Delaware Riverkeeper Network v. Federal Energy Regulatory Commission , 243 F. Supp. 3d 141 ( 2017 )


Menu:
  •                             UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    )
    DELAWARE RIVERKEEPER                          )
    NETWORK, et al.,                              )
    )
    Plaintiffs,                     )
    )
    v.                                      )       Civil Action No. 16-cv-416 (TSC)
    )
    FEDERAL ENERGY REGULATORY                     )
    COMMISSION, et al.,                           )
    )
    Defendants.                     )
    )
    MEMORANDUM OPINION
    The Federal Energy Regulatory Commission (FERC) is empowered to issue
    “certificate[s] of public convenience and necessity” allowing entities to transport natural gas and
    to construct, extend, acquire, or operate natural gas pipelines. 15 U.S.C. § 717f. Plaintiffs, an
    environmental organization and its executive director, assert that FERC is unable to make
    unbiased determinations on the issuance of pipeline certificates because of a provision of the
    Omnibus Budget Reconciliation Act of 1986 (the Omnibus Act) which requires FERC to recover
    its annual operating costs directly from the entities it regulates. 42 U.S.C. § 7178. Plaintiffs
    claim that the Commission’s structure and the resulting actual or perceived bias has deprived
    them of constitutional Due Process under the Fifth Amendment. The PennEast Pipeline
    Company intervened as a Defendant, and before the court are both PennEast’s and FERC’s
    motions to dismiss the Complaint.
    For the reasons below, both Defendants’ motions to dismiss will be GRANTED.
    1
    I.      BACKGROUND
    Plaintiff Delaware Riverkeeper Network (DRN) is a non-profit organization established
    in 1988 to protect and restore the Delaware River and its associated watershed, tributaries, and
    habitats, reaching parts of New Jersey, New York, Pennsylvania, and Delaware. (Compl. ¶ 25).
    DRN has more than 16,000 members, some of whom own land that has been impacted by
    pipelines authorized by the Commission in the past, and DRN believes that others own land that
    will be impacted by future pipelines. (Id. ¶¶ 35, 48). Plaintiffs allege that “DRN’s members
    who live within the blast radius of proposed or existing Commission-jurisdictional pipelines are
    concerned about the increased risk of bodily and/or property harm as a result of pipeline
    accidents or explosions.” (Id. ¶ 49).
    PennEast applied for a certificate of public convenience and necessity allowing it to
    build a new natural gas pipeline system in New Jersey and Pennsylvania, and on September 28,
    2015, Plaintiffs filed a motion to intervene in the FERC review process opposing the request.
    (Id. ¶ 92). Pursuant to FERC regulations, Plaintiffs’ unopposed motion to intervene was granted.
    (Id. ¶ 93); 18 C.F.R. § 385.214(c)(1). Plaintiffs brought this suit before completion of the FERC
    review process, alleging that the review process is itself constitutionally deficient. At the
    motions hearing on March 3, 2017, counsel for FERC informed the court that FERC has delayed
    the PennEast project twice to conduct additional environmental reviews, and that as of that date,
    it had not approved the project or granted a certificate.
    FERC certification proceeds in several steps. The first is the “pre-filing process,” in
    which the applicant must make an initial filing including, among other things, the desired
    schedule of the project, anticipated application filing date, and desired date of Commission
    approval; information about zoning; a detailed map and description; a list of state agencies in the
    2
    project area with permitting requirements, and a description of the applicant’s negotiations with
    those agencies; a list of other persons and organizations of interest whom the applicant has
    contacted about the project; a description of any planning work that has already been done; an
    “acknowledgement” that a complete Environmental Report is required with the application at the
    time of filing; and a proposed Public Participation Plan for “facilitat[ing] stakeholder
    communications and public information.” 18 C.F.R. § 157.21.
    Once the applicant has applied for the certificate, FERC then determines whether “‘the
    applicant is able and willing properly to do the acts and to perform the service proposed ... and
    that the proposed service’ and ‘construction ... is or will be required by the present or future
    public convenience and necessity.’” Minisink Residents for Envtl. Pres. & Safety v. FERC, 
    762 F.3d 97
    , 101 (D.C. Cir. 2014) (quoting 15 U.S.C. § 717f(e)). In deciding whether to approve the
    application and grant the certificate, FERC conducts an environmental review as required by the
    National Environmental Policy Act (NEPA), 42 U.S.C. §§ 4321–4370h. FERC can approve or
    deny the application, and can “attach to the issuance of the certificate and to the exercise of the
    rights granted thereunder such reasonable terms and conditions as the public convenience and
    necessity may require.” 15 U.S.C. § 717f.
    The statutory scheme allows “[a]ny person, State, municipality, or State commission
    aggrieved by an order issued by the Commission” to “apply for a rehearing within thirty days
    after the issuance of [an] order,” for example, approving or rejecting construction of a pipeline.
    15 U.S.C. § 717r(a). If the Commission does not respond to the request for rehearing within
