Sanchez v. Alston Construction Co. CA2/2 ( 2022 )


Menu:
  • Filed 6/24/22 Sanchez v. Alston Construction Co. CA2/2
    NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not
    certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been
    certified for publication or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    SECOND APPELLATE DISTRICT
    DIVISION TWO
    MARIA DEL CARMEN REYES                                         B309232
    SANCHEZ, Individually and as
    Personal Representative, etc.,                                 (Los Angeles County
    Super. Ct. No.
    Plaintiff and Appellant,
    BC670915)
    v.
    ALSTON CONSTRUCTION
    COMPANY, INC.,
    Defendant and Respondent.
    APPEAL from a judgment of the Superior Court of Los Angeles
    County, Olivia Rosales, Judge. Affirmed.
    Greenberg & Ruby, David H. Greenberg, Emily A. Ruby; Gusdorff
    Law, Janet Gusdorff; The Farias Firm and James G. Farias for Plaintiff
    and Appellant.
    Friedenthal, Heffernan & Brown, Daniel Friedenthal, Jay D.
    Brown, James Lee; Ropers, Majeski, Terry Anastassiou and Maureen
    C. O’Hara for Defendant and Respondent.
    While working on a roof at a construction site, Leonel Carrasco
    Torres fell through a skylight and was severely injured. His employer,
    KML Services, Inc. (KML) was a subcontractor on the job. Torres and
    his wife Maria Del Carmen Reyes Sanchez filed a personal injury suit.
    The named defendants included the general contractor, Alston
    Construction Company, Inc. (Alston). The trial court granted Alston
    summary judgment based on the Privette doctrine (Privette v. Superior
    Court (1993) 
    5 Cal.4th 689
    ), which holds a hirer of an independent
    contractor is typically not liable for contractor’s negligence. (Id. at pp.
    691–692.) Plaintiffs timely appealed. We affirm.
    FACTS AND PROCEDURAL BACKGROUND
    Alston is a construction general contractor. Alston acts solely in
    a managerial capacity and hires independent contractors to perform
    the actual construction work.
    In 2015, Alston contracted with PanCal 11525 Shoemaker LLC
    (PanCal) to alter an existing building and construct a parking lot for
    FedEx Ground Package System, Inc. (FedEx Project). Alston
    contracted with AMPCO Contracting, Inc. (AMPCO) to demolish
    existing structures and pavement. In turn, AMPCO hired KML to
    remove asbestos from the structures before the demolition began.
    The Alston/AMPCO agreement contained a set of rules related to
    worksite safety, among them Alston’s “Site Specific Safety Plan.” The
    plan expressly delegated worksite safety, including “safety training and
    equipment” and “[f]all prevention and/or protection” to AMPCO and its
    lower-tiered subcontractors. The plan also required subcontractors to
    “perform and document pre-task planning to identify any hazards
    related to their work.” AMPCO understood and agreed that it was
    responsible for ensuring that its lower-tiered contractors comply with
    the plan. The AMPCO/KML agreement referenced and expressly
    incorporated the Alston/AMPCO agreement, including worksite safety
    obligations for lower-tiered contractors. Alston could inspect all
    subcontractors’ work and had the right to shut down the FedEx Project
    and/or have offending subcontractor employees removed if they were
    not complying with safety regulations.
    2
    Alston’s project superintendent, Chuck Gonzalez, was responsible
    for general management of the worksite, including worksite safety.
    However, Gonzalez “was not responsible for supervising or monitoring
    the activities of the independent contractors or their employees.”
    Torres was one of the KML workers assisting in the removal of
    asbestos from an existing structure. On the morning of Torres’s
    accident, project superintendent Gonzalez conducted a tailgate safety
    meeting before work began. Among the attendees were Torres and
    KML’s foreman. Gonzalez discussed job safety, including fall
    protection. He also climbed a ladder to the roof line and “glanced” at
    the roof where the asbestos remediation was to occur. Gonzalez then
    asked the KML foreman to go up on the roof to locate tie-off points to
    anchor workers’ safety harnesses. The foreman climbed the ladder and,
    after a minute, stated, “ ‘Everything is good to go.’ ” The safety meeting
    concluded, and KML employees began their work. Gonzalez went to
    another part of the worksite.
