Tanana Chiefs Conference v. Azar ( 2022 )


Menu:
  •                                UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    TANANA CHIEFS CONFERENCE,
    Plaintiff,
    v.
    Civil Action No. 20-2902 (RDM)
    XAVIER BECERRA, Secretary of U.S.
    Department of Health and Human Services, et
    al.,
    Defendants.
    MEMORANDUM OPINION AND ORDER
    Plaintiff Tanana Chiefs Conference (“TCC”) brings this breach-of-contract action against
    the Secretary of the Department of Health and Human Services and the Director of the Indian
    Health Service (collectively, “IHS”) seeking damages for IHS’s failure to pay TCC certain
    amounts allegedly due under an agreement between the parties known as the Alaska Tribal
    Health Compact.1 Dkt. 1 (Compl.). IHS moves to dismiss the case for lack of subject-matter
    jurisdiction pursuant to Federal Rule of Civil Procedure 12(b)(1), Dkt. 15, arguing that (1) TCC
    failed to comply with the presentment requirement contained in the Contract Disputes Act
    (“CDA”), 
    41 U.S.C. §§ 7101
    , et seq., and, then, attempting to rectify that misstep, (2) TCC
    changed the nature of its claim before this Court, again in violation of the CDA. Dkt. 15-1 at 6.
    1
    Pursuant to Fed. R. Civ. P. 25(d), the current Secretary of Health and Human Services, Xavier
    Becerra, and the current Director of IHS, Elizabeth A. Fowler, are “automatically substituted” as
    parties with no effect on TCC’s “substantial rights.” Fed. R. Civ. P. 25(d).
    1
    The Court is unpersuaded. The claim that TCC submitted to IHS gave the agency
    “adequate notice of the basis and amount of the claim,” and that is all that is required. Cont.
    Cleaning Maint., Inc. v. United States, 
    811 F.2d 586
    , 592 (Fed. Cir. 1987). And although TCC’s
    claim before this Court is not identical to the one that it presented to IHS, it is “based on the
    same set of operative facts underlying the claim presented to [IHS],” which, once again, is all
    that the CDA requires. Tunica-Biloxi of La. v. United States, 
    577 F. Supp. 2d 382
    , 409 (D.D.C.
    2008) (internal quotation marks omitted) (alteration in original).
    The Court will therefore DENY IHS’s motion to dismiss.
    I. BACKGROUND
    A.     Statutory Background
    IHS is a component of the Department of Health and Human Services (“HHS”) charged
    with providing medical and public health services to American Indian and Alaska Native people.
    See Lincoln v. Vigil, 
    508 U.S. 182
    , 185 (1993). It is responsible for administering federal health
    care programs for the benefit of these communities in the first instance. See 
    25 U.S.C. § 1661
    (c).
    But under the Indian Self-Determination and Education Assistance Act (the “ISDEAA”), 
    25 U.S.C. § 5301
     et seq., a tribe can elect to contract with the Secretary of HHS (through IHS) to
    take over the operation and administration of these programs, 
    id.
     § 5321(a)(1). ISDEAA
    contracts come in different forms, two of which are relevant here. A “self-determination
    contract,” authorized by Title I of the ISDEAA, is a discrete agreement for the transfer of
    responsibility over a federal program. Id. A “self-governance compact,” authorized by Title V,
    is a more involved agreement that “set[s] forth the general terms of the government-to-
    government relationship between the Indian tribe and the Secretary.” Id. § 5384(b). A compact
    can entail the transfer of responsibility over multiple government programs to the tribe or tribal
    2
    organization and is accompanied by a funding agreement detailing the funds the federal
    government will provide for the operation and administration of these programs. Id. § 5385.
    In either case, IHS agrees to provide two types of funding to the tribe or tribal
    organization with which it has contracted. Id. § 5325(a). The first, known as the “baseline” or
    “Secretarial amount,” Tunica-Biloxi Tribe of La., 
    577 F. Supp. 2d at 388
    , is a quantum of
    funding “not . . . less than” the Secretary would have provided for the operation of the relevant
    program had it remained under federal management, 
    25 U.S.C. § 5325
    (a)(1). The second type is
    for “contract support costs” (“CSCs”). 
    Id.
     § 5325(a)(2). These cover the incremental
    administrative expenses that a contracting tribe or tribal organization incurs to manage and
    oversee the contract appropriately. Id.; Cherokee Nation of Okla. v. Leavitt, 
    543 U.S. 631
    , 634–
    35 (2005). The statute subdivides CSCs into two further categories: direct and indirect. 
    25 U.S.C. § 5325
    (a)(3)(A). Direct contract support costs pertain to a particular program and include
    items such as workers’ compensation insurance and training costs for employees dedicated to
    that program. See Cherokee Nation, 
    543 U.S. at 635
    ; Dkt. 1 at 11 (Compl. ¶ 33). Indirect
    contract support costs, by contrast, cover overhead costs for items that benefit multiple programs
    and include items such as information technology expenses and the cost of financial management
    tools. See id.; 
    25 U.S.C. § 5325
    (a)(3)(A)(ii); Dkt. 1 at 9 (Compl. ¶ 26).
    Because indirect costs relate to overhead benefiting more than one program, IHS and the
    contracting tribe or tribal organization try to allocate these costs amongst the various programs
    they support. Dkt. 1 at 9 (Compl. ¶ 26). This cost allocation is typically accomplished using
    what is known as an “indirect cost rate,” a ratio calculated by dividing the total indirect costs by
