well within the class of agency actions reviewable under section 119(a)(1)(A).” 
    Id.
     The
    court based this determination on three considerations: 1) the structure and language of
    the NWPA evinced congressional intent to vest the courts of appeals with jurisdiction
    over cases such as this one; 2) relevant legislative history did not compel a contrary
    result; and 3) policy considerations supported the conclusion. 
    Id.
     Subsequently, the
    D.C. Circuit exercised original jurisdiction over several cases brought under the NWPA
    challenging agency actions without any discussion of its jurisdictional limits under the
    statute.3
    3
    See Commonwealth Edison v. U.S. Dep’t of Energy, 
    877 F.2d 1042
    , 1045
    (D.C. Cir. 1989) (challenging the Treasury bill rate applied by DOE pursuant to the
    section 302(a)(4) fee provision); Nat’l Ass’n of Regulatory Utility Comm’rs v. U.S. Dep’t
    of Energy, 
    851 F.2d 1424
     (D.C. Cir. 1988); Wisconsin Elec. Power v. Dep’t of Energy,
    
    778 F.2d 1
    , 3 (D.C. Cir. 1985). In addition to the D.C. Circuit, other circuit courts have
    also asserted jurisdiction over cases brought under NWPA Title III. See Ala. Power Co.
    v. U.S. Dep’t of Energy, 
    307 F.3d 1300
     (11th Cir. 2002); Natural Res. Def. Council, Inc.
    v. Abraham, 
    244 F.3d 742
     (9th Cir. 2001).
    05-5162                                     4
    Subsequently, the DOE began to see claims under the Standard Contract for its
    failure to begin collecting SNF from the power companies by January 31, 1998. The
    DOE initially issued a regulation which stated that it “does not have an unconditional
    statutory or contractual obligation to accept nuclear waste beginning January 31, 1998
    in the absence of a repository or interim storage facility constructed under the Act.” 
    60 Fed. Reg. 21,793
     (1995) (“Final Interpretation of Nuclear Waste Acceptance Issues”).
    However, in Indiana Michigan Power Co. v. Department of Energy, the D.C. Circuit held
    that, contrary to DOE’s regulation, the agency was obliged to begin accepting SNF on
    January 31, 1998, even in the absence of a repository. 
    88 F.3d 1272
    , 1277 (D.C. Cir.
    1996).4 However, the court held that no remedy was available to the companies until
    after the deadline had passed. The court’s jurisdiction over the case was not at issue.
    The DOE proceeded by arguing that its failure to perform was an “unavoidable
    delay” under the contract and was therefore not compensable.          A group of power
    companies sought a writ of mandamus from the D.C. Circuit requiring the DOE to
    comply with Indiana Michigan and begin SNF collection by the contracted deadline. In
    Northern States Power Co. v. United States Department of Energy, 
    128 F.3d 754
     (D.C.
    Cir. 1997), the court held that this mandamus request was not proper because the
    companies had adequate remedies under the Standard Contract. However, so that the
    companies would be able to enforce the terms of the contract to effectuate the DOE’s
    duty, the court issued a writ of mandamus forbidding the DOE from claiming, in
    proceedings under its contracts, that its failure to perform was “unavoidable” because a
    repository was not available.
    4
    See also N. States Power Co. v. Dep’t of Energy, No. 94-1457, 
    1995 WL 05
    -5162                                     5
    Soon after issuing the Northern States Power opinion just discussed, the D.C.
    Circuit issued an unpublished opinion clarifying its jurisdictional position in the case. In
    the opinion, the court sought to reiterate that the 1997 opinion merely “describes the
    nature of the DOE’s obligation, which was created by the NWPA and undertaken by the
    DOE under the Standard Contract. It does not place the question of contract remedies
    in this court, nor set up this court as a source of remedies outside the Standard
    Contract.” N. States Power Co. v. U.S. Dep’t of Energy, No. 97-1064, 
    1998 WL 276581
    ,
    at *2 (D.C. Cir. May 5, 1998). Shortly thereafter, several power companies with NWPA
    Standard Contracts, including PSEG, filed claims for breach of contract and damages
    for the DOE’s failure to meet the January 1, 1998 deadline in the Court of Federal
    Claims.
    Another company, Wisconsin Electric Power, however, continued to seek
    remedies at the D.C. Circuit. Wis. Elec. Power v. U.S. Dep’t of Energy, 
    211 F.3d 646
    ,
    647 (D.C. Cir. 2000). Wisconsin Electric sought a writ of mandamus that the NWPA
    required both monetary and non-monetary remedies for breach of the Standard
    Contract. The company claimed the D.C. Circuit had jurisdiction under two bases: 1) its
    authority to enforce its prior mandates, or 2) directly under section 119 of the NWPA.
    The court held that it did not have jurisdiction under its authority to enforce prior
    mandates because while “[t]hose mandates prohibit the DOE from interpreting the
    NWPA and its contracts with utilities in a manner that would relieve the Department of
    its unconditional obligation to begin disposing of SNF on January 31, 1998; [they]
    expressed no opinion about the relief the DOE would have to provide for breach of that
    479714, *1 (D.C. Cir. July 28, 1995) (dismissing the case for lack of final agency action).
    05-5162                                      6
    obligation.” 
    Id. at 648
    . The court also refused to assert jurisdiction under section 119 of
    the NWPA directly because while the statute “grants the court jurisdiction over cases
    seeking review of: (1) final action taken by the agency pursuant to the NWPA, and (2)
