Abrams v. PH Architects, LLC , 183 Conn. App. 777 ( 2018 )


Menu:
  • ***********************************************
    The “officially released” date that appears near the be-
    ginning of each opinion is the date the opinion will be pub-
    lished in the Connecticut Law Journal or the date it was
    released as a slip opinion. The operative date for the be-
    ginning of all time periods for filing postopinion motions
    and petitions for certification is the “officially released”
    date appearing in the opinion.
    All opinions are subject to modification and technical
    correction prior to official publication in the Connecticut
    Reports and Connecticut Appellate Reports. In the event of
    discrepancies between the advance release version of an
    opinion and the latest version appearing in the Connecticut
    Law Journal and subsequently in the Connecticut Reports
    or Connecticut Appellate Reports, the latest version is to
    be considered authoritative.
    The syllabus and procedural history accompanying the
    opinion as it appears in the Connecticut Law Journal and
    bound volumes of official reports are copyrighted by the
    Secretary of the State, State of Connecticut, and may not
    be reproduced and distributed without the express written
    permission of the Commission on Official Legal Publica-
    tions, Judicial Branch, State of Connecticut.
    ***********************************************
    MARC ABRAMS v. PH ARCHITECTS, LLC, ET AL.
    (AC 40164)
    Prescott, Elgo and Blawie, Js.
    Syllabus
    The plaintiff homeowner sought to recover damages from the defendants,
    P Co., an architectural firm, and V Co., a general contractor, which he
    had hired to design and perform substantial renovations to his home
    and surrounding property. The plaintiff’s complaint alleged, as to P Co.,
    breach of the architectural contract, breach of warranty, and profes-
    sional negligence, and, as to V Co., breach of the home construction
    contract and breach of a separate contract to construct a stone wall.
    The defendants each filed counterclaims alleging that the plaintiff
    breached the contracts by failing to pay invoices for services rendered
    and sought, inter alia, the sums that the plaintiff had withheld in
    retainage. Following a trial, the court rendered judgment permitting the
    plaintiff to keep a small portion of the retainage for certain work by V
    Co. that was defective or incomplete, but otherwise rendered judgment
    in favor of the defendants on the complaint and on their counterclaims
    and awarded them damages. On the plaintiff’s appeal to this court, held:
    1. The plaintiff could not prevail on his claim that the trial court improperly
    failed to enforce provisions of his contracts with V Co. and P Co. per-
    taining to how change orders and payment requisitions were to be
    initiated and processed:
    a. The plaintiff’s claim that V Co. breached the construction contract
    by failing to follow change order procedures was unavailing; the plaintiff
    failed to allege that ground in his complaint as a basis for V Co.’s breach
    of contract, the trial court did not address the claim in rejecting that
    count of the complaint, as the court was limited to the allegations in
    the complaint and had no duty to scrutinize the parties’ agreement
    looking for potential additional breaches, and, therefore, the issue could
    not form the basis of a claim on appeal that the trial court improperly
    rejected the plaintiff’s claim that V Co. breached the construction
    contract.
    b. The trial court properly rejected the plaintiff’s claim that P Co.’s
    actions in handling change orders and billing procedures amounted to
    a material breach of its contract with the plaintiff; that court found no
    material breach of contract with respect to P Co. while it was still on
    the project and that any failure of V Co. to follow strict contract proce-
    dures after P Co. was terminated from the project could not be attributed
    to P Co., and the plaintiff did not demonstrate that the court’s factual
    findings were unsupported by the record or that the court failed to give
    due consideration to the terms of the contract in determining that P
    Co. had not breached its contract with the plaintiff regarding its handling
    of change orders.
    2. The plaintiff’s claim that V Co. failed to construct the wall and fence in
    a particular location and with certain specifications required by the wall
    contract was unavailing, the trial court having found that the specifica-
    tions and location of the wall were modified by subsequent agreement
    of the parties; that court found that the repositioning of the wall was
    done at the plaintiff’s request when he was confronted with the potential
    extra cost of building the wall at a location involving significant ledge
    rock and tree removal, that any deviation from the terms of the contract
    was authorized and approved by the plaintiff, and that the parties had
    agreed to modify the terms of the contract by moving the location of
    the wall to avoid increasing the contract price, which was an expressed
    concern of the plaintiff, who failed to demonstrate that the court’s
    finding regarding the modification of the contract was clearly erroneous.
    3. The plaintiff could not prevail on his claim that the trial court failed to
    enforce provisions of his architectural contract with P Co. that required
    P Co. to provide contract administration services and to represent his
    best interests with respect to the project; although the architectural
    contract required P Co. to monitor the construction process and review
    the final work, it also stated that the scope of P Co.’s services during
    the actual construction would be finalized at a future meeting once the
    scope of the project was better understood, which the court determined
    left some uncertainty, no evidence was presented that a meeting to
    determine the final scope of the work ever occurred, and there was no
    evidentiary foundation for the plaintiff’s claim that P Co. breached its
    contract prior to P Co. departing the project, as the court found that,
    prior to the plaintiff terminating P Co. from the project, P Co. effectively
    had complied with its contract administration duties by monitoring the
    progress of the project, engaging in discussions on-site regarding the
    construction of the rock wall, and reviewing and discussing with the
    plaintiff a proposed change order submitted by V Co.
    4. The plaintiff failed to demonstrate his claim that P Co. had breached
    the professional standard of care applicable to architects: although the
    plaintiff presented expert testimony from a practicing architect who
    had prepared a list of purportedly incomplete or defective work, which
    indicated that P Co. had failed to adequately advise the plaintiff regarding
    a radiant heat system under the flooring, to design a code-compliant
    pool enclosure, and to design a code-compliant cover or enclosure for
    the hot tub, P Co.’s expert contradicted much of that expert’s testimony
    and, as the trier of fact, the trial court had the authority to resolve that
    conflict as it saw fit and was not required to credit any part of the
    testimony by the plaintiff’s expert; moreover, there was an evidentiary
    basis for the court’s decision to reject the testimony of the plaintiff’s
    expert, as the court found that the plaintiff made a final decision regard-
    ing radiant heat after P Co. was no longer involved with the project,
    that although P Co. had told the plaintiff at their first meeting that the
    pool would need to have fencing around it in order to comply with the
    town’s pool code, the plaintiff insisted otherwise and that a proper pool
    enclosure fence was specifically not included in the scope of work that
    the plaintiff set out for P Co., and that hot tub manufacturers provide
    code-compliant covers for hot tubs and that such a cover was on the
    tub when it was installed.