    While sweeping debris off the roof, Torres stepped through a
    fiberglass skylight. The skylight broke and Torres fell to the cement
    slab below. He sustained catastrophic injuries. Torres received
    medical care and benefits from KML’s workers’ compensation
    insurance.
    Torres and Sanchez (plaintiffs) filed a complaint against Alston
    and other defendants for negligence and loss of consortium.1
    Specifically, plaintiffs alleged Torres’s fall resulted from defendants’
    failure “to properly maintain and [sic] the premises.”
    1 Torres died during the pendency of this appeal and his wife
    Maria Del Carmen Reyes Sanchez was granted leave to substitute in as
    plaintiff on the negligence claim. (Code Civ. Proc., § 377.30; Cal. Rules
    of Court, rule 8.36(a).) For simplicity, for trial court proceedings we
    refer to both parties collectively as “plaintiffs” unless we need to
    designate Torres alone by name. Where appropriate in the
    “DISCUSSION” section, rather than use “plaintiffs” we refer solely to
    “Sanchez” as appearing both in an individual and a representative
    capacity in this appeal.
    3
    Alston moved for summary judgment. Alston argued that, as a
    general contractor, Alston was not liable for worksite injuries suffered
    by an independent contractor’s employee. Alston reasoned it neither
    retained control over worksite safety conditions nor negligently
    exercised any alleged control that affirmatively contributed to Torres’s
    injury.
    In opposition, plaintiffs mainly argued that triable issues of fact
    existed whether Alston was responsible for worksite safety and for
    warning contract workers about the skylight, a concealed hazard.
    Plaintiffs added that certain aspects of the Alston/AMPCO and
    AMPCO/KML contracts meant that Alston solely retained
    responsibility for the FedEx Project. As a result, plaintiffs contended,
    worksite safety duties were never successfully delegated to the lower-
    tiered contractors. Plaintiffs also alleged Alston was liable for
    breaching California Occupational Health and Safety (Cal-OSHA)
    regulations.
    The trial court granted summary judgment, finding that Torres’s
    negligence claim against Alston was barred by the Privette doctrine.
    The ruling also disposed of his wife’s loss of consortium claim.
    Following entry of judgment, plaintiffs appealed.
    DISCUSSION
    On appeal, Sanchez contends there are triable issues of fact:
    (1) whether Alston presumptively delegated its worksite safety duties
    to the lower-tiered contractors or, if Alston did, (2) whether the
    “retained control” and “concealed hazard” exceptions to the Privette
    doctrine applied, making Alston liable for Torres’s injury. Sanchez also
    maintains the Privette doctrine should be abolished as unconstitutional.
    I.     The Privette Doctrine
    “Workers’ compensation ‘ “is the exclusive remedy against an
    employer for injury or death of an employee.” [Citation.]’ (Privette,
    supra, 5 Cal.4th at p. 697.) In Privette, the Supreme Court held that
    ‘an independent contractor’s employee should not be allowed to recover
    damages from the contractor’s hirer, who “is indirectly paying for the
    cost of [workers’ compensation] coverage, which the [hired] contractor
    4
    presumably has calculated into the contract price.” ’ ” (Alvarez v.
    Seaside Transportation Services LLC (2017) 
    13 Cal.App.5th 635
    , 640.)
    Thus, the so-called Privette doctrine bars an employee of an
    independent contractor from recovering damages from the hirer of the
    contractor for a worksite injury. (SeaBright Ins. Co. v. US Airways,
    Inc. (2011) 
    52 Cal.4th 590
    , 594.) In other words, a subcontractor’s
    employee injured on the job is generally entitled to no greater damages
    than a similarly injured employee of a general contractor. Both
    employees are limited to receiving workers’ compensation benefits.
