O & G Industries, Inc. v. American Home Assurance Co. ( 2021 )


Menu:
  • ***********************************************
    The “officially released” date that appears near the be-
    ginning of each opinion is the date the opinion will be pub-
    lished in the Connecticut Law Journal or the date it was
    released as a slip opinion. The operative date for the be-
    ginning of all time periods for filing postopinion motions
    and petitions for certification is the “officially released”
    date appearing in the opinion.
    All opinions are subject to modification and technical
    correction prior to official publication in the Connecticut
    Reports and Connecticut Appellate Reports. In the event of
    discrepancies between the advance release version of an
    opinion and the latest version appearing in the Connecticut
    Law Journal and subsequently in the Connecticut Reports
    or Connecticut Appellate Reports, the latest version is to
    be considered authoritative.
    The syllabus and procedural history accompanying the
    opinion as it appears in the Connecticut Law Journal and
    bound volumes of official reports are copyrighted by the
    Secretary of the State, State of Connecticut, and may not
    be reproduced and distributed without the express written
    permission of the Commission on Official Legal Publica-
    tions, Judicial Branch, State of Connecticut.
    ***********************************************
    O AND G INDUSTRIES, INC. v. AMERICAN HOME
    ASSURANCE COMPANY
    (AC 43135)
    Cradle, Alexander and Harper, Js.
    Syllabus
    The plaintiff, a concrete supply company, sought to recover payment under
    certain surety bonds issued by the defendant, claiming that it had not
    been paid the amount it was owed for supplying concrete and other
    materials to the bonds’ principal, M Co. M Co. entered into a subcontrac-
    tor agreement with C Co. to deliver and pour concrete for a construction
    project. C Co. then engaged the plaintiff to supply concrete materials
    to C Co. to comply with its subcontractor agreement. After receiving a
    joint credit agreement and lien waiver from M Co., the plaintiff began
    supplying concrete and sent invoices directly to M Co., which paid the
    plaintiff in full. C Co. was unhappy with this arrangement and, thereafter,
    the plaintiff opened an account with C Co., albeit for a different project.
    Subsequently, the plaintiff continued to provide C Co. with concrete
    and charged C Co. directly; however, C Co. did not pay the plaintiff.
    The plaintiff informed M Co. of C Co.’s nonpayment and M Co. provided
    payment to C Co. to forward to the plaintiff, but C Co. failed to do so.
    After C Co. defaulted, the plaintiff sent the defendant a notice of claim
    under the payment bond, and recorded a mechanic’s lien against the
    owner of the construction project. The defendant issued a substitute
    bond, as a surety, which the plaintiff accepted as a substitute for its
    mechanic’s lien. Thereafter, M Co. issued a response to the defendant
    in which it denied that the plaintiff’s claim had any merit. The defendant
    refused to pay the plaintiff under the payment bond or the substitute
    bond, and the plaintiff brought the present action against the defendant.
    The defendant asserted nine special defenses against the plaintiff, alleg-
    ing, inter alia, that the plaintiff acted in bad faith and was reckless in
    its dealings with C Co. Held:
    1. The trial court did not err in finding that the defendant failed to sustain
    its burden of proof in showing that the plaintiff conducted its business
    with C Co. recklessly, in bad faith, or with a dishonest purpose in
    providing C Co. with its own account, not demanding payment immedi-
    ately upon default, or bringing an action on the unpaid balance, as the
    court’s factual findings and the evidence in the record supported the
    court’s conclusions; the plaintiff was not a party to the payment bond
    agreement, the plaintiff took more protective steps than the defendant,
    which had failed to include any provisions in its bond agreement to
    require M Co., who brought C Co. into the construction project, to
    complete credit checks on subcontractors before bringing them
    onboard, the plaintiff did not act recklessly where it took reasonable
    steps to execute a joint check agreement with M Co., M Co. was on
    notice that C Co. had not been forwarding payment to the plaintiff, yet
    M Co. continued advancing payment for the materials directly to C Co.,
    and there was sufficient evidence to support the court’s finding that the
    plaintiff’s conduct in continuing to supply materials to C Co. for the
    project did not rise to the level of common-law recklessness.
    2. The defendant cannot prevail on its claim that the trial court erred in
    finding that the plaintiff satisfied the express condition precedent to a
    valid claim as delineated in the payment bond, namely, that the plaintiff
    provide the defendant with a copy of the plaintiff’s written contract or
    purchase order with C Co., as the court’s finding that the forty-five
    invoices submitted to the defendant, which set forth the relationship
    between C Co. and the plaintiff, were sufficient to comply with the
    provisions of the payment bond; there was no dispute that the plaintiff
    supplied materials to C Co. for the construction project for which the
    plaintiff was not paid, and the plaintiff attached the invoices with its
    proof of claim form, indicating that C Co. and the plaintiff had an ongoing
    agreement for the materials to be supplied to C Co. for the benefit of
    the project; moreover, the payment bond failed to exclude any specific
    type of agreements or to indicate that proof of certain types of agree-
    ments were disallowed upon making a claim.
    3. This court declined to review the merits of the defendant’s claim that the
    trial court erred by allowing the plaintiff to recover damages in excess
    of the penal sum of the substitute bond; the defendant raised no objec-
    tions at trial regarding the award of prejudgment or offer of compromise
    interest as part of the damages award, or the court’s calculus of its award.
    4. The trial court did not abuse its discretion by allowing the plaintiff to
    present rebuttal evidence after the defendant rested without introducing
    any evidence or testimony during its case-in-chief when the defendant
    pleaded special defenses and partly geared its lengthy cross-examination
    of the plaintiff’s sole witness toward addressing those special defenses;
    because the court had the sound discretion as to the order of its proceed-
    ings and because the court had barred the plaintiff from addressing the
    defendant’s special defenses in its case-in-chief on the basis that those
    special defenses had not yet been raised, the court properly allowed
    rebuttal evidence limited only to the defendant’s special defenses; the
    plaintiff’s rebuttal was not presented to bolster its case-in-chief but,
    rather, to refute or contradict the evidence the defendant put forth
    during its cross-examination of the plaintiff’s witness concerning the
    defendant’s special defenses, and the documents that the defendant
    admitted during that cross-examination, which as the defendant con-
    ceded, were evidence.
    Argued November 9, 2020—officially released May 18, 2021
    Procedural History
    Action to recover damages for, inter alia, the defen-
    dant’s denial of the plaintiff’s claim for failure of pay-
    ment by a principal under certain bonds issued by the
    defendant as surety, brought to the Superior Court in
    the judicial district of Stamford-Norwalk, where it was
    tried to the court, Tierney, J.; judgment for the plaintiff,
    from which the defendant appealed to this court.
    Affirmed.
    Louis R. Pepe, with whom was Rory M. Farrell, for
    the defendant (appellant).
    Jared Cohane, with whom was Timothy T. Corey,
    for the plaintiff (appellee).
    Opinion
    HARPER, J. The defendant, American Home Assur-
    ance Company, appeals from the judgment of the trial
    court rendered in favor of the plaintiff, O & G Industries,
    Inc., finding that the plaintiff was entitled to payment
    under certain bonds issued by the defendant as surety,
    including a payment bond and a bond (substitute bond)
    that had been substituted for the discharge of a mechan-
    ic’s lien filed by the plaintiff in connection with materi-
    als it had furnished for a construction project. On
    appeal, the defendant claims that the court erred by (1)
    failing to find that the plaintiff breached its obligation
    of ‘‘diligence and utmost good faith’’ owed to the defen-
    dant, (2) finding that the plaintiff satisfied the condition
    precedent to the payment bond, (3) allowing the plain-
    tiff to recover beyond the penal sum of the mechanic’s
    lien bond, and (4) allowing the plaintiff to put on a
    rebuttal case after the defendant had rested its case
    without calling any witnesses or introducing any evi-
    dence.1 We disagree and, accordingly, affirm the judg-
    ment of the trial court.
    The following facts, either found by the court or
    undisputed in the record, and procedural history are
    relevant to our resolution of this appeal. The plaintiff
    is a producer and supplier of construction materials,
    including concrete, with a place of business in Torring-
    ton. A large scale, eighteen-story residential apartment
    building construction project (project) in Stamford
    commenced at 1011 Washington Boulevard, which is
    owned by Stamford Phase Four JV, LLC (owner). The
    owner and The Morganti Group, Inc. (Morganti), the
    general contractor, entered into a construction contract
    on January 28, 2016. The first executed payment bond
    was an agreement between the owner as the obligee,
    Morganti as the principal, and the defendant as the
    surety. The defendant served as surety on the payment
    bond and a performance bond. Those bonds were
    issued by the defendant, each in the penal sum of
    $53,690,000, naming Morganti as the bonded principal.
