Sema Construction v. City of Tustin CA4/3 ( 2014 )


Menu:
  • Filed 5/13/14 Sema Construction v. City of Tustin CA4/3
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
    or ordered published for purposes of rule 8.1115.
    IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
    FOURTH APPELLATE DISTRICT
    DIVISION THREE
    SEMA CONSTRUCTION, INC.,
    Plaintiff and Appellant,                                          G046874
    v.                                                  (Super. Ct. No. 30-2008-00101147)
    CITY OF TUSTIN,                                                        OPINION
    Defendant and Respondent.
    Appeal from a judgment of the Superior Court of Orange County, Kim
    Garlin Dunning, Judge. Affirmed.
    Musick, Peeler & Garrett and Jack W. Fleming; Snell & Wilmer, Richard
    A. Derevan and Todd E. Lundell for Plaintiff and Appellant.
    Woodruff, Spradlin & Smart, M. Lois Bobak, Joseph W. Forbath and
    Magdalena Lona-Wiant for Defendant and Respondent.
    *               *               *
    Plaintiff SEMA Construction, Inc. (SEMA) appeals from a judgment
    awarding it $486,555 in compensatory damages plus prejudgment interest against
    defendant City of Tustin (Tustin) in an action for breach of a public works contract. The
    judgment is based on Tustin’s underpayment for SEMA’s disposal of groundwater from a
    construction site. SEMA contends the trial court erred in limiting its recovery, arguing
    the terms of the parties’ contract and their conduct before any dispute arose entitled it to a
    much larger award. Finding no error, we affirm the judgment.
    FACTS AND PROCEDURAL BACKGROUND
    1. Background
    SEMA was the successful bidder on a $23.8 million contract to build roads
    on property within an area previously used by the United States Marine Corp. as a
    helicopter base. The area is referred to as the Tustin Legacy project. The work included
    “construction of sanitary sewers, storm drains, reclaimed water lines, [and] domestic
    water lines.” Irvine Ranch Water District (IRWD) was the entity that would take over
    operation of the completed pipelines and it entered into a contract with Tustin to
    reimburse it for certain construction related expenses.
    The contract consisted of six lettered sections and two appendices.
    Sections A and B covered Tustin’s notice to contractors of the project, plus blank
    contractor bid forms. Section C was the contract agreement containing SEMA’s
    successful bids for each item of work to be performed, its performance and labor and
    material bonds, and insurance certificate. Section D contained the contract’s general
    provisions. Sections E and EH covered special contract terms. The latter part, section
    EH, dealt with construction work in a portion of the project known to have soil
    contamination and described as the Area of Institutional Control (AIC). In part, the
    2
    contract required SEMA to obtain and bear the cost of “all permits . . . for this project”
    and to “comply with all rules and regulations included in [the] permits.”
    The contract’s general provisions also incorporated the most recent edition
    of the Standard Specifications for Public Works (i.e., “Greenbook”) and declared the
    Greenbook “will control . . . except as amended by the plans, these special provisions, or
    other contract documents.” The Greenbook provides that “[n]ew or unforeseen work will
    be classified as ‘extra work’ when the Engineer determines that it is not covered by
    Contract Unit Prices or stipulated unit prices.” In the event “extra work is deemed
    necessary, the scope of the work shall be documented under the terms and conditions of
    the City[’s] . . . Contract Change Order form . . . .”
    The portion of the agreement that covered installing drains and water lines
    required SEMA to remove groundwater seeping into the trenches during construction, a
    process known as dewatering. Payment for the cost of dewatering was covered in two
    separate contract sections. Under section C, SEMA agreed to receive a lump sum of
    $380,700 for sheeting, shoring, bracing and dewatering the sewer, storm, and water
    trenches. Section E-21 stated “the lump sum contract price[]” for this work “shall be
    considered full compensation . . . and no additional compensation will be allowed.”
    Section EH required SEMA to perform groundwater sampling in the AIC.
    Additive Bid Item A4, covering the treatment of contaminated liquids, specified
    “contaminated groundwater generated during dewatering activities, . . . be treated, if
    required by permit” through “a granular activated carbon (GAC) treatment system”
    before being “disposed into a sanitary sewer or off-site wastewater treatment facility.”
