Oltmans Construction v. Bayside Interiors , 10 Cal. App. 5th 355 ( 2017 )


Menu:
  • Filed 3/30/17
    CERTIFIED FOR PUBLICATION
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FIRST APPELLATE DISTRICT
    DIVISION THREE
    OLTMANS CONSTRUCTION CO.,
    Cross-complainant and Appellant,
    A147313
    v.
    BAYSIDE INTERIORS, INC.,                               (San Mateo County
    Super. Ct. No. CIV527704)
    Cross-defendant and Respondent.
    This appeal presents for interpretation an indemnity provision in a construction
    subcontract providing indemnity to a general contractor for injury claims arising out of
    the scope of the subcontractor’s work “except to the extent the claims arise out of, pertain
    to, or relate to the active negligence or willful misconduct” of the general contractor.
    Does this provision preclude the general contractor from recovering any indemnity if its
    active negligence contributed to the injury, or does the provision limit recoverable
    indemnity to the portion of liability attributable to the negligence of others? The same
    question arises as to the meaning of Civil Code section 2782.05,1 which renders void and
    unenforceable an indemnity provision “to the extent the claims arise out of, pertain to, or
    relate to the active negligence or willful misconduct of that general contractor.” The trial
    court adopted the former interpretation but we conclude this was error. Under such a
    provision the general contractor is precluded from recovering indemnity for liability
    incurred as a result of its own active negligence but may be indemnified for the portion of
    liability attributable to the fault of others. Therefore, summary judgment was erroneously
    entered against the general contractor on its indemnity claim.
    1
    All statutory references are to the Civil Code unless otherwise indicated.
    1
    Background
    This action arises out a jobsite injury suffered by Gerardo Escobar, an employee of
    O’Donnell Plastering, Inc. (O’Donnell). O’Donnell was a sub-subcontractor of cross-
    defendant Bayside Interiors, Inc. (Bayside), which was a subcontractor of cross-
    complainant Oltmans Construction Co. (Oltmans), the general contractor on a
    construction project in Menlo Park. Escobar brought suit against Oltmans (and against
    the owner of the property), alleging, inter alia, that Oltmans negligently cut and left
    unsecured a skylight opening in the roof of the building under construction, through
    which Escobar fell and suffered injuries when installing scaffolding that O’Donnell had
    contracted with Bayside, the plastering subcontractor, to erect. Oltmans filed a cross-
    complaint against Bayside and O’Donnell, which contains the claims at issue in this
    appeal. The cross-complaint states six causes of action, alleging, inter alia, a right to
    express contractual indemnity and also breach of Bayside’s contractual obligation to
    provide certificates of insurance certifying that Oltmans was covered as an additional
    insured under liability policies the subcontractors were obligated to obtain.2
    The basic facts concerning the incident giving rise to Escobar’s injury appear
    largely without dispute in the parties’ summary judgment papers. On April 13, 2013, an
    Oltmans employee, Dennis Raia, was cutting an opening for the installation of a skylight
    on the roof of the building when Oltmans’ project superintendent instructed him to stop
    work temporarily and secure the opening because debris was falling on other workers
    below. Raia placed over the opening, which itself was covered with plywood, a skylight
    curb, a 25-pound wooden frame with wire mesh over the top. He did not attach the curb
    to the roof. On April 17, before Raia had returned to complete his job, Escobar and
    another O’Donnell employee came to the jobsite to erect scaffolding. While tying the
    scaffolding to the building Escobar climbed to the roof and while walking there fell
    2
    The six causes of action of the cross-complaint are labelled “Breach of Contract,”
    “Express Contractual Indemnity,” “Comparative Equitable Indemnity,” “Contribution,”
    “Declaratory Relief for Duty to Defend,” and “Declaratory Relief for Duty to
    Indemnify.”
    2
    through the opening that had been partially cut and covered. Escobar had climbed to the
    roof without wearing fall-protection gear and did not recall observing the skylight or the
    skylight curb.
