New Milford v. Standard Demolition Services, Inc. ( 2022 )


Menu:
  • ***********************************************
    The “officially released” date that appears near the be-
    ginning of each opinion is the date the opinion will be pub-
    lished in the Connecticut Law Journal or the date it was
    released as a slip opinion. The operative date for the be-
    ginning of all time periods for filing postopinion motions
    and petitions for certification is the “officially released”
    date appearing in the opinion.
    All opinions are subject to modification and technical
    correction prior to official publication in the Connecticut
    Reports and Connecticut Appellate Reports. In the event of
    discrepancies between the advance release version of an
    opinion and the latest version appearing in the Connecticut
    Law Journal and subsequently in the Connecticut Reports
    or Connecticut Appellate Reports, the latest version is to
    be considered authoritative.
    The syllabus and procedural history accompanying the
    opinion as it appears in the Connecticut Law Journal and
    bound volumes of official reports are copyrighted by the
    Secretary of the State, State of Connecticut, and may not
    be reproduced and distributed without the express written
    permission of the Commission on Official Legal Publica-
    tions, Judicial Branch, State of Connecticut.
    ***********************************************
    TOWN OF NEW MILFORD v. STANDARD
    DEMOLITION SERVICES, INC.
    (AC 43874)
    Bright, C. J., and Elgo and Bear, Js.
    Syllabus
    The plaintiff town sought to recover damages from the defendant contractor
    for breach of contract. The plaintiff owned a vacant brass mill factory
    that was contaminated with, inter alia, polychlorinated biphenyls
    (PCBs). The plaintiff, on the advice of consultants, applied to the United
    States Environmental Protection Agency (EPA) for permission to demol-
    ish and clean up the property and engage contractors to perform the
    work. The plaintiff issued a notice inviting prospective contractors to
    provide bids for the third phase of the project, which involved the
    demolition, abatement and remediation of the property. The notice indi-
    cated that the contractor would be allowed to keep the scrap value of
    any structural steel salvaged from the site. The plaintiff made all public
    information about the project available to prospective bidders, including
    a report from one of its consultants that referenced the presence of
    PCBs throughout the building. The plaintiff also provided a letter to all
    prospective bidders clarifying that the selected contractor would be
    responsible for the sampling and disposal of any PCB contaminated
    material. The defendant submitted the winning bid for the contract, in
    which it did not allocate any funds for the remediation or disposal of
    any contaminated structural steel on the site, as it believed that the
    steel was not contaminated and could be recycled without remediation.
    Once selected, the defendant executed a certification acknowledging
    that it had read and agreed to abide by all conditions set forth in the
    EPA’s approval letter for the third phase of the project, which included
    attachments regarding the cleanup of PCB contaminated material and
    correspondence between the EPA and the plaintiff regarding the PCB
    contamination of various materials, including steel beams. The parties
    then entered into a contract for the phase three work, which expressly
    incorporated the EPA approval letter and established a 140 day deadline
    for the defendant to complete the job. Two months after the plaintiff
    had issued the defendant a notice to proceed, the defendant still had
    not obtained EPA approval of its contractor work plan, which was
    required before it could begin any substantial demolition work, and it
    had become engaged in a dispute with the plaintiff regarding the testing
    and disposal of the structural steel on the property. The defendant
    contended that the plaintiff mischaracterized the steel, leading it to
    believe that the steel was not contaminated and could be disposed of
    without remediation. The defendant claimed that it remained ready, able
    and willing to perform the work on the project, but it refused to do so
    if it was required to sample the steel to determine whether it was
    contaminated and told the plaintiff that it had accidentally executed the
    contract, as it had submitted its bid without information regarding the
    contamination of the steel or knowledge that the disposal of any contami-
    nated steel would be its responsibility. Thereafter, the plaintiff sent a
    letter to the defendant, notifying the defendant that it was in default
    because, inter alia, it would not be able to timely complete its work
    under the contract and had anticipatorily breached various provisions
    of the contract, and, consequently, its employment was terminated. The
    plaintiff rebid the project and hired C Co. to complete the work on the
    site, including the testing and disposal of the structural steel. C Co. was
    unable to finish its work, however, due in part to the increased expense
    and time required to finish the project as a result of the defendant’s
    intervention, which led to additional testing requirements imposed by
    both the EPA and the trial court. The trial court found that the plaintiff
    had established its claim for breach of contract and had suffered dam-
    ages, limited to the liquidated damages provision of the contract, in an
    amount equal to 254 days, less the retainage held by the plaintiff. The
    defendant appealed, and the plaintiff cross-appealed, claiming that the
    trial court erred in its award of damages. Held:
    1. The defendant’s claim that the trial court misapplied state and federal
    environmental laws was belied by the trial court’s findings, which were
    supported by the record: the defendant did not raise before the trial
    court, nor did the trial court address, the defendant’s claims that the
    plaintiff lacked proper authorization from the EPA to work on the undis-
    closed waste at the site or that the plaintiff and the trial court disregarded
    certain statutory (§ 22a-467) requirements relating to the disposal of
    PCB contaminated material, and, accordingly, this court declined to
    address those claims; moreover, the defendant’s claims that the plaintiff
    failed to adequately characterize the site and that the plaintiff was
    required under the contract to paint chip test the steel beams prior to
    the defendant performing any work at the site lacked merit, as the trial
    court found that the contract did not require paint chip testing, that the
    testimony of the plaintiff’s expert witnesses that paint chip sampling
    under such circumstances was not customary was credible, that there
    was no express statement in the contract that the steel was not contami-
    nated, that the plaintiff performed its obligations under the contract, and
    that the contract overwhelmingly placed the obligation for the testing,
    handling and processing of the material on the site on the defendant
    and expressly made clear that the risk of the condition of the materials
    being different than anticipated was solely on the defendant, and such
    findings were supported by the clear and unambiguous provisions of
    the contract and the documents related thereto; furthermore, this action
    involved a breach of contract claim, and the defendant failed to provide
    a clear explanation as to how its claims concerning the EPA regulations
    circumvented the trial court’s findings regarding the contract and failed
    to raise at trial its claims that the plaintiff’s conduct constituted a viola-
    tion of the EPA regulations and that the trial court erred in failing to
    find such a violation; additionally, although the defendant may have
    made its bid and entered the contract on the basis of a mistaken basic
    assumption, neither the trial court nor this court was permitted to rewrite
    the contract or to relieve the defendant of its obligations thereunder,
    as the defendant was a sophisticated and experienced party with respect
    to the type of work covered by the contract, it had the opportunity to
    address any issues it had with the proposed terms and interpretation
    of the contract prior to its execution, and the circumstances of the
    contract formation were not unconscionable.
    2. This court declined to review the defendant’s claim that the trial court
    erred in finding that the contract was not impossible to perform: because
    the defendant failed to plead impossibility as a special defense, such
    issue was not properly before the trial court, which, accordingly, did
    not undertake the necessary analysis of such claim nor did it make any
    findings thereon, and, as a result, the trial court could not have erred
    in failing to find that the defendant’s performance under the contract
    was impossible; moreover, it was incumbent on the defendant to seek
    an articulation of the trial court’s decision as to its failure to make a
    finding on a claim that the defendant alleged was properly before the
    trial court, and, in the absence of such an articulation, the record was
    inadequate for this court to review the claim.
    3. The defendant’s challenge to the trial court’s implicit determination that
    the plaintiff lawfully had terminated the contract was unavailing: the
    defendant’s claim was premised on a faulty assumption, namely, that
    the plaintiff was in default under the contract, because the trial court
    expressly found that the plaintiff had performed its obligations under
    the contract and that there was ample evidence of the defendant’s breach
    of its obligations under the contract, which findings were supported by
    the record.
    4. The defendant’s claim that the change orders granted to C Co. in connec-
    tion with additional paint chip testing requirements imposed by the
    EPA—which were not a part of the defendant’s contract with the plain-
    tiff—constituted an admission by the plaintiff that its contract with the
    defendant could not have been performed without such testing was
    contrary to the record and unavailing: the defendant’s argument failed
    to acknowledge the basis for the change orders sought by C Co., namely,
    that the trial court found that the plaintiff was not required to conduct
    paint chip sampling under the contract with the defendant because the
    EPA did not require such testing until after the plaintiff had terminated
    that contract, as the requirement was instituted as a result of the defen-
    dant’s unilaterally contacting the EPA with respect to the paint chip
    sampling it had conducted on the site as part of this litigation; moreover,
    such finding was supported by the record and was not clearly erroneous.
    5. Although the amount of the trial court’s award of liquidated damages was
    proper, that court erroneously failed to determine whether the plaintiff
    proved that it had suffered any compensable actual or consequential
    nondelay damages:
    a. The trial court improperly determined that liquidated damages were
    the plaintiff’s exclusive remedy under the contract: the language in the
    liquidated damages provision clearly applied to damages resulting from
    delay, there was no language in the contract expressly stating that such
    damages were the plaintiff’s exclusive remedy for a breach unrelated to
    the defendant’s delay in performance, and to interpret liquidated damages
    as the plaintiff’s sole remedy would render the contract’s damages and
    losses provision superfluous; accordingly, the trial court erroneously
    failed to determine whether the plaintiff proved that it had suffered any
    compensable actual or consequential nondelay damages and, if so, the
    amount of such damages, and, as a result, the case was remanded to
    the trial court for a new hearing in damages.
    b. The trial court did not err in limiting the award of liquidated damages
    to 254 days: the plaintiff’s claim on appeal that liquidated damages instead
    should have run through the date of the trial court’s decision failed, as
    the plaintiff did not make such a request at trial and the premise of
    such claim no longer existed because it was based on the trial court’s
    determination that liquidated damages were the plaintiff’s exclusive rem-
    edy under the contract, which this court concluded was made in error.
    Argued November 30, 2021—officially released April 26, 2022
    Procedural History
    Action to recover damages for breach of contract,
    and for other relief, brought to the Superior Court in
    the judicial district of Litchfield, where the defendant
    filed a counterclaim; thereafter, the matter was tried
    to the court, Shaban, J.; judgment for the plaintiff on
    the complaint and on the counterclaim, from which the
    defendant appealed and the plaintiff cross appealed to
    this court. Reversed in part; further proceedings.
    Raymond A. Garcia, with whom were Nyle K. Davey,
    and, on the brief, Lauren Lyngholm Crowe and Jona-
    than A. Krumeich, for the appellant-cross appellee
    (defendant).
    John D. Tower, with whom was Graham W. Moller,
    for the appellee-cross appellant (plaintiff)
    Opinion
    BEAR, J. The defendant, Standard Demolition Ser-
    vices, Inc., appeals from the judgment of the trial court
    rendered in favor of the plaintiff, the town of New
    Milford, on the plaintiff’s complaint for breach of a
    contract entered into by the parties and as to all counts
    of a counterclaim filed by the defendant. On appeal,
    the defendant claims that (1) the court misapplied state
    and federal environmental regulations, (2) the court
    erred in not finding that the contract was impossible
    to perform, (3) the court improperly determined that
    the plaintiff lawfully had terminated the contract,1 and
    (4) evidence of certain change orders executed by the
    plaintiff in connection with a subsequent contract with
    a different contractor, pursuant to which the plaintiff
    had agreed to modify terms of that contract, constituted
    admissions that the plaintiff’s contract with the defen-
    dant was defective and could not be performed by the
    defendant as written. The plaintiff has cross appealed,
    claiming that the court erred in its award of damages
    to the plaintiff. We affirm the judgment of the court in
    favor of the plaintiff on its complaint for breach of
    contract and as to all counts of the defendant’s counter-
    claim, but we reverse it in part with respect to the award
    of damages and remand the case for a new hearing in
    damages.
    At the trial of this matter, which spanned over twenty-
    two days, the parties testified, presented lay and expert
    witnesses, and submitted 273 documents into evidence.
    In a comprehensive memorandum of decision, the
    court, Shaban, J., found the following facts: ‘‘The plain-
    tiff is the owner of an industrial property located at 12
    Scovill Street in New Milford, which it acquired through
    a tax foreclosure in 1999. The property consists of fifty-
    three acres [and] includes an approximately 315,000
    square foot vacant brass mill factory contaminated with
    polychlorinated biphenyls (PCBs) and asbestos con-
    taining materials . . . . The plaintiff renamed the site
    the ‘Century Enterprise Center’ and hired consultants
    to help evaluate the environmental hazards on the site.
    Under the guidance of the consultants, the plaintiff
    made decisions about how it would apply to the United
    States Environmental Protection Agency (EPA) for per-
    mission to demolish and clean up the property and
    engage contractors to perform the work.
    ‘‘Prior to its involvement with the defendant, the
    plaintiff had already completed two phases of the work
    in its effort to clean up the property. In phases I and
    II of the project, the plaintiff’s consultants, Tighe &
    Bond, had characterized the structural steel on the site
    as ‘non-porous.’2 The EPA approved the work proposed
    by the plaintiff through its consultants for phases I and
    II and it was completed. For phase III of the project,
    the demolition, abatement, and remediation work, the
    plaintiff hired TRC Environmental Corporation (TRC)
    as its consultant and project manager. In performing
    its evaluation of the site, TRC reviewed and relied on
    the findings of the prior consultants from the phase I
    and II portions of the project. During the earlier phases,
    there had been extensive communication between the
    prior consultants and the EPA about the project. TRC
    found that the work had been allowed to proceed as
    proposed and that wipe sampling of ‘porous’ surfaces
    had been done.3 In 2015, after TRC set the scope of
    work for phase III, the plaintiff applied for and secured
    a $2.5 million grant from the Department of Economic
    and Community Development . . . for the project.
    ‘‘Thereafter, the plaintiff issued a Notice to Bidders
    [notice] inviting prospective contractors to provide bids
    for the demolition, abatement, and remediation of the
    property based on the proposed plan developed by TRC.
    . . . Bid packages were made available to all of the
    prospective bidders as part of the notice, which
    included the proposed contract documents.4 The docu-
    ments were also available through an on-line website.
    The notice recited that additional documents were
    available for review in a public reading room at the
    New Milford Public Works facility. Electronic thumb
    drives were also made available that included all histori-
    cal records, plans, drawings, studies, and other relevant
    information from phases I and II. . . . The bid forms
    provided to the prospective contractors included a line
    item for the scrap value of the structural steel [that]
    the contractor would be allowed to keep. All of the
    public information in the plaintiff’s possession regard-
    ing all three phases of the project, including correspon-
    dence with the EPA, was made available to prospective
    bidders for inspection and review. This included a facil-
    ity investigation document prepared by Tighe & Bond
    that referenced the presence of PCBs throughout the
    building’s interior that had likely been spread through
    dust. . . . This also included an engineering evalua-
    tion/cost analysis relative to the interior of the building.
    . . . On May 26, 2015, a mandatory prebid meeting was
    held by the plaintiff with the prospective bidders. . . .
    Following that meeting, on June 2, 2015, the plaintiff
    held an open house and walk-through at the site for all
    prospective bidders. . . . The defendant attended the
    open house and physically viewed the site. Both prior
    to and following the meeting and open house, and prior
    to the submission of its bid, the defendant submitted
    to the plaintiff multiple requests for information about
    the project to which the plaintiff responded. . . .
    ‘‘In addition, the plaintiff invited all potential bidders
    to submit in writing any questions they may have had
    about the project. By letter of June 12, 2015, the plaintiff
    provided all potential bidders with the responses to a
    list of those questions that had been submitted as of
    June 10, 2015, in a document described as ‘Clarification
    No. 1.’ . . . Several questions dealt with the sampling
    and disposal of PCB contaminated materials. The funda-
    mental response to each of these questions was that the
    contractor selected for the project would be responsible
    for the sampling and disposal of all such materials. The
    plaintiff conveyed that its only obligation was to do
    verification sampling of items left on-site after the job
    was completed. . . .
    ‘‘On June 15, 2015, following completion of its inquir-
    ies and review of the bid specifications, the defendant
    submitted its bid in the amount of $2,713,950 on the
    forms supplied by the plaintiff, which included Clarifi-
    cations Nos. 1 and 2 as addenda. . . . The defendant’s
    bid did not provide for the remediation, abatement, and
    disposal of the contaminated structural steel on the site
    based on its belief that the information made available
    by the plaintiff represented or implied that the struc-
    tural steel was not contaminated and could be recycled
    without remediation. . . .
    ‘‘By letter of July 16, 2015, the plaintiff notified the
    defendant that it was the successful bidder. . . . On
    September 1, 2015, the EPA issued a five page approval
    letter authorizing the plaintiff to move forward with
    phase III of the project subject to the conditions set
    forth in the letter. . . . At the time of its bid, the defen-
    dant was aware that the EPA could impose additional
    conditions on the work to be done beyond those set
    forth in the proposed contract. Paragraph 13 of the
    approval letter provides: ‘The PCB cleanup standard
    for porous surfaces (i.e., concrete) and soil shall be
    less than or equal to . . . 1 part per million (‘‘ppm’’)
    for unrestricted use or disposal. The PCB cleanup stan-
    dard for non-porous surfaces (e.g., overhead cranes,
    steel beams) shall be less than . . . 10 µ/100 cm for
    unrestricted disposal and/or recycling. (a) PCB contam-
    inated wastes shall be removed and disposed of as
    detailed in the [attached Administrative Record], except
    as follows . . . (ii) Steel beams shall be disposed of
    as a [greater than or equal to] 50 ppm PCB waste or
    alternatively shall be sampled to determine PCB dis-
    posal requirements [and] (iii) If samples are collected,
    sampling analytical results and proposed waste disposal
    details shall be submitted to [the] EPA for review prior
    to removal of these wastes from the [s]ite.’ . . . The
    EPA’s definition of the steel beams as non-porous was
    consistent with the definition that had been given by
    Tighe & Bond in phase II of the project. . . .
    ‘‘The EPA’s letter was accompanied by two attach-
    ments, the first of which set forth the ‘PCB Cleanup
    and Disposal Approval Conditions,’ and the second of
    which was identified as the ‘Administrative Record
    (Notification).’ . . . Paragraph 11 (a) [of attachment
    one] required the plaintiff to provide to the EPA ‘a
    certification signed by its selected abatement/demoli-
    tion contractor [the defendant], stating that the contrac-
    tor(s) has read and understands the Notification, and
    agrees to abide by the conditions specified in this
    [a]pproval . . . .’
    ‘‘Attachment [two] consists of a series of documents
    and correspondence reviewed by the EPA prior to the
    issuance of its approval . . . [some of which included]
    discussions of PCB contamination of various materials
    including overhead cranes and steel beams. Also, § 5.8
    of the phase I PCB Source Removal Notification dated
    December, 2004, prepared by Tighe & Bond references
    PCB wipe sample test results for nonporous materials
    such as building interior walls and beams. . . .
    ‘‘In its September 1, 2015 approval letter, the EPA
    noted that ‘[a]ttachment [two] provides a list of support-
    ing information for the [p]hase III project . . . which
    [the] EPA considered for this [a]pproval. All submittals
    in their entirety are considered ‘‘the Notification.’’’ . . .
    The next day, September 2, 2015, the plaintiff forwarded
    by e-mail a copy of the approval letter to the defendant.
    . . . That e-mail had appended to it all of the materials
    making up the attachments to the approval letter. In
    the e-mail, Michael Zarba . . . the public works direc-
    tor for the plaintiff, asked that the defendant review
    the materials and let him know as soon as possible if
    there were any questions. . . . In response, the defen-
    dant sent by e-mail a letter dated September 3, 2015,
    which was the certification relative to the ‘Notification’
    that was required by the approval letter. . . . The letter
    expressly states that ‘[the defendant] has read and
    understands the ‘‘Self-Implementing On-site Cleanup &
    Disposal Plan,’’ dated January, 2015, prepared for the
    [plaintiff] for the Century Enterprise Center project.
    [The defendant] agrees to abide by all aspects of the
    conditions specified in the EPA approval.’ . . . This
    included compliance with EPA regulations under 
    40 C.F.R. § 761
     relative to the removal and abatement of
    PCBs. The defendant did not raise any questions as to
    the materials submitted or the conditions of the
    approval letter. Thereafter, on September 4, 2015, the
    parties executed a highly extensive and detailed con-
    tract for the work on the project that expressly incorpo-
    rated the approval letter. . . .
    ‘‘Following receipt of the certification letter and the
    execution of the contract, the plaintiff issued to the
    defendant a letter dated September 14, 2015, which
    constituted a ‘Notice to Proceed’ as required by the
    terms of the contract. . . . That notice directed the
    defendant to commence work on the project and
    reminded the defendant that pursuant to the terms of
    the contract it had 140 calendar days to complete the
    job, thereby creating a deadline of February 1, 2016.
    Thereafter, the defendant commenced work on the proj-
    ect, including the preparation and submission of certain
    documents to TRC for its review and approval as the
    plaintiff’s project manager. More specifically, the defen-
    dant was required to submit a contractor work plan
    (CWP) for the PCB remediation to be done by the defen-
    dant on the job site. The CWP, subject to the approval
    of TRC, was in turn to be submitted to the EPA for its
    review and approval. The first CWP, dated September
    24, 2015, was submitted to the plaintiff on September
    29, 2015, and was based in part on TRC’s own Modified
    Self-Implementing Phase III Remediation Plan dated
    January, 2015. . . . The first CWP . . . was reviewed
    by TRC and found [to be] insufficient in various ways.
    The comments of TRC were forwarded to the defendant
    on October 2, 2015, by e-mail and specifically referenced
    that the CWP should ‘[i]nclude a discussion of steel
    beam sampling and disposal means and methods per
    [paragraph] 13 (a) (ii) of [the] EPA’s approval letter’
    and ‘[i]nclude a statement that sampling analytical
    results will be submitted to [the] EPA for review prior
    to disposal per [paragraph] 13 (a) (iii) of [the] EPA’s
    approval letter.’ . . . With respect to § 2.4 of the pro-
    posed plan regarding remediation of overhead cranes,
    TRC commented that ‘[t]he EPA’s approval states that
    the beams must be handled and disposed of as a [greater
    than or equal to] 50 ppm PCB waste or will be sampled
    to determine disposal requirements.’ Following the
    receipt of TRC’s comments, the defendant hired an inde-
    pendent consultant with expertise in the handling of
    PCBs and submitted the plan and TRC’s comments to
    him for his review. . . .
    ‘‘The defendant was also required to submit to TRC
    for its review and approval, a health and safety plan
    . . . as well as a demolition work plan. TRC reviewed
    the [health and safety plan], found it lacking and pro-
    vided comments thereon to the defendant. As of Octo-
    ber 19, 2015, TRC had not received a response to those
    comments. . . . TRC insisted that the [health and
    safety plan] and other plans had to be approved before
    substantive physical work on the project could begin
    despite the defendant’s belief that it was for review
    purposes only. . . .
    ‘‘While attempting to work this out, the parties contin-
    ued to work toward an acceptable CWP. Following the
    review of the original CWP by the defendant’s consul-
    tant for approximately one month, a second CWP was
    submitted to TRC on November 6, 2015 . . . . In the
    second CWP, the defendant proposed that, as part of
    its operations, it would conduct wipe sampling of the
    steel columns for PCB characterizations to determine
    whether the structural steel could be disposed of consis-
    tent with [paragraph] 13 (a) (ii) of the EPA’s approval
    letter. . . . The defendant also proposed paint chip
    sampling of the overhead crane steel to determine how
    it should be disposed of. On November 9, 2015, TRC
