Ondraka v. Bochinski, Inc. CA4/1 ( 2014 )


Menu:
  • Filed 2/14/14 Ondraka v. Bochinski, Inc. CA4/1
    NOT TO BE PUBLISHED IN OFFICIAL REPORTS
    California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
    publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
    or ordered published for purposes of rule 8.1115.
    COURT OF APPEAL, FOURTH APPELLATE DISTRICT
    DIVISION ONE
    STATE OF CALIFORNIA
    JOSEPH ONDRAKA et al.,                                              D060970
    Plaintiffs and Appellants,
    v.                                                         (Super. Ct. No. GIN55193)
    BOCHINSKI, INC., et al.,
    Defendants and Respondents.
    APPEAL from a judgment of the Superior Court of San Diego County, William S.
    Dato, Judge. Affirmed.
    David A. Kay for Plaintiffs and Appellants.
    No appearance for Defendants and Respondents.
    INTRODUCTION
    Joseph and Annette Ondraka appeal from a judgment awarding them a net amount
    of $3,697 in their action against Bochinski, Inc. (corporation) and Stephen Bochinski
    (Bochinski) for breach of contract and other claims. They contend we must reverse the
    judgment because the court: (1) did not allow them to establish the invalidity of the
    corporation's contractor's license through alter ego evidence; (2) mistakenly determined
    Business and Professions Code section 7159 1 did not apply; (3) mistakenly determined
    the parties modified the change order procedures in their contract by their conduct; (4)
    failed to interpret key contract provisions against the corporation as the contract drafter ;
    (5) mistakenly found Bochinski's testimony credible; (6) awarded the corporation an
    excessive amount on its cross-complaint; and (7) deprived them of due process of law.
    We conclude each of these contentions lacks merit and affirm the judgment.
    BACKGROUND
    The Ondrakas contracted with the corporation, a general contracting firm run by
    Bochinski, to build a main house on their property (project). The corporation had
    previously built a guest house on the same property. Under the terms of the contract, the
    corporation agreed to furnish all labor, materials, equipment and other facilities required
    to complete the project according to certain plans prepared by the Ondrakas' architect.
    The Ondrakas agreed to pay the corporation $730,487.13, "subject to adjustments for
    [c]hanges in the work as may be agreed to by the [parties]" or required by the contract.
    Exhibit 2 of the contract contained a cost breakdown specifying both the work covered by
    the contract as well as the work outside the scope of the contract for which the Ondrakas
    were solely responsible.
    1     Further statutory references are also to the Business and Professions Code unless
    otherwise stated.
    2
    The contract identified November 1, 2005, as the approximate project completion
    date. The Ondrakas negotiated for this completion date because of financing concerns if
    the project was not completed within one year. The contract further provided that "[t]ime
    is of the essence" and required the corporation to give the Ondrakas a progress and
    completion schedule (schedule) and to conform to the schedule, including to any agreed
    upon schedule changes, schedule changes otherwise allowed under the contract, or
    schedule changes required by circumstances beyond the corporation's control.
    Nonetheless, the contract excused the corporation for any delay in completing the project
    caused by, among other occurrences, acts of the Ondrakas or their agents and unforeseen
    contingencies beyond the corporation's control.
    The contract permitted the Ondrakas to change the project's scope of work with
    written notice to the corporation. If the Ondrakas' changes, plan errors, or circumstances
    beyond the control of the corporation required an adjustment to the contract price or
    schedule, the corporation was to submit an estimate of the adjustment to the Ondrakas.
    Any price adjustments were to be generally consistent with the contract's pricing
    structure. However, to the extent the contract's pricing structure was inapplicable, the
    contract provided "the cost of the [c]hange and/or the adjustment to the [schedule] shall
    be determined by time and materials on the basis of the cost to the [corporation] plus five
    percent (5%) for overhead, and fifteen percent (15%) for supervision and profit." The
    corporation was not required to perform a change until it and the Ondrakas agreed in
    writing on the specifics of the change, the cost or credit for it, and the schedule
    adjustment.
    3
    If the Ondrakas failed to make a payment required by the contract, the contract
    permitted the corporation to suspend its work until paid. Similarly if the Ondrakas
    disputed a change or payment for a change, the contract permitted the corporation to
    suspend its work until the dispute was resolved.
