Cb&i Areva Mox Services, LLC v. United States ( 2018 )


Menu:
  •       In the United States Court of Federal Claims
    No. 16-950C, 17-2017C, 18-80C, 18-522C, 18-677C, 18-691C, 18-710C
    (consolidated)
    (Filed: June 11, 2018)
    *************************************
    *
    CB&I AREVA MOX SERVICES, LLC,       *
    *         US/Russia Plutonium Management and
    Plaintiff,      *         Disposition Agreement; National Nuclear
    *         Security Administration; Cost-Plus-Fee
    v.                                  *         Construction Contract; Rules 12 and 56
    *         Cross-Motions; Availability of Declaratory
    THE UNITED STATES,                  *         Relief; Government Claim Under Contract
    *         Disputes Act; Statute of Limitations.
    Defendant.      *
    *
    *************************************
    Mark J. Linderman, with whom were Dennis J. Callahan and Stephen L. Bacon, Rogers
    Joseph O’Donnell, PC, San Francisco, California for Plaintiff.
    Joseph E. Ashman, Senior Trial Counsel, with whom were P. Davis Oliver and Anthony
    Schiavetti, Trial Attorneys, and Chad A. Readler, Acting Assistant Attorney General,
    Robert E. Kirschman, Jr., Director, and Allison Kidd-Miller, Assistant Director,
    Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington,
    D.C. for Defendant.
    OPINION AND ORDER
    WHEELER, Judge.
    Plaintiff CB&I AREVA MOX Services, LLC (“MOX Services”) commenced this
    action on August 5, 2016. The action arises from MOX Services’ cost reimbursement
    contract with the Department of Energy, National Nuclear Security Administration
    (“NNSA”) to construct a Mixed Oxide Fuel Fabrication Facility at the Department of
    Energy’s Savannah River Site, near Aiken, South Carolina. On November 3, 2017, with
    the Court’s approval, MOX Services filed a Supplemental Complaint for Damages and
    Declaratory Relief consisting of five counts: (1) Breach of Contract (Incentive Fee); (2)
    Declaratory Relief (Premature Claw Back of Provisional Incentive Fee); (3) Breach of
    Contract (Fixed Fee On Out-of-Scope Work and for the Realization of Risks NNSA
    Assumed); (4) Breach of Contract (Request for Equitable Adjustment Preparation Costs);
    and (5) Declaratory Relief (Request for Equitable Adjustment Preparation Costs).
    This case, docket no. 16-950C, was the first in a series of actions that MOX Services
    filed under the same contract. The cases were filed separately in this Court because of
    individual claims that MOX Services had submitted to the contracting officer, and because
    of the NNSA’s issuance of individual contracting officer final decisions. On May 15, 2018,
    the Court ordered the consolidation of these cases for further proceedings and trial.
    The present controversy concerns cross-motions that the parties filed under Rules
    12 and 56 of the Court. On December 27, 2017, MOX Services filed a motion for partial
    summary judgment regarding Counts II and V (the declaratory relief counts) of the
    Supplemental Complaint. MOX Services contends that Count II presents a pure question
    of contract interpretation on whether the NNSA prematurely clawed back $21.6 million of
    cost/schedule incentive fee payments it had made to MOX Services. Similarly, MOX
    Services contends that Count V presents a question of regulatory interpretation on whether
    the attorneys’ fees and other professional consultant costs claimed by MOX Services for
    reimbursement as contract administration costs in investigating and preparing a Request
    for Equitable Adjustment (“REA”) constitute “legal costs” that must comply with the
    requirements of 10 C.F.R. Part 719 (2013).1
    On February 1, 2018, Defendant filed a motion for partial dismissal regarding
    Counts II, III, and V of the Supplemental Complaint. Defendant argues that Counts II and
    V should be dismissed for lack of jurisdiction because they were not presented to the
    contracting officer, they do not present a case or controversy and are not ripe, and because
    declaratory relief may not be granted when money damages are adequate. Defendant also
    moved for partial dismissal of Count III because MOX Services failed to provide required
    contractual notice of the claim, and because the claim allegedly is time barred by the
    Contract Disputes Act’s six-year statute of limitations, 
    41 U.S.C. § 7103
    (a)(4) (2011).
    On March 28, 2018, Defendant filed a response to MOX Services’ motion for partial
    summary judgment, and purported to cross-move for partial summary judgment in its
    favor. However, as MOX Services notes, Defendant’s “cross-motion” essentially was only
    a response, and not a cross-motion, to the arguments advanced by MOX Services. MOX
    Services, with some justification, objected to Defendant’s filing of the final reply brief
    through the use of a “cross-motion.” The Court nevertheless has accepted all of the briefs
    1
    10 C.F.R. Part 719, entitled “Contractor Legal Management Requirements,” calls for Department of
    Energy contractors to submit detailed information to the agency whenever a contractor retains a law firm
    or individual attorney as outside counsel. Payment of law firm invoices by the agency is subject to
    contractor compliance with these requirements.
    2
    submitted by the parties, concluding that Defendant did not obtain any advantage by filing
    the final brief.
    The parties completed their briefing by April 25, 2018. The Court heard oral
    argument on the motions on May 17, 2018. For the reasons explained below, the Court
    GRANTS MOX Services’ motion for partial summary judgment on Counts II and V, and
    DENIES Defendant’s motion to dismiss Counts II, III, and V, and DENIES Defendant’s
    cross-motion for partial summary judgment.
    Factual Background2
    On March 22, 1999, the NNSA awarded Contract No. DE-AC02-99CH10888 to
    MOX Services’ predecessor in interest, Duke Cogema, Stone & Webster, LLC. The Mixed
    Oxide Fuel Fabrication Facility (“MFFF”) is intended to transform weapons-grade
    plutonium into mixed oxide fuel rods that may be used in commercial nuclear power plants.
    The MFFF represents the United States’ performance of its obligations under the
    Plutonium Management and Disposition Agreement (“PMDA”) between the United States
