Ventura29 v. City of San Buenaventura CA2/6 ( 2023 )


Menu:
  • Filed 1/4/23 Ventura29 v. City of San Buenaventura CA2/6
    NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions
    not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion
    has not been certified for publication or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    SECOND APPELLATE DISTRICT
    DIVISION SIX
    VENTURA29, LLC,                                                2d Civ. No. B313060
    (Super. Ct. No. 56-2020-
    Plaintiff and Appellant,                                 00539754-CU-EI-VTA)
    (Ventura County)
    v.
    CITY OF SAN
    BUENAVENTURA,
    Defendant and Respondent.
    Ventura29, LLC, appeals from the judgment of dismissal
    entered after the trial court had sustained, without leave to
    amend, a demurrer to its second amended complaint (complaint).
    The demurrer was filed by respondent City of San Buenaventura
    (City).
    In 2015 appellant purchased property (the Property) on
    East Thompson Boulevard in City. The complaint alleged that
    appellant “is in the process of developing a multi-unit townhome
    project” on the Property.
    The complaint consists of four causes of action. The first
    cause of action is for inverse condemnation. Appellant claims
    City’s modification of an approved grading plan for the Property
    “resulted in an unconstitutional taking for which [it] is entitled to
    just compensation.” We conclude appellant forfeited its
    objections to the modification because it failed to exhaust its
    administrative remedies.
    Appellant contends the complaint states causes of action for
    private nuisance, trespass, and negligence based on City’s
    dumping of uncertified fill on the Property in 1977. We conclude
    these causes of action are barred by the statute of limitations.
    Accordingly, we affirm the judgment of dismissal.
    The Complaint
    The complaint alleged: “In 2006 the prior owner of the
    Property, V2V Ventures, Inc. (‘V2V’) received Tentative Tract
    Map approval from the City to construct 29 townhouses on the
    Property.” “V2V . . . retained a geotechnical engineering firm,
    Earth Systems Pacific (‘Earth Systems’), to conduct soils test on
    the Property . . . .” Appellant took title to the Property in 2015.
    It “is currently in the process of developing a 29-unit townhouse
    project . . . pursuant to the same City-approved Tentative Tract
    Map that V2V obtained in 2006.”
    In 2018 Earth Systems prepared a Geotechnical
    Engineering Report for appellant. The report is attached as
    Exhibit A to the complaint. The report noted that extensive
    uncertified fill was encountered in test trenches excavated on the
    Property.
    City acknowledges that it approved a grading plan
    submitted by appellant. The complaint alleged, “[T]he Grading
    Plan states: ‘recommendations and conclusions of [Earth
    2
    Systems’ 2018 report], shall be thoroughly complied with. . . .
    [T]he mentioned report . . . [is] hereby . . . made a part of this
    grading plan.’”
    As a condition of approving appellant’s project, City
    required it “to construct a pedestrian-only walking path across
    [an adjoining] City-owned property [(“the City Parcel” or “City’s
    Parcel”)] in order to connect [appellant’s] property with a nearby
    City park.” City acquired its parcel in 1967.
    The complaint continued: “After commencing excavation for
    the project, . . . [appellant] soon discovered . . . that significant
    amounts of uncertified fill were buried to considerable depths
    under the entirety of the City [Parcel] where the walking path
    was to be constructed, as well as under a portion of [appellant’s]
    property.” “The buried materials consisted almost exclusively of
    concrete curb and gutter, concrete street sections, footings,
    asphalt and rebar, all of which are consistent with waste from
    public works projects.”
    Earth Systems proposed “an engineering solution . . . to use
    geofabric to stabilize the areas with uncertified fill located
    outside of the Project building pads as well as on the City Parcel
    where [appellant] was required to install a walking path.” The
    City inspector, Burt Yanez, orally informed appellant that Brad
    Starr, the City Engineer, had rejected appellant’s proposal.
    Yanez said “that [appellant] must excavate the Property and the
    entire City Parcel to native bottoms, otherwise the City would
    revoke all Project grading approvals.”1 “This requirement far
    1 It is doubtful that Yanez said appellant must remove the
    uncertified fill over the entire City Parcel. The complaint later
    stated, “Plaintiff was not aware . . . that it would eventually be
    required to move all . . . fill buried under the . . . City Parcel
    3
    exceeded the extent of grading contemplated or required in the
    [approved] Grading Plan.”
