Tip Top Construction, Inc. v. Donahoe , 695 F.3d 1276 ( 2012 )


Menu:
  •   United States Court of Appeals
    for the Federal Circuit
    __________________________
    TIP TOP CONSTRUCTION, INC.,
    Appellant,
    v.
    PATRICK R. DONAHOE, POSTMASTER GENERAL,
    Appellee.
    __________________________
    2011-1509
    __________________________
    Appeal from the Postal Service Board of Contract Ap-
    peals in no. 6351, Administrative Judge Norman D.
    Menegat.
    ____________________________
    Decided: September 19, 2012
    ____________________________
    MICHAEL A. GORDON, Michael A. Gordon, PLLC, of
    Washington, DC, argued for the appellant.
    DAVID A. HARRINGTON, Senior Trial Counsel, Com-
    mercial Litigation Branch, Civil Division, United States
    Department of Justice, of Washington, DC, argued for
    appellee. With him on the brief were TONY WEST, Assis-
    tant Attorney General, JEANNE E. DAVIDSON, Director,
    and BRYANT G. SNEE, Deputy Director.
    __________________________
    TIP TOP CONSTRUCTION   v. USPS                              2
    Before RADER, Chief Judge, MAYER, and SCHALL, Circuit
    Judges.
    SCHALL, Circuit Judge.
    Tip Top Construction, Inc. (“Tip Top”) appeals the fi-
    nal decision of the Postal Service Board of Contract Ap-
    peals (“PSBCA” or “Board”) granting-in-part and denying-
    in-part Tip Top’s appeal under the Contract Disputes Act
    of 1978, as amended (“CDA”), 41 U.S.C. §§ 7101–7109.
    Tip Top Constr., Inc., PSBCA No. 6351, 11-1 B.C.A.
    ¶ 34,726, 
    2011 WL 1226107
    (Apr. 1, 2011) (“Board Deci-
    sion”). In its decision, the PSBCA ruled that Tip Top was
    entitled to recover $2,565 of the $12,400 it claimed as an
    equitable adjustment resulting from a change order under
    its indefinite quantity job order contract with the Postal
    Service for renovation and alteration of postal facilities in
    the U.S. Virgin Islands (the “contract”). 
    Id., slip op. at
    16.
    The Board ruled that Tip Top was not entitled to recover
    the balance of the amount claimed, $9,835, because it had
    failed to demonstrate that the costs at issue were incurred
    as a result of the change order. 
    Id., slip op. at
    17. Be-
    cause we conclude that this latter ruling by the Board was
    based upon an error of law and not supported by substan-
    tial evidence, we reverse and remand the case to the
    Board with the instruction that it grant Tip Top’s appeal
    in its entirety.
    BACKGROUND
    I.
    The Postal Service awarded the contract to Tip Top on
    July 26, 2007. 
    Id., slip op. at
    2, ¶ 1. The contract con-
    templated that from time to time the Postal Service would
    assign Tip Top individual projects by issuing work orders.
    
    Id. 3 TIP TOP
    CONSTRUCTION   v. USPS
    The contract specified a procedure for the issuance of
    a work order. 
    Id., slip op. at
    2–3, ¶ 3. First, the Postal
    Service and Tip Top would hold a Joint Scope Meeting, at
    which the Postal Service would explain to Tip Top the
    work it wished to have done and Tip Top could provide
    input. Next, the Postal Service would prepare a “Detailed
    Scope of Work,” on which Tip Top would base its proposal
    for the work. The proposal would be a lump-sum fixed-
    price proposal which would be contained in a “Price
    Proposal Package” which Tip Top would present to the
    Postal Service. If the Postal Service accepted Tip Top’s
    Price Proposal Package, it would issue a work order for
    the project. 
    Id., slip op. at
    3–4, ¶ 5. Contract Clause
    B.309 stated, “The contractor shall not recover any costs
    arising out of or related to the development of the work
    order including but not limited to the costs to review the
    Detailed Scope of Work or prepare a Price Proposal Pack-
    age . . . .” Contract Clause B.309, Work Order (Clause F-
    302) (March 2006), subsection I. The contract also con-
    tained a changes clause. See Contract Clause B.1006,
    Changes (Construction) (Clause B-37) (March 2006)
    Modified, subsections a,c.