    rejected the proposed plan. . . . By e-mail on Novem-
    ber 12, 2015, to the defendant, TRC provided specific
    comments deleting the proposed paint chip sampling
    language and put in language about wipe sampling con-
    sistent with the EPA’s approval letter. Richard Gille of
    TRC credibly testified that the reason for deleting the
    paint chip test language was that such testing was
    unnecessary as it would not show any PCB surface
    contamination on the steel (given that paint chip sam-
    pling is designed to determine if a product is manufac-
    tured with PCBs, i.e., that it is bulk waste product). That
    same e-mail also indicated that TRC was still awaiting
    a revised [health and safety plan] from the defen-
    dant. . . .
    ‘‘Based on the comments of TRC, the defendant sub-
    mitted a third proposed CWP on November 13, 2015
    . . . which deleted the paint chip sampling language.
    . . . On November 18, 2015, following some additional
    edits requested by TRC, the defendant submitted its
    fourth proposed CWP . . . . TRC recommended to the
    plaintiff that it be submitted to the EPA for approval.
    . . . That recommendation was based on TRC’s con-
    tractual authority to review and approve such plans.
    The plan called for the defendant to conduct wipe sam-
    pling of the steel columns. . . . It expressly recited
    that ‘[i]n accordance with the EPA [a]pproval [l]etter,
    the steel within the building is assumed to contain PCB
    concentrations [greater than] 50 ppm in surface contam-
    ination caused by previous transformer remediation
    and/or historic site activities. Wipe sampling will be
    conducted in order to prove that the structural elements
    can be recycled without restriction. . . . Steel found
    to contain PCB above the remedial goal will be decon-
    taminated again in accordance with [40] C.F.R. [§]
    761.79 and/or will be disposed of as PCB remediation
    waste.’ . . . The plan was submitted to the EPA on
    November 18, 2015. The plan, however, was not
    approved because the EPA responded with comments
    and questions it wanted addressed. This included ques-
    tions about the possible wipe sampling of cranes and
    steel beams and testing of the expansion joint caulking.
    . . . The EPA did not suggest or ask for paint chip
    sampling. In light of the comments and questions, on
    December 10, 2015, the parties agreed that they would
    hold off on resubmitting a CWP or doing further work
    until after TRC had done testing of the expansion joint
    caulking to determine if there was PCB contamination
    and, if so, how it should be treated for purposes of
    disposal. . . . The additional testing took six days and
    was done by the plaintiff.
    ‘‘By letter dated December 15, 2015, the defendant
    issued a formal notice of delay to the plaintiff claiming
    the project had been delayed by ninety-four days due
    to the actions of the plaintiff. . . . Among other things,
    the formal notice cited the plaintiff’s failure to ‘initially
    characterize and remove potentially PCB contaminated
    paints and dust on the steel beams and expansion joint
    material in the concrete.’ . . . The defendant also sub-
    mitted with the letter a new work schedule indicating
    a completion date of on or about May 4, 2016. On
    December 16, 2015, TRC directed the defendant to ‘con-
    tinue with [the] EPA work plan preparation and submit
    for review by TRC using your planned method for
    expansion joint removal. Disposal considerations will
    be addressed later.’ . . . On December 22, 2015, the
    defendant responded that it would like any test results
    forwarded to it as it was likely that the EPA would
    require the information in the CWP. . . .
    ‘‘Because it had taken approximately two months to
    obtain a CWP acceptable to TRC and the plaintiff for
    submission to the EPA for its consideration, the defen-
    dant elected to demobilize from the site on November
    20, 2015, as it had not yet obtained an approved CWP
    to allow it to do any substantive demolition work. . . .
    The defendant had earlier indicated to TRC that it would
    not remobilize on the site until the CWP was approved.
    . . . Edward Doubleday of TRC credibly testified that
    he spoke with Stephen Goldblum, the president of the
    defendant, who stated that the defendant would not
    proceed with further work until the plaintiff took
    responsibility for anything related to the contaminated
    steel, including any wipe sampling. Also, during the
    period from mid-September to mid-December, the par-
    ties, through TRC, became engaged in a dispute over the
    characterization, testing and disposal of the structural
    steel on the site. The defendant contends that the plain-
    tiff had mischaracterized the structural steel as nonpo-
    rous and that it should have been characterized as
    porous given that many steel beams were painted. The
    defendant claims that the mischaracterization effec-
    tively led it to believe that the steel was not contami-
    nated and could be disposed of without remediation.
    How the steel was characterized had cost implications
    as any steel with a PCB concentration of greater than
    50 ppm could only be disposed of at a limited number
    of waste facilities, which, in turn, would result in higher
    disposal fees and transportation costs. There were also
    higher decontamination costs.
    ‘‘Under the terms of the contract . . . any ‘[s]teel for
    salvage shall become the property of the Contractor.
    . . . The risk for quantity and value of scrap shall be
    the Contractor[’s]’ . . . . Line 8 of the bid form also
    stated that the ‘[q]uantity and value of scrap above and
    below the Lump Sum bid is at Contractor[’s] . . . sole
    risk/reward.’ . . . In bidding the project on the pre-
    sumption the steel was not contaminated, the defendant
    had not allocated any costs associated with the disposal
    of contaminated steel. The defendant took the position
    that, under the contract, the steel was to be tested for
    PCBs and that it was the responsibility of the plaintiff
    to do so. The defendant further contended that the
    failure to properly characterize the steel resulted in its
    inability to recycle it in such a way that it would be
    able to obtain a financial credit of at least $200,000 as
    anticipated by the bid and contract for an estimated
    1000 tons of steel at $200 per ton.
    ‘‘This issue over who was to do the PCB sampling of
    the structural steel and the subsequent disposal was
    discussed as early as September 22, 2015, during the
    weekly job meeting. At that meeting, TRC made refer-
    ence to paragraph 13 (a) (ii) of the EPA approval letter
    and advised the defendant that it was [the defendant’s]
    responsibility as the project contractor to do the sam-
    pling of the steel. This is also evidenced, in part, by the
    weekly meeting minutes, which note that the defendant
    claimed several of the EPA requirements specified in
    the EPA approval letter were the basis for a change in
    the contract. . . . In response, TRC indicated to the
    defendant on each occasion that if it was seeking a
    change in the contract it should formally submit a writ-
    ten request in accordance with its terms. . . . Eventu-
    ally, on November 27, 2015, the defendant submitted a
    written notice to the plaintiff seeking a change to the
    contract based on a ‘discovery of undocumented condi-
    tions,’ which were described as follows: ‘The structural
    steel of the building has not been characterized to the
    satisfaction of the EPA. This characterization sampling
    is not included as our work in the specification.’ . . .
    This notice was followed by a November 30, 2015 letter
    from the defendant directly to the plaintiff detailing its
    issues with the steel sampling and disposal. . . . Gen-
    erally, the defendant contended that the bid documents
    did not include the initial characterization of the struc-
    tural steel, the final approved Modified Self-Implement-
    ing Plan, and the disposal of any hazardous (contami-
    nated) steel as the defendant’s obligation. The
    defendant took the position that, because this informa-
    tion had not been provided to it during the bidding
    process, ‘the final contract was then accidently exe-
    cuted by [the defendant] after the [plaintiff’s] incorpora-
    tion of the EPA [a]pproval [l]etter—without price
    change—despite significant increased scope and poten-
    tial adverse cost impact.’ . . . Nonetheless, the defen-
    dant indicated [that] it remained ready, willing, and able
    to perform the work on the project. By this point in
    time, approximately 55 percent of the time allocated
    for the completion of the work had passed. While stating
    [that] it remained ready, willing and able to do the work,
    the defendant also made statements to TRC at weekly
    job meetings around the same time that it would not
    perform any work if it was required to sample the
    steel. . . .
    ‘‘The plaintiff responded by letter dated December
    9, 2015, effectively rejecting the defendant’s claims and
    reminding it that time was of the essence relative to
    the completion date under the terms of the contract.
    . . . The defendant responded on December 15, 2015,
    noting that, because the plaintiff ‘failed to initially char-
    acterize and remove potentially PCB contaminated
    paints and dusts on the steel beams and expansion joint
    material in the concrete,’ it was unable to complete the
    CWP, which was needed in order to allow the start of
    demolition activities. . . . The defendant claimed that,
    as a result of the plaintiff’s failures, it was entitled to
    a compensable delay of ninety-four days in the comple-
    tion of the contract. . . . Thereafter, the plaintiff
    issued a letter dated January 4, 2016, notifying the defen-
    dant that it was in default and was therefore terminated
    from its employment under the contract, effective Janu-
    ary 11, 2016. . . . As of the date of the letter, the defen-
    dant had yet to provide to the plaintiff a revised CWP,
    an acceptable [health and safety plan], or a demolition
    work plan. The basis for the termination letter was that
    the defendant would not be able to timely complete the
    work, it failed or refused to comply with pertinent laws,
    ordinances or the instructions of the engineer (TRC),
    violated or anticipatorily breached various provisions of
    the contract, and failed to press the work to completion.
    Further, [the defendant having contended] in its Novem-
    ber 30, 2015 letter that [it] had ‘accidently executed’
    the contract, the plaintiff considered the defendant to
    have renounced and anticipatorily breached the con-
    tract. There was credible testimony from both parties
    that no substantive work was done on the project there-
    after. Based on the defendant’s own payment applica-
    tion for work done through November 30, 2015, only
    9.51 percent of the work on the project had been done.
    . . . As of January 11, 2016, including the six day con-
    tract extension provided by the plaintiff to the defen-
    dant, 82 percent of the time allowed for the completion
    of the work had passed (119 of the 146 days). Shortly
    thereafter, on January 15, 2016, the plaintiff filed the
    present complaint against the defendant.
    ‘‘While pursuing its complaint, the plaintiff undertook
    the effort to complete the project by putting out to bid
    what it saw as the remaining work to be done. . . .
    Following a procedure similar to that of the original
    bid, including the contractor’s bid meeting, on-site visit,
    and the provision of documents for review and question
    clarifications, a total of nine contractors submitted bids
    on the project. [The March 31, 2016 bid of] Costello
    Dismantling [Company, Inc.] (Costello) . . . of
    $2,962,207 was accepted by the plaintiff. . . . The
    scope of work to be done was the same as that of the
    defendant except for the work that had already been
    completed by the defendant. Costello commenced work
    on the project shortly thereafter. Mike Costello, as proj-
    ect manager for Costello, credibly testified that, at the
    time of its original bid in 2015, Costello understood from
    its reviews of the bid documents and specifications
    that PCB contamination existed on the job site in the
    concrete and expansion joint caulking. Similar to the
    defendant, Costello also considered the structural steel
    to be recyclable. Costello, however, recognized that it
    bore the risk of the steel being contaminated and might
    have to bear the cost of any testing or disposal. Upon
    its rebid, in 2016, Costello understood that it might bear
    the cost of the testing and disposal given the terms of
    the EPA approval letter and the contract. Therefore, at
    the time of both bids, Costello took into consideration
    that decontamination was required by the contract
    specifications consistent with what it considered to be
    the surficial standard for testing as set out in the approval
    letter. In other words, wipe sampling was going to be
    required as part of the job.
    ‘‘Costello’s work on the project was interrupted when
    the defendant directly contacted the EPA by e-mail
    dated September 1, 2016, to provide it with information
    about paint sampling that was to be done on the site
    pursuant to an August [19], 2016 order of this court in
    this action.5 . . . This e-mail was sent approximately
    eight months after the defendant had been dismissed
    from the job. What followed was a series of e-mails and
    phone calls between the defendant and the EPA through
    November 21, 2016. This correspondence included
    reports and findings from the defendant’s consultant
    and trial expert, John Insall of Partner Engineering,
    regarding the paint sampling and the results thereof,
    which showed that some of the samples contained PCBs
    in excess of 50 ppm. . . .
    ‘‘During this time, Costello continued other work on
    the project, providing CWPs and revisions of the plans
    based on the review and comments of both TRC and
    the EPA. As part of the plans, Costello, which operated
    with the understanding that it had the contractual
    responsibility for the sampling of PCBs on the steel
    beams and other surfaces, submitted to TRC for its
    approval a PCB sampling plan dated August 17, 2016,
    prepared by its consultant, Strategic Environmental
    Services, Inc. . . . That plan noted that previous inves-
    tigations had reported PCB concentrations in excess
    of EPA limits on painted metal surfaces of the main
    carrying beams for the overhead cranes. TRC approved
    the plan and, in turn, submitted it to the EPA for its
    approval. . . . A series of correspondence followed
    from September 9, 2016, to November 9, 2016, between
    the plaintiff and the EPA in which additional questions
    and comments, including those about painted surfaces,
    were made by the EPA. . . . Included was a comment
    by the EPA that should the paint chip samples sought
    by the defendant (in the court action) reveal PCBs in
    the paint, a change to the decontamination plan might
    be necessary. . . . After the submission of the multiple
    CWPs, the EPA approved Costello’s CWP on October
    5, 2016. . . . Costello then began the demolition of the
    structure at the site. Subsequently, following the receipt
    of the paint chip sample results from the defendant
    through Insall on November 21, 2016, the EPA did
    require additional testing of the steel beams and other
    materials. That testing was ultimately done by the plain-
    tiff.
    ‘‘While the litigation continued, Costello still attempted
    to do certain work on the property. During the course
    of its work on the project, Costello submitted eleven
    change order requests. Most, but not all, were approved
    by TRC. . . . By September 21, 2017, nearly a year
    after the EPA first approved Costello’s CWP, the EPA
    approved the plaintiff’s plan for decontamination and
    recycling of the structural steel. . . . The approval was
    consistent with the original September 1, 2015 approval
    letter subject to certain additional conditions such as
    the additional testing of steel beams and other materi-
    als, which were the result, in part, of the court-ordered
    paint chip sample results that the defendant unilaterally
    provided to the EPA on November 21, 2016. It also
    required the plaintiff to provide to the EPA and the
    Connecticut Department of Energy and Environmental
    Protection [department] the paint chip and wipe sample
    results of any waste to be shipped off-site. This was,
    in effect, the requirement to do verification sampling,
    which the plaintiff was already obligated to do under
    the terms of the contract[s] with both the defendant and
    Costello. Such conditions were within the discretion of
    the EPA to add and required the plaintiff, where paint
    chip samples revealed the presence of PCBs [greater
    than or equal to] 50 ppm, to decontaminate or dispose
    of the steel in accordance with paragraph 13 (a) (ii)
    and (iii) of the original approval letter. In effect, the
    EPA required the plaintiff to do nothing more than what
    it was originally required to do relative to the disposal
    of the steel. The letter was not amended or modified
    relative to the characterization and treatment of the
    steel beams, nor were any other of its terms or provi-
    sions changed in that regard. As worded, the original
    approval letter did not specifically detail the frequency
    of sampling or preclude the decontamination of the
    steel to bring the PCBs down to a level where the steel
    could be recycled. . . .
    ‘‘Having done wipe sampling of the structural steel
    as part of its work, Costello found some beams were
    beyond acceptable contamination standards. Following
    completion of the sampling, Costello then began decon-
    tamination of those beams through a pilot decontamina-
    tion program, which proved very successful. The decon-
    tamination process, however, was stopped due to this
    pending litigation, which had prompted the EPA to seek
    the additional testing. . . . To that point there only
    remained a few contaminated items. Mike Costello
    credibly testified, as a disclosed expert, that had Cos-
    tello been able to complete the decontamination pro-
    cess, there was a disposal facility that would have
    accepted the steel for recycling. Also, as part of the
    scope of its work, Costello was to take down the roof
    of the building, which it had done sometime in the fall
    of 2016. . . . Because of the defendant’s correspon-
    dence to the EPA regarding the test results, the EPA
    also asked for the testing of the roofing material, which
    added additional cost and delay to the completion of
    the project. . . . In fact, because of the issue being
    raised by the defendant, Costello was never able to
    finish the project, including the treatment and disposal
    of the steel for recycling. This was in part because,
    rather than disposing of the steel and debris, it then
    had to stockpile it on the site for examination and
    testing. . . . By that point, the plaintiff’s available
    funds for the project were exhausted and the work
    ceased.’’ (Citations omitted; emphasis in original; foot-
    notes in original; footnote added; footnotes omitted.)
    In its complaint, the plaintiff alleged a single count
    of breach of contract by the defendant. Specifically, the
    plaintiff alleged that, via a letter dated January 4, 2016,
    it had declared the defendant to be in default of the
    contract and had given the defendant seven days’ notice
    that the defendant’s employment under the contract
    was terminated. The complaint further alleged that the
    defendant breached the parties’ contract in one or more
    of the ways set forth in the January 4, 2016 termination
    letter, which stated that the defendant (1) had failed
    to complete its work under the contract in a timely
    manner; (2) had failed or refused to comply with perti-
    nent laws, regulations and instructions of the engineer
    for the project; (3) anticipatorily breached material pro-
    visions of the contract; and (4) did not vigorously per-
    form its obligations as required by article 2.1.2 of the
    contract.
    In response, the defendant filed an answer and nine
    special defenses. The nine special defenses alleged that
    the plaintiff’s action was barred, in whole or in part,
    by the following: (1) the failure of the complaint to
    state a claim for which relief could be granted; (2)
    unilateral mistake in the terms of the contract; (3) fraud
    in the inducement; (4) equitable estoppel; (5) unclean
    hands; (6) waiver; (7) a failure to mitigate damages; (8)
    a material breach of the contract by the plaintiff; and
    (9) the plaintiff’s failure to comply with the conditions
    for termination of the contract. The defendant also filed
    a fourth amended, eight count counterclaim alleging,
    in count one, breach of contract for failure to pay; in
    count two, breach of contract for the plaintiff’s delays
    in the performance of its work under the contract; in
    count three, wrongful termination; in count four, negli-
    gent misrepresentation; in count five, a violation of
    General Statutes § 52-557n (b) (8) by the plaintiff for
    failing to conduct a proper inspection of the property;
    in count six,6 a violation of § 52-557n (b) (9) by the
    plaintiff for failing to detect or prevent pollution of the
    environment; in count seven, breach of the duty of
    good faith and fair dealing; and in count eight, unjust
    enrichment.7
    In its lengthy memorandum of decision, the court
    found that the plaintiff had established its claim for
    breach of contract and had suffered damages. After
    examining and rejecting the defendant’s special defenses
    and the six remaining counts of its counterclaim, the
    court addressed the issue of damages. The court found
    that article 2, § 2.1.1 of the contract was a valid provi-
    sion for liquidated damages, rather than a penalty. It
    further found that, although the plaintiff had presented
    considerable evidence of its actual and consequential
    damages, the plaintiff could not claim both liquidated
    damages and actual and consequential damages, as the
    liquidated damages provision of the contract did not
    ‘‘allow an independent claim for actual and consequen-
    tial damages.’’ The court concluded that the plaintiff
    was ‘‘limited in its claim of damages to those attribut-
    able under its liquidated damages provision, article 2,
    § 2.1.1. Although such damages are often typically deter-
    mined by when the job is finally completed by the
    breaching party, here, the plaintiff dismissed the defen-
    dant from the job. Costello was hired to finish the job,
    but because of the defendant’s interaction with the EPA
    and the subsequent additional work and testing, it was
    unable to do so, as the funds available to the plaintiff
    to complete the project were exhausted. Although the
    job was never completed, the plaintiff has not sought
    liquidated damages beyond 260 days (adjusted to 254
    days), which falls shortly after Costello received notice
    of the EPA’s approval of the CWP. Thus, the total amount
    of liquidated damages due the plaintiff is found to be
    $508,000.’’
    Next, the court addressed the retainage8 held by the
    plaintiff. Pursuant to General Statutes § 49-41b, the
    amount of retainage held by a municipality in any public
    work contract is limited to 5 percent of any periodic
    or final payment due a general contractor. In the present
    case, under the contract the plaintiff was entitled to
    retain 10 percent ‘‘of each estimate until final comple-
    tion and acceptance of all work covered by [the] con-
    tract.’’ The court found that $18,628, which represented
    10 percent of the cost of the work deemed completed
    by the defendant, was held by the plaintiff as retainage.
    The court explained that, although that amount com-
    ported with the terms of the contract agreed to by the
    parties, they were, nevertheless, bound by the terms of
    the statute. Accordingly, the court concluded that the
    correct amount of retainage held should have been
    $9314, and it set off the excess retainage against the
    amount due the plaintiff in liquidated damages, which
    resulted in an award in the amount of $498,686. The
    remaining retainage, $9314, was credited toward the
    plaintiff’s damages, which resulted in a further reduc-
    tion in the award due the plaintiff to $489,372. Judgment
    was rendered in favor of the plaintiff on its breach of
    contract claim in that amount. This appeal followed.
    Additional facts and procedural history will be set forth
    as necessary.
    I
    THE DEFENDANT’S APPEAL
    On appeal, the defendant claims that (1) the court
    misapplied state and federal environmental regulations,
    (2) the court erred in not finding that the contract was
    impossible to perform, (3) the court improperly deter-
    mined that the plaintiff lawfully had terminated the
    contract, and (4) evidence of certain change orders
    executed by the plaintiff in connection with its contract
    with Costello, pursuant to which the plaintiff had agreed
    to modify terms of that contract, constituted admissions
    that the plaintiff’s contract with the defendant was
    defective and could not be performed by the defendant
    as written.
    Before we address the defendant’s claims, we first
    set forth our well established standard of review in
    cases involving the issue of contract interpretation.9
    ‘‘The elements of a breach of contract claim are the
    formation of an agreement, performance by one party,
    breach of the agreement by the other party, and dam-
    ages. . . . The interpretation of definitive contract lan-
    guage is a question of law over which our review is
    plenary. . . . By contrast, the trial court’s factual find-
    ings as to whether and by whom a contract has been
    breached are subject to the clearly erroneous10 standard
    of review and, if supported by evidence in the record,
    are not to be disturbed on appeal.’’ (Citations omitted;
    footnote added; internal quotation marks omitted.) CCT
    Communications, Inc. v. Zone Telecom, Inc., 
    327 Conn. 114
    , 133, 
    172 A.3d 1228
     (2017). ‘‘[T]he intent of the
    parties [to a contract] is to be ascertained by a fair and
    reasonable construction of the written words and . . .
    the language used must be accorded its common, natu-
    ral, and ordinary meaning and usage where it can be
    sensibly applied to the subject matter of the contract.
    . . . Where the language of the contract is clear and
    unambiguous, the contract is to be given effect
    according to its terms. A court will not torture words
    to import ambiguity where the ordinary meaning leaves
    no room for ambiguity . . . . Similarly, any ambiguity
    in a contract must emanate from the language used in
    the contract rather than from one party’s subjective
    perception of the terms. . . . [T]he mere fact that the
    parties advance different interpretations of the lan-
    guage in question does not necessitate a conclusion
    that the language is ambiguous. . . . If a contract is
    unambiguous within its four corners, intent of the par-
    ties is a question of law requiring plenary review. . . .
    When the language of a contract is ambiguous, the
    determination of the parties’ intent is a question of fact,
    and the trial court’s interpretation is subject to reversal
    on appeal only if it is clearly erroneous.’’ (Internal quota-
    tion marks omitted.) Assn. Resources, Inc. v. Wall, 
    298 Conn. 145
    , 183, 
    2 A.3d 873
     (2010).
    Moreover, ‘‘[c]ourts do not unmake bargains unwisely
    made. Absent other infirmities, bargains moved on cal-
    culated considerations, and whether provident or
    improvident, are entitled nevertheless to sanctions of
    the law. . . . Although parties might prefer to have the
    court decide the plain effect of their contract contrary
    to the agreement, it is not within its power to make a
    new and different agreement . . . .’’ (Internal quota-
    tion marks omitted.) Detar v. Coast Venture XXVX, Inc.,
    
