Wu v. Lian Tong, LLC CA1/3 ( 2023 )


Menu:
  • Filed 3/30/23 Wu v. Lian Tong, LLC CA1/3
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or
    ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FIRST APPELLATE DISTRICT
    DIVISION THREE
    BING WU et al.,
    Plaintiffs and Appellants,                                  A163131, A163455, A163635,
    A163768
    v.
    LIAN TONG, LLC, et al.,                                               (City & County of San Francisco
    Super. Ct. No. CGC-21-589219)
    Defendants and Respondents.
    Appellants, Bing Wu and Kai Ming Lei, filed this malicious prosecution
    action against two sets of respondents, Lian Tong, LLC and its owner Sheng
    Liu (collectively, Lian Tong), and Lian Tong’s former counsel, the Horner Law
    Group, P.C., Clifford Horner, and Brendan Dooley (collectively, Horner Law).
    Appellants contend that respondents lacked probable cause and acted with
    malice when they pursued a claim against appellants for breaching a
    restaurant construction contract. Lian Tong and Horner Law each filed
    special motions to strike appellants’ complaint pursuant to California’s anti-
    SLAPP statute. (Civ. Proc. Code, § 425.16, subd. (b); undesignated statutory
    references are to this code.) The trial court granted both motions and
    awarded respondents attorney fees. We affirm.
    1
    BACKGROUND
    I. The Underlying Case
    The underlying case arose out of a failed project to construct a
    restaurant at two commercial addresses (565 and 575) on 4th Street in San
    Francisco.
    A. The Contracts
    Property owner Lian Tong retained Bing Wu Construction Company
    (BW Construction) to work on its restaurant project pursuant to a contract
    executed on March 30, 2014 (the BW contract). Three individual contractors
    signed the BW contract on behalf of BW Construction: James Chen, who
    drafted the contract, and appellants, Wu and Lei. The BW contract was
    executed on behalf of Lian Tong by Yi Fang Liu (Y.F. Liu), who is the father
    of respondent Sheng “Leo” Liu (Liu). The seven-page contract outlines work
    BW Construction agreed to perform, which ranged from demolition to
    finishing work to other “miscellaneous” tasks. (Block capitalization omitted.)
    The contract price was $400,000, which was to be paid in installments as
    various stages of the project were completed. The last two terms of the
    contract became the focus of the underlying case, so we repeat them here:
    “Time of Performance [¶] The work specified in this contract shall be
    started immediately once the owner provides the approved permits and
    drawings. The duration for the whole project is about 6 months and the
    whole work shall be completely done after the 6 months of the beginning
    date.
    “Permits and Approvals [¶] Owner shall pay for all the fees to apply
    for the state and local permits, the cost to apply for the utilities services and
    all necessary surveys for performing the work specified above. If the
    contractor pays the permit fee during the time for processing, the owner shall
    2
    reimburse the money to the contractor per invoice. The owner is responsible
    for providing the approved & stampped [sic] plan for #575 which is supposed
    to be built [as] a restaurant.” This last sentence was handwritten on the
    typed page.
    Ten months later, on February 6, 2015, Chen and Y.F. Liu executed a
    “Contract Termination Agreement” on behalf of BW Construction and Lian
    Tong. The document was handwritten by Chen in Chinese on a piece of lined
    paper.
    On February 12, 2015, Chen on behalf of Egoodat Inc. and Y.F. Liu on
    behalf of Lian Tong executed a new construction contract (the Egoodat
    contract). This written agreement is a marked up version of the BW contract
    that substituted Egoodat’s name for BW Construction’s name at the top of the
    document and added the following handwritten term at the bottom: “the
    whole project is awarded to Egoodat, Inc. since the date of 2/12/15.”
    Appellants are not parties to the Egoodat contract.
    B. The Lawsuit
    In February 2016, Lian Tong filed a complaint for damages arising out
    of the restaurant project, alleging causes of action for breach of contract
    against BW Construction, breach of contract and negligence against Egoodat,
    and fraud and breach of contract against Chen. As support for these claims,
    Lian Tong alleged the following facts: The BW contract Chen negotiated on
    behalf of BW Construction provided that work would begin “immediately”
    once Lian Tong provided “approved permits and drawings,” and the parties
    “agreed and understood” that the project would be completed within six
    months, “or approximately by early October 2014.” For months, Chen made
    false representations that work was progressing. In February 2015, Lian
    Tong discovered that no work had been completed, and Chen admitted that
    3
    his business partner had stolen the BW contract funds, which prevented BW
    Construction from starting work. Because BW Construction failed to
    perform, Lian Tong had to find another contractor, and Chen proposed that
    his other company, Egoodat, would do the work. On February 12, 2015, the
    parties made handwritten changes to the BW contract and then executed
    that document. Egoodat’s work was deficient, and the project was never
    completed. Ultimately, Lian Tong was forced to terminate its lease with its
    restaurant tenant and suffered damages in excess of $1,000,000.
    Chen and Egoodat filed a joint answer to Lian Tong’s complaint, and
    Egoodat also filed a cross-complaint against Lian Tong for breach of contract
    and “Common Counts.” Initially, BW Construction failed to respond to the
    complaint, but in September 2016, appellants obtained relief from default
    and filed a general denial answer on behalf of BW Construction, which they
    identified as their fictitious business name.
