Building and Construction Trades Department, Afl-Cio v. Chao ( 2009 )


Menu:
  •                         UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    ____________________________________
    )
    BUILDING AND CONSTRUCTION            )
    TRADES DEPARTMENT, AFL-CIO,          )
    )
    Plaintiff,        )
    )
    v.                             )   Civil Action No. 06-677 (RBW)
    )
    HILDA L. SOLIS, Secretary of Labor,  )
    and STEVEN CHU, Secretary of Energy, )
    )
    Defendants.       )
    ____________________________________)
    MEMORANDUM OPINION
    The Building and Construction Trades Department, AFL-CIO (the “BCT”), the plaintiff
    in this civil lawsuit, “seeks judicial intervention to compel . . . the Secretary of Labor . . . to issue
    an administrative determination concerning application of the Davis-Bacon Act, [
    40 U.S.C. §§ 3141-44
    , 3146-47 (2006),] . . . to [the] construction of three buildings intended for the sole
    and exclusive use of the . . . Department of Energy . . . that has been unreasonably withheld.”
    First Amended Complaint Seeking Mandatory Injunctive Relief for Agency Action Unlawfully
    Withheld, Declaratory Relief and Review of Agency Action (the “Compl.”) ¶ 1. Additionally,
    the plaintiff “seek[s] judicial review of a [purported] final agency determination by [the
    Department of Energy] that the Davis-Bacon Act does not apply to construction of two other
    buildings intended for the sole and exclusive use of [the Department of Energy],” 
    id.,
     under the
    Administrative Procedures Act, 
    5 U.S.C. §§ 551-59
    , 701-06, 1305, 3105, 3344, 4301, 5335,
    5372, 7521 (2006) (the “APA”), and 
    28 U.S.C. § 1361
     (2006), 
    id. ¶ 2
    . 1 Both defendants seek to
    dismiss the plaintiff’s claims against them pursuant to Federal Rules of Civil Procedure 12(b)(1)
    and 12(b)(6). After carefully considering the plaintiff’s amended complaint, the defendants’
    joint motion to dismiss, and all submissions made in conjunction with the defendants’ joint
    motion, 2 the Court concludes for the reasons that follow that it must grant the defendants’ motion
    in its entirety, but that the scope of that motion does not encompass all of the claims raised by the
    plaintiff.
    I. Background
    The following facts are alleged in the plaintiff’s amended complaint or are matters of
    public record. The Davis-Bacon Act, enacted by Congress in 1931 and amended most recently
    in 2002, provides in pertinent part that “[t]he advertised specifications for every contract in
    excess of $2,000[] to which the Federal Government . . . is a party[] for [the] construction,
    alteration, or repair . . . of public buildings . . . which requires or involves the employment of
    mechanics or laborers shall contain a provision stating the minimum wages to be paid” to those
    mechanics and laborers. 
    40 U.S.C. § 3142
    (a). “The minimum wages shall be based on the
    wages [that] the Secretary of Labor determines to be prevailing for the corresponding classes of
    laborers and mechanics” employed on similar projects in the “civil subdivision of the State in
    which the work is to be performed,” 
    id.
     § 3142(b), and “[e]very contract” covered by the statute
    1
    The plaintiff’s amended complaint names Elaine L. Chao and Samuel W. Bodman, the former Secretary of Labor
    and Secretary of Energy, respectively, as defendants in their official capacities. The Court has substituted the names
    of Secretary Solis and Secretary Chu for former Secretary Chao and former Secretary Bodman pursuant to Federal
    Rule of Civil Procedure 25(d).
    2
    In addition to the plaintiff’s amended complaint and the defendants’ joint motion to dismiss, the Court considered
    the following documents in reaching its decision: (1) the Memorandum of Points and Authorities in Support of
    Defendants’ Joint Motion to Dismiss (the “Defs.’ Mem.”), (2) the Memorandum of Points and Authorities in
    Opposition to Defendants’ Joint Motion to Dismiss (the “Pl.’s Opp’n”), and (3) the Defendants’ Joint Reply to
    Plaintiff’s Memorandum of Points and Authorities in Opposition to Defendants’ Joint Motion to Dismiss (the
    “Defs.’ Reply”).
    2
    “must contain stipulations that,” inter alia, the “contractor or subcontractor shall pay all
    mechanics and laborers . . . the full amounts accrued at [the] time of payment, computed at wage
    rates not less than those stated in the advertised specifications,” id. § 3142(c)(1). Under
    Department of Labor regulations, “[a]ll questions relating to the application and interpretation of
    wage determinations . . . shall be referred to the Administrator [of the Wage and Hour Division
    of the Department of Labor],” whose “rulings and interpretations shall be authoritative.” 
    29 C.F.R. § 5.13
     (2007).
    The plaintiff is “an unincorporated labor organization . . . chartered by the American
    Federation of Labor-Congress of Industrial Organization . . . and composed of eleven (11)
    national and international building and construction trade unions.” Compl. ¶ 8. The plaintiff
    “has chartered more than 300 state and local building and construction trades councils,” which
    “consist[] of local building and construction trades unions that collectively represent more than
    three (3) million workers.” 
    Id.
     “[M]any” of these workers “have been employed or may seek
    employment by private contractors and subcontractors retained to construct buildings” in Oak
    Ridge, Tennessee. 
    Id.
    “On October 1, 1999,” the Department of Energy “entered into a contract with UT-
    Battelle, LLC (‘UT-Battelle’) . . . for the maintenance and operation of the Oak Ridge National
    Laboratory ([the] ‘ORNL’)” located in Oak Ridge, Tennessee. 
    Id. ¶ 11
    . In August of 2000, UT-
    Battelle submitted an infrastructure revitalization project for the ORNL, which would require the
    “construction of eleven new facilities and renovation of existing [facilities] for the ORNL.” 
    Id. ¶ 12
    . The plan called for the new facilities to be constructed by a private developer, who would
    then lease the facilities to UT-Battelle for use by the Department of Energy. 
    Id. ¶ 13
    . The
    Department of Energy approved this plan on March 21, 2001. 
    Id. ¶ 15
    .
    3
    Shortly thereafter, on April 19, 2001, UT-Battelle formed a new not-for-profit
