Standing Rock Sioux Tribe v. United States Army Corps of Engineers ( 2018 )


Menu:
  •                            UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    STANDING ROCK SIOUX TRIBE,
    Plaintiff,
    and
    CHEYENNE RIVER SIOUX TRIBE,
    Plaintiff-Intervenor,
    Civil Action No. 16-1534 (JEB) (and
    v.                                       Consolidated Case Nos. 16-1769 and
    16-267)
    U.S. ARMY CORPS OF ENGINEERS,
    Defendant,
    and
    DAKOTA ACCESS, LLC,
    Defendant-Intervenor and Cross-
    Claimant.
    MEMORANDUM OPINION
    Once more into the breach over the Dakota Access Pipeline goes this Court, though for
    the first time addressing claims of the Yankton Sioux Tribe and Robert Flying Hawk, the
    Chairman of the Tribe’s Business and Claims Committee. While the Plaintiffs may have
    changed, the underlying claims are quite familiar. As with the Standing Rock and Cheyenne
    River Sioux Tribes before them, the Yankton Sioux challenge the construction and operation of
    the Dakota Access Pipeline under the National Historic Preservation Act, the National
    Environmental Protection Act, and the 1851 Treaty of Laramie. Specifically, Plaintiffs allege
    1
    that Defendants – the U.S. Army Corps of Engineers, the U.S. Fish and Wildlife Service, and an
    assortment of federal employees of both agencies – violated the NHPA by failing to adequately
    consult with the Tribe regarding historical and cultural sites, violated NEPA by unlawfully
    segmenting their analyses of the pipeline’s environmental impacts, and violated the 1851 Treaty
    by granting approvals for DAPL without first obtaining the Tribe’s consent.
    Both sides have now filed Cross-Motions for Summary Judgment on the Tribe’s NEPA
    and Treaty-based claims. Defendants additionally urge the Court to dismiss as moot Plaintiffs’
    NHPA counts, asserting that they are no longer viable in light of DAPL’s completed
    construction. Agreeing that it can provide no effective remedy on this last score, the Court will
    dismiss the NHPA claims. It will also grant summary judgment for Defendants with respect to
    Plaintiffs’ Treaty-based count, which the Tribe essentially withdrew during briefing. Finally, the
    Court concludes that Plaintiffs have not shown that the Corps and FWS improperly “segmented”
    their analysis of the pipeline’s environmental consequences, thus yielding summary judgment for
    Defendants on the NEPA claims as well.
    I.      Background
    A.      Factual and Statutory Background
    The lengthy factual history of the Dakota Access Pipeline, a 1,200-mile domestic-oil
    pipeline running from North Dakota to Illinois, is set forth in this Court’s prior Opinions and
    need not be repeated here. See, e.g., Standing Rock Sioux Tribe v. U.S. Army Corps of
    Engineers (Standing Rock I), 
    205 F. Supp. 3d 4
    , 12-15 (D.D.C. 2016). The Court will, however,
    provide a brief background of this Tribe’s participation in DAPL’s development and an overview
    of the specific federal actions related to the pipeline.
    2
    A federally recognized Tribe that is headquartered in Wagner, South Dakota, the Yankton
    Sioux have approximately 9,000 enrolled members. See ECF No. 292 (Yankton MSJ) at 3.
    Their Reservation is located in South Dakota, hundreds of miles from the much-contested Lake
    Oahe crossing and at least 60 miles from any other part of DAPL’s path. See ECF No. 321 at 5
    (Map 2). The Tribe nonetheless opposes the construction and routing of the pipeline, alleging
    that it will harm a number of its environmental interests.
    Since the pipeline project was proposed, Plaintiffs insist that they have “continually
    sought to protect” their tribal lands from the “serious risk of harm” it poses. See Yankton MSJ at
    4. This assertion is somewhat belied, however, by the record regarding the Tribe’s cooperation
    (or lack thereof) with the federal agencies involved in the project. The Yankton did not attend
    multiple meetings held by the Corps and FWS to discuss DAPL (meetings that were attended by
    other interested tribes), see Exhs. I (January 25, 2016, Corps Meeting Log), J (December 8,
    2015, Corps Meeting Log), V (List of Invitees to FWS Meetings), W (FWS Meeting Log), nor
    did they respond to numerous efforts by the Corps and FWS to engage in discussion regarding
    the pipeline. See Exhs. N (Letter from Col. Henderson, May 10, 2016), O (Letter from Col.
    Henderson, May 6, 2016), P (Email Chain Discussing Corps’ Attempts to Contact Yankton, May
    2, 2016), Q (Email Chain Discussing Consultation, April 15-22, 2016), T (Letter from FWS to
    Chairman Flying Hawk), U (Letter from FWS to Tribal Officer Little). Regardless of the Tribe’s
    level of participation in the consultation process, however, the Yankton have since objected to
    the pipeline’s construction and routing.
    In particular, Plaintiffs contest the process by which the Corps and FWS issued a series of
    permits and permissions necessary for the pipeline to cross federally regulated lands and waters.
    Although DAPL runs almost entirely across private property, 3% of the pipeline is on federally
    3
    managed land and thus required governmental approval. See Standing Rock 
    I, 205 F. Supp. 3d at 13
    . The permits needed for these portions of the pipeline were issued by four separate entities
    – three districts of the Corps and one district of FWS. In evaluating these permissions, each
    agency division conducted an environmental assessment under the National Environmental
    Protection Act.
    NEPA requires that federal agencies evaluate the environmental effects of major
    government actions, but it “imposes only procedural requirements.” Dep’t of Transp. v. Public
    Citizen, 
    541 U.S. 752
    , 756 (2004). If a project will “significantly” affect the “quality of the
    human environment,” NEPA requires that the agency complete a detailed Environmental Impact
    Statement (EIS). See 42 U.S.C. § 4332(C). To determine whether or not there will be such
    significant effects, however, the agency first prepares a shorter Environmental Analysis (EA).
    This “concise public document” discusses the need for the proposal, the alternatives, the
    environmental impacts of the proposed action, and the agencies and persons consulted. See 40
    C.F.R. § 1508.9(a), (b). If the EA concludes that there will be no significant environmental
    impact, the agency may forgo completing a full EIS and may instead issue the EA and a Finding
    of No Significance (FONSI).
    This was the route chosen by the federal agencies charged with evaluating the DAPL-
    related permissions. In July 2016, the Corps’ Omaha District issued an EA and FONSI related to
    the crossings of Corps-managed lands and flowage easements at Lake Oahe and Lake
    Sakakawea in North Dakota. See Exh. A (Omaha District EA and FONSI). In August of that
    year, the Corps’ St. Louis District issued its own EA and FONSI, which addressed four crossings
    in Illinois, three of which spanned less than 700 feet, and one of which crossed a federal flowage
    easement for approximately 2.5 miles. See Exh. B (St. Louis District EA and FONSI). The
    4
    Corps’ Rock Island District also issued a permission under Section 408 of the Rivers and
    Harbors Act for a crossing of the Mississippi River, after the district determined that the proposal
    qualified for a categorical exclusion under NEPA. See Exh. C (Rock Island District
    Memorandum). Finally, the FWS issued an EA in May 2016 and a FONSI in June of that year,
    and it granted Dakota Access permission to cross five wetland easements and one grassland
    easement in North Dakota. See Exhs. D (FWS EA), E (FWS FONSI). These easements, which
    were over 60 miles from the water crossings evaluated by the Corps, affected 71.8 acres of the
    pipeline route, or less than 1% of the total North Dakota and South Dakota project area. See
    FWS EA at 18. In total, therefore, the federal agencies issued three EAs and complementary
    FONSIs and one categorical exclusion, each of which in turn facilitated the various permissions
    and permits needed for DAPL to cross federally managed lands. It is these NEPA analyses, and
    the process by which they were conducted, to which Plaintiffs now object.
    B.      Procedural History
    1.     History of DAPL Litigation
    The Yankton Sioux Tribe initiated the instant suit on September 9, 2016, when it filed a
    Complaint against the United States Army Corps of Engineers, the United States Fish and
    Wildlife Service, and four individual Defendants – Dan Ashe, Director of FWS; John W.
    Henderson, Commander of the Corps’ Omaha District; Anthony Mitchell, Commander of the
    Corps’ St. Louis District; and Todd Semonite, the Corps’ Commanding General and Chief of
    Engineers. See Case No. 16-1796, ECF No. 1 (Yankton Sioux Compl.). In February 2017,
    Defendant Dakota Access moved to intervene in support of federal Defendants, a motion that
    was not opposed by the Tribe and was subsequently granted by the Court. 
    Id., ECF No.
    17
    (Dakota Access Motion to Intervene); Minute Order of March 13, 2017 (Granting Motion to
    5
    Intervene as Unopposed). That March, upon an unopposed motion by the Corps, the Tribe’s case
    was consolidated with challenges to DAPL filed by the Standing Rock, Cheyenne River, and
    Oglala Sioux Tribes. See Minute Order of March 17 (Consolidation Order).
    For the past fourteen months, others among the consolidated Plaintiffs have made
    multiple attempts to prevent oil from flowing through the pipeline. Indeed, this Court has now
    issued five Opinions in this case – all addressing various claims by the Standing Rock and
    Cheyenne River Sioux Tribes. These Tribes’ first pass at preventing pipeline construction was a
    motion for a preliminary injunction based solely on the NHPA, asserting that the ongoing
    clearing and grading of the land along DAPL’s route disrupted sacred tribal sites. See Standing
    Rock 
    I, 205 F. Supp. 3d at 7-9
    . On September 9, 2016, the Court denied emergency relief, and
    construction proceeded. 
    Id. at 37.
    On February 8, 2017, the Corps granted Dakota Access an easement pursuant to the
    Mineral Leasing Act, authorizing it to cross federal lands at Lake Oahe and complete the
    pipeline. See ECF No. 172-11 (Easement). The next day, Cheyenne River filed another motion
    for preliminary injunction and an application for a temporary restraining order, this time alleging
    violations of the Religious Freedom Restoration Act. See ECF Nos. 98, 99; Standing Rock
    Sioux Tribe v. U.S. Army Corps of Engineers (Standing Rock II), 
    239 F. Supp. 3d 77
    , 81
    (D.D.C. 2017), appeal dismissed, No. 17-5043, 
    2017 WL 4071136
    (D.C. Cir. May 15, 2017).
    Believing these religious-freedom claims unlikely to succeed, the Court issued an Opinion
    denying this preliminary injunction as well. See Standing Rock 
    II, 239 F. Supp. 3d at 80
    . As
    these emergency motions were ongoing, Standing Rock and Cheyenne River filed cross-motions
    for summary judgment. See ECF Nos. 117 (SRST MSJ), 131 (CRST MSJ), 172 (Corps MSJ),
    185 (DA MSJ). Now focusing on their environmental claims, the Tribes challenged the Corps’
    6
    decision to issue the easement on the basis of its July 25, 2016, EA and FONSI, contending that
    the agency had violated NEPA by failing to complete a full EIS.
    On June 14, 2017, two weeks after DAPL became fully operational, the Court granted in
    part and denied in part the parties’ motions and remanded certain issues to the Corps. See
    Standing Rock Sioux Tribe v. U.S. Army Corps of Engineers (Standing Rock III), 
    255 F. Supp. 3d
    101 (D.D.C. 2017). It rejected Plaintiffs’ motion with respect to their claims under the
    Mineral Leasing Act and upheld the majority of the Corps’ determinations under NEPA. 
    Id. at 152,
    147. It granted the Tribes’ motion, however, with respect to three discrete flaws in the
    Corps’ environmental analysis. 
    Id. at 147.
    Although the Court remanded these issues to the
    Corps for further analysis, it did not decide whether the easement should be vacated pending
    such remand. 
    Id. at 147-48.
    That determination followed in the Court’s October 11, 2017,
    Opinion, in which it concluded that there was a “serious possibility” that the Corps would be
    able to substantiate its prior determinations and thus denied vacatur pending remand. See
    Standing Rock Sioux Tribe v. U.S. Army Corps of Engineers (Standing Rock IV), 
    2017 WL 4564714
    (D.D.C. Oct. 11, 2017). Finally, this past December, the Court issued an Opinion
    imposing a series of interim measures during the remand process, each tailored to keeping the
    Court informed as to the conditions at Lake Oahe pending further analysis by the Corps. See
    Standing Rock Sioux Tribe v. U.S. Army Corps of Engineers (Standing Rock V), 
    2017 WL 6001726
    (D.D.C. Dec. 4, 2017). The remand process remains ongoing and will extend past
    April 2, 2018. See ECF No. 338 (Corps’ Notice).
    2.     Yankton Motion for Summary Judgment
    Only now, as that remand is ongoing and further analysis is underway, have the Yankton
    Sioux and Robert Flying Hawk chosen to enter the fray. On November 13, 2017, they brought
    7
    the instant Motion for Partial Summary Judgment on the basis of their claims arising under
    NEPA and the Tribe’s 1851 Treaty of Laramie with the United States. See Yankton MSJ.
    Specifically, the Tribe asserts that Defendants violated NEPA by segmenting their evaluation of
    DAPL’s environmental impacts among multiple federal agencies and Corps divisions. 
    Id. at 5-
    16. Arguing that the various federal permissions for the pipeline are “connected” or “similar”
    actions under the meaning of NEPA’s implementing regulations, Plaintiffs contend that
    Defendants were thus required to conduct a consolidated, programmatic assessment of the
    approvals. 
    Id. at 5-
    6. Plaintiffs additionally move for summary judgment on their claim that, by
    failing to obtain the Tribe’s free and informed consent prior to granting authorizations for
    DAPL’s construction, the Corps and FWS violated the Tribe’s 1851 Treaty of Fort Laramie and
    the federal government’s trust responsibilities to the Tribe. 
    Id. at 19-29.
    On January 10, 2018, federal Defendants filed their Opposition to Plaintiffs’ claims and
    cross-moved for partial summary judgment. See ECF No. 320 (Corps Opp.) Dakota Access, as
    a Defendant-Intervenor and Cross-Claimant, also filed its own Opposition and brief in support of
    federal Defendants’ Cross-Motion. See DA Opp. In their briefing, Defendants additionally
    moved to dismiss the Tribe’s NHPA claims as moot in light of DAPL’s completed construction
    and current operation. Plaintiffs filed their Reply and Opposition on January 26, 2018, in which
    they continue to request summary judgment on their NEPA counts, but “withdraw” their Motion
    with respect to their Treaty- and trust-based claims. See ECF No. 324 (Yankton Reply). They
    also oppose Defendants’ Motion with respect to the dismissal of their NHPA claim, asserting
    that the related counts in their Complaint remain viable. With briefing complete, the Court must
    now determine whether summary judgment is appropriate for either party.
    8
    II.    Legal Standard
    The parties have cross-moved for partial summary judgment on the administrative record.
    The summary-judgment standard set forth in Federal Rule of Civil Procedure 56(c), therefore,
    “does not apply because of the limited role of a court in reviewing the administrative record.”
    Sierra Club v. Mainella, 
    459 F. Supp. 2d 76
    , 89 (D.D.C. 2006); see also Bloch v. Powell, 227 F.
    Supp. 2d 25, 30 (D.D.C. 2002), aff'd, 
    348 F.3d 1060
    (D.C. Cir. 2003). “[T]he function of the
    district court is to determine whether or not as a matter of law the evidence in the administrative
    record permitted the agency to make the decision it did.” Sierra 
    Club, 459 F. Supp. 2d at 90
    (quotation marks and citation omitted). “Summary judgment is the proper mechanism for
    deciding, as a matter of law, whether an agency action is supported by the administrative record
    and consistent with the [Administrative Procedure Act] standard of review.” Loma Linda Univ.
    Med. Ctr. v. Sebelius, 
    684 F. Supp. 2d 42
    , 52 (D.D.C. 2010) (citation omitted), aff'd, 408 Fed.
    App’x. 383 (D.C. Cir. 2010).
    The Administrative Procedure Act “sets forth the full extent of judicial authority to
    review executive agency action for procedural correctness.” FCC v. Fox Television Stations,
    Inc., 
    556 U.S. 502
    , 513 (2009). It requires courts to “hold unlawful and set aside agency action,
    findings, and conclusions” that are “arbitrary, capricious, an abuse of discretion, or otherwise not
    in accordance with law.” 5 U.S.C. § 706(2)(A). Agency action is arbitrary and capricious if, for
    example, the agency “entirely failed to consider an important aspect of the problem, offered an
    explanation for its decision that runs counter to the evidence before the agency, or is so
    implausible that it could not be ascribed to a difference in view or the product of agency
    expertise.” Motor Vehicle Mfrs. Ass'n of U.S., Inc. v. State Farm Mut. Auto. Ins., 
    463 U.S. 29
    ,
    43 (1983). This is a “narrow” standard of review, under which “a court is not to substitute its
    9
    judgment for that of the agency.” 
    Id. Rather, the
    Court “will defer to the [agency's]
    interpretation of what [a statute] requires so long as it is ‘rational and supported by the record.’”
    Oceana, Inc. v. Locke, 
    670 F.3d 1238
    , 1240 (D.C. Cir. 2011) (quoting C & W Fish Co. v. Fox,
    