    5. The trial court’s findings regarding the plaintiff’s ‘‘punch list’’ that identified
    certain items of work that V Co. allegedly had left incomplete or in need
    of repair were not clearly erroneous; the plaintiff’s claim called into
    doubt the trial court’s calculation of the portion of the retainage that
    the plaintiff was permitted to keep for incomplete or defective work,
    which the plaintiff maintained exceeded $500,000, the trial court deter-
    mined that the punch list and its associated pricing were rife with errors
    and exaggerations and included, for example, the costs associated with
    removing and reconstructing the stone wall and removing the entire
    interior hardwood floor, and that court previously had determined there
    was no credible evidence or economic rationale that supported taking
    those the corrective actions.
    Argued April 9—officially released July 31, 2018
    Procedural History
    Action seeking to recover damages for, inter alia,
    breach of contract, and for other relief, brought to the
    Superior Court in the judicial district of Stamford-Nor-
    walk, where the defendant V.A.S. Construction, Inc.,
    filed a counterclaim; thereafter, the named defendant
    filed a counterclaim; subsequently, the matter was tried
    to the court, Hon. Taggart D. Adams, judge trial referee;
    judgment for the defendants on the complaint and coun-
    terclaims, from which the plaintiff appealed to this
    court. Affirmed.
    Jane I. Milas, for the appellant (plaintiff).
    Jared Cohane, with whom was Alexa T. Millinger,
    for the appellee (named defendant).
    Gregory J. Williams, for the appellee (defendant
    V.A.S. Construction, Inc.).
    Opinion
    PRESCOTT, J. This appeal arises out of a dispute
    between a homeowner and the architectural firm and
    general contractor that he hired to design and perform
    substantial renovations to his home and surrounding
    property in Greenwich. The plaintiff, Marc Abrams,
    appeals, following a trial to the court, from the judgment
    rendered against him on his complaint and on the coun-
    terclaims of the defendants, PH Architects, LLC (PH),
    and V.A.S. Construction, Inc. (VAS). The plaintiff claims
    on appeal that the court improperly (1) failed to enforce
    provisions in his contracts with VAS and PH related to
    the processing of change orders and invoices; (2) failed
    to find that VAS had breached a separate contract gov-
    erning the construction of a stone wall and fence on
    the property; (3) failed to enforce provisions in his
    contract with PH pursuant to which PH agreed to pro-
    vide contract administration services; (4) failed to con-
    clude that PH was liable for professional negligence
    because it had breached the professional standard of
    care for architects; and (5) made clearly erroneous fac-
    tual findings with respect to a ‘‘punch list’’ that was
    prepared on behalf of the plaintiff by a third party.1
    We are not persuaded by the plaintiff’s claims and,
    accordingly, affirm the judgment of the court.2
    The following facts, which either were found by the
    court or are undisputed in the record, and procedural
    history are relevant to our discussion of the plaintiff’s
    claims on appeal. The plaintiff is a New York attorney
    employed by a firm that oversees union elections. In
    2010, he purchased an existing, single-family home
    located in Greenwich at 39 Hunting Ridge Road (prop-
    erty). The property consists of an approximately four
    acre lot that, in addition to a split-level home, features
    an outdoor swimming pool, a pond, a barn, and a ten-
    nis court.
    On May 14, 2010, the plaintiff entered into a contract
    with PH, an architectural firm, for services related to
    the design of renovations and additions that the plaintiff
    sought to make to the interior of the home and to the
    surrounding property (architectural contract). He was
    introduced to the principals of PH, Peter Paulos and
    Philip Hubbard, by his realtor, and met with them at
    the property on May 11, 2010, to discuss the renovation
    project. At that meeting, the plaintiff conveyed to the
    architects his desire to contain the overall cost of the
    project, indicating to them that, in designing and quoting
    the project, they should contemplate using only the
    highest quality materials and labor in order to help
    guard against the possibility of the project later running
    over budget. He believed that by getting quotes for
    high end materials and workmanship, any subsequent
    changes that occurred likely would involve a reduction,
    rather than an increase, in the overall price of the
    project.
    PH drafted a proposal dated May 12, 2010, that listed
    all of the proposed work items and set forth the hourly
    rates that PH would charge for various aspects of its
    work, including taking detailed measurements of the
    property and preparing a schematic design of the
    planned house alterations. The proposal also provided
    that, after completing the schematic design, PH would
    prepare outline specifications to use in soliciting prelim-
    inary bids from contractors. PH would next make any
    necessary changes to the schematic design, following
    which it would establish a lump sum fee for preparing
    complete drawings and negotiating and administrating
    construction contracts. The proposal expressly left
    open the cost for PH’s services during the actual con-
    struction period. The parties signed the proposal on
    May 14, 2010, which all parties agree constitutes the
    entirety of the architectural contract between the plain-
    tiff and PH.
    A schematic design limited to the house renovations
    was completed in June, 2010. The plaintiff approved
    the design, but wanted additional information regarding
    potential construction costs. With the consent of the
    plaintiff, PH also obtained additional landscape archi-
    tectural plans from a third party. The plaintiff, however,
    rejected those landscape plans. He also rejected the
    initial bid that PH had obtained for the housing renova-
    tions, believing it was too high. He then authorized PH
    to complete a more detailed set of structural drawings
    and specifications for the residence in order to solicit
    additional construction bids.
    After receiving bids, PH prepared a bid comparison
    sheet for the plaintiff that showed bids ranging from
    $1.2 million to over $1.5 million. The plaintiff was
    unhappy and wanted the overall cost of the project
    reduced significantly, indicating to Hubbard that he
    wanted the total cost to be closer to $600,000. In Octo-
    ber, 2010, PH prepared a list of possible changes that
    could help to reduce costs, including eliminating a pro-
    posed office and a closet addition. The plaintiff
    approved many of PH’s cost saving proposals. He also
    suggested, however, additional changes not in the origi-
    nal plan, including adding a side deck, an outdoor fire-
    place, and a larger master bedroom. After incorporating
    the changes approved by the plaintiff, PH obtained
    new bids.
    VAS, a general contracting business owned by Vin-
    cent Sciarretta, consistently was the low bidder
    throughout the bidding process. VAS constructs new
    homes and additions to existing homes. It submitted a
    bid of between $860,000 and $912,000.