    corporation called the UT-Battelle Development Corporation (“UT-Battelle Development”) to
    “implement[] the privately financed elements of the UT-Battelle plan.” 
    Id. ¶ 16
    . UT-Battelle
    Development solicited proposals “for the design, construction, and lease of . . . three privately
    funded facilities” in accordance with UT-Battelle’s revitalization plan. 
    Id. ¶ 17
    . Under that plan,
    the developer selected by UT-Battelle Development would “enter[] into a 25-year [g]round
    [l]ease of the real property on which the three buildings would be located, with a possible
    extension of not more than five additional years,” 
    id. ¶ 18
    , and would lease the facilities
    constructed on that real property to UT-Battelle Development, which would then sub-lease the
    facilities to UT-Battelle for ten-year terms, 
    id. ¶ 19
    .
    Pursuant to UT-Battelle’s revitalization plan, the Department of Energy “conveyed title
    to the parcel of land” on its site in Oak Ridge “where the three buildings would be located by
    quitclaim deed to [UT-Battelle Development]” on June 18, 2001. 
    Id. ¶ 21
    . The quitclaim deed
    “reserved to [the Department of Energy] the right to repurchase all or any part of the land
    conveyed and any improvements for a nominal consideration” so long as no sub-leases had been
    terminated prior to the expiration of UT-Battelle Development’s lease on the facilities. 
    Id.
     This
    conveyance led BCT president Edward C. Sullivan to submit a request to the Acting
    Administrator of the Department of Labor Wage and Hour Division “pursuant to 
    29 C.F.R. § 5.13
     for a determination whether the Davis-Bacon Act applie[d] to construction of the three
    privately-financed buildings on land conveyed by [the Department of Energy] to [UT-Battelle
    Development].” 
    Id. ¶ 22
    . Sullivan’s letter notwithstanding, UT-Battelle Development
    proceeded unabated with UT-Battelle’s revitalization plan, selecting a developer in August of
    2001 and executing a ground lease with the developer that same month. 
    Id. ¶¶ 23-24
    .
    4
    “Subsequently, [the Department of Energy] and [UT-Battelle
    Development] . . . submitted position statements on September 20, 2001, and September 28,
    2001, respectively,” in which they “argued strenuously that the Davis-Bacon Act [did] not apply
    to construction of the three privately-financed buildings” on the Department of Energy’s former
    property. 
    Id. ¶ 25
    . Over six months later, “in a letter dated May 13, 2002,” the Department of
    Labor’s Wage and Hour Division responded to Sullivan’s inquiry by requesting that the
    Department of Energy “submit a report within 30 days on the facts relating to the issue raised by
    [Sullivan’s inquiry] and a statement of [the Department of Energy’s] position regarding the
    applicability of the Davis-Bacon Act” to the three facilities under construction pursuant to UT-
    Battelle’s revitalization plan. 
    Id. ¶ 26
    . “To the best knowledge” of the plaintiff,
    “[the Department of Energy] never responded” to this request. 
    Id. ¶ 27
    .
    “[H]aving heard nothing further from [the Department of Energy] or [the Wage and Hour
    Division] for more than one year,” the plaintiff “sought a meeting in January [of] 2003 with
    representatives of [the Wage and Hour Division] to discuss the status of [Sullivan’s 2001
    inquiry]” regarding the application of the Davis-Bacon Act to the construction of new facilities at
    the Department of Energy’s Oak Ridge site. 
    Id. ¶ 28
    . “Sullivan followed up this meeting” 3 by
    submitting “a lengthy letter to Wage and Hour Administrator Tammy D. McCutchen dated
    January 30, 2003.” 
    Id. ¶ 29
    . In his letter, Sullivan contested the arguments raised by the
    Department of Energy and UT-Battelle Development in their 2001 letters “and presented
    additional arguments” in support of his position that the Davis-Bacon Act applied to the three
    buildings under construction at the Oak Ridge site. 
    Id. ¶ 29
    .
    3
    The plaintiff does not explicitly allege in its amended complaint that the Wage and Hour Division of the
    Department of Labor agreed to and actually did meet with Sullivan as requested, but the Court infers this to be the
    case based on the plaintiff’s allegation that Sullivan submitted a letter to the Wage and Hour Administrator
    “follow[ing] . . . this meeting.” Compl. ¶ 29.
    5
    Alfred B. Robinson, Jr., the Senior Policy Advisor to the Wage and Hour Administrator,
    responded to this letter in a correspondence of his own dated March 26, 2003. 
    Id. ¶ 30
    . In that
    correspondence, Robinson stated that the Department of Labor had asked the Department of
    Energy to provide additional documents to ensure a thorough review of the matter by the Wage
    and Hour Division. 
    Id.
     However, as Sullivan pointed out in his reply letter dated April 14, 2003,
    by that time “construction of the three buildings had begun and was nearing completion without
    application of the Davis-Bacon Act.” 
    Id. ¶ 32
    . Ultimately, the Wage and Hour Division
    “refused . . . to take any action with regard to [Sullivan’s 2001 inquiry] for the next two years,
    during which time construction of the three buildings was completed.” 
    Id. ¶ 34
    .
    While awaiting final action from the Wage and Hour Division, the plaintiff learned “in
    mid-2004 that [the Department of Energy] was contemplating an arrangement similar to the one
    executed for construction of the three buildings” on its site in Oak Ridge “for construction of a
    production-support complex and another building to house a visitors center, historical exhibits[,]
    and a 400-seat auditorium within [the Department of Energy’s] Y-12 National Security
    Complex, which is also located on the Oak Ridge [s]ite.” 
    Id. ¶ 35
    . After Robinson, “now
    Deputy Wage and Hour Administrator,” asked the Department of Energy to provide information
    regarding the possibility of a construction project involving the Y-12 National Security Complex
    at Sullivan’s request, 
    id. ¶ 37
    , R. Paul Detwiler, the Acting Deputy General Counsel for the
    National Nuclear Security Administration (the “NNSA”), informed Robinson in a letter dated
    October 3, 2005, “that NNSA was contemplating the sale of two parcels of real property it
    own[ed] at the [Department of Energy’s Oak Ridge site] to a private[,] non-profit corporation,”
    
