Kim v. PCP-Sundance CA4/1 ( 2021 )


Menu:
  • Filed 1/11/21 Kim v. PCP-Sundance CA4/1
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
    or ordered published for purposes of rule 8.1115.
    COURT OF APPEAL, FOURTH APPELLATE DISTRICT
    DIVISION ONE
    STATE OF CALIFORNIA
    YOUNG KIM et al.,                                                    D076510
    D076799
    Plaintiffs and Respondents,
    v.
    (Super. Ct. No. 37-2019-
    PCP-SUNDANCE, LP,                                                    00019492-CU-PA-CTL)
    Defendant and Appellant.
    PCP-SUNDANCE, LP,                                                    D076610
    Plaintiff and Appellant,
    v.                                                          (Super. Ct. No. 37-2019-
    00022741-CU-PA-CTL)
    YOUNG KIM et al.,
    Defendants and Respondents.
    APPEALS from judgments and orders of the Superior Court of San
    Diego County, John S. Meyer, Judge. Affirmed.
    Rudderow Law Group, Daniel T. Rudderow and Chris C. Chapman for
    Plaintiff/Defendant/Appellant PCP-Sundance, LP.
    Simpson Delmore Greene, John A. Simpson and Ross M. Poole for
    Plaintiffs/Defendants/Respondents Young Kim and Hwa Kim.
    INTRODUCTION
    These consolidated appeals by PCP-Sundance, LP (PCP) arise from an
    arbitration PCP initiated against Young Kim and Hwa Kim (together, the
    Kims) under an indemnity agreement the parties entered into in connection
    with a mobile home park the Kims sold to PCP. PCP sought approximately
    $1.75 million in damages, yet recovered only about $3,400 on claims the
    arbitrator found were undisputed. Thus, although PCP obtained a net
    recovery, the arbitrator found the Kims were the prevailing parties and
    awarded them about $78,000 in attorney fees and costs. The arbitrator offset
    PCP’s damages award against the Kims’ fees/costs recovery, and provided for
    only a net recovery to the Kims of about $75,000.
    The Kims filed a petition in the trial court seeking to confirm the
    award. PCP filed a separate petition under a new case number seeking to
    vacate the award on the grounds the arbitrator exceeded his authority (Code
    Civ. Proc., § 1286.2, subd. (a)(4)),1 and that the award was procured by fraud
    and undue means (id., subd. (a)(1)), or in violation of fundamental fairness
    principles. Alternatively, PCP sought to correct the award (§ 1286.6, subd.
    (c)) to eliminate the allegedly improper offset.
    The trial court granted the Kims’ petition and entered judgment in
    their favor in the case they filed, and denied PCP’s petition and entered a
    judgment of dismissal in the case PCP filed. The court thereafter awarded
    the Kims about $30,000 in attorney fees and costs incurred in confirming the
    award, and about $3,000 in interest that accrued on the award between the
    1     Undesignated statutory references are to the Code of Civil Procedure.
    2
    arbitrator’s issuance of it and the court’s entry of judgment (postaward,
    prejudgment interest).2
    PCP appeals the judgments and postjudgment orders.
    PCP raises three challenges arising from the judgments. First, PCP
    challenges the procedure (but purportedly not the underlying factual
    findings) by which the arbitrator determined the Kims were the prevailing
    parties. Second, assuming the trial court properly confirmed the award, PCP
    alternatively contends the court erred by not “correcting” the award to
    eliminate the arbitrator’s offset of PCP’s damages award against the Kims’
    attorney fees/costs award. Third, PCP contends the trial court erred by
    failing to issue a statement of decision explaining its rulings granting the
    Kims’ petition and denying PCP’s.
    PCP raises two challenges to the trial court’s postjudgment orders.
    First, PCP contends the Kims were not entitled to recover postaward,
    prejudgment interest for a variety of procedural and substantive reasons.
    Second, PCP contends the trial court erred by awarding the Kims a “grossly
    excessive” amount of attorney fees and costs incurred in confirming the
    arbitration award.
    For reasons we will explain, we conclude all of PCP’s contentions lack
    merit. Accordingly, we affirm the judgments and postjudgment orders.
    2     The Kims filed duplicative motions for fees/costs/interest in each of the
    superior court cases, which the trial court granted in virtually identical
    minute orders. For readability, we sometimes refer to the duplicative
    motions and orders in the singular form.
    3
    FACTUAL AND PROCEDURAL BACKGROUND
    Background3
    In October 2015, the Kims entered into an agreement to sell to PCP a
    mobile home park in Lemon Grove (the park). The parties used a standard
    form purchase agreement (the PSA).
    PCP is “an investment company specializing in the purchase and
    operation of mobile home parks.” Before the close of escrow, PCP performed
    extensive due diligence on many aspects of the park’s financial and physical
    condition, “including [by] examining voluminous documents concerning rent
    revenue and expenses, . . . walking the property,” and “retain[ing] the
    services of expert consultants.” Because PCP “was a sophisticated
    organization dedicated to the purchase and operation of mobile home parks,”
    it “was or should have been apparent to” PCP that the park “was a lower end
    property of single wide trailers, whose tenants were economically
    challenged.”
    “During the many years [the Kims] owned the park, [they] made
    improvements to the electrical and sewer systems,” undertook reasonable
    security measures, and properly repaired or maintained common area
    facilities.
    “Before the close of escrow on February 17, 2016, during the four-
    month due diligence period, through disclosures and investigation, [PCP]
    became aware that there were several potential problems, which were not
    3      We base our background summary largely on the factual summary in
    the arbitrator’s final arbitration award. Additionally, we note that although
    it appears the arbitration hearing was reported, the appellate record contains
    only about 10 pages of excerpts from partial reporter’s transcripts of the
    three-day hearing that were attached to various materials the parties filed in
    the trial court.
    4
    anticipated in the original sale agreement. PCP requested the Kims to
    reduce the sale price by about $400,000, but they refused. To complete the
    sale, the Kims agreed to provide certain concessions to [PCP] in a Special
    Indemnity Agreement (SIA).”
    “The SIA focused on compensating PCP for problems [it] had identified
    in [its] due diligence. PCP was especially concerned with the costs of
    bringing unlawful detainer lawsuits and other costs related to such lawsuits”
    for “ ‘tenants with past-due balances as of the “Closing” of the PSA.’ ” The
    parties expressly negotiated and agreed that the SIA would not cover lost
    income, lost leasing opportunities, or costs of re-letting.
    The SIA also provided for “indemnity in third party proceedings”
    (capitalization omitted) arising from claims by tenants regarding the
    condition of the park or by the park’s terminated property manager.
    The SIA included an arbitration provision4 and an attorney fees
    provision.5
    4     The arbitration provision states: “ln the event the parties are unable to
    resolve a dispute as provided above, the parties shall immediately thereafter
    submit such dispute to arbitration for binding resolution. The arbitration
    shall be through and according to the rules of the American Arbitration
    Association, commercial arbitration. The arbitrator’s decision shall be final
    and any party thereto may confirm and, if necessary, enforce such award in
    the Superior Court for Orange or San Diego Counties, California.”
    5      The attorney fee provisions states: “ATTORNEYS’ AND EXPERT
    FEES AND COSTS. In the event of any claim or dispute arising out of this
    Agreement, or a breach of any of the covenants, obligations, or indemnities
    contained in this Agreement, the prevailing party in such claim, dispute, or
    breach shall be entitled to have and recover from the losing party, in addition
    to relief obtained, its reasonable attorneys’ and expert fees and costs incurred
    in connection with such dispute, claim or breach, whether incurred in
    connection with litigation or arbitration (but not mediation or conciliation).”