    On December 6, 2010, the plaintiff entered into a
    contract with VAS for construction services involving
    the additions and renovations to the home contained
    in the architectural plans (construction contract). The
    contract was a standard form American Institute of
    Architects (AIA) agreement that included a total con-
    tract price for the renovations and additions of
    $921,557.34.
    The plaintiff later entered into an additional AIA con-
    tract with VAS on December 16, 2010, for the construc-
    tion of a stone wall on the property (wall contract).
    The stone wall was intended to run along the front of
    the house, connect with perimeter fencing around the
    remainder of the property, and include two operating
    gates. The contract called for a concrete footing to be
    placed three and one-half feet below grade to secure
    the fencing. The total additional cost for the wall con-
    tract was $229,985.80.
    Due to significant conflicts that arose between the
    plaintiff and PH,3 PH left the project prior to its comple-
    tion. The plaintiff never engaged a replacement archi-
    tect to oversee the project. Serious conflicts also arose
    between VAS and the plaintiff regarding, inter alia, cer-
    tain change orders submitted by VAS. Nevertheless,
    despite the plaintiff failing to make all requested prog-
    ress payments, VAS continued working on the construc-
    tion project, substantially completing its work by late
    November or early December, 2011.
    The plaintiff, who was unhappy with the results and
    overall cost of the project, initiated the present action
    in September, 2012. The operative amended complaint
    was filed on September 20, 2013, and contained five
    counts, the first three directed against PH and the
    remaining two against VAS.
    With respect to PH, count one alleged that PH
    breached the architectural contract with the plaintiff
    by ‘‘failing to provide complete and accurate plans and
    specifications for the construction of the project, failing
    to provide construction administration services, failing
    to monitor the cost and the quality of construction of
    the project, failing to correct the errors, omissions, and
    deficiencies in the services and work product provided
    by PH, failing to address [the plaintiff’s] reasonable
    questions and concerns, and instead abandoning the
    project when problems were becoming apparent to [the
    plaintiff].’’ Count two alleged that PH had breached an
    express warranty that guaranteed it was qualified to
    perform the services undertaken in the architectural
    contract and that it would do so with the care, diligence,
    and skill exercised by professional architects. Count
    three sounded in professional negligence, alleging that
    PH breached its duty to perform with ‘‘that degree of
    skill, care, and diligence [that] professional architects
    normally exhibit under like and/or similar circum-
    stances.’’
    With respect to the remaining counts against VAS,
    count four alleged that VAS breached both the home
    construction contract and the wall contract in a variety
    of ways. More particularly, the plaintiff alleged that VAS
    breached the contracts by failing to complete the work,
    using lesser quality materials than specified, and per-
    forming defective work that would require repair or
    replacement. The plaintiff provided the following addi-
    tional examples of VAS’ alleged breach of the home
    construction contract: ‘‘[T]he master bedroom deck is
    poorly constructed; stairs are not adequately secured
    and shake significantly when walked on; plumbing fix-
    tures in various locations are loose and not properly
    centered or installed; the electrical system is incom-
    plete and many switches do nothing; the supply duct-
    work in the basement has not been insulated; tile in
    areas such as the laundry room is cracked; interior trim
    is defective and there are many instances of miters
    opening up; bilco door is not installed properly or
    weatherstripped; trim boards at exterior of dining nook
    are warping and delaminating below and around win-
    dows; material for front gates and fence is not what
    was specified and is of lower quality; cabinets are incor-
    rectly installed; flooring is cupping and will have to
    be removed; many items of work remain incomplete.’’
    Count five sounded in negligence. The plaintiff alleged
    that VAS, as a general contractor, owed him a duty to
    perform its work pursuant to the contract and free from
    defects, and that it breached that duty, citing again the
    defects set forth in the breach of contract count.
    In addition to filing an answer and special defenses
    denying any liability, the defendants each filed a breach
    of contract counterclaim against the plaintiff. In its
    counterclaim, PH alleged that the plaintiff had breached
    the architectural contract by wrongfully terminating it
    from the project and by failing to pay PH in full for the
    engineering and architectural services rendered prior
    to its termination. VAS alleged in its counterclaim that,
    with the exception of certain obligations that the plain-
    tiff wrongfully prevented or precluded it from per-
    forming, it had performed or substantially performed
    all of its obligations under its contracts with the plaintiff
    and, yet, the plaintiff had failed to pay invoices totaling
    $132,996.18 and to release an additional $85,613.46
    being held in retainer.4 The plaintiff denied the defen-
    dants’ special defenses and counterclaims.
    A trial to the court, Hon. Taggart D. Adams, judge
    trial referee, was conducted between April 26 and May
    6, 2016. The parties each submitted a posttrial memo-
    randum on October 12, 2016.
    On February 7, 2017, the court issued its memoran-
    dum of decision, disposing of all counts of the complaint
    and the counterclaims. With respect to PH, the court
    concluded that the plaintiff had failed to prove any of
    his causes of action, rendering judgment against him
    on counts one through three of the complaint. The court
    also rendered judgment against the plaintiff on PH’s
    counterclaim, awarding damages of $3991.56.
    With respect to VAS, the court found that the plaintiff
    had failed to prove that VAS breached either the home
    construction contract or the wall contract. The court
    nevertheless found that the plaintiff was entitled to
    keep $8450 of the retainage as a result of certain incom-
    plete or defective work. The court rendered judgment
    in favor of VAS on its counterclaim, and awarded it
    damages of $132,966.18 plus 6 percent prejudgment
    interest of $24,092.34, as well as $77,162.46, the net
    balance of the retainage. This appeal followed.
    Before turning to our discussion of the plaintiff’s
    claims, we first address the appropriate standard of
    review, which is disputed by the parties. ‘‘It is well
    established that [i]n a case tried before a court, the
    trial judge is the sole arbiter of the credibility of the
    witnesses and the weight to be given specific testimony.
    . . . On appeal, we do not retry the facts or pass on the
    credibility of witnesses. . . . We afford great weight
    to the trial court’s findings because of its function to
    weigh the evidence and determine credibility. . . .
