Fisheries Survival Fund v. Jewell ( 2018 )


Menu:
  •                             UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    )
    FISHERIES SURVIVAL FUND, et al.,              )
    )
    Plaintiffs,                     )
    )
    v.                                      )       Case No. 16-cv-2409 (TSC)
    )
    SALLY JEWELL, et al.,                         )
    )
    Defendants.                     )
    )
    MEMORANDUM OPINION
    This case concerns a Bureau of Ocean Energy Management (“BOEM”) plan to lease a
    nautical area off the coast of New York to Defendant-Intervenor Statoil Wind US, LLC
    (“Statoil”), for development of a wind energy facility. Plaintiffs 1, including the Fisheries
    Survival Fund, claim that in issuing the lease, BOEM violated the National Environmental
    Policy Act (“NEPA”), the Outer Continental Shelf Lands Act (“OCSLA”), and the
    Administrative Procedure Act (“APA”). Plaintiffs filed a motion for preliminary injunction,
    which this court denied. Memorandum Opinion, ECF No. 26. Now before the court are
    Plaintiffs’ Motion for Summary Judgment, ECF No. 39, Defendant-Intervenor’s Cross-Motion
    for Summary Judgment, ECF No. 40, and Defendants’ Motion for Summary Judgment, ECF No.
    42. For the reasons stated herein, Plaintiffs’ motion will be DENIED, Defendants’ motion will
    be GRANTED, and Defendant-Intervenor’s motion will be DENIED as moot.
    1
    The other Plaintiffs are: Borough of Barnegat Light, NJ; the Town Dock; Seafreeze Shoreside;
    Sea Fresh USA; Rhode Island Fishermen’s Alliance; Garden State Seafood Association; Long
    Island Commercial Fishing Association; the Town of Narragansett, RI; the Narragansett
    Chamber of Commerce; the City of New Bedford, MA; and the Fishermen’s Dock Co-Operative
    of Point Pleasant.
    1
    I.      BACKGROUND
    A. Statutory & Regulatory Framework
    1. OCSLA
    As amended by the Energy Policy Act of 2005, Pub. L. 109-58, 119 Stat. 594 (2005),
    OCSLA authorizes BOEM to issue leases, easements, or rights-of-way for offshore renewable
    energy projects. 43 U.S.C. § 1337(p)(1)(C). In exercising this authority, BOEM is required to
    consult with the U.S. Coast Guard and other relevant federal agencies, and must consider several
    factors that include, inter alia, safety, protection of the environment, prevention of waste,
    conservation of natural resources, national security interests, and—critically—“the location of . .
    . a lease. . . for an area of the outer Continental Shelf” and “any other use of the sea or seabed,
    including use for a fishery, a sealane, a potential site of a deepwater port, or navigation.” 
    Id. § 1337(p)(4)(A)–(L)
    & (J)(i)–(ii).
    2. NEPA
    NEPA was enacted to establish “a national policy [to] encourage productive and
    enjoyable harmony between man and his environment,” to “prevent or eliminate damage to the
    environment,” and “to enrich the understanding of the ecological systems and natural resources
    important to the Nation.” 42 U.S.C. § 4321; see also Dep’t of Transp. v. Pub. Citizen, 
    541 U.S. 752
    , 756–57 (2004). NEPA serves these goals by imposing “procedural requirements on federal
    agencies with a particular focus on requiring agencies to undertake analyses of the environmental
    impact of their proposals and actions.” Pub. 
    Citizen, 541 U.S. at 756
    –57; Theodore Roosevelt
    Conservation P’ship v. Salazar, 
    616 F.3d 497
    , 503 (D.C. Cir. 2010) (noting that “[NEPA] is an
    ‘essentially procedural’ statute, meant to ensure ‘a fully informed and well-considered decision,
    not necessarily’ the best decision”) (quoting Vermont Yankee Nuclear Power Corp. v. Natural
    2
    Res. Def. Council, Inc., 
    435 U.S. 519
    , 558 (1978)). The statute requires that the relevant agency
    (1) “consider every significant aspect of the environmental impact of a proposed action,”
    Baltimore Gas & Elec. Co. v. Nat. Res. Def. Council, Inc., 
    462 U.S. 87
    , 97 (1983) (quoting
    Vermont 
    Yankee, 435 U.S. at 553
    ), and (2) “inform the public that the agency has considered
    environmental concerns in its decisionmaking process.” Weinberger v. Catholic Action of
    Hawaii/Peace Educ. Project, 
    454 U.S. 139
    , 143 (1981).
    “NEPA requires that when an agency proposes a ‘major Federal action[] significantly
    affecting the quality of the human environment,’ the agency must prepare and circulate for
    public review and comment an environmental impact statement (“EIS”) that examines the
    environmental impact of the proposed action and compares the action to other alternatives.”
    Theodore Roosevelt Conservation 
    P’ship, 616 F.3d at 503
    (quoting 42 U.S.C. § 4332(2)(C)); see
    also Sierra Club v. Van Antwerp, 
    661 F.3d 1147
    , 1153 (D.C. Cir. 2011). Nevertheless, an EIS is
    not always necessary. See Public Citizen v. NHTSA, 
    848 F.2d 256
    , 265 (1988) (“NEPA requires
    the preparation of a complete EIS for ‘major federal actions significantly affecting the quality of
    the human environment.’”) (emphasis in original). Agencies may “prepare a more limited
    document”—known as an Environmental Assessment (“EA”)—if a proposed action is neither
    categorically excluded from the EIS requirement nor of the kind that would normally require an
    EIS. See 40 C.F.R. §§ 1501.4(a)–(b); Pub. 
    Citizen, 541 U.S. at 757
    (“CEQ regulations allow an
    agency to prepare . . . an [EA] . . . if the agency’s proposed action neither is categorically
    excluded from the requirement to produce an EIS nor would clearly require the production of an
    EIS.”). An EA is a “concise public document” intended to “[b]riefly provide sufficient evidence
    and analysis for determining whether to prepare an environmental impact statement or a finding
    of no significant impact.” 40 C.F.R. §§ 1508.9(a)(1); Pub. 
    Citizen, 541 U.S. at 757
    –58. Where
    3
    preparation of an EA leads an agency to decide that an EIS is unnecessary, the agency is required
    to issue a “finding of no significant impact”—“a document . . . briefly presenting the reasons
    why an action . . . will not have a significant effect on the human environment and for which an
    environmental impact statement will therefore not be prepared.” 40 C.F. R. §§ 1501.4(e),
    1508.13.
    B. BOEM’s Leasing Process
    In accordance with OCSLA, BOEM promulgated a series of regulations governing the
    leasing and management of offshore renewable energy projects. See 30 C.F.R. § 585.200–234.
    Pursuant to these regulations, the commercial leasing process may be initiated by both solicited
    and unsolicited applications. A solicited application is one in which BOEM itself identifies the
    potential development site and initiates the leasing process by publishing a notice of Request for
    Interest (“RFI”) or a Call for Information and Nominations in the Federal Register. See 30
    C.F.R. §§ 585.210, 585.211(a). An unsolicited application is one in which a potential developer
    applies for a site not otherwise under consideration by BOEM. See 30 C.F.R. § 585.230.
    Upon receiving an unsolicited request, BOEM publishes a RFI to seek public comment
    and determine whether there is competitive interest from other developers. 
    Id. § 585.231(b).
    If
    there is competitive interest, BOEM proceeds with the competitive process. 
    Id. § 585.231(c)(1).
    Otherwise, it publishes a notice of Determination of No Competitive Interest and follows a
    separate procedure. 
    Id. § 585.231(d)–(i).
    Regardless of the procedure adopted in any case,
