Semac Electric Co. v. Skanska USA Building, Inc. ( 2020 )


Menu:
  • ***********************************************
    The “officially released” date that appears near the be-
    ginning of each opinion is the date the opinion will be pub-
    lished in the Connecticut Law Journal or the date it was
    released as a slip opinion. The operative date for the be-
    ginning of all time periods for filing postopinion motions
    and petitions for certification is the “officially released”
    date appearing in the opinion.
    All opinions are subject to modification and technical
    correction prior to official publication in the Connecticut
    Reports and Connecticut Appellate Reports. In the event of
    discrepancies between the advance release version of an
    opinion and the latest version appearing in the Connecticut
    Law Journal and subsequently in the Connecticut Reports
    or Connecticut Appellate Reports, the latest version is to
    be considered authoritative.
    The syllabus and procedural history accompanying the
    opinion as it appears in the Connecticut Law Journal and
    bound volumes of official reports are copyrighted by the
    Secretary of the State, State of Connecticut, and may not
    be reproduced and distributed without the express written
    permission of the Commission on Official Legal Publica-
    tions, Judicial Branch, State of Connecticut.
    ***********************************************
    SEMAC ELECTRIC COMPANY, INC. v. SKANSKA
    USA BUILDING, INC.
    (AC 41054)
    Alvord, Devlin and Norcott, Js.
    Syllabus
    The plaintiff subcontractor, E Co., sought to recover damages from the
    defendant, S Co., for, inter alia, breach of contract in connection with
    a dispute arising from a project relating to the expansion and renovation
    of a hospital. Pursuant to its contract with S Co., E Co. agreed to perform
    all electrical work for the project. The contract provided that E Co. had
    a duty to coordinate with S Co., that E Co. had made allowances for
    all hindrances and delays to its work, and that E Co. would work within
    S Co.’s schedule, which S Co. may revise from time to time. S Co. had
    the right to direct a change in E Co.’s work on written notice and, during
    the course of the project, thirty-eight change orders were issued. After
    several months, E Co. sent S Co. a notice, alleging a cardinal change
    to the contract due to issues that arose during the preceding months
    and asserting that it could only continue to perform under the contract
    if S Co. agreed to additional financial terms. S Co. responded that E
    Co.’s refusal to proceed under the contract constituted default and, the
    next day, S Co. terminated E Co. E Co. alleged that S Co. had breached
    the contract by its wrongful termination of E Co., and S Co. filed a
    counterclaim, alleging, inter alia, breach of contract. S Co. also filed a
    third-party complaint against K and T, the chief financial officer and
    president of E Co., respectively, alleging, inter alia, fraudulent conduct.
    The case was tried to the court, which rendered judgment in part for
    S Co. on its counterclaim, and in favor of K and T on the third-party
    complaint. On S Co.’s appeal and E Co.’s cross appeal to this court, held:
    1. The trial court properly rejected E Co.’s claim that there had been a
    cardinal change in the contract terms and properly concluded that E
    Co. breached the contract by abandoning the project: the court properly
    focused on the nature and impact of the delays on the work expected
    of and performed by E Co., which were not extraordinary in a project
    of this magnitude, and neither the character nor the nature of the work
    expected of or performed by E Co. was altered in any way, and E Co.
    was compensated for the changes in its work up until the time that it
    issued its notice of cardinal change to S Co., E Co. was required to
    anticipate unforeseen modifications to E Co.’s sequence of construction
    and the schedule parameters of the contract when it signed the contract,
    as the contract language demonstrated that the parties contemplated
    the possibility of scheduling delays and changes; moreover, there was
    no evidence that the change orders altered the nature of E Co.’s work,
    and, in executing each change order, E Co. attested that it was compen-
    sated for associated costs and delays, and it was clear that the changes
    were not so profound that they were not redressable under the contract,
    as they were, in fact, redressed via the change orders.
    2. The trial court properly concluded that S Co. materially breached its
    contract with E Co. by failing to provide E Co. with a forty-eight hour
    cure period before terminating its contract with E Co.: even though S
    Co. claimed that the court erred in assuming that it had terminated E
    Co. pursuant to the contract provision requiring it to give E Co. forty-
    eight hours to cure its breach, because S Co. pleaded in its counterclaim
    that it had declared E Co. in default pursuant to the contract, the court
    properly held the parties to their contractual obligations; moreover, S
    Co.’s reliance on certain common-law principles overlooked the clear
    contractual language requiring a cure period, which did not include any
    exceptions, and which outlined the procedure if E Co. abandoned the
    project or defaulted on its obligations and the court correctly determined
    that S Co. should be held to the contract provisions because to hold
    otherwise would excuse S Co.’s noncompliance with the contract and
    would create a new and different agreement, which courts cannot do;
    furthermore, the court’s enforcement of the cure period did not render
    meaningless another provision of the contract stating that S Co.’s con-
    tractual remedies were not exclusive, because S Co. could not turn to
    the common law to avoid an express contractual obligation.
    3. The trial court’s award of damages was not erroneous: this court disagreed
    with S Co.’s claim that, due to E Co.’s material breach, S Co. was excused
    from further performance of its contractual obligations and was entitled
    to expectation damages, because S Co. also breached the contract by
    failing to afford E Co. a forty-eight hour cure period, transforming its
    termination for cause of E Co. into a termination for convenience and,
    accordingly, S Co. could not claim entitlement to a common-law remedy
    after forfeiting its right to a contractual remedy as a result of its own
    breach; moreover, E Co. could not prevail on its claim that the court
    erred in not awarding a termination payment pursuant to the contract,
    because, although the court concluded that E Co. was entitled to a
    termination payment, the court found that E Co.’s billing practices were
    too irregular to award damages on the basis of its invoices, which
    the contract had provided for, and, instead, calculated the payment by
    determining the percentage of the project E Co. had completed and
    multiplying that percentage by the contract price; although potentially
    imprecise, it could not reasonably be argued that this method ran afoul
    of the contract or was unfair to E Co.
    4. The trial court did not err in finding that K and T did not commit fraud
    when they swore under oath to the accuracy of invoices submitted to
    S Co. for goods and services they represented to S Co. that they had
    paid to other subcontractors, but actually never did pay; K’s and T’s
    conduct strained the bounds of fraud, revealing, at best, gross incompe-
    tence, but the court nevertheless found that, on the basis of its observa-
    tion of K’s and T’s demeanor and attitude, neither K nor T acted with
    fraudulent intent, and this court does not second-guess the court’s credi-
    bility assessments.
    Argued October 16, 2019—officially released February 11, 2020
    Procedural History
    Action to recover damages for, inter alia, breach of
    contract, and for other relief, brought to the Superior
    Court in the judicial district of Hartford, Complex Litiga-
    tion Docket, where the defendant filed a counterclaim;
    thereafter, the court, Young, J., granted the defendant’s
    motion to implead Kevin Pope et al. as third-party defen-
    dants, and the defendant filed a third-party complaint
    against the third-party defendants; subsequently, the
    court, Moukawsher, J., dismissed the defendant’s
    claims of defamation and tortious interference, and the
    matter was tried to the court, Moukawsher, J.; judgment
    in part for the defendant on the counterclaim and judg-
    ment for the third-party defendants on the third-party
    complaint; thereafter, the court granted the defendant’s
    motion for prejudgment interest, and the defendant
    appealed and the plaintiff cross appealed to this
    court. Affirmed.
    Bruce Meller, pro hac vice, with whom were Michael
    J. Donnelly, Kevin W. Munn and, on the brief, Eric B.
    Miller, for the appellant-cross appellee (named
    defendant).
