Federal Energy Regulatory Commission v. City Power Marketing, LLC , 199 F. Supp. 3d 218 ( 2016 )


Menu:
  •                             UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    FEDERAL ENERGY REGULATORY
    COMMISSION,
    Plaintiff,
    v.                                         Civil Action No. 15-1428 (JDB)
    CITY POWER MARKETING, LLC, and
    K. STEPHEN TSINGAS,
    Defendants.
    MEMORANDUM OPINION
    City Power Marketing, LLC, an energy-trading firm founded by K. Stephen Tsingas,
    engaged in “virtual trading” in wholesale electricity markets. Virtual traders do not actually supply
    or receive electricity but instead stake out market positions that are effectively bets on how
    electricity prices will change over time. In other words, they engage in a kind of arbitrage. And
    their efforts are generally thought to improve the overall efficiency of energy markets.
    According to the Federal Energy Regulatory Commission (FERC or Commission),
    however, in July 2010 City Power engaged in a series of manipulative virtual trades that hurt the
    market while generating more than $1 million of profit for City Power. In essence, City Power
    found a way to place trades that had no risk of earning or losing money on the basis of price
    changes but that nonetheless triggered a financial credit for City Power from the market operator.
    After a lengthy investigation, FERC concluded that these trades constituted a fraudulent scheme
    that violated the Commission’s Anti-Manipulation Rule, 18 C.F.R. § 1c.2. FERC also concluded
    that by failing to reveal the existence of certain archived instant messages during the investigation,
    City Power had violated the Commission’s Market Behavior Rule 3, 18 C.F.R. § 35.41(b), which
    requires truthful communications by parties subject to FERC’s authority. FERC ordered City
    1
    Power to disgorge its profits and assessed penalties of $15 million on City Power and Tsingas.
    Disputing their liability, City Power and Tsingas did not pay. As provided for in the Federal Power
    Act, FERC therefore filed this action seeking an order affirming its penalty assessment.
    City Power and Tsingas—whom the Court will collectively call “City Power,” unless
    context indicates otherwise—have moved to dismiss, arguing that FERC’s claims under both the
    Anti-Manipulation Rule and Market Behavior Rule 3 fail as a matter of law. City Power also
    argues that this case should be treated like a normal civil action subject to the Federal Rules of
    Civil Procedure, not a summary review of agency action. The Court largely agrees with City
    Power on this latter point, and will follow the normal course of district-court adjudication. But the
    Court disagrees that FERC’s claims are unsound. Assuming the truth of FERC’s allegations, as
    the Court must at this stage, FERC has stated plausible claims under both the Anti-Manipulation
    Rule and Market Behavior Rule 3. City Power’s motion to dismiss will therefore be denied.
    BACKGROUND
    I. PJM’S WHOLESALE ELECTRICITY MARKET
    This case concerns allegedly illegal trading in the wholesale electricity market run by PJM
    Interconnection, LLC (PJM).        PJM is the independent, nonprofit Regional Transmission
    Organization (RTO) that administers the electric grid in a 13-state region that extends from North
    Carolina to New Jersey to Illinois and includes the District of Columbia. As part of administering
    the grid, PJM operates a wholesale electricity auction of the sort recently described by the Supreme
    Court:
    These wholesale auctions serve to balance supply and demand on a
    continuous basis, producing prices for electricity that reflect its value at
    given locations and times throughout each day. Such a real-time
    mechanism is needed because, unlike most products, electricity cannot be
    stored effectively. Suppliers must generate—every day, hour, and minute—
    the exact amount of power necessary to meet demand from the utilities and
    2
    other “load-serving entities” (LSEs) that buy power at wholesale for resale
    to users. To ensure that happens, wholesale market operators [such as PJM]
    obtain (1) orders from LSEs indicating how much electricity they need at
    various times and (2) bids from generators specifying how much electricity
    they can produce at those times and how much they will charge for it.
    Operators accept the generators’ bids in order of cost (least expensive first)
    until they satisfy the LSEs’ total demand. The price of the last unit of
    electricity purchased is then paid to every supplier whose bid was accepted,
    regardless of its actual offer; and the total cost is split among the LSEs in
    proportion to how much energy they have ordered. So, for example,
    suppose that at 9 a.m. on August 15 four plants serving Washington, D.C.
    can each produce some amount of electricity for, respectively, $10/unit,
    $20/unit, $30/unit, and $40/unit. And suppose that LSEs’ demand at that
    time and place is met after the operator accepts the three cheapest bids. The
    first three generators would then all receive $30/unit.
    FERC v. Elec. Power Supply Ass’n, 
    136 S. Ct. 760
    , 768–69 (2016). The clearing price at a
    particular location, or “node,” on the PJM grid is called the “locational marginal price” (LMP).
    PJM operates a so-called “dual settlement market,” meaning that it runs two rounds of
    bidding for each operating day. It first runs a “day-ahead market,” which “allows market
    participants to secure prices for electric energy the day before the operating day and hedge against
    price fluctuations that can occur in real time. One day ahead of actual dispatch, participants submit
    supply offers and demand bids for energy. These bids are applied to each hour of the day and for
    each pricing location [i.e., node] on the system.” FERC, Energy Primer: A Handbook of Energy
    Market Basics 95 (Nov. 2015). PJM takes all of the bids and offers, crunches the numbers, and
    determines what the clearing price—the “day-ahead LMP”—will be at each node. Generators who
    offered to supply energy for less than the clearing price are committed to supply that energy and
    are paid the day-ahead LMP; buyers who bid to purchase energy for more than the clearing price
    are committed to their purchases and pay the day-ahead LMP. 
    Id. The next
    day’s actual supply of and demand for electricity, however, might be different
    from what the day-ahead market presumed. A generation unit might unexpectedly fail, affecting
    supply, or the weather might be much different than predicted, affecting demand. PJM therefore
    3
    also runs a “real-time market” designed “to meet energy needs within each hour of the current
    day.” 
    Id. (The real-time
    market is also sometimes called the “spot market” or “balancing market.”)
    As the name suggests, offers and bids in this market are made in real time. “Real-time LMPs are
    calculated at five-minute intervals based on actual grid operating conditions as calculated in PJM’s
    market systems.” 
    Id. PJM’s wholesale
    market is not restricted to those engaging in “physical transactions,” i.e.,
    those who will actually deliver or actually receive electricity. Traders who neither have nor want
    actual megawatts can engage in “virtual transactions.”
    A virtual transaction does not require generation to be dispatched or load to
    be served. Rather, it allows a market participant to arbitrage day-ahead
    versus real-time prices by either purchasing or selling a position in the day-
    ahead market, and then doing the opposite in an equal volume at the same
    location in the real-time market, thereby taking no physical position when
    the system is dispatched.
    City Power Mktg., LLC, 152 FERC ¶ 61,012 at P 17 n.38 (2015) (“Penalty Assessment Order”).
    Suppose, for example, that a trader believes that the real-time LMP at a particular node will
    be higher than the day-ahead LMP. (Perhaps the trader has reason to believe that the temperature
    there will be higher than most forecasts predict, meaning increased air-conditioning use and hence
    increased power consumption.) The trader makes a virtual bid in the day-ahead market to buy
    100MW at $25/MW. If his bid clears, then to offset his purchase, he must also sell 100MW at the
    same node in the real-time market. If his prediction turns out to have been correct, and the real-
    time LMP rises to $30/MW, he makes a profit: he “bought” 100MW for $2500 in the day-ahead
    market and “sold” it for $3000 in the real-time market. Likewise, a trader who correctly predicts
    that the real-time LMP will be lower can conduct a mirror-image virtual transaction, promising in
    the day-ahead market to supply 100MW in exchange for $3000, and then buying those 100MW in
    the real-time market for only $2500. These sorts of arbitrage transactions—the first is called a
    4
    “decrement bid,” the second an “increment offer”—are good not only for the traders but also for
    the market as a whole. Virtual trading encourages price convergence between the day-ahead and
    real-time markets, and provides price discovery, market liquidity, and increased competition.