    The contract also permitted the Ondrakas to terminate the work at their
    convenience with written notice to the corporation. If the Ondrakas terminated the work,
    they had to pay the corporation its actual costs for the work performed up to the
    termination date, as well as the actual costs incurred because of the termination, plus 20
    percent for supervision and profit.
    As the project progressed, the parties did not follow the contract's change order
    procedures. Instead, Bochinski would verbally advise the Ondrakas when a change was
    necessary, or the Ondrakas would verbally advise Bochinski about a change they desired.
    Bochinski would give the Ondrakas a general price range for the change and the
    corporation would bill for the change on a time and materials basis. There was rarely any
    discussion or written statement regarding the effect of the change on the project's timing.
    While the parties dispute the cause, they agreed there were substantial delays in
    completing the project. The project was still being framed in November 2005, and in
    December the Ondrakas had to obtain an extension of their construction loan. At that
    point, the corporation estimated the project would take another six months to complete.
    Further straining the parties' relationship, a billing dispute arose over the
    application of the contract's overhead surcharge provision. The Ondrakas believed the
    4
    surcharge applied only to labor and materials. The corporation believed the surcharge
    applied to labor, materials, supervision, and profit.
    On June 13, 2006, Joseph sent the corporation a memo stating the Ondrakas would
    no longer pay any supervision, profit or overhead surcharges until they received an
    accounting for the overhead surcharges incurred to that point. The next day Bochinski
    visited the Ondrakas to discuss the issue. After a heated exchange between Annette and
    Bochinski, the corporation declined to continue working on the project, which was then
    only 60 to 65 percent complete. A few days later, the Ondrakas notified the corporation
    they were terminating the contract. The project was completed without further
    involvement from the corporation.
    Two months after terminating the contract, the Ondrakas sued the defendants.
    Their operative second amended complaint included causes of action for breach of
    contract, negligence, negligent misrepresentation, intentional misrepresentation, and
    violation of multiple Business and Professions Code provisions. The complaint also
    alleged the corporation was Bochinski's alter ego and the corporation was not a licensed
    contractor. The corporation filed a cross-complaint against the Ondrakas for failing to
    pay for work completed before contract termination.
    After a lengthy bench trial, which did not include a trial of the Ondrakas' alter ego
    claims, the court issued a statement of decision finding each party had breached the
    contract in certain respects and awarding the Ondrakas net damages of $3,697.
    5
    DISCUSSION
    I
    Corporation's Licensure
    A
    The Ondrakas' original and first amended complaints alleged on information and
    belief that the corporation was a licensed general building contractor. However, their
    second amended complaint alleged that, while the corporation held itself out as a licensed
    contractor, it was not licensed because it did not comply with all of the formalities
    necessary to be a valid corporation. The second amended complaint additionally alleged
    the corporation was Bochinski's alter ego and he was not a licensed contractor either.2
    Based on the corporation's alleged lack of proper licensure, the Ondrakas sought the
    return of all monies they paid the corporation for the construction of the main house
    under section 7031, subdivision (b).
    The court decided against the Ondrakas on this point. The court found that,
    because the Ondrakas had admitted the corporation was licensed in their original
    complaint, they had not controverted the corporation's licensure. In addition, the court
    found the corporation had established it was duly licensed by producing a verified license
    certification from the Contractors' State License Board. The court further found the
    2      The parties do not dispute Bochinski did not have a contractor's license. They also
    do not dispute he was not required to have a license as long as the corporation had a valid
    license.
    6
    Ondrakas had not established the corporation's failure to comply with various close
    corporate formalities allowed them to recover under section 7031.
    The court made its findings without the benefit of alter ego evidence because the
    court bifurcated and ultimately never tried the Ondrakas' alter ego claims. On appeal, the
    Ondrakas contend we must reverse the judgment and allow them to establish through
    alter ego evidence that the corporation was a sham and, therefore, the corporation's
    license was invalid.
    B
    Generally, a contractor may not sue to recover money for performing work for
    which a license is required unless the contractor alleges the contractor was duly licensed
    at the time the contractor performed the work. (§ 7031, subd. (a).) Concomitantly, "a
    person who utilizes the services of an unlicensed contractor may bring an action in any
    court of competent jurisdiction in this state to recover all compensation paid to the
    unlicensed contractor for performance of any act or contract." (§ 7031, subd. (b).) When
    controverted, the licensee has the burden of establishing licensure or prope r licensure,
    which "shall be made by production of a verified certificate of licensure from the
    Contractors' State License Board." (§ 7031, subd. (d).)