    Apart from the workers’ compensation-based rationale
    undergirding the Privette doctrine, the Supreme Court has recently
    placed greater emphasis on the rationale that a “presumptive
    delegation of tort duties occurs when the hirer turns over control of the
    worksite to the contractor so that the contractor can perform the
    contracted work.” (Sandoval v. Qualcomm Incorporated (2021) 
    12 Cal.5th 256
    , 271 (Sandoval).) “Over time, we’ve recast our primary
    rationale for the Privette doctrine in terms of delegation rather than
    workers’ compensation.” (Id. at p. 270; Gonzalez v. Mathis (2021) 
    12 Cal.5th 29
    , 41 [“Our more recent cases emphasize delegation as the key
    principle underlying this rule”].) As a result, “[t]here is a strong
    presumption under California law that a hirer of an independent
    contractor delegates to the contractor all responsibility for workplace
    safety.” (Gonzalez, at p. 37.)
    II.    Exceptions to the Privette doctrine
    Nonetheless, there are exceptions to the Privette doctrine. They
    apply in situations where the presumption of delegation is overcome:
    Under the “retained control” exception, “a hirer owes a duty to a
    contract worker if the hirer retains control over any part of the work
    and actually exercises that control so as to affirmatively contribute to
    the worker’s injury.” (Sandoval, supra, 12 Cal.5th at p. 271, citing
    Hooker v. Department of Transportation (2002) 
    27 Cal.4th 198
    , 202
    (Hooker).) Under the “concealed hazard” exception, “a landowner-hirer
    owes a duty to a contract worker if the hirer fails to disclose to the
    5
    contractor a concealed premises hazard.” (Sandoval, at p. 271, citing
    Kinsman v. Unocal Corp. (2005) 
    37 Cal.4th 659
    , 664 (Kinsman).)
    III. The Privette Presumption and Summary Judgment
    “ ‘A defendant moving for summary judgment . . . may
    demonstrate that the plaintiff’s cause of action has no merit by showing
    that (1) one or more elements of the cause of action cannot be
    established, or (2) there is a complete defense to that cause of action.’
    {Citation.] [¶] Generally, ‘the party moving for summary judgment
    bears an initial burden of production to make a prima facie showing of
    the nonexistence of any triable issue of material fact.’ ” (AMN
    Healthcare Inc. v. Aya Healthcare Services, Inc. (2018) 
    28 Cal.App.5th 923
    , 933–934.) We review the trial court’s grant of summary judgment
    de novo. (Id. at p. 934.)
    In negligence cases, where an independent contractor’s employee
    suffers a worksite injury, the hirer who invokes the Privette doctrine
    and moves for summary judgment must present a factual showing for
    the doctrine to apply. That factual showing is the hirer employed the
    independent contractor for work at the jobsite and the employee was
    injured while working at the site. (Alvarez v. Seaside Transportation
    Services LLC, supra, 13 Cal.App.5th at p. 644.) Once this factual
    showing is made, the presumption of delegation is triggered and the
    burden shifts to the plaintiff/employee. If the plaintiff does not raise
    triable issues of fact, the defendant/hirer is entitled to summary
    judgment. (Alvarez, at p. 646.)
    The plaintiff can rebut the presumption of delegation by
    presenting evidence making a prima facie showing of a triable issue of
    fact in support of one or more exceptions. (Aguilar v. Atlantic Richfield
    Co. (2001) 
    25 Cal.4th 826
    , 850–851.)
    IV. Alston Made the Requisite Factual Showing for the
    Privette Presumption To Apply
    Alston established it was entitled to the presumption of
    delegation. Alston presented evidence it hired AMPCO, who then hired
    Torres’s employer KML for the FedEx Project. Torres was injured
    while working on the project. KML’s workers’ compensation insurance
    6
    covered Torres’s injuries. “This evidence was sufficient to establish
    that the Privette presumption applied and, therefore, shifted the
    burden to plaintiff to raise a triable issue of fact.” (Alvarez v. Seaside
    Transportation Services LLC, supra, 13 Cal.App.5th at p. 644.)