    the agency’s failure to take any action required by the NWPA[,] . . . a contract breach by
    the DOE does not violate a statutory duty. The Court of Federal Claims, not this court,
    is the proper forum for adjudicating contract disputes.” 
    Id.
     (citations omitted).
    III.
    Several breach of contract cases seeking damages for the DOE’s failure to begin
    SNF collection on January 1, 1998 have proceeded at the Court of Federal Claims and
    at this court with no discussion of a lack of subject matter jurisdiction over the claims.
    See Me. Yankee Atomic Power Co. v. United States, 
    225 F.3d 1336
     (Fed. Cir. 2000);
    N. States Power Co. v. United States, 
    224 F.3d 1361
     (Fed. Cir. 2000). Then, in Boston
    Edison Co. v. United States, the Court of Federal Claims considered the issue of
    subject matter jurisdiction over the SNF cases and held that it did possess such
    jurisdiction. 
    64 Fed. Cl. 167
     (2005), The court held that the plain text of section 119
    granted original and exclusive jurisdiction to the courts of appeals in six instances, none
    of which relate to Title III of the Act. 
    Id. at 179
    . Therefore, the court held that section
    119 did not affect jurisdiction over actions taken under Title III, and accordingly did not
    displace the Court of Federal Claims of its Tucker Act jurisdiction over an alleged
    breach of contract. 
    Id.
    In 2005, a judge of the Court of Federal Claims sua sponte issued an order
    requesting the government and four utility plaintiffs with SNF claims on her docket to
    show cause why the claims should not be dismissed or transferred for lack of subject
    05-5162                                       7
    matter jurisdiction. See Florida Power I, 64 Fed. Cl. at 44-63. After briefing by the
    parties, the court held that it lacked jurisdiction over the four breach of contract claims.
    Id. at 44.   The court first adopted the D.C. Circuit’s reasoning for its assertion of
    jurisdiction in General Electric, agreeing that DOE actions under Title III fall under the
    class of agency actions reviewable under section 119 of the NWPA. Id. at 40. It then
    rejected the D.C. Circuit’s reasoning in Wisconsin Electric Power which held that section
    119 did not vest the courts of appeals with jurisdiction over breach of contract cases
    under the NWPA. Id. at 63. The court noted that the D.C. Circuit could not confer
    jurisdiction on the Court of Federal Claims by disavowing jurisdiction contrary to statute.
    Id. Since the court’s analysis of case law, legislative history, and the structure of the
    statute led it to conclude that only the courts of appeals possessed jurisdiction over all
    claims regarding the statutorily imposed deadline, she dismissed the case for lack of
    jurisdiction. Id. at 40.
    In Florida Power I, the Court of Federal Claims further held that this court had
    identified “[t]wo circumstances in which statutory obligations in a contract [are] not
    enforceable by actions for breach of contract.” 64 Fed. Cl. at 39 (citing City of Burbank
    v. United States, 
    273 F.3d 1370
    , 1377 (Fed. Cir. 2001)). The circumstances were 1)
    that the contract provisions were statutorily mandated, and 2) the existence of a
    statutory provision that actions taken pursuant to the statute “shall” be filed in the courts
    of appeals. The court found that here, the contract term was statutorily required and not
    negotiated, the contract was the result of administrative hearings and rule-making, and
    all evidence regarding the rule-making fall inside the administrative record. Id. at 40.
    Therefore, the inclusion of the term was action taken pursuant to the statute and the first
    05-5162                                      8
    factor was present. Secondly, as in the statute at issue in City of Burbank, the court
    held that the NWPA required challenges to agency actions pursuant to the statute to be
    brought in the courts of appeals. It held that City of Burbank thus required that the
    courts of appeals had exclusive jurisdiction over all actions relating to that contract term
    and dismissed all four cases. Id. at 40.
    Subsequently, the four SNF cases dismissed in Florida Power I were reassigned
    to other judges at the Court of Federal Claims.           The plaintiffs filed motions for
    reconsideration in each of the four cases, arguing that the Court of Federal Claims did
    possess jurisdiction to hear their breach of contract claims. In three of the cases, the
    judges granted the motions for reconsideration and reversed the holding that the court
    lacked jurisdiction. In one, the court held that the language of section 119 and structure
    of the Act did not support courts of appeals jurisdiction over Title III cases through
    section 119. Duke Power v. United States, No. 98-485C, slip op. (Fed. Cl. Mar. 3,
    2005). In another, the Court of Federal Claims judge adopted the reasoning in Boston
    Edison and Duke Power. Neb. Pub. Power Dist. v. United States, No. 01-116C, slip op.
    at 2 (Fed. Cl. Mar. 30, 2005). And in the third case, the judge agreed with the reasoning
    in the three opinions above in holding that it had subject matter jurisdiction over the
    claims. Fla. Power & Light Co. v. United States, 
    66 Fed. Cl. 93
     (2005).
    In the fourth case dismissed by Florida Power I, the case before us, the Court of
    Federal Claims denied the plaintiff’s motion for reconsideration on the basis that no new
    evidence or law had been presented to justify reconsideration of the dismissal for lack of
    jurisdiction. PSEG Nuclear, L.L.C. v. United States, No. 01-551C, slip op. (Fed. Cl. Apr.