    Thus, those findings are binding upon this court unless
    they are clearly erroneous in light of the evidence and
    the pleadings in the record as a whole. . . . A finding
    of fact is clearly erroneous when there is no evidence
    in the record to support it . . . or when although there
    is evidence to support it, the reviewing court on the
    entire evidence is left with the definite and firm convic-
    tion that a mistake has been committed.’’ (Citations
    omitted; internal quotation marks omitted.) De La Con-
    cha of Hartford, Inc. v. Aetna Life Ins. Co., 
    269 Conn. 424
    , 431–32, 
    849 A.2d 382
    (2004).
    The plaintiff seeks to frame his claims on appeal as
    implicating our plenary review, arguing that his claims
    involve questions of contract interpretation or chal-
    lenge legal conclusions of the court. It is axiomatic that
    matters of law are entitled to plenary review on appeal.
    See Crews v. Crews, 
    295 Conn. 153
    , 162, 
    989 A.2d 1060
    (2010). It is similarly well settled that, if definitive con-
    tract language exists, ‘‘the determination of what the
    parties intended by their contractual commitments is
    a question of law.’’ (Internal quotation marks omitted.)
    Tallmadge Bros., Inc. v. Iroquois Gas Transmission
    System, L.P., 
    252 Conn. 479
    , 495, 
    746 A.2d 1277
    (2000);
    see also 11 S. Williston, Contracts (4th Ed.1999) § 30:6,
    pp. 77–83 (‘‘[t]he interpretation and construction of a
    written contract present only questions of law, within
    the province of the court . . . so long as the contract
    is unambiguous and the intent of the parties can be
    determined from the agreement’s face’’ [internal quota-
    tion marks omitted]). Moreover, whether contractual
    language is plain and unambiguous is itself a question
    of law subject to plenary review. See United Illuminat-
    ing Co. v. Wisvest-Connecticut, LLC, 
    259 Conn. 665
    ,
    669–70, 
    791 A.2d 546
    (2002).
    The defendants, by contrast, maintain that the plain-
    tiff’s claims on appeal do not truly raise any substantive
    questions of law or involve construction of relevant
    contract provisions but, rather, only seek to have this
    court reassess the credibility of witnesses and retry
    the court’s factual findings underlying its determination
    that the plaintiff failed to demonstrate that either defen-
    dant materially breached its contract with the plaintiff
    or is otherwise liable for damages. ‘‘The determination
    of whether a contract has been materially breached is
    a question of fact that is subject to the clearly erroneous
    standard of review.’’ Efthimiou v. Smith, 
    268 Conn. 487
    , 493, 
    846 A.2d 216
    (2004). We agree with the defen-
    dants that the plaintiff’s claims on appeal primarily are
    factual in nature. Accordingly, although we review de
    novo any questions of law that arise, to the extent that
    the plaintiff merely challenges the factual underpin-
    nings for the court’s legal conclusions, we will not
    engage in a wholesale reweighing of the evidence, but
    will review such claims under our clearly erroneous
    standard of review. With these principles in mind, we
    turn to a discussion of the specific claims raised by
    the plaintiff.
    I
    The plaintiff first claims that the court improperly
    failed to enforce provisions of his contracts with VAS
    and PH, specifically, provisions pertaining to how
    change orders and payment requisitions were to be
    initiated and processed.5 According to the plaintiff, VAS
    failed to follow the procedures set forth in the construc-
    tion contract, which required it to obtain the plaintiff’s
    approval for any changes prior to performing the associ-
    ated work. Further, he argues that, pursuant to his con-
    tract with PH, PH was required to review and approve
    payment requisitions and change orders submitted by
    VAS, but PH failed to insure that VAS followed the
    procedures in the construction contract.
    In response, VAS argues that, to the extent the plain-
    tiff’s claim is directed at it, we should reject that claim
    for three reasons. First, VAS argues that the plaintiff’s
    claim falls outside the scope of the pleadings because
    the plaintiff never alleged in his complaint that VAS
    breached the construction contract by failing to adhere
    to provisions governing change orders and payments,
    nor was that issue decided by the court. Second, VAS
    argues that the plaintiff has failed adequately to brief
    this claim. Third, VAS argues that the claim fails on
    its merits.
    PH argues that the claim also fails with respect to it
    because the trial court properly rejected the plaintiff’s
    allegation that PH had breached its contract with the
    plaintiff by failing to adhere precisely to requirements
    in the change order provisions of the construction con-
    tract. PH notes that, prior to leaving the project, it was
    only involved with the processing of a single change
    order and that the court found that PH’s omission of
    that change order on a certified payment requisition
    was ‘‘not of serious moment,’’ or, in other words, not
    a material breach of contract.6
    The following additional facts are relevant to this
    claim. Pursuant to the architectural contract, PH agreed
    to provide ‘‘contract administration’’ services during
    the construction phase of the project. Contract adminis-
    tration was defined in the architectural contract as fol-
    lows: ‘‘monitoring the construction process, making
    periodic site visits, representing [the plaintiff] during
    the construction process, reviewing and approving
    applications for payment to the contractor, review of
    the final work, preparation of a punch list to complete
    the work and issuing final acceptance of the work.’’ The
    architectural contract contains no express provision
    about PH’s responsibilities regarding the processing
    and handling of change orders; such provisions are
    found in the construction contract. In particular, article
    7 of the general conditions of the construction contract
    contains a number of provisions that governed the pro-
    cess by which the parties were permitted to make
    changes to the work.
    In its memorandum of decision, the court addressed
    the plaintiff’s arguments regarding improper change
    orders and invoicing procedures in addressing the plain-
    tiff’s assertions of breach of contract against PH. In
    that context, the court stated as follows: ‘‘[I]t is true
    that PH did approve an application for payment to VAS
    on April 29, 2011 . . . in which VAS had not included
    the fact that a change order in the amount of $5141.80
    had been previously approved by [the plaintiff] in writ-
    ing on March 31, 2011. . . . This oversight is not of
    serious moment, because [the plaintiff] had already paid
    for the change order on April 26, [2011] . . . and subse-
    quent change orders signed by [the plaintiff] clearly
    showed all the additions to the original contract price
    that had been approved. . . . More importantly, [the
    plaintiff’s] claim that PH never submitted or reviewed
    with him any proposed change orders is without eviden-
    tiary support. Indeed, it was PH’s submission to [the
    plaintiff] of the VAS proposed change orders, including
    the addition of radiant heat to the project, that precipi-
    tated the previously discussed virulent e-mail by [the
    plaintiff] to PH on May 24, 2011. . . . In addition, on
    May 13, 2011, there was a meeting at the construction
    site during which a number of proposals, changes, new
    architectural sketches and costs were discussed. . . .