    Sanchez, however, argues that deficiencies in the Alston/AMPCO
    and AMPCO/KML contracts rendered them unenforceable. As a
    consequence, according to Sanchez, Alston failed to delegate its
    worksite safety duties to the lower-tiered contractors; the presumption
    of delegation did not apply.
    Sanchez first contends the Alston/AMPCO contract may not have
    been timely executed. It is undisputed that both parties signed the
    agreement, but the electronic signature line reveals AMPCO signed it
    on the date of Torres’s accident. Sanchez maintains this means a
    triable issue exists whether the contract was signed after Torres fell,
    making the agreement unenforceable. However, Sanchez cannot
    speculate on potential untimeliness to create a triable issue of fact.
    (Doe v. Salesian Society (2008) 
    159 Cal.App.4th 474
    , 481 [opposing
    party cannot controvert moving party’s evidence by mere speculation or
    possibility]; Lyons v. Security Pacific Nat. Bank (1995) 
    40 Cal.App.4th 1001
    , 1014 [same].) In any event, Sanchez failed to show the
    Alston/AMPCO agreement was not binding unless signed by both
    parties. (Kaneko v. Okuda (1961) 
    195 Cal.App.2d 217
    , 225 [absent “a
    showing that a contract is not to be deemed complete unless signed by
    all parties, the parties signing may be bound though others have not
    signed”].) Moreover, there is no evidence the parties treated the
    Alston/AMPCO contract as not being fully consummated between them.
    Sanchez also contends the AMPCO/KML contract was
    unenforceable because it appeared contingent upon a condition
    precedent, a contract with another entity, that never occurred. A
    condition precedent may be impliedly waived by conduct. (See Sosin v.
    Richardson (1962) 
    210 Cal.App.2d 258
    , 264.) Here, the record leaves
    no question that when Torres was injured, KML was working as
    AMPCO’s subcontractor on the FedEx Project in accordance with their
    agreement. Further, AMPCO acknowledged it had complete
    7
    responsibility to ensure KML and other subcontractors complied with
    Alston’s safety rules while working on the project. Because the
    evidence established the presumptive delegation applied, the burden
    shifted to plaintiffs to raise a triable issue of fact.
    V.     Summary Judgment was Proper
    Sanchez argues that even if Alston met its initial burden as the
    moving party, they succeeded in raising triable issues of fact in support
    of the “retained control” and “concealed hazard” exceptions. Sanchez
    also argues Alston breached its nondelegable duties under Cal-OSHA.
    A.     Plaintiffs Failed to Raise a Triable Issue of
    Fact to Support the Retained Control Exception
    Under the retained control exception, a hirer is subject to liability
    if the hirer retained control over the independent contractor’s work and
    exercised that retained control in a way that affirmatively contributed
    to the contract worker’s injury. (Sandoval, supra, 12 Cal.5th at p. 271.)
    “A hirer ‘retains control’ where it retains a sufficient degree of
    authority over the manner of performance of the work entrusted to the
    contractor.” (Sandoval, supra, 12 Cal.5th at p. 275.) A “hirer ‘actually
    exercise[s]’ its retained control over the contracted work when it
    involves itself in the contracted work ‘such that the contractor is not
    entirely free to do the work in the contractor’s own manner.’ ” (Id. at
    p. 276.)
    Sanchez seeks to recover under the retained control exception
    because Alston “retained and exercised control over worksite safety and
    the means and manner in which KML’s employees perform their work.”
    It appears Sanchez is relying on the PanCal/Alston contract and the
    incorporated Site Specific Plan, which provides that Alston would be
    “fully and solely responsible” for worksite safety. Alston’s position as a
    worksite manager, however, does not support an inference that Alston
    “in fact involve[d] itself [in the contracted work], such as through
    direction, participation, or induced reliance.” (Sandoval, supra, 12
    Cal.5th at p. 276; Tverberg v. Fillner Construction, Inc. (2012) 
    202 Cal.App.4th 1439
    , 1446 [“a hirer is not liable to a contractor or a
    contractor’s employee merely because it retains control over safety
    8
    conditions”].) Nothing in the record indicates that Alston actually
    exercised any form of direct control over KML’s work or that Alston
    restricted Torres and other KML workers from performing their work
    in their own manner. With respect to the roof in particular, Sanchez
    offers no evidence that Alston had any discussions or issued any
    instructions to KML regarding skylights or roof safety, undertook
    responsibility to inspect the roof before KML began work, interfered
    with or prohibited any inspections of the roof before work began,
    advised KML employees on where or how to tie off their harnesses, or
    otherwise how to perform their work on the roof. (See, e.g., Madden v.