    the total amount of direct costs of all the programs to which the indirect cost pool pertains. 
    Id.
    (Compl. ¶¶ 26–27). The resulting ratio is then applied to the direct costs of each individual
    3
    program to determine the dollar value of indirect costs attributable to that program. 
    Id.
     (Compl.
    ¶ 27).
    Disputes that arise under the ISDEAA are subject to the CDA, 
    25 U.S.C. §§ 5331
    (d),
    5391(a), which provides a “comprehensive framework for resolving contract disputes between
    executive branch agencies and government contractors,” Menominee Indian Tribe of Wisc. v.
    United States, 
    614 F.3d 519
    , 521 (D.C. Cir. 2010). The CDA contains a “mandatory
    administrative process”—referred to as “presentment”—that “requires contractors to present
    ‘[e]ach claim’ they have to a contracting officer for decision.” Menominee Indian Tribe of Wisc.
    v. United States, 
    577 U.S. 250
    , 252 (2016) (alteration in original) (quoting 
    41 U.S.C. § 7103
    (a)).
    Once a claim has been presented, a contracting officer must provide a final decision on the claim
    within a specified period, typically 60 days. 
    41 U.S.C. §§ 7103
    (d), 7103(f)(1)–(2). “Failure by a
    contracting officer to issue a decision on a claim within the required period of time is deemed to
    be a decision by the contracting officer denying the claim.” 
    Id.
     § 7103(f)(5).
    After this process has run its course, dissatisfied claimants have a right to challenge the
    contracting officer’s decision. The CDA typically allows claimants to appeal to an agency board
    or to seek judicial review in the United States Court of Federal Claims. Id. § 7104(a)–(b)(1).
    The ISDEAA provides tribes and tribal organizations a third option: review in federal district
    court. 
    25 U.S.C. § 5331
    (a).
    B.       Factual Background
    Except where specifically controverted by evidence submitted in support of IHS’s motion
    to dismiss for lack of jurisdiction, the following allegations are taken as true for purposes of the
    pending motion. See Phoenix Consulting Inc. v. Republic of Angola, 
    216 F.3d 36
    , 40 (D.C. Cir.
    2000).
    4
    The Tanana Chiefs Conference is an Alaska-based tribal health organization—an “Indian
    Tribe” under the ISDEAA—comprised of forty-two Alaska Native member villages. Dkt. 1 at 2
    (Compl. ¶ 5). It is a party to the Alaska Tribal Health Compact (the “Title V Compact”), a self-
    governance compact under Title V of the ISDEAA between a number of Alaskan tribes and
    tribal organizations and IHS. 
    Id.
     (Compl. ¶ 5). In 2013, TCC was also party to a separate Title I
    self-determination contract (the “Title I Contract”) with IHS pertaining to one of TCC’s member
    tribes, the Native Village of Tanana. Id. at 5 (Compl. ¶ 12).
    Under the Title V Compact, TCC operates and administers a variety of federal health care
    programs and receives funding for these activities through a funding agreement incorporated into
    the compact. Id. (Compl. ¶¶ 7–8, 11, 15). During the period relevant to this litigation, the Title
    V Compact operated pursuant to a multiyear funding agreement known as the “FY 2011-2013
    FA.” Id. at 4–5 (Compl. ¶ 11). That funding agreement, like other such agreements, required
    IHS to pay TCC the “Secretarial amount” as well as both direct and indirect contract support
    costs, as those concepts are defined in 
    25 U.S.C. § 5325
    . 
    Id.
     at 5–7 (Compl. ¶¶ 15–19). For
    purposes of the Title V Compact, indirect costs were calculated using the indirect cost rate
    methodology, and TCC’s indirect cost rates were developed for separate subparts of direct costs,
    resulting in multiple indirect cost rates. 
    Id.
     at 9–10 (Compl. ¶¶ 27–29).
    This litigation concerns the amount of contract support funding IHS owes TCC for fiscal
    year 2013. 
    Id.
     at 10–11 (Compl. ¶¶ 31, 34). Although the merits of the parties’ dispute are not at
    issue today, the short of it is that TCC alleges that IHS did not adequately reimburse it for both
    its direct and indirect contract support costs. 
    Id.
     (Compl. ¶¶ 31, 34). As to the former, TCC
    contends that IHS failed to pay TCC in full for its direct contract support costs. 
    Id. at 11
     (Compl.
    5
    ¶ 34). With respect to the latter, TCC alleges that IHS applied the relevant indirect cost rate to
    the wrong direct cost base, resulting in IHS underpaying TCC. 
    Id. at 10
     (Compl. ¶ 31).
    On September 30, 2019, TCC sent a claim letter to IHS requesting reimbursement for the
    contract support costs that it contends IHS improperly withheld in 2013. 
    Id. at 13
     (Compl. ¶ 42).
    The subject of the letter was: “Contract Disputes Act claim for unpaid contract support costs due
    in FY 2013 under Indian Self-Determination Act Compact and associated Funding Agreements.”
    Dkt. 1-4 at 1. The letter begins with the following text and table:
    The Tanana Chiefs Conference (TCC) hereby claims the right to immediate
    payment of $12,153,793 plus interest, due and owing to TCC under the provisions
    of the above-referenced Compact and associated funding agreements, as amended,
    in effect between the parties for fiscal year 2013:
    Expectancy
    Damages from       Expectancy
    Additional IDC    Damages from
    Fiscal   Total Direct   Total Indirect    on Unfunded     Lost Third-Party
    Year      CSC Due         CSC Due         IDC & DCSC          Revenue          Total
    FY
    $3,347,642      $4,085,965        $1,767,329        $2,952,857      $12,153,793
    2013
    