    931 F.2d 1556
    , 1562 (D.C. Cir. 1991)). Although a reviewing court “may not supply a reasoned
    basis for the agency’s action that the agency itself has not given,” a decision that is not fully
    explained may, nevertheless, be upheld “if the agency's path may reasonably be discerned.”
    Bowman Transp., Inc. v. Arkansas-Best Freight System, Inc., 
    419 U.S. 281
    , 285-86 (1974)
    (citations omitted).
    III.   Analysis
    A.      Preliminary Issues
    Before turning to the crux of this case – the Tribe’s NEPA challenge to Defendants’
    environmental assessments – the Court first pauses to address four preliminary issues.
    1. LCvR 7(h)
    First, and simplest, is the question of whether Plaintiffs are correct that, because
    Defendants “failed to controvert any facts identified by [the Tribe] in the statement of material
    facts[,] . . . this Court should assume Plaintiffs’ facts are admitted” under Local Rule 7(h). See
    Yankton Reply at 3. They are not. Indeed, as Defendants accurately note, Rule 7(h) does not
    apply in cases such as this one in which judicial review is based solely on the administrative
    record. See All. for Nat. Health U.S. v. Sebelius, 
    775 F. Supp. 2d 114
    , 118 (D.D.C. 2011)
    (noting that “in cases in which judicial review is based solely on the administrative record, the
    parties are not required to submit statements of disputed or undisputed material facts”) (internal
    quotations omitted). The Court, therefore, will not treat Plaintiff’s facts as admitted and will
    instead evaluate the parties’ claims on the basis of the underlying administrative record.
    10
    2.      Treaty and Trust Claims
    The Court next looks at the Tribe’s Treaty-based claims. Plaintiffs’ Motion relies in part
    on the first count of their Complaint, which alleged that Defendants violated the 1851 Treaty of
    Laramie, the federal trust responsibilities to the Tribe, and the United Nations Declaration on the
    Rights of Indigenous Peoples (UNDRIP). See Compl., ¶¶ 81-90. More specifically, Plaintiffs
    assert that Defendants failed to “consider the impacts of [their] actions to the Tribe’s 1851 Treaty
    Rights” and that the Corps breached its “fiduciary duty to consider how its actions may affect a
    tribe’s treaty rights.” Yankton MSJ at 20, 29. In their Oppositions and Cross-Motions,
    Defendants contend that this matter was already disposed of in Standing Rock II. They argue,
    moreover, that regardless of this Court’s prior Opinion, Plaintiffs are unable to identify any
    retained tribal rights in land or waters that would be affected by DAPL’s construction. See
    Corps Opp. at 18-19 (stating that “Plaintiffs offer no “compelling reason why this Court should
    reconsider” its prior Opinion addressing treaty rights), 27-28 (noting that Yankton’s current
    lands are 230 miles away from the Lake Oahe crossing and the Tribe has “not identified any
    possibility . . . that a spill would impact [its] lands”); DA Opp. at 21 (“Yankton’s arguments
    based on treaty and trust obligation are indistinguishable from those the Court already considered
    and resolved.”).
    Plaintiffs were apparently persuaded by such arguments. In its Reply, the Tribe stated
    that “after reviewing [f]ederal Defendants’ response, and given the complexities of rules for
    interpretation of treaties, Plaintiffs hereby withdraw the [] claim presented in their motion for
    partial summary judgment regarding [Defendants’] failure to consider the Tribe’s treaty rights,
    and choose not to pursue that claim at this time.” Yankton Reply at 2.
    11
    This attempt at a limited “withdrawal” is, unfortunately for the Tribe, not a fruitful legal
    tactic. Parties are not permitted to float trial balloons in motions for summary judgment, only to
    retract but preserve their claims when the opposing party makes a stronger argument. Instead, by
    retreating from their Treaty-based claims “after reviewing” Defendants’ response, the Tribe has
    essentially conceded that the Court should grant the Corps’ Cross-Motion for Summary
    Judgment on this issue. See Abraham v. Diagnostic Ctr. Hosp. Corp. of Texas, 
    138 F. Supp. 2d 809
    , 816 (S.D. Tex. 2001) (granting summary judgment for opposing party when plaintiff
    “cho[se] not to pursue” a given claim raised in initial motion for summary judgment).
    Yet even if the Tribe had not withdrawn the relevant portions of its Motion, it would not
    have prevailed. Defendants are correct that in light of this Court’s prior Opinion rejecting nearly
    identical trust and treaty arguments made by the Standing Rock and Cheyenne River Sioux
    Tribes, Yankton’s claims are ultimately futile. See Standing Rock III, 
    255 F. Supp. 3d
    at 145.
    Indeed, Plaintiffs make no attempt to distinguish their position from that deemed deficient in
    Standing Rock III. They instead assert that they “object to this Court’s holding in [its] June 14,
    2017, Memorandum Opinion” and “incorporate[] Standing Rock Sioux Tribe’s arguments . . . as
    to why treaties and U.S. trust responsibilities can provide the law to apply.” Yankton MSJ at 30
    n.4; see 
    id. at 29
    n.3 (“adopt[ing]” Standing Rock’s arguments regarding federal Defendants’
    “enhanced responsibility to consider Tribe’s treaty rights”). Disagreement, however, is not a
    legal basis for this Court to reverse its prior conclusions. Having already held that the Corps did
    not have to address the 1851 “Treaty rights qua Treaty Rights” and that the “general trust
    relationship between the Government and Indian tribes . . . alone does not afford an Indian tribe
    with a cause of action against the Government,” Standing Rock III, 
    255 F. Supp. 3d
    at 131, 145,
    the Court finds no grounds for letting the Tribe proceed on this portion of Count I.
    12
    The Court will additionally grant summary judgment with respect to Plaintiffs’ UNDRIP
    claim. As Defendants accurately note, courts have consistently held that UNDRIP is a non-
    binding declaration that does not create a federal cause of action. See Corps Opp. at 19 n.8;
    Isaac v. Sigman, 
    2017 WL 2267264
    , at *6 (D.N.J. May 24, 2017) (collecting cases). The Tribe
    makes no argument as to why this Court should find otherwise. It will thus grant summary
    judgment in favor of Defendants on this entire count.
    3.      Standing
    Defendants additionally contend that the Tribe falls short of establishing standing for the
    purpose of bringing their NEPA and NHPA claims. See Corps Opp. at 29. In particular, the
    Corps asserts that Plaintiffs “do not provide a specific and concrete plan to return to or use Lake
    Oahe specifically or identify how any federal action causes them harm.” 
    Id. at 30.
    The Tribe’s
    declarations, according to Defendants, “do not establish current or future use of the areas around
    Lake Oahe” and instead only “mention past visits” to the area and the fact that “unnamed tribal
    members hunt, gather and perform ceremony with water including the Missouri River in North
    and South Dakota.” 
    Id. The Corps
    casts these assertions as “generalized grievance[s]” and thus
    insufficient to confer standing under Article III. 
    Id. at 29.
    In order to establish standing, a plaintiff must show that: (1) she has suffered an “injury
    in fact” that is (a) concrete and particularized and (b) actual or imminent, rather than conjectural
    or hypothetical; 2) the injury is caused by, or fairly traceable to, the challenged action; and 3) it
    is likely, rather than merely speculative, that the injury will be redressed by a favorable decision.
    See Friends of the Earth, Inc. v. Laidlaw Envtl. Servs., 
    528 U.S. 167
    , 180–81 (2000). Because
    Plaintiffs here seek to enforce a procedural right – namely, Defendants’ alleged violation of
    NEPA by conducting separate environmental analyses – they may, however, “assert that right
    13
    without meeting all the normal standards for redressability and immediacy.” Summers v. Earth
    Island Inst., 
    555 U.S. 488
    , 496 (2009). To defeat a defendant’s summary-judgment motion, a
    plaintiff must make these required showings by averring specific facts; conclusory allegations in
    a complaint or other pleading are insufficient to establish standing on summary judgment. See
    Lujan v. Nat'l Wildlife Fed'n, 
    497 U.S. 871
    , 888–89 (1990). In environmental cases, “plaintiffs
    adequately allege injury in fact when they aver that they use the affected area and are persons
    ‘for whom the aesthetic and recreational values of the area will be lessened’ by the challenged
    activity.” Friends of the 
    Earth, 528 U.S. at 183
    (quoting Sierra 
    Club, 405 U.S. at 735
    ).
    Here, the Court concludes that the Tribe adequately pled these requisites for standing.
    Plaintiffs’ declarations discuss Tribe members’ past use of the areas affected by DAPL’s
    construction and operation, including those surrounding Lake Oahe, as well as the injuries they
    fear from the pipeline’s presence on such lands. See Decl. of Faith Spotted Eagle, ¶¶ 12, 19-23
    (stating that she has “performed ceremony and prayer at Lake Oahe and near the proposed
    Missouri River crossing site” and “[i]n doing so . . . used water” for “medicine and for spiritual
    purposes,” “gathered medicine very near the pipeline corridor at Lake Oahe,” and that DAPL
    will “result in . . . emotional, spiritual, psychological, and cultural damage” to the Yankton
    people via the potential destruction of such resources); Decl. of Kip Spotted Eagle, ¶¶ 10-13
    (stating that Tribal members “continue[] to hunt, gather and perform ceremony with water . . .
    including near the pipeline,” and that he has “been invited to hunt and fish in this area by
    members of the Standing Rock Sioux Tribe”); Decl. of Glenn Drapeau, ¶¶ 9-10 (stating that the
    Tribe, of which he is a member, “depend[s] on a number of plants that grow . . . near and within
    the pipeline corridor, including the Lake Oahe crossing area, for prayer, ceremony, and
    14
    medicine,” and that “[o]peration of the Pipeline will harm . . . [the Tribe’s] sacred water, sacred
    burial sites, and . . . way of life and spirituality”).
    Such averments of use of the areas affected by the pipeline and allegations of specific
    harms that may befall declarants and the Tribe from DAPL’s presence are sufficient for Plaintiffs
    to establish injury in this case. See Friends of the 
    Earth, 528 U.S. at 181
    ; W. Land Exch. Project
    v. U.S. Bureau of Land Mgmt., 
    315 F. Supp. 2d 1068
    , 1078–79 (D. Nev. 2004) (finding standing
    under NEPA when “colorable, if somewhat attenuated, geographical nexus between the areas
    visited by [Plaintiff] and BLM’s action”). Standing is thus no bar here.
    4.       NHPA Claims
    The Court last considers whether Plaintiffs’ NHPA claims should be dismissed as moot,
    in light of the fact that “construction is complete and oil is flowing.” Standing Rock IV, 
    2017 WL 4564714
    , at *11. The Tribe brings four claims for relief under the NHPA, alleging that: (1)
    “[i]n the development of the Corps Omaha EA[,] . . . [the] Corps violated the consultation
    requirement contained in the NHPA” and unlawfully found that no historical properties would be
    affected by its actions; (2) “[i]n issuing NWP 12, [the] Corps violated . . . the NHPA,” and its
    decision to approve NWP was thus “arbitrary, capricious, an abuse of discretion, and not in
    accordance with law”; (3) by “issu[ing] letters verifying more than 200 [pre-construction
    notifications] for [DAPL] located in North Dakota, South Dakota, Iowa, and Illinois without
    meaningfully consulting with the Tribe,” including “at least eleven of which are on the Tribe’s
    aboriginal title lands,” the Corps violated the NHPA; and (4) the Corps violated the Act by
    defining the area of potential effects “unlawfully narrowly” and thus failed to account for the fact
    that “[t]he clearing, grading, excavation, and construction that would occur along [DAPL’s]
    route would destroy . . . historic or culturally significant sites encountered.” Compl., ¶¶ 91-92,
    15
    103-104, 115-117, 122-129, 131-140. Defendants respond that all of these counts are now moot,
    as “the alleged injury complained of . . . has already occurred and cannot be redressed by a
    favorable judicial decision.” Corps Reply at 10.
    Article III of the U.S. Constitution limits federal courts to resolving actual cases or
    controversies and thus “prevents their passing on moot questions – ones where intervening
    events make it impossible to grant the prevailing party effective relief.” Burlington N. R.R. Co.
    v. Surface Transp. Bd., 
    75 F.3d 685
    , 688 (D.C. Cir. 1996) (citing Church of Scientology v.
    United States, 
    506 U.S. 9