    05-5162                                      9
    22, 2005). PSEG timely appealed the Court of Federal Claims’ decision to this court.
    We have jurisdiction pursuant to 
    28 U.S.C. § 1295
    (a)(3).
    DISCUSSION
    The sole question before this court is whether the Court of Federal Claims
    possesses subject matter jurisdiction over PSEG’s claims arising out of breach of the
    Standard Contract. “In a given case, whether Tucker Act jurisdiction exists is a question
    of law that we review without deference to the decision of the trial court.” In re United
    States, No. 06-M806, --F.3d--, 
    2006 WL 2597835
    , at *5 (Fed. Cir. Sept. 11, 2006)
    (citing Core Concepts of Fla., Inc. v. United States, 
    327 F.3d 1331
    , 1334 (Fed. Cir.
    2003); Clark v. United States, 
    322 F.3d 1358
    , 1362 (Fed. Cir. 2003)). We hold that the
    NWPA did not strip the Court of Federal Claims of its Tucker Act jurisdiction over
    PSEG’s claims.
    Both parties agree on appeal that the Court of Federal Claims erred in finding no
    jurisdiction, but propose different rationales as to why that court has jurisdiction. The
    parties agree that section 119 of the NWPA encompasses judicial review of actions
    taken under section 302, thereby conferring the courts of appeals with jurisdiction to
    review those actions. The government urges that section 302 required only a single
    DOE action, namely the inclusion of the January 1, 1998 deadline in the Standard
    Contract. Because the term was included in the contract, the government argues, any
    further claim regarding the deadline does not arise under section 302 of the NWPA, but
    is a contract performance dispute that falls within the Court of Federal Claims’ Tucker
    Act jurisdiction. Meanwhile, while PSEG agrees that section 119 does not strip the
    Court of Federal Claims of jurisdiction over its breach of contract damages claim, it
    05-5162                                    10
    argues that the courts of appeals continue to have jurisdiction under section 119 over
    agency actions under section 302. The difference in the parties’ positions amounts to
    whether the courts of appeals continue to have jurisdiction to decide the propriety of
    agency actions under section 302 once the government includes the required language
    in the Standard Contract. Because this issue need not be resolved in this appeal, we
    merely agree with the parties that the Court of Federal Claims is vested with jurisdiction
    over PSEG’s breach of contract case and that the NWPA does not strip the court of its
    Tucker Act jurisdiction.
    The Tucker Act generally vests the Court of Federal Claims with jurisdiction to
    render judgment in government contract disputes. See 
    28 U.S.C. § 1491
    (a) (2000).
    This jurisdiction is supplanted only if, in a specific jurisdictional statute, Congress grants
    exclusive jurisdiction over a contract dispute to another court. City of Burbank, 
    273 F.3d at 1377
    . The NWPA did not strip the Court of Federal Claims of its jurisdiction over
    PSEG’s claims because it did not vest that jurisdiction in another court.
    The NWPA contains only one jurisdictional provision, section 119. Section 119
    confers the courts of appeals with jurisdiction over, inter alia, “any final decision or
    action of the Secretary, the President, or the Commission under this part; [or] (B)
    alleging the failure of the Secretary, the President, or the Commission to make any
    05-5162                                      11
    decision, or take any action, required under this part . . . .”5 
    42 U.S.C. § 10139
     (2000).
    By its terms, section 119 only refers to agency actions required under Title I, Subtitle A
    of the NWPA, entitled “Repositories for Disposal of High-Level Radioactive Waste and
    Spent Nuclear Fuel.” Therefore, section 119 of the NWPA confers jurisdiction over
    agency actions taken during development of a repository for SNF disposal.
    The NWPA requires that contracts entered into between the DOE and persons
    holding title to SNF “shall provide that” the disposal shall begin “not later than January
    31, 1998” in section 302. This section is in Title III of the Act, entitled “Other Provisions
    Relating to Radioactive Waste.” We agree with the parties, the Court of Federal Claims
    in this case, and the D.C. Circuit that agency actions mandated under Title III which
    5
    NWPA section 119(a)(1) states in its entirety:
    (a) Jurisdiction of United States courts of appeals
    (1) Except for review in the Supreme Court of the United States, the
    United States courts of appeals shall have original and exclusive
    jurisdiction over any civil action--
    (A) for review of any final decision or action of the Secretary, the
    President, or the Commission under this part;
    (B) alleging the failure of the Secretary, the President, or the Commission
    to make any decision, or take any action, required under this part;
    (C) challenging the constitutionality of any decision made, or action taken,
    under any provision of this part;
    (D) for review of any environmental impact statement prepared pursuant
    to the National Environmental Policy Act of 1969 (42 U. S.C. 4321 et seq.)
    with respect to any action under this part, or as required under section
    10155(c)(1) of this title, or alleging a failure to prepare such statement with
    respect to any such action;
    (E) for review of any environmental assessment prepared under section
    10132(b)(1) or 10155(c)(2) of this title; or
    (F) for review of any research and development activity under subchapter
    II of this chapter.
    