    BOEM must consult throughout the leasing process with state task forces, other state and local
    representatives, and with representatives of Indian Tribes whose interests may be affected. 
    Id. §§ 585.102(e),
    585.211(a)–(d), 585.231(e).
    4
    Before issuing a lease, BOEM follows a four-step procedure, issuing a Call for
    Information and Nominations, completing the Area Identification process, publishing a Proposed
    Sale Notice, and publishing a Final Sale Notice. 
    Id. § 585.211(a)–(d).
    Once BOEM has issued a
    lease, the lessee must submit a Site Assessment Plan for review before any assessment activity
    takes place. 
    Id. §§ 585.601,
    585.605. Even after completing a site assessment, a lessee may not
    begin construction until it has submitted, and BOEM has approved, a Construction and
    Operations Plan. 
    Id. § 585.620(c).
    BOEM can accept, reject, or accept with modifications a
    lessee’s Site Assessment or Construction and Operations Plan, 
    id. §§ 585.613,
    585.628, and must
    analyze the potential environmental impacts of the plans. See 
    id. §§ 585.613,
    585.620(c).
    C. Lease OCS–A 0512
    In September 2011, a consortium of energy companies consisting of the New York Power
    Authority, Long Island Power Authority, and Consolidated Edison (collectively, “the
    Consortium”), proposed developing a wind energy facility covering approximately 81,500 acres
    of ocean off the coast of New York. NYAR-0074853, 0074854. Due to safety concerns about
    shipping lanes, the Consortium later amended the request to cover 81,130 acres, or about 127
    square miles. NYAR-0074140. The Consortium claims the proposed project has “the potential
    to be the largest offshore wind energy facility in the United States.” NYAR-0074853. Since the
    Consortium’s request was unsolicited, BOEM initiated an RFI on January 4, 2013 to gauge other
    companies’ interest in developing the area. 78 Fed. Reg. 760-02 (Jan. 4, 2013). The RFI also
    requested that “interested and affected parties comment and provide information about site
    conditions and multiple uses within the area identified in this notice that would be relevant to the
    proposed project or its impacts.” 
    Id. at 760
    –61.
    5
    After reviewing nominations of interest and acknowledging competitive interest in the
    area, BOEM initiated the competitive leasing process. Compl. ¶ 54. On May 28, 2014, BOEM
    published (1) a Notice of Intent to prepare an EA and (2) a Call for Information and Nominations
    from companies interested in commercial wind energy leases in the proposed wind farm area. 79
    Fed. Reg. 30,643–44 (May 28, 2014); 79 Fed. Reg. 30,645. BOEM also began the “Area
    Identification” process to “identify offshore locations that appear most suitable for wind energy
    development” and “designat[e] . . . an area with the greatest wind resource potential, minimal
    environmental and space use conflict, and possible alternatives for environmental analysis.”
    NYAR-0044172; 30 C.F.R. § 585.211(b). BOEM completed this process on March 14, 2016,
    thereby marking the area as available for lease. See NYAR-0045776.
    On June 6, 2016, BOEM published a “Proposed Sale Notice for Commercial Leasing for
    Wind Power on the Outer Continental Shelf Offshore New York” in the Federal Register. 81
    Fed. Reg. 36,336 (June 6, 2016) (NYAR-0047230). The Proposed Sale Notice included a sixty-
    day comment period, which closed on August 6, 2016. 
    Id. On June
    6, BOEM also published an
    EA, along with a Notice of Availability for a thirty-day public comment period. 81 Fed. Reg.
    36,344 (June 6, 2016) (NYAR-0047238). According to the Notice of Availability, the EA
    focused on assessing the potential impact of and reasonable alternatives to “commercial wind
    lease issuance, site characterization activities (geophysical, geotechnical, archaeological, and
    biological surveys) and site assessment activities (including the installation and operation of a
    meteorological tower and/or buoys).” 
    Id. The Notice
    also stated that “[s]hould a lessee propose
    to construct a commercial wind facility through submission of a [Construction and Operations
    Plan], BOEM would conduct a separate site and project-specific [NEPA] analysis, likely an
    [EIS], and would provide additional opportunities for public involvement . . . .” 
    Id. After 6
    requests from Plaintiff Fisheries Survival Fund and other groups, BOEM extended the public
    comment period to July 13, 2016. Compl. ¶ 62.
    On October 31, 2016, BOEM published the Final Sale Notice for the lease sale of the
    area. 81 Fed. Reg. 75,429 (Oct. 31, 2016) (NYAR-0075588). BOEM determined that fourteen
    different bidders were “legally, technically, and financially qualified to hold a commercial wind
    lease” and to bid in the auction. 
    Id. at 75,430
    (NYAR-0075589). BOEM also published its
    revised EA, which found no significant impact for commercial wind lease issuance and related
    activities within the area. 81 Fed. Reg. 75,438 (Oct. 31, 2016). The finding of no significant
    impact concluded that “the reasonably foreseeable environmental impacts . . . would not
    significantly impact the quality of the human environment,” and “therefore, the preparation of an
    environmental impact statement [was] not required.” Id.; see also NYAR-0074241. The EA
    stated that “BOEM reduces its impacts early in the planning process by conducting site
    identification through public stakeholder meetings to avoid areas that may have significant
    impacts on the environment, including marine mammals.” NYAR-0074521.
    On December 15 and 16, BOEM held a lease auction, which Statoil won with a
    $42,469,725 bid. See Commercial Lease of Submerged Lands for Renewable Energy
    Development on Continental Shelf (NYAR-0046753). BOEM and Statoil executed the lease on
    March 15, 2017. NYAR-0046759. The lease grants Statoil the exclusive right to conduct site
    characterization activities and, within one year of lease issuance, to propose a Site Assessment
    Plan. NYAR-0046753; 30 C.F.R. §§ 585.601, 585.605. If BOEM approves the Plan, Statoil will
    have five years to engage in site assessment—including conducting surveys and using towers or
    buoys to evaluate wind resources—and propose a Construction and Operations Plan, 30 C.F.R.
    §§ 585.235(a)(2), 585.601(b), which must include detailed data and information to support the
    7
    plan for the wind facility, and proposals for minimizing environmental impact. 30 C.F.R. §
    585.626(b). BOEM would then conduct “an appropriate NEPA analysis” based on the
    information included in the Construction and Operations Plan, before deciding whether to
    approve the Plan. 30 C.F.R. § 585.628(b).
    II.     LEGAL STANDARD
    The APA requires courts to “set aside any agency action that is ‘arbitrary and capricious,
    an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A). In
    assessing a summary judgment motion brought under the APA, courts are “not empowered to
    substitute [their] judgment for that of the agency.” Beyond Nuclear v. U.S Dep’t of Energy, 
    233 F. Supp. 3d 40
    , 47 (D.D.C. 2017) (quoting Citizens to Preserve Overton Park, Inc. v. Volpe, 
    401 U.S. 402
    , 416 (1971)). Rather, the court’s role is to “determine whether or not as a matter of law
    the evidence in the administrative record permitted the agency to make the decision it did.” Coe
    v. McHugh, 
    968 F. Supp. 2d 237
    , 239–40 (D.D.C. 2013) (quoting Occidental Eng’g Co. v. INS,
    