    Summit View, Inc. (2008) 
    165 Cal.App.4th 1267
    , 1276-1277.)
    Sanchez also contends Alston exercised retained control over
    KML’s work based on the deposition testimony of Chuck Gonzalez,
    Alston’s project superintendent. According to Sanchez, Gonzalez
    “voluntarily undertook responsibility for inspecting the worksite and
    supervising KML’s employees, but failed to identify any of the unsafe
    conditions or work practices.” This misstates the evidence. Gonzalez’s
    uncontroverted testimony was that he did not “inspect” or handle the
    KML equipment to ensure it was safe for KML workers. That was
    KML’s responsibility. As for the worksite, Gonzalez testified he asked
    the KML foreman to go up on the roof to look for tie-off points for the
    workers’ safety harnesses. But Gonzalez did not direct the foreman
    concerning the location or installation of the tie-off points, which were
    also part of KML’s responsibility. Gonzalez further testified it was
    KML’s responsibility to identify all safety hazards on the roof,
    including skylights.
    Sanchez further asserts Alston affirmatively contributed to
    Torres’s injury. She points to what she perceives as Alston’s failure to
    undertake certain safety precautions, contrary to the Site Specific
    Safety Plan. Among them were Alston’s lack of a pre-project hazard
    assessment of the roof and implementation of fall protection rules.
    Sanchez also makes much of Alton’s rush to have the work begin before
    Gonzalez could distribute Alston’s safety materials to KML employees.
    9
    To be sure, a hirer’s acts or omissions apart from the independent
    contractors can be found to affirmatively contribute to a contract
    worker’s injury. (Sandoval, supra, 12 Cal.5th at p. 277.) But Sanchez
    does not explain how these omissions by Alston affirmatively
    contributed to the worksite injury. To the extent Sanchez is asking us
    to infer that if Alston had not omitted these safety precautions, the
    skylight would have been discovered and Torres’s injuries would not
    have occurred, we decline to do so. It is true that courts are to consider
    all evidence and inferences reasonably drawn from that evidence in
    ruling on a summary judgment motion. (Aguilar v. Atlantic Richfield
    Co., supra, 25 Cal.4th at p. 843.) At the same time, those inferences
    must be reasonably deducible from the evidence, rather than from mere
    speculation, as is the case here. (Waschek v. Department of Motor
    Vehicles (1997) 
    59 Cal.App.4th 640
    , 647.)
    We conclude the evidence in the record cited by Sanchez and
    reasonable inferences from that evidence do not create a triable issue of
    fact regarding Alston’s exercise of retained delegation and affirmative
    contribution, in part because some of the evidence cited by Sanchez
    does not say what Sanchez claims it says and because some of her
    arguments rest on speculation.
    B.      Plaintiffs Failed to Raise a Triable Issue of
    Fact to Support the Concealed Hazard Exception
    Under Kinsman’s “concealed hazard” exception, the hirer is liable
    only if (1) it knew, or should have known, of a latent or concealed
    preexisting hazardous condition on its property; (2) the independent
    contractor did not know and could not reasonably have discovered the
    hazardous condition; and (3) the hirer failed to warn the contractor
    about the condition. (Kinsman, supra, 37 Cal.4th at p. 675.)