    “At no time during or subsequent to this conversation did
    any City representative inform [appellant] that such a
    determination to deny [its] grading proposal might have been
    appealable to the City’s Public Works Director pursuant to
    Municipal Code Section 12.210.030.[2] [Appellant] had no
    idea . . . that such a remedy was potentially available. In any
    event, it would have been infeasible to stop the Project in order to
    pursue an appeal due to extensive overhead costs, carrying cost
    and a balloon payment on a construction loan.”
    Appellant removed “approximately 80 million pounds of
    uncertified material, the great majority of which [was on] the
    City Parcel. . . . [It] initially negotiated orally with City
    where the walking trail was to be installed.” (Italics added.) In
    its brief appellant alleges, “[T]he City Engineer . . . made the
    demand that [appellant] remove all uncertified fill throughout
    the Property and the City Parcel where the walking trail was to
    be installed.” (Italics added.)
    2 City’s Municipal Code Section 12.210.030 provides:
    “Appeals from permit conditions, or to allow alternate grading
    methods, or for other forms of relief from determinations or
    decisions by the City Engineer, may be made to the Public Works
    Director. The appeal shall be filed within ten calendar days after
    the final action, determination, or decision by the City Engineer.
    The appeal shall be on forms as provided by the Public Works
    Director and shall specifically set forth the grounds for appeal
    and reason or basis for disagreement with the decision of the City
    engineer. The Public Works Director shall have the authority to
    hear such appeals and grant exceptions to particular
    requirements of this Part 2, or approve alternative grading
    methods or permit conditions . . . .”
    4
    representatives for reimbursement or credits, and later
    submitted a request in writing through [its] counsel. All requests
    for reimbursement were denied.”
    Appellant hired a construction forensics firm, Xpera Group
    (Xpera), to research the uncertified fill. Xpera “concluded that
    the uncertified fill at issue is waste from City public works
    projects that was dumped on the City Parcel and the Property by
    the City in or around 1977 when the topography of the City
    Parcel changed from a steep drop off to a gradual slope.”
    “[Appellant’s] causes of action . . . did not accrue until [its]
    discovery of the illegally placed uncertified fill in April 2019.”
    “[Appellant] has incurred, and will continue to incur, in excess of
    $1,000,000 in additional Project costs related to the excavation of
    the uncertified fill and other debris, remediation, lost time,
    overhead, and interest payments to lenders and investors caused
    by the delay in the Project timeline.”
    The complaint consists of four causes of action: (1) inverse
    condemnation, (2) private nuisance, (3) trespass, and (4)
    negligence. The first cause of action alleged that City’s dumping
    of uncertified fill on the Property and the City Parcel, along with
    City’s requirement that appellant remove the fill, “result[ed] in a
    taking and damaging of the value of the Property in an amount
    in excess of $1,000,000.” The second through fourth causes of
    action are based on City’s dumping of uncertified fill on the
    Property and the City Parcel.
    The complaint’s prayer for relief requests “compensatory
    special damages” and “general damages.”
    Demurrer: General Principles and Standard of Review
    “A demurrer tests the legal sufficiency of factual allegations
    in a complaint. [Citation.] A trial court’s ruling sustaining a
    5
    demurrer is erroneous if the facts alleged by the plaintiff state a
    cause of action under any possible legal theory. [Citations.]” (Lee
    Newman, M.D., Inc. v. Wells Fargo Bank (2001) 
    87 Cal.App.4th 73
    , 78.)
    “[W]e apply the de novo standard of review in an appeal
    following the sustaining of a demurrer . . . .” (California
    Logistics, Inc. v. State of California (2008) 
    161 Cal.App.4th 242
    ,
    247.) “[W]e assume the truth of all facts properly pleaded in the
    complaint and its exhibits or attachments, as well as those facts
    that may fairly be implied or inferred from the express
    allegations. [Citation.] ‘We do not, however, assume the truth of
    contentions, deductions, or conclusions of fact or law.’ [Citation.]”
    (Cobb v. O’Connell (2005) 
    134 Cal.App.4th 91
    , 95.)
    “The plaintiff has the burden of showing that the facts
    pleaded are sufficient to establish every element of the cause of
    action and overcoming all of the legal grounds on which the trial
    court sustained the demurrer, and if the defendant negates any
    essential element, we will affirm the order sustaining the
    demurrer as to the cause of action. [Citation.]” (Martin v.
    Bridgeport Community Assoc., Inc. (2009) 
    173 Cal.App.4th 1024
    ,
    1031.)
