National Parks Conservation Association v. Salazar , 965 F. Supp. 2d 67 ( 2013 )


Menu:
  •                   UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    ______________________________
    )
    NATIONAL PARKS CONSERVATION   )
    ASSOCIATION, et al.,          )
    )
    Plaintiffs,    )
    )
    v.             )    Civil Action No. 12-1690 (RWR)
    )
    SALLY JEWELL,1 et al.,        )
    )
    Defendants.    )
    ______________________________)
    MEMORANDUM OPINION
    The National Parks Conservation Association and nine other
    organizations2 brought this suit against the Secretary of the
    Interior and the Northeast Regional Director of the U.S. National
    Park Service (“NPS”) challenging NPS’ decision to grant special
    use permits and an extended right-of-way for the construction of
    the Susquehanna to Roseland Transmission Line (“S-R Line”)
    through three national park areas -- the Delaware Water Gap
    National Recreation Area, the Middle Delaware National Scenic and
    Recreational River, and the Appalachian National Scenic Trail
    1
    Under Federal Rule of Civil Procedure 25(d), current
    Secretary of the Interior Sally Jewell is automatically
    substituted for former Secretary Kenneth Salazar.
    2
    The other plaintiff organizations include the Appalachian
    Mountain Club, Appalachian Trail Conservancy, Association of New
    Jersey Environmental Commissions, Delaware Riverkeeper Network,
    New Jersey Highlands Coalition, New York-New Jersey Trail
    Conference, Rock the Earth, Sierra Club and Stop the Lines.
    - 2 -
    (collectively, “the Parks”).     PPL Electric Utilities Corporation
    and Public Service Electric and Gas Company, the utilities
    companies that applied to NPS to build the S-R Line, intervened
    in this matter.     Plaintiffs moved for summary judgment arguing
    that the NPS failed to properly review the environmental
    consequences of the S-R Line project in the environmental impact
    statement (“EIS”), in violation of the National Environmental
    Protection Act (“NEPA”), 
    42 U.S.C. § 4321
     et seq., and that NPS
    unlawfully decided to grant the special use permits and an
    extended right-of-way, in violation of the NPS Organic Act, 
    16 U.S.C. § 1
     et seq. and the Wild and Scenic Rivers Act (“WSRA”),
    
    16 U.S.C. § 1271
     et seq.     The federal defendants and the
    intervenor defendant utilities companies cross-moved for summary
    judgment.   Because NPS’ actions were not arbitrary and
    capricious, the plaintiffs’ motion for summary judgment will be
    denied and the defendants’ cross-motions for summary judgment
    will be granted.3
    BACKGROUND
    The intervenor-defendants own a right-of-way through the
    Parks upon which the current 230 kilovolt (“kV”) Bushkill-to-
    3
    The federal defendants also move to strike the declaration
    of Pamela Underhill and all references to the declaration in the
    plaintiffs’ summary judgment reply brief. Because the summary
    judgment motions will be decided without consideration of the
    Underhill declaration, the federal defendants’ motion to strike
    will be denied as moot. Moreover, the plaintiffs’ motion for a
    preliminary injunction will be denied as moot.
    - 3 -
    Kittatinny transmission line (“B-K Line”) stands.    Compl. ¶ 44;
    Pls.’ Mem. of Law in Supp. of Mot. for Summ. J. (“Pls.’ Mem.”) at
    7; Def.-Intervenors’ Mem. of P. & A. in Opp’n to Pls.’ Mot. for
    Summ. J. and in Supp. of Def.-Intervenors’ Cross-Mot. for Summ.
    J. (“Intervenor Defs.’ Mem.”) at 7; Mem. in Supp. of Fed. Defs.’
    Cross-Mot. for Summ. J. and Opp’n to Pls.’ Mot. for Summ. J.
    (“Federal Defs.’ Mem.”) at 2.    In 2007, PJM Interconnection, LLC,
    (“PJM”), which oversees the electrical transmission system in the
    region, identified electric grid reliability violations with the
    B-K Line.   Intervenor Defs.’ Mem. at 5; Federal Defs.’ Mem. at 2;
    AR 73982, 78554.   PJM decided that a 500-kV electric transmission
    line was the preferred solution for the reliability violations
    which had been identified.    NPS Susquehanna to Roseland 500kV
    Transmission Line Right-of-Way and Special Use Permit Final
    Environmental Impact Statement (“FEIS”) at 4 (AR 47865);
    AR 73982.   The intervenor defendants applied to NPS for a special
    use permit to allow for “construction, maintenance and operation
    of the S-R Line across [the Parks], the expansion of the existing
    [right-of-way], and the replacement of an existing 230-kV
    transmission line it owns.”    FEIS at 4 (AR 47865); see also NPS
    Susquehanna to Roseland 500-kV Transmission Line Right-of-Way and
    Special Use Permit, Record of Decision (“ROD”) at 1 (AR 116587);
    Compl. ¶ 53.   The proposed S-R Line would replace the existing
    B-K Line and include larger towers, an additional circuit, and a
    - 4 -
    widened right-of-way to accommodate the changes.   Compl. ¶ 53;
    FEIS at 4 (AR 47865); ROD at 1 (AR 116587).
    NPS conducted an environmental review and published a Draft
    Environmental Impact Statement (“DEIS”) in 2011 that identified
    various alternative routes for building a replacement
    transmission line, identified mitigation measures, and discussed
    the environmental consequences of each alternative.     See Federal
    Defs.’ Mem. at 8; Intervenor Defs.’ Mem. at 11; ROD at 21
    (AR 116607).   In January 2012, the applicants proposed a
    methodology for compensatory mitigation and estimated that
    $36,494,241 should be provided in compensatory mitigation for the
    project in their comments to the DEIS.   AR 78239-48.   After the
    public comment period closed, NPS issued the Final Environmental
    Impact Statement (“FEIS”) and identified NPS’ preferred
    alternative as the applicant’s proposed route.   FEIS at vii
    (AR 47840); Federal Defs.’ Mem. at 5.    NPS then issued the Record
    of Decision (“ROD”) in October 2012 that granted the utilities
    companies’ request for special use permits and an expanded right-
    of-way for the construction of the S-R Line.   Pls.’ Mem. at 26;
    Intervenor Defs.’ Mem. at 13; Federal Defs.’ Mem. at 6-7; ROD at
    1-30 (AR 116586-616).   In December 2012, NPS issued the special
    use permits to the utilities company for the project, and the
    utilities companies and the federal defendants entered into a
    Memorandum of Agreement that set forth details about the
    - 5 -
    compensatory mitigation measures and established the Middle
    Delaware Mitigation Fund (“the Fund”).   Intervenor Defs.’ Mem. at
    16-17; Federal Defs.’ Mem. at 7; see Federal Defs.’ Opp’n to
    Pls.’ Mot. for a Prelim. Inj., Ex. B, Memorandum of Agreement.
    DISCUSSION
    Summary judgment may be granted on a claim if “there is no
    genuine dispute as to any material fact and the movant is
    entitled to judgment as a matter of law.”   Fed. R. Civ. P. 56(a).
    In a case involving review of a final agency action
    under the APA, however, the standard set forth in Rule
    56(c) does not apply because of the limited role of a
    court in reviewing the administrative record. . . .
    “[T]he function of the district court is to determine
    whether or not as a matter of law the evidence in the
    administrative record permitted the agency to make the
    decision it did.” . . . Summary judgment thus serves
    as the mechanism for deciding, as a matter of law,
    whether the agency action is supported by the
    administrative record and otherwise consistent with the
    APA standard of review.
    Center for Food Safety v. Salazar, 
    898 F. Supp. 2d 130
    , 138
    (D.D.C. 2012) (quoting Sierra Club v. Mainella, 
    459 F. Supp. 2d 76
    , 89–90 (D.D.C. 2006)); see also Flaherty v. Bryson, 
    850 F. Supp. 2d 38
    , 47 (D.D.C. 2012) (“Because this case involves a
    challenge to a final administrative decision, the Court’s review
    on summary judgment is limited to the Administrative Record.”).
    The complaint asserts eleven causes of action including
    eight4 NEPA claims, one NPS Organic Act claim, and two WSRA
    4
    The complaint asserts that NPS violated NEPA by failing to
    consider all reasonable alternatives for the S-R Line project in
    - 6 -
    claims.   See Compl. at 33-41.   Review of final agency actions
    under these statutes is governed by the arbitrary and capricious
    standard of the Administrative Procedure Act (“APA”), 
    5 U.S.C. §§ 701-706
    .   See Nevada v. Dep’t of Energy, 
    457 F.3d 78
    , 87 (D.C.
    Cir. 2006) (stating that courts “apply the APA’s arbitrary and
    capricious standard to a NEPA challenge”); Daingerfield Island
    Protective Soc’y v. Babbitt, 
    40 F.3d 442
    , 446 (D.C. Cir. 1994)
    (finding that the NPS’ exercise of discretion under the NPS
    Organic Act must be upheld unless it violated the APA’s arbitrary
    and capricious standard); Hells Canyon Alliance v. U.S. Forest
    Serv., 
    227 F.3d 1170
    , 1176-77 (9th Cir. 2000) (stating that
    review of the WSRA is governed by the APA).    “Generally, ‘[t]he
    Count Four, failing to consider and disclose all direct and
    indirect effects of the S-R Line project in Counts Five and Six,
    failing to consider and disclose a connected action in Count
    Seven, failing to consider cumulative impacts of the S-R Line
    project in Count Eight, failing to consider and disclose
    mitigation measures in Count Nine, failing to prepare a
    supplemental EIS in Count Ten, and prejudging and approving the
    selected alternative in Count Eleven. However, the plaintiffs’
    summary judgment memorandum asserts arguments directed at claims
    in Counts Four, Five, Six, Nine, and Ten. The plaintiffs’
    summary judgment memorandum does not address directly Count Seven
    or Count Eight, but their arguments supporting Counts Five and
    Six regarding the scope of the agency’s review appear to involve
    the claims in Counts Seven and Eight. In addition, the
    plaintiffs’ arguments supporting Count Eleven’s claim of
    prejudgment are based on the plaintiffs’ arguments regarding
    mitigation measures. See Pls.’ Mem. at 15-17. The plaintiffs’
    claim in Count Eleven, then, depends on the resolution of their
    claims in Count Nine. Counts Nine and Eleven will be addressed
    in Section I.A., Count Ten will be addressed in Section I.B.,
    Count Four will be addressed in Section I.C., and Counts Five to
    Eight will be addressed in Section I.D. below.
    - 7 -
    scope of review under the ‘arbitrary and capricious’ standard is
    narrow and a court is not to substitute its judgment for that of
    the agency.’”   Pettiford v. Sec’y of Navy, 
    774 F. Supp. 2d 173
    ,
    181 (D.D.C. 2011) (quoting Motor Vehicle Mfrs. Ass'n v. State
    Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983)).   “However,
    this deferential standard cannot permit courts ‘merely to rubber
    stamp agency actions,’ . . . nor be used to shield the agency’s
    decision from undergoing a ‘thorough, probing, in-depth review.’”
    Flaherty, 850 F. Supp. 2d at 47 (quoting NRDC v. Daley, 
    209 F.3d 747
    , 755 (D.C. Cir. 2000); Midtec Paper Corp. v. United States,
    
