The C.A. Harrison Companies, LLC v. Karen Evans and Charles Evans ( 2022 )


Menu:
  • Notice: This opinion is subject to formal revision before publication in the
    Atlantic and Maryland Reporters. Users are requested to notify the Clerk of the
    Court of any formal errors so that corrections may be made before the bound
    volumes go to press.
    DISTRICT OF COLUMBIA COURT OF APPEALS
    No. 19-CV-0690
    THE C.A. HARRISON COMPANIES LLC, APPELLANT,
    V.
    KAREN EVANS AND CHARLES EVANS, APPELLEES.
    Appeal from the Superior Court
    of the District of Columbia
    (CAR-3870-15)
    (Hon. Hiram E. Puig-Lugo, Trial Judge)
    (Argued December 1, 2020                                Decided January 13, 2022)
    Vanessa Carpenter Lourie for appellant.
    Victor E. Long for appellees.
    Before GLICKMAN, BECKWITH, and DEAHL, Associate Judges.
    DEAHL, Associate Judge: Karen and Charles Evans hired the C.A. Harrison
    Companies, LLC (CAH) to manage the renovation of their home. CAH was
    supposed to oversee and supervise the project’s general contractor, Capital Services
    Management, Inc. (CSMI). Unbeknownst to the Evanses, CSMI quit the job shortly
    after the renovation work began and CAH unilaterally and without consulting them
    2
    decided to fill the role of general contractor, a job it was not licensed to perform.
    Several months and several hundreds of thousands of dollars later, the Evanses
    discovered the unauthorized substitution, terminated their contract with CAH, and
    hired a new general contractor to complete the renovation.
    CAH sued for breach of contract. The Evanses counterclaimed, arguing they
    had no enforceable contract with CAH because it was not licensed to perform as a
    general contractor, yet filled that role in violation of the District’s home
    improvement regulations, 16 D.C.M.R. §§ 800, et seq. (2009). Because of that
    violation, the Evanses maintained that not only did they owe CAH nothing under
    their contract, but that they were entitled to a return of the funds they had already
    paid to CAH for its unlicensed work. The Superior Court agreed with the Evanses
    and ordered CAH to pay $314,394.35 in damages, an amount that included
    disgorgement of all funds the Evanses had paid to CAH after CSMI walked off the
    job. CAH now appeals, arguing that the home improvement regulations did not
    apply to it and, even if they did, the trial court erred in its calculation of damages.
    We disagree with CAH’s first argument. CAH assumed the role of general
    contractor and took on the responsibility of delivering the contracted-for renovations
    to the Evanses. It therefore had a “home improvement contract” with the Evanses,
    3
    and because it was not licensed as a home improvement contractor, its acceptance
    of progress payments “in advance of all work required to be performed” violated 16
    D.C.M.R. § 800.1. We agree with CAH, to an extent, on its second point. There
    appear to be several errors in how the trial court calculated damages. We therefore
    affirm the trial court’s judgment, save for its damages award, which we vacate and
    remand for reconsideration and recalculation.
    I.
    In February 2014, the Evanses entered into two contracts for the purpose of
    completing renovation work on a home they purchased in the District. The first was
    a development management agreement with CAH, in which CAH agreed to oversee
    the renovation project, including supervising the general contractor and ensuring the
    renovation project was completed according to the Evanses’ specifications. In
    exchange, the Evanses agreed to pay CAH $25,000 in management fees, paid in
    $5000 installments over the course of the project. The second was an agreement
    with a general contractor, CSMI, which agreed to perform the renovation work for
    $270,270.
    To finance the project, the Evanses obtained a loan from Sandy Spring Bank.