    When, as here, “a demurrer has been sustained without
    leave to amend, unless failure to grant leave to amend was an
    abuse of discretion, the appellate court must affirm the judgment
    if it is correct on any theory. [Citations.] If there is a reasonable
    possibility that the defect in a complaint can be cured by
    amendment, it is an abuse of discretion to sustain a demurrer
    without leave to amend. [Citation.] The burden is on the
    plaintiff . . . to demonstrate the manner in which the complaint
    might be amended.” (Hendy v. Losse (1991) 
    54 Cal.3d 723
    , 742.)
    6
    Trial Court’s Ruling on Cause of
    Action for Inverse Condemnation
    “‘To state a cause of action for inverse condemnation,
    the property owner must show there was an invasion or
    appropriation (a “taking” or “damaging”) [by a public entity] of
    some valuable property right which the property owner possesses
    . . . and the invasion or appropriation directly and specially
    affected the property owner to his injury.’” (City of Los Angeles v.
    Superior Court (2011) 
    194 Cal.App.4th 210
    , 221.)
    Appellant argues that the complaint states a cause of
    action for inverse condemnation based on the City Engineer’s
    modification of the grading permit to require the removal of the
    uncertified fill on the Property and the City Parcel. Appellant
    asserts: “[Th]e City imposed an illegal development
    condition . . . .” “This substantial verbal modification completely
    changed the scope of [appellant’s] project as approved by the City,
    and unquestionably resulted in an unconstitutional taking for
    which [it] is entitled to just compensation.”
    The trial court concluded that appellant’s cause of action
    for inverse condemnation was barred because it had not
    exhausted its administrative and judicial remedies: “[Appellant]
    had a means of challenging the oral modification of the permit.
    [It] could have refused to comply and administratively appealed
    from the revocation of the grading permit. Alternatively, [it]
    could have filed a petition for writ of mandate in the superior
    court challenging the illegal (i.e., oral) modification of the grading
    permit. . . . [¶] But having accepted the benefits of the permit
    issued it without resorting to the available means of
    contemporaneously challenging it, [appellant] may not now sue
    for inverse condemnation.”
    7
    Doctrine of Exhaustion of Administrative Remedies
    “A demurrer may properly be granted based on the failure
    to adequately plead an exhaustion of administrative remedies.
    [Citation.] A plaintiff must exhaust the administrative remedies
    available before resorting to the courts. . . . [¶] Allowing the
    administrative agency or organization an opportunity to redress
    the alleged wrong without interference by the courts may make
    litigation unnecessary and relieve the courts of an unnecessary
    burden. [Citation.] Even if the plaintiff does not obtain complete
    relief, there may be partial relief that reduces the likelihood and
    scope of litigation. [Citation.] An administrative remedy
    ordinarily provides a more economical and less formal forum to
    resolve disputes and provides an opportunity to mitigate
    damages. [Citation.] The exhaustion requirement also promotes
    the development of a more complete factual record and allows the
    agency to apply its expertise, both of which assist later judicial
    review if necessary. [Citation.] All of these factors both promote
    judicial economy and afford due respect to the administrative or
    organizational dispute resolution process.” (Shuer v. County of
    San Diego (2004) 
    117 Cal.App.4th 476
    , 482; see also
    Campbell v. Regents of University of California (2005) 
    35 Cal.4th 311
    , 321 [“‘Exhaustion of administrative remedies is “a
    jurisdictional prerequisite to resort to the courts”. . .’”]; McKart v.
    United States (1969) 
    395 U.S. 185
    , 195 [“A complaining party
    may be successful in vindicating his rights in the administrative
    process. If he is required to pursue his administrative remedies,
    the courts may never have to intervene”].)
    “The exhaustion doctrine has certain exceptions.
    [Citation.] The doctrine does not apply when the administrative
    remedy is inadequate. [Citation.] For example, it does not apply
    8
    when the administrative procedure is too slow to be effective
    [citation], or when irreparable harm would result by requiring
    exhaustion of administrative remedies before seeking judicial
    relief [citations], or when it is clear that seeking administrative
    remedies would be futile [citation].” (City of San Jose v.
    Operating Engineers Local Union No. 3 (2010) 
    49 Cal.4th 597
    ,
    609.)
