HVAC Specialist, Inc. v. Dominion Mechanical Contractors, Inc. , 201 A.3d 1205 ( 2019 )


Menu:
  • Notice: This opinion is subject to formal revision before publication in the
    Atlantic and Maryland Reporters. Users are requested to notify the Clerk of the
    Court of any formal errors so that corrections may be made before the bound
    volumes go to press.
    DISTRICT OF COLUMBIA COURT OF APPEALS
    Nos. 16-CV-1220 & 16-CV-1278
    HVAC SPECIALIST, INC., APPELLANT/CROSS-APPELLEE
    V.
    DOMINION MECHANICAL CONTRACTORS, INC., APPELLEE/CROSS-APPELLANT.
    Appeals from the Superior Court
    of the District of Columbia
    (CAB-9870-15)
    (Hon. Jeanette Jackson Clark, Trial Judge)
    (Argued February 21, 2018                             Decided February 28, 2019)
    Nancy D. Greene for appellant/cross-appellee.
    Stephanie M. Rochel, admitted pro hac vice, for appellee/cross-appellant.
    Richard Mann and Hanna L. Blake were on the brief.
    Before THOMPSON and BECKWITH, Associate Judges, and WASHINGTON,
    Senior Judge.
    THOMPSON, Associate Judge: These consolidated appeals are from Superior
    Court orders that dismissed claims and counterclaims brought by appellant/cross-
    appellee HVAC Specialist, Inc. (“HVAC”) and appellee/cross-appellant Dominion
    Mechanical Contractors, Inc. (“Dominion”). All of the claims and counterclaims
    2
    relate to the renovation of the Takoma Elementary School in the District of
    Columbia, a project for which HVAC was a heating, ventilation, and air
    conditioning subcontractor to Dominion. In a March 11, 2016, order (the “March
    11 order”), the Superior Court dismissed HVAC’s claim against Dominion for
    indemnification or contribution. Subsequently, through a November 17, 2016,
    order (the “November 17 dismissal order”), the court dismissed all of the
    remaining claims and counterclaims on the ground that the subcontract was illegal,
    and therefore void, because, at all relevant times, HVAC lacked the relevant
    license to do business in the District of Columbia as a refrigeration and air
    conditioning contractor. We affirm the judgment of the Superior Court.
    I.
    The subcontract, dated August 2, 2011, required HVAC to “perform a
    portion of the heating, ventilation and air conditioning work” on the project.
    Specifically, HVAC was to furnish and install refrigeration piping, to receive and
    install heating, ventilation, and air conditioning equipment, to charge the
    equipment with gas, and to assist with the startup of equipment at the elementary
    school.   HVAC ran into difficulties paying its employees and suppliers, and
    Dominion eventually terminated the subcontract for HVAC’s alleged default.
    3
    There followed the parties’ claims and counterclaims for breach of contract and
    related causes of action. HVAC, a Virginia corporation, filed its initial complaint
    in December 2012, while it was an unregistered “foreign filing entity or foreign
    limited liability partnership doing business in the District,” a status that precluded
    it from “maintain[ing] an action in the District.” 
    D.C. Code § 29-105.02
     (b)
    (2011). Dominion moved for dismissal of HVAC’s complaint on that basis, and
    the Superior Court dismissed the original complaint without prejudice. HVAC
    filed its new complaint on December 22, 2015. Dominion initially responded by
    filing a motion to dismiss, arguing that the court should dismiss the action for lack
    of subject matter jurisdiction and should additionally dismiss some of the counts
    for failure to state a claim. On March 11, 2016, the trial court granted Dominion’s
    motion as to Count III of HVAC’s complaint, a claim for indemnification or
    contribution. 1
    Thereafter, on March 25, 2016, Dominion filed its answer to the December
    22, 2015, complaint, asserting counterclaims of breach of contract and termination
    for default. Dominion asserted a number of affirmative defenses in its answer, but
    1
    The court reasoned that HVAC’s prayer for those “equitable remedies”
    could not succeed because those remedies “apportion damages among [joint]
    tortfeasors,” and HVAC and Dominion “are not joint tortfeasors.”
