Woodstock Community Trust & Housing Vt. PUD ( 2010 )


Menu:
  •                               Superior Court of Vermont
    Environmental Division
    ===========================================================================
    E N T R Y O R D E R
    ===========================================================================
    Woodstock Community Trust & Housing Vermont         Docket No. 203-10-09 Vtec
    Project:     Woodstock Road PUD
    Applicant:   Woodstock Community Trust, Inc.
    Municipal DRB Planned Unit Development
    Cross-Motions for Summary Judgment, Nos. 3 & 4
    Two appeals are pending involving a 36-unit housing development in West
    Woodstock. This Court issued a decision on a prior application for the project property
    in In re Woodstock Community Trust and Housing Vermont PRD, No. 100-5-07 (Vt.
    Envtl. Ct. Oct. 15, 2008.) The 2008 decision determined that some aspects of the prior
    proposal met the standards of the municipal ordinance, while other aspects of the prior
    proposal did not meet the applicable review standards. Question I of the Statement of
    Questions in the present municipal appeal, No. 203-10-09 Vtec, involves whether this
    case presents an impermissible successive application. It has been submitted to the
    Court on cross-motions for summary judgment.
    The statute allows, but does not require, an appropriate municipal panel such as
    the DRB, and hence this Court in this de novo appeal, to “reject an appeal or request for
    reconsideration . . . if the [DRB] considers the issues raised by the appellant in the
    appeal have been decided in an earlier appeal or involve substantially or materially the
    same facts . . . .” 24 V.S.A. § 4470. The Vermont Supreme Court has explained that a
    municipal panel should “not entertain a second application concerning the same
    property after a previous application has been denied, unless a substantial change of
    conditions ha[s] occurred.” In re Armitage, 
    181 Vt. 241
    , 244 (2006) (citing In re Carrier,
    
    155 Vt. 152
    , 158 (1990)). The substantial change in conditions may involve an extrinsic
    occurrence, not at issue in the present appeal, such as a change in the zoning ordinance
    applicable to the project, or a widening or re-routing of a neighboring roadway.
    Equally, the requisite substantial change may be a change in the project design to
    address the reasons for which the first application was denied. That is, a municipal
    panel may consider a successive application “when the application has been
    substantially changed so as to respond to objections raised in the original application or
    when the applicant is willing to comply with conditions the commission or court is
    empowered to impose.” In re Jolley Associates, 
    2006 VT 132
    , ¶ 12, 
    181 Vt. 190
     (quoting
    In re Carrier, 155 Vt. at 158); see also, e.g., In re McGrew, 
    2009 VT 44
    , ¶ 10 (“[A] local
    planning agency or court may consider a second application which has been
    Page 1 of 2
    substantially changed to respond to objections to the first.”); In re Dunkin Donuts S.P.
    Approval (Montpelier), 
    2008 VT 139
    , ¶ 8 (By “address[ing] all concerns that prevented
    approval of the prior application,” an applicant is not bound by the previous denial and
    may resubmit a proposal to the appropriate municipal panel.).
    Exhibit A to Appellee-Applicant’s motion contains the application’s narrative
    describing the changes to the proposed project; it includes a section specifically relating
    the changes in the application to specific paragraphs of the Court’s 2008 decision
    addressing the reasons for which the former application was denied. The application
    now before the Court has been redesigned or changed to address the concerns that
    prevented approval of the prior application. Accordingly, Appellants’ motion for
    summary judgment to dismiss this application as an impermissible successive
    application is DENIED. This determination simply means that the application can
    proceed to its merits in this Court; it is not a ruling as to whether any redesigned
    element of the project now meets the applicable review standards.
    As discussed at the telephone conference held on July 12, 2010, the dates of
    October 20, October 21, and October 29 may be available to begin the trial (otherwise
    scheduled for November 1 through 4) on an earlier date, as preferred by Appellee-
    Applicants. The parties agreed to move the trial up to begin on the earliest available of
    those dates, and to check with their witnesses as to whether those dates are available in
    the witnesses’ schedules. On or before July 20, 2010, the parties shall report any
    unavailable dates in writing to the Court.
    Also as discussed at the telephone conference, the parties may file as prefiled
    testimony or evidence any testimony or evidence presented at the hearing of the earlier
    case. Supplemental direct testimony may be presented from any witness whose
    prefiled testimony is filed, and all witnesses shall be made available at trial for cross-
    examination. On or before September 3, 2010, the parties shall provide each other and
    the Court with a list of what prefiled testimony or evidence they propose to submit. A
    telephone conference has been scheduled for September 13, 2010, to discuss the
    proposed prefiled testimony and exhibits.
    __________________________________________      _July 13, 2010_____________
    Judge                                 Date
    ========================================================================
    Date copies sent to: ____________               Clerk's Initials _______
    Copies sent to:
    Attorney Kaveh S. Shahi for Appellants
    Attorney C. Daniel Hershenson for Appellees Woodstock Community Trust,
    Inc., and Housing Vermont
    Attorney Todd C. Steadman for Town of Woodstock
    Attorney Mark L. Lucas for NRB Land Use Panel, for information only
    Page 2 of 2
    

Document Info

Docket Number: 203-10-09 Vtec

Filed Date: 7/13/2010

Precedential Status: Precedential

Modified Date: 4/24/2018