    Appellants also filed a cross-complaint against Lian Tong and Y.F. Liu
    for breach of contract, fraud, and declaratory relief. Appellants alleged that
    Lian Tong breached the 2015 termination contract by failing to release
    appellants from the BW contract and that Y.F. Liu fraudulently induced
    appellants to execute the 2015 contract by falsely representing that
    appellants would be released from the BW contract.
    As support for its cross-claims, appellants alleged the following facts:
    After executing the BW contract, Lian Tong caused delays that prevented BW
    Construction from starting work on the project by failing to provide approved
    plans and failing to obtain permission from its property owners’ association.
    Due to such delays, “none of which were caused” by appellants, it became
    “impracticable and/or impossible” for BW Construction to perform the BW
    contract. On February 6, 2015, appellants and Lian Tong entered into a “new
    4
    written contract,” which released appellants’ from the BW contract in
    exchange for a payment of $20,500 to Lian Tong and its agent, Y.F. Liu.
    When this new contract was negotiated, Y.F. Liu represented that appellants
    would be released from the BW contract if they paid $20,500, but Lian Tong
    and Y.F. Liu never intended to release appellants or cancel the BW contract.
    Pretrial litigation was vigorous and protracted, as documented in the
    30-page register of actions for the underlying case. Meanwhile, the parties
    actively pursued discovery, taking 11 depositions, exchanging interrogatories,
    and disclosing experts. Chen, appellants Wu and Lei, and respondent Liu all
    gave depositions. However, Y.F. Liu was in China, and the trial court denied
    appellants’ motion to compel Lian Tong to produce Y.F. Liu for a deposition.1
    In January 2019, appellants filed a first amended cross-complaint,
    which included the following new allegations: Immediately before the BW
    contract was executed, Y.F. Liu made false representations that Lian Tong
    had obtained all necessary approvals to begin construction, and that
    construction could begin immediately. When the BW contract was executed,
    Lian Tong’s restaurant project had not been approved by the Palms Owners’
    Association (the Palms). Lian Tong’s delay in obtaining approval from the
    Palms constituted a breach of the BW contract, prevented BW Construction
    from performing its contractual obligations, and “barred” Lian Tong from
    terminating the BW contract, appellants alleged. Appellants alleged further
    that they were harmed because Lian Tong misled them to believe that
    approval from the Palms had been obtained, and then “unreasonably delayed
    in obtaining [that] approval until January 2015.”
    1 The register of actions lists several documents that appear to be
    relevant to matters discussed in the appellate briefs, but that the court does
    not find in the Appellants’ Appendix, such as this discovery order.
    5
    Lian Tong challenged appellants’ amended cross-claims by filing a
    motion to strike, a motion for judgment on the pleadings, and a motion for
    summary judgment. To support its summary judgment motion, Lian Tong
    obtained a declaration from Y.F. Liu that was executed in China. Y.F. Liu
    stated, among other things, that: Chen and his partner BW Construction
    agreed to build the restaurant pursuant to plans for the initial work that had
    been prepared by Derrick Wu, and Lian Tong provided those approved plans
    and permits to BW Construction, as the BW contract required; prior to
    execution of the BW contract, Y.F. Liu did not say or represent that Lian
    Tong had already obtained approval for the project from the Palms; BW
    Construction and Chen caused delays by failing to obtain consent for
    construction from the Palms and by failing to take other steps necessary to
    commence construction; when the BW contract was terminated, Y.F. Liu did
    not represent that appellants or Chen would be released from the contract
    but only that the agreement was terminated.
    On May 14, 2019, the superior court granted Lian Tong’s motion to
    strike portions of the first amended cross-complaint, including appellants’
    prayer for attorney fees, which was stricken because they failed to allege any
    contractual or statutory basis for recovering attorney fees. The court also
    granted Lian Tong’s motion for judgment on the pleadings, but granted
    appellants leave to amend its fraud claim and to allege a new cause of action
    for recission of the 2015 termination contract. That ruling mooted Lian
    Tong’s fully briefed motion for summary judgment, which was taken off
    calendar. The following month, appellants dismissed Y.F. Liu as a cross-
    defendant. The register of actions shows that appellants filed a second
    6
    amended cross-complaint, but as best we can determine, this document is not
    in the appellate record.2
    In September 2019, Lian Tong filed its operative first amended
    complaint, which included the following new allegations: BW Construction
    was a 50/50 partnership between appellants and Chen. The BW contract
    required Lian Tong to provide “approved and stamped plans for the project,”
    but did not hold Lian Tong responsible for obtaining approvals from entities
    other than the city’s building department, such as the Palms. When the BW
    contract was negotiated, the parties knew that Y.F. Liu did not speak English
    and was soon to leave on a trip to China. So they made an oral agreement
    that the Chen-BW Construction partnership would obtain any additional
    approvals that were required “to commence and complete the construction of
    the restaurant.” Subsequently, when Lian Tong learned that appellants and
    Chen failed to obtain approval from the Palms, it “mitigate[d] this breach” by
    enlisting other agents who assisted Lian Tong in finally securing approval
    from the Palms on January 5, 2015.