    On January 31, 2016, Morganti entered into a written
    subcontractor agreement with Concrete Superstruc-
    tures, Inc. (CSS), of Bloomfield. Morganti hired CSS to
    deliver and pour concrete for the project. The subcon-
    tract price was $3,710,000. CSS then contacted the plain-
    tiff and requested that the plaintiff supply materials to
    CSS so that CSS could fulfill its obligations to Morganti
    under the subcontractor agreement. CSS submitted a
    credit application and credit agreement to the plaintiff
    in April, 2016, after receiving a price quotation from
    the plaintiff. The Redi-Mix price quotation provided CSS
    with a list of items for sale, their prices, and payment
    and billing information. The credit agreement included
    the billing and credit conditions that governed the
    agreement between CSS and the plaintiff. The plaintiff
    conducted a credit check on CSS and the personal guar-
    antor, Douglas Cartelli, and decided not to extend credit
    to CSS for the project at that time and put the applica-
    tion aside. In July, 2016, Morganti sent the plaintiff a
    joint check agreement and lien waiver. The plaintiff
    then supplied the concrete and other related materials
    called for in the subcontract to CSS and delivered them
    to the site from April until September, 2016. During
    that time period, the plaintiff sent invoices directly to
    Morganti for the materials and was paid in full by Mor-
    ganti for a total value of $385,988. On July 20, 2016,
    CSS e-mailed the plaintiff to express its displeasure
    with the plaintiff’s choice to continue to bill Morganti
    directly instead of directly dealing with CSS. CSS threat-
    ened to use a different concrete supplier if the plaintiff
    did not open an account for CSS and bill CSS directly.
    The plaintiff then reconsidered CSS’ credit application
    on August 11, 2016, and approved CSS for a credit
    limit of $3000; however, the account was for a project
    unrelated to the Washington Boulevard project at issue.
    The joint check agreement previously sent to the plain-
    tiff in July, 2016, was returned to Morganti in Septem-
    ber, 2016, with amendments, including the redaction of
    the lien waiver provision. While the amended joint
    check agreement was under review by Morganti, the
    plaintiff furnished construction supplies to CSS from
    September 3 through December 2, 2016, for a total value
    of $484,919.30, but charged CSS directly instead of Mor-
    ganti. Morganti informed the plaintiff on November 1,
    2016, that the plaintiff’s amended joint check agreement
    had been denied. The plaintiff also informed Morganti
    on or about November 1, 2016, that CSS had yet to pay
    for any of the materials the plaintiff had furnished for
    the project since September, 2016, with a total balance
    owed of approximately $255,512. Morganti gave CSS
    another $225,000 after being informed of the balance
    due to the plaintiff, which had been paid timely up
    until September, 2016. For each transaction between
    September and December, 2016, CSS would request
    payment from Morganti in order to pay the balance
    owed to the plaintiff for the deliveries. Although Mor-
    ganti made payments to CSS that CSS was supposed
    to use to pay the plaintiff, CSS did not forward the
    payments to the plaintiff. Consequently, CSS defaulted
    after accruing a $484,919.30 balance that it owed to the
    plaintiff.
    The parties also stipulated to the following facts.
    The materials delivered by the plaintiff to CSS from
    September through December, 2016, were all billed to
    CSS under a credit account that CSS had opened with
    the plaintiff on or about August 11, 2016, for a project
    that was taking place in Norwalk—the Wall Street The-
    ater project.2 The delivery tickets and invoices showed
    that the plaintiff’s supplies were sold to CSS only and
    were not sold or delivered to any other party. It is
    undisputed that CSS failed to pay the plaintiff for the
    materials it delivered to the project between September
    and December, 2016. Moreover, there is no dispute as
    to the quality or value of the materials that the plaintiff
    had delivered to CSS.
    On February 2, 2017, the plaintiff mailed the defen-
    dant a notice of claim under the payment bond after
    CSS had defaulted. The plaintiff sent timely notice to
    Morganti of its intent to file a mechanic’s lien. The
    plaintiff then proceeded to record a mechanic’s lien
    against the owner’s Washington Boulevard property on
    February 28, 2017, to secure payment for the materials
    that the plaintiff had provided to the project. There is
    no dispute that the mechanic’s lien was filed timely. In
    response, on March 6, 2017, the defendant issued the
    substitute bond, as a surety, in the penal sum of
    $533,411.23, which the plaintiff accepted as a substitute
    for its mechanic’s lien pursuant to General Statutes
    § 49-37.3
    On March 16, 2017, Morganti issued a response to the
    defendant as to the plaintiff’s claim under the payment
    bond, effectively denying that the plaintiff’s claim had
    any merit. The defendant later denied the plaintiff’s
    claim on April 6, 2017. After multiple correspondences
    between the plaintiff and Morganti, the defendant sent
    an e-mail on May 5, 2017, to the plaintiff and Morganti
    affirming its decision to deny the plaintiff’s claim and
    refused to pay the plaintiff under both the payment
    bond and the substitute bond.
    The plaintiff then brought this action against the
    defendant, claiming that it had not been paid the amount
    owed under the substitute bond of $484,919.30. As the
    trial court delineated in its memorandum of decision,
    ‘‘[t]he operative complaint is the first amended com-
    plaint dated July 25, 2017. . . . It is a two count com-
    plaint with each count claiming damages in the same
    amount of $484,919.30. The first count seeks that
    amount of damages based upon a bond substituted for
    the discharge of a $484,919.30 mechanic’s lien issued
    by the plaintiff . . . on February 28, 2017. . . . The
    defendant . . . supplied that bond on March 6, 2017
    . . . in the amount of $533,411.23. The second count
    is a suit against the defendant . . . by the plaintiff . . .
    on [the] payment bond issued by [the defendant] as
    surety to the project contractor . . . [Morganti] . . . .
    The plaintiff claim[ed] damages on the second count
    in the amount of $484,919.30 plus interest, costs and
    attorney’s fees. The operative answer is the November
    20, 2017 amended answer and special defenses. . . .
    Nine special defenses have been asserted by [the defen-
    dant] in [its] eleven page amended answer and special
    defenses . . . .’’ (Citations omitted.)
    In its nine special defenses, the defendant alleged that
    (1) the plaintiff’s reckless conduct in how it conducted
    business with CSS by allowing CSS to have its own
    account, despite CSS being deemed not creditworthy,
    and by failing to demand timely payments, exposed the
    plaintiff, the defendant, Morganti, and the owner to an
    unreasonable risk that CSS would run up a large, unpaid
    balance, (2) the plaintiff’s claims were barred by the
    doctrine of unclean hands as a result of the plaintiff’s
    reckless, unreasonable, and unfair conduct, (3) the
    plaintiff’s claims were barred by the doctrine of avoid-
    able consequences and/or its failure to mitigate its dam-
    ages, (4) the plaintiff’s claims were barred by the doc-
    trine of estoppel, (5) the plaintiff’s claims were barred
    by the doctrine of laches because it had failed to take
    action to address the inability of CSS to submit timely
    payments, (6) the plaintiff’s claims against the defen-
    dant were barred in their entirety because both the
    owner and Morganti, as bond principal for the defen-
    dant, had paid in full for all of the concrete material
    furnished by the plaintiff to CSS for the project, (7)
    the plaintiff’s substitute bond claim was ‘‘barred to the
    extent that its underlying mechanic’s lien was invalid
    pursuant to [General Statutes] § 49-33 et seq. because
    the lien amount [was] overstated and because no
    amounts [were] due and owing [to the plaintiff] from the
    owner, Morganti, or [the defendant],’’ (8) the plaintiff’s
    payment bond claim was barred because the plaintiff
    had not ‘‘submitted a valid ‘[c]laim’ in accordance with
    the terms and conditions of the payment bond and,
    therefore, [had] not satisfied all conditions precedent
    to recovery under the payment bond,’’ and (9) the plain-
    tiff’s claims were ‘‘barred, in whole or in part, because
    the contract that [the plaintiff was] seeking to enforce
    [was] an oral contract for the sale of goods in excess
    of $500 and, therefore, unenforceable pursuant to . . .
