501 East 51st Street etc. v. Kookmin Best Ins. Co., Ltd. ( 2020 )


Menu:
  • Filed 4/2/20; Certified for Publication 4/16/20 (order attached)
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    SECOND APPELLATE DISTRICT
    DIVISION EIGHT
    501 EAST 51ST STREET,                               B293605
    LONG-BEACH-10 LLC,
    (Los Angeles County
    Plaintiff and Appellant,                        Super. Ct. No. NC061176)
    v.
    KOOKMIN BEST INSURANCE
    CO., LTD., et al.,
    Defendants and Respondents.
    APPEAL from a judgment of the Superior Court of Los
    Angeles County, Mark C. Kim, Judge. Affirmed.
    Donahoo & Associates, Richard E. Donahoo; Esner, Chang
    & Boyer, Stuart B. Esner and Holly N. Boyer for Plaintiff and
    Appellant.
    De La Peña & Holiday, Gregory De La Peña and
    K. Anderson Franco for Defendants and Respondents.
    **********
    This is an insurance bad faith lawsuit. Plaintiff 501 East
    51st Street, Long Beach-10 LLC appeals the judgment following
    summary adjudication in favor of defendants Kookmin Best
    Insurance Co., Ltd., doing business as Leading Insurance
    Company, and Leading Insurance Group Insurance Ltd., doing
    business as Leading Insurance Company, on plaintiff’s claim for
    breach of the covenant of good faith and fair dealing relating to
    the parties’ insurance contract. Plaintiff sued after defendants
    denied plaintiff’s claim for damages to its Long Beach apartment
    complex allegedly caused by a ruptured underground water main.
    Experts hired by plaintiff and defendants provided conflicting
    reports on the cause of the damage. We agree with the trial court
    there is no material dispute whether defendants denied the claim
    in good faith based on an expert report concluding the damage
    was not caused by the broken water main, and affirm the
    judgment.
    BACKGROUND
    Plaintiff sued defendants for breach of the covenant of good
    faith and fair dealing, fraud in the inducement, breach of
    contract, estoppel, negligence, negligent misrepresentation, and
    declaratory relief based on defendants’ denial of plaintiff’s
    insurance claim.
    Defendants moved for summary adjudication of plaintiff’s
    claim for breach of the covenant of good faith and fair dealing.
    Defendants argued the “genuine dispute doctrine” provided a
    complete defense to a finding of bad faith. Defendants presented
    evidence the denial of plaintiff’s claim was based on expert
    opinions that the damage to plaintiff’s building was caused by
    long-term settlement and earth movement, which was not a
    2
    covered loss under the policy. The parties do not dispute that
    settlement-related damage was not covered under the policy.
    1.     Facts Supporting the Summary Adjudication Motion
    a.    Plaintiff’s insurance claim and expert report
    The subject property is a 10-unit, two-building apartment
    complex, built in 1963. Plaintiff purchased the property in 2012,
    and defendants first issued a policy insuring the property in
    2013.
    Sometime between December 31, 2015 and January 2,
    2016, an underground water main burst next to the southwest
    side of the building. Plaintiff alleged the “building moved and
    cracked because of the soil movement triggered by the pipe
    failure.”
    Plaintiff presented its claim to defendants on March 8,
    2016, claiming damage to the building caused by the ruptured
    water main. In April 2016, plaintiff provided defendants with a
    report prepared by American Geotechnical, Inc. (AGI). AGI
    performed a “limited geotechnical investigation” of the property
    to “evaluate site conditions relating to the reported building
    distress following a waterline break near the south end of the
    building.” The scope of the evaluation was limited to
    “observation, photo documentation of the site conditions, [and] a
    floor-level survey of the interior of the first level units . . . .” The
    investigation did not involve any subsurface investigation or soil
    testing.
    The report noted cracks in the interior walls and the
    concrete slab floors of units 1 and 4. Regarding the exterior of
    the building, the report noted “significant cracks on the
    foundation stem wall in the south side of the building near the
    reported water leak.” There were also “[n]umerous stucco
    3
    cracks.” The report noted “significant floor deformation,” with
    “downward tilting to the rear as well as to the right and left sides
    of the building. The steepest floor tilt . . . occurs at the left side of
    Unit 1, close to the reported water leak.”