    The subcontract between Oltmans and Bayside contains, as paragraph 11, an
    indemnity provision reading in part as follows: “[Bayside] shall, to the fullest extent
    permitted by law, indemnify, defend, protect and hold harmless [Oltmans] . . . from and
    against each and all of the following: [¶] (a) Any claims . . . arising out of (i) the scope of
    the work of [Bayside], or (ii) breach of the obligations of [Bayside] arising from the
    scope of work under this subcontract . . . , or (iv) any other act or omission arising out of
    the work of [Bayside or its] sub-subcontractors . . . resulting in or alleged to have resulted
    in . . . bodily injury . . . . The indemnification and defense required by this Paragraph
    11(a) shall apply in all described matters herein except to the extent the claims arise out
    of, pertain to, or relate to the active negligence or willful misconduct of the contractor
    parties . . ., or to the extent such obligation is inconsistent with the provisions of
    California Civil Code 2782.05.” (Italics added.)
    Paragraph 10(f) of the subcontract provides: “[Bayside] shall not allow any
    consultant or sub-subcontractor to commence any work until [Bayside] obtains from such
    consultant or sub-subcontractor . . . an indemnification in form and substance identical to
    the indemnity set forth in paragraph 11 of the subcontract, with the modification that such
    indemnity shall be from the consultant or sub-subcontractor for the benefit of [Oltmans]
    . . . .”
    Bayside moved for summary judgment on Oltmans’ cross-complaint arguing,
    among other things, that the undisputed facts establish that Oltmans’ employee was
    actively negligent in failing to secure the skylight curb to the roof and that the active
    negligence precludes Oltmans from obtaining any defense or indemnity under the terms
    of the indemnity provision. Oltmans argued that there is a material disputed fact as to its
    alleged active negligence and that, even if actively negligent, it is entitled to be
    indemnified for the portion of any liability incurred as a result of the negligence of others,
    specifically negligence of Escobar or O’Donnell.
    3
    O’Donnell also moved for summary judgment on Oltmans’ cross-complaint.
    While Bayside’s motion was pending, the court granted O’Donnell’s motion on the
    ground that because O’Donnell had not executed its sub-subcontract prior to the date of
    Escobar’s injury, Labor Code section 38643 precludes any recovery under the indemnity
    provision contained in the sub-subcontract that O’Donnell eventually executed. In
    supplemental briefing on Bayside’s motion after that ruling, Oltmans argued that
    summary judgment should be denied on the additional ground that Bayside’s failure to
    obtain a signed agreement from O’Donnell before O’Donnell began its work constituted a
    breach of Bayside’s obligations under paragraph 10(f) of Bayside’s subcontract.
    After argument, the court granted Bayside’s motion for summary judgment. In a
    written order, the court ruled that “Oltmans’ conduct in leaving a partially cut skylight on
    the roof of a building for several days, without securing a cover, and failing to advise
    O’Donnell’s employees of the hazard clearly constitutes active negligence on Oltmans’
    part. As such, Bayside’s duty to indemnify and hold Oltmans harmless is precluded by
    Oltmans’ own conduct.” The trial court rejected Oltmans’ response that, even if actively
    negligent, it is entitled to indemnification for any portion of fault that may be apportioned
    to O’Donnell or others, and that the words “to the extent” should be construed as barring
    indemnity for Escobar’s injuries only to the extent of Oltmans’ own active negligence.
    The trial court “reject[ed] this argument, [finding] that the parties’ subcontract is indeed a
    general indemnity agreement. An actively negligent indemnitee cannot recover under a
    general indemnity contract, even where other parties are contributorily negligent,” citing
    McCrary Construction Co. v. Metal Deck Specialists, Inc. (2005) 
    133 Cal. App. 4th 1528
    ,
    1541. The court also rejected Oltmans’ breach of contract claim, stating that the issue was
    “neither supported by any facts in Oltmans’ separate statement in opposition to Bayside’s
    3
    Labor Code section 3864 provides: “If an action as provided in this chapter prosecuted
    by the employee . . . against the third person results in judgment against such third
    person, or settlement by such third person, the employer shall have no liability to
    reimburse or hold such third person harmless on such judgment or settlement in absence
    of a written agreement so to do executed prior to the injury.”
    4
    motion, nor specifically pled in Oltmans’ cross-complaint” and that summary judgment
    could not be denied “on issues not raised by the pleadings.”4
    Oltmans timely appealed from the resulting adverse judgment.
    Discussion
    1. Express Contractual Indemnity
    Preliminarily, we note that summary judgment may well have been improper
    because Bayside failed to present evidence establishing Oltmans’ active negligence as a
    matter of law. We agree that if Oltmans was negligent, its negligence would have been
    active, rather than passive, as that distinction has been drawn in applying the law
    applicable to indemnity agreements. (Rossmoor Sanitation, Inc. v. Pylon, Inc. (1975) 
    13 Cal. 3d 622
    , 629 (Rossmoor); Morgan v. Stubblefield (1972) 
    6 Cal. 3d 606
    , 626-627.)