    Penalty Assessment Order at P 20 & n.48; see also PJM Interconnection, Virtual Transactions in
    the PJM Energy Markets 22–31 (Oct. 12, 2015) (explaining how virtual transactions help mitigate
    both buyer- and supplier-side market power).
    This case centers on another, more complex transaction called an “Up-To Congestion”
    transaction (UTC). Whereas the virtual transactions described in the preceding paragraph revolve
    around price changes at a single node, a UTC is concerned with the changing spread of prices
    between two nodes. It works like this: The trader selects a “source” node and a “sink” node,
    specifies a number of megawatts, and bids a maximum amount by which the day-ahead LMP at
    the sink might exceed the day-ahead LMP at the source. (The price difference correlates with the
    transmission congestion between the nodes, hence the name “Up-To Congestion.”) If the actual
    day-ahead price difference is less than the trader’s bid, the UTC transaction clears, and the trader
    must pay the day-ahead price difference times the number of megawatts specified. The trader will
    then receive the real-time price difference between the nodes (times the number of megawatts).
    Thus, if the price difference, or “spread,” between the nodes is larger in real time, the UTC
    transaction is profitable. See Penalty Assessment Order at PP 2 n.7, 18.
    An example will illustrate. A UTC trader might pick source A and sink B, specify 100MW,
    and say that the day-ahead price at B will be no more than $40/MW greater than at A. After the
    day-ahead market clears, it turns out the price at B is $120/MW and the price at A is $90/MW.
    Because the difference is less than the trader specified, her transaction clears, and she must pay
    $3000: the actual difference ($30/MW) times the number of megawatts (100). Luckily for the
    5
    trader, the price spread grows between the day-ahead and real-time markets. In the real-time
    market, the price at B is up to $130/MW; at A, down to $85/MW. Hence, the trader receives
    $4500: the real-time price difference ($45/MW) times the number of megawatts (100). Taken as
    a whole (and ignoring certain transaction costs for the moment), the UTC turned a profit of $1500.
    At the time of the events in this case, many traders were using UTCs as a “purely virtual
    product.” Penalty Assessment Order at P 19. But UTCs had been “initially created as a tool to
    hedge congestion price risk associated with physical transactions.” 
    Id. at P
    18. Apparently
    because of that original connection to physical transactions, PJM required UTC transactions, even
    virtual ones, “to be associated with transmission service reservations, which, once obtained,
    provided the right to flow electricity across the PJM system.” 
    Id. at P
    22. There was normally a
    charge to obtain a transmission reservation, but there was a legitimate way for UTC traders to
    avoid that charge. For reasons that are not important, PJM did not require UTC traders to reserve
    the same transmission path (i.e., source and sink) that the UTC involved, and it did not charge a
    fee for transmission reservations where the sink was located in a neighboring RTO’s territory.
    This meant that, regardless of which nodes were involved in the UTC, a trader could always choose
    to obtain a free transmission reservation by specifying a transmission path with a sink in the
    neighboring RTO. 
    Id. These free
    reservations, however, were not eligible to receive a “Marginal Loss Surplus
    Allocation” (MLSA) payment, a type of financial credit that is central to this case. When
    electricity is transmitted across the grid, some energy is inevitably lost in the form of heat. This
    is called “line loss.” To ensure that the market price at each node reflects the actual cost of
    providing energy at that location, the LMP that PJM calculates for each node incorporates a line
    loss component. In 2006 FERC instructed PJM to start using a new method for setting the price
    6
    of the line loss component. Atl. City Elec. Co. v. PJM Interconnection, LLC, 115 FERC ¶ 61,132
    (2006). This new “marginal loss method” would result in more accurate price signals, and hence
    a more efficient allocation of electricity-generation resources, but (for reasons not worth detailing
    here) it would also lead PJM to “receive[] more payments than necessary to compensate for actual
    line losses, resulting in a surplus revenue.” Penalty Assessment Order at P 24. PJM therefore had
    to establish a method for disbursing the “marginal loss surplus” to market participants. PJM
    originally proposed (and FERC agreed) that the surplus should be paid to load-serving entities
    (LSEs) in proportion to their share of total load, on the theory that LSEs pay for the fixed costs of
    the transmission grid. Atl. City Elec. Co. v. PJM Interconnection, LLC, 117 FERC ¶ 61,169 at
    PP 12–13, 27–28 (2006).
    In what became known as the Black Oak proceeding, a group of virtual traders challenged
    both the marginal loss method of setting prices and the original MLSA payment scheme. The
    traders argued that because their virtual transactions did not result in actual power flows, they
    should not have to pay for line losses. Alternatively, they argued that if they had to pay for line
    losses, they should also get MLSA payments. In March 2008, FERC rejected their arguments,
    concluding that they should have to pay for line losses just like all other market participants and
    should not get MLSA payments because they did not contribute to the fixed costs of the grid.
    Black Oak Energy, LLC v. PJM Interconnection, LLC, 122 FERC ¶ 61,208 (2008). In October
    2008, however, FERC partially reconsidered its decision. FERC adhered to its position that, in
    general, virtual transactions should not entitle traders to MLSA credit. In doing so FERC
    repeatedly expressed concern that, otherwise, virtual traders might “conduct trades simply to
    receive a larger credit.” Black Oak Energy, LLC v. PJM Interconnection, LLC, 125 FERC
    ¶ 61,042 at P 38 n.46 (2008); see also 
    id. at P
    43. But FERC concluded that because virtual traders
    7
    placing UTC bids did pay transmission costs and therefore did support the fixed costs of the grid,
    it appeared discriminatory not to give MLSA credit for those transactions specifically. 
    Id. at P
    P 48–49. PJM accordingly revised its tariff and began paying MLSA to traders for UTC
    transactions that cleared the market and were associated with a paid transmission reservation.
    Penalty Assessment Order at P 25. By contrast, a UTC associated with a free transmission
    reservation (obtained by selecting a transmission sink in the neighboring RTO), was not eligible
    for MLSA. 
    Id. at P
    22.
    One final and important point about MLSA: In some circumstances, the MLSA payment a
    trader received would exceed the cost of reserving the associated transmission (plus other
    transaction costs). That is, sometimes the MLSA payment could be large enough to cover the cost
    of placing a UTC trade, and then some. This was most likely to be true during hours of peak usage,
    when marginal losses, and hence MLSA payments, would be high. See 
    id. at P
    52.
    II. DEFENDANTS’ ALLEGED CONDUCT
    A. Trading Conduct
    Defendant K. Stephen Tsingas is the founder and controlling owner of defendant City
    Power Marketing, LLC, an energy-trading firm he started in 2005. Penalty Assessment Order at
    P 12. City Power’s trading in the PJM marketplace focused on UTCs, with City Power seeking to
    identify through intensive research pairs of nodes where the price spread was likely to widen
    substantially between the day-ahead and real-time markets. 
    Id. at P
    43. But in July 2010, FERC
    alleges, City Power developed a new strategy—a strategy that at bottom was “a fraudulent UTC
    trading scheme to receive excessive amounts of MLSA payments.” 
    Id. at P
    3. City Power’s
    trading activity itself tells part of the story, but further detail is supplied by online instant messages
    (IMs) sent between Tsingas (who went by the handle “traderyoda”) and a City Power partner
    8
    named Tim Jurco (“jurco831”). Jurco saved these IMs and, as will be explained later, they
    eventually wound up in FERC’s hands.
    The story begins in late June 2010, when Tsingas observed that other virtual traders were
    making unusually large transmission reservations.             FERC Enforcement Staff Report and
    Recommendation, City Power Mktg, LLC & K. Stephen Tsingas, App’x A to Pl.’s Ex. 2 [ECF No.
    1-4] at 13–15 (“Staff Report”). (Traders could see each other’s transmission reservations but not
    their pricing nodes. 
    Id. at 13.)
    Tsingas noticed that these large reservations were during peak
    hours and suggested to Jurco that the other traders were “doing cheap stuff to collect losses”—i.e.,
    to get MLSA. 
    Id. at 15.