    Assuming, without deciding, the Ondrakas properly controverted the corporation's
    licensure, the corporation met its burden of establishing its licensure by producing the
    requisite verified certificate. Nonetheless, relying on Wright v. Issak (2007) 
    149 Cal. App. 4th 1116
    (Wright) and Buzgheia v. Leasco Sierra Grove (1997) 
    60 Cal. App. 4th 374
    (Buzgheia), the Ondrakas contend the court should have allowed them to present
    7
    alter ego evidence to establish the corporation's license was invalid because the
    corporation itself was invalid for not complying with necessary corporate formalities.
    In both Wright and Buzgheia, the courts permitted challenges to facially valid
    contractor's licenses with evidence of circumstances which, if established, resulted in the
    licenses' automatic suspension under specific statutes. 
    (Wright, supra
    , 149 Cal.App.4th
    at pp. 1120-1122; 
    Buzgheia, supra
    , 60 Cal.App.4th at pp. 385-387.) The Ondrakas,
    however, have not identified any statute providing a corporate contractor is not duly
    licensed if it does not comply with corporate formalities. They also have not identified
    any statute providing for the automatic suspension of a corporation's contractor's license
    in such circumstances.3 Accordingly, they have not established that the court
    prejudicially erred by failing to permit them to present evidence of such noncompliance.
    (See Ball v. Steadfast-BLK (2011) 
    196 Cal. App. 4th 694
    , 702-703 [Section 7031 does not
    preclude a contractor's recovery where the contractor purportedly violated licensing laws,
    but no statute automatically suspended the contractor's license or rendered it invalid due
    to the violations].)
    3       Section 7076.2, subdivision (a), provides for the automatic suspension of a
    corporation's license if the corporation, after 30 days' notice, fails to provide satisfactory
    proof it is registered and in good standing with the Secretary of State. The Ondrakas do
    not cite or rely upon this statute nor do they suggest they can present evidence showing
    the corporation received or failed to respond to such a notice.
    8
    II
    Application of Section 7159
    A
    The Ondrakas' causes of action against the defendants included a claim the
    contract was invalid because it violated section 7159 in multiple respects. However, the
    court determined section 7159 did not apply because the contract was not a "home
    improvement" contract within the meaning of the statute. The Ondrakas dispute this
    determination, but we agree section 7159 does not apply here.
    B
    Section 7159 "identifies the projects for which a home improvement contract is
    required, outlines the contract requirements, and lists the items that shall be included in
    the contract." (§ 7159, subd. (a)(1).) A "home improvement contract" is a contract
    between an owner or tenant and a contractor for the performance of a home improvement
    priced at more than $500. (§§ 7151.2, 7159, subd. (b).) " 'Home improvement' means
    the repairing, remodeling, altering, converting, or modernizing of, or adding to,
    residential property." (§ 7151.) It includes "the construction, erection, replacement, or
    improvement of driveways, swimming pools, including spas and hot tubs, terraces,
    patios, awnings, storm windows, landscaping, fences, porches, garages, fallout shelters,
    basements, and other improvements of the structures or land which is adjacent to a
    dwelling house." (Ibid.) Essentially then, "[a] 'home improvement contract' is a
    contract . . . that provides for the remodeling, alteration, repair, or improvement of a
    9
    personal residence, in excess of $500." (Miller & Starr, Cal. Real Estate (3d ed. 2010),
    § 27:55, p. 27-240.)
    The evidence in this case shows the Ondrakas contracted with the corporation for
    the construction of a separate, primary residence. It does not show they contracted for
    the remodeling, alteration, repair, or improvement of their existing guest house.
    Accordingly, the court correctly determined section 7159 did not apply.
    Moreover, contracts made in violation of section 7159 are not necessarily void.
    They may be enforced in appropriate cases to avoid unjust enrichment. (Asdourian v.
    Araj (1985) 
    38 Cal. 3d 276
    , 292-293; Arya Group, Inc. v. Cher (2000) 
    77 Cal. App. 4th 610
    , 615-616.) As the Ondrakas have not established, or attempted to establish, the
    corporation's alleged violations of section 7159 would have precluded enforcement of the
    contract, they have not established they were prejudiced by the court's failure to apply
    section 7159.