    and Russia. Under the PMDA, the United States and Russia agreed to dispose of 34 metric
    tons of weapons-grade plutonium roughly in parallel.
    Construction of the MFFF is a considerable undertaking, and when built will
    constitute one of the largest and most complex fabrication facilities in the world.
    According to MOX Services, the main physical plant will require over 4.5 million cubic
    feet of concrete and 70 million pounds of reinforced steel. The hundreds of process units
    and other equipment to be installed in the plant, many of which include conveyors and lifts
    and are sealed within hardened glove boxes, are being fabricated by specialty
    manufacturers in the United States and around the world at great expense. The controls
    and utilities that join the building to the equipment will require, among other utility delivery
    channels, over 80 miles of piping, nearly 1,300 miles of cabling, and over 1.3 million
    pounds of HVAC ducts. As a nuclear construction project where contractors will be
    working with weapons-grade plutonium and uranium oxide, the operations are governed
    by the regulations of the Nuclear Regulatory Commission.
    The contract consists of a base contract for the design of the MFFF and three
    options: Option 1 is for construction of the MFFF (including fabrication and installation of
    process unit equipment and cold start-up); Option 2 is for the operation of the MFFF; and
    Option 3 ultimately is for the deactivation of the MFFF.
    2
    The facts below are taken from MOX Services’ Supplemental Complaint, and are assumed to be true for
    purposes of Defendant’s motion for partial dismissal. See Bell Atl. Corp. v. Twombly, 
    550 U.S. 544
    , 572
    (2007); Scheuer v. Rhodes, 
    416 U.S. 232
    , 236–37 (1974). The Court also is satisfied that the declaratory
    relief counts of MOX Services’ Supplemental Complaint (Counts II and V) present legal questions of
    contract and regulatory interpretation, and that no material fact issues exist.
    3
    On May 20, 2008, MOX Services and the NNSA executed Modification 124 to the
    contract, which definitized the construction phase of the project (Option 1). The NNSA
    awarded Option 1 to MOX Services on a cost reimbursement basis, with MOX Services
    eligible to earn various types of fee or profit, including incentive fee. The contract includes
    the standard Federal Acquisition Regulation (“FAR”) clause, FAR 52.243-2 (2007),
    Changes (Cost Reimbursement). This clause allows the NNSA’s contracting officer to
    make changes within the scope of the project, and requires the contracting officer to make
    commensurate adjustments to the estimated costs and schedule, fee and other terms. The
    changes clause also applies to constructive changes performed by the contractor without a
    formal change order. In particular, the contract described certain risks that were not
    included in the original scope of work, for which the NNSA would be responsible if the
    risks materialized. The potential impacts of these risks were significant in terms of cost
    and schedule, but were difficult, if not impossible, to quantify.
    The contract language describes the risks associated with uncertainties in the
    Congressional appropriations process. To effectively plan and manage a project of the size
    and scope of the MFFF requires sufficient, predictable, and reliable Congressional funding.
    The NNSA accepted risks related to the amount and timing of project funding, and agreed
    to process appropriate changes to the contract if this risk materialized.
    As noted, the 1998 PMDA that gave rise to the MFFF project requires the plutonium
    disposition efforts of the United States and Russia to proceed roughly in parallel with each
    other. Because the risks associated with implementing the parallelism requirement were
    not quantifiable and were beyond MOX Services’ control, the contract specifically and
    broadly excluded risks “related to” the Russian parallelism requirement from its scope.
    Since the NNSA accepted these risks, they were beyond the scope of the contract, and their
    potential impacts on the project were not included in the MFFF cost or schedule estimates.
    The Russian program has lagged behind that of the United States, with the
    parallelism requirement exerting a drag on MFFF progress. Russia was slow to settle on
    the MFFF methodology to meet its plutonium disposition obligations. Once Russia
    determined that it would rely on versions of the same technology MOX Services planned
    to deploy on the U.S. MFFF, it took years to work out and ratify a liability protocol under
    which Russia would use the technology.
    The cost and schedule of the MFFF has escalated dramatically. Originally, the
    estimated cost was less than $4 billion, and the completion date was targeted for 2016. At
    present, the estimated cost is $9.9 billion, and the estimated completion date is in 2029.
    A. Incentive Fee Facts (Count II)
    Under Option 1 of the contract, beginning in the first quarter of fiscal year 2008,
    MOX Services was eligible to earn quarterly incentive fees for making progress toward
    completing MFFF construction within certain cost and schedule parameters. The
    4
    contract’s “Project/Cost Incentive Fee Band & Schedule” includes a “6.75% Fee Schedule”
    and a “7% Fee Schedule.” The “7% Fee Schedule” became effective upon the execution
    of a contract modification for a “hot start” of the project. MOX Services asserts that the
    NNSA wrongly has refused to execute a “hot start” modification to avoid paying the higher
    fee, and thus contends that it is entitled to use the 7% Fee Schedule. MOX Services’
    certified claim to the contracting officer uses the 7% Fee Schedule, but for purposes of its
    motion for partial summary judgment, MOX Services uses the 6.75% Fee Schedule.
    The incentive fee provisions also include a vesting schedule. For at least the first
    year after MOX Services invoices for quarterly incentive fees, the entire incentive fee is
    provisional. For as long as MOX Services’ performance has remained within the cost and
    schedule parameters during the previous four quarters, 50% of the provisional incentive