    The Trial Court Did Not Err in Sustaining the
    Demurrer for Failure to Exhaust Administrative Remedies
    Municipal Code section 12.210.030 provided appellant an
    administrative remedy – an appeal to City’s Public Works
    Director – but appellant did not avail itself of this remedy. (See
    ante, fn. 2 at p. 4.) The complaint explained, “[I]t would have
    been infeasible to stop the Project in order to pursue an appeal
    due to extensive overhead costs, carrying cost and a balloon
    payment on a construction loan.” (Italics added.) “The cost . . . to
    stop work on the Project was infeasible and would have resulted
    in catastrophic losses.” (Italics added.)
    The above-quoted explanation for not exhausting
    administrative remedies is based on the conclusion that the
    pursuit of an appeal to the Public Works Director would have
    required appellant to stop work on the project. This is a
    conclusion of fact that we do not accept as true. “We treat the
    demurrer as admitting all material facts properly pleaded, but
    not contentions, deductions or conclusions of fact or law.”
    (Serrano v. Priest (1971) 
    5 Cal.3d 584
    , 591.)
    If appellant had appealed, while the appeal was pending it
    could have removed the uncertified fill where the buildings were
    to be constructed and within a three-foot distance from the
    buildings’ foundations. The removal of this fill would have been
    9
    mandatory even if the City Engineer had not modified the
    grading plan. In its brief appellant notes that Earth Systems’
    approved “Grading Plans only required excavation to native
    bottoms below the building foundations and in a 3-foot perimeter
    around the foundations.”3
    If the appeal had not been decided by the time this required
    excavation was completed, appellant could have started to
    excavate the remainder of the Property. The excavation of the
    City Parcel would have been left for last. The complaint alleged
    that “the great majority of [the 80 million pounds of uncertified
    fill] was removed from the City Parcel.”
    Thus, appellant had nothing to lose by filing an appeal. We
    reject its claim that “time-sensitive construction . . . would have
    come to a grinding halt with no forward progress until an . . .
    appeal right was exhausted.” The claim is contradicted by
    appellant’s contention that it “would have immediately appealed
    the [City Engineer’s] determination to at least preserve its rights
    3   Earth Systems recommended: “The existing ground
    surface within the construction limits of the proposed building
    should be initially prepared for grading by removing all . . . non-
    complying fill.” (Italics added.) “Due to the presence of artificial
    fill soils, overexcavation and recompaction of soils in the building
    areas will be necessary to decrease the potential for settlement
    and provide more uniform bearing conditions. Soils should be
    overexcavated to the deeper depth of either 2.5 feet below the
    bottom of the deepest foundation element of mat and post-
    tensioned slab foundations or through all uncertified fill.
    Remedial excavations should be performed to a distance of at least
    3 feet laterally beyond the outside edge of the foundation elements,
    if possible.” (Italics added.)
    10
    had it known the City intended the Engineer’s determination to
    be appealable.”
    The complaint assumes that an appeal would have been a
    protracted affair. This is speculation. We do not know how long
    the appeal would have taken. Since the grading of the Property
    was underway, appellant justifiably could have requested an
    expedited appeal.
    There is no reason why an appeal could not have been
    expeditiously decided. City’s appellate procedure is simple and
    straightforward. The complaining party appeals to the Public
    Works Director. “The appeal shall be on forms as provided by the
    Public Works Director and shall specifically set forth the grounds
    for appeal and reason or basis for disagreement with the decision
    of the City [E]ngineer.” (Muni. Code § 12.210.030.) “[T]he Public
    Works Director shall determine one of the following: 1. The City
    Engineer's decision was a reasonable interpretation of this Part 2
    and that determination shall stand; or 2. Based on findings
    supported by substantial evidence: . . . There are alternate
    grading methods that will provide equivalent levels of protection
    of the public health and safety. Such alternates shall be
    specifically delineated in upholding the appeal.” (Ibid.) The
    municipal code does not require the Public Works Director to
    conduct an evidentiary hearing. “The decision of the Public
    Works Director shall be final and there shall be no further appeal
    to the City Council or any City advisory body.” (Ibid.)
    If appellant had filed an appeal, the parties may have
    reached a compromise. In the absence of a compromise, we do
    not know what the Public Works Director would have decided.
    The Director was not bound by the City Engineer’s decision. The
    Director may have accepted Earth Systems’ alternative
    11
    mitigation measures, particularly under the pedestrian-only
    walking path on City’s Parcel. The walking path would not be
    subjected to heavy loads.
    At oral argument before this court, appellant’s counsel
    insisted that it was unfair for the City Engineer to modify the
    approved grading plan after appellant had commenced grading
    the construction site. But in view of appellant’s failure to appeal
    to the Public Works Director, it would be unfair to impose upon
    City an unexpected potential liability of more than $1 million for
    the cost of complying with the modification.