    thirty days, it is deemed denied. At that point, a party who is aggrieved can obtain a review in
    the federal Court of Appeals where the natural gas company is located. 
    Id. Regulations allow
    “[a]ny person” to file a motion to intervene; if the motion is not opposed within 15 days, the
    3
    person becomes a party automatically, see 18 U.S.C. § 385.214(a), (c), and is therefore qualified
    to appeal the denial of rehearing to the appropriate Court of Appeals.
    The D.C. Circuit has held that section 717r’s language requiring the Commission to take
    action with regard to a rehearing request within 30 days, or have it deemed denied, does not
    require FERC to act on the merits. California Co. v. Fed. Power Comm’n, 
    411 F.2d 720
    , 722
    (D.C. Cir. 1969). The Court noted that its previous decision had “apparently agreed” with
    FERC’s assertion that “the Commission has power to act on applications for rehearing beyond
    the 30-day period so long as it gives notice of this intent.” 
    Id. (quoting Texaco-Ohio
    Gas Co. v.
    Fed. Power Comm’n, 
    207 F.2d 615
    , 617 (1953)). Where the Commission issues a “tolling
    order” within 30 days indicating that it is postponing deciding on the merits but not yet denying
    an application for rehearing, the Court has found a party’s appeal remains unripe because “the
    tolling orders do not resolve the rehearing requests but simply extend the time to consider them.”
    City of Glendale v. FERC, No. 03-1261, 
    2004 WL 180270
    , at *1 (D.C. Cir. Jan. 22, 2004)
    (unpublished). Tolling orders have no explicit statutory basis, but have been upheld by the First
    and Fifth Circuits, as well as by the D.C. Circuit in several unpublished orders. Kokajko v.
    FERC, 
    837 F.2d 524
    (1st Cir. 1988); Gen. Am. Oil Co. of Texas v. Fed. Power Comm’n, 
    409 F.2d 597
    , 599 (5th Cir. 1969); California 
    Co., 411 F.2d at 722
    ; California Mun. Utils. Ass’n v.
    FERC, No. 01-1156, 
    2001 WL 936359
    , at *1 (D.C. Cir. July 31, 2001); City of Glendale, 
    2004 WL 180270
    at *1.
    Plaintiffs claim the Commission is unconstitutionally structurally biased because of its
    funding mechanism, which requires the Commission to recover its budget by charging regulated
    4
    natural gas companies, see 42 U.S.C. § 7178,1 because Commissioners may be removed only for
    cause, and because “the Commission is insulated from Congressional budgetary oversight,”
    resulting in deprivation of their Fifth Amendment due process rights. They argue that the
    Commission’s actual bias supports their claim of structural bias, as evidenced by the
    Commission’s: 100 percent approval rate; failure to enforce the terms and conditions of its
    certificates; treating requests for rehearing arbitrarily by issuing indefinite tolling orders; never
    granting a request for rehearing to a non-industry party; never determining that a full
    Environmental Impact Statement is necessary after completing an Environmental Assessment;
    failure to ever fund its Office of Public Participation; and “revolving door” through which former
    Commissioners have gone on to work in industry positions. (Compl. ¶¶ 175–240). Plaintiffs
    suggest FERC is able to effectuate pro-industry bias through the use of eminent domain and
    preemption of local and state laws; preventing Plaintiffs from attaining due process. (Id. ¶¶ 241–
    261).
    Plaintiffs ask the court to either declare FERC’s reimbursement mechanism to be
    unconstitutional, or declare the Commission’s power of eminent domain or authority to preempt
    state and local laws to be unconstitutional. They also ask the court to declare the PennEast
    certification procedure specifically, along with the procedure the Commission utilized for any
    project in the Delaware River Basin, to be a violation of due process.
    II.      LEGAL STANDARD
    A. Federal Rule of Civil Procedure 12(b)(1)
    In evaluating a motion to dismiss under Rule 12(b)(1), the court must “assume the truth
    of all material factual allegations in the complaint and ‘construe the complaint liberally, granting
    1
    Plaintiffs claim these charges comprise twenty percent of the Commission’s overall budget and
    100 percent of the gas program budget. (Opp. at 37).
    5
    plaintiff the benefit of all inferences that can be derived from the facts alleged.’” Am. Nat’l Ins.
    Co. v. FDIC, 
    642 F.3d 1137
    , 1139 (D.C. Cir. 2011) (quoting Thomas v. Principi, 
    394 F.3d 970
    ,
    972 (D.C. Cir. 2005)). However, “‘the court need not accept factual inferences drawn by
    plaintiffs if those inferences are not supported by facts alleged in the complaint, nor must the
    Court accept plaintiff’s legal conclusions.’” Disner v. United States, 
    888 F. Supp. 2d 83
    , 87
    (D.D.C. 2012) (quoting Speelman v. United States, 
    461 F. Supp. 2d 71
    , 73 (D.D.C. 2006)).
    Further, under Rule 12(b)(1), the court “is not limited to the allegations of the complaint,” Hohri
    v. United States, 
    782 F.2d 227
    , 241 (D.C. Cir. 1986), vacated on other grounds, 
    482 U.S. 64
    (1987), and “a court may consider such materials outside the pleadings as it deems appropriate to
    resolve the question [of] whether it has jurisdiction to hear the case.” Scolaro v. D.C. Bd. of
    Elections & Ethics, 
    104 F. Supp. 2d 18
    , 22 (D.D.C. 2000) (citing Herbert v. Nat’l Acad. of Scis.,
    