    C. The Trial
    In late October 2019, the case was assigned for a jury trial before the
    honorable Newton Lam. Lian Tong filed an in limine motion seeking
    permission for Y.F. Liu to testify via Skype from China, which appellants
    opposed pursuant to a prior discovery order. When appellants’ motion to
    2 Appellants have filed a 4,193-page Appellant’s Appendix, which is
    accompanied by indices that list multiple “Compendium[s] of Evidence” some
    containing hundreds of pages of documents. Appellants’ indices are
    inadequate. (Cal. Rules of Court, rule 8.124(d)(1), rule 8.144(b)(5).) Each
    volume of an appellants’ appendix must include an index that lists “each
    document” contained in the appendix, and the “page where it first appears.”
    (Rule 8.144(b)(5)(A).)
    7
    compel Y.F. Liu’s deposition was denied, the court had ruled that Lian Tong
    would not be permitted to rely on Y.F. Liu’s declaration or trial testimony
    “unless and until” they made arrangements for appellants to take his
    deposition.
    During the in limine hearing, Lian Tong argued that Y.F. Liu should be
    permitted to testify at trial notwithstanding the discovery order because he
    had been restricted by the government from leaving China and, under
    international rules, his deposition could not be compelled but his testimony
    at trial potentially could be. The trial court recognized that Y.F. Liu was a
    “significant witness” for “every side” because he was “the primary mover with
    regards to the inception of the relationship between the parties.” But
    ultimately it barred Y.F. Liu’s testimony pursuant to the discovery order.
    Appellants also filed a successful pretrial motion to limit the testimony
    of Lian Tong’s expert, Derrick Wu. According to Lian Tong, Wu is a licensed
    architect and construction manager with 30 years’ experience. Lian Tong
    anticipated eliciting a wide range of opinions from Wu, including that BW
    Construction was responsible for obtaining approval from the Palms.
    However, at trial the court limited Wu’s expertise “to that of an architect.”
    In November 2019, the jury trial was held over the course of two and a
    half weeks. During trial, appellants dismissed their rescission claim against
    Lian Tong and elected to go forward on their cross-claim for fraud. After the
    close of evidence but before the case was submitted to the jury, the court
    ruled on multiple motions for directed verdicts.
    Appellants sought a directed verdict of Lian Tong’s breach of contract
    claim pursuant to their affirmative defense that performance of the BW
    contract was impossible, arguing that they could not have completed the
    contract before it was terminated due to delays in obtaining approval from
    8
    the Palms. Characterizing this defense as an issue of law, the court
    concluded that because approval from the Palms was not obtained until
    January 2015, BW could not have completed its work within the six-month
    contract period. On this basis, the court granted appellants (and Chen) a
    directed verdict as to Lian Tong’s cause of action for breach of the BW
    contract. By contrast, the court found that appellants’ cross-claim for fraud
    was based on issues of fact. Thus, although the court expressed confusion
    and skepticism about appellants’ fraud theories, Lian Tong’s motion for a
    directed verdict of that cross-claim was denied.
    On December 5, 2019, the jury returned verdicts on remaining claims.
    We do not find a complete set of the verdicts in this appellate record, but it
    appears from the judgment, that the jury found Lian Tong proved only one
    claim, its negligent misrepresentation claim against Chen, for which it was
    awarded $35,880. Moreover, Lian Tong was held liable to appellants for
    fraudulent misrepresentation, although appellants were awarded $75,000
    instead of the $501,000 in damages they requested during closing argument.
    II. The Malicious Prosecution Case
    In January 2021, appellants filed a complaint against Lian Tong and
    Horner Law for malicious prosecution based on the filing and continued
    prosecution of Lian Tong’s cause of action for breach of the BW contract.
    Appellants allege that Lian Tong’s breach of contract claim was not
    supported by probable cause because there was no basis for disputing that:
    Lian Tong had the contractual duty to obtain all approvals for the restaurant
    project; Lian Tong did not obtain approval from the Palms until January
    2015; and six months from that approval date had not passed when Lian
    Tong terminated the BW contract.
    9
    Appellants also allege that Lian Tong attempted to manufacture
    probable cause to sue appellants by suppressing evidence that it had not
    obtained approval for its project when the BW contract was executed, and by
    purporting to rely on an approval letter from the Palms that was dated
    January 5, 2014, despite knowing that the letter was misdated, as the Palms
    did not actually approve the project until January 5, 2015. Appellants allege
    that they did not discover the letter was misdated until October 2018, when
    Veronica Nguyen was deposed on behalf of the Palms. After Nguyen’s
    deposition, respondent Dooley allegedly became “frantic,” and respondents
    subsequently served a statutory offer to compromise Lian Tong’s claim
    against appellants in exchange for a waiver of costs. Appellants characterize
    the offer to compromise as “an acknowledgement” that Lian Tong’s claim
    against appellants was “objectively baseless, fabricated, groundless,
    meritless, unsupported, and untenable.”
    Appellants allege further that the underlying action was filed for an
    improper purpose. Lian Tong’s alleged purpose was “pay back,” because Lian
    Tong’s owner, respondent Liu, believed that appellants had stolen the BW
    contract funds and abandoned the restaurant project. And Horner Law
    allegedly pursued the claim because they wanted “exorbitant attorneys’ fees
    and bills.”
    In April 2021, Horner Law filed a special motion to strike appellants’
    complaint (§ 425.16), arguing the malicious prosecution claim challenges
    activity protected by the anti-SLAPP statute and there is no probability
    appellants’ will prevail on their claim at trial. The trial court agreed, and
    granted Horner Law’s motion. Subsequently, Lian Tong filed their anti-
    SLAPP motion, making essentially the same arguments Horner Law made.