    SEMA was also directed to “obtain and pay for any permit required for disposal to
    the . . . sewer system from [IRWD].”
    The contract authorized SEMA to receive “payment for the actual
    quantities [treated] . . . multiplied by the unit price[] stated,” but specified the
    “[d]etermination[] of the actual quantities . . . will be made by the [City] Engineer,”
    3
    which after “review with the Contractor . . . will be final and binding.” SEMA agreed to
    charge a fixed unit price of 16 cents per gallon for this work. Tustin’s request for bids
    estimated the amount of contaminated liquids requiring GAC treatment at 500,000
    gallons, but warned this figure was “approximate only.”
    In its April 2005 notice to proceed with the work, Tustin informed SEMA it
    had retained Washington Group International, Inc. (WGI) to administer the project and
    Arturo Diaz, WGI’s resident engineer, was the construction manager. SEMA was told to
    direct “[a]ll official correspondence and billing” to Diaz.
    After SEMA was awarded the contract, the parties learned IRWD either
    would not or could not allow the discharge of groundwater into its system. It was then
    decided to obtain a discharge permit from the Orange County Sanitation District (OCSD)
    and dispose of the groundwater through its facilities. OCSD required the permit
    application to be filed by Tustin. In addition, it agreed to issue the permit only if SEMA
    treated all groundwater removed from the entire project site through dewatering with the
    GAC process before discharging it into the sewer system. SEMA informed Diaz it
    expected to be paid for the treatment of all groundwater at the Bid Item A4 unit price.
    On September 2, 2005, Diaz sent SEMA a letter stating he would issue a
    contract change order (CCO 19) to use the Bid Item A4 method of payment for the
    treatment of liquids “processed through the treatment facility and disposed to the [s]ewer
    [s]ystem.” OCSD issued its permit four days later and Diaz issued CCO 19 the same day.
    However, CCO 19 listed the price adjustment as “0.00.” At trial Diaz testified, “This
    change order was just for modification to allow payment of hazardous and nonhazardous
    water, in that at that time it was not anticipated [the quantity treated] w[ould] exceed the
    quantity allowed in the contract . . . .”
    By September 20 SEMA had discharged 880,000 gallons of GAC treated
    groundwater through OCSD’s system. SEMA submitted an invoice to Tustin requesting
    payment for this work at the Bid Item A4 unit price. Tustin paid the invoice. However,
    4
    by October 4, SEMA had treated and discharged approximately 2.5 million gallons of
    groundwater.
    On September 26, a meeting was held between Diaz and city officials about
    the need to renegotiate the cost for the dewatering process. The next day, Diaz issued
    another contract change order (CCO 2). It stated, in part, “Quantity beyond 125% of the
    original Bid Item [A4] (i.e. 625,000 Gallons) will be subject to adjustment” under the
    Greenbook’s provisions governing changes in work initiated by a contracting agency.
    Under section 3-2.2.1 of the Greenbook, where “a change is ordered in an
    item of work covered by a Contract Unit Price . . . [not] involv[ing] a substantial change
    in character of the work,” an adjustment in payment “will be based upon the increase or
    decrease in quantity and the Contract Unit Price.” But “[a]djustments in excess of 25
    percent [of the total cost of a bid item] may be done by [either] extension of Contract
    Unit Prices as described above, or pursuant to 3-2.2.3.” The latter provision states
    “[a]djustments in payment for changes . . . will be determined by agreement between
    Contractor and Agency” and, if they are “unable to reach agreement, the Agency may
    direct the Contractor to proceed on the basis of Extra Work in accordance with 3-3,”
    which authorizes a contractor to be paid on a time and materials, plus markup basis
    through the use of “daily report[s] . . . listing all labor, materials, and equipment involved
    for that day . . . .”
    On October 6, SEMA sent WGI and Diaz a letter declining to sign either
    CCO 19 or CCO 2. As for CCO 19, SEMA noted it “was poorly drafted in that it did not
    have quantities, cost, or adjustment of time.” SEMA refused to sign CCO 2 because “as
    drafted . . . it changed the specifications retroactively while the work is progressing on an
    item of work.” The letter then stated: “A meter reading will be taken by the end of
    business day on October 6, 2005 and the City must pay SEMA for such quantity
    according to the existing specifications. After October 6 . . . the item will be paid with
    adjustment upon the City drafting a new CCO to reflect that.”