    The construction portion of the loan totaled $295,270, which covered the cost of the
    4
    renovation work under CSMI’s contract ($270,270) plus CAH’s management fee
    ($25,000). The terms of the loan set a draw schedule, which permitted the release
    of funds in increments roughly commensurate with how much of the work had been
    completed. To receive funds through the draw schedule, the Evanses had to submit
    an itemized draw request supported by the relevant documents, including any
    invoices reflecting the construction expenses. An inspector from the bank could
    then visit the worksite to ensure the work had been completed as represented. If
    confirmed, the bank would wire the requested funds. From the outset, the Evanses
    entrusted CAH with preparing the draw requests, receiving any funds wired from
    the bank, and disbursing the funds accordingly.
    Prior to the start of the renovation work, the Evanses purchased three cashier’s
    checks totaling $35,777: one payable to CAH for $5000, one payable to CSMI for
    $27,027, and one payable to an architect for $3750. Not long after, in June 2014,
    the renovation work began with demolition on the Evanses’ house. About a month
    later, CSMI stopped working on the renovation project. Instead of informing the
    Evanses of their general contractor’s departure, CAH assumed CSMI’s role and
    responsibilities.   From that point forward, CAH managed the subcontractors
    formerly hired by CSMI and began directly hiring and supervising its own
    subcontractors to complete the renovation work. CAH never disclosed this new
    5
    arrangement to the Evanses, who for many months believed it was still CSMI
    performing as their general contractor.
    During the time CAH was performing CSMI’s role, it submitted five draw
    requests to Sandy Spring Bank, and it received a total of $172,197.46.1 A fraction
    of that ($15,000) was for CAH’s management fee, while the remaining $157,197.46
    was for the construction costs of the renovation project. By the end of January 2015,
    a little over $87,000 remained on the loan to complete the renovation project, $5000
    of which was earmarked for CAH’s final management fee. But the renovation
    project then hit a standstill when the Evanses discovered CSMI was no longer
    working on the project, prompting them to terminate their contract with CAH and
    hire a new general contractor to complete the renovation.
    After its termination, CAH filed a Notice of Mechanic’s Lien on the Evanses’
    property, claiming it was owed the final $5000 management fee as well as
    $23,378.10 in costs CAH allegedly expended on the renovation project but was
    1
    The first draw occurred on August 20, 2014, totaling $31,177.54; the second
    draw occurred on September 17, 2014, totaling $29,457.64; the third draw occurred
    on September 26, 2014, totaling $54,002; the fourth draw occurred on December 9,
    2014, totaling $48,148.02; and the fifth draw occurred on January 21, 2015, totaling
    $9,412.26.
    6
    never reimbursed for. CAH then filed a complaint in the Superior Court of the
    District of Columbia to enforce the lien. The Evanses counterclaimed, alleging CAH
    performed work as a home improvement contractor without a proper license in
    violation of the District’s home improvement regulations, 16 D.C.M.R. §§ 800-899,
    so that whatever contractual relationship it had with CAH was null and void. The
    Evanses also counterclaimed for breach of contract and unlawful trade practices in
    violation of the D.C. Consumer Protection Procedures Act (CPPA), 
    D.C. Code §§ 28-3901
     to 3913 (2013 Repl.).
    Following a six-day bench trial, the trial court ruled predominantly for the
    Evanses. It found that CAH performed work as an unlicensed contractor after its
    assumption of CSMI’s responsibilities, rendering the contract between CAH and the
    Evanses null and void. The trial court refused to enforce the mechanic’s lien and
    determined that clear and convincing evidence existed that CAH engaged in
    unlawful trade practices under the CPPA. As for damages, the trial court ordered
    CAH to disgorge all payments it had received during the course of the renovation
    project, which the court believed totaled $207,973.08, and awarded an additional
    $106,421.26 for costs incurred by the Evanses to complete the renovation project
    after CAH was terminated. The trial court did not specify a theory of damages under
    which those additional costs were awarded.
    7
    CAH now brings this appeal. It argues that (1) the home improvement
    regulations do not apply to it because it was not a home improvement contractor,
    and (2) even if they do apply, the trial court erred in its calculation of damages. 2
    II.
    We begin with CAH’s lead argument, that the District’s home improvement
    regulations did not apply to it because it was not a home improvement contractor.