    id. ¶ 38
    , which would use funds raised by the City of Oak Ridge Industrial Development Board
    “to purchase the property from [the Department of Energy] at fair market value and construct
    6
    two buildings that would be leased by [the entity managing the Y-12 National Security Complex]
    and paid for” by the NNSA, 
    id. ¶ 39
    . This response led Sullivan to renew his inquiry as to
    whether the Davis-Bacon Act applied to the buildings constructed pursuant to UT-Battelle’s
    revitalization plan on October 17, 2005. 
    Id. ¶ 41
    .
    Having received no response from Robinson, the plaintiff filed its initial complaint in this
    Court on April 14, 2006. Five days later, Robinson, “now Acting Wage and Hour Administrator,
    advised . . . Sullivan that[] because construction of the three buildings” at the Department of
    Energy’s Oak Ridge site was completed, there was no need to determine whether the Davis-
    Bacon Act applied to the construction contracts for those facilities. 
    Id. ¶ 44
    . In light of this
    letter, the plaintiff filed an amended complaint on April 21, 2006.
    In its amended complaint, the plaintiff seeks injunctive and declaratory relief against
    Secretary Solis for the Department of Labor’s alleged violations of the APA in failing to issue a
    determination as to whether the Davis-Bacon Act applied to the three facilities built pursuant to
    UT-Battelle’s revitalization plan. Am. Compl. ¶¶ 47-50, 54-60. It also seeks a writ of
    mandamus compelling Secretary Solis to issue such a determination pursuant to 
    28 U.S.C. § 1361
    . 
    Id. ¶¶ 51-53
    . Finally, the plaintiff seeks injunctive and declaratory relief against
    Secretary Chu for the Department of Energy’s alleged violations of the APA “by failing to insure
    that a provision mandating compliance with the prevailing wage requirement in the Davis-Bacon
    Act is incorporated in each of the contracts and subcontracts” for the facilities and improvements
    to be built at the Y-12 National Security Complex. 
    Id. ¶ 62
    ; see also 
    id. ¶¶ 68-70
     (claiming that a
    declaratory judgment against Secretary Chu should be entered based on the same facts). The
    plaintiff also seeks injunctive relief directly under the Davis-Bacon Act. 
    Id. ¶¶ 71-73
    .
    7
    In support of their joint motion to dismiss the plaintiff’s amended complaint, the
    defendants argue that the plaintiff’s claims against Secretary Solis arising from the Department
    of Labor’s alleged failure to follow the requirements of 
    5 U.S.C. § 555
    (b) (Counts I-III of the
    amended complaint) 4 should be dismissed because (1) insofar as the plaintiff seeks to “compel
    agency action unlawfully withheld or unreasonably delayed” pursuant to 
    5 U.S.C. § 706
    (1), it
    fails to state a claim for relief now that the Department of Labor has made a determination about
    the merits of the plaintiff’s request with Robinson’s April 19, 2006 letter, Defs.’ Mem. at 15-16,
    and (2) insofar as it seeks a writ of mandamus compelling Secretary Solis to fulfill her
    obligations under § 555(b), the plaintiff does not satisfy the stringent criteria for the issuance of
    the writ, id. at 16-24. Further, the defendants argue that the plaintiff’s claims against Secretary
    Chu under the APA (Counts VI-VII of the amended complaint) should be dismissed because the
    plaintiff purportedly (1) does not state a claim that falls within the limited waiver of sovereign
    immunity provided by the APA, id. at 25-28, and (2) has failed to exhaust the appropriate
    administrative remedies, id. at 28-30. The defendants do not advance any arguments regarding
    Counts IV, V, or VIII of the amended complaint. 5
    The plaintiff argues in opposition to the defendants’ motion that Robinson’s April 19
    letter does not constitute an actual response to the plaintiff’s request for a Davis-Bacon coverage
    determination, Pl.’s Opp’n at 11-13, and that the criteria for the issuance of a writ of mandamus
    4
    The plaintiff actually refers to the “First Cause of Action” through the “Eighth Cause of Action” in its amended
    complaint. For ease of reference, the Court will refer to the “First Cause of Action” as “Count I,” the “Second
    Cause of Action” as “Count II,” and so forth.
    5
    The defendants contend that the APA is “the sole basis for [the plaintiff’s] separate cause of action against the
    Secretary of Energy.” Defs.’ Mem. at 25. This is plainly in error. In Count VIII of the amended complaint, the
    plaintiffs assert that “by failing to insure that a stipulation was incorporated in each agreement for the lease of two
    buildings . . . requir[ing] all contractors and subcontractors to pay all mechanics and laborers employed directly on
    the site of the work in accordance with . . . the Davis-Bacon Act,” the “Secretary of Energy and
    lower[-]level [Department of Energy] officials violated . . . the Davis-Bacon Act.” Compl. ¶ 72. The defendants
    appear to have overlooked this claim in crafting their joint motion to dismiss.
    8
    as well as mandatory injunctive relief under the APA have been met in this instance, id. at 14-28.
    It argues strenuously that the Department of Energy’s determination that its contracts with the
    ORNL are not subject to the Davis-Bacon Act constitutes a “final agency action” subject to
    judicial review under the APA, id. at 29-34, and that exhaustion of administrative remedies is not
    required for actions under the Davis-Bacon Act, id. at 34-41. The defendants contest each of
    these points in their reply memorandum. Defs.’ Reply at 1-13.
    II. Standard of Review
    As set forth above, the defendants seek relief pursuant to both Federal Rule of Civil