    974 F.2d 192
    , 197 (D.C. Cir. 1992)).
    Federal courts are vested with the power of judicial review extending only to “Cases” and
    “Controversies.” U.S. Const. art. III, § 2. Courts have, in interpreting this limitation on judicial
    power, “developed a series of principles termed ‘justiciability doctrines,’ among which are
    standing ripeness, mootness, and the political question doctrine.” Nat’l Treasury Emps. Union v.
    United States, 
    101 F.3d 1423
    , 1427 (D.C. Cir. 1996) (citing Allen v. Wright, 
    468 U.S. 737
    , 750
    (1984)).
    Standing requires, at a minimum, that a plaintiff have “suffered an ‘injury in fact,’” that
    was or is “actual or imminent, not ‘conjectural’ or ‘hypothetical;’” that there be a causal
    relationship between the injury and the basis for the claim; and that it be “‘likely,’ as opposed to
    merely ‘speculative,’ that the injury will be ‘redressed by a favorable decision’.” Lujan v. Defs.
    of Wildlife, 
    504 U.S. 555
    , 560–61 (1992) (quoting Allen v. Wright, 
    468 U.S. 737
    , 756 (1984);
    6
    Whitmore v. Arkansas, 
    495 U.S. 149
    , 155, (1990); Simon v. E. Ky. Welfare Rights Org., 
    426 U.S. 26
    , 38, (1976)). The plaintiff bears the burden of proof to establish each of the elements of
    Article III standing. Arpaio v. Obama, 
    797 F.3d 11
    , 19 (D.C. Cir. 2015) (citing 
    Lujan, 504 U.S. at 561
    ).
    Ripeness also “shares the constitutional requirement of standing that an injury in fact be
    certainly impending.” Nat’l Treasury Emps. 
    Union 101 F.3d at 1427
    . Additionally, the ripeness
    doctrine has a “prudential aspect;” in which the “court balances ‘the fitness of the issues for
    judicial decision and the hardship to the parties of withholding court consideration’—that extends
    beyond standing’s constitutional core.” 
    Id. at 1427–28
    (quoting Abbott Labs. v. Gardner, 
    387 U.S. 136
    , 149 (1967)). A court can decline to exercise jurisdiction where it finds that there is
    little hardship to the parties and the issue is not well-suited to adjudication. The D.C. Circuit has
    recognized that where there is a claim of actual bias in an administrative proceeding, there is a
    “presumption in favor of withholding judicial review until after final agency action.” Air Line
    Pilots Ass’n, Int’l v. Civil Aeronautics Bd., 
    750 F.2d 81
    , 88 (D.C. Cir. 1984). A court may
    consider an actual bias claim unripe in the absence of final agency action.
    B. Federal Rule of Civil Procedure 12(b)(6)
    A Rule 12(b)(6) motion to dismiss “tests the legal sufficiency of a complaint.”
    Browning v. Clinton, 
    292 F.3d 235
    , 242 (D.C. Cir. 2002). In order to survive a motion to
    dismiss, a complaint must contain factual allegations that are “enough to raise a right to relief
    above the speculative level.” Bell Atl. Corp. v. Twombly, 
    550 U.S. 544
    , 555 (2007).
    Additionally, the facts alleged in the complaint must “state a claim to relief that is plausible on
    its face.” 
    Id. at 570.
    The “plausibility standard is not akin to a ‘probability requirement,’ but it
    asks for more than a sheer possibility that a defendant has acted unlawfully.” Ashcroft v. Iqbal,
    