    On July 3, while pondering the other traders’ strategy, Tsingas had an
    insight:
    traderyoda: wonder what points they’re doing
    traderyoda: or is it the rope-a-dope
    traderyoda: that may be the trick
    traderyoda: do both sides to collect losses
    traderyoda: EUREKA
    traderyoda: those bastards
    
    Id. at 16–17.
    By “do both sides to collect losses,” Tsingas was referring to “round-trip” trading:
    placing one UTC trade with source A and sink B, and a simultaneous trade with source B and sink
    A. This combination of trades was guaranteed not to earn or lose money on the basis of changing
    price spreads, for any profit the A-to-B trade might yield would be offset by an equal loss on the
    B-to-A trade. But, if the trader chose to pay for transmission, the transaction would generate
    MLSA. See Penalty Assessment Order at P 45. Jurco saw the potential:
    jurco831: nice
    jurco831: load up [i.e., trade in large volumes]
    jurco831: net flat [i.e., no profit or loss from price spreads]
    jurco831: collect [i.e., get MLSA]
    9
    jurco831: that is dirty dirty
    jurco831: but legal I guess
    Staff Report at 17.    Later that day City Power began placing round-trip trades with paid
    transmission reservations. Sure enough, the MLSA exceeded the cost of transmission (and other
    transaction costs) and so City Power got paid for its “net flat” trades. All told, over the course of
    July 2010 City Power collected $455,730 in net profit from round-trip trades. Penalty Assessment
    Order at PP 47–48.
    City Power developed a second type of “loss trade” in short order. This one entailed
    placing UTCs between two nodes named SOUTHIMP and SOUTHEXP, which were “import and
    export pricing points of the same PJM interface, and which ha[d] equivalent prices in both the day-
    ahead and real-time markets.” 
    Id. at P
    49. The result of this equivalent pricing, as Tsingas
    observed in a message to Jurco, was that “SOUTHIMP-SOUTHEXP settles at $0 all the time, DA
    [day-ahead] and RT [real-time].” Staff Report at 22. Once again, then, a UTC trade would yield
    no profit or loss, but could generate MLSA. City Power traded SOUTHIMP-SOUTHEXP for
    roughly a week in early July and collected $106,401 in net profit. Penalty Assessment Order at
    P 49. Tsingas remarked on their success during this period:
    traderyoda: these losses paid well the few days we had 2,000 mw’s
    jurco831: great
    traderyoda: as in 100k plus
    traderyoda: feels sleazy
    jurco831: wow
    Staff Report at 25. But Jurco became concerned about this particular trading path:
    jurco831: back to the losses thing – I feel really funny about the southimp-
    southexp but I think you’re right about the other deals
    
    Id. Jurco worried
    that the SOUTHIMP-SOUTHEXP trades “could be great ammo” for PJM’s
    Market Monitor, the independent entity tasked with ensuring the competitive and efficient
    10
    operation of the market. Penalty Assessment Order at P 50; see also Elec. Power Supply Ass’n v.
    FERC, 
    391 F.3d 1255
    , 1260 (D.C. Cir. 2004) (describing market monitors). City Power stopped
    trading this path in mid-July. Penalty Assessment Order at P 50.
    City Power’s third (and final) type of loss trade involved trading between nodes
    NCMPAIMP and NCMPAEXP. Although these two nodes did not always have identical prices,
    they had historically experienced only very small differences. 
    Id. at P
    51. Unlike SOUTHIMP-
    SOUTHEXP, then, this path could result in spread gains or losses, but they would reliably be
    minimal. As it turned out, City Power’s NCMPAIMP-NCMPAEXP trades in the second half of
    July 2010 earned $100,642 through price-spread gains. 
    Id. at P
    52. Those gains, however, were
    wiped out (and then some) by the transaction costs of placing the trades. 
    Id. (noting transaction
    costs of approximately $532,060). Once again, it was the MLSA payments that made these
    transactions profitable: City Power’s net profit after receiving MLSA was $716,227. 
    Id. Throughout July
    2010 Tsingas expressed amazement and concern about the volumes of
    transmission being reserved by others that he suspected were engaged in similar trading:
    traderyoda: the amount of trans sold has gone up over 2 fold over the last few
    weeks
    jurco831: totally
    traderyoda: even 3-4 fold some days
    traderyoda: hard to turn down 150K for doing nothing
    Staff Report at 32. Tsingas worried that “pigs” reserving huge volumes of transmission were
    “making the game more difficult,” 
    id. at 36,
    and wanted City Power to keep a lower profile.
    traderyoda: I would suggest doing it in small blocks if possible
    traderyoda: like 750 [MW] at a time
    jurco831: ok
    traderyoda: it looks less honerous [sic]
    …
    11
    traderyoda: maybe we set a max [of] 1000 for any deal, what do you think?
    jurco831: yes
    …
    traderyoda: this is the stay below the radar plan
    
    Id. at 28.
    City Power was not able to stay under the radar for much longer, though. By late July PJM
    and the Market Monitor had begun to examine City Power’s and other firms’ UTC trades. See 
    id. at 39;
    Penalty Assessment Order at P 27. City Power ceased its loss trades at the end of July. See
    Penalty Assessment Order at P 3. All told, the firm had collected more than $2 million of MLSA
    from those trades, for a total profit (after transaction costs) of almost $1.3 million. 
    Id. at P
    P 52
    n.128, 161.
    B. Instant Messaging Conduct
    In August 2010 PJM notified FERC’s Office of Enforcement (Enforcement) about City
    Power’s unusual trading, which PJM suggested was undertaken with the intent to manipulate the
    market. Penalty Assessment Order at PP 27–30. Enforcement began investigating and on August
    18 sent City Power a document retention directive. 
    Id. at P
    53. The next day Jurco told Tsingas
    that he had been archiving his IMs:
    jurco831: did a little homework last night
    jurco831: looking through my IM archives
    jurco831: do you archive yours?
    traderyoda: unfortunately not
    traderyoda: so, are we guilty or righteous?
    jurco831: 6/28 – first IM discussion
    jurco831: you literally wrote EUREKA!
    jurco831: we mention losses a lot
    jurco831: I don’t know – most of the conversation is benign
    jurco831: we do identify certain trades as “loss” trades
    12
    traderyoda: the only question is how many trades had zero risk
    jurco831: we talk about the SE trade
    jurco831: saying that’s one we’re not comfortable with
    Staff Report at 53. Several weeks later Tsingas told Jurco he was “an idiot” for having saved his
    IMs and told him to stop archiving them, which Jurco did. 
    Id. at 54.
    Despite being aware of Jurco’s relevant archived IMs, Tsingas failed to reveal their
    existence to Enforcement on any number of occasions. In early October 2010, for instance,
    Tsingas provided sworn testimony to Enforcement staff. Asked whether he knew if City Power
    kept records of IMs, he replied, “I don’t think we do.” Penalty Assessment Order at P 54. Asked
    whether Jurco or other colleagues “have set up their accounts to where it retains instant messages,”
    he replied, “I don’t believe they do, you know, but I don’t know 100 percent for a fact.” 
    Id. Tsingas also
    denied having attempted, after receiving the document retention directive, “to see if
    they have instant messages on their system.” 
    Id. In December
    2010 Tsingas certified on behalf
    of City Power that it had provided true, accurate, and complete responses to Enforcement’s
    November 2010 data request for “all communications” relating to UTC trading—even though City
    Power had not provided Jurco’s archived IMs. 
    Id. at P
    55. In November 2011 Tsingas responded
    to another Enforcement data request, this one specifically about IMs. Tsingas said that City Power
    had “reviewed computer files to determine if instant messages had been saved or otherwise
    archived on company computers. They were not.” 
    Id. at P
    56. He also said that by November
    2011 Jurco was no longer with the firm and that “prior requests to Mr. Jurco to produce any
    responsive instant messages did not reveal any such instant messages.” 
    Id. Tsingas further
    affirmed that “upon receipt of [Enforcement’s] document preservation directive, it was determined
    that City Power Marketing was not in possession of any responsive instant messages, and therefore
    no steps were required to prevent destruction of any such messages.” 