    After PH left the project there was no architect with
    whom [the plaintiff] could discuss the proposed
    changes.’’ (Citations omitted.)
    A
    We turn first to the plaintiff’s claim that VAS breached
    its construction contracts with the plaintiff by failing
    to comply with change order procedures. We agree with
    VAS that the breach of contract claim as set forth in
    the operative complaint did not include or rely upon any
    allegation that VAS had failed to adhere to provisions in
    the construction contract pertaining to change orders.
    Accordingly, this aspect of the plaintiff’s claim fails.
    ‘‘The pleadings determine which facts are relevant
    and frame the issues for summary judgment proceed-
    ings or for trial. . . . The principle that a plaintiff may
    rely only [on] what he has alleged is basic. . . . It is
    fundamental in our law that the right of a plaintiff to
    recover is limited to the allegations [in] his complaint.
    . . . A complaint must fairly put the defendant on
    notice of the claims . . . against him. . . . The pur-
    pose of the complaint is to limit the issues to be decided
    at the trial of a case and is calculated to prevent surprise.
    . . . Only those issues raised by the [plaintiff] in the
    latest complaint can be tried [by the trier of fact].’’
    (Citations omitted; internal quotation marks omitted.)
    White v. Mazda Motor of America, Inc., 
    313 Conn. 610
    ,
    621, 
    99 A.3d 1079
    (2014).
    In its breach of contract count against VAS, the plain-
    tiff’s allegations specifying the manner in which VAS
    allegedly breached its contracts with the plaintiff were
    limited to assertions that VAS had not satisfactorily
    completed aspects of the construction project, had used
    inferior and unspecified materials, or had performed
    defective work that would require repair or replace-
    ment. Although there was testimony at trial discussing
    how change orders were handled, the plaintiff never
    sought to amend his complaint to include additional
    specifications of breach of contract to its count against
    VAS. If the plaintiff had provided notice of this aspect
    of its claim through proper pleading, VAS may have
    produced additional evidence or tailored its presenta-
    tion of evidence differently.
    In considering a breach of contract claim, the trial
    court is limited to the allegations in the complaint and
    has no duty to scrutinize the parties’ agreement looking
    for potential additional breaches. The court’s silence
    in its memorandum of decision with respect to VAS’
    alleged noncompliance with the contract’s change order
    procedures is further evidence that this issue was not
    properly raised to the court.
    In sum, we conclude that the failure to follow change
    order procedures was not raised in the operative com-
    plaint as a basis for the plaintiff’s count alleging breach
    of the construction contract by VAS, nor was the issue
    addressed by the trial court in rejecting that count of
    the complaint. Accordingly, that issue cannot form the
    basis of a claim on appeal that the court improperly
    rejected the plaintiff’s allegation that VAS breached the
    construction contract.
    B
    We next turn to the plaintiff’s claim that PH breached
    its contract with the plaintiff by failing to ensure that
    VAS adhered to change order and billing procedures
    set forth in the construction contract. According to the
    plaintiff, the trial court failed to give effect to those
    contract requirements. We are not persuaded.
    As a preliminary matter, we note that the plaintiff has
    not claimed that the court misconstrued any particular
    language in the contract that would invoke our plenary
    review. The plaintiff also has failed to direct our atten-
    tion to any part of the record that would support his
    assertion that the trial court committed legal error by
    failing to consider or give effect to any particular con-
    tract provision. To the contrary, in discussing the par-
    ties’ disputes over the procedures followed with respect
    to changes to the project and the resulting change in
    the contract price, the trial court specifically cited to
    article seven of the contract, which, as we have indi-
    cated, contains all the relevant provisions governing
    change order procedures.
    We therefore construe the plaintiff’s claim as chal-
    lenging the court’s rejection of his argument that PH’s
    actions in handling change orders and billing proce-
    dures amounted to a material breach of its contract with
    the plaintiff. It is important to reiterate that ‘‘[w]hether
    there was a breach of contract is ordinarily a question
    of fact. . . . We review the court’s findings of fact
    under the clearly erroneous standard.’’ (Internal quota-
    tion marks omitted.) Neubig v. Luanci Construction,
    LLC, 
    124 Conn. App. 425
    , 433, 
    4 A.3d 1273
    (2010). The
    court found no material breach of contract with respect
    to PH while it was still on the project. Specifically,
    the court found that the plaintiff had not produced an
    evidentiary foundation for his claim that PH had not
    consulted with him or sought his approval on change
    orders. To the contrary, the court found that the evi-
    dence presented showed that such consultation in fact
    had occurred. The court also determined that the plain-
    tiff had failed to demonstrate that he was harmed by
    technical problems with paperwork. Further, any fail-
    ure of VAS to follow strict contract procedures after
    PH left the project could not be attributed to PH because
    the court found that the plaintiff ‘‘terminated Hubbard’s
    services and constructively terminated Paulos’ services
    by his conduct,’’ a finding that is not challenged on
    appeal.
    The plaintiff has not demonstrated that the court’s
    factual findings are unsupported by the record nor are
    we left on the basis of our review with a conviction
    that a mistake has been made. We accordingly reject
    his claim that the court failed to give due consideration
    to the terms of the contract in determining that PH had
    not breached its contract with the plaintiff regarding
    its handling of change orders.
    II
    Next, the plaintiff claims that, in concluding that he
    failed to prove that VAS breached the wall contract,
    the court failed to enforce provisions of that contract
    requiring VAS to construct the wall and fence combina-
    tion in a particular location with certain specifications.
    In response, VAS argues that we should uphold the
    court’s conclusion either because the plaintiff failed to
    establish proof of damages, which is a required element
    of a breach of contract cause of action, or because
    the court determined that the parties had modified the
    contract provisions relied on by the plaintiff. We agree
    with VAS that the specifications and location of the
    wall were modified by subsequent agreement of the
    parties, as found by the court, and that the court prop-
    erly ruled in favor of VAS on that aspect of the plaintiff’s
    claim of breach of contract.
    The following additional facts are relevant to this
    claim. VAS began work on the stone wall and fence
    combination in March, 2011. Issues began to arise
    regarding the construction and location of the stone
    wall, which prompted an on-site meeting at the end of
    March between the plaintiff, VAS, and PH. At that time,
    Hubbard spray painted along the ground where he
    believed the center line of the wall should run according
    to the plans. Sciarretta explained to the plaintiff that if
    VAS constructed the wall using Hubbard’s line, it would
    involve the cutting of trees and, more importantly,
    require the removal of ledge rock, each of which would
    result in extra costs being added to the wall contract.