    However, we question whether Bayside’s proffered evidence was sufficient to establish
    as a matter of law that Oltmans was negligent. Oltmans’ employee, Raia, did place over
    the partial opening, which was covered by plywood, a 25-pound wooden frame to which
    was attached wire mesh that presumably would have prevented the accident had it
    remained in place. The skylight curb was placed against the wall of the building. There is
    no evidence that Raia had any reason to expect others to be on the roof before he
    returned, that the 25-pound wooden frame was likely to move or be moved if not screwed
    or otherwise attached to the roof, or—unlike the situation in Morgan v. Stubblefield, on
    which Bayside heavily relies—that the roof site was in violation of construction safety
    orders. (Morgan v. 
    Stubblefield, supra
    , at p. 626.) Hence, Bayside’s evidence arguably
    was insufficient to conclusively establish that the steps Raia took to secure the opening
    were unreasonable and to shift the burden of presenting contrary evidence to Oltmans.
    We need not resolve the question, however, because we conclude there is a more
    fundamental error in the premise on which summary judgment was granted.
    4
    The court also rejected Oltmans’ claims for equitable indemnity and contribution. On
    appeal, Oltmans does not challenge those rulings.
    5
    The development in California of the law governing the interpretation of
    indemnity agreements has been chronicled in numerous decisions. A helpful summary is
    found in the case on which Bayside and the trial court order place particular reliance,
    McCrary Construction Co. v. Metal Deck Specialists, 
    Inc., supra
    , 
    133 Cal. App. 4th 1528
    .
    There, the court explained: “ ‘Indemnity may be defined as the obligation resting on one
    party to make good a loss or damage another party has incurred. [Citation.] This
    obligation may be expressly provided for by contract [citation], it may be implied from a
    contract not specifically mentioning indemnity [citation], or it may arise from the equities
    of particular circumstances [citations]. Where, as here, the parties have expressly
    contracted with respect to the duty to indemnify, the extent of that duty must be
    determined from the contract and not by reliance on the independent doctrine of equitable
    indemnity. [Citation.]’ [Citations.] [¶] Some California cases have interpreted express
    indemnity provisions by reference to a classification system described in MacDonald &
    Kruse, Inc. v. San Jose Steel Co. (1972) 
    29 Cal. App. 3d 413
    .” (McCrary Construction Co.
    at p. 1536.) The opinion then explains the three classifications described in MacDonald
    & Kruse, before continuing with the approach that has to a large extent supplanted those
    classifications. “In 
    Rossmoor[, supra
    , 
    13 Cal. 3d 622
    ], our Supreme Court described the
    governing law as follows: ‘If an indemnity clause does not address itself to the issue of an
    indemnitee’s negligence, it is referred to as a “general” indemnity clause. [Citations.]
    While such clauses may be construed to provide indemnity for a loss resulting in part
    from an indemnitee’s passive negligence, they will not be interpreted to provide
    indemnity if an indemnitee has been actively negligent. [Citations.] [¶] Provisions
    purporting to hold an owner harmless “in any suit at law” [citation], “from all claims for
    damages to persons” [citation], and “from any cause whatsoever” [citation], without
    expressly mentioning an indemnitee’s negligence, have been deemed to be “general”
    clauses.’ [Citation.] [¶] Rossmoor explained, however, that the analysis of an indemnity
    clause was a matter of contract interpretation and the ‘active-passive dichotomy’ was not
    ‘wholly dispositive.’ [Citation.] ‘[W]hile adhering to the underlying distinction between
    active and passive negligence which has long been accepted by the bench, the bar, and
    6
    the insurance industry, we hold that . . . the question whether an indemnity agreement
    covers a given case turns primarily on contractual interpretation, and it is the intent of the
    parties as expressed in the agreement that should control. When the parties knowingly
    bargain for the protection at issue, the protection should be afforded. This requires an
    inquiry into the circumstances of the damage or injury and the language of the contract;
    of necessity, each case will turn on its own facts.’ ” (Id. at pp. 1537-1538.) The court
    continued, “Thus, following Rossmoor, an indemnity provision that does not refer to the
    issue of the indemnitee’s negligence will be considered to be a general indemnity clause
    under which the indemnitee is not entitled to indemnity for its active negligence, unless
    the circumstances of the case and language of the contract evince a different intent by the
    parties.” (Id. at p. 1538.)