    857 F.2d 1487
    , 1499 (D.C. Cir. 1988)).   “Courts ‘will uphold a
    decision of less than ideal clarity if the agency’s path may
    reasonably be discerned.’”   Public Citizen, Inc. v. FAA, 
    988 F.2d 186
    , 197 (D.C. Cir. 1993) (quoting Bowman Transp., Inc. v.
    Arkansas-Best Freight Sys., Inc., 
    419 U.S. 281
    , 286 (1974)).
    I.   NATIONAL ENVIRONMENTAL PROTECTION ACT
    “NEPA ‘requires that agencies assess the environmental
    consequences of federal projects by following certain procedures
    during the decision-making process.’”    Brady Campaign to Prevent
    Gun Violence v. Salazar, 
    612 F. Supp. 2d 1
    , 13 (D.D.C. 2009)
    (quoting City of Alexandria, Va. v. Slater, 
    198 F.3d 862
    , 866
    (D.C. Cir. 1999)).   “[T]he twofold purpose of NEPA [is] to ensure
    that a federal agency considers environmental consequences in
    making its decision and to inform the public that the agency has
    - 8 -
    done so.”    Wilderness Soc’y v. Salazar, 
    603 F. Supp. 2d 52
    , 65-66
    (D.D.C. 2009) (citing Weinberger v. Catholic Action of
    Hawaii/Peace Educ. Project, 
    454 U.S. 139
    , 143 (1981)); see also
    Robertson v. Methow Valley Citizens Council, 
    490 U.S. 332
    , 349
    (1989).
    A.     Mitigation measures
    NEPA requires a federal agency to prepare an EIS for “‘major
    Federal actions significantly affecting the quality of the human
    environment.’”    Duncan’s Point Lot Owners Ass’n v. Fed. Energy
    Regulatory Comm’n, 
    522 F.3d 371
    , 376 (D.C. Cir. 2008) (quoting 
    42 U.S.C. § 4332
    (2)(C)).    One of the purposes of the EIS is to
    “sharply defin[e] the issues and provid[e] a clear basis for
    choice among options by the decisionmaker and the public.”      
    40 C.F.R. § 1502.14
    .    The regulations of the Council on
    Environmental Quality5 (“CEQ”) state that an EIS must “[i]nclude
    appropriate mitigation measures not already included in the
    proposed action or alternatives[,]” 
    40 C.F.R. § 1502.14
    (f), and
    5
    The CEQ was established by NEPA and has promulgated
    regulations interpreting NEPA’s requirements. The D.C. Circuit
    has recognized that “‘the binding effect of CEQ regulations is
    far from clear,’” Nevada v. Dep’t of Energy, 
    457 F.3d 78
    , 87 n.5
    (D.C. Cir. 2006) (quoting TOMAC v. Norton, 
    433 F.3d 852
    , 861
    (D.C. Cir. 2006)), but “both agencies and courts have
    consistently looked to them for guidance[,]” Flaherty, 850 F.
    Supp. 2d at 69 n.19 (citing, among others, Sierra Club v. Van
    Antwerp, 
    661 F.3d 1147
    , 1154–55 (D.C. Cir. 2011)).
    - 9 -
    discuss “means to mitigate adverse environmental impacts[,]” 
    40 C.F.R. § 1502.16
    (h).6
    “[O]ne important ingredient of an [environmental impact
    statement] is the discussion of steps that can be taken to
    mitigate adverse environmental consequences.”         Robertson, 
    490 U.S. at 351
    .       Robertson explained that without a discussion about
    mitigation measures, “neither the agency nor other interested
    groups and individuals can properly evaluate the severity of the
    adverse effects.”       
    Id. at 352
    .    However, NEPA does not “demand
    the presence of a fully developed plan that will mitigate
    environmental harm before an agency can act” or a “detailed
    explanation of specific measures which will be employed to
    mitigate the adverse impacts of a proposed action[.]”         
    Id. at 353
    .       Instead, an agency’s discussion of potential mitigation
    measures in an EIS must include “sufficient detail to ensure that
    environmental consequences have been fairly evaluated.”         Theodore
    6
    The CEQ regulations state that
    Mitigation includes:
    (a) Avoiding the impact altogether by not taking a
    certain action or parts of an action.
    (b) Minimizing impacts by limiting the degree or
    magnitude of the action and its implementation.
    (c) Rectifying the impact by repairing,
    rehabilitating, or restoring the affected
    environment.
    (d) Reducing or eliminating the impact over time
    by preservation and maintenance operations during
    the life of the action.
    (e) Compensating for the impact by replacing or
    providing substitute resources or environments.
    