    fee payment becomes final, and cannot be reclassified or taken back by NNSA. The other
    half of each quarter’s incentive fee remains provisional.
    The NNSA paid MOX Services for 12 quarterly incentive fee payments for fiscal
    years 2008 through 2010. Thereafter, NNSA determined that MOX Services was no longer
    within the applicable cost and schedule parameters. The NNSA suspended further
    incentive fee payments in February 2011. In total, the NNSA paid MOX Services $29.1
    million, of which $21.6 million is provisional. The breakdown of NNSA’s incentive fee
    payments to MOX Services is as follows:
    Period Earned         Quarterly    Provisional           Provisional      Vested Value
    Incentive Amount Percentage              Value
    Available
    2008, Q1           $750,000        50%                 $375,000           $375,000
    2008, Q2           $750,000        50%                 $375,000           $375,000
    2008, Q3           $750,000        50%                 $375,000           $375,000
    2008, Q4           $750,000        50%                 $375,000           $375,000
    2009, Q1          $3,000,000       50%                $1,500,000         $1,500,000
    2009, Q2          $3,000,000       50%                $1,500,000         $1,500,000
    2009, Q3          $3,000,000       50%                $1,500,000         $1,500,000
    2009, Q4          $3,000,000       50%                $1,500,000         $1,500,000
    2010, Q1          $3,525,000      100%                $3,525,000             -0-
    2010, Q2          $3,525,000      100%                $3,525,000             -0-
    2010, Q3          $3,525,000      100%                $3,525,000             -0-
    2010, Q4          $3,525,000      100%                $3,525,000             -0-
    Totals           $29,100,000                        $21,600,000         $7,500,000
    5
    On September 29, 2016,3 MOX Services submitted a certified claim to NNSA for
    approximately $53 million in suspended incentive fee, representing the incentive fee
    amounts from fiscal years 2011 to 2015 that NNSA has not paid. In responding to the
    certified claim on December 7, 2016, the contracting officer issued two final decisions in
    a single letter. Not only did the contracting officer deny the certified claim for $53 million,
    but he demanded MOX Services to refund all of the provisional incentive fee payments
    previously made. As relevant here, the contracting officer directed MOX Services to return
    $21.6 million in provisional incentive fee in MOX Services’ possession. Through a
    combination of direct payments and reduced NNSA payments of MOX Services’ invoices,
    MOX Services has satisfied NNSA’s demand for repayment of the provisional incentive
    fee plus interest.
    B. REA Facts (Count V)
    In June 2015, MOX Services submitted Request for Equitable Adjustment 15-001,
    “Cost/Schedule Incentive Fee Payment,” to NNSA. MOX Services asserted in the REA
    that MOX Services was entitled to cost and schedule adjustments to bring MOX Services’
    performance within the parameters for the award of suspended incentive fee. Later in 2015,
    MOX Services informed NNSA that it had expended over $2 million for outside counsel
    and accounting consultants to assist in investigating and preparing the REA. MOX
    Services notified NNSA that it would seek reimbursement of these REA preparation costs.
    The parties disagreed on whether the REA preparation costs would be allowable as contract
    administration expenses.
    On August 17, 2015, the parties agreed that MOX Services would submit a separate
    invoice for the REA preparation costs in order to isolate these costs from other MOX
    Services’ costs. MOX Services submitted Voucher 202C in the amount of $2,244,972 for
    reimbursement of professional costs incurred in the preparation of the REA.
    The NNSA refused to pay Voucher 202C. On February 15, 2016, MOX Services
    submitted a certified claim to NNSA for $2,244,972. On May 11, 2016, the contracting
    officer issued a final decision denying the certified claim. Among other reasons for
    denying the claim, the contracting officer maintained that the REA preparation costs are
    unallowable because MOX Services had failed to comply with 10 C.F.R. Part 719. In
    particular, the contracting officer contended that MOX Services failed to comply with 
    10 C.F.R. § 719.20
     (2013), which required MOX Services to submit a copy of its engagement
    letter with outside counsel, and with 
    10 C.F.R. §§ 719.40
     and 719.44(a) (2013), which
    require compliance with 10 C.F.R. Part 719 in order for legal counsel and consulting costs
    to be allowable.
    3
    Some of these events have transpired since the original filing of the lawsuit, but were later included in
    Plaintiff’s November 3, 2017 Supplemental Complaint for Damages and Declaratory Relief.
    6
    Jurisdiction and Standard of Review
    Rule 56(a) of the Court permits a motion for summary judgment on all or part of a
    claim or defense. The summary judgment process is designed to avoid trial where there
    are no genuine issues of material fact. See, e.g., Cont’l Can Co. v. Monsanto Co., 
    948 F.2d 1264
    , 1265 (Fed. Cir. 1991). The moving party has the initial burden of showing an
    absence of genuine issues of material fact, and that the facts entitle it to judgment as a
    matter of law. RCFC 56(c); Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 323 (1986).
    The Court has jurisdiction under the Tucker Act “to grant nonmonetary relief in
    connection with contractor claims, including claims requesting an interpretation of contract
    terms.” Alliant Techsystems, Inc. v. United States, 
    178 F.3d 1260
    , 1270 (Fed. Cir. 1999).
    The Tucker Act itself provides that:
    The Court of Federal Claims shall have jurisdiction to render
    judgment upon any claim by or against, or dispute with, a
    contractor arising under section 7104(b)(1) of title 41,
    including a dispute concerning termination of a contract, rights
    in tangible or intangible property, compliance with cost
    accounting standards, and other nonmonetary disputes on
    which a decision of the contracting officer has been issued
    under section 6 of that Act.
    