    556 U.S. 662
    , 678 (2009). In considering a motion to dismiss for failure to state a claim under
    7
    Rule 12(b)(6), a court must construe the complaint in the light most favorable to the plaintiffs
    and “must assume the truth of all well-pleaded allegations.” Warren v. District of Columbia, 
    353 F.3d 36
    , 39 (D.C. Cir. 2004).
    III.      ANALYSIS
    A. Justiciability
    i. Standing
    Defendants FERC and PennEast contend that Plaintiffs—the Delaware Riverkeeper
    Network and its Director—do not have standing to bring this suit. An association may have
    standing when it can demonstrate that it meets the elements of standing as an entity, or when “its
    members would otherwise have standing to sue in their own right, the interests at stake are
    germane to the organization’s purpose, and neither the claim asserted nor the relief requested
    requires the participation of individual members in the lawsuit.” Friends of the Earth, Inc. v.
    Laidlaw Envtl. Servs. (TOC), Inc., 
    528 U.S. 167
    , 181 (2000).
    Plaintiffs’ Complaint states that “DRN is . . . deeply familiar with the impacts to human
    health, the environment, and property rights as a result of pipeline construction activity.”
    (Compl. ¶ 39). It indicates that DRN “brings this action on behalf of the organization as part of
    the pursuit of its organizational mission, and on behalf of its impacted members, the board, and
    staff.” (Id. ¶ 41). According to the Complaint, DRN’s director, Maya K. van Rossum,
    “regularly visits” the Delaware River and “has taken family, friends, DRN members, and other
    interested people onto the Delaware River and its tributaries to educate them.” (Id. ¶ 45). The
    Complaint asserts that “DRN’s members . . . have had their aesthetic, recreational, and property
    interests harmed as a result of construction and operational activity” of pipelines within the
    Commission’s jurisdiction. (Id. ¶ 46). The Complaint alleges that the various pipelines’ impact
    on DRN members is both past and future, including “damage to real estate,” “encroachment of
    8
    construction debris upon their homes and property,” “increased risk of bodily and/or property
    harm as a result of pipeline accidents or explosions,” members’ property being subject to
    eminent domain proceedings, which in turn “compromise[s]” members’ “bargaining position
    with pipeline companies for easement agreements,” and aesthetic degradation of public parks
    affecting members’ recreational interests. (Id. ¶¶ 48–52). Generally, the Complaint alleges
    irreparable injury to “members’ aesthetic, conservation, economic, recreational, scientific,
    educational, wildlife preservation, and property interests.” (Id. ¶ 54). It also alleges injury in the
    form of FERC’s “violat[ion] [of] DRN’s right to timely judicial review of Commission
    certificates.” (Id. ¶ 53).
    FERC argues that Plaintiffs cannot establish standing: while allegations of past injury
    cannot be used to attain standing for declaratory or injunctive relief, as Plaintiffs seek, their
    claims of future injury are too attenuated and speculative. See Clapper v. Amnesty Int’l USA,
    
    133 S. Ct. 1138
    , 1147 (2013) (upholding dismissal of suit for declaratory relief regarding
    provision of Foreign Intelligence Surveillance Act because plaintiffs could not demonstrate “that
    the injury is certainly impending” (internal quotation marks omitted). PennEast adds that DRN
    has not stated any facts that would establish standing based on injury to DRN itself.
    Plaintiffs’ opposition clarifies that they do not argue that DRN has standing as an
    organization, but rather that they intend to demonstrate only associational standing. They
    maintain that they have associational standing because DRN’s members, including director
    Rossum (whom Plaintiffs call “the Riverkeeper”), “have suffered a constitutional injury” in the
    form of being “subject to a biased decisionmaking process, or the appearance of a biased
    process.” (Opp. at 9). Plaintiffs argue that they need not demonstrate a protected liberty or
    property interest in order to have standing, because the deprivation of fair process itself
    9
    constitutes sufficient injury. Plaintiffs cite a case in which the Seventh Circuit found a church
    had experienced constitutional injury in the form of deprivation of due process when a medical
    commission with a direct financial stake in the matter presided over a determination of whether
    to revert the church’s land title. United Church of the Med. Ctr. v. Med. Ctr. Comm’n, 
    689 F.2d 693
    (7th Cir. 1982). Plaintiffs also cite a Sixth Circuit case in which landowners alleged, among
    other things, deprivation of due process by a state agency, which plaintiffs claimed was biased in
    favor of the state’s interests, and which granted a permit to a waste water treatment facility
    impacting their land. Hammond v. Baldwin, 
    866 F.2d 172
    , 176 (6th Cir. 1989). The court found
    that “the injury is the submission [to a biased decision-making process] itself; the biased (or
    potentially biased) decision may also result in injury, but it is a separate, distinct one.” 
    Id. But neither
    the Sixth nor Seventh Circuit addressed what type of interest has to be at
    stake for a biased decision-making process to constitute injury. Both cases made an implicit
    assumption that the plaintiffs had a cognizable liberty interest at stake, which they pursued in an
    allegedly biased administrative forum. The Supreme Court has explicitly rejected the argument
    that a procedural injury alone is sufficient for standing: “deprivation of a procedural right
    without some concrete interest that is affected by the deprivation—a procedural right in vacuo—
    is insufficient to create Article III standing. Only a ‘person who has been accorded a procedural
    right to protect his concrete interests can assert that right without meeting all the normal
    standards for redressability and immediacy.’” Summers v. Earth Island Inst., 
    555 U.S. 488
    , 496
    (2009) (emphasis added) (quoting 
    Lujan, 504 U.S. at 572
    n.7).
    Plaintiffs suggest that their status as intervenors in the PennEast proceeding—which
    required them to demonstrate an “interest which may be directly affected by the outcome of the
    proceeding,” see 18 C.F.R. § 385.214, is sufficient to establish standing based on procedural
    10
    injury. But leave to intervene in the FERC proceedings is granted automatically absent
    opposition, meaning that a person could be granted intervenor status without actually
    demonstrating any interest that may be affected by the proceeding. While neither FERC nor
    PennEast objected to the intervention, this court’s jurisdiction requires that the plaintiffs have
    standing, and jurisdiction is not waivable.
    Plaintiffs must, therefore, demonstrate a concrete interest tethered to the alleged
    deprivation of due process in order to have standing, but the inquiry is not identical to the
    question of whether they have stated a claim for a procedural due process violation, which
    requires a protected liberty or property interest. The threshold for the former is lower.
    Plaintiffs submitted six declarations from DRN members and van Rossum, describing
    some past pipeline-related injuries, (see Farrell Decl.), as well as future likely injuries of the type
    stated in the Complaint: the upsetting impact of seeing the Delaware River and surrounding area
    “permanently altered and damaged by the Project” (van Rossum Decl. ¶ 11); negative impact to
    the use and enjoyment of areas near the pipeline resulting from deforestation, construction, and
    decreased wildlife (van Rossum Decl. ¶ 13); potential damage to property that sits fifty to a
    hundred feet from the PennEast proposed pipeline (Rader Decl. ¶¶ 7, 11); potential damage from
    proximity to a proposed pipeline expansion by Columbia Gas and/or from possible drilling under
    a DRN member’s property for that project, as well as excessive construction noise (Nelson Decl.
    ¶¶ 16, 25, 27, 32–22); potential impact on property values and ability to enjoy wildlife (Heindel
    Decl. ¶¶ 9, 13); and potential adverse impact to commercial hay production and drinking water
    quality (Kelly-Mackey Decl. ¶¶ 21, 28).
    The court finds Plaintiffs have stated sufficiently concrete and imminent injury, tethered
    to the alleged procedural due process violation, for the purposes of standing. Plaintiffs have
    11
    plausibly alleged the high likelihood of PennEast’s approval for the pipeline project, as well as
    the high likelihood that its members will suffer concrete and particularized injuries as a result. 2
    FERC argues that the alleged potential injuries are too speculative because the pipeline has not
    been approved and “may never be,” but FERC’s interpretation of the Supreme Court’s standing
    precedent is too narrow. The likelihood of approval is enough. See City of Los Angeles v. Lyons,
    