    On May 26, 2009, the Postal Service issued Tip Top a
    work order to replace the air conditioning system at the
    Main Post Office in Christiansted, Virgin Islands, for the
    price of $229,736.92. Subsequently, on July 26, 2009, Tip
    Top sent the Postal Service’s construction manager, Victor
    Morales, its mechanical subcontractor’s submittals. The
    subcontractor planned to install Carrier Air Cooled Con-
    densers Model 09DK020 and a Carrier Air Cooled Indoor
    Unit Air Handler Model 05BV024. The proposed con-
    densers could be used with refrigerants R-12, R-22, R-500,
    and R-134a; the proposed air handler could be used with
    refrigerants R-22 and R-410a. The equipment submittals
    did not identify the refrigerant Tip Top planned to use.
    TIP TOP CONSTRUCTION   v. USPS                          4
    The Postal Service’s construction manager approved the
    submittals, and based on that approval, Tip Top’s me-
    chanical subcontractor ordered the listed equipment and
    associated fittings and piping.
    In September of 2009, Tip Top sent its submittal for
    the system refrigerant to Mr. Morales. In the submittal
    Tip Top stated that it planned to use R-22 refrigerant. On
    September 18, 2009, Mr. Morales returned the submittal
    to Tip Top marked “Reviewed, no exceptions taken.”
    Later that same day, however, Mr. Morales emailed Tip
    Top stating that Tip Top should ignore the previous
    approval and that R-410a refrigerant should be used in
    the system. A week later, Ivan Diaz, Tip Top’s consultant
    for the project, responded that the equipment previously
    ordered from Carrier Corp. (“Carrier”) was only available
    with R-22 refrigerant and that a change in equipment
    would involve additional cost and penalties estimated at
    $20,000. Mr. Diaz asked how Tip Top should proceed.
    Mr. Morales responded on September 28, 2009, asking Tip
    Top to submit a proposal to furnish and install air condi-
    tioning equipment that used R-410a refrigerant.
    During the period September 18 through October 13,
    2009, Mr. Diaz assisted Tip Top in negotiating the re-
    quired change with its mechanical subcontractor and
    Carrier. On October 13th, Tip Top submitted to the
    Postal Service specifications for air conditioning equip-
    ment that used R-410a refrigerant.
    The submittal was approved by the Postal Service on
    October 15, 2009. Shortly thereafter, on October 19, 2009,
    Tip Top, through Mr. Diaz, submitted a proposal in the
    amount of $28,838.43 for additional costs associated with
    changing the air conditioning system from one using R-22
    refrigerant to one using R-410a refrigerant.
    5                              TIP TOP CONSTRUCTION   v. USPS
    In early November 2009, Robert Manka, the Postal
    Service’s contracting officer, orally instructed Tip Top to
    proceed with the change in refrigerant. Subsequently, on
    January 12, 2010, Mr. Manka directed Tip Top in writing
    to proceed with the change in equipment from a system
    using R-22 refrigerant to one using R-410a refrigerant.
    Mr. Manka’s letter stated in pertinent part as follows:
    Tip Top Construction is hereby directed to proceed
    with the equipment refrigerant change from R22
    to R410a as detailed in the scope-of-work provided
    by Mr. Ivan Diaz in his letter dated October 19,
    2009 to . . . Project Manager Victor Morales for a
    price to be determined later but not to exceed
    $28,838.43.
    During the period between September of 2009 and
    June of 2010, Tip Top and the Postal Service discussed
    pricing of the changed work. Until March 8, 2010, Mr.
    Diaz conducted the negotiations on behalf of Tip Top.
    From that point on, Percy Hollins, Tip Top’s president,
    conducted the negotiations.
    The critical issue in the negotiations was whether Tip
    Top was entitled to recover the costs it incurred in prepar-
    ing the $28,838.43 estimate that Mr. Diaz submitted to
    Mr. Morales on October 18, 2009. On April 8, 2010, Mr.