    The relevant regulation prohibits an unlicensed contractor from accepting payment
    “for a home improvement contract . . . in advance of the full completion of all work
    required to be performed under the contract.” 16 D.C.M.R. § 800.1; 3 see also
    Capital Constr. Co. v. Plaza West Coop. Ass’n, 
    604 A.2d 428
    , 429-30 (D.C. 1992).
    A “[h]ome improvement contract” is “an agreement for the performance of home
    2
    CAH also argues the trial court abused its discretion when it permitted the
    Evanses’ expert, Deborah Anderson, to testify as an expert witness in accounting.
    But as the Evanses point out, Anderson’s testimony “played no role in the trial
    court’s decision,” a point which CAH does not dispute. Any error in permitting
    Anderson to testify was thus harmless and we need not consider the issue further.
    See 
    D.C. Code § 11-721
    (e) (2012 Repl.) (“[T]he District of Columbia Court of
    Appeals shall give judgment after an examination of the record without regard to
    errors or defects which do not affect the substantial rights of parties.”).
    Section 800.1 was originally enacted as 5Y D.C.R.R. § 2.1 (1970) and the
    3
    modern regulation is identical in all material respects to its prior iteration. See
    Thompson v. Wolfrey, 
    483 A.2d 636
    , 636-37 & nn.1-2 (D.C. 1984).
    8
    improvement work for a contract price of three hundred dollars ($300) or more.” 16
    D.C.M.R. § 899.1 (2009). “Home improvement work” is, in turn, defined as “the
    addition to or alteration, conversion, improvement, modernization, remodeling,
    repair, or replacement of a residential property, or a structure adjacent to the
    residential property.” Id.
    A home improvement contract contravening this prohibition against
    unlicensed contractors accepting progress payments is “void and unenforceable,
    even on a quasi-contractual basis.” Capital Constr., 
    604 A.2d at 430
     (internal
    citations omitted). Thus, “[i]f an unlicensed contractor accepts payment before
    completion of work under the contract, . . . the contractor is not entitled to contract
    damages and must return any payment received for work performed.” Carlson
    Constr. Co., Inc. v. Dupont West Condo., Inc., 
    932 A.2d 1132
    , 1135 (D.C. 2007).
    Our court has heard the complaint that “the nullification of a contract effected
    by receipt of advance payments alone is [a] harsh and disproportionate” result,
    Cevern, Inc. v. Furbish, 
    666 A.2d 17
    , 20 (D.C. 1995), but we have consistently held
    that result is justified, citing two reasons. First, the regulation is not a blanket
    prohibition against contractors accepting progress payments, but requires only that
    a contractor be licensed before accepting such payments—“a simple administrative
    9
    matter” for the “qualified contractor.” 
    Id.
     Licensure provides “simple and sufficient
    proof” of the contractor’s qualifications to perform the work of a general contractor.
    
    Id. at 21
    . Second, the purpose of the District’s home improvement regulations is “to
    protect consumers against unscrupulous dealings by home improvement
    contractors.” Truitt v. Miller, 
    407 A.2d 1073
    , 1077-78 (D.C. 1979). “[A]nything
    but an unyielding rule would put temptation in the way of unqualified (and
    unscrupulous) contractors and invite recurrence of the same abuses that underlay
    enactment of the regulatory scheme.” Cevern, 
    666 A.2d at 20
    . For these reasons,
    “potential unfair applications of the rule at the margins have not persuaded us to
    sacrifice the benefits of a clear-cut, unmistakable requirement, with equally clear
    consequences for noncompliance, in this area of consumer protection.” 
    Id.