    Id. 13 City
    Power never revealed the existence of or turned over Jurco’s IMs, but Enforcement
    later obtained them. 
    Id. at P
    57. Many of the Jurco-Tsingas conversations discuss City Power’s
    July 2010 UTC trades. Over the course of their conversations Tsingas said that their loss trading
    “feels sleazy”; described loss trading generally as a “scam,” a “game,” “just high volume churn,”
    and a way to make money “for doing nothing”; and acknowledged that the Market Monitor
    “could’ve ripped into me for the SIMP-SEXP and the round trip ovec stuff.” Staff Report at 25,
    32–33, 36–37, 39. (OVEC was a node City Power used in its round-trip trades. 
    Id. at 20–21.)
    For
    his part, Jurco called loss trading “dirty dirty,” “great ammo” for the Market Monitor, and “free
    money.” 
    Id. at 17,
    25, 36. And in a conversation with another City Power partner, Jurco said loss
    trading “isn’t trading, it’s playing the rules.” 
    Id. at 34.
    III. PROCEDURAL HISTORY
    As noted, FERC began investigating City Power’s UTC trading in August 2010. Penalty
    Assessment Order at P 31. The investigation took several years and was followed by unsuccessful
    settlement discussions. 
    Id. at P
    34. Finally, in March 2015 FERC issued an Order to Show Cause
    and Notice of Proposed Penalty, in which it suggested that City Power’s trading had violated
    FERC’s Anti-Manipulation Rule, 18 C.F.R. § 1c.2, and that its misstatements and omissions
    regarding Jurco’s IMs had violated FERC’s Market Behavior Rule 3, concerning truthful
    communications with FERC, 18 C.F.R. § 35.41(b). City Power Mktg., LLC, 150 FERC ¶ 61,176
    (2015).
    The Show Cause Order also required City Power to elect within 30 days one of two
    procedural paths offered by the Federal Power Act (FPA), 16 U.S.C. §§ 791 et seq., for the
    imposition of penalties. 
    Id. at P
    6. Pursuant to Section 31(d)(2) of the FPA, City Power could
    choose to have a formal, on-the-record agency hearing in front of an administrative law judge,
    14
    whose determination could then be reviewed by a court of appeals. See 16 U.S.C. § 823b(d)(2).
    Or, pursuant to Section 31(d)(3), it could choose to let FERC “promptly assess” the proposed
    penalty, and if City Power did not pay within 60 days, FERC would “institute an action in the
    appropriate district court of the United States for an order affirming the assessment of the civil
    penalty.” 
    Id. § 823b(d)(3).
    Under this second option, the court would have “authority to review
    de novo the law and the facts involved” and “to enter a judgment enforcing, modifying, and
    enforcing as so modified, or setting aside” the penalty assessed. 
    Id. § 823b(d)(3)(B).
    City Power
    chose the second option and also filed an answer to the Show Cause Order. Penalty Assessment
    Order at P 37.
    On July 2, 2015, FERC issued its Penalty Assessment Order. FERC concluded that City
    Power had indeed violated the Anti-Manipulation Rule in that it had “deceived PJM into disbursing
    MLSA payments by creating the false impression that City Power was trading to arbitrage price
    differentials when, in fact, it was engaging in trades solely to collect MLSA payments to the
    detriment of other market participants.” 
    Id. at P
    6. FERC also found that City Power’s statements
    to FERC Enforcement staff regarding IMs were false or misleading, in violation of Market
    Behavior Rule 3. 
    Id. at P
    9. FERC ordered City Power to disgorge roughly $1.2 million in unjust
    profits, and also assessed a $14 million penalty against City Power, for which City Power and
    Tsingas were jointly and severally liable, and a separate $1 million penalty against Tsingas. 
    Id. at P
    P 1, 257.
    City Power did not pay the penalty within 60 days, and thus on September 1, 2015, FERC
    filed this action asking the Court to affirm the Penalty Assessment Order. City Power filed a
    motion to dismiss, arguing that FERC’s claims under both the Anti-Manipulation Rule and Market
    Behavior Rule 3 fail as a matter of law, and also raising a number of procedural issues. See Defs.’
    15
    Mem. Supp. Mot. Dismiss [ECF No. 12] (“Defs.’ Mem.”); see also Pl.’s Opp’n [ECF No. 16];
    Defs.’ Reply [ECF No. 18]. On June 1, 2016, the Court held a hearing on the motion. See Hr’g
    Tr. [ECF No. 21]. Roughly a week after the hearing, FERC sought leave to file a supplemental
    memorandum in support of its position. The Court granted leave and also authorized City Power
    to file a response, which it did. See Pl.’s Supp. Mem. [ECF No. 24]; Defs.’ Supp. Resp. [ECF No.
    23].
    DISCUSSION
    I. APPLICABLE PROCEDURES
    Before turning to City Power’s arguments for dismissal, the Court confronts a threshold
    question regarding the nature of this proceeding. City Power argues that this is a standard civil
    action, governed by the Federal Rules of Civil Procedure, in which it should be entitled to
    discovery just like any other civil litigant and, if factual disputes persist, to a jury trial on the merits.
    FERC, by contrast, while acknowledging the Court’s discretion to determine appropriate
    procedures (which might include discovery and a trial or hearing), says this is not a normal civil
    action; in light of the extensive, adversarial proceedings at the agency level, and of certain statutory
    language, FERC argues that the Court should start with the assumption that it need only examine
    the agency record and the Penalty Assessment Order. The Court concludes that, for the most part,
    City Power has the better of this argument. Notwithstanding the significant proceedings that
    occurred at the agency level, the Court will treat this as a standard civil action, governed by the
    Federal Rules of Civil Procedure. In so deciding, the Court agrees with much of the reasoning in
    FERC v. Maxim Power Corp., Civ. No. 15-30113-MGM, 
    2016 WL 4126378
    , at *4–11 (D. Mass.
    July 21, 2016).
    16
    The starting point of the analysis is the FPA. As noted earlier, FPA Section 31(d) creates
    two pathways by which a penalty can be imposed. Under the default option—call it Option 1—
    once FERC provides notice of its proposed penalty,
    the Commission shall assess the penalty, by order, after a determination of
    violation has been made on the record after an opportunity for an agency
    hearing pursuant to [5 U.S.C. § 554] before an administrative law judge . .
    . . Such assessment order shall include the administrative law judge’s
    findings and the basis for such assessment. . . . Any person against whom
    a penalty is assessed under this paragraph may . . . institute an action in the
    United States court of appeals for the appropriate judicial circuit for judicial
    review of such order in accordance with chapter 7 of title 5. The court shall
    have jurisdiction to enter a judgment affirming, modifying, or setting aside
    in whole or in [p]art, the order of the Commission, or the court may remand
    the proceeding to the Commission for such further action as the court may
    direct.
    16 U.S.C. § 823b(d)(2). Option 1 thus describes a traditional form of judicial review of agency
    action, based on the record developed in an agency proceeding, which is familiar in administrative
    law. But some alleged violators, including City Power, have the choice of instead selecting Option
    2, which sets out a less familiar path:
    (A) In the case of any civil penalty with respect to which the procedures of
    this paragraph have been elected, the Commission shall promptly assess
    such penalty, by order, after the date of the receipt of the notice . . . of the
    proposed penalty.
    (B) If the civil penalty has not been paid within 60 calendar days . . . , the
    Commission shall institute an action in the appropriate district court of the
    United States for an order affirming the assessment of the civil penalty. The
    court shall have authority to review de novo the law and the facts involved,
    and shall have jurisdiction to enter a judgment enforcing, modifying, and
    enforcing as so modified, or setting aside in whole or in [p]art such
    assessment.
    
    Id. § 823b(d)(3).
    City Power chose Option 2. The question now is what procedures govern the
    “action in the appropriate district court.”