    4
    did not assert illegality of the contract as a defense. 2 On August 8, 2016, however,
    Dominion filed another motion to dismiss, wherein it alleged that HVAC could not
    recover under the subcontract or under “a quantum meruit or quasi-contractual
    basis” because HVAC “had no license” when it entered into the subcontract and
    performed work under it. In particular, Dominion asserted that, at all relevant
    times, HVAC lacked the refrigeration and air conditioning contractor’s license it
    was required to have under District of Columbia law to perform work under the
    subcontract.   Opposing Dominion’s motion to dismiss, HVAC argued that
    Dominion waived any illegality defense by failing to assert it in the prior case, and
    for nearly 8 months after HVAC refiled its complaint, despite knowledge of
    HVAC’s licensure status. To the extent Dominion did not waive the asserted
    illegality defense, HVAC further argued, Dominion was “estopped” from raising
    the defense after having filed a counterclaim for damages for breach of the
    allegedly void contract.
    In ruling on Dominion’s motion to dismiss, the Superior Court noted that
    “[b]y its own admission,” HVAC “‘had no license to do business in the District of
    2
    Dominion represents that it became aware of HVAC’s expired licenses
    only in July 2016, months after it filed its answer and asserted its affirmative
    defenses and counterclaims. HVAC asserts that Dominion was aware no later than
    October 2013 that HVAC was unlicensed.
    5
    Columbia when it entered into the [s]ubcontract.’” The court explained that it was
    “constrained to grant” Dominion’s motion “inasmuch as the statutes and
    regulations requiring licenses for businesses operating in the District of Columbia
    are very clear that businesses performing refrigeration or air conditioning work
    must have a license to do so and there are no exceptions.” Relying primarily on
    this court’s opinion in Sturdza v. United Arab Emirates, 
    11 A.3d 251
    , 257 (D.C.
    2011), the court concluded that HVAC “could not recover in contract or in
    quantum mer[ui]t for services rendered.” Citing this court’s opinion in Billes v.
    Bailey, 
    555 A.2d 460
    , 463 (D.C. 1989), the court reasoned that even though
    Dominion “was aware that [HVAC] had no District of Columbia license at the time
    they entered into [the] [s]ubcontract,” “the doctrine of unclean hands does not
    entitle [HVAC] to recover in the instant action.”      Although recognizing that
    Dominion “belatedly filed [its] Motion to Dismiss based on [HVAC’s] failure to
    have the required District of Columbia licenses,” the court did not specifically
    address HVAC’s argument that Dominion waived or was estopped from asserting
    the defense of illegality. The court dismissed Dominion’s counterclaims because
    they were “based on a void contract.”3 These consolidated appeals followed.
    3
    The court also reasoned — erroneously, Dominion argues, that Dominion
    “acknowledged in its [a]nswer that the statute of limitations bar[red] [Dominion’s
    assertion of] claims related to th[e] case.”
    6
    II.
    We focus on the November 17 dismissal order because our conclusion
    regarding the subcontract’s unenforceability is dispositive of all of HVAC’s
    claims, including those dismissed through the March 11 order.4 Our review of the
    4
    HVAC argues that the Superior Court erred in dismissing its Count III
    claim for indemnification or contribution through the March 11 order. The
    Superior Court stated that the indemnification or contribution claim “d[id] not
    appear to arise out of a contract between the parties.” Disagreeing with the
    Superior Court on that point, we uphold the dismissal of Count III on the ground
    that the basis for Count III is what the complaint refers to as “the Payroll
    Agreement” between the parties — i.e., “an additional verbal agreement whereby
    Dominion would advance HVAC funds to meet its payroll and supplier obligations
    until regular billings and collections started for work performed on the Project.”
    Like the parties’ written subcontract, the alleged verbal contractual indemnification
    agreement arose out of HVAC’s “engag[ing] . . . in the business of installing,
    maintaining, repairing, or replacing refrigeration and air conditioning equipment.”
    [A322; see 17 DCMR § 303.1 (2011)] As explained in the text infra, HVAC was
    required to have a refrigeration and air conditioning contractor license to engage in
    that business. We conclude that any agreement by Dominion to indemnify HVAC
    for its project payroll expenses, or to contribute to those expenses, is as
    unenforceable as the written subcontract. See Contemporary Mission, Inc. v.
    Bonded Mailings, Inc., 
    671 F.2d 81
    , 83 (2d Cir. 1982) (citing authority that even if
    a contract is not itself unlawful, “the bargain may still be illegal if it is closely
    connected with an unlawful act”). Further, the fact of HVAC’s non-licensed
    status, which was not known to the Superior Court when it declined to dismiss
    HVAC’s indemnity/contribution claim as set out in the original complaint, was
    new information that undermines HVAC’s argument that the viability of the
    indemnity/contribution claim is the binding “law of the case.” See Kritsidimas v.