    CAH argues that § 800.1 does not apply to it because it did not have a home
    improvement contract with the Evanses. It does not dispute the well-established
    proposition that a general contractor who oversees a home improvement project and
    is charged with “the actual ‘delivery’ of a finished project” is subject to this home
    improvement regulation. Karr v. C. Dudley Brown & Assocs., Inc., 
    567 A.2d 1306
    ,
    1309 (D.C. 1989); see also Truitt, 
    407 A.2d at 1078-79
    . 4 Rather, CAH contends that
    4
    CAH does, at times, make arguments that seem to contravene the
    proposition. For instance, in its reply brief it suggests that CAH was not a home
    10
    it was neither hired nor paid to serve as the general contractor overseeing the
    Evanses’ project. In its view, it was a mere advisor on the project, similar to the
    consultant in Karr who we recognized fell outside of the regulation’s proscription
    against progress payments. See 
    567 A.2d at 1309-10
    . But CAH’s role in the
    renovation work went far beyond that of a mere consultant. CAH acted as the
    general contractor for the Evanses’ home improvement project when it assumed the
    authority to hire and supervise subcontractors, and took on the responsibility for final
    delivery.
    CAH simply does not resemble the consultant in Karr, which concerned an
    expert who was paid on an hourly basis to advise a general contractor on a home
    improvement contractor because its owner, Christopher Harrison, was never
    personally “doing any work on the project physically.” That is beside the point. Our
    precedents make clear that the home improvement regulations apply to general
    contractors. See, e.g., Karr, 
    567 A.2d at 1308-09
     (repeatedly stressing that
    consultant was “not a ‘general contractor’” because he was not charged with “actual
    ‘delivery’ of a finished product.”). General contractors typically are not the ones on
    the ground swinging the hammers, but instead insure, guarantee, and supervise the
    work of subcontractors. See General Contractor, Black’s Law Dictionary (10th ed.
    2014) (defining “General Contractor” as one “who contracts for the completion of
    an entire project, including . . . hiring and paying subcontractors, and coordinating
    all the work”); 16 D.C.M.R. § 899.1 (defining “home improvement contractor” as
    the one who “enters . . . into a home improvement contract with a homeowner”).
    11
    improvement project. 5 
    567 A.2d at 1307
    . In Karr, the consultant had no “direct
    authority over the work of” the general contractor. 
    Id. at 1308-09
    . It was the general
    contractor, not the consultant, who solicited bids from subcontractors, oversaw their
    work, and “assumed direct responsibility for completion of the renovation.” 
    Id. at 1309
    . Under those circumstances, we held that the consultant was not governed by
    the home improvement regulations and nothing prevented him from collecting his
    hourly wages prior to completion of the project. 
    Id. at 1309-10
    .
    Here, CAH has far more in common with the general contractor in Karr than
    the consultant. From the moment CSMI quit and stopped acting as the project’s
    general contractor, it was CAH that stepped into the role. It was CAH that contracted
    directly with subcontractors. It was CAH that exercised supervisory authority over
    the work performed by the subcontractors. Most importantly, it was CAH that took
    on the responsibility of delivering the final product and completing the project. CAH
    was not merely advising the Evanses or some other general contractor interposed
    between the parties. It was running the show. CAH needed a license to perform that
    role, and because it lacked one, its acceptance of progress payments violated § 800.1.
    5
    That project was for an older home and the general contractor “had no
    particular experience with older homes,” so (at the general contractor’s
    recommendation) the homeowners also hired a consultant to advise the general
    contractor on that aspect of the work. Karr, 
    567 A.2d at 1307
    .
    12
    We decline to narrow our focus to the four corners of the development
    management agreement CAH had with the Evanses and will not ignore CAH’s actual
    course of performance during the renovation project, as CAH suggests we should.
    Even if we were to take that approach, it appears the development management
    agreement is a home improvement contract on its terms. 6 In any event, our review
    is not so constrained. We have consistently used a more functional approach to
    determine whether an entity is covered by the home improvement regulations. In
    Karr, we noted the significance of the fact that the consulting contractor did not
    assume the role of the general contractor as the renovation project progressed,
    indicating that a party’s course of performance is important to assessing whether it
    fits within the regulations. 