    AGI opined that “existing building distress was
    substantially contributed to by the water main break. The water
    introduced to the soil medium appears to have triggered
    differential foundation movement causing the stress features to
    develop. Some of the distress may have pre-existed and be due to
    longterm soil influences as well as inadequate original design
    and/or construction. [¶] Further investigation including soil
    sampling and testing can be performed to determine the site soil
    conditions.”
    AGI recommended the building’s foundation be reinforced
    with piers, going at least 20 feet deep, as well as repairs to the
    slab foundation. The preliminary cost to repair the damage, and
    relocate tenants, was estimated to be $258,900.77.
    b. Defendants’ investigation and expert
    At the time the claim was tendered, David Koch was
    defendants’ Property Supervisor. He was responsible for
    determining whether the loss was covered under plaintiff’s policy,
    and to retain experts to help make that determination. Irene
    Bernardo worked under Mr. Koch, administering the
    investigation of the claim.
    After receiving AGI’s report and repair estimate,
    defendants retained J.S. Held LLC, a construction consulting
    firm, to assist in investigating the claim. Upon J.S. Held’s
    recommendation, defendants also retained Wiss, Janney, Elstner
    Associates (WJE) to inspect plaintiff’s property and determine
    the cause of the damage.
    4
    On June 4, 2016, WJE associates Ann Harrer and Adrienne
    Goetz conducted a site survey. John Machin, a cost estimator
    with J.S. Held, and plaintiff’s representative, Alex Stamires,
    were also present during the site survey.
    WJE issued its report on June 29, 2016, detailing its
    investigation and findings. As part of its investigation, WJE
    reviewed AGI’s report, and inspected the interior and exterior of
    the complex. WJE did not conduct any soil tests. According to
    the report, Mr. Stamires told WJE the water line supply break
    occurred three to four feet underground, at the southwest corner
    of the building. During a two- or three-day period, water leaked
    from the broken pipe, creating a mud slurry that traveled along
    the western façade of the building, and down a sloped
    embankment away from the building.
    WJE noted numerous previous repairs to the stucco on the
    building, at the west and south facades, and near the water leak.
    Mr. Stamires informed WJE that no exterior repairs or
    repainting had been done since the property was purchased in
    2012. WJE noted that “[a]t some locations, particularly at the
    sound end of the main building, some of the [previously repaired]
    cracks have opened up . . . .”
    Unit 1 is a ground floor apartment, closest to the leak. The
    glass for unit 1’s window had been replaced with an acrylic sheet,
    as the glass for the unit had broken three times since the pipe
    break. Sealant had been applied to a crack on the bottom of the
    window frame following the pipe break, and the crack had
    widened since its application because the crack was no longer
    sealed. Cracks were noted throughout the interior of the
    apartment, but were predominantly in the southwest bedroom
    closest to the water leak, and the living room. The tenants
    5
    reported that they had filled drywall cracks emanating from the
    corner of a closet door following the pipe leak, but that the cracks
    had since widened. Also, the door to their unit was sticking, and
    there was “vertical offset” of the slab floor in the living room
    which was not noticeable before the leak. The floor noticeably
    sloped to the south.
    WJE concluded that “[t]he previously repaired interior and
    exterior cracking, and the [floor level] survey performed by [AGI],
    indicate that away from the vicinity adjacent from the reported
    water supply line break location there are changes in elevation
    across the slab of the main building. The changes in elevation
    noted indicate that at least some settlement and movement of the
    building occurred prior to the water supply line break event and
    subsequent running water from the broken line. However, the
    reopening of previously repaired cracks, presence of open cracks,
    observed discontinuity with vertical offset in Unit 1, and the
    multiple occurrences of glass breakage of the window in Unit 1 as
    reported by residents, indicate that there has been some
    movement or settlement of the building since the early 2016
    water supply line break event. Existing settlement-related
    conditions were likely exacerbated as a result of the water
    released due to the supply line break. However, it is of note that
    there has been ongoing, general settlement of the building,
    downwards towards the west, which will likely continue, and
    which is not a result of the recent water supply line break and
    subsequent running water.”