    42 U.S.C. § 10139
     (2000).
    05-5162                                      12
    relate to the creation of repositories for spent nuclear fuel fall within the class of actions
    subject to review by the courts of appeals under section 119.
    The remaining issue, therefore, is whether the breach of contract alleged by
    PSEG is also an agency action subject to review by the courts of appeals. PSEG’s
    claims are for breach of the Standard Contract’s provision requiring that the government
    begin SNF collection by the statutorily mandated date. It does not challenge an agency
    action taken under the agency’s statutory mandate.
    In this regard, it is instructive to consider our decision in City of Burbank, a
    breach of contract action against the Bonneville Power Administration (“BPA”). 
    273 F.3d 1370
    . There, we considered the scope of the judicial review provision contained in
    the Pacific Northwest Electric Power Planning and Conservation Act of 1980, 
    16 U.S.C. §§ 839
    -839h (“NPA”).       The NPA permitted the BPA to enter into contracts which
    included some statutorily mandated provisions and other provisions that were freely
    negotiated between the parties. The judicial review provision of the NPA vested the
    Ninth Circuit with exclusive jurisdiction over certain claims challenging the BPA’s
    actions.   This court held that “where disputed contract provisions are statutorily
    mandated or are arrived at via an administrative hearing under the [Administrative
    Procedures Act] in which the pertinent facts are reflected in an administrative record,
    the Ninth Circuit possesses exclusive jurisdiction” under the NPA’s judicial review
    provision. City of Burbank, 
    273 F.3d at 1380
    . However, we found that the provision did
    not strip the Court of Federal Claims of its Tucker Act jurisdiction because 1) the
    contract terms that the BPA had allegedly breached were not statutorily mandated, and
    2) no pertinent facts relevant to the breach or the alleged damages were contained in
    05-5162                                      13
    an administrative record. The factors applicable in City of Burbank also illuminate our
    analysis of PSEG’s claims.
    The contract term at issue, the January 1, 1998 date for beginning SNF
    collection, was clearly statutorily mandated. However, the key question is not whether
    the breached contract provision was statutorily mandated, but whether the claims at
    issue involve the agency’s authority under that statutory mandate. As both parties note,
    section 302 of the NWPA only required that the DOE include certain obligations in its
    contracts. Therefore, judicial review as to whether the DOE properly incorporated these
    obligations within its contracts may fall within the jurisdiction conferred to the courts of
    appeals in section 119. However, the performance of and any damages for failure to
    meet those obligations were not provided for by statute. The claims at issue here
    involve only issues of whether the DOE breached its contractual obligations, and if so,
    to what damages, if any, PSEG is entitled for the breach. Because these are not within
    the DOE’s statutory obligations under the NWPA, City of Burbank does not compel us to
    conclude that section 119 of the NWPA strips the Claims Court of its Tucker Act
    jurisdiction over PSEG’s claim merely because the claim involves a statutorily mandated
    provision.
    There is also no basis for concluding that PSEG’s claims can be resolved by
    resort to the administrative record. The Court of Federal Claims in Florida Power I
    seemed to reach this conclusion because the DOE published its proposed Standard
    Contract in the Federal Register and used an administrative rulemaking to develop the
    terms of the contract.    However, the DOE was not statutorily required to use the
    administrative rulemaking process or to even develop a Standard Contract. Rather, it
    05-5162                                     14
    did so because it preferred developing a contract with standard provisions that could be
    used with multiple contractees to the extent practicable. See 
    48 Fed. Reg. 5458
    , 5459
    (Feb. 4, 1983). DOE cannot unilaterally confer jurisdiction over contract claims to the
    courts of appeals by its choice to develop a contract through administrative rulemaking.
    In addition, any damages here will require extensive factual findings outside the
    administrative record. For example, the Standard Contract contains many provisions
    which were not statutorily mandated but will affect any measurement of damages.6 In
    addition, any necessary calculation of damages for different contracting utilities will
    require individual inquiries into when their SNF would have been collected and stored.
    Where damages for breach are not within the administrative record, jurisdiction properly
    lies with the Court of Federal Claims, which is equipped to hear evidence and determine
    such damages. See General Electric, 
    764 F.2d at 903
     (concluding that section 119 of
    the NWPA should confer courts of appeals with exclusive jurisdiction over “judicial
    review of administrative agency actions” considering “there are no factual findings to be
    made” and “the court of appeals is fully able to consider” an administrative record). Any
    issues related to the types of damages permitted under the contract, if any, and the
    extent of those damages can be resolved by solely resolving the DOE’s contractual
    obligations.
    6
    For example, the government cites the following sections in the Standard
    Contract, among others, that are relevant to these claims but not statutorily mandated:
    Article V regarding the procedure through which different nuclear utilities would receive
    their SNF acceptance allocations; Article VI.B regarding the order in which SNF would
    be accepted from nuclear utilities; Articles VI.A and Appendix E concerning the technical
    requirements that SNF being accepted must satisfy to be accepted as part of the initial
    acceptance queue. See 
    10 C.F.R. § 961.11
    .
    05-5162                                    15
    CONCLUSION
    As in City of Burbank, there is no statutory provision conferring jurisdiction over
    PSEG’s claims on another court. Further, these claims do not require the Court of
    Federal Claims to inquire solely into the administrative record, but to resolve factual
    issues regarding what damages are provided for by the parties in the contract.
    Therefore, we hold that the Court of Federal Claims has jurisdiction under the Tucker
    Act to hear PSEG’s breach of contract claims.
    COSTS
    No costs.
    REVERSED
    05-5162                                   16
    