    Procedure 12(b)(1) and Rule 12(b)(6). However, the defendants seek relief under Rule 12(b)(1)
    against Secretary Solis only with respect to the plaintiff’s petition for a writ of mandamus—an
    argument the Court does not reach on its merits for the reasons set forth below. See infra n.6.
    And while the defendants assert that the plaintiff’s claims against Secretary Chu should be
    dismissed both “for lack of subject[-]matter jurisdiction and for failure to state a claim upon
    which relief can be granted,” Defs.’ Mem. at 2, “[t]he judicial review provisions of the APA are
    not jurisdictional,” Air Courier Conference of Am. v. Am. Postal Workers Union AFL-CIO, 
    498 U.S. 517
    , 523 n.3 (1991). 6 Accordingly, the Court addresses the only standard of review actually
    6
    The Court recognizes that the District of Columbia Circuit has described the exhaustion requirements of the APA
    as “jurisdictional” on at least one prior occasion. See, e.g., Balt. Gas and Elec. Co. v. FERC, 
    252 F.3d 456
    , 458
    (D.C. Cir. 2001) (“The ban on judicial review of actions ‘committed to agency discretion by law’ [under 
    5 U.S.C. § 701
    (a)(2)] is jurisdictional. . . . That is, Congress has not given the courts the power to hear challenges to an
    agency’s exercise of the discretion with which Congress has entrusted it.”). However, the Supreme Court has since
    cautioned against “drive-by jurisdictional rulings that should be accorded no precedential effect on the question
    whether the federal court had authority to adjudicate the claim in suit,” Arbaugh v. Y&H Corp., 
    546 U.S. 500
    , 511
    (2006) (internal citation and quotation marks omitted), and the District of Columbia Circuit has more recently
    followed the lead of the Supreme Court in describing the requirements for judicial review set forth in the APA as
    non-jurisdictional. See, e.g., John Doe, Inc. v. DEA, 
    484 F.3d 561
    , 565 (D.C. Cir. 2007) (“When judicial review is
    sought under the APA, . . . the requirement of ‘final agency action’ is not jurisdictional.”); Center for Auto Safety v.
    Nat’l Highway Safety Admin., 
    452 F.3d 798
    , 805 (D.C. Cir. 2006) (“[I]n cases . . . in which judicial review is
    sought under the APA rather than a particular statute prescribing judicial review, the requirement of final agency
    action is not jurisdictional.”). As the exhaustion requirements of the APA are denominated as “except[ions],” 
    5 U.S.C. § 701
    (a), to the other “judicial review provisions of the APA,” Air Courier Conference, 
    498 U.S. at
    523 n.3,
    (continued . . . )
    9
    governing the disposition of the defendants’ motion: the standard governing a motion to dismiss
    for failure to state a claim under Rule 12(b)(6).
    On a motion to dismiss under Rule 12(b)(6), the Court “must treat the complaint’s factual
    allegations as true and must grant [the] plaintiff the benefit of all reasonable inferences from the
    facts alleged” in considering motions to dismiss under Rule 12(b)(6). Trudeau v. FTC, 
    456 F.3d 178
    , 193 (D.C. Cir. 2006) (internal citation and quotation marks omitted). The Court may only
    consider the facts alleged in the complaint, any documents attached as exhibits thereto, and
    matters subject to judicial notice in weighing the merits of the motion. EEOC v. St. Francis
    Xavier Parochial Sch., 
    117 F.3d 621
    , 624-25 (D.C. Cir. 1997). The Court’s focus is therefore
    restricted to the facts as alleged by the plaintiff, which must be sufficiently detailed “to raise a
    right to relief above the speculative level.” Bell Atl. Corp. v. Twombly, ___ U.S. ___, 
    127 S. Ct. 1955
    , 1965 (2007).
    III. Legal Analysis
    Based upon the positions taken by the parties in their respective memoranda of law, the
    issues before the Court fall into two discrete categories. The first issue, which runs through all
    of the arguments made by the parties with respect to the plaintiff’s claims against Secretary
    Solis, is whether the Department of Labor satisfied its regulatory obligations regarding the
    plaintiff’s coverage determination request when the Acting Wage and Hour Administrator issued
    his ruling on April 19, 2006, denying the plaintiff’s request as moot. The second issue is
    whether the Department of Energy’s decision to sell parcels of property to a private developer
    without ensuring that any construction contracts entered into by the developer observe the
    provisions of the Davis-Bacon Act gives rise to an immediate cause of action under the APA or
    by the statute itself, it stands to reason that those exceptions must be non-jurisdictional as well. The Court will
    therefore treat them as such.
    10
    is instead a preliminary decision that must first be challenged through the administrative process.
    The Court considers each of these issues in turn.
    A.       Claims Against Secretary Solis (Counts I-III)
    Counts I through III of the plaintiff’s amended complaint turn on the notion that the
    Department of Labor has unlawfully refused to rule on the merits of the plaintiff’s request for a
    determination as to whether the Davis-Bacon Act applies to the buildings constructed at the
    ORNL from 2001-2003. Pursuant to 
    5 U.S.C. § 555
    (b), an agency covered by the APA must
    “proceed to conclude a matter presented to it” “within a reasonable time,” and if the “agency
    action” is “unlawfully withheld or unreasonably delayed,” a “reviewing court” may compel the
    agency to act, 
    5 U.S.C. § 706
    (1). “Were it otherwise, agencies could effectively prevent judicial
    review of their policy determinations by simply refusing to take final action.” Cobell v. Norton,
    