    [General Statutes] § 42a-2-201.’’4 In essence, the plaintiff
    alleged in its complaint that it was not paid in full
    by either CSS or Morganti. The plaintiff made a claim
    against the defendant by reason of the defendant’s issu-
    ance of the two bonds—the payment bond and the
    substitute bond. After a five day trial, the court con-
    cluded that the plaintiff had carried its burden and
    proved that it was entitled to damages for breach of
    the payment bond and the substitute bond, and that
    the defendant’s first five special defenses, which were
    equitable in nature, were not applicable to the plaintiff’s
    claims at law on the surety bonds. Notwithstanding that
    determination, the court did, in fact, examine the merits
    of the defendant’s first five special defenses and found,
    in the alternative, that the defendant had failed to sus-
    tain its burden of establishing those special defenses.5
    Specifically, the court found that the defendant failed to
    sustain its burden of showing that the plaintiff’s conduct
    amounted to common-law recklessness, bad faith, or
    unclean hands. The court also found in favor of the
    plaintiff as to the remaining special defenses. This
    appeal followed. Additional facts and procedural his-
    tory will be set forth as necessary.
    I
    The defendant claims that the court erred when it
    found that the defendant had failed to sustain its burden
    of proving that the plaintiff’s conduct was reckless and
    unreasonable, and breached the obligation of ‘‘diligence
    and the utmost good faith.’’ We disagree.
    We set forth the appropriate standard of review and
    relevant legal principles for this claim. A court’s factual
    findings underlying its determination that a party failed
    to sustain its burden of proof will not be disturbed on
    appeal unless they are clearly erroneous. See Schiavone
    v. Bank of America, N.A., 
    102 Conn. App. 301
    , 304, 
    925 A.2d 438
     (2007); Kelman v. McDonald, 
    24 Conn. App. 398
    , 400–401, 
    588 A.2d 667
     (1991). As such, ‘‘the court’s
    finding that the [defendant] failed to meet [its] burden
    of proof’’ must be ‘‘supported by facts in the record and
    reasonable inferences drawn therefrom.’’ Schiavone v.
    Bank of America, N.A., supra, 304. ‘‘On appeal, it is the
    function of this court to determine whether the decision
    of the trial court is clearly erroneous. . . . This
    involves a two part function: where the legal conclu-
    sions of the court are challenged, we must determine
    whether they are legally and logically correct and
    whether they find support in the facts set out in the
    memorandum of decision; where the factual basis of
    the court’s decision is challenged we must determine
    whether the facts set out in the memorandum of deci-
    sion are supported by the evidence or whether, in light
    of the evidence and the pleadings in the whole record,
    those facts are clearly erroneous.’’ (Citation omitted.)
    Pandolphe’s Auto Parts, Inc. v. Manchester, 
    181 Conn. 217
    , 221–22, 
    435 A.2d 24
     (1980).
    ‘‘We do not examine the record to determine whether
    the trier of fact could have reached a conclusion other
    than the one reached. Rather, we focus on the conclu-
    sion of the trial court, as well as the method by which
    it arrived at that conclusion, to determine whether it
    is legally correct and factually supported.’’ Id., 222. ‘‘The
    [fact-finding] function is vested in the trial court with
    its unique opportunity to view the evidence presented
    in a totality of circumstances, i.e., including its observa-
    tions of the demeanor and conduct of the witnesses
    and parties, which is not fully reflected in the cold,
    printed record which is available to us.’’ (Internal quota-
    tion marks omitted.) Cavolick v. DeSimone, 
    88 Conn. App. 638
    , 646, 
    870 A.2d 1147
    , cert. denied, 
    274 Conn. 906
    , 
    876 A.2d 1198
     (2005). ‘‘In reviewing the trial judge’s
    factual findings, we give the evidence the most favor-
    able reasonable construction in support of the judg-
    ment.’’ (Internal quotation marks omitted.) Kelman v.
    McDonald, supra, 
    24 Conn. App. 401
    . Further, ‘‘the
    defendant bears the burden of proof on [its] special
    defense(s).’’ Kaye v. Housman, 
    184 Conn. App. 808
    ,
    817, 
    195 A.3d 1168
     (2018). The defendant must prove
    the allegations in its special defenses by a fair prepon-
    derance of the evidence in a civil trial. See Ramsay v.
    Camrac, Inc., 
    96 Conn. App. 190
    , 206, 
    899 A.2d 727
    ,
    cert. denied, 
    280 Conn. 910
    , 
    908 A.2d 538
     (2006).
    The following facts and procedural history are rele-
    vant to our resolution of this claim. The defendant’s first
    five special defenses alleged that the plaintiff engaged
    in reckless, unreasonable and unfair conduct, and that
    the plaintiff’s claims were barred by the doctrines of
    unclean hands, avoidable consequences and/or its fail-
    ure to mitigate its damages, estoppel and laches. Special
    defenses two through five incorporated the first special
    defense by reference. Before the commencement of
    trial, the court ordered the parties to file pretrial briefs
    addressing their legal claims and applicable law. In its
    pretrial brief, the defendant claimed, inter alia, that the
    plaintiff was not entitled to recovery under the bonds
    because the plaintiff had failed to exercise ‘‘diligence
    and utmost good faith’’ by conducting business with
    CSS in a ‘‘commercially unreasonable’’ manner. The
    defendant also likened the requirement of ‘‘diligence
    and utmost good faith’’ to the implied covenant of good
    faith and fair dealing.
    After a five day trial, in light of its factual findings,
    the court found that the defendant had failed to sustain
    its burden of proof as to its special defenses. In doing
    so, the court determined that the defendant’s first five
    special defenses were equitable in nature and could
    be summarized as alleging that the plaintiff’s conduct
    amounted to common-law recklessness, bad faith in the
    performance of contractual obligations amounting to a
    breach of the implied covenant of good faith and fair
    dealing, and a violation of the equitable concept of
    unclean hands. In its memorandum of decision, the
    court discussed Aetna Bank v. Hollister, 
    55 Conn. 188
    ,
    212, 
    10 A. 550
     (1886), and Wolthausen v. Trimpert, 
    93 Conn. 260
    , 269, 
    105 A. 687
     (1919), cases on which the
    defendant relied for its claim that the plaintiff’s reckless
    conduct discharged the defendant of any duty to pay
    the plaintiff under the surety bonds.
    In its analysis, the court noted that neither of the
    century old cases to which the defendant had cited
    explained what the phrase ‘‘diligence and utmost good
    faith’’ required. The court specifically noted that Wol-
    thausen merely established when a party’s conduct is
    not negligent under the ‘‘utmost good faith’’ standard.
    The court determined that the defendant’s claim was
    similar to the contractual principle of the implied cove-
    nant of good faith and fair dealing enunciated in Pacelli
    Bros. Transportation, Inc. v. Pacelli, 
    189 Conn. 401
    ,
    407, 
    456 A.2d 325
     (1983), in which our Supreme Court
    equated the phrase ‘‘utmost good faith’’ with ‘‘fair deal-
    ing.’’6
    The court thereafter explained that it had to deter-
    mine ‘‘what standards must be shown by the defendant
    to defeat the plaintiff’s claim upon the bond based on
    the plaintiff’s omissions or commissions.’’ The court
    determined that it would need to assess the plaintiff’s
    conduct through the ‘‘lens of common-law recklessness,
    unclean hands, and bad faith’’ to establish whether the
    plaintiff was barred from recovery because the defen-
    dant, in essence, alleged that the plaintiff’s conduct
    discharged the defendant from any obligation to pay
    under the surety bonds.7 (Internal quotation marks
    omitted.)
    Furthermore, the court explained that, because the
    court in Pacelli likened ‘‘utmost good faith’’ to ‘‘fair
    dealing,’’ the defendant would need to show that the
    plaintiff had acted in bad faith amounting to a breach
    of the implied covenant of good faith and fair dealing
    where the defendant deemed the plaintiff’s conduct to
    be ‘‘reckless,’’ ‘‘unfair,’’ and ‘‘unreasonable.’’ Thus, as
    it pertained to the defendant’s claim that the plaintiff
    breached the obligation of ‘‘diligence and the utmost
    good faith,’’ the court determined that the defendant
    had to show that the plaintiff acted in bad faith and that
    a contract existed, which is also required to establish
    a breach of the implied covenant of good faith and fair
    dealing.