    Louis R. Pepe, with whom was Laura W. Ray, for
    the appellee-cross appellant (plaintiff).
    Richard P. Weinstein, with whom, on the brief, was
    Sarah Black Lingenheld, for the appellees (defendant
    Kevin Pope et al.).
    Opinion
    DEVLIN, J. In this action arising from the expansion
    and renovation of Stamford Hospital (hospital), both
    parties, the plaintiff, Semac Electric Company, Inc.
    (Semac), and the defendant, Skanska USA Building, Inc.
    (Skanska), appeal from the judgment of the trial court,
    challenging the court’s determinations that they both
    breached the contract between them, and awarding
    Skanska damages in the amount of $3,857,130.77,1 as
    reimbursement for funds that Skanska had overpaid to
    Semac for work that Semac had not performed. Skanska
    also claims that the trial court erred in finding that
    the individual third-party defendants, Kevin Pope and
    Thomas Scanlon, the chief financial officer of Semac
    and the president of Semac, respectively, did not engage
    in fraudulent conduct when they signed, under oath,
    invoices misrepresenting that Semac had paid other
    subcontractors for certain goods and services. We
    affirm the judgment of the trial court.
    The trial court set forth the following relevant facts.
    As the general contractor retained by the hospital to
    serve as the construction manager for the construction
    of a new building on its existing campus (project), Skan-
    ska entered into a subcontract with Semac, dated March
    5, 2014, pursuant to which Semac agreed to perform
    all necessary electrical work on the project for the sum
    of $14,785,462. On October 19, 2015, after working for
    several months on the project, Scanlon delivered to
    Skanska a ‘‘Notice of Cardinal Change and Material
    Breach of Subcontract’’ (Notice of Cardinal Change),
    wherein Semac stated: ‘‘[T]here has been a cardinal
    change to our subcontract due to the drastic and unfore-
    seen modifications and changes that have been made
    to Semac’s sequence of construction and the schedule
    parameters set forth in the subcontract, which has
    unreasonably altered the character of the work and
    unduly increased its cost.’’ In the multipage letter,
    Semac identified several specific issues that arose dur-
    ing the preceding months of construction, and asserted:
    ‘‘As a result of the cumulative effect and the severe
    magnitude and quality of the scheduling and sequencing
    delays and disruptions and other assumptions contem-
    plated by the subcontract, the entire nature of the elec-
    trical work for this [p]roject is something totally differ-
    ent than anyone reasonably anticipated or
    contemplated at the time of entering into a subcon-
    tract.’’ Semac asserted that it could continue to perform
    under the subcontract only if Skanska agreed to an
    increase in the contract price, and to certain additional
    financial terms. Semac concluded: ‘‘We trust that . . .
    Skanska will work with us to reach this equitable solu-
    tion. Otherwise, Semac will be excused from further
    performance and cease work as of October 23, 2015,
    in which case we would seek compensation for all work
    performed through that date.’’
    In response, on October 21, 2015, Skanska advised
    Semac that its refusal to proceed under the terms of
    the subcontract constituted a default under that con-
    tract, and that, if Semac failed to cure the default, Skan-
    ska would pursue its contractual rights.
    The next day, on October 22, 2015, Skanska termi-
    nated Semac, and notified Semac that it was taking
    possession of Semac’s ‘‘materials, tools, appliances,
    equipment and other items.’’ (Internal quotation marks
    omitted.) In turn, Semac accused Skanska of material
    breach of the subcontract on the ground of wrongful ter-
    mination.
    On October 23, 2015, Semac commenced this action.
    In its second amended complaint, Semac alleged that
    Skanska had materially breached the contract by virtue
    of the cardinal changes of which it had given Skanska
    notice on October 19, 2015, failing to make monthly
    progress payments for work completed by Semac, fail-
    ing to compensate Semac for additional work that was
    performed by Semac and was not required by the origi-
    nal contract, and failing to pay the overtime premium
    required by Semac to complete that work. Semac
    claimed that Skanska had wrongfully terminated it and
    confiscated its tools and equipment. In addition to the
    breach of contract and wrongful termination counts,
    Semac alleged causes of action sounding in quantum
    meruit, breach of the implied covenant of good faith
    and fair dealing, violation of the Connecticut Unfair
    Trade Practices Act, General Statutes § 42-110a et. seq.,
    conversion, and civil theft. Semac sought monetary
    damages, including statutory interest and attorney’s
    fees pursuant to General Statutes § 42-158j, and declara-
    tory relief.
    Skanska essentially denied all of Semac’s allegations,
    and asserted multiple special defenses, asserting that
    Semac waived many of its claims by, inter alia, failing
    to submit claims for overtime premiums and accepting
    payment for the work completed and failing to comply
    with the dispute resolution provisions of the contract.
    Skanska also filed a counterclaim alleging that Semac
    breached the contract by failing to perform and com-
    plete the work and effectively abandoning performance,
    and committed fraud and civil theft by submitting billing
    to Skanska for work that it had not performed and goods
    that it had not procured.2 Finally, Skanska claimed a
    ‘‘setoff,’’ alleging: ‘‘To the extent that Semac is entitled
    to damages from Skanska, Skanska is entitled to set
    off for the amount of loss or damages sustained as a
    result of Semac’s actions.’’
    Semac denied all of Skanska’s special defenses and
    the essential allegations of Skanska’s counterclaim.
    Semac asserted multiple special defenses to Skanska’s
    counterclaim, the most pertinent of which was its alle-
    gation that Skanska’s claims were barred by its own
    material breach of the contract. Like Skanska, Semac
    alleged: ‘‘To the extent that Skanska is entitled to dam-
    ages from Semac, Semac is entitled to a setoff for the
    amount of loss or damage sustained as a result of Skan-
    ska’s actions, as alleged in Semac’s [second]
    amended complaint.’’
    Skanska denied all of Semac’s special defenses. Skan-
    ska also filed a third-party complaint against Pope and
    Scanlon, alleging fraudulent misrepresentation regard-
    ing Semac’s billing for services and goods that it never
    performed or purchased. Pope and Scanlon denied the
    allegations of the third-party complaint and asserted
    seven special defenses to the claims against them. Skan-
    ska denied all of Pope and Scanlon’s special defenses
    to its third-party complaint.
    The parties tried this case to the court over a period
    of several days. Semac sought damages for Skanska’s
    wrongful termination, in the amount of the unpaid por-
    tion of the contract price. Skanska sought damages
    from Semac for the $28,754,711.81 that Skanska had to
    pay for other subcontractors and suppliers to complete
    the electrical work that Semac failed to complete under
    the contract3 and for the reimbursement of funds that
    Semac had overbilled Skanska and which Skanska
    had paid.