    28 U.S.C. § 1491
    (a)(2) (2011) (emphasis added). In addition, a “claim” under the FAR
    “means a written demand or written assertion by one of the contracting parties seeking, as
    a matter of right, the payment of money in a sum certain, the adjustment or interpretation
    of contract terms, or other relief arising under or relating to [the] contract.” FAR 52.233-
    1(c) (2014) (emphasis added).
    During contract performance, the Court has broad discretion to grant declaratory
    relief if the claim presents “a fundamental question of contract interpretation or a special
    need for early resolution of a legal issue.” Alliant Techsystems, 
    178 F.3d at 1271
    . When
    deciding whether it is appropriate to grant declaratory relief, the Court should consider
    “whether the claim involves a live dispute between the parties, whether a declaration will
    resolve the dispute, and whether the legal remedies available to the parties would be
    adequate to protect the parties’ interests.” 
    Id.
     Moreover, the contractor is not required to
    wait until performance is completed before asserting a contract interpretation claim. 
    Id. at 1266
     (“The point is simply that the disputes clause does not impose an additional obligation
    to wait until performance is completed before filing a claim for relief from the contracting
    officer’s decision.”)
    With regard to Defendant’s motion for partial dismissal, a challenge to the “court’s
    general power to adjudicate in specific areas of substantive law . . . is properly raised by a
    7
    12(b)(1) motion.” Palmer v. United States, 
    168 F.3d 1310
    , 1313 (Fed. Cir. 1999). In
    determining whether it has subject matter jurisdiction to entertain a plaintiff’s complaint,
    the Court should presume all factual allegations to be true and construe all reasonable
    inferences in favor of the plaintiff. Scheuer v. Rhodes, 
    416 U.S. 232
    , 236-37 (1974).
    However, if the Court’s jurisdiction is challenged, a plaintiff cannot rely merely upon the
    allegations in the complaint, but must instead bring forth relevant, competent proof to
    establish jurisdiction. See McNutt v. Gen. Motors Acceptance Corp., 
    298 U.S. 178
    , 189
    (1936). The plaintiff bears the burden of establishing the Court’s jurisdiction by a
    preponderance of the evidence. Reynolds v. Army & Air Force Exch. Serv., 
    846 F.2d 746
    ,
    748 (Fed. Cir. 1988).
    When considering a motion to dismiss a complaint for failure to state a claim upon
    which relief may be granted under Rule 12(b)(6), the Court must accept as true all factual
    allegations submitted by the plaintiff. Bell Atl. Corp. v. Twombly, 
    550 U.S. 544
    , 555
    (2007). Accepting those allegations as true, for the plaintiff to survive dismissal, the Court
    must conclude that “the plaintiff pleads factual content that allows the court to draw the
    reasonable inference that the defendant is liable for the misconduct alleged.” Ashcroft v.
    Iqbal, 
    556 U.S. 662
    , 678 (2009) (citing Twombly, 
    550 U.S. at 556
    ). The plaintiff’s factual
    allegations must be substantial enough to raise the right to relief above the speculative
    level, accepting all factual allegations in the complaint as true and indulging all reasonable
    inferences in favor of the non-movant. Twombly, 
    550 U.S. at 545
    ; Chapman Law Firm
    Co. v. Greenleaf Constr. Co., 
    490 F.3d 934
    , 938 (Fed. Cir. 2008). In the government
    contracts context, the plaintiff must “provide sufficient factual allegations in the complaint
    to support success on the type of contract claim alleged in the complaint.” Extreme
    Coatings, Inc. v. United States, 
    109 Fed. Cl. 450
    , 455 (2013).
    Discussion
    A. MOX Services’ Motion for Partial Summary Judgment
    1. Provisional Incentive Fees (Count II)
    The incentive fee issue presented in the cross-motions is whether MOX Services is
    entitled to retain provisional incentive fee payments until the construction of the MFFF is
    completed, or whether the NNSA is entitled to demand return of the provisional incentive
    fee payments before construction is completed. The parties agree that the amount in
    dispute is $21.6 million.
    The interpretation of a contract is a legal question that is subject to resolution by
    summary judgment. Forman v. United States, 
    329 F.3d 837
    , 841 (Fed. Cir. 2003). “A
    contract is read in accordance with its express terms and the plain meaning thereof.” C.
    Sanchez & Son, Inc. v. United States, 
    6 F.3d 1539
    , 1543 (Fed. Cir. 1993). Provisions that
    are clear and unambiguous must be given their plain and ordinary meaning. Alaska
    8
    Lumber & Pulp Co. v. Madigan, 
    2 F.3d 389
    , 392 (Fed. Cir. 1993). A contract is ambiguous
    only where its terms are amenable to more than one reasonable interpretation. Grumman
    Data Sys. Corp. v. Dalton, 
    88 F.3d 990
    , 997 (Fed. Cir. 1996).
    Here, the contract provisions taken together unambiguously provide that the
    incentive fee NNSA pays to MOX Services is to remain in the custody of MOX Services
    until the MFFF construction is completed. The provisional incentive fees are used
    explicitly to adjust cost sharing between the parties when construction is finished. Only at
    project completion does any unvested incentive fee become subject to potential payback to
    NNSA. An understanding of all the pertinent contract provisions yields this result.
    Section B, Contract Line Items (“CLINs”) 0001 through 0006, established the
    estimated cost reimbursement amounts for the construction of the MFFF. The total
    estimated cost in Section B.2 is $4,560,353,510, exclusive of fee. The total estimated fee
    in CLIN 0007 is $268,082,369. By adding these two amounts together, the total estimated
    price for the MFFF, cost plus fee, is $4,828,435,879. The fee in CLIN 0007 is broken
    down among fixed fee ($77,599,035), incentive fee ($148,055,406), and award fee
    ($42,427,928). Of the $148,055,406 in incentive fees, the incentive fee pool for the Option
    1 MFFF is $76,862,871. This amount represents the incentive fee that MOX Services could
    receive by staying within the cost and schedule parameters of CLIN 0002. Pl.’s Mot. for
    Partial Summ. J., App., APPX004, Dec. 27, 2017.
    Section J, Attachment 7, provides for a sharing of cost savings, or cost overruns as
    the case may be, at the time of project completion. 
    Id.
     at APPX023. If the final project
    costs are less than the adjusted Total Project Cost (“TPC”), the contractor earns 25 cents
    for every dollar under the adjusted TPC. Section J.7, paragraph C, “Collateral
    Savings/Cost Share,” provides “The Contractor’s share of savings under this Paragraph is
    capped at $200,000,000, which is in addition to fees calculated under Paragraphs A and B
    above. Cost overrun remittance is capped at remaining provisional fee, as computed per
    Paragraph A above.” 
    Id.
     at APPX025 (emphasis added). Paragraph A, “Final
    Cost/Schedule Incentive Fee Payment Determination,” states “At project completion,
    defined as the submittal and acceptance of the CD-4 [contract completion] package, all
    provisional payments convert to final payments provided the project cost at completion is
    less than or equal to the Adjusted TPC.” 
    Id.
     (emphasis added).
    Additional incentive fee provisions are contained in Section B.3(b)(1),
    “Cost/Schedule Incentive Fee,” and Section J, Attachment 7, “Cost/Schedule Incentive Fee
    Plan.”
    Section B.3(b)(1)(iv) states in pertinent part:
    (iv) Cost/Schedule Incentive Fee payments to the Contractor
    shall be 100% provisional for the 12 months following the
    9
    period in which it is earned. At the end of the fifth quarter
    following the quarter the incentive fee is earned, 50% of the
    Interim Incentive Fee payments received by the Contractor will
    become permanent provided the Contractor’s performance is
    still within established parameters. This process will continue
    each quarter of Option 1 performance. If at any time the
    Contractor is not performing within the cost and schedule
    parameters established per Incentive/Milestone Fee Plan,
    paragraph 2.A, payments of that incentive fee shall stop and all
    such incentive fee that is provisional shall remain provisional
    until the Contractor’s performance improves to once again fall
    within established cost and schedule parameters established
    per Incentive /Milestone Fee Plan.
    