    5
    The Arbitration
    In June 2018, PCP filed a demand for arbitration under the SIA (but
    not the PSA). The parties agreed to arbitrate their dispute according to
    commercial arbitration rules of the American Arbitration Association (AAA).
    Retired judge Ronald Prager served as arbitrator (Arbitrator).
    PCP’s Claims
    PCP sought $1,754,428.50 for breach of the SIA. Some of the items for
    which PCP sought indemnity related to costs incurred evicting six park
    tenants who allegedly were in arrears at the close of escrow. But the vast
    majority related to claims for lost rent and utility payments from tenants;
    advertising expenses; security services; upgrades to the park’s sewer and
    electrical systems because the Kims “fail[ed] to disclose the true condition[s]
    of the . . . system[s]”; and a claimed “overpayment in the purchase price for
    the park” (bolding and underlining omitted).
    On its overpayment claim, PCP sought more than $1.6 million. PCP
    accused the Kims of perpetrating “a massive fraud” by “[lying] about the
    condition and value of [the park],” “conceal[ing] the fact that the park . . . was
    actually plagued with numerous problems and issues,” and “falsely
    represent[ing]” the park’s annual income. PCP maintained it “relied upon
    [the Kims’] representations.”
    Exchange of Proposed Awards
    At an arbitration readiness conference conducted about three weeks
    before the arbitration hearing, the Arbitrator directed the parties to submit
    proposed arbitration awards before the start of the three-day hearing.
    PCP timely submitted its proposed award, reiterating its claim for
    approximately $1.75 million in damages.
    6
    The Kims submitted their proposed award one day late, without
    objection from PCP. The Kims’ proposed award conceded PCP was entitled to
    recover $3,396.25 in eviction-related expenses for three of the six park
    tenants whom PCP alleged were in arrears at the close of escrow. The Kims’
    proposed award rejected the remainder of PCP’s claims.
    Hearing and Awards
    The arbitration hearing was held on January 7-9, 2019.
    About one week after the hearing concluded, the Arbitrator issued an
    Interim Arbitration Award (the Interim Award) awarding PCP $3,396.25 in
    damages for expenses incurred evicting the three park tenants the Kims had
    acknowledged were in arrears at the close of escrow. The Arbitrator found
    PCP’s remaining claims were “not within the scope of the SIA . . . because the
    Kims did not cause the charges to be incurred, or because there was no
    evidence that [the] claims are supported by any evidence.”
    After receiving further briefing, the Arbitrator determined the Kims
    were the prevailing parties for purposes of awarding attorney fees and costs.
    The Arbitrator explained in his Final Arbitration Award (the Final Award)
    that because the Kims conceded PCP was entitled to recover the $3,396.25 it
    received as damages (out of the $1.75 million it requested), the Kims had
    prevailed on all the disputed issues, which the Arbitrator reiterated were “not
    within the scope of the SIA . . . .” The Arbitrator awarded the Kims
    $78,236.43 in attorney fees and costs.
    In the Final Award, the Arbitrator offset the $3,396.25 in damages the
    Kims owed to PCP against the $78,236.43 in attorney fees and costs PCP
    owed to the Kims, for a net recovery to the Kims of $74,840.18.
    7
    Trial Court Proceedings
    Petitions to Confirm and Vacate/Correct
    About three weeks after the Arbitrator issued the Final Award, the
    Kims filed a petition in the superior court seeking to confirm it. About two
    weeks after that, PCP filed a response to the Kims’ petition, and filed a
    separate petition (under a new case number) seeking to vacate or correct the
    Final Award. The trial court consolidated the cases, along with a separate
    lawsuit PCP had since filed against the Kims alleging fraud and contract
    claims under the PSA (but not the SIA).6
    PCP argued the court should vacate, rather than confirm, the Final
    Award because the Arbitrator erred by relying on the Kims’ untimely
    proposed award to determine they were the prevailing parties. Alternatively,
    if the court elected to confirm the award, PCP argued the court should correct
    it because the Arbitrator improperly offset the parties’ recoveries and
    awarded the Kims a net recovery. PCP requested that the trial court issue a
    statement of decision.
    After hearing argument, the trial court granted the Kims’ petition and
    denied PCP’s. The court explained its ruling in a three-page minute order.
    The court thereafter entered separate judgments confirming the Final
    Award, and dismissing PCP’s petition to vacate it.
    Postjudgment Proceedings
    The Kims then moved to recover attorney fees ($32,918.50) and costs
    ($2,120.51) incurred in confirming the Final Award; and postaward,
    6     The appellate record contains many duplicative materials filed in the
    separate superior court cases. Except when necessary for clarity, we do not
    distinguish between the separate cases.
    8
    prejudgment interest ($2,890.50) for the period between issuance of the Final
    Award and entry of judgment. PCP opposed the motion.
    After receiving extensive briefing and hearing argument, the trial court
    awarded the Kims $28,086 in attorney fees and $2,069.36 in costs (both
    slightly less than requested); and $2,890.50 in postaward, prejudgment
    interest.
    Appeals
    PCP appeals (1) the judgment confirming the Final Award (appeal No.
    D076510); (2) the judgment dismissing PCP’s petition to vacate or correct the
    award (appeal No. D076610); and (3) the postjudgment orders awarding the
    Kims attorney fees, costs, and prejudgment interest (appeal Nos. D076799
    and D076610). We consolidated the appeals.
    DISCUSSION
    I. CHALLENGES TO THE JUDGMENTS
    PCP raises three challenges arising from the judgments: (1) the trial
    court erred by confirming, rather than vacating, the Final Award;
    (2) alternatively, the trial court erred by failing to correct the Final Award to
    eliminate the offset of PCP’s damages against the Kims’ attorney fees and
    costs; and (3) the trial court erred by failing to issue a statement of decision.
    We explain, in turn, why each of these contentions is without merit.
    A. Confirming, Rather Than Vacating, the Final Award
    PCP contends the trial court erred in confirming the Final Award
    because the Arbitrator exceeded his authority by relying on the Kims’
    untimely proposed award to determine they were the prevailing parties,
    which further caused the award to be procured by fraud or undue means.
    PCP further maintains the Arbitrator erred by applying a fraud analysis to
    breach of contract claims.
    9
    1. Background
    At the arbitration readiness conference, the Arbitrator directed the
    parties to submit proposed arbitration awards as follows:
    “By the commencement of the arbitration, each side is to
    prepare a proposed arbitration award, analogous to a
    proposed statement of decision in a court trial.”
    On the first morning of the hearing, PCP submitted its proposed award.
    When the Arbitrator asked the Kims’ counsel where his proposed award was,
    counsel responded, “We’ll have it by the end of today.” The Arbitrator
    responded, “Okay.” PCP did not object.
    Counsel proceeded to give opening statements. According to
    declarations the Kims’ counsel later submitted to the trial court (to which
    PCP did not object), the Kims’ counsel conceded during his opening statement
    “that the Kims did not dispute” that “PCP was entitled to reimbursement
    from the Kims” for expenses associated with the eviction of three specific
    park tenants who were in arrears at the close of escrow.
    On the second morning of the hearing, the Kims’ counsel personally
    served a proposed award on the Arbitrator and PCP’s counsel. PCP did not
    object that the proposed award was untimely.
    In their proposed award, the Kims conceded PCP was entitled to
    recover $3,396.25 in damages for expenses associated with evicting three
    tenants who were in arrears at the close of escrow. The proposed award also
    stated that “[b]ecause PCP . . . is awarded less than what it claimed against
    [the Kims], . . . [the Kims] are the prevailing party” entitled to attorney fees
    and costs under the SIA.