    Sheskin, 
    411 A.2d 370
    , 372-73 (D.C. 1980) (explaining that the “law of the case”
    (continued…)
    7
    November 17 dismissal order is de novo. See Williams v. District of Columbia, 
    9 A.3d 484
    , 488 (D.C. 2010).
    The various District of Columbia Code provisions and regulations cited in
    the November 17 dismissal order require licensure with respect to the refrigeration
    and air conditioning “occupation[] or profession[],” because it is one that has “been
    determined to require regulation in order to protect public health, safety or welfare,
    or to assure the public that persons engaged in such occupations or professions
    have the specialized skills or training required to perform the services offered.”
    (…continued)
    does not control “where the first ruling is clearly erroneous in light of newly-
    presented facts”).
    HVAC additionally contends that dismissal of Count III was error because
    HVAC and Dominion are “joint tortfeasor[s] as a matter of law” pursuant to 
    26 U.S.C. § 3505
     (b) (establishing tax liability of a person who “supplies funds to or
    for the account of an employer for the specific purpose of paying wages of the
    employees of such employer” with knowledge that the employer will not be able to
    make timely payment of associated withholding taxes). For the reasons set forth in
    Dominion’s brief at pages 39-45, we find that argument to be without merit. We
    note in particular that “[a] prerequisite to an equitable indemnity claim is that the
    party seeking it . . . have discharged the liability for the party against whom it is
    sought . . . .” District of Columbia v. Washington Hosp. Ctr., 
    722 A.2d 332
    , 341
    (D.C. 1998). HVAC has neither alleged nor furnished evidence showing that it has
    paid any taxes that were Dominion’s responsibility to pay.
    8
    
    D.C. Code § 47-2853.04
     (a) (2011); 
    D.C. Code § 47-2853.04
     (a)(29) (2011).5
    Further, “[t]he rule is well-established in the District of Columbia that a contract
    made in violation of a licensing statute that is designed to protect the public will
    usually be considered void and unenforceable, and that the party violating the
    statute cannot collect monies due on a quasi-contractual basis either.” Sturdza, 
    11 A.3d at 257
     (internal quotation marks and brackets omitted); see also 
    id.
     at 256
    n.19 (declining to create an exception for commercial transactions or an exception
    based on the sophistication of the parties); Saul v. Rowan Heating & Air
    Conditioning, Inc., 
    623 A.2d 619
    , 621 (D.C. 1993) (“This jurisdiction has held
    consistently that a contract entered in violation of a licensing statute or regulation
    directed at protecting the public is void and unenforceable.”). “Although the
    operation of this rule may appear to be harsh and disproportionate in some cases,
    we have uniformly rejected appeals to deviate from or mitigate it; the potential
    5
    The Superior Court also cited inter alia 
    D.C. Code § 47-2853.02
     (a)
    (2011) (“No person shall practice, attempt to practice, or offer to practice an
    occupation or profession for which a license, certification, or registration is
    required under this subchapter without a current valid license, certificate, or
    registration in accordance with the requirements of this subchapter.”); 17 DCMR §
    303.1 (2011) (“Except as specifically provided otherwise in this section, no person
    shall engage in or be employed in the business of installing, maintaining, repairing,
    or replacing refrigeration and air conditioning equipment, within the limits set
    forth in § 301, without being licensed to do so.”); and 17 DCMR § 315.1 (2011)
    (“No person shall perform work without having been issued the license under
    which that work may be performed. The license must be currently valid and in full
    force and effect.”).
    9
    unfair applications of the rule at the margins have not persuaded us to sacrifice the
    benefits of a clear-cut, unmistakable requirement, with equally clear consequences
    for noncompliance.” Sturdza, 
    11 A.3d at 257
     (internal quotation marks omitted).
    That the party asserting illegality was familiar with the licensing rules and
    knew of the contractor’s unlicensed status does not prevent operation of the
    foregoing rule. See Billes, 
    555 A.2d at 462
     (“[T]he doctrines of in pari delicto and
    unclean hands do not entitle an unlicensed . . . contractor to recover in a suit for an
    unpaid balance under a contract that is void,” because courts “must pay deference
    to the legislature’s intentional exposure of unlicensed contractors, which
    discourages unlicensed work[.]”).