    III
    Written Change Orders
    A
    The parties' contract specified procedures for change orders, including requiring
    written notice of the proposed change, a written estimate of the price of the changes, and
    a written agreement to the changes signed by both parties. The court found neither party
    complied with nor insisted the other party comply with these procedures. Instead, the
    parties consistently addressed change orders informally. The court, therefore, found the
    parties modified the contract's change order procedure by their conduct. Alternatively,
    10
    the court found the Ondrakas waived compliance with the formal change order
    procedure.
    On appeal, the Ondrakas contend the court erred in its determination because
    "[e]xisting contract law does not provide for the oral modification of required written
    contract terms by 'conduct' or implicit waiver." Instead, under existing law, they contend
    the change order procedure could not be orally modified unless the modification was
    supported by new consideration, which did not occur. We conclude there is no merit to
    these contentions.
    B
    The Ondrakas support their position by citing to Civil Code section 1698,
    subdivision (c), which provides in part: "Unless the contract otherwise expressly
    provides, a contract in writing may be modified by an oral agreement supported by new
    consideration." Assuming, without deciding, this code section applies to this case, it is
    not dispositive as subdivision (d) of the code section provides: "Nothing in this section
    precludes in an appropriate case the application of rules of law concerning . . . waiver of a
    provision of a written contract." As the court correctly noted, parties may by their
    conduct waive a requirement for a contract modification to be in writing if evidence
    shows the modification conforms to their intent. (Biren v. Equality Emergency Medical
    Group, Inc. (2002) 
    102 Cal. App. 4th 125
    , 141). Since the Ondrakas do not dispute the
    evidence supports the court's finding in this respect, the Ondrakas have not established
    the court erred in determining the corporation did not breach the contract by failing to
    follow the contract's change order procedure.
    11
    IV
    Interpreting Contract Against Corporation
    The Ondrakas contend the court erred by failing to interpret several contract
    provisions against the corporation as the drafter of the contract. To support their position,
    they rely on Civil Code section 1654, which provides: "In cases of uncertainty not
    removed by the preceding rules, the language of a contract should be interpreted most
    strongly against the party who caused the uncertainty to exist." However, Civil Code
    section 1654, does not apply unless other canons of construction fail to dispel the
    uncertainty. (Decter v. Stevenson Properties (1952) 
    39 Cal. 2d 407
    , 418; California
    National Bank v. Woodbridge Plaza LLC (2008) 
    164 Cal. App. 4th 137
    , 145; Oceanside
    84, Ltd. v. Fidelity Federal Bank (1997) 
    56 Cal. App. 4th 1441
    , 1448.) The Ondrakas do
    not discuss how the court arrived at the challenged interpretations or why the court did
    not or could not rely on other canons of construction. Consequently, they have not
    established the court erred by failing to apply Civil Code section 1654 in this case.
    V
    Bochinski's Credibility
    The Ondrakas contend the court improperly evaluated their fraud claims because,
    for various stated reasons, the court mistakenly found Bochinski's testimony was
    credible. We note that none of the Ondrakas' arguments on this point is supported with
    citation to authority. " 'Appellate briefs must provide argument and legal authority for
    the positions taken. "When an appellant fails to raise a point, or asserts it but fails to
    12
    support it with reasoned argument and citations to authority, we treat the point as
    waived." ' " (Cahill v. San Diego Gas & Electric Co. (2011) 
    194 Cal. App. 4th 939
    , 956.)
    Additionally, because the evaluation of a witness's credibility necessarily involves
    consideration of the witness's demeanor and manner of testifying, the evaluation is not
    susceptible to appellate review. (Meiner v. Ford Motor Co. (1971) 
    17 Cal. App. 3d 127
    ,
    141.) "The law has long recognized the problem of appellate review in the matter of
    credibility of witnesses based upon their demeanor, and for that reason the rule has
    evolved that the trier of facts is the sole and exclusive judge of the credibility of
    witnesses as determined by their demeanor. . . . [¶] On the cold record a witness may be
    clear, concise, direct, unimpeached, uncontradictedbut on a face to face evaluation, so
    exude insincerity as to render his credibility factor nil. Another witness may fumble,
    bumble, be unsure, uncertain, contradict himself, and on the basis of a written transcript
    be hardly worthy of belief. But one who sees, hears and observes him may be convinced
    of his honesty, his integrity, his reliability. All of this is because a great deal of that
    highly delicate process we call evaluating the credibility of a witness is based on what
    might be called, for lack of a better word, 'intuition'that intangible, inarticulable
    capacity of one human being to evaluate the sincerity, honesty and integrity of another
    human being with whom he comes in contact. There is no way of knowing or proving
    how much of the testing process is encompassed in the 'traditional' tests of credibility
    such as provable bias or interest, contradiction or impeachment, all demonstrable on the
    record, and how much of that evaluation process comes from the purely subjective
    13
    reaction of the trier of facts to the attitude, demeanor and manner of testifying of the
    witnessnot demonstrable on the record." (Id. at pp. 140-141.)