    The defendant sought to establish that the plaintiff
    acted in bad faith by engaging in reckless conduct in
    its dealings with CSS. The court interpreted the defen-
    dant’s claim that the plaintiff engaged in reckless con-
    duct as an allegation rooted in common-law reckless-
    ness. The court then concluded that the defendant failed
    to show that the plaintiff’s conduct amounted to com-
    mon-law recklessness. In support of that conclusion,
    the court found that, because the plaintiff played no
    part in bringing the defaulting party, CSS, into the con-
    struction project, Morganti or the defendant should
    have conducted credit checks on CSS. Moreover, the
    plaintiff was not a party to a contract with the owner,
    Morganti, or the defendant, as CSS was the party that
    sought out the plaintiff, which sold and delivered the
    materials and supplies to CSS only, and requested that
    the plaintiff supply materials to CSS. Therefore, the
    plaintiff had no contractual obligations to the defendant
    outside of what it was required to submit for a valid
    claim against the payment bond. Additionally, the court
    found that the plaintiff’s failure to institute an action
    against CSS was not unreasonable because there was
    a compelling and reasonable inference created from
    the evidence produced at trial that CSS was judgment
    proof at the time its contract was terminated and there-
    after. Thus, the court found that the defendant failed
    to sustain its burden of proof as to the allegations of
    common-law recklessness and bad faith by the plaintiff.
    In essence, the court found that, because the defendant
    failed to show that the plaintiff’s conduct amounted to
    common-law recklessness, it failed to sustain its burden
    of proof that the plaintiff acted in bad faith.
    On appeal, the defendant claims that the court com-
    mitted reversible error when it found that the plaintiff’s
    conduct did not bar the plaintiff from recovering under
    the surety bonds. The defendant relies on Aetna Bank
    v. Hollister, supra, 
    55 Conn. 212
    , and Wolthausen v.
    Trimpet, supra, 
    93 Conn. 269
    , in asserting that the plain-
    tiff breached the standard of care owed to the defen-
    dant. The defendant claims that the plaintiff’s reckless
    conduct should discharge the defendant, as the surety,
    from its obligation to pay the plaintiff under the surety
    bonds because the court in Aetna Bank proclaimed that
    ‘‘diligence and the utmost good faith are required to be
    observed by a party claiming against a surety.’’ Aetna
    Bank v. Hollister, supra, 212. The plaintiff counters that
    the cases cited by the defendant to buttress its argument
    are more than a century old and were decided before
    the development of modern construction suretyship
    law. The plaintiff distinguishes Aetna Bank by demon-
    strating that the court in Aetna Bank rejected the sure-
    ty’s argument that it should be discharged from any
    indemnity obligations for lack of notice when the bank
    waited years before deciding to bring an action on the
    bond The court in Aetna Bank rejected the surety’s
    argument and found for the bank because the bond
    contained no express notice requirement, and, thus, it
    could not be said that the bank failed to adhere to a
    ‘‘duty of diligence and utmost good faith.’’ Id. In the
    present case, the court determined that the defendant’s
    reference to a duty of ‘‘diligence and the utmost good
    faith’’ is comparable to the implied covenant of good
    faith and fair dealing. We agree with the court’s well
    reasoned analysis.
    Because the defendant’s bad faith claim hinges on
    whether the plaintiff’s conduct amounts to ‘‘unreason-
    able’’ and reckless conduct, we first determine whether
    the evidence in the record supports the court’s finding
    that the plaintiff’s conduct did not amount to common-
    law recklessness.
    With regard to common-law recklessness, ‘‘[u]nder
    Connecticut common law, [r]ecklessness requires a
    conscious choice of a course of action either with
    knowledge of the serious danger to others involved in
    it or with knowledge of facts which would disclose this
    danger to any reasonable [person], and the actor must
    recognize that his conduct involves a risk substantially
    greater . . . than that which is necessary to make his
    conduct negligent. . . . [W]e have described reckless-
    ness as a state of consciousness with reference to the
    consequences of one’s acts. . . . It is more than negli-
    gence, more than gross negligence. . . . The state of
    mind amounting to recklessness may be inferred from
    conduct. But, in order to infer it, there must be some-
    thing more than a failure to exercise a reasonable
    degree of watchfulness to avoid danger to others or to
    take reasonable precautions to avoid injury to them.
    . . . The result is that . . . reckless conduct tends to
    take on the aspect of highly unreasonable conduct,
    involving an extreme departure from ordinary care, in
    a situation where a high degree of danger is apparent.’’
    (Emphasis omitted; internal quotation marks omitted.)
    Williams v. Housing Authority, 
    159 Conn. App. 679
    ,
    693–94, 
    124 A.3d 537
     (2015), aff’d, 
    327 Conn. 338
    , 
    174 A.3d 137
     (2017).
    As the court in the present case noted, the blame the
    defendant assigns to the plaintiff is misplaced. There
    was sufficient evidence to support the court’s finding
    that the plaintiff took more protective steps than the
    defendant, who had failed to include any provisions in
    its bond agreement to require Morganti, who brought
    CSS into the fold, to complete credit checks on subcon-
    tractors before bringing them onto the project. The
    evidence shows that Morganti also had sent the plaintiff
    a joint check agreement in July, 2016, which included
    a provision stating that it would not give the plaintiff
    any right ‘‘to file or maintain a lien or claim for alleged
    nonpayment for any labor, materials or services per-
    formed on the [p]roject, against the [o]wner . . . or
    the [c]onstruction [m]anager or its sureties.’’ That provi-
    sion, as found by the court, implicated the plaintiff’s
    right to file a mechanic’s lien, which contravenes Gen-
    eral Statutes § 42-158l.8 The plaintiff amended the joint
    check agreement, redacted the portion of it that impli-
    cated the plaintiff’s right to file a mechanic’s lien, and
    returned the agreement to Morganti in September, 2016,
    but Morganti refused to enter into the joint check agree-
    ment with the plaintiff unless the plaintiff accepted the
    redacted provision in the agreement.
    The evidence in the record supports the finding that
    the plaintiff did not act recklessly when the plaintiff
    took reasonable steps to execute a joint check agree-
    ment with Morganti. The joint check agreement would
    have required Morganti to issue a check with both the
    plaintiff and CSS identified as payees. Moreover, as the
    testimony at trial established, Morganti was on notice
    that CSS had not been forwarding payments to the
    plaintiff by the fall of 2016, yet Morganti continued
    advancing payment for the materials directly to CSS.
    Accordingly, there was sufficient evidence to support
    the court’s finding that the plaintiff’s conduct in continu-
    ing to supply materials to CSS for the project did not
    rise to the level of common-law recklessness.
    Likewise, the evidence supports the court’s finding
    that the defendant failed to sustain its burden of show-
    ing that the plaintiff acted in bad faith. ‘‘[I]t is axiomatic
    that the . . . duty of good faith and fair dealing is a
    covenant implied into a contract or a contractual rela-
    tionship. . . . In other words, every contract carries
    an implied duty requiring that neither party do anything
    that will injure the right of the other to receive the
    benefits of the agreement. . . . The covenant of good
    faith and fair dealing presupposes that the terms and
    purpose of the contract are agreed upon by the parties
    and that what is in dispute is a party’s discretionary
    application or interpretation of a contract term. . . .
    ‘‘To constitute a breach of [the implied covenant of
    good faith and fair dealing], the acts by which a defen-
    dant allegedly impedes the plaintiff’s right to receive
    benefits that he or she reasonably expected to receive
    under the contract must have been taken in bad faith.
    . . . Bad faith in general implies both actual or con-
    structive fraud, or a design to mislead or deceive
    another, or a neglect or refusal to fulfill some duty or
    some contractual obligation, not prompted by an honest
    mistake as to one’s rights or duties, but by some inter-
    ested or sinister motive. . . . Bad faith means more
    than mere negligence; it involves a dishonest pur-
    pose. . . .
    ‘‘Accordingly, because the covenant of good faith and
    fair dealing only requir[es] that neither party [to a con-
    tract] do anything that will injure the right of the other
    to receive the benefits of the agreement, it is not impli-
    cated by conduct that does not impair contractual
    rights.’’ (Citation omitted; internal quotation marks
    omitted.) Capstone Building Corp. v. American Motor-
    ists Ins. Co., 
    308 Conn. 760
    , 794–95, 
    67 A.3d 961
     (2013).