    An oft-cited case subsequent to Rossmoor, emphasizing that the fundamental
    question in applying a contractual indemnity provision is interpretation of the parties’
    intent, is Morton Thiokol, Inc. v. Metal Building Alteration Co. (1987) 
    193 Cal. App. 3d 1025
    . In that case, the indemnitee under a general indemnity provision was held to be
    entitled to indemnification despite its active negligence. The court “agree[d] with the
    proposition that indemnity should be afforded under any circumstances where to do so
    furthers the manifest intent of the parties to the contract and where the loss sustained
    could not have occurred without the indemnitor’s negligence.” (Id. at p. 1029.) The court
    considered its conclusion to be faithful to the admonition in Rossmoor “that the active-
    passive rubric ought not to be wholly dispositive, but that instead the enforceability of an
    indemnity agreement shall primarily turn upon a reasonable interpretation of the intent of
    the parties.” (Id. at p. 1030.)
    The indemnity provision in the present case is not literally a “general” indemnity
    clause as used in Rossmoor because it does address itself to the issue of the indemnitee’s
    negligence. In paragraph 11 of the subcontract, Bayside does agree to indemnify Oltmans
    against all claims arising out of the scope of its work, but the paragraph goes on to state
    that the provision “shall apply in all described matters herein except to the extent the
    claims arise out of, pertain to, or relate to the active negligence or willful misconduct of
    7
    the contractor parties . . . , or to the extent such obligation is inconsistent with the
    provisions of California Civil Code 2782.05.” This language plainly implies that Oltmans
    is entitled to indemnification for a claim that arises out of its negligence that is not active
    negligence or willful misconduct. What is disputed is whether its active negligence
    precludes it from recovering any indemnity or only from being indemnified for the
    portion of its liability based on its own active negligence or intentional misconduct.
    Contrary to Bayside’s argument and the trial court’s decision, McCrary
    Construction Co. does not support the former interpretation. Although the court there
    held that the indemnitee whose active negligence contributed to the injured party’s claim
    was not entitled to indemnification, the indemnitee in that case was seeking
    indemnification only for the portion of liability that was attributable to its own active
    negligence. In the underlying action liability had already been apportioned on a
    comparative fault basis. The court noted that it was not “necessary to resolve [the
    indemnitor’s] contention that a general indemnity clause should be interpreted as
    providing for at most comparative indemnity. . . . [H]owever, the practical effect of [its]
    decision . . . will be consistent with comparative indemnity principles, as it will leave [the
    indemnitee and the indemnitor] each liable to the plaintiffs in the proportion the jury
    found each responsible for [the injury].” (McCrary Construction Co. v. Metal Deck
    Specialists, 
    Inc., supra
    , 133 Cal.App.4th at p. 1541, fn. omitted.)
    Hernandez v. Badger Construction Equipment Co. (1994) 
    28 Cal. App. 4th 1791
    ,
    1818-1823 provides compelling authority for interpreting the indemnity provision here to
    permit indemnification for the portion of Oltmans’ liability attributable to the negligence
    of others. Although not the basis for its decision, the Hernandez court noted that the
    foundation of the holding in McDonald & Kruse. Inc., that under a general indemnity
    provision the indemnitor will not be responsible for any indemnity if the indemnitee’s
    negligence contributed to the injured party’s injuries, “appears substantially undercut by
    the subsequently evolving and presumably more equitable trend in statutory and case law
    toward allocating liability in proportion to comparative fault.” (Hernandez, at p. 1823.)
    There, “based upon reasonable interpretation of the contract in light of its language, the
    8
    circumstances of Employee’s injury, and the parties’ intent in accord with Rossmoor . . . ,
    supra, 
    13 Cal. 3d 622
    and Morton Thiokol, Inc. v. Metal Building Alteration Co
    ., supra
    ,
    193 Cal.App.3d. 1025” (Hernandez, pp. 1822-1823), the court held that despite being
    found to have been actively negligent, the indemnitee was entitled to indemnification for
    the portion of its liability attributable to the negligence of the indemnitor. “Reasonably
    read, the contractual indemnity language here did not obligate [indemnitor] to indemnify
    [indemnitee] for [indemnitee’s] own negligence. Neither could [indemnitee] reasonably
    expect to be indemnified for its own negligence. However, reasonably construed, the
    contractual language obligated [indemnitor] to indemnify [indemnitee] for the portion of
    [indemnitee’s] liability attributable to [indemnitor’s] fault. Such interpretation is
    consistent with [indemnitee’s] reasonable expectation it would be indemnified for
    liability arising from the negligence of [indemnitor]. Thus, we conclude despite its 20
    percent active negligence [indemnitee] was contractually entitled to indemnification from
    [indemnitor] for the portion of plaintiffs’ joint and several economic damage award
    attributable to [indemnitor’s] 55 percent negligence that is ultimately paid by
    [indemnitee].” (Id. at p. 1822.)