    VI
    Excess Award
    The court awarded the corporation $66,959 on its cross-complaint against the
    Ondrakas. The Ondrakas contend this amount was excessive because the corporation
    only requested an award of $20,610.38 in its cross-complaint. Neither the record nor the
    law supports this contention.
    The record does not support this contention because a fair reading of the
    corporation's cross-complaint indicates the corporation did not limit its damages claim to
    $20,610.38. Rather, the corporation sought damages "in the sum of $20,610.38 for work
    performed under [the contract], plus such additional compensatory and consequential
    sums including, without limitation, costs of delay, costs of termination, lost profits, and
    investigation costs resulting from said breaches, all in an amount to [be] proven at
    trial . . . ." (Italics added.)
    Even if the corporation had limited its damages claim to $20,610.38, the
    corporation was not necessarily barred from recovering additional damages. In a
    contested action, "the court may grant the plaintiff any relief consistent with the case
    made by the complaint and embraced within the issue." (Civ. Proc. Code, § 580, subd.
    (a); American Motorists Ins. Co. v. Cowan (1982) 
    127 Cal. App. 3d 875
    , 883 [following a
    trial on the merits, the court may grant any form of relief supported by the evidence and
    to which the parties had notice, whether the relief was requested in the pleadings or not].)
    14
    Further, the court admitted evidence showing the corporation sustained $66,950 in
    damages from the Ondrakas' breach of the contract. "The parties thus actually tried the
    issues of damages in amounts above the limits set forth in the body of the complaint. The
    amount of the trial court's judgment on those issues therefore could not have come as any
    surprise to [the Ondrakas] and was the source of no prejudice to [them] since no
    additional time or effort by [them] was required to meet those issues." (Castaic Clay
    Manufacturing Co. v. Dedes (1987) 
    195 Cal. App. 3d 444
    , 450; see also, Grubb & Ellis
    Co. v. Bello (1993) 
    19 Cal. App. 4th 231
    , 241 [in a contested case, a prayer which seeks
    the wrong or inadequate relief is not a serious defect].)
    VII
    Due Process Violations
    A
    The court conducted the bench trial in this case over 15 days between March 22
    and April 29, 2010. At the outset of the trial, the court deferred all rulings on relevancy
    objections. The court explained it did not believe there was a need to be terribly
    concerned about relevancy objections for a bench trial. It also assured the parties it
    would not be basing its decision on irrelevant information.
    The parties' trial estimate was 10 days. On the eighth day of trial, in the midst of
    the Ondrakas case-in-chief, it became clear to the court the parties would exceed their
    estimate. After a chambers meeting to discuss scheduling, the court determined it would
    be unreasonable to allow the presentation of evidence to exceed counsel's estimate by
    more than 50 percent. Consequently, the court limited the parties' presentation of
    15
    evidence to a total of 15 days, with four of the days allocated to the corporation and
    Bochinski and the remainder to the Ondrakas.
    Between May and mid-June 2010, the parties filed written closing arguments and
    in mid-July, they apparently orally argued their respective positions for an entire day.4
    They then submitted supplemental closing briefs between early August and early
    September. The Ondrakas' supplemental closing brief included relevancy objections to
    all or part of 23 exhibits. The corporation and Bochinski responded to the objections in
    one of their supplemental closing briefs.5
    The court ordered the matter submitted on September 9, 2010. In November, the
    court vacated its submission order pending "the preparation of transcripts of certain of the
    witnesses' testimony." The court ordered the matter resubmitted in February 2011. The
    court subsequently discovered the transcripts of two primary witnesses' testimony were
    incomplete. After receiving the completed transcripts, it again ordered the matter
    resubmitted as of April 11, 2011.