    On the final day of the hearing, the Arbitrator asked the Kims’ counsel
    how the Kims could be deemed the prevailing party if they had conceded they
    “owe some money.” Counsel responded that “the prevailing party issue has to
    10
    be resolved post-award,” but also observed preliminarily that the Kims could
    be deemed the prevailing party because PCP was “seeking . . . $1.7 million”
    but recovered only “$3,200,” which “cannot be, under any analysis, evaluated
    as a prevailing party.”
    About one week after the hearing concluded, the Arbitrator issued his
    Interim Award awarding PCP $3,396.25 in eviction-related expenses for the
    three tenants the Kims had acknowledged were in arrears at the close of
    escrow. The Interim Award did not reference the Kims’ proposed award.
    Each side thereafter submitted a motion asking the Arbitrator to
    declare it the prevailing party and to award it attorney fees and costs. In its
    motion, PCP argued it was the prevailing party because it obtained a
    recovery of $3,396.25, while the Kims recovered nothing. In their motion, the
    Kims argued they were the prevailing party because PCP sought $1.75
    million in damages on 29 claims, yet recovered only $3,396.25 on only a
    portion of those claims, which the Kims conceded “[f]rom the inception of
    arbitration.”
    The Arbitrator explained in the Final Award why he agreed the Kims
    were the prevailing parties:
    “In this case PCP made 29 claims totaling $1,754,428.50.
    At the arbitration, the Kims conceded claims relating to
    eviction costs for three tenants in arrears at the close of
    escrow totaling $3,396.25. However, the arbitrator decided
    all contested issues in favor of the Kims and against
    PCP. . . . Because the Kims prevailed on all the issues
    actually litigated at trial, even though the judgment of
    $3,396.25 is in favor of PCP, the Kims are entitled to
    attorney fees and expert witness costs under the terms of
    the [SIA].”
    The Final Award did not reference the Kims’ proposed award.
    11
    2. Legal Principles
    Through the California Arbitration Act (§ 1280 et seq.), the Legislature
    has expressed a “ ‘strong public policy in favor of arbitration as a speedy and
    relatively inexpensive means of dispute resolution.’ ” (Moncharsh v. Heily &
    Blase (1992) 
    3 Cal.4th 1
    , 9 (Moncharsh).) “To promote this alternative means
    of dispute resolution, the law minimizes judicial intervention in the
    proceedings, in part, by the doctrine of arbitral finality.” (Jones v.
    Humanscale Corp. (2005) 
    130 Cal.App.4th 401
    , 407.)
    “Most legal errors in arbitration are not reviewable. [Citations.]”
    (Heimlich v. Shivji (2019) 
    7 Cal.5th 350
    , 367 (Heimlich).) “[B]oth because it
    vindicates the intentions of the parties that the award be final, and because
    an arbitrator is not ordinarily constrained to decide according to the rule of
    law, it is the general rule that, ‘The merits of the controversy between the
    parties are not subject to judicial review.’ [Citations.] More specifically,
    courts will not review the validity of the arbitrator’s reasoning. [Citations.]
    Further, a court may not review the sufficiency of the evidence supporting an
    arbitrator’s award. [Citations.]” (Moncharsh, supra, 3 Cal.4th at p. 11.)
    Section 1286.2, “which sets forth grounds for vacating an arbitration
    award, is an exception to the general rule precluding judicial review.” (SWAB
    Financial, LLC v. E*Trade Securities, LLC (2007) 
    150 Cal.App.4th 1181
    ,
    1196 (SWAB).) As relevant here, this statute authorizes a court to vacate an
    arbitral award when “[t]he award was procured by corruption, fraud or other
    undue means” (§ 1286.2, subd.(a)(1)), or when “[t]he arbitrators exceeded
    their powers and the award cannot be corrected without affecting the merits
    of the decision” (id., subd. (a)(4)).
    A court may also vacate an arbitral award if there are “similar
    ‘circumstances involving serious problems with the award itself, or with the
    12
    fairness of the arbitration process.’ [Citations.] Otherwise, judicial
    corrections are limited to remedying ‘obvious and easily correctable
    mistake[s],’ ‘technical problem[s],’ and actions in excess of authority so long
    as the correction leaves the merits of the decision unaffected.” (Heimlich,
    supra, 7 Cal.5th at p. 367; see Moncharsh, 
    supra,
     3 Cal.4th at pp. 11-13, 33.)
    We generally review de novo a trial court’s ruling confirming an
    arbitration award. (Richey v. AutoNation, Inc. (2015) 
    60 Cal.4th 909
    , 918,
    fn. 1 (Richey).) “However, we apply the substantial evidence test to the trial
    court’s ruling to the extent it rests upon a determination of disputed factual
    issues.” (SWAB, supra, 150 Cal.App.4th at p. 1196.)
    3. Analysis
    We conclude the Arbitrator did not exceed his authority by relying on
    the Kims’ untimely proposed award to determine they were the prevailing
    parties, nor did doing so constitute fraud or undue means.
    We begin by clarifying the scope of PCP’s challenge. PCP makes clear
    in its briefing that it does not challenge the Arbitrator’s rationale in
    concluding that if the Kims truly conceded PCP was entitled to recover all the
    damages it was ultimately awarded, then the Kims were the prevailing
    parties because they prevailed on all the disputed claims. Indeed, such a
    challenge would fail because “[a]n arbitrator’s legal or factual error in
    determining which party prevailed may not be reversed.” (Heimlich, supra,
    7 Cal.5th at p. 367.) Instead, PCP challenges only “the means by which the
    [A]rbitrator” made that determination: by “improperly rel[ying] upon an
    untimely filed proposed arbitration award from the [Kims] as the sole basis to
    improperly find that the damages awarded . . . to PCP were never
    contested . . . .”
    13
    So clarified, PCP’s challenge fails at the outset because the record does
    not support PCP’s underlying factual predicate that the Arbitrator, in fact,
    relied on the Kims’ untimely proposed award “as the sole basis for the finding
    that [they] were a prevailing party.” First, the Arbitrator did not cite or
    reference the Kims’ proposed award anywhere in the Interim or Final
    Awards. Rather, the Final Award merely states: “At the arbitration, the
    Kims conceded claims . . . totaling $3,396.25.” (Italics added.) Second, the
    record shows that the Kims’ counsel stated during his opening statement
    “that the Kims did not dispute” that “PCP was entitled to reimbursement
    from the Kims” for expenses associated with the eviction of three specific
    park tenants who were in arrears at the close of escrow. Similarly, the record
    shows the Kims’ counsel again conceded during closing arguments “that the
    Kims are conceding that they owe PCP some money.”
    PCP argues that some excerpts from the reporter’s transcript of the
    closing arguments indicate the Kims only conditionally conceded certain
    damages depending on how the Arbitrator might ultimately construe the SIA.
    To the extent PCP is challenging the Arbitrator’s factual determination that
    the Kims truly conceded the damages “[a]t the arbitration,” the challenge
    fails. (Moncharsh, 
    supra,
     3 Cal.4th at p. 11 [“a court may not review the
    sufficiency of the evidence supporting an arbitrator’s award”].) And, in any
    event, because PCP has provided us with only 10 pages of partial reporter’s
    transcripts from a three-day hearing, PCP has not met its burden as the
    “appellant to demonstrate, on the basis of the record presented to the appellate
    court, that the trial court committed an error that justifies reversal.”
    (Jameson v. Desta (2018) 
    5 Cal.5th 594
    , 609, italics added.)
    Thus, PCP’s claim fails as a factual matter. But even if it did not, it
    would fail on its legal merits.
