Professional Electrical Contractors of Connecticut, Inc. v. Stamford Hospital ( 2020 )


Menu:
  • ***********************************************
    The “officially released” date that appears near the be-
    ginning of each opinion is the date the opinion will be pub-
    lished in the Connecticut Law Journal or the date it was
    released as a slip opinion. The operative date for the be-
    ginning of all time periods for filing postopinion motions
    and petitions for certification is the “officially released”
    date appearing in the opinion.
    All opinions are subject to modification and technical
    correction prior to official publication in the Connecticut
    Reports and Connecticut Appellate Reports. In the event of
    discrepancies between the advance release version of an
    opinion and the latest version appearing in the Connecticut
    Law Journal and subsequently in the Connecticut Reports
    or Connecticut Appellate Reports, the latest version is to
    be considered authoritative.
    The syllabus and procedural history accompanying the
    opinion as it appears in the Connecticut Law Journal and
    bound volumes of official reports are copyrighted by the
    Secretary of the State, State of Connecticut, and may not
    be reproduced and distributed without the express written
    permission of the Commission on Official Legal Publica-
    tions, Judicial Branch, State of Connecticut.
    ***********************************************
    PROFESSIONAL ELECTRICAL CONTRACTORS OF
    CONNECTICUT, INC. v. THE STAMFORD
    HOSPITAL ET AL.
    (AC 41931)
    Bright, Moll and Bear, Js.
    Syllabus
    The plaintiff, a second tier subcontractor, sought to recover damages from
    the defendants H Co., a hospital, S Co., a general contractor, and E Co.,
    a subcontractor, for, inter alia, quantum meruit or unjust enrichment,
    and to collect on a bond issued by the defendant F Co. posted pursuant
    to statute (§ 49-37), in connection with a dispute arising from a project
    relating to the expansion and renovation of H Co. Following the trial
    court’s granting of motions for summary judgment filed by F Co. and
    S Co., the plaintiff appealed to this court. Held:
    1. The trial court erred in granting S Co.’s motion for summary judgment
    on the count of the complaint in which the plaintiff alleged that H Co.,
    S Co. and E Co. were liable in quantum meruit or unjust enrichment;
    the plaintiff alleged that it performed services at the request of H Co.,
    S Co. and E Co., and that H Co., S Co. and E Co. accepted and benefited
    from the plaintiff’s work, and S Co. presented no evidence establishing
    that it paid E Co. or someone else for the plaintiff’s specific services,
    and, thus, there existed a genuine issue of material fact with respect to
    the plaintiff’s claim for quantum meruit or unjust enrichment.
    2. The trial court erred in granting the motion for summary judgment filed
    by S Co. and F Co. on the count of the complaint in which the plaintiff
    sought to collect on the surety bond issued by F Co.: under Connecticut’s
    mechanic’s lien statutes (§§ 49-33 and 49-36), recovery was not barred
    to the second tier subcontractor plaintiff solely because the first tier
    subcontractor had been paid in full by S Co.; moreover, S Co. and F
    Co. could not prevail on their alternative ground for affirmance that the
    lienable fund had been exhausted by the costs of the project and that
    the plaintiff did not have a contract with H Co., S Co. or F Co.; there
    was a lienable fund still available in the amount still owed by H Co. to
    S Co. at the time the plaintiff gave statutory notice (§§ 49-34 and 49-35)
    of its lien to H Co., regardless of whether H Co. continued to make
    payments to the nondefaulted S Co., a construction of the applicable
    statutes that was supported by the legislative history.
    Argued November 18, 2019—officially released March 17, 2020
    Procedural History
    Action to recover damages for, inter alia, breach of
    contract, and for other relief, brought to the Superior
    Court in the judicial district of Stamford, where the
    plaintiff withdrew the action as to the named defendant;
    thereafter, the court, Hon. Edward R. Karazin, Jr.,
    judge trial referee, granted the motions for summary
    judgment filed by the defendant Skanska USA Building,
    Inc., et al., and rendered judgment thereon, from which
    the plaintiff appealed to this court. Reversed in part;
    further proceedings.
    Kenneth A. Votre, for the appellant (plaintiff).
    Michael J. Donnelly, with whom was Kevin W. Munn,
    for the appellee (defendant Sanska USA Building, Inc.).
    Charles I. Miller filed a brief for the appellee (defen-
    dant Fidelity and Deposit Company of Maryland).
    Opinion
    BRIGHT, J. The plaintiff, Professional Electrical Con-
    tractors of Connecticut, Inc., appeals from the summary
    judgment rendered by the trial court in favor of the
    defendants Fidelity and Deposit Company of Maryland
    (Fidelity)1 and Skanska USA Building, Inc. (Skanska).2
    On appeal, the plaintiff claims that the court erred in
    rendering summary judgment on counts two and three
    of its complaint because there were genuine issues of
    material facts and neither defendant was entitled to
    judgment as a matter of law. Specifically, the plaintiff
    claims that (1) Skanska failed to prove that there existed
    no issues of material fact on the plaintiff’s equitable
    claim of quantum meruit or unjust enrichment, and (2)
    neither defendant established that it was entitled to
    judgment as a matter of law on the plaintiff’s bond
    claim because the claim is viable pursuant to General
    Statutes §§ 49-33 and 49-36. We agree with the plaintiff
    on both claims. Accordingly, we reverse in part and
    affirm in part the judgment of the trial court.3
    The following facts, which were uncontested for sum-
    mary judgment purposes, and procedural history are
    relevant to our consideration of the issues on appeal.
    The plaintiff commenced this action by service of pro-
    cess on January 4, 2017. In its complaint, the plaintiff
    alleged, in count one, that Semac Electrical Company,
    Inc. (Semac), Skanska, and The Stamford Hospital (hos-
    pital) were in breach of contract on the basis of the
    following alleged facts: the hospital had entered into a
    contract with Skanska to provide construction services
    to the hospital (project); Skanska entered into a subcon-
    tract agreement with Semac for electrical work on the
    project; Semac entered into a second tier subcontract
    agreement with the plaintiff to perform electrical work
    on the project; on October 3, 2015, the plaintiff began
    to furnish materials and services for the project; the
    plaintiff furnished materials and services in accordance
    with the terms of its contract; the plaintiff has
    demanded payments in the amount of $38,509.07; and
    Semac, Skanska, and the hospital all have refused to
    pay the plaintiff for its materials and services in breach
    of contract.
    In count two of its complaint, the plaintiff alleged
    that Semac, Skanska, and the hospital were liable under
    the theories of quantum meruit or unjust enrichment.
    In addition to the facts alleged in count one, which the
    plaintiff incorporated into count two, the plaintiff also
    alleged that it performed services and incurred costs
    at the request of Semac, Skanska, and the hospital; its
    services were worth at least $38,509.07; Semac, Skan-
    ska, and the hospital accepted and benefited from the
    plaintiff’s work; the plaintiff requested payment for the
    reasonable value of the services it rendered; Semac,
    Skanska, and the hospital have refused to pay the plain-
    tiff; and Semac, Skanska, and the hospital have been
    unjustly enriched.
    In the third count of its complaint, the plaintiff sought
    to collect on the bond pursuant to General Statutes § 49-
    37. Specifically, it alleged in count three that Skanska
    submitted a bond in the amount of $38,509.07 in substi-
    tution for the mechanic’s lien that had been filed against
    the hospital in the original amount of $42,359.97; on
    January 27, 2016, Fidelity issued the surety bond in the
    amount of $42,359.97; Skanska has failed to pay the
    plaintiff, despite repeated demands for the sum of
    $38,509.07; and Fidelity has refused to pay the plaintiff
    on the bond.
    Fidelity filed an answer and set forth a special defense
    in which it alleged that the lienable fund had been
    exhausted by the costs of the project, and that the
    plaintiff did not have a contract with the hospital, Skan-
    ska, or Fidelity. Skanska also filed an answer in which
    it, inter alia, denied having any type of contract with
    the plaintiff, and it left the plaintiff to its proof on other
    allegations set forth in the complaint. Skanska did not
    file a special defense.