    In Maryland Casualty Co. v. Bailey & Sons, Inc. (1995) 
    35 Cal. App. 4th 856
    , 868-
    869, the same court that decided Hernandez v. Badger Construction Equipment Co
    ., supra
    , 
    28 Cal. App. 4th 1791
    stated that Hernandez should not be read “so broadly” as to
    necessarily permit an actively negligent indemnitee to recover indemnity on a
    comparative fault basis from the indemnitor. Rather, the court reaffirmed that the general
    rule limiting the right of an actively negligent indemnitee to obtain indemnification “may
    not always apply and is merely a tool to be used to ascertain the intent of the parties.”
    (35 Cal.App.4th at p. 869.) The court should not “ignore the traditional rule for
    interpreting contractual intent if there is a basis in the record to show the parties intended
    the rule to apply to their contracts.” (Ibid.)
    The indemnity provision in the present case makes unmistakably clear that the
    parties intended to limit the indemnitee Oltmans’ right to indemnification for liability
    arising out of the scope of the indemnitor Bayside’s work only “to the extent” the claims
    9
    arose out of Oltmans’ active negligence or willful misconduct. Had the parties intended
    to prohibit Oltmans from obtaining any indemnification if it was actively negligent, that
    prohibition could have been stated simply and straightforwardly. Rather, the provision
    limits the right to indemnification only “to the extent” of Oltmans’ active negligence, and
    no more.
    Oltmans cites numerous cases from other jurisdictions that have held that such
    language in an indemnity provision creates a comparative fault standard for an award of
    indemnity. (MT Builders v. Fisher Roofing, Inc. (Ariz.Ct.App. 2008) 
    197 P.3d 758
    , 765
    [A provision “limited [indemnitor’s] indemnity obligation ‘to the extent caused in whole
    or in part by any negligent act or omission of the Subcontractor.’ . . . [¶] . . . [O]ther
    courts have construed this or virtually identical language as creating a comparative fault
    or negligence arrangement whereby the indemnitor’s liability is limited ‘to the extent’ it
    and its supervisees were at fault.”]; Nusbaum v. Kansas City (Mo. 2003) 
    100 S.W.3d 101
    ,
    106 [“The phrase ‘to the extent caused’ expresses an intention to limit the indemnitor’s
    liability to the portion of fault attributed to the indemnitor.”]; East-Harding, Inc. v.
    Horace A. Piazza & Associates (Ark.Ct.App. 2002) 
    91 S.W.3d 547
    , 551 [“Courts in other
    jurisdictions, considering indemnification provisions virtually identical to the one at issue
    in the present case, have agreed that the phrase ‘but only to the extent caused’ expresses
    the intent to limit the indemnitor’s liability to that portion of fault attributed to the
    indemnitor.”]; Greer v. City of Philadelphia (Pa. 2002) 
    795 A.2d 376
    , 379 [“By agreeing
    to language stating that [indemnitees] were indemnified for damages ‘only to the extent
    that’ the damages were caused by the negligence of [indemnitor] and its sub-
    subcontractors, employees and anyone for whom it may be liable, the parties
    communicated their intent to limit any indemnification to that portion of damages
    attributed to the negligence of [indemnitor] and those under its supervision.”]; Hagerman
    Construction Corp. v. Long Electric Co. (Ind.Ct.App. 2000) 
    741 N.E.2d 390
    , 393-394
    [“[T]he phrase ‘but only to the extent” clearly limits indemnitor’s obligation to indemnify
    [indemnitee] only to the extent that [indemnitor], its sub-subcontractors, employees, and
    anyone for whom it may be liable are negligent.”]; Braegelmann v. Horizon Development
    10
    Co. (Minn.Ct.App. 1985) 
    371 N.W.2d 644
    , 646 [“The additional phrase, ‘to the extent
    caused,’ . . . suggests a ‘comparative negligence’ construction under which each party is
    accountable ‘to the extent’ their negligence contributes to the injury.”]; Mautz v. J.P.
