Phillips v. Mabus , 894 F. Supp. 2d 71 ( 2012 )


Menu:
  •                    UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    )
    SEBASTIAN PHILLIPS, et. al,     )
    )
    Plaintiffs,     )
    ) Civil Action No. 11-2021 (EGS)
    v.                    )
    )
    RAYMOND E. MABUS, et. al,       )
    )
    Defendants.     )
    )
    MEMORANDUM OPINION
    Plaintiffs, Sebastian Phillips and the company he owns,
    Marine Design Dynamics, Inc. (hereinafter “MDD”), bring suit
    against various officials in the United States Navy as well as
    certain of MDD’s former employees.   Plaintiffs allege they were
    effectively debarred from government contracting with the Navy
    without notice and a hearing, in violation of their Fifth
    Amendment due process rights.   Plaintiffs also allege a variety
    of common law causes of action against MDD’s former employees as
    well as two government employees.    When this case was initially
    filed plaintiffs moved for a temporary restraining order and
    preliminary injunction against the federal defendants, seeking
    to enjoin them from de facto debarring MDD from government
    contracting.   On December 7, 2011, following a hearing on
    plaintiffs’ emergency motions, the plaintiffs and federal
    defendants agreed and stipulated to a consent preliminary
    injunction.   Now pending before the Court are (1) the federal
    defendants’ motion to dismiss, or in the alternative for summary
    judgment, (2) plaintiffs’ motion to enforce the consent
    preliminary injunction, and (3) motions to dismiss filed by
    three of plaintiffs’ former employees.     Upon consideration of
    the motions, the responses, and the replies thereto, the
    relevant caselaw and the record in this case as a whole, the
    motions will be DENIED.
    I.   FACTUAL AND PRODCEDURAL BACKGROUND1
    Plaintiff Marine Design Dynamics, Inc., a District of
    Columbia-based government contractor, is a Naval Architecture
    firm specializing in ship energy conservation for the Navy and
    other government clients.   In 2006, MDD began working as a
    subcontractor to Computer Sciences Corporation (“CSC”),
    performing work under CSC’s SeaPort e-prime contract with the
    Naval Sea Systems Command of the Department of the Navy
    (“NAVSEA”), contract number N001788-04-D-4030-EHO2.    Under CSC’s
    NAVSEA contract, MDD performed work for the Navy’s Operational
    Logistics Integration Program (“OPLOG”) at its Carderock
    1
    For purposes of ruling on a motion to dismiss, the factual
    allegations must be presumed true and liberally construed in
    favor of the plaintiff. Scheuer v. Rhodes, 
    416 U.S. 232
    , 236
    (1974); Sparrow v. United Air Lines, Inc., 
    216 F.3d 1111
    , 1113
    (D.C. Cir. 2000). Therefore, unless stated otherwise, the facts
    set forth herein are taken from the Amended Complaint and its
    accompanying exhibits.
    2
    facility.    From 2006 through 2011, all the work MDD performed
    for OPLOG was pursuant to this arrangement under the CSC
    contract.    This work comprised most of MDD’s government
    contracting work, and plaintiffs derive all of their revenue and
    income from government contracting.
    In November 2009, MDD entered into a second contract, this
    time as a prime contractor for the Navy, to provide engineering
    and program management services to the energy conservation
    program for the Combat Logistic Force ships of the Military
    Sealift Command (“MSC”).    That contract, number N00033-10-802,
    specified a one year term, with an option for MSC to renew for
    two additional years, until November 2012.
    Between March and July of 2011, four key MDD employees who
    had performed significant work on the OPLOG projects - Michael
    Mazzocco, Volker Stammnitz, William Muras and Matthew Miller -
    left MDD.    Plaintiffs allege that before leaving MDD, each of
    the key employees solicited OPLOG management and arranged to
    take the work they were performing for MDD with them when they
    left.    At least two of the departing employees, Mazzocco and
    Stammnitz, formed their own businesses to compete with MDD.
    Plaintiffs allege that after leaving MDD, all four former
    employees did, in fact, continue to perform the same work for
    OPLOG as they had performed at MDD.    In addition, Mazzocco
    allegedly spread rumors that MDD was double or triple billing
    3
    the government for its work.   Plaintiffs claim these rumors are
    false, and that moreover, they have not been given formal notice
    of the rumors or an opportunity to respond to them.
    Nevertheless, as a result of the rumors, the government began to
    deny plaintiffs work.   First, on April 13, 2011, plaintiffs were
    notified that OPLOG manager Charles Traugh was “pulling back”
    $700,000 of OPLOG work previously budgeted for MDD, under the
    CSC contract, in FY 2011.   Plaintiffs allege that this $700,000
    was reallocated to others, including Mazzocco, Stammnitz, Muras,
    and Miller, who received the money after leaving MDD.
    Shortly thereafter, on or about May 18, 2011, Mazzocco,
    Stammnitz, and Muras met in Boston with NAVSEA and OPLOG
    employees, including NAVSEA Chief Technology Officer Michael
    Bosworth, OPLOG program manager Traugh, and assistant program
    manager William Robinson.   Plaintiffs allege that during that
    meeting, Bosworth and Traugh, working with Mazzocco, Stammnitz
    and Muras, decided to eliminate MDD entirely from the OPLOG
    budget in Fiscal Year (“FY”) 2012, and redirect plaintiffs’ work
    to the departing or already departed MDD employees.   Plaintiffs
    allege that OPLOG’s FY 2012 budget, developed by Traugh and
    Robinson, had included a minimum of $2.7 million for MDD.
    During a meeting to review the OPLOG program on July 13,
    2011, Bosworth implemented the decisions reached at the May 2011
    meeting in Boston.   He instructed Traugh that OPLOG was to
    4
    immediately cease giving any OPLOG work to plaintiffs, and to
    continue the moratorium through at least FY 2012.   On July 28,
    2011, Traugh met with plaintiff Phillips and informed him that
    OPLOG would not be tasking work to MDD for FY 2012 under the CSC
    prime contract or any existing prime contract.   Plaintiffs
    allege that they have been awarded no new work at OPLOG, through
    the CSC contract or any other contract, since July 2011.
    Without any work to perform at OPLOG, MDD attempted to get
    additional work through other components of the Navy.
    Specifically, plaintiffs attempted to obtain work as a
    subcontractor to Gryphon Technologies, which has a prime
    contract with NAVSEA.   See Am. Compl. Exhibits O, P, Q; see also
    Fed. Defs.’ Mot. to Dismiss or in the Alternative for Summ. J.,
    Ex. C, Decl. of Kevin D. Baetsen (“Baetsen Decl.”), Exs. 1-3.
    MDD’s ability to obtain this work, however, was subject to
    NAVSEA appointing a government employee to serve as a Technical
    Point of Contact (“TPOC”).   Initially, Tom Martin, director of
    the energy office at NAVSEA headquarters, agreed to serve as
    TPOC, but later informed other Navy personnel that he could not
    do so because he had been informed that there were problems
    “tracking the money” MDD had charged the government for its
    OPLOG work.   Martin explained that he had been “directed by
    [his] leadership not to be involved with any contract that
    includes MDD,” regardless of whether the contract was to perform
    5
    OPLOG work or work for a different component of the Navy.       Am.
    Complaint ¶¶ 87, 89 (quoting Oct. 7, 2011 email from T. Martin).
    Finally, MDD alleges that the defendants attempted to
    interfere with its existing contract with MSC (contract number
    N00033-10-802) before it was renewed for FY 2012 by, inter alia,
    attempting to divert work under that contract to former MDD
    employees.   These alleged attempts were unsuccessful; in the
    fall of 2011, MSC exercised its final one-year option on its
    contract with MDD, which will expire in November 2012.    Baetsen
    Decl. ¶ 4.
    On November 16, 2011, Plaintiffs initiated this suit
    against several Navy officials as well as the four former MDD
    employees discussed above.   Plaintiffs moved for a temporary
    restraining order and preliminary injunction against the federal
    defendants only, alleging plaintiffs had been de facto debarred
    from government contracting without notice and a hearing in
    violation of their fifth amendment right to due process of law.
    Pls.’ Mot. for Temp. Rest. Order at 4-5.    Following briefing on
    the motion, the Court held a hearing on December 7, 2011.       At
    the hearing’s conclusion, the parties agreed and stipulated to
    the entry of a preliminary injunction.     See Order Granting
    Stipulated Prelim. Inj.; see also Minute Order of Dec. 7, 2012.
    In relevant part, the Stipulated Preliminary Injunction (1)
    enjoined the government from taking any additional action to
    6
    implement or spread the de facto debarment, (2) required the
    Navy to allow MDD to compete for new work and to continue
    performing contracts it was currently performing under the same
    standards applicable to other contractors, and (3) required the
    Navy to communicate the foregoing information to CSC and
    Gryphon.   See 
    Id.
    Following the preliminary injunction proceedings,
    Plaintiffs filed an Amended Complaint.   Count I asserts that the
    federal defendants violated plaintiffs’ constitutional right to
    due process by blacklisting them for government contracting
    without procedural safeguards, and seeks declaratory and
    injunctive relief.   Count II asserts the same claims against
    Bosworth and Traugh in their individual capacities and seeks
    damages of $2.5 million.   Counts III – VIII assert breach of
    fiduciary duty and civil conspiracy against Mazzocco, Stammnitz,
    Muras, and Miller, and common law defamation against Mazzocco.
    Finally, Count IX alleges common law interference with
    contractual relations by Traugh and Robinson in their official
    and individual capacities.   The federal defendants, as well as
    Mazzocco, Stammnitz, and Muras have moved to dismiss the Amended
    Complaint; the federal defendants have also moved in the
    alternative for summary judgment.    Plaintiffs, for their part,
    have filed a motion to enforce the preliminary injunction.
    These motions are ripe for resolution by the Court.
    7
    II.   STANDARD OF REVIEW2
    On a motion to dismiss for lack of subject-matter
    jurisdiction under Rule 12(b)(1), the plaintiff bears the burden
    of establishing that the court has subject-matter jurisdiction.
    Lujan v. Defenders of Wildlife, 
    504 U.S. 555
    , 561 (1992).      “The
    court must address the issue of jurisdiction as a threshold
    matter, because absent jurisdiction the court lacks the
    authority to decide the case on any other grounds.”    Am. Farm
    Bureau v. EPA, 
    121 F. Supp. 2d 84
    , 91 (D.D.C. 2000).      Moreover,