    The trial court found the key issue was whether Alston knew or
    should have known of the hazardous condition. Even the most cursory
    review of the evidence in this case shows plaintiffs cannot satisfy this
    element. Nothing in the record suggests Alston knew or should have
    known about the skylights. In his deposition, FedEx Project manager
    Richard Babcock testified the skylights were never discussed during
    10
    pre-project worksite meetings. He also stated the skylights were not
    visible from above or below, and because the structure was 50 years
    old, there were no drawings depicting the skylights. Project
    superintendent Gonzalez testified he never saw the FedEx Project
    before the day of the accident, and he had no prior knowledge of the
    skylights on the roof. Further, Gonzalez did go on top of the roof, but
    quickly looked at it from the top of the ladder. He never saw the
    skylights. And, as we have discussed above in connection with the
    Hooker exception, Alston never undertook the responsibility to inspect
    the roof for any hazards that could endanger KML employees. That
    responsibility was exclusively KML’s.
    Sanchez counters the project site plans may have shown the
    skylights on the roof, and had Gonzalez been afforded adequate time
    for a pre-job inspection, he may have found the skylights. Sanchez
    further claims the KML foreman’s notes from the pre-accident meeting
    that day expressly warned workers not to step on the skylights.
    However, because the plaintiffs’ expert determined the admonition was
    not written by the foreman, Sanchez argues a triable issue of fact exists
    whether Alston added the admonition later as a “coverup.” Once again,
    Sanchez improperly relies on speculation, but also argument and
    theory in an attempt to defeat summary judgment. (Wiz Technology,
    Inc. v. Coopers & Lybrand (2003) 
    106 Cal.App.4th 1
    , 10–11.)
    We conclude Sanchez has failed to raise a triable issue of fact
    whether Alston knew or should have known of the skylights, a
    concealed hazardous condition.
    VI. Cal-OSHA Does Not Impose Nondelegable Duties
    Upon Alston
    Sanchez additionally contends the Cal-OSHA regulations set
    forth in California Code of Regulations, title 8, section 1511,
    subdivision (b) (pre-work worksite hazard survey), section 1644 (metal
    scaffold), and section 3212, subdivision (a)(1) (floor and roof opening
    guards) impose a nondelegable duty on Alston.
    Generally, a plaintiff can rely on statutory or regulatory law to
    show that a defendant owes the plaintiff a duty of care. (Elsner v.
    11
    Uveges (2004) 
    34 Cal.4th 915
    , 927, fn. 8.) However, our Supreme Court
    has held that Cal-OSHA regulations do not impose nondelegable duties
    upon a hirer of an independent contractor. (SeaBright Ins. Co. v. US
    Airways Inc., 
    supra,
     52 Cal.4th at p. 594.) In SeaBright, an employee
    of an independent contractor hired by an airline to repair a luggage
    conveyor was injured when his arm was caught in the conveyor’s
    moving parts. (Id. at p. 594.) Here, Sanchez attempts to distinguish
    SeaBright by arguing the Supreme Court intended that the hirer
    presumptively delegates its tort duties only with respect to the job that
    the contract worker was specifically hired to do. According to Sanchez,
    unlike the injured worker in SeaBright, Torres was not hired “to
    perform work on the skylights, or discuss the skylights with anyone
    prior to KML beginning work.” We are not persuaded. The Supreme
    Court expressly stated the delegation “includes any tort law duty the
    hirer owes to the contractor’s employees to comply with applicable
    statutory or regulatory safety requirements.” (SeaBright, at p. 594.)
    Thus, there are no triable issues of fact whether nondelegable duties
    exist.
    VII. Constitutionality of the Privette doctrine
    Notwithstanding the two recent California Supreme Court
    opinions reaffirming the Privette doctrine, Sanchez contends it is
    unconstitutional. We are bound by our high court’s decisions on this
    issue and conclude the doctrine is not unconstitutional. (Auto Equity
    Sales, Inc. v. Superior Court (1962) 
    57 Cal.2d 450
    , 455.)
    12
    DISPOSITION
    The judgment is affirmed. Alston Construction Company, Inc. is
    to recover its costs on appeal.
    NOT TO BE PUBLISHED.
    LUI, P. J.
    We concur:
    ASHMANN-GERST, J.
    HOFFSTADT, J.
    13