    74 Conn. App. 319
    , 323, 
    811 A.2d 273
     (2002). ‘‘It also is
    settled that [t]he individual clauses of a contract . . .
    cannot be construed by taking them out of context and
    giving them an interpretation apart from the contract
    of which they are a part. . . . A contract should be
    construed so as to give full meaning and effect to all
    of its provisions . . . .’’ (Internal quotation marks omit-
    ted.) FCM Group, Inc. v. Miller, 
    300 Conn. 774
    , 811, 
    17 A.3d 40
     (2011).
    A
    The defendant’s first claim is that the court misap-
    plied state and federal environmental laws. Specifically,
    the defendant focuses on the court’s statement, which
    it characterizes as erroneous, that, ‘‘[a]t the heart of
    the dispute between the parties is whether the plaintiff
    was obligated to do sampling of the structural steel for
    PCBs under the terms of the contract, of which the
    September 1, 2015 EPA approval letter was a part.’’
    The defendant claims, instead, that its dispute with the
    plaintiff ‘‘was about the obligation to characterize the
    waste coming off the site based on the EPA regulations
    and state law, not the contract.’’ The defendant further
    claims that the court, by focusing on the contract, ‘‘mis-
    applied the state and federal regulatory scheme as it
    pertains to cleanup projects affecting regulated PCB
    contamination,’’ and that, by ‘‘focusing on the steel, it
    disregarded the other PCB contaminated waste
    revealed by the EPA imposed testing, the requirements
    of General Statutes § 22a-467, and the effect of EPA
    regulations.’’
    For example, the defendant asserts that the notifica-
    tion provided by the plaintiff to the regulators was inad-
    equate and did not comply with 
    40 C.F.R. § 761.61
     (a)
    (3) because the plaintiff, by not testing various PCB
    contaminated materials, did not provide all required
    information. As a result, the defendant claims that the
    notification ‘‘did not provide authorization to perform
    work affecting undisclosed regulated waste,’’ nor did
    the approval letter ‘‘authorize the [plaintiff] to perform
    work on undisclosed waste.’’ The defendant also claims
    that the plaintiff disregarded the requirements of § 22a-
    467 because it never had a permit to remediate the
    waste from the site.
    The defendant’s claims are based on its assertion that
    ‘‘[t]he state and federal environmental regulatory schemes
    both articulate a stringent policy preventing the distur-
    bance of PCB contaminated waste unless and until the
    nature and extent of the contamination is determined
    and disclosed to the regulators, and they approve the
    plan for remediation and disposal of regulated waste.’’
    In support of this proposition, the defendant cites to
    