    HVAC, which acknowledges that at all relevant times it lacked a
    refrigeration and air conditioning contractor’s license, does not contest the general
    applicability of any of the foregoing. Instead, as its primary argument on appeal,
    HVAC renews its argument that Dominion either waived the affirmative defense of
    illegality when it failed to timely assert HVAC’s non-licensed status, or is estopped
    from asserting the defense because of its reliance on the assertedly illegal contract
    to pursue a claim against HVAC for damages for breach of the contract.
    10
    HVAC is correct that, as a general rule, a defendant’s “[f]ailure to raise
    affirmative defenses [in its answer] constitutes a waiver of those defenses.” Grp.
    Health Ass’n, Inc. v. Reyes, 
    672 A.2d 74
    , 75 (D.C. 1996) (internal quotation marks
    omitted); see also D.C. Super. Ct. Civ. R. 8 (c)(1) (2016) (“In pleading to a
    preceding pleading, a party shall set forth affirmatively . . . any . . . matter
    constituting an avoidance or affirmative defense,” including “illegality.”). This
    court has, however, allowed “exception[s] to th[e] waiver rule” where there is no
    prejudice to the non-moving party. See Group Health Ass’n, 
    672 A.2d at 75-76
    .
    Prejudice will not be found where the non-moving party “has had an adequate
    opportunity to respond” to the challenge. United States v. Krieger, 
    773 F. Supp. 580
    , 583 (S.D.N.Y 1991) (citing Allied Chem. Corp. v. Mackay, 
    695 F.2d 854
    , 856
    (5th Cir. 1983)). Moreover, “it is not absolutely necessary to plead the illegality of
    a contract which is also contrary to public policy,” and indeed a “court may, sua
    sponte, step in and deny the right to any relief under an agreement without
    reference to the state of the pleadings, whenever it becomes apparent that the
    agreement is antagonistic to the interests of the public.” Krieger, 
    773 F. Supp. at 583
     (internal quotation marks and brackets omitted) (considering defendant’s
    illegality defense even though its was raised five years after the filing of the
    complaint).
    11
    HVAC asserts that both it and the court system were prejudiced by
    Dominion’s belated assertion of the affirmative defense of illegality after nearly
    four years of litigation.6 Whether or not that is so, we conclude that under the
    public policy exception to the waiver rule, which is precedential law in our
    jurisdiction, the affirmative defense of illegality is not waivable in the context of a
    contract entered into in contravention of a District of Columbia law, such as a
    licensing requirement, that is “designed to protect the public,” Sturdza, 
    11 A.3d at 257
    , and that “affords significant protections to the public.” Saul, 
    623 A.2d at 622
    .
    The United States Court of Appeals for the District of Columbia Circuit
    established long ago that “[t]he invalidity of [a] contract may not be waived ‘by
    any system of pleading, or even by the express stipulation of the parties.’” Noonan
    v. Gilbert, 
    68 F.2d 775
    , 776 (D.C. Cir. 1934) (quoting Oscanyan v. Arms Co., 
    103 U.S. 261
    , 267 (1881) (“[T]he law will not lend its support to a claim founded upon
    6
    HVAC asserts, for example, that “[h]ad Dominion timely raised [the
    illegality] defense in the [o]riginal [c]ase, HVAC may have been able to assert a
    fraud claim based on Dominion’s representations that HVAC did not have to hold
    a separate license to perform the contract.” But the record discloses that HVAC,
    which previously held a Refrigeration and Air Conditioning Contractor license and
    employed an individual with a Master Mechanic license, was aware of the
    licensing laws and of potential problems with its licensure status and makes it
    doubtful that HVAC could reasonably have relied on any such representation by
    Dominion. An email dated August 15, 2011, from Denise Brewer to Omar Brewer
    (co-owners of HVAC) recognizes that HVAC “is not compliant as we discussed a
    couple days ago, . . . . I am not willing to accept the possible liability for operating
    any new work without compliance.”
    12
    its violation.” (internal quotation marks omitted))).      For the same reason, we
    conclude that Dominion’s counterclaim for breach of the subcontract did not estop
    it from asserting as an affirmative defense HVAC’s violation of the refrigeration
    and air conditioning contractor licensing laws. Cf. Journal of Commerce, Inc. v.