    40 C.F.R. § 1508.20
    .
    - 10 -
    Roosevelt Conservation P’ship v. Salazar, 
    616 F.3d 497
    , 503 (D.C.
    Cir. 2010) (quoting Robertson, 
    490 U.S. at 352
    ).     “NEPA ‘does not
    require agencies to discuss any particular mitigation plans that
    they might put in place,’ nor does it ‘require agencies –- or
    third parties –- to effect any.’”    
    Id.
     (quoting Citizens Against
    Burlington, Inc., v. Busey, 
    938 F.2d 190
    , 206 (D.C. Cir. 1991)).
    After preparing a draft EIS, an agency must “[r]equest comments
    from the public, affirmatively soliciting comments from those
    persons or organizations who may be interested or affected.”      
    40 C.F.R. § 1503.1
    (a)(4).
    “‘The court’s role is to ensure that the agency takes a
    ‘hard look’ at the environmental consequences of an action, not
    to interject its own judgment as to the course of action to be
    taken.’”   Wilderness Soc’y, 
    603 F. Supp. 2d at 59
         (quoting
    Hammond v. Norton, 
    370 F. Supp. 2d 226
    , 240 (D.D.C. 2005)).       “If
    the adverse environmental effects of the proposed action are
    adequately identified and evaluated, the agency is not
    constrained by NEPA from deciding that other values outweigh the
    environmental costs.”    Robertson, 
    490 U.S. at 350
    .
    Plaintiffs argue that NPS’ discussion of mitigation measures
    in the EIS is deficient for two reasons.    First, plaintiffs argue
    that NPS did not take a “hard look” at the environmental
    consequences because the FEIS included only general mitigation
    measures that do not include the contents of the mitigation
    - 11 -
    plans, and did not provide “supporting analytical data” about the
    mitigation measures or assessments about the actual mitigating
    effects of the plans.    Pls.’ Mem. at 42-43.   Second, plaintiffs
    contend that NPS failed to analyze in the EIS the compensatory
    mitigation measures.    Id. at 39-40.   Thus, the public never had
    an opportunity to evaluate the compensatory mitigation measures
    and assess the merits of the Fund, including what land would be
    acquired and how the agency decided that the compensatory
    mitigation would mitigate the environmental harm arising from the
    project.   Id.; Pls.’ Reply at 33-35.
    An EIS is not required to contain “detailed, uncheangeable
    mitigation plans for long-term development projects.”    Theodore
    Roosevelt Conservation P’ship, 
    616 F.3d at 517
    .    In Theodore
    Roosevelt, the D.C. Circuit considered whether the Bureau of Land
    Management (“BLM”) satisfied NEPA’s requirement to include
    mitigation measures when it issued an EIS before authorizing
    drilling permits in Wyoming.    The EIS included several specific
    mitigation measures to protect wildlife and plants, including
    limitations on building structures near the greater sage grouse’s
    habitat and muffling generator noises to avoid disturbances.
    Theodore Roosevelt, 
    616 F.3d at 516
    .    The mitigation plan also
    discussed performance goals which the agency would strive to
    accomplish, included flexible monitoring and protection measures
    which the BLM could modify, and relied on a “review team” which
    - 12 -
    would develop specific criteria to evaluate adherence to those
    goals.   
    Id.
        In addition, the mitigation plan included particular
    protective measures which should be applied for each drill plan
    but recognized that the “exact application of mitigation measures
    will be determined on a site-specific basis[.]”     
    Id.
       The D.C.
    Circuit reviewed whether the EIS was sufficient and held that
    NEPA’s mandate to discuss mitigation measures was met because the
    agency “set[] forth both fixed mitigation measures and an
    adaptive management plan[.]”     
    Id. at 517
    .
    In this case, the FEIS discusses potential mitigation
    measures and their effectiveness.     See FEIS at 386 (AR 48247)
    (wetlands), 431 (AR 48292) (landscape connectivity), 463-64 (AR
    48324-25) (special status species).      Appendix F of the FEIS sets
    forth a wide range of potential mitigation measures and plans
    covering impacts to the Parks’ resources.      See FEIS, App. F (AR
    48920-45).     For example, NPS requires the applicants to submit
    specific mitigation plans (i.e., drilling plans, spill prevention
    and response plan, soil and erosion control plans, vegetation
    management plans, etc.) for NPS review and approval, identified
    the goals and procedures to be implemented by the applicants’
    plans, discussed particular materials to be used in construction,
    and asserted a variety of other mitigation measures.      
    Id.
    Because the FEIS in this case sets forth both “fixed mitigation
    measures” and “adaptive management plan[s]” in the EIS similar to
    - 13 -
    those upheld in Theodore Roosevelt, NPS did not violate NEPA’s
    mandate to discuss possible mitigation measures.
    The plaintiffs’ argument regarding compensatory mitigation
    also fails because the plaintiff has not shown that the agency’s
    analysis in the EIS was insufficient.   The FEIS states that
    [i]n instances where impacts cannot be avoided and
    mitigation is not feasible, compensation for resources
    lost or degraded through project construction,
    operation, and maintenance would be required. . . .
    Compensation would be used to help ensure the
    stewardship of natural, cultural, scenic, and
    recreational resources, thus allowing for [among other
    uses] . . . acquisition in fee or easement of lands
    within or adjacent to [the Appalachain National Scenic
    Trail] and [the Delaware Water Gap National Recreation
    Area] . . . [and] implementation of the parks’ existing
    natural, historic, and recreational plans[.]
    FEIS at 72-73 (AR 47933-34).   The FEIS further states that “[t]he
    preferred alternative also includes mitigation in the form of
    compensation for unavoidable adverse impacts.   . . .
    Compensation would only be considered for adverse impacts that
    cannot be completely avoided.”   FEIS at 75 (AR 47936).   The
    discussion in the FEIS reflects that the environmental
    consequences of the construction of the S-R Line were identified
    and compensation was considered as a part of the multi-component
    mitigation plan.   For example, the FEIS discussed a specific
    feature of the compensatory mitigation when it referred to the
    requirement that “for new actions where impacts on wetlands
    cannot be avoided, proposals must include plans for compensatory
    mitigation that restores wetlands on NPS lands at a minimum
    - 14 -
    acreage ratio of 1 to 1 for the preferred alternative.”       FEIS at
    386 (AR 48247).    This level of detail comports with NEPA
    requirements.
    These circumstances are similar to those in Busey.       In that
    case, the FAA issued an EIS that set forth a general plan
    regarding mitigation efforts to blunt the effects of a
    significant increase of noise from an expanded airport.       Busey,
    
    938 F.2d at 205
    .    There, the EIS discussed mitigation measures
    that included buying property from owners of nearby locations,
    insulating doors and windows of nearby homes and buying easements
    from other home owners; estimated the cost of such measures; and
    explained that a future study will “flesh out the details of the
    mitigation plans.”    
    Id.
       The plaintiffs in that case “want[ed]
    the specifics now; . . . [and] demand[ed] that the FAA finish its
    . . . study before the agency be allowed to approve the . . .
    proposal.”   
    Id. at 206
    .    The D.C. Circuit found that the
    plaintiffs sought more information in the EIS than NEPA required
    and that the EIS in Busey was reasonably complete even though the
    study that would have provided details for the mitigation plans
    had not been completed.
    Here, the plaintiffs also want the specifics of compensatory
    mitigation measures now, but the FEIS was required to provide
    only “a reasonably complete discussion of potential mitigation
    measures.”   See Busey, 
    938 F.2d at 206
     (quoting Robertson, 490
    - 15 -
    U.S. at 352).   The plaintiffs note correctly that the FEIS did
    not provide an estimate of the compensatory mitigation amount.
    However, the administrative record reflects that the amount of
    potential compensatory mitigation varied significantly even after
    the FEIS was issued.   For example, the January 2012 applicants’
    proposal in their comments to the DEIS was $36 million, AR 78246-
    47, the July 2012 net environmental benefit analysis prepared by
    an NPS contractor was $89 million, AR 58377, a September 2012 NPS
    internal draft memorandum reflects the total amount of $62
    million, AR 73356-57, the October 2012 ROD required at least $56
    million, ROD at 15 (AR 116601), and the Memorandum of Agreement
    creating the Fund required the applicants to deposit $66 million
    in the Fund, Mem. of Agreement at 2.     Although an estimate could
    have been provided by NPS at the EIS stage, the plaintiffs were
    aware of the applicants’ proposed methodology and suggested
    compensation amount that was included in the DEIS comments, AR
    78239-48, and appended to the FEIS for informational purposes,
    FEIS, App. N (AR 49830-50045).    The plaintiffs have not shown
    that the omission of NPS’ own compensatory mitigation estimate in
    the FEIS pending negotiations with the applicants to flesh out
    the full economic value of the compensatory mitigation
    constitutes a NEPA violation.    In particular, the plaintiffs have
    not shown how the omission of this figure undermines the FEIS’
    detailed analysis of the environmental consequences of the agency
    - 16 -
    action.     The general mitigation plans included in the FEIS were
    “reasonably complete” because it included “sufficient detail to
    ensure that environmental consequences have been fairly
    evaluated[.]”     Robertson, 490 at 352.   Because the plaintiffs
    have not shown that NPS did not take a “hard look” at the
    environmental consequences of the agency action or that the
    agency failed to include mitigation measures as required by the
    CEQ regulations, the defendants are entitled to summary judgment
    on this claim.
    B.      Supplemental EIS
    The plaintiffs argue that NPS violated NEPA when NPS did not
    prepare a supplemental EIS when NPS and the applicants reached an
    agreement that the applicants would deposit $66 million in the
    Fund.     Pls.’ Mem. at 40-41.   A supplemental EIS is required when
    “[t]here are significant new circumstances or information
    relevant to environmental concerns and bearing on the proposed
    action or its impacts.”     
    40 C.F.R. § 1502.9
    (c)(1)(ii).   “A
    supplemental EIS is only required where new information provides
    a seriously different picture of the environmental landscape.”
    City of Olmsted Falls, Ohio v. FAA, 
    292 F.3d 261
    , 274 (D.C. Cir.
    2002) (internal quotation marks omitted); see also Blue Ridge
    Envtl. Def. League v. Nuclear Regulatory Comm’n, 
    716 F.3d 183
    ,
    196 (D.C. Cir. 2013) (“New and significant information presents a
    seriously different picture of the environmental impact of the
    - 17 -
    proposed project from what was previously envisioned.” (internal
    quotation marks omitted)).    “[W]hether a change is ‘substantial’
    so as to warrant [a supplemental EIS] is determined not by the
    modification in the abstract, but rather by the significance of
    the environmental effects of the changes.”   Pub. Emps. for Envtl.
    Responsibility v. U.S. Dep’t of the Interior, 
    832 F. Supp. 2d 5
    ,
    29-30 (D.D.C. 2011).
    The CEQ regulations reflect that “[a] significant effect may
    exist even if the Federal agency believes that on balance the
    effect will be beneficial.”   
    40 C.F.R. § 1508.27
    (b)(1).
    [E]ven if post-EIS changes in a project are beneficial
    to the environment or are intended to mitigate
    environmental impact, if those changes are significant,
    a supplemental statement is required:
    The proper question is not the intent behind the
    actions, but the significance of the environmental
    impacts. And even if . . . the new land use will
    be beneficial in impact, a beneficial impact must
    nevertheless be discussed in an EIS, so long as it
    is significant. NEPA is concerned with all
    significant environmental effects, not merely
    adverse ones.
    National Wildlife Fed’n v. Marsh, 
    721 F.2d 767
    , 782-83 (11th Cir.
    1983) (quoting Envtl. Def. Fund v. Marsh, 
    651 F.2d 983
    , 993 (5th
    Cir. 1981)); but see Alliance to Save the Mattaponi v. U.S. Army
    Corps of Eng’rs, 
    606 F. Supp. 2d 121
    , 137 (D.D.C. 2009) (“When a
    change reduces the environmental effects of an action, a
    supplemental EIS is not required.”).    However, supplementation of
    an EIS is not necessary when the mitigation measure is within the
    scope of the EIS’s discussion of mitigation measures or is a
    - 18 -
    minor variation from it.   See Sierra Club v. Van Antwerp, 
    526 F.3d 1353
    , 1360 (11th Cir. 2008) (finding that where a proposed
    action is a “minimizing measure,” the agency does not need to
    supplement the EIS because “a minimizing measure’s effects on the
    environment will usually fall within the scope of the original
    NEPA analysis”); see also Russell Country Sportsmen v. United
    States Forest Serv., 
    668 F.3d 1037
    , 1045 (9th Cir. 2011) (“[A]
    modified alternative [that] only lessens environmental impacts
    may tend to show that the new alternative is a ‘minor variation
    of one of the alternatives discussed in the draft EIS’ and is
    ‘qualitatively within the spectrum of alternatives that were
    discussed in the draft [EIS].’” (quoting Forty Most Asked
    Questions Concerning CEQ’s National Environmental Policy Act
    Regulations, 
    46 Fed. Reg. 18,026
    , 18,035 (Mar. 23, 1981)).
    Therefore, new information that provides significant beneficial
    environmental effects triggers the supplemental EIS requirement,
    but new information which results in environmental effects that
    are within the scope of the EIS’ analysis do not require
    supplementation.
    “The decision to undertake a supplemental EIS is subject to
    a ‘rule of reason.’”   City of Olmsted Falls, Ohio, 
    292 F.3d at 274
     (quoting Marsh v. Or. Natural Res. Council, 
    490 U.S. 360
    , 374
    (1989)).
    Application of the “rule of reason” . . . turns on the
    value of the new information to the still pending
    - 19 -
    decisionmaking process. In this respect the decision
    whether to prepare a supplemental EIS is similar to the
    decision whether to prepare an EIS in the first
    instance: If there remains “major Federal actio[n]” to
    occur, and if the new information is sufficient to show
    that the remaining action will “affec[t] the quality of
    the human environment” in a significant manner or to a
    significant extent not already considered, a
    supplemental EIS must be prepared.
    Or. Natural Res. Council, 490 U.S. at 374; see also Nat’l Comm.
    for the New River v. Fed. Energy Regulatory Comm’n, 
    373 F.3d 1323
    , 1330 (D.C. Cir. 2004).7    An agency’s decision whether to
    prepare a supplemental EIS is entitled to deference under the
    arbitrary and capricious standard.       Nat’l Comm. for the New
    River, 
    373 F.3d at
    1330 (citing Or. Natural Res. Council, 490
    U.S. at 375-76); City of Olmsted Falls, Ohio, 
    292 F.3d at 274
    .
    7
    The significance of the impacts depends on the “context”
    and “intensity” of the impacts as defined by the CEQ regulations.
    Or. Natural Res. Council, 490 U.S. at 374 n.20. The CEQ
    regulations state:
    (a) Context. This means that the significance of an
    action must be analyzed in several contexts such as
    society as a whole (human, national), the affected
    region, the affected interests, and the locality.
    Significance varies with the setting of the proposed
    action. . . .
    (b) Intensity. This refers to the severity of impact.
    Responsible officials must bear in mind that more than
    one agency may make decisions about partial aspects of
    a major action. The following should be considered in
    evaluating intensity:
    (1) Impacts that may be both beneficial and
    adverse. A significant effect may exist even if
    the Federal agency believes that on balance the
    effect will be beneficial. . . .
    