    Federal Rule of Civil Procedure 1 is the logical place to start. It begins: “These rules govern
    the procedure in all civil actions and proceedings in the United States district courts, except as
    17
    stated in Rule 81.” Rule 81 contains no exception for a case of this sort. Of course, in addition to
    those identified in Rule 81, Congress can specify that certain types of actions are governed by
    procedures other than the Federal Rules. See N.H. Fire Ins. Co. v. Scanlon, 
    362 U.S. 404
    , 407 &
    n.6 (1960). But a “clear expression” of such congressional intent is “necessary” before a court
    should depart from the Federal Rules. Califano v. Yamasaki, 
    442 U.S. 682
    , 700 (1979). There is
    no clear expression of such intent here. FPA Section 31(d)(3) does not explicitly make the Federal
    Rules inapplicable, nor is it incompatible with their application. See Maxim Power, 
    2016 WL 4126378
    , at *6.
    FERC emphasizes the word “review” in Section 31(d)(3), which it says indicates that the
    district court should not engage in plenary adjudication. But the Court does not think “review” is
    enough to indicate a summary proceeding. The statute at issue in Califano provided for district
    court “review” of an agency decision, and the Supreme Court still held that the Federal Rules
    governed. 
    See 442 U.S. at 698
    –701 & n.12. And in United States v. First City National Bank of
    Houston, the Supreme Court examined a statute that instructed district courts to “review de novo
    the issues presented.” 
    386 U.S. 361
    , 368 (1967) (internal quotation marks omitted). The Court
    rejected the argument
    that the use of the word “review” rather than “trial” indicates a more limited
    scope to judicial action. The words “review” and “trial” might conceivably
    be used interchangeably. The critical words seem to us to be “de novo” and
    “issues presented.” They mean to us that the court should make an
    independent determination of the issues.
    
    Id. Here, the
    FPA’s instruction “to review de novo the law and the facts involved” likewise signals
    that the Court should make an independent determination of the issues. The logical procedures to
    govern that determination are those set forth in the Federal Rules.
    Furthermore, the Court does not see why it should place special weight on the agency
    record or presume that City Power should not get discovery. Option 1 clearly envisions the
    18
    development of a comprehensive record at the agency level and record-based review by a court of
    appeals. But Option 2 does not mandate any particular agency procedures, and places judicial
    review in a district court, where factual development through discovery is the norm. Even FERC
    ultimately concedes that Option 2 does not confine the Court’s analysis to the materials compiled
    at the agency. See Pl.’s Opp’n at 37. FERC nonetheless thinks that the record will prove adequate,
    and emphasizes that City Power was given the opportunity to submit whatever materials it wished
    at the agency level. See 
    id. But although
    City Power had the opportunity submit any evidence it
    wished, it did not necessarily have the ability to obtain it. Unlike FERC, City Power did not have
    the authority to subpoena records or depose witnesses during the agency proceedings. Once it has
    that ability, City Power might be able to show that the factual landscape is meaningfully different
    from what FERC’s Penalty Assessment Order indicates. See Maxim Power, 
    2016 WL 4126378
    ,
    at *10.
    FERC suggests that if City Power wanted discovery, it should have chosen Option 1, the
    formal hearing before an administrative law judge.          See 
    id. at 39–40;
    Hr’g Tr. at 71–72
    (“[Defendants] gave up the guaranteed opportunity to have discovery and an evidentiary hearing.
    They had that. They turned it down.”). But the Court does not see why the fact that discovery is
    available under Option 1 suggests that it is not available under Option 2. There is no reason that
    Option 2 must provide defendants with fewer procedural protections. The Court thinks it more
    natural to assume that both Options allow defendants to fully develop their factual defenses, just
    in different settings. See Maxim Power, 
    2016 WL 4126378
    , at *11.
    Contrary to FERC’s suggestion, interpreting Option 2 to provide for full-dress adjudication
    in district court does not render the agency process culminating in the Penalty Assessment Order
    (and the Order itself) “a pointless exercise.” Pl.’s Opp’n at 40. There is no escaping the fact that
    19
    under Option 2 FERC must first determine at the agency level whether to assess the penalty. If
    the agency proceeding is as fair and adversarial as FERC proclaims, presumably it sometimes leads
    FERC to decide not to assess a penalty at all (or to assess a much smaller one), obviating the need
    for judicial proceedings entirely. That is hardly pointless. Nor is it pointless to embody the
    assessment decision in an order, for the act of reducing a decision to writing can itself influence
    the decisionmaking process. See, e.g., Arlinghaus v. Ritenour, 
    543 F.2d 461
    , 464 (2d Cir. 1976)
    (per curiam) (“A decisionmaker obliged to give reasons to support his decision may find they do
    not; ‘the opinion will not write.’ ”). And, as has been true here, a penalty assessment order will
    help the district court fully grasp FERC’s factual allegations and legal theories. Thus, the value
    of the agency proceeding and order is not erased by the availability of discovery and de novo
    adjudication in the district court. 1
    In sum, the Court will treat this case like a normal civil action governed by the Federal
    Rules. That does not, however, stop FERC from seeking affirmance of the Penalty Assessment
    Order right away. If FERC is convinced that the agency record contains all of the relevant evidence
    and shows conclusively that City Power is liable, FERC can move for summary judgment
    promptly. See Fed. R. Civ. P. 56(b). But City Power will be free to argue that without discovery
    “it cannot present facts essential to justify its opposition,” at which point the Court might defer
    consideration of the motion until City Power has had the opportunity to gather those facts. See
    Fed. R. Civ. P. 56(d). And the Court will apply the usual summary judgment standard in resolving
    any such motion.
    1
    One of FERC’s concerns is sandbagging: FERC worries that City Power might present arguments and
    evidence in this proceeding that it could have but failed to present to the agency in response to the Show Cause Order.
    See Pl.’s Opp’n at 37–38 & n.35; Hr’g Tr. at 72. If this occurs, FERC will be free to argue that City Power has waived
    those issues. The Court will evaluate any such argument if and when FERC makes it.
    20
    The Court does reserve judgment on one issue: whether City Power is entitled to a jury
    trial. City Power says it is; FERC says it isn’t. The Court does not see why it must resolve this
    dispute now. Even in a case where the right to a jury trial is undisputed, that right only comes into
    play if the case makes it past the summary judgment stage. If the plaintiff is entitled to summary
    judgment, the defendant’s theoretical right to a jury trial is irrelevant, for there will be no trial
    whatsoever. See Calvi v. Knox Cty., 
    470 F.3d 422
    , 427 (1st Cir. 2006) (“[A] grant of summary
    judgment does not compromise the Seventh Amendment’s jury trial right because that right exists
    only with respect to genuinely disputed issues of material fact.”); 10A Charles Alan Wright et al.,
    Federal Practice and Procedure § 2714 (3d ed. 1998). This case might be resolved at summary
    judgment, mooting the question whether City Power is in theory entitled to a jury trial. Because
    the Court might not need to answer this question at all, it will not do so now. See PDK Labs. Inc.
    v. DEA, 
    362 F.3d 786
    , 799 (D.C. Cir. 2004) (Roberts, J., concurring in part and concurring in the
    judgment) (highlighting “the cardinal principle of judicial restraint—if it is not necessary to decide
    more, it is necessary not to decide more”).
    *               *               *
    With this threshold question of procedure out of the way, the Court can turn to City Power’s
    arguments for dismissal. The parties agree, and so does the Court, that these arguments should be
    assessed under the usual standard governing Rule 12(b)(6) motions to dismiss. Defs.’ Mem. at 7–
    8; Pl.’s Opp’n at 3–4. Under that standard, a court must presume the truth of a complaint’s factual
    allegations, though it is “not bound to accept as true a legal conclusion couched as a factual
    allegation.” Bell Atl. Corp. v. Twombly, 
    550 U.S. 544
    , 555 (2007) (internal quotation marks
    omitted). The court then asks whether the facts alleged suffice “to state a claim to relief that is
    21
    plausible on its face.” Ashcroft v. Iqbal, 
    556 U.S. 662
    , 678 (2009) (internal quotation marks
    omitted).