    753 F.2d 766
    , 769–70 (9th Cir. 1985)).
    Generally, an agency action is arbitrary if:
    the agency has relied on factors which Congress has not intended it to consider,
    entirely failed to consider an important aspect of the problem, offered an
    explanation for its decision that runs counter to the evidence before the agency, or
    is so implausible that it could not be ascribed to a difference in view or the product
    of agency expertise.
    Delaware Riverkeeper Network v. FERC, 
    753 F.3d 1304
    , 1313 (D.C. Cir. 2014) (quoting Motor
    Vehicle Mfrs. Ass’n of the U.S., Inc. v. State Farm Mut. Auto. Ins., 
    463 U.S. 29
    , 43 (1983)). This
    standard also applies when assessing compliance with NEPA and the adequacy of an EIS. City of
    Olmsted Falls, OH v. FAA, 
    292 F.3d 261
    , 269 (D.C. Cir. 2002) (citing Marsh v. Oregon Natural
    Resources Council, 
    490 U.S. 360
    , 376 (1989)). “Courts may not use their review of an agency’s
    8
    environmental analysis to second-guess substantive decisions committed to the discretion of the
    agency,” Del. Riverkeeper 
    Network, 753 F.3d at 1313
    , and must instead “review the EIS to
    ‘ensure that the agency took a “hard look” at the environmental consequences of its decision to
    go forward with the project.’” Olmsted 
    Falls, 292 F.3d at 269
    (quoting City of Grapevine, Tex. v.
    DOT, 
    17 F.3d 1502
    , 1503–04 (D.C. Cir. 1994)).
    III.    DISCUSSION
    The parties’ motions for summary judgment present two broad issues: (1) whether
    Defendants violated NEPA by improperly segmenting their NEPA analysis, failing to consider a
    reasonable range of alternatives, and failing to prepare an EIS in deciding the site of the
    proposed wind farm area; and (2) whether Defendants violated their obligations under OCSLA
    by failing to consider a number of relevant factors in the site selection process, failing to
    consider those factors in proceeding with the lease sale, and/or acting in accordance with a
    regulatory procedure that exceeds the authority granted under OCSLA. Pls. Mot. Summ. J. at
    38–47, 47–54, ECF No. 39-1; Def. Intervenors Mot. Summ. J. at 17–24, 24–32, ECF No. 40;
    Defs. Mot. Summ. J. at 29–44, 45–54, ECF No. 42. The parties also raise issues of standing and
    constitutional ripeness. See, e.g., ECF No. 42 at 22–28. As these latter issues present
    jurisdictional questions, this court will address them at the threshold.
    A. Standing
    Plaintiffs, who bear the burden of establishing standing, see Kokkonen v. Guardian Life
    Ins. Co. of Am., 
    511 U.S. 375
    , 377 (1994), claim a procedural injury relating to BOEM’s
    issuance of the lease. Plaintiffs contend that “the heart of [their] injury” results from BOEM’s
    decision to issue the lease on key fishing grounds “prior to obtaining any public input or
    considering fishing, environmental, or safety interests with respect to the physical boundaries of
    9
    that area,” in violation of NEPA and OCSLA. ECF No. 39-1 at 37. Plaintiffs further allege that
    they will be injured by the “exploration and development of a wind farm” in the area that will
    likely follow from issuance of the lease and “directly damage the natural resources in that area, .
    . . physically preclude . . . fisheries from operating fishing vessels in that area, . . . [and] pose
    navigational safety issues.” ECF No. 39-1 at 37.
    Defendants respond that Plaintiffs’ allegations of harm do not establish standing “because
    they all relate to the possible future approval of the construction of a wind energy facility,” rather
    than “the site characterization and site assessment activities associated with issuance of the
    lease.” Defs. Opp’n Mot. at 23, ECF No. 43. According to Defendants, Plaintiffs’ alleged future
    injuries “fail to demonstrate that the construction of a wind energy facility is substantially
    probable,” ECF No. 53 at 3 (emphasis in original), insofar as the construction depends on future
    events—including the preparation and approval of multiple reports and a development plan—
    that have not occurred and may not occur for six years, if at all. ECF No. 43 at 24.
    Standing is a jurisdictional prerequisite—an “irreducible constitutional minimum” that
    requires a plaintiff to show: (1) an “injury in fact” that is “concrete and particularized” and
    “actual or imminent, not conjectural or hypothetical”; (2) that the injury is “fairly traceable to the
    challenged action of the defendant”; and (3) that it is “likely, as opposed to merely speculative,
    that the injury will be redressed by a favorable decision.” Chamber of Commerce of U.S. v.
    E.P.A., 
    642 F.3d 192
    , 200 (D.C. Cir. 2011) (quoting Bennett v. Spear, 
    520 U.S. 154
    , 167 (1997));
    Summers v. Earth Island Inst., 
    555 U.S. 488
    , 492 (2009) (noting that standing doctrine “requires
    federal courts to satisfy themselves that ‘the plaintiff has alleged such a personal stake in the
    outcome of the controversy’ as to warrant his invocation of federal-court jurisdiction.”) (quoting
    Warth v. Seldin, 
    422 U.S. 490
    , 498 (1975)).
    10
    When a party alleges injury to its procedural rights, “courts relax the normal standards of
    redressability and imminence.” Sierra Club v. Fed. Energy Regulatory Comm’n, 
    827 F.3d 59
    , 65
    (D.C. Cir. 2016). In such cases, “the primary focus of the standing inquiry is not the imminence
    or redressability of the injury to the plaintiff, but whether a plaintiff who has suffered a personal
    and particularized injury has sued a defendant who has caused that injury.” City of Dania Beach
    v. FAA, 
    485 F.3d 1181
    , 1185 (D.C. Cir. 2007) (quoting Fla. Audubon Soc’y v. Bentsen, 
    94 F.3d 68
    , 664 (D.C. Cir. 1996) (en banc)). “To establish injury-in-fact in a ‘procedural injury’ case,
    petitioners must show that ‘the government act performed without the procedure in question will
    cause a distinct risk to a particularized interest of the plaintiff.’” 
    Id. at 1185
    (quoting Fla.
    Audubon 
    Soc’y, 94 F.3d at 663
    ). In other words, “[a] violation of the procedural requirements of
    a statute is sufficient to grant a plaintiff standing to sue, so long as the procedural requirement
    was designed to protect some threatened concrete interest of the plaintiff.” City of Dania 
    Beach, 485 F.3d at 1185
    (quoting City of Waukesha v. EPA, 
    320 F.3d 228
    , 234 (D.C. Cir. 2003)); see
    also Sierra 
    Club, 827 F.3d at 65
    (“[A]n adequate causal chain must contain at least two links:
    one connecting the omitted [NEPA analysis] to some substantive government decision that may
    have been wrongly decided because of the lack of [proper NEPA analysis] and one connecting
    that substantive decision to the plaintiff’s particularized injury.”). A plaintiff alleging a violation
    of some procedural right “never has to prove that if he had received the procedure the substantive
    result would have been altered,” and need only show “that the procedural step was connected to
    the substantive result.” Sugar Cane Growers Cooperative v. Veneman, 
    289 F.3d 89
    , 95 (D.C.
    Cir. 2002).
    Plaintiffs are entitled to bring their OCSLA and NEPA claims under a procedural
    standing theory because they have demonstrated a threat to a sufficiently concrete and
    11
    particularized interest in the wind farm area, and the alleged procedural deficiencies are
    connected to a substantive governmental decision—issuing the lease—that is in turn connected
    to a risk of harm to Plaintiffs’ identified interests. See Dania 
    Beach, 485 F.3d at 1185
    (describing need for distinct risk to particularized interest in procedural injury context); Sierra
    