    WJE recommended that “floor finishes in Unit 1 be
    removed to investigate further the noted floor slab discontinuity
    and vertical offset. This investigation should be completed to
    determine potential extent of distress as well as to determine a
    6
    repair procedure.” WJE made no recommendations on how the
    damage should be repaired.
    c.     Defendants retain coverage counsel
    On June 30, 2016, defendants retained Mark R. Israel of
    Daniels, Fine, Israel, Schonbuch & Lebovits, LLP to provide legal
    advice regarding coverage for the damage under the policy.
    Mr. Israel was asked to determine whether there was coverage
    for plaintiff’s damages under the “efficient proximate cause”
    standard. He reviewed the policy, and the AGI and WJE reports.
    On July 27, 2016, Mr. Israel provided defendants with an
    opinion letter summarizing his conclusions. Under the policy,
    damage to the building caused by earth movement and
    settlement are excluded, but water damage resulting from an
    “accidental discharge” of water was covered. He noted that both
    AGI and WJE agreed there was “pre-existing, ongoing general
    settlement” of the building. He noted that “there are a number of
    candidates for the ‘efficient proximate cause’ of loss,” but that
    “both experts concur that the water leak set in motion forces that
    seriously exacerbated the preexisting condition of the property
    and likely caused new damage.”
    Mr. Israel ultimately concluded “damage to the insured
    apartment building attributable to the recent water line break is
    covered. There was undoubtedly pre-existing settlement and
    cracking at the insured location. To the extent the experts can
    reasonably segregate the repair cost between the two types of
    damage, then coverage would exist only for damage allocable to
    the pipe break.” He recommended that “in addition to having
    your experts assess that issue, you may wish to request water
    usage records from the insured location to verify that this leak
    7
    was a sudden occurrence in the December-January time frame as
    opposed to a chronic condition at the property.”
    d.    Defendants seek further expert opinions
    Because neither the AGI nor the WJE reports provided a
    definitive opinion that the water main break was the efficient
    proximate cause of the damage, on September 16, 2016, Mr. Koch
    requested that WJE perform additional testing. Also, on
    October 5, 2016, defendants retained Geotechnical and
    Environment Sciences Consultants, Ninyo & Moore. Ninyo &
    Moore provided a report on December 6, 2016, and on
    December 5, 2016, WJE provided a supplemental report.
    Ninyo & Moore visited the site on October 11, 2016,
    reviewed the regional geological setting and site geology, and
    conducted “subsurface exploration consisting of the excavation,
    logging, and sampling of two hand excavated test pits and
    four hand-augered exploratory borings around the subject
    building.” Soil samples were taken from the borings and test pits
    and sent to a laboratory for testing.
    Ninyo & Moore observed numerous previously patched
    cracks in the stucco. Some of those cracks experienced “minor re-
    opening.” They also inspected the exposed slab floor in unit 1,
    and noticed large cracks in the concrete. The “slab cracks were
    generally noted to have aged characteristics including rounded
    and worn edges,” and were filled with debris. They also noted
    that “topping slab/replacement slab” had been applied to the
    southwest bedroom floor, attempting to level the sloping floor.
    Ninyo & Moore formed the following opinion: “Based on
    our evaluation, the cracks in the walls and floor slab and the tilt
    of the floors of the subject building were caused by long-term
    differential soil movement. The soil movement that has affected
    8
    the building is attributable to settlement of soils along the west
    side of the building, as indicated by the low areas and contour
    pattern of the . . . floor level survey . . . , and heave of expansive
    clayey soil under the eastern portion of the building. Based on
    our site observations, the settlement is related to the poor surface
    drainage conditions observed along the west side of the building.
    Long-term infiltration of water into the foundation soils on the
    west side of the structure due to roof runoff and incident rainfall
    has resulted in long-term settlement in this area.”
    “Based on our evaluation, we conclude that the reported
    December 31, 2015, pipe leak did not contribute to the tilt of the
    building floor or the cracks in the building. The tenants of the
    building reportedly observed water from the leaking pipe flowing
    into the drainage channel property to the north of the subject
    site. Based on our . . . surveying around the southwest part of
    the site, surface drainage in the vicinity of the reported pipe leak
    location would tend to flow away from the building toward the
    south and west into the drainage channel property adjacent to
    the subject site. . . . This suggests that water from the leaking
    pipe escaped to the ground surface and flowed away from the
    building and that a significant amount of water did not infiltrate
    the subsurface soils at the location of the leak. Additionally, the
    tilt of the slab-ongrade is relatively consistent from the south end
    of the building to the north end and cracks in the building walls
    were observed to be widespread across the structure. . . . We did
    not observe indications that the distress was isolated at the
    location of the reported pipe leak at the southwest corner of the
    building. . . .”