    Id.
     (emphasis added). The letter goes on to explain that “[d]uring the covered years, TCC’s
    Compact, funding agreements, indirect cost agreements, and the ISDEAA obligated the United
    States to pay TCC no less than the full amount of contract support costs, including indirect costs
    and direct contract support costs, associated with TCC’s operation of the IHS programs,
    functions, services, and activities specified in TCC’s contracts with IHS, as amended.” 
    Id.
    (emphasis added). It further states that TCC’s claims “seek the sums set forth above and,
    without limitation, all other damages arising out of IHS’s failure to pay full contract support
    costs as required by the ISDEAA and TCC’s contracts.” 
    Id. at 2
    . (emphasis added). These
    claims, TCC adds, are “supported by the originals of all contracts, contract modifications,
    6
    funding agreements, amendment thereto, indirect cost rate agreements, and audits, all of which
    are in the custody of the Government.” 
    Id. at 2
     (emphasis added).
    Appended to the letter are two pages of financial schedules. The first page sets forth
    TCC’s preferred methodology for categorizing costs. 
    Id. at 2, 5
    . The second page sets forth an
    alternative methodology should IHS disagree with TCC’s preferred approach and, instead,
    require “that claims for direct and indirect CSC . . . be further broken down according to the
    portion of TCC’s health program funded by IHS appropriated funds versus other funding
    sources.” 
    Id. at 2, 6
    . As the letter explains, TCC provided this alternative analysis “to facilitate
    the agency’s review of these claims.” 
    Id. at 2
    . For both methodologies, however, the left
    column on the schedule includes the contract numbers for both the Title I Contract and the Title
    V Compact, and right most column of the schedule, which contains the dollar value figures, is
    labeled “TANANA CHIEFS CONFERENCE Title I & V Agreements.” 
    Id. at 5, 6
    .
    IHS responded to TCC’s claim letter on November 26, 2019, with two almost identical
    letters—one addressing TCC’s Title I Contract and the other addressing TCC’s Title V Compact.
    Both responses assert: “IHS hereby determines that the [TCC claim] letter does not constitute a
    proper claim under the CDA,” because it did not adhere to the “requirement that a claim ask for
    payment of a specific sum of money under the contract,” as mandated by 
    25 C.F.R. § 900.218
    (a)(1). Dkt. 1-5 at 1–2. According to IHS, TCC’s letter did not specify “which
    contract has been breached for what amount,” but, rather, “assert[ed] claim(s) for breaches of
    two contracts and/or funding agreements or compact for $12,153,793, without information
    regarding the amount at issue as to either contract.” 
    Id.
     As a result, according to IHS, “[t]he
    [claim] letter and attachments did not state a sum certain under the contract in accordance with
    7
    the law,” and “the awarding official [was] not required to render a decision on the claim or
    claims.” 
    Id.
    C.     Procedural Background
    TCC filed this lawsuit on October 9, 2020, asserting four breach-of-contract claims and
    one claim for breach of the ISDEAA. Dkt. 1 at 17–21 (Compl. ¶¶ 60, 64,70, 72, 78). TCC asks
    the Court for declaratory relief; $10,386,464 in damages plus interest; and fees and costs. Dkt. 1
    at 22. The $10,386,464 in damages that TCC seeks is equal to the $12,153,793 it sought before
    IHS, less the $1,767,329 it requested at that time for “Expectancy Damages from Additional IDC
    [(indirect costs)] on Unfunded IDC & DCSC [(direct contract support costs)].” Dkt. 1 at 21 n.4,
    22; Dkt. 1-4 at 1.
    TCC’s complaint disavows any claim under the Title I Contract and states that TCC has
    only ever sought damages related to the Title V Compact. Dkt. 1 at 5, 13, 15 (Compl. ¶¶ 12, 43,
    47). Although TCC “acknowledges that the heading of one of the columns in the calculations
    tables referenced its Title I contract,” it contends that these tables were not part of its “claim,”
    which was embodied only in the claim letter. 
    Id. at 15
     (Compl. ¶ 47). From TCC’s perspective,
    the data tables were analytical aides that TCC included in its submission merely to help IHS
    review TCC’s claim and that do not negate the claim letter’s focus on the Compact. 
    Id.
     (Compl.
    ¶ 47). All that matters, according to TCC, is that the letter only sought payment pursuant to the
    “Compact and associated Funding Agreements.” Dkt. 1-4 at 1.
    IHS moves to dismiss TCC’s complaint for lack of subject-matter jurisdiction. Dkt. 15.
    IHS’s position is that TCC failed properly to present its claim at the administrative level and
    therefore failed to satisfy a mandatory prerequisite to this Court’s jurisdiction under the CDA
    and ISDEAA. Dkt. 15-1 at 17. In addition, IHS argues that TCC’s complaint represents an
    8
    improper effort to cure its defective presentment and to circumvent the CDA’s procedures. 
    Id. at 17
    , 19–22. As IHS sees it, TCC initially brought claims under both its Title V Compact and
    Title I Contract but now seeks damages only for breach of its Title V Compact. 
    Id.
     at 19–22.
    That, IHS insists, amounts to TCC pursuing a different claim judicially than it did
    administratively, something the CDA forbids. 
    Id.
    II. ANALYSIS
    A.      Whether TCC Adequately Submitted a “Claim” to IHS
    “Subject matter jurisdiction defines the [tribunal’s] authority to hear a given type of
    case.” Carlsbad Tech., Inc. v. HIF Bio, Inc., 
    556 U.S. 635
    , 639 (2009). The issue of subject-
    matter jurisdiction arises here because TCC is suing the United States and its agencies (through
    its officers), and, “[a]bsent a waiver, sovereign immunity shields the Federal Government and its
    agencies from suit.” FDIC v. Meyer, 
    510 U.S. 471
    , 475 (1994). Because “[s]overeign immunity
    is jurisdictional in nature[,] . . . the ‘terms of the [the United States’] consent to be sued in any
    court define that court’s jurisdiction to entertain the suit.’” 
    Id.
     (third alteration in original)
    (quoting United States v. Sherwood, 
    312 U.S. 584
    , 586 (1941)). As the Court will explain in
    more detail shortly, the ISDEAA contains a limited waiver of sovereign immunity, 
    25 U.S.C. § 5331
    (a), but it conditions that waiver on a party presenting its claim to a contracting officer for
    decision before suing in federal court, 
    id.
     § 5331(d); 
    41 U.S.C. § 7103
    (a)(1).
    Although the plaintiff bears the burden of demonstrating that the court has subject-matter
    jurisdiction, the nature of that burden varies depending on the stage of the proceeding. Lujan v.
    Defs. Of Wildlife, 
    504 U.S. 555