    After the court granted Lian Tong’s motion, Horner Law and Lian Tong filed
    10
    motions for attorney fees and costs. (§ 425.16, subd. (c)(1).) Both motions
    were granted. Horner Law was awarded $115,577.30 and Lian Tong was
    awarded $45,031.
    DISCUSSION
    Appellants contend the trial court erred by granting the anti-SLAPP
    motions, and for that reason alone the attorney fee orders must also be
    reversed.
    I. Standards Governing Anti-SLAPP Motions
    Section 425.16 authorizes a special motion to strike a cause of action
    arising from an act in furtherance of the defendant’s constitutional right of
    petition or free speech in connection with a public issue. (§ 425.16, subd. (b).)
    “The purpose [of the statute] is to curtail the chilling effect meritless lawsuits
    may have on the exercise of free speech and petition rights, and the statute is
    to be interpreted broadly to accomplish that goal. (§ 425.16, subd. (a).)”
    (Schaffer v. City and County of San Francisco (2008) 
    168 Cal.App.4th 992
    ,
    998.) To resolve an anti-SLAPP motion, the trial court engages in a two-step
    process: “First, the court decides whether the defendant has made a
    threshold showing that the challenged cause of action is one arising from
    protected activity. . . . If the court finds such a showing has been made, it
    then determines whether the plaintiff has demonstrated a probability of
    prevailing on the claim.” (Equilon Enterprises v. Consumer Cause, Inc. (2002)
    
    29 Cal.4th 53
    , 67 (Equilon).)
    Appellants concede that respondents made a threshold showing that
    the anti-SLAPP statute applies in this case. A “cause of action [for] malicious
    prosecution arises from an underlying lawsuit and involves allegations that
    the defendant committed a tort by engaging in the underlying action.”
    (Neurelis, Inc. v. Aquestive Therapeutics, Inc. (2021) 
    71 Cal.App.5th 769
    , 784
    11
    (Neurelis).) Thus, malicious prosecution claims “fall within the purview of
    the anti-SLAPP statute.” (Jarrow Formulas, Inc. v. LaMarche (2003) 
    31 Cal.4th 728
    , 735 (Jarrow).)
    Under the second step of the section 425.16 inquiry, appellants had the
    burden to produce evidence of a probability of prevailing on their claim.
    (Equilon, 
    supra,
     29 Cal.4th at p. 67.) To meet that burden, they were
    required to establish that their malicious prosecution claim “ ‘ “is both legally
    sufficient and supported by a sufficient prima facie showing of facts to
    sustain a favorable judgment” ’ ” if their evidence is credited. (Vargas v. City
    of Salinas (2009) 
    46 Cal.4th 1
    , 19–20.)
    “A claim for malicious prosecution requires that the plaintiff
    demonstrate (1) the defendant brought (or continued to pursue) a claim in the
    underlying action without objective probable cause, (2) the claim was pursued
    by the defendant with subjective malice, and (3) the underlying action was
    ultimately resolved in the plaintiff's favor.” (Lane v. Bell (2018) 
    20 Cal.App.5th 61
    , 67.) Here, the trial court found that appellants failed to
    make a sufficient prima facie showing to establish the first two elements of
    this claim. We independently review the trial court’s findings on appeal.
    (Rusheen v. Cohen (2006) 
    37 Cal.4th 1048
    , 1056.)
    II. Probable Cause
    “ ‘An action is deemed to have been pursued without probable cause if it
    was not legally tenable when viewed in an objective manner as of the time
    the action was initiated or while it was being prosecuted.’ ” (Neurelis, supra,
    71 Cal.App.5th at p. 800.) This inquiry “ ‘calls on the trial court to make an
    objective determination of the “reasonableness” of the defendant’s conduct.’ ”
    (Parrish v. Latham & Watkins (2017) 
    3 Cal.5th 767
    , 776 (Parrish).) It is not
    sufficient to establish that the prior claim was “ ‘ultimately found to lack
    12
    merit.’ ” (Neurelis, at p. 800.) The prior claim is “unsupported by probable
    cause only if ‘ “ ‘any reasonable attorney would agree [that it is] totally and
    completely without merit.’ ” ’ [Citations.] ‘This rather lenient standard for
    bringing a civil action reflects “the important public policy of avoiding the
    chilling of novel or debatable legal claims.” ’ [Citation.] The standard
    safeguards the right of both attorneys and their clients ‘ “ ‘to present issues
    that are arguably correct, even if it is extremely unlikely that they will
    win.’ ” ’ ” (Parrish, at p. 776.)
    Applying these principles, we affirm the finding that Lian Tong’s
    breach of contract claim against appellants was legally tenable. The BW
    contract stated that work would commence once the owner provided approved
    permits and drawings, without identifying any specific permit or drawing or
    delineating what approvals were required. The contract required Lian Tong
    to provide the “approved & stamp[ed] plan,” but it did not define this
    handwritten term that was added to the typed contract, or otherwise address
    who was responsible for obtaining approval from the Palms to start
    construction work at the site of the restaurant project. Thus, the language of
    the contract did not foreclose Lian Tong’s theory that they were required to
    provide BW Construction with copies of the preliminary architectural plans
    and designs that had been approved by the city, and that any subsequent
    approval, such as authorization from the Palms, would be secured by the
    contractors.