    On March 29, 2018, Skanska filed a motion for sum-
    mary judgment on the plaintiff’s complaint. In its
    motion, Skanska argued that it was entitled to judgment
    as a matter of law because (1) there was no lienable
    fund available because all funds had been exhausted
    in completing the project, (2) there existed no contract
    between it and the plaintiff, and (3) its payment to
    Semac, the party with whom the plaintiff had con-
    tracted, barred the plaintiff’s claims for quantum meruit
    or unjust enrichment. In support of its motion for sum-
    mary judgment, Skanska submitted the affidavit of
    Michael J. Smerglio, the executive director of facilities
    management for the hospital. Smerglio averred that the
    hospital and Skanska had entered into a contract for
    the construction and renovation of the hospital, which
    required Skanska to act as the construction manager
    for the project. He also averred that Skanska would
    send the hospital periodic requests for payment on the
    basis of the work that had been completed, and that
    the hospital would produce the payments after making
    any necessary adjustments. Further, he averred that the
    hospital and Skanska had entered into a series of change
    orders that expanded and refined the work to be done
    on the project, which then adjusted the final contract
    price to a maximum price of $284,091,867. Smerglio
    acknowledged that the plaintiff served the hospital with
    a notice of mechanic’s lien on January 13, 2016, and
    that, as of that date, the hospital had paid to Skanska
    the sum of $216,637,556.56 on the project, and that it
    had not paid any other entity for work done on the
    project. Smerglio additionally averred that, after Janu-
    ary 13, 2016, the hospital paid Skanska an additional
    $67,354,375.44 for work on the project, for a total of
    $283,991,932, with the remaining $99,935 held as
    retainage, pending completion of some punch list items.
    Smerglio also declared that Skanska had not been in
    default on its contract with the hospital. Appended to
    Smerglio’s affidavit were several exhibits, the first of
    which provided that the original amount of the contract
    between the hospital and Skanska, before the series
    change orders, was $267,706,729.
    Skanska also submitted the affidavit of Mark Miller,
    its senior vice president and the director for the project.
    Miller averred in relevant part that in October, 2015,
    Semac breached its subcontract with Skanska and aban-
    doned the project, requiring Skanska to hire replace-
    ment subcontractors to complete the work at an
    increased cost, which was borne by Skanska and not
    by the hospital. Miller further attested that there never
    was a contract between Skanska and the plaintiff, the
    hospital and the plaintiff, or Fidelity and the plaintiff
    in relation to the project, and that the plaintiff was a
    second tier subcontractor on the project.
    On April 2, 2018, Fidelity filed a motion for summary
    judgment, specifically joining Skanska’s motion and
    memorandum as to count three of the plaintiff’s com-
    plaint, which is the bond claim.
    The plaintiff filed an opposition to the motions for
    summary judgment, arguing that there were genuine
    issues of material fact that prohibited the granting of
    the motions for summary judgment and that there was
    no merit to the motions as to the bond claim because
    it is uncontested that the lienable fund was not
    exhausted at the time the plaintiff filed its mechanic’s
    lien. No affidavits or other evidence were attached to
    the plaintiff’s memorandum in opposition.
    On July 11, 2018, the court rendered summary judg-
    ment in favor of the defendants, concluding that there
    were no genuine issues of material fact and that the
    defendants were entitled to judgment as a matter of
    law. As to the plaintiff’s claim for breach of contract,
    the court stated that the plaintiff had conceded that it
    did not have a contract with Skanska and, therefore,
    that count one of the complaint was not viable as to
    Skanska. As to the plaintiff’s claim for quantum meruit
    or unjust enrichment, set forth in count two of the
    complaint, the court, referencing and taking judicial
    notice of the related case of Semac Electric Co. v. Skan-
    ska USA Building, Inc., Superior Court, judicial district
    of Hartford, Complex Litigation Docket, Docket No.
    X07-CV-XX-XXXXXXX-S (August 23, 2017), aff’d, 195 Conn.
    App. 695,      A.3d      (2020) (Semac), pointed out that
    ‘‘[t]he record in Semac [was] silent on whether Skanska
    dealt with the plaintiff prior to Semac’s breach, directed
    the plaintiff’s performance and knowingly accepted its
    services, or represented that Skanska [would] compen-
    sate the plaintiff for work done.’’ Nonetheless, the court
    concluded that judgment was appropriate on this count
    of the plaintiff’s complaint because it concluded that
    there was no evidence of an implied contract between
    Skanska and the plaintiff.
    As to the bond claim, the court concluded that the
    defendants’ argument that the lienable fund had been
    exhausted was not compelling, but, relying on Brian’s
    Floor Covering Supplies, LLC v. Spring Meadow
    Elderly Apartments, Superior Court, judicial district of
    Fairfield, Docket No. CV-XX-XXXXXXX-S (March 22, 2006),
    concluded that Skanska already had paid Semac for the
    plaintiff’s work, and, therefore, the plaintiff could not
    recover under the bond. The court, thereafter, rendered
    judgment in favor of the defendants. This appeal
    followed.
    ‘‘In seeking summary judgment, it is the movant who
    has the burden of showing the nonexistence of any
    issue of fact. The courts are in entire agreement that
    the moving party for summary judgment has the burden
    of showing the absence of any genuine issue as to all
    the material facts, which, under applicable principles
    of substantive law, entitle him to a judgment as a matter
    of law. The courts hold the movant to a strict standard.
    To satisfy his burden the movant must make a showing
    that it is quite clear what the truth is, and that excludes
    any real doubt as to the existence of any genuine issue
    of material fact. . . . As the burden of proof is on the
    movant, the evidence must be viewed in the light most
    favorable to the opponent. . . . When documents sub-
    mitted in support of a motion for summary judgment
    fail to establish that there is no genuine issue of material
    fact, the nonmoving party has no obligation to submit
    documents establishing the existence of such an issue.
    . . . Once the moving party has met its burden, how-
    ever, the opposing party must present evidence that
    demonstrates the existence of some disputed factual
    issue. . . . It is not enough, however, for the opposing
    party merely to assert the existence of such a disputed
    issue. Mere assertions of fact . . . are insufficient to
    establish the existence of a material fact and, therefore,
    cannot refute evidence properly presented to the court
    under Practice Book § [17-45]. . . . Our review of the
    trial court’s decision to grant [a] motion for summary
    judgment is plenary.’’ (Citations omitted; footnote omit-
    ted; internal quotation marks omitted.) Allstate Ins. Co.
    v. Barron, 
    269 Conn. 394
    , 405–406, 
    848 A.2d 1165
    (2004).
    I
    The plaintiff claims that the court erred in rendering
    summary judgment on count two of its complaint
    because Skanska failed to prove that there exists no
    issue of material fact on the equitable claim of quantum
    meruit or unjust enrichment. The plaintiff argues that
    it sufficiently alleged in its complaint that Skanska knew
    of and accepted the plaintiff’s work, and that this allega-
    tion, which has not been rebutted sufficiently by the
    defendants’ evidence, alone demonstrates the existence
    of an issue of material fact as to whether there was an
    implied contract between the plaintiff and Skanska,
    which would support count two of its complaint sound-
    ing in the theories of quantum meruit and unjust enrich-
    ment. The plaintiff also argues that the issue of whether
    Skanska paid Semac in full for the work done by the
    plaintiff has no bearing on its claims for quantum meruit
    or unjust enrichment because Semac did not pay the
    plaintiff, and Skanska accepted the benefit of the plain-
    tiff’s work. Skanska argues that the plaintiff’s claim
    sounds only in unjust enrichment, not in quantum
    meruit, which the plaintiff disputes vigorously in its
    reply brief. On the merits of the plaintiff’s claim, Skan-
    ska argues that, because it paid Semac for the work
    done by the plaintiff, the plaintiff cannot recover from
    Skanska but must seek its recovery from Semac. We
    agree with the plaintiff.
    ‘‘Quantum meruit and unjust enrichment are noncon-
    tractual means of recovery in restitution. Quantum
    meruit is a theory of recovery permitting restitution in
    the context of an otherwise unenforceable contract. In
    contrast, recovery under a theory of unjust enrichment
    applies in the absence of a quasi-contractual relation-
    ship. . . . Because both doctrines are restitutionary,
    the same equitable considerations apply to cases under
    either theory. The terms of an unenforceable contract
    will often be the best evidence for restitution of the
    reasonable value of services rendered in quantum
    meruit, although sometimes the equities may call for a
    more restrictive measure. . . . [Our Supreme Court]
    has used quantum meruit and unjust enrichment inter-
    changeably, or as equivalent terms for recovery in resti-
    tution.’’ (Citations omitted.) Walpole Woodworkers, Inc.
    v. Manning, 
    307 Conn. 582
    , 587 n.9, 
    57 A.3d 730
    (2012).
    ‘‘Quantum meruit is a theory of contract recovery
    that does not depend upon the existence of a contract,
    either express or implied in fact. . . . Rather, quantum
    meruit arises out of the need to avoid unjust enrichment
    to a party, even in the absence of an actual agreement.
    . . . Quantum meruit literally means as much as he has
    deserved . . . . Centered on the prevention of injus-
    tice, quantum meruit strikes the appropriate balance
    by evaluating the equities and guaranteeing that the
    party who has rendered services receives a reasonable
    sum for those services. Unjust enrichment applies
    whenever justice requires compensation to be given for
    property or services rendered under a contract, and no
    remedy is available by an action on the contract . . . .