    , 561 (1992). At the motion-to-dismiss stage, it is often sufficient
    for the plaintiff to allege facts sufficient to sustain the court’s jurisdiction. 
    Id.
     But an opposing
    party may increase the stakes by “pos[ing] a ‘factual’ challenge to the Court’s jurisdiction,” Hale
    9
    v. United States, No. 13-1390, 
    2015 WL 7760161
    , at *3 (D.D.C. Dec. 2, 2015), which requires
    the court to “go beyond the pleadings and [to] resolve any disputed issues of fact the resolution
    of which is necessary to a ruling upon the motion to dismiss,” Phoenix Consulting Inc., 
    216 F.3d at 40
    . When the movant raises such a factual challenge, the Court may consider the
    uncontroverted allegations contained in the complaint, any undisputed facts, and “the court’s
    resolution of disputed facts.” Herbert v. Nat’l Acad. of Scis., 
    974 F.2d 192
    , 197 (D.C. Cir.
    1992).
    Although IHS asks the Court to consider two documents that were not attached to the
    complaint, which it suggests support its thesis that the schedules attached to TCC’s claim
    “appear to derive their values from both the Title I Contract and the Title V FY 2013 Funding
    agreement,” Dkt. 15-1 at 22, the pending motion more closely resembles a facial, rather than a
    factual, challenge to the Court’s jurisdiction. For one thing, IHS has not offered a declaration
    explaining the calculation that it asks the Court to make. But, more importantly, the dispute
    between the parties is, in relevant respects, principally a dispute about how best to characterize
    TCC’s September 30, 2019 claim letter, and not a dispute about the underlying facts. In this
    sense, TCC’s allegation that it did not submit a claim for payment under its Title I Contract is not
    a “factual” allegation entitled to a presumption of truth, see Ashcroft v. Iqbal, 
    556 U.S. 662
    , 678
    (2009) (conclusory statements and legal conclusions need not be accepted as true), nor is it
    dispositive of the question presented. And, by the same token, IHS’s contention that the
    schedules “appear to derive their value from both the Title I Contract and [the] Title V” Compact
    does not resolve the matter. Dkt. 15-1 at 22. Rather, the question presented is simply whether
    TCC’s letter provided IHS with sufficient notice of TCC’s claim to trigger the applicable waiver
    of sovereign immunity.
    10
    As noted above, the ISDEAA waives sovereign immunity for certain disputes arising
    under its provisions, 
    25 U.S.C. § 5331
    (a), and incorporates the procedural requirements of the
    CDA, id § 5331(d). To avail itself of the ISDEAA’s sovereign-immunity waiver, a party must
    adhere to those of the CDA’s requirements that constitute the preconditions of the United States’
    consent to suit. See James M. Ellett Const. Co., Inc. v. United States, 
    93 F.3d 1537
    , 1541–42
    (Fed. Cir. 1996). The Court of Appeals for the Federal Circuit, the court of appeals most often
    tasked with review of CDA actions, see 
    41 U.S.C. § 7104
    (b)(1); 
    28 U.S.C. § 1295
    (a)(3), has held
    that presentment is one such requirement, explaining that absent “both a valid claim . . . and a
    contracting officer’s final decision on that claim,” courts lack jurisdiction to hear actions brought
    under the CDA. James M. Ellett Const., 
    93 F.3d at
    1541–42; M. Maropakis Carpentry, Inc. v.
    United States, 
    609 F.3d 1323
    , 1327–28 (Fed. Cir. 2010). This Court has held the same, and the
    parties have not urged the Court to adopt a contrary view. Tunica-Biloxi Tribe of La., 
    577 F. Supp. 2d at
    407–08. Accordingly, to meet its burden of establishing that this Court has
    jurisdiction, TCC must show that it presented its claim to IHS in accordance with the CDA and
    that it now brings suit respecting that same claim.
    The first part of the inquiry turns on whether TCC’s submission meets the definition of a
    “claim” under the CDA and ISDEAA. IHS regulations define the term “claim” to mean “a
    written demand by one of the contracting parties, asking for one or more of the following: (1)
    [p]ayment of a specific sum of money under the contract; (2) [a]djustment or interpretation of
    contract terms; or (3) [a]ny other claim relating to the contract.” 
    25 C.F.R. § 900.218
    (a). This
    definition echoes the definition of a CDA “claim” contained in the Federal Acquisition
    Regulations: “[a] written demand or written assertion by one of the contracting parties seeking,
    as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of
    11
    contract terms, or other relief arising under or relating to the contract.” 
    48 C.F.R. § 52.233-1
    (c).
    All agree that TCC’s letter to IHS was a written demand asking for payment of money. The
    question, therefore, is whether this demand was “specific” and “under the contract” in question
    in the relevant sense.
    IHS says the answer is no. It points to Federal Circuit precedent that reads the statute and
    regulations to require “a clear and unequivocal statement that gives the contracting officer
    adequate notice of the basis and amount of the claim.” Dkt. 15-1 at 18 (quoting Cont. Cleaning
    Maint., 
    811 F.2d at 592
    ). And TCC’s claim was, in IHS’s view, “anything but clear.” 
    Id.
     What
    troubles IHS about TCC’s letter is that, although it repeatedly discusses the Title V Compact, it
    also contains some indications that TCC was seeking relief under the Title I Contract as well.
    Notably, the letter references “contracts,” in the plural, several times. Dkt. 15-1 at 19. The
    schedules attached to the letter also mention both contracts and, according to IHS (and TCC does
    not dispute it), they have the contract numbers for both contracts listed at the top. 
    Id.
     IHS
    argues that these references rendered TCC’s submission “so opaque” with respect to what sum of
    money TCC was asking for and under which contract that IHS was never put on notice of the
    basis and amount of TCC’s claim. 
    Id.
     at 18–19.
    The Court declines to accept such an exacting interpretation of what is, as IHS
    acknowledges, a mere notice requirement. The Court of Federal Claims has repeatedly
    explained that evaluating the sufficiency of a claim for presentment purposes is a practical, rather
    than a technical exercise, and that a claim need only “be stated in a manner which allows for
    reasonable determination of the recovery available at the time the claim is presented and/or
    decided by the contracting officer.” Metric Constr. Co. v. United States, 
    1 Cl. Ct. 383
    , 391
    (1983). Whether a claimant provided adequate notice is thus a “common sense analysis” that
    12
    “views the contractor’s submission as a whole.” CPS Mech. Contractors, Inc. v. United States,
    