    United States Dep’t of Treasury, No. 86-1075, 
    1988 U.S. Dist. LEXIS 17610
    , at
    *19 (D.D.C. Mar. 30, 1988) (rejecting plaintiff’s estoppel argument because
    estopping the defendant from repudiating the agreement set out in certain
    memoranda of understanding would “require th[e] [c]ourt to breathe life into an
    illegal bargain[]”).
    HVAC makes three additional arguments in support of its breach of contract
    claim. First, it argues that it was not actually required to have a license because its
    employees could work under Dominion’s license. It is true that under 17 DCMR
    § 303.2, there is no licensing requirement for “persons performing refrigeration or
    air conditioning work under the personal supervision of, and under the authority of
    a permit issued to, a validly licensed Master Refrigeration and Air Conditioning
    Mechanic or Master Refrigeration and Air Conditioning Mechanic Limited, who is
    responsible for the proper performance of the work.” However, as we observed in
    Saul, “[t]he licensing regulations distinguish between those who ‘engage in the
    business’ and those who are ‘employed in’ or who ‘perform work in’ the field,”
    13
    and “[t]he exception in § 303.2 appears to be designed solely to allow individuals
    to work as subordinates to a master mechanic without obtaining a license.” 
    623 A.2d at 621
     (emphasis added); see also 
    id. at 622
     (“perceiv[ing] a clear distinction
    between [the company president’s] individual license and the type of license which
    [the contracting company] was required to obtain before contracting or performing
    the work involved”). Under 
    D.C. Code § 47-2853.04
     (a)(29) and 17 DCMR
    § 303.6 (a), as a “corporation proposing to engage in or be employed in the
    business of installing, maintaining, repairing, or replacing refrigeration and air
    conditioning equipment,” HVAC was required to have a “Refrigeration and Air
    Conditioning Contractor” license. See also Saul, 
    623 A.2d at 621-22
     (explaining
    that “a ‘Refrigeration and Air Conditioning Contractor’ entitles the holder to
    engage in the business,” whereas a Master Mechanic license “allow[s] the holder
    only to supervise or perform the type of work covered by the regulations as
    distinguished from engaging in the business[]”; holding therefore that even though
    the company president held a Master Mechanic license in his individual capacity,
    “this could not excuse Rowan, Inc., the contracting party, from obtaining the
    required license before engaging in the business[]”); Highpoint Townhouses, Inc. v.
    Rapp, 
    423 A.2d 932
    , 934 (D.C. 1980) (“The mere fact that Rapp Co. was working
    under a permit obtained by a master plumber does not, in itself, satisfy or excuse
    Rapp Co. from the licensing requirement.”). In addition, as Dominion notes, D.C.
    14
    Code § 47-2851.02 (c) (2011) prohibited Dominion, as “[a] person issued a license
    under this subchapter,” from “willfully allow[ing] any other person required to
    obtain a separate license to operate under [its] license.”
    HVAC’s second argument is equally unavailing. It asserts that even if a
    portion of the subcontract was illegal, it should be permitted to recover with
    respect to the tasks performed under the contract (such as “order[ing] equipment
    and materials,” for which it “was due an equipment acquisition fee,” and providing
    “unspecified ‘start-up assistance’”) for which a license was not required. This
    argument is not persuasive; we fail to see how entering into and performing under
    a commercial contract to order heating, ventilation, and air conditioning equipment
    and materials and to assist with the start-up of such equipment, do not constitute
    engaging in the business of a refrigeration and air conditioning contractor, for
    which a license was required under § 47-2853.04 (a)(29) and 17 DCMR § 303.6.
    In its reply brief and at oral argument, HVAC advanced the additional
    argument that dismissal of its complaint was premature because, with “a full
    opportunity to conduct discovery,” it might have been able to prove that its work
    on the Takoma Elementary School project fell within the licensing exception
    established by 17 DCMR § 315.8 (2011): “No person without a license required by
    15
    this chapter may perform any air conditioning or refrigeration work in the District
    of Columbia except in buildings under the control of the officer in charge of Public
    Buildings and Grounds or of the Architect of the Capitol” (emphasis added). Not
    only does it appear that HVAC has raised this argument for the first time on appeal
    and not until its reply brief, 7 but HVAC joined in a consent motion that advised the
    Superior Court that Dominion’s “pending dispositive motion m[ight] dismiss the
    entire case” and that a postponement of the discovery deadline and suspension of
    discovery would “serve to promote efficiency and judicial economy[.]” HVAC
    will not be heard now to complain that it needed additional discovery to counter
    Dominion’s motion. 8
    7
    The court’s longstanding practice is not to address arguments raised for
    the first time in a reply brief, see Union Mkt. Neighbors v. District of Columbia
    Zoning Comm’n, No. 17-AA-42, 
    2018 D.C. App. LEXIS 489
    , at *6 (D.C. Dec. 13,
    2018), or at oral argument, see Long v. United States, 
    83 A.3d 369
    , 381 n.17 (D.C.