    because subject-matter jurisdiction relates to the Court’s power
    to hear the claim, the Court must give the plaintiff’s factual
    allegations closer scrutiny when resolving a Rule 12(b)(1)
    motion than would be required for a Rule 12(b)(6) motion.
    Uberoi v. EEOC, 
    180 F. Supp. 2d 42
    , 44 (D.D.C 2001).      In
    resolving a motion to dismiss for lack of subject-matter
    jurisdiction, the Court “may consider the complaint supplemented
    by undisputed facts evidenced in the record, or the complaint
    supplemented by undisputed facts plus the court’s resolution of
    disputed facts.”   Coal. For Underground Expansion v. Mineta, 
    333 F.3d 193
    , 198 (D.C. Cir. 2003) (internal citations and quotation
    marks omitted).
    2
    This section addresses the standard of review for the motions
    to dismiss, or in the alternative for summary judgment. The
    standard of review for plaintiff’s motion for enforcement of the
    stipulated preliminary injunction is addressed infra.
    8
    A motion to dismiss under Federal Rule of Civil Procedure
    12(b)(6) tests the legal sufficiency of a complaint. Browning v.
    Clinton, 
    292 F.3d 235
    , 242 (D.C. Cir. 2002). A complaint must
    contain “a short and plain statement of the claim showing that
    the pleader is entitled to relief, in order to give the
    defendant fair notice of what the ... claim is and the grounds
    upon which it rests.” Bell Atl. Corp. v. Twombly, 
    550 U.S. 544
    ,
    555 (2007) (internal quotation marks and citations omitted).
    While detailed factual allegations are not necessary, plaintiff
    must plead enough facts “to raise a right to relief above the
    speculative level.” 
    Id.
    When ruling on a Rule 12(b)(6) motion, the Court may
    consider “the facts alleged in the complaint, documents attached
    as exhibits or incorporated by reference in the complaint, and
    matters about which the Court may take judicial notice.”
    Gustave-Schmidt v. Chao, 
    226 F. Supp. 2d 191
    , 196 (D.D.C. 2002).
    The Court must construe the complaint liberally in plaintiff’s
    favor and grant plaintiff the benefit of all reasonable
    inferences deriving from the complaint. Kowal v. MCI Commc’ns
    Corp., 
    16 F.3d 1271
    , 1276 (D.C. Cir. 1994). However, the Court
    must not accept plaintiff’s inferences that are “unsupported by
    the facts set out in the complaint.” 
    Id.
     “[O]nly a complaint
    that states a plausible claim for relief survives a motion to
    dismiss.” Ashcroft v. Iqbal, 
    556 U.S. 662
    , 679 (2009).
    9
    Summary judgment is appropriate “if the movant shows that
    there is no genuine dispute as to any material fact and the
    movant is entitled to judgment as a matter of law.” Fed. R. Civ.
    P. 56(a); see Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 248
    (1986). Though the Court must draw all justifiable inferences
    in favor of the non-moving party in deciding whether there is a
    disputed issue of material fact, “[t]he mere existence of a
    scintilla of evidence in support of the [non-movant]’s position
    will be insufficient; there must be evidence on which the jury
    could reasonably find for the [non-movant].” Anderson, 
    477 U.S. at 252
    .
    III. ANALYSIS
    A. Federal Defendants’ Motion to Dismiss, or, in the
    Alternative, for Summary Judgment
    The federal defendants move to dismiss plaintiffs’ claims
    against them in Counts I, II, and IX of the Amended Complaint
    for lack of jurisdiction and failure to state a claim upon which
    relief can be granted.   In the alternative, the federal
    defendants argue that summary judgment should be granted on
    Counts I and II.
    1. Sovereign Immunity
    Federal defendants argue that sovereign immunity bars
    plaintiff’s claims in Count I against the federal defendants in
    their official capacities.   Fed. Defs.’ Mot. to Dismiss or for
    10
    Summ. J. at 4-8 (hereinafter “Fed. Defs.’ Mem.”).    The
    plaintiffs contend that the government has waived sovereign
    immunity for claims seeking non-monetary relief against the
    United States, its agencies and federal officers acting in an
    official capacity.    Pls.’ Opp’n to Fed. Defs.’ Mot. to Dismiss
    at 27-28.    Plaintiffs are correct.   See 
    5 U.S.C. § 702
    ; see also
    P&V Enters. v. United States Army Corps of Eng’rs, 
    466 F. Supp. 2d 134
    , 140-41 (D.D.C. 2006).    In Count I of the Amended
    Complaint, plaintiffs seek only declaratory and injunctive
    relief, and their claims are against federal officers in their
    official capacities.3   Accordingly, the waiver of sovereign
    immunity found in Section 702 of the APA applies to plaintiffs’
    claims against the federal defendants.
    2. Sufficiency of Plaintiffs’ Claims that a De Facto
    Debarment Occurred
    Federal defendants also argue that plaintiffs cannot show
    the government’s actions constituted de facto debarment in
    violation of the due process clause of the Fifth Amendment.
    Fed. Defs.’ Mem. at 27-31.    Defendants principally argue that no
    de facto debarment occurred for two reasons:    (1) because MSC
    exercised an option on its contract with MDD on October 30,
    3
    For the same reasons, federal defendants’ assertion that
    plaintiffs may not allege Bivens claims against Mabus, Greenert,
    McCoy and Kaskin for the actions of Bosworth and Traugh on a
    theory of respondeat superior is irrelevant. Fed. Defs.’ Mem.
    at 15-17. Plaintiffs do not bring Bivens claims against these
    four federal defendants. See Pls.’ Opp’n at 30.
    11
    2011, which provided work for MDD until late 2012, plaintiffs
    did not lose all of their government work and accordingly were
    not debarred; and (2) in order to give rise to Fifth Amendment
    protections, de facto debarment must be based on charges of a
    lack of integrity, which, according to federal defendants,
    plaintiffs do not allege.
    De facto debarment occurs when a contractor has, for all
    practical purposes, been suspended or blacklisted from working
    with a government agency without due process, namely, adequate
    notice and a meaningful hearing.      Trifax Corp. v. Dist. of
    Columbia, 
    314 F.3d 641
    , 643-44 (D.C. Cir. 2003); TLT Constr.
    Corp. v. United States, 
    50 Fed. Cl. 212
    , 215 (2001).     To
    demonstrate de facto debarment, plaintiffs must show “a
    systematic effort by the procuring agency to reject all of the
    bidder’s contract bids.   Two options exist to establish a de
    facto debarment claim:    1) by an agency’s statement that it will
    not award the contractor future contracts; or 2) by an agency’s
    conduct demonstrating that it will not award the contractor
    future contracts.”   TLT Constr., 50 Fed. Cl. at 215-16 (internal
    citations and quotations omitted).
    Plaintiffs argue that they have adequately alleged both of
    these options, although they need allege only one to survive a
    motion to dismiss.   Pls.’ Opp’n at 11.    First, Plaintiffs
    allege, and defendants do not dispute that two Navy officials,
    12
    Traugh and Bosworth, stated they would not permit plaintiffs to
    work on any future contracts.   Am. Compl. ¶¶ 79-84; see also
    Fed. Defs.’ Mem. Ex. A, Traugh Decl. at ¶ 8 (“I decided, with
    Mr. Bosworth’s concurrence, that OPLOG would no longer use MDD
    as a subcontractor starting with work funded from FY 2012
    appropriations.”); Ex. B., Bosworth Decl. at ¶ 7 (“I . . .
    directed Charles Traugh . . . not to renew the association of
    OPLOG with MDD starting in FY 2012.”)   Plaintiffs allege that
    these statements applied to their attempts to receive work at
    OPLOG as well as other components of the Navy, as demonstrated
    by NAVSEA employee Tom Martin’s statement that “I have been
    directed by my leadership not to be involved with any contract
    that includes MDD,” even if the contract had nothing to do with
    OPLOG.   Am. Compl. ¶ 89.
    Plaintiffs also argue they have alleged a de facto
    debarment by the agency’s conduct: namely, the Navy has taken
    away MDD’s existing work and refused to permit MDD to obtain
    additional work in several instances.   First, in April 2011, the
    Navy “pulled back” $700,000 that had been allocated to MDD for
    subcontracting work with CSC during FY 2011.   Am. Compl. ¶¶ 56-
    57.   Next, in July 2011 the Navy announced its intention not to
    award MDD any more work under the CSC prime contract and to
    prohibit MDD from receiving any more work from OPLOG under any
    contract through FY 2012.   Id. ¶¶ 73-74, 78-79.   Plaintiffs
    13
    allege they have received no new work from OPLOG since summer
    2011.     Id. ¶ 83.    Third, the Navy also indicated, via emails
    dated September 15, 2011 and October 7, 2011, that MDD would not
    get any funding on any future contract or subcontract, whether
    through OPLOG or NAVSEA.       Id. ¶¶ 87-92.   The Navy also refused
    to appoint a TPOC, which is a condition precedent to obtaining
    this work.     Id.    Finally, Plaintiffs allege that federal
    defendants attempted to stop – albeit unsuccessfully –
    plaintiffs from performing the final year of work on plaintiffs’
    single remaining contract to perform work for the Navy.         Id. ¶
    94.   Plaintiffs allege that “all of their revenue and income
    derive from Federal Government contracts, primarily OPLOG and
    MSC contracts,” and that defendants’ actions threaten to put
    plaintiffs out of business.      Id. ¶ 95.
    The Court agrees that plaintiffs have met their burden to
    allege a de facto debarment sufficient to survive a motion to
    dismiss.    First, plaintiffs have alleged multiple Navy officials
    stated that plaintiffs would not be awarded any future
    contracts.    As noted above, courts have found categorical
    statements that contractors will not be awarded any future
    contracts may amount to a de facto debarment.        See TLT Constr.
    Corp., 50 Fed. Cl. at 215; see also CRC Marine Servs. v. United
    States, 
    41 Fed. Cl. 66
    , 84 (1988)(a contractor may allege de
    facto debarment by evidence of statements, by agency officials
    14
    or employees, that he would not be awarded any contract at the
    present or in the future); Related Indus., Inc. v. United
    States, 
    2 Cl. Ct. 517
    , 525 (1983)(same).
    Second, plaintiffs have alleged that the agency’s conduct
    amounts to a systematic effort to preclude it from future
    contracting.   In Art-Metal USA, Incorporated v. Solomon, this
    Court found that de facto debarment occurred when the government
    terminated one of the movant’s contracts in its entirety and
    held in abeyance the awards of four additional contracts for
    which the contractor had submitted bids.   The plaintiff did not
    have to prove that it had lost 100% of its work to show de facto
    debarment; it was sufficient to show that the government’s
    actions were aimed at the overall status of the plaintiff as a
    contractor, specifically at plaintiff receiving new contracts.
    