    Id.
     at APPX007. Section J.7, “Final Incentive Fee Payment,” states:
    The final incentive fee determination will be calculated by
    the [contracting officer] subsequent to the end of the final
    evaluation period, i.e., September 2016 (if that date is not
    extended). The final incentive fee determination will be based
    on the total allowable, final project costs for the physical
    completion and acceptance of the MFFF the work scope
    defined by CLIN 0002. The costs shall be calculated using the
    Contractor’s approved Earned Value Management System and
    the results of any Government audits.
    The final incentive fee payment will be based upon overall
    progress and will reflect the difference between the final
    incentive fee determination and the sum of quarterly
    provisional incentive fee payments made during the period of
    the contract, subject to the maximum fee amounts in Section B
    and this plan. If the sum of quarterly provisional incentive fee
    payments made during the period of the contract is greater than
    the overall fee that is calculated by the [contracting officer] in
    his/her final incentive fee determination, the contractor shall
    reimburse the amount of fee already paid that is greater than
    the amount of fee earned.
    The final incentive fee payment shall be limited by the
    Maximum amount of Fee available in Section B, subject to the
    contractor’s achievement of the minimum performance
    requirements and threshold requirements of this plan.
    10
    APPX026-027.
    The NNSA’s attempt to claw back $21.6 million in provisional incentive fees is
    premised on the assertion that MOX Services has hopelessly exceeded the estimated
    project cost, has no chance of meeting the project schedule parameter, and thus will not be
    able to show entitlement to any incentive fees at project completion. In opposition, MOX
    Services maintains that the estimated project cost and schedule must be adjusted under the
    changes clause, FAR 52.243-2, because MOX Services is not responsible for the increased
    costs and schedule delays incurred to date. These contentions present factual issues that
    will be resolved in the other claims that MOX Services has submitted to the Court. It
    remains to be seen whether the estimated cost and schedule will require adjustment.
    Regardless of which party is responsible for the increased costs and schedule delays,
    none of the contract provisions permits the NNSA to claw back provisional incentive fees
    before the completion of the MFFF. What is most troubling here is that the contracting
    officer used the denial of MOX Services’ certified claim, and demand for refund of $21.6
    million, as a way to gain leverage over MOX Services through baseless retaliation. The
    law requires contractors to certify that their claims are “made in good faith,” that all
    “supporting data are accurate and complete to the best of the contractor’s knowledge and
    belief,” and that the amount requested “accurately reflects the contract adjustment for
    which the contractor believes the Federal Government is liable.” 
    41 U.S.C. § 7103
    (b)
    (2011). Surely, a reciprocal obligation to act in good faith applies to the government. See
    Moreland Corp. v. United States, 
    76 Fed. Cl. 268
    , 292 (2007) (“Under the Contract
    Disputes Act, a contracting officer’s review of certified claims submitted in good faith is
    not intended to be a negotiating game where the agency may deny meritorious claims to
    gain leverage over the contractor.”) The same reasoning applies where the contracting
    officer conjures up a baseless claim to demand immediate refund of provisional incentive
    fees.
    The Court in effect is granting declaratory relief requiring the NNSA to return $21.6
    million to MOX Services until the MFFF project is completed. MOX Services may submit
    an invoice to the NNSA for this amount attaching a copy of this decision.
    2. REA Preparation Expenses (Count V)
    At the May 17, 2018 oral argument, Defendant’s counsel conceded that 10 C.F.R.
    Part 719 does not apply to MOX Services, and cannot be relied upon as a basis to oppose
    MOX Services’ claims for REA preparation expenses. Oral Arg., Tr. 29, May 17, 2018
    (“[W]e are not contesting the issue of the applicability of 10 CFR 719.”) Accordingly, the
    11
    Court grants declaratory relief in favor of MOX Services on this contract interpretation
    issue.
    B. Defendant’s Motion for Partial Dismissal
    In its February 1, 2018 motion for partial dismissal, Defendant asserts that Counts
    II, III, and V of MOX Services’ Supplemental Complaint should be dismissed for failure
    to state a claim upon which relief may be granted under Rule 12(b)(6), and for lack of
    subject matter jurisdiction under Rule 12(b)(1). With regard to Count III, Defendant
    argues: (1) that the claim is not based upon any contractual provision; and (2) that MOX
    Services failed to submit the claim to the contracting officer within six years of accrual.
    With regard to Counts II and V, Defendant contends that: (1) the contract interpretation
    claims were not presented to the contracting officer; (2) the Court lacks jurisdiction because
    they do not present a case or controversy, and are not ripe; and (3) declaratory relief is not
    appropriate where money damages are adequate.
    1. Count III (Breach of Contract)
    The Government’s alleged infirmities regarding Count III are without merit. The
    suggestion that MOX Services’ breach of contract claim is not based upon a specific
    contract provision is simply wrong. As MOX Services points out, the NNSA was obligated
    to increase the congressional baseline for the MFFF project and to issue a corresponding
    modification to the contract to account for “fee bearing” changes and certain “outside of
    the project risks” that were expressly assumed by NNSA. MOX Services asserts that the
    NNSA has failed to fulfill these obligations.
    The thrust of Defendant’s argument seems to be that Count III is styled as a breach
    of contract claim rather than an equitable adjustment claim, but this is a semantic
    distinction without a substantive difference. See Reflectone, Inc. v. Dalton, 
    60 F.3d 1572
    ,
    1577 (Fed. Cir. 1995) (equating an REA with the assertion of a breach of contract claim)
    (citing Crown Coat Front Co. v. United States, 
    386 U.S. 503
    , 511 (1967) (“With respect to
    claims arising under the typical government contract, the contractor has agreed in effect to
    convert what otherwise might be claims for breach of contract into claims for equitable
    adjustment.”)). This Court has rejected similar attempts by the Government to dismiss
    causes of action by elevating form over substance. See, e.g., M.A. DeAtley Constr., Inc.
    v. United States, 
    71 Fed. Cl. 370
    , 377 (2006) (noting that “the court is not inclined to
    dismiss a cognizable claim based solely on an improper label where the substance is
    correct” and that “is especially so where, as here, the substance of the claim is so readily
    identifiable that Defendant could discern Plaintiff’s intent”). Here, MOX Services has
    based its claim for fixed fee on both the changes clause and other risk-shifting provisions
    that have been disregarded by the NNSA. There is no question that MOX Services
    followed the procedures of the Contract Disputes Act by submitting the REA and then a
    12
    certified claim for fixed fee, putting all of these issues squarely before the contracting
    officer for a decision.
    Defendant contends that MOX Services cannot state a claim under the changes
    clause because it did not comply with the requirement under FAR § 52.243-2(c) (2007) to
    assert a right to an equitable adjustment within 30 days of receiving a written change order.
    This argument might apply if any change orders existed here, but they do not. If there were
    no change orders, notice did not need to be submitted within the 30-day period. Jo-Bar
    Mfg. Corp. v. United States, 
    210 Ct. Cl. 149
    , 156 (1976) (holding that “[i]n the constructive
    change situation, notice of the claim need not be presented ‘within the specific number of
    days allowed’ by the Changes clause”) (citations omitted).
    Defendant’s position reflects a “severe and narrow application of the notice
    requirements” which has often been rejected. See, e.g., Hoel-Steffen Constr. Co. v. United
    States, 
    197 Ct. Cl. 561
    , 573 (1972) (stating that notice provisions should be applied
    liberally where the government is aware of the relevant facts). Even if some notice
    requirement applied here, MOX Services’ claim is not precluded because Defendant knew
    all of the operative facts giving rise to the claims. Nova Grp./Tutor-Saliba v. United States,
    