    The plaintiff ‘‘eventually directed that the wall be placed
    nearer the house to avoid ledge . . . and tree removal.’’
    In its memorandum of decision, the court rejected
    the plaintiff’s claim that VAS breached the wall contract
    because the wall was not constructed on or near the
    perimeter of his property along Hunting Ridge Road as
    set forth in the contract and accompanying architec-
    tural drawings. The court found that VAS had con-
    structed the wall as the plaintiff directed. Specifically,
    the court found that ‘‘the repositioning of the wall was
    done at [the plaintiff’s] request when he was confronted
    with the potential extra cost of building the wall at a
    location involving significant ledge rock and tree
    removal.’’ Accordingly, any deviation from the terms of
    the contract was authorized and approved by the
    plaintiff.7
    If parties have modified the terms of a contract, they
    are contractually bound by those modified terms and,
    consequently, cannot be found in breach of the original
    terms. ‘‘Modification of a contract may be inferred from
    the attendant circumstances and conduct of the par-
    ties.’’ Herbert S. Newman & Partners, P.C. v. CFC Con-
    struction Ltd. Partnership, 
    236 Conn. 750
    , 762, 
    674 A.2d 1313
    (1996). ‘‘Whether the parties to a contract
    intended to modify the contract is a question of fact.
    . . . The resolution of conflicting factual claims falls
    within the province of the trial court. . . . The trial
    court’s findings are binding upon this court unless they
    are clearly erroneous in light of the evidence and the
    pleadings in the record as a whole. . . . We cannot
    retry the facts or pass on the credibility of the witness.’’
    (Citations omitted; internal quotation marks omitted.)
    
    Id. Here, rather
    than failing to enforce provisions of the
    wall contract requiring VAS to construct the wall and
    fence in a particular location with certain specifica-
    tions, the court found that the parties had agreed to
    modify the terms of the contract by moving the location
    of the wall to avoid increasing the contract price, which
    was an expressed concern of the plaintiff. On the basis
    of our review of the record, the plaintiff has failed to
    persuade us that the trial court’s finding that he agreed
    to the modification of the contract and directed VAS
    to build the wall where it currently stands is clearly
    erroneous. We accordingly reject his claim.
    III
    The plaintiff next claims that, with respect to the
    architectural contract between him and PH, the court
    failed to enforce provisions that required PH to provide
    contract administration services and to represent his
    best interests with respect to the project. We disagree.
    Pursuant to the architectural contract, after the
    design and planning phase of the project was finished
    and actual construction work had begun, PH agreed to
    continue to provide services to the plaintiff for the
    balance of the project. In addition to other services,
    the contract provided that PH would provide ‘‘contract
    administration,’’ which, as previously indicated, was
    described in the agreement as ‘‘monitoring the construc-
    tion process, reviewing and approving applications for
    payment to the contractor, review of the final work,
    preparation of a punch list to complete the work and
    issuing final acceptance of the work.’’
    Significantly, the contract also stated that ‘‘[t]he
    scope of [PH’s] services during the actual construction
    can be finalized at a future meeting once the scope is
    better understood.’’ The court indicated in its decision
    that this language ‘‘left some uncertainty’’ as to PH’s
    contractual responsibilities during the construction
    phase, particularly because no evidence was presented
    that a meeting to determine the final scope of the work
    ever occurred.
    The plaintiff does not dispute the court’s finding that
    there was no evidence of a meeting to finalize the scope
    of PH’s work during construction. Nevertheless, the
    plaintiff argues that the language regarding contract
    administration is clear and unambiguous, and that the
    court failed to give effect to that language in considering
    whether PH had breached its duties to the plaintiff to
    provide contract administration services.
    As already discussed in part I B of this opinion, how-
    ever, the court determined that there was no evidentiary
    foundation for the plaintiff’s breach of contract claim
    against PH, and that, prior to the plaintiff terminating
    PH from the project, PH effectively had complied with
    its contract administration duties by monitoring the
    progress of the project, engaging in discussions on-site
    regarding the construction of the rock wall, and by
    reviewing and discussing with the plaintiff a proposed
    change order submitted by VAS. Because the plaintiff
    has not demonstrated that the court rejected his claim
    on the basis of clearly erroneous factual findings, we
    reject his claim.
    IV
    We turn next to the plaintiff’s claim that the court
    improperly concluded that he had failed to demonstrate
    that PH had breached the professional standard of care
    applicable to architects. We do not agree.
    In order to prevail on a claim of professional negli-
    gence or malpractice, a plaintiff has the burden to show
    the following: ‘‘(1) a duty to conform to a professional
    standard of care for the plaintiff’s protection; (2) a devi-
    ation from that standard of care; (3) injury; and (4) a
    causal connection between the deviation and the
    claimed injury.’’ Stuart v. Freiberg, 
    316 Conn. 809
    , 833,
    
    116 A.3d 1195
    (2015). Ordinarily, whether a profession-
    al’s conduct met the required standard of care or devi-
    ated from that standard are questions of fact to be
    decided by the trier of fact. See Campbell v. Palmer,
    
    20 Conn. App. 544
    , 548, 
    568 A.2d 1064
    (1990).
    To meet his burden of establishing the standard of
    care applicable to architects and to show a deviation
    from that standard, the plaintiff presented expert testi-
    mony from Jonathan Hodosh, a practicing architect.
    His firm, George Hodosh Associates, concentrates on
    residential additions and alterations. Hodosh visited the
    property in March and April, 2012, and prepared a
    ‘‘punch list’’ of purportedly incomplete or defective
    items. Hodosh’s punch list was admitted into evidence
    at trial. Hodosh testified that, in his opinion, PH
    breached the standard of care in three ways, by failing
    (1) to advise the plaintiff adequately about installing a
    radiant heat system under the flooring, (2) to design a
    code-compliant pool enclosure, and (3) to design a
    code-compliant cover or enclosure for the hot tub.