    Manka sought guidance within the Postal Service on this
    issue, writing “If one of our JOC Contractor firms hires a
    firm to do their cost estimating for proposals and modifi-
    cations is the cost . . . considered an overhead charge or
    does it become a direct or indirect billable cost?” After
    receiving an answer to his inquiry, Mr. Manka sent an
    email to Mr. Hollins on April 16, 2010, quoting to Mr.
    Hollins the advice which he had been given: “The cost is
    an overhead charge and is not a billable cost. We recom-
    mend you review contract clause F-302 titled Work Order
    TIP TOP CONSTRUCTION   v. USPS                            6
    subparagraph I, in the associated contract which provides
    specific discussion on processing work orders.” Notably,
    the advice Mr. Manka received and which he passed on to
    Mr. Hollins only addressed Mr. Manka’s question insofar
    as it related to cost estimating for work orders. It did not
    address his question insofar as it related to cost estimat-
    ing for modifications under the contract’s changes clause.
    Beginning in April of 2010, counsel advised Mr. Hollins
    and assisted him in his continuing negotiations with the
    Postal Service.
    Negotiations between Tip Top and the Postal Service
    ended on June 18, 2010. That day, Mr. Hollins wrote Mr.
    Manka, stating, “Tip Top . . . has reviewed the Postal
    Services’ responses dated April 16, 2010, April 23, 2010,
    and June 8, 2010 to our emails with outside counsel and
    do not consider your position substantially justified.” Mr.
    Hollins wrote that Tip Top therefore was submitting “a
    claim and request for an equitable adjustment under the
    Contract Disputes Act.” Tip Top’s claim was in the total
    amount of $34,553.77. This was comprised of (i) Tip Top’s
    subcontractor’s price for the change (in the amount of
    $18,757.43, plus 10% profit, 4% insurance, and 4% gross
    receipts tax, for a subtotal of $22,133.77); (ii) $9,655 for
    “Preparation Costs & Extended Overhead; and (iii) $2,745
    for “Legal Fees.”
    On June 23, 2010, Mr. Manka issued a contracting of-
    ficer’s final decision in which he granted Tip Top an
    equitable adjustment in the amount of $22,133.77. He
    denied the balance of the claim, in the amount of $12,400.
    Mr. Manka based his partial denial of Tip Top’s claim on
    two considerations. First, he concluded that the proposal
    preparation costs were barred by Contract Clause B.309.
    As noted above, that clause provides that contractor’s
    costs in connection with work orders are not recoverable.
    Second, he concluded that it was unreasonable for Tip Top
    7                             TIP TOP CONSTRUCTION   v. USPS
    to spend $6,704.66 to prepare a change order valued at
    only $22,133.77.
    II.
    Tip Top appealed the contracting officer’s final deci-
    sion to the PSBCA, seeking to recover $12,400, the
    amount of its claim which Mr. Manka had denied. In its
    appeal, Tip Top elected to proceed under the Board’s
    accelerated procedure, which is available in the case of a
    claim of less than $50,000. See 39 C.F.R. § 955.13. Under
    that procedure, the Board decides an appeal on the record
    without an oral hearing. See 
    id. § 955.12. On
    April 1, 2011, the PSBCA issued its decision on
    Tip Top’s appeal. The Board ruled that Tip Top was
    entitled to recover $2,565 for costs incurred by Tip Top’s
    consultant, Mr. Diaz, through October 15, 2009. That was
    the day on which Mr. Morales, on behalf of the Postal
    Service, accepted Tip Top’s equipment proposal for an air
    conditioning system using R-410a refrigerant. Board
    Decision, slip op. at 7–8, ¶ 20, 16. The Postal Service had
    urged that the provision in Contract Clause B.309 barred
    recovery of the costs Tip Top sought. The Board rejected
    this argument. The Board stated that Clause B.309 did
    not apply to Tip Top’s claim because the clause only
    barred recovery of contractor costs incurred in reviewing a
    Detailed Scope of Work. This, the Board stated, was “a
    process exclusive to award of the original work order.”