    40 C.F.R. § 1508.27
    .
    - 20 -
    Here, the plaintiffs assert that the new information
    identified in the ROD -- the amount of money that the applicants
    must place in the Fund -- is significant enough to necessitate a
    supplemental EIS.    Pls.’ Mem. at 40-41.   Specifically, “[t]he
    expenditure of $66 million to undertake land acquisitions and to
    implement stewardship activities in and around the Parks will
    have significant environmental impacts that have not yet been
    considered under NEPA, and an SEIS is required accordingly.”
    Pls.’ Reply at 35.    The federal defendants argue that no
    supplemental EIS is required because the amount of compensatory
    mitigation does not change the environmental consequences that
    were identified and addressed by the FEIS.     Federal Defs.’ Mem.
    at 38-39; Federal Defs.’ Reply at 17-20.     Overall, the federal
    defendants argue that “[a]lthough the details and final figure
    would change as a result of NPS’ independent assessment and
    computations,” the FEIS was sufficient by disclosing the adverse
    impacts and acknowledging that cash compensation would be used to
    obtain other lands.    Federal Defs.’ Reply at 19-20.
    The plaintiffs have not met their burden of showing that the
    new information is significant enough to require NPS to prepare a
    supplemental EIS.    The amount of compensatory mitigation and the
    details about the Fund revealed by the ROD and the Memorandum of
    Agreement do not change the assessment of adverse environmental
    consequences of the action addressed in the FEIS.     The
    - 21 -
    applicant’s comments to the DEIS provided the utilities
    companies’ methodology for arriving at the compensatory
    mitigation figure, including the specific per acre value.    The
    plaintiffs point to no authority that reflects that the change in
    potential mitigation funds from the applicants’ proposed figure
    of $36,494,241 to the Memorandum of Agreement’s figure of $66
    million is significant or that this increase in compensatory
    mitigation substantially changes the beneficial environmental
    consequences of the action.   The FEIS includes compensatory
    mitigation as a part of the mitigation plan and the plaintiffs
    have not shown how the new information, the precise amount of
    compensation, represents a major variation from or was
    qualitatively different than the discussion of compensatory
    mitigation in the FEIS.
    Although NPS could have provided its own independent
    analysis and methodology for identifying the corresponding
    monetary value between the compensatory mitigation measures and
    the adverse impacts in the FEIS, the plaintiffs have not shown
    that NPS was required to do so.   Thus, NPS’ decision to not
    prepare a supplement regarding compensatory mitigation is
    entitled to deference and the plaintiffs have not shown that the
    NPS acted arbitrarily and capriciously when it failed to
    supplement the FEIS after determining the final amount of
    compensatory mitigation.
    - 22 -
    C.   Scope of alternatives
    The plaintiffs also argue that NPS did not consider a
    reasonable range of alternatives in the EIS to the approval of
    the special use permits and expanded right-of-way for the S-R
    Line project.   Pls.’ Mem. at 43-44.   In particular, the
    plaintiffs assert that NPS failed to consider non-transmission
    alternatives such as “[t]he use of distributed energy generation
    sites and localized renewable energy[.]”    
    Id. at 44
    .   Under NEPA,
    agencies must “[r]igorously explore and objectively evaluate all
    reasonable alternatives, and for alternatives which were
    eliminated from detailed study, briefly discuss the reasons for
    their having been eliminated.”    
    40 C.F.R. § 1502.14
    (a).   “[A]n
    agency bears the responsibility for deciding which alternatives
    to consider in an [EIS].”   Busey, 
    938 F.2d at 195
    .    An agency
    must follow the “rule of reason” which governs “both which
    alternatives the agency must discuss, and the extent to which it
    must discuss them” and the CEQ regulations require an agency to
    “discuss only alternatives that are feasible, or (much the same
    thing) reasonable.”   
    Id.
     (internal quotation marks omitted).
    Courts should “uphold [the agency’s] discussion of alternatives
    so long as the alternatives are reasonable and the agency
    discusses them in reasonable detail.”    
    Id. at 196
    .   The “agenc[y]
    must look hard at the factors relevant to the definition of
    purpose” and when asked to approve a specific plan, “the agency
    - 23 -
    should take into account the needs and goals of the parties
    involved in the application.”    
    Id.
         Busey further explained that
    “[a]n agency cannot redefine the goals of the proposal that
    arouses the call for action; it must evaluate alternative ways of
    achieving its goals, shaped by the application at issue and by
    the function that the agency plays in the decisional process.”
    