    We agree with the court’s assessment in its memoran-
    dum of decision that the main thrust of Hodosh’s expert
    testimony regarding the radiant heat system was that
    PH should have brought in a mechanical engineer to
    design the system and to evaluate the interactions
    between it and the existing hot air system. He opined
    that PH should have reconsidered use of the cherry and
    oak flooring included in the initial architectural plans
    in light of the decision to introduce a radiant heat sys-
    tem. He also was critical of the fact that PH had made
    no provisions in its original plans for a protective enclo-
    sure for the hot tub and the swimming pool.
    In response, PH presented its own expert, James
    Lawler, also a licensed architect. Lawler contradicted
    much of Hodosh’s testimony. Lawler testified that PH’s
    construction drawings and specifications were both
    thorough and well prepared for use by a contractor in
    executing the design plan. Lawler’s professional opin-
    ion was that PH had provided the plaintiff with a high
    level of service. Accordingly, the evidence before the
    court regarding PH’s exercise of its professional respon-
    sibilities under the contract was conflicting. As the trier
    of fact, the court had the authority to resolve this con-
    flict as it saw fit, and was not required to credit any
    part of Hodosh’s testimony. See Arroyo v. University
    of Connecticut Health Center, 
    175 Conn. App. 493
    , 518,
    
    167 A.3d 1112
    (‘‘[if] expert testimony conflicts, it
    becomes the function of the trier of fact to determine
    credibility and, in doing so, it could believe all, some
    or none of the testimony of either expert’’ [internal
    quotation marks omitted]), cert. denied, 
    327 Conn. 973
    ,
    
    174 A.3d 192
    (2017).
    In fact, the court ultimately rejected Hodosh’s testi-
    mony, finding it unpersuasive for several reasons. First,
    the court found that at the time the plaintiff made a
    final decision to have radiant heat installed in the home,
    PH was no longer involved with the project. The court
    found that installing radiant heating was proposed in
    a ‘‘VAS change order in May, 2011, [which] contain[ed]
    the first cost data related to radiant heat that was for-
    warded by PH to [the plaintiff] for discussion and pre-
    cipitated the departure of PH from the project. Prior
    to that time, PH did not do any design work or coordi-
    nate with any mechanical engineer relating to radiant
    heat because it was entirely uncertain from PH’s stand-
    point whether [the plaintiff] had a real interest in install-
    ing such a system since he had shown a strong interest
    in cutting costs.’’
    The court further found that Hodosh’s criticism of
    PH regarding a code-compliant pool enclosure and hot
    tub cover were unsupported by the evidence. The court
    found that, at their very first meeting, PH had told the
    plaintiff that the pool would need to have fencing
    around it in order to comply with the pool code in
    Greenwich. The plaintiff indicated to PH, however, that
    he believed fencing around the perimeter of the prop-
    erty would enclose both the pool and the pond and that
    the fencing needed to be in compliance with code. The
    court credited Hubbard’s testimony that PH would
    never have advised the plaintiff that a perimeter fence
    would suffice for purposes of a pool enclosure. The
    court ultimately found on the basis of the evidence
    presented that ‘‘a proper pool enclosure fence was spe-
    cifically not included in the scope of work [the plaintiff]
    set out for PH. . . . In fact, at the end of the project,
    it was VAS that apparently convinced [the plaintiff] a
    proper pool enclosure was needed and had it installed.’’
    With respect to the hot tub cover, the court credited
    the testimony of Lawler and Sciarretta that hot tub
    manufacturers provide code-compliant covers for hot
    tubs, that such a cover was on the tub when it was
    installed, and a code-compliant cover was on the tub
    when Lawler visited the property in April, 2016.
    It is clear in the present case that the court rejected
    the testimony of the plaintiff’s expert and credited the
    testimony of PH’s expert in finding that PH had not
    breached the professional standard of care required of
    architects. Our review of the record shows that there
    is an evidentiary basis for the court’s decision and we
    will not engage in a reweighing of the evidence or revisit
    the court’s credibility determinations. Because the
    plaintiff has failed to demonstrate either a legal or fac-
    tual basis for disturbing the court’s decision rejecting
    his claim of professional negligence by PH, we reject
    his claim.
    V
    Finally, the plaintiff claims that the trial court made
    erroneous factual findings with respect to a ‘‘punch list’’
    that identified certain items of work that VAS allegedly
    had left incomplete or in need of repair. Principally,
    the plaintiff takes issue with the court’s references to
    the monetary figures associated with the items on the
    punch list as ‘‘estimates.’’ The plaintiff argues that ‘‘the
    process of estimating the cost of punch list items is
    well recognized in the case law as a means of putting
    a dollar value to the items on a punch list’’ and that
    the court based its decision ‘‘on a belief that ‘estimating’
    is not an accepted methodology for pricing a punch
    list.’’ We note that the plaintiff’s brief lacks clarity in
    placing this claim into context; however, we construe
    the claim as intended to call into doubt the court’s
    calculation of damages, in particular the amount of the
    retainage that the court permitted the plaintiff to keep
    for incomplete or defective work. Regardless, although
    the plaintiff is correct that the court rejected the costs
    associated with the items on the punch list, a review
    of the relevant portion of the court’s decision reveals
    that it did so, not because it rejected any particular
    methodology for determining damages or the use of
    reasonable estimates, but because it concluded that the
    punch list and the associated pricing were ‘‘rife with
    errors, lack of knowledge and exaggerations.’’ Accord-
    ingly, the very premise of the plaintiff’s claim on appeal
    lacks merit.
    The following additional facts are relevant to the
    plaintiff’s claim. The plaintiff sought to prove the
    amount of his alleged damages against VAS through the
    admission of a punch list that contained various items
    identified by his architect expert, Hodosh, as either
    being incomplete or in need of repair. In addition to
    the punch list, the plaintiff entered as an exhibit at trial
    the deposition transcript of an experienced contractor,
    Todd Lukas. Attached as part of the transcript was
    Lukas’ written report detailing his cost estimates for
    completing the Hodosh punch list items. The total cost
    estimated by Lukas was $563,539. Included in his calcu-
    lations were costs associated with the removal of the
    existing stone wall and its reconstruction at a different
    location, and the removal of the entire interior hard-
    wood floor.
    The court rejected Lukas’ deposition testimony and
    his estimate of costs associated with the Hodosh punch
    list as unpersuasive. The court did so not because
    Lukas’ costs were merely estimates and, thus, somehow
    unreliable, as the plaintiff claims, but because the court
    determined there was no credible evidence or economic
    rationale that supported taking the corrective actions
    upon which those estimates were based. For example,
    because the court already had determined that the
    existing wall was built at a location and in a manner
    approved by the plaintiff, it naturally rejected the esti-
    mated cost of completely removing and rebuilding it.