    
    Id., slip op. at
    11. The Board continued that it was the
    changes clause of the contract that governed Tip Top’s
    claim for an equitable adjustment resulting from the
    Postal Service’s change order. The Board ruled that Tip
    Top had met the requirements for recovery under this
    clause as far as the $2,565 in costs relating to Mr. Diaz’s
    work prior to October 15, 2009 were concerned. The
    Board stated that the costs were compensable because
    TIP TOP CONSTRUCTION   v. USPS                            8
    they represented “an increase in [Tip Top’s] direct cost of
    performance due to the change.” 
    Id., slip op. at
    16.
    The PSBCA also ruled, however, that Tip Top was not
    entitled to recover the balance of its claim, in the amount
    of $9,835. This amount consisted of Mr. Diaz’s fees and
    overhead costs after October 15, 2009, until he left the job
    in March of 2010. It also consisted of legal fees in the
    amount of $2,745 for work done during the period April 21
    through June 8, 2010. In denying recovery of this part of
    Tip Top’s claim, the Board stated that the negotiations
    between Tip Top and the Postal Service after October 15,
    2009, relating to recovery of Tip Top’s estimating costs,
    which resulted in work by Mr. Diaz and outside counsel,
    “had nothing to do with performance of the changed work
    or genuine contract administration and were solely di-
    rected at trying to convince the contracting officer to
    accept [Tip Top’s] figure for the change and maximizing
    [Tip Top’s] monetary recovery.” 
    Id., slip op. at
    18. The
    Board concluded: “[O]nce the substitute equipment was
    approved, nothing remained to be negotiated except the
    price. There is no evidence that the parties’ negotiations
    addressed an extended delivery schedule or any other
    changes to contract performance requirements.” 
    Id., slip op. at
    18–19. The Board also found that Tip Top had not
    adequately documented Mr. Diaz’s charges, stating, “As
    the consultant likely was working on other project mat-
    ters, it was incumbent upon [Tip Top] to identify hours, if
    any, spent on the equipment change issue, and it has not
    done so.” 
    Id., slip op. at
    17.
    Tip Top has timely appealed the PSBCA’s decision.
    We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10).
    9                                TIP TOP CONSTRUCTION   v. USPS
    DISCUSSION
    I.
    We review appeals from the PSBCA under the stan-
    dard set forth in 41 U.S.C. § 7107(b):
    (1) [T]he decision of the agency board on a ques-
    tion of law is not final or conclusive; but
    (2) the decision of the agency board on a question
    of fact is final and conclusive and may not be set
    aside unless the decision is--
    (A) fraudulent, arbitrary, or capricious;
    (B) so grossly erroneous as to necessarily
    imply bad faith; or
    (C) not supported by substantial evidence.
    II.
    Tip Top first contends that the Board committed legal
    error by holding that its consultant and attorney costs
    associated with the negotiations relating to the price of
    the changed work were not recoverable. That holding, Tip
    Top argues, conflicts with this court’s holding in Bill
    Strong Enterprises, Inc. v. Shannon, 
    49 F.3d 1541
    (Fed.
    Cir. 1995). Appellant’s Br. 19–22. There, we held that,
    under the Federal Acquisition Regulation (“FAR”), con-
    sultant costs incurred by a contractor in connection with
    negotiations relating to the additional compensation to
    which the contractor was entitled by reason of govern-
    ment-caused delay of the job were allowable as contract
    administration costs, even though the negotiations even-
    tually failed. Bill 
    Strong, 49 F.3d at 1550
    . Thus, Tip Top
    urges, the consultant and legal fees it incurred in negoti-
    ating the price of the change order are recoverable as
    contract administration costs. The fact that the contract
    TIP TOP CONSTRUCTION   v. USPS                          10
    at issue is not governed by the FAR is irrelevant, Tip Top
    claims, because the contract is governed by a changes
    clause which is substantially similar to the standard
    changes clause in the FAR. 1 Appellant’s Reply Br. 5.
    Tip Top also argues that the Board’s finding of insuf-
    ficient evidence supporting certain consultant costs was
    not supported by substantial evidence. Specifically, Tip
    Top takes issue with the Board’s treatment of Mr. Diaz’s
    fees after October 15, 2009, when the substitute equip-
    ment was approved. Tip Top contends that it provided
    ample support for those costs in the form of Mr. Diaz’s
    timesheets and declarations from Mr. Diaz and Mr.