    Permitting a developer to bring an action for damages
    without exhausting its administrative remedies would have a
    chilling effect on governmental regulation of new construction.
    Construction is a risky business. The developer can never be
    certain of what it will find when it grades the construction site.
    Unforeseen, subsurface conditions may be discovered. Their
    discovery may lead public officials to believe that modifications of
    approved plans are necessary to assure that the project is
    soundly constructed and does not compromise public safety. This
    is what happened here. Public officials will be loath to modify
    approved construction plans if, without seeking available
    administrative review, the developer may comply with the
    modifications, complete the project, and then recover from the
    government the cost of the modifications.
    If appellant had filed an appeal, City would have been
    promptly alerted “‘that [the City Engineer’s] decision [was] being
    questioned’ and [would have been] allow[ed] . . . to mitigate
    potential damages” and “propose alternative mitigation
    measures. . . . Land use planning decisions entail a delicate
    balancing of interests. An under protest exception to the general
    12
    waiver rule [in the present case] would upset this balance
    and inject uncertainty into the planning process.” (Lynch v.
    California Coastal Com. (2017) 
    3 Cal.5th 470
    , 480.) “If every
    owner who disagrees with the conditions of a permit could
    unilaterally decide to comply with them under protest, do the
    work, and file an action in inverse condemnation on the theory of
    economic coercion, complete chaos would result in the
    administration of this important aspect of municipal affairs.”
    (Pfeiffer v. City of La Mesa (1977) 
    69 Cal.App.3d 74
    , 78,
    superseded by statute on other grounds as stated in Shapell
    Industries, Inc. v. Governing Board (1991) 
    1 Cal.App.4th 218
    ,
    241.)
    Appellant maintains that the City Engineers’ oral
    modification of the grading plan “violated the City’s Municipal
    Code,” which required that the modification be approved in
    writing by the City Engineer. The complaint alleged: “The
    modification to the Grading Plan was imposed verbally [i.e.,
    orally,] in the field, with no supporting documentation . . . .” But
    the absence of a writing does not excuse appellant’s failure to
    exhaust its administrative remedies before bringing an action for
    inverse condemnation.
    The complaint alleged appellant did not know it had a right
    to appeal the City Engineer’s decision to the Public Works
    Director. “Ignorance of the law is no excuse. This maxim is so
    long standing and so well established that it is part of the very
    fabric of our legal system.” (Diaz v. Grill Concepts Services, Inc.
    (2018) 
    23 Cal.App.5th 859
    , 869; see also Tarrant v. Butler (1960)
    
    180 Cal.App.2d 235
    , 240 [“knowledge of the building and
    zoning laws will be imputed to a property owner”].) Appellant’s
    ignorance is particularly inexcusable because it was a
    13
    sophisticated real estate developer. “Developers are
    sophisticated entities, capable of and expected to conduct due
    diligence to determine their rights and duties.” (North Murrieta
    Community, LLC v. City of Murrieta (2020) 
    50 Cal.App.5th 31
    ,
    45.) Appellant never asked City officials if the City Engineer’s
    decision was appealable or otherwise reviewable by higher
    authority.
    City Is Not Equitably Estopped
    From Asserting a Forfeiture
    Appellant claims City is equitably estopped from asserting
    a forfeiture based on appellant’s failure to exhaust administrative
    remedies because City did not inform appellant of its right to
    appeal. Appellant asserts: “[N]either the City Engineer nor any
    other City representatives ever said anything about [appellant’s]
    right to an appeal.” “The City’s actions led [appellant] to believe,
    in good faith, that the City Engineer’s determination was not one
    that could be appealed . . . .” “[T]he City’s complete failure to
    apprise [appellant] of its alleged appeal rights constitutes a clear
    breach of the City’s duty to inform applicants of remedies
    available to challenge adverse actions.”
    “The doctrine [of equitable estoppel] ‘ordinarily will not
    apply against a governmental body except in unusual instances
    when necessary to avoid grave injustice and when the result will
    not defeat a strong public policy. . . .’” (Steinhart v. County of Los
    Angeles (2010) 
    47 Cal.4th 1298
    , 1315.) “‘The doctrine . . . is
    founded on notions of equity and fair dealing and provides that a
    person may not deny the existence of a state of facts if that
    person has intentionally led others to believe a particular
    circumstance to be true and to rely upon such belief to their
    detriment. . . . “‘Generally speaking, four elements must be
    14
    present in order to apply the doctrine . . . : (1) the party to be
    estopped must be apprised of the facts; (2) he must intend that his
    conduct shall be acted upon, or must so act that the party
    asserting the estoppel had a right to believe it was so intended; (3)
    the other party must be ignorant of the true state of facts; and (4)
    he must rely upon the conduct to his injury.’”’” (McGlynn v. State
    of California (2018) 
    21 Cal.App.5th 548
    , 561, italics added.)