    461 U.S. 95
    , 105 (1983) (plaintiff’s “standing to seek the injunction requested depended on
    whether he was likely to suffer future injury”). If Plaintiffs had to wait until the project was
    approved, they would be effectively unable to seek review for a procedural due process violation.
    Although PennEast may, as FERC states, change the route of the pipeline in the future, the fact
    that, at the time the Complaint was filed, the proposed route would touch or impact the
    declarants’ property is enough. FERC asks the court to interpret standing in such a way that
    would render declarative or injunctive relief unavailable under any circumstances, if the conduct
    giving rise to imminent injury had not yet occurred. “Imminent” cannot be read out of the
    standard, as FERC seems to request. Plaintiffs’ alleged future injuries are not as attenuated as in
    Arpaio v. Obama or Clapper. Nor is FERC’s citation to Metcalf v. Nat’l Petroleum Council, 
    553 F.2d 176
    , 177 (D.C. Cir. 1977), in which the court found plaintiffs did not have standing based
    on their status as “consumers and citizens,” apposite. Plaintiffs here cite harms that are
    significantly more particularized than the Metcalf plaintiffs. The harms are also more specific
    than those in Summers, in which the Court found an absence of Article III standing where the
    2
    Plaintiffs cite as evidence of actual bias that the Commission has a 100% approval rate for its
    projects. (Compl. ¶ 99). PennEast responds with several examples of denials of certificate
    applications, (PennEast Mot. to Dismiss at 28), which Plaintiffs in turn say do not disprove their
    claim that “Defendants have a perfect approval record for pipeline projects that come before the
    Commission for a vote.” (Opp. at 39–40). There appears to be no dispute that the approval rate
    is high, regardless of whether it is 100 percent; the court finds it is high enough to state a
    likelihood of approval for standing purposes.
    12
    plaintiff alleged “plans to visit several unnamed national forests in the future” and a “vague
    desire to return” to the Allegheny National Forest. 
    Summers, 555 U.S. at 495
    –96.
    The other two elements of standing are causation and redressability. Plaintiffs’
    Complaint and the declarations submitted with their Opposition plausibly allege causation.
    While the past harms described in the declarations do not support injunctive relief, they do
    demonstrate that the potential injuries Plaintiffs describe would be “fairly . . . traceable” to the
    Commission’s approval of a pipeline project. 
    Lujan, 504 U.S. at 560
    . Plaintiffs need not prove
    causation at the motion to dismiss stage; they must only plausibly allege it. When the
    Commission grants a certificate to a specific proposed pipeline project, and the project results in
    harm to wildlife or construction on a person’s property, or near a person’s property, in a way that
    causes them harm, the result is “fairly traceable.”
    Redressability is a slightly more challenging element, but is “loosen[ed]” in the
    procedural due process context, at least where statutory procedural rights are at issue. See
    