    On August 23, 2017, the court issued a memoran-
    dum of decision wherein it concluded that both Semac
    and Skanska breached the contract. The court rejected
    Semac’s claim of cardinal change and concluded that
    Semac breached the contract when it refused to con-
    tinue to perform its contractual obligations. The court
    further found, however, that Skanska breached the con-
    tract by terminating Semac without affording it forty-
    eight hours to cure its breach in accordance with the
    contract. The court concluded that, because Skanska
    failed to afford Semac the contractual forty-eight hours
    to cure its breach, it was required to pay Semac for the
    work it had performed, and it was not entitled to recover
    damages to complete the project. The court determined
    that Semac had completed 65 percent of the work that it
    had contracted to complete, and multiplied the revised
    contract price of $19,114,535, which was determined
    by multiple change orders agreed to and executed by
    the parties, by that percentage to determine the amount
    to which Semac was entitled for the work it had per-
    formed, $12,424,447. Because, however, Semac had
    already billed Skanska $14,785,764.36 for the work it
    had performed, and Skanska had paid that amount,
    the court concluded that Skanska was entitled to be
    reimbursed $2,361,317.36. The court further found that
    Skanska paid Semac for materials and labor allegedly
    provided by two separate additional subcontractors,
    but were never actually paid for by Semac. The court
    concluded that Skanska was entitled to reimbursement
    for those amounts—$769,790.93 and $252,273.51,
    respectively. Finally, the court determined that Semac
    had improperly marked up its labor cost and ordered
    that it reimburse Skanska in the amount of $473,748.97
    for this misrepresentation. The court thus awarded
    Skanska a total of $3,857,130.77. The court found that
    Skanska failed to prove that Pope and Scanlon engaged
    in fraudulent conduct, and rejected the parties’
    remaining claims.
    Semac thereafter filed a motion for reconsideration
    and correction of the court’s award of damages on the
    grounds that the court allegedly omitted an undisputed
    credit due to Semac for certain work it had performed
    on the project and that certain portions of the court’s
    damages award that compensated Skanska for overpay-
    ments resulted in double recovery. The court granted
    reargument, but rejected Semac’s arguments and
    affirmed its earlier decision.
    By way of an additional memorandum of decision
    dated November 6, 2017, the trial court granted, over
    Semac’s objection, Skanska’s motion for prejudgment
    interest, increasing the total amount of damages to
    $4,262,390.56. This appeal, filed by Skanska, and, cross
    appeal, filed by Semac, followed.
    The following general principles are pertinent to the
    parties’ claims on appeal. ‘‘It is axiomatic that [t]he
    scope of our appellate review depends upon the proper
    characterization of the rulings made by the trial court.
    To the extent that the trial court has made findings of
    fact, our review is limited to deciding whether such
    findings were clearly erroneous. [If], however, the trial
    court draws conclusions of law, our review is plenary
    and we must decide whether its conclusions are legally
    and logically correct and find support in the facts that
    appear in the record. . . .
    ‘‘In a case tried before a court, the trial judge is the
    sole arbiter of the credibility of the witnesses and the
    weight to be given specific testimony. . . . It is within
    the province of the trial court, as the fact finder, to
    weigh the evidence presented and determine the credi-
    bility and effect to be given the evidence. . . .
    ‘‘[I]n private disputes, a court must enforce the con-
    tract as drafted by the parties and may not relieve a
    contracting party from anticipated or actual difficulties
    undertaken pursuant to the contract, unless the con-
    tract is voidable on grounds such as mistake, fraud or
    unconscionability. . . . [C]ourts do not unmake bar-
    gains unwisely made. . . . Although parties might pre-
    fer to have the court decide the plain effect of their
    contract contrary to the agreement, it is not within its
    power to make a new and different agreement; con-
    tracts voluntarily and fairly made should be held valid
    and enforced in the courts. . . . In construing an unam-
    biguous contract, the controlling factor is the intent
    expressed in the contract, not the intent which the
    parties may have had or which the court believes they
    ought to have had. . . . [If] . . . there is clear and
    definitive contract language, the scope and meaning of
    that language is not a question of fact but a question
    of law. . . .
    ‘‘The required elements necessary to sustain an action
    for breach of contract are the formation of an agree-
    ment, performance by one party, breach of the agree-
    ment by the other party and damages. . . . The exis-
    tence of a contract is a question of fact to be determined
    by the trier on the basis of all of the evidence.’’ (Citations
    omitted; internal quotation marks omitted.) Coppola
    Construction Co. v. Hoffman Enterprises Ltd. Partner-
    ship, 
    157 Conn. App. 139
    , 158–60, 
    117 A.3d 876
    , cert.
    denied, 
    318 Conn. 902
    , 
    122 A.3d 631
    (2015), and cert.
    denied, 
    318 Conn. 902
    , 
    123 A.3d 882
    (2015).
    ‘‘We often have stated that whether a contract has
    been breached is a question of fact . . . and that this
    court lacks the authority to make findings of facts or
    draw conclusions from primary facts found. . . . Fac-
    tual conclusions may be drawn on appeal, however, if
    the subordinate facts found [by the trial court] make
    such a conclusion inevitable as a matter of law . . .
    or [if] the undisputed facts [as they appear] in the record
    make the factual conclusion so obvious as to be inher-
    ent in the trial court’s decision.’’ (Citations omitted;
    internal quotation marks omitted.) 
    Id., 171–72. With
    these principles in mind, we turn to the parties’ claims
    on appeal.
    I
    We begin with Semac’s assertion that the trial court
    erred in rejecting its claim of cardinal change. Although
    this claim is raised by way of Semac’s cross appeal,
    and is thus not chronologically first in the procedural
    posture of this appeal, it is the first of a chain of events
    that gave rise to this litigation. We agree with the trial
    court that there was not a cardinal change in the terms
    of the contract and, therefore, that Semac breached the
    contract by abandoning the project.
    In addressing Semac’s claim of cardinal change, the
    trial court set forth the following relevant facts. The
    court first addressed the issue of ‘‘whether radical
    changes were made to the character and timing of the
    work.’’ The court found: ‘‘The job was building a twelve
    floor hospital loaded with specialty wiring needs and
    equipment. Three unanticipated events threw off the
    detailed schedule adopted at the beginning of the job.
    First, the steel frame of the building took longer than
    expected. Second, the building’s glass siding—its cur-
    tain wall—took far longer than expected, leaving large
    parts of the building open to the weather. Third, Skan-
    ska had to scrap its planned approach to coordinating
    trades—the BIM (building information management)
    coordination—and start over, imposing that duty on the
    trades themselves.’’ (Internal quotation marks omitted.)
    The court determined that ‘‘[t]he cumulative effect of
    these delays meant that by the summer of 2015, Skanska
    had lost months to these delays and was fighting to
    recover its schedule.’’
    Through its project manager, Mark Miller, Skanska
    aggressively sought to make up for the time lost as a
    result of the aforementioned delays to complete the
    project by April, 2016, so that the hospital could open
    in September, 2016. The court noted: ‘‘Miller pushed
    his subcontractors pretty hard. From Semac he
    demanded—and paid for—overtime work and pressed
    the company to reach quickly, and then exceed, the
    peak of its promised manpower—without any addi-
    tional money. Miller’s plans also required Semac to
    increase its flexibility in working around other trades
    and working between various sections of the building.
    Doubtless all this put a strain on Semac. It was a big
    job; it was behind schedule, and everyone was required
    to hustle to make the whole thing work.’’
    The court considered the expert testimony offered
    by the parties and found that Skanska’s witnesses were
    more convincing in their testimony that ‘‘in large proj-
    ects, changes and strains are routine’’ over the testi-
    mony of Semac’s expert, who ‘‘dismissed even the
    court’s suggestion that some delays on big projects are
    routine.’’ The court reasoned: ‘‘This was no routine proj-
    ect. . . . And as for time delays—assuming they mat-
    ter—as much as Skanska can’t pretend the job was
    routine, Semac can’t ignore that the job was completed
    close to on time, in addition to never changing its basic
    character. There was no year of delay; no surprise sec-
    ond tower to erect. Indeed, Skanska credibly claims
    that—for matters under its control—it would have met
    the preopening substantial completion date described
    in the schedule but for Semac bailing out at a critical
    moment. It also rightly emphasizes that, out of sixty-
    seven subcontractors, nobody bailed out but Semac.’’