    As part of its supplemental report, WJE reviewed water
    bills for the subject property for the months between August 2015
    9
    and January 2016. The January bill reflected water use that was
    9,500 gallons higher than previous months. WJE also inspected
    the exposed slab floor for unit 1, and noticed significant cracking,
    and that topping cement had been added to the southwest corner
    of the bedroom. WJE used ground penetrating radar (GPR) to
    examine the conditions below the slab. “GPR surveys performed
    in several locations throughout the exposed slab revealed that the
    slab is largely unreinforced, and as a result, does not have the
    tensile strength to resist differential movement, which results in
    cracking. Some areas of the slab exhibit evidence of previous
    repairs.”
    WJE concluded that “the previous repairs to the exterior
    cracks and evidence of the slab-on-ground cracking indicates that
    the cracks initiated prior to the water supply line break of
    December 2015. Previous repairs to the exterior walls and
    interior slab also indicate that ongoing attempts to mitigate the
    long-term settlement of the building have occurred, including
    installation of a topping or leveling material in the bedroom. In
    conclusion, there has been ongoing, general settlement of the
    building, downwards toward the south and west, resulting in the
    observed cracking in the slab and walls of Unit I, which will
    likely continue without remediation of the conditions that are
    causing this settlement, and which is not a result of the
    December 2015 water supply line break and subsequent
    discharge of water.”
    Mr. Israel reviewed both the Ninyo & Moore report and
    WJE’s supplemental report, and on December 7, 2016, Mr. Israel
    forwarded these reports to plaintiff.
    On January 23, 2017, plaintiff provided defendants with a
    2012 property inspection report which had been prepared in
    10
    connection with plaintiff’s purchase of the property. The report
    noted cracking and bubbling in the stucco requiring repairs and
    further evaluation, and problems with the window in unit 1. The
    window would fall out of its tracks and required further
    evaluation. The inspector also noted cracking in the drywall, and
    that the slab in unit 4 is “badly cracked and feels as though the
    crack is offset. Cause of the cracking is unknown and . . . needs
    to be determined.”
    e.    Defendants deny plaintiff’s claim
    After reviewing all these reports, Mr. Israel prepared a
    second coverage evaluation concluding the “efficient proximate
    cause of the foundation damage was long-term differential soil
    movement which cause of loss is explicitly excluded by the terms
    of the policy.” Mr. Israel sent this coverage opinion to plaintiff on
    February 6, 2017.
    2.     Plaintiff’s Facts in Opposition to Summary
    Adjudication
    Plaintiff argued there were triable issues as to whether
    there was a “genuine dispute,” reasoning there was ample
    evidence from which a jury could conclude that defendants “acted
    unreasonably and that [their] investigation was biased.”
    Specifically, plaintiff argued that the property was in good
    condition when it was purchased and when defendants first
    extended coverage to plaintiff; WJE initially concurred with
    plaintiff’s expert that the leak caused new damage to the
    building; defendants received an initial coverage opinion that
    there was coverage under the policy that defendants did not
    disclose to plaintiff; the decision to extend coverage changed
    when defendants received a higher than expected estimate to
    repair the damage; WJE changed its opinion without conducting
    11
    any further investigation; new experts were hired only to “pursue
    coverage denial”; and defendants anticipated litigation, from
    which it could be inferred their denial was in bad faith.
    a.     Condition of property at time of purchase
    In 2013, defendants had the property inspected as part of
    their due diligence before issuing an insurance policy. The
    report, written by E&S Inspections, Inc. provided no in-depth
    description of the condition of the property, but instead noted
    that the property was in “satisfactory” or “average” condition, and
    included 11 general photographs of the building, none of which
    included sufficient detail to show cracking to the building’s stucco
    or settlement of the building.