    5
    Diaz responded to SEMA’s October 6 correspondence a few weeks later.
    He summarized some relevant contract terms and events concerning the dewatering issue
    and stated as follows: “It was never envisioned that water outside of the [AIC] would
    require filtration prior to discharge. However, the permit issued by the OCSD requires
    that all groundwater be filtered . . . . Initially, as a convenience, the City chose to utilize
    an existing bid item (A4) for this new work. As it is now obvious that the quantity of
    water to be discharged . . . far exceeds the original estimated units . . ., it is appropriate
    that an adjustment be made for payment for the work. [¶] [T]he City suggests . . . that
    payment under Bid Item Number A4 be fixed at 500 units [per 1,000 gallons] at the price
    bid. Thereafter, any additional costs incurred as a result of additional work performed by
    SEMA would be reimbursed on either a Time and Materials basis, or on a unit price basis
    if such unit price is agreeable between the parties.”
    The letter gave SEMA until October 31 to respond “regarding which
    method of payment i[t] preferred,” which was later extended to November 4. Diaz
    also requested SEMA provide documentation on “costs to date” and its “calculation of
    cost . . . on a unit price basis for the first 500 units, as well as subsequent units” and
    warned “[i]f SEMA fails to provide the requested information,” “the City will issue a
    unilateral Change Order . . . setting forth the method of payment and corresponding rates.
    SEMA may pursue the applicable remedies provided under the contract, if it disagrees
    with the City’s decisions.”
    In a November 1 letter to WGI and Diaz, SEMA’s project manager stated
    in part: “October 6 . . . is the date which SEMA . . . received WGI’s CCO 2 changing bid
    item A4 to be subject to the 125% adjustment clause. It is SEMA’s position that we
    should be paid at the bid item price for water treated through October 6 . . . . However,
    we understand that this pay request . . . does not reflect what the City intends to pay
    under bid item A4. We understand that the City will not continue to pay for water treated
    at bid item price beyond what has been paid to date . . . .” Diaz answered SEMA’s
    6
    correspondence on November 11, reiterating Tustin’s request for documentation
    concerning the “costs to date” and “calculation of cost” for “subsequent units.” He also
    stated, “The City still believes it is important for both parties to resolve this matter as
    soon as possible to mitigate future claims.”
    SEMA’s project manager finally responded to Diaz’s October 21
    correspondence on November 14. He disagreed “with [Diaz’s] summary of what
    transpired in some of the meetings,” and noted “[u]pon . . . receiving draft CCO 2 and
    recognizing that the City elected to adjust the bid price, SEMA was willing to accept a
    price adjustment to the bid item but did not agree with the retroactive effect that CCO 2
    had. [¶] SEMA is committed to working with the City in resolving this issue . . . .”
    The parties never reached an agreement on the amount owed to SEMA for
    its dewatering and SEMA did not provide Tustin with the requested time and materials
    cost information. But the trial court found relevant the following portion of a November
    29 letter a Tustin engineering services manager sent to an IRWD project manager.
    That letter stated in relevant part as follows: “From the onset of
    the . . . excavation activities for the . . . sewer mainline . . ., the project has had issues
    with the proper handling and disposal of groundwater. . . . Moreover, . . . the [OCSD]
    required that ALL groundwater being discharged to the sewer would require treatment
    utilizing a [GAC] filter. At the time the contract was bid, it was anticipated that the only
    treatment required would be in the AIC. [¶] As the contractor’s operations were in
    suspension due to the dewatering issues, the City made the determination that all water
    should be treated and pumped into the OCSD sewer facility . . . . As a result of the
    changed conditions for discharge (i.e. the requirement for GAC treatment), and to
    preclude further delays to the contractor . . . [t]he city directed the contractor to utilize the
    existing bid item for treated water (Bid Item A4) for all water discharged into the OCSD
    facilities. [¶] As this is clearly a change of condition, we have requested the contractor
    provide information regarding [its] incurred costs for treating the additional volume of
    7
    water. It is our intention to pay the bid price for treated water up to the engineer’s
    estimated quantity and negotiate a price for the additional quantity of water treated.”