    2013).
    8
    And in any event, case law suggests that, as referred to in § 315.8, the
    phrase “officer in charge of Public Buildings and Grounds” is a reference to the
    Director of the National Park Service, whom Congress made responsible for the
    Park Police, see Richardson v. United States, 
    520 A.2d 692
    , 694-95 (D.C. 1987);
    and that the phrase “Public Buildings and Grounds” may be a reference to “federal
    reservations in the District’s environs” that are under the jurisdiction of the Park
    Police, 
    id. at 695
    , rather than to public buildings, such as elementary schools, that
    are under the control of the District of Columbia.
    16
    III.
    Through its breach-of-contract counterclaim, Dominion sought judgment
    against HVAC “in an amount to be proved at trial, plus interest, reasonable
    attorneys’ fees, costs, and any other relief the Court deems appropriate.” Through
    its termination for default counterclaim, Dominion sought in addition its costs of
    completing HVAC’s work and delay damages. Dominion asserts that “District
    law . . . prevents only the unlicensed contractor from recovering on a contract and
    does not disable the other party from a recovery.” In its briefs on appeal, however,
    Dominion cites cases that support a more limited recovery. Dominion quotes, for
    example this court’s statement in Saul that “[o]rdinarily, when a party sues
    successfully to rescind a contract determined to be void and unenforceable because
    of the contractor’s violation of licensing statutes or regulations, the appropriate
    remedy is a return of the money paid.” 
    623 A.2d at
    622 n.4. See also, e.g., Nixon
    v. Hansford, 
    584 A.2d 597
    , 598-99 (D.C. 1991) (determining that appellant was
    “entitled to judgment on her counterclaim” to recoup the amount paid to an
    unlicensed home improvement contractor even though both parties knew the law
    and the unlicensed status of the worker when entering into the contract). For its
    part, HVAC relies on the principle that neither party can enforce a void contract.
    17
    See, e.g., McMahon v. Anderson, Hibey & Blair, 
    728 A.2d 656
    , 658 (D.C. 1999)
    (“[W]hen parties have entered into an illegal contract, such contract is
    unenforceable and, typically, we leave the parties where we find them.”). HVAC
    also contends that Dominion’s claims are time-barred.
    We conclude that we need not consider the merits of Dominion’s
    counterclaims.   That is because we read Dominion’s briefs in this matter as
    representing that it seeks only conditionally to recover from HVAC; that is,
    Dominion seeks a set-off in the event that this court allows HVAC’s claims to
    proceed. See Dominion’s Br. at 2 (“In the event that this Honorable Court reverses
    the trial court’s order, Dominion’s counterclaims should also be reinstated[.]”);
    Dominion’s Br. at 48 (“[S]hould the Court somehow decide that [HVAC’s] claims
    should be returned to the trial court, Dominion should be allowed to assert its
    contract claims as set-offs[.]”); Dominion’s Reply Br. at 2 (“Dominion’s claim
    should be reinstated should this Honorable Court decide to remand the case.”);
    Dominion’s Reply Br. at 3 (acknowledging that HVAC, “is defunct and in
    receivership”); and Dominion’s Reply Br. at 5 (“Dominion requests partial reversal
    to reinstate its counterclaim . . . should the Court somehow conclude that
    [HVAC’s] unlicensed status did not disable it from resort to the courts and then
    remand the case for further proceedings.”). At oral argument as well, Dominion
    18
    represented that it is “willing to give up [the] counterclaim[s]” if HVAC’s claims
    do not go forward. Having affirmed the dismissal of HVAC’s claims, we take
    Dominion at its word and do not decide whether its counterclaims were improperly
    dismissed (the issue now being moot).
    Wherefore, the judgment of the Superior Court is
    Affirmed.