    40 C.F.R. § 761.61
     (a) (2), which provides in relevant
    part that ‘‘[a]ny person conducting self-implementing
    cleanup of PCB remediation waste must characterize
    the site adequately . . . .’’11 According to the defen-
    dant, the plaintiff, by mischaracterizing the steel beams
    as nonporous and by failing to paint chip sample the
    structural steel prior to submitting its plan for approval
    by the EPA, did not adequately characterize the site
    and thereby violated 
    40 C.F.R. § 761.61
     (a) (2).
    The defendant’s claims of violations by the plaintiff
    of state and federal statutes and regulations can be
    distilled to one central claim, namely, that the plaintiff,
    prior to entering into the contract with the defendant,
    should have tested and analyzed samples of all of the
    waste at the site in order to be able to characterize the
    site adequately. As a result of the plaintiff’s failure to
    do so, the defendant alleges that the information pro-
    vided to the EPA was ‘‘limited or false,’’ as it did not
    cover the undisclosed contaminated waste. Thus,
    according to the defendant, the Notification and
    approval letter from the EPA could not and did not
    provide authorization to perform work on the undis-
    closed waste, which precluded the defendant from per-
    forming any such work until the plaintiff performed the
    necessary testing and the EPA provided the necessary
    authorization. We disagree and conclude that the defen-
    dant’s claims are belied by the court’s findings, which
    are supported by the record.
    1
    First, from our review of the record, it does not
    appear that the defendant raised its claim before the
    court that the plaintiff lacked proper authorization from
    the EPA to perform work on the undisclosed waste at
    the site, as it was not mentioned in the defendant’s
    posttrial brief nor did the court address it in its memo-
    randum of decision. Rather, the defendant argued at
    trial that the plaintiff’s mischaracterization of the steel
    made it impossible for the defendant to perform under
    the contract and that the plaintiff breached the contract
    by failing to characterize the steel properly. This court,
    therefore, will not address the issue of the adequacy
    of the EPA approval letter authorizing the plaintiff to
    commence work on phase III of the project, as that
    issue was not raised before or decided by the trial
    court. See Lebanon Historical Society, Inc. v. Attorney
    General, 
    209 Conn. App. 337
    , 351 n.12, 
    268 A.3d 734
    (2021) (declining to review claim that was not distinctly
    raised before or decided by trial court). Moreover,
    because the court did not reference § 22a-467 in its
    decision, nor did the defendant raise any claim pursuant
    to that statute before the court in its special defenses,
    counterclaim or posttrial brief, we also decline to
    address the defendant’s claim that the plaintiff, and the
    court, disregarded the requirements of § 22a-467. See id.
    2
    The following facts are relevant to the defendant’s
    claims that the plaintiff did not characterize the site
    adequately and was required under the contract to paint
    chip test the steel beams before the defendant could
    perform any work at the site. The plaintiff submitted a
    notification to the EPA seeking approval of a proposed
    plan to address the removal of PCB contaminated build-
    ing materials from the project site. In response, on
    September 1, 2015, the EPA issued an approval letter
    authorizing the plaintiff to move forward with phase
    III of the project subject to the conditions set forth in
    the letter and two attachments. The first attachment
    required the plaintiff to provide to the EPA ‘‘a certifica-
    tion signed by its selected abatement/demolition con-
    tractor, stating that the contractor(s) has read and
    understands the Notification, and agrees to abide by
    the conditions specified in [the] [a]pproval . . . .’’ The
    second attachment included documents and correspon-
    dence reviewed by the EPA prior to the issuance of its
    approval, which, as the court found, included ‘‘discus-
    sions of PCB contamination of various materials includ-
    ing overhead cranes and steel beams.’’ By e-mail, dated
    September 3, 2015, the defendant, as the contractor,
    provided the certification required by the approval let-
    ter, stating that it read and understood the cleanup and
    disposal plan for the project site and agreed to abide
    by the conditions set forth by the EPA in the approval
    letter, which included compliance with EPA regulations
    under 
    40 C.F.R. § 761
     relative to the removal and abate-
    ment of PCBs. Subsequently, the parties entered into
    the contract, and, by letter dated September 14, 2015,
    the plaintiff provided the defendant with a notice to
    proceed as required under the contract.
    As stated previously in this opinion, the court found
    that the parties’ dispute centered on whether the con-
    tract obligated the plaintiff to do paint chip sampling
    of the structural steel to determine the presence of
    PCBs at an improper level. In addressing this issue,
    the court found that the testimony of Goldblum, the
    defendant’s president, and Lawrence Kurt, who pre-
    pared the CWP for the defendant, made ‘‘clear that the
    defendant’s position was that paint chip sampling of
    the steel was necessary for it to be sold to scrap dealers
    as recyclable material.’’ The general truth of that state-
    ment, however, is irrelevant because the court found
    that the contract does not specify any requirement for
    paint chip testing, and our examination of the contract
    confirms that finding. Additionally, the court found the
    testimony of the plaintiff’s expert witnesses ‘‘to be cred-
    ible12 and of greater weight than that of the defendant’s
    expert’’; (footnote added); on the issue of whether it is
    customary to require paint chip sampling under circum-
    stances similar to those in the present case.13 The court
    further found that, ‘‘[w]ith respect to any testing that
    might have been required to comply with any regulatory
    provisions under 
    40 C.F.R. § 761
    , the defendant
    acknowledged that it had such an obligation when it
    expressly certified in its letter on September 3, 2015,
    that it had read and understood the terms of the EPA’s
    Notification and agreed to abide by the specifications
    set out in the approval letter.’’ The court also specifi-
    cally found that ‘‘there is no express statement [in the
    contract] that the steel is not contaminated,’’ which
    undermines the primary basis for the defendant’s argu-
    ment about the plaintiff’s alleged mischaracterization
    of the site.14 Finally, the court found that ‘‘the plaintiff
    performed its obligations under the contract.’’
    We conclude that the court’s findings are supported
    by the clear and unambiguous provisions of the con-
    tract. For example, the provision of the contract govern-
    ing the transportation and disposal of hazardous materi-
    als requires that ‘‘[a]ll labor, materials, tools, equipment,
    services, testing, insurance, and incidentals which are
    necessary or required to perform the work in accor-
    dance with applicable governmental regulations, indus-
    try standards and codes, and these specifications, shall
    be provided by the Contractor.’’ (Emphasis added.) The
    contract further provides that ‘‘[a]ll characterization
    sampling and analysis for disposal shall be conducted
    by the CONTRACTOR, with supervision from the ENGI-
    NEER, where indicated,’’ and that ‘‘[t]he Contractor is
    responsible for verifying actual locations and quantities
    of the items with hazardous/regulated material/waste
    constituents and for their proper handling and dis-
    posal.’’ Moreover, neither the contract nor the approval
    letter required the plaintiff to do paint chip sampling.
    As the court properly found, the contract, when viewed
    as a whole, ‘‘overwhelmingly placed the obligation for
    the testing, handling and processing of the materials
    on the site upon the defendant.’’ Indeed, as the court
    observed, ‘‘[f]rom the broadest perspective, while the
    defendant argues that it was the plaintiff who was
    responsible for managing and disposing of the PCBs
    on the site, the very purpose of the plaintiff awarding
    the contract to the defendant was to have it do that
    very work,’’ and ‘‘[w]hat the defendant viewed as extra
    work with respect to the testing and treatment of the
    structural steel was reasonably within the scope of the
    work called for by the contract and the EPA approval
    letter.’’
    In the present case, the court correctly found that
    the contract ‘‘overwhelmingly placed the obligation for
    the testing, handling and processing of the materials on
    the site upon the defendant.’’ The court also thoroughly
    discussed the risks assumed by the defendant under the
    contract and found that the plaintiff was not obligated
    to test the waste ‘‘except in the context of doing verifica-
    tion testing, which the parties do not dispute. All charac-
    terization of the waste that had previously been done
    in phases I and II of the project, which work had been
    approved by the EPA, was disclosed to the defendant
    as part of the bid process and within the contract docu-
    ments. The contract specifically addressed the charac-
    terization of the waste . . . [and required it to be con-
    ducted by the contractor]. . . . The fact that the
    defendant may not have accounted for the potential
    contamination or testing of some structural steel, which
    had been thought to have been recyclable, and therefore
    resulted in the need for additional work both in terms
    of time and labor, was a risk that it contractually bore.’’
    (Citation omitted.) The court further stated that ‘‘[t]he
    contract expressly made clear that the risk of the condi-
    tion of the materials being different than anticipated
    was solely on the contractor. Hence, if it turned out
    that the assumption as to the recyclability of the steel
    was wrong, the risk as to the quantity and value of any
    recyclable steel was to be borne by the [defendant].
    Both the original bid form and the proposed/executed
    contract documents so stated.’’ These findings are
    amply supported by the clear language of the contract
    and the documents related thereto that were submitted
    into evidence. The defendant’s claim on appeal that
    the plaintiff was required to do the testing that the
    defendant, itself, had contracted to perform simply
    lacks merit.
    3
    Although, on appeal, the defendant casts the primary
    issue as involving the plaintiff’s obligation to character-
    ize waste in accordance with the EPA regulations and
    state law, this case involves a claim for breach of con-
    tract, and the defendant has not challenged many of the
    court’s findings and conclusions related to the plaintiff’s
    breach of contract claim nor has it provided a clear
    explanation as to how its claims concerning the EPA
    regulations circumvent the court’s findings regarding
    the contract. As we stated previously, ‘‘[t]he elements
    of a breach of contract claim are the formation of an
    agreement, performance by one party, breach of the
    agreement by the other party, and damages.’’ (Internal
    quotation marks omitted.) CCT Communications, Inc.
    v. Zone Telecom, Inc., supra, 
    327 Conn. 133
    . In determin-
    ing whether those elements had been satisfied, the court
    thoroughly, and properly, analyzed the provisions of
    the contract.
    The defendant’s claim that this case concerns the
    issue of the plaintiff’s obligation to characterize the
    waste based on the requirements of certain EPA regula-
    tions, not on the pertinent language of the contract, is
    undercut by the defendant’s arguments before the court
    and in its posttrial brief, which is replete with arguments
    relating to the provisions of the contract. Although, in
    making those arguments, the defendant referred to EPA
    regulations, its claims at trial were premised on the
    contract, and the defendant relied on those regulations
    as a basis for its claim that the plaintiff breached the
    contract. On appeal, however, the defendant, without
    reference to the contract and as an excuse to escape
    its contractual obligations, argues that the plaintiff’s
    conduct constitutes a violation of those regulations and
    that the court erred in failing to find such a violation.
    The defendant cannot take one path at trial and, when
    that fails, choose another on appeal. See Bligh v. Travel-
    ers Home & Marine Ins. Co., 
    154 Conn. App. 564
    , 577,
    
    109 A.3d 481
     (2015) (‘‘[o]rdinarily appellate review is
    not available to a party who follows one strategic path
    at trial and another on appeal, when the original strategy
    does not produce the desired result’’ (internal quotation
    marks omitted)). The defendant’s claim, therefore, fails.
    4
    Finally, it is also important to note the court’s finding
    that, ‘‘[i]n this transaction, the defendant was a sophisti-
    cated and experienced party in a highly specialized area
    of work, which had, or had available to it if it wished,
    the advice of consultants or counsel prior to entering
    into the transaction. In fact, the defendant’s president,
    Goldblum, is himself an attorney. In the bid documents,
    the defendant provided a detailed and extensive list of
    its experience in the field of demolition, remediation
    and abatement, referencing fifty-three projects it had
    completed or [was] actively working on between 2008
    and 2014.’’ The court further found that the defendant
    ‘‘was given every opportunity to address any issues it
    had with the proposed terms and interpretation of the
    contract prior to its execution,’’ that ‘‘[i]t was not an
    innocent [party] that was somehow unknowingly duped
    into entering into an agreement of which it had no real
    knowledge or understanding,’’ and that, even though
    the court understood ‘‘the source of the frustration and
    dismay of the defendant as to the condition of the prop-
    erty being other than that which it had assumed,’’ under
    the contract, the defendant bore the risk of its failure
    to account ‘‘for the potential contamination or testing
    of some structural steel which had been thought to
    have been recyclable . . . .’’
    With the benefit of hindsight, the defendant, in an
    effort to shift the burden and responsibility for site
    testing from it to the plaintiff, effectively is requesting
    this court to rewrite its contract with the plaintiff, which
    would be contrary to the well established principle that
    ‘‘parties are free to contract for whatever terms on
    which they may agree. This freedom includes the right
    to contract for the assumption of known or unknown
    hazards and risks that may arise as a consequence of
    the execution of the contract. Accordingly, in private
    disputes, a court must enforce the contract as drafted
    by the parties and may not relieve a contracting party
    from anticipated or actual difficulties undertaken pur-
    suant to the contract, unless the contract is voidable on
    grounds such as mistake, fraud or unconscionability.’’
    Holly Hill Holdings v. Lowman, 
    226 Conn. 748
    , 755–56,
    