    59 Fed. Cl. 760
    , 763 (2004); 
    id.
     (noting that “[t]o be adequate” a claim need only “sufficiently
    inform the [contracting officer] of what is being claimed such that the CO can meaningfully
    review the claim”); see also Menominee Tribe of Wis. v. United States, 
    764 F.3d 51
    , 55 (D.C.
    Cir. 2014), aff’d, 
    577 U.S. 250
     (2016) (explaining that a claim request “need not be detailed” and
    may consist of a “short written statement outlining the basis of the claim, estimating damages,
    and requesting a final decision”). A contractor’s submission can meet this threshold even if
    some of the factors on which the contractor’s demand is based “are, or will be disputed,” Metric
    Constr., 
    1 Cl. Ct. at 391
    , or if some amount of work on the contracting officer’s part is required
    to determine the claimant’s bottom-line, see Tunica-Biloxi Tribe of La., 577 F. Supp. at 410
    (noting that although a claimant’s submission was “hardly a model of clarity, it nevertheless
    provide[d] sufficient information for a reviewing agency like IHS to calculate the amount of
    damages alleged for each claim through ‘simple arithmetic’” (quoting Metric Constr., 
    1 Cl. Ct. at 392
    )). Nor, finally, need the sum certain requested even be the correct measure of what the
    claimant is owed, when all is said and done. See Sun Eagle Corp. v. United States, 
    23 Cl. Ct. 465
    , 472 (1991). The point of the administrative review process, after all, is to vet the accuracy
    of claims and to resolve disputed facts. In sum, although presentment imposes certain non-
    negotiable obligations on claimants, the bar for meeting those obligations is not as high as IHS
    suggests. The purpose of the notice requirement is to provide an opportunity for the contracting
    officer to review the claim, not to weed out claims or to limit the government’s exposure.
    Viewed under the appropriate standard, TCC’s claim was adequate. The table on the first
    page of its claim letter not only sets forth the total value of TCC’s claim—$12,153,793—it also
    breaks that total down into its constituent parts so that its basis can be better understood. Dkt. 1-
    13
    4 at 1. IHS does not dispute that the claim was for a sum certain and that it was for identified
    categories of costs.
    Instead, IHS’s argument turns on the contention that TCC failed to attribute the amount
    sought “to either of [the] two unique contracts in effect during the timeframe at issue.” Dkt. 15-1
    at 17. That contention, however, is difficult to square with the words that appear in the claim
    letter itself. To start, the letter is captioned: “Contract Disputes Act claim for unpaid contract
    support costs due in FY 2013 under Indian Self-Determination Act Compact and associated
    Funding Agreements.” Dkt. 1-4 at 1. There is little doubt that the “Compact” refers to the Title
    V Compact at issue in this case, and the parties agree that the Compact was accompanied by an
    “associated” funding agreement, which was itself subject to “modifications,” see Dkt. 15-1 at 7,
    11; Dkt. 1 at 4-5 (Compl. ¶¶ 11, 13); Dkt. 17 at 6-7. Read in this light, a contracting officer
    would have little difficulty in construing the caption of the claim letter to seek relief under the
    Title V Compact, the FY 2011-2013 Funding Agreement, and any related modifications to those
    agreements. Significantly, the caption says nothing about the Title I Contract.
    The body of the letter reaffirms this understanding. The very first sentence seeks
    “payment of $12,153,793 plus interest, due and owing to TCC under the provisions of the above-
    refenced Compact and associated funding agreements, as amended, in effect between the parties
    for fiscal year 2013.” Dkt. 1-4 at 1. Again, that assertion is unambiguous and does not even hint
    at a claim under the Title I Contract. Then, after including a chart specifying the specific
    categories of costs at issue and explaining that the claim was submitted pursuant to the CDA and
    ISDEAA, the letter continues: “During the covered years, TCC’s Compact, funding agreements,
    indirect cost agreements and the ISDEAA obligated the United States to pay TCC no less than
    the full amount of contract support costs, including indirect costs and direct contract support
    14
    costs, associated with TCC’s operation of the IHS program, functions, services, and activities
    specified in TCC’s contracts with IHS, as amended.” 
    Id.
     Once again, the claim is
    unambiguously premised on the “Compact” and the associated agreements.
    Taken as a whole, the letter constituted a “clear and unequivocal statement” that gave
    IHS “adequate notice of the basis and amount of the claim.” Cont. Cleaning Maint., 
    811 F.2d at 592
    . Upon reading the letter, the contracting officer would have known how much money TCC
    wanted and the reasons why it thought it was entitled to it. Nothing more is needed. There was
    no mistaking that TCC was claiming funds allegedly owed under the Title V Compact.
    In response, IHS observes that TCC’s claim letter thrice uses the plural “contracts”
    instead of the singular “contract.” Dkt. 15-1 at 19, 21; Dkt. 19 at 6, 8–9. That usage might
    reasonably be explained by the fact that TCC’s Title V Compact claim involved multiple
    agreements—the Compact itself, the funding agreement, and any modifications to that
    agreement. Dkt. 1-4 at 2. But, even if TCC was arguably sloppy at times and used the plural
    when the singular was called for, that imprecision is far from sufficient to overcome the letter’s
    repeated, clear assertions that the claim sought payment for amounts due under the Compact and
    “associated” agreements. IHS never suggests that the Title I Contract was an “associated”
    agreement for these purposes, and, indeed, one can easily imagine that the agency would have
    declined to consider a claim for damages under the Title I Contract had TCC sought such relief
    while merely referring to an “associated” agreement.
    In any event, it cannot reasonably be maintained that a few instances of plural rather than
    singular language rendered TCC’s request inscrutable or mysterious. “The content, not the
    form,” of a submission “determines what is sought in the claim.” Bruhn Newtech, Inc. v. United
    States, 
    129 Fed. Cl. 656
    , 663 (2016). “[N]o magic words”—or magic forms of tense— “[are]
    15
    required.” Id.; see Placeway Constr. Corp. v. United States, 
    920 F.2d 903
    , 908 (Fed. Cir. 1990)
    (“[T]his court [has] de-emphasized the importance of the form in which claims are submitted,
    stating, ‘We know of no requirement in the Disputes Act that a “claim” must be submitted in a
    particular form or use any particular wording.’” (quoting Cont. Cleaning Maint., 
    811 F.2d at 592
    )).
    IHS’s arguments based on the supporting financial schedules are more substantial but still
    fail to demonstrate that TCC’s administrative notice was fatally deficient. On those schedules,
    TCC references the Title I Contract, and, apparently, also references the corresponding contract
    number. Dkt. 1-4 at 5–6. The Court agrees with IHS that a reasonable contracting officer could
    have concluded that those analyses—standing alone—supported a claim for relief under both the
    Title V Compact and the Title I Contract. But when viewed in the context of TCC’s entire
    submission, those references to the Title I Contract are best viewed as an oversight in the
    supporting materials, and not as a separate request for damages under a contract that TCC never
    mentioned in its claim letter. When considered together with the letter’s caption and text, it
    cannot be said that these column labels stood as a barrier to IHS receiving reasonable notice of
    the “basis and amount” of TCC’s claim. Cont. Cleaning Maint., 
    811 F.2d at 592
    . The amount
    TCC sought was clear: $12,153,793. Dkt. 1-4 at 1. Whether that amount represented a correct
    calculation of what IHS owed TCC under the Title V Compact, was slightly inflated because
    TCC mistakenly included a small amount that TCC could have sought, but did not seek, under
    the Title I Contract, or instead was incorrect for any other reason is a merits question and not a
    jurisdictional one.
    Nor could the mistaken inclusion of expenses from the Title I Contract have had a
    significant impact on the total amount at issue, thereby preventing IHS from forming a
    16
    reasonable estimate of the funds it might have to pay. The “Cumulative Funding Report” for the
    Title V Compact, which IHS proffers in an exhibit to its motion to dismiss, “shows [a] total FY
    2013 funding of $52,617,909,” including “$1,871,568 in direct Contract Support Costs . . . and
    $6,999,836 in indirect Contract Support Costs.” Dkt. 15-1 at 22–23 n.8. In contrast, under the
    Title I Contract for FY 2013, TCC “received $704,771, including $283 in direct Contract
    Support Costs and $126,873 in indirect Support Costs.” 
    Id.
     at 23 n.8. Accordingly, accepting
    IHS’s reported figures as at least in the ballpark, even if TCC mistakenly included a number
    approximating the full value of what was paid for contract support costs under the Title I
    Contract, that would have amounted to only about 1% of the $12,153,793 that TCC sought in its