    Nothing in the record suggests that City officials intentionally led
    appellant to believe that the City Engineer’s decision was not
    appealable or that City officials “so act[ed] that [appellant] had a
    right to believe [they had] so intended.” (Ibid.) The issue of
    appealability was never discussed.
    Appellant cites no authority imposing a duty upon City to
    inform a real estate developer of its right to appeal a decision by
    the City Engineer. In the absence of such a duty, an estoppel
    cannot be based on mere silence. “Generally speaking, ‘“mere
    silence on the part of a party will not create an estoppel unless he
    was under some obligation to speak, and a party invoking such
    estoppel must show that it was the duty of the other to speak,
    and that he has not only been induced to act by reason of
    such silence, but that the other had reasonable cause to believe
    that he would so act.”’” (Johnson v. Johnson (1960) 
    179 Cal.App.2d 326
    , 330.)
    Appellant quotes the following excerpt from Asimow et al.,
    Cal. Practice Guide: Administrative Law (The Rutter Group, Nov.
    2022 update) ¶ 15.108: “‘An agency can be estopped from relying
    on the exhaustion of remedies defense where it negligently
    misadvised the private party about the need to exhaust a remedy
    or because the agency made a party's access to that remedy
    difficult.’” City did not engage in such conduct.
    15
    Uniwill v. City of Los Angeles Is Distinguishable
    Appellant contends, “This case fits squarely within the
    holding of Uniwill v. City of Los Angeles [(2004) 
    124 Cal.App.4th 537
     (Uniwill)] . . . . The facts could not be more analogous . . . .”
    Based on Uniwill, appellant argues that its “decision to continue
    with the project did not function as a waiver of its right to sue the
    City for inverse condemnation.”
    Uniwill is distinguishable. There, the City of Los Angeles
    issued Uniwill a tentative tract map approving construction of a
    shopping center. Uniwill began construction of the project. After
    it had expended approximately $6.5 million, the city informed
    Uniwill that it “would not certify to the Advisory Agency that
    Uniwill had complied with the conditions of the Tentative Tract
    Map” unless Uniwill conveyed an easement, performed trenching
    work, and paid a fee. (Uniwill, supra, 124 Cal.App.4th at p. 540.)
    “Uniwill determined that it was economically unfeasible to stop
    the project and commence litigation to vindicate its rights.
    Consequently, Uniwill complied with the City's ‘unlawful
    exaction’ under protest and, after completing the project, filed
    suit in inverse condemnation.” (Ibid.)
    The trial court sustained the city’s demurrer to Uniwill’s
    complaint because pursuant to Government Code section
    66499.37, “Uniwill was required to commence [but did not
    commence] an action or proceeding within 90 days after . . . it
    learned of the City’s demand that Uniwill grant the . . .
    easement, and . . . its failure to do so barred the action.”
    (Uniwill, supra, 124 Cal.App.4th at p. 542.) At the time of the
    trial court’s decision, Government Code section 66499.37
    provided, “‘Any action or proceeding to attack . . . the decision of
    an advisory agency, appeal board or legislative body concerning a
    16
    subdivision, . . . or to determine the reasonableness, legality or
    validity of any condition attached thereto, shall not be
    maintained by any person unless such action or proceeding is
    commenced and service of summons effected within 90 days after
    the date of such decision. . . .’” (Id. at p. 539, fn. 1, italics added.)
    The Court of Appeal reversed because Uniwill’s complaint
    “alleged that the City’s demand that it grant . . . an easement . . .
    was not a requirement imposed by the Advisory Agency as a
    condition for the grant of permission to develop the property.
    Rather, it was merely a threat, uttered by a City
    representative . . . to deprive Uniwill of what it was legally
    entitled to, issuance of a Final Tract Map and a certificate of
    occupancy upon completion of the project in conformity with the
    governmental approvals already issued. [¶] The City cites no
    case in support of its contention that a threat issued by an agent
    of the City under the circumstances described above which
    results in the taking of private property must be challenged in an
    action or proceeding filed within 90 days of the threat.” (Uniwill,
    supra, 124 Cal.App.4th at pp. 543-544.)