    Club, 827 F.3d at 65
    (discussing components of an adequate causal chain in procedural injury
    context). The Plaintiffs in this case include those who use or depend on the use of the wind farm
    area and the natural resources contained therein for fishing, navigation, and associated economic
    and recreational benefits. See ECF No. 39-1 at 15–17, 21–25. The use or enjoyment of wildlife
    is a cognizable interest for standing purposes, see Ctr. for Biological Diversity v. U.S.
    Department of Interior, 
    563 F.3d 466
    , 479 (D.C. Cir. 2009) (“CBD”) (citing Lujan v. Defenders
    of Wildlife, 
    504 U.S. 555
    , 562–63 (1992)) (affirming the appropriateness of an interest in
    enjoyment of wildlife), and here, that interest is concrete and particularized insofar as it refers to
    specific marine species and activities within a distinct, identified area. See 
    Bentsen, 94 F.3d at 667
    –68 (emphasizing need for particularization of alleged environmental interests in form of
    geographic nexus to claim of particularized injury). Furthermore, Plaintiffs claim—in multiple
    declarations—that their interest in the use or enjoyment of the area under the lease will be
    damaged or altogether precluded by development. See, e.g., ECF No. 3-1 at 2–3, 5–9, 133–40,
    115–16.
    The court notes that the lease only authorizes site characterization and assessment, and
    that construction—the development phase involving the most transformative activity—has not
    yet received approval, and depends on multiple contingencies occurring over a six-year period.
    See ECF No. 43 at 24; ECF No. 53 at 11. Nevertheless, this fact does not render Plaintiffs’
    alleged injury too speculative or hypothetical for purposes of standing. The relevant injury here
    12
    is the injury that Plaintiffs allege regarding the development process as a whole, including the
    lease sale phase. While the lease itself may not authorize construction of the wind farm, it is
    undeniably a milestone in the lessee’s plan to transform an area currently used for industrial and
    recreational fishing into an area that Plaintiffs allege is likely to be rendered unsuitable for such
    purposes. Although the lease does not dispel all contingencies associated with the project, it
    does increase the probability that any planned development will occur in the designated area. In
    other words, Plaintiffs have alleged a particularized threat to their concrete interest in use of the
    leased area insofar as their stated concern is the progress of a development project affecting that
    interest.
    It also appears that the challenged leasing decision is causally connected to an increased
    risk of harm to Plaintiffs’ particularized interests, insofar as the decision increases the risk to
    their enjoyment of the marine life in the area likely to be affected by the development. See 
    CBD, 563 F.3d at 479
    (approving procedural theory of standing because “adoption of an irrationally
    based Leasing Program could cause a substantial increase in the risk to [Petitioners’] enjoyment
    of the animals affected by the offshore drilling”); see 
    also 827 F.3d at 65
    (noting need to connect
    substantive decision that may have been wrongly decided to a particularized injury). For these
    reasons, Plaintiffs have successfully articulated a procedural theory of Article III standing. 2
    2
    While the analysis of the standing issue applies directly to the municipal plaintiffs, the
    associational plaintiffs must satisfy additional requirements. Organizations have standing to sue
    on behalf of their members if: “(1) at least one of [the organization’s] members would have
    standing to sue in his or her own right; (2) ‘the interests it seeks to protect are germane to the
    organization’s purpose’; and (3) ‘neither the claim asserted nor the relief requested requires the
    participation of individual members in the lawsuit.’” Sierra Club v. FERC, 
    827 F.3d 59
    , 65 (D.C.
    Cir. 2016) (quoting WildEarth Guardians v. Jewell, 
    738 F.3d 298
    , 305 (D.C. Cir. 2013)). Here,
    the associational plaintiffs have standing to sue on behalf of their members, whose declarations
    demonstrate that they share the interest and injury identified above. See, e.g., ECF No. 3-1 at 1–
    5, 133–40, 115–16. Moreover, the associational plaintiffs’ organizational purposes—broadly, to
    promote the interests of Atlantic fishermen—plainly relate to the fishing industry and commercial
    13
    B. Ripeness of NEPA Claims
    Plaintiffs contend that their NEPA 3 claims are ripe because “the Lease precludes any
    further action for the most critical stage of the leasing process—project siting—and constitutes
    an irretrievable commitment of resources,” the key trigger for an agency’s NEPA obligations.
    Pls. Opp. to Def. & Def. Intervenor Mot. at 23, ECF No. 48. Defendants argue that the NEPA
    claims are not ripe because they “allege that BOEM failed to properly analyze the environmental
    impacts of constructing and operating a wind energy facility,” even though BOEM has yet to
    approve the construction or operation of such a facility. ECF No. 43 at 25.
    The ripeness doctrine is related to standing, and requires that a litigant’s claims be
    “constitutionally and prudentially ripe,” so as to protect (1) “the agency’s interest in crystallizing
    its policy before that policy is subjected to judicial review,” (2) “the court’s interests in avoiding
    unnecessary adjudication and in deciding issues in a concrete setting,” and (3) “the petitioner’s
    interest in prompt consideration of allegedly unlawful agency action.” Nevada v. Department of
    Energy, 
    457 F.3d 78
    , 84 (D.C. Cir. 2006) (quoting Eagle–Picher Indus., Inc. v. EPA, 
    759 F.2d 905
    , 915 (D.C. Cir. 1985)). In “determining whether a dispute is ripe for review, courts consider
    ‘both the fitness of the issues for judicial decision and the hardship to the parties of withholding
    court consideration.’” Am. Tort Reform Ass’n v. Occupational Safety & Health Admin., 
    738 F.3d 387
    , 396 (D.C. Cir. 2013) (quoting Abbott Laboratories v. Gardner, 
    387 U.S. 136
    , 149 (1967)).
    or recreational fishing. See ECF No. 39 at 2, 34 (describing plaintiffs and organizational purpose);
    Ctr. for Sustainable Economy v. Jewell, 
    779 F.3d 588
    , 597 (D.C. Cir. 2015) (“CSE”) (“The
    germaneness requirement [of associational standing] mandates ‘pertinence between litigation
    subject and organizational purpose.’”) (quoting Humane Soc. of the United States v. Hodel, 
    840 F.2d 45
    , 58 (D.C. Cir. 1988)).
    3
    Plaintiffs’ OCSLA claims “concern OCSLA requirements that are implicated at the initial stage
    of a leasing program,” and are therefore ripe. 
    CBD, 563 F.3d at 484
    .
    14
    Courts must also consider: “(1) whether delayed review would cause hardship to the plaintiffs;
    (2) whether judicial intervention would inappropriately interfere with further administrative
    action; and (3) whether the courts would benefit from further factual development of the issues
    presented.” 
    Nevada, 457 F.3d at 84
    (quoting Ohio Forestry Ass’n, Inc. v. Sierra Club, 
    523 U.S. 726
    , 733 (1998)). Typically, “[a] claim is not ripe for adjudication if it rests upon contingent
    future events that may not occur as anticipated, or indeed may not occur at all.” 
    Nevada, 457 F.3d at 85
    (quoting Texas v. United States, 
    523 U.S. 296
    , 300 (1998)).
    An agency’s NEPA obligations mature “only once it reaches a ‘critical stage of a decision
    which will result in irreversible and irretrievable commitments of resources to an action that will
    affect the environment.’” 
    CBD, 563 F.3d at 480
    (quoting Wyoming Outdoor Council v. United
    States Forest Service, 
    165 F.3d 43
    , 49 (D.C. Cir. 1999) (“Wyo. Outdoor Council II”)). Cases
    involving multiple-stage leasing programs—arising in the oil and gas context—indicate that an
    agency reaches this critical stage when it “no longer retain[s] the authority to preclude all surface
    disturbing activities subsequent to issuing an oil and gas lease,” such that “an EIS assessing the
    full environmental consequences of leasing must be prepared before commitment to any actions
    that might affect the quality of the human environment.” Wyo. Outdoor Council 
    II, 165 F.3d at 49
    (alteration in original) (quoting Sierra Club v. Peterson, 
    717 F.2d 1409
    , 1415 (D.C. Cir.
    1983)); see also Conner v. Burford, 
    848 F.2d 1441
    , 1451 (9th Cir. 1988) (“[U]nless surface-
    disturbing activities may be absolutely precluded, the government must complete an EIS before
    it makes an irretrievable commitment of resources . . . .”). In other words, lease issuance triggers
    15
    NEPA obligations unless the issuing agency “retain[s] the authority to preclude all surface
    disturbing activities.” Wyo. Outdoor Council 
    II, 165 F.3d at 49
    . 4
    Though the parties agree that the above legal standard is appropriate, they disagree on
    how it should be applied. Plaintiffs contend that to avoid making an irreversible commitment of
    resources, the agency making a lease sale must unilaterally retain “the absolute right to prevent
    all surface-disturbing activity.” ECF No. 48 at 22 (quoting 
    Conner, 848 F.2d at 1449
    ) (emphasis
    in original). They argue that BOEM does not retain the absolute right because its ability to
    cancel a lease is limited by lease criteria and Statoil’s regulatory compliance. ECF No. 48 at 11–
    12. Defendants respond that the lease language establishes BOEM’s absolute authority to
    preclude activity in the leased area, that Plaintiffs misunderstand the applicable legal standard in
    contending otherwise, and that “because BOEM retains the authority to deny a [Construction and
    Operations Plan], the issuance of the lease to Statoil was not an irreversible and irretrievable
    commitment of resources.” ECF No. 53 at 14, 15. In the court’s view, the applicable regulations
    and the terms of the lease preclude Statoil from engaging in any construction activities, and vest
    complete authority in BOEM to preclude such activity in the leased area before the Construction