    125 Fed. Cl. 469
    , 474 (2016) (noting that “the Government’s actual or imputed notice of
    circumstances giving rise to the claim have ‘weighed against strict enforcement of the time
    limit’”) (citations omitted). Even if any doubt exists on this issue, the question can only
    be decided on the basis of a fully developed factual record.
    It is also well settled that the Contract Disputes Act’s six-year statute of limitations
    is an affirmative defense that does not relate to this Court’s jurisdiction to hear a matter.
    Sikorsky Aircraft Corp. v. United States, 
    773 F.3d 1315
    , 1320–22 (Fed. Cir. 2014). The
    Government has the burden of proving this defense. See Shell Oil Co. v. United States,
    
    751 F.3d 1282
    , 1297 (Fed. Cir. 2014). Further, the Federal Circuit has recognized that
    “[d]ismissal at the pleading stage on statute-of-limitations grounds ordinarily is improper
    unless it is ‘apparent from the face of the complaint that the claim is time-barred.’” ABB
    Turbo Sys. AG v. TurboUSA, Inc., 
    774 F.3d 979
    , 985 (Fed. Cir. 2014) (citations omitted).
    The question of “whether and when a CDA claim accrued is determined in
    accordance with the FAR, the conditions of the contract, and the facts of the particular
    case.” Kellogg Brown & Root Servs. v. Murphy, 
    823 F.3d 622
    , 626 (Fed. Cir. 2016); see
    also Parsons Global Servs. v. McHugh, 
    677 F.3d 1166
    , 1170 (Fed. Cir. 2012). Here,
    Option 1 obligated the NNSA to increase the congressional baseline for the MFFF Project
    and to execute a corresponding modification to the contract’s Total Project Cost to account
    for “fee-bearing” changes and certain “outside of the project risks” that were assumed by
    NNSA. According to MOX Services, “fee-bearing” changes and materialized risks have
    occurred, but NNSA has failed to process a baseline change to add fee to the contract.
    Thus, MOX Services’ claim did not “accrue” until it reasonably should have known that
    NNSA would refuse to re-baseline the project as it promised to do. See Ariadne Fin. Servs.
    13
    Pty. Ltd. v. United States, 
    133 F.3d 874
    , 878 (Fed. Cir. 1998) (“[A] breach of contract
    claim accrued when [the plaintiff] should have known that it had been damaged by the
    government’s breach.”)
    The congressional re-baselining process is a mandatory pre-claim procedure
    identified in the contract as the mechanism to adjust the fee to account for “fee-bearing”
    scope changes and “outside of the project risks” that materialized. Defendant does not
    mention that process and wrongly presumes that MOX Services should have claimed fee
    on out-of-scope work before NNSA even authorized a re-baselining effort and before MOX
    Services submitted its re-baselining proposal. As the Federal Circuit recently observed,
    “precedent illustrates that the limitations period does not begin to run if a claim cannot be
    filed because mandatory pre-claim procedures have not been completed.” Murphy, 823
    F.3d at 628; see also Bay Area Laundry & Dry Cleaning Pension Trust Fund v. Ferbar
    Corp., 
    522 U.S. 192
    , 200 (1997) (holding under “basic limitations principles” that the
    statute of limitations cannot begin until such time as the claimant is legally eligible to bring
    the claim). Here, the re-baselining proposal in late 2012 was just the first step towards
    completion of the mandatory pre-claim procedure envisioned by the parties to address fee
    on out-of-scope work.
    MOX Services could not have known of the breach – and its claim did not accrue –
    until it knew or should have known that the NNSA would not process a baseline change to
    add fee to the contract. The NNSA did not even direct MOX Services to start the re-
    baseline process until January 2012 – well within the six-year statute of limitations.
    2. Counts II and V (Declaratory Relief)
    Count II is an affirmative government claim in which the NNSA clawed back $21.6
    million in provisional incentive fee payments previously made to MOX Services. MOX
    Services did not present a certified claim to the contracting officer for this amount.
    However, the $21.6 million claw back amount is an affirmative government claim, and
    does not require a presentment to the contracting officer. Total Eng’g, Inc. v. United States,
    