    In addition to the complaint itself, the court can examine documents attached to or
    incorporated in the complaint, and matters subject to judicial notice. See Trudeau v. FTC, 
    456 F.3d 178
    , 183 (D.C. Cir. 2006). Here, FERC attached to its complaint the 125-page Penalty
    Assessment Order, the Show Cause Order, and its Enforcement Staff’s Report and
    Recommendation, which is repeatedly referenced in the Penalty Assessment Order. The Court
    will consider all of these materials. Insofar as these materials recount disagreements of fact
    between FERC and City Power, the Court will at this stage accept FERC’s version as true.
    II. THE ANTI-MANIPULATION RULE
    City Power seeks dismissal of FERC’s claim under the Anti-Manipulation Rule on several
    grounds. The first and most fundamental is that FERC has failed to allege any fraudulent conduct
    that violates the Rule. But the Court is ultimately unpersuaded. FERC has plausibly alleged that
    UTC trading was allowed in the PJM market for the purpose of arbitrage, and that while City
    Power’s transactions had the superficial appearance of arbitrage trades, they were in fact
    specifically designed not to serve that purpose, and instead to do nothing but rake in MLSA
    payments. If true, as FERC has alleged, this trading was deceptive and constituted a scheme to
    defraud. At this stage of the proceedings, then, the Court cannot conclude that FERC’s claim
    under the Anti-Manipulation Rule fails as a matter of law.
    Enacted as part of the Energy Policy Act of 2005 (EPAct), Pub. L. No. 109-58, 119 Stat.
    594, Section 222 of the FPA provides in relevant part:
    It shall be unlawful for any entity (including an entity described in section
    824(f) of this title), directly or indirectly, to use or employ, in connection
    with the purchase or sale of electric energy or the purchase or sale of
    transmission services subject to the jurisdiction of the Commission, any
    22
    manipulative or deceptive device or contrivance (as those terms are used in
    section 78j(b) of title 15), in contravention of such rules and regulations as
    the Commission may prescribe as necessary or appropriate in the public
    interest or for the protection of electric ratepayers.
    16 U.S.C. § 824v(a). On the basis of this statutory authority, FERC promulgated the Anti-
    Manipulation Rule in January 2006. Prohibition of Energy Market Manipulation, Order No. 670,
    114 FERC ¶ 61,047, 71 Fed. Reg. 4244 (2006). The relevant portion of the Rule states:
    It shall be unlawful for any entity, directly or indirectly, in connection with
    the purchase or sale of electric energy or the purchase or sale of transmission
    services subject to the jurisdiction of the Commission,
    (1) To use or employ any device, scheme, or artifice to defraud,
    (2) To make any untrue statement of a material fact or to omit to state a
    material fact necessary in order to make the statements made, in the light
    of the circumstances under which they were made, not misleading, or
    (3) To engage in any act, practice, or course of business that operates or
    would operate as a fraud or deceit upon any entity.
    18 C.F.R. § 1c.2(a).
    In promulgating the Anti-Manipulation Rule, FERC offered an expansive definition of
    “fraud,” deeming it “to include any action, transaction, or conspiracy for the purpose of impairing,
    obstructing or defeating a well-functioning market.” Order No. 670, 114 FERC ¶ 61,047 at P 50.
    Read for all it’s worth, this definition might appear to jettison any requirement of misrepresentation
    or deception, contrary to the common understanding of fraud. See, e.g., Ed Peters Jewelry Co. v.
    C & J Jewelry Co., 
    215 F.3d 182
    , 191 (1st Cir. 2000) (“The hallmarks of fraud are
    misrepresentation or deceit.”). That reading, however, would be inconsistent with Congress’s
    command that “manipulative or deceptive device or contrivance” in FPA Section 222 means the
    same thing that it means in 15 U.S.C. § 78j(b), better known as Section 10(b) of the Securities
    Exchange Act of 1934 (SEA). Despite the disjunctive phrasing “manipulative or deceptive,” it is
    well-established that conduct cannot run afoul of Section 10(b) unless it involves deception. See,
    23
    e.g., SEC v. Pirate Inv’r LLC, 
    580 F.3d 233
    , 239 (4th Cir. 2009); Foss v. Bear, Stearns & Co., 
    394 F.3d 540
    , 541 (7th Cir. 2005); see also Schreiber v. Burlington N., Inc., 
    472 U.S. 1
    , 6–8 (1985).
    The same, then, is true of FPA Section 222. And if the statute requires deception, so too must the
    Anti-Manipulation Rule. Cf. Ernst & Ernst v. Hochfelder, 
    425 U.S. 185
    , 212–14 (1976) (noting
    that the scope of SEC Rule 10b-5 cannot exceed that of SEA Section 10(b)).
    That said, Section 10(b) case law indicates that the Court should not take a cramped view
    of the types of deception that can give rise to fraud. See Superintendent of Ins. v. Bankers Life &
    Cas. Co., 
    404 U.S. 6
    , 12 (1971) (“Section 10(b) must be read flexibly, not technically and
    restrictively.”). Importantly, deception need not take the form of “a specific oral or written
    statement,” for “[c]onduct itself can be deceptive.” Stoneridge Inv. Partners, LLC v. Sci.-Atlanta,
    
    552 U.S. 148
    , 158 (2008). And the same conduct may or may not be deceptive depending on an
    actor’s purpose. See Markowski v. SEC, 
    274 F.3d 525
    , 529 (D.C. Cir. 2001). Securities
    transactions that would be lawful if based on a genuine belief that the market has misvalued a
    security can be unlawfully deceptive if undertaken to obtain some side benefit. In Markowski, for
    example, the D.C. Circuit held that an underwriting firm (Global) had violated SEC Rule 10b-5 by
    trading with the “external purpose” of propping up the price of a security it had underwritten in
    order “to maintain customer interest in Global generally and to sustain confidence in its other
    securities.” 
    Id. And in
    Koch v. SEC, the D.C. Circuit affirmed that it violates Rule 10b-5 to “mark
    the close”: to trade at the very end of the day with the goal of driving the day’s closing price up or
    down, which can trigger various collateral benefits for the trader. 
    793 F.3d 147
    , 152–56 (D.C. Cir.
    2015); see also 5 Thomas Lee Hazen, Treatise on the Law of Securities Regulation § 14:47 (7th
    ed. 2016) (discussing marking the close). Markowski and Koch thus reveal an important point:
    under Section 10(b), securities traders are not free to trade for whatever purpose they wish. Traders
    24
    are presumed to be trading on the basis of their best estimates of a security’s underlying economic
    value, see, e.g., ATSI Commc’ns, Inc. v. Shaar Fund, Ltd., 
    493 F.3d 87
    , 100–01 (2d Cir. 2007),
    and to trade for other purposes can be deceptive.
    That brings us to the crucial premise of FERC’s theory in this case—namely, that virtual
    traders were allowed to engage in UTC trading for a particular purpose: “to profit by arbitraging
    the price differences between two nodes in the day-ahead and real-time markets.” Penalty
    Assessment Order at P 102; see also, e.g., 
    id. at P
    115. Perhaps at a later stage of this litigation
    City Power will be able to show that this premise is false, but for now FERC has at least plausibly
    alleged that it is true. It is plausible, first, because the foremost reason to allow virtual energy
    trading is that it helps to converge day-ahead and real-time prices, which leads to a more efficient
    market overall. See, e.g., ISO New England, Inc., 113 FERC ¶ 61,055 at PP 29–31, 37–38 (2005);
    Metin Celebi et al., Virtual Bidding: The Good, the Bad and the Ugly, Electricity Journal, June
    2010, at 16, 18. But price convergence can only occur if virtual traders try to accurately predict
    price differences and place trades that embody those predictions; “net flat” trades cannot spur
    convergence. FERC’s present view of virtual UTC trading, moreover, is consistent with what it
    said in the 2008 Black Oak orders. There FERC described UTCs as “arbitrage transactions” and
    the virtual traders engaged in them as “arbitrageurs.” 122 FERC ¶ 61,208 at P 50 & n.85. In those
    same orders, FERC expressed clear disapproval of the possibility that virtual traders might seek to
    profit by simply maximizing MLSA instead of reacting to price differences. 