    Id. at 199
    .   “The goals of an action delimit the universe of the
    action’s reasonable alternatives.”       
    Id. at 195
    .   The CEQ
    regulations require that the “reasonable alternatives” in an EIS
    must include the alternative of taking no action.        
    40 C.F.R. § 1502.14
    .
    In Hammond v. Norton, 
    370 F. Supp. 2d 226
     (D.D.C. 2005), the
    Bureau of Land Management approved the construction of a
    petroleum pipeline.   There, the FEIS discussed the no action
    alternative to building the pipeline briefly, stating that there
    was a need for additional petroleum products, identifying the
    annual deficits in petroleum if the pipeline were not built and
    concluding that the purpose and need of the application would not
    be met if the no action alternative were selected.        
    Id.
     at 241-
    42.   The court found that “this discussion, while brief, lays out
    the costs and benefits of the no action alternative with enough
    specificity to allow meaningful comparison with other
    alternatives.   No more is required.”      
    Id. at 242
    .
    - 24 -
    In this case, the NPS discussed the purpose of the action as
    “deciding whether to issue the applicant the permits it needs to
    construct a double-circuit 500-kV transmission line across three
    units of the national park system.”    FEIS at i (AR 47834).   In
    addition, the NPS explained that the need to replace the current
    B-K line with the new S-R Line arose from “grid reliability
    criteria violations” identified by PJM and was based on the
    approvals of Pennsylvania Public Utility Commission and New
    Jersey Board of Public Utilities.   
    Id.
     at iv-v (AR 47837-38).
    NPS identified the no action alternative as denying the utilities
    companies’ application to build the S-R Line, 
    id.
     at v (AR
    47838).   The proposal that “arouse[d] the call to action” was the
    utilities companies’ request for a special use permit and
    expanded right-of-way to replace the current transmission line
    with the larger S-R Line.   The FEIS states that the application
    was “driven by a need for transmission capacity.”    Id. at 71 (AR
    47932).   Further, NPS specifically considered, among other
    alternatives, the use of “distributed energy generation sites and
    localized renewable energy[,]” and decided that this alternative
    did “not meet the purpose and need for federal action or that of
    the applicant.”   Id.
    Here, NPS followed NEPA’s requirements by considering the
    range of alternatives flowing from the proposal’s purpose,
    including consideration of the application’s method of achieving
    - 25 -
    the goals and alternative methods.      In particular, the no action
    alternative is considered and dismissed in the FEIS and ROD.      See
    FEIS at 35 (AR 47896); ROD at 15-16, 18 (AR 116601-02, 116604).
    The agency decided that the alternatives would not meet the
    applicants’ goals and that it was likely that the applicants
    would attempt to unilaterally replace the B-K Line within the
    current right-of-way if the NPS denied the application.     Even if
    plaintiffs disagree with NPS’ analysis, the plaintiffs have not
    shown that NPS violated NEPA by failing to review alternatives
    which were raised, discussed and rationally rejected in the FEIS.
    D.     Scope of environmental impacts
    The plaintiffs also argue that the agency did not take a
    “hard look” at the full scope of the project’s environmental
    impacts.    Pls.’ Mem. at 44-45.   NPS recognized that the utilities
    companies could determine the route of the S-R Line outside of
    the boundaries of the Parks.    Thus, NPS identified Visual Split
    Location (“VSL”) points which refer to “[t]he geographical point
    outside the parks at which it becomes physically possible for the
    applicant to route the line as it sees fit.”     FEIS at 33 (AR
    47894).    “The determination of the VSLs is important because
    while NPS can require the applicant to follow a specific route
    inside the VSLs, the NPS cannot require the applicant to follow a
    certain route beyond these points.”     Id. at 34 (AR 47895).
    Therefore, NPS limited its review to the area between the VSLs
    - 26 -
    for each alternative.   Id. at 33-34 (AR 47894-95).   Plaintiffs
    argue that NPS did not consider the impact of construction of the
    S-R Line on the viewshed of another national park unit: Steamtown
    National Historic Site in Pennsylvania and that “the agency’s
    narrowly delimited review failed to consider the full scope of
    harm that construction of the length of the S-R Line might
    inflict on resources and values within the Delaware Water Gap[.]”
    Pls.’ Mem. at 44-45.
    An agency’s decision about the appropriate scope of the FEIS
    is entitled to deference.   See Kleppe v. Sierra Club, 
    427 U.S. 390
    , 414 (1976) (finding that the “determination of the extent
    and effect of these [cumulative environmental impacts], and
    particularly identification of the geographic area within which
    they may occur, is a task assigned to the special competency of
    the appropriate agencies”).   As is stated above, an agency’s NEPA
    review is limited to major Federal actions which “includ[e]
    actions with effects that may be major and which are potentially
    subject to Federal control and responsibility.”   40 C.F.R.
    1508.18.   “‘Effects’ is defined to ‘include: (a) Direct effects,
    which are caused by the action and occur at the same time and
    place,’ and ‘(b) Indirect effects, which are caused by the action
    and are later in time or farther removed in distance, but are
    still reasonably foreseeable.’”   Dep’t of Transp. v. Public
    Citizen, 
    541 U.S. 752
    , 764 (2004) (quoting 40 C.F.R. 1508.8).
    - 27 -
    “NEPA requires ‘a reasonably close causal relationship’
    between the environmental effect and the alleged cause.”   
    Id. at 767
     (quoting Metro. Edison Co. v. People Against Nuclear Energy,
    
    460 U.S. 766
    , 774 (1983)).   A reasonably close causal
    relationship is similar to the requirement of proximate causation
    in tort law.   
    Id.
     (citing Metro. Edison Co., 
    460 U.S. at 774
    ).
    To determine whether an agency must consider a particular effect,
    courts must “look to the underlying policies or legislative
    intent in order to draw a manageable line between those causal
    changes that may make an actor responsible for an effect and
    those that do not.”    Metro. Edison Co., 
    460 U.S. at
    774 n.7; see
    also Dep’t of Transp., 
    541 U.S. at 768
    .
    The plaintiffs rely on Sierra Club v. Mainella, 
    459 F. Supp. 2d 76
     (D.D.C. 2006).   In that case, the court considered the
    impact of directional drilling on land outside of a national
    preserve to extract oil and gas from beneath the preserve.
    Mainella, 459 F. Supp. 2d at 79.   Mainella found that the NPS’
    decision to allow directional drilling operations under the
    preserve violated NEPA because the NPS failed to evaluate the
    environmental effects from the surface activities of the
    directional drilling that occurred outside of the preserve.     Id.
    at 105-06.   Mainella reasoned that
    it makes sense for NPS to assess the impacts from
    surface activities because there is a reasonably close
    causal relationship between such impacts and NPS’s
    decision to grant an operator access to oil and gas
    - 28 -
    beneath the Preserve pursuant to an exemption from the
    9B regulations. The surface drilling activities are
    functionally inseparable from the downhole drilling
    activities, which may not take place until NPS grants
    the operator access through the Preserve, either
    pursuant to a 9B plan of operations or by an exemption
    from that requirement under section 9.32(e).
    Id. at 105.   Therefore, “NEPA requires NPS to evaluate impacts on
    the Preserve from adjacent surface drilling activities[.]”    Id.
    at 105-06.
    The plaintiffs assert that Mainella requires the agency to
    look beyond the Parks’ boundaries to assess other indirect
    effects of the S-R Line based on the “‘reasonably close causal
    relationship’ between the agency’s grant of right-of-way and
    special use permits and the siting of the S-R Line on either side
    of the Park.”   Pls.’ Reply at 38.   Here, the challenged agency
    action was not NPS’ approval of the entire S-R Line.    Instead,
    NPS decided to grant the applicants an extended right-of-way and
    special use permits to construct the S-R Line through the Parks.
    ROD at 2 (AR 116588).   Thus, the environmental consequences of
    the entire S-R Line were not at issue before the agency in
    creating the EIS.   Instead, the agency’s review was limited to
    the portion of the S-R Line through the Parks and any
    environmental effects caused by the construction in the Parks.
    To satisfy NPS’ duty to consider the environmental effects of the
    S-R Line construction on areas outside of the Parks, NPS
    rationally used the VSLs to limit the area of study to the area
    - 29 -
    where NPS controlled the utilities companies’ decision to
    construct the S-R Line along a particular route.
    However, NPS had an obligation to assess any environmental
    effects that had a reasonably close causal relationship to the
    agency action allowing construction through the Parks.    This
    situation is dissimilar from the circumstances in Mainella
    because the plaintiffs have not shown how construction of the S-R
    Line outside of the Parks is functionally inseparable from any
    activities inside of the Parks that NPS must regulate.    If the
    plaintiffs’ arguments are limited to the construction of the S-R
    Line immediately outside of the Parks, the plaintiffs have not
    explained why the agency’s use of VSL points was insufficient to
    satisfy NEPA’s requirements for assessing environmental impacts
    outside of the Parks.   The plaintiffs do not identify any
    environmental effects arising from the S-R Line’s construction
    similar to the directional drilling that occurred in Mainella.
    The plaintiffs argue that NEPA required NPS to assess the
    environmental impacts to the Steamtown National Historical Site.
    However, the plaintiffs have not shown how any environmental
    effects to Steamtown have a reasonably close causal relationship
    to the decision to allow construction within the Parks.    To
    trigger NEPA’s requirement to assess areas beyond the boundaries
    of the Parks, the plaintiffs must do more than show that the S-R
    Line as a whole would have environmental effects on another area
    - 30 -
    of federal land.   Instead, the plaintiffs must show why the
    agency action in this case, the decision to allow the S-R Line to
    be built through the Parks, caused the environmental effects of
    the S-R Line’s construction elsewhere.   Whether the environmental
    effects were on federal lands or non-federal lands, the issue is
    whether the environmental effects were caused by the agency’s
    action.
    Here, the plaintiffs simply assert that NPS knew what the
    entire route of the S-R Line would be and that this knowledge
    required NPS to assess the indirect effects of the S-R Line to
    locations outside the Parks.   See Pls.’ Reply at 37-38.   However,
    the plaintiffs have not identified the reasonably close causal
    relationship between the environmental effects that they have
    identified, such as impacts to the viewshed of Steamtown, and the
    decision to grant the permits for the expanded right-of-way and
    construction in the Parks.   Thus, the plaintiffs have not shown
    that the scope of NPS’ analysis in the FEIS was arbitrary and
    capricious.   Because the plaintiffs have not shown that the NPS’
    actions violated NEPA, the plaintiffs’ motion for summary
    judgment on the NEPA claims will be denied and judgment will be
    entered for the defendants on the NEPA claims.
    II.   NPS ORGANIC ACT
    The NPS Organic Act was implemented to “promote and regulate
    the use of the Federal areas known as national parks, . . . which
    - 31 -
    purpose is to conserve the scenery and the natural and historic
    objects and the wild life therein . . . by such means as will
    leave them unimpaired for the enjoyment of future generations.”
    