    Indeed, lack of a remedy under the contract is a precon-
    dition for recovery based upon unjust enrichment. Not
    unlike quantum meruit, it is a doctrine based on the
    postulate that it is contrary to equity and fairness for
    a defendant to retain a benefit at the expense of the
    plaintiff.’’ (Citations omitted; internal quotation marks
    omitted.) Gagne v. Vaccaro, 
    255 Conn. 390
    , 401, 
    766 A.2d 416
    (2001).
    ‘‘[A] right of recovery under the doctrine of unjust
    enrichment is essentially equitable, its basis being that
    in a given situation it is contrary to equity and good
    conscience for one to retain a benefit which has come
    to him at the expense of another. . . . With no other
    test than what, under a given set of circumstances, is
    just or unjust, equitable or inequitable, conscionable or
    unconscionable, it becomes necessary in any case
    where the benefit of the doctrine is claimed, to examine
    the circumstances and the conduct of the parties and
    apply this standard. . . .
    ‘‘Unjust enrichment is a very broad and flexible equi-
    table doctrine that has as its basis the principle that it
    is contrary to equity and good conscience for a defen-
    dant to retain a benefit that has come to him at the
    expense of the plaintiff. . . . The doctrine’s three basic
    requirements are that (1) the defendant was benefited,
    (2) the defendant unjustly failed to pay the plaintiff for
    the benefits, and (3) the failure of payment was to the
    plaintiff’s detriment. . . . All the facts of each case
    must be examined to determine whether the circum-
    stances render it just or unjust, equitable or inequitable,
    conscionable or unconscionable, to apply the doctrine.’’
    (Citations omitted; internal quotation marks omitted.)
    
    Id., 408–409. In
    the present case, in count two of its complaint,
    the plaintiff alleges that Skanska is liable to it under
    the theories of quantum meruit or unjust enrichment.
    Specifically, the plaintiff alleges in count two that Skan-
    ska entered into a contract with the hospital to provide
    construction services on the project; Skanska entered
    into a subcontract agreement with Semac to perform
    electrical work on the project; Semac entered into a
    second tier subcontract agreement with the plaintiff to
    perform electrical work on the project; the plaintiff, on
    October 3, 2015, began to furnish materials and services
    for the project; the plaintiff performed services and
    incurred costs at the request of Skanska; Skanska
    accepted and benefited from the plaintiff’s work; the
    plaintiff demanded payment in the amount of
    $38,509.07 for its services from Skanska; and Skanska
    refused to pay the plaintiff.
    In its motion for summary judgment as to count two
    of the plaintiff’s complaint, Skanska argued that,
    because it had paid Semac, the party with whom the
    plaintiff had a written contract, the plaintiff’s claims
    against Skanska were barred. In support of its motion
    for summary judgment, Skanska relied on the affidavit
    of Miller and the court’s decision in the Semac case.
    Miller averred in relevant part that in October, 2015,
    Semac breached its subcontract with Skanska and aban-
    doned the project, requiring Skanska to hire replace-
    ment subcontractors to complete the electrical work
    at an increased cost, which was borne by Skanska and
    not by the hospital. Miller further attested that the plain-
    tiff was a second tier subcontractor on the project, and
    that there existed no contract between Skanska and
    the plaintiff. In the Semac case, the court held that
    Semac had overbilled Skanska, and it rendered judg-
    ment in favor of Skanska and against Semac in the
    amount of $4,262,390.56. Semac Electrical Co. v. Skan-
    ska USA Building, 
    Inc., supra
    , Superior Court Docket
    No. X07-CV-XX-XXXXXXX-S. Skanska argues that because
    it is undisputed that it paid Semac and replacement
    contractors more than the amount it contractually was
    required to pay Semac, as a matter of law, it cannot
    have been unjustly enriched by not paying the plaintiff
    for any work it performed. We are not persuaded.
    The Miller affidavit and the court’s decision in the
    Semac case do not speak to the plaintiff’s allegations
    in count two that it began working on the project on
    October 3, 2015, that it obtained materials and provided
    services in the amount of $38,509.07 for the project,
    that it completed its work, that Skanska accepted and
    benefited from the plaintiff’s work, that the plaintiff
    performed services and incurred costs at the request
    of Skanska and that Skanska has never paid for the
    plaintiff’s work.4 The trial court, in its decision in the
    Semac case, calculated damages due to Skanska based
    on the court’s analysis of the percentage of work com-
    pleted by Semac compared to how much Semac was
    paid. 
    Id. The trial
    court in that case made no finding
    that Semac had been paid for the work performed by
    the plaintiff. The lack of such a finding is particularly
    significant because the court specifically found that
    Semac had been compensated for the work performed
    by two other subcontractors. Additionally, as the trial
    court in the present case stated, it also is unknown
    whether Skanska ‘‘dealt with the plaintiff prior to Sem-
    ac’s breach, directed the plaintiff’s performance and
    knowingly accepted its services, or represented that [it
    would] compensate the plaintiff for work done.’’
    The fact that Skanska paid replacement electrical
    contractors more than it was contractually obligated
    to pay Semac, as averred to by Miller, or overpaid
    Semac, as found by the trial court in the Semac case,
    says nothing about whether Skanska ever paid Semac
    or anyone else for the work performed by the plaintiff.
    Without evidence to the contrary, it is entirely possible
    that the additional costs incurred by Skanska for electri-
    cal work were unrelated to the work performed by the
    plaintiff. If that is the case, then Skanska was unjustly
    enriched because it received the benefit of the plaintiff’s
    work without ever paying anyone for it. The court was
    not in a position to resolve this issue on summary judg-
    ment because Skanska failed to present evidence estab-
    lishing that there was no genuine issue of material fact
    that it had paid Semac or someone else for the plaintiff’s
    specific services.
    The cases relied on by Skanska are consistent with
    our analysis. In Providence Electric Co. v. Sutton Place,
    Inc., 
    161 Conn. 242
    , 245–47, 
    287 A.2d 379
    (1971), our
    Supreme Court held that the plaintiff subcontractor
    who had supplied appliances to the general contractor
    to be installed in apartments in the defendant owner’s
    building could not prevail on a claim of unjust enrich-
    ment against the owner because the plaintiff failed to
    prove that the owner had not paid the general contrac-
    tor for the appliances. 
    Id. According to
    the court, ‘‘[i]n
    this case, the plaintiff has clearly demonstrated that
    [the owner] has derived a benefit: Electrical appliances
    were installed in its apartments. If, however, [the
    owner] paid [the general contractor] for those appli-
    ances, then the enrichment, in the absence of fraud,
    has not been unjust.’’ (Emphasis added.) 
    Id., 246. The
    question then is whether the owner, or in this case,
    Skanska, paid for the precise goods and/or services
    supplied by the subcontractor. In Nation Electrical
    Contracting, LLC v. St. Dimitrie Romanian Orthodox
    Church, 
    144 Conn. App. 808
    , 
    74 A.3d 474
    (2013), this
    court upheld the trial court’s unjust enrichment award
    to the plaintiff subcontractor because there was suffi-
    cient evidence that the defendant owner had not paid
    the general contractor for the plaintiff’s work even
    though the owner had ‘‘paid far in excess of the contract
    price to complete the project.’’ 
    Id., 818–19. Conse-
    quently, Skanska was entitled to summary judgment
    only if it submitted evidence sufficient to establish that
    there was no genuine issue of material fact that it paid
    for the specific work performed by the plaintiff. It failed
    to do so.
    It is the movant’s burden at the summary judgment
    stage to prove that there exists no disputed issue of
    material fact and that it is entitled to judgment as a
    matter of law. See, e.g., Allstate Ins. Co. v. 
    Barron, supra
    , 
    269 Conn. 405
    . The absence of any evidence
    to refute the plaintiff’s allegations that it performed
    services at the request of Skanska, and that Skanska
    accepted and benefited from the plaintiff’s work
    because it never paid for that work, creates genuine
    issues of material fact with respect to the plaintiff’s
    claim for quantum meruit or unjust enrichment.5 Nei-
    ther Miller’s affidavit nor the court’s decision in the
    Semac case, submitted by Skanska in support of its
    motion for summary judgment on count two of the
    plaintiff’s complaint, addresses these material allega-
    tions. Accordingly, the court erred in granting Skanska’s
    motion for summary judgment on count two of the
    plaintiff’s complaint.