    The court found that Semac had made a profit every
    month of the job, right up until October, 2015, when it
    issued the Notice of Cardinal Change. The court found:
    ‘‘In fact, Skanska demanded—and got sworn declara-
    tions with every change order saying that Semac had
    been fully paid for any ‘delays, acceleration, or loss of
    efficiency encountered by [Semac] in the performance
    of the [w]ork through the date of this [c]hange order
    . . . .’ ’’
    The court noted the ‘‘many irregularities’’ in Semac’s
    billing to Skanska, and found that ‘‘[s]ome of Semac’s
    bid calculations are indecipherable and even misleading
    to a degree. Its internal paper seems to equivocate about
    profit. It shows a profit in one place and then takes it
    away in another. Semac got paid by Skanska for some
    goods and services without telling Skanska that it was
    pocketing the money and not paying for the labor and
    materials because of a claimed dispute. It hid payments
    to its owner in its billing records by sending them to a
    shell company for nonexistent materials for the job.
    It changed managers on the job three times, suffered
    significant employee turnover rates, and employed far
    more than an ordinary number of cheaper and less
    productive apprentices on the job. It told Skanska that it
    was billing Skanska its actual costs for labor on contract
    change jobs when it was instead pocketing a profit on
    every hour worked. It swore in payment documents
    that it had been paid for delays on the job and then
    pulled the rug out from under Skanska by claiming the
    opposite. It never adequately tied its alleged losses from
    delays to particular parts of the job. And the written
    records of communications before the [issuance to
    Skanska of the Notice of Cardinal Change] do not nearly
    reflect the kind of urgency that would suggest that
    things happening on the site were at a critical juncture
    requiring Skanska’s urgent financial intervention.
    Instead, one day in October, 2015, there was a blunt
    letter from Semac to Skanska demanding money and—
    within several days—there was this lawsuit.’’
    The court concluded: ‘‘This case doesn’t meet con-
    temporary views in commercial cases of what is a radi-
    cal or cardinal change. . . . In October, 2015, [Semac]
    wrote to Skanska saying that it would leave if it did
    [not] get the extra money that it asked for. When Skan-
    ska refused to pay or even parley, Semac affirmed in
    telephone calls that it would pick up its tools and go
    home. The day after Semac affirmed this, Skanska found
    that Semac had dismissed its own subcontracted labor
    for the day and was busying its own men with removing
    their equipment and tools from the site. Semac insists
    that some men were somewhere still working on the
    actual job, but the evidence supporting this claim is
    vague and the evidence against it is better. Skanska
    officials searched the site and found nobody from
    Semac working anywhere. Semac never said who was
    doing what, [or] where, that supposedly meant they
    were still on the job. It has not proved it was carrying
    on with the work while merely trying to negotiate.
    ‘‘Semac temporarily or permanently abandoned
    working, and under Section 12.1 of the contract aban-
    doning the work—even temporarily—is a material
    breach of the contract. Thus, Semac materially
    breached its contract with Skanska.’’
    On appeal, Semac claims4 that ‘‘[s]ignificant delays
    in the coordination work, the steel construction and
    installation of the curtain wall—all Skanska’s responsi-
    bilities—contributed to the cardinal change.’’ We are
    unpersuaded.
    Although our case law has not addressed an issue of
    cardinal change per se, it has addressed an analogous
    situation in which the final plans for a certain project
    differed so substantially from the original plans for
    which the parties had contracted that the initial contract
    was rendered a nullity. Randolph Construction Co. v.
    Kings East Corp., 
    165 Conn. 269
    , 
    334 A.2d 464
    (1973).
    In Randolph Construction Co., our Supreme Court held:
    ‘‘In dealing with contract provisions allowing alter-
    ations or modifications, an appropriate standard for
    substantiality is whether such changes unreasonably
    alter the character of the work or unduly increase its
    cost, or effect such a material change as to constitute
    a radical departure from the original contract.’’ 
    Id., 274. ‘‘The
    issue of substantiality, a determination of whether
    the enumerated differences in the final plans were sub-
    stantial, is a question of fact which depends on a consid-
    eration of the circumstances. . . . The factual issue
    includes . . . the total undertaking covered by the
    writing, the amount of work affected by the alterations
    and the net change in the cost of performance.’’ (Cita-
    tions omitted.) 
    Id. Consistent with
    the court’s ruling in Randolph Con-
    struction Co., other jurisdictions have explained that
    ‘‘[a] cardinal change is a drastic modification beyond
    the scope of the contract that altered the nature of
    the thing to be constructed.’’ (Internal quotation marks
    omitted.) Pellerin Construction, Inc. v. Witco Corp.,
    
    169 F. Supp. 2d 568
    , 587 (E.D.La. 2001). ‘‘By definition, a
    cardinal change is so profound that it is not redressable
    under the contract.’’ (Internal quotation marks omit-
    ted.) 
    Id. A cardinal
    change thus constitutes a breach
    of contract. 
    Id. The standard
    courts look to in deciding whether a
    cardinal change is present is ‘‘whether the modified job
    was essentially the same work as the parties bargained
    for when the contract was awarded.’’ (Internal quota-
    tion marks omitted.) Air-A-Plane Corp. v. United
    States, 
    408 F.2d 1030
    , 1033 (Ct. Cl. 1969). ‘‘[T]here is a
    cardinal change if the ordered deviations altered the
    nature of the thing to be constructed.’’ (Internal quota-
    tion marks omitted.) 
    Id. ‘‘[T]he problem
    is a matter of
    degree varying from one contract to another and can
    be resolved only by considering the totality of the
    change and this requires recourse to its magnitude as
    well as its quality.’’ (Internal quotation marks omitted.)
    
    Id. ‘‘There is
    no exact formula . . . . Each case must
    be analyzed on its own facts and in light of its own
    circumstances, giving just consideration to the magni-
    tude and quality of the changes ordered and their cumu-
    lative effect upon the project as a whole.’’ (Internal
    quotation marks omitted.) 
    Id. Here, Skanska
    and Semac entered into a 241 page
    contract, pursuant to which Semac agreed to perform
    all of the electrical work for the project. Section 2.4 of
    exhibit E to the contract addressed the duty of Semac
    to coordinate its work with Skanska, the hospital and
    other subcontractors, and provided that Semac ‘‘shall
    not be entitled to an adjustment of the [s]ubcontract
    [a]mount or an extension of time for its field coordina-
    tion activities as [Semac] shall anticipate and provide
    for such activities in the [s]ubcontract [a]mount and
    agreed time for performance.’’ Section 3.1 provided that
    Semac represented that it had ‘‘taken into consideration
    and made allowances for all hindrances and delays inci-
    dent to its [w]ork as provided in Sections 2.2 and 2.4’’
    Section 3.2 provided that Semac would perform its work
    in accordance with the schedule set by Skanska ‘‘as it
    may be revised and amended from time to time by
    [Skanska], including in Section 9.2.’’ Section 9.2 pro-
    vided that Skanska ‘‘shall be entitled to decide the time,
    order and priority for performance of the various por-
    tions of [Semac’s] [w]ork’’ and that Semac would ‘‘not
    be entitled to an adjustment of the [s]ubcontract
    [a]mount or an extension of time in connection with
    any such direction by [Skanska] as [Semac] shall antici-
    pate and provide for such activities in the [s]ubcontract
    [a]mount and agreed time for performance.’’ Section
    9.3 provided that Skanska could require Semac to
    ‘‘increase its labor force, number of shifts and/or over-
    time operations, days of work, or to provide additional
    equipment or materials.’’