    ‘‘[T]he existence of a contract between the parties is a
    necessary antecedent to any claim of breach of the duty
    of good faith and fair dealing.’’ Hoskins v. Titan Value
    Equities Group, Inc., 
    252 Conn. 789
    , 793, 
    749 A.2d 1144
     (2000).
    The defendant relies on the plaintiff’s decision to
    provide CSS with its own account and not to demand
    payment immediately or to bring an action on the bal-
    ance as indicia that the plaintiff failed to act in good
    faith. That claim fails because, as the court noted, the
    defendant had no contract with the plaintiff, nor did
    the court find any facts to support the defendant’s claim
    that the plaintiff acted in bad faith or with a dishonest
    purpose.9
    In summary, the court’s factual findings supporting
    its conclusions that the defendant failed to show that
    the plaintiff conducted its business with CSS recklessly,
    in bad faith or with a dishonest purpose, and that the
    plaintiff was not a party to the payment bond agreement
    are fully supported by evidence in the record. Thus, we
    agree with the court’s finding that the defendant failed
    to sustain its burden of proof in showing that the plain-
    tiff’s conduct was reckless and in bad faith. Accordingly,
    the defendant’s claim must fail.
    II
    The defendant next claims that the court erred in
    finding that the plaintiff satisfied the express condition
    precedent to a valid claim as delineated in the payment
    bond, namely, that the plaintiff provide the defendant
    with a copy of the plaintiff’s written contract or pur-
    chase order with the subcontractor, CSS. We are not
    persuaded.
    relevant legal principles. To the extent that we interpret
    any of the payment bond provisions, ‘‘[i]f a contract is
    unambiguous within its four corners, the determination
    of what the parties intended by their contractual com-
    mitments is a question of law. . . . When the language
    of a contract is ambiguous, [however] the determination
    of the parties’ intent is a question of fact, and the trial
    court’s interpretation is subject to reversal on appeal
    only if it is clearly erroneous. . . . In interpreting con-
    tract items, we have repeatedly stated that the intent of
    the parties is to be ascertained by a fair and reasonable
    construction of the written words and that the language
    used must be accorded its common, natural, and ordi-
    nary meaning and usage where it can be sensibly applied
    to the subject matter of the contract.’’ (Internal quota-
    tion marks omitted.) Winthrop v. Winthrop, 
    189 Conn. App. 576
    , 581–82, 
    207 A.3d 1109
     (2019).
    ‘‘Whether the language is ambiguous is itself a ques-
    tion of law, upon which our review on appeal is de
    novo. . . . In determining whether a contract is ambig-
    uous, the words of the contract must be given their
    natural and ordinary meaning. . . . A contract is unam-
    biguous when its language is clear and conveys a defi-
    nite and precise intent. . . . Contract language is
    unambiguous when it has a definite and precise mean-
    ing about which there is no reasonable basis for a differ-
    ence of opinion.’’ (Citation omitted; internal quotation
    mark omitted.) Western Dermatology Consultants, P.C.
    v. VitalWorks, Inc., 
    146 Conn. App. 169
    , 187, 
    78 A.3d 167
     (2013), aff’d, 
    322 Conn. 541
    , 
    153 A.3d 574
     (2016).10
    Moreover, the determination that the plaintiff satis-
    fied all of the conditions precedent to the payment bond
    is a factual finding, ‘‘and it is axiomatic that [t]he trial
    court’s [factual] findings are binding upon this court
    unless they are clearly erroneous in light of the evidence
    and the pleadings in the record as a whole. . . . We
    cannot retry the facts or pass on the credibility of the
    witnesses. . . . A finding of fact is clearly erroneous
    when there is no evidence in the record to support it
    . . . or when although there is evidence to support it,
    the reviewing court on the entire evidence is left with
    the definite and firm conviction that a mistake has been
    committed.’’ (Internal quotation marks omitted.)
    McKay v. Longman, 
    332 Conn. 394
    , 417, 
    211 A.3d 20
    (2019).
    The following additional facts are relevant to this
    claim. Section 16 of the payment bond agreement sets
    out relevant definitions applicable to the payment bond.
    Section 16.1 defines what constitutes a valid claim
    under the payment bond and what is minimally required
    to make a valid claim.11 The plaintiff sent the defendant
    a notice of claim under the payment bond on February
    2, 2017. On February 23, 2017, a representative for the
    defendant sent the plaintiff a proof of claim form for
    the plaintiff to complete in order to submit its claim.
    The proof of claim form required, inter alia, information
    about the claimant, a description of the services or
    materials provided for the project, the dates of the deliv-
    eries or services provided, the name of the contractor
    or subcontractor that was furnished the services or
    materials, a copy of invoices and delivery tickets, and
    the amount due to the claimant. The plaintiff submitted
    the proof of claim form on March 2, 2017. The plaintiff’s
    proof of claim form also included, inter alia, an attach-
    ment of forty-five unpaid invoices, which showed that
    it had not been paid for the materials it had delivered
    to CSS. Morganti disputed the claim by way of a letter
    sent to the defendant’s claims representative on March
    16, 2017, stating that the plaintiff’s bond claim was
    without merit and that neither the defendant nor Mor-
    ganti was liable to the plaintiff for any unpaid balances.
    Specifically, Morganti’s response indicated that the
    plaintiff’s claim should not be paid because the plaintiff
    failed to include a copy of any contract or purchase
    order between the plaintiff and CSS; therefore, it could
    not be ascertained if the amount included on the form
    submitted by the plaintiff was an accurate reflection of
    the balance owed. The defendant thereafter denied the
    plaintiff’s claim in a letter dated April 6, 2017, asserting
    that it was denying the plaintiff’s claim because it was
    ‘‘not in a position to intercede [to] make payment of
    the amounts claimed’’ because there appeared to be
    ‘‘legitimate issues of controversy between Morganti and
    the [plaintiff].’’ The plaintiff sent the defendant a letter
    dated April 10, 2017, contesting the bases set forth in
    Morganti’s March 16, 2017 letter. Morganti then sent
    the defendant’s claims representative a letter dated May
    3, 2017, reiterating the reasons it believed the plaintiff’s
    claim must be denied. The defendant confirmed its
    denial of the plaintiff’s claim in an e-mail sent to the
    plaintiff and Morganti on May 5, 2017.
    At trial, Robert Jonke, the plaintiff’s credit manager
    and sole testifying witness, testified that there was a
    signed credit agreement between CSS and the plaintiff,
    along with signed delivery tickets, invoices, and a price
    quotation. Jonke also stated that each verbal order CSS
    placed was confirmed by written delivery tickets, which
    included a list of the materials ordered.
    The court looked to the terms of the payment bond
    and found that there was no condition in the agreement
    stating that oral agreements were unacceptable, nor
    was there a requirement that the agreement or contract
    be executed in one single document. The court found
    that the plaintiff had satisfied all of the conditions of
    the payment bond. Particularly, the court found that
    exhibit 51, which included the notice of claim, satisfied
    ‘‘items 1, 2, 4, 5, 6, 7, and 8 of § 16.1 of the payment
    bond.’’ Moreover, the court found that item 3 of § 16.1
    of the payment bond, which called for the submission
    of a copy of an agreement or purchase order, was satis-
    fied by exhibit 67, which included the signed delivery
    tickets and invoices on the plaintiff’s business letter-
    head. Additionally, the court found that the documents
    contained in exhibits 5 and 6, which included the Redi-
    Mix price quotation and materials price quotation, and
    the credit agreement executed by CSS and the plaintiff,
    also satisfied item 3 of § 16.1.12 The defendant claimed
    that only invoices were submitted. Nevertheless, the
    court found that the plaintiff established by a prepon-
    derance of the evidence that there was indeed an agree-
    ment between CSS and the plaintiff, and the documents
    the plaintiff provided satisfied the condition precedent
    of § 16.1 of the payment bond.