    and Operations Plan is approved. Therefore, issuing the lease does not constitute an irreversible
    and irretrievable commitment of resources. See Wyo. Outdoor Council 
    II, 165 F.3d at 49
    .
    Accordingly, Plaintiffs’ NEPA claims must be dismissed as unripe at this stage.
    4
    Plaintiffs do not address ripeness in their memorandum in support of their motion for summary
    judgment. In their opposition to Defendants’ motion, Plaintiffs appear to question in passing
    whether the standard in cases involving oil and gas leases should apply in the Outer Continental
    Shelf context or to renewable energy leases. ECF No. 48 at 19. Nevertheless, they do not offer
    any argument as to why the court should decline to apply that standard, and do not offer any
    alternative standard, instead opting to argue their position from within the oil and gas lease legal
    framework, which the court finds analogous and appropriate.
    16
    On its own, the lease at issue does no more than grant Statoil the exclusive right to submit
    a Site Assessment Plan and Construction and Operations Plan to BOEM for approval. NYAR-
    0046754. No activity is permitted absent the submission and approval of these plans, NYAR-
    0046754, and the lease provides that (1) “[the] lease does not, by itself, authorize any activity
    within the leased area,” (2) “the Lessor will decide whether to approve a SAP or COP in
    accordance with the applicable regulations in 30 CFR Part 585,” and (3) “the Lessor retains the
    right to disapprove a SAP or COP based on the Lessor’s determination that the proposed
    activities would have unacceptable environmental consequences . . . .” NYAR-0046754.
    Moreover, BOEM regulations provide that a lease can be cancelled if, after “notice and
    opportunity for a hearing,” BOEM determines that “continued activity under the lease or grant”:
    (i)     Would cause serious harm or damage to natural resources; life (including
    human and wildlife); property; the marine, coastal, or human environment;
    or sites, structures, or objects of historical or archaeological significance;
    and
    (ii)    That the threat of harm or damage would not disappear or decrease to an
    acceptable extent within a reasonable period of time; and
    (iii)   The advantages of cancellation outweigh the advantages of continuing the
    lease or grant in force.
    30 C.F.R. § 585.437(b)(4)(i)–(iii).
    The thrust of Plaintiffs’ first argument is that BOEM’s authority to preclude activity in
    the wind farm area cannot be absolute if it is subject to conditions, and that the criteria set forth
    above are conditions. Thus, Plaintiffs argue, the lease represents a commitment of resources, and
    therefore their NEPA claims are ripe. See 
    Conner, 848 F.2d at 1449
    –50 (noting that leases
    permitting surface-disturbing activities subject to conditions do not retain authority to absolutely
    preclude activities and, therefore, constitute a commitment of resources); 
    Peterson, 717 F.2d at 1412
    , 1414–15 (same).
    17
    Though it is true that the criteria may be “conditions” in the sense that BOEM must make
    certain findings—after notice and an opportunity for a hearing—before disapproving a
    Construction and Operations Plan and/or cancelling a lease, it does not necessarily follow that
    “BOEM’s own regulations preclude BOEM from changing its mind unilaterally.” ECF No. 48 at
    20. That is because none of the “conditions” at issue involve or presuppose any transfer of
    authority to prevent lease activities out of BOEM’s hands, which was not the case with the leases
    in Peterson and Conner.
    Peterson involved an oil and gas leasing program for certain National Forests,
    administered by the United States Forest Service and Department of the Interior 
    (“Department”). 717 F.2d at 1410
    . The leasing program divided lands into those designated as “highly
    environmentally sensitive” and “non-highly environmentally sensitive.” 
    Id. Leases contained
    either a “No Surface Occupancy Stipulation (NSO Stipulation)”—preventing any surface
    activities without departmental approval—or stipulations representing “reasonable,” “mitigating”
    conditions on drilling and other activities, but with no ability to bar those activities entirely. 
    Id. at 1412,
    1414. The D.C. Circuit concluded that the Department had failed to comply with NEPA
    by neglecting to conduct a full EIS before issuing leases that relinquished the authority to
    prevent all 
    development. 717 F.2d at 1414
    . Critical to the Circuit’s reasoning was that under the
    terms of the leases without NSO Stipulations, “the government could not deny an application for
    a permit to drill, but could only enforce the lease stipulations to control and/or mitigate any
    environmental damage which result[s] from the drilling.” 
    Id. at 1414
    & n.7 (emphasis in
    original).
    Conner involved the same legal issue in virtually identical factual 
    circumstances. 848 F.2d at 1444
    –46 (describing NEPA challenge to leasing program that issued NSO or non-NSO
    18
    oil and gas leases in forest land). Citing Peterson, the Ninth Circuit concluded that issuing non-
    NSO oil and gas leases effectively traded the authority to preclude all activity for the authority to
    regulate that activity, and such a trade required an EIS. See 
    id. at 1450
    (emphasis added). 5
    In this case, the criteria at issue do not contemplate trading preclusion authority for
    regulatory authority. The criteria do not alter the fact that Statoil must submit Site Assessment
    and Construction and Operations Plans before starting development, or that BOEM retains the
    authority to prevent any activity in the wind farm area by rejecting any Site Assessment or
    Constructions and Operations Plan that Statoil submits. The criteria stem from BOEM’s
    commitment to “NEPA’s goal of insuring that federal agencies infuse in project planning a
    thorough consideration of environmental values,” 
    id. at 1451,
    and ensuring that NEPA-related
    preclusion authority is exercised according to due process and for NEPA-related reasons.
    Accordingly, the presence of these “conditions” does not transform the lease into an irretrievable
    commitment of resources. 6
    Plaintiffs also contend that their NEPA claims are ripe because the lease is the final word
    “for the most critical stage of the leasing process—the siting of development,” ECF No. 48 at 14,
    and therefore constitutes an irretrievable commitment of resources. But this contention
    5
    Although these cases do not address ripeness per se, their analysis applies here because an
    agency’s irretrievable commitment of resources also triggers the obligation to conduct an EIS. 
    See 848 F.2d at 1450
    ; 
    CBD, 563 F.3d at 480
    .
    6
    Plaintiffs also contend that 30 C.F.R. § 585.628(f)(2) constitutes a “condition” on BOEM’s right
    to absolutely preclude development activities, because it indicates that BOEM will give reasons
    for any disapproval of a Construction and Operations Plan and allow the lessee to resubmit without
    the identified defects. 
    Id. However, as
    with the other criteria described above, Section
    585.628(f)(2) does not appear to require BOEM to relinquish authority to preclude all activity
    within the leased area. Though the provision does grant the lessee an opportunity to cure any
    defects in the Plan, it does not confer any right to engage in the equivalent of surface disturbing
    activities, which still require approval from BOEM.
    19
    misrepresents the nature of the lease, which makes no promises other than giving the lessee the
    exclusive right to survey the area and submit a proposal. See NYAR-0046754, 0046760.
    Indeed, at least part of the purpose of conducting site characterization in the leased area is to
    determine whether the site is suitable for the proposed purpose. NYAR-0074262 (“After lease
    issuance, a lessee would conduct surveys and, if authorized to do so pursuant to an approved
    SAP, install meteorological measurement devices to characterize the site’s environmental and
    socioeconomic resources and conditions and to assess the wind resources in the proposed lease
    area. A lessee would collect this information to determine whether the site is suitable for
    commercial development . . . .”). Against this background, the lease sale does not represent the
    final word on anything, nor does it commit any resources, even putting aside the question of
    whether it does so irretrievably. 7
    7
    Plaintiffs also note in passing that several of the cases addressing ripeness in the context of multi-
    stage leasing programs identified lease issuance as the point when NEPA claims ripen. ECF No.
    48 at 10–11 & n.8; see also, e.g., 
    CBD, 563 F.3d at 480
    (identifying specific lease sales as point
    of irreversible and irretrievable commitment). But this interpretation is misleading. Wyoming
    Outdoor Council II—the case upon which more recent cases such as CBD and CSE relied—
    described lease issuance as the critical stage for ripeness only as part of an explicit application of
    the Peterson rule. See Wyoming Outdoor Council 
    II, 165 F.3d at 49
    . As this court has already
    discussed, the heart of the Peterson rule is the question of whether the agency retains the authority
    to preclude all surface disturbing activity. 
    Peterson, 717 F.2d at 1414-15
    ; see also Wyoming
    Outdoor Council v. Bosworth, 
    284 F. Supp. 2d 81
    , 92–93 (D.D.C. 2003) (noting that Wyoming II
    “based its irreversible commitment finding on the fact that the agency had chosen not to retain its
    authority to preclude all surface-disturbing activities after lease issuance,” that the NEPA claim in
    the case before it was unripe where lease issuance did not involve relinquishment of preclusive
    authority or resolution of development contingency, and that ripeness is a “flexible” doctrine, not
    “a per se rule”). In Wyoming II, CBD, and CSE, the agency could not have relinquished its
    preclusive authority because it had yet to take any specific action under the leasing program. See
    