    The court issued a proposed statement of decision on June 30, 2011, and directed
    the parties to file any objections to it in accordance with rule 3.1590(d) of the California
    Rules of Court. On July 13, the Ondrakas filed a request for statement of decision
    seeking the factual and legal bases for the court's decision on 81 issues. Two days later,
    the court struck the request because the court had already issued a proposed statement of
    4      The corporation and Bochinski's written closing arguments are not in the record.
    In addition, there is no transcript of the oral arguments in the record.
    5      None of the challenged exhibits are in the record.
    16
    decision. The court then granted the Ondrakas 10 days' leave to file and serve any
    objections to the proposed statement. The court additionally advised the Ondrakas, "A
    seriatim list of the sort contained in the stricken request is not sufficient, particularly
    given the fact that most of the listed issues were addressed in the proposed statement.
    Rather, the objections should identify specific alleged defects in the proposed statement
    with a clear and concise explanation why the factual determinations are not supported by
    the trial record or why the legal reasoning is in error. The objections should also identify
    any necessary issues that were not addressed in the proposed statement, explaining why
    reaching those issues is necessary to the decision in light of the [c]ourt's reasoning. In
    this regard, in particular, [the Ondrakas'] counsel should explain why resolution of the
    bifurcated alter ego claims . . . is required and, if so, how those remaining issues should
    be tried." (Italics added.)
    On July 25, 2011, the Ondrakas filed objections to the proposed statement. Their
    objections did not address the bifurcated alter ego claims. The corporation and Bochinski
    filed their response to the Ondrakas' objections on August 18. The court issued its final
    statement of decision on September 12. The statement of decision did not address the
    relevancy objections or the bifurcated alter ego claims. Given the Ondrakas' failure to
    address the alter ego claims in their objections to the proposed statement, the court
    determined the Ondrakas had waived them.
    B
    The Ondrakas contend the court deprived them of due process of law by deferring
    and then failing to rule on their relevancy objections, by imposing strict time limits on the
    17
    trial that precluded them from calling all the witnesses they wanted to call, by taking 18
    months to complete the proposed statement of decision, by rendering a decision when it
    only had access to part of the trial transcripts, and by failing to conduct the bifurcated
    portion of the trial before completing proposed statement of decision. We conclude there
    is no merit to any of these points.
    1
    Regarding the relevancy objections, generally a court's failure to formally decide a
    reserved ruling on an evidentiary objection is an implied ruling in favor of admissibility
    and against the objection. (Clopton v. Clopton (1912) 
    162 Cal. 27
    , 32.) Although the
    practice of handling objections in this fashion is discouraged, an appellate court will not
    reverse a judgment because of this practice absent a showing of prejudice. (Ebner v.
    West Hollywood Transfer Co. (1919) 
    45 Cal. App. 186
    , 191.) No prejudice exists where
    the challenged evidence was admissible. (Casey v. Richards (1909) 
    10 Cal. App. 57
    , 61.)
    In addition, we presume a court sitting without a jury did not base its decision on
    irrelevant evidence where there is competent evidence to support the decision. (Southern
    California Jockey Club v. California Horse Racing Bd. (1950) 
    36 Cal. 2d 167
    , 176;
    Monogram Industries, Inc. v. Sar Industries, Inc. (1976) 
    64 Cal. App. 3d 692
    , 704.) The
    Ondrakas have not included the challenged evidence in the record (see fn. 3, ante) or
    attempted to demonstrate any of it was inadmissible. They also have not attempted to
    rebut the presumption the court did not base its decision on irrelevant evidence.
    Accordingly, they have not established they were prejudiced by the court's failure to rule
    on the deferred relevancy objections.
    18
    2
    Regarding the trial time limits, "courts have fundamental inherent equity,
    supervisory, and administrative powers, as well as inherent power to control litigation
    before them. [Citation.] 'In addition to their inherent equitable power derived from the
    historic power of equity courts, all courts have inherent supervisory or administrative
    powers which enable them to carry out their duties, and which exist apart from any
    statutory authority. [Citations.] "It is beyond dispute that 'Courts have inherent
    power . . . to adopt any suitable method of practice, both in ordinary actions and special
    proceedings, if the procedure is not specified by statute or by rules adopted by the
    Judicial Council.' [Citation.]" [Citation.] That inherent power entitles trial courts to
    exercise reasonable control over all proceedings connected with pending litigation . . . in
    order to insure the orderly administration of justice.' " (Rutherford v. Owens-Illinois, Inc.