    Summers, 555 U.S. at 497
    . (See also FERC Reply at 5). FERC focuses its redressability
    analysis on the underlying potential harms described by Plaintiffs, not the procedural harm they
    allege from being subject to a biased proceeding. (“Riverkeeper’s only basis to think [that the
    requested relief would alter how the Commission operates] is a misguided claim that the
    Commission would not approve natural gas pipelines but-for its supposed structural bias.”
    (FERC Reply at 11)). But because Plaintiffs’ alleged injury is procedural, and the alleged
    potential aesthetic and environmental harms are the concrete interests that give Plaintiffs enough
    of a claim of a procedural right for purposes of standing, the redressability analysis involves the
    procedural injury and not the underlying concrete interests. Plaintiffs need not allege that FERC
    would decide not to approve PennEast or any other pipeline in order to demonstrate
    13
    redressability; they need only allege, as they do, that the requested relief would redress their
    procedural injury. The court finds that Plaintiffs have Article III standing.3
    ii. Ripeness
    PennEast devotes several pages to arguing that Plaintiffs’ actual bias claim is not ripe. In
    response, Plaintiffs indicate that they do not intend to bring an actual bias claim regarding the
    PennEast pipeline approval, but rather to use that pipeline as an “example” of structural bias.
    PennEast’s concerns about ripeness are not implicated in a structural bias claim.
    B. Rule 12(b)(6)
    Stating a claim for a procedural due process violation requires a showing that (1) an
    official has deprived the plaintiff (2) of liberty or property (3) without “providing appropriate
    procedural protections.” Atherton v. D.C. Office of Mayor, 
    567 F.3d 672
    , 689 (D.C. Cir. 2009).
    FERC emphasizes that even if Plaintiffs could “show a constitutionally cognizable property
    interest,” they fail to state a claim of unconstitutional bias or appearance of bias. PennEast
    argues that Plaintiffs have failed to demonstrate deprivation of a protected liberty or property
    interest.
    i.   Deprivation of a liberty or property interest
    3
    FERC claims that Plaintiffs’ suit is “a preemptive attempt to avoid D.C. Circuit precedent that
    actual bias claims with ‘no foundation’ lack standing.” (FERC Mot. to Dismiss at 19) (citing No
    Gas Pipeline, 
    756 F.3d 764
    , 770 (D.C. Cir. 2014)). In No Gas Pipeline, the D.C. Circuit rejected
    a constitutional challenge to FERC’s funding structure, finding that it had jurisdiction only to
    review the grant of a specific pipeline certificate, and district court would be the appropriate
    forum in which to bring a constitutional claim. The Court also noted, “lest we overlook anything
    which we should address, we note that [plaintiff] has made no real attempt to demonstrate
    standing . . . while [plaintiff] asserts that there is actual bias and not merely an appearance, it
    provides no foundation upon which we could review that claim.” 
    Id. at 770.
    The Court
    explained that plaintiff’s evidence of actual bias, the high approval rate, did not actually suggest
    bias. 
    Id. The Court
    did not find an absence of injury, causation, or redressability for the
    purposes of standing. This court does not interpret the D.C. Circuit’s comment to mean that
    actual bias claims without foundation lack standing; evidence of actual bias would go to failure
    to state a claim under Rule 12(b)(6), not standing.
    14
    Plaintiffs conflate the requirements of standing with the requirements of stating a claim
    for a procedural due process violation, suggesting that they need not demonstrate deprivation of
    a protected liberty or property interest in order to survive the motion to dismiss. But
    administrative decision-maker bias is a subset of procedural due process, not an independent area
    of law. The Supreme Court addressed the issue of administrative decision-maker bias in Tumey
    v. Ohio, 
    273 U.S. 510
    (1927); Ward v. Village of Monroeville, 
    409 U.S. 57
    (1972); and
    Schweiker v. McClure, 
    456 U.S. 188
    (1982). All three cases involved clear liberty or property
    interests: in Tumey, a criminal fine and accompanying imprisonment; in Ward, fines for traffic
    tickets; and in McClure, Medicare benefits. It is one of the basic tenets of procedural due
    process claims that a liberty or property interest is required. See Mathews v. Eldridge, 
    424 U.S. 319
    , 332, (1976) (“Procedural due process imposes constraints on governmental decisions which
    deprive individuals of ‘liberty’ or ‘property’ interests within the meaning of the Due Process
    Clause of the Fifth or Fourteenth Amendment.”). Plaintiffs have not provided any precedent
    suggesting that there may be a procedural due process claim where there is no protected liberty
    or property interest.
    Plaintiffs argue that the Pennsylvania Constitution creates and confers a property right in
    the environment that is afforded due process protection. Article I, section 27 of the state
    constitution reads: “The people have a right to clean air, pure water, and to the preservation of
    the natural, scenic, historic and esthetic values of the environment. Pennsylvania’s public natural
    resources are the common property of all the people, including generations yet to come. As
    trustee of these resources, the Commonwealth shall conserve and maintain them for the benefit
    of all the people.” Pa. Const. art. I, § 27. Plaintiffs argue the right to clean air, pure water, and
    preservation of the environment is analogous to the right created by the state constitution to a
    15
    free public education, which a federal district court found merited due process protection. See
    Mullen v. Thompson, 
    155 F. Supp. 2d 448
    , 452 (W.D. Pa. 2001) (finding that state constitution
    creates a right to free public education, but no right to public education at a school of plaintiffs’
    choice).
    Mullen v. Thompson is not analogous to the case at bar. While free public education is a
    right that is specific to an individual, section 27 creates a general, public right. Pennsylvania
    courts have affirmed this principle. See, e.g., Payne v. Kassab, 
    361 A.2d 263
    , 273 (1976)
    (“merely to assert that one has a common right to a protected value under the trusteeship of the
    State, and that the value is about to be invaded, creates no automatic right to relief”). While
    section 27 may confer a public right that would entitle plaintiffs to sue the state of Pennsylvania
    for failing to protect the environment, it does not create a federal protected property interest for
    purposes of the Fifth or Fourteenth Amendment. As PennEast points out, it would be untenable
    for every citizen of Pennsylvania to have a federal due process right at stake any time the state
    takes action that could impact the environment. Moreoever, the language of section 27 is too
    vague to confer a property interest, as it does not state how clean the water must be or how pure
    the air. See Town of Castle Rock v. Gonzales, 
    545 U.S. 748
    , 763–64 (2005) (rejecting a claim
    that restraining order statute mandating that police “use every reasonable means to enforce a
    restraining order” created a property interest protected by due process).
    Plaintiffs also hint at potential impact to real property as a property interest for which
    they are guaranteed due process. But any actual taking of real property related to a FERC
    proceeding would occur through the process of eminent domain, which would be a separate
    proceeding from the issuance of a certificate, and which has generated its own due process
    jurisprudence. Plaintiffs do not appear to be challenging a lack of due process in the exercise of
    16
    eminent domain; they appear to challenge the FERC proceedings which sometimes lead to
    eminent domain, and the real property at stake in potential subsequent eminent domain
    proceedings does not constitute a protected property interest granting the Plaintiffs additional,
    pre-eminent domain due process rights during the certificate approval stage.
    Neither are aesthetic interests or enjoyment of wildlife “liberty interests” of the type
    protected by the Fifth Amendment. Liberty interests that garner such protection include liberty
    from actual physical restraint; marriage and reproductive choices, and the right to live in the
    United States, see Kerry v. Din, 
    135 S. Ct. 2128
    , 2142 (2015) (citing Griswold v. Connecticut,
    