    Hollins. Appellant’s Br. 15–19. Noting that this evidence
    was unrebutted, Tip Top argues that the Board’s finding
    that Mr. Diaz was likely working on other matters was
    based purely on improper speculation. 
    Id. at 19. The
    government responds by first arguing that Tip
    Top’s attorney fees are not recoverable because costs
    incurred to prepare and document a claim for equitable
    adjustment are not recoverable. Appellee’s Br. 10. Ac-
    cording to the government, the record establishes that Tip
    Top’s attorney fees were incurred in the filing of a claim
    and thus they are not recoverable. 
    Id. at 11–12. Next,
    the government contends that Tip Top failed to
    provide sufficient evidence to support its claim for con-
    sultant costs incurred after October 15, 2009. According
    to the government, the invoices of Mr. Diaz do not provide
    sufficient detail to determine the type of work he per-
    formed. 
    Id. at 12–16. The
    government further argues the
    declarations provided by Mr. Hollins and Mr. Diaz are
    after-the-fact and of dubious value. 
    Id. Additionally, the 1
       Postal Service contracts are not governed by the
    FAR. In re Appeal of Kirkpatrick, PSBCA No. 3832, 96-2
    B.C.A. ¶ 28,599, 
    1996 WL 590751
    (Oct. 11, 1996).
    11                            TIP TOP CONSTRUCTION   v. USPS
    government states that Mr. Diaz’s costs are unreasonable
    because of the ratio between his costs and the cost of the
    change. 
    Id. at 16–17. III.
         The PSBCA held that costs incurred after approval of
    the substitute equipment were not recoverable. As seen,
    the basis for the Board’s holding was its determination
    that the efforts of Tip Top’s consultant after October 15,
    2009, and the work of its attorney through June 8, 2010,
    were “solely directed at trying to convince the contracting
    officer to accept Appellant’s figure for the change and
    maximizing Appellant’s monetary recovery,” and there-
    fore “had nothing to do with performance of the changed
    work or genuine contract administration.” Board Decision,
    slip. op. at 18. Thus, the Board reasoned that even
    though during the period between October 15, 2009,
    through June 8, 2010, the parties were negotiating the
    price of the changed work, the negotiations did not relate
    to contract administration because the Postal Service
    already had accepted the substitute equipment and
    because Tip Top was trying to persuade the contracting
    officer to agree to its price of $28,838.43.
    Under the changes clause of the contract, Tip Top was
    entitled to an equitable adjustment for any increase in its
    costs due to the change in the refrigerant. See Contract
    Clause B.1006, Changes (Construction) (Clause B-37)
    (March 2006) Modified, subsections a,c (“If any change
    under this clause causes an increase or decrease in the
    supplier’s cost of, or the time required for, the perform-
    ance of any part of the work under the contract, whether
    or not changed by any order, the contracting officer will
    make an equitable adjustment and modify the contract in
    writing.”). The question is whether costs arising from
    negotiations relating to the price of the changed work are
    TIP TOP CONSTRUCTION   v. USPS                           12
    recoverable in this case because they constituted part of
    the increased costs arising from the change directed by
    the Postal Service. The government does not appear to
    dispute that costs associated with general contract ad-
    ministration are recoverable. Indeed, the government
    acknowledged at oral argument that costs associated with
    price negotiations are potentially recoverable if the requi-
    site showing is made to the Board. Oral Arg. at 25:23,
    available at http://www.cafc.uscourts.gov/oral-argument-
    recordings/2011-1509/all (“[Costs associated with price
    negotiation are] potentially recoverable if the requisite
    showing is made to the Board.”). Rather, the government
    argues that Tip Top’s consultant costs and attorney fees
    are not recoverable because they were incurred in the
    process of claim preparation. In short, both the PSBCA
    and the government take the position that reasonable
    contract administration costs arising in the setting of a
    change order are recoverable. 2 We do not disagree. It
    seems to us proper that if a change order requires a
    contractor to incur contract administration costs, those
    costs are recoverable to the extent they are reasonable.
    Thus, the dispute depends on whether the costs are
    classified as general contract administration costs or
    claim preparation costs.