    , 11 (1992)). Put otherwise, mootness is established when no
    opportunity remains for the court to provide “any meaningful relief to Plaintiffs’ alleged
    injuries.” Sierra Club v. U.S. Army Corps of Eng’rs, 
    803 F.3d 31
    , 44 (D.C. Cir. 2015)
    (quotation omitted).
    Here, Plaintiffs claim that the Corps violated the NHPA’s requirement that a “federal
    agency . . . consult with Indian tribes that attach cultural or religious significance to property
    affected by the agency’s undertakings.” Standing Rock III, 
    255 F. Supp. 3d
    at 155 (internal
    quotation marks and citation omitted). The Tribe alleged in its Complaint that, as a result of this
    inadequate consultation, DAPL’s ongoing construction would pose an impermissible risk to
    tribal sites. The question now is whether, in light of DAPL’s completion, there remains any
    means by which the Court can still grant Plaintiffs “meaningful relief.”
    The Court concludes that the answer is in the negative. The alleged “injuries” arising
    from Defendants’ NHPA violations are tethered to the timeline of DAPL’s construction and
    operation; in other words, tribal consultation and the granting of relevant federal permissions are
    actions that take place prior to the execution of a given project. See Standing Rock I, 205 F.
    Supp. 3d at 7 (NHPA “encompasses sites of cultural or religious significance to Indian tribes and
    16
    requires that federal agencies consult with tribes prior to issuing permits that might affect these
    historic resources”). Indeed, in its very first Opinion in this case, the Court found as much. A
    year and a half ago, addressing Standing Rock’s similar contention, this Court wrote that “[t]he
    risk that construction may damage or destroy cultural resources is now moot for the 48% of the
    pipeline that has already been completed.” 
    Id. at 35.
    It noted that “whatever harms may have
    occurred from DAPL construction, the Court’s intervention . . . can no longer avoid them”; as a
    result, for those sites at which construction was complete, the “die [was] cast.” 
    Id. This conclusion,
    moreover, reflected Standing Rock’s own understanding of the Act, as the Tribe
    explicitly acknowledged the potential for construction activities to moot its NHPA claims against
    Defendants. See ECF No. 24 (Standing Rock Reply) at 19-20, 23-24 (stating that “should DAPL
    be permitted to continue construction[,] . . . then the [] consultation process sought by the Tribe
    would be rendered moot” and noting that such consultation would “no longer be meaningful in
    those areas” in which “construction (including clearing and grading) has been completed”).
    The specter of mootness raised in Standing Rock’s earlier filings has now come to pass –
    construction is complete and oil is flowing through the pipeline. This advancement in DAPL’s
    development in turn dooms Yankton’s NHPA efforts. The Tribe’s first three claims mentioned
    above are explicitly premised on alleged violations of the consultation requirements under § 106
    of the Act. Now that construction of the pipeline has occurred, the Court agrees with Defendants
    (and the Standing Rock Sioux) that such consultation would no longer be “meaningful.”
    Similarly, the Court is unable to order effective relief with respect to Plaintiff’s final NHPA
    claim, which alleges that the Corps improperly defined the area of potential effects. This count
    relies on the Tribe’s assertion that “the clearing, grading, excavation, and construction that would
    occur along the duration of the [p]ipeline route would destroy any historic or culturally
    17
    significant sites encountered.” Compl., ¶ 139. These construction-related activities have now
    occurred, and, accordingly, the potential for the preservation of historic or cultural sites no
    longer exists. Cf. Sierra 
    Club, 803 F.3d at 43-44
    (stating that, in the NEPA context, “claims
    relating to the construction of [a] pipeline” may be moot and citing cases in which “the
    completion of the [challenged] project . . . eliminated the opportunity for any meaningful relief,”
    but finding that claims “addressing the environmental impacts resulting from the enhanced use
    of” the pipeline remained viable).
    Although the Tribe asserts in its Reply that meaningful relief remains available because
    the “risk of a spill through operation and maintenance of the Pipeline still . . . threatens the
    Tribe’s cultural and historic sites,” such an emphasis on ongoing harms is nowhere to be found
    in Plaintiffs’ Complaint, nor are such prospective injuries supported by the record. See Yankton
    Reply at 3, 30-31; Benavides v. Hous. Auth. of San Antonio, Tex., 
    238 F.3d 667
    , 670 (5th Cir.
    2001) (dismissing NHPA claims as moot when challenged project was partially constructed and
    “there [was] no evidence on the record that further agency review could possibly affect” the
    “substantially-completed” project). Instead, Plaintiffs’ NHPA claims and relevant declarations
    are predicated upon a concern with pre-construction consultation and assessments. See Yankton
    Reply at 29 (requesting relief under NHPA based on Defendants’ alleged errors in “identifying
    the area of potential effects too narrowly and violat[ing] duties to consult with the Tribe . . . [on]
    protection of historic and cultural locations”). The time for such conversations and evaluations
    has passed. The Court therefore concludes that there are no “live remedial implications” to
    Plaintiffs’ claims. See Sierra 
    Club, 803 F.3d at 43
    ; Finca Santa Elena, Inc. v. U.S. Army Corps
    of Engineers, 
    62 F. Supp. 3d 1
    , 5 (D.D.C. 2014) (discussing “long line of cases in the courts of
    appeal holding environmental challenges to completed construction projects to be moot”); Bayou
    18
    Liberty Ass'n, Inc. v. U.S. Army Corps of Eng’rs, 
    217 F.3d 393
    , 397–98 (5th Cir. 2000) (finding
    no ability to grant “meaningful relief” when challenged construction had “been substantially
    completed”).
    This conclusion is not altered, moreover, by the fact that the Tribe sought both injunctive
    and declaratory relief with respect to its NHPA claims. See Compl. at 32-33. Plaintiffs assert
    that the Court is still able to grant its requested declaratory remedies, and that their NHPA claims
    thus remain viable. See Yankton Reply at 31. Yet, as is evident from the discussion above, any
    declaration by the Court at this point in time – after construction is complete and the clearing,
    grading, and excavation have taken place – would be of no practical effect. To issue declaratory
    relief would be tantamount to issuing an advisory opinion, a result not within this Court’s power.
    See Weiss v. Sec'y of U.S. Dep't of Interior, 
    459 F. App'x 497
    , 500 (6th Cir. 2012) (dismissing
    NHPA claims as moot when “effects on the [site’s] historic character have already occurred,” as
    Court could not “give any meaningful relief and any declaratory judgment would be an advisory
    opinion”) (internal citation and quotation marks omitted); Bayou Liberty 
    Ass'n, 217 F.3d at 397
    –
    98 (finding request for declaratory judgment in NHPA suit after challenged construction had
    occurred “amounts to a request for an advisory opinion from this court”). Because it can provide
    no meaningful remedy to address Plaintiffs’ alleged injuries arising from their NHPA claims, the
    Court will dismiss the relevant counts of the Tribe’s Complaint as moot.
    B.      NEPA
    The Court at last turns to what remains of the Cross-Motions for Summary Judgment –
    i.e., Plaintiffs’ NEPA claims. The Tribe’s Motion focuses on Count VI of its Complaint, which
    alleges that federal Defendants “unlawfully piecemealed and segmented approval and analysis of
    the Pipeline utilizing three separate EAs and FONSIs.” Yankton Compl., ¶ 168. Specifically,
    19
    Plaintiffs allege that the Corps and FWS violated NEPA’s “anti-segmentation principle” by
    choosing to issue discrete EAs for the various components of the pipeline requiring federal
    permissions. 
    Id., ¶ 166.
    This principle seeks to prevent agencies from “avoid[ing] the NEPA
    requirement that an EIS be prepared for all major federal actions with significant environmental
    impacts by dividing an overall plan into component parts.” Taxpayers Watchdog, Inc. v.
    Stanley, 
    819 F.2d 294
    , 298 (D.C. Cir. 1987). The Tribe claims that here, such “segmentation of
    Federal approvals” violated NEPA’s implementing regulation, 40 C.F.R. § 1508.25, which
    addresses the environmental analysis of “connected, cumulative, or similar” actions. See
    Yankton MSJ at 9-14. Defendants respond that the decision to issue separate EAs and FONSIs
    was well within their discretion. See Corps Reply at 2. They assert that the three EAs at issue –
    the Omaha Corps District, St. Louis Corps District, and FWS assessments – were not
    “connected” or “similar” actions, and that § 1508.25 thus did not require any omnibus analysis of
    the various federal approvals.
    1.     Deference to Agencies
    In evaluating the parties’ Cross-Motions, the Court begins with the question of deference.
    According to federal Defendants, “[A]n agency’s scoping decision is entitled to deference,”
    including the Corps’ and FWS’s decision to “limit[] their review to areas within their
    jurisdiction.” Corps Opp. at 8. Plaintiffs counter, somewhat confusingly, that because federal
    Defendants “are part of the same entity – the United States – and the United States is required to
    conduct the NEPA analysis,” no deference is due to the agencies’ independent scoping
    determinations. See Yankton Reply at 13. This line of argument is unavailing, as the scoping
    process clearly falls under the authority of each agency charged with conducting a NEPA
    analysis. As the Supreme Court has held, “An agency enjoys broad discretion in determining
    20
    how best to handle related, yet discrete, issues in terms of procedures and priorities.” Mobil Oil
    Exploration & Producing Se. Inc. v. United Distribution Cos., 
    498 U.S. 211
    , 230 (1991)
    (citations omitted); see also Weiss v. Kempthorne, 
    580 F. Supp. 2d 184
    , 188 (D.D.C. 2008)
    (discussing deference given to agency decision in context of NEPA’s connected-actions
    regulation); Thomas v. Peterson, 
    753 F.2d 754
    , 758 (9th Cir. 1985) (noting that agencies are
    given “considerable discretion” in defining scope of an environmental analysis), abrogated on
    other grounds by Cottonwood Envtl. Law Ctr. v. US Forest Serv., 
    789 F.3d 1075
    , 1090 (9th Cir.
    2015). Plaintiffs’ suggestion that agency discretion is somehow subsumed by the ultimate
    oversight of the “United States” is simply untethered from any legal support. Similarly futile is
    the Tribe’s contention that because “[s]coping informs the rest of the analysis[,] . . . a defective
    scoping should not be entitled to deference.” Yankton Reply at 13-14. This statement puts the
    cart of conclusion before the horse of deference. In other words, the initial question is whether
    an agency’s scoping decision is due deference as a matter of law. If so, the Court then considers
    whether this presumption is rebutted by any arbitrary or capricious action during the
    decisionmaking process.
    Here, the Court agrees with Defendants that the Corps’ and FWS’s scoping
    determinations are entitled to deference under NEPA. As this Circuit has held, “[T]he line-
    drawing decisions necessitated” in agencies’ “treatment of [a] project’s relation to other
    government activities” are “vested in the agencies, not the courts.” Coal. on Sensible Transp.,
    Inc. v. Dole, 
    826 F.2d 60
    , 66 (D.C. Cir. 1987). The “latters’ role,” therefore, “is simply to ensure
    that” the agency’s scoping decision does not violate the law. 
    Id. (quotation omitted).
    Indeed,
    even when an environmental analysis “addresses one of a series of closely related proposals, the
    decision whether to prepare a programmatic impact statement is committed to the agency’s
    21
    discretion.” Grunewald v. Jarvis, 
    776 F.3d 893
    , 904-05 (D.C. Cir. 2015). The Court addressed
    this standard in Standing Rock I, when it held that the determination of “the scope of the effects”
    of federal permission related to DAPL fell “squarely within the expertise of the [agency]” and
    was “entitled to deference under the 
    APA.” 205 F. Supp. 3d at 31
    . In light of this deferential
    standard, it is up to Plaintiffs to show that the agencies acted “arbitrarily in refusing to prepare
    one comprehensive” evaluation or in “determin[ing] the region, if any, with respect to which a
    comprehensive statement is necessary.” Kleppe v. Sierra 
    Club, 427 U.S. at 412
    , 416; see
    