    II
    The plaintiff next claims that the court erred as a
    matter of law in rendering summary judgment on count
    three of its complaint. Specifically, the plaintiff argues
    that its bond claim is viable under a proper reading of
    our mechanic’s lien statutes, including §§ 49-33, 49-36,
    and 49-37.6 The defendants argue that the court properly
    granted the motion for summary judgment on the third
    count of the plaintiff’s complaint, but for the wrong
    reason. Specifically, they argue that they were entitled
    to judgment as a matter of law on count three of the
    plaintiff’s complaint because the lienable fund was
    exhausted in completing the project, and there were
    no funds remaining to give to the plaintiff.7 We agree
    with the plaintiff that its claim remains viable.
    ‘‘Those who provide services or materials in connec-
    tion with the construction of a building are entitled to
    claim a lien on the land that they have improved if they
    fall into one of two categories. Lienors are protected
    if they have a claim either (1) by virtue of an agreement
    with or the consent of the owner of the land, or (2) by
    the consent of some person having authority from or
    rightfully acting for such owner in procuring labor or
    materials. General Statutes § 49-33. Lienors in the sec-
    ond category must give timely notice of their intent to
    claim a lien in order to perfect their lien, while those
    in the first category need not give such notice. General
    Statutes § 49-35. Lienors in the second category include
    subcontractors and persons who furnish materials or
    services by virtue of a contract with the original contrac-
    tor or with any subcontractor, that is to say at least
    first and second tier subcontractors. General Statutes
    § 49-35. No mechanic’s lien may exceed the price which
    the owner has agreed to pay for the building being
    erected or improved, and the owner is entitled, further-
    more, to credit for payments made in good faith to the
    original contractor before receipt of notice of such a
    lien or liens. General Statutes §§ 49-33 and 49-36. If
    the contract price which the owner agreed to pay the
    original contractor is insufficient to cover all the liens,
    claimants other than the original contractor are to be
    paid first, and, if necessary, on a pro rata basis. General
    Statutes § 49-36.’’ (Emphasis added; footnote omitted.)
    Seaman v. Climate Control Corp., 
    181 Conn. 592
    , 595–
    96, 
    436 A.2d 271
    (1980)8; see also ProBuild East, LLC
    v. Poffenberger, 
    136 Conn. App. 184
    , 191–92, 
    45 A.3d 654
    (2012).
    ‘‘General Statutes § 49-33 establishes a lien in favor
    of subcontractors by virtue of an agreement with or by
    consent of the owner of the land upon which the build-
    ing is being erected . . . . It is well established that
    [i]t is not necessary to their lien status that [a subcon-
    tractor] have any direct contractual relationship either
    with the owner or with the general contractor . . . .
    All that is necessary is that the defendant consented to
    have a building erected on its property and that the lien
    was for materials or services provided in the erection
    of said building.’’ (Citations omitted; internal quotation
    marks omitted.) Connecticut Carpenters Benefit Funds
    v. Burkhard Hotel Partners II, LLC, 
    83 Conn. App. 352
    ,
    362, 
    849 A.2d 922
    (2004).
    We first address the reasoning set forth by the trial
    court in rendering summary judgment on the bond
    claim. The court held that ‘‘because Skanska already
    paid Semac . . . it was not obligated to pay the plaintiff
    . . . .’’ But see footnote 4 of this opinion. We disagree
    with the premise of this holding. Our Supreme Court
    in Seaman v. Climate Control 
    Corp., supra
    , 
    181 Conn. 596
    –97, addressed this precise question and clearly held
    that, under our mechanic’s lien statutes, recovery would
    not be barred to a second tier subcontractor solely
    because ‘‘the first tier subcontractor with whom they
    contracted has been paid in full by the general contrac-
    tor.’’ The trial court, therefore, erred in rendering sum-
    mary judgment on this ground. We next consider the
    alternative ground for affirmance raised by the defen-
    dants on appeal.
    We have examined all of the cases raised by the
    parties, as well as conducted our own examination of
    our appellate case law, and we have found nothing
    factually analogous with the present case. Accordingly,
    we must determine, as a matter of first impression,
    whether a lienable fund is exhausted when, after proper
    notice that a subcontractor has filed a mechanic’s lien
    on the property, the property owner continues to pay
    the general contractor for work on the project until the
    general contractor has been paid the full contract price.
    Guided by our General Statutes, relevant legislative his-
    tory, and our relevant case law, we conclude that when
    the general contractor is not in default, unless there
    were payments made in bad faith, the lienable fund is
    the amount still owed by the property owner to the
    general contractor at the time the property owner
    receives notice of the lien pursuant to General Statutes
    § 49-34,9 regardless of whether it continues to make
    payments to the nondefaulted general contractor. See
    General Statutes § 49-36 (c) (in determining amount of
    lienable fund, property owner allowed credit for what-
    ever good faith payments it has made to general contrac-
    tor before it received notice of lien); see generally Gen-
    eral Statutes § 49-35 (regarding subcontractor’s notice
    of intent);10 H & S Torrington Associates v. Lutz Engi-
    neering Co., 
    185 Conn. 549
    , 555, 
    441 A.2d 171
    (1981)
    (subcontractor or materialman may give property
    owner § 49-35 notice of intent prior to recording
    mechanic’s lien certificate or may give notice under
    §§ 49-34 and 49-35 with service of lien certificate; two
    separate notices not required).11
    Although, as noted previously in this opinion, neither
    this court nor our Supreme Court has addressed the
    precise issue before us, certain decisions by our
    Supreme Court interpreting the relevant statutes at
    issue in this case inform our analysis. We start with
    our Supreme Court’s decision in Seaman, a case quite
    similar in many respects to the present case, and one
    relied on by all parties on appeal. In Seaman, the plain-
    tiff, who was the property owner, contracted with a
    general contractor to construct apartment style hous-
    ing. Seaman v. Climate Control 
    Corp., supra
    , 
    181 Conn. 593
    . The general contractor then entered into a subcon-
    tract agreement for the installation of plumbing equip-
    ment on the project, and the subcontractor, thereafter,
    entered into two second tier subcontract agreements,
    one with a supplier and one with a servicer. 
    Id., 593–94. The
    second tier subcontractors, who were the defen-
    dants in the case, had no contractual relationship with
    the plaintiff or the general contractor, and their work
    was not directed or controlled by either of them. 
    Id., 594. The
    general contractor had paid the subcontractor
    nearly the full amount of its subcontract price when
    the subcontractor defaulted and walked off the job. 
    Id., 594 and
    n.3. Although having been paid by the general
    contractor, the subcontractor had not paid the defen-
    dants. 
    Id., 594–95. The
    defendants notified the property
    owner of their intention to file a mechanic’s lien; at
    that time, the property owner still owed the general
    contractor $89,157, with an additional cost of $8005.91
    to complete the work left unfinished by the defaulting
    subcontractor. 
    Id., 594. The
    defendants each filed a
    mechanic’s lien, one in the amount of $40,697.66 and
    the other in the amount of $7702, the total of which
    was ‘‘substantially less than the amount remaining due
    . . . to the general contractor . . . .’’ 
    Id., 595. The
    par-
    ties thereafter stipulated that the $7702 amount should
    be $6526. 
    Id. Unlike the
    hospital in the present case,
    the property owner in Seaman did not pay the general
    contractor the outstanding balance he owed, but,
    rather, he retained that money after receiving notice of
    the liens. 
    Id., 596. Our
    Supreme Court explained in Seaman: ‘‘The sub-
    contractors, even though they are second tier rather
    than first tier subcontractors, are prima facie within
    the ambit of the mechanic’s lien law. It is not necessary
    to their lien status that they have any direct contractual
    relationship either with the owner or with the general
    contractor (denominated the original contractor in the
    statutes). They have concededly given timely notice to
    the owner, in proper form, of their liens. There is an
    identifiable fund which appropriate claims for mechan-
    ic’s liens may reach, since the owner has retained an
    unpaid balance due under his contract with the general
    contractor that exceeds in amount the totality of the
    mechanic’s lien claims.’’ 
    Id. Our Supreme
    Court then
    explained that the defendants, which were second tier
    subcontractors, were not barred from recovery on their
    liens simply because the first tier subcontractor, with
    whom they had contracted, had been paid in full by the
    general contractor. 
    Id., 596–97. Our
    Supreme Court then set forth its analysis of § 49-
    33: ‘‘In interpreting this section, the complexity of which
    should not be underestimated . . . we are guided by
    [well settled] principles of construction. Although the
    mechanic’s lien law creates a statutory lien in deroga-
    tion of the common law, its remedial purpose to furnish
    security for a contractor’s labor and materials requires
    a generous construction. . . . Even bearing in mind
    the statute’s beneficent purpose, we are, however, con-
    strained by the language of the statute as we find it,
    and cannot rewrite the statute or adopt the reasoning
    of precedents in other jurisdictions with different stat-
    utes. . . .