    Mr. Koch testified in his deposition that if the inspection
    revealed “apparent damage or issues,” an insurance policy would
    not likely have been issued. He also testified that the 2013 report
    was not provided to defendants’ experts, WJE and Ninyo &
    Moore.
    b.     Defendants initially decided to extend coverage
    Claim file notes entered on July 26, 2016 by Ms. Bernardo
    recorded that Mr. Israel “[j]ust completed the analysis, we will
    extend coverage to unit 1 only, he wanted to see previous water
    bill for this property first for review then finalize[] his report,
    submit to KBIC Mr. Koch and move forward.”
    Plaintiff provided the water bills to defendants on
    August 8, 2016. That same day, Mr. Machin, the cost estimator
    with defendants’ construction consulting firm, told defendants in
    his opinion, “9,537 gallons more in the month of December-
    January over the monthly average . . . is representative of enough
    water to cause the settling and deformation described.”
    12
    August 10, 2016 notes in the claim file record that
    Mr. Israel told defendants that if the experts agreed the water
    line break caused the damage to plaintiff’s property, the next step
    would be to “formulate cost[s]” of repair. However, he cautioned
    that further investigation might be warranted.
    Defendants provided the water bills to WJE, and on
    August 16, 2016, WJE informed defendants that the water bills
    did not change their findings from their earlier report that pre-
    existing settlement of the building “was likely exacerbated as a
    result of the water supply line break.” WJE also maintained that
    settlement of the building would likely continue, unrelated to the
    water line break.
    According to Mr. Stamires, defendants did not provide
    plaintiff with WJE’s initial June report which stated in part,
    “Existing settlement-related conditions were likely exacerbated
    as a result of the water released due to the supply line break.”
    Moreover, “[t]he Carrier never disclosed to me the decision to
    extend coverage in July 2016” or that they asked “Mr. Machin to
    prepare an estimate for repair of damages related to the loss.”
    Defendants also did not give Mr. Israel’s July coverage opinion to
    plaintiff. Mr. Israel advised defendants that the letter was for
    their use, and that the opinion was privileged.
    c.     J.S. Held LLC prepares repair estimate
    On July 27, 2016, defendants forwarded a copy of WJE’s
    June report to Mr. Machin of J.S. Held LLC “so he can start
    writing estimate for unit 1.” According to July 28, 2016 notes in
    the claim file, Mr. Machin told defendants there were “lots of
    issues” with writing an estimate for unit 1. He recommended
    further evaluation by the engineers, including evaluation of the
    slab to “get a better picture and write a report” of the damage.
    13
    On September 3, 2016, Mr. Machin provided an estimate to
    repair unit 1 to his colleague at J.S. Held, Mr. John Gillen. The
    total repair costs for unit 1 were estimated to be $227,752.90.
    On September 5, 2016, Mr. Gillen emailed Mr. Machin,
    asking him to “clarify the extent of slab replacement and
    releveling” because the estimate was “more than . . . expected and
    quite a bit more than the Insured’s estimate, so I want to be sure
    before we send.”
    On September 8, 2016, Mr. Machin discussed the estimate
    with defendants, and again explained there were a lot of
    “unknowns” that made providing an estimate difficult, and that
    WJE had not recommended the scope of work or how to repair the
    damage to the building. He suggested having a conference call
    with defendants, Mr. Gillen, WJE, and Mr. Israel to discuss how
    to proceed.
    The conference call was held on September 9. Mr. Machin
    expressed concerns that “there is something going on [in] the
    middle of the building that we do not know” and that there was
    extensive settlement on the north side of the building, away from
    the pipe leak. The parties decided that WJE would write a
    proposal for further investigations so that they “can tell for sure
    if all the cracks are related to [the water pipe leak] or . . .
    settlement.”
    d.    Defendants hire new expert
    Ms. Harrer with WJE sent a proposal to perform additional
    investigations to J.S. Held on September 13, 2016. She
    recommended that the floor finishes in unit 1 be removed so that
    the floor could be further investigated. She proposed that WJE
    visually survey the exterior of the building for any noticeable
    changes since its June investigation. WJE would use GPR to
    14
    determine the condition of the slab including its thickness and
    reinforcement. WJE’s investigation would not include samples or
    material testing, but these services were recommended.