    Id. at 1308
    . This approach also comports with our long-
    held recognition that the home improvement regulations must be interpreted to
    accomplish their “legislative purpose of protecting homeowners from fraudulent and
    unscrupulous practices in the home improvement industry.” Capital Constr., 
    604 A.2d at 430
    . Allowing CAH to evade licensing requirements despite its assumption
    6
    The development management agreement, as written, provided that CAH
    agreed to “cause the Work . . . to be completed,” “and to “supervise and inspect the
    progress of any Work at the Project until completion thereof . . . .” CAH’s owner
    further testified that the “purpose of the [development management] agreement
    [was] to make sure or assist the homeowners in making sure the project [was]
    completed.” Based on this language and testimony, the development management
    agreement seems to designate CAH’s role as a home improvement contractor rather
    than as a mere consultant.
    13
    of the general contractor’s role would provide a clear roadmap for other
    unscrupulous contractors to do likewise and would substantially undermine the
    regulations and licensing requirements.
    CAH also argues, citing Schloss v. Davis, that the home improvement
    regulations are “not applicable where the contractor . . . only serve[s] as a conduit
    for the payment to subcontractors for a fee.” 
    131 A.2d 287
     (Md. 1957). But Schloss
    (1) is not binding on this court, (2) does not have persuasive force because it was
    interpreting a very different set of Maryland regulations, and (3) does not apply on
    its own terms to the facts of this case. 7      In Schloss, the court observed that
    Maryland’s licensure requirements for general contractors were “for revenue and not
    for regulation,” so that a failure to obtain a contractor’s license should not render
    void a contract made absent the required license. 
    Id. at 291
    . CAH asserts that we
    endorsed Schloss’s reasoning when we “favorably cited” it in Truitt, but that
    mischaracterizes the case. In Truitt, all we said was that Schloss was not applicable
    on its own terms. Truitt, 
    407 A.2d at 1078-79
    . Moreover, we have since rejected
    Schloss’s reasoning as incompatible with our own regulations. In Cevern, we
    7
    When CAH assumed CSMI’s role as general contractor, it became
    responsible not only for transmitting funds to subcontractors, but also for their hiring
    and supervision. Indeed, as discussed above, CAH “was actually responsible for
    completing the project.” Karr, 
    567 A.2d at 1309
    .
    14
    explained, contra Schloss, that the District’s requirement that a general contractor
    be licensed is not “designed solely to raise revenue,” but instead serves the
    regulatory function of ensuring that general contractors are qualified to take on that
    role. 
    666 A.2d at 21
    .
    Having determined that the home improvement regulations apply to CAH—
    and that the parties indeed had a “home improvement contract”—we can easily
    dispense with CAH’s argument that it did not receive any payment for a home
    improvement contract. CAH does not dispute that it received close to $180,000 from
    Sandy Spring Bank during the course of, and prior to full completion of, the
    renovation project. Those payments were accepted by CAH (1) under a home
    improvement contract, and (2) before the work was fully completed. Therefore,
    because (3) CAH was not “licensed as a home improvement contractor,” (4) CAH
    contravened 16 D.C.M.R. § 800.1. Accordingly, we find that the trial court was
    correct that the contract between CAH and the Evanses was void and unenforceable,
    and that the Evanses were entitled to a return of all funds they had already paid to
    CAH under that home improvement contract. 8
    8
    In light of our determination that the contract between CAH and the Evanses
    was void and unenforceable, CAH’s argument that it was entitled to enforcement of
    its mechanic’s lien is without merit. See Cevern, 
    666 A.2d at 18
     (an unlicensed
    15
    III.
    CAH also challenges the trial court’s calculation of damages. The awarded
    damages fall into two categories: (1) disgorgement of funds paid out during the
    course of the renovation project, and (2) compensation for additional contract-like
    costs the Evanses incurred to complete the renovation project following CAH’s
    termination. CAH challenges both aspects of the awarded damages, claiming the
    disgorgement award was erroneously calculated and the additional damages were
    not permitted. We agree, to an extent, with each point.
    A.