    120 Fed. Cl. 10
    , 15 (2015) (“The CDA does not require the contractor to jump through
    such an extra hoop and refile its defense to a Government claim as a so-called contractor’s
    ‘claim’ where it is not seeking any separate monetary relief or contract adjustment.”); see
    Placeway Constr. Corp. v. United States, 
    920 F.2d 903
    , 907 (Fed. Cir. 1990) (holding that
    under a letter from the contracting officer to the contractor, “[a]s a final decision on a
    government claim, the Claims Court has jurisdiction, even though the claim was not
    certified”); HNV Cent. River Front Corp. v. United States, 
    25 Cl. Ct. 606
    , 610 (1992)
    (“There is no statutory requirement to certify government claims, and the United States
    Claims Court has jurisdiction provided that the contracting officer’s decision is final.”)
    Defendant’s resort to M. Maropakis Carpentry, Inc. v. United States, 
    609 F.3d 1323
    ,
    1327 (Fed. Cir. 2010), is unavailing. Maropakis does not apply where, as here, the
    14
    contractor is not seeking an adjustment to contract terms. See Total Eng’g, 120 Fed. Cl. at
    15 (denying the Government’s jurisdictional argument because, “[u]nlike the contractor in
    Maropakis, [the plaintiff was] not seeking an adjustment of contract terms, but [was]
    simply defending against a Government claim”).
    The letter denying MOX Services’ certified claim for incentive fee states in the
    subject line that it is in part a “Demand for Repayment of Unearned Provisional Incentive
    Fee – Contracting Officer’s Final Decision.” Partial Summ. J., App., APPX033. The final
    decision states: “NNSA hereby determines that MOX Services is not entitled to unearned
    Incentive Fee previously paid to MOX Services on a provisional basis in the amount of
    $21,600,000.” Id. at APPX035. The final decision further states that “[t]he provisional
    amount… must be returned to the Government.” Id. at APPX038. The letter described the
    appeals process that MOX Services could employ for challenging the final decision. Id. at
    APPX040–041. There is no question that MOX Services has the right to appeal the
    Government’s affirmative claim.
    The Court rejects out of hand Defendant’s ripeness argument that there is no case
    or controversy presented in Count II. As addressed earlier in this opinion, MOX Services
    has claimed that the NNSA clawed back $21.6 million to which it had no right, if at all,
    until the completion of the Option 1 MFFF Project. Declaratory relief is appropriate here
    to resolve a ripe dispute on whether the contract can be interpreted to support the NNSA’s
    claw back of the provisional incentive fee in question.
    Count V is resolved by again citing the concession of Government counsel during
    the May 17, 2018 oral argument that “we are not contesting the issue of the applicability
    of 10 CFR 719.” Oral Arg., Tr. 29, May 17, 2018. Defendant no longer contends that it
    has a basis for dismissal of Count V.
    Conclusion
    For the foregoing reasons, Plaintiff’s motion for partial summary judgment is
    GRANTED, and Defendant’s motion for partial dismissal is DENIED. Defendant’s cross-
    motion for summary judgment also is DENIED.
    IT IS SO ORDERED.
    s/Thomas C. Wheeler
    THOMAS C. WHEELER
    Judge
    15
    