    473 F. Supp. 1
    , 4, 5 n.7 (D.D.C. 1978).    Similarly, in Leslie &
    Elliott Company v. Garrett, this court found de facto debarment
    when the Navy refused to award plaintiff two contracts for which
    it had been the lowest bidder because the evidence showed the
    Navy “had determined that it should no longer do business with”
    the contractor at the submarine base.   
    732 F. Supp. 191
    , 196
    (D.D.C. 1990).   Likewise, this Circuit has found that de facto
    debarment may lie where there has been exclusion from “virtually
    all government work for a fixed period of time,” Reeve Aleutian
    Airways, Incorporated v. United States, 
    982 F.2d 594
    , 598 (D.C.
    15
    Cir. 1993) (citations and quotations omitted); or where the
    government’s conduct “has the broad effect of largely precluding
    [plaintiffs] from pursuing” government work. Trifax Corp., 
    314 F.3d at 644
     (citation omitted).
    Defendants contend that plaintiffs cannot show a de facto
    debarment as a matter of law because plaintiffs “were
    subsequently awarded work by the alleged debarring agency;”
    namely, on October 30, 2011, MSC exercised the final option of a
    three-year contract with MDD.   The MSC contract, which was
    initially awarded in 2009, will expire in November 2012.   Fed.
    Defs.’ Mot. at 27-28, Baetsen Decl. ¶ 4.4
    The present record is cloudy as to the extent of the Navy’s
    disqualification of plaintiffs.    The facts currently before the
    court do not reveal whether MSC’s exercise of the final option
    of its three year contract with MDD is tantamount to a new or
    “future” contract awarded after the alleged debarment, or, in
    the alternative, is effectively a continuation of a contract
    awarded in 2009, well before the alleged debarment.   Ultimately,
    4
    Defendants point out that, under the Federal Acquisition
    Regulations, agencies may not exercise options on current
    contracts with contractors that have been debarred absent
    compelling circumstances. Fed. Defs.’ Reply at 9 (citing 
    48 C.F.R. § 9-405-1
    (b)(3)). This provision is not dispositive
    here, as it only governs contractors who have been officially
    debarred. Plaintiffs here have alleged de facto debarment,
    which rests on the claim that defendants have ignored their own
    regulations and are instead engaged in an unauthorized effort to
    preclude them from receiving future work.
    16
    development of these facts may be dispositive as to the de facto
    debarment claim.   However, at the motion to dismiss stage, when
    the Court must view all facts in the light most favorable to
    plaintiffs, the statements and actions alleged in the Amended
    Complaint make out a plausible claim to de facto debarment.
    While plaintiffs have not lost 100% of their contracting work,
    they have plausibly claimed that they have been barred from
    performing work on several contracts and thus have been broadly
    precluded from future work with the Navy.   Courts have often
    found that, while “[p]reclusion from a single contract is
    insufficient to establish de facto debarment,” an allegedly
    broad based preclusion across multiple contracts (or, in this
    case, subcontracts) gives rise to a viable claim for de facto
    debarment.   Highview Eng’g, Inc. v. United States Army Corps. of
    Eng’rs, Case 3:08-647, 
    2012 U.S. Dist. LEXIS 45249
    , *20 (W.D.
    Ky. Mar. 30, 2012)(collecting cases); see also Leslie & Elliott
    Co., 
    732 F. Supp. at 197
    ; Art-Metal, 
    473 F. Supp. at 5
    .
    Accordingly, the Court concludes that plaintiffs have stated a
    claim of de facto debarment sufficient to survive a motion to
    dismiss.
    The Court likewise rejects the federal defendants’ claim
    that plaintiffs have not asserted a de facto debarment claim
    because they have not alleged they were barred from government
    contracting due to charges of fraud, dishonesty, or lack of
    17
    integrity.   As this Circuit has held, individuals and
    corporations have a due process liberty interest in avoiding the
    damage to their reputation and business caused by the stigma of
    broad preclusion from government contracting.     Reeve, 
    982 F.2d at 598
    ; see also Trifax, 
    314 F.3d at 643-44
    .    Assuming arguendo
    that the broad preclusion from contracting must be based on
    charges of fraud, dishonesty, or lack of integrity in order to
    give rise to a protected liberty interest, the Court finds
    plaintiffs have alleged such charges in this case.
    Specifically, plaintiffs have alleged Bosworth and Traugh
    decided to bar them from Navy work because of rumors that
    plaintiffs were submitting fraudulent bills to the government.
    Am. Compl. ¶¶ 52, 87-93.   Indeed, Bosworth and Traugh provided
    declarations in support of the government’s motion to dismiss
    stating that they decided to stop working with plaintiffs
    because of their “lack of transparency.”   Fed. Defs.’ Mem.,
    Decl. of Charles Traugh at ¶ 8.    Traugh and Bosworth assert that
    MDD’s invoices did not contain sufficient information “to
    evaluate whether the price [the Navy] paid for [MDD’s] work was
    reasonable” and, despite repeated requests for more detail, MDD
    refused to provide additional information.     Id. at ¶¶ 6-7; see
    also Fed. Defs.’ Mem., Decl. of Michael Bosworth at ¶¶ 4-5.
    Defendants’ own statements confirm that concerns about
    18
    plaintiffs’ honesty and integrity animated the decision to stop
    them from performing more government work.
    3. Standing and Mootness
    In their reply, defendants argue for the first time that
    plaintiffs lack standing under Article III.    Fed. Defs.’ Reply
    at 2.    To satisfy Article III's standing requirements, a
    plaintiff must show that, at the time the suit is filed,
    (1) [he] has suffered an "injury in fact" that is (a)
    concrete and particularized and (b) actual or imminent, not
    conjectural or hypothetical; (2) the injury is fairly
    traceable to the challenged action of the defendant; and
    (3) it is likely, as opposed to merely speculative, that
    the injury will be redressed by a favorable decision.
    Friends of the Earth, Inc. v. Laidlaw Envtl. Servs., Inc., 
    528 U.S. 167
    , 180-81 (2000).     While the proof required to establish
    standing increases as the suit proceeds, at the motion to
    dismiss stage “general factual allegations of injury resulting
    from the defendant’s conduct may suffice.”     Lujan v. Defenders
    of Wildlife, 
    504 U.S. 555
    , 561 (1992) (internal citations and
    quotation marks omitted).
    Reprising their arguments that plaintiffs have not been de
    facto debarred as a matter of law, the federal defendants claim
    plaintiffs have suffered no “injury in fact because they were
    not de facto debarred.”     Fed. Defs.’ Reply at 2.   For the
    reasons explained above, plaintiffs have stated a claim for de
    facto debarment.     The Court also rejects federal defendants’
    19
    claim that plaintiffs cannot show injury in fact because they
    have not presented evidence “that they attempted to get future
    contracts” after the alleged debarment, but “were prevented from
    doing so.”   Id. at 5.    A claim of de facto debarment may be
    justiciable absent the formality of plaintiffs bidding on and
    being denied future contracts after the alleged debarment.       See
    Dynamic Aviation v. Dep’t of Interior, 
    898 F. Supp. 11
    , 13
    (D.D.C. 1995) (where possession of pilot and aviation
    credentials was a condition precedent to performing government
    work, and plaintiff’s credentials had been revoked, plaintiff
    need not show he had bid on government work after the revocation
    to present a justiciable controversy).    In this case, Plaintiffs
    allege that as a result of their de facto debarment, they lost
    $700,000 of work they had already been allocated in FY 2011,
    over $2.5 million of future work which had been set aside for
    MDD in OPLOG’s FY 2012 budget, and an additional future
    subcontract with Gryphon Technologies.    These alleged losses
    clearly constitute an injury in fact for the purposes of Article
    III standing.
    Defendants also argue that plaintiffs’ injuries are not
    redressable because, even if they were de facto debarred, they
    are not currently entitled to receive any contract work.    Fed.
    Defs.’ Reply at 7-9.     As discussed supra, this argument is
    premature; plaintiffs have alleged that they lost work to which
    20
    they were entitled, which is all that is required at the
    pleading stage.   Lujan, 
    504 U.S. at 561
    .    Moreover, even
    assuming arguendo defendants are correct, this does not
    necessarily deprive plaintiffs of standing to seek prospective
    injunctive or declaratory relief.    Indeed, plaintiffs have
    already received a preliminary injunction which, inter alia,
    enjoins defendants from taking any further action to preclude
    plaintiffs from contracting, and rescinds certain actions they
    had taken to that effect.   This injunction, however, only
    remains in place pending a final determination of the merits of
    the action.   13 James Wm. Moore, et. al, Moore’s Federal
    Practice, § 65.20 (3d ed. 1997).     Moreover, plaintiffs have
    alleged a likelihood of future violations of their rights by the
    defendants, and accordingly have standing to pursue a
    declaratory judgment.   Am. Compl. ¶¶ 83, 89, 95, 98; see also
    Fair Employment Council of Greater Washington v. BMC Mktg.
    Corp., 
    28 F.3d 1268
    , 1273 (D.C. Cir. 1994).
    Finally, the complaint is not moot.     Federal defendants’
    mootness argument rests solely on the assertion that they have
    taken action to change their conduct after the lawsuit was
    filed, mainly, that they have complied with the consent
    Stipulated Preliminary Injunction.    Fed. Defs.’ Reply at 9-10.
    Defendants cannot rely on their voluntary cessation of the
    challenged conduct as a basis for mootness unless “subsequent
    21
    events made it absolutely clear that the allegedly wrongful
    behavior could not reasonably be expected to recur.”      Friends of
    the Earth, 
    528 U.S. at 189
     (citations omitted).    Defendant has
    provided no evidence on this point; indeed, notwithstanding the
    preliminary injunction, the declarations of Charles Traugh and
    Michael Bosworth do not indicate that OPLOG or NAVSEA will
    consider plaintiffs for any future work.   Accordingly,
    defendants have not satisfied their “heavy burden of persuading”
    the court that the challenged conduct cannot reasonably be
    expected to recur.    Id.
    4. Federal Tort Claims Act
    In Count IX of the Amended Complaint, plaintiffs allege
    Traugh and Robinson tortiously interfered with their contractual
    relations, their prospective contractual relations, and their
    prospective advantageous relationships.    Specifically, they
    allege that Traugh and Robinson:
       Induced MDD’s key employees to breach their fiduciary
    duties to MDD, by taking its work and its business
    opportunities;
       Prevented MDD from performing task orders under the
    CSC contract, and redirected funds allocated for MDD
    under that contract;
       Interfered with other contracts of MDD’s, such as its
    contract with the MSC;
       Published defamatory statements about MDD to injure
    plaintiffs in their trade or business.
    Am. Compl. ¶ 195.    In response, the federal defendants filed a
    certification pursuant to the Westfall Act, 29 U.S.C § 2679,
    22
    stating that Traugh and Robinson were acting within the scope of
    their employment during the incidents alleged by plaintiffs, and
    that the United States should therefore be substituted as sole
    defendant in lieu of Traugh and Robinson.   The federal
    defendants then moved to dismiss Count IX, arguing that
    plaintiffs’ claims against the United States are excluded from
    the Federal Tort Claims Act’s (“FTCA”) waiver of sovereign
    immunity and that plaintiffs failed to exhaust their
    administrative remedies under the FTCA.   In their opposition to
    defendants’ motion, plaintiffs have requested discovery in order
    to contest whether Traugh’s and Robinson’s actions were, in
    fact, within the scope of their employment.   For the following
    reasons, the Court concludes that plaintiffs have met their
    burden to obtain limited discovery on the scope of Robinson’s
    and Traugh’s employment.
    The Westfall Act provides that federal officials are immune
    from state tort lawsuits for money damages if the employee was
    “acting within the scope of employment during the alleged
    incident.”    Haddon v. United States, 
    68 F.3d 1420
    , 1422-23 (D.C.
    Cir. 1995).
    Upon certification by the Attorney General that the
    defendant employee was acting within the scope of his
    office or employment at the time of the incident out of
    which the claim arose, any civil action or proceeding
    commenced upon such a claim in a United States district
    court shall be deemed an action against the United States .
    23
    . . . and the United States shall be substituted as the
    party defendant.
    