    In addition to this proposal, Ms. Harrer cut and pasted
    some background information from WJE’s June report. Other
    than reviewing the water bills, and participating in the
    September 9 conference call, WJE had not performed any
    additional investigations since its June report. Nevertheless,
    the proposal phrased some matters differently than the June
    report. For example, the proposal substituted the term “may”
    for the phrase “has been” in stating that there “may have been
    some movement or settlement of the building since the early
    2016 water supply line break event.” Ms. Harrer also
    tempered her previous conclusion that “[e]xisting settlement-
    related conditions were likely exacerbated as a result of the
    water released due to the supply line break,” by adding,
    “however, the extent of damage, if any, caused by the January
    2016, even[t] are not known at this time” to the end of the
    sentence.
    According to Ms. Bernardo, it was Mr. Koch who suggested
    that new experts be hired. On October 3, 2016, she wrote an
    email to Mr. Koch asking him to approve Ninyo & Moore’s
    budget of $15,000. On October 5, 2016, Mr. Koch responded by
    asking “Why is budget so expensive?” Later that same day,
    Mr. Koch approved the budget, writing to Ms. Bernardo, “Seems
    expensive in pursuit of coverage denial. OK for engineer.”
    e.    Defendants deny claim
    In December 2016, following the receipt of reports from
    WJE and Ninyo & Moore, the claim file includes notes
    indicating a “potential lawsuit” and “this file will be in
    15
    litigation.” The context for these notes was that the reports
    concluded the damage was not attributable to the water main
    break, and that the coverage attorney, Mr. Israel, was going to
    provide these reports to plaintiff.
    f.     Plaintiff seeks denial of motion pursuant to
    Code of Civil Procedure section 437c,
    subdivision (h)
    Plaintiff argued the motion should be denied under
    section 437c, subdivision (h), because defendants’ person most
    knowledgeable about the investigation and denial of plaintiff’s
    claim, William Walker, was instructed by counsel not to answer
    53 questions during his July 20, 2018 deposition. Specifically, he
    refused to answer “Was the denial of the claim appropriate?”
    Counsel objected that the question improperly called for expert
    opinion.
    Plaintiff’s counsel’s declaration in support of the opposition
    averred: “The refusal of Defendant to answer questions in
    deposition prevented me from obtaining essential discovery
    regarding the denial of the claim, which I would have found
    useful in preparing the opposition to this motion.” “There were
    other similar questions to which the PMK witness was so
    instructed and refused to answer. The instruction and refusal to
    answer each of the 53 questions severely limited the usefulness of
    the deposition and was prejudicial to Plaintiff in that facts
    essential to justify opposition may exist but cannot, for reasons
    stated, be presented. On this ground alone, per CCP §437(c)(h)
    the Court should deny the motion and make any other order as
    may be just.”
    16
    3.     Defendants’ Reply
    Defendants’ reply argued that plaintiff’s evidence did not
    show that defendants acted unreasonably, or refute their
    evidence that there was a genuine dispute. The reply did not
    address plaintiff’s argument that the motion should be denied
    pursuant to section 437c, subdivision (h).
    4.     Trial Court’s Ruling
    The trial court granted the motion, finding defendants had
    satisfied their burden under the genuine dispute doctrine, and
    that plaintiff’s opposition evidence did not raise a triable issue of
    material fact. The trial court’s ruling did not address plaintiff’s
    request for denial of the motion under section 437c,
    subdivision (h). Plaintiff dismissed its remaining claims without
    prejudice, judgment was entered in favor of defendants, and this
    timely appeal followed.
    DISCUSSION
    “[T]he party moving for summary judgment [or
    adjudication] bears the burden of persuasion that there is no
    triable issue of material fact and that he is entitled to judgment
    as a matter of law.” (Aguilar v. Atlantic Richfield Co. (2001)
    
    25 Cal. 4th 826
    , 850 (Aguilar).) “Once the [movant] has met that
    burden, the burden shifts to the [other party] to show that a
    triable issue of one or more material facts exists as to [that] cause
    of action . . . .” (Code Civ. Proc., § 437c, subd. (p)(2); Aguilar, at
    p. 850.) The party opposing summary judgment “shall not rely
    upon the allegations or denials of its pleadings to show that a
    triable issue of material fact exists but, instead, shall set forth
    the specific facts showing that a triable issue of material fact
    exists . . . .” (§ 437c, subd. (p)(2).) A triable issue of material fact
    exists where “the evidence would allow a reasonable trier of fact
    17
    to find the underlying fact in favor of the party opposing the
    motion in accordance with the applicable standard of proof.”