    628 A.2d 1298
     (1993); see also Coppola Construction
    Co. v. Hoffman Enterprises Ltd. Partnership, 
    157 Conn. App. 139
    , 159, 
    117 A.3d 876
     (‘‘[C]ourts do not unmake
    bargains unwisely made. . . . Although parties might
    prefer to have the court decide the plain effect of their
    contract contrary to the agreement, it is not within its
    power to make a new and different agreement; con-
    tracts voluntarily and fairly made should be held valid
    and enforced in the courts.’’ (Internal quotation marks
    omitted.)), cert. denied, 
    318 Conn. 902
    , 
    122 A.3d 631
    (2015), and cert. denied, 
    318 Conn. 902
    , 
    123 A.3d 882
    (2015). Although ‘‘the defendant may have used a mis-
    taken basic assumption in making its bid and entering
    into the contract,’’ that does not permit this court or
    the trial court to rewrite the contract or to relieve the
    defendant of its obligations thereunder, especially when
    the defendant is an experienced and sophisticated com-
    mercial party with respect to the type of work covered
    by the contract, rather than an unsophisticated party
    that was misled or deceived into entering into the con-
    tract, the circumstances of which, the court concluded,
    were not unconscionable.
    B
    The defendant next claims that the court erred in not
    finding that the contract was impossible to perform.
    We decline to review the claim.
    This court previously has addressed the defense of
    impossibility, stating: ‘‘Practice Book § 10-50 provides
    that [f]acts which are consistent with [the claimant’s
    allegations] but show, notwithstanding, that the plaintiff
    has no cause of action, must be specially alleged. . . .
    The defense of impossibility does not aim to establish
    the absence of a breach of the contract; rather it
    assumes breach and instead seeks to show that a party
    is excused from performance because at the time [the]
    contract [was] made, [his] performance under it is
    impracticable without his fault because of a fact of
    which he has no reason to know . . . . 2 Restatement
    (Second), Contracts, Existing Impracticability or Frus-
    tration § 266, p. 338 (1981). Accordingly, such defense
    must be specially pleaded.’’ (Citation omitted; internal
    quotation marks omitted.) Howard-Arnold, Inc. v.
    T.N.T. Realty, Inc., 
    145 Conn. App. 696
    , 711–12, 
    77 A.3d 165
     (2013), aff’d, 
    315 Conn. 596
    , 
    109 A.3d 473
     (2015).
    In the present case, the plaintiff argues that this court
    should decline to review the defendant’s impossibility
    claim because it was not pleaded as a special defense.
    It claims that, because the defendant failed to plead
    a special defense of impossibility, the court did not
    undertake the necessary analysis of such a claim, nor
    did it make findings thereon, and, thus, it could not have
    erred in failing to find that the defendant’s performance
    under the contract was impossible. In opposition, the
    defendant argues that the issue of impossibility is prop-
    erly before this court. Specifically, the defendant claims
    that it raised the claim in its posttrial brief and that
    the court addressed the issue in its memorandum of
    decision. We agree with the plaintiff.
    First, we note that the defendant has not addressed
    in its reply brief the issue raised by the plaintiff concern-
    ing the defendant’s failure to plead impossibility as a
    special defense, which, by itself, is fatal to its claim, as
    our case law is clear that impossibility must be pleaded
    as a special defense. See 
    id.
     The court, therefore, could
    not have erred in failing to make a finding on an issue
    that was not properly before it. Moreover, the defendant
    relies on its claims that the court addressed the issue
    in its decision and that the defendant raised the issue
    in its posttrial brief as part of its argument that the
    plaintiff materially had breached the contract. Our
    review of the court’s decision, however, demonstrates
    that, although the court referenced a number of the
    defendant’s claims, including the claim that the plain-
    tiff’s mischaracterization of the steel made it impossible
    for the defendant to perform under the contract, the
    court did not make any express findings regarding
    whether the contract itself was impossible to perform.
    The only finding regarding impossibility made by the
    court was its finding that, given the course of events
    that had transpired, as of December, 2015, it would
    have been impossible for the defendant to complete
    the work in a timely manner; the court never made
    a finding that it would have been impossible for the
    defendant to perform the work under the contract in
    the first place beginning in September, 2015, as claimed
    by the defendant on appeal.
    Additionally, even if the issue of whether it was
    impossible for the defendant to perform its obligations
    under the contract was properly before the court,
    because the court failed to make any findings as to that
    issue, we would have to speculate as to whether the
    court rejected the claim or simply overlooked it. It was
    incumbent on the defendant to seek an articulation of
    the court’s decision as to its failure to make a finding
    on a claim the defendant alleges was properly before
    the court. In the absence of such an articulation, the
    record is inadequate for us to review the claim. See
    McCarthy v. Chromium Process Co., 
    127 Conn. App. 324
    , 335, 
    13 A.3d 715
     (2011) (‘‘It is well established that
    [i]t is the appellant’s burden to provide an adequate
    record for review. . . . It is, therefore, the responsibil-
    ity of the appellant to move for an articulation or rectifi-
    cation of the record where the trial court has failed to
    state the basis of a decision . . . to clarify the legal
    basis of a ruling . . . or to ask the trial judge to rule
    on an overlooked matter. . . . In the absence of any
    such attempts, we decline to review this issue.’’ (Inter-
    nal quotation marks omitted.)).
    C
    The defendant next claims that the court improperly
    determined that the plaintiff lawfully had terminated
    the contract.15 In support of this claim, the defendant
    argues that ‘‘[a] party to a contract already in default
    cannot terminate the other,’’ and that the plaintiff ‘‘was
    clearly in default by the end of November when the
    CWP was rejected.’’ Thus, according to the defendant,
    ‘‘[u]nless and until the CWP was approved, [the defen-
    dant] had no authority to perform any work that
    affected PCB contaminated waste.’’ We are not per-
    suaded.
    We first note that the court did not make an express
    finding that the plaintiff lawfully had terminated the
    contract. Such a finding, however, can be inferred from
    the court’s rejection of count three of the defendant’s
    counterclaim, which alleged that the plaintiff wrong-
    fully had terminated the defendant from the job.
    Although the defendant appears to be challenging that
    determination, its very limited briefing on the issue fails
    to address the court’s determination that the defendant
    had failed to establish the allegations of its wrongful
    termination claim in count three of its counterclaim.
    We, therefore, do not undertake an analysis of the
    court’s decision relating thereto.
    The defendant’s claim that the plaintiff did not law-
    fully terminate the contract is premised on a faulty
    assumption, namely, that the plaintiff was in default
    under the contract. The record does not support that
    assertion, and the court made no such finding of default
    by the plaintiff. In fact, the court expressly found that
    the plaintiff had performed its obligations under the
    contract and that there was ample evidence of the
    defendant’s breach. Specifically, the court stated: ‘‘First,
    the contract contained a ‘time is of the essence’ clause
    requiring the defendant to finish the job on or before
    February 1, 2016. TRC had granted a six day extension
    to allow for the testing of the expansion joint caulking
    for PCB contamination as requested by the EPA, which
    moved the deadline back to February 7, 2016. There
    was credible testimony from Doubleday, Zarba and
    [Richard] McManus that the defendant would not have
    been able to meet that deadline. Collectively they cited
    several factors, including, but not limited to: (1) the
    defendant waiting seven weeks (forty-eight days)
    before obtaining a demolition permit for the job site;
    (2) the multiple delays in preparing an acceptable CWP,
    which included over a month’s delay while the defen-
    dant hired a consultant to review the plan; (3) the defen-
    dant’s election to demobilize from the site on or about
    November 20, 2015; (4) McManus’ opinion that the mill-
    ing of the concrete called for in the contract would
    take sixty-nine days as opposed to the thirty days the
    defendant had estimated; (5) the ongoing dispute over
    who was responsible for the testing of the steel for PCB
    contamination despite the plaintiff’s continued insis-
    tence that it was the defendant’s obligation to do so;
    (6) the defendant’s delay between at least November
    3, 2015, and November 27, 2015, in submitting a written
    change order request based on its repeated oral claim
    that several of the EPA requirements specified in the
    approval letter were the basis for a change in the con-
    tract despite TRC’s equally repeated response that such
    a claim would only be considered if submitted in writing
    pursuant to the contract; (7) the failure to submit a
    revised [health and safety plan]; (8) the failure to submit
    a demolition work plan; (9) the November 20, 2015 letter
    from the defendant and statement at the December 8,
    2015 job meeting advising the plaintiff that the defen-
    dant would not proceed with any further work on the
    job until a CWP was done; (10) its statement in that
    same letter and at the job meetings on November 24,
    2015, December 1, 2015, and December 8, 2015, that it
    would not perform any work if [it] was required to
    sample the steel; (11) that the issues on the character-
    ization of the steel and the paint chip testing were still
    to be resolved; (12) that less than 10 percent of the
    work called for on the project had been completed as
    of both December of 2015 and the date of the termina-
    tion; and (13) based on its December 15, 2015 letter to
    the plaintiff claiming a ninety-four day delay due to
    plaintiff’s actions and the defendant’s own proposed
    revised project schedule that called for a completion
    date of May 4, 2016. Given these facts, it is clear that
    it would have been impossible for the defendant to
    have finished the job by February 6, 2016.’’ (Footnotes
    omitted.)
    These findings provide ample support for the court’s
    determination that, in December, 2015, the defendant
    could not have finished the job in a timely manner as
    required under the contract. Therefore, the defendant’s
    challenge to the court’s implicit determination that the
    plaintiff lawfully had terminated the contract is unavail-
    ing.16
    D
    The defendant next claims that evidence of certain
    change orders executed by the plaintiff in connection
    with its contract with Costello, pursuant to which the
    plaintiff had agreed to modify terms of that contract,
    constituted admissions that the plaintiff’s contract with
    the defendant was defective and could not be performed
    by the defendant as written. We disagree.
    In its memorandum of decision, the court found that
    Costello submitted eleven change order requests during
    the course of its work on the project and that most of
    those requests were approved by TRC. The court further
    stated: ‘‘The defendant has argued that the court should
    also consider the conduct of the plaintiff in its handling
    of the similar contract with Costello following the rebid
    of the project. The defendant argues that, as to Costello,
    TRC allowed change orders similar to those asked for
    [by the defendant] and denied to the defendant by TRC,
    and that those change orders often revolved around the
    requirements for testing and decontamination. This, the
    defendant contends, is an admission on the part of the
    plaintiff as to the actual intent of the contract, which
    was that the original obligation for the testing of PCB
    contamination was that of the plaintiff. To this end, the
    defendant cites Putnam Park Associates v. Fahne-
    stock & Co., 
    73 Conn. App. 1
    , 10–11, 
    807 A.2d 991
     (2002),
    for the general proposition that a court may use the
    parties’ actions as an aid to determine the meaning of
    the contract. While that general proposition is true, the
    defendant’s reference to the case is misplaced, as the
    defendant asks the court to look at the actions of the
    plaintiff with respect to a different party on a different,
    albeit similar, contract. . . . The plaintiff’s actions do
    not involve the same two parties and, therefore, the
    principle cited is inapplicable.’’ (Citation omitted.) We
    agree with the court.
    The fatal flaw in the defendant’s argument is its fail-
    ure to acknowledge the basis for the change orders
    sought by Costello. Approximately eight months after
    the defendant’s contract with the plaintiff was termi-
    nated, the defendant directly contacted the EPA by
    e-mail regarding certain paint chip sampling requested
    by the defendant as part of this litigation that was to
    be performed on the site in accordance with an order
    of the trial court dated August 19, 2016.17 This resulted
    in a series of e-mails and telephone calls between the
    defendant and representatives of the EPA and had the
    effect of interrupting the work being performed by Cos-
    tello. Subsequently, TRC submitted to the EPA a plan
    proposed by Costello for PCB sampling, after which a
    series of correspondence between the plaintiff and the
    EPA followed. Those exchanges included ‘‘a comment
    by the EPA that should the paint chip samples sought
    by the defendant (in the court action) reveal PCBs in
    the paint, a change to the decontamination plan might
    be necessary.’’ The results of that paint chip sampling
    did prompt the EPA to require additional testing of the
    steel beams and other materials, including testing of
    roofing material, which caused additional expenses and
    delayed the project. Significantly, the court found that,
    ‘‘[a]t no time before the defendant unilaterally inter-
    vened by contacting the EPA with the court ordered
    paint chip sample results on November 21, 2016, did
    the EPA expressly require the plaintiff to do any paint
    chip sampling and provide the results thereof.’’
    Following its examination of the language of the con-
    tract and the approval letter, and its consideration of
    the expert testimony presented,18 the court found that
    paint chip sampling was not required to be done by the
    plaintiff under its contract with the defendant. That
    finding is supported by the record and is not clearly
    erroneous. The defendant’s claim, therefore, that the
    change orders granted to Costello in connection with
    the additional paint chip testing requirements imposed
    by the EPA, which were not part of the defendant’s
    contract with the plaintiff, constituted an admission by
    the plaintiff that its contract with the defendant could
    not be performed without such testing is contrary to
    the record and fails.
    II
    THE CROSS APPEAL
    In its cross appeal, the plaintiff challenges the court’s
    award and calculation of damages. Specifically, the
    plaintiff claims that the court erred in its award and
    calculation of damages with respect to the following:
    (1) ‘‘the court interpreted the contract’s liquidated dam-
    ages . . . provision . . . as the only measure of dam-
    ages available for all elements of the [plaintiff’s] loss
    when that provision is not the exclusive measure of
    damages for breach and does not preclude the award
    of the [plaintiff’s] nondelay damages, inclusive of direct
    and consequential damages unrelated to delay in [the
    project’s] completion’’; (2) ‘‘there is no lawful basis for
    limiting per diem [liquidated damages] to 254 days’’;
    and (3) ‘‘the court erred in its prospective calculation
    of damages by not taking into account the $167,652
    paid by the [plaintiff] to [the defendant] when it com-
    pared [the defendant’s] and Costello’s contracts for the
    purpose of determining the [plaintiff’s] completion
    costs.’’19 We agree with the plaintiff’s first claim.
    We first set forth the following findings concerning
    the issue of damages made by the court in its memoran-
    dum of decision: ‘‘[T]he plaintiff has submitted a sum-
    mary of damages with supporting documentation claim-
    ing an amount due of $1,855,936. . . . Categorically,
    the claimed damages fall into three areas. First, the
    difference in the contract price between the defendant
    and Costello for the job to be done. Second, additional
    expenses for the rebidding of the job and the engi-
    neering support that went with it. Third, project dam-
    ages for both contractual liquidated damages and addi-
    tional work the plaintiff was required to do as a result
    of the defendant’s unilateral communications with the
    EPA following its dismissal from the job.
    ‘‘As to the first category, the difference in the contract
    price, the defendant’s accepted bid in June, 2015, was
    $2,713,950. Upon rebid in March, 2016, Costello was
    awarded the contract for $2,962,207. The difference is
    an additional cost of $248,257. . . . The bid forms pro-
    vided to the bidders between the original bid and the
    rebid were identical but for the assumption of the credit
    for salvageable steel. The original bid form estimated
    1000 tons and the rebid form estimated 2400 tons. Both
    indicated that the quantity and value of the salvageable
    steel was at the contractor’s sole risk/reward.
    ‘‘As to the second category, the additional expenses
    for the rebidding of the job and the engineering support
    that went with it, the plaintiff claims payments of
    $167,652 made to the defendant, payments of $92,300
    toward construction support in 2015, the escalation of
    unit prices resulting in an additional cost of $17,913,
    payments of $47,230 toward the support of the rebid
    process, $23,800 for the disposal of bags with asbestos
    containing material that had been left on-site by the
    defendant, $10,259 for fencing, and $583 for advertise-
    ment of the project rebid. These expenses total
    $359,737. The court finds evidentiary support for most
    of the claimed expenses. However, the expense of
    $167,652 is not properly claimed as damages as these
    were payments for work done by the defendant, which
    had been approved by TRC following the submission
    of the defendant’s first two pay applications. . . .
    Accounting for that payment, the total expenses claimed
    are $192,085.
    ‘‘As to the final category, project damages for both
    contractual liquidated damages and the additional work
    the plaintiff was required to do as a result of both the
    court action and the defendant’s communications with
    the EPA following its dismissal from the job, the plaintiff
    claims a total amount due of $1,247,942. The largest
    component of the figure comes from the claim of liqui-
    dated damages in the amount of $520,000 for the 260
    day period commencing from February 1, 2016, at the
    rate of $2000 per day. In order to complete the work that
    remained to be done after the defendant’s dismissal,
    Costello’s March 31, 2016 bid of $2,962,207 was
    accepted by the plaintiff. . . . Costello later com-
    menced work on the project on essentially the same
    terms as the defendant. Following Costello’s prepara-
    tion of a CWP and other minor work, it received notice
    from the plaintiff on October 5, 2016, that the EPA had
    approved the CWP and [that it] could commence work
    in earnest. . . . However, in the fall of 2016, additional
    work was required to be done on the project, which
    included additional PCB [testing] and . . . testing [of
    asbestos containing materials], decontamination, shear-
    ing and sizing of steel beams, site maintenance, and
    disposal of additionally identified contaminated waste
    and other tasks. These specific costs were reflected in,
    but not limited to, change orders [numbers] 3, 5, 6, 7,
    8, 9, 10 and 11. . . . All of the other additional work
    was necessary as a result of Insall’s correspondence
    on behalf of the defendant to the EPA between Septem-
    ber 1, 2016, and November 21, 2016, long after the defen-
    dant had been dismissed from the job. That correspon-
    dence raised the issue of paint chip testing for PCB
    contamination at the site and claimed that other debris
    had come in contact with contaminated soil. This neces-
    sitated stopping work on the project from December 5
    to December 16, 2016, and eventually resulted in at
    least an additional 200 paint chip tests. . . . Some of
    the other damages claimed, outside of the change
    orders, related to the paint study that had been initiated
    but not completed, and the potential for additional dis-
    posal costs related to the steel. The total amount
    claimed as to all of these actual and estimated costs is
    $1,247,942.
    ‘‘With respect to that third category, the plaintiff’s
    claim of liquidated damages for the defendant’s failure
    to timely complete the job is for 260 days commencing
    from February 1, 2016, to October 19, 2016. . . . The
    contract called for completion of the work by that date
    (i.e., within 140 days). Article 2, § 2.1.1 of the contract
    states: ‘Failure of the Contractor to meet this estab-
    lished timeframe will result in liquidated damages being
    assessed in the amount of $2,000/day for each and every
    calendar day beyond the contract time limit.’ . . . In
    this instance, the plaintiff claims a total of $520,000. As
    previously noted, the court has found that there was
    an extension of the contract to February 7, 2016. There-
    fore, the claim must be adjusted to a commencement
    date of February 7, 2016, for a revised total of 254 days
    at $2000 per day for a total of $508,000.’’ (Citations
    omitted.)
    The court next examined the liquidated damages pro-
    vision of the contract and determined that it was a valid,
    enforceable provision of the contract, as it met the three
    criteria necessary to establish that the provision is one
    for liquidated damages and not a penalty. The court,
    after citing the principle set forth in Hanson Develop-
    ment Co. v. East Great Plains Shopping Center, Inc.,
    