    28 U.S.C. § 2679
    (d)(1).     The Attorney General’s certification
    constitutes prima facie evidence that the employee was acting
    within the scope of his employment, and once the certification
    has been made, the plaintiff challenging the certification has
    the burden of “alleging facts that, if true, would establish
    that the defendants were acting outside the scope of their
    employment.”     Stokes v. Cross, 
    327 F.3d 1210
    , 1215 (D.C. Cir.
    2003).   As this Circuit has explained, “if a plaintiff meets
    this pleading burden, he may, if necessary, attain limited
    discovery to resolve any factual disputes over jurisdiction.”
    Wuterich v. Murtha, 
    562 F.3d 375
    , 381 (D.C. Cir. 2009) (internal
    citations omitted); see also Stokes, 
    327 F.3d 1210
    , 1213 (the
    certification does not have “any particular evidentiary weight,”
    therefore, if plaintiff alleges “a material dispute as to the
    scope issue, the district court must resolve it[.]” (internal
    citations omitted)).
    In order to determine whether a federal employee was acting
    within the scope of his employment, the Court must apply the law
    in the state in which the alleged tort occurred.      
    Id. at 1214
    .
    District of Columbia law is drawn from the Restatement (Second)
    of Agency.     
    Id.
       The Restatement provides in pertinent part:
    Conduct of a servant is within the scope of employment if,
    but only if, (a) it is of the kind he is employed to
    24
    perform; (b) it occurs substantially within the authorized
    time and space limits; (c) it is actuated, at least in
    part, by a purpose to serve the master; and (d) if force is
    intentionally used by the servant against another, the use
    of force is not unexpected by the master.
    Restatement (Second) of Agency § 228(1).   The second, third and
    fourth elements are irrelevant here because plaintiffs do not
    contest that the alleged events occurred substantially within
    authorized time and space limits or were actuated, in some part,
    with the purpose to serve the master, nor do they allege the use
    of force.   The plaintiffs do, however, attempt to rebut the
    United States’ scope-of-employment certification under the first
    prong of the Restatement test, claiming “it is difficult to
    understand that the [actions described in paragraph 195 of the
    Amended Complaint] could be considered to be related to the work
    Robinson and Traugh were employed to perform.”   Pls.’ Opp’n at
    33.
    To qualify as conduct of the kind they were employed to
    perform, Robinson’s and Traugh’s actions must have either been
    “of the same general nature as that authorized” or “incidental
    to the conduct authorized.”   Restatement (Second) 229.   The
    current record sheds little light on the duties Traugh and
    Robinson are authorized to perform.   In the Amended Complaint,
    plaintiffs assert that Traugh, in his capacity as OPLOG program
    manager, and/or Robinson, in his capacity as OPLOG’s assistant
    program manager, had the authority to, inter alia, (1) oversee
    25
    plaintiffs’ work, (2) review and approve their “deliverables”
    and invoices, (3) develop OPLOG’s budget and allocate funds to
    various contractors, and (4) block any contractor from
    contracting to perform work on OPLOG projects.     Am. Compl. ¶¶
    29-31, 73, 82.
    However, in their opposition to the federal defendants’
    motion to dismiss, plaintiffs take a contrary position.     They
    assert that Traugh (and presumably his assistant Robinson), have
    limited, if any authority to (a) oversee OPLOG funding to
    government contractors and ensure it is well and prudently
    spent; (b) request that prime contractors replace employees or
    subcontractors, or assign follow-on tasks to current employees
    or subcontractors; or (c) ensure that the work performed by
    government contractors and subcontractors conforms to contract
    requirements.    See Pls.’ Opp’n to Fed. Defs.’ Mem., Ex. B.,
    Decl. of Sebastian Phillips, ¶¶ 28-31, 39.     Plaintiffs assert
    that most or all of this authority is vested in either the prime
    contractors for whom MDD works or in the Navy’s contracting
    officers, not Traugh or Robinson.5    Id.   Traugh maintains that he
    5
    It is worth noting that other documents provided by the Navy
    seem to provide at least some support for these assertions.
    Specifically, the memorandum issued by NAVSEA in response to the
    Consent Preliminary Injunction provides, in relevant part, that
    the Navy’s Seaport-e contracts, which include the contracts with
    CSC and Gryphon at issue in this case, “do not permit Command
    personnel to direct a prime contractor to select, or decline to
    select, a given subcontractor for a given item of work. Other
    26
    is authorized to perform all of these duties, but, other than
    his declaration, has provided no evidence to support his
    assertions.     See Fed. Defs.’ Mem., Ex. A., Traugh Decl.
    The Court is troubled by plaintiffs’ contradictory
    characterizations of the scope of Traugh’s and Robinson’s
    employment.     Nevertheless, plaintiffs have alleged facts in
    their opposition to the Motion to Dismiss that, taken as true,
    could rebut the Attorney General’s certification.     Accordingly,
    plaintiffs will be allowed to conduct limited discovery on the
    scope-of-employment issue.     The federal defendants’ motion to
    dismiss Count XI on grounds of sovereign immunity and failure to
    exhaust under the FTCA is therefore denied without prejudice to
    refiling at the appropriate time.
    5. Qualified Immunity
    In Count II of the Amended Complaint, plaintiffs sue Traugh
    and Bosworth in their individual capacity for the de facto
    debarment.     Qualified immunity is “a defense that shields
    officials from suit if their conduct did not violate clearly
    established statutory or constitutional rights of which a
    reasonable person would have known.”      Bame v. Dillard, 
    637 F.3d 380
    , 384 (D.C. Cir. 2011) (internal citations omitted).      To
    contractual direction may be issued only by cognizant
    contracting officers.” See Pls.’ Mot. to Enforce Stip. Prelim.
    Inj. at Ex. K, Mem. from NAVSEA Commander K.M. McCoy to NAVSEA
    and Naval Service War Center, Dec. 20, 2011.
    27
    determine whether an official is entitled to qualified immunity,
    the Court must consider whether the facts, viewed in the light
    most favorable to plaintiffs, establish a violation of a
    constitutional right, and if so, whether that right was clearly
    established at the time of the alleged violation.   Pearson v.
    Callahan, 
    555 U.S. 223
    , 231-32 (2009).   “An official enjoys
    protection from a lawsuit where his conduct is objectively
    reasonable in light of existing law.   Conversely, an officer is
    not shielded where he could be expected to know that certain
    conduct would violate statutory or constitutional rights.”
    Brown v. Fogle, 
    819 F. Supp. 2d 23
    , 28-29 (D.D.C. 2011)(quoting
    Farmer v. Moritsugu, 
    163 F.3d 610
    , 613 (D.C. Cir. 1998)(internal
    quotation marks omitted)).
    As set forth above, de facto debarment of a government
    contractor without due process and on grounds of dishonesty,
    fraud or lack of integrity violates the Fifth Amendment.   Traugh
    and Bosworth contend, however, that (1) their job duties
    permitted them to terminate all of MDD’s work with OPLOG, bar it
    from obtaining new work with OPLOG, and refuse to appoint a TPOC
    for MDD to obtain work via NAVSEA based on their concerns that
    MDD was not charging a reasonable price or providing the best
    value to the government, and (2) their actions did not bar
    plaintiff from obtaining any and all additional work for the
    Navy, and therefore did not constitute de facto debarment.     Fed.
    28
    Defs.’ Mem. at 12-15.6    Federal Defendants’ framing of Traugh’s
    and Bosworth’s actions highlights the factual disputes that
    prevent dismissal of Count II on grounds of qualified immunity.
    The resolution of these questions, specifically, defendants’
    authority to bar MDD from performing future work at OPLOG, as
    well as the breadth of MDD’s preclusion from government
    contracting, depend on development of the facts, and the Court
    must accept the truth of the plaintiffs’ factual allegations on
    a motion to dismiss.     Accordingly, the Court will deny
    defendants’ Rule 12(b)(6) motion to dismiss on the ground of
    qualified immunity.
    6
    Traugh and Bosworth also contend that plaintiffs’
    constitutional rights are not clearly established. They claim
    there is no authority specifically permitting subcontractors, as
    opposed to prime government contractors, to allege de facto
    debarment, or holding that a government official other than a
    contracting officer or a “senior official” may effect a de facto
    debarment. Fed. Defs.’ Mem. at 12. These claims are
    unpersuasive. See, e.g., 
    48 C.F.R. § 9.405-2
     (subcontractors
    are impacted by debarments; once a contractor has been debarred,
    it is effectively prohibited from serving as a subcontractor on
    government contracts); see also Highview Eng’g v. Hawkins, Case
    08-647, 
    2010 U.S. Dist. LEXIS 75102
     (July 26, 2010)(finding
    plaintiff stated a claim of de facto debarment by project
    manager and attorney). Moreover, plaintiffs need not identify
    factually indistinguishable precedent in order to defeat a claim
    of qualified immunity. “The facts of such cases need not be
    materially similar, but have only to show that the state of the
    law [at the time of the incident] gave [the officer] fair
    warning that [his alleged misconduct] ... was unconstitutional."
    Bame, 637 F.3d at 384 (internal citations and quotations
    omitted)(alterations in original).
    29
    6. Summary Judgment
    Federal defendants have presented material outside the
    pleadings, and the Court has considered those materials.
    Accordingly, the Court will treat the motion as one for summary
    judgment in the alternative.     See Holy Land Found. for Relief &
    Dev. v. Ashcroft, 
    333 F.3d 156
    , 165 (D.C. Cir. 2003).     As a
    general matter, summary judgment is premature unless all parties
    “have had a full opportunity to conduct discovery.”     Liberty
    Lobby, 
    477 U.S. at 257
    .    After reviewing the parties’ filings,
    and for the reasons explained above, the court concludes that
    the factual record is not sufficiently developed to allow a
    determination as to whether genuine issues of material fact
    exist.   Accordingly, the defendants’ motion for summary judgment
    is denied without prejudice to refiling at the appropriate time,
    in order to permit plaintiffs the benefit of discovery.
    7. Conclusion
    For the foregoing reasons, the Court concludes plaintiffs
    have stated a claim for de facto debarment in Count I.     Further,
    because of the factual allegations presented by plaintiffs at
    this state of the litigation, the court cannot find, as a matter
    of law, that the qualified immunity defense is properly asserted
    as to Count II or that substitution of the United States and
    dismissal under the FTCA is appropriate as to Count IX.
    30
    Accordingly, the Federal Defendants’ motion to dismiss or, in
    the alternative, for summary judgment is DENIED.
    B. Plaintiffs’ Motion to Enforce Stipulated Preliminary