    On appeal, the defendant claims that the court erred
    in finding that the plaintiff fulfilled the prerequisite to
    receiving payment under the payment bond.13 The
    defendant contends that the plaintiff failed to furnish
    any agreements or purchase orders between CSS and
    the plaintiff. The defendant claims that § 16.1 of the
    payment bond agreement requires all claimants, such
    as the plaintiff, to submit at least a ‘‘copy of the agree-
    ment or purchase order pursuant to which labor, materi-
    als or equipment was furnished for use in performance
    of the [c]onstruction [c]ontract . . . .’’ According to
    the defendant, the plaintiff did not submit a written
    document detailing the agreement between the plaintiff
    and CSS for purchase of the materials, and the docu-
    ments relied on by the court were not indicative of an
    agreement. The defendant claims that neither the Redi-
    Mix price quotation nor the materials price quotation
    relied on by the court was signed by CSS. Moreover,
    the defendant argues that many delivery tickets were
    unsigned by CSS and the signed delivery tickets
    included no terms and conditions of the sale so as to
    constitute a written agreement. The defendant further
    contends that the bulk of the documents on which the
    court relied to establish a contractual relationship or
    agreement between CSS and the plaintiff were never
    submitted to the defendant. The defendant identifies
    this as an indispensable condition precedent that bars
    the plaintiff’s ability to recover because the defendant
    is entitled to review the agreement between a subcon-
    tractor and a supplier, such as the plaintiff. Finally, the
    defendant takes issue with the fact that the agreement
    between CSS and the plaintiff was ‘‘only an oral agree-
    ment’’ and the plaintiff sent invoices instead of a written
    agreement or purchase order.
    ‘‘Whether the performance of a certain act by a party
    to a contract is a condition precedent to the duty of
    the other party to act depends on the intent of the
    parties as expressed in the contract and read in the
    light of the circumstances surrounding the execution
    of the instrument.’’ (Internal quotation marks omitted.)
    Pack 2000, Inc. v. Cushman, 
    311 Conn. 662
    , 676–77,
    
    89 A.3d 869
     (2014). ‘‘A condition is an event, not certain
    to occur, which must occur . . . before performance
    under a contract becomes due. . . . If the condition is
    not fulfilled, the right to enforce the contract does not
    come into existence.’’ (Citation omitted; internal quota-
    tion marks omitted.) Feinberg v. Berglewicz, 
    32 Conn. App. 857
    , 860, 
    632 A.2d 709
     (1993).
    Jonke testified at trial that each order placed by CSS
    was orally agreed to and memorialized or confirmed
    by invoices and delivery tickets. Item 3 of § 16.1 of
    the payment bond calls for a copy of an agreement or
    purchase order that evidences the labor, materials or
    equipment furnished for use in the project. It can rea-
    sonably be inferred that the purpose of item 3 is for
    the defendant to be provided with evidence that there
    existed an agreement between the claimant and a con-
    tractor or subcontractor to provide materials, labor,
    or equipment for the project. The information in the
    invoices identified CSS as the party receiving the labor,
    materials or equipment; provided an itemized list with
    a description of the services, materials or supplies deliv-
    ered to CSS; and included the total price, the invoice
    date, and where the delivery took place. The invoices
    were also on the plaintiff’s letterhead. The invoices
    submitted by the plaintiff set out exactly what materials
    the plaintiff agreed to furnish to CSS. Item 3 of § 16.1
    of the payment bond makes no mention of a require-
    ment of a written agreement being necessary for the
    claim to be deemed valid.
    There is no dispute that the plaintiff supplied materi-
    als to CSS for the project for which the plaintiff was
    not paid. The plaintiff provided the defendant with
    forty-five invoices with its proof of claim indicating that
    CSS and the plaintiff had an ongoing agreement for the
    materials to be supplied to CSS for the benefit of the
    project. The defendant acknowledges that there was
    such an agreement between the plaintiff and CSS but,
    nevertheless, challenges the form in which the plaintiff
    supplied proof of that agreement. The payment bond
    failed to exclude any specific type of agreements or to
    indicate that proof of certain types of agreements was
    disallowed upon making a claim.
    Because we agree with the court’s conclusions con-
    cerning the interpretation of the payment bond, we
    conclude that the court’s finding that the forty-five
    invoices submitted to the defendant, which set forth
    the relationship between CSS and the plaintiff, were
    sufficient to comply with item 3 of § 16.1 of the payment
    bond was supported by the evidence. Thus, there was
    no error.
    III
    The defendant next claims that the court erred by
    allowing the plaintiff to recover damages in excess of
    the penal sum of the substitute bond.14 For the reasons
    that follow, we decline to review the merits of this claim.
    The following facts and procedural history are rele-
    vant to this claim. As noted previously, the plaintiff had
    recorded a mechanic’s lien against Morganti for the
    balance owed on account of the materials it had sup-
    plied to the project. Thereafter, the plaintiff, Morganti,
    and the defendant executed the substitute bond agree-
    ment whereby the plaintiff agreed to discharge the
    mechanic’s lien and transfer the mechanic’s lien to a
    substitute bond, which the defendant posted as surety.
    Morganti and the defendant agreed to be bound to the
    plaintiff for up to $533,411.23, which covered the
    mechanic’s lien of $484,919.30 and included an addi-
    tional $48,491.93, the amount included for costs and
    interest pursuant to § 49-37. In May, 2018, the plaintiff
    filed an offer of compromise with the court offering
    to settle all of its claims against the defendant if the
    defendant paid the plaintiff $460,000. The defendant
    failed to respond to, or to take action on, the plaintiff’s
    offer of compromise.
    After finding that the $484,919.30 amount due to the
    plaintiff had been wrongfully withheld by the defendant,
    the court rendered judgment on both counts of the
    complaint in favor of the plaintiff and awarded the
    plaintiff a total of $628,403, with attorney’s fees to be
    determined after a postjudgment hearing.15 The court’s
    calculus included the $484,919 damages owed to the
    plaintiff, $57,930 in prejudgment interest, and $85,554
    in offer of compromise interest.
    With respect to the prejudgment interest, the court,
    in its discretion, awarded the plaintiff prejudgment
    interest of 5 percent per annum pursuant to General
    Statutes § 37-3a, which provides in relevant part that,
    ‘‘[e]xcept as provided in sections 37-3b, 37-3c and 52-
    192a, interest at the rate of ten percent a year, and no
    more, may be recovered and allowed in civil actions
    . . . including actions to recover money loaned at a
    greater rate, as damages for the detention of money
    after it becomes payable. . . .’’ The court also awarded
    the plaintiff offer of compromise interest pursuant to
    General Statutes § 52-192a (c), which authorizes the
    court to add interest of 8 percent per annum if ‘‘the
    plaintiff made an offer of compromise which the defen-
    dant failed to accept,’’ and the plaintiff recovers ‘‘an
    amount equal to or greater than the sum certain speci-
    fied in the plaintiff’s offer of compromise . . . .’’ The
    court then indicated that a postjudgment hearing would
    take place in order for the parties to address issues
    concerning the calculation of attorney’s fees, offer of
    compromise interest and prejudgment interest. The
    court also allowed the parties to ‘‘file a timely procedur-
    ally correct motion to reargue concerning the determi-
    nation of interest in any form and the calculation
    thereof.’’ Neither party submitted a motion to reargue
    regarding the damages award nor did either party raise
    any objections as to the court’s calculations.16
    The defendant’s claim is waived because it raised no
    objections at trial regarding the award or the court’s
    calculus. ‘‘Generally, to preserve an issue for review, a
    party must . . . object or otherwise assert such issue.
    A party cannot preserve a claim through inaction but,
    instead, must engage in affirmative conduct at an appro-
    priate time.’’ MBNA America Bank, N.A. v. Bailey, 
    104 Conn. App. 457
    , 467, 
    934 A.2d 316
     (2007). ‘‘[T]o review
    [a] claim, which has been articulated for the first time
    on appeal and not before the trial court, would result
    in a trial by ambuscade of the trial judge.’’ (Internal
    quotation marks omitted.) Ed Lally & Associates, Inc.
    v. DSBNC, LLC, 
    145 Conn. App. 718
    , 729, 
    78 A.3d 148
    (2013)
    Thus, because the defendant failed to raise any objec-
    tions at trial concerning the court’s award of prejudg-
    ment and offer of compromise interest as part of its
    damages award, this claim is waived and an analysis
    of its merits is not warranted.
    IV
    The defendant next claims that the court erred in
    allowing the plaintiff to put on a rebuttal case after the
    defendant rested its case without calling any witnesses
    or introducing any evidence. We disagree.
    We first set forth the standard of review for this claim.
    ‘‘It is well settled that the admission of rebuttal evidence
    lies within the sound discretion of the trial court.’’