    240 F.3d 1081
    , 1095 (D.C. Cir. 2001).
    Courts in this circuit “assess several factors in order to determine whether an agency’s
    delay is ‘unreasonable.’” In re Int’l Chem. Workers Union, 
    958 F.2d 1144
    , 1149 (D.C. Cir.
    1992).
    First, the court should ascertain the length of time that has elapsed
    since the agency came under a duty to act. . . . Second, the
    reasonableness of the delay must be judged in the context of the
    statute which authorizes the agency’s action. . . . Third, the court
    must      examine      the     consequences     of    the    agency’s
    delay. . . . [And f]inally, the court should give due consideration in
    the balance to any plea of administrative error, administrative
    convenience, practical difficulty in carrying out a legislative
    mandate, or need to prioritize in the face of limited resources.
    
    Id.
     (internal citation and quotation marks omitted).
    Here, more than five years passed from the date of the plaintiff’s first request for a
    coverage determination of the ORNL construction project undertaken by the Department of
    11
    Energy in 2001 and the filing of the plaintiff’s initial complaint in this Court. A delay of that
    duration is completely contrary to the statutory scheme giving rise to the Department of Labor’s
    oversight obligations, which presupposes that a determination as to whether the Davis-Bacon Act
    applies to a particular contract will take place prior to the execution of the contract, see 
    40 U.S.C. § 3142
     (setting forth requirements for prospective “contract[s] . . . to which the Federal
    Government . . . is a party” for the “construction, alteration, or repair . . . of public buildings and
    public works”), and provides no remedial relief other than that set forth in the contracts
    themselves, 
    id.
     §§ 3143-44. Indeed, the Acting Wage and Hour Administrator’s eventual
    determination that the plaintiff’s claim was moot suggests that the Department of Labor’s delay
    inured to its own benefit insofar as it obviated the need for any determination on the merits of the
    plaintiff’s coverage determination request, and there is no suggestion in the record before the
    Court that this delay was due to any special difficulties faced by the Department of Labor in
    rendering its decision. Thus, there is little question that, as of the date of the commencement of
    this lawsuit, the Department of Labor had “unreasonably delayed” its ruling on the plaintiff’s
    Davis-Bacon coverage determination request.
    The problem for the plaintiff is that its request to remedy this delay is moot. A claim is
    moot “if the judgment, regardless of which way it goes, will neither presently affect the parties’
    rights nor have a more-than-speculative chance of affecting them in the future,” Noble v.
    Sombrotto, 
    525 F.3d 1230
    , 1241 (D.C. Cir. 2008) (internal citation and quotation marks
    omitted); i.e., “when the issues presented are no longer ‘live’ or the parties lack a legally
    cognizable interest in the outcome,” County of Los Angeles v. Davis, 
    440 U.S. 625
    , 631 (1979)
    (internal citation and quotation marks omitted). The mootness doctrine is distinct from that of
    standing only in that “the standing inquiry remains focused on whether the party invoking
    12
    jurisdiction had the requisite stake in the outcome when the suit was filed,” Davis v. FEC, ___
    U.S. ___, ___, 
    128 S. Ct. 2759
    , 2769 (2008), whereas “[a] court determines whether a case is
    moot at the time of review and not at the time of filing,” Mogu v. Chertoff, 
    550 F. Supp. 2d 107
    ,
    110 n.5 (D.D.C. 2008).
    In Counts I through III of its amended complaint, the plaintiff asks that the Court compel
    a ruling from the Department of Labor on its Davis-Bacon coverage determination request. The
    Department of Labor has issued just such a ruling in the form of its Acting Wage and Hour
    Administrator’s April 19, 2006 letter. Thus, the plaintiff lacks any “legally cognizable interest”
    in having the Court determine whether the Department of Labor’s delay in responding to the
    plaintiff’s inquiries was unreasonable. In other words, its request for injunctive relief compelling
    Secretary Solis to act on its Davis-Bacon coverage determination request, whether articulated as
    a cause of action arising under the APA or as a petition for the writ of mandamus, is moot. See
    James Luterbach Constr. Co., Inc. v. Adamkus, 
    781 F.2d 599
    , 602 (11th Cir. 1986) (holding that
    request for declaratory judgment regarding applicability of federal regulations to construction
    contract by the Environmental Protection Agency was moot once construction was completed). 7
    The plaintiff argues that the Acting Wage and Hour Administrator’s April 19, 2006 letter
    did not “actually respond[]” to the plaintiff’s request for a Davis-Bacon coverage determination
    because the Acting Wage and Hour Administrator did not decide the merits of the plaintiff’s
    request, choosing instead to deny the request as moot. Pl.’s Opp’n at 12. But the plaintiff cites
    to no statutory or regulatory authority requiring the Department of Labor to rule on the merits of
    every wage determination request submitted to it. To the contrary, “an agency has ‘substantial
    7
    Because the plaintiff’s petition for the issuance of a writ of mandamus compelling Secretary Solis to consider the
    plaintiff’s request for a Davis-Bacon coverage determination is moot as well, the Court does not address the merits
    of that request.
    13
    discretion’ to decide whether to hear issues which might be precluded by mootness.” RT
    Commc’ns, Inc. v. FCC, 
    201 F.3d 1264
    , 1267 (10th Cir. 2000) (internal citation and quotation
    marks omitted). And while “[t]he subject matter of agencies’ jurisdiction naturally is not
    confined to cases or controversies inasmuch as agencies are creatures of [A]rticle I [of the
    Constitution]” as opposed to Article III, Tenn. Gas Pipeline Co. v. Fed. Power Comm’n, 
    606 F.2d 1373
    , 1380 (D.C. Cir. 1979), “[an] agency’s determination of mootness is informed by an
    examination of the proper institutional role of an adjudicatory body and a concern for judicial
    economy,” Climax Molybdenum Co. v. Sec’y of Labor, 
    703 F.2d 447
    , 451 (10th Cir. 1963).
    Consequently, “an agency acts within its discretion in refusing to hear a case that would be
    considered moot if tested under the Article III ‘case or controversy’ requirement.” 
    Id.
    It may be that the Acting Wage and Hour Administrator’s mootness determination is, as
    the plaintiff describes it, nothing more than “a post hoc rationalization for [the] Secretary of
    Labor’s unlawful and unreasonable failure to respond to [the plaintiff’s] June 25, 2001 request
    for a Davis-Bacon coverage determination.” Pl.’s Opp’n at 12. But if the Department of Labor
    has somehow abused its discretion in denying the plaintiff’s request as moot, the proper course
    of action is for the plaintiff to challenge the merits of that conclusion under 
    5 U.S.C. § 706
    (2),
    not to force the Department of Labor to issue new decisions in response to the plaintiff’s request
    until it receives one it deems satisfactory. Therefore, Counts I through III of the plaintiff’s
    amended complaint must be dismissed as moot.
    B.     Claims Against Secretary Chu (Counts VI-VII)
    Counts VI through VII of the plaintiff’s amended complaint concern the Department of
    Energy’s purported “fail[ure] to insure that a provision mandating compliance with the
    prevailing wage requirement in the Davis-Bacon Act is incorporated in each of the contracts and
    14
    subcontracts for construction of two buildings . . . within the boundaries of the Y-12 National
    Security Complex,” Compl. ¶ 62; see also 
    id. ¶ 69
     (same), which the plaintiff casts as an abuse of
    the Department of Energy’s discretion under the APA. As the Court noted above, the defendants
    seek to dismiss these claims on the grounds that the Department of Energy has not issued a “final
    decision” subject to APA review and that the plaintiff has not exhausted its administrative
    remedies. Defs.’ Mem. at 25-30; Defs.’ Reply at 6-13. “[T]he concepts of ‘final decision’ and
    ‘exhaustion’ are often closely intertwined and sometimes confused,” but the concepts “are not
    identical, . . . no matter how often they converge.” Daniels v. Union Pac. R. Co., 
    530 F.3d 936
    ,
    940 n.9 (D.C. Cir. 2008) (internal citation and quotation marks omitted). As the Supreme Court
    explained in Darby v. Cisneros, 
    509 U.S. 137
     (1993):
    The finality requirement is concerned with whether the initial
    decisionmaker has arrived at a definitive position on the issue that
    inflicts an actual, concrete injury; the exhaustion requirement
    generally refers to administrative and judicial procedures by which
    an injured party may seek review of an adverse decision and obtain
    a remedy if the decision is found to be unlawful or otherwise
    inappropriate.
    