    CBD, 563 F.3d at 480
    (noting that agency “had only approved the Leasing Program at issue,” and
    that “[n]o lease-sales had yet occurred”); 
    CSE, 779 F.3d at 599
    –600 (same); Wyo. Outdoor Council
    
    II, 165 F.3d at 49
    –50 (same). In Peterson and Conner, ripeness turned on lease issuance because
    the agency relinquished authority by the terms of the leases. 
    Peterson, 717 F.2d at 1414
    (noting
    that since the “decision to allow surface disturbing activities” was made “at the leasing stage,”
    NEPA obligations attached at that point) (emphasis in original). But in this case—as in
    Bosworth—the lease does not relinquish preclusive authority. 
    See 284 F. Supp. 2d at 93
    .
    20
    For these reasons, Plaintiffs’ NEPA claims are not ripe.
    C. OCSLA Violations
    Plaintiffs allege that Defendants violated OCSLA by (1) failing to properly consider and
    provide for fishing, safety, conservation of natural resources, and navigation during both the site
    selection and the lease issuance process; and (2) adopting a set of regulations that on their face
    exceed the authority granted by OCSLA. ECF No. 39 at 47, 51–52. Statoil responds that (1) the
    regulations BOEM adopted were a reasonable interpretation of OCSLA’s congressional
    mandate, ECF No. 40 at 17–19; (2) BOEM considered all relevant OCSLA factors at all relevant
    stages—through stakeholder meetings and public commentary—before reasonably deciding to
    adopt some changes and defer consideration of certain potential risks, ECF No. 40 at 19–22; and
    (3) BOEM’s analysis of potential alternatives to development of the wind farm area was
    adequate. ECF No. 40 at 22–28. BOEM echoes these contentions and further argues that
    Plaintiffs’ OCSLA claims are procedurally barred by their failure to observe the statutorily
    mandated sixty-day waiting period. ECF No. 42 at 28. The court agrees that Plaintiffs’ OCSLA
    claims are barred for noncompliance with the statute.
    OCSLA establishes a private right of action for persons “having a valid legal interest
    which is or may be adversely affected” by an agency’s violation of OCSLA or its associated
    regulations. 43 U.S.C. § 1349(a)(1). OCSLA also provides that “[e]xcept as provided in
    paragraph (3) of this subsection, no action may be commenced . . . prior to sixty days after the
    plaintiff has given notice of the alleged violation, in writing, under oath, to the Secretary.” 43
    U.S.C. § 1349(a)(2)(A). Compliance with the sixty-day notice period is mandatory, although
    Section 1349(a)(3) provides an exception when “the alleged violation constitutes an imminent
    threat to the public health or safety or would immediately affect a legal interest of the plaintiff.”
    21
    