    14
    An arbitrator exceeds his authority when he violates “ ‘specific
    restrictions’ ” in “ ‘the rules of arbitration.’ ” (Emerald Aero, LLC v. Kaplan
    (2017) 
    9 Cal.App.5th 1125
    , 1140 (Emerald Aero); see Advanced Micro Devices,
    Inc. v. Intel Corp. (1994) 
    9 Cal.4th 362
    , 367 (Advanced Micro Devices).) The
    parties agreed their arbitration would be governed by the AAA’s commercial
    rules. Yet, PCP has not identified any specific AAA rule the Arbitrator
    violated by accepting the Kims’ untimely proposed award.
    The only AAA rule PCP cites is commercial arbitration rule R-23, which
    states:
    “The arbitrator may issue any orders necessary to enforce
    the provisions of Rule R-21 [Preliminary Management
    Hearing with the Arbitrator] and R-22 [Exchange of
    Information between the Parties] and to otherwise achieve
    a fair, efficient, and economical resolution of the case,
    including, but not limited to: [¶] . . . [¶]
    “(d) in the case of willful non-compliance with any order
    issued by the arbitrator, drawing adverse inferences,
    excluding evidence and other submissions, and/or making
    special allocations of costs or an interim award of costs
    arising from such non-compliance . . . .” (Italics added.)
    PCP contends this rule “require[d]” the Arbitrator to enforce his
    deadline. (Italics added.) But the rule states that an arbitrator may issue
    orders to enforce compliance with other rules, not that the arbitrator shall or
    must do so. “ ‘Ordinarily, when a statute provides a court “may” do
    something, the statute is permissive, not mandatory, and grants the court a
    discretionary authority.’ ” (Lo v. Lee (2018) 
    24 Cal.App.5th 1065
    , 1071-1072.)
    We thus decline to read AAA’s rule R-23 as requiring an arbitrator to enforce
    compliance with all deadlines. Rather, under the traditional approach,
    arbitrators generally “have discretion to extend deadlines given their ‘wide
    latitude’ to conduct arbitrations.” (Chelmowski v. AT&T Mobility, LLC (N.D.
    15
    Ill., July 28, 2016, No. 15 C 10980) 
    2016 WL 8202738
    , at *4; see Sy First
    Family Ltd. Partnership v. Cheung (1999) 
    70 Cal.App.4th 1334
    , 1342
    [“Unless the parties otherwise agree, the rules of evidence and judicial
    procedure do not apply” in arbitration]; § 1282.2, subd. (d).)
    The cases PCP cites to support its contention that the Arbitrator
    exceeded his authority are distinguishable because they either did not involve
    violation of an arbitration rule at all (see Pacific Crown Distributors v.
    Brotherhood of Teamsters (1986) 
    183 Cal.App.3d 1138
    , 1146 (Pacific Crown);
    Baker Marquart LLP v. Kantor (2018) 
    22 Cal.App.5th 729
    , 732, 737 (Baker
    Marquart)), or involved violation of a specific nondiscretionary arbitration
    rule (see Emerald Aero, supra, 9 Cal.App.5th at p. 1140 [allowing last-minute
    addition of substantial punitive damages claim violated specific AAA rules
    that “require a party to specify in his or her initial filing ‘the relief sought and
    the amount involved,’ and require the parties to provide written notice of any
    changes to this claim information,” italics added]). Indeed, Emerald Aero is
    particularly instructive because the AAA rules at issue there used the
    mandatory words “must” and “shall” (Emerald Aero, at pp. 1140-1141, italics
    added),7 whereas the rule PCP cites here (rule R-23) uses the permissive
    “may.”
    PCP maintains the Arbitrator also exceeded his authority by applying a
    fraud analysis to PCP’s contract claim. PCP bases this assertion on the
    7     Emerald Aero quoted AAA rule R-6(a), which states, “Written notice of
    [a] change of claim amount must be provided to the AAA and all parties”; and
    AAA rule R-6(b), which states that “Any new or different claim or
    counterclaim . . . shall be made in writing and filed with the AAA, and a copy
    shall be provided to the other party, who shall have a period of 14 calendar
    days . . . to file an answer . . . .” (Emerald Aero, supra, 9 Cal.App.5th at
    pp. 1140-1141, italics added.)
    16
    following two-line passage from the seven-page Final Award: “It was or
    should have been apparent to [PCP], that [the park] was a lower end property
    of single wide trailers, whose tenants were economically challenged.” This
    single, out-of-context snippet from the “[b]ackground” section of the Final
    Award falls flat for several reasons. First, we generally do not review an
    arbitrator’s legal reasoning, even “where an error of law appears on the face
    of the award.” (Moncharsh, 
    supra,
     3 Cal.4th at p. 28.) Second, the Arbitrator
    made clear in the “[a]nalysis” section of the Final Award that he was
    applying a contract analysis, explaining the disputed claims “are denied
    because they are not within the scope of the SIA” (italics added). PCP even
    acknowledges in its reply brief that “[t]he arbitrator stated in the final award
    it was ruling on the SIA, not fraud.” Finally, the Arbitrator’s fleeting
    reference to what PCP “was or should have been aware of” is understandable
    in light of PCP’s extensive references to fraud concepts—that the Kims
    perpetrated “a massive fraud” by “conceal[ing]” and “falsely represent[ing]”
    things that PCP “relied upon”—in its own submissions to the Arbitrator.
    Turning to PCP’s claim that the Arbitrator’s alleged reliance on the
    Kims’ untimely proposed award constituted extrinsic fraud, undue means, or
    violated fundamental fairness principles, PCP again misplaces its reliance on
    Pacific Crown, Baker Marquart, and Emerald Aero.
    The Pacific Crown court upheld the trial court’s finding of extrinsic
    fraud based on a party’s submission of a post-hearing brief that introduced a
    new issue on which the arbitrator ultimately ruled in that party’s favor.
    (Pacific Crown, supra, 183 Cal.App.3d at p. 1146.) This required vacatur of
    the arbitrator’s award because the post-hearing submission deprived the
    opposing party the “ ‘opportunity to present evidence in [the] arbitration’ ” to
    confront the new claim. (Id. at p. 1149.)
    17
    And the Baker Marquart court held that an arbitration award was
    obtained by undue means where the arbitration panel ruled in favor of the
    claimant by relying on information contained in the claimant’s “ex parte
    ‘confidential arbitration brief’ that [the claimant] did not provide or otherwise
    reveal to [the respondent]” (Baker Marquart, supra, 22 Cal.App.5th at p. 732)
    until after the arbitration panel ruled in favor of the claimant and the
    claimant was seeking to confirm the award in court (id. at p. 737). This
    required vacatur of the arbitration award because the opposing party had “no
    true opportunity to respond [during the arbitration] to the new claims raised
    in the confidential brief.” (Id. at p. 740.)
    But unlike the aggrieved parties in Pacific Crown and Baker Marquart,
    PCP was not deprived of the opportunity to address new evidence or
    arguments during the arbitration. The Kims served their proposed award on
    PCP before the start of the second day of a three-day hearing. This afforded
    PCP two days’ worth of opportunities to rebut with evidence or argument any
    new claims or theories the Kims introduced in their proposed award (e.g., by
    objecting during the hearing if the Kims appeared to dispute damages they
    purported to concede in their proposed award). Yet, PCP never objected,
    thereby waiving the Kims’ noncompliance with the Arbitrator’s deadline.
    (See Hotels Nevada, LLC v. L.A. Pacific Center, Inc. (2012) 
    203 Cal.App.4th 336
    , 353 [waiver principles apply in arbitration proceedings]; AAA
    commercial arbitration rule R-41 [“Any party who proceeds with the
    arbitration after knowledge that any provision or requirement of these rules
    has not been complied with and who fails to state an objection in writing
    shall be deemed to have waived the right to object.”].)