    Id. at 144
    .
    With respect to the issue of finality, § 10(c) of the APA, codified as 
    5 U.S.C. § 704
    ,
    provides:
    Agency action made reviewable by statute and final agency action
    for which there is no other adequate remedy in a court are subject
    to judicial review. A preliminary, procedural, or intermediate
    agency action or ruling not directly reviewable is subject to review
    on the review of the final agency action. Except as otherwise
    expressly required by statute, agency action otherwise final is final
    for the purposes of this section whether or not there has been
    presented or determined an application for a declaratory order, for
    any form of reconsideration, or, unless the agency otherwise
    requires by rule and provides that the action meanwhile is
    inoperative, for an appeal to superior agency authority.
    15
    The APA defines the term “agency action” as “the whole or a part of an agency rule,
    order, license, sanction, relief, or the equivalent or denial thereof, or failure to act,” 
    5 U.S.C. § 551
    (13); i.e., actions by an agency that are “circumscribed” and “discrete.” Norton v. S. Utah
    Wilderness Alliance, 
    542 U.S. 55
    , 62 (2004). As for finality, “two requirements must be
    satisfied . . . : [f]irst, the action must mark the ‘consummation’ of the agency’s decisionmaking
    process, . . . [a]nd second, the action must be one by which rights or obligations have been
    determined, or from which legal consequences will flow.” Bennett v. Spear, 
    520 U.S. 176
    , 177-
    78 (1997) (internal citation and quotation marks omitted). “The core question is whether the
    agency has completed its decisionmaking process, and whether the result of that process is one
    that will directly affect the parties.” Franklin v. Massachusetts, 
    505 U.S. 788
    , 797 (1992); see
    also Nat’l Ass’n of Home Builders v. U.S. Army Corps of Eng’rs, 
    417 F.3d 1272
    , 1278 (D.C.
    Cir. 2005) (“[A]n agency action is final if . . . it is ‘definitive’ and has a ‘direct and
    immediate . . . effect on the day-to-day business’ of the party challenging it . . . .” (quoting FTC
    v. Standard Oil Co., 
    449 U.S. 232
    , 239 (1980) (internal citation and quotation marks omitted))).
    The defendant argues that the plaintiff has failed to allege any final agency action on the
    part of the Department of Energy “because they [were] subject to administrative review by the
    Secretary of Labor.” Defs.’ Mem. at 26-27. They note that pursuant to 
    29 C.F.R. § 5.13
    , “any
    party dissatisfied with an agency’s [Davis-Bacon Act] coverage determination [must] bring that
    dispute before the Wage and Hour Administrator,” 
    id. at 27
    , then “file an[y] appeal with the
    Administrative Review Board,” 
    id.
     at 28 (citing 
    29 C.F.R. § 7.9
    ), and contend that “[i]n light of
    [these] regulations, there is no question that the opinions of the [Department of Energy’s]
    contracting officials do not constitute a ‘final order’ of the Secretary of Energy that may be
    reviewed immediately by a federal district court,” 
    id.
    16
    This argument runs afoul of the plain language of § 704. That section expressly provides
    that “agency action otherwise final is final for the purposes of this section whether or not there
    has been . . . an appeal to superior agency authority” except where that review is (1) “require[d]
    by rule” and (2) the rule “provides that the action meanwhile is inoperative.” 
    5 U.S.C. § 704
    . As
    the plaintiff correctly notes, “[t]here is no provision in [the] Secretary of Labor’s regulations[]
    [that] provides a procedure that effectively renders inoperative an initial decision by [the
    Department of Labor] . . . concerning [the] application and interpretation of the Davis-Bacon Act
    when the Wage and Hour Administrator is asked to . . . issue a ruling or determination.” Pl.’s
    Opp’n at 40-41.
    The defendants do not dispute this point. Rather, they argue that the “Wage and Hour
    Administrator has the authority to require that the contracting agency terminate and resolicit the
    contract with the valid wage determination,” and may “require the agency to incorporate the
    valid wage determination retroactive to the beginning of the construction.” Defs.’ Reply at 12
    (citing 
    29 C.F.R. § 1.6
    (f) (2008)). Assuming this is so, that authority still does not satisfy
    § 704’s requirement “that the action . . . is inoperative” while it is subject to review by the
    “superior agency authority,” and therefore does not render any action by the Department of
    Energy “non-final” for purposes of § 704.
    Instead, it is the second requirement of finality—that the agency action have “a ‘direct
    and immediate . . . effect on the day-to-day business’ of the party challenging it,” Nat’l Ass’n of
    Home Builders, 417 F.3d at 1278 (quoting Standard Oil Co., 
    449 U.S. at 239
     (internal citation
    and quotation marks omitted))—that derails the plaintiff’s claims against Secretary Chu. The
    problem for the plaintiff is that it is neither involved in nor directly affected by the “Secretary of
    Energy’s sale of land [at the] NNSA’s Y-12 National Security Complex,” which is the only
    17
    “agency action” by the Department of Energy challenged by the plaintiff. Pl.’s Opp’n at 34. 8
    Instead, its “rights” will only be “determined,” Bennett, 520 U.S. at 178, when the purchaser of
    the land for sale at the Y-12 National Security Complex enters into a construction contract with a