    (Aguilar, at p. 850.)
    Our Supreme Court has made clear that the purpose of the
    1992 and 1993 amendments to the summary judgment statute
    was “ ‘to liberalize the granting of [summary judgment]
    motions.’ ” (Perry v. Bakewell Hawthorne, LLC (2017) 
    2 Cal. 5th 536
    , 542; 
    Aguilar, supra
    , 25 Cal.4th at p. 854.) It is no longer
    called a “disfavored” remedy. “Summary judgment is now seen as
    a ‘particularly suitable means to test the sufficiency’ of the
    plaintiff’s or defendant’s case.” (Perry, at p. 542.) On appeal, “we
    take the facts from the record that was before the trial court . . . .
    ‘ “We review the trial court’s decision de novo, considering all the
    evidence set forth in the moving and opposing papers except that
    to which objections were made and sustained.” ’ ” (Yanowitz v.
    L’Oreal USA, Inc. (2005) 
    36 Cal. 4th 1028
    , 1037, citation omitted.)
    a.     Genuine dispute doctrine
    California law requires insurers to pay for covered losses
    caused by an insured risk. If a loss was caused by more than
    one occurrence, including covered and not-covered events, then
    the insurer is liable only if the “efficient proximate cause” or the
    “predominate” cause was a covered risk. (City of Carlsbad v.
    Insurance Co. of State of Pennsylvania (2009) 
    180 Cal. App. 4th 176
    , 183.)
    “ ‘Before an insurer can be found to have acted in bad faith
    for its delay or denial in the payment of policy benefits, it must be
    shown that the insurer acted unreasonably or without proper
    cause.’ . . . ‘Where there is a genuine issue as to the insurer’s
    liability under the policy for the claim asserted by the insured,
    there can be no bad faith liability imposed on the insurer for
    18
    advancing its side of that dispute.’ . . . [¶] ‘The “genuine
    dispute” doctrine may be applied where the insurer denies a
    claim based on the opinions of experts.’ . . . Reliance on an
    expert . . . ‘will not automatically insulate an insurer from a bad
    faith claim based on a biased investigation.’ . . . Although an
    insurer may rely on experts, summary judgment on a bad faith
    claim must be denied where the evidence shows ‘the insurer
    dishonestly selected its experts[,] the insurer’s experts were
    unreasonable[,] [or] the insurer failed to conduct a thorough
    investigation.’ ” (McCoy v. Progressive West Ins. Co. (2009)
    
    171 Cal. App. 4th 785
    , 793, citations omitted.)
    Here, defendants presented evidence that there was a
    genuine dispute that the pipe rupture (a covered loss) was not the
    efficient proximate cause of the damage, and that the efficient
    proximate cause was earth movement or settlement (an excluded
    loss). Specifically, defendants presented evidence that its
    experts, WJE and Ninyo & Moore, concluded the damage to the
    building was caused by earth settlement and not the pipe
    rupture.
    Plaintiff makes much of the fact that there was evidence
    defendants initially decided the damage may have been covered,
    and only sought additional expert opinions after the estimate for
    repairs exceeded their expectations. However, plaintiff ignores
    evidence that both AGI and WJE noted extensive pre-existing
    settlement damage to the building in their initial reports, and
    cautioned that further investigations and testing should be
    conducted to determine the cause of the damage and the
    necessary repairs. Moreover, when asked to provide a repair
    estimate, Mr. Machin cautioned there were many “unknowns,”
    and further investigation was warranted. Mr. Israel similarly
    19
    guarded his initial coverage evaluation, cautioning there were
    other possible causes of the damage, and that the experts should
    attempt to apportion the damage between the various causes,
    including pre-existing earth movement and the pipe rupture.
    Plaintiff also complains that WJE changed its opinion in its
    September 13 proposal, without conducting any further
    investigation. Nothing in the record supports this inference.
    WJE had participated in the September 9 conference call, where
    Mr. Machin raised concerns about his ability to write an accurate
    repair proposal based on the number of “unknowns” before WJE
    drafted its proposal. We can infer no dishonesty or
    unreasonableness from these facts.