    PCP suggests it was excused from objecting when the Kims submitted
    their proposed award because PCP did not appreciate its significance until
    18
    the Arbitrator allegedly relied on it in rendering the Final Award. But PCP
    cites no legal authority to support this proposition. (See San Diegans for
    Open Government v. San Diego State University Research Foundation (2017)
    
    13 Cal.App.5th 76
    , 106, fn. 17 [“ ‘ “[the] appellant must present meaningful
    legal analysis supported by citations to authority,” ’ ” italics added].)
    Moreover, PCP’s premise is factually dubious because the Kims’ proposed
    award expressly revealed its significance by stating the following: “Because
    PCP . . . is awarded less than what it claimed against [the Kims], the
    [Arbitrator] finds that [the Kims] are the prevailing party . . . entitled to
    recover its attorney’s fees and costs . . . .”
    Additionally, the fundamental fairness principles our court discussed in
    Emerald Aero are not implicated here. (Emerald Aero, supra, 9 Cal.App.5th
    at p. 1143.) The claimants in Emerald Aero initially sought $1 million in
    damages in their arbitration claim summary (id. at p. 1132), but increased
    their demand on the literal eve of the hearing (at 4:38 p.m., no less) to seek
    more than $10 million in compensatory damages and punitive damages of “a
    ‘multiplier of three (3x) the actual damages’ ” (id. at p. 1135). The arbitrator
    ultimately awarded the claimants more than $30 million in damages. (Id. at
    p. 1135.) The trial court confirmed this award, finding that the notice served
    the afternoon before the hearing was sufficient. (Id. at p. 1137.)
    Our court reversed. (Emerald Aero, supra, 9 Cal.App.5th at p. 1146.)
    Beyond the violation of specific, nondiscretionary AAA rules discussed above,
    our court found the claimants did not provide sufficient notice “under
    fundamental fairness principles.” (Id. at p. 1141.) “First, in addition to the
    lack of notice of the punitive damages claim, the record [was] unclear
    whether [the respondent] had notice of several . . . critical hearings and
    orders in the case” that ultimately led to his default. (Id. at p. 1143.)
    19
    “Second, there was substantial ambiguity as to the amount of claimed
    compensatory damages” because the claimants initially sought $1 million in
    their arbitration claim summary, but $10 million in their damages brief.
    (Ibid.) Third, we found the AAA acted improperly by denying the respondent
    the opportunity to seek post-hearing relief from a new arbitrator (ibid.) after
    the previous arbitrator recused himself post-hearing from all AAA matters
    (id. at p. 1136). Finally, our court observed that “the amount of the damages
    award—approximately $30 million—warrant[ed] particular attention.” (Id.
    at p. 1144.)
    These fairness principles simply are not implicated here. The Kims did
    not drastically increase the amount of a claim at the virtual last minute. To
    the contrary, they conceded PCP was entitled to recover a precise amount of
    damages on specific claims. There was no dispute that PCP received actual
    notice of the Kims’ concession, which their counsel personally served on PCP
    during the hearing. There were no administrative issues on AAA’s behalf
    that precluded PCP from addressing the Kims’ concession with the
    Arbitrator. Finally, the amounts of the conceded damages ($3,396.25) and
    the attorney fees/costs award ($78,236.43) simply are not of the magnitude
    that “warrant[ed] particular attention” in Emerald Aero. (Emerald Aero,
    supra, 9 Cal.App.5th at p. 1144.)
    In sum, based on the limited grounds available for judicial review of
    final arbitration awards, PCP has not shown that the trial court erred in
    confirming the Final Award.
    B. Correcting the Final Award to Eliminate the Offset
    PCP alternatively contends the trial court erred by failing to “correct”
    the Final Award because the Arbitrator’s offset of PCP’s damage award
    against the Kims’ attorney fees and costs award is a correctible
    20
    “imperfect[ion] in a matter of form, not affecting the merits of the
    controversy.” (§ 1286.6, subd. (c).) We disagree.
    Parties to an arbitration agreement “have bargained for the relatively
    free exercise” of the arbitrator’s “flexibility, creativity and sense of fairness”
    in choosing a remedy. (Advanced Micro Devices, 
    supra,
     9 Cal.4th at p. 374.)
    Thus, “unless specifically restricted by the agreement to following legal
    rules,” arbitrators “ ‘are not bound to award on principles of dry law, but may
    decide on principles of equity and good conscience’ ” (id. at pp. 374-375),
    including by “grant[ing] equitable relief that a Court could not” (id. at p. 389).
    Nothing prohibited the Arbitrator from offsetting the parties’
    competing recoveries. First, the SIA’s arbitration provision did not limit the
    Arbitrator’s authority in this respect. (See fn. 4, ante.) Second, offsetting
    competing recoveries is a recognized equitable concept. (See Wade v.
    Schrader (2008) 
    168 Cal.App.4th 1039
    , 1048 [“At common law, a setoff is
    based upon the equitable principle that parties to a transaction involving
    mutual debts and credits can strike a balance between them.”]; Jhaveri v.
    Teitelbaum (2009) 
    176 Cal.App.4th 740
    , 753 [“The right of offset rests upon
    the inherent power of the court to do justice to parties appearing before it.”].)
    Finally, the AAA’s commercial rules authorize arbitrators to “ ‘grant any
    remedy or relief that the arbitrator deems just and equitable and within the
    scope of the agreement.’ ” (Cohen v. TNP 2008 Participating Notes Program,
    LLC (2019) 
    31 Cal.App.5th 840
    , 871 (Cohen).)
    PCP misplaces its reliance on Jess v. Herrmann (1979) 
    26 Cal.3d 131
    ,
    143 (Jess) to support the proposition that offset is available only when
    expressly authorized by statute or consented to by the parties. The Jess court
    recognized the general availability of offset as an efficient means to “ ‘simply
    eliminate[ ] a superfluous exchange of money between the parties.’ ” (Id. at
    21
    p. 137.) But recognizing the remedy has its roots in equity (id. at pp. 142-
    143), the court created an equitable exception limiting the remedy’s
    availability in negligence cases involving comparative fault apportioned
    between adequately insured parties (id. at pp. 141-142). Those equitable
    concerns simply are not present here.
    C. Statement of Decision
    PCP asserts the judgments must be reversed because the court refused
    to provide a statement of decision under section 1291.8 We need not weigh in
    on the split of authorities regarding whether the trial court was required to
    issue one in this context,9 because the court stated its minute order would
    constitute a statement of decision, and we conclude the comprehensive
    minute order adequately explained the legal and factual bases for the court’s
    determination as to each principal controverted issue.
    1. Background
    When PCP opposed the Kims’ petition to confirm the Final Award and
    filed a petition of its own seeking to vacate or correct it, PCP also filed a
    request for a statement of decision addressing the following questions:
    “(1) Should the arbitration award be vacated . . . ?
    “(2) Did the arbitrator prejudice PCP by allowing [the
    Kims] to submit an untimely proposed arbitration award
    contrary to the [arbitration readiness conference order]?
    8      Section 1291 states: “A statement of decision shall be made by the
    court, if requested pursuant to Section 632, whenever an order or judgment,
    except a special order after final judgment, is made that is appealable under
    this title.”
    9     Compare Metis Development LLC v. Bohacek (2011) 
    200 Cal.App.4th 679
    , 687 (Metis) (statement of decision required) with Rebmann v. Rohde
    (2011) 
    196 Cal.App.4th 1283
    , 1294 (statement of decision not required).
    22
    “(3) Did the arbitrator prejudice PCP when stating in the
    final award that the Kims conceded the $3,396.25 at the
    arbitration?