    195 Conn. 60
    , 64, 
    485 A.2d 1296
     (1985), that ‘‘a seller
    may not retain a stipulated sum as liquidated damages
    and also recover actual damages,’’ concluded that the
    plaintiff was ‘‘limited in its claim of damages to those
    attributable under its liquidated damages provision,
    article 2, § 2.1.1. Although such damages are often typi-
    cally determined by when the job is finally completed
    by the breaching party, here the plaintiff dismissed the
    defendant from the job. Costello was hired to finish the
    job, but because of the defendant’s interaction with the
    EPA and the subsequent additional work and testing,
    it was unable to do so as the funds available to the
    plaintiff to complete the project were exhausted.
    Although the job was never completed, the plaintiff
    has not sought liquidated damages beyond 260 days
    (adjusted to 254 days), which falls shortly after Costello
    received notice of the EPA’s approval of the CWP. Thus,
    the total amount of liquidated damages due the plaintiff
    is found to be $508,000.
    ‘‘As to any finding of damages, it remains for the
    court to address the retainage20 held by the plaintiff in
    excess of the statutory limits set forth in . . . § 49-
    41b,21 as noted in the discussion of count one of the
    defendant’s counterclaim. That statute limits the
    amount of retainage held by a municipality in any public
    work contract to 5 percent of any periodic or final
    payment due a general contractor. In this instance, arti-
    cle 4, § 4.1.5 of the contract, entitled ‘Retainage,’ states,
    ‘[T]he [plaintiff] shall retain ten percent (10%) . . . of
    each estimate until final completion and acceptance of
    all work covered by this contract.’ . . . A review of
    the pay applications submitted by the defendant and
    approved by TRC show that $18,628 was held as
    retainage, which represented 10 percent of the amount
    of the work deemed completed by the defendant. . . .
    The amounts withheld by the plaintiff comport with the
    terms of the contract, which both parties had volunta-
    rily and mutually agreed to. Nonetheless, they are both
    bound by the statute. As a result, the correct amount
    of retainage held should have been $9314. Accordingly,
    the court will set off the excess retainage of $9314
    against the amount due the plaintiff, bringing the total
    damage award to $498,686. The remaining retainage
    held by the plaintiff in the equal amount of $9314 shall
    be credited toward the plaintiff’s damages pursuant to
    article 5, § 5.1. That provision allows the plaintiff to
    withhold any further payments to the contractor when
    it has failed to complete the work within the time period
    called for by the contract. Allowing this second amount
    as a credit to the defendant, given that the amounts are
    already in the possession of the plaintiff, an additional
    adjustment of $9314 is made to the award of damages,
    further reducing the total amount due the plaintiff to
    $489,372.’’ (Citations omitted; footnotes added.) In mak-
    ing those findings, the court relied on the testimony of
    Doubleday, Zarba and Mike Costello, along with other
    documentary evidence submitted by the plaintiff.
    Before we address the merits of the claims on the
    cross appeal, we set forth our standard of review. ‘‘As
    a general rule, in awarding damages upon a breach of
    contract, the prevailing party is entitled to compensa-
    tion which will place [it] in the same position [it] would
    have been in had the contract been properly performed.
    . . . Such damages are measured as of the date of the
    breach. . . . For a breach of a construction contract
    involving defective or unfinished construction, dam-
    ages are measured by computing either (i) the reason-
    able cost of construction and completion in accordance
    with the contract, if this is possible and does not involve
    unreasonable economic waste; or (ii) the difference
    between the value that the product contracted for
    would have had and the value of the performance that
    has been received by the plaintiff, if construction and
    completion in accordance with the contract would
    involve unreasonable economic waste.’’ (Internal quota-
    tion marks omitted.) Naples v. Keystone Building &
    Development Corp., 
    295 Conn. 214
    , 224, 
    990 A.2d 326
    (2010); see also Duffy v. Woodcrest Builders, Inc., 2
    Conn. Cir. 137, 143, 
    196 A.2d 606
     (1963) (‘‘[i]n the case
    of a defaulting building contractor, the situation is nor-
    mally that of recovering the reasonable cost of getting
    the work done by another’’ (internal quotation marks
    omitted)).
    ‘‘The [injured party] has the burden of proving the
    extent of the damages suffered. . . . Although the
    [injured party] need not provide such proof with [m]ath-
    ematical exactitude . . . the [injured party] must nev-
    ertheless provide sufficient evidence for the trier to
    make a fair and reasonable estimate. . . . As we have
    stated previously, the determination of damages is a
    matter for the trier of fact. . . . Accordingly, we review
    the trial court’s damages award under the clearly erro-
    neous standard, under which we overturn a finding of
    fact when there is no evidence in the record to support
    it . . . or when although there is evidence to support
    it, the reviewing court on the entire evidence is left
    with the definite and firm conviction that a mistake has
    been committed.’’ (Internal quotation marks omitted.)
    DeMattio v. Plunkett, 
    199 Conn. App. 693
    , 721–22, 
    238 A.3d 24
     (2020).
    A
    The plaintiff claims that the court erred in determin-
    ing that the contract’s liquidated damages provision
    was the exclusive measure of damages for breach of
    the contract. We agree.
    We first set forth general principles governing liqui-
    dated damages. ‘‘The law is well established in this
    jurisdiction, as well as elsewhere, that a term in a con-
    tract calling for the imposition of a penalty for the
    breach of the contract is contrary to public policy and
    invalid, but a contractual provision fixing the amount
    of damages to be paid in the event of a breach is enforce-
    able if it satisfies certain conditions. . . . A contractual
    provision for a penalty is one the prime purpose of
    which is to prevent a breach of the contract by holding
    over the head of a contracting party the threat of punish-
    ment for a breach.’’ (Citations omitted.) Berger v. Sha-
    nahan, 
    142 Conn. 726
    , 731, 
    118 A.2d 311
     (1955). ‘‘A
    provision for liquidated damages [on the other hand]
    . . . is one the real purpose of which is to fix fair
    compensation to the injured party for a breach of con-
    tract. In determining whether any particular provision
    is for liquidated damages or for a penalty, the courts
    are not controlled by the fact that the phrase liquidated
    damages or the word penalty is used. Rather, that which
    is determinative of the question is the intention of the
    parties to the contract. Accordingly, such a provision
    is ordinarily to be construed as one for liquidated dam-
    ages if three conditions are satisfied: (1) The damage
    which was to be expected as a result of the breach of
    the contract was uncertain in amount or difficult to
    prove; (2) there was an intent on the part of the parties
    to liquidate damages in advance; and (3) the amount
    stipulated was reasonable in the sense that it was not
    greatly disproportionate to the amount of the damage
    which, as the parties looked forward, seemed to be
    the presumable loss which would be sustained by the
    contractee in the event of a breach of the contract.’’22
    (Internal quotation marks omitted.) Tsiropoulos v. Rad-
    igan, 
    163 Conn. App. 122
    , 127–28, 
    133 A.3d 898
     (2016);
    see also Banta v. Stamford Motor Co., 
    89 Conn. 51
    , 54,
    
    92 A. 665
     (1914) (‘‘ ‘As a general rule parties are allowed
    to make such contracts as they please, including con-
    tracts to liquidate and fix beforehand the amount to be
    paid as damages for a breach of such contracts; but
    the courts have always exercised a certain power of
    control over contracts to liquidate damages, so as to
    keep them in harmony with the fundamental general
    rule that compensation shall be commensurate with
    the extent of the injury. . . . When the nature of the
    engagement is such that upon a breach of it the amount
    of damages would be uncertain or difficult of proof,
    and the parties have beforehand expressly agreed upon
    the amount of damages and that amount is not greatly
    disproportionate to the presumable loss, their
    expressed intent will be carried out.’ ’’).
    Because the plaintiff’s challenge to the court’s inter-
    pretation of the liquidated damages provision in the
    contract as being the plaintiff’s exclusive remedy for
    the defendant’s breach of the contract involves a matter
    of contract interpretation, we set forth our well estab-
    lished standard of review governing such claims.
    ‘‘[W]here there is definitive contract language, the deter-
    mination of what the parties intended by their contrac-
    tual commitments is a question of law. . . . Because
    a question of law is presented, review of the trial court’s
    ruling is plenary, and this court must determine whether
    the trial court’s conclusions are legally and logically
    correct, and whether they find support in the facts
    appearing in the record. . . . [T]he intent of the parties
    [to a contract] is to be ascertained by a fair and reason-
    able construction of the written words and . . . the
    language used must be accorded its common, natural,
    and ordinary meaning and usage where it can be sensi-
    bly applied to the subject matter of the contract.’’ (Cita-
    tion omitted; internal quotation marks omitted.) Detar
    v. Coast Venture XXVX, Inc., supra, 
    74 Conn. App. 322
    –
    23.
    In the present case, liquidated damages are covered
    by article 2 of the contract. Article 2, § 2.1, which gov-
    erns the time frame of the contract, provides: ‘‘The
    contract period is established from the Notice to Pro-
    ceed issued by the Engineer for a period of 140 days,
    including weekends and holidays. The work should be
    substantially complete at that time, unless the Contrac-
    tor has been granted an extension by methods defined
    and prescribed herein.’’ That provision is followed by
    § 2.1.1, titled ‘‘Liquidated Damages,’’ which provides:
    ‘‘Failure of the Contractor to meet this established time-
    frame will result in liquidated damages being assessed
    in the amount of $2,000/day for each and every calendar
    day beyond the contract time limit.’’ Section 2.1.2 of
    article 2 further provides that time is of the essence23
    for the general performance of the contract and, addi-
    tionally, that, ‘‘[i]n the event the Contractor fails to
    perform the work in a timely manner due to the Contrac-
    tor’s poor planning, financial status, errors in construc-
    tion or any other reason directly attributed to the Con-
    tractor’s circumstances, the [plaintiff] may institute
    default proceedings against the Contractor to recover
    damages and losses.’’ (Emphasis added.)
    In making its determination that liquidated damages
    were the plaintiff’s exclusive remedy under the con-
    tract, the court cited Hanson Development Co. v. East
    Great Plains Shopping Center, Inc., supra, 
    195 Conn. 64
    , for the principle that ‘‘a seller may not retain a
    stipulated sum as liquidated damages and also recover
    actual damages.’’ Specifically, the court stated: ‘‘Where
    the parties have entered into a voluntary agreement as
    to how to address any potential damages from a breach
    of contract, such agreement if validly entered into is
    to be enforced. Therefore, the plaintiff’s claim for both
    liquidated damages and consequential damages is an
    attempt to have its cake and eat it too. In Saturn Con-
    struction Co. [v. Dept. of Public Works, Superior Court,
    judicial district of Hartford, Docket No. CV-XX-XXXXXXX-
    S (October 17, 1994), in which the court found enforce-
    able a liquidated damages provision in a state contract
    that provided for liquidated damages of $1000 per day
    for failure to complete a construction job in a timely
    manner], Judge Sheldon noted that it is possible,
    depending on the wording of the liquidated damages
    provision, to obtain both under narrow circumstances:
    ‘[A]lthough an unrestricted liquidated damages clause
    operates as a bar to the recovery of all actual or conse-
    quential damages for breach of the contract; Camp v.
    Cohn, 
    151 Conn. 623
    , 626, 
    201 A.2d 187
     (1964); parties
    to a contract may choose to narrow the scope of their
    liquidated damages clause by clearly expressing that
    intention either in the language of the clause itself or
    in the remaining language of the contract.’ For example,
    the clause could be limited to the loss of use of a
    proposed property. In the present case, interpreting the
    contract as a matter of law, the language of the liqui-
    dated damages clause is not limited in any way that
    would allow an independent claim for actual and conse-
    quential damages. The parties having agreed upon the
    terms of the liquidated damages clause, the court is not
    free to disregard it or read other terms into the con-
    tract.’’
    We conclude that the court improperly determined
    that liquidated damages were the plaintiff’s exclusive
    remedy under the contract. Our Supreme Court has
    ‘‘long . . . held that contracting parties may decide on
    a specified monetary remedy for the failure to perform
    a contractual obligation.’’ Bellemare v. Wachovia Mort-
    gage Corp., 
    284 Conn. 193
    , 203, 
    931 A.2d 916
     (2007).
    Moreover, ‘‘[p]arties to a contract may agree on the
    remedies available in the event of a breach of contract.
    If the language of the agreement discloses that the par-
    ties intended to limit the remedies to those stated, the
    agreement will be enforced and the party will be limited
    to the exclusive remedies outlined in the agreement.
    . . . A contract will not be construed to limit remedial
    rights unless there is a clear intention that the enumer-
    ated remedies are exclusive.’’ (Emphasis added; inter-
    nal quotation marks omitted.) International Marine
    Holdings, Inc. v. Stauff, 
    44 Conn. App. 664
    , 676, 
    691 A.2d 1117
     (1997). That principle is supported by the
    language of the Uniform Commercial Code and General
    Statutes § 42a-2-719 (1), under which the language of
    a limited remedy in a contract that is designed to be
    the sole exclusive remedy must be clearly expressed.
    See Gaynor Electric Co. v. Hollander, 
    29 Conn. App. 865
    , 871–72, 872 n.4, 
    618 A.2d 532
     (1993).
    The language of the contract in the present case does
    not support the court’s conclusion that liquidated dam-
    ages were the plaintiff’s exclusive remedy. The liqui-
    dated damages provision in § 2.1.1 of article 2, which
    provides that the failure of the contractor to meet the
    time frame established therein will result in liquidated
    damages, clearly applies to damages resulting from
    delay; there is no language expressly stating that such
    damages are the plaintiff’s exclusive remedy for a
    breach of the contract not related to the defendant’s
    delay in performance, and the fact that the contract
    provided for liquidated damages caused by the defen-
    dant’s failure to perform the work within the time frame
    set forth in the contract does not, by itself, demonstrate
    a clear intent that such delay damages are the exclusive
    remedy available to the plaintiff under the contract,
    which must be viewed in its entirety. See Vaccaro v.
    Shell Beach Condominium, Inc., 
    169 Conn. App. 21
    ,
    49, 
    148 A.3d 1123
     (2016) (‘‘[t]he contract must be viewed
    in its entirety, with each provision read in light of the
    other provisions . . . and every provision must be
    given effect if it is possible to do so’’ (internal quotation
    marks omitted)), cert. denied, 
    324 Conn. 917
    , 
    154 A.3d 1008
     (2017). In the present case, the time is of the
    essence provision in § 2.1.2 of article 2 of the contract
    specifically allows the plaintiff to institute default pro-
    ceedings against the defendant to recover ‘‘damages
    and losses’’ if the defendant fails ‘‘to perform the work in
    a timely manner due to the [defendant’s] poor planning,
    financial status, errors in construction or any other
    reason directly attributed to the [defendant’s] circum-
    stances . . . .’’ Notably, § 2.1.2 of article 2 does not
    reference ‘‘liquidated damages’’; instead, it refers to
    ‘‘damages and losses.’’ Because § 2.1.1 of article 2 of
    the contract specifically references ‘‘liquidated dam-
    ages,’’ the fact that § 2.1.2, instead, references ‘‘damages
    and losses’’ is evidence of a contractual intent to allow
    for the recovery of nondelay damages and losses, in
    addition to the liquidated damages due to delays
    allowed in § 2.1.1. To construe the contract otherwise
    would render that provision in § 2.1.2 superfluous. See
    Assn. Resources, Inc. v. Wall, 
    supra,
     