    The resolution of the dewatering price issue was further complicated by
    leaks from manhole pipes and covers installed by a SEMA subcontractor named Precon.
    SEMA eventually determined Precon was responsible for the leaks and reached a
    settlement with it. Tyler Faulkner, SEMA’s project manager, sent an e-mail to Azzam
    Saad, its contracts manager, in August 2006 stating the “dewatering for repairs . . . is in
    the range of 20 million gallons in the past 7-8 months.” At trial, Faulkner stated on direct
    examination, this estimate “was kind of an out-of-the-hat number . . . to scare Precon.”
    When cross-examined, he acknowledged he reviewed the project’s file before sending the
    e-mail and “intended to provide Mr. Saad with accurate information.” In addition, Tustin
    impeached Faulkner with testimony from his deposition where he also admitted using the
    project file to make the estimate rather than picking a number “out of thin air.”
    During the course of the project, SEMA treated over 36.5 million gallons of
    groundwater that was discharged into OCSD’s sewers.
    2. The Litigation
    SEMA sued Tustin seeking over $5.8 million in compensatory damages. In
    turn, Tustin filed a cross-complaint for indemnity against IRWD. Initially, the parties
    agreed to try the case in two phases, the first based on the complaint.
    At the end of phase one, the trial court issued a 15-page statement of
    decision explaining the basis of its decision on three issues. First, the court rejected
    SEMA’s claim it was entitled to be paid at the rate of $.16 for each gallon of liquid it
    treated through the dewatering process. The court stated, “Bid Item A4 was intended to
    apply only to the pre-disposal treatment of contaminated groundwater in the [AIC],” and
    “OCSD[’s] permit requirement for the treatment of all groundwater before disposal did
    not expand the reach of . . . Bid Item A4 . . . .” It also found “no credible evidence, from
    8
    [SEMA’s] expert . . . or otherwise, to support a reliable calculation as to the amount of
    groundwater extracted and treated from areas inside the AIC, compared to areas out the
    AIC.”
    Second, the court held Tustin was not financially obligated to pay for all of
    the groundwater SEMA treated. It credited SEMA’s own expert’s admission on cross-
    examination that “the treatment and dewatering that occurred when SEMA was repairing
    faulty work should not be charged to [Tustin].” But the court rejected this witness’
    estimate that the repairs caused only 7.4 million gallons of additional groundwater, noting
    he acknowledged “no expert could review these records after the fact and accurately
    estimate” the amount of “treated groundwater . . . attributable to [the] repair work.” In
    contrast, the court found Faulkner’s original e-mail estimate “credible and reliable,”
    citing his “testimony . . ., including those portions of impeachment testimony read from
    his deposition.” Thus, it found “the total number of gallons of groundwater treated per
    the requirements of the OCSD permit and potentially properly chargeable to [Tustin] to
    be 36.5 million gallons less 20 million gallons, for a total of 16.5 million gallons.”
    Finally, the court found Tustin owed SEMA additional sums for the
    treatment of groundwater, but limited the recovery to the groundwater treated through
    October 6, 2005. The court held Tustin was “bound by Mr. Diaz’s September 2, 2005
    letter . . . concerning the . . . interim agreement to pay . . . Bid Item A4’s Contract Unit
    Price to treat groundwater outside the AIC,” which Tustin “ratified . . . in its November
    29, 2005 letter to IRWD.” However, it concluded “the decision to initially use . . . Bid
    Item A4 to temporarily cover the costs of treating all groundwater was a convenience to
    keep the project moving” and “did not constitute a modification of the terms of . . . [the]
    A4 Bid Item” other than “to allow the use of already-budgeted contract funds for a
    limited time to deal with the OCSD’s unanticipated permit requirement.”