Document Info

Docket Number: 2005-5162

Citation Numbers: 465 F.3d 1343

Judges: Lourie, Prost, Rader

Filed Date: 9/29/2006

Precedential Status: Precedential

Modified Date: 8/3/2023

Authorities (14)

Alabama Power Co. v. United States Department of Energy , 307 F.3d 1300 ( 2002 )

Natural Resources Defense Council, Inc. Snake River ... , 244 F.3d 742 ( 2001 )

Indiana Michigan Power Company v. Department of Energy and ... , 88 F.3d 1272 ( 1996 )

Wisconsin Electric Power Co. v. United States Department of ... , 211 F.3d 646 ( 2000 )

Commonwealth Edison Co. v. United States Department of ... , 877 F.2d 1042 ( 1989 )

Northern States Power Co. v. United States Department of ... , 128 F.3d 754 ( 1997 )

William A. Clark v. United States , 322 F.3d 1358 ( 2003 )

Core Concepts of Florida, Incorporated v. United States , 327 F.3d 1331 ( 2003 )

City of Burbank, California v. United States , 273 F.3d 1370 ( 2001 )

national-association-of-regulatory-utility-commissioners-v-us-department , 851 F.2d 1424 ( 1988 )

maine-yankee-atomic-power-company-connecticut-yankee-atomic-power-company , 225 F.3d 1336 ( 2000 )

Northern States Power Company v. United States , 224 F.3d 1361 ( 2000 )

wisconsin-electric-power-company-v-department-of-energy-and-united-states , 778 F.2d 1 ( 1985 )

general-electric-uranium-management-corporation-v-united-states-department , 764 F.2d 896 ( 1985 )

View All Authorities »