    Injunction
    1. Factual Background and the Parties’ Positions
    As discussed supra, on December 7, 2011, the parties agreed
    and stipulated to a Consent Preliminary Injunction.    Plaintiffs
    argue that defendants have refused to comply with the terms of
    the injunction.    They seek to have this Court enforce its terms
    and hold the federal defendants in contempt.
    The terms of the Consent Preliminary Injunction enjoin the
    Navy as follows.
    (1) Federal defendants are enjoined from taking any action
    to implement, enforce, or spread to any agency of the
    federal government the de facto debarment of plaintiffs
    from contracting.
    (2) Federal defendants are required to allow Marine Design
    Dynamics, Inc. (“MDD”) to compete for, and if awarded,
    receive and perform contracts, subcontracts, task orders,
    task instructions and orders under indefinite quantity
    contracts, in the same manner and under the same standards
    applicable to other contractors and subcontractors, unless
    and until debarment or suspension proceedings are properly
    initiated, or until further order of this Court, including
    but not limited to the following:
    (a)     Plaintiffs’ subcontract under the Navy’s prime
    contract with Computer Sciences Corporation
    (“CSC”) pursuant to its SEAPORT-e contract,
    N00178-04-D-4030-EH02. The government shall
    appoint a Technical Point of Contact between
    Operational Logistics Integration Program
    (“OPLOG”) and CSC for this purpose.
    (b)     Successor contracts to MDD’s prime contract with
    31
    Military Sealift Command (“MSC”), N00033-10-C-
    8002, which is expected to expire November 1,
    2012.
    (c) Federal Defendants shall communicate to CSC and
    Gryphon Technologies, rescinding any guidance or
    instruction that work was to be removed from or
    not given to MDD, in effect restoring the status
    quo ante.7 Federal Defendants shall appoint a
    Technical Point of Contact between Naval Sea
    Systems Command of the Department of the Navy
    (“NAVSEA”), MSC and Gryphon Technologies for this
    purpose.
    (3) Federal defendants are required to allow MDD to
    maintain and perform its existing contracts, subcontracts,
    task orders, task instructions and orders under indefinite
    quantity contracts, in the same manner and under the same
    standards applicable to other contractors, unless and until
    debarment or suspension proceedings are properly initiated,
    or until further order of this Court, including but not
    limited to the following:
    (a) Plaintiffs’ existing prime contract with MSC,
    N00033-10-C-8002.
    (b) Plaintiffs’ existing subcontract under the Navy’s
    prime contract with CSC pursuant to its SEAPORT-e
    contract, N00178-04-D-4030-EH02.
    In response to the Consent Preliminary Injunction, the Navy
    took the following actions.   First, on December 20, 2011,
    defendant Vice Admiral McCoy, NAVSEA’s Commander, sent a
    memorandum from NAVSEA’s counsel, Sophie Krasik, with the
    Consent Preliminary Injunction attached, to NAVSEA’s Contracts
    Directorate, NAVSEA’s Ship Engineering Directorate (where
    7
    This sentence was crafted by the parties in off the record
    discussions and the parties inserted it into the Stipulated
    Preliminary Injunction at the end of the hearing. Tr. of Oral
    Argument at 70-71.
    32
    Bosworth is employed) and the Naval Surface Warfare Center
    (under whose command OPLOG falls).      Defs.’ Opp’n to Pls.’ Mot.
    to Enforce at 4.    The memorandum explains the Consent
    Preliminary Injunction and directs Navy employees to “maintain a
    position of strict neutrality toward MDD, neither encouraging
    nor interfering with: (1) the efforts of MDD to obtain work from
    prime contractors; or (2) prime contractors’ decision whether or
    not to subcontract with MDD . . . The injunction is consistent
    with the Navy’s SeaPort-e prime contracts, which do not permit
    Command personnel to direct a prime contractor to select, or
    decline to select, a given subcontractor for a given item of
    work.    Other contractual direction may be issued only by
    cognizant contracting officers.”       See Pls.’ Mot. to Enforce, Ex.
    K.
    Second, on December 16, 2011, Michael Kistler, the
    Executive Director in the NAVSEA Engineering Directorate, issued
    an email designating Chris Cable as TPOC for any MSC work
    ordered through a Seaport-e prime contractor, including but not
    limited to Gryphon Technologies, and Charles Traugh as TPOC for
    any OPLOG work.    Plaintiffs immediately objected to the choice
    of Traugh, and in response the Navy replaced him with another
    NAVSEA employee, Greg Doerrer.    Pls.’ Mot. to Enforce at 6; Fed.
    Defs.’ Opp’n at 14.
    33
    Third, on December 20, 2011, Lindsay Alexander, Contracting
    Officer for CSC and Gryphon Technologies, the two SeaPort-e
    prime contractors from whom MDD alleged it had been precluded
    from receiving subcontracting work, sent CSC and Gryphon a
    letter enclosing the Consent Preliminary Injunction and
    explaining, inter alia, that MDD must have the same opportunity
    to compete for and perform work as any other contractor.   The
    letter also states, in relevant part, “the terms of your prime
    task order do not permit most Navy personnel to issue direction
    to you to select, or decline to select, a given subcontractor
    for a given item of work or to issue any other contractual
    direction.   Rather, only contracting officers may issue
    contractual direction, and that direction cannot contradict the
    terms of the court order.”   Pls.’ Mot. to Enforce, Exs. M, N.8
    Plaintiffs argue none of these actions comply with the
    Consent Preliminary Injunction.    According to Plaintiffs, the
    Navy’s actions are deficient in three respects.   First, they
    claim the Navy’s communications with its own personnel as well
    as CSC, Gryphon and Alion “distort” the terms of the preliminary
    injunction and convey a negative impression of plaintiffs.
    8
    The Navy also sent this letter to one additional company, Alion
    Science and Technology Corporation. In the letter to Alion,
    Lindsay Alexander explained that the Consent Preliminary
    Injunction only required communication to CSC and Gryphon, but
    “because Alion holds a [prime contract] substantially identical
    to those of CSC and Gryphon, we are informing you as well of
    this aspect of the court order.” Id. Ex. L.
    34
    Pls.’ Mot. to Enforce at 8-14.   Second, they claim the Navy did
    not appoint a “suitable” TPOC for the OPLOG work, first, by
    appointing defendant Traugh, and then, upon plaintiffs’
    objection, replacing him with defendant Greg Doerrer, who has
    not been accused of any wrongdoing but who “was present at the
    [July 13, 2011] meeting at which” Bosworth instructed Traugh to
    terminate MDD’s work for OPLOG in 2012.    Id. at 6.   Finally,
    plaintiffs claim that the Navy has not restored “the status quo
    ante” by awarding MDD subcontracting work with CSC, at OPLOG, or
    with Gryphon, at NAVSEA/MSC.   According to plaintiffs, MDD was
    “scheduled to receive $2.7 in OPLOG work in FY 2012” and “was in
    the final stages of being awarded a $5.529 M contract with the
    MSC under a subcontract with Gryphon.”    Id. at 5.    Plaintiffs
    request the Court fine the Navy, award attorneys’ fees, and
    order the Navy to (1) prohibit the Navy from disseminating any
    communications regarding this litigation without plaintiffs’
    consent; (2) appoint a “suitable” TPOC, and (3) “restore the
    status quo ante” with respect to OPLOG and MSC work.    Pls.’
    Proposed Order Granting Motion to Enforce.
    The Navy responds that it has not violated the terms of the
    injunction.   The government notes that all of its communications
    to Navy personnel and government contractors provided a copy of
    the Stipulated Preliminary Injunction as an attachment, thereby
    enabling every recipient to review the Order’s terms.    Fed.
    35
    Defs.’ Opp’n at 16-19.    It also asserts that the letters
    explaining the Injunction accurately conveyed the Navy’s
    responsibilities under the Order. Id.      With respect to
    appointment of a TPOC for OPLOG work, the Navy points out the
    Injunction “only directed the Navy to appoint a TPIC for OPLOG
    work; it did not . . . grant Plaintiffs any voice in the
    appointment.”     Id. at 14.   Nevertheless, at plaintiffs’ request
    it replaced Traugh with Doerrer “who is also an OPLOG employee
    but is not in a subordinate or supervisory position to Mr.
    Traugh.”    Id.
    Finally, the government points out that restoration of “the
    status quo ante” does not require plaintiffs to be awarded
    additional work with CSC or a new subcontract with Gryphon
    Technologies.     The government claims that “plaintiffs nowhere
    assert, nor can they, that MDD had an actual contract terminated
    or a pending award withheld because of the alleged debarment.”
    Id. at 6.   With respect to work to be performed for OPLOG under
    a subcontracting agreement with CSC, the government points out
    that “performance under the [CSC] contract does not commence
    until the contractor receives a delivery order . . . plaintiff
    MDD did not have a delivery order to perform Fiscal Year 2012
    work under its . . . contract with CSC.”      Id. at 6, n.4.   “A
    company’s placement in the budget” for FY 2012, which is all
    that MDD alleged had occurred with respect to its award of OPLOG
    36
    work, “does not guarantee work for that company.”     Id. at 7.
    Likewise, the government asserts that MDD had not been awarded a
    contract to perform MSC work under a subcontract with Gryphon;
    indeed, federal defendants argue that the government had not
    even agreed upon the scope of work to be done under any proposed
    subcontract.   Id. at 7-9.   The Navy therefore argues that:
    The status quo ante of each of the alleged debarments found
    the parties far from ready to enter into any sort of
    contractual arrangement. Rather, MDD was eligible for
    prime contracts and subcontracts, a very different status .
    . . . Restoring the status quo ante therefore meant
    restoring MDD’s eligibility to compete, which is just what
    the Navy did.
    Id. at 11.
    1. Discussion
    An order granting injunctive relief is enforceable by the
    district court’s power of contempt.    See Gunn v. Univ. Comm. to
    End War in Viet Nam, 
    399 U.S. 383
    , 389 (1970).    A contempt
    finding is proper where “the putative contemnor has violated an
    order that is clear and unambiguous” and the violation of an
    order is “proved by clear and convincing evidence.”     Armstrong
    v. Executive Office of the President, Office of Admin., 
    1 F.3d 1274
    , 1289 (D.C. Cir. 1993) (citation and internal quotation
    marks omitted).   “In the context of civil contempt, the clear
    and convincing standard requires a quantum of proof adequate to
    demonstrate a reasonable certainty that a violation occurred.”
    37
    Breen v. Tucker, 
    821 F. Supp. 2d 375
    , 383 (D.D.C. 2011)
    (citations and internal quotation marks omitted).
    In this case, neither party argues that the Stipulated
    Consent Preliminary Injunction they reached is ambiguous; the
    parties only dispute whether the Navy violated the Order.
    Armstrong, 
    1 F.3d at 1289
    .     The Court concludes the government
    has not.    The stipulated injunction requires the government