    ‘‘Two sentences in § 49-33 are central to the argu-
    ments of the parties. ‘[A] mechanic’s lien shall [not]
    attach to any . . . building . . . in favor of any sub-
    contractor to a greater extent in the whole than the
    amount which the owner has agreed to pay to any
    person through whom [the] subcontractor claims
    . . . . [General Statutes § 49-33 (e).] Any such subcon-
    tractor shall be subrogated to the rights of the person
    through whom such subcontractor claims . . . .’ [Gen-
    eral Statutes § 49-33 (f).] The plaintiff urges that the
    second sentence subrogates the second tier subcontrac-
    tor to the rights of the first tier subcontractor while the
    defendants claim to be subrogated to the rights of the
    general contractor. These disparate interpretations are
    crucial to this appeal, since the first tier subcontractor,
    having been fully paid, has no right to which anyone
    could be subrogated, while the general contractor, as
    yet partially unpaid, remains a suitable candidate for
    subrogation. The parties are at odds both about the
    significance of the exact wording of § 49-33 and about
    its relationship to our existing case law.’’ (Citations
    omitted; footnote omitted.) 
    Id., 597–99. The
    court
    explained that a second tier subcontractor is subro-
    gated to the rights of the general contractor when the
    first tier subcontractor defaults after having been paid,
    leaving unpaid the second tier subcontractor. 
    Id., 603– 604.
    Our Supreme Court explained that it is significant
    that under our legislative scheme ‘‘all subcontractors
    are preferred to the general contractor if the lienable
    fund is inadequate to cover [all] outstanding claims.’’12
    
    Id., 605; see
    General Statutes § 49-36. When considering
    the plaintiff’s argument in Seaman that the court’s con-
    struction of § 49-33 would result in the ‘‘unjust enrich-
    ment of second tier subcontractors,’’ our Supreme
    Court stated the following: ‘‘How the risk of defaulting
    first tier subcontractors should be allocated between
    the owner and the general contractor is not an issue
    presently before us, although we observe that contrac-
    tors generally are deemed to make a number of implied
    warranties, including the warranty that there are no
    outstanding liens. Cf. Uniform Commercial Code §§ 2-
    312 and 3-417, General Statutes §§ 42a-2-312 and 42a-
    3-417.’’13 
    Id., 606. The
    significant difference between the facts in Sea-
    man and the facts in the present case is that the prop-
    erty owner in Seaman, after he received notice of the
    second tier subcontractors’ liens, retained the balance
    due to the nondefaulted general contractor, whereas,
    in the present case, the hospital, after it received notice
    of the plaintiff’s lien, continued to make payments to
    the nondefaulted general contractor, Skanska. The
    defendants argue that, pursuant to the language in §§ 49-
    33 (e) and (f) and 49-36, this fact makes all the difference
    because the lienable fund became exhausted when the
    hospital paid the full contract price to Skanska.
    In support of this argument, the defendants princi-
    pally rely on our Supreme Court’s decision in Rene Dry
    Wall Co. v. Strawberry Hill Associates, 
    182 Conn. 568
    ,
    
    438 A.2d 774
    (1980). In that case, the plaintiff subcon-
    tractor sought to foreclose a mechanic’s lien held
    against the defendant owner whose property was
    improved by the plaintiff’s work. 
    Id., 569. The
    defendant
    argued that it was excused from the obligation to pay
    the plaintiff because of good faith payments made to
    the general contractor before notice of the plaintiff’s
    lien and ‘‘because of expenditures reasonably incurred
    to complete the construction project after the general
    contractor’s default.’’ 
    Id. The court
    concluded that the
    issues in the case were framed by the relevant statutory
    provisions regarding mechanic’s liens. In particular, the
    court held that ‘‘General Statutes §§ 49-33 and 49-36
    . . . define and delimit the fund to which a properly
    noticed mechanic’s lien may attach. Both of these sec-
    tions start with the proposition that no mechanic’s lien
    may attach to any building or land in an amount greater
    than the price which the owner has agreed to pay to
    the general contractor for the building being erected
    or improved. This amount may be diminished to the
    extent that it exceeds ‘the reasonable cost . . . of satis-
    factory completion of the contract plus any damages
    resulting from . . . default for which [the general con-
    tractor] might be held liable to the owner.’ General
    Statutes § 49-33. The amount may be diminished further
    by ‘bona fide payments, as defined in section 49-36,
    made by the owner [to the general contractor] before
    receiving notice of [the mechanic’s] lien or liens.’ ’’
    (Footnotes omitted.) 
    Id., 571–72.14 The
    defendants argue that, applying the reasoning of
    Rene Dry Wall Co., the plaintiff cannot collect on the
    bond because the combination of the amounts paid by
    the hospital in good faith prior to notice of the plaintiff’s
    lien and the amounts paid to Skanska to complete the
    construction project equal the amount the hospital
    agreed to pay for the project. Thus, they argue, there
    is no lienable fund available to the plaintiff. The plaintiff
    argues in response that Rene Dry Wall Co. is distinguish-
    able and inapplicable to this case because Skanska was
    never in default of its contract with the hospital.
    According to the plaintiff, pursuant to § 49-33, an owner
    is entitled to credits against the lienable fund only for
    payments made after notice of a subcontractor’s lien
    when it is required to make such payments because of
    the general contractor’s default. We agree with the
    plaintiff.
    Section 49-33 provides in relevant part: ‘‘(e) A
    mechanic’s lien shall not attach . . . in favor of any
    subcontractor to a greater extent in the whole than the
    amount which the owner has agreed to pay to any
    person through whom the subcontractor claims subject
    to the provisions of section 49-36.
    ‘‘(f) Any such subcontractor shall be subrogated to
    the rights of the person through whom the subcontrac-
    tor claims, except that the subcontractor shall have a
    mechanic’s lien or right to claim a mechanic’s lien in
    the event of any default by that person subject to the
    provisions of sections 49-34, 49-35 and 49-36, provided
    the total of such lien or liens shall not attach . . . to
    a greater amount in the whole than the amount by which
    the contract price between the owner and the person
    through whom the subcontractor claims exceeds the
    reasonable cost, either estimated or actual, as the case
    may be, of satisfactory completion of the contract plus
    any damages resulting from such default for which that
    person might be held liable to the owner and all bona
    fide payments, as defined in section 49-36, made by the
    owner before receiving notice of such lien or liens.’’
    Section 49-36 provides in relevant part: ‘‘(a) No
    mechanic’s lien may attach . . . to a greater amount
    in the whole than the price which the owner agreed
    to pay for the building and its appurtenances or the
    development of any such lot, or the development of
    any such plot of land. . . .
    ‘‘(c) In determining the amount to which any lien or
    liens may attach . . . the owner of the [property] . . .
    shall be allowed whatever payments he has made, in
    good faith, to the original contractor or contractors,
    before receiving notice of the lien or liens. No payments
    made in advance of the time stipulated in the original
    contract may be considered as made in good faith,
    unless notice of intention to make the payment has
    been given in writing to each person known to have
    furnished materials or rendered services at least five
    days before the payment is made.’’ (Emphasis added.)
    The plaintiff argues that, under a proper reading of
    these statutes, when the general contractor is not in
    default, the lienable fund must be determined at the
    time the lien is filed and notice given to the property
    owner. The defendants argue that the plaintiff’s inter-
    pretation of the statutes ‘‘would create a perverse incen-
    tive by encouraging property owners to terminate the
    general contractor when a subcontractor gives notice
    of a lien in order to take advantage of the reduction
    for the cost to complete the work. In other words,
    because [the plaintiff’s] interpretation of the statute[s]
    would permit the lienable fund to be reduced when the
    general contractor defaults or is terminated, a property
    owner who otherwise had no intention to terminate the
    general contractor may do so after receiving notice of
    a lien in order to reduce the amount available to the
    lienor.’’ The defendants contend that the plain language
    of § 49-33 (f) ‘‘provides that the lienable fund is reduced
    by the cost to complete the contract, and that reduction
    applies whether or not the general contractor defaults.’’
    During oral argument before this court, the plaintiff
    explained that it believed that the defendants’ construc-
    tion of our statutory scheme regarding mechanic’s liens
    would lead to absurd results because a lien or a bond,
    specifically meant to protect the subcontractors, includ-
    ing second tier subcontractors, would be useless
    because a nondefaulted general contractor, after a prop-
    erly noticed lien had been filed by a subcontractor,
    could get paid fully, including profit, thereby exhausting
    the fund, and the subcontractors would be left with no
    secured claim, despite their preference in the statute.