    Id. § 1349(a)(3).
    See Hallstrom v. Tillamook County, 
    493 U.S. 20
    , 23 n.1, 26, 31 (1989)
    (holding that nearly identical sixty-day notice provision in Resource Conservation and Recovery
    Act represented a mandatory precondition to suit and expressly noting similarity to 43 U.S.C. §
    1349(a)(2)); Duke Energy Field Servs. Assets, LLC v. Fed. Energy Regulatory Comm’n, 150 F.
    Supp. 2d 150, 156 (D.D.C. 2001) (“[T]he citizen suit provision in the instant [OCSLA] case
    plainly bars all cases which do not comply with the provision . . . .”) (emphasis in original).
    Thus, unless they face an imminent threat to public health or safety or some immediate effect on
    a legal interest, plaintiffs must comply with the sixty-day notice provision. Hornbeck Offshore
    Servs., LLC v. Salazar, 
    696 F. Supp. 2d 627
    , 633 (E.D. La. 2010) (citing Duke Energy, 150 F.
    Supp. 2d at 156).
    Plaintiffs advance two arguments in support of their compliance with OCSLA’s pre-suit
    requirements: (1) since the lease auction occurred only forty-five days after the Final Sale Notice
    was published, they did not have sixty days to notify Defendants of their claims before the Final
    Sale and should therefore be excused from compliance with the sixty-day requirement, ECF No.
    48 at 23–24; and (2) their claims fall within Section 1349(a)(3)’s exception because the lease
    “immediately affect[s] a legal interest of the plaintiff” insofar as it grants Statoil a property
    interest, along with “attendant rights to condition the access of others,” and firmly determines the
    boundaries of the wind farm area. ECF No. 48 at 24.
    Neither of these arguments is persuasive. The fact that there were fewer than sixty days
    between publication of the Final Sale Notice and the lease sale does not excuse Plaintiffs from
    compliance with the sixty-day notice period. They have identified no provision of the statute
    that requires BOEM to schedule its lease sales to accommodate potential claimants, and the plain
    language of Section 1349(a)(1) contains no ambiguity that is susceptible to such an
    22
    interpretation. Rather, as in Hallstrom, Plaintiffs essentially argue that the statute “should be
    given a flexible or pragmatic construction” that would accommodate their view of the 
    equities. 493 U.S. at 26
    . The court declines to engage in such an exercise. Congress has already
    addressed this situation in Section 1349(a)(1), which contains “explicit and unambiguous”
    language that “must be given palpable effect.” Duke 
    Energy, 150 F. Supp. 2d at 155
    ; see also
    