    Additionally, article 10 of exhibit E specifically
    addressed, ‘‘Changes and Impacts.’’ Section 10.1 pro-
    vided that Skanska had the right, in its discretion, to
    direct a change upon written notice to Semac. The con-
    tract set forth a detailed procedure for the implementa-
    tion of change orders. Section 10.3 provided Skanska
    with the sole discretion to determine whether different
    pricing was required as a result of a change order, and,
    if so, Skanska had the sole discretion to determine
    the amount of additional compensation. Sections 10.3
    through 10.9 specifically set forth the procedure that
    Semac was required to follow to claim additional com-
    pensation for the change orders, and provided that a
    failure to follow those procedures would result in a
    waiver of any such claim. Section 11.3 provided that,
    in agreeing to the contract amount, Semac had assessed
    its ability to recover additional compensation in connec-
    tion with a work delay or interference.
    Despite the comprehensive and unequivocal contract
    language cited in the preceding paragraphs, Semac
    claimed that there had been a cardinal change ‘‘to the
    planned method and sequence of construction for the
    electrical work’’ that it had contracted to perform.
    Semac claimed that there had been a cardinal change
    ‘‘due to the drastic and unforeseen modifications and
    changes that have been made to Semac’s sequence of
    construction and the schedule parameters set forth in
    the subcontract, which has unreasonably altered the
    character of the work and unduly increased its cost.’’
    Specifically, Semac stated that due to the failure to
    provide a weathertight building on schedule, the
    sequence of its work was different than originally con-
    templated, and Semac was required to work faster and
    under conditions that were not covered in the contract,
    thus resulting in increased costs that were not antici-
    pated by Semac.
    Semac’s claim fails because, as aptly found by the
    trial court, Semac was required to anticipate issues of
    this nature when it submitted its bid for and signed the
    contract. The explicit language of the contract demon-
    strated clearly that the parties contemplated the possi-
    bility, and even the likelihood, of delays and changes
    in the originally planned schedule, and required Semac
    to anticipate those possibilities. Although the project
    experienced multiple delays, some of which were signif-
    icant and some that resulted in the resequencing of
    Semac’s work and a change of the time of the year
    during which its workers were required to work, Semac
    was still performing the same work that it had con-
    tracted to perform. Although Skanska and Semac exe-
    cuted thirty-eight change orders, there was no evidence
    presented that the change orders altered the character
    or nature of the work that Semac had originally con-
    tracted to perform. In executing each change order,
    Semac attested that it had been fully compensated ‘‘for
    all costs, claims, markups, and expenses, direct or indi-
    rect, attributable to this or any other prior [c]hange
    [o]rders’’ and ‘‘for any delays, acceleration, or loss of
    efficiency encountered by [Semac] in the performance
    of the [w]ork through the date of this [c]hange [o]rder,
    and the performance of this and any prior [c]hange
    [o]rders by or before the date of [s]ubstantial [c]omple-
    tion.’’ It is clear that the changes in the project were
    not so profound that they were not redressable under
    the contract, as they were, in fact, redressed via the
    change orders executed by the parties. The final change
    order, to which Semac agreed and for which it was
    compensated, was dated October 12, 2015, less than
    two weeks prior to Semac’s issuance to Skanska of the
    Notice of Cardinal Change.
    Moreover, despite representing to Skanska that it was
    billing for actual costs of labor, Semac was actually
    inflating its bills to make a profit ‘‘on every hour
    worked.’’5 This fact alone belies Semac’s claim that the
    changes to the project so materially affected its costs
    that it had no choice but to abandon it and supports
    the trial court’s determination that the situation leading
    up to the claim of cardinal change could not have been
    so urgent as to justify Semac’s demand for further funds.
    Although the trial court employed colorful hyperbole
    to demonstrate that the character of the final product,
    the hospital, had not changed, Semac is correct in its
    assertion that the end result does not dictate the exis-
    tence of a cardinal change. That was not, however, the
    focal point of the trial court’s reasoning. The trial court
    focused, and properly so, on the nature and impact of
    the delays on the work expected of and performed by
    Semac. Those delays were not extraordinary in a project
    of this magnitude and complexity. Neither the character
    nor the nature of the work expected of or performed
    by Semac was ever altered in any way, never mind in
    a way that could be construed as substantial or radical.
    Moreover, the delays were contemplated in the contract
    between Semac and Skanska, and Semac was compen-
    sated for them right up until it issued its Notice of
    Cardinal Change to Skanska. On the basis of the forego-
    ing, we agree with the trial court’s determination that
    Semac failed to prove that there was a cardinal change
    in the terms of its contract with Skanska and with its
    conclusion that Semac materially breached the
    contract.
    II
    We next address Skanska’s challenge to the trial
    court’s conclusion that it also materially breached its
    contract with Semac by failing to provide Semac with
    a full forty-eight hour cure period before terminating
    its contract. Skanska does not dispute that it waited
    only twenty-four hours from the time that it rejected
    Semac’s Notice of Cardinal Change to terminate Semac.
    Skanska argues, however, that, for various reasons,
    Semac was not entitled to a forty-eight hour cure period.
    We disagree.
    ‘‘Although it is generally accepted that contracting
    parties may reserve the right to terminate a contract
    for convenience or cause upon a specified period of
    notice . . . [i]f a party who has a power of termination
    by notice fails to give the notice in the form and at the
    time required by the agreement, it is ineffective as a
    termination. . . . One who deviates from the terms and
    the circumstances specified in the agreement for giving
    notice . . . may be regarded as having repudiated the
    contract, with all the effects of repudiation including
    giving the injured party a right to damages . . . .’’ (Cita-
    tions omitted; internal quotation marks omitted.) Cop-
    pola Construction Co. v. Hoffman Enterprises Ltd.
    
    Partnership, supra
    , 
    157 Conn. App. 169
    . ‘‘[A] party’s
    failure to comply with the notice provision in a termina-
    tion clause . . . amounts to a material breach of the
    contract.’’ 
    Id., 172. Here,
    the trial court concluded that Skanska ‘‘violated
    the contract terms when it responded to Semac’s moves
    by declaring that it was terminating Semac for cause’’
    without affording Semac forty-eight hours to cure its
    default under the contract. The court noted that Skan-
    ska’s rush to terminate Semac was likely ‘‘motivated
    by the contract clause that allowed Skanska to seize
    Semac’s equipment following a for-cause termination.’’
    The court reasoned: ‘‘Under the contract, Skanska had
    the right to terminate Semac anytime it wanted with
    cause or without. But for Skanska to terminate Semac
    for cause as it said it was and grab Semac’s equipment,
    the contract provides that it had to give Semac forty-
    eight hours to cure its breach and get back on the job.
    The contract doesn’t name any exception or qualify this
    rule in any way. It doesn’t say that the provision doesn’t
    apply when the other party breaches first. It doesn’t
    say it doesn’t apply when the other party isn’t likely
    to make use of the forty-eight hour period to cure.
    Elsewhere in the contract it does say that Skanska may
    seek any other remedies available at law outside the
    contract, but it doesn’t say anything about rewriting
    explicit provisions already contained in the contract to
    make them easier on Skanska. So the forty-eight hour
    notice that was not given had to be given for Skanska
    to terminate Semac for cause.
    ‘‘In pressing a strict application of the contract, Skan-
    ska must suffer the consequences of its own handiwork.