    Id. at P
    51; 125 FERC
    ¶ 61,042 at PP 38 n.46, 43. And FERC has plausibly alleged that City Power “understood the
    arbitrage-based purpose of UTC trading in PJM.” Penalty Assessment Order at P 181; see also 
    id. at P
    P 182–86 (cataloging evidence of City Power’s knowledge that loss trading was inconsistent
    with the purpose of UTC trading). At this stage of the litigation, then, the Court accepts the
    25
    premise that it was understood by PJM and market participants that the purpose of virtual UTC
    trading was to profit through price arbitrage.
    With that premise in hand, and assuming the truth of FERC’s allegations, it is not hard to
    see the deception: City Power’s loss trades were sham transactions. They did not embody
    predictions about how prices would change between the day-ahead and real-time markets. Far
    from attempting to profit from changing price spreads, City Power consciously engineered these
    trades so that there would be no (or almost no) change in the price spreads at all. As discussed
    earlier, City Power did this in two ways. In some instances it placed UTC trades in “round-trip”
    pairs—A-to-B and B-to-A—so that any profitable price movement in one trade would be offset by
    equal but opposite movement in the other. In other instances it selected two nodes that it knew
    would have identical (or nearly identical) prices, so that the price difference in both the day-ahead
    and real-time markets would always be zero. Both types of trades were designed so that they could
    not possibly serve the purpose that all players knew UTCs were intended to serve: price arbitrage.
    They had the outward form of UTCs but none of the economic substance. In short, they were
    fakes. City Power placed these fake trades so that it could reserve large volumes of paid
    transmission, which in turn led PJM to hand over the MLSA payments. Sham transactions, of no
    value to the market, in order to get real payout—as alleged, then, this was a scheme to defraud,
    and hence a violation of the Anti-Manipulation Rule.
    City Power’s primary counterargument is that it told PJM exactly what it was doing. It did
    so, it says, through the very act of placing its trades. City Power says that in placing its trades
    through PJM’s online platform, it necessarily revealed to PJM all of the relevant details—the
    nodes, price points, and volumes. And because all the details were accurately disclosed, the
    26
    argument goes, City Power cannot be deemed to have done anything deceptive. See Defs.’ Mem.
    at 23–24; Defs.’ Reply at 8.
    But this argument takes too narrow a view of deception in this context. At the time of these
    events, traders were placing hundreds of UTC bids per day through PJM’s computerized trading
    platform. See Monitoring Analytics, LLC, 2010 State of the Market Report for PJM, Volume 1,
    at 15 (Mar. 10, 2011) (noting roughly 600 UTC bids per day in this period). PJM did not—could
    not—analyze the economics of each trade as it was placed; as long as the trade had the form of a
    UTC, the system let it through. Given the computerized mechanics of the market and the volume
    of activity, City Power could place its sham trades without their being noticed. And according to
    FERC’s allegations, City Power knew it was doing exactly that. That is why City Power
    consciously chose to trade in relatively small volumes: to “stay below the radar” and avoid drawing
    any attention to its trades. Penalty Assessment Order at P 154. Thus, even though City Power
    transmitted raw data that in theory would have allowed PJM to figure out that the loss trades were
    economic nullities, it was predictable that PJM would not in fact perceive the true nature of the
    transactions. Just as attempting to purchase goods with a counterfeit bill is deceptive even if one
    writes a tiny “NOT REAL!” in the corner, so too were City Power’s loss trades.
    City Power also argues the loss trades cannot be considered sham trades because they
    involved real risk. See Defs.’ Supp. Resp. at 16–18. The NCMPAIMP-NCMPAEXP trades
    involved real price-spread risk, says City Power, pointing to the undisputed fact that City Power
    made “$100,642 in spread gains” from those trades. 
    Id. at P
    144. And the round-trip trades had
    risk in that, if the price spread were big enough, one of the paired trades would fail to clear, leaving
    City Power exposed to price-spread risk on the remaining trade. But these theoretical risks do not
    prove that the loss trades were not sham transactions. FERC alleges that City Power chose the
    27
    NCMPAIMP-NCMPAEXP path precisely because there would be some price spreading, which
    would make the trades look like arbitrage, but the spreads would be so small that any losses would
    reliably be overwhelmed by the MLSA payout. See 
    id. at P
    51. In other words, if FERC’s
    allegations are true, the NCMPAIMP-NCMPAEXP trades were just well-disguised sham trades.
    As for the round-trip trades, the theoretical risk was essentially no risk in practice: according to
    FERC, both legs of City Power’s round-trip trades cleared 99% of the time. 
    Id. at P
    107. And
    there is no escaping the conclusion that the SOUTHIMP-SOUTHEXP trades (about which City
    Power has little to say) lacked substance: FERC alleges that there was no price spread at all on this
    path during the relevant period and that City Power knew there would be no spread. 
    Id. at P
    127.
    Nothing about the loss trades, as alleged, is inconsistent with FERC’s theory that they were sham
    transactions designed for the exclusive purpose of generating MLSA payments.
    City Power also argues that the Anti-Manipulation Rule claim must fail because FERC has
    not adequately alleged that City Power caused any harm. See Defs.’ Mem. at 25–26; Defs.’ Reply
    at 13–15. But, for starters, why must FERC allege harm? The SEC need not show harm when it
    brings an enforcement action under Rule 10b-5. Graham v. SEC, 
    222 F.3d 994
    , 1001 n.15 (D.C.
    Cir. 2000). Why should FERC have to do so under the Anti-Manipulation Rule? By prohibiting
    “any device, scheme, or artifice to defraud” and “any act, practice, or course of business that
    operates or would operate as a fraud or deceit upon any entity,” the Rule covers even unsuccessful
    schemes that harm no one. Cf. 
    Markowski, 274 F.3d at 529
    (“Just because a manipulator loses
    money doesn’t mean he wasn’t trying.”). In any event, FERC has quite plainly alleged harm: City
    Power took home more than $2 million of MLSA as a result of its phony UTCs. Penalty
    Assessment Order at P 161. Even if the total amount of MLSA for PJM to distribute would have
    been less without City Power’s activity—City Power did pay for transmission, after all—City
    28
    Power clearly extracted more than it contributed. And that means that City Power wound up with
    money that would have otherwise been paid to other market participants. That is harm. City Power
    suggests that FERC needs to identify each of those other market participants by name, but there is
    no basis for such a requirement. Although Federal Rule of Civil Procedure 9(b) requires fraud
    claims to be pleaded with particularity, in terms of harm, it is enough for a plaintiff to state “what
    was obtained or given up as a consequence of the fraud.” U.S. ex rel. Joseph v. Cannon, 
    642 F.2d 1373
    , 1385 (D.C. Cir. 1981) (internal quotation marks omitted). FERC has done so: as a
    consequence of the loss trades, City Power obtained more than $2 million of MLSA.
    In sum, FERC’s allegations—both those about the nature of UTC trading in PJM generally
    and those about City Power’s trading in particular—suffice to state a claim under the Anti-
    Manipulation Rule. At later stages of this case, of course, City Power will have the chance to
    argue that those allegations are unsupported by the evidence. But at this point FERC has at least
    “state[d] a claim to relief that is plausible on its face.” 
    Iqbal, 556 U.S. at 678
    (internal quotation
    marks omitted).
    III. FAIR NOTICE
    City Power next argues that FERC’s Anti-Manipulation Rule claim fails for lack of fair
    notice. “Due process requires that parties receive fair notice before being deprived of property. . . .
    In the absence of notice—for example, where the regulation is not sufficiently clear to warn a party
    about what is expected of it—an agency may not deprive a party of property by imposing civil or
    criminal liability.” Gen. Elec. Co. v. EPA, 
    53 F.3d 1324
    , 1328–29 (D.C. Cir. 1995). City Power
    maintains that, assuming its alleged conduct is now deemed to violate the Anti-Manipulation Rule,
    City Power could not have known in advance that FERC would consider its trades unlawful. It
    therefore cannot be penalized. See Defs.’ Mem. at 26–28; Defs.’ Reply at 15–16.