    Grunewald, 776 F.3d at 905
    (in determining whether comprehensive environmental analysis was
    “necessary,” court will overturn agency decision only if it “is arbitrary and capricious”); Earth
    Island Inst. v. Elliott, 
    2017 WL 5526572
    , at *13 (E.D. Cal. Nov. 17, 2017) (“A plaintiff must
    show that an agency’s decision not to prepare a single EIS was an arbitrary action.”).
    2.      Framework of Segmentation Analysis
    Deference thus established, the Court next discusses the general parameters of Plaintiffs’
    claim that the Corps and FWS impermissibly “segmented” their environmental analysis.
    Under NEPA, an agency acts unlawfully when it “divides connected, cumulative, or
    similar federal actions into separate projects and thereby fails to address the true scope and
    impact of the activities that should be under consideration.” Delaware Riverkeeper Network v.
    FERC, 
    753 F.3d 1304
    , 1314 (D.C. Cir. 2014); see PEACH v. U.S. Army Corps of Eng’rs, 
    87 F.3d 1242
    , 1247 (11th Cir. 1996) (stating that anti-segmentation rule ensures agencies “cannot
    evade [their] responsibilities under [NEPA] by artificially dividing a major federal action into
    smaller components, each without a significant impact”) (internal quotation marks and citation
    omitted).
    22
    The initial task in addressing a segmentation claim is identifying the “overall plan” or
    “major federal action” that has allegedly been sub-divided. See Save Barton Creek Ass'n v. Fed.
    Highway Admin., 
    950 F.2d 1129
    , 1139 (5th Cir. 1992) (noting that “[t]he case law which deals
    with . . . improper segmentation almost always involves a situation where a ‘major Federal
    action’ is found to exist and then the [issue] of segmentation is evaluated”). Here, both sides
    struggle somewhat with this definitional question.
    According to Defendants, the Tribe is identifying the federal action at issue as “the entire
    pipeline” project, see Corps Opp. at 9, which they contend is squarely precluded by the D.C.
    Circuit’s holding in Sierra 
    Club, 803 F.3d at 44
    . There, the court disagreed with the plaintiff’s
    position that the Corps had violated NEPA by failing to conduct a “review of the entire pipeline”
    at issue. 
    Id. at 44.
    It found instead that the “connected actions regulation . . . does not dictate
    that NEPA review encompass private activity outside the scope of the sum of the geographically
    limited federal actions.” 
    Id. at 49.
    The court thus rejected the plaintiff’s contention that the
    entire pipeline, the vast majority of which fell outside federal control, should have been
    addressed in a programmatic environmental analysis. 
    Id. at 50-51.
    The Tribe, Defendants assert, is making “functionally the same argument” here. See
    Corps Opp. at 9. If Plaintiffs were in fact asserting that NEPA required a DAPL-wide
    assessment, the Corps would be correct in deeming such a claim futile. The Tribe would,
    moreover, be precluded from making such an argument not only by the holding in Sierra Club,
    but also by one of the Court’s prior Opinions in this case. In Standing Rock I, it rebuffed
    Standing Rock’s argument that federal Defendants were required to engage in a whole-pipeline
    analysis. The Court denied the need for any such comprehensive evaluation, finding that “a
    federal agency with limited jurisdiction over specific activities related to a pipeline” is not
    23
    “required to consider all the effects of the entire 
    pipeline.” 205 F. Supp. 3d at 31
    ; see also Sierra
    Club, Inc. v. Bostick, 
    787 F.3d 1043
    , 1051-54 (10th Cir. 2015) (holding Corps was not required
    to prepare NEPA analysis of entire pipeline when verifying permits for 485-mile oil pipeline
    crossing over 2,000 waterways); Winnebago Tribe of Neb. v. Ray, 
    621 F.2d 269
    , 272-73 (8th
    Cir. 1980) (concluding same for electric utility line).
    Yet the Court believes that the Yankton Sioux’s segmentation claim is more nuanced
    than Defendants contend. Although the Tribe certainly confuses the matter somewhat by
    referring repeatedly to the “entire pipeline project” and the “impacts of the [p]ipeline,” it also
    raises the narrower argument that NEPA required a “comprehensive agency action review of the
    connected and similar federal actions” related to DAPL. See Yankton Reply at 1, 8, 10; Yankton
    MSJ at 6 (emphasis added). Plaintiffs contrast this claim with “whole pipeline review,”
    explaining that they are limiting their challenge to the series of actions within federal permitting
    authority. See Yankton Reply at 9-10.
    This narrower claim, contrary to Defendants’ assertions, is not precluded by Sierra Club.
    Rather, it fits within a line of argument explicitly left open by that opinion. As the court there
    noted, plaintiff had, at oral argument, advanced the claim that “the connected action regulation
    require[s] that the federal actions in this case – the easements, the other areas within federal
    jurisdiction” – should have been considered connected and “analyzed together” under NEPA.
    