    16 U.S.C. § 1
    .   The D.C. Circuit has recognized that “[b]ecause
    the Organic Act is silent as to the specifics of park management,
    the Secretary has especially broad discretion on how to implement
    his statutory mandate.”   Davis v. Latschar, 
    202 F.3d 359
    , 365
    (D.C. Cir. 2000).   However, the NPS Organic Act “prohibits uses
    which impair park resources and values.”   Greater Yellowstone
    Coal. v. Kempthorne, 
    577 F. Supp. 2d 183
    , 194 (D.D.C. 2008).     “An
    impairment is an impact that, in the professional judgment of the
    responsible NPS manager, would harm the integrity of park
    resources and values, including the opportunities that otherwise
    would be present for the enjoyment of those resources or values.”
    Mainella, 459 F. Supp. 2d at 99 (internal quotation marks
    omitted); accord, NPS Management Policies § 1.4.5.   In reviewing
    an agency’s action under the APA, the court must determine
    whether the agency “‘articulate[d] a satisfactory explanation for
    its action including a rational connection between the facts
    found and the choice made.’”   Mainella, 459 F. Supp. 2d at 90
    (alteration in original) (quoting Alpharma, Inc. v. Leavitt, 
    460 F.3d 1
    , 6 (D.C. Cir. 2006)).   This standard requires NPS to
    provide a “specific and detailed explanation as to how it arrived
    at [its] conclusion[.]”   Bluewater Network v. Salazar, 721 F.
    - 32 -
    Supp. 2d 7, 30 (D.D.C. 2010).     In particular, “[m]erely
    describing an impact and stating a conclusion of nonimpairment is
    insufficient, for this merely sets forth ‘the facts found’ and
    ‘the choice made,’ without revealing the ‘rational connection’ --
    the agency’s rationale for finding that the impact described is
    not an impairment.”   Mainella, 459 F. Supp. 2d at 100.      “The
    agency’s decisions are entitled to a ‘presumption of regularity,’
    and although ‘inquiry into the facts is to be searching and
    careful, the ultimate standard of review is a narrow one.’”         Id.
    (citation omitted) (quoting Citizens to Preserve Overton Park,
    Inc. v. Volpe, 
    401 U.S. 402
    , 415-16 (1971)).
    In Mainella, NPS’ description of the environmental
    consequences to park resources from directional drilling outside
    of the national preserve used undefined conclusory labels such as
    “negligible,” “minor,” “moderate,” and “major” to describe the
    adverse impacts from the drilling with “little or no explanation
    of how NPS reached them.”   
    Id.
    As NPS notes in each decision, “[w]hether an impact
    meets this [impairment] definition depends on the
    particular resources and values that would be affected;
    the severity, duration, and timing of the impact; the
    direct and indirect effects of the impact; and the
    cumulative effects of the impact in question and other
    impacts.” But it is just that assessment that is
    lacking here. Any reasoned explanation must set forth
    which of those factors were significant in leading NPS
    to conclude that an impact is not an impairment -- or
    that a group of impacts collectively is not an
    impairment.
    - 33 -
    