    Citing the “written exchange[s] . . . in the September – November 2005
    time frame,” the court found “both parties understood [Tustin] was obligated to pay
    9
    [SEMA] at the . . . Bid Item A4 rate . . . for all water treated through . . . October 6,
    2005.” The parties stipulated SEMA treated 3,920,970 gallons of groundwater through
    October 6, 880,000 of which Tustin had already paid SEMA at the rate of $.16 per gallon.
    That left an unpaid balance of 3,040,970 gallons and, at the $.16 per gallon rate, Tustin
    owed SEMA $465,555.
    The court then addressed SEMA’s entitlement to be paid for the remaining
    balance of 12,579,030 gallons of groundwater it had treated. In doing so, the court
    applied the provisions of the Greenbook. It held the amount SEMA would be entitled to
    receive was governed by sections 3-2.2.3 and 3-3. Section 3-2.2.3 states in relevant part,
    “[a]djustments in payments for changes . . . will be determined by agreement between
    Contractor and Agency,” or “[i]f [they are] unable to reach agreement, the Agency may
    direct the Contractor to proceed on the basis of Extra Work in accordance with 3-3.” As
    noted above, section 3-3 authorizes payment for work on a time and materials plus
    markup basis.
    In support of this conclusion, the court found: (1) OCSD’s permit
    “requirement to pre-treat all groundwater before disposal, whether or not tested for
    contamination and everywhere on the site, within and beyond the AIC” constituted both
    “‘change initiated by the agency’” and “‘involve[d] a substantial change in character of
    the work from that shown on the Plans or included in the Specifications’ for a Contract
    Unit Price item”; and (2) given the “undisputed evidence that the total cost for the new
    work was more than 33 times the original estimate,” “[t]he additional groundwater
    treatment far exceeded 25% of the total cost of such treatment . . . .” Referring to Diaz’s
    October 21, 2005 letter to SEMA, the court further found Tustin “acted under section 3-3
    when it asked SEMA to furnish ‘time and material’ calculations and other pertinent cost
    information,” but noted “the evidence was undisputed that SEMA never complied with
    [Tustin’s] request . . . .”
    10
    The court agreed SEMA’s failure to provide documentation of its costs to
    Tustin during construction did not preclude its recovery at trial. But, citing SEMA’s
    “deliberate decision in the litigation not to offer any ‘time and materials plus markup’
    evidence at trial, . . . despite several exchanges with the court and opposing counsel on
    this very issue,” the court declined to award any amount because “there [wa]s no
    evidence in the form of daily reports” or other “competent evidence in the trial record
    upon which to make such an award.” Rather, since SEMA “chose to rely on the legal
    argument as a matter of contract interpretation that it was entitled to $.16 per gallon
    for all groundwater treatment during construction,” the court held SEMA “knowingly
    waived the right to collect time and materials plus markup payments for the
    12,579,030 . . . gallons of dewatering water treated after October 6, 2005.”
    After the court entered judgment on the complaint, Tustin dismissed its
    cross-complaint against IRWD.
    DISCUSSION
    1. Introduction
    The following legal principles apply in this case. The rules of contract
    interpretation generally governing contracts between private parties apply to the
    public works contract at issue here. (P&D Consultants, Inc. v. City of Carlsbad (2010)
    
    190 Cal. App. 4th 1332
    , 1340; Civ. Code, § 1635.) “‘[T]he primary object of all
    interpretation is to ascertain and carry out the intention of the parties’” (City of
    Manhattan Beach v. Superior Court (1996) 
    13 Cal. 4th 232
    , 238) “as it existed at the time
    of contracting . . . .” (Civ. Code, § 1636.) “‘All the rules of interpretation must be
    considered and each given its proper weight, where necessary, in order to arrive at the
    true effect of the instrument.’” (City of Manhattan Beach v. Superior 
    Court, supra
    , 13
    Cal.4th at p. 238.) “‘[L]anguage in a contract must be interpreted as a whole, and in the
    11
    circumstances of the case,’” and “[c]onstruction cannot lead to unfair or absurd results
    but must be reasonable and fair.” (California National Bank v. Woodbridge Plaza LLC
    (2008) 
    164 Cal. App. 4th 137
    , 143.)