    Similarly, the court found that the plaintiff had failed
    to prove that problems with portions of the existing
    flooring required the complete removal of all flooring
    in the home, instead crediting the testimony given by
    a flooring expert that the defects complained of by the
    plaintiff could be remedied by sanding and refinishing
    only the affected portions of the floor. The court never
    stated that estimating the cost of punch list items was
    an inherently flawed methodology.8
    As we have already indicated in this opinion, it was
    well within the authority of the court as the trier of fact
    to reject as unpersuasive Lukas’ opinion and instead to
    credit the contrary testimony of other expert witnesses.
    See Ferri v. Pyramid Construction Co., 
    186 Conn. 682
    ,
    690, 
    443 A.2d 478
    (1982) (credibility of expert witnesses
    and weight to accord their testimony within province
    of trier of fact, ‘‘who is privileged to adopt whatever
    testimony he reasonably believes to be credible’’ [inter-
    nal quotation marks omitted]). As previously explained,
    it is outside the role of this court to second-guess the
    credibility determinations of the trier of fact. See, e.g.,
    Computer Reporting Service, LLC v. Lovejoy & Associ-
    ates, LLC, 
    167 Conn. App. 36
    , 48, 
    145 A.3d 266
    (2016).
    Because the plaintiff has failed to demonstrate that
    the court’s decisions were premised upon any clearly
    erroneous factual findings, we reject his claim.
    The judgment is affirmed.
    In this opinion the other judges concurred.
    1
    A ‘‘punch list’’ generally refers to a list of items that a contractor must
    complete or repair before final payment on a project will become due. See
    FCM Group, Inc. v. Miller, 
    300 Conn. 774
    , 783, 
    17 A.3d 40
    (2011).
    2
    We note that the statement of issues in the plaintiff’s brief differs signifi-
    cantly and substantively from how the issues are briefed. To the extent that
    the statement of issues raises additional claims that have not been briefed,
    those claims are deemed abandoned. See Stamatopoulos v. ECS North
    America, LLC, 
    172 Conn. App. 92
    , 96 n.3, 
    159 A.3d 233
    (2017).
    3
    According to the court, the plaintiff ‘‘seemed eager to express himself
    as strongly as possible throughout this project,’’ which included ‘‘some
    particularly aggressive, bellicose and unpleasant e-mails authored by the
    plaintiff.’’ The court set forth the following facts underlying the conflict
    between the plaintiff and PH: ‘‘Serious conflicts in connection with the home
    renovation project arose with change order requests submitted by VAS in
    May, 2011. . . . VAS submitted suggested change orders which included
    proposed pricing for the addition of radiant heating in the house. . . . A
    revised request by VAS included a ‘log starter’ for indoor and outdoor
    fireplaces . . . and one concerning the stone wall. The largest item was the
    addition of radiant heating, about $28,000. PH e-mailed all this information
    to [the plaintiff] with the comment that PH had reviewed it and was prepared
    to discuss the issues with [the plaintiff] at an upcoming meeting. . . . After
    receiving a negative response from [the plaintiff], Paulos replied that PH
    did not approve or recommend the change order request from VAS and
    suggested a ‘private discussion’ with [the plaintiff]. . . . At that point, on
    May 26, 2011, at 11:39 p.m., [the] plaintiff sent a message to Paulos,
    demeaning Paulos’ father-in-law, calling him a ‘scumbag fraud,’ attacking
    VAS’ pricing, and stating, ‘[t]he price is going to be what I want or we settle
    in court and lawsuits will be in millions. Game over. Fight back? Ask Maria
    [Claudio, the plaintiff’s assistant] what will happen. I do not lose EVER.’
    . . .’’
    ‘‘Hubbard and Paulos testified they were both shocked when they read
    [the plaintiff’s] vituperative and obscene middle of the night e-mail. . . .
    Paulos, who read the message the next morning while preparing his children
    for school, was also nervous about his family. . . . Hubbard and Paulos
    decided to contact their insurance company and attorney, and Paulos had
    no further contact with [the plaintiff]; Paulos testified that from that point
    ‘I was not working for [the plaintiff].’ . . . Subsequently, a letter was pre-
    pared by PH terminating its services for [the plaintiff], but it was not sent,
    because on June 2, 2011, [the plaintiff] e-mailed Hubbard that Hubbard’s
    services were terminated, and incongruously adding that ‘[Paulos] was who
    I hired and prefer to have solely involved.’ . . . With Hubbard fired and
    Paulos avoiding all contact with [the plaintiff], a formal letter of PH’s with-
    drawal was sent to [the plaintiff’s] attorney on June 3, [2011].’’
    4
    VAS later amended its counterclaim to add additional counts seeking
    to recover damages under alternative theories of unjust enrichment and
    quantum meruit.
    5
    As the court aptly explained in its memorandum of decision, ‘‘[a] change
    order is a means to increase or decrease the contracted price for construction
    work caused by a change in the scope of work, in materials, the time
    required, or otherwise.’’
    6
    This claim with respect to PH is closely related to the plaintiff’s additional
    claim, addressed in part III of this opinion, that PH breached its agreement
    to provide contract administration services, which the plaintiff argues placed
    a duty on PH to oversee the project and to protect the plaintiff’s fidu-
    ciary interests.
    7
    The court also rejected the plaintiff’s claim that the repositioning of the
    wall resulted in $305,000 in damages, which his expert had estimated to be
    the cost of removing and replacing the stone wall and fence. The court
    indicated: ‘‘There is no evidence or economic rationale to support incurring
    the costs of removing and rebuilding the stone wall, even if the court had
    not found its location to be the result of [the plaintiff’s] decisions.’’ (Empha-
    sis added.)
    8
    The court did indicate that it believed the plaintiff had utilized ‘‘a make-
    shift method of proving damages’’; (emphasis added); however, we do not
    agree with the plaintiff that this was intended to suggest that it generally
    was impermissible to use estimates to assign value to punch list items.
    

Document Info

Docket Number: AC40164

Citation Numbers: 193 A.3d 1230, 183 Conn. App. 777

Filed Date: 7/31/2018

Precedential Status: Precedential

Modified Date: 1/12/2023