    allow MDD to compete for, and if awarded, perform work for the
    Navy.    Stip. Prelim. Inj. ¶ 2.   It also requires the government
    to allow MDD to maintain and perform its existing work in the
    same manner and under the same circumstances applicable to other
    contractors.     Id. ¶ 3.   The Stipulated Injunction does not
    purport to define the work MDD has been or would be awarded,
    except to identify one contract on which the parties agreed MDD
    had been awarded work in FY 2011 (the CSC contract) and one in
    which it had been awarded work continuing in FY 2012 (MDD’s
    prime contract with MSC).
    It may be that the plaintiffs will be able to establish
    that they had been awarded, or all-but-awarded, additional work
    for OPLOG or MSC, and that they would have received such work
    but-for the de facto debarment.      However, no requirement that
    the Navy or the contractors give plaintiffs this work is plain
    on the face of the Stipulated Preliminary Injunction.      See,
    e.g., United States v. Armour & Co., 
    402 U.S. 673
    , 681-2 (1971)
    38
    (“the [stipulated injunction] must be construed as it is
    written, and not as it might have been written had the plaintiff
    established his factual claims and legal theories in
    litigation.”)9
    Plaintiffs’ arguments that the government violated the
    Consent Preliminary Injunction by its allegedly misleading
    communications with Navy personnel and government contractors,
    and by failing to appoint a “suitable” TPOC likewise fail.
    While plaintiffs may wish the government’s communications had
    been worded differently, they describe the substance of the
    Stipulated Injunction and, indeed, plaintiff does not dispute
    that a true and correct copy of the Injunction was provided as
    an attachment.   Likewise, while the Court agrees that the
    government’s initial appointment of Traugh as TPOC was at best,
    imprudent, the government has since replaced him with Greg
    9
    Plaintiffs rely on a phrase the parties added to the
    Injunction during off the record discussions -- “in effect
    restoring the status quo ante,” –- to justify their position
    that the Navy is required to award MDD additional OPLOG and MSC
    work. Plaintiffs’ argument is meritless. The sentence in which
    the phrase appears reads as follows: “Federal Defendants shall
    communicate to CSC and Gryphon Technologies, rescinding any
    guidance or instruction that work was to be removed from or not
    given to MDD, in effect restoring the status quo ante.” Stip.
    Prelim. Inj. ¶ 2(c). Read in context, this requires the Navy to
    tell CSC and Gryphon that the Navy had withdrawn any objection
    to MDD, a requirement the Navy has fulfilled. It does not state
    that CSC or Gryphon had contracted, or would have contracted,
    with MDD for present or future work but for the Navy’s
    instructions not to use MDD.
    39
    Doerrer, an OPLOG employee who has not been charged by
    plaintiffs with any wrongdoing.
    Based on the foregoing, the Court concludes that plaintiffs
    have not met their burden to show, by clear and convincing
    evidence, that the Navy violated the Stipulated Preliminary
    Injunction.     Accordingly, the Motion to Enforce is DENIED.
    C. MDD’s Former Employees’ Motions to Dismiss
    Three of MDD’s four former employees named in this action
    have filed motions to dismiss.     See Motions to Dismiss by
    Michael Mazzocco, Volker Stammnitz, and William Muras.        The
    Amended Complaint alleges breach of fiduciary duty and civil
    conspiracy as to each of them.    Am. Compl. Counts III, IV, V,
    and VIII.    Additionally, the Amended Complaint asserts a common
    law defamation claim against Mazzocco.       
    Id.
     Count VII.   The
    Court will address each cause of action in turn.
    1. Breach of Fiduciary Duty
    Employees, particularly managers and officers, “owe an
    undivided and unselfish loyalty to the corporation” during the
    term of their employment, “such that there shall be no conflict
    between duty and self-interest.”       Mercer Management Consulting
    v. Wilde, 
    920 F. Supp. 219
    , 233 (D.D.C. 1996) (internal
    citations and quotation marks omitted); see also Gov’t Relations
    v. Howe, Case No. 05-1081, 
    2007 U.S. Dist. LEXIS 4952
    , *33
    (D.D.C. Jan. 24, 2007); PM Servs. Co. v. Odoi Assoc., Inc., Case
    40
    No. 03-1810, 
    2006 U.S. Dist. LEXIS 655
    , *84 (D.D.C. Jan. 4,
    2006).   Although an agent may “make arrangements or plans to go
    into competition with his principal before terminating his
    agency,” he may only do so “provided no unfair acts are
    committed or injury done [to] his principal.”      Mercer, 
    920 F. Supp. at 233
     (citation omitted).      Specifically, in preparing to
    compete, an employee may not engage in “misuse of confidential
    information, solicitation of the firm’s customers, or
    solicitation leading to a mass resignation of the firm’s
    employees.”   Furash & Co. v. McClave, 
    130 F. Supp. 2d 48
    , 54
    (D.D.C. 2001) (citing Mercer, 
    920 F. Supp. at 233
    ).      “The
    ultimate determination of whether an employee has breached his
    fiduciary duties to his employer by preparing to engage in a
    competing enterprise must be grounded upon a thoroughgoing
    examination of the facts of the particular case.”      
    Id.
     (internal
    citations omitted).
    As a general rule, an employee’s fiduciary duty ends upon
    termination of the employment relationship.      Draim v. Virtual
    Geosatellite Holdings, Inc., 
    631 F. Supp. 2d 32
    , 40 (D.D.C.
    2009).   “An agent after termination of his employment, in the
    absence of an agreement to the contrary, may compete with his
    former principal.”    United States Travel Agency, Inc. v. World-
    Wide Travel Service Corp., 
    235 A.2d 788
    , 789 (D.C. 1967).
    41
    Plaintiffs allege that Mazzocco, Stammnitz, and Muras
    breached their fiduciary duty of loyalty to MDD both during and
    for a year after their employment, during which they were
    allegedly subject to a non-compete agreement.   Am. Compl. ¶¶ 34-
    36 and Exs. A-C, MDD Employee Handbook and Code of Business
    Conduct.   All three employees were senior officers and key
    employees at MDD.   Am. Compl. ¶¶ 33, 128-29, 146-47, 159-60.
    All three employees resigned from MDD in the spring of 2011;
    Mazzocco and Stammnitz formed independent companies to compete
    with plaintiffs either during or immediately following their
    employment with MDD.   Am. Compl. ¶¶ 47-51, 62-65.   Plaintiffs
    principally allege that Mazzocco violated his fiduciary duties
    as follows:
       “Confirmed” with Robinson, before leaving MDD in March
    2011, that he would be able to continue performing the
    same work for OPLOG, and in the same position, after
    leaving MDD, thus soliciting MDD’s customers and
    business opportunities. Am. Compl. ¶¶ 44-45, 139.
       Signed an agreement in February 2011 on behalf of his
    new company, Alytic, Inc., with a competitor of MDD to
    exchange proprietary information, thus competing with
    MDD while still employed there and misusing its
    confidential and proprietary information. Am. Compl.
    ¶¶ 49, 140.
       Solicited other employees to resign their positions
    with MDD and join him at OPLOG, thus leading to a
    “mass resignation” of plaintiffs’ employees. Am.
    Compl. ¶ 139.
       Attended a meeting with Muras, Stammnitz, and Navy
    officials in Boston in May 2011, at which he worked to
    have plaintiffs removed from OPLOG’s 2011 and 2012
    42
    budget in order to obtain plaintiffs’ work for
    himself, thus soliciting MDD’s customers and business
    opportunities during the term of his alleged non-
    compete agreement. Am. Compl. ¶¶ 68-88, 138-39.
    Plaintiffs’ allegations regarding Stammnitz and Muras are
    very similar.   Plaintiffs primarily allege that both solicited
    MDD’s customers and business opportunities at OPLOG while they
    were employed with MDD, as well as during the term of their non-
    compete agreements, by (1) arranging to continue performing the
    same work for OPLOG after leaving MDD, while still employed with
    MDD; and (2) attending the Boston meeting, at which they worked
    to exclude MDD from OPLOG’s 2011 and 2012 budgets in order to
    obtain plaintiffs’ work for themselves, also while still
    employed with MDD.   Am. Compl. ¶¶ 59-64, 66, 68-77, 152-55, 164-
    67.
    The defendants argue that these allegations are
    insufficient.   They claim they had no binding non-compete
    contract with MDD, therefore plaintiffs cannot state a claim for
    any of their actions after they resigned from MDD.      See Muras
    Mot. to Dismiss at 9, Stammnitz Mot. to Dismiss at 7-9, Mazzocco
    Mot. to Dismiss at 6-8.   They also claim plaintiffs cannot show
    proximate cause between the alleged breach and plaintiffs’
    injuries, because the Navy, not MDD’s former employees, made the
    decisions to remove work from plaintiffs.   Muras Mot. to Dismiss
    43
    at 6-7, Stammnitz Mot. to Dismiss at 11-12, Mazzocco Mot. to
    Dismiss at 8-9.10
    10
    Stammnitz additionally argues that the claim against him
    should be dismissed on abstention grounds because plaintiffs
    filed a substantially identical counterclaim in Stammnitz’
    pending Superior Court lawsuit against the MDD and Sebastian
    Phillips. The Court will not dismiss on this basis. Federal
    district courts have a “virtually unflagging obligation... to
    exercise the jurisdiction given them.” Colorado River Water
    Conservation Dist. v. United States, 
    424 U.S. 800
    , 817 (1976).
    In determining whether a case is appropriate for Colorado River
    abstention, the Court's task “is to ascertain whether there
    exist ‘exceptional’ circumstances, the ‘clearest of
    justifications,’ that can suffice... to justify the surrender of
    that jurisdiction,” Moses H. Cone Mem'l Hosp. v. Mercury Constr.
    Corp., 
    460 U.S. 1
    , 25-26 (1983) (citations omitted); see also
    Handy v. Shaw, Bransford, Veilleux & Roth, 
    325 F.3d 346
    , 348
    (D.C. Cir. 2003) (“A district court's authority to dismiss a
    case within its jurisdiction in favor of parallel local court
    proceedings is limited.”). The Supreme Court has articulated
    six factors that a district court must consider in deciding
    whether the circumstances of a particular case are exceptional:
    (1) whether one court has first assumed jurisdiction over
    property; (2) the inconvenience of the federal forum; (3) the
    desirability of avoiding piecemeal litigation; (4) the order in
    which jurisdiction was obtained by the concurrent forums, (5)
    the source of the law that will provide the rules of the
    decision; and (6) the adequacy of the state court proceeding to
    protect the rights of the parties, see Moses H. Cone, 
    460 U.S. at 24-26
    . A district court’s analysis of the above factors
    should not be mechanical, but rather the district court should
    carefully balance the factors that apply to the given case,
    “with the balance heavily weighted in favor of the exercise of
    jurisdiction.” 
    Id. at 16
    . The Court finds that none of the
    factors weighs strongly in favor of abstention. Because this
    case does not involve jurisdiction over property, and because
    both the federal and state forums are located in the District of
    Columbia and are thus equally convenient, the first and second