    Moreover, Lian Tong had evidence to support their theory. In 2013, the
    city approved Lian Tong’s preliminary construction plans and issued permits
    authorizing work to begin.3 Prior to execution of the BW contract, Lian Tong
    3 Appellants have filed two requests for judicial notice of documents
    pertaining to an application for an additional building permit that was dated
    13
    architect Derrick Wu discussed the project with a representative of the Palms
    who stated that the Palms did not oppose the project. And, after the BW
    contract was executed, Y.F. Liu told Liu that Chen had agreed to obtain
    formal approval from the Palms. Other witnesses who had been involved in
    the project testified that they too believed that Chen was responsible for
    obtaining approval from the Palms, including Palms representative Victoria
    Nguyen. There was also evidence that Chen did take steps to obtain approval
    from the Palms during the period the BW contract was in effect. Under these
    circumstances, it cannot be said that all reasonable lawyers would agree that
    Lian Tong’s breach of contract claim was totally and completely without
    merit.
    Appellants argue that evidence that BW Construction had a
    contractual obligation to obtain approval from the Palms is irrelevant,
    characterizing the issue of who was responsible for obtaining this approval as
    a “red herring.” The record of the underlying action shows otherwise. As our
    background summary reflects, the pleaded theory in the operative first
    amended complaint was that BW Construction and Chen breached the BW
    contract by failing to do any work during the period the BW contract was in
    effect, which included failing to secure approval from the Palms. Appellants
    did not just dispute this claim, they based their cross-complaint on
    allegations that it was Lian Tong rather than BW Construction who breached
    the BW contract by failing to secure consent for the project from the Palms.
    April 8, 2014. These requests are denied for two reasons. First, appellants
    are seeking notice of documents that were not before the court that ruled on
    the anti-SLAPP motions. (See e.g., Jozefowicz v. Allstate Ins. Co. (2019) 
    35 Cal.App.5th 829
    , 837, fn. 4.) Second, appellants fail to show that these
    documents are relevant to a material issue on appeal. (See e.g., People ex rel.
    Lockyer v. Shamrock Foods Co. (2000) 
    24 Cal.4th 415
    , 422, fn. 2.)
    14
    Appellants insist that the question of who was responsible for obtaining
    Palms approval never mattered in the underlying case. They reason that
    regardless of who was responsible for obtaining approval from the Palms,
    there was no basis for disputing that this necessary approval had not been
    secured in time for BW Construction to complete its work within the six-
    month contract period. At oral argument before this court, appellants
    presented another version of this theory, which posits that Lian Tong lacked
    probable cause because there was no basis for disputing that approval of the
    final design plans for the restaurant had not been obtained from the City’s
    Department of Building Inspection in time for BW Construction to complete
    its work within the six-month contract period. These hindsight arguments
    are both versions of appellants’ impossibility defense, which resonated with
    the trial court and resulted in the directed verdict. But the fact that
    appellants were able to prove their defense at trial does not mean there was
    no probable cause for the substantively different breach of contract claim
    alleged and litigated by Lian Tong, which was that appellants breached the
    BW contract not only or specifically because they failed to complete the
    project within six months, but because they failed to do any work, including
    failing to obtain approval from the Palms.
    Appellants offer three reasons why their successful result below
    compels a finding that Lian Tong’s breach of contract claim was prosecuted
    without probable cause. First, they contend that the directed verdict they
    obtained from Judge Lam compels a finding that there was no probable cause
    for Lian Tong’s breach of contract claim. Appellants reason that Judge Lam’s
    finding that there was no substantial evidence to support a verdict in favor of
    Lian Tong at trial proves that Lian Tong’s claim was objectively untenable.
    An analogous argument was rejected in Jarrow, supra, 
    31 Cal.4th 728
    , which
    15
    involved a malicious prosecution case that was filed after the underlying case
    was dismissed on summary judgment. As the Supreme Court explained, the
    fact that an underlying claim was terminated based on a finding of
    insufficiency of the evidence does not establish as a matter of law that
    probable cause to bring that claim was lacking. (Id. at pp. 742–743.)
    “[E]very case litigated to a conclusion has a losing party, but that does not
    mean the losing position was not arguably meritorious when it was pled.
    [Citation.] And just as an action that ultimately proves nonmeritorious may
    have been brought with probable cause, successfully defending a lawsuit does
    not establish that the suit was brought without probable cause.” (Id. at
    p. 743.)
    Appellants rely on Puryear v. Golden Bear Ins. Co. (1998) 
    66 Cal.App.4th 1188
    , which holds that “probable cause requires evidence
    sufficient to prevail in the action or at least information reasonably
    warranting an inference there is such evidence.” (Id. at p. 1195, italics
    added.) Appellants ignore the second part of this holding, which confirms
    that the probable cause analysis is substantively different from the question
    whether the underlying claim was ultimately proven by substantial evidence.