    CAH does not dispute that disgorgement is a proper remedy for contracts
    performed in violation of the home improvement regulations. Our “court has long
    adhered to the policy of requiring an unlicensed home improvement contractor to
    return to the homeowner payment it received for the job if the contractor received
    the payment in advance of completion of the job at a time when it was unlicensed.”
    Remsen Partners, Ltd. v. Stephen A. Goldberg Co., 
    755 A.2d 412
    , 418 (D.C. 2000)
    contractor who violates the home improvement regulations “forfeit[s] the right to
    recover for work performed on either a contract or quantum meruit theory”).
    16
    (collecting cases).   CAH challenges only the trial court’s calculation of the
    disgorgement award, alleging three distinct errors.
    First, CAH argues the trial court ordered it to disgorge funds above and
    beyond the amount it received during the course of the renovation project. We agree.
    The trial court ordered CAH to disgorge $207,973.08 and return it to the Evanses.
    But that amount includes $30,777 worth of cashier’s checks the Evanses paid
    directly to CSMI ($27,027) and an architect ($3750) prior to the start of the
    renovation project. Because those amounts were not paid to CAH they should have
    been deducted from the amount ordered to be disgorged. The record evidence shows
    that CAH itself received $177,197.46, comprised of $157,197.46 for construction
    costs and $20,000 for its management fee. That is $30,775.62 less than what the
    trial court awarded, with the difference attributable to the cashier’s checks that
    should have been deducted. 9
    The Evanses do not dispute the factual point that the cashier’s checks paid out
    to third-party vendors were reflected in the disgorgement award. The trial court
    9
    There is a slight $1.38 discrepancy between the amount of the cashier’s
    checks ($30,777) and the amount that should be deducted to reflect the amount
    actually received by CAH ($30,775.62). The source of that discrepancy is not clear.
    17
    believed otherwise—that the cashier’s checks were funds expended above and
    beyond the $207,973 award. It was simply wrong about that. A summary of the
    $207,973 figure that the trial court relied upon in calculating its disgorgement award
    reflects a “Miscellaneous” cost totaling $30,777—the exact amount of the two
    cashier’s checks.   It is thus clear that the cashier’s checks were part of the
    $207,973.08 figure, and the Evanses acknowledged as much at trial and further
    conceded it during the oral argument on appeal. The trial court clearly erred when
    it concluded otherwise, leading to its erroneous failure to limit its disgorgement
    award to the money actually paid to CAH.
    Second, CAH argues the disgorgement award should not have included
    amounts CAH relayed to certain licensed subcontractors. This argument stems from
    the regulations’ definition of “home improvement work,” which exempts from its
    scope, “work performed by licensed electricians, plumbers and gasfitters, or
    refrigeration and air conditioning mechanics, so long as the work performed by them
    is limited to that of their licensed occupation.” 16 D.C.M.R. § 899.1. According to
    CAH, because the above-listed work does not qualify as “home improvement work,”
    any funds paid to subcontractors performing such work should have been subtracted
    from the trial court’s disgorgement award. We appeared to endorse that approach to
    excluding payments relayed to licensed subcontractors from any disgorgement
    18
    award in Truitt, in which we opined “where a home improvement contractor
    contracts to renovate an entire house . . . and subcontracts out certain responsibilities
    which have assurances of quality, the contractor should not be held liable for those
    operations should it be determined that the contractor was not duly licensed.” 
    407 A.2d at 1078
    . As an initial matter, it does not appear Truitt put the issue to rest. The
    point was conceded by the appellee in that case, see 
    id.,
     and the court seemed to
    accept that concession without focusing “the judicial mind . . . upon the precise
    question,” so that this statement might best be seen as dictum rather than binding
    precedent. Murphy v. McCloud, 
    650 A.2d 202
    , 205 (D.C. 1994) (“The rule of stare
    decisis is never properly invoked unless in the decision put forward as precedent the
    judicial mind has been applied to and passed upon the precise question.”).