    factors are neutral. The third factor is the avoidance of
    piecemeal litigation. In analyzing the problem of piecemeal
    litigation, courts must “look beyond the routine inefficiency
    that is the inevitable result of parallel proceedings to
    determine whether there is some exceptional basis for requiring
    the case to proceed entirely in state court,” such as severe
    44
    Plaintiffs have clearly stated a claim for breach of
    fiduciary duty.   Even assuming arguendo that plaintiffs had no
    enforceable non-compete agreement with the employees after the
    termination of employment, the Amended Complaint contains
    factual allegations that Mazzocco, Stammnitz, and Muras all
    solicited MDD’s customers and business opportunities while they
    were still employed by MDD.   Plaintiffs have also alleged that
    they suffered damages – namely, loss of OPLOG work in 2011 and
    2012 – as a proximate cause of their former employees’ actions.
    To establish proximate cause, the plaintiffs must allege that
    prejudice to one of the parties. Johns v. Rozet, 
    770 F. Supp. 11
    , 15 (D.D.C. 1991) (citations omitted). The Court is not
    persuaded that parallel litigation would severely prejudice
    defendant in this case, particularly because the plaintiffs have
    indicated a willingness to dismiss their counterclaims in the
    Superior Court case and where the Superior Court Judge has
    demonstrated sensitivity to the burdens of duplicative
    discovery. See Pls.’ Opp’n to Stammnitz Mot. at 14-16;
    Stammnitz’ Suppl. Reply, Ex. B, Order of Superior Court Judge
    Craig Iscoe. The fourth factor, the order in which the courts
    obtained jurisdiction, is neutral because neither case has
    progressed beyond the early stages. The fifth factor, the source
    of law, does not weigh in favor of abstention because state law
    issues do not govern all claims in this lawsuit, and the state
    law claims alleged do not appear to involve novel or complex
    legal issues. See Rozet, 
    770 F. Supp. at 16
    . Finally, the sixth
    factor, the adequacy of the Superior Court to protect the rights
    of the parties, does not weigh in favor of abstention. Although
    the issues between plaintiffs and Stammnitz turn on local law,
    this action is the only one where all of MDD’s former employees
    have been joined, and accordingly this Court is in a better
    position to comprehensively protect plaintiffs’ interests, and
    no worse a position to protect Stammnitz’s interests. Having
    balanced the relevant factors, with the balance heavily weighted
    in favor of the exercise of jurisdiction, the Court has
    determined that this case does not present "exceptional
    circumstances" that would justify abstention.
    45
    “there was a direct and substantial causal relationship between
    the defendant’s breach of the standard of care and the
    plaintiff’s injuries and that the injuries were foreseeable.”
    Convit v. Wilson, 
    980 A.2d 1104
    , 1125 (D.C. 2009).     Here,
    plaintiffs contend that Mazzocco, Stammnitz, and Muras deprived
    plaintiff MDD of work by (1) soliciting OPLOG to take work away
    from MDD and take it for themselves after leaving MDD, and (2)
    working with OPLOG officials to change existing budgets, in
    order for Mazzocco, Stammnitz, and Muras to take the work that
    had previously been allotted to plaintiffs.    As a direct result,
    plaintiffs allege, they lost over $2.5 million in Fiscal Year
    2012.    At this preliminary stage, plaintiffs have clearly met
    their burden to plead proximate cause.    Accordingly, the Motions
    to Dismiss Counts III, IV and V will be DENIED.
    2. Civil Conspiracy
    Civil conspiracy is not an underlying tort, but only a
    means for establishing vicarious liability for an underlying
    tort.     Paul v. Howard Univ., 
    754 A.2d 297
    , 310 n.27 (D.C. 2000).
    Plaintiffs allege that Mazzocco, Stammnitz, Muras and Miller
    conspired to breach their fiduciary duties to MDD “by the
    elimination of Plaintiff MDD from the OPLOG FY 2012 budget, and
    the solicitation of MDD’s . . . client, OPLOG[.]”    Am. Compl. ¶
    188.    Mazzocco, Stammnitz, and Muras argue that plaintiffs have
    46
    failed to plead the existence of a civil conspiracy with
    particularity.11   The Court disagrees.
    To establish a prima facie case of civil conspiracy,
    plaintiffs must show (1) an agreement between two or more
    persons (2) to participate in an unlawful act, and (3) an injury
    caused by an unlawful overt act performed by one of the parties
    to the agreement in furtherance of the common scheme.    Paul, 
    754 A.2d at 310
     (citation omitted).    Plaintiffs must plead the
    elements of conspiracy with particularity; “bald speculation or
    a conclusory statement that individuals are co-conspirators is
    insufficient to establish” a claim for conspiracy.    3M Co. v.
    Boulter, 
    842 F. Supp. 2d 85
    , 112 (D.D.C. 2012) (internal
    citations omitted).
    Plaintiffs have met their burden to plead a conspiracy
    between their former employees.    Plaintiffs allege the following
    11
    Additionally, Mazzocco and Stammnitz claim immunity under the
    “intracorporate immunity” doctrine, in which an entity, its
    officers and agents are presumed to act as a single enterprise
    and may not be found to have conspired with one another. Wesley
    v. Howard Univ., 
    3 F. Supp. 2d 1
    , 3 (D.D.C. 1998). Assuming the
    doctrine applies here, where the employees were allegedly
    conspiring against the corporation, intracorporate immunity may
    be overcome when the employees act outside the scope of their
    employment. Weaver v. Gross, 
    605 F. Supp. 210
    , 214-15 (D.D.C.
    1985). Plaintiffs have alleged facts in their Amended Complaint
    suggesting that Mazzocco, Stammnitz and Muras were acting
    outside the scope of their employment and pursuing their
    personal interests by conspiring to take clients and business
    opportunities for themselves and away from MDD. Accordingly,
    defendants’ motion to dismiss on the basis of intracorporate
    immunity is denied.
    47
    facts in support of their claim that the employees agreed to
    leave MDD and to take MDD’s business for themselves in their new
    ventures.    First, when plaintiff Phillips asked Mazzocco, the
    first employee to leave MDD, whether he was taking other
    employees with him, he responded “not initially.”    Am. Compl. ¶
    45.   Second, in the following months, three additional employees
    left MDD to “join” Mazzocco.    Id. ¶ 55.   Third, the departing
    employees needed funding for their new ventures, so they
    obtained “help” from Defendants Robinson and Traugh to obtain
    the $700,000 “pull-back” from MDD’s FY 2011 budget and all of
    the money from MDD’s FY 2012 budget, with money from both fiscal
    years to be reallocated to MDD’s former employees.     Id. ¶ 56-58;
    68-77.   Fourth, the departing employees all met in Boston where
    they agreed, with Bosworth, Traugh, and Robinson, to eliminate
    MDD’s funding for FY 2012 and prepare a new budget in which the
    former employees would receive the work instead.     Id. ¶ 68-77.
    Taking these allegations and all reasonable inferences therefrom
    as true, plaintiffs have stated a plausible claim of civil
    conspiracy.
    3. Defamation
    Finally, Mazzocco moves to dismiss Count VII, in which
    plaintiffs seek damages for defamation.     Plaintiffs allege that
    Mazzocco spread rumors to OPLOG and MSC that plaintiffs had
    double and triple billed OPLOG for services rendered to OPLOG,
    48
    that these statements were false, and that the statements
    injured plaintiffs in their profession.    Am. Compl. ¶¶ 179-186.
    In order to state a claim for defamation, a plaintiff must
    allege “(1) that the defendant made a false and defamatory
    statement concerning the plaintiff; (2) that the defendant
    published the statement concerning the plaintiff; (3) that the
    defendant’s fault in publishing the statement amounted to at
    least negligence; and (4) either that the statement was
    actionable as a matter of law irrespective of special harm or
    that its publication caused the plaintiff special harm.”
    Jankovic v. Int’l Crisis Group, 
    494 F.3d 1080
    , 1088 (D.C. Cir.
    2007).   Mazzocco argues, unsuccessfully, that the defamation
    claim should be dismissed.
    Mazzocco first claims plaintiffs did not plead sufficient
    factual allegations to support a defamation claim.    Mazzocco
    Mot. to Dismiss at 10-11.    Not so.   The Amended Complaint
    alleges that Mazzocco spread false rumors “amongst the OPLOG
    community, including OPLOG’s management and Plaintiff MDD’s
    customers on its prime contract with the Military Sealift
    Command, that Plaintiff MDD was double billing, and even triple
    billing, the government on OPLOG projects.”    Am. Compl. ¶¶ 52-
    53.   The Amended Complaint further alleges that these false
    statements caused plaintiffs to lose their government
    contracting work.   The plaintiffs clearly allege defamatory
    49
    statements.   See Jankovic, 494 F.2d at 1091 (“a statement is
    defamatory if it tends to injure the plaintiff in his trade,
    profession or community standing.”) (citation omitted).
    Second, Mazzocco claims that even if he made these
    statements, they are covered by the “common interest privilege.”
    Mazzocco Mot. to Dismiss at 11-12.    The common interest
    privilege protects otherwise defamatory statements made “(1) in
    good faith, (2) on a subject in which the party communicating
    has an interest, or . . . honestly believes he has a duty to a
    person having a corresponding interest or duty, (3) to a person
    who has such a corresponding interest.”    Mastro v. Potomac Elec.
    Power Co., 
    447 F.3d 843
    , 858 (D.C. Cir. 2006).    However, the
    privilege does not exist unless “the publisher believes, with
    reasonable grounds, that his statement is true.” Altimont, Inc.
    v. Chatelain, Samperton & Nolan, 
    374 A.2d 284
    , 290 (D.C. 1977)
    (citation omitted).   In this case, plaintiffs have alleged that
    Mazzocco did not believe these statements were true because he
    “knew from his previous employment” with MDD that the statements
    were “false,” but made them “for the purpose of damaging his
    prior employer’[s] reputation as an honest Government contractor
    for reasons of personal malice and unlawful competitive
    advantage.”   Am. Compl. ¶ 54.   Accordingly, Mazzocco’s assertion
    of the common interest privilege fails at the motion to dismiss
    stage.   For the same reasons, the Court rejects Mazzocco’s
    50
    claims that the statements were true and therefore not
    defamatory, and/or that he was not “at least negligent” in
    publishing the statements.   Mazzocco Mot. to Dismiss at 12-14.
    Accordingly, the Court will DENY Mazzocco’s motion to
    dismiss Count VII of the Amended Complaint.
    IV.   CONCLUSION
    For the foregoing reasons, the Court will deny the Federal
    Defendants’ Motion to Dismiss or in the Alternative for Summary
    Judgment, the Plaintiffs’ Motion to Enforce the Stipulated
    Preliminary Injunction, Michael Mazzocco’s Motion to Dismiss,
    Volker Stammnitz’s Motion to Dismiss, and William Muras’s Motion
    to Dismiss.   An appropriate Order will accompany this Memorandum
    Opinion.
    Signed:    Emmet G. Sullivan
    United States District Judge
    September 30, 2012
    51
    