    During questioning by the appellate panel, this court
    asked Skanska’s counsel whether a nondefaulted gen-
    eral contractor essentially could just ask for full pay-
    ment from the property owner in exchange for bonding
    off every subcontractor lien, including second tier sub-
    contractors, thereby reducing the lienable fund to zero
    and avoiding the preference in the statutes in favor of
    the subcontractors. Skanska’s counsel responded that
    the second tier subcontractors still could bring a claim
    against the party with whom they had a written con-
    tract, and, he argued, if the situation were similar to the
    present case, where ‘‘there’s a bad actor sub[contractor,
    then] somebody gets the short end of the stick . . . .’’
    We conclude that the defendants’ construction of our
    statutes is not only inconsistent with the language of
    the statutes, but it would lead to absurd results, incon-
    sistent with the legislative purpose of those statutes.
    Although in derogation of the common law, the reme-
    dial purpose of § 49-33 is to ‘‘furnish security for a
    contractor’s labor and materials . . . .’’ Seaman v. Cli-
    mate Control 
    Corp., supra
    , 
    181 Conn. 597
    . Pursuant to
    §§ 49-33 and 49-36, the amount of a mechanic’s lien may
    not exceed the price that the property owner has agreed
    to pay for the building being erected or improved, and
    the property owner is entitled to credit for payments
    it made in good faith to the general contractor before
    receipt of notice of such a lien. See 
    id., 596. If
    the
    contract price that was agreed on by the general con-
    tractor and the property owner is insufficient to cover
    all the liens, ‘‘claimants other than the original contrac-
    tor are to be paid first, and, if necessary, on a pro rata
    basis.’’ (Emphasis added.) Id.; see General Statutes § 49-
    36 (b). ‘‘[A]ll subcontractors are preferred to the general
    contractor if the lienable fund is inadequate to cover
    outstanding claims.’’ 
    Id., 605. ‘‘[I]f
    the owner still owes
    money to the general contractor when a second-tier
    subcontractor files a mechanic’s lien, the second-tier
    subcontractor can seek recovery from the owner even
    where the general contractor has made full payment to
    the first-tier subcontractor who hired the second-tier
    subcontractor.’’ (Emphasis added.) D. Rosengren, 13
    Connecticut Practice Series: Construction Law (2005)
    § 6:2, p. 125.
    ‘‘In [General Statutes (1918 Rev.) §] 5220 [(now § 49-
    36)], the opening provision clearly applies to all
    mechanics’ liens by whomsoever held, and provides
    that they shall not exceed the total which the owner
    was to pay under his contract. It then explicitly provides
    that the contractor’s own lien shall be subordinated
    to those of subcontractors, entitling them to payment
    before him, and if the available fund does not pay the
    subcontractor liens in full, the fund must be appor-
    tioned between them. The subcontractor’s right to a
    lien, though inchoate comes into existence when he
    begins furnishing materials . . . and becomes per-
    fected when he files his lien having complied with all
    statutory requirements. These rights which are given
    the subcontractor cannot be taken from him or abridged
    by act of the contractor or the owner.’’ (Citation omit-
    ted; emphasis added; internal quotation marks omitted.)
    Purcell, Inc. v. Libbey, 
    111 Conn. 132
    , 137, 
    149 A. 225
    (1930).
    The defendants contend that older case law is not
    controlling because there was an important change in
    our statutes that occurred in 1953; see Public Acts 1953,
    No. 502, § 1; that modified what is now § 49-33. They
    contend that No. 502 of the 1953 Public Acts ‘‘add[ed]
    the language in what is now . . . § 49-33 (f) providing
    that the amount available to subcontractors is reduced
    by the ‘reasonable cost . . . of satisfactory completion
    of the contract . . .’ ’’ and that this language applies
    ‘‘whether or not the general contractor defaults.’’ The
    legislative history of No. 502 of the 1953 Public Acts
    does not support the defendants’ position.
    In 1953, the House of Representatives introduced
    House Bill No. 1733, 1953 Sess., which ultimately
    became No. 502 of the 1953 Public Acts, modifying
    General Statutes (Cum. Supp. 1951) § 1273b (formerly
    General Statutes (1949 Rev.) § 7217), now § 49-33. In
    1953, the legislature added the language, ‘‘except that
    such subcontractor shall have such a lien or right to
    claim such a lien in the event of any default by such
    person . . . provided the total of such lien or liens
    shall not attach . . . to a greater amount in the whole
    than the amount by which the contract price between
    the owner and such person exceeds the reasonable cost
    . . . of satisfactory completion of the contract plus any
    damages resulting from such default for which such
    person might be held liable to the owner and all bona
    fide payments . . . made by the owner before receiv-
    ing notice of such liens or liens’’; see No. 502 of the
    1953 Public Acts; which remains a part of § 49-33 today,
    specifically, § 49-33 (f). The defendants contend that
    the legislature meant this language to apply even when
    the general contractor is not in default. The plaintiff
    contends that this language applies only when the gen-
    eral contractor is in default. In light of the legislative
    history of No. 502 of the 1953 Public Acts and the pur-
    pose for which it was enacted, we agree with the
    plaintiff.
    House Bill No. 1733 was introduced to correct a statu-
    tory problem that was uncovered by our Supreme Court
    in Rowley v. Salladin, 
    139 Conn. 642
    , 
    96 A.2d 219
    (1953).
    In Rowley, the general contractor had abandoned the
    project without paying the subcontractor, who then
    filed a mechanic’s lien. 
    Id., 644. The
    property owner
    argued that the subcontractor had no right to the lien
    because, pursuant to General Statutes (Cum. Supp.
    1951) § 1273b (now § 49-33), the subcontractor was sub-
    rogated only to the rights of the general contractor,
    who had no right to a lien because he had defaulted.
    
    Id. After construing
    the plain language of the statute,
    our Supreme Court agreed. 
    Id., 644–45. In
    response to Rowley, members of the legislature
    introduced House Bill No. 1733. Representative Kenyon
    W. Greene, in moving for acceptance of the bill,
    explained that it was introduced to ‘‘provid[e] [that] the
    subcontractor’s right of [a] mechanic’s lien shall not be
    lost by default of the general contractor . . . .’’ 5 H.R.
    Proc., Pt. 8, 1953 Sess., pp. 3313–14; see also Conn.
    Joint Standing Committee Hearings, Judiciary, Pt. 3,
    1953 Sess., pp. 760–63. Thus, what is now § 49-33 was
    amended to ensure that an owner could not use a gen-
    eral contractor’s default as an excuse not to pay a sub-
    contractor for work that benefitted the owner. At the
    same time, the amendment protected the owner who
    was forced to incur additional costs due to the general
    contractor’s default. There simply is nothing in the lan-
    guage or legislative history of the 1953 amendment that
    suggests that an owner is entitled to take credit for
    payments made to a general contractor not in default
    after having received notice of the subcontractor’s lien.
    In fact, such an interpretation would run contrary to
    the 1953 amendment’s intent to provide greater protec-
    tion to subcontractors.
    Prior to the 1953 amendment to what is now § 49-
    33, the only amounts the owner was entitled to credit
    against the lienable fund were ‘‘whatever payments he
    shall have made, in good faith, to the [general] contrac-
    tor or contractors before receiving notice of such lien
    or liens.’’ General Statutes (1949 Rev.) § 7220. The 1953
    amendment gave the owner an additional credit for any
    funds it had to pay after notice of the subcontractor’s
    lien, due to the general contractor’s default. Such pro-
    tection for the owner makes sense because, once the
    general contractor defaults, the owner would be forced
    to find someone else to complete the project and would
    be required to pay that third party for their work. Under
    that specific circumstance, the legislature chose to
    place the risk of the defaulting general contractor on
    the subcontractor and not the owner, to the extent the
    owner’s costs of completing the construction project
    equaled or exceeded the amount he had contracted to
    pay the general contractor. However, where the general
    contractor is not in default, there is no need to protect
    the owner by permitting it to continue to pay the general
    contractor at the expense of subcontractors who have
    filed valid mechanic’s liens on the owner’s property. The
    owner need only withhold payments from the general
    contractor until the subcontractor’s mechanic’s liens
    are resolved. There is no third party who was previously
    a stranger to the construction project that must be
    compensated for its work. In such a circumstance, the
    risk of not getting paid properly is placed on the general
    contractor, consistent with the preference in favor of
    subcontractors expressly set forth in § 49-36 (b). Put
    another way, expanding the language of § 49-33 to pay-
    ments made when the general contractor is not in
    default, as suggested by the defendants, would eviscer-
    ate the protections provided to subcontractors in § 49-
    36 (b) and (c).