    “(4) As a result of this prejudice, did the arbitrator further
    prejudice PCP by finding that [the] Kims were a prevailing
    party even though the $3,396.25 was in fact disputed by
    [the Kims] throughout all three days of the arbitration as
    evidenced by the transcript of proceedings?
    “(5) Is there a defect in the form of the award by the offset
    applied by the arbitrator?”
    The day before the hearing on the petitions, the trial court issued a
    three-page tentative ruling explaining why the court intended to grant the
    Kims’ petition and deny PCP’s. First, the court explained the Arbitrator did
    not exceed his authority by receiving the Kims’ untimely proposed award
    because PCP failed to identify any AAA rule that the Arbitrator violated.
    Second, the court explained that the extrinsic fraud and undue means at
    issue in Pacific Crown, supra, 
    183 Cal.App.3d 1138
     and Baker Marquart,
    supra, 
    22 Cal.App.5th 729
     were not implicated here. Third, the court rejected
    PCP’s factual premise “that the Final Award made reference to the Kims’
    proposed arbitration award as the basis for determining the Kims were the
    prevailing party.” Fourth, the court rejected PCP’s claim it was prejudiced by
    the Kims’ untimely proposed award because (1) “PCP had the opportunity to
    object when the Kims submitted the proposed arbitration award . . . , but did
    not”; and (2) “PCP had the opportunity to object to the Kims' argument that
    they are the prevailing party based in part on the fact that they conceded the
    claims which form the basis for the award,” which “was raised during the
    arbitration and in the motion for attorney fees.” Finally, the court denied
    PCP’s alternative request to correct the Final Award, finding Jess, supra, 
    26 Cal.3d 131
     distinguishable.
    23
    After hearing argument, the trial court indicated its tentative ruling
    would become the order of the court. PCP’s counsel reminded the court that
    PCP had requested a statement of decision. The court responded that it did
    not believe it was required to provide one because there had not been a trial,
    but, in any event, the court stated its tentative ruling (later confirmed in a
    minute order) “will be the statement of decision . . . .” (Italics added.)
    2. Legal Principles
    If properly requested and required, a statement of decision must
    “explain[ ] the factual and legal basis for [the trial court's] decision as to each
    of the principal controverted issues at trial.” (§ 632.) A statement of decision
    “will be deemed adequate ‘if it fairly discloses the determinations as to the
    ultimate facts and material issues in the case.’ ” (Altavion, Inc. v. Konica
    Minolta Systems Laboratory, Inc. (2014) 
    226 Cal.App.4th 26
    , 45 (Altavion);
    see Pannu v. Land Rover North America, Inc. (2011) 
    191 Cal.App.4th 1298
    ,
    1314, fn. 12 [“ ‘the trial court is not required to respond point by point to
    issues posed in a request for a statement of decision’ ”].) “ ‘[T]he term
    “ultimate fact” generally refers to a core fact, such as an essential element of
    a claim.’ ” (Metis, supra, 200 Cal.App.4th at p. 689; Muzquiz v. City of
    Emeryville (2000) 
    79 Cal.App.4th 1106
    , 1125 [“ ‘findings of ultimate facts
    necessarily include findings on all intermediate evidentiary facts necessary to
    sustain them. [Citation.]’ ”].) A “material issue” “ ‘is one which is relevant
    and essential to the judgment and closely and directly related to the trial
    court’s determination of the ultimate issues in the case.’ ” (R.E. Folcka
    Construction, Inc. v. Medallion Home Loan Co. (1987) 
    191 Cal.App.3d 50
    , 53.)
    “[A] trial court’s error in failing to issue a requested statement of
    decision is not reversible per se, but is subject to harmless error review.”
    (F.P. v. Monier (2017) 
    3 Cal.5th 1099
    , 1108; see id. at pp. 1114-1115.)
    24
    3. Analysis
    The trial court’s three-page minute order, which the court stated “will
    be the statement of decision,” fulfilled the purposes of a statement of decision
    because it “ ‘fairly disclose[d] the determinations as to the ultimate facts and
    material issues in the case.’ ” (Altavion, supra, 226 Cal.App.4th at p. 45.)
    By explaining why it was granting the Kims’ petition and denying
    PCP’s, the trial court adequately addressed the material issue posed in PCP’s
    request for a statement of decision: whether “the arbitration award [should]
    be vacated.”
    The court also adequately addressed PCP’s subsidiary questions. The
    court explained it rejected PCP’s prejudice claim because “PCP had the
    opportunity to object . . . , but did not,” and PCP ultimately addressed the
    issue in its briefing to the Arbitrator about who was the prevailing party. By
    explaining that the record did not support PCP’s claim that the Kims’
    proposed award was the sole basis for the Arbitrator’s conclusion that the
    Kims had conceded certain damages, the court adequately addressed PCP’s
    queries whether “the arbitrator prejudice[d] PCP when stating in the final
    award that the Kims conceded the $3,396.25 at the arbitration,” and whether
    this “further prejudice[d] PCP by finding that [the] Kims were a prevailing
    party . . . .” Finally, in explaining why Jess is distinguishable, the court
    adequately addressed PCP’s query whether there was “defect in the form of
    the award by the offset applied by the arbitrator.”
    Particularly in light of the limited judicial review to which arbitral
    awards are subject, the trial court’s explanations were sufficient.
    25
    II. CHALLENGES TO POSTJUDGMENT ORDERS
    PCP also appeals the trial court’s postjudgment orders granting the
    Kims’ requests for (1) postaward, prejudgment interest; and (2) attorney fees
    and costs incurred in confirming the Final Award.
    A. Postaward, Prejudgment Interest
    The trial court granted the Kims’ request under Civil Code section
    3287, subdivision (a)10 for $2,890.50 in postaward, prejudgment interest from
    the issuance of the Final Award to the entry of judgment. PCP contends the
    court erred in doing so because (1) the court awarded interest on an
    “unliquidated” sum; (2) the Kims were required to make the request to the
    Arbitrator, not the trial court; (3) their request to the trial court, if allowed,
    was untimely because it was not made before entry of judgment; and (4)
    prejudgment interest cannot be awarded on a recovery of attorney fees and
    costs, but only on “damages.” These contentions are without merit.
    1. Background
    The Kims did not request postaward, prejudgment interest from the
    Arbitrator, and the Arbitrator did not award it. Rather, they first requested
    it from the trial court in their formal response to PCP’s petition to vacate or
    correct the Final Award.
    The trial court did not address the Kims’ request for interest in its
    minute order confirming the Final Award, so the Kims promptly applied ex
    parte for an order shortening time to reconsider the issue. The court declined
    10     Civil Code section 3287, subdivision (a) states in part: “A person who is
    entitled to recover damages certain, or capable of being made certain by
    calculation, and the right to recover which is vested in the person upon a
    particular day, is entitled also to recover interest thereon from that day,
    except when the debtor is prevented by law, or by the act of the creditor from
    paying the debt.”
    26
    the ex parte request, but stated it would consider the issue at a noticed
    hearing on the Kims’ impending motion for attorney fees and costs.
    Before it resolved the fees/costs and interest issues, the trial court
    entered a judgment confirming the Final Award and ordering PCP to pay the
    Kims $74,840.18. The judgment also stated the court would address on a
    specified date the Kims’ impending requests for attorney fees/costs and
    postaward, prejudgment interest.
    The Kims then filed a noticed motion seeking attorney fees, costs, and
    postaward, prejudgment interest. PCP opposed the motion. After hearing
    argument, the trial court granted the Kims’ request for $2,890.50 in
    postaward, prejudgment interest.