Document Info

Docket Number: Civil Action No. 2011-2021

Citation Numbers: 894 F. Supp. 2d 71

Judges: Judge Emmet G. Sullivan

Filed Date: 9/30/2012

Precedential Status: Precedential

Modified Date: 8/31/2023

Authorities (43)

Dolly Kyle Browning and Direct Outstanding Creations ... , 292 F.3d 235 ( 2002 )

Mastro, Brian A. v. Potomac Elec Power , 447 F.3d 843 ( 2006 )

Fair Employment Council of Greater Washington, Inc. v. Bmc ... , 28 F.3d 1268 ( 1994 )

Stokes, Billy v. Cross, Steven , 327 F.3d 1210 ( 2003 )

Sparrow, Victor H. v. United Airlines Inc , 216 F.3d 1111 ( 2000 )

Reeve Aleutian Airways, Inc. v. United States of America , 982 F.2d 594 ( 1993 )

Trifax Corp. v. District of Columbia , 314 F.3d 641 ( 2003 )

Farmer, Dee v. Moritsugu, Kenneth , 163 F.3d 610 ( 1998 )

Wuterich v. Murtha , 562 F.3d 375 ( 2009 )

Holy Land Foundation for Relief & Development v. Ashcroft , 333 F.3d 156 ( 2003 )

scott-armstrong-gary-m-stern-eddie-becker-national-security-archive-center , 1 F.3d 1274 ( 1993 )

Handy v. Shaw, Bransford, Veilleux & Roth , 325 F.3d 346 ( 2003 )

Charles Kowal v. MCI Communications Corporation , 16 F.3d 1271 ( 1994 )

Coalition for Underground Expansion v. Mineta , 333 F.3d 193 ( 2003 )

Furash & Co., Inc. v. McClave , 130 F. Supp. 2d 48 ( 2001 )

Alfred A. Altimont, Inc. v. Chatelain, Samperton & Nolan , 374 A.2d 284 ( 1977 )

United States Travel Agency, Inc. v. World-Wide Travel ... , 235 A.2d 788 ( 1967 )

Paul v. Howard University , 754 A.2d 297 ( 2000 )

Convit v. Wilson , 980 A.2d 1104 ( 2009 )

Jankovic v. International Crisis Group , 494 F.3d 1080 ( 2007 )

View All Authorities »