    Uniwill has no bearing on the present appeal. Uniwill
    held that the 90-day filing deadline of Government Code section
    66499.37 does not apply where, after approval of a tentative tract
    map and commencement of the project, the city demands that the
    developer comply with additional conditions but the demand
    constitutes a mere threat instead of a requirement imposed by
    the advisory agency. The present appeal does not involve the
    applicability of section 66499.37. Furthermore, in Uniwill the
    city did not contend that the developer had failed to exhaust its
    administrative remedies.
    17
    Remaining Causes of Action Are
    Barred by the Statute of Limitations
    The remaining causes of action are private nuisance,
    trespass, and negligence. For these causes of action, the
    applicable statutes of limitations are one year for the
    presentation of a claim to the City (Gov. Code, § 911.2; see
    Alexander v. Exxon Mobil (2013) 
    219 Cal.App.4th 1236
    , 1263),
    and three years for filing a civil action. (Code Civ. Proc., § 338,
    subd. (b)); see Shamsian v. Atlantic Richfield Co. (2003) 
    107 Cal.App.4th 967
    , 979; Cyr v. McGovran (2012) 
    206 Cal.App.4th 645
    , 650.)
    “The statute of limitations usually commences when a
    cause of action ‘accrues,’ and it is generally said that ‘an
    action accrues on the date of injury.’” (Bernson v. Browning-
    Ferris Industries (1994) 
    7 Cal.4th 926
    , 931.) Based on the
    complaint, the statutes of limitations began to run “in or around
    1977” when City dumped the uncertified fill on the Property and
    the City Parcel. To avoid the bar of the statute of limitations,
    appellant relies on the discovery rule. Appellant claims it did not
    discover the uncertified fill until April 2019.
    “An important exception to the general rule of accrual is
    the ‘discovery rule,’ which postpones accrual of a cause of action
    until the plaintiff discovers, or has reason to discover, the cause
    of action. [Citations.] [¶] A plaintiff has reason to discover a
    cause of action when he or she ‘has reason at least to suspect a
    factual basis for its elements.’ [Citations.] Under the discovery
    rule, suspicion of one or more of the elements of a cause of action,
    coupled with knowledge of any remaining elements, will
    generally trigger the statute of limitations period.” (Fox v.
    Ethicon Endo-Surgery, Inc. (2005) 
    35 Cal.4th 797
    , 806-807.)
    18
    “A plaintiff whose complaint shows on its face that his or
    her claim would be barred by the applicable orthodox statute of
    limitations, and who intends to rely on the discovery rule to toll
    the orthodox limitation period, ‘must specifically plead facts
    which show (1) the time and manner of discovery and (2) the
    inability to have made earlier discovery despite reasonable
    diligence. [Citations.] Mere conclusory assertions that delay in
    discovery was reasonable are insufficient and will not enable the
    complaint to withstand general demurrer. [Citation.]’
    [Citations.] Arguments that discovery-rule issues are necessarily
    factual and cannot be resolved on demurrer have been rejected.”
    (CAMSI IV v. Hunter Technology Corp. (1991) 
    230 Cal.App.3d 1525
    , 1536-1537 (CAMSI).)
    The trial court ruled that the three remaining causes of
    action “are time-barred [by the statute of limitations] and that
    [appellant] has not pleaded facts bringing [them] with[in] the
    ‘discovery rule.’” The court explained: “For purposes of the
    statute of limitations, the knowledge of [appellant’s] predecessors
    [i.e., previous owners of the Property] is imputed to it. [Citation.]
    [Appellant] concedes that its ‘predecessors as early as 2004 may
    have been aware of the existence of some uncertified fill located
    underneath some specific portions of the subject properties.’ . . .
    [Appellant] does not vigorously resist the proposition that these
    three causes of action would have accrued by this time, if not
    sooner. Therefore, the limitations period would have expired
    prior to the time this action was commenced in 2020.”
    The trial court did not err. In the complaint appellant
    made allegations only as to its own lack of discovery. But if prior
    owners of the Property “knew or should have known that [City]
    had [dumped uncertified fill on the Property,] their knowledge
    19
    would have been imputed to [appellant].” (CAMSI, supra, 230
    Cal.App.3d at p. 1537; see also Bradler v. Craig (1969) 
    274 Cal.App.2d 466
    , 472.) “In an action involving tortious injury to
    property, the injury is considered to be to the property itself
    rather than to the property owner, and thus the running of the
    statute of limitations against a claim bars the owner and all
    subsequent owners of the property. [Citations.] In other words,
    the statute of limitations does not commence to run anew every
    time the ownership of the property changes hands.” (Beck
    Development Co. v. Southern Pacific Transportation Co. (1996) 
    44 Cal.App.4th 1160
    , 1216.)