    Id.
       (alterations in original) (citations omitted).   Similarly,
    in Bluewater, NPS failed to identify a “logical link” between the
    description of the consequences of PWC emissions on water quality
    and NPS’ non-impairment decision.   Bluewater, 721 F. Supp. 2d at
    30.   In particular, NPS provided “little or no basis for
    understanding why an identified impact fails to rise to the level
    of an impairment.”   Id.
    The plaintiffs argue that NPS’ decision to grant the special
    use permits and expanded right of way violated the NPS Organic
    Act because NPS did not articulate the rational connection
    between the identified adverse environmental impacts arising from
    building the S-R line and the non-impairment determination.
    Pls.’ Mem. at 28.    In particular, the plaintiffs argue that NPS’
    Non-Impairment Determination (“NID”)8 shows that NPS’ decision
    was arbitrary and capricious because NPS failed to 1) explain why
    adverse impacts did not result in impairment, 2) connect the
    impairment threshold to any objective standards, and 3) explain
    the inconsistences between restoration projections in the FEIS
    and the ROD.   Id. at 28-33.
    The plaintiffs cite the NID’s rationale regarding impairment
    to the visual resources and rivers in the affected areas.    Pls.’
    8
    The parties agree that the NID included in the
    Administrative Record is not the final version. Pls.’ Mem. at 7
    n.6; Intervenor Defs.’ Mem. at 16 n.10; Federal Defs.’ Mem. at 7
    n.7. The final NID was included as an attachment to the federal
    defendants’ motion for summary judgment.
    - 34 -
    Mem. at 28-30.    The NID’s section on visual resources
    acknowledges significant environmental impacts arising from the
    S-R Line project.    The NID states that “[t]he selected
    alternative will . . . result in unavoidable adverse impacts
    because the larger transmission line structure will remain a
    visible intrusion that degrades the existing scenic quality of
    the area that it traverses.”    Federal Defs.’ Mem., Ex. A, NID at
    12.   However, the NID explains that the S-R Line will be built
    along the route of the existing transmission line and will
    include measures to reduce the impact to the visual resources.
    Id.   In particular, the NID states that the non-impairment
    decision is based on the mitigating effects of placing tower
    structures at the maximum feasible distance from roadway and
    trail crossings, using non-reflective neutral colored painting,
    using monopoles to replace the current lattice towers,
    revegetating the disturbed areas, reducing the width of the
    permanent cleared right-of-way, and “allowing areas not needed to
    maintain the line to succeed to forest inside the [right-of-
    way.]”   Id.   Unlike in Mainella and Bluewater, the NID in this
    case does not simply identify the environmental impacts and
    assert a non-impairment decision based on a conclusory label.
    Instead, NPS provided specific reasons why the S-R Line project
    would not impair the visual resources of the Parks.    Although NPS
    could have included more detail assessing “the severity,
    - 35 -
    duration, and timing of the impact” to visual resources, the
    discussion in this case sets forth a rational explanation for the
    agency’s actions.   Although the plaintiffs may disagree with the
    agency’s conclusion regarding non-impairment, NPS has set forth
    “a rational connection between the facts found and the choice
    made” that the adverse environmental impacts on visual resources
    will not impair the Parks resources.
    The plaintiffs also cite the NID’s discussion of the adverse
    consequences to the Middle Delaware River.   The NID states that
    “[a]dverse impacts to visual qualities of the river will extend
    beyond the river itself” and “[t]he presence of taller towers,
    thicker and more numerous lines, and bird diverters will be seen
    not only as boaters pass below the wires, but as they approach
    from both upstream and downstream directions.”   Id. at 13.
    However, the NID refers to the explanation discussed above
    concerning visual resources as a partial basis for the non-
    impairment decision regarding the river resources of the Parks.
    Id.   In addition, the NID refers to the explanations in the
    historic structures and archaeology sections of the NID.   Id.
    Those sections describe specific mitigation measures to limit the
    adverse impacts to the resources in the Parks such as avoiding
    any archeological resources, halting construction where unknown
    resources are discovered and placing trees and vegetation between
    the historic resources and the transmission line.   Id. at 9-10.
    - 36 -
    The NID states that “[s]cientific resources, including water
    quality, also will not be impaired because construction or
    disturbance will not occur in the river nor within a 100-foot
    buffer from the river’s edge.”     Id. at 13.   Overall, the NID
    states that the line will cross the river at only one location
    and that the access roads for the S-R Line construction will not
    be visible from the river.   Id.    Thus, unlike in Bluewater and
    Mainella, NPS has asserted a rational basis for why the adverse
    impacts identified in the NID do not rise to the level of
    impairment and provided a logical link between the description of
    the impact and the non-impairment decision.
    The plaintiffs further argue that NPS “failed to connect the
    impairment threshold to ‘any objective standards that have been
    announced or evaluated.’”    Pls.’ Mem. at 28 (quoting Bluewater,
    721 F. Supp. 2d at 33).   Both Bluewater and Mainella support the
    proposition that general descriptions of impacts or “unbounded
    terms” that provide no objective standard for comparison are
    insufficient to satisfy the requirements of the NPS Organic Act
    under APA review.   See Bluewater Network, 721 F. Supp. 2d at 33;
    Mainella, 459 F. Supp. 2d at 101 (“An unbounded term cannot
    suffice to support an agency’s decision because it provides no
    objective standard for determining what kind of differential
    makes one impact more or less significant than another.” (citing
    Tripoli Rocketry Ass’n, Inc. v. Bureau of Alcohol, Tobacco,
    - 37 -
    Firearms, & Explosives, 
    437 F.3d 75
    , 81 (D.C. Cir. 2006))).
    Specifically, the plaintiffs challenge NPS’ analysis in the
    geological resources section that the project’s adverse impacts
    will not “‘substantially change the scenic landscapes’” in the
    parks.   Pls.’ Mem. at 31 (quoting NID at 4).     However, NPS
    explained that the basis for that conclusion was that the adverse
    impacts to geological resources “will occur entirely within the
    [right-of-way] corridor and will be limited to specific locations
    where towers will be installed.”     NID at 4.   Further, the NID
    discussed the low probability of boreholes and the shallow nature
    of the drilling.   Id. at 3-4.    Although the NID could have
    provided more details regarding the geological consequences, the
    NID asserted reasons for the conclusion and objective statements
    about the extent of damage to the geological resources.
    The plaintiffs also challenge the NID’s discussion of
    archeological impacts.   That section states that “‘known
    archeological sites will be avoided for the most part or the
    effects will be limited to just a portion of the site[.]’”       Pls.’
    Mem. at 31 (quoting NID at 10).     However, the archeological
    resources portion of the FEIS states that a total of 25
    archeological sites were identified along the alignment for the
    alternative that was selected.     FEIS at 221 (AR 48082).   Then,
    the NID specifies that two archeological sites could be affected
    and discusses specific mitigation measures for project work near
    - 38 -
    archeological resources in the Parks including “avoid[ing] or
    minimiz[ing] ground-disturbing activities to the most significant
    portions of the site.”   NID at 9.   NPS also referred to the
    intended mitigation measures as described in Appendix F of the
    FEIS.   Id.   NPS has provided a sufficient rationale as the basis
    for the non-impairment determination because the non-impairment
    determination is not built on undefined and conclusory terms as
    happened in Bluewater and Mainella.
    Plaintiffs contend that the NID is inconsistent with the
    FEIS with respect to how long the disturbed areas of the Parks
    would take to return to their original conditions.    In
    particular, the plaintiffs assert that the NID states that
    disturbed areas will “‘succeed to forest over time[,]’” but the
    FEIS states that these areas, including mature forests and
    wetlands, may not return to the previous condition.    Pls.’ Mem.
    at 31-32 (quoting NID at 6-9).   However, the NID is consistent
    with the FEIS because both documents reflect that certain
    disturbed areas would not be able to recover fully after
    construction.   Specifically, the NID concedes in each section
    cited by the plaintiffs that cleared areas within the right-of-
    way will result in permanent losses to vegetation, but that areas
    outside of the right-of-way and areas within the right-of-way
    that are not required for the operation of the S-R Line (such as
    the access roads and tower foundations) will be “allowed to
    - 39 -
    succeed to forested area over time.”    See NID at 6.    The NID
    states that the cleared areas in this project will be allowed to
    recover, but the NID does not contradict the FEIS because the NID
    does not claim that any mature forest will be restored to its
    original state within the 15-year period that the FEIS analyzed.
    See NID at 6; FEIS at 411 (AR 48272).    Further, the NID states
    that compensatory mitigation will restore impacted wetlands at a
    minimum acreage of 1 to 1 and that the project does not entail
    the conversion of wetland to non-wetland.    NID at 5.    Thus, NPS’
    non-impairment decision will be upheld because the plaintiffs
    have not shown that NPS acted arbitrarily and capriciously in
    concluding that the S-R Line project will not result in
    impairment of the Parks’ resources and values.
    Plaintiffs further argue that NPS did not provide a reasoned
    analysis for the approval of the special use permits and expanded
    right of way for the S-R Line in light of the significant adverse
    environmental impacts which would result from the construction.
    Pls.’ Mem. at 33-37.   In particular, plaintiffs argue that the
    ROD reflects that the agency based the decision to reject the no
    action alternative on “speculation[] about potential litigation”
    and that the agency was incorrect in its legal assessment.      Id.
    at 34.
    An agency’s decision may be rationally based on legal advice
    and analysis regarding contractual or easement matters.      See
    - 40 -
    Daingerfield Island Protective Soc’y v. Babbitt, 
    823 F. Supp. 950
    , 956-57 (D.D.C. 1993).     In Daingerfield, the district court
    reviewed the NPS’ decision to approve an interchange design.       
    Id. at 953
    .    The government had entered into a Land Exchange
    Agreement that granted a developer an easement to build an
    exchange that would have access to the George Washington Memorial
    Parkway.    
    Id. at 952
    .   NPS assessed the potential interchange
    designs and considered recommending that no interchange be built,
    but NPS was advised by counsel that the Land Exchange Agreement
    required that the interchange be built and that “the only choice
    left to NPS was to approve the least intrusive interchange
    possible, which it did, or to refuse to approve any interchange
    at all, which would have violated the Exchange Agreement that it
    had been informed was legally binding on the federal government.”
    
    Id. at 956
    .    The plaintiffs challenged NPS’ decision arguing that
    no interchange should have been built based on environmental
    concerns.    
    Id.
       The district court explained that “[w]here
    several administrative solutions exist for a problem, courts will
    uphold any one with a rational basis, so long as the balancing of
    competing solutions is not an arbitrary one.”     
    Id.
       Because the
    administrative record in Daingerfield reflected that NPS had
    evaluated the options and decided on the least intrusive design
    alternative, the NPS’ decision was upheld and the district
    court’s decision and rationale was affirmed by the D.C. Circuit.
    - 41 -
    Daingerfield Island Protective Soc’y v. Babbitt, 
    40 F.3d 442
    , 446
    (D.C. Cir. 1994).
    In this case, the feasibility of the no-action alternative
    lies at the center of this dispute.     The ROD explains that the no
    action alternative was not feasible because the utilities
    companies own a property interest in the existing right-of-way,
    upon which they could build a new line within the current right-
    of-way without NPS approval.   ROD at 18.   The plaintiffs contest
    the utilities companies’ rights under the easements and argue
    that the utilities companies were required to gain NPS approval
    even if they attempted to build the transmission line without an
    expanded right-of-way.   Specifically, the plaintiffs contend that
    NPS has the authority to prohibit the utilities companies from
    building the S-R Line within the existing right-of-way.    The
    plaintiffs state that the utilities companies may not use their
    easement in a way that would create a “high risk of fire” caused
    by insufficient clearance between the proposed S-R Line and the
    trees around the right-of-way.   Pls.’ Mem. at 34-35.   This legal
    dispute remains unresolved.9
    9
    The essence of the dispute is whether the utilities
    companies’ easements include the right to cut down and remove
    trees outside of the right-of-way on either side of the easement.
    The plaintiffs argue that the utilities companies do not have the
    right to remove trees outside of the right-of-way. Thus, the
    utilities companies cannot safely construct the new S-R Line
    within the existing right-of-way and NPS approval is required for
    any attempt to build the S-R Line within the existing right-of-
    way. Pl.’s Reply at 22-23. If true, that conclusion would
    - 42 -
    The question presented here is not whether the utilities
    companies could have built the S-R Line within the current right-
    of-way without NPS approval.   Instead, the narrow question
    presented here is whether NPS made a rational decision that the
    no action alternative was not feasible and that an alternative
    option was preferred.   Faced with “significant uncertainty” and a
    “strong probability” that the outcome -- either the unilateral
    building of the new transmission line within the intervenor-
    defendants’ right-of-way or future litigation regarding the
    easements and a potential takings claim -- would be “worse for
    park resources than the selected alternative[,]” NPS decided that
    the no action alternative was not feasible.   ROD at 18.   Much
    like in Daingerfield, NPS recognized that the best alternative
    for the environment was the no action alternative.   However, NPS
    considered in reaching its decision the legal analysis regarding
    whether the utilities companies could build the S-R Line without
    approval and the utilities companies’ statements that they
    intended to build the line without NPS approval.   Id.; see AR
    undermine NPS’ decision to reject the no action alternative.
    However, the utilities companies counter that the easements
    expressly release the utilities companies from any liability from
    trimming or cutting down trees that interfere with the
    transmission lines. Intervenor Defs.’ Mem. at 26-28. Thus, the
    utilities companies argue that they can clear vegetation on
    either side of the easement and avoid any risk of fire and can
    safely build the S-R Line without NPS approval. Intervenor
    Defs.’ Reply at 3-7. Further, the utilities companies state they
    have removed trees near the transmission line as recently as
    2010. 
    Id.
     at 5 n.3 (citing AR 77470).
    - 43 -
    28475-77; 77432-33.   NPS decided that the “least intrusive”
    option would be the best alternative.   While plaintiffs argue
    that the NPS’ authority over the utilities companies’ use of the
    easements is uncontroversial, this property dispute paired with
    the strong likelihood that the utilities companies would seek to
    continue construction of the transmission line, provided a
    rational basis for NPS to reject the no action alternative.    The
    plaintiffs have not shown that NPS’ decision was arbitrary and
    capricious and the defendants are entitled to summary judgment on
    the NPS Organic Act claim.
    III. WILD AND SCENIC RIVERS ACT
    The WSRA was implemented to protect and preserve the values
    of designated rivers in the United States.   See 
    16 U.S.C. § 1271
    .
    The WSRA states that each component of the wild and scenic rivers
    system “shall be administered in such manner as to protect and
    enhance the values which caused it to be included in said system
    without . . . limiting other uses that do not substantially
    interfere with public use and enjoyment of these values.”    
    16 U.S.C. § 1281
    (a).   Additionally, the WSRA provides that
    no department or agency of the United States shall
    assist by loan, grant, license, or otherwise in the
    construction of any water resources project that would
    have a direct and adverse effect on the values for
    which such river was established . . . . Nothing
    contained in the foregoing sentence, however, shall
    preclude licensing of, or assistance to, developments
    below or above a wild, scenic or recreational river
    area . . . which will not invade the area or
    unreasonably diminish the scenic, recreational, and
    - 44 -
    fish and wildlife values present in the area on the
    date of designation of a river as a component of the
    National Wild and Scenic Rivers System.
    