    298 Conn. 183
     (‘‘the
    law of contract interpretation . . . militates against
    interpreting a contract in a way that renders a provision
    superfluous’’ (internal quotation marks omitted)); see
    also Old Colony Construction, LLC v. Southington, 
    316 Conn. 202
    , 214–15, 
    113 A.3d 406
     (2015) (‘‘[w]hen a con-
    tract expressly preserves remedies following termina-
    tion, such a reservation must be given full effect absent
    evidence of a more limited intent’’).
    We next must reconcile our conclusion with the gen-
    eral principle cited by the trial court that ‘‘a plaintiff
    may not recover both liquidated damages and actual
    damages.’’24 McClintock v. Rivard, 
    219 Conn. 417
    , 430
    n.13, 
    593 A.2d 1375
     (1991). We hold that, under the
    specific language of the contractual provisions at issue
    here, our conclusion is not inconsistent with that princi-
    ple. When, as here, a liquidated damages provision is
    limited in its application to damages resulting from
    delays and does not expressly provide that liquidated
    damages are the exclusive remedy, it does not prevent
    the recovery of actual damages for items to which the
    liquidated damages provision does not apply, i.e., non-
    delay damages. See 22 Am. Jur. 2d, Damages § 539
    (2022) (‘‘[a] provision for liquidated damages does not
    prevent the recovery of actual damages caused by
    events that are not covered by the liquidated damages
    clause unless the contract expressly precludes the
    recovery of damages other than those enumerated’’).
    It stands to reason that, so long as the predicate for both
    awards is not the same, the recovery of both liquidated
    damages and actual or consequential damages will not
    result in an impermissible double award. Accordingly,
    although, because of the liquidated damages provision,
    the plaintiff cannot additionally recover actual or com-
    pensatory damages resulting from the delays caused by
    the defendant, the liquidated damages provision of the
    contract does not preclude the plaintiff from recovering
    from the defendant nondelay actual and consequential
    damages.
    Although Connecticut courts have not yet squarely
    addressed this issue,25 our conclusion is consistent with
    holdings of many state courts.26 For example, in Fra-
    man Mechanical, Inc. v. Dormitory Authority of the
    State of New York, Docket No. A1114-14, 
    2019 WL 1747007
    , *10 (N.Y. Sup. March 7, 2019) (decision with-
    out published opinion, 
    114 N.Y.S.3d 814
     (2019)), the
    Supreme Court of New York for Albany County stated:
    ‘‘Ordinarily, a party is awarded either actual damages
    or liquidated damages, but not both when the predicate
    for the awards is the same . . . . The rationale for this
    rule is that liquidated damages, by their nature, are in
    lieu of, not in addition to, other compensatory damages
    . . . . As a corollary, both actual and liquidated dam-
    ages are recoverable damages when the predicate for
    the awards differ in kind . . . . As the United States
    Supreme Court has observed: There is no reason why
    parties competent to contract may not agree that certain
    elements of damage difficult to estimate shall be cov-
    ered by a provision for liquidated damages and that
    other elements shall be ascertained in the usual manner.
    Provisions of a contract clearly expressed do not cease
    to be binding upon the parties, because they relate to
    the measure of damages . . . J.E. Hathaway & Co. v.
    United States, 
    249 U.S. 460
    , 464 [
    39 S. Ct. 346
    , 
    63 L. Ed. 707
     (1919)].’’ (Citations omitted; internal quotation
    marks omitted.)
    Our conclusion also gives effect to the plain language
    of article 2, § 2.1.2 of the contract, providing that, if the
    defendant failed to complete its work in a timely manner
    due to the various reasons set forth, including poor
    planning or ‘‘any other reason directly attributed to the
    [defendant’s] circumstances,’’ the plaintiff could insti-
    tute default proceedings to recover damages and losses,
    which necessarily must mean damages and losses other
    than those attributable to the delays. See Old Colony
    Construction, LLC v. Southington, supra, 
    316 Conn. 212
     (determination of whether defendant was entitled
    to default based remedies was governed by express
    terms of parties’ contract). It can be inferred from the
    court’s many findings in its comprehensive decision
    that the defendant’s failure to complete the work in a
    timely manner was due to poor planning or other rea-
    sons attributable to the work it agreed to perform, as
    the court found that the plaintiff had performed its
    obligations under the contract; that ‘‘the defendant may
    have used a mistaken basic assumption in making its
    bid and entering into the contract, which ultimately
    resulted in consequences adverse to it’’; that the defen-
    dant’s delay in doing the necessary testing and work
    was primarily the result of the defendant failing to ‘‘sub-
    mit an acceptable CWP, [health and safety plan] and
    demolition work plan to TRC so that it could, in turn,
    submit any needed documents to the EPA for its
    approval, which was necessary for substantive work to
    begin’’; that the defendant elected to demobilize from
    the site on or about November 20, 2015; that the defen-
    dant had refused to proceed with any further work until
    a CWP was done or if it was required to sample the
    steel; that, as of December, 2015, the defendant had
    finished less than 10 percent of the work required under
    the contract; and that the defendant had failed to
    account for the potential contamination or testing of
    some structural steel, which had been thought to have
    been recyclable and which, thereby, resulted in the need
    for additional work both in terms of time and labor.
    We conclude, therefore, that the court erroneously
    failed to determine whether the plaintiff proved that it
    had suffered any compensable actual or consequential
    nondelay damages and, if so, the amount of such dam-
    ages. Because the court did not make any factual find-
    ings about the existence and amount of the plaintiff’s
    compensable nondelay related damages, we must remand
    this case to the trial court for a new hearing in dam-
    ages.27 At trial, the plaintiff sought three categories of
    alleged nondelay damages: (1) the difference in the
    contract price between what the plaintiff agreed to pay
    the defendant and what it agreed to pay Costello alleg-
    edly for similar work; (2) additional costs associated
    with rebidding the job and the engineering support that
    went with it after the contract between the defendant
    and the plaintiff was terminated; and (3) additional
    costs to complete the job beyond Costello’s accepted
    bid. On the basis of the issues raised on appeal, we
    provide the following guidance as to questions the court
    should consider with respect to each category of dam-
    ages, given that these issues are certain to arise on
    remand.28
    With respect to the first category of damages—the
    difference in contract price between the plaintiff’s con-
    tract with the defendant and its contract with Costello—
    the plaintiff argues on appeal that ‘‘[t]he court erred in
    failing to account for [the $167,652 sum it had paid to
    the defendant] when it calculated the difference between
    [the defendant’s] and Costello’s contract price.’’ On
    remand, not only will the court need to calculate the
    difference in price between the two contracts, but it
    also will need to consider any differences in the scope
    of the two contracts, as well as the fact that the defen-
    dant’s contract with the plaintiff had been partially per-
    formed, which will factor into the court’s calculation
    of the cost of the remaining work covered under the
    plaintiff’s contract with Costello. Put another way, the
    plaintiff is entitled to damages for services that the
    defendant was supposed to complete but that Costello
    completed for a higher price.
    As to the second category of damages—damages
    associated with rebidding the project—the court will
    need to determine whether the requested damages are
    either delay or nondelay damages. For example, a claim
    that the plaintiff incurred additional costs to oversee
    the project because it was delayed would be covered
    by the liquidated damages clause of the parties’ contract
    and may not be additionally awarded as actual damages.
    On the other hand, the costs of drafting, printing, and
    distributing the new bid package and of reviewing bids
    submitted in response thereto would not be delay dam-
    ages because they are damages caused by the defen-
    dant’s failure to perform, rather than its delayed perfor-
    mance.
    Finally, for the third category of damages—the plain-
    tiff’s claimed additional costs to complete the job over
    Costello’s contract price—the court will need to deter-
    mine whether such costs naturally flow from the defen-
    dant’s default of its performance obligation under the
    parties’ agreement and whether they were foreseeable
    to the defendant. On remand, therefore, the court must
    determine if the alleged damages flowing from the
    defendant’s posttermination conduct have a sufficient
    nexus to its breaches of the contract, which the court
    found occurred in November and December, 2015, prior
    to when the plaintiff terminated its contract with the
    defendant in January, 2016. See Calig v. Schrank, 
    179 Conn. 283
    , 286, 
    426 A.2d 276
     (1979) (‘‘[i]t is hornbook
    law that to be entitled to damages in contract a plaintiff
    must establish a causal relationship between the breach
    and the damages flowing from that breach’’); Mead-
    owbrook Center, Inc. v. Buchman, 
    149 Conn. App. 177
    ,
    186, 
    90 A.3d 219
     (2014) (‘‘proof of causation . . . prop-
    erly is classified as part and parcel of a party’s claim for
    breach of contract damages’’); 3 Restatement (Second),
    Contracts § 346, p. 110 (1981) (in order to receive any-
    thing other than nominal damages, party must prove
    both that breach of contract ‘‘caused’’ loss and amount
    of loss). Additionally, ‘‘[a]s our Supreme Court has
    explained, [i]n an action founded . . . on breach of
    contract . . . the recovery of the plaintiffs [is] limited
    to those damages the defendant had reason to foresee
    as the probable result of the breach at the time when
    the contract was made. Neiditz v. Morton S. Fine &
    Associates, Inc., 
    199 Conn. 683
    , 689 n.3, 
    508 A.2d 438
    (1986); see also Meadowbrook Center, Inc. v. Buchman,
    [supra, 188–89] (under Connecticut law, the causation
    standard applicable to breach of contract actions asks
    . . . whether [the plaintiff’s damages] were foreseeable
    to the defendant and naturally and directly resulted
    from the defendant’s conduct).’’ (Internal quotation
    marks omitted.) Bruno v. Whipple, 
    186 Conn. App. 299
    ,
    311–12, 
    199 A.3d 604
     (2018), cert. denied, 
    331 Conn. 911
    , 
    203 A.3d 1245
     (2019). For example, if, because of
    the defendant’s breach, the cost of completion became
    greater due to adverse weather conditions that would
    not have impacted the project had the defendant prop-
    erly performed its obligations, the court would have
    to determine if such damages were foreseeable to the
    defendant and a natural consequence of the breach. On
    remand, the court will have to determine whether the
    plaintiff has made that necessary connection.
    B
    The last issue we must address is the plaintiff’s claim
    that the court erred in limiting the award of liquidated
    damages to 254 days. We disagree.
    In its memorandum of decision, the court specifically
    found that, ‘‘[a]lthough the job was never completed,
    the plaintiff has not sought liquidated damages beyond
    260 days (adjusted to 254 days), which falls shortly
    after Costello received notice of the EPA’s approval of
    the CWP. Thus, the total amount of liquidated damages
    due the plaintiff is found to be $508,000,’’ which the
    court adjusted to $489,372 after it accounted for the
    retainage held by the plaintiff. (Emphasis added.) In its
    cross appeal, however, the plaintiff seeks additional
    liquidated damages for a time period that was not
    requested at trial. Specifically, in its appellate brief,
    the plaintiff explains that it had calculated liquidated
    damages ‘‘through the date on which Costello reached
    the same point in the project where [the defendant] left
    off’’ on the basis of its ‘‘understanding that [liquidated
    damages] were not the exclusive measure of its dam-
    ages. The exhibit [submitted into evidence by the plain-
    tiff detailing the damages it sought] was compiled based
    on the premise that it would be unfair to seek [liquidated
    damages] against [the defendant] during Costello’s per-
    formance of project work.’’ Given the court’s determina-
    tion that liquidated damages were the plaintiff’s exclu-
    sive remedy under the contract, however, the plaintiff
    now claims on appeal that liquidated damages ‘‘should
    have been run through the date of the court’s decision
    on December 20, 2019, a period of 1413 days.’’
    This claim requires little discussion. It is well settled
    that ‘‘[a] party cannot present a case to the trial court
    on one theory and then seek appellate relief on a differ-
    ent one . . . . For this court to . . . consider [a] claim
    on the basis of a specific legal ground not raised during
    trial would . . . [be] unfair both to the [court] and to
    the opposing party.’’ (Emphasis omitted; internal quota-
    tion marks omitted.) Overley v. Overley, 
    209 Conn. App. 504
    , 512, 
    268 A.3d 691
     (2021). ‘‘[A]n appellate court is
    under no obligation to consider a claim that is not
    distinctly raised at the trial level. . . . The requirement
    that [a] claim be raised distinctly means that it must
    be so stated as to bring to the attention of the court
    the precise matter on which its decision is being asked.
    . . . The reason for the rule is obvious: to permit a
    party to raise a claim on appeal that has not been raised
    at trial—after it is too late for the trial court . . . to
    address the claim—would encourage trial by ambus-
    cade . . . .’’ (Emphasis in original; internal quotation
    marks omitted.) 
    Id., 511
    . In the present case, the plaintiff
    requested that the court award liquidated damages for
    a period of 260 days, which was adjusted by the court
    to account for a period of time in which the contract
    had been extended. The court awarded the plaintiff
    exactly what it had requested, with the exception of
    the adjustment, which the plaintiff has not challenged.
    We agree with the defendant that the plaintiff cannot
    on appeal now claim that the court should have based
    its award on a time period different from the one that
    the plaintiff relied on and requested at trial. See White
    v. Mazda Motor of America, Inc., 
    313 Conn. 610
    , 619–20,
    
    99 A.3d 1079
     (2014). Furthermore, the plaintiff’s claim
    is premised on the court’s determination that liquidated
    damages were the plaintiff’s exclusive remedy. Because
    we have concluded that the court erred in reaching that
    conclusion and that the plaintiff is entitled to actual or
    consequential nondelay damages to the extent they can
    be proved by a preponderance of the evidence, the
    premise of the plaintiff’s claim on appeal no longer
    exists. Accordingly, this claim fails.
    III
    CONCLUSION
    In summary, the court properly rendered judgment
    in favor of the plaintiff on its breach of contract claim.
    Although the court’s award of liquidated damages in
    the amount of $489,372 was proper, the court erred in
    concluding that liquidated damages were the plaintiff’s
    exclusive remedy under the contract, which does not
    expressly preclude the recovery of damages other than
    the liquidated damages resulting from delays and, in
    fact, expressly allows the plaintiff to seek recovery for
    ‘‘damages and losses’’ in addition to the delay related
    liquidated damages. The court, thus, erroneously failed
    to determine whether the plaintiff proved that it had
    suffered any compensable actual or consequential non-
    delay damages and, if so, the amount of such damages.
    As a result, we must remand this case to the court for
    a new hearing in damages.
    The judgment is reversed in part and the case is
    remanded for a new hearing in damages consistent with
    this opinion; the judgment is affirmed in all other
    respects.
    In this opinion the other judges concurred.
    1
    In its statement of issues, the defendant lists as its second issue
    ‘‘[w]hether the trial court erred as a matter of law by deciding that [the
    defendant] repudiated its obligations to perform under the contract . . . .’’
    In its brief, however, the defendant characterizes the issue as whether
    ‘‘[t]he trial court erred in holding that the [plaintiff] lawfully terminated [the
    contract].’’ Because the defendant has not briefed the issue relating to its
    repudiation of the contract, we decline to address it. See Regional School
    District 8 v. M & S Paving & Sealing, Inc., 
    206 Conn. App. 523
    , 539 n.12,
    
    261 A.3d 153
     (2021) (declining to review claim not briefed, which was
    deemed abandoned).
    2
    ‘‘EPA regulations define a ‘non-porous’ surface, in part, as follows: ‘Non-
    porous surface means a smooth, unpainted solid surface that limits the
    penetration of liquid containing PCBs beyond the immediate surface. . . .’
    
    40 C.F.R. § 761.3
     [2015] . . . .’’ (Citation omitted.)
    3
    ‘‘EPA regulations define a ‘porous’ surface as follows: ‘Porous surface
    means any surface that allows PCBs to penetrate or pass into itself including,
    but not limited to, paint or coating on metal . . . .’ 
    40 C.F.R. § 761.3
     [2015]
    . . . . Some of the structural steel on the site, including overhead cranes,
    had painted surfaces.’’ (Citation omitted.)
    4
    ‘‘[Article 1 of the contract defined ‘Contract Documents’ as follows]:
    Whenever the term ‘Contract Documents’ is used [in the contract], it shall
    include the Agreement, Information to Bidders, General Specifications, Bid
    Documents, Technical Specifications, Special Notes, Addenda, and Project
    Plans, including all modifications thereof incorporated in the documents
    before their execution.’’
    5
    On May 23, 2016, the defendant had filed a motion for an order preserving
    the site and for permission to inspect and test the site for possible PCBs
    and other environmental contaminants. In its motion, the defendant claimed
    that ‘‘[t]he tests [had to] be conducted to enable the defendant to determine
    if PCBs are present on structural steel to be demolished at, above or below
    acceptable levels and local, state and federal regulations,’’ and that ‘‘[t]he
    testing [was] critical because an issue in this case will be whether the
    structural steel, which may be contaminated or coated by PCBs, can be
    recycled in an unregulated manner or must be handled as excluded PCB
    bulk product waste/state of Connecticut regulated waste, PCB bulk product
    waste, and/or PCB remediation waste.’’ In response, the plaintiff filed a
    motion for a protective order barring the defendant from performing paint
    chip sampling for PCBs on the structural steel as proposed by the defendant
    in its motion for order. In an order dated August 19, 2016, which addressed
    the defendant’s motion for order and the plaintiff’s motion for a protective
    order, as well as the parties’ objections thereto, the court ordered the
    defendant to identify, through counsel, fifteen areas from which it would
    like to receive pieces of the structural components of the building, which
    were to be cut in pieces three to five inches in length, and the defendant
    was to have those pieces tested ‘‘in whatever way it want[ed]’’ at a laboratory
    agreed to by the parties.
    6
    Counts five and six of the defendant’s counterclaim had been stricken
    by the court, which rendered judgment in favor of the plaintiff on those
    counts. They are not at issue in this appeal.
    7
    In response to the defendant’s counterclaim, the plaintiff alleged ten
    special defenses. Specifically, the first, second, third, fourth and fifth special
    defenses cite to specific provisions of the contract as a bar to recovery by
    the defendant. The sixth special defense alleges that the plaintiff is protected
    by governmental immunity, the seventh, that the defendant did not mitigate
    its damages, the eighth, payment by the plaintiff, the ninth, that the defendant
    anticipatorily breached the contract, and the tenth, that the defendant con-
    tractually had assumed any risks relating to its performance under the
    contract. In its memorandum of decision, the court addressed the plaintiff’s
    special defenses to the six remaining counts of the defendant’s counterclaim
    and stated that ‘‘the court has elected to address the plaintiff’s first, second,
    third, fourth and fifth special defenses, with respect to the fourth count
    of the defendant’s counterclaim alleging negligent misrepresentation. The
    plaintiff has established those special defenses by a preponderance of the
    evidence. However, because the court has found [that] the defendant has
    failed to meet its burden of proof as to each [count] of its [counterclaim],
    [the court] need not further address any of the plaintiff’s special defenses.’’
    8
    General Statutes § 42-158i (3) defines ‘‘ ‘retainage’ ’’ as ‘‘a sum withheld
    from progress payments to the contractor or subcontractor, otherwise pay-
    able to a contractor or subcontractor by an owner conditioned on substantial
    or final completion of all work in accordance with the terms of a written
    or verbal construction contract, but does not include any sum withheld due
    to the contractor’s or subcontractor’s failure to comply with construction
    plans and specifications.’’
    9
    In its brief, the defendant argues that this case involves a question of
    statutory interpretation and, thus, that the sole applicable standard of review
    is plenary review. We disagree. As the plaintiff aptly points out in its brief,
    the plaintiff and the defendant have not asserted causes of action grounded
    on the application of a statute, regulation, or ordinance, whether federal or
    state. Instead, the causes of action asserted by the parties stem from the
    contract, and the court’s ruling was based on its interpretation of that con-
    tract.
    10
    ‘‘The trial court’s findings are binding upon this court unless they are
    clearly erroneous in light of the evidence and the pleadings in the record
    as a whole. . . . In applying the clearly erroneous standard of review,
    [a]ppellate courts do not examine the record to determine whether the trier
    of fact could have reached a different conclusion. Instead, we examine the
    trial court’s conclusion in order to determine whether it was legally correct
    and factually supported. . . . This distinction accords with our duty as an
    appellate tribunal to review, and not to retry, the proceedings of the trial
    court. . . . [I]n a case tried before a court, the trial judge is the sole arbiter
    of the credibility of the witnesses and the weight to be given specific testi-
    mony. . . . The credibility and the weight of expert testimony is judged by
    the same standard, and the trial court is privileged to adopt whatever testi-
    mony [it] reasonably believes to be credible. . . . On appeal, we do not
    retry the facts or pass on the credibility of witnesses.’’ (Internal quotation
    marks omitted.) DeMattio v. Plunkett, 
    199 Conn. App. 693
    , 711–12, 
    238 A.3d 24
     (2020).
    11
    The defendant’s reliance on 
    40 C.F.R. § 761.61
     (a) (2) is unavailing. Any
    obligation of the plaintiff to characterize the site adequately pursuant to
    that regulation relates to the plaintiff’s representations in its notification to
    the EPA, not to the defendant. The plaintiff’s obligations to the defendant
    arise under the contract, not the federal regulation.
    12
    ‘‘[T]o the extent that the court’s decision is founded on its credibility
    determinations, we cannot second-guess those determinations on appeal.’’
    Alpha Beta Capital Partners, L.P. v. Pursuit Investment Management, LLC,
    