    September 30, 2019 claim.
    Moreover, to the extent TCC mistakenly included items related to the Title I Contract in
    its claim, IHS has proven itself up to the task of parsing the details and developing an informed
    position, demonstrating that the information TCC provided was sufficient to allow IHS
    “meaningfully [to] review the claim.” CPS Mech. Contractors, 
    59 Fed. Cl. at 763
    . IHS’s brief
    argues that the figures on which TCC based its calculations correspond exactly to certain items
    from the Title V Compact added together with corresponding items from the Title I Contract.
    Dkt. 15-1 at 22–23. The Court, of course, takes no position at this time on whether IHS is
    correct about that. But the fact that IHS was able to form a view on the issue with the materials
    it had in hand confirms that it had ample information to form an opinion respecting TCC’s claim
    and could easily have denied relief to the extent the schedules sought amounts in excess of the
    amount due under the Title V Compact and the agreements affiliated with the Compact, which is
    all that the claim letter sought. Courts have repeatedly held that if the amount of damages arising
    from a claim can be determined with “simple arithmetic,” the claim has been adequately
    17
    presented. See, e.g., Tunica-Biloxi Tribe of La., 
    577 F. Supp. 2d at 410
    ; Metric Constr. Co., 
    1 Cl. Ct. at 392
    ; CPS Mech. Contractors, 
    59 Fed. Cl. at 764
    . Here, no arithmetic was necessary to
    ascertain the amount that TCC was seeking—that is, $12,153,793—and IHS had no apparent
    difficulty assessing the merits of that claim.
    None of the authorities IHS invokes in support of its more demanding view of the notice
    requirement can bear the weight IHS places on them. The first is the interpretive principle that
    waivers of sovereign immunity are to be strictly construed in favor of the sovereign. Dkt. 15-1 at
    17; see also Lehman v. Nakshian, 
    453 U.S. 156
    , 161 (1981) (“[L]imitations and conditions upon
    which the Government consents to be sued must be strictly observed and exceptions thereto are
    not to be implied.”).2 The second is the IHS regulation that defines a “claim” as “a written
    demand . . . asking for . . . payment of a specific sum of money under the contract.” 
    25 C.F.R. § 900.218
    (a)(1). As the Court understands IHS’s argument, these authorities work in tandem:
    the regulation uses the definite article “the” and refers to a singular “contract,” and this language
    must be strictly construed to exclude any submission that refers to more than one contract.
    But even accepting that contestable interpretation of the regulation,3 TCC submitted a
    “claim.” It asked in writing for $12,153,793—a specific sum of money—“due and owing to
    2
    TCC argues that it has a countervailing (and codified) canon: 
    25 C.F.R. § 900.3
    (b)(11), which
    states that “The Secretary’s commitment to Indian self-determination requires that these
    regulations be liberally construed for the benefit of Indian tribes and tribal organizations to
    effectuate the strong Federal policy of self-determination and, further, that any ambiguities
    herein be construed in favor of the Indian tribe or tribal organization so as to facilitate and enable
    the transfer of services, programs, functions, and activities, or portions thereof, authorized by the
    Act.” Because IHS’s motion fails even without resort to this regulation, the Court need not
    decide whether it applies to the waiver of sovereign immunity at issue in this case.
    3
    Among other things, that reading of the definition of “claim” proves too much, since here—as,
    presumably, in many or most cases—the government’s obligation is premised on several related
    agreements, including the overarching compact or agreement, the funding agreement, and
    18
    TCC under the provisions of the above-referenced Compact and associated funding agreements,
    as amended, in effect between the parties for fiscal year 2013.” Dkt. 1-4 at 1. The “above-
    referenced Compact” is TCC’s “Indian Self-Determination Act Compact”—i.e., the Title V
    Compact. 
    Id.
     A request for a dollar figure under a particular contract satisfies § 900.218(a)(1)
    even by IHS’s own strict-construction lights. As explained, the specific sum of money TCC
    requested may or may not constitute an accurate assessment of what it was due under the Title V
    Compact (because that figure may include a small amount related to the Title I Contract, or it
    may be incorrect for any number of other reasons). But asking for an incorrect specific sum
    under a contract is not the same thing as asking for an unspecific sum under an unspecified
    contract or contracts. This case might involve the former situation, but it does not present the
    latter.
    Notably, IHS fails to point to any case in which a court has deployed the sovereign
    immunity canon to render a claim like TCC’s inadequate. To the contrary, courts no doubt
    aware of that maxim have time and again recognized that CDA presentment is a notice
    requirement, not something more demanding. See, e.g., CPS Mech. Contractors, 
    59 Fed. Cl. at
    763–64 (recognizing that presentment is jurisdictional but also that it requires only “a clear and
    unequivocal statement that gives the CO adequate notice of the basis for the claim” and that
    allows “the amount in dispute” to be “easily determined”); Cont. Cleaning Maint., 
    811 F.2d at
    591–93 (same); Tunica-Biloxi Tribe of La., 
    577 F. Supp. 2d at
    407–11 (same). Although IHS
    repeatedly cites to M. Maropakis, that case is consistent with this understanding. There, the
    Federal Circuit cited to the strict requirements of sovereign immunity to reject the notion that a
    whatever modifications the parties may have adopted. That is the way government contracting
    typically works.
    19
    claimant could “ignore the jurisdictional requirements of the CDA” by failing to provide
    “adequate notice” of the actual value of its claim, “state a sum certain,” and “request a final
    decision.” M. Maropakis, 
    609 F.3d at 1329
    . TCC, by contrast, did not ignore these requirements
    and, in fact, requested a specific sum from IHS. Dkt. 1-4 at 1. Even if not crystal clear, TCC’s
    claim letter put IHS on notice, which is all it had to do.
    B.     Whether TCC Presses a Different Claim Than It Did Before IHS
    Shifting its emphasis, IHS argues that TCC now seeks to correct the defects with its
    presentment by bringing a different claim before this Court than it did before IHS, effectively
    circumventing presentment. Dkt. 15-1 at 14–15. In its complaint and briefing, TCC has
    steadfastly maintained that it seeks relief under only the Title V Compact. Dkt. 1 at 13 (Compl.
    ¶ 43); Dkt. 17 at 7. This TCC may not do, says IHS, when its initial claim letter sought relief
    under both the Compact and the Title I Contract, or alternatively, was so vague that it was
    impossible to determine which contract or contracts were at issue. Dkt. 15-1 at 21. IHS suggests
    that the numbers tell the story, pointing out that although the figures TCC provided with its claim
    letter cannot be reconciled with the funding TCC received and expenses it incurred under the
    Title V Compact, they do match up with the equivalent values for the Title V Compact and Title
    I Contract added together. Dkt. 15-1 at 22–23. For instance, according to IHS, what TCC’s
    second schedule labels “Total Funding Awarded” corresponds not to the total funding IHS
    awarded TCC under the Title V Compact, but rather the combined value of the funding for the
    Title V Compact and Title I Contract. 
    Id.
     IHS insists that this and similar examples it offers
    show that TCC asserted claims under two contracts at the administrative level and that it is not
    playing it straight with the Court now. 
    Id.
    20
    There are several problems with this reasoning. Most notably, it fails to accept the
    possibility that TCC’s claim letter was premised, as the letter says it was, on an alleged breach of
    the “Compact and associated Fund Agreements,” Dkt. 1-4 at 1, and that the inclusion of a small
    amount from the Title I Contract in the attached schedules was simply an oversight, which IHS
    or TCC could easily have corrected. Or, framed more generally, IHS’s alternative argument
    adds little, if anything, to its motion. If IHS were correct that TCC’s presentment was defective,
    that alone would deprive the Court of jurisdiction. But if not, then the premise of this alternative
    argument—that TCC presented an overly vague claim stemming from two contracts—is faulty.
    Because the Court holds that TCC adequately presented its claim to IHS, it necessarily rejects the
    notion that this claim was a two-contract jumble irreconcilable with the demands TCC more
    clearly makes in its complaint.
    Putting this difficulty aside, even on its own terms IHS’s different-claim argument is
    unpersuasive. IHS is correct that a court action under the CDA “must be ‘based on the same
    claim previously presented to and denied by the contracting officer.’” Scott Timber Co. v.
    United States, 
    333 F.3d 1358
    , 1365 (Fed. Cir. 2003) (quoting Cerberonics, Inc. v. United States,
    