    We will never know what might have happened during
    that forty-eight hour period. Semac was facing ruin by
    continuing on the same terms, so absent some change
    it almost certainly would have left. But maybe Miller’s
    call for negotiations would have prevailed after every-
    one cooled down, and some sort of compromise might
    have been reached. It would have been tough, but the
    notice period might have achieved something. What is
    clear is that by giving no warning of its intention to
    terminate Semac, Skanska didn’t give the required forty-
    eight hours’ notice required by its contract.’’
    On the basis of the foregoing, and relying on this
    court’s decision in Coppola Construction Co. v. Hoff-
    man Enterprises Ltd. 
    Partnership, supra
    , 157 Conn.
    App. 169, in which we held that failing to give a required
    termination notice at the required time is a material
    contract breach, the court concluded that both Semac
    and Skanska materially breached the contract.
    In challenging the trial court’s determination that it
    breached its contract with Semac, Skanska does not
    dispute that it did not afford Semac forty-eight hours
    to cure its default. Skanska argues, however, that, for
    several reasons, Semac was not entitled to that cure
    period. Skanska first claims that the court erred in
    assuming that it terminated Semac pursuant to § 12.1
    of the contract, the provision that required it to give
    Semac forty-eight hours to cure its breach. Because
    Skanska actually pleaded in its counterclaim that it had
    ‘‘declared Semac in default . . . pursuant to exhibit E,
    article 12 of the subcontract,’’ the court properly held
    the parties to their obligations under that section of the
    contract. Moreover, Skanska’s reliance on § 12.1 can
    be inferred from its communications to Semac follow-
    ing its receipt of the Notice of Cardinal Change wherein
    it threatened to exercise its rights under the contract
    if Semac did not rescind its repudiation of the contract,
    specifically its right to seize all of Semac’s tools and
    equipment, a right afforded under § 12.1.
    Skanska also argues that Semac’s material breach
    and repudiation of the contract and its abandonment
    of the project absolved Skanska of its obligation to
    afford Semac a forty-eight hour cure period. In support
    of this claim, Skanska argues for the application of
    multiple common-law principles that are often applica-
    ble to contract disputes, namely, the principles of first
    breach, repudiation, anticipatory breach, and waiver.
    Skanska’s argument for the application of these princi-
    ples overlooks the clear language of § 12.1 of the con-
    tract that outlined the procedure to be followed if
    Semac abandoned the project or otherwise defaulted
    on its contractual obligations. Section 12.1 explicitly
    and comprehensively sets forth the parties’ rights and
    responsibilities in the event Semac was terminated for
    its abandonment of the project, the very basis for Skan-
    ska’s termination. We agree with the trial court’s deter-
    mination that Skanska should be held to the words of
    the contract, just as Semac had been, and was thus not
    excused from affording Semac a forty-eight hour cure
    period. To hold otherwise would excuse Skanska’s non-
    compliance with a contractual requirement, and ‘‘would
    create a new and different agreement, which courts
    cannot do.’’ Coppola Construction Co. v. Hoffman
    Enterprises Ltd. 
    Partnership, supra
    , 
    157 Conn. App. 171
    , citing Collins v. Sears, Roebuck & Co., 
    164 Conn. 369
    , 374, 
    321 A.2d 444
    (1973) (in construing contract,
    court cannot disregard words used by parties or revise,
    add to, or create new agreement).
    Skanska also claims that, ‘‘[i]n light of Semac’s con-
    duct, verbal, and written statements from October 19,
    2015 through October 22, 2015, it is uncontroverted that
    Semac would not perform under the subcontract and
    that waiting an additional [twenty-four] hours for a rec-
    onciliation that was not coming would have been futile.’’
    Skanska argues that Semac told it ‘‘in at least six differ-
    ent ways that it would be leaving’’ the project, and thus
    affording Semac an additional twenty-four hours to cure
    its breach would have been futile. As noted, the contract
    expressly provided that Semac was afforded a forty-
    eight hour cure period, and did not provide for any
    exceptions or qualifications to that requirement. Addi-
    tionally, we agree with the trial court that it cannot
    be known for certain, despite Semac’s repeated and
    unwavering representations that it would not continue
    to work on the project unless Skanska met its monetary
    demands, what the parties may have worked out. The
    trial court found that ‘‘[w]e will never know what might
    have happened during that forty-eight hour period.’’ We
    decline to speculate that waiting the additional hours
    required under the contract would have been futile.
    Skanska finally contends that the trial court’s
    enforcement of § 12.1 of the contract, and its rejection
    of Skanska’s assertion of various common-law doc-
    trines to defend its failure to abide by the express con-
    tract language of § 12.1 requiring the forty-eight hour
    cure period rendered meaningless § 19.5 of the contract,
    which provided that the remedies outlined in the con-
    tract were not the exclusive remedies available to Skan-
    ska. Although § 19.5 provides that the remedies set forth
    under the contract are not the exclusive remedies of
    the parties, we do not agree with Skanska’s contention
    that it can turn to the common law to avoid an obligation
    contained expressly in the contract.
    In sum, we agree with the trial court’s conclusion
    that, just as Semac was bound by the express language
    of the contract that contemplated the potential of delays
    and changes of sequencing, Skanska is bound by the
    language of the contract that expressly set forth the
    procedure that Skanska was required to follow if Skan-
    ska wanted to terminate Semac for abandonment of
    the project. Skanska cannot use the common law to
    excuse it from abiding by the language of the contract
    that it drafted. As the trial court noted, the contract
    very heavily favored Skanska, and Skanska failed to
    afford Semac one of the few protections afforded to
    Semac under the contract. In so doing, the trial court
    properly found that Skanska breached the contract.6
    III
    Both parties also challenge the court’s award of dam-
    ages to Skanska in the amount of $3,857,130.77.7 ‘‘It is
    axiomatic that the sum of damages awarded as compen-
    sation in a breach of contract action should place the
    injured party in the same position as he would have
    been in had the contract been performed. . . . The
    injured party, however, is entitled to retain nothing in
    excess of that sum which compensates him for the
    loss of his bargain. . . . Guarding against excessive
    compensation, the law of contract damages limits the
    injured party to damages based on his actual loss caused
    by the breach. . . . The concept of actual loss accounts
    for the possibility that the breach itself may result in
    a saving of some cost that the injured party would
    have incurred if he had had to perform. . . . In such
    circumstances, the amount of the cost saved will be
    credited in favor of the wrongdoer . . . that is, sub-
    tracted from the loss . . . caused by the breach in cal-
    culating [the injured party’s] damages. . . . The plain-
    tiff has the burden of proving the extent of the damages
    suffered.’’ (Citation omitted; internal quotation marks
    omitted.) Coppola Construction Co. v. Hoffman Enter-
    prises Ltd. 
    Partnership, supra
    , 
    157 Conn. App. 162
    .
    ‘‘[W]e review [a] trial court’s damages award under
    the clearly erroneous standard, under which we over-
    turn a finding of fact when there is no evidence in the
    record to support it . . . or when although there is
    evidence to support it, the reviewing court on the entire
    evidence is left with the definite and firm conviction
    that a mistake has been committed.’’ (Internal quotation
    marks omitted.) 
    Id., 176. With
    the previously cited principles in mind, we begin
    by reviewing the factual and legal bases underlying the
    trial court’s award of damages. The court noted that
    ‘‘Semac said it was due around $3.6 million for work
    completed to date when it left the job and wants an
    order for this money among other things. Skanska’s
    counterclaim seeks some $26 million, almost all of it
    for the cost of completing the work using replacement
    subcontractors. Because they both assume a breach of
    contract only by their adversary, both parties’ claims
    for damages are wrong.’’