    Although it involved the recovery of costs under the
    FAR, our discussion in Bill Strong provides guidance on
    how to classify costs. 3 In Bill Strong, a contractor who
    2     As seen, the Board allowed recovery of Mr. Diaz’s
    costs incurred up to October 15, 2009, but denied recovery
    of his costs and the fees of Tip Top’s attorney after that
    date. The Board stated that these latter costs and fees
    “had nothing to do with performance of the changed work
    or genuine contract administration . . . .” Board Decision,
    slip. op. at 18.
    3    The government argues that our subsequent rul-
    ing in Reflectone, Inc. v. Dalton, 
    60 F.3d 1572
    (Fed. Cir.
    13                             TIP TOP CONSTRUCTION   v. USPS
    was renovating housing units on a military base asserted
    that it was incurring increased costs because the govern-
    ment was releasing the units for work out of 
    sequence. 49 F.3d at 1542
    . In response to the contractor’s assertion,
    the government requested cost data and information from
    the contractor. The contractor, in turn, hired a third-
    party consulting firm to handle the submission of data to
    the government. 
    Id. at 1543. Eventually
    the parties
    reached a settlement agreement. 
    Id. The agreement, however,
    specifically excluded the costs of the third-party
    consultant’s fees, and the parties agreed that the con-
    tracting officer would issue a final decision on the recov-
    erability of those fees. 
    Id. The contracting officer
    denied
    recovery of the fees, stating that the work performed by
    the third-party consultant was performed after the com-
    pletion of the contract work and was thus “not incurred in
    connection with the actual performance of the work.” 
    Id. at 1543–44. In
    deciding the case, we examined the distinction be-
    tween costs incurred in connection with the administra-
    tion of a contract and costs incurred in connection with
    the prosecution of a CDA claim, the former being recover-
    able, but the latter not. 
    Id. at 1549. In
    analyzing the two
    types of costs, we observed the following:
    In the practical environment of government
    contracts, the contractor and the CO usually enter
    a negotiation stage after the parties recognize a
    1995) (en banc) casts doubt upon the discussion of cost
    classification in Bill Strong. In Reflectone, we addressed
    when a claim arises for purposes of the CDA and over-
    ruled Bill Strong on this point. The discussion in Bill
    Strong regarding whether a particular cost should be
    classified as either a contract administration cost or a cost
    incidental to the prosecution of a claim, however, remains
    good law.
    TIP TOP CONSTRUCTION   v. USPS                              14
    problem regarding the contract. The contractor
    and the CO labor to settle the problem and avoid
    litigation. Although there is sometimes an air of
    adversity in the relationship between the CO and
    the contractor, their efforts to resolve their differ-
    ences amicably reflect a mutual desire to achieve
    a result acceptable to both. This negotiation proc-
    ess often involves requests for information by the
    CO or Government auditors or both, and, inevita-
    bly, this exchange of information involves costs for
    the contractor. These costs are contract admini-
    stration costs, which should be allowable since
    this negotiation process benefits the Government,
    regardless of whether a settlement is finally
    reached or whether litigation eventually occurs
    because the availability of the process increases
    the likelihood of settlement without litigation.
    Additionally, contractors would have a greater in-
    centive to negotiate rather than litigate if these
    costs of contract administration were recoverable.
    In classifying a particular cost as either a con-
    tract administration cost or a cost incidental to
    the prosecution of a claim, contracting officers, the
    Board, and courts should examine the objective
    reason why the contractor incurred the cost. If a
    contractor incurred the cost for the genuine pur-
    pose of materially furthering the negotiation proc-
    ess, such cost should normally be a contract
    administration cost allowable under FAR 31.205–
    33, even if negotiation eventually fails and a CDA
    claim is later submitted. On the other hand, if a
    contractor’s underlying purpose for incurring a
    cost is to promote the prosecution of a CDA claim
    against the Government, then such cost is unal-
    lowable under FAR 31.205–33.
    15                              TIP TOP CONSTRUCTION   v. USPS
    
    Id. at 1549–50 (citations
    omitted). We held that, under
    this framework, the contractor’s consultant costs were
    recoverable. 