    (See also Arcaro v. Silva & Silva Enterprises Corp. (1999) 
    77 Cal.App.4th 152
    , 156–157 [“probable cause is lacking ‘when a prospective plaintiff and
    counsel do not have evidence sufficient to uphold a favorable judgment or
    information affording an inference that such evidence can be obtained for
    trial’ ”].) Here, for example, Lian Tong’s version of the events depended
    largely on Y.F. Liu, as he negotiated the BW contract on their behalf. Lian
    Tong also relied on expert testimony to support its theory that BW
    Construction was responsible for obtaining approval from the Palms. It was
    not until the case went to trial that it became clear that Y.F. Liu’s testimony
    16
    would be excluded, and that Derrick Wu would not be qualified as an expert
    regarding the responsibilities of a contractor. These facts provide additional
    support for concluding that Lian Tong’s claim was supported by probable
    cause.
    Appellants’ second theory is that respondents are collaterally estopped
    from disputing that the underlying breach of contract claim was unsupported
    by probable cause. The same theory was rejected in Plumley v. Mockett
    (2008) 
    164 Cal.App.4th 1031
    , 1049, which we follow here. Collateral estoppel
    precludes re-litigation of an issue only if it is “ ‘identical’ ” to an issue that
    was previously litigated and actually and necessarily decided on the merits in
    a prior proceeding. (Id. at pp. 1048–1049.) The issue whether probable cause
    supported Lian Tong’s breach of contract claim was neither litigated nor
    necessarily decided in the underlying action.
    Finally, appellants contend that a finding of probable cause cannot be
    based on the evidence that Lian Tong relied on in the underlying litigation
    because, when the court rules on an anti-SLAPP motion, all conflicts in the
    evidence must be resolved in favor of the plaintiff. (Citing Lee v. Kim (2019)
    
    41 Cal.App.5th 705
    .) “[I]n the ‘summary-judgment-like procedure’ of a
    special motion to strike we do not weigh evidence or resolve conflicting
    factual claims. [Citations.] We further must draw all reasonable inferences
    from the evidence in favor of . . . the plaintiff.” (Id. at p. 720.) But contrary
    to appellants’ contentions, these principles do not preclude us from
    considering the evidence Lian Tong relied on below. Indeed, that is the very
    inquiry we must undertake to conduct a probable cause inquiry. To put the
    matter another way, by confirming the trial court’s finding that some
    evidence supported Lian Tong’s breach of contract claim, we are neither
    crediting that evidence nor resolving conflicting factual claims. We are
    17
    simply recognizing that a reasonable attorney could find that Lian Tong’s
    claim was not totally and completely without merit. (Parrish, supra,
    3 Cal.5th at p. 776.)
    Appellants make lengthy arguments about why their evidence in the
    underlying action, when considered in isolation and viewed favorably to
    them, doomed Lian Tong’s breach of contract claim. These arguments do not
    alter our conclusion because the issue here is not whether appellants were
    entitled to a favorable judgment in the underlying case. The issue is whether
    Lian Tong’s claim was objectively untenable and, as discussed, they had
    evidence to support their pleaded theory. Thus, we affirm the trial court’s
    finding that appellants fail to carry their burden of proving that Lian Tong’s
    breach of contract case was prosecuted without probable cause.
    III. Malice
    “The ‘malice’ element of the malicious prosecution tort relates to the
    subjective intent or purpose with which the defendant acted in initiating the
    prior action.” (Sheldon Appel Co. v. Albert & Oliker (1989) 
    47 Cal.3d 863
    ,
    874.) “The motive of the defendant must have been something other than
    that of bringing a perceived guilty person to justice or the satisfaction in a
    civil action of some personal or financial purpose. [Citation.] The plaintiff
    must plead and prove actual ill will or some improper ulterior motive.”
    (Downey Venture v. LMI Ins. Co. (1998) 
    66 Cal.App.4th 478
    , 494, italics
    omitted; Soukup v. Law Offices of Herbert Hafif (2006) 
    39 Cal.4th 260
    , 292
    [quoting Downey].) Facts showing that a prior claim was filed without
    probable cause may support an inference of malice. (Soukup, at p. 292;
    Downey, at p. 498, fn. 29.) But “the absence of probable cause alone is
    insufficient to establish a prima facie case of malice.” (Roche v. Hyde (2020)
    
    51 Cal.App.5th 757
    , 826–827.) “ ‘In other words, the presence of malice must
    18
    be established by other, additional evidence,’ ” and must “ ‘include proof of
    either actual hostility or ill will on the part of the defendant or a subjective
    intent to deliberately misuse the legal system for personal gain or
    satisfaction at the expense of the wrongfully sued defendant.’ ” (HMS
    Capital, Inc. v. Lawyers Title Co. (2004) 
    118 Cal.App.4th 204
    , 218.)
    Applying these principles, we affirm the trial court’s finding that
    appellants fail to make a prima facie showing of malice as to either set of
    respondents. Appellants unsuccessfully rely on the rule that malice can be
    inferred from the absence of probable cause because, as explained, they fail to
    show that Lian Tong’s breach of contract claim was unsupported by probable
    cause. Moreover, appellants produce no additional evidence to show that
    either Lian Tong or Horner Law had an improper motive for bringing the
    prior action.
    Appellants contend that respondent Liu’s trial testimony in the
    underlying action constitutes evidence of Lian Tong’s malice. Specifically,
    appellants rely on testimony by Liu that he made the decision to sue
    appellants because he believed they had stolen contract funds and abandoned
    the project, which made him angry. Testimony to this effect would show that
    Liu was angry at appellants because he genuinely believed they breached the
    BW contract, which is not evidence of a nefarious motive unrelated to a
    legitimate litigation purpose.