    Furthermore, the defendants’ interpretation of the
    relevant statutes would lead to absurd results in that
    it would permit an owner and a general contractor to
    render a subcontractor’s lien essentially meaningless.
    The facts of this case show exactly how such a result
    can be accomplished. It is undisputed that at the time
    the plaintiff filed its mechanic’s lien there were more
    than sufficient funds still unpaid by the hospital to Skan-
    ska to cover the plaintiff’s claim. Rather than withhold-
    ing money from Skanska to pay any amounts duly owed
    to the plaintiff pursuant to its lien, the hospital paid the
    full contract amount to Skanska. Under the defendants’
    interpretation of § 49-33, doing so wiped out the lienable
    fund, and, with it, the plaintiff’s lien, and created a
    preference in favor of the general contractor at the
    expense of a subcontractor. Not only is there nothing
    in the language or legislative history of § 49-33 that
    remotely suggests such a result; the result is flatly con-
    trary to the preference in favor of subcontractors set
    forth in § 49-36 (b). We cannot conclude that the legisla-
    ture intended a result that is so completely at odds with
    the remedial purpose of the mechanic’s lien statutes.
    Finally, the defendants’ claim that the plaintiff’s read-
    ing of §§ 49-33 and 49-36 would lead to the perverse
    result that owners would be incentivized to find a rea-
    son to hold general contractors in default makes little
    sense. According to the defendants, an owner who has
    received notice of a mechanic’s lien from a subcontrac-
    tor would be motivated to manufacture a default by the
    general contractor in order to terminate the general
    contractor in order to reduce the size of the lienable
    fund available to the subcontractor. There are several
    problems with this hypothesis. First, it ignores what
    could be significant transaction costs the owner would
    incur by replacing a performing contactor with a new
    contractor unfamiliar with the project. Second, it
    ignores the fact that, by engaging in such conduct, the
    owner would expose itself to liability to the general
    contractor for breach of contract. Third, to the extent
    the owner concluded that it would be profitable to
    breach its contract with the general contractor, whether
    a subcontractor filed a mechanic’s lien likely would not
    change that conclusion. Finally, the defendants have
    not described a precise scenario that would lead an
    owner to manufacture a default by the general contrac-
    tor, and we cannot think of a scenario in which the
    owner would not be acting against its economic interest
    by terminating the general contractor simply to reduce
    the amount available to a subcontractor lienor. The
    amount available to the subcontractor lienor would only
    be reduced to the extent that the owner paid an amount
    equal to or greater than its contract price with the
    defaulted general contractor. It would defy logic for an
    owner to terminate a general contractor just so it can
    incur more costs to avoid paying the subcontractor
    lienor.
    On the basis of the foregoing analysis, we conclude
    that the lienable fund was the amount owed by the
    hospital to Skanska at the time the plaintiff gave notice
    of its mechanic’s lien to the hospital in accordance
    with §§ 49-34 and 49-35. Accordingly, the defendants’
    alternative ground for affirmance fails.
    The judgment is reversed with respect to counts two
    and three of the plaintiff’s complaint, and the case is
    remanded to the trial court for further proceedings
    according to law; the judgment is affirmed in all
    other respects.
    In this opinion the other judges concurred.
    1
    The plaintiff withdrew the matter as to the named defendant, The Stam-
    ford Hospital. Fidelity is the surety that issued a bond in substitution for
    the mechanic’s lien that the plaintiff had filed against the hospital. See
    General Statutes §§ 49-33 and 49-37.
    2
    Semac Electrical Company, Inc. (Semac), also is a defendant in this
    matter. Although Semac initially had appeared by counsel in the trial court,
    the court, on December 12, 2017, granted counsel’s motion for permission
    to withdraw its appearance. No further action appears to have been taken
    against Semac, who now is a nonappearing defendant, and the matter
    remains pending as to Semac in the trial court. For purposes of this appeal,
    we refer to Skanska and Fidelity as the defendants unless further clarification
    is necessary.
    3
    The court also rendered summary judgment in favor of Skanska as to
    count one of the plaintiff’s complaint, which alleged that Skanska had
    breached a contract with the plaintiff. The plaintiff does not challenge that
    judgment in this appeal. Thus, we affirm the judgment in favor of Skanska
    as to count one.
    4
    Although Skanska had alleged in its answer that it fully had paid Semac
    for the plaintiff’s work, Miller made no such attestation in his affidavit. In
    fact, he averred that ‘‘[t]he total amount paid to the replacement electrical
    contractors exceeded the remaining amount of the original subcontract
    with Semac.’’ (Emphasis added.)
    5
    Because we conclude that there is a genuine issue of material fact as
    to whether Skanska ever paid for the plaintiff’s services, we need not address
    whether the plaintiff could prevail on its claim in the event that Skanska
    fully had paid Semac for the plaintiff’s work, if the plaintiff proves that
    Skanska, despite such payment, had requested that the plaintiff continue
    performing work on the project. We also need not determine whether there
    are additional issues of material fact that rendered summary judgment inap-
    propriate.
    6
    General Statutes § 49-33 provides in relevant part: ‘‘(a) If any person has
    a claim for more than ten dollars for materials furnished or services rendered
    in the construction, raising, removal or repairs of any building or any of its
    appurtenances or in the improvement of any lot or in the site development
    or subdivision of any plot of land, and the claim is by virtue of an agreement
    with or by consent of the owner of the land upon which the building is
    being erected or has been erected or has been moved, or by consent of the
    owner of the lot being improved or by consent of the owner of the plot of
    land being improved or subdivided, or of some person having authority from
    or rightfully acting for the owner in procuring the labor or materials, the
    building, with the land on which it stands or the lot or in the event that the
    materials were furnished or services were rendered in the site development
    or subdivision of any plot of land, then the plot of land, is subject to the
    payment of the claim. . . .
    ‘‘(e) A mechanic’s lien shall not attach to any such building or its appurte-
    nances or to the land on which the same stands or to any lot or to any plot
    of land, in favor of any subcontractor to a greater extent in the whole than
    the amount which the owner has agreed to pay to any person through whom
    the subcontractor claims subject to the provisions of section 49-36.
    ‘‘(f) Any such subcontractor shall be subrogated to the rights of the person
    through whom the subcontractor claims, except that the subcontractor shall
    have a mechanic’s lien or right to claim a mechanic’s lien in the event of
    any default by that person subject to the provisions of sections 49-34, 49-
    35 and 49-36, provided the total of such lien or liens shall not attach to any
    building or its appurtenances, or to the land on which the same stands or
    to any lot or to any plot of land, to a greater amount in the whole than the
    amount by which the contract price between the owner and the person
    through whom the subcontractor claims exceeds the reasonable cost, either
    estimated or actual, as the case may be, of satisfactory completion of the
    contract plus any damages resulting from such default for which that person
    might be held liable to the owner and all bona fide payments, as defined
    in section 49-36, made by the owner before receiving notice of such lien or
    liens. . . .’’
    General Statutes § 49-36 provides in relevant part: ‘‘(a) No mechanic’s
    lien may attach to any building or its appurtenances, or to the land on which
    the same stands, or any lot, or any plot of land, in favor of any person, to
    a greater amount in the whole than the price which the owner agreed to
    pay for the building and its appurtenances or the development of any such
    lot, or the development of any such plot of land. . . .
    ‘‘(c) In determining the amount to which any lien or liens may attach
    upon any land or building, or lot or plot of land, the owner of the land or
    building or lot or plot of land shall be allowed whatever payments he has
    made, in good faith, to the original contractor or contractors, before receiving
    notice of the lien or liens. No payments made in advance of the time stipu-
    lated in the original contract may be considered as made in good faith,
    unless notice of intention to make the payment has been given in writing
    to each person known to have furnished materials or rendered services at
    least five days before the payment is made.’’
    General Statutes § 49-37 provides in relevant part: ‘‘(a) Whenever any
    mechanic’s lien has been placed upon any real estate pursuant to sections
    49-33, 49-34 and 49-35, the owner of that real estate, or any person interested
    in it, may make an application to any judge of the Superior Court that the
    lien be dissolved upon the substitution of a bond with surety, and the judge
    shall order reasonable notice to be given to the lienor of the application.
    . . .’’
    7
    Pursuant to Practice Book § 63-4, Skanska and Fidelity submitted this
    argument as an alternative ground for affirmance.
    8
    We note that the lien statutes referenced in Seaman v. Climate Control
    
    Corp., supra
    , 
    181 Conn. 592
    , are from the 1979 revision of the General
    Statutes. Although several of those statutes have been amended by the
    legislature since our Supreme Court’s decision in Seaman, those amend-
    ments have no bearing on the merits of this appeal.