    Hallstrom, 493 U.S. at 27
    (noting in analogous context that “[g]iving full effect to the words of
    the statute preserves the compromise struck by Congress”). Against this background, the court
    sees no justification for adopting an interpretation of Section 1349(a)(1) that “flatly contradicts
    the language of the statute.” 
    Hallstrom, 493 U.S. at 27
    .
    Moreover, Congress provided for situations in which the rigid sixty-day notice
    requirement of Section 1349(a)(1) would create unacceptable hardship by carving out an
    exception for exigent circumstances. See 43 U.S.C. § 1349(a)(3). To be eligible for that
    exception, a plaintiff must (1) provide notice of the alleged violation, and (2) demonstrate an
    imminent threat to public health or safety or that the alleged violation would immediately affect
    a plaintiff’s legal interests. 43 U.S.C. § 1349(a)(3). While Plaintiffs in this case provided notice,
    and even signaled their intention to invoke the provision in their notice letter, ECF No. 3-1 at
    148, they have failed to demonstrate any imminent threat to public health or safety, or any
    immediate effect on their legal interests that would authorize their claim under Section
    1349(a)(3). As noted earlier, the lease has no immediate effect except to grant Statoil the right to
    submit an Site Assessment Plan and, potentially, a Construction and Operations Plan. Nothing
    in the lease authorizes Statoil to exclude others from the leased area or condition access to that
    area, and to the extent that the lease grants a type of property interest to Statoil, this grant fails to
    23
    satisfy Section 1349(a)(3), which concerns the effect on a plaintiff’s legal interest. See 43 U.S.C.
    § 1349(a)(3).
    This case therefore differs from those in which the requirements of Section 1349(a)(3)
    were met. See Chevron, U.S.A., Inc. v. FERC, 
    193 F. Supp. 2d 54
    , 64–65 (D.D.C. 2002) (finding
    Section 1349(a)(3) satisfied where agency intended to “disclose the plaintiffs’ commercially
    sensitive information within five days,” which “would detrimentally affect the plaintiffs’ legal
    interest in preserving the confidentiality of the information and in maintaining its suits
    [challenging disclosure orders]”); 
    Hornbeck, 696 F. Supp. 2d at 636
    n.8 (noting in alternative
    that immediate loss of business relationships satisfied requirements of Section 1349(a)(3)).
    Here, compliance with the sixty-day notice period would not have caused any immediate injury
    or loss of a legal right. Accordingly, Plaintiffs cannot invoke Section 1349(a)(3), and their
    OCSLA claims are barred for failure to comply with the terms of Section 1349(a)(1).
    IV.    CONCLUSION
    For the foregoing reasons, the court hereby concludes that Defendants’ Motion for
    Summary Judgment will be GRANTED, Plaintiffs’ Motion for Summary Judgment will be
    DENIED, and Defendant-Intervenor’s Motion will be DENIED AS MOOT. An appropriate
    order accompanies this memorandum opinion.
    Date: September 30, 2018                                      2018.09.30
    23:28:44
    -04'00'
    TANYA S. CHUTKAN
    United States District Judge
    24
    

Document Info

Docket Number: Civil Action No. 2016-2409

Judges: Judge Tanya S. Chutkan

Filed Date: 9/30/2018

Precedential Status: Precedential

Modified Date: 10/1/2018

Authorities (33)

james-r-conner-v-robert-burford-director-bureau-of-land-management , 848 F.2d 1441 ( 1988 )

occidental-engineering-company-a-delaware-corporation-and-yi-ling-wang-v , 753 F.2d 766 ( 1985 )

Center for Biological Diversity v. US Dept. of Interior , 563 F.3d 466 ( 2009 )

THEODORE ROOSEVELT CONSERVATION v. Salazar , 616 F.3d 497 ( 2010 )

City Dania Beach FL v. FAA , 485 F.3d 1181 ( 2007 )

Sierra Club v. Van Antwerp , 661 F.3d 1147 ( 2011 )

City of Grapevine, Texas v. Department of Transportation, ... , 17 F.3d 1502 ( 1994 )

Sierra Club v. R. Max Peterson, in His Official Capacity as ... , 717 F.2d 1409 ( 1983 )

City of Olmsted Falls, Ohio v. Federal Aviation ... , 292 F.3d 261 ( 2002 )

Humane Society of the United States v. Donald P. Hodel, ... , 840 F.2d 45 ( 1988 )

Sugar Cane Growers Cooperative of Florida v. Veneman , 289 F.3d 89 ( 2002 )

Wyoming Outdoor Council v. United States Forest Service , 165 F.3d 43 ( 1999 )

City of Waukesha v. Environmental Protection Agency , 320 F.3d 228 ( 2003 )

eagle-picher-industries-inc-v-united-states-environmental-protection , 759 F.2d 905 ( 1985 )

public-citizen-v-national-highway-traffic-safety-administration-ford , 848 F.2d 256 ( 1988 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... , 103 S. Ct. 2856 ( 1983 )

Department of Transportation v. Public Citizen , 124 S. Ct. 2204 ( 2004 )

Wyoming Outdoor Council v. Bosworth , 284 F. Supp. 2d 81 ( 2003 )

Hornbeck Offshore Services, L.L.C. v. Salazar , 696 F. Supp. 2d 627 ( 2010 )

Chevron U.S.A., Inc. v. Federal Energy Regulatory Commission , 193 F. Supp. 2d 54 ( 2002 )