    381 U.S. 479
    , 485–486 (1965) and Ng Fung Ho v. White, 
    259 U.S. 276
    , 284–285 (1922)); and
    reputation, see Gen. Elec. Co. v. Jackson, 
    610 F.3d 110
    , 121 (D.C. Cir. 2010).
    Because Plaintiffs have not identified any liberty or property interest that is cognizable
    under the Fifth Amendment’s due process clause, they have failed to state a claim upon which
    relief can be granted. The declarations attached to Plaintiffs’ opposition allege some degree of
    past property damage caused by FERC-approved pipelines, but those allegations do not allege a
    “deprivation” of a protected liberty or property interest within the meaning of the Fifth
    Amendment. Negligent conduct on the part of the government does not constitute a Fifth
    Amendment deprivation. Davidson v. Cannon, 
    474 U.S. 344
    , 347 (1986). Additionally,
    Plaintiffs have not alleged a sufficient connection between the Commission’s conduct and the
    potential deprivations they foresee in the form of damage to property from drilling or potential
    dangers from pipeline accidents.
    ii. Structural or actual bias
    Although the court finds that Plaintiffs have failed to state a claim for procedural due
    process violation based on Plaintiffs’ inability to demonstrate deprivation of a protected liberty
    or property interest, the court will also address Plaintiffs’ claims of bias.
    17
    Plaintiff’s claim of structural bias is that the Budget Act’s provision requiring that FERC
    recoup its annual operating budget through a proportional charge on the regulated entities means
    that FERC cannot make unbiased determinations on applications for certificates. FERC argues,
    and the court agrees, that Plaintiffs have not plausibly pleaded that the funding structure results
    in bias. Plaintiffs do not dispute that Congress determines FERC’s budget, which has no
    relationship to the number of approved pipelines or the quantity of gas being transported within
    FERC’s jurisdiction. Plaintiffs do claim that there are “contested issues of fact” surrounding
    whether FERC can “increase its annual revenues beyond the amount appropriated by Congress.”
    (Opp. at 28). But this statement, without more, is insufficient; the court is not required to assume
    the truth of allegations by Plaintiffs that directly conflict with the statutory scheme at issue. The
    plain language of the statute indicates that FERC does not have control over its own budget. The
    Commission’s budget cannot be increased by approving pipelines; rather, 42 U.S.C. § 7178
    requires the Commission to make adjustments to “eliminate any overrecovery or underrecovery.”
    If Plaintiffs are unhappy with Congress’s chosen appropriations to the Commission (“Congress
    does not set meaningful expense limits on the commission,” (Opp. at 30)), Plaintiffs’ recourse
    lies with their legislative representatives.
    Unlike the agencies in Tumey, Ward, and McClure, FERC stands to gain no direct benefit
    from the approval of a particular pipeline project. If FERC does not approve any one project, its
    budget remains the same, with the proportional volumetric charge per gas company being
    slightly higher. If FERC commissioners also had ownership interests in gas companies, they
    might individually have a financial stake in granting certificates because it would reduce the
    proportional charges on their own companies. See, e.g., Gibson v. Berryhill, 
    411 U.S. 564
    , 578
    (1973) (finding state optometry board unconstitutionally biased because, as private practitioners,
    18
    board members had a pecuniary interest in revoking the licenses of plaintiffs in order to subsume
    their business).
    But the Commission’s general, long-term interest in its own continued existence does not
    result in a “possible temptation to the average [person] as a judge . . . which might lead him not
    to hold the balance nice, clear, and true.” 
    Tumey, 273 U.S. at 532
    . The connection between the
    act of approving an individual pipeline and the financial sustainability of the Commission as a
    whole is simply too remote to create any such bias. Not only are there “[m]ore than twenty-five
    federal agencies [that] receive a portion, if not all, of their respective operating costs through the
    collection of user fees and other annual assessments” (see Statement of Interest of the United
    States at 14, ECF No. 13), but the theory does not pass muster. Given the lifespan of a natural
    gas pipeline, which Plaintiffs allege “can extend twenty years, forty years, or longer” (Compl. ¶
    122), it is not plausible that the potential for FERC’s budget to “dry up” if FERC stopped
    approving pipeline projects is imminent or tangible enough to create any bias. See Dugan v.
    Ohio, 
    277 U.S. 61
    , 62–63 (1928) (finding no due process violation where defendant was
    convicted in mayor’s court and portions of the fines assessed went into general fund out of which
    mayor’s fixed salary was paid).
    Plaintiffs argue that discovery is necessary to gather information regarding the dates that
    all current pipeline projects will theoretically have run their full course, but the court disagrees
    with the premise that the existence of such a date creates a potential for bias. Additionally, if it
    became clear at some future point that FERC’s ability to recoup its full budget through
    volumetric charges was jeopardized, Congress would likely come up with a new funding
    mechanism, because ultimately it is Congress, not regulated pipeline companies, that funds the
    Commission and determines its authority and activities.
    19
    Because the court finds there is no inherent structural bias or appearance of structural
    bias, Plaintiffs’ purported examples of actual bias, which Plaintiffs offer as “evidence of the
    Commission’s inherent bias” (Opp. at 8), are not relevant to the court’s analysis. Allegations of
    actual bias cannot create structural bias where the court determines there is none. The Budget
    Act on its face does not create a FERC funding mechanism that creates unconstitutional bias for
    the basic reason that approval of pipeline projects does not increase FERC’s budget. Plaintiffs
    have not alleged facts upon which relief could be granted.4
    IV.      Conclusion
    For the reasons set forth above, both Defendants’ motions to dismiss will be
    GRANTED.
    A corresponding order will issue separately.
    Dated: March 22, 2017
    Tanya S. Chutkan
    TANYA S. CHUTKAN
    United States District Judge
    4
    Because the court finds that Plaintiffs fail to state a claim under Rule 12(b)(6), and dismissal is
    therefore appropriate, the court will not reach FERC’s argument that the court should exercise its
    discretion to dismiss a declaratory judgment case. (FERC Mot. to Dismiss at 41–42).
    20
    