    13 Cl. Ct. 415
    , 417 (1987)). This rule follows from 
    41 U.S.C. § 7103
    (a)’s requirement that
    before a court can exercise jurisdiction over a claim under the CDA, “the contractor must have
    received the contracting officer’s final decision on that claim.” M. Maropakis, 
    609 F.3d at 1328
    .
    To determine whether a plaintiff has satisfied this condition, courts assess whether the complaint
    “is based on the same set of operative facts underlying the claim presented to the contracting
    officer.” Cerberonics, 
    13 Cl. Ct. at 417
    . Under the “operative facts” inquiry, “[i]f the court will
    have to review the same or related evidence to make its decision” as did the contracting officer,
    “then only one claim exists.” Placeway Const., 
    920 F.2d at 907
    . If, “[o]n the other hand,” “the
    21
    claims as presented to the [contracting officer] will necessitate a focus on a different or unrelated
    set of operative facts as to each claim, then separate claims exist.” 
    Id.
     This analysis focuses on
    the core factual basis for the claim, not every last detail. For example, a plaintiff can request
    greater damages than it did before the contracting officer, Santa Fe Eng’r’s, Inc. v. United States,
    
    818 F.2d 856
    , 858 (Fed. Cir. 1987), and even “assert differing legal theories,” so long as it
    ultimately “claim[s] essentially the same relief,” Scott Timber, 
    333 F.3d at 1365
    . Because the
    operative facts test exists to vindicate the statutory requirement of presentment, courts must also
    evaluate “whether the scheme of adjudication prescribed by the CDA is undermined . . . by
    circumventing the statutory role of the contracting officer to receive and pass judgment on the
    contractor’s entire claim.” Affiliated Constr. Grp., Inc. v. United States, 
    115 Fed. Cl. 607
    , 612
    (2014) (quoting Cerberonics, 
    13 Cl. Ct. at 418
    ). “In other words, the claim before the court
    cannot be said to arise from the same operative facts unless it is clear that the claim presented to
    the contracting officer was specific enough to give the officer notice of the basis of the claim and
    allow him to make an informed judgment about it.” 
    Id.
    TCC’s claims before this Court are based on the same “operative facts” that were
    presented to IHS. The relief sought in the complaint is identical to that which TCC sought
    before the contracting officer, except that TCC has opted not to seek one category of relief that it
    sought there. Dkt. 1 at 21 n.4; compare Dkt. 1 at 21 (Compl. ¶ 78), with Dkt. 1-4 at 1. As a
    result, every dollar of damages TCC seeks here it sought from IHS in the first instance. Dkt. 1 at
    21 n.4. This is, by any standard, “essentially the same relief,” Scott Timber, 
    333 F.3d at 1365
    ,
    and, for that reason, TCC’s lawsuit does not raise any prospect of circumvention. TCC is not
    asking this Court to decide a new question or to consider a claim that IHS was denied the
    opportunity to consider. To the contrary, TCC is asking the Court to decide a subset of the
    22
    questions it presented in the administrative process. The sort of shift that raises the specter of
    circumvention is a request for new or greater relief. TCC complaint narrows the scope of its
    claim and thus does just opposite.
    IHS closes with a warning: “Under Tanana Chiefs Conference’s theory of the case, a
    contractor could submit claims tied to several contracts and so long as some sum was demanded,
    the onus would be on the relevant agency to sort out the source of its obligation to pay that
    alleged sum. There would be no requirement for the claimant to specify the source of the sum
    demanded, including by identifying the contract giving rise to any obligation to pay.” Dkt. 19 at
    12. The Court fails to see how that is so. TCC did specify the source of the sum demanded, just
    as it identified the contract giving rise to IHS’s alleged obligation to pay. For all its hand
    wringing about TCC’s letter, IHS cannot point to a single sentence in the claim letter itself in
    which TCC requested payment under any contract other than the Title V Compact. Indeed, if
    anything, it is IHS’s position that raises the specter of confusion, since it invites contracting
    officers to ignore the text of the claim letter and, instead, to consider whether any supporting
    materials provided along with the claim include an element of damages attributable to a different
    contract and, if so, to decline to consider the claim—thereby precluding judicial review—based
    on his or her belief that the supporting documentation shows that the claim is actually for
    amounts attributable to a different contract. IHS’s concern about whether the claim that TCC
    presented in the administrative process and that it seeks to pursue before this Court erroneously
    includes amounts related to a different contract is fair game. But that is a question for another
    day.
    23
    CONCLUSION
    For the foregoing reasons, the Court DENIES Defendants’ motion to dismiss. Dkt. 15.
    SO ORDERED
    /s/ Randolph D. Moss
    RANDOLPH D. MOSS
    United States District Judge
    Date: September 15, 2022
    24
    