Document Info

Docket Number: 16-950

Judges: Thomas C. Wheeler

Filed Date: 6/11/2018

Precedential Status: Precedential

Modified Date: 6/11/2018

Authorities (20)

Colonel David W. Palmer, II v. United States , 168 F.3d 1310 ( 1999 )

C. Sanchez and Son, Incorporated v. United States , 6 F.3d 1539 ( 1993 )

Karen S. Reynolds v. Army and Air Force Exchange Service , 846 F.2d 746 ( 1988 )

M. Maropakis Carpentry, Inc. v. United States , 609 F.3d 1323 ( 2010 )

Continental Can Company Usa, Inc. And Continental Pet ... , 948 F.2d 1264 ( 1991 )

Reflectone, Inc. v. John H. Dalton, Secretary of the Navy , 60 F.3d 1572 ( 1995 )

Alliant Techsystems, Inc., Global Environmental Solutions ... , 178 F.3d 1260 ( 1999 )

Ariadne Financial Services Pty. Ltd. And Memvale Pty. Ltd. ... , 133 F.3d 874 ( 1998 )

Grumman Data Systems Corporation v. John H. Dalton, ... , 88 F.3d 990 ( 1996 )

Alaska Lumber & Pulp Company, Inc. v. Edward R. Madigan, ... , 2 F.3d 389 ( 1993 )

Placeway Construction Corporation v. The United States , 920 F.2d 903 ( 1990 )

Wallace Forman v. United States , 329 F.3d 837 ( 2003 )

PARSONS GLOBAL EX REL. ODELL INTERN. v. McHugh , 677 F.3d 1166 ( 2012 )

McNutt v. General Motors Acceptance Corp. , 56 S. Ct. 780 ( 1936 )

Scheuer v. Rhodes , 94 S. Ct. 1683 ( 1974 )

Crown Coat Front Co. v. United States , 87 S. Ct. 1177 ( 1967 )

Celotex Corp. v. Catrett, Administratrix of the Estate of ... , 106 S. Ct. 2548 ( 1986 )

Bay Area Laundry & Dry Cleaning Pension Trust Fund v. ... , 118 S. Ct. 542 ( 1997 )

Bell Atlantic Corp. v. Twombly , 127 S. Ct. 1955 ( 2007 )

Ashcroft v. Iqbal , 129 S. Ct. 1937 ( 2009 )

View All Authorities »