    Id. at 1550–51. With
    the guidance provided
    in Bill Strong, we turn to the present case.
    After reviewing the record in light of the discussion in
    Bill Strong, we conclude that the PSBCA erred in holding
    that the consultant costs and attorney fees which are at
    issue were not “genuine contract administration costs”
    because they were “solely directed at . . . maximizing [Tip
    Top’s] monetary recovery.” Board Decision, slip op. at 17–
    18. On October 19, 2009, Tip Top submitted its proposal
    for the additional costs associated with the change.
    Thereafter, in response to the proposal, the contracting
    officer, in his January 12, 2010 letter, specifically referred
    to “a price to be determined later.” Subsequently, Tip Top
    and the Postal Service negotiated over the pricing of the
    changed work. Through March 8, 2010, Mr. Diaz handled
    the negotiations on behalf of Tip Top. After that, Mr.
    Hollins conducted the negotiations for Tip Top. On April
    16, 2010, Mr. Manka advised Tip Top by email of the
    guidance he had received from within the Postal Service
    as to the recovery of Tip Top’s consultant costs. 
    Id., slip op. at
    9, ¶ 27. Negotiations then continued with Tip Top
    assisted by counsel. 
    Id., slip op. at
    9, ¶ 28. Tip Top then
    submitted a claim under the CDA on June 18, 2010. 
    Id., slip op. at
    10, ¶ 29. The contracting officer’s final decision
    issued on June 23, 2010. 
    Id., slip op. at
    10, ¶ 31.
    In our view, both the costs of Mr. Diaz’s work between
    October 15, 2009, and March 8, 2010, and counsel’s fees
    through June 8, 2010, were incurred “for the genuine
    purpose of materially furthering the negotiation process.”
    Bill 
    Strong, 49 F.3d at 1550
    . The contracting officer, in
    his letter of January 15, 2010, expressly left open for
    further negotiation the issue of price. Thereafter, Tip Top
    and the contracting officer continued to engage in negotia-
    TIP TOP CONSTRUCTION   v. USPS                          16
    tions over the price of the changed work in order to avoid
    litigation. 4 Only on June 18, 2010, did negotiations
    finally end when Tip Top submitted its claim under the
    CDA. Simply because the negotiations related to the
    price of the change does not serve to remove the associ-
    ated costs from the realm of negotiation and genuine
    contract administration costs. Consideration of price is a
    legitimate part of the change order process. In holding
    otherwise, the Board, we believe, erred.
    IV.
    Having held that the Board committed legal error, we
    review whether substantial evidence supports the Board’s
    alternative holding that Tip Top failed to establish its
    costs for the time period after the substitute equipment
    was approved. Based upon the record before us, we find
    the Board’s holding unsupported.
    Tip Top provided timesheets for Mr. Diaz’s work for
    the relevant time period. To the extent more detail was
    needed, Tip Top submitted declarations from Mr. Diaz
    and Mr. Hollins describing the work performed by Mr.
    Diaz. Additionally, Tip Top submitted attorney billing
    records to support its claim for attorney fees. This evi-
    dence was unrebutted. In reviewing the evidence, the
    Board engaged in speculation that Mr. Diaz was working
    on other projects, speculation which is not supported by
    the record. In view of the evidence before us, we hold that
    Tip Top adequately supported its costs for the time period
    after the substitute equipment was approved and that
    4    We see nothing in the record suggesting that ei-
    ther Tip Top or the Postal Service negotiated in other
    than good faith. In addition, by only claiming attorney
    fees incurred through June 8, 2010, Tip Top limited its
    claim to fees incurred during the negotiation process.
    17                              TIP TOP CONSTRUCTION   v. USPS
    those costs were reasonable in light of the course of the
    price negotiations.
    CONCLUSION
    For the foregoing reasons, we reverse the ruling by
    the Board insofar as it denied-in-part Tip Top’s appeal.
    We remand the case to the Board with the instruction
    that it grant Tip Top’s appeal in its entirety. This means
    that Tip Top is entitled to recover $9,835 for consultant
    costs and attorney fees, plus interest to the extent allowed
    by the CDA.
    Appellant shall have its costs.
    REVERSED and REMANDED