    Even if we assume it is binding precedent, however, it does not help CAH
    here because CAH did not substantiate what amounts, if any, it passed on to licensed
    subcontractors. CAH directs us to over 200 pages of bank records reflecting invoices
    and checks supposedly paid out for work performed on the renovation contract, as
    well as a ledger which summarily references expenses for “electrical” or “plumbing”
    work. But the cited materials say nothing about whether those subcontractors had
    the appropriate licenses at the relevant times. There was no evidence from which
    the trial court might have deducted amounts paid to licensed subcontractors because
    19
    CAH never gave a particularized or substantiated account of any amounts paid to
    licensed subcontractors. While CAH faults the trial court for “wholly fail[ing] to
    make a determination of the sums paid to licensed contractors,” it was CAH that
    failed to provide the court with any factual basis for deducting such amounts from
    the damages that the Evanses established.
    Third, CAH repackages its argument that it did not accept any payment for a
    home improvement contract. Rather, in its view, any funds it received were either
    payment for its management fee or were funneled to subcontractors or vendors for
    services and construction materials, and to the extent it performed any general
    contractor functions it did so gratis.   This argument fails for reasons already
    articulated: following its assumption of CSMI’s responsibilities, any payment CAH
    accepted was payment for a home improvement contract and was therefore properly
    disgorged. See, e.g., Bathroom Design Inst. v. Parker, 
    317 A.2d 526
    , 528 (D.C.
    1974) (“[T]hose who do home improvement business without a license . . . [and]
    exact[] payment without performing . . . [must] pay back the fruits of [the] illegal
    agreement.”) (internal quotation omitted); Marzullo v. Molineaux, 
    651 A.2d 808
    ,
    810 n.3 (D.C. 1994) (“Any moneys paid may be recovered from the [unlicensed]
    contractor, and no quantum meruit may be awarded.”). This includes any payments
    CAH accepted but did not ultimately retain for its own financial gain. See generally
    20
    Truitt, 
    407 A.2d 1073
     (affirming trial court’s disgorgement of funds paid for work
    completed by subcontractors); Nixon v. Hansford, 
    584 A.2d 597
     (D.C. 1991)
    (affirming disgorgement of deposit used only to purchase materials rather than
    payment for skill or labor).
    In sum, the trial court erred when it failed to deduct from its disgorgement
    award the money the Evanses paid directly to CSMI and the architect, and on remand
    we instruct it to adjust the award to reflect only the funds actually received by CAH.
    B.
    In addition to disgorgement, the trial court awarded $106,421.26 to the
    Evanses for costs they incurred to complete the renovation project after terminating
    CAH: $60,190.37 for CAH’s refusal “to provide subcontractor information”; $4200
    for debris clean-up; $5160 for granite that was provided and not returned; $7442.32
    for tile; $2499.76 for bank costs resulting from a delay in the renovation project;
    $22,041.81 for rent payments; and $4887 for storage costs. The trial court did not
    articulate any theory for awarding these additional damages, and CAH contends
    there was no basis for them. The Evanses counter by floating two potential theories
    in defense of this additional award, arguing that it is justified either (1) under a
    breach of contract theory, or (2) for CAH’s violations of the D.C. Consumer
    21
    Protection Procedures Act (CPPA), 
    D.C. Code §§ 28-3901
    , et seq. Because it is not
    clear that these damages were appropriate under either theory, we remand for the
    trial court to vacate this additional award or, alternatively, to clarify the basis for it.
    If this amount was awarded under a breach of contract theory, that would raise
    several potential difficulties. First, the trial court never found that CAH breached
    any contract; it in fact seemed to rule against the Evanses on their breach of contract
    counterclaim. The Evanses pled a breach of contract counterclaim in conjunction
    with a tortious interference claim, and the trial court ruled that the claim for “tortious
    interference with contract [and] breach of contract is denied.” Second, it is not at all
    clear that the Evanses would be entitled to both recoup money they paid under a
    contract later determined to be void for CAH’s lack of licensure, and then further
    collect on a theory that CAH breached the nullified contract. Cf. Kent Homes, Inc.
    v. Frankel, 
    128 A.2d 444
    , 445 (D.C. 1957) (when a contract is procured by fraud,
    “if a party chooses to rescind [the contract] he cannot also recover damages for the
    fraud,” because those remedies are “mutually exclusive”). We recently declined to
    resolve that question in a similar context in HVAC Specialist, Inc. v. Dominion Mech.