    The court reasoned: ‘‘[B]oth parties here breached.
    Semac can’t fairly claim expectation damages as its
    reward for temporarily or permanently abandoning the
    contract. . . . Skanska, by contrast, had the right to
    terminate Semac for convenience without any grace
    period at all. . . . Indeed, the Skanska contract says
    that an erroneous termination for cause converts auto-
    matically to a termination for convenience. That con-
    tract also says termination for convenience means
    Skanska must pay—not expectation damages—but the
    money due for the work performed to date. That money
    is the right measure here, but as we will see, it doesn’t
    matter. The damages would be the same as expecta-
    tion damages.
    ‘‘In calculating what was due [to] Semac for work up
    to the date of its departure, Semac points out that it
    had several bills to Skanska outstanding when it left
    the job. It claims [that] Skanska’s breach means it had
    the right to stop work and, more important, Skanska
    had commanded it to cease performing. The latter fact
    certainly means Semac didn’t have to complete the job
    under the contract terms. After all, Skanska can’t have
    it both ways. Given that the contract terms mean that
    Skanska terminated Semac for its own convenience,
    Skanska can’t contradictorily claim that Semac should
    have kept working or pay for the cost of replacement
    subcontractors. It might have been different with a
    proper termination for cause based on Semac temporar-
    ily or permanently abandoning the job, but that’s not
    what the contract says happened here.
    ‘‘So Semac didn’t need to complete the job, isn’t liable
    for the costs of replacement subcontractors, and is due
    the money that was owed to it at the time it left.’’ In so
    finding, the court determined that Semac was entitled
    to a termination payment under § 12.4 of its contract
    with Skanska. The court nevertheless concluded that
    Semac ‘‘wasn’t due any money at the time it left and
    actually had money the contract required it to return
    to Skanska.’’
    To determine the amount of the termination payment
    to which Semac was entitled, the trial court found that
    it could not simply rely upon the amounts billed by
    Semac due to its billing ‘‘irregularities and its incentive
    to inflate its bills . . . .’’ The court thus determined
    that the best way to determine the amount to which
    Semac was entitled was to ascertain the percentage of
    the entire contract that Semac had fulfilled and multiply
    that percentage by the total amount of the contract.
    Both parties presented testimony as to their respective
    views as to the percentage of the job that had been
    completed when Semac was terminated, but the court
    found that the most persuasive testimony in this regard
    was offered by Miller, Skanska’s project manager, who
    opined that Semac had completed 65 percent of the
    job. The court adopted Miller’s position and calculated
    that Semac was entitled to $12,424,447, which was 65
    percent of the revised contract price of $19,114,535.
    Because Semac had already billed and been paid
    $14,785,764.36 from Skanska, Semac had received
    $2,361,317.36 more than it should have for the work
    that it had completed. To that amount, the trial court
    added funds that Semac had collected from Skanska
    for overpayments to two of Semac’s subcontractors and
    overpayment for labor rates on which Semac improp-
    erly had added a profit, for a total additional amount
    of $1,495,813.41. The court thus concluded that Semac
    owed Skanska a total of $3,857,130.77.8
    On appeal, Skanska argues that, ‘‘[d]ue to Semac’s
    material breach, Skanska was excused from further
    performance of its obligations under the contract, and
    was entitled to expectation damages.’’ Skanska claims,
    ‘‘as a result of the trial court’s incorrect determination
    that Skanska also breached the subcontract, it improp-
    erly failed to award its expectation damages.’’ Because
    we disagree with Skanska’s argument that it did not
    breach the contract, as discussed herein, we also reject
    its claim that it was entitled to expectation damages.
    Skanska also claims that it is entitled to expectation
    damages under the common law because § 19.5 pro-
    vided that its contractual remedies were not its exclu-
    sive remedies. We disagree. As stated previously, § 12.1
    of the contract explicitly provided for the procedure to
    be followed by Skanska in the event of a breach by
    Semac. Skanska failed to abide by the express require-
    ment that it afford Semac a forty-eight hour cure period
    and, thus, also breached the contract, and its termina-
    tion for cause of Semac was transformed into a termina-
    tion for convenience. Skanska cannot now claim entitle-
    ment to a common-law remedy after it forfeited its right
    to a contractual remedy as a result of its own breach.
    Semac argues that the court erred in not awarding
    it a termination payment under § 12.4 of the contract,
    which was triggered when Skanska failed to afford
    Semac a forty-eight hour cure period, transforming the
    termination for cause into a termination for conve-
    nience. Semac’s challenge in this regard is misplaced
    in that the trial court expressly did conclude that Semac
    was entitled to the termination payment when it con-
    cluded that Semac ‘‘didn’t need to complete the job,
    isn’t liable for the costs of replacement subcontractors,
    and is due the money that was owed to it at the time
    it left.’’ The court further found, however, that Semac’s
    billing practices were too irregular to confidently award
    damages based upon Semac’s invoices, as contemplated
    by § 12.4 of the contract, which provided that the termi-
    nation payment ‘‘shall be comprised of: (i) amounts
    invoiced and due for [w]ork performed but not yet paid;
    (ii) payment for [w]ork satisfactorily completed but not
    yet invoiced by [Semac] prior to the termination; (iii)
    retainage held by [Skanska] at the date of termination;
    and (iv) all reasonable, actual termination costs
    incurred by [Semac] in terminating the [w]ork . . . .’’
    The court therefore employed an alternative method
    of calculating the termination payment by determining
    the percentage of the project that Semac had completed
    and multiplying that percentage by the total contract
    price. Although potentially somewhat imprecise, it can-
    not reasonably be argued that this method of calculating
    the termination payment ran afoul of § 12.4 of the con-
    tract, or that it was unfair to Semac. Indeed, it is consis-
    tent with Semac’s claim that it be paid for the work
    that it completed and its theory of quantum meruit.9 If
    Semac had not front-loaded its invoices, ensuring that
    it made a profit for every month that it billed Skanska,
    it would not have been in the position of having its
    termination payment credited by monies that it should
    not have prematurely collected from Skanska. In light
    of the foregoing, we conclude that the trial court’s
    award of damages was not erroneous.
    IV
    Finally, Skanska claims that the trial court erred in
    failing to find that Pope and Scanlon committed fraud
    when they swore under oath to the accuracy of invoices
    submitted to Skanska for a total of $1,022,064.44 for
    goods and services that it represented it had paid, but
    actually never did pay, to other subcontractors, Gexpro
    and TPC Associates, Inc. We are not persuaded.
    ‘‘[I]t is well settled that the essential elements of fraud
    are: (1) a false representation was made as a statement
    of fact; (2) it was untrue and known to be untrue by
    the party making it; (3) it was made to induce the other
    party to act upon it; and (4) the other party did so act
    upon that false representation to his injury. . . . All of
    these ingredients must be found to exist. . . . Addi-
    tionally, [t]he party asserting such a cause of action
    must prove the existence of the first three of [the]
    elements by a standard higher than the usual fair pre-
    ponderance of the evidence, which . . . we have
    described as clear and satisfactory or clear, precise and
    unequivocal. . . . Finally, [t]he party claiming fraud
    . . . has the burden of proof. . . . Whether that bur-
    den has been met is a question of fact that will not
    be overturned unless it is clearly erroneous.’’ (Internal
    quotation marks omitted.) Trumbull v. Palmer, 
    123 Conn. App. 244
    , 257, 
    1 A.3d 1121
    , cert. denied, 
    299 Conn. 907
    , 
    10 A.3d 526
    (2010).