    See 803 F.3d at 51
    . The court stated that such a claim “for NEPA analysis limited to the
    [federal] verification and easement areas” was “an accurate statement of the connected actions
    doctrine.” 
    Id. at 44,
    51. Because plaintiffs had forfeited such an argument below, however, the
    Circuit “had no occasion to consider it.” 
    Id. at 51,
    44.
    24
    For this Court, then, the decision in Sierra Club serves only to identify a lacuna in the
    binding precedent – how to apply the anti-segmentation rule to federal actions encompassed
    within a larger, private project. Here, Plaintiffs are challenging federal Defendants’ decision to
    issue “three separate and distinct EAs, three separate and distinct FONSIs, and one categorical
    exclusion classification for their own respective actions related to the Pipeline project,” in lieu of
    a consolidated analysis of all such federal permissions related to DAPL. See Yankton MSJ at 11.
    This limited anti-segmentation claim appears to fit within the narrow opening left ajar by the
    holdings of Sierra Club and this Court’s prior Opinion. See Sierra 
    Club, 803 F.3d at 49
    (recognizing potentially viable claim that an agency “unlawfully failed to perform NEPA
    analysis on sections . . . short of the entire length of the pipeline” that fell under federal control).
    The Court treats in turn the Tribe’s arguments on “connected actions” and “similar actions.”
    3.      Connected Actions
    Having established the framework of the anti-segmentation rule and the parameters of
    Plaintiffs’ NEPA claims, the Court begins with the Tribe’s allegation that Defendants violated
    the Act’s implementing regulation, 40 C.F.R. § 1508.25, by not treating the DAPL-related
    permissions as “connected” actions requiring a programmatic environmental analysis.
    Under § 1508.25(a)(1), connected actions are those that “(i) automatically trigger other
    actions which may require [an EIS]; (ii) cannot or will not proceed unless other actions are taken
    previously or simultaneously; or (iii) are interdependent parts of a larger action and depend on
    the larger action for their justification.” Although Defendants argue that this regulation applies
    only to EIS analyses, and not EAs (as were issued in this case), this contention conflicts with
    Circuit precedent stating that “when determining the contents of an EA or an EIS, an agency
    must consider all connected actions.” Delaware 
    Riverkeeper, 753 F.3d at 1314
    (emphasis
    25
    added). The Court will therefore proceed with the assumption that, if the various DAPL
    permissions are in fact “connected actions” under NEPA, Defendants were required to include
    them within the scope of a consolidated environmental review – whether it took the form of an
    EIS or an EA.
    So, are the discrete federal permissions here in fact “connected”? Plaintiffs offer four
    major arguments in favor of finding such a relationship: (1) the federal projects do not have
    “substantial independent utility”; (2) the approval of each federal permit constrained the
    consideration of alternatives for other portions of the pipeline; (3) the permits and permissions
    were “justified by” a larger federal action; and (4) the federal projects are “interdependent” and
    have a “synergistic” environmental effect. The Court addresses each separately.
    a. Substantial Independent Utility
    Under this Circuit’s decision in Taxpayers, federal projects can only be analyzed
    separately if each project has, inter alia, “substantial independent 
    utility.” 819 F.2d at 298
    . In
    other words, this test asks “whether one project will serve a significant purpose even if a second
    related project is not built.” Hammond v. Norton, 
    370 F. Supp. 2d 226
    , 247 (D.D.C. 2005)
    (quoting Coal. on Sensible 
    Transp., 826 F.2d at 69
    ). On this issue, Plaintiffs argue that “no
    separate component of the Pipeline considered by Federal Defendants and analyzed in three
    separate EAs can possibly have independent utility” because “[i]f one federal approval for the
    Pipeline had been denied, Pipeline construction could not have been completed and the whole
    project would have been rendered utterly useless.” Yankton MSJ at 13.
    This line of argument, as Defendants accurately note, ignores the facts on the ground.
    Most significantly, 97% of DAPL runs through private land. This means that vast swaths of the
    pipeline could be constructed without any federal permissions or permits whatsoever, and that, if
    26
    a given federal authorization was denied for a portion of the remaining 3%, the project could be
    re-routed to avoid the contentious crossing or easement. See Standing Rock 
    I, 205 F. Supp. 3d at 32
    (noting that “the route taken by the pipeline through private lands . . . is driven by factors that
    have little to do with the discrete activities that the Corps needs to permit”). Indeed, such re-
    routing occurred throughout the lifespan of the pipeline project, including in response to the
    findings of the FWS EA. See FWS EA at 7, 13-16 (discussing route modifications and
    alternatives); Standing Rock 
    I, 205 F. Supp. 3d at 14
    (noting that pipeline route was “modified
    140 times in North Dakota alone to avoid potential cultural resources”); Exh. Y (Letter from
    Jackie Rodgers of Osage Nation confirming DAPL reroute at Mississippi River crossing); Corps
    Opp. at 14 n.7 (noting prior re-routing). Far from rendering the “whole project . . . entirely
    useless,” the denial of one federal approval could simply result in a shift in the pipeline’s course.
    It follows, therefore, that each discrete federal permission had “substantial independent
    utility,” as each would allow that portion of the pipeline to proceed as planned, while any denial
    would result in re-routing – with no apparent impact on the other federally regulated components
    of the project. Cf. City of Williams v. Dombeck, 
    151 F. Supp. 2d 9
    , 19–20 (D.D.C. 2001)
    (finding water-transportation system connected to larger federal action because construction of
    water pipeline “[would] not proceed unless [the other action] proceeds previously or
    simultaneously”) (internal quotation marks omitted).
    The limited federal involvement with DAPL and the potential for re-routing additionally
    distinguishes this case from Delaware Riverkeeper, upon which Plaintiffs rely. In that case, the
    projects at issue addressed upgrades to a natural-gas pipeline, meaning that a federal agency –
    FERC – had jurisdiction over projects along its entire length. 
    See 753 F.3d at 1307-08
    . Because
    FERC was tasked with analyzing the environmental impacts of construction and operation for
    27
    the whole pipeline, there was simply no way for it to be re-routed so as to not require agency
    approval. 
    Id. at 1308
    (noting that the approvals were “physically, functionally, and financially
    connected and interdependent”). If FERC had approved certain segments and denied others, the
    project could not proceed. As the court in Delaware Riverkeeper found, each phase of the
    pipeline’s approval and permitting process “fit with the others like puzzle pieces,” and thus the
    “agency was obliged to assess the entire pipeline for environment[al] effects.” 
    Id. at 1319.
    DAPL, by contrast, is not so beholden to overall federal approval; as this Court noted in
    Standing Rock I, “[N]o permitting” does not mean “no 
    pipeline.” 205 F. Supp. 3d at 31
    . The
    project’s construction and routing could instead be tailored or modified to avoid problematic
    federal lands or water. 
    Id. This conclusion
    remains as true today as when the Court issued its
    first Opinion in this case. It follows, therefore, that the Corps’ and FWS’s actions related to the
    pipeline have “substantial independent utility.” The denial of one federal approval for this
    pipeline does not preclude, or even necessarily affect, the remaining federal actions.
    b. Consideration of Alternatives
    The Tribe next posits that “each approval issued [by the Corps and FWS] sufficiently
    constrained the consideration of alternatives for other portions of the pipeline to mandate
    consideration of all approvals in a single NEPA document.” Yankton MSJ at 13. According to
    Plaintiffs, the “approval of one segment clearly foreclosed the opportunity to consider other
    reasonable alternatives, as the approval of one segment at a specific location decreased route
    options for other segments of the pipeline.” 
    Id. Defendants counter
    that their consideration of
    alternatives to each permit and permission was not so constrained, pointing to the fact that the
    EAs each “contains a section devoted to alternatives to the federal action.” DA Opp. at 19
    28
    Defendants have the better of this argument. Indeed, a review of the three EAs at issue
    demonstrates that the two Corps districts and FWS clearly considered a full panoply of
    alternatives – including, in each case, a “no-action” alternative that consisted of a scenario in
    which the pipeline was not constructed. See Omaha Dist. EA at 12-13; St. Louis Dist. EA at 12-
    15; FWS EA at 15. As made evident by the agencies’ analyses, the approval for any one
    crossing or permission did not restrict the consideration of different route options or alternatives
    for the other proposed actions. See also Coal. on Sensible 
    Transp., 826 F.2d at 69
    (rejecting
    claim that project approval would “restrict consideration of alternatives for related projects”
    because no indication that each permission would “effectively commit [federal] decisionmakers
    to a future course of action”).
    c. Larger Federal Action
    Plaintiffs next assert that the various federal permits and permissions are “connected”
    because they “are justified by a larger federal action” – that is, but for an overarching federal
    project, the discrete approvals would not have been required. They contend that the actions of
    the Corps and FWS were “clearly parts of a larger action,” stating that “the permits and
    permissions issued by Federal Defendants were part of, and justified by, the . . . greater
    implementation of the Pipeline.” Yankton Reply at 10-11. Yet, as discussed above, any
    suggestion that DAPL as a whole constitutes a “federal action” is unavailing in light of Sierra
    Club and Standing Rock II. The narrower question, therefore, is whether the federal permits and
    permissions were justified by any larger federal action and thus required a consolidated NEPA
    analysis. See Yankton Reply at 12 (acknowledging that Tribe “do[es] not argue that the entire
    pipeline should have been analyzed, but rather, that the permits and permissions . . . should have
    been analyzed together in a single NEPA process”); see also Sierra Club v. U.S. Army Corps, 64
    