    Contractors, Inc., but suggested that recovery might be limited to a return of the
    22
    money paid to an unlicensed contractor, to the exclusion of damages for breach of
    contract. 10 
    201 A.3d 1205
    , 1213-14 (D.C. 2019).
    In certain circumstances, special damages above and beyond disgorgement
    may be awarded following the rescission of a contract, “in order that the parties
    might be placed in status quo ante.” See Kent Homes, 
    128 A.2d at 446
    ; see also
    Family Constr. v. District of Columbia Dep’t of Consumer & Reg. Affairs, 
    484 A.2d 250
    , 255 (D.C. 1984) (return of money paid and restoration of property to status quo
    ante allowed where contract found void). But if that was the trial court’s basis for
    these additional amounts, it needs to explain why (in its view) this additional
    $106,421.26 was necessary to restore the Evanses to their pre-contract position,
    because all indications are that this additional amount was an unjustified windfall.
    The disgorgement award alone seems to have placed the Evanses in a far better
    position than the status quo ante; they had a substantial portion of their renovation
    project completed by CAH free of charge.
    10
    During oral argument, counsel for the Evanses suggested that, although the
    trial court determined the home improvement contract CAH assumed after CSMI’s
    departure was null and void, it did not find the same for the development
    management agreement. That is wrong. The trial court explicitly ruled that the
    development management agreement itself was null and void.
    23
    The Evanses also suggest that the additional contract damages were
    permissible under the CPPA. The CPPA affords consumers affected by unlawful
    trade practices the ability to obtain or recover the following remedies:
    (A)   (i) Treble damages, or $1,500 per violation,
    whichever is greater, payable to the consumer;
    (ii) Notwithstanding sub-subparagraph (i) of this
    subparagraph, for a violation of 28-3904(kk) a
    consumer may recover or obtain actual damages.
    Actual damages shall not include dignitary
    damages, including pain and suffering.
    (B) Reasonable attorney’s fees;
    (C) Punitive damages;
    (D) An injunction against the use of the unlawful trade
    practice;
    (E) In representative actions, additional relief as may be
    necessary to restore to the consumer money or property,
    real or personal, which may have been acquired by means
    of the unlawful trade practice; or
    (F) Any other relief which the court determines proper.
    
    D.C. Code § 28-3905
    (k)(2). Assuming the trial court awarded damages under the
    CPPA, it did not identify a particular provision justifying such an award. We have
    doubts the awarded relief here would fit under any of the above-enumerated types
    of relief under the CPPA, particularly where the trial court expressly declined to
    24
    award treble damages under the CPPA, 11 and there was no finding of “evil motive,
    actual malice, or [] willful disregard for the rights of the plaintiff” to suggest punitive
    damages were warranted. Dist. Cablevision Ltd. P’ship v. Bassin, 
    828 A.2d 714
    ,
    725 (D.C. 2003).
    Without a clear articulation of the trial court’s basis for awarding the
    additional $106,421.26, we will not conclusively opine on the propriety of that
    award. Suffice it to say that we doubt that additional award can be justified based
    on any position the Evanses advance on appeal. We remand for the trial court to
    either subtract that amount from its damages award or articulate a basis under which
    it thinks it appropriate.
    *      *      *
    We affirm the trial court’s judgment, save for its calculation of damages,
    which we vacate and remand for reconsideration consistent with this opinion.
    So ordered.
    11
    The Evanses did not file a cross-appeal challenging the trial court’s refusal
    to grant treble damages, or the more nominal remedy of $1500 per CPPA violation.