    As a general rule, “‘“[A]n appellate court is not bound by a construction of
    the contract based solely upon the terms of the written instrument without the aid of
    evidence [citations], where there is no conflict in the evidence [citations], or a
    determination has been made upon incompetent evidence [citation].”’” (City of
    Manhattan Beach v. Superior 
    Court, supra
    , 13 Cal.4th at p. 238; see also Parsons v.
    Bristol Development Co. (1965) 
    62 Cal. 2d 861
    , 865-866.) But “[o]n an appeal
    challenging the interpretation given to a writing, . . . the substantial evidence rule will
    apply in cases where the parties present conflicting extrinsic evidence to aid in the
    interpretation.” (Burch v. Premier Homes, LLC (2011) 
    199 Cal. App. 4th 730
    , 742.) In
    this circumstance, “we examine the evidence in the light most favorable to the prevailing
    party and give that party the benefit of every reasonable inference. We accept all
    evidence favorable to the prevailing party as true and discard contrary evidence. We do
    not reweigh the evidence or reconsider credibility determinations.” (Katsura v. City of
    San Buenaventura (2007) 
    155 Cal. App. 4th 104
    , 107.)
    2. Analysis
    SEMA attacks the trial court’s decision on several grounds. We find all of
    its contentions lack merit.
    First, SEMA claims the court erred in construing the contract to mean its
    right to recover $.16 per gallon for treatment of groundwater was limited to the area
    covered by the AIC. It argues the terms of the contract do not limit Bid Item A4 to that
    area, noting it was required to create an environmental work plan for the project that
    included a contingency plan for contaminated materials discovered outside of the AIC
    and that the engineer had authority to apply the requirements of section EH if
    12
    contaminated materials were discovered elsewhere. In addition, SEMA focuses on the
    fact the contract obligated it to obtain all required permits and to comply with the
    requirements imposed by them.
    What SEMA ignores is the fact Bid Item A4 related only to the treatment of
    groundwater and other liquids found to be contaminated. Contrary to its interpretation of
    the contract, SEMA was not automatically entitled to charge $.16 per gallon for all
    groundwater disposed from the AIC or anywhere else within the project site. Rather, the
    contract acknowledged the AIC was an area where contaminants in the soil and
    groundwater were known to exist. The contract contained provisions requiring SEMA to
    conduct testing for the presence of contaminants within the AIC as well as a contingency
    plan in the event contaminants were discovered elsewhere in the project site. But in each
    case, SEMA was entitled to charge the Bid Item A4 price only for its treatment of
    contaminated material.
    SEMA places great emphasis on the fact the contract obligated it to obtain
    and adhere to the requirements of permits, including permits for the discharge of
    groundwater and that OCSD’s permit directed it to treat all groundwater. But as noted,
    we must construe the contract “as to give effect to the mutual intention of the parties as it
    existed at the time of contracting.” (Civ. Code, § 1636.) SEMA acknowledges in its
    opening brief, and the parties stipulated at trial, that IRWD was involved in the project to
    install sewers and pipelines in the Tustin Legacy site and had even agreed to reimburse
    Tustin for part of the expense to do this work. The portion of the contract applying to
    “[c]ontaminated liquids . . . generated during dewatering activities,” expressly stated
    SEMA “shall obtain and pay for any permit required for disposal to the sanitary sewer
    system from [IRWD].” Thus, it is reasonable to assume that when the parties entered
    into the contract they both understood IRWD would issue a permit requiring only
    contaminated groundwater or other liquids be subjected to the more expensive GAC
    treatment before discharge.
    13
    This assumption went out the window when IRWD backed out of allowing
    the use of its facilities to dispose of groundwater and other liquids. The permit obtained
    from OCSD several months later substantially altered the handling of groundwater during
    the dewatering process. OCSD insisted all groundwater from the entire project site,
    contaminated or not, be subjected to the GAC treatment process before being discharged
    into its sewer system. The mere fact that OCSD’s permit required GAC treatment for all
    groundwater did not magically extend the Bid Item A4 unit price, which by its terms only
    applied to contaminated water encountered in one section of the project site, to the
    discharge of all groundwater.