    Patti Co. (N.J. Super.Ct.App.Div. 1997) 
    688 A.2d 1088
    , 1092 [accord]; Frank v. MSI
    Construction Managers, Inc. (Mich.Ct.App. 1995) 
    527 N.W.2d 79
    , 81 [accord]; Dillard
    v. Shaughnessy, Fickel and Scott Architects (Mo.App. 1994) 
    884 S.W.2d 722
    , 724-725
    [accord]; Brown v. Boyer-Washington Blvd. Associates (Utah 1993) 
    856 P.2d 352
    , 354-
    355 [accord].)
    Bayside argues that all of these cases are inapplicable because the “to the extent”
    language in the various indemnity provisions applied to the extent of the indemnitor’s
    obligations and not to the extent of the indemnitee’s right to obtain indemnification. This
    is a distinction without a difference. The provision here states that Oltmans is entitled to
    indemnification from all liability arising out of the scope of Bayside’s work “except to
    the extent” the liability arises out of Oltmans’ active negligence or willful misconduct.
    The meaning of “to the extent” is no less clear in one instance than the other. In both
    instances the phrase is a qualification, either of the extent of the indemnitor’s obligation
    or the extent of the indemnitee’s entitlement. In both cases the apparent intent is to
    apportion liability as between the indemnitor and the indemnitee based on the
    proportionate—or comparative—fault of the parties.
    That this is the meaning of the qualification is made clearer still by the final
    qualification included in the same sentence of the indemnity provision: “or to the extent
    such obligation is inconsistent with the provisions of California Civil Code [section]
    2782.05.” Subparagraph (a) of section 2782.05 provides, with inapplicable exceptions,
    that “provisions . . . affecting any construction contract and amendments thereto entered
    on or after January 1, 2013 that purport to insure or indemnify . . . a general contractor
    . . . by a subcontractor against liability for claims of death or bodily injury to persons . . .
    are void and unenforceable to the extent the claims arise out of, pertain to, or relate to the
    active negligence or willful misconduct of that general contractor . . . .” Prior to the
    adoption of this section in 2011, section 2782, subdivision (a) had already rendered void
    11
    and unenforceable a provision in a construction contract providing indemnity to one
    whose “sole negligence or willful misconduct” caused an injury giving rise to liability.
    The purpose of the new provision added in 2011 was to apportion liability on an
    equitable basis in proportion to the fault of the various parties. According to one of the
    proponents of the legislation, reflected in the Assembly committee report on the bill,
    “This measure would require the commercial construction industry to adopt a fair and
    equitable distribution of liability and that each party, including subcontractors, be held
    responsible for the alleged defects or damage on construction job-sites caused by [their]
    work but not for the alleged defects or damage caused by other parties.” (Assem. Com.
    on Judiciary, Analysis of Sen. Bill No. 474 (2011-2012 Reg. Sess.) June 28, 2011
    [proposed amendment], p 14.) Numerous letters submitted to the Legislature in support of
    the bill emphasized, “SB 474 would simply establish a proportionate, or comparative,
    liability standard which would hold each party responsible for the damage he/she
    caused.” (E.g., Mark D. Brown, Struc Steel, Inc., letter to Assembly Members, June 23,
    2011.) Another submission in support of the measure responded to the argument that the
    bill would “immunize[] a subcontractor from any liability for his/her own acts on a
    project” by pointing out that was “not true” and that “S.B. 474 has subcontractor
    indemnity obligations to [the] extent they are liable.” (Skip Daum, Capitol
    Communications Group, Floor Alert, May 23, 2011.) Still another letter stated, “SB 474
    . . . requires a system where a subcontractor is only on the hook for the percentage of
    fault or negligence that they are found to have committed.” (Ray LeVangie, Jr., United
    Association of Journeymen and Apprentices etc., letter to Senator Leland Yee, May 16,
    2011.) Another floor alert on behalf of numerous construction trade organizations pointed
    out, “SB 474 will restore a comparative fault policy holding ALL contractors and
    subcontractors responsible for their own actions.” (Air Conditioning Sheet Metal
    Association et al., Senate Floor Alert, May 25, 2011.) Section 1 of Senate Bill No. 474,
    which enacted section 2782.05, “finds and declares that it is in the best interests of this
    state and its citizens and consumers to ensure that every construction business in the state
    is responsible for losses that it, as a business, may cause.” (Stats. 2011, ch. 707, § 1.)