    29 F. Supp. 3d 128
    , 154 (D.D.C. 2014), aff’d, 
    803 F.3d 31
    (stating that “connected actions
    regulation requires that the impact on the environment of all aspects of a particular major federal
    action be evaluated together”) (emphasis added).
    Here, Plaintiffs can identify no such overarching federal project upon which the various
    permissions rely. Instead, the record is clear that federal permission was needed for only limited,
    discrete components of DAPL’s construction. See Corps Opp. at 10 (noting that “there was no
    single proposal for the pipeline submitted to Corps and FWS”). Although all of the federal
    authorizations were part of the pipeline project, the project was not itself a federal undertaking.
    See Sierra 
    Club, 803 F.3d at 49
    (noting that while oil pipeline at issue was “undoubtedly a single
    physically, functionally, and financially connected project,” “less than five percent [was] subject
    to federal review,” and thus agency was not required to evaluate impact of entire pipeline)
    (internal quotation marks omitted). This again distinguishes the facts of this case from those of
    Delaware Riverkeeper, in which FERC had jurisdiction over the entire pipeline, and each related
    permission was thus contingent upon the agency’s approval of the pipeline’s overall certification.
    The agency actions at issue here, by contrast, are not “justified by” or reliant upon any broader
    federal permission. See Sierra Club v. US Army Corps of Eng’rs, 
    990 F. Supp. 2d 9
    , 37 (D.D.C.
    2013) (noting “general reluctance to conclude that federal action with respect to a small portion
    of a pipeline” is sufficient to “federalize the entire project”).
    d. Synergistic Effect
    Last, the Tribe is unable to demonstrate that the discrete federal permissions were
    “interdependent” or that they had any “synergistic effect.” Plaintiffs cite to Kleppe v. Sierra
    Club, 
    427 U.S. 390
    (1976), which held that proposals that have a “synergistic environmental
    impact upon a region . . . must be considered together.” 
    Id. at 410.
    Here, however, the Tribe is
    30
    unable to identify any such synergy connecting the discrete DAPL permissions. Each of the EAs
    and FONSIs addresses geographically isolated crossings or easements, and there is no suggestion
    in the record that environmental impacts in one location would have repercussions for another.
    Indeed, it is difficult to imagine how the construction of a river crossing in Illinois could possibly
    affect the environment at Lake Oahe, which is located hundreds miles away and separated by the
    states of Iowa and South Dakota. See DA Opp. at 1 (Map 1). This, therefore, is not a case in
    which the environmental impacts or harms arising from a set of discrete federal permissions
    would, if combined, be greater than the sum of the parts.
    This lack of interaction between the sites addressed in each EA distinguishes this case
    from NRDC v. Hodel, 
    865 F.2d 288
    (D.C. Cir. 1988). Hodel involved the federal review of
    permissions for a series of offshore drilling leases in two ecologically sensitive locations. 
    Id. at 297.
    The Secretary of the Interior had determined that each lease would not have a significant
    environmental effect, a conclusion plaintiff challenged under § 1508.25. 
    Id. at 298.
    The court in
    Hodel agreed. It held that the Secretary had erred by separately evaluating the lease permissions
    because, acting together, the discrete drilling locations would affect marine mammals and
    migratory species. 
    Id. at 299-300.
    While a single drilling lease may not have had such effect,
    the court found that the actions were connected by their interdependent and synergistic impacts.
    By failing to consider the cumulative effects of all the leases, the Secretary impermissibly
    ignored the actual environmental repercussions of granting the multiple permissions.
    Here, by contrast, the permissions at issue are for ecologically distinct waters and lands.
    Counter to Plaintiffs’ assertion that the sites are “interdependent,” Yankton MSJ at 14, there is
    no indication that DAPL’s passage through one crossing or easement would have spillover
    environmental effects at another. The Court, consequently, finds no basis upon which to deem
    31
    the federal approvals “interdependent” or as having any synergistic environmental impact. See
    Earth Island Inst., 
    2017 WL 5526572
    , at *14 (separate NEPA review appropriate where actions
    in question were located in different watersheds on opposite sides of Greenhorn Mountains).
    4.      Similar Actions
    In addition to maintaining that the approvals were “connected actions,” Plaintiffs assert
    that the Corps’ and FWS’s assessments were “similar actions” under § 1504.25. The Court
    begins with the threshold issue of whether the Tribe has in fact forfeited this claim. According to
    Defendants, the “similar actions” contention is unavailable, as “neither Plaintiffs nor any other
    commenter raised the argument that FWS and the Corps’ actions should be considered together
    as ‘similar actions,’” Corps Opp. at 13 n.5, and “[i]t is well-established that issues not raised in
    comments before the agency are waived.” DA Opp. at 24 (quoting Nat’l Wildlife Fed’n v. EPA,
    