    third party and either does or does not require the contractor to observe the requirements of the
    Davis-Bacon Act. Until the purchaser actually fails to impose this requirement on the
    construction contractor, there will be no “actual, concrete injury” suffered by the plaintiff.
    Darby v. Cisneros, 
    509 U.S. at 144
    .
    Due to the lapse in time between the date when the plaintiff’s opposition to the
    defendant’s motion to dismiss was filed (July 28, 2006) and the issuance of this memorandum
    opinion, 9 it may well be the case that the Department of Energy has since sold the parcels in
    question and that the purchaser has contracted for construction on those parcels. But even if this
    is the case, and even if the purchaser did not require the construction contractor to abide by the
    requirements of the Davis-Bacon Act, those events would not make any action taken by the
    Department of Energy final with respect to the plaintiff. Rather, under those circumstances the
    purchaser would be the entity engaging in some final action with respect to the plaintiff. Such an
    action would not, however, be subject to scrutiny under the APA because the statute provides
    8
    As the Court noted above, the plaintiff describes the “agency action” taken by the Department of Energy
    somewhat differently in its amended complaint, identifying the “agency action” at issue as the Department of
    Energy’s “fail[ure] to insure that a provision mandating compliance with the prevailing wage requirement in the
    Davis-Bacon Act is incorporated in each of the contracts and subcontracts for construction of two buildings . . .
    within the boundaries of the Y-12 National Security Complex.” Compl. ¶ 62; see also id. ¶ 69 (same). But whether
    framed as a “fail[ure] to insure” a particular result or as a simple sale of real estate, the bottom line is the same: the
    rights of the plaintiff’s constituents will not be “denie[d],” nor their “legal relationship” with the owner of any land
    upon which buildings are being constructed at the Y-12 National Security Complex “fixe[d],” Reliable Automatic
    Sprinkler Co., Inc. v. Consumer Prod. Safety Comm’n, 
    324 F.3d 726
    , 731 (D.C. Cir. 2003), until the owner
    contracts for construction of the building without requiring the contractor to observe the requirements of the Davis-
    Bacon Act.
    9
    The long delay in the issuance of this memorandum opinion was due in large part to the high volume of cases
    pending before this Court and in part due to an internal recordkeeping error in this Court’s Chambers that has since
    been corrected. The Court regrets any inconvenience caused by this delay.
    18
    relief only to “[a] person suffering legal wrong . . . or adversely affected or aggrieved by agency
    action,” 
    5 U.S.C. § 702
     (emphasis added), and the purchaser of the buildings in question, at least
    according to the plaintiff, would have been a “private[,] non-profit corporation,” Compl. ¶ 38.
    This does not, however, foreclose relief under the APA to the plaintiff. As the plaintiff is
    well aware, it can request a determination from the Department of Labor as to whether the
    Davis-Bacon Act applies to any construction contracts entered into by purchasers of any real
    property at the Y-12 National Security Complex pursuant to 
    29 C.F.R. § 5.13
    . If the Department
    of Labor does not rule on the plaintiff’s request in a timely manner, the plaintiff can request
    relief from this Court pursuant to 
    5 U.S.C. § 706
    (1). And if the Department of Labor issues a
    ruling that the plaintiff believes is arbitrary and capricious, it can request relief from this Court
    pursuant to 
    5 U.S.C. § 706
    (2), just as it has done in Counts IV and V of its amended complaint.
    But the Court cannot enjoin or declare unlawful activity by an agency that does not definitively
    injure the plaintiff in any way. Counts VI throughVII of the amended complaint must therefore
    be dismissed.
    IV. Conclusion
    In some respects, the arguments resolved by the Court today are much ado about nothing.
    Counts IV and V of the plaintiff’s amended complaint, which the defendants have not
    challenged, directly address the reasonableness of the Acting Wage and Hour Secretary’s
    decision to reject the plaintiff’s request for a Davis-Bacon coverage determination as moot. And
    if the Court were to conclude that the Davis-Bacon Act gives rise to a private right of action,
    Count VIII of the amended complaint would put the coverage determination issue squarely
    before the Court, which would appear to be the result desired by the plaintiff all along.
    Therefore, in addition to granting the defendants’ motion to dismiss and dismissing Counts I
    19
    through III and VI and VII of the plaintiff’s amended complaint, the Court will order the parties
    to file a joint proposed briefing schedule to address the viability of Counts IV, V, and VIII of the
    amended complaint so that the Court can bring this case to a final resolution.
    SO ORDERED this 4th day of March, 2009. 10
    REGGIE B. WALTON
    United States District Judge
    10
    An order will be entered contemporaneously with this memorandum opinion (1) granting the defendants’ motion
    to dismiss, (2) dismissing Counts I through III and V through VII of the plaintiff’s amended complaint, and (3)
    directing the parties to file a joint proposed briefing schedule within thirty days of the entry of the order.
    20
    