    ‘‘A finding of fact is clearly erroneous when there is
    no evidence in the record to support it . . . or when
    although there is evidence to support it, the reviewing
    court on the entire evidence is left with the definite
    and firm conviction that a mistake has been committed.
    . . . [A]s a reviewing court [w]e must defer to the trier
    of fact’s assessment of the credibility of the witnesses
    that is made on the basis of its firsthand observation
    of their conduct, demeanor and attitude. . . . The
    weight to be given to the evidence and to the credibility
    of witnesses is solely within the determination of the
    trier of fact. . . . In reviewing factual findings, [w]e do
    not examine the record to determine whether the
    [court] could have reached a conclusion other than the
    one reached. . . . Instead, we make every reasonable
    presumption . . . in favor of the trial court’s ruling.’’
    (Internal quotation marks omitted.) McLeod v. A Better
    Way Wholesale Autos, Inc., 
    177 Conn. App. 423
    , 450,
    
    172 A.3d 802
    (2017).
    Here, in rejecting Skanska’s claim that Pope and
    Scanlon engaged in fraudulent conduct, the trial court
    reasoned: ‘‘The court had ample time to judge what
    Scanlon and Pope said and how they said it. The court
    can’t find they clearly and convincingly committed
    fraud when they overcharged Skanska. Pope’s approach
    to being [chief financial officer], as he explained it,
    made some sense. His job was to sign for Semac after
    other people at the company were presumed to have
    vetted what he was to sign. He didn’t do their jobs for
    them; he signed on behalf of his company in reliance
    on what his company told him. Skanska may find it
    unconvincing, but Pope’s rationale about the Gexpro
    advanced billing of material isn’t clearly and convinc-
    ingly fraudulent either. It was supported by documents
    directly noting that material being charged for had not
    yet been received. At a minimum, he seemed to have
    sincerely and not heedlessly believed the advance bill-
    ing was a reasonable practice and that is enough to
    avoid culpability given the applicable standard.
    ‘‘Like Pope, Scanlon never bothered to read the entire
    contract or the waivers being signed. But as we have
    seen, it almost didn’t matter what they said anyway.
    Semac had to agree or lose the contract to the next
    bidder or, after signing the main contract, get no pay
    for the work it did. Given the relative positions of the
    parties, Semac had no choice, and the court does not
    believe Skanska’s suggestions that it should assume it
    would have agreed to material changes to the bargain if
    asked. As commercial and consumer contracts become
    increasingly intricate and the bargains increasingly
    unbalanced, it is a sad truth that hardly anyone reads
    them anymore while the courts and the lawyers keep
    on reading them and the courts almost always enforce
    them. This predictable form of neglect can’t form the
    basis for fraud since in this context Scanlon’s neglect
    was more pragmatic than reckless. This and some of
    his arguably inconsistent and inadequate efforts may
    have put his company on the hook for breach of con-
    tract, but they don’t support a finding that Scanlon
    committed fraud.
    ‘‘Fraud is something beyond Semac stretching things
    concerning the materials and the money it withheld for
    instance from subcontractor TPC. About TPC, Semac
    interpreted things in the light most favorable to itself,
    including its view that because the payments weren’t
    due to TPC, in its view it is protected by the language
    in the waivers about having paid all money ‘due’ to
    subcontractors. But this doesn’t amount to a lie or reck-
    less misstatement or, at least in light of the court’s
    credibility judgments there isn’t clear and convincing
    evidence of intent or recklessness: merely strained and
    self-interested interpretations. None of them amount to
    good reasons to impose massive financial liabilities on
    Scanlon or Pope.’’
    On appeal, Skanska argues that the record clearly
    showed that Pope and Scanlon acted fraudulently by
    not reading or verifying the accuracy of the content of
    the invoices to which they swore under oath. To be
    sure, that conduct, even as described by the trial court,
    strains the bounds of fraud, and reveals, at best, gross
    incompetence displayed by Pope and Scanlon. The trial
    court nevertheless found that, based upon its observa-
    tion of the demeanor and attitude of Pope and Scanlon,
    neither of them acted with fraudulent intent. Because
    we cannot second-guess the trial court’s credibility
    assessments, its rejection of Skanska’s fraud claim
    must stand.
    The judgment is affirmed.
    In this opinion the other judges concurred.
    1
    The court also awarded prejudgment interest in the amount of
    $405,259.79, for a total due to Skanska of $4,262,390.56. Neither party has
    challenged the court’s award of prejudgment interest.
    2
    Skanska also alleged defamation and tortious interference, but those
    claims were dismissed for lack of subject matter jurisdiction.
    3
    Prior to trial, the parties stipulated to the fact that Skanska spent
    $28,754,711.81 for other subcontractors and suppliers to complete Semac’s
    subcontract scope of work.
    4
    In its brief to this court, Semac claims: ‘‘The gravamen of this lawsuit
    . . . centers on whether the original $19.1 million construction contract,
    which the trial court found to be 65 percent complete when Skanska wrong-
    fully terminated Semac, but which cost an additional $28.7 million to finish
    after Semac left, is a fundamentally different contract than the one Semac
    agreed to perform. In the original contract Semac bargained for about 119,000
    hours of work, but by the time the contract was complete, the nature of
    the work and conditions of performance had changed so dramatically that
    the total labor hours required for completion of the electrical work exceeded
    430,000.’’ (Emphasis in original.) Semac argues that the trial court erred in
    rejecting its claim of cardinal change because it had ‘‘agreed to perform
    electrical work for Skanska for $19.1 million, [but c]hanges to Semac’s
    working conditions . . . increased the total cost of the electrical work to
    $45.6 million, [and] thus constituted a cardinal change as a matter of law.’’
    Semac contends: ‘‘The $45.6 million contract Skanska demanded was simply
    not the $19.1 million electrical contract for which Semac bargained.’’
    As explained herein, and conceded by counsel, this argument is not factu-
    ally accurate. The cardinal change upon which Semac relied on October 22,
    2015, did not, and, obviously, could not have contemplated the amount of
    money and hours that Skanska would be required to expend to complete
    the electrical work on the project several months after Semac refused to
    continue to its work on the project. Indeed, much of the additional cost is
    attributable to the fact that the substitute electrical contractors presented
    exorbitant bills that Skanska had to pay in order to finish the project on time.
    5
    Although not necessarily relevant to our review of the trial court’s rejec-
    tion of Semac’s claim of cardinal change, we note the likely validity of
    the court’s speculation of Semac’s true reason for abandoning the project:
    because it had front-loaded its billing, it realized that it was running out of
    funds in the fixed price contract against which it could bill Skanska.
    6
    Semac asserts that Skanska’s failure to allow it the full forty-eight hours
    to cure had the legal effect of maintaining Semac’s conduct in the status
    of a default and not a breach. We do not agree. While Skanska’s failure to
    afford the required cure period breached the contract, it in no way exoner-
    ated Semac for its own material breach.
    7
    This amount does not include the court’s award of prejudgment interest.
    8
    Semac subsequently moved for reconsideration of the amount of dam-
    ages based on an alleged miscalculation of certain of the credits applied to
    the termination payment. The court granted reargument, but affirmed its
    decision. This is not relevant to the claims on appeal.
    9
    Semac claims in its brief to this court that it was entitled to a termination
    payment under § 12.4 of the contract in the amount of $2,108,290.87. As
    Semac explains, this is the same amount that it would be entitled to under
    a theory of quantum meruit for the value of the work that it had completed.
    This is the very basis upon which the court calculated its award of damages.