    286 F.3d 554
    , 562 (D.C. Cir. 2002)). In response, the Tribe asserts that it need not have
    identified the similar-actions claim during the comment period “because a different entity . . .
    had explicitly raised the issue.” Yankton Reply at 25. Plaintiffs then refer to a lone comment on
    the proposed St. Louis District EA that quoted the text of § 1508.25, including the “connected,
    cumulative, or similar actions” language. 
    Id. at 27
    (citing St. Louis EA, Comment 2-2).
    Plaintiffs also argue that, regardless of whether the similar-actions argument was raised in
    comments, the Court should not consider it forfeited because it falls within the realm of those “so
    obvious that there is no need for a commentator to point [it] out specifically in order to preserve
    its ability to challenge a proposed action.” 
    Id. at 28
    (quoting Dep’t of Transp. v. Pub. Citizen,
    
    541 U.S. 752
    , 765 (2004)).
    After examining the underlying record, the Court agrees with Defendants that the
    “similar actions” issue was not raised “with sufficient specificity reasonably to alert the agency”
    32
    during the comment period. See Tex Tin Corp. v. EPA, 
    935 F.2d 1321
    , 1323 (D.C. Cir. 1991).
    The single mention of the word “similar” in the comments appears to be the one Plaintiffs cite
    from the St. Louis EA, which arises in the context of reciting verbatim the full language of §
    1504.25. Neither that comment, nor any other, makes any attempt to apply that “similar actions”
    text to the DAPL decisionmaking process or argues that federal Defendants erred in failing to
    consider their respective permissions and permits under that prong of the regulation. As
    Defendants acknowledge, this is in contrast to the “connected actions” issue, which was
    explicitly raised and addressed in depth by a number of commenters. See, e.g., Exh. 14 (Sierra
    Club Comment) (discussing § 1504.25, but addressing only “connected actions” prong of
    regulation). While the Tribe is correct that it may rely on the comments of other entities in
    arguing against waiver, see Nat. Res. Def. Council v. EPA, 
    824 F.2d 1146
    , 1151 (D.C. Cir.
    1987), here it cannot show that any entity sufficiently raised the “similar actions” claim before
    the agencies so as to give them notice of the issue. See Northside Sanitary Landfill, Inc. v.
    Thomas, 
    849 F.2d 1516
    , 1519 (D.C. Cir. 1988) (holding that “by neglecting timely to put the
    [agency] on proper notice of its objections, [Plaintiff] has forfeited its right to have this court
    examine those objections on the merits”).
    Similarly, Plaintiffs cannot demonstrate that the issue is “so obvious” that it need not
    have been pointed out in order to be preserved as a basis for a later legal challenge. See Dep't of
    
    Transp., 541 U.S. at 765
    . Indeed, it stands to reason that if the “similar actions” argument was so
    self-evident, the multiple commenters who addressed the issue of segmentation would have at
    least referred to such an allegedly straightforward claim. The fact that the comments instead
    discussed only the “connected actions” prong of § 1508.25 speaks to the relative obscurity of the
    “similar actions” issue. Because no commenter made any substantive contention that the
    33
    agencies’ actions were similar, and because such an argument was not “obvious,” the Court will
    deem this issue forfeited.
    Out of an abundance of caution, however, the Court also notes that even if this claim
    were preserved, the Tribe would still not prevail. Under § 1508.25, similar actions are those that,
    “when viewed with other reasonably foreseeable or proposed agency actions, have similarities
    that provide a basis for evaluating their environmental consequences together, such as common
    timing or geography.” Plaintiffs contend that the federal permissions at issue in this case share
    such a resemblance. In particular, the Tribe focuses on the “common timing” of the Corps’ and
    FWS’s actions, noting that the agencies’ decisionmaking processes “took place at roughly the
    same time,” with the relevant federal permits and permissions issued within a span of ten
    months. See Yankton MSJ at 15; Reply at 19.
    Simultaneity of agency actions is not, however, dispositive of their similarity. Instead, §
    1508.25 clearly states that the ultimate question is whether a set of actions “ha[s] similarities that
    provide a basis for evaluating their environmental consequences” in a single assessment. As this
    Circuit has put it, a comprehensive analysis is appropriate under § 1508.25 when the
    “sufficiently similar character of actions is such that [a programmatic analysis] is the ‘best way’
    to assess their combined impacts.” Coal. on Sensible 
    Transp., 826 F.2d at 70
    n.8 (citation
    omitted). Such a standard does not, contrary to the Tribe’s suggestion, mandate that all actions
    with temporal proximity are “best” assessed in a single EIS or EA.
    The implementing regulation, moreover, also lists common geography as another
    potential indicator of similarity – a factor that, in this case, cuts against finding such
    commonality between the DAPL-related permissions. As discussed above, the three EAs and
    FONSIs were for geographically and ecologically distinct areas of federal control. As
    34
    Defendants note, the assessments addressed actions that were “not physically connected” and
    instead were “spread over hundreds of miles across multiple states.” Corps Opp. at 16. The
    permissions and permits, moreover, were for different environmental resources: the Omaha
    District EA addressed the crossing of Lakes Oahe and Sakakawea; the St. Louis EA looked at a
    series of lake, creek, and channel crossings and drainage districts in Illinois; and the FWS EA
    was concerned with the agency’s jurisdiction over wetland and grassland easements.
    Such geographic isolation and ecological diversity, the Corps contends, defeat any
    suggestions of similarity between the federal actions. Plaintiffs counter that “[w]hile the
    geographic locations for the various agency actions are not the same, they all occurred along the
    same linear pipeline route,” and thus “[t]here can be no doubt that Federal Defendants’ actions
    were ‘similar.’” Yankton MSJ at 16 (emphasis omitted). The Court does not share the Tribe’s
    certainty on this issue. Instead, it finds that the geographic and substantive differences among
    the three actions demonstrate that they are not “similar” within the meaning of § 1508.25.
    Plaintiffs also vaguely allude to other alleged similarities among the DAPL-related
    actions. Although it focuses largely on the temporal overlap between the various federal
    permissions, the Tribe asserts that “Defendants’ actions involved the same singular pipeline
    which would transport the same crude oil, rendering the actions’ potential impacts similar if not
    identical.” Yankton MSJ at 15. Again, this argument does not reflect the reality of the pipeline
    – a project that spans four states over its 1,200-mile route. The discrete parcels of federal lands
    and easements the pipeline encounters along this corridor are not, simply by virtue of being in
    DAPL’s path, “similar.” Indeed, one need only reference the EAs at issue in this case to
    understand that, far from presenting “identical” environmental considerations, each federal
    permission reflects site-specific and distinct ecological concerns. Although the pipeline may be
    35
    a “singular” private undertaking, its environmental impacts and the related federal assessments
    are far more diverse.
    ***
    In sum, the Court concludes that Defendants’ environmental assessments are not
    “connected” or “similar” federal actions. Instead, they are discrete analyses that address
    ecologically and geographically disparate areas of federal jurisdiction. The Corps and FWS,
    accordingly, were under no obligation to consider these authorizations together. The Court
    observes, moreover, that a major rationale for the anti-segmentation rule is especially
    inapplicable in this case. Enforcement of the principle seeks, in large part, to prevent agencies
    from disguising the actual environmental impacts of a given governmental project by dividing
    the action into artificially created components. See Macht v. Skinner, 
    715 F. Supp. 1131
    , 1135
    (D.D.C. 1989), aff'd, 
    889 F.2d 291
    (D.C. Cir. 1989) (anti-segmentation principle serves to “weed
    out projects which are pretextually segmented, and for which there is no independent reason to
    exist”). Yet this is not a case in which a broader agency action was fragmented into arbitrary
    parts in order to hide its total environmental effect. DAPL is a largely private project, and
    Defendants’ decision to treat the limited federal involvement with the pipeline as discrete agency
    actions evinces no bad faith or attempt to circumvent NEPA’s environmental protections. Such a
    determination was instead a reasonable exercise of the agencies’ discretion, and the Court will
    therefore defer to Defendants’ decision to conduct three separate EAs and FONSIs in this case.
    C.      Harmless Error
    Finally, even if Defendants’ actions did violate NEPA, the Court concludes that such
    violations did not prejudice Plaintiffs, as there is no indication that the agencies would have
    reached a different outcome if they had in fact considered the DAPL-related actions in toto.
    36
    The Tribe argues that the Court should not apply harmless-error doctrine in this context,
    noting that certain cases finding improper segmentation of NEPA analyses have not explicitly
    addressed the question of prejudice. See Yankton Reply at 21. Yet just because other courts
    have not applied harmless error does not prevent this Court from doing so. Rather, the inquiry
    into whether a NEPA plaintiff suffered prejudice is well established in the relevant precedent.
    See, e.g., Pub. Employees for Envtl. Responsibility v. Hopper, 
    827 F.3d 1077
    , 1087–88 (D.C.
    Cir. 2016) (applying harmless-error analysis in NEPA context); Save Our Heritage, Inc. v. FAA,
    