    2. Legal Principles
    Civil Code section 3287, which provides for the recovery of prejudgment
    interest on damages awards, applies to arbitration awards. (Tenzera, Inc. v.
    Osterman (2012) 
    205 Cal.App.4th 16
    , 21 (Tenzera).) “The purpose of
    prejudgment interest is to compensate the prevailing party for the loss of
    money during the period before the judgment is entered.” (Ibid.)
    The Kims requested postaward, prejudgment interest under Civil Code
    section 3287, subdivision (a), which provides that a party is entitled as a
    matter of right to “recover prejudgment interest on an amount awarded when
    the damages are certain, or capable of being made certain by calculation, and
    the right to recover those damages is vested” as of a date certain. (Tenzera,
    supra, 205 Cal.App.4th at p. 21.) By contrast, under subdivision (b),
    prejudgment interest is merely discretionary when the award is “based upon
    a cause of action in contract where the claim was unliquidated” (i.e., not for a
    sum certain). (Civ. Code, § 3287, subd. (b).)
    27
    “We review the trial court’s prejudgment interest award for legal
    error.” (Tenzera, supra, 205 Cal.App.4th at p. 21.)
    3. Analysis
    We conclude PCP’s challenges to the trial court’s award of postaward,
    prejudgment interest are without merit.
    First, we reject PCP’s contention that, because the amount of attorney
    fees and costs the Kims incurred in the arbitration was disputed in that
    forum, the sum was unliquidated for purposes of entitling the Kims to
    postaward, prejudgment interest. As soon as the Arbitrator determined the
    Kims were the prevailing parties and awarded them a specified sum in
    attorney fees and costs, that sum became liquidated. (See Pierotti v. Torian
    (2000) 
    81 Cal.App.4th 17
    , 27 (Pierotti) [final arbitration award fixes the
    amount of the claim as of “the date the arbitrator renders his award”];
    Tenzera, supra, 205 Cal.App.4th at p. 22 [claim became “a fixed liability as of
    the date of the final arbitration award”]; SCIE LLC v. XL Reinsurance
    America, Inc. (9th Cir. 2010) 
    397 Fed.Appx. 348
    , 352 [“The award of fees and
    expenses incurred in arbitration was fixed and made certain at the time of
    the arbitration award . . . .”].) The fact PCP sought to vacate or correct the
    award in the trial court does not negate the fact that the amount of the claim
    was liquidated. (Tenzera, supra, 205 Cal.App.4th at p. 22 [damages were
    liquidated as of the date of the final arbitration award even when the award
    was initially vacated by the trial court before being reinstated by the Court of
    Appeal].)
    Thus, because the Final Award fixed the amount of the Kims’ claim,
    they were entitled to postaward, prejudgment interest on it—so long as their
    request was otherwise proper.
    28
    Second, in this vein, we are not persuaded by PCP’s contention that the
    Kims were required to request interest from the Arbitrator instead of the
    trial court. Although parties may contract to grant arbitrators the authority
    to award postaward, prejudgment interest, trial courts may award such
    interest so long as the arbitrator has not already addressed the issue and
    declined to award interest. (See Pierotti, supra, 81 Cal.App.4th at pp. 27-28
    [“in our view, the arbitrator never considered or ruled on the precise issue
    [the appellant] raises here: whether he is entitled to interest under Civil
    Code section 3287, subdivision (a) for the period between the award and the
    time the court entered judgment confirming the award”]; Britz, Inc. v. Alfa-
    Laval Food & Dairy Co. (1995) 
    34 Cal.App.4th 1085
    , 1106 (Britz); Knight et
    al., Cal. Practice Guide: Alternative Dispute Resolution (The Rutter Group
    2020) ¶ 5:435 [“If prejudgment interest is not included in the award, a court
    may add such interest in proceedings to confirm the award.”].)
    The cases PCP cites to support a contrary conclusion are
    distinguishable. Corona v. Amherst Partners (2003) 
    107 Cal.App.4th 701
    involved only attorney fees and costs incurred during the arbitration (not
    interest accruing after it), and thus the issue was reserved exclusively for the
    arbitrator before whom the fees and costs were incurred. (Id. at p. 706.)
    Similarly, in Maaso v. Signer (2012) 
    203 Cal.App.4th 362
     (Maaso), the issues
    of attorney fees, costs, and prejudgment interest (under a different
    prejudgment interest statute for personal injury claims, Civ. Code, § 3291)
    were reserved exclusively for the arbitrator because it required the arbitrator
    to make a discretionary ruling about whether the prevailing party was
    entitled to expert costs, and “ ‘the arbitrator, not the trial court, . . . is best
    situated to determine the amount of reasonable attorney fees and costs to be
    awarded for the conduct of the arbitration proceeding.’ ” (Maaso, at p. 379.)
    29
    Unlike the discretionary determinations about events occurring during
    the arbitrations in Corona and Maas, the trial court here—presented with
    the Final Award liquidating the amount of the Kims’ award—faced only a
    nondiscretionary duty (Civ. Code, § 3287, subd. (a)) to award interest
    accruing after the arbitration was complete. Thus, the Kims could request
    the award from the trial court in the first instance.
    Third, there is no merit to PCP’s contention that the Kims’ request to
    the trial court, if allowed, was untimely under North Oakland Medical Clinic
    v. Rogers (1998) 
    65 Cal.App.4th 824
    , which held that a request for
    prejudgment interest “must be made by way of motion prior to entry of
    judgment, or . . . in the form of a motion for new trial no later than the time
    allowed for filing such a motion.” (Id. at p. 831.) As detailed above, the Kims
    repeatedly requested prejudgment interest before entry of judgment—in their
    response to PCP’s petition and in their ex parte request for an order
    shortening time. Moreover, the judgment expressly acknowledged their
    request was pending.
    Finally, PCP’s assertion that prejudgment interest is unavailable
    because the Kims’ award consists entirely of attorney fees and costs (rather
    than “damages”) misunderstands the nature of a final arbitration award.
    The court in Britz, supra, 
    34 Cal.App.4th 1085
     explained that because an
    “arbitration award itself result[s] in a new and fixed liability,” it is
    tantamount to a contractual “judgment in [the prevailing party]’s favor.” (Id.
    at p. 1107.) And because “it is clear that interest after [a judicial] judgment
    accrues as to the entire award, including attorney fees,” awarding interest on
    an entire “contractual judgment”—including attorney fees—“serve[s] the
    same purpose.” (Id. at p. 1107, italics added.) Indeed, the Britz court
    reasoned that to hold otherwise “would punish [the prevailing party] for
    30
    using arbitration instead of the court system.” (Ibid.) Stated differently,
    prejudgment interest is available on attorney fees contained in an arbitration
    award because, “[a]lthough the interest [is] pre-‘judicial judgment,’ it [is]
    post-‘contractual judgment.’ ” (Ibid., italics added.)
    We find this reasoning persuasive, as have many other courts. (See
    Pierotti, supra, 
    81 Cal.App.4th 17
     at p. 27 [“Britz controls this case.”]; County
    of Solano v. Lionsgate Corp. (2005) 
    126 Cal.App.4th 741
    , 753, fn. 9 [“The
    [prevailing party] was actually entitled to interest on its entire recovery [of
    civil penalties, and attorney fees and costs], not just on the amount of the
    penalties as specified by the arbitrator.”]; ITN Flix, LLC v. Trejo (C.D.Cal.,
    Sept. 30, 2020, No. 220CV01978ODWAGRX) 
    2020 WL 5820978
    , at *4 [“[a]
    prevailing party in arbitration is entitled [under California law] to pre-
    judgment interest on the entire award, including attorneys’ fees,” italics
    added]; Sailfrog Software, Inc. v. Theonramp Group, Inc. (N.D.Cal., Jan. 20,
    1998, No. Civ. 97-7014 MISC SW) 
    1998 WL 30100
    , at *6 [“interest after an
    arbitration award but before a judicial judgment accrues as to the entire
    award, including attorneys’ fees,” italics added].)