    12
    To the extent the negligence of Bayside’s sub-subcontractor contributed to the
    injury of its employee, as Oltmans has alleged, denying Oltmans indemnification for the
    portion of any liability it may occur attributable to that fault would be inconsistent not
    only with the language of the contractual indemnity provision but with the purpose
    behind section 2782.05. In moving for summary judgment Bayside did not offer evidence
    to prove, and did not purport to prove, that Escobar’s injury was caused solely by
    Oltmans’ negligence. Therefore, even assuming that Oltmans’ active negligence was one
    cause of Escobar’s injury, Oltmans may still be entitled to indemnification from Bayside
    for the portion of any liability it occurs attributable to O’Donnell or others. Therefore,
    summary judgment was not properly granted against Oltmans.5
    2. Breach of contractual obligation to obtain insurance
    Paragraph 17(a) of Oltmans’ cross-complaint alleges that Bayside materially
    breached its subcontract by “failing to obtain insurance required by the terms of the
    subcontract[].” Bayside’s special interrogatory No. 19 addressed to Oltmans asked
    Oltmans to state all facts “to support the allegation at par. 17(a) of your cross-complaint,
    that Bayside materially breached its subcontract with you by ‘failing to obtain insurance
    required by the terms of the subcontracts.’ ” In response Oltmans answered, “At the time
    of that allegation, no insurer had yet agreed to defend and indemnify Oltmans without
    reservation.” Yet, in moving for summary judgment, Bayside made no attempt to negate
    the allegation. Its moving papers failed to address the issue entirely. When the issue was
    raised by Oltmans in supplemental papers following the granting of the summary
    judgment in favor of O’Donnell, the trial court correctly noted that Oltmans had not
    addressed the issue in its separate statement in opposition to Bayside’s summary
    5
    Should trial of Escobar’s underlying claim produce an allocation of fault among the
    various parties, the indemnity issue could become academic for the same reasons it did in
    McCrary Construction Co. v. Metal Deck Specialists, 
    Inc., supra
    , 133 Cal.App.4th at
    page 1541. However, there are several possibilities under which the issue could affect
    Oltmans’ right to recover, including an allocation of fault to O’Donnell and a judgment
    against Oltmans for the full amount of Escobar’s economic damages, or a settlement of
    Escobar’s claim without an apportionment of fault.
    13
    judgment motion. But the court was incorrect, as indicated above, that the issue was not
    “specifically pled in Oltmans’ cross-complaint.” In its initial opposition to the summary
    judgment motion Oltmans did not present facts to establish Bayside’s breach in this
    respect, but it was under no obligation to do so. Because Bayside’s moving papers
    included no facts tending to negate Oltmans’ allegation that Bayside had committed such
    a breach, Bayside did not make a prima facie showing that the claim lacks merit and the
    burden did not shift to Oltmans to present evidence supporting its claim. (Code Civ.
    Proc., § 437c, subd. (p)(2); Y.K.A. Industries, Inc. v. Redevelopment Agency of City of
    San Jose (2009) 
    174 Cal. App. 4th 339
    , 366-367; Nazaretyan v. Cal. Physicians’ Service
    (2010) 
    182 Cal. App. 4th 1601
    , 1614.) Summary judgment in favor of Bayside therefore
    also was improper on this ground.
    Disposition
    Subsequent to submission of briefing in this matter, the parties have advised this
    court that a settlement has been reached calling for dismissal of the appeal. Therefore,
    rather than reversing and remanding the matter for further proceedings consistent with
    this opinion, as we would otherwise do in view of our conclusion that summary judgment
    was erroneously granted, we hereby dismiss the appeal pursuant to the stipulation of the
    parties.
    _________________________
    Pollak, J.
    We concur:
    _________________________
    McGuiness, P. J.
    _________________________
    Siggins, J.
    14
    Trial court:                        San Mateo County Superior Court
    Trial judge:                        Honorable Susan Irene Etezadi
    Counsel for cross-complainant and   ARCHER NORRIS
    appellant:                          W. Eric Blumhardt
    ROPERS, MAJESKI, KOHN & BENTLEY, PC
    Susan H. Handelman
    Counsel for cross-defendant and     CHRISTENSEN EHRET LLP
    respondent:                         Jennifer K. Stinnett
    James C. Keowen
    15