    269 F.3d 49
    , 59–62 (1st Cir. 2001) (same); Laguna Greenbelt, Inc. v. U.S. Dep't of Transp., 
    42 F.3d 517
    , 527 (9th Cir. 1994) (same).
    Defendants assert that the Tribe has identified “no concrete environmental impact that
    was missed by the alleged segmenting of the discrete permissions” by the Corps and FWS. See
    Corps Opp. at 17-18. The Court agrees. The Tribe describes the actual impact of Defendants’
    allegedly improper segmentation in only the vaguest of terms, stating that the use of separate
    analyses left the Tribe “with no means to truly understand or weigh in on the vast cumulative
    impacts this project can and will have on the human environment” and generally alleging that by
    using three separate EAs, Defendants “concealed the cumulative environmental impacts of the
    project.” Yankton MSJ at 2.
    Yet there is no indication in the record that Defendants “concealed” any cumulative
    environmental impacts or that they “faile[ed] to do the analysis . . . to determine the cumulative
    impacts” of all of the federal actions. See Yankton Reply at 5-6. On the contrary, each of the
    three EAs contains a section explicitly titled “cumulative impacts,” discussing the potential
    cumulative effects of each permission and addressing the potential for the relevant permit to
    interact with other federal actions – including those related to the pipeline. See Omaha EA at 98-
    37
    107; FWS EA at 33-35; St. Louis EA and FONSI at 83-94. If the agencies were attempting to
    “hid[e] the ball” as to DAPL’s cumulative impacts, see Yankton MSJ at 19, they did a poor job
    indeed.
    Beyond providing no evidence of Defendants’ alleged “concealment,” Plaintiffs have not
    identified any actual harms that arose from the division of the agencies’ analysis. The goal of
    NEPA is to ensure that the public is provided with relevant information and the opportunity to
    participate in agency decisionmaking. See Robertson v. Methow Valley Citizens Council, 
    490 U.S. 332
    , 349 (1989) (NEPA “guarantees that the relevant information will be made available to
    the larger audience that may also play a role in both the decision-making process and the
    implementation of that decision”). In this case, Plaintiffs provide no explanation as to how
    Defendants’ alleged segmentation of the DAPL-related permissions frustrated such ends.
    In fact, the high volume of comments and active public dialogue throughout the
    permitting process undermine any conclusion that NEPA’s participatory goals were somehow
    stymied by the use of three separate EAs. See Yankton MSJ at 5 (acknowledging “multitude of
    comments” regarding Defendants’ actions). Although the Tribe may have preferred that the
    assessments be combined into a single document, there is no indication in the record that such
    consolidation would have had any meaningful effect. Plaintiffs, like the rest of the public, seem
    to have had no difficulty reviewing the three discrete documents – or voicing their concerns
    regarding the agencies’ conclusions. See Nevada v. Dep't of Energy, 
    457 F.3d 78
    , 90–91 (D.C.
    Cir. 2006) (finding lack of prejudice from alleged NEPA violation when “[t]he many comments
    submitted in response to the []EIS manifest that the public had sufficient information to
    comment”).
    38
    Contrary to the Tribe’s assertion that “had [Defendants] not broken the analysis into three
    pieces, it would seem a foregone conclusion that the cumulative impact would have easily
    crossed the threshold for requiring an EIS” rather than an EA, see Yankton Reply at 5, the record
    in this case does not support such an assumption. Because the Tribe is unable to specifically
    explicate, much less demonstrate, how Defendants’ discrete analyses “inherently lowered the
    level of environmental review that they conducted,” 
    id. at 22,
    the Court is unconvinced that any
    omnibus assessment would have altered the agencies’ analysis. As Plaintiffs can demonstrate no
    actual harm arising from the use of the three EAs, the Court concludes that any improper
    segmentation in this case constitutes harmless error.
    ***
    As a final note, the Court observes that its conclusions today are not necessarily the end
    of the road for the Yankton Sioux’s involvement with DAPL. As of October 20, 2017, the Tribe
    has been contacted by Defendants and asked to provide input during the ongoing remand
    analysis. See ECF No. 306, Exh. 1 (Letter from Corps requesting information from Yankton to
    assist in remand). Plaintiffs will therefore have the opportunity to voice their remaining
    concerns regarding the Corps’ environmental assessments and, if they choose, to engage in an
    active dialogue with Defendants as this case continues to move forward.
    IV.    Conclusion
    For the foregoing reasons, the Court will deny Plaintiffs’ Motion for Summary Judgment,
    grant Defendants’ Cross-Motion for Summary Judgment, and dismiss Plaintiffs’ Count I as
    moot. A contemporaneous Order so stating will issue this day.
    .
    39
    /s/ James E. Boasberg
    JAMES E. BOASBERG
    United States District Judge
    Date: March 19, 2018
    40
    

Document Info

Docket Number: Civil Action No. 2016-1534

Judges: Judge James E. Boasberg

Filed Date: 3/19/2018

Precedential Status: Precedential

Modified Date: 3/19/2018

Authorities (36)

Save Our Heritage, Inc. v. Federal Aviation Administration , 269 F.3d 49 ( 2001 )

Preserve Endangered Areas of Cobb's History, Inc. v. United ... , 87 F.3d 1242 ( 1996 )

Benavides v. Housing Authority of San Antonio , 238 F.3d 667 ( 2001 )

winnebago-tribe-of-nebraska-v-col-james-w-ray-district-engineer-omaha , 621 F.2d 269 ( 1980 )

Bayou Liberty Ass'n v. United States Army Corps of Engineers , 217 F.3d 393 ( 2000 )

save-barton-creek-association-we-care-austin-and-austin-crossroads , 950 F.2d 1129 ( 1992 )

Burlington Northern Railroad Company v. Surface ... , 75 F.3d 685 ( 1996 )

Taxpayers Watchdog, Inc. v. Ralph L. Stanley, Administrator,... , 819 F.2d 294 ( 1987 )

Bloch, Felix S. v. Powell, Colin L. , 348 F.3d 1060 ( 2003 )

Natural Resources Defense Council, Inc. v. Donald P. Hodel, ... , 865 F.2d 288 ( 1988 )

harold-thomas-dba-allison-ranch-and-cook-ranch-v-r-max-peterson-in-his , 753 F.2d 754 ( 1985 )

Northside Sanitary Landfill, Inc. v. Lee M. Thomas, ... , 849 F.2d 1516 ( 1988 )

Coalition on Sensible Transportation, Inc. v. Elizabeth Dole , 826 F.2d 60 ( 1987 )

the-laguna-greenbelt-inc-a-california-non-profit-corporation-the-laguna , 42 F.3d 517 ( 1994 )

C & W Fish Company, Inc. v. William W. Fox, Jr., Assistant ... , 931 F.2d 1556 ( 1991 )

Tex Tin Corporation v. U.S. Environmental Protection Agency , 935 F.2d 1321 ( 1991 )

natural-resources-defense-council-inc-v-us-environmental-protection , 824 F.2d 1146 ( 1987 )

Natl Wldlf Fed v. EPA , 286 F.3d 554 ( 2002 )

MacHt v. Skinner , 715 F. Supp. 1131 ( 1989 )

Loma Linda University Medical Center v. Sebelius , 684 F. Supp. 2d 42 ( 2010 )

View All Authorities »