    SEMA alternatively argues Diaz authorized it to charge $.16 per gallon for
    its treatment of all groundwater in his September 2, 2005 letter. But the trial court found
    this authorization, which Tustin ratified, was only an interim decision to avoid further
    delays in completing the project. SEMA disputes this conclusion, but the issue presents a
    credibility question and we defer to the trial court’s findings on it. (Nestle v. Santa
    Monica (1972) 
    6 Cal. 3d 920
    , 925.) Further, even SEMA’s own correspondence
    recognized Diaz’s September 2 authorization was not set in stone. It acknowledged
    Tustin’s right to adjust the compensation owed to it for treating all groundwater, but only
    objected to the city’s attempt to do so after the fact. SEMA’s project manager explained
    in his October 6 letter that he refused to sign CCO 2 because “as drafted . . . it changed
    the specifications retroactively while the work is progressing on an item of work.”
    (Italics added.) Again, on November 14, the project manager wrote to Diaz stating,
    “Upon . . . receiving draft CCO 2 and recognizing that the City elected to adjust the bid
    price, SEMA was willing accept a price adjustment to the bid item but did not agree with
    the retroactive effect that CCO 2 had.” (Italics added.) The trial court found in SEMA’s
    favor on this point, awarding it recovery at the unit price for all groundwater it treated
    through October 6, 2005.
    14
    Next, SEMA attacks the trial court’s 20 million gallon reduction in the
    amount of groundwater subject to compensation due to its subcontractor’s faulty work. It
    relies on Faulkner’s direct examination testimony deriding his 20 million gallon e-mail
    estimate as “an out-of-the-hat number . . . to scare Precon.” But the trial court relied on
    not only that e-mail, which Faulkner sent to a co-employee and not Precon, but his
    admissions during cross-examination, plus the impeachment of his testimony with a
    contrary statement from his deposition. We conclude the record supports the trial court’s
    resolution of this disputed issue. (Foreman & Clark Corp. v. Fallon (1971) 
    3 Cal. 3d 875
    ,
    881 [“‘When a finding of fact is attacked on the ground that there is not any substantial
    evidence to sustain it, the power of an appellate court begins and ends with the
    determination as to whether there is any substantial evidence contradicted or
    uncontradicted which will support the finding of fact’”].) Merely because there was
    contrary evidence rejected by the trial court does not justify a reversal of this finding.
    As the trial court found OCSD’s permit requirement concerning the
    handling of groundwater discharged into its sewers amounted to a substantial change in
    the character of the work contemplated by the parties when they entered into the contract.
    Since the evidence established the parties never reached an agreement on compensation
    for the groundwater treated after October 6, 2005, the court invoked the terms of the
    Greenbook to determine SEMA was entitled to compensation for its treatment of the
    balance of the groundwater on a time and materials plus markup basis. However, due to
    SEMA’s tactical choice to stand on its $.16 per gallon claim and refusal to present
    evidence justifying an award for time and materials, plus markup, the court declined to
    award anything to it.
    SEMA’s final contention challenges this ruling, arguing the contract
    excluded the use of “the Greenbook’s safety valve” to allow for adjustment of the unit
    price for a deviation in the quantity of contaminated material from Tustin’s original
    estimate. Its interpretation misconstrues the parties’ contract. First, the contract
    15
    expressly declared the Greenbook’s provisions applied “except as amended by the plans,
    the[] special provisions, or other contract documents.” Second, the clause on which
    SEMA relies only precluded the “[a]djustment of unit prices for [the] Additive Bid
    Item[s]” where it resulted “due to a variation from the estimated quantities . . . .” By its
    terms, this clause was limited to variations in the amount of contaminated materials
    included within the Additive Bid Items. Here, as the trial court found, OCSD’s
    requirement that all groundwater, contaminated or not, be treated with the GAC process,
    thereby resulting in a 33-fold increase in the volume of treated groundwater, constituted a
    substantial change in the character of the work, not merely a variation in the quantity of
    contaminated liquids requiring treatment before discharge.
    DISPOSITION
    The judgment is affirmed. Respondent shall be entitled to its costs on
    appeal.
    RYLAARSDAM, ACTING P. J.
    WE CONCUR:
    ARONSON, J.
    FYBEL, J.
    16
    