    Appellants also argue that malice can be inferred from respondents’
    failure to conduct a factual investigation before filing the underlying action,
    citing Citizens of Humanity, LLC v. Hass (2020) 
    46 Cal.App.5th 589
    , 607–
    608. In that case, a jeans manufacturer (Citizens) obtained a dismissal with
    prejudice of a class action lawsuit alleging that Citizens engaged in an unfair
    business practice by mislabeling its jeans, and then filed a malicious
    19
    prosecution action against two class representatives and the attorneys who
    filed the underlying action. (Id. at pp. 593 & 595.) A special motion to strike
    Citizens’ complaint was denied because Citizen’s evidence was sufficient to
    establish a probability of prevailing on the merits as to each element of the
    malicious prosecution claim. (Id. at p. 597.) Prima facie proof of malice
    included evidence that the underlying lawsuit was filed on behalf of a “shill
    plaintiff,” for the improper purpose of forcing a settlement that was not
    related to the merits of the claim, and that attorneys filed the action without
    investigating the factual claims of the class representatives. (Id. at pp. 606–
    607.) We find no comparable evidence of malice in this record.
    Appellants use perceived weaknesses in Lian Tong’s breach of contract
    case to infer that an adequate investigation was not conducted. We are not
    persuaded by these convoluted arguments. For example, appellants contend
    that during trial in the prior action, Liu admitted he did not have personal
    knowledge about the negotiations that culminated in the 2015 termination
    contract, and that this so called admission is proof that Lian Tong filed the
    underlying action without knowing the true facts. We disagree. Liu relied on
    an agent (his father) to negotiate the contracts, a circumstance that does not
    strike us as remarkable or uncommon, and that does not support a
    reasonable inference of malice. Appellants also posit that Horner Law “did
    not discuss” or “investigate any of the case facts” with their clients. But they
    cite no evidence to prove these accusations, which are contradicted by
    attorney declarations that were filed in support of the anti-SLAPP motions.
    Taking a different tack, appellants contend that respondents did know
    the true facts, and yet knowingly presented false ones, thus showing their
    malice. Appellants cite Nunez v. Pennisi (2015) 
    241 Cal.App.4th 861
    , which
    states that malice can be found when “a plaintiff ‘asserts a claim with
    20
    knowledge of its falsity.’ ” (Id. at p. 877, italics omitted.) Appellants attempt
    to invoke this rule by contending that Lian Tong’s original complaint “falsely
    alleged construction was required to be completed by October 2014.” First,
    the original complaint contained no allegation to the effect that the BW
    contract required that construction be completed by October 2014. Rather,
    Lian Tong alleged that “[t]he parties agreed and understood that pursuant to
    the terms of the [BW contract], the Project was to be completed within six
    months or approximately by early October 2014.” Moreover, the BW contract
    was attached and incorporated into the original complaint, thus undermining
    appellants’ apparent theory that Lian Tong somehow misrepresented what
    the contract actually said.
    Appellants also contend malice can be inferred from alleged discovery
    abuses by respondents, citing Roche v. Hyde, supra, 
    51 Cal.App.5th 757
    .
    That malicious prosecution action was filed after termination of a lawsuit
    arising out the sale of Roche’s winery to Ram’s Gate. In the underlying
    litigation, Ram’s Gate alleged that Roche was liable for breach of contract
    and fraud for withholding a seismic report that materially impacted the value
    of the winery, but dismissed its action after evidence emerged that the report
    had been disclosed to Ram’s Gate attorney Hyde prior to the sale, and that
    Ram’s Gate had violated multiple discovery orders by suppressing this fact.
    In Roche’s malicious prosecution action, the appellate court affirmed orders
    denying anti-SLAPP motions filed by Ram’s Gate and Hyde. (Id. at p. 769.)
    In Roche v. Hyde, supra, 
    51 Cal.App.5th 757
    , the two primary issues on
    appeal were whether the winery litigation terminated in Roche’s favor and
    whether Ram’s Gate lacked probable cause to bring it, but the court also
    rejected attorney Hyde’s contention that Roche failed to make a prima facie
    showing of malice. Roche v. Hyde confirms the general principle that lack of
    21
    probable cause can raise an inference of malice but that the absence of
    probable cause alone is insufficient to establish a prima face case of malice.
    (Id. at pp. 826–827.) Roche’s additional evidence of malice consisted of “a
    pattern of discovery misconduct and the manner in which it was carried out.”
    (Id. at p. 827.) Specifically, Roche showed that the Ram’s Gate parties had
    deliberately withheld the seismic report in direct violation of multiple
    discovery orders under circumstances that amounted to fraudulent
    concealment. (Id. at p. 812.)
    Unlike the Roche v. Hyde plaintiff, appellants fail to show that the
    underlying claim against them was not supported by probable cause. Nor do
    they provide additional evidence of malice demonstrated through discovery
    misconduct. Instead, they misconstrue discovery disputes by portraying
    them as discovery abuse. For example, appellants attempt to infer malice
    from the fact that Lian Tong failed to produce Y.F. Liu for a deposition. But
    appellants’ motion to compel Y.F. Liu’s deposition was denied. Moreover, the
    in limine order precluding Y.F. Liu from testifying at trial via Skype was not
    based on a finding that Lian Tong engaged in misconduct, but that Y.F. Liu
    was an unavailable witness. Further, appellants likely benefited from Y.F.