Document Info

Docket Number: Civil Action No. 2006-0677

Judges: Judge Reggie B. Walton

Filed Date: 3/4/2009

Precedential Status: Precedential

Modified Date: 10/30/2014

Authorities (22)

RT Communications, Inc. v. Federal Communications Commission , 201 F.3d 1264 ( 2000 )

Balt Gas Elec Co v. FERC , 252 F.3d 456 ( 2001 )

Cobell, Elouise v. Norton, Gale A. , 240 F.3d 1081 ( 2001 )

Trudeau v. Federal Trade Commission , 456 F.3d 178 ( 2006 )

Ctr Auto Sfty v. Natl Hwy Traf Sfty , 452 F.3d 798 ( 2006 )

John Doe, Inc. v. Drug Enforcement Administration , 484 F.3d 561 ( 2007 )

County of Los Angeles v. Davis , 99 S. Ct. 1379 ( 1979 )

Reliable Automatic Sprinkler Co. v. Consumer Product Safety ... , 324 F.3d 726 ( 2003 )

In Re International Chemical Workers Union , 958 F.2d 1144 ( 1992 )

Equal Employment Opportunity Commission v. St. Francis ... , 117 F.3d 621 ( 1997 )

tennessee-gas-pipeline-company-a-division-of-tenneco-inc-v-federal , 606 F.2d 1373 ( 1979 )

Daniels v. Union Pacific Railroad , 530 F.3d 936 ( 2008 )

Noble v. Sombrotto , 525 F.3d 1230 ( 2008 )

Mogu v. Chertoff , 550 F. Supp. 2d 107 ( 2008 )

Federal Trade Commission v. Standard Oil Co. , 101 S. Ct. 488 ( 1980 )

Air Courier Conference of America v. American Postal ... , 111 S. Ct. 913 ( 1991 )

Franklin v. Massachusetts , 112 S. Ct. 2767 ( 1992 )

Darby v. Cisneros , 113 S. Ct. 2539 ( 1993 )

Norton v. Southern Utah Wilderness Alliance , 124 S. Ct. 2373 ( 2004 )

Arbaugh v. Y & H Corp. , 126 S. Ct. 1235 ( 2006 )

View All Authorities »