    9
    General Statutes § 49-34 provides: ‘‘A mechanic’s lien is not valid unless
    the person performing the services or furnishing the materials (1) within
    ninety days after he has ceased to do so, lodges with the town clerk of the
    town in which the building, lot or plot of land is situated a certificate in
    writing, which shall be recorded by the town clerk with deeds of land, (A)
    describing the premises, the amount claimed as a lien thereon, the name
    or names of the person against whom the lien is being filed and the date
    of the commencement of the performance of services or furnishing of materi-
    als, (B) stating that the amount claimed is justly due, as nearly as the same
    can be ascertained, and (C) subscribed and sworn to by the claimant, and
    (2) not later than thirty days after lodging the certificate, serves a true and
    attested copy of the certificate upon the owner of the building, lot or plot
    of land in the same manner as is provided for the service of the notice in
    section 49-35.’’
    10
    General Statutes § 49-35 provides in relevant part: ‘‘(a) No person other
    than the original contractor . . . or a subcontractor whose contract with
    the original contractor is in writing and has been assented to in writing by
    the other party to the original contract, is entitled to claim any such mechan-
    ic’s lien, unless, after commencing, and not later than ninety days after
    ceasing, to furnish materials or render services for such construction . . .
    such person gives written notice to the owner of the building, lot or plot
    of land and to the original contractor that he or she has furnished or com-
    menced to furnish materials, or rendered or commenced to render services,
    and intends to claim a lien therefor on the building, lot or plot of land;
    provided an original contractor shall not be entitled to such notice, unless,
    not later than fifteen days after commencing the construction . . . such
    original contractor lodges with the town clerk of the town in which the
    building, lot or plot of land is situated an affidavit in writing, which shall
    be recorded by the town clerk with deeds of land, (1) stating the name
    under which such original contractor conducts business, (2) stating the
    original contractor’s business address, and (3) describing the building, lot
    or plot of land. . . .
    ‘‘(b) No subcontractor, without a written contract complying with the
    provisions of this section, and no person who furnishes material or renders
    services by virtue of a contract with the original contractor or with any
    subcontractor, may be required to obtain an agreement with, or the consent
    of, the owner of the land, as provided in section 49-33, to enable him to
    claim a lien under this section.’’
    11
    Our Supreme Court explained in H & S Torrington Associates that the
    enactment of the notice requirement set forth in § 49-34 ‘‘was intended to
    protect the due process rights of property owners who would not otherwise
    have actual notice of the recorded lien.’’ H & S Torrington Associates v.
    Lutz Engineering 
    Co., supra
    , 
    185 Conn. 554
    . It also explained that the
    enactment of the notice requirement set forth in § 49-35 ‘‘was concerned
    with the protection of the owner of the property, who might not otherwise
    know what, if any, subcontractors the principal contractor had employed
    . . . so that payments to the main contractor may be withheld . . . .’’
    (Citations omitted; emphasis added; internal quotation marks omitted.) 
    Id. A subcontractor
    may satisfy simultaneously in one document the notice
    requirements of both §§ 49-34 and 49-35. 
    Id., 555. ‘‘Two
    separate notices are
    not necessary to accomplish the purpose of the statutes.’’ 
    Id. 12 The
    legislature’s desire to protect the rights of subcontractors, further
    is demonstrated by the enactment of NO. 99-153 of the 1999 Public Acts
    (P.A. 99-153), codified at General Statutes § 42-158l. In § 4 of P.A. 99-153,
    the legislature ‘‘placed substantial restrictions on a party’s right to include
    lien waivers in construction contracts.’’ D. Rosengren, 13 Connecticut Prac-
    tice Series: Construction Law (2005) § 6:8, p. 140. Furthermore, ‘‘it is well
    settled that the general contractor cannot bargain away the lien rights of
    subcontractors and materialmen who: (1) are not themselves privy to the
    general contractor’s agreement containing the waiver; (2) do not agree with
    the general contractor to waive their lien right; or (3) do not adopt the
    lien waiver provision as incorporated in the contract between the general
    contractor and the owner.’’ 
    Id., pp. 141–42.
       Subsection (a) of § 42-158l provides: ‘‘Any provision in a construction
    contract or any periodic lien waiver issued pursuant to a construction con-
    tract that purports to waive or release the right of a contractor, subcontractor
    or supplier engaged to perform services, perform labor or furnish materials
    under the construction contract to (1) claim a mechanic’s lien, or (2) make
    a claim against a payment bond, for services, labor or materials which have
    not yet been performed and paid for shall be void and of no effect.’’
    13
    General Statutes § 42a-2-312 provides: ‘‘(1) Subject to subsection (2)
    there is in a contract for sale a warranty by the seller that (a) the title
    conveyed shall be good, and its transfer rightful; and (b) the goods shall be
    delivered free from any security interest or other lien or encumbrance of
    which the buyer at the time of contracting has no knowledge.
    ‘‘(2) A warranty under subsection (1) will be excluded or modified only
    by specific language or by circumstances which give the buyer reason to
    know that the person selling does not claim title in himself or that he is
    purporting to sell only such right or title as he or a third person may have.
    ‘‘(3) Unless otherwise agreed a seller who is a merchant regularly dealing
    in goods of the kind warrants that the goods shall be delivered free of the
    rightful claim of any third person by way of infringement or the like but a
    buyer who furnishes specifications to the seller must hold the seller harmless
    against any such claim which arises out of compliance with the specifi-
    cations.’’
    General Statutes § 42a-3-417, as amended by No. 91-304 of the 1991 Public
    Acts, provides: ‘‘(a) If an unaccepted draft is presented to the drawee for
    payment or acceptance and the drawee pays or accepts the draft, (i) the
    person obtaining payment or acceptance, at the time of presentment, and
    (ii) a previous transferor of the draft, at the time of transfer, warrant to the
    drawee making payment or accepting the draft in good faith that: (1) The
    warrantor is, or was, at the time the warrantor transferred the draft, a person
    entitled to enforce the draft or authorized to obtain payment or acceptance
    of the draft on behalf of a person entitled to enforce the draft; (2) the draft
    has not been altered; and (3) the warrantor has no knowledge that the
    signature of the drawer of the draft is unauthorized.
    ‘‘(b) A drawee making payment may recover from any warrantor damages
    for breach of warranty equal to the amount paid by the drawee less the
    amount the drawee received or is entitled to receive from the drawer because
    of the payment. In addition, the drawee is entitled to compensation for
    expenses and loss of interest resulting from the breach. The right of the
    drawee to recover damages under this subsection is not affected by any
    failure of the drawee to exercise ordinary care in making payment. If the
    drawee accepts the draft, breach of warranty is a defense to the obligation
    of the acceptor. If the acceptor makes payment with respect to the draft,
    the acceptor is entitled to recover from any warrantor for breach of warranty
    the amounts stated in this subsection.
    ‘‘(c) If a drawee asserts a claim for breach of warranty under subsection
    (a) based on an unauthorized endorsement of the draft or an alteration of
    the draft, the warrantor may defend by proving that the endorsement is
    effective under section 42a-3-404 or 42a-3-405 or the drawer is precluded
    under section 42a-3-406 or 42a-4-406 from asserting against the drawee the
    unauthorized endorsement or alteration.
    ‘‘(d) If (i) a dishonored draft is presented for payment to the drawer or
    an endorser or (ii) any other instrument is presented for payment to a party
    obliged to pay the instrument, and (iii) payment is received, the following
    rules apply: (1) The person obtaining payment and a prior transferor of the
    instrument warrant to the person making payment in good faith that the
    warrantor is, or was, at the time the warrantor transferred the instrument,
    a person entitled to enforce the instrument or authorized to obtain payment
    on behalf of a person entitled to enforce the instrument. (2) The person
    making payment may recover from any warrantor for breach of warranty
    an amount equal to the amount paid plus expenses and loss of interest
    resulting from the breach.
    ‘‘(e) The warranties stated in subsections (a) and (d) cannot be disclaimed
    with respect to checks. Unless notice of a claim for breach of warranty is
    given to the warrantor within thirty days after the claimant has reason to
    know of the breach and the identity of the warrantor, the liability of the
    warrantor under subsection (b) or (d) is discharged to the extent of any
    loss caused by the delay in giving notice of the claim.
    ‘‘(f) A cause of action for breach of warranty under this section accrues
    when the claimant has reason to know of the breach.’’
    14
    We note that § 49-33, referenced in Rene Dry Wall Co. v. Strawberry
    Hill 
    Associates, supra
    , 
    182 Conn. 568
    , is from the 1979 revision of the General
    Statutes. Although § 49-33 has been amended by the legislature since our
    Supreme Court’s decision in Rene Dry Wall Co., those amendments have
    no bearing on the merits of this appeal.