    193 Conn. App. 381
    , 441, 
    219 A.3d 801
     (2019), cert. denied, 
    334 Conn. 911
    ,
    
    221 A.3d 446
     (2020), and cert. denied, 
    334 Conn. 911
    , 
    221 A.3d 446
     (2020).
    13
    The court found: ‘‘The defendant’s expert, Insall, testified that it was
    his opinion that paint chip testing was required. On cross-examination,
    however, Insall first acknowledged that he could not say whether the painted
    steel was to be treated as bulk product waste or remediation waste. This
    of course would affect what test might be appropriate, or, if any test would be
    required at all. Secondly, Insall acknowledged that the EPA had information
    available to it from phase II of the project that referenced painted building
    columns, that the EPA had approved surficial (wipe) samples for painted
    surfaces including columns, that the EPA had the discretion to allow this,
    and that it never revoked its September 1, 2015 approval letter.
    ‘‘Insall also testified that paragraph 13 of the approval letter dealt with
    site characterization. Yet, a reading of that paragraph says nothing about
    characterization of the site or any action necessary to make a characteriza-
    tion. Insall even conceded that if material referenced was considered as
    bulk waste product, there is no characterization requirement under 
    40 C.F.R. § 761
    . A site characterization is done in the process of obtaining an approval
    letter, not as a condition of the approval.
    ‘‘With respect to the disposal standards relative to contamination and
    recyclability, Insall opined that the standards referenced were for the over-
    head steel cranes and not the steel beams. However, this makes little sense
    as the wording of the letter places the cranes and beams together in the
    same sentence in the description of cleanup standards for nonporous sur-
    faces. Insall further opined that there was a distinction between ‘columns’
    and ‘beams’ in that columns were vertical and beams were horizontal. The
    importance of the distinction to Insall was that dust accumulates on hori-
    zontal beams and that paragraph 13 only covers horizontal beams. On its
    face, Insall’s testimony clearly implies that dust did not accumulate on the
    vertical beams, which borders on being a ludicrous statement. See State v.
    Zayas, 
    195 Conn. 611
    , 620, 
    490 A.2d 68
     (1985) (‘[i]t is an abiding principle
    of jurisprudence that common sense does not take flight when one enters
    a courtroom’).
    ‘‘While the report Insall submitted to the EPA (which was put into evi-
    dence) was highly detailed, his credibility was put into issue by his testimony.
    To the extent there was credible evidence put forth, it does not outweigh
    the collective testimony of the plaintiff’s experts on the subjects addressed.’’
    14
    The basis for the defendant’s claim of negligent misrepresentation by
    the plaintiff at trial was its assertion that the plaintiff had misrepresented
    the condition of the steel beams. The court, however, found that the defen-
    dant had failed to prove its claim of negligent misrepresentation by a prepon-
    derance of the evidence and, in addition, had waived any such claim of
    misrepresentations by the plaintiff as to the condition of the steel beams
    under various provisions of the contract. Specifically, the court found that,
    ‘‘[t]he plaintiff had disclosed in advance to all prospective bidders, including
    the defendant, up to the date of the signing of the contract, all project
    documents and historical data that had been acquired through phases I and
    II, as well as a copy of the proposed contract and supporting documents,
    and eventually, the EPA approval letter.’’ The court examined the bidding
    documents and contractual provisions, which make clear that the bidder
    was responsible for investigating the physical condition of the site and could
    not rely on information provided by the plaintiff. For example, § 3.7.1 of
    article 3 of the contract provides that ‘‘[the defendant] agrees that [it] shall
    not use or be entitled to use any such information made available to [it]
    through the contract documents or otherwise or obtained by [it] in [its]
    own examination of the site, as a basis of or ground for any claim against
    the [plaintiff] . . . .’’ The court found that the § 3.7.1 disclaimer provision,
    along with others in the contract, were sufficient to defeat the defendant’s
    claim of negligent misrepresentation. The court further noted that Kurt, who
    had prepared the CWP for the defendant, acknowledged in his testimony
    that he was aware of the provision in the phase III remediation plan that
    ‘‘referenced that the overhead steel cranes reportedly contained [a certain
    level of] surface contamination’’ and that, ‘‘[w]hen asked why the defendant
    had not done greater testing in light of the information and his having
    physically seen the cranes and other painted steel at the walk-through on
    the site, Kurt simply stated that it was ‘my error.’ ’’ The court, thus, concluded
    that the defendant had failed to establish that the plaintiff misled either the
    EPA or the defendant as to the condition of the site.
    With respect to the issue of waiver, the court found that, ‘‘[t]hroughout
    the process, the plaintiff advised the defendant and all other potential bidders
    they were not to rely on any representations made by the plaintiff, that it
    offered no warranties and that they should satisfy themselves through their
    own investigation as to the character and condition of the site.’’ As the court
    stated, ‘‘[w]hile claiming [that] the plaintiff had misrepresented the condition
    of the steel and thereby affected the ability of the defendant to properly
    bid and do the job, the defendant’s own affirmative statements, which are
    contractually binding, run counter to that position. The terms make clear
    that the defendant had carefully reviewed the documents made available
    to it, had physically viewed the site and was aware of conditions that might
    affect the cost and work to be done.’’ The defendant has not challenged the
    court’s findings regarding waiver on appeal.
    15
    See footnote 1 of this opinion.
    16
    To the extent that the defendant’s claim can be construed as a challenge
    to the court’s finding that it breached the contract, that claim fails as well,
    as the court’s finding that the defendant breached the contract was not
    clearly erroneous.
    17
    See footnote 5 of this opinion.
    18
    With respect to the change orders, the court found that ‘‘there was
    credible documentary and testimonial evidence from Doubleday, Zarba and
    Mike Costello to establish the validity of those expenses. . . . These
    expenses were a direct consequence of the defendant’s failure to complete
    the contract and its unilateral correspondence with the EPA subsequent to
    its dismissal from the job. That contact resulted in not only expanded PCB
    testing, it raised disposal costs and required both Costello and TRC to
    remain on the job much longer and to perform more work than originally
    anticipated.’’ (Citations omitted.)
    19
    In light of our conclusion that the issue of damages must be remanded
    to the court for a new hearing, we do not address the plaintiff’s third claim.
    20
    See footnote 8 of this opinion.
    21
    General Statutes 49-41b provides in relevant part: ‘‘When any public
    work is awarded by a contract for which a payment bond is required by
    section 49-41 and such contract contains a provision requiring the general
    or prime contractor under such contract to furnish a performance bond in
    the full amount of the contract price, the following shall apply . . . (3) If
    the awarding authority is a municipality, (A) the municipality shall not
    withhold more than five per cent from any periodic or final payment which
    is otherwise properly due to the general or prime contractor under the terms
    of such contract . . . .’’
    We note that, although § 49-41b has been amended by the legislature since
    the events underlying the present appeal; see, e.g., Public Acts 2016, No.
    16-104, § 1; those amendments have no bearing on the merits of this appeal.
    In the interest of simplicity, we refer to the current revision of the statute.
    22
    In the present case, the court found that the liquidated damages provi-
    sion was enforceable because all three criteria had been met to establish
    the validity of the liquidated damages provision: damages resulting from a
    breach of contract were uncertain at the time the parties entered into the
    contract; the parties clearly expressed their intent to liquidate damages in
    advance as expressed in article 2, § 2.1.1; and the amount stipulated was
    reasonable. The defendant did not challenge the enforceability of the liqui-
    dated damages provision at trial, nor has it challenged on appeal the court’s
    finding concerning its validity and enforceability. The court’s finding that
    the provision was valid and enforceable, thus, is not at issue in this appeal.
    23
    ‘‘When it is said that time is of the essence, the proper meaning of the
    phrase is that the performance by one party at the time specified in the
    contract or within the period specified in the contract is essential in order to
    enable him to require performance from the other party. . . . Its commonly
    understood meaning is that insofar as a time for performance is specified
    in the contract, failure to comply with the time requirement will be consid-
    ered to be a material breach of the agreement.’’ (Internal quotation marks
    omitted.) Blackwell v. Mahmood, 
    120 Conn. App. 690
    , 699 n.4, 
    992 A.2d 1219
     (2010).
    24
    ‘‘Actual or compensatory damages, the terms being synonymous, are
    damages in satisfaction of, or in recompense for, loss or injury sustained.’’
    (Internal quotation marks omitted.) Manning v. Pounds, 2 Conn. Cir. 344,
    346, 
    199 A.2d 188
     (1963).
    25
    In its brief, the plaintiff argues that Dean v. Connecticut Tobacco Corp.,
    
    88 Conn. 619
    , 625, 
    92 A. 408
     (1914), and Banta v. Stamford Motor Co., supra,
    
    89 Conn. 51
    , both support the principle that a liquidated damages provision
    in a contract does not preclude the nonbreaching party from seeking and
    being awarded damages for defective or unfinished construction, or for
    nondelay damages not covered by the liquidated damages provision. We
    disagree. One of the issues before our Supreme Court in Dean was whether
    the defendant was harmed by a jury instruction relating to the third count
    of its counterclaim, which alleged a claim for special damages through injury
    to harvested tobacco resulting from delay in the completion of a warehouse
    beyond the stipulated date. Dean v. Connecticut Tobacco Corp., supra, 624.
    The court concluded that, because the evidence in support of the claim for
    special damages was speculative, the jury instruction that there could be
    no recovery of those damages was amply justified. Id., 624–25. Furthermore,
    the court noted that the parties had a provision in their contract for liquidated
    damages to be recoverable for any delay in the completion of the work and
    stated that ‘‘[t]he parties having stipulated in advance as to the amount of
    damages recoverable, further recovery, or recovery upon some other basis,
    could not, of course, be had.’’ Id., 625–26. In Banta, the issue before our
    Supreme Court was whether the liquidated damages provision in the parties’
    contract providing for the recovery of liquidated damages in the event of
    delay in the completion of the construction of a pleasure boat was a penalty,
    which the law would not enforce. Banta v. Stamford Motor Co., supra, 54.
    The court determined that the provision was enforceable, as the amount of
    liquidated damages provided for in the contract was not unreasonable; id.,
    57; and stated that, because ‘‘[t]he defendant, by its contract with the plaintiff,
    agreed to pay these sums in the event named . . . [i]t must abide by its
    bargain . . . .’’ Id., 54. In neither case did our Supreme Court address the
    issue or conclude that a party may recover both liquidated damages and
    completion or other nondelay damages.
    26
    See Delaware Limousine Service, Inc. v. Royal Limousine Service,
    Inc., Docket No. C.A. 87C-FE-104, 
    1991 WL 89787
    , *1 (Del. Super. May 2,
    1991) (following general rule that liquidated damages provision does not
    prevent recovery of actual damages caused by events that are not covered by
    liquidated damages clause unless contract expressly provides that damages
    other than those enumerated shall not be recovered); Lawson v. Durant,
    
    213 Kan. 772
    , 775, 
    518 P.2d 549
     (1974) (same); Meyer v. Hansen, 
    373 N.W.2d 392
    , 395 (N.D. 1985) (same); Visa, Inc. v. Sally Beauty Holdings, Inc., Docket
    No. 02-20-00339-CV, 
    2021 WL 5848758
    , *12 (Tex. App. December 9, 2021)
    (same), petition for review filed (Tex. February 23, 2022) (No. 22-0024);
    VanKirk v. Green Construction Co., 
    195 W. Va. 714
    , 719, 
    466 S.E.2d 782
    (1995) (same), cert. denied, 
    518 U.S. 1028
    , 
    116 S. Ct. 2571
    , 
    135 L. Ed. 2d 1087
     (1996); see also A. Miner Contracting, Inc. v. Toho-Tolani County
    Improvement District, 
    233 Ariz. 249
    , 258, 
    311 P.3d 1062
     (Ariz. App. 2013)
    (‘‘a party may not receive actual and liquidated damages for the same injury;
    however, actual damages related to the cost of completion are separate and
    distinct from liquidated damages intended to compensate for injury resulting
    from delay’’), review denied, Arizona Supreme Court (March 21, 2014);
    Draper v. Westwood Development Partners, LLC, Docket No. CIV.A. 4428-
    MG, 
    2010 WL 2432896
    , *3 (Del. Ch. June 3, 2010) (‘‘[u]nless a contract
    provides that liquidated damages are to be the exclusive remedy for a
    breach, a liquidated damages provision does not preclude other relief to
    the nonbreaching party, if the actual damages are caused by an event not
    contemplated by the parties in the liquidated damages clause’’); Phillips v.
    Gomez, 
    162 Idaho 803
    , 810, 
    405 P.3d 588
     (2017) (‘‘a liquidated damages
    clause does not preclude a party from suing for actual damages if that right
    is preserved in the contract between the parties’’ (internal quotation marks
    omitted)); Spinella v. B-Neva, Inc., 
    94 Nev. 373
    , 376, 
    580 P.2d 945
     (1978)
    (claim that liquidated damages clause was sole measure of damages available
    was refuted by plain and unambiguous language of provision, which mani-
    fested intent that liquidated damages compensated only for delay in perfor-
    mance, and, thus, award of actual damages resulting from contractor’s defec-
    tive workmanship was proper); Construction Contracting & Management,
    Inc. v. McConnell, 
    112 N.M. 371
    , 377, 
    815 P.2d 1161
     (1991) (‘‘an award of
    actual damages unrelated to delay does not preclude an award of liquidated
    damages for delay-related damages’’ as ‘‘[t]he vice to be guarded against is
    a duplication of damages’’ (internal quotation marks omitted)); Noble v.
    Ogborn, 
    43 Wn. App. 387
    , 390, 
    717 P.2d 285
     (liquidated damages clause does
    not preclude party from seeking actual damages when that right is preserved
    in contract), review denied, 
    106 Wn. 2d 1004
     (1986).
    27
    In determining whether the liquidated damages clause was a reasonable
    estimate of damages and not a penalty, the court noted that the plaintiff
    presented credible evidence supporting specific items of damage and the
    amounts thereof. The context in which the court’s determinations were
    made, in its analysis of the reasonableness of liquidated damages, however,
    is different from that where the court actually would be making the required
    finding that the plaintiff proved its damages by a preponderance of the
    evidence. Thus, we cannot rely on the court’s findings regarding this evidence
    to direct that judgment be rendered for the plaintiff on the items and amounts
    identified by the court as supported by the evidence with respect to the
    reasonableness of liquidated damages. Furthermore, the plaintiff argues on
    appeal that the court miscalculated the amount of its actual damages with
    respect to at least one category of actual damages. For these reasons, we
    believe that a remand for a new damages hearing is required.
    28
    We do not intend this to be an exhaustive list of relevant issues for the
    court to consider at the damages hearing. We merely identify and address
    specific issues raised by the parties in this appeal.