    Liu’s unavailability, as Lian Tong sought to rely on his account of discussions
    with Chen. Appellants ignore all of these pertinent facts, which undermine
    their theory that the failure to produce Y.F. Liu is proof of malice.
    Finally, appellants contend that malice can be inferred from evidence
    that Horner Law attempted to coerce a settlement from appellants after it
    became clear that Lian Tong’s breach of contract claim was without merit.
    Appellants base this claim on Golden State Seafood, Inc. v. Schloss (2020) 
    53 Cal.App.5th 21
    , which is factually inapposite but confirms the general rule
    that malice can be inferred from continued prosecution of an action after a
    22
    plaintiff becomes aware that its action lacks probable cause. (Id. at p. 38.)
    Golden State Seafood also confirms the principle that an inference of malice
    must be supported by some evidence in addition to a lack of probable cause.
    (Ibid.) In that case, there was evidence that the underlying lawsuit was filed
    for the purpose of securing a settlement unrelated to the merits of the case.
    (Id. at pp. 38–39.)
    Here, appellants contend that malice can be inferred from a May 23,
    2019, confidential settlement communication Horner Law sent to appellants’
    counsel. In that letter, Horner Law proposed settling the entire dispute
    between the parties in exchange for mutual releases. As support for the
    proposal, Horner Law relied primarily on the fact that the superior court had
    just granted Lian Tong judgment on the pleadings with respect to appellants’
    first amended cross-complaint. Horner Law also argued that because
    appellants had demanded attorney fees in connection with their unsuccessful
    contract claims, Lian Tong could also demand fees incurred in defeating those
    claims, even absent an attorney fee clause. And Horner Law pointed out that
    appellants had yet to pay financial sanctions that had been imposed against
    them for their discovery violations.
    Appellants argue that Horner Law’s May 2019 settlement offer is
    evidence of malice because when the offer was made, Horner Law knew that
    (1) their client’s case was totally lacking in merit, and (2) there was no legal
    basis for claiming attorney fees against appellants. Both prongs of this
    argument are flawed.
    First, appellants contend that Horner Law had known since October
    2018 that their client’s case was totally lacking in merit. According to this
    argument, when appellants took the deposition of Palms representative
    Veronica Nguyen, Lian Tong’s entire case fell apart because Nguyen’s
    23
    testimony established that the Palms had not approved the restaurant
    project until January 2015. This fact was dispositive, appellants contend,
    because respondents “could no longer take the objectively baseless position
    [that] appellants breached the restaurant construction contract by failing to
    complete construction by October 2014.” This argument conflates Lian
    Tong’s breach of contract claim with appellants’ impossibility defense. Lian
    Tong’s claim was that appellants breached the BW contract by taking Lian
    Tong’s money and never doing any work on the project, not by failing to
    complete the entire project within six months of the date that the contract
    was executed.
    The second part of appellants’ argument is that malice can be inferred
    from the May 2019 settlement offer because Horner Law knew they had no
    legitimate basis for threatening to seek attorney fees from appellants if the
    case was not settled. Apparently, Horner Law’s claim that it could seek
    attorney fees was based on a misreading of Civil Code section 1717. But this
    legal error does not mean their confidential settlement offer supports an
    inference of malice.
    The record shows that the May 2019 letter was sent shortly after Lian
    Tong obtained favorable rulings on its motions for judgment on the pleadings
    and/or to strike appellants’ first amended cross-claims. Thus, the settlement
    proposal offered appellants an opportunity to end the litigation without
    incurring the expense of revising their own theories and having to defend
    against a viable breach of contract claim. Regardless of whether the
    “threat[]” to seek attorney fees was objectively sound, it appears that the May
    2019 settlement offer was based on Horner Law’s subjective assessment of
    the value of appellants’ claims at that point in the litigation. Appellants fail
    to point to any other evidence that would support an inference of malice.
    24
    IV. The Attorney Fees Orders
    Appellants do not separately address the orders granting respondents
    attorney fees. Their sole contention is that these orders must be reversed
    because the anti-SLAPP motions should not have been granted. As
    explained, appellants fail to show that the trial court erred by granting
    respondents’ special motions to strike appellants’ malicious prosecution
    claim.
    “Section 425.16, subdivision (c) authorizes an award of attorney fees
    and costs to the prevailing party. Further, the right of a prevailing defendant
    to recover attorney fees and costs adequately compensates him for ‘the
    expense of responding to a baseless lawsuit.’ ” (Conroy v. Spitzer (1999) 
    70 Cal.App.4th 1446
    , 1454–1455.) Respondents are the prevailing defendants
    on the special motions to strike and, therefore, their motions for attorney fees
    were properly granted. (§ 425.16, subd. (c).)
    DISPOSITION
    Appellants filed four separate appeals from the orders granting the
    special motions to strike and awarding respondents attorney fees, which were
    consolidated in this court. The appealed orders are all affirmed.
    Respondents are awarded costs on appeal.
    TUCHER, P.J.
    WE CONCUR:
    PETROU, J.
    RODRÍGUEZ, J.
    25
    Bing Wu et al. v. Lian Tong, LLC, et al. (A163131/A163455/A163635/A163768)
    26