    The complaint “wholly fails to show that [prior owners of
    the Property] would have been unable, despite reasonable
    diligence, to have discovered” the uncertified fill. (CAMSI, supra,
    230 Cal.App.3d at p. 1537.) In view of the enormity of the
    amount of fill (80 million pounds on the Property and the City
    Parcel), it is difficult to understand how the owner of the
    Property at the time of the dumping would not have been aware
    of it or would not have had reason to discover it. The complaint
    alleged that, because of the dumping, “[t]he topography of the
    City Parcel changed in or around 1977, from a steep
    approximately 20-foot drop-off to a gradual slope . . . .” The
    Xpera Report, attached as Exhibit D to the complaint, stated that
    in 1977 the dumping of fill “over the entire combined City Site
    and Project Site . . . created a manufactured slope across the
    boundary area of the Project Site and the City Site.”
    In the trial court appellant acknowledged “that the
    Property owner in 1977 and its successors possibly may have
    been aware that the City dumped material on the City Parcel and
    the Property.” In a trench dug on the Property in 2006, Earth
    20
    Systems found “large amounts of debris ranging from blocks of
    concrete up to 2.5’ [2.5 feet] in diameter to asphalt pieces up to 7’
    [7 feet] long.”
    Appellant maintains that, irrespective of whether its
    predecessors knew or had reason to know of the dumping of the
    uncertified fill, the causes of action are not time-barred because
    they do “not seek recovery for a direct injury resulting
    immediately from the . . . dumping . . . . The principal harm
    suffered by [appellant] was caused by the City’s unforeseeable,
    unjustifiable and unlawful demand that [appellant] remove tons
    of the City’s waste from the City’s own property. [Appellant’s]
    action for damages for the injury caused by the City’s dumping of
    uncertified fill is not a traditional trespass upon real property,
    but rather in the nature of an action upon the case at common
    law for a consequential injury.” (Italics added.) “[T]he statute of
    limitations only starts to run upon [appellant’s] sustaining the
    consequential injury, and its knowledge thereof.”
    “The common law drew a distinction between two types of
    actions for injuries to real property. If the injury was an
    immediate and direct result of the act complained of, then an
    action for trespass was the appropriate remedy. On the other
    hand, where the damages did not immediately ensue from the act
    complained of, the damages were deemed to have been
    consequential, and the only remedy was an action ‘on the case.’”
    (Elton v. Anheuser-Busch Beverage Group, Inc. (1996) 
    50 Cal.App.4th 1301
    , 1305; see also Hicks v. Drew (1897) 
    117 Cal. 305
    , 310 [“‘where damages do not immediately ensue from the act
    complained of, it is consequential, and case is the proper remedy;
    and, on the contrary, where the act itself, and not the
    21
    consequence of it, occasions the mischief, trespass is the right
    action’”].)
    Appellant’s “action on the case” theory is based on its claim
    that the primary injury to its property was not caused by the
    dumping of the uncertified fill. Instead, it was caused by the
    consequences of the dumping, i.e., the City Engineer’s
    unjustifiable modification of the grading permit to require
    appellant to remove the fill. Therefore, appellant argues, the
    statute of limitations on the causes of action began to run when
    the City Engineer made the modification.
    The “action on the case” theory is of no assistance to
    appellant. The theory in effect restates the first cause of action
    for inverse condemnation. As we have explained at length ante,
    pages 8-16, appellant forfeited its right to object to the
    modification of the grading plan because it had complied with the
    modification without exhausting its administrative remedies.
    Disposition
    The judgment is affirmed. City shall recover its costs on
    appeal.
    NOT TO BE PUBLISHED.
    YEGAN, J.
    We concur:
    GILBERT, P. J.
    BALTODANO, J.
    22
    Mark S. Borrell, Judge
    Superior Court County of Ventura
    ______________________________
    Price, Postel & Parma and Timothy E. Metzinger, Todd A.
    Amspoker, Cameron Goodman, for Plaintiff and Appellant.
    Olivarez Madruga Law and Thomas M. Madruga, Lloyd
    Pilchen, for Defendant and Respondent.