    (Internal quotation marks omitted.) Boone v. Boeh-
    ringer Ingelheim Pharmaceuticals, Inc., 
    335 Conn. 547
    ,
    573, 
    239 A.3d 1175
     (2020). ‘‘Our standard of review of
    the [defendant’s] claim is that of whether the court
    abused its discretion in allowing this . . . testimony.
    . . . Discretion means a legal discretion, to be exer-
    cised in conformity with the spirit of the law and in a
    manner to subserve and not to impede or defeat the
    ends of substantial justice. . . . It goes without saying
    that the term abuse of discretion . . . means that the
    ruling appears to have been made on untenable
    grounds. . . . In determining whether the trial court
    has abused its discretion, we must make every reason-
    able presumption in favor of the correctness of its
    action.’’ (Citation omitted; internal quotation marks
    omitted.) Cafro v. Brophy, 
    62 Conn. App. 113
    , 118–19,
    
    774 A.2d 206
    , cert. denied, 
    256 Conn. 933
    , 
    776 A.2d 1149
    (2001). ‘‘This court will affirm a trial court’s admission
    of rebuttal evidence which would have been normally
    presented as part of the case-in-chief unless the party
    claiming error sustains his burden of establishing harm-
    ful error.’’ State v. Lisella, 
    187 Conn. 335
    , 337–38, 
    445 A.2d 922
     (1982).
    At trial, the defendant rested without calling any wit-
    nesses regarding its special defenses; however, the
    defendant did cross-examine Jonke, the only witness
    presented at trial by the plaintiff. The defendant cross-
    examined Jonke for several days and also admitted
    various documents as exhibits concerning its special
    defenses during the plaintiff’s case-in-chief. The court
    did not allow the plaintiff to submit evidence to rebut
    the defendant’s special defenses in its case-in-chief.
    Instead, after the defendant rested and over the defen-
    dant’s objection, the court allowed the plaintiff to call
    Lawrence Rosati as a rebuttal witness based on the
    defendant’s cross-examination. Rosati served as Mor-
    ganti’s project executive on the construction project in
    question. The court also allowed the plaintiff, over the
    defendant’s objection, to introduce e-mail correspon-
    dence between CSS and Morganti, as well as spread-
    sheets created by CSS for billing requests submitted to
    Morganti, in order for the plaintiff to establish that
    Morganti continued to give CSS money even after Mor-
    ganti was on notice that CSS had not been paying the
    plaintiff. The spreadsheets purportedly showed that
    there was a sum due to the plaintiff in early fall of 2016.
    Before determining that the plaintiff was allowed to put
    forth the rebuttal witness, the court heard the parties’
    arguments as to whether the plaintiff was permitted to
    proceed with its witness. The plaintiff posited that it
    was calling the rebuttal witness ‘‘[b]ecause there was
    evidence produced during cross-examination’’ by the
    defendant addressing the defendant’s special defenses.
    The plaintiff also argued that it should be allowed to
    put on the rebuttal witness because the court barred
    the plaintiff from putting on any evidence in its case-
    in-chief to address the defendant’s special defenses.
    The defendant countered by asserting that the law does
    not allow a party to submit rebuttal testimony where
    the opposing party has not presented any evidence in
    its case-in-chief because there is no case to rebut, irre-
    spective of whether evidence concerning the defen-
    dant’s special defenses was proffered by the defendant
    during the plaintiff’s case-in-chief.
    The court noted that the defendant offered evidence
    during its extensive cross-examination of the plaintiff’s
    sole witness, and the defendant also ‘‘proffered some
    documents in evidence.’’ The court also indicated that
    the defendant did not have to put forth any evidence
    in its direct case in order to sustain its burden of proof
    on the special defenses because the defendant could
    sustain its burden by the evidence the plaintiff put
    before the court. While primarily resting its reasoning
    on the findings in State v. Lisella, 
    supra,
     
    187 Conn. 335
    , the court asserted that the threshold question is
    whether the plaintiff’s proffered evidence ‘‘could have
    been introduced at an earlier stage in the proceedings.’’
    The court allowed the plaintiff’s rebuttal evidence on
    the basis of its discretion as provided under Practice
    Book § 15-5 and also because it had denied the plaintiff
    the opportunity to present evidence to rebut the defen-
    dant’s special defenses during the plaintiff’s case-in-
    chief.17 Before allowing the plaintiff to put forth the
    evidence, the court iterated to the parties that the scope
    of the plaintiff’s rebuttal evidence was limited only to
    the defendant’s nine special defenses. The plaintiff was
    not allowed to submit rebuttal evidence in support of
    its case-in-chief.
    ‘‘[R]ebuttal evidence is that which refutes the evi-
    dence [already] presented . . . rather than that which
    merely bolsters one’s case.’’ (Internal quotation marks
    omitted.) Boone v. Boehringer Ingelheim Pharmaceuti-
    cals, Inc., supra, 
    335 Conn. 573
    . ‘‘[A] general contradic-
    tion of the testimony given by the defendant is consid-
    ered permissible rebuttal testimony.’’ (Internal
    quotation marks omitted.) 
    Id.,
     573–74. The court in
    Boone also cited to 1 K. Broun, McCormick on Evidence
    (7th Ed. 2013) § 4, p. 16, for the proposition that a
    plaintiff is ‘‘confined to testimony refuting the defense
    evidence,’’ unless the court, in its discretion, permits a
    party to ‘‘depart from the regular scope of rebuttal.’’
    (Internal quotation marks omitted.) Id., 574.
    ‘‘[T]he policy behind restrictions on the presentation
    of rebuttal testimony is that a plaintiff is not entitled
    to a second opportunity to present evidence that should
    reasonably have been presented in [its] case-in-chief.’’
    (Internal quotation marks omitted.) Cafro v. Brophy,
    supra, 
    62 Conn. App. 120
    . In Cafro, we determined that
    the trial court abused its discretion when it allowed the
    plaintiffs to call a witness at the last minute after the
    plaintiffs had rested their case-in-chief and the witness
    testified about a highly contested issue. 
    Id.
     The distinc-
    tion in the present case, however, is that the plaintiff
    was specifically barred by the trial court from introduc-
    ing any evidence to rebut the defendant’s special
    defenses during its case-in-chief, even after the defen-
    dant submitted evidence concerning the special
    defenses. The court indicated that it had barred the
    plaintiff from presenting such evidence because it
    believed it to be improper to allow the plaintiff to put
    on a rebuttal case during its case-in-chief where, at the
    time the plaintiff initially presented the evidence, the
    issue of the special defenses had not yet been raised.
    The defendant’s sole contention on appeal related to
    this issue is that the plaintiff should not be allowed to
    submit rebuttal evidence because the defendant did not
    present any evidence or testimony during the defen-
    dant’s case-in-chief. The record shows that the defen-
    dant engaged in a lengthy cross-examination of the
    plaintiff’s sole witness and admitted evidence during
    the plaintiff’s case-in-chief, and, as the defendant con-
    ceded at trial, cross-examination is indeed evidence.
    The plaintiff’s rebuttal was not presented to bolster
    its case-in-chief but, rather, to refute or contradict the
    evidence the defendant put forth during the defendant’s
    cross-examination of Jonke concerning the defendant’s
    special defenses, and the documents that the defendant
    admitted during that cross-examination. Thus, the argu-
    ment advanced by the defendant is untenable.
    As our Supreme Court has observed, the trial court
    has the sound discretion as to the order of the proceed-
    ings. See Boone v. Boehringer Ingelheim Pharmaceuti-
    cals, Inc., supra, 
    335 Conn. 573
    ; see also Practice Book
    § 15-5. We cannot conclude that the court abused its
    discretion by allowing the plaintiff’s rebuttal evidence
    after the defendant rested without putting forth any
    evidence in its case-in-chief where, as here, the defen-
    dant pleaded special defenses in its pleadings and,
    partly, geared its cross-examination of the plaintiff’s
    witness toward addressing those special defenses.
    Additionally, the court barred the plaintiff from
    addressing the defendant’s special defenses in its case-
    in-chief. Accordingly, the court did not abuse its discre-
    tion in allowing the plaintiff’s rebuttal evidence.
    The judgment is affirmed.
    In this opinion the other judges concurred.
    1
    See footnote 5 of this opinion.
    2
    The Wall Street Theater project was a construction project unrelated to
    the project at issue.