    PCP cites Union Pacific Railroad Co. v. Santa Fe Pacific Pipelines, Inc.
    (2014) 
    231 Cal.App.4th 134
     to support the proposition that attorney fees and
    costs do not constitute “damages” on which prejudgment interest may be
    awarded under Civil Code section 3287. (Union Pacific, at p. 202 [observing
    that Civ. Code “section 3281 defines damages as involving unlawful conduct
    by a ‘person in fault’ and [Civ. Code] section 3287 requires damages before
    prejudgment interest may be awarded”].) Regardless of whether that holds
    true in traditional litigation, Union Pacific does not address the particular
    circumstance before us—an arbitral award of contractual attorney fees and
    31
    costs reduced to a “post-‘contractual judgment.’ ” (Britz, supra, 34
    Cal.App.4th at p. 1107.)
    B. Trial Court’s Award of Attorney Fees and Costs
    PCP contends the trial court erred in awarding the Kims the “grossly
    excessive” amount of $30,155.36 in attorney fees and costs incurred in
    confirming the Final Award. (Bolding and capitalization omitted.) We find
    no abuse of discretion.
    1. Background
    After the trial court granted the Kims’ petition to confirm the Final
    Award and denied PCP’s petition to correct or vacate it, the Kims moved for
    an award of attorney fees and costs as the prevailing party in each
    proceeding. The Kims supported their motions with (1) declarations from
    their counsel establishing the amount of work performed and the attorneys’
    billing rates; (2) memoranda of costs; and (3) copies of billing records for the
    pertinent work. The Kims sought $32,918.50 in attorney fees, and $2,120.51
    in costs.
    PCP opposed the Kims’ motions, arguing the Kims’ legal bills showed
    “that most of the fees sought are not only excessive in nature but are actually
    directly related to [PCP’s pending] fraud case.” However, PCP did not
    address any specific billing entries.
    In reply, the Kims’ counsel submitted additional declarations and
    billing records showing that the pending fee request did not include work on
    the fraud case.
    At the hearing, PCP’s counsel argued the Kims’ request was “grossly
    excessive” and “terribly inflated” because “these petition matters are very
    basic and simple.” He argued the Kims’ counsel should have spent only about
    18 hours, not the 140 hours for which they sought to recover fees. When
    32
    pressed by the court, PCP’s counsel acknowledged he provided “no
    breakdown” of specific billing entries to which he objected.
    In a subsequent minute order, the trial court determined the Kims
    were the prevailing parties and awarded them $28,086 in attorney fees and
    $2,069.36 in costs. The court explained it reduced the fee request by
    $4,832.50 because it was unnecessary for two attorneys to have attended the
    hearing on the petitions, and because some of the work on the instant
    motions was excessive. “Otherwise, the Court [found] that the work
    performed and the number of hours expended [were] reasonable and
    necessary.” The court explained it did not further reduce the fee award
    because “PCP fail[ed] to dispute any specific line item(s) presented in
    counsel’s billing invoices” or “identif[y] any amount of time that would be
    appropriately allocated to the fraud case.”
    2. Legal Principles
    The prevailing party in a judicial proceeding to confirm, correct, or
    vacate an arbitration award is entitled to recover attorney fees (when
    authorized by contract) and costs incurred in that proceeding. (§§ 1293.2,
    1033.5, subd. (a)(10(A); Cohen, supra, 31 Cal.App.5th at pp. 877-878.)
    “[T]he fee setting inquiry in California ordinarily begins with the
    ‘lodestar,’ i.e., the number of hours reasonably expended multiplied by the
    reasonable hourly rate.” (PLCM Group, Inc. v. Drexler (2000) 
    22 Cal.4th 1084
    , 1095.) “The lodestar figure may then be adjusted, based on
    consideration of factors specific to the case, in order to fix the fee at the fair
    market value for the legal services provided.” (Ibid.)
    The party seeking fees and costs “ ‘ “bear[s] the burden of establishing
    entitlement to an award and documenting the appropriate hours expended
    and hourly rates.” ’ ” (Roth v. Plikaytis (2017) 
    15 Cal.App.5th 283
    , 290
    33
    (Roth).) “ ‘California courts do not require detailed time records, and trial
    courts have discretion to award fees based on declarations of counsel
    describing the work they have done and the court’s own view of the number of
    hours reasonably spent. [Citations.]’ ” (Syers Properties III, Inc. v. Rankin
    (2014) 
    226 Cal.App.4th 691
    , 698.)
    Once the moving party meets its burden, the burden shifts to the
    opposing party “to present specific objections, supported by rebuttal
    evidence.” (Roos v. Honeywell Internat., Inc. (2015) 
    241 Cal.App.4th 1472
    ,
    1494 (Roos).) “In challenging attorney fees as excessive because too many
    hours of work are claimed, it is the burden of the challenging party to point to
    the specific items challenged, with a sufficient argument and citations to the
    evidence. General arguments that fees claimed are excessive, duplicative, or
    unrelated do not suffice. Failure to raise specific challenges in the trial court
    forfeits the claim on appeal.” (Premier Medical Management Systems, Inc.
    v. California Ins. Guarantee Assn. (2008) 
    163 Cal.App.4th 550
    , 564 (Premier
    Medical); see Gorman v. Tassajara Development Corp. (2009) 
    178 Cal.App.4th 44
    , 101 [“The party opposing the fee award can be expected to
    identify the particular charges it considers objectionable.”]; Raining Data
    Corp. v. Barrenechea (2009) 
    175 Cal.App.4th 1363
    , 1376.)
    “ ‘We review an order granting or denying fees for an abuse of
    discretion. [Citation.] “Because the ‘experienced trial judge is the best judge
    of the value of professional services rendered in his court,’ we will not disturb
    the trial court’s decision unless convinced that it is clearly wrong, meaning
    that it is an abuse of discretion.” ’ ” (Roth, supra, 15 Cal.App.5th at p. 290.)
    C. Analysis
    PCP does not dispute that the Kims were the prevailing party or that
    their counsels’ billing rates were reasonable. Instead, PCP asserts only that
    34
    the trial court abused its discretion by awarding fees for an unreasonable
    number of hours. The court did not abuse its discretion.
    Contrary to PCP’s contention on appeal, the Kims did not “fail[ ] to
    meet their burden” in the trial court. Rather, they supported their motions
    with declarations from counsel and—though not required—extensive billing
    records. Once the Kims produced this evidence, the burden shifted to PCP “to
    present specific objections, supported by rebuttal evidence.” (Roos, supra,
    241 Cal.App.4th at p. 1494.)
    PCP failed to do so. Instead, PCP’s counsel merely offered his view of
    how much time the Kims’ counsel should have spent. And when pressed by
    the trial court, counsel admitted he had “no breakdown” of specific billing
    entries he deemed excessive or that related only to the fraud case. This was
    insufficient to rebut the Kims’ showing. (Premier Medical, supra, 163
    Cal.App.4th at p. 564 [“General arguments that fees claimed are excessive,
    duplicative, or unrelated do not suffice.”].)
    DISPOSITION
    The judgments and postjudgment orders are affirmed.
    HALLER, J.
    WE CONCUR:
    HUFFMAN, Acting P. J.
    GUERRERO, J.
    35
    

Document Info

Docket Number: D076510

Filed Date: 1/11/2021

Precedential Status: Non-Precedential

Modified Date: 1/11/2021