Document Info

Docket Number: Civil Action No. 2016-0416

Citation Numbers: 243 F. Supp. 3d 141

Judges: Judge Tanya S. Chutkan

Filed Date: 3/22/2017

Precedential Status: Precedential

Modified Date: 1/13/2023

Authorities (44)

John Kokajko, D/B/A Voyageurs v. Federal Energy Regulatory ... , 837 F.2d 524 ( 1988 )

general-american-oil-company-of-texas-v-federal-power-commission-humble , 409 F.2d 597 ( 1969 )

Thomas, Oscar v. Principi, Anthony , 394 F.3d 970 ( 2005 )

Victor Herbert v. National Academy of Sciences , 974 F.2d 192 ( 1992 )

united-church-of-the-medical-center-a-religious-corporation-v-medical , 689 F.2d 693 ( 1982 )

jerry-hammond-jane-allen-offutt-and-william-n-offutt-iv-md , 866 F.2d 172 ( 1989 )

Dolly Kyle Browning and Direct Outstanding Creations ... , 292 F.3d 235 ( 2002 )

William Hohri v. United States , 782 F.2d 227 ( 1986 )

Lee Metcalf, of U.S. Senate v. National Petroleum Council , 553 F.2d 176 ( 1977 )

Texas-Ohio Gas Co. v. Federal Power Commission , 207 F.2d 615 ( 1953 )

National Treasury Employees Union v. United States , 101 F.3d 1423 ( 1996 )

American Nat. Ins. Co. v. FDIC , 642 F.3d 1137 ( 2011 )

the-california-company-v-federal-power-commission-union-texas-petroleum , 411 F.2d 720 ( 1969 )

Warren v. District of Columbia , 353 F.3d 36 ( 2004 )

Atherton v. District of Columbia Office of the Mayor , 567 F.3d 672 ( 2009 )

General Electric Co. v. Jackson , 610 F.3d 110 ( 2010 )

Payne v. Kassab , 468 Pa. 226 ( 1976 )

Air Line Pilots Association, International v. Civil ... , 750 F.2d 81 ( 1984 )

Speelman v. United States , 461 F. Supp. 2d 71 ( 2006 )

Scolaro v. District of Columbia Bd. of Elections and Ethics , 104 F. Supp. 2d 18 ( 2000 )

View All Authorities »