    3
    General Statutes § 49-37 (a) provides in relevant part: ‘‘Whenever any
    mechanic’s lien has been placed upon any real estate pursuant to sections
    49-33, 49-34 and 49-35, the owner of that real estate, or any person interested
    in it, may make an application to any judge of the Superior Court that the
    lien be dissolved upon the substitution of a bond with surety, and the judge
    shall order reasonable notice to be given to the lienor of the application.
    . . . Whenever a bond has been substituted for any lien, pursuant to this
    section, unless an action is brought to recover upon the bond within one
    year from the date of recording the certificate of lien, the bond shall be void.’’
    4
    On appeal, the defendant does not contest the court’s findings as to its
    sixth, seventh, and ninth special defenses. With respect to the defendant’s
    sixth special defense, which alleged that the plaintiff’s claims under the
    bonds were barred because the owner and Morganti had paid in full for the
    materials supplied when they paid CSS, the court found for the plaintiff
    because it was undisputed that the plaintiff had not received any payments
    from the owner, Morganti, or CSS for the $484,919.30 owed to the plaintiff
    for the materials it furnished and because General Statutes § 49-36 ‘‘only
    permits such prepayment credit to property owners, not the general contrac-
    tor.’’
    With respect to the seventh special defense, which alleged that the plain-
    tiff’s substitute bond claim was barred because neither the owner, Morganti,
    nor the defendant owed the plaintiff for the materials supplied, the court
    found for the plaintiff because the parties had stipulated to the fact that
    the plaintiff indeed was owed $484,919.30 for materials it supplied that were
    used for the project.
    As to the ninth special defense, the court found that the plaintiff’s claims
    were not barred because the oral agreement between CSS and the plaintiff
    fell under the ‘‘specially manufactured exception’’ under § 42a-2-201 (3) and,
    thus, was an enforceable agreement. Further, alternatively, the court found
    that the delivery tickets and the credit agreement signed by CSS were
    sufficient to satisfy the requirement for a signed writing.
    5
    Although the defendant also claims on appeal that the court erred when
    it determined that its equitable special defenses did not apply to the surety
    action at law brought by the plaintiff, we need not address that claim in
    light of the fact that the court did, in fact, examine the merits of those
    equitable special defenses and determined, in the alternative, that the defen-
    dant had failed to meet its burden of proof as to those special defenses.
    Moreover, in its appellate brief, the defendant contests only the court’s
    findings as to whether the plaintiff breached the obligation of ‘‘diligence
    and the utmost good faith’’ the defendant believed it was owed, and the
    court’s findings as to whether the plaintiff’s conduct was ‘‘unreasonable’’
    and ‘‘reckless.’’ Because the defendant has not challenged the court’s finding
    that the plaintiff was not barred from recovering under the bonds pursuant
    to the doctrine of unclean hands, we review only the court’s finding that
    the defendant did not sustain its burden of establishing that the plaintiff
    breached the obligation of ‘‘diligence and the utmost good faith.’’
    6
    As noted previously, the defendant also had asserted the same theory
    in its pretrial brief.
    7
    Although the court referenced ‘‘unclean hands,’’ we only discuss the
    court’s findings as to bad faith and common-law recklessness. See footnote
    5 of this opinion.
    8
    General Statutes § 42-158l (a) provides: ‘‘Any provision in a construction
    contract or any periodic lien waiver issued pursuant to a construction con-
    tract that purports to waive or release the right of a contractor, subcontractor
    or supplier engaged to perform services, perform labor or furnish materials
    under the construction contract to (1) claim a mechanic’s lien, or (2) make
    a claim against a payment bond, for services, labor or materials which have
    not yet been performed and paid for shall be void and of no effect.’’
    9
    The defendant must establish that a contract existed between it and the
    plaintiff, and that the plaintiff acted in bad faith in carrying out its obligations
    under the contract in order to sustain a claim that the plaintiff acted in bad
    faith amounting to a breach of the implied covenant of good faith and fair
    dealing. As the court found, ‘‘[a]ll material suppliers had the right to make
    a claim upon the payment bond simply by meeting the terms of § 16.1 [of
    the payment bond]. No other conditions were set forth in the payment bond
    for any material supplier to make a claim that they had not been paid for
    materials furnished to them to this construction project. The payment bond
    did not require any material supplier to perform credit checks on the subcon-
    tractor who hired them. The payment bond makes no mention of [the plain-
    tiff] by name. [The plaintiff] did not sign, guarantee or otherwise participate
    in a modification or amendment of the payment bond. . . . When CSS
    proposed in September, 2016, to charge [the plaintiff’s] materials to CSS’
    account, [Morganti] did not object nor did it or the defendant offer certain
    protective tools to verify that CSS would in fact pay [the plaintiff] in full
    and timely.’’
    10
    The defendant does not contest the court’s interpretation of the payment
    bond’s provisions on appeal.
    11
    Section 16.1 of the payment bond provides that a valid claim must
    include a written statement by the claimant and include, at minimum, (1)
    ‘‘the name of the claimant’’; (2) ‘‘the name of the person for whom the labor
    was done, or materials or equipment furnished’’; (3) ‘‘a copy of the agreement
    or purchase order pursuant to which labor, materials or equipment was
    furnished for use in the performance of the [c]onstruction [c]ontract’’; (4)
    ‘‘a brief description of the labor, materials or equipment furnished’’; (5) ‘‘the
    date on which the [c]laimant last performed labor or last furnished materials
    or equipment for use in the performance of the [c]onstruction [c]ontract’’; (6)
    ‘‘the total amount earned by the [c]laimant for labor, materials or equipment
    furnished as of the date of the [c]laim’’; (7) ‘‘the total amount of previous
    payments received by the [c]laimant’’; and (8) ‘‘the total amount due and
    unpaid to the [c]laimant for labor, materials or equipment furnished as of
    the date of the [c]laim.’’
    12
    On appeal, the defendant challenges only the court’s finding that the
    documents furnished by the plaintiff satisfied item 3 of § 16.1 of the payment
    bond. The defendant does not contest the court’s findings that the plaintiff
    satisfied items 1, 2, 4, 5, 6, 7, and 8 of § 16.1 of the payment bond.
    13
    We note that the plaintiff was not a party to the payment bond agreement
    or contract but merely a claimant as defined in § 16.2 of the payment bond,
    which provides in relevant part that a claimant is an ‘‘individual or entity
    having a direct contract with the [c]ontractor or with a subcontractor of
    the [c]ontractor to furnish labor, materials or equipment for use in the
    performance of the [c]onstruction [c]ontract. The term [c]laimant also
    includes any individual or entity that has rightfully asserted a claim under
    an applicable mechanic’s Iien . . . .’’
    14
    We note that the defendant is not contesting the court’s decision as to
    the amount awarded under count two of the complaint, in which the plaintiff
    sought relief under the payment bond that had a penal sum of approximately
    $53 million.
    15
    We note that ‘‘a judgment on the merits is final for purposes of appeal
    even though the recoverability or amount of attorney’s fees for the litigation
    remains to be determined.’’ (Internal quotation marks omitted.) Doyle Group
    v. Alaskans for Cuddy, 
    164 Conn. App. 209
    , 218, 
    137 A.3d 809
    , cert. denied,
    
    321 Conn. 924
    , 
    138 A.3d 284
     (2016). Moreover, ‘‘[w]hether the claim for
    attorney’s fees is based on statute, a contract, or both, the pendency of a
    ruling on an award for fees and costs does not prevent, as a general rule,
    the merits judgment from becoming final for purposes of appeal.’’ (Internal
    quotation marks omitted.) Id., 220.
    16
    We do not consider whether the defendant was required to file a motion
    to reargue in order to preserve this claim. The defendant’s claim, however,
    is waived because it failed to file or raise any objections at trial regarding
    the court’s award.
    17
    Practice Book § 15-5 (a) provides in relevant part: ‘‘Unless the judicial
    authority for cause permits otherwise, the parties shall proceed with the
    trial and argument in the following order:
    ‘‘(1) The plaintiff shall present a case-in-chief.
    ‘‘(2) The defendant may present a case-in-chief.
    ‘‘(3) The plaintiff and the defendant may present rebuttal evidence in
    successive rebuttals, as required. The judicial authority for cause may permit
    a party to present evidence not of a rebuttal nature, and if the plaintiff is
    permitted to present further evidence in chief, the defendant may respond
    with further evidence in chief. . . .’’