    (1997) 
    16 Cal. 4th 953
    , 967.) We review a court's exercise of its inherent power for abuse
    of discretion. (People v. Alvarez (1996) 
    14 Cal. 4th 155
    , 209.)
    In this case, the record shows the court imposed time limits on the presentation of
    evidence after it became clear the parties would far exceed their trial estimate. Even with
    the time limits, the court permitted the parties to exceed their trial estimate by 50 percent
    and allocated more than two-thirds of the available time to the Ondrakas. The court also
    permitted the parties to present extensive written and oral closing arguments. Although
    the time limits may have prevented the Ondrakas from presenting all of their character
    evidence, they were able to present the key evidence in their case, including their own
    testimony and their expert's testimony. They were also able to extensively question
    19
    Bochinski, whose testimony had more direct bearing on the assessment of his credibility
    than any character evidence would have had. Accordingly, we cannot conclude the court
    abused its discretion in imposing the time limits.
    3
    Regarding the time lapse between the end of the trial and the court's issuance of
    the statement of decision, the Ondrakas perfunctorily assert without citation to authority
    that the time lapse was prejudicial under the circumstances and, therefore, warrants
    reversal. "One cannot simply say the court erred, and leave it up to the appellate court to
    figure out why." (Niko v. Foreman (2006) 
    144 Cal. App. 4th 344
    , 368.) In addition, as we
    have previously noted, " '[a]n appellate brief "should contain a legal argument with
    citation of authorities on the points made. If none is furnished on a particular point, the
    court may treat it as waived, and pass it without consideration." ' " (Ibid.)
    Moreover, the record shows the time lapse was not due to any dereliction on the
    court's part. Several months were consumed by the parties' submission of written and
    oral closing arguments. Most of the rest of the time was consumed waiting for transcripts
    of the principal witnesses' testimony. After receiving the transcripts and finally
    submitting the matter, the court produced a 32-page proposed statement of decision in
    approximately a month and a half. The statement included a detailed factual and legal
    analysis of the parties' respective claims. The Ondrakas do not assert there is insufficient
    evidence to support any of the court's findings. Accordingly, they have not demonstrated
    either that the time lapse was error or that it prejudicially harmed them.
    20
    4
    Finally, the Ondrakas contend that we must reverse the judgment because the
    court failed to conduct a bifurcated trial on their alter ego claims. They have forfeited
    this contention because they have provided no analysis or authority supporting it. (Niko
    v. 
    Foreman, supra
    , 144 Cal.App.4th at p. 368.) They have also forfeited this contention
    because the court specifically invited them to explain why, in light of the proposed
    statement of decision, it was necessary to try their alter ego claims and they did not
    accept the court's invitation. (See Code Civ. Proc., § 634, Fladeboe v. American Isuzu
    Motors Inc. (2007) 
    150 Cal. App. 4th 42
    , 59; Ermoian v. Desert Hospital (2007) 
    152 Cal. App. 4th 475
    , 497-498; Golden Eagle Ins. Co. v. Foremost Ins. Co. (1993) 
    20 Cal. App. 4th 1372
    , 1380 [failure to raise specific objections to omissions or ambiguities
    in a statement of decision waives the right to challenge the omissions or ambiguities on
    appeal].) Although they assert on appeal the evidence was necessary for them to
    challenge the corporation's licensure, we are not persuaded by this assertion for the
    reasons stated in part I, ante. Accordingly, the Ondrakas have not demonstrated the
    court's failure to conduct a trial on their alter ego claims was prejudicial error. (See
    Domach v. Spencer (1980) 
    101 Cal. App. 3d 308
    313 [where findings are made on issues
    which determine cause and uphold judgment, other issues are immaterial and failure to
    make findings on them does not constitute prejudicial error].)
    21
    DISPOSITION
    The judgment is affirmed. Respondents are awarded their appeal costs.
    MCCONNELL, P. J.
    WE CONCUR:
    NARES, J.
    AARON, J.
    22
    

Document Info

Docket Number: D060970

Filed Date: 2/14/2014

Precedential Status: Non-Precedential

Modified Date: 4/18/2021