Document Info

Docket Number: Civil Action No. 2020-2902

Judges: Judge Randolph D. Moss

Filed Date: 9/15/2022

Precedential Status: Precedential

Modified Date: 9/15/2022

Authorities (22)

Phoenix Consulting, Inc. v. Republic of Angola , 216 F.3d 36 ( 2000 )

Victor Herbert v. National Academy of Sciences , 974 F.2d 192 ( 1992 )

Menominee Indian Tribe of Wisconsin v. United States , 614 F.3d 519 ( 2010 )

M. Maropakis Carpentry, Inc. v. United States , 609 F.3d 1323 ( 2010 )

Scott Timber Company v. United States , 333 F.3d 1358 ( 2003 )

Santa Fe Engineers, Inc. v. The United States , 818 F.2d 856 ( 1987 )

Metric Construction Co. v. United States , 1 Cl. Ct. 383 ( 1983 )

Cerberonics, Inc. v. United States , 13 Cl. Ct. 415 ( 1987 )

Sun Eagle Corp. v. United States , 23 Cl. Ct. 465 ( 1991 )

Contract Cleaning Maintenance, Inc. v. The United States , 811 F.2d 586 ( 1987 )

Placeway Construction Corporation v. The United States , 920 F.2d 903 ( 1990 )

James M. Ellett Construction Company, Inc. v. United States , 93 F.3d 1537 ( 1996 )

United States v. Sherwood , 61 S. Ct. 767 ( 1941 )

Tunica-Biloxi Tribe of La. v. United States , 577 F. Supp. 2d 382 ( 2008 )

Lehman v. Nakshian , 101 S. Ct. 2698 ( 1981 )

Lujan v. Defenders of Wildlife , 112 S. Ct. 2130 ( 1992 )

Lincoln v. Vigil , 113 S. Ct. 2024 ( 1993 )

Federal Deposit Insurance v. Meyer , 114 S. Ct. 996 ( 1994 )

Cherokee Nation of Okla. v. Leavitt , 125 S. Ct. 1172 ( 2005 )

Ashcroft v. Iqbal , 129 S. Ct. 1937 ( 2009 )

View All Authorities »