    Plaintiff also makes much of Mr. Koch’s email approving
    the $15,000 budget for an additional expert report and stating it
    seemed expensive “in pursuit of coverage denial,” and the claim
    file notes stating litigation was anticipated. We do not find it is
    reasonable to infer bad faith from the email or from these file
    notes. Mr. Koch may have been of the opinion that defendants
    already had enough expert information on which to deny the
    claim, and another $15,000 was too much to spend, but he
    approved the budget anyway, and defendants’ coverage denial
    was indisputably based on the additional expert report. As for
    the file notes, litigation often results from coverage denial, and
    file notes stating the obvious are not reasonably viewed as
    evidence of bad faith.
    We agree with the trial court’s assessment that none of
    plaintiff’s evidence raised a triable issue that this was not a
    genuine coverage dispute. There is no dispute that defendants
    based their claim denial on the final expert report, and there is
    no evidence that report was contrived or false. As the trial court
    20
    aptly stated, “Initial opinions are often superseded by further
    investigation.”
    b.    Section 437c, subdivision (h)
    Section 437c, subdivision (h) provides: “If it appears from
    the affidavits submitted in opposition to a motion for summary
    judgment or summary adjudication, or both, that facts essential
    to justify opposition may exist but cannot, for reasons stated, be
    presented, the court shall deny the motion, order a continuance to
    permit affidavits to be obtained or discovery to be had, or make
    any other order as may be just.” A party seeking continuance or
    denial of a motion under section 437c, subdivision (h) must show
    that the facts to be obtained are essential to opposing the motion,
    that there is reason to believe such facts may exist, and that
    additional time is needed to obtain these facts. (Wachs v. Curry
    (1993) 
    13 Cal. App. 4th 616
    , 623.) The party’s supporting
    declarations must show: “(1) ‘Facts establishing a likelihood that
    controverting evidence may exist and why the information sought
    is essential to opposing the motion’; (2) ‘The specific reasons why
    such evidence cannot be presented at the present time’; (3) ‘An
    estimate of the time necessary to obtain such evidence’; and
    (4) ‘The specific steps or procedures the opposing party intends to
    utilize to obtain such evidence.’ ” (Johnson v. Alameda County
    Medical Center (2012) 
    205 Cal. App. 4th 521
    , 532, italics omitted.)
    Here, the sum total of plaintiff’s argument on this point in
    the trial court was one heading, and two sentences, at the
    conclusion of plaintiff’s opposition brief: “Other facts may exist
    essential to denial, however, Defendants refused to answer
    53 questions in PMK deposition. Denial is proper pursuant to
    CCP 437(c)(h).” Counsel’s supporting declaration was very
    general, and did not explain why the answer to any of the
    21
    questions at the PMK deposition was essential to opposing the
    summary adjudication motion. The only testimony that plaintiff
    complains it was unable to obtain was an opinion about whether
    denial of the claim was “appropriate,” and we see no reason to
    conclude the PMK’s opinion, whether yes or no, would be a
    material fact, or that it was essential to oppose the motion.
    DISPOSITION
    The judgment is affirmed. Respondents are awarded their
    costs on appeal.
    GRIMES, J.
    WE CONCUR:
    BIGELOW, P. J.
    WILEY, J.
    22
    Filed 4/16/20
    CERTIFIED FOR PUBLICATION
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    SECOND APPELLATE DISTRICT
    DIVISION EIGHT
    501 EAST 51ST STREET,                   B293605
    LONG-BEACH-10 LLC,
    (Los Angeles County
    Plaintiff and Appellant,            Super. Ct. No. NC061176)
    v.
    ORDER CERTIFYING
    KOOKMIN BEST INSURANCE                      OPINION FOR
    CO., LTD., et al.,                          PUBLICATION
    Defendants and Respondents.           [No change in judgment]
    THE COURT:
    The opinion in the above-entitled matter filed on April 2,
    2020, was not certified for publication in the Official Reports. For
    good cause, it now appears that the opinion should be published
    in the Official Reports and it is so ordered.
    There is no change in the judgment.
    ____________________________________________________________
    BIGELOW, P. J.              GRIMES, J.            WILEY, J.
    

Document Info

Docket Number: B293605

Filed Date: 4/16/2020

Precedential Status: Precedential

Modified Date: 4/16/2020