    16 U.S.C. § 1278
    (a).    The WSRA provides three classifications for
    rivers in the system: scenic, recreational and wild.        See 
    16 U.S.C. § 1273
    (b).   The portion of the river which the S-R Line
    will cross is designated as scenic.        See Publication of
    Classification Map for the Middle Delaware River, 
    45 Fed. Reg. 3396
     (Jan. 17, 1980).
    The plaintiffs allege that NPS’ decision to grant the
    permits and the expanded right-of-way was arbitrary and
    capricious because the NPS did not give “primary emphasis” to
    protecting the river, Compl. ¶ 102 (citing 
    16 U.S.C. § 1281
    (a)),
    and because the project qualified as a water resources project
    that would have a “direct and adverse effect on the values for
    which such river was established,”        Compl. ¶ 105 (quoting 
    16 U.S.C. § 1278
    (a).   The plaintiffs argue that the record reflects
    that the project violates the WSRA because construction would
    substantially interfere with the public use and enjoyment of the
    rivers.   Pls.’ Mem. at 37-38.    The defendants counter that,
    although the NPS acknowledged that the S-R Line will have some
    negative effects on the river’s scenic values, the S-R Line
    creates no substantial interference because most of the river
    view will remain unchanged and the NPS required measures to
    mitigate the detrimental impacts to riparian areas.        See
    - 45 -
    Intervenor Defs.’ Mem. at 38; Federal Defs.’ Mem. at 23-24
    (citing ROD at 13 (AR 116599)).
    In general, an agency’s assessment about whether an action
    substantially interferes with public use and enjoyment of the
    river’s values is entitled to deference.    See Rivers Unlimited v.
    U.S. Dep’t of Transp., 
    533 F. Supp. 2d 1
    , 5 (D.D.C. 2008); Hells
    Canyon Alliance v. U.S. Forest Serv., 
    227 F.3d 1170
    , 1178 (9th
    Cir. 2000).   Furthermore, “the mere existence of some decline in
    scenic value does not establish . . . substantial[]
    interfere[nce.]”   Hells Canyon Alliance, 
    227 F.3d at 1178
    .   In
    evaluating whether new construction or modifications would create
    a substantial interference, an agency may consider the existing
    structures and uses of a river, including those that pre-date the
    river’s protection under the WSRA.     See Rivers Unlimited, 
    533 F. Supp. 2d at 5
    .
    In this case, NPS acknowledged that “[t]he presence of the
    taller towers, thicker and more numerous lines, and bird
    diverters” will have an adverse impact upon visitors in the
    Parks.   ROD at 13 (AR 116599).   The FEIS discusses the adverse
    impacts resulting from the construction of the S-R Line in
    further detail as well.   See, e.g., FEIS at 695-96 (AR 48556-57)
    (considering the potential detrimental impacts of new
    construction on the river’s scenic value).    However, the NPS
    provided a reasonable basis for finding that the S-R Line will
    - 46 -
    not violate the WSRA by substantially interfering with the visual
    quality of the river.   The S-R Line will cross the river at the
    same place as the existing B-K Line does and the agency referred
    to the visual resources section which cited the use of neutral
    colored paints to reduce reflection and the use of monopoles
    rather than lattice towers as factors underlying their decision.
    NID at 12-13.   The NPS considered the extent to which the new
    towers and access roads would be visible within the Appalachain
    National Scenic Trail and the Delaware Water Gap National
    Recreation Area, identified the potential negative effects of the
    S-R Line and discussed measures to lessen its visual impact.     
    Id. at 12-13
    .   The agency’s consideration of potentially adverse
    consequences to public use and enjoyment of the river and its
    identification of methods to mitigate and avoid such effects
    demonstrate that its decision was not arbitrary and capricious.
    See Hells Canyon Alliance, 
    227 F.3d at 1178-79
    ; Rivers Unlimited,
    
    533 F. Supp. 2d at 5
    .   The agency therefore rationally determined
    that the S-R Line does not substantially interfere with the
    visual quality of the river.
    While the plaintiffs may disagree with NPS’ conclusion, they
    have not carried their burden of showing that the agency’s
    decision was arbitrary or capricious.   Thus, the plaintiffs’
    motion for summary judgment on the WSRA claims will be denied and
    - 47 -
    the defendants’ cross-motion for summary judgment will be
    granted.
    CONCLUSION
    The plaintiffs have not shown that NPS’ decisions in this
    case were arbitrary and capricious.    The defendants have shown
    that the agency’s decision is rationally based on the
    administrative record.   NPS’ actions will be upheld under each
    statute, the plaintiffs’ motion for summary judgment will be
    denied and the defendants’ cross-motions for summary judgment
    will be granted.   An appropriate Order accompanies this
    memorandum opinion.
    SIGNED this 30th day of August, 2013.
    /s/
    RICHARD W. ROBERTS
    Chief Judge
    

Document Info

Docket Number: Civil Action No. 2012-1690

Citation Numbers: 965 F. Supp. 2d 67

Judges: Chief Judge Richard W. Roberts

Filed Date: 8/30/2013

Precedential Status: Precedential

Modified Date: 8/31/2023

Authorities (35)

National Wildlife Federation v. John O. Marsh, Secretary of ... , 721 F.2d 767 ( 1983 )

Sierra Club v. Van Antwerp , 526 F.3d 1353 ( 2008 )

Natl Com New Riv Inc v. FERC , 373 F.3d 1323 ( 2004 )

Russell Country Sportsmen v. US Forest Service , 668 F.3d 1037 ( 2011 )

environmental-defense-fund-and-louisville-nashville-railroad-company-and , 651 F.2d 983 ( 1981 )

hells-canyon-alliance-v-united-states-forest-service-michael-dombeck , 227 F.3d 1170 ( 2000 )

Tripoli Rocketry v. Bur ATF , 437 F.3d 75 ( 2006 )

TOMAC v. Norton, Gale A. , 433 F.3d 852 ( 2006 )

THEODORE ROOSEVELT CONSERVATION v. Salazar , 616 F.3d 497 ( 2010 )

City of Alexandria, Virginia,appellees v. Rodney E. Slater, ... , 198 F.3d 862 ( 1999 )

citizens-against-burlington-inc-v-james-b-busey-iv-administrator , 938 F.2d 190 ( 1991 )

Sierra Club v. Van Antwerp , 661 F.3d 1147 ( 2011 )

Duncan's Point Lot Owners Ass'n v. Federal Energy ... , 522 F.3d 371 ( 2008 )

Paul Davis Iii,appellants v. John Latschar, Superintendent, ... , 202 F.3d 359 ( 2000 )

Public Citizen, Inc., Aviation Consumer Action Project, and ... , 988 F.2d 186 ( 1993 )

Nat Resrc Def Cncl v. Daley, William M. , 209 F.3d 747 ( 2000 )

Alpharma Inc v. Leavitt, Michael , 460 F.3d 1 ( 2006 )

City of Olmsted Falls, Ohio v. Federal Aviation ... , 292 F.3d 261 ( 2002 )

midtec-paper-corporation-v-united-states-of-america-and-interstate , 857 F.2d 1487 ( 1988 )

Pettiford v. Secretary of the Navy , 774 F. Supp. 2d 173 ( 2011 )

View All Authorities »