    29
    The Court disagrees. The Anti-Manipulation Rule gave clear notice that fraudulent
    schemes of all sorts were prohibited. As City Power concedes, FERC did not need to identify
    every possible form of fraud in advance, an obviously impossible task. See Hr’g Tr. at 18:1–9.
    The fair notice question, then, boils down to whether City Power should have known its UTC loss
    trading was a fraudulent scheme. The answer is yes. Accepting once more the truth of FERC’s
    allegations about the nature of UTC trading, see supra pp. 25–26, a reasonable person would have
    recognized that loss trades of this sort were sham transactions, and that to use them as a mechanism
    for collecting MLSA—to get money “for doing nothing,” as Tsingas allegedly put it—would
    constitute a scheme to defraud.
    City Power’s creative attempt to bolster its fair notice argument by invoking the Black Oak
    proceeding is unpersuasive.       City Power notes that in the 2008 Black Oak orders FERC
    acknowledged that paying MLSA to virtual traders could “creat[e] an incentive for arbitrageurs to
    engage in purchase decisions, not because of price divergence, but simply to increase line loss
    payments.” 125 FERC ¶ 61,042 at P 43. According to City Power, FERC thus accurately
    predicted the emergence of loss trading, and yet it did not warn market participants that it
    considered such trading fraudulent. In City Power’s view, then, market participants lacked fair
    notice that they could be penalized for such trades.
    This is an implausible reading of the Black Oak orders. Those orders make abundantly
    clear FERC’s view that virtual traders should be seeking to profit by accurately predicting price
    differences between the day-ahead and real-time markets, and that it did not want traders to have
    an incentive to trade with the aim of merely maximizing MLSA. See 125 FERC ¶ 61,042 at PP 38
    n.46, 43; 122 FERC ¶ 61,208 at P 51. It is true that FERC’s decision to let UTCs become eligible
    for MLSA wound up creating precisely that bad incentive, but the Black Oak orders did not predict
    30
    that outcome. FERC seems to have thought that as long as UTC traders were paying for
    transmission, there would be no harmful distortion of incentives. See 125 FERC ¶ 61,042 at P 43
    (expressing concern about the distorting effect of the “payment of the surplus to arbitrageurs that
    is unrelated to the transmission costs”). FERC was wrong about that. But it is untenable to read
    the Black Oak orders as predicting UTC loss trading, much less tacitly endorsing it. There is no
    escaping the orders’ clear message that FERC did not want market participants “to conduct trades
    simply to receive a larger [MLSA] credit.” 
    Id. at P
    38 n.46.
    To be clear, the Court’s point is not that the Black Oak orders alone provided sufficient
    notice that City Power’s loss trading was unlawful. The key source of notice was the Anti-
    Manipulation Rule itself, which made clear that all forms of fraud were prohibited. The point here
    is that the Black Oak orders cannot fairly be read to say (or even imply) that loss trading was
    permissible or non-fraudulent.
    IV. FERC’S JURISDICTION
    City Power’s final argument for dismissal of the Anti-Manipulation Rule claim is that
    FERC lacks jurisdiction over City Power’s loss trades. City Power thinks that is so, in short,
    because these were virtual trades that did not result in the actual interstate transmission of power.
    See Defs.’ Mem. at 28–32; Defs.’ Reply at 17–18. But City Power’s view of FERC’s authority is
    too narrow.
    FPA Section 222 gives FERC authority to prohibit the use of any fraudulent scheme “in
    connection with the purchase or sale of electric energy or the purchase or sale of transmission
    services subject to the jurisdiction of the Commission.” 16 U.S.C. § 824v(a). FERC’s jurisdiction
    over “the transmission of electric energy in interstate commerce,” 
    id. § 824(b)(1),
    covers all
    transmission on an interconnected, multi-state grid like PJM’s, see New York v. FERC, 
    535 U.S. 31
    1, 16 (2002) (“[T]ransmissions on the interconnected national grids constitute transmissions in
    interstate commerce.”). Thus, when a market participant pays to reserve a share of the transmission
    available on PJM’s network that is a purchase of “transmission services subject to the jurisdiction
    of the Commission.” The fact that a virtual trader might not ultimately use that reservation to flow
    physical power is irrelevant. All traders, virtual and real, use the same system for reserving
    transmission and compete for the same finite amount of transmission capacity. The entire process
    of transmission allocation in PJM is therefore subject to FERC’s jurisdiction. And that brings City
    Power’s scheme within FERC’s authority under the Anti-Manipulation Rule. The heart of the
    scheme, after all, was to reserve significant amounts of paid transmission in order to collect MLSA.
    The scheme was thus “in connection with the purchase or sale of . . . transmission services subject
    to the jurisdiction of the Commission.” See Penalty Assessment Order at P 202.
    Because City Power’s reservation of jurisdictional transmission services is an adequate
    basis for FERC’s authority, the Court need not examine FERC’s other jurisdictional arguments—
    though it notes in passing that those arguments seem bolstered by the Supreme Court’s recent
    analysis of FERC’s authority in FERC v. Electric Power Supply Ass’n, 
    136 S. Ct. 760
    (2016)
    (holding that FERC has authority to regulate wholesale market operators’ compensation of demand
    response commitments).
    V. INDIVIDUAL LIABILITY UNDER THE ANTI-MANIPULATION RULE
    Tsingas raises an additional argument in his individual capacity. He notes that FPA Section
    222 authorizes FERC to prohibit the use of deceptive devices by “any entity.” A natural person,
    Tsingas contends, is not an “entity” and therefore cannot violate the Anti-Manipulation Rule. The
    Anti-Manipulation Rule claim against him as an individual should therefore be dismissed, he says.
    See Defs.’ Mem. at 32–36; Defs.’ Reply at 18–21. Although this argument is not without some
    32
    intuitive appeal, the Court is ultimately unconvinced, and instead agrees with the three other courts
    to have addressed this question that the term “entity” in Section 222 can include individuals. See
    FERC v. Maxim Power Corp., Civ. No. 15-30113-MGM, 
    2016 WL 4126378
    , at *14–15 (D. Mass.
    July 21, 2016); FERC v. Silkman, Civ. No. 13-13054-DPW, 
    2016 WL 1430009
    , at *20–21 (D.
    Mass. Apr. 11, 2016); FERC v. Barclays Bank PLC, 
    105 F. Supp. 3d 1121
    , 1145–46 (E.D. Cal.
    2015).
    Tsingas is correct that the word “entity” is often used to denote something other than an
    individual person. See, e.g., Samantar v. Yousuf, 
    560 U.S. 305
    , 315 (2010) (“ ‘entity’ typically
    refers to an organization, rather than an individual”). Some dictionary definitions suggest that
    “entity” does not encompass an individual. See, e.g., Black’s Law Dictionary 650 (10th ed. 2014)
    (“An organization (such as a business or a governmental unit) that has a legal identity apart from
    its members or owners.”). And in some statutes the term is used in a way that clearly does not
    include individuals. See, e.g., Am. Dental Ass’n v. Shalala, 
    3 F.3d 445
    , 446–48 (D.C. Cir. 1993).
    But “entity” sometimes has a broader meaning.         Some dictionaries indicate that an
    individual person is an “entity.” See, e.g., Webster’s II New College Dictionary 383 (2005)
    (“Something that exists as a particular and discrete unit ”); Black’s Law Dictionary 1219 (10th ed. 2014) (defining
    “nonpracticing entity” as a “person or company that acquires patents with no intent to use, further
    develop, produce, or market the patented invention” (emphasis added)). The D.C. Circuit has
    likewise said that “entity” “may include a natural person,” in addition to various types of
    organizations. City of Abilene v. FCC, 
    164 F.3d 49
    , 52 (D.C. Cir. 1999). Various statutes use the
    phrase “person or other entity” (emphasis added), suggesting that an individual is one type of
    33
    “entity.” See, e.g., 8 U.S.C. § 1324b(a)(1); 42 U.S.C. § 3605(a). And the bankruptcy code
    expressly includes individuals within its definition of “entity.” 11 U.S.C. § 101(15), (41).
    In sum, absent a statutory definition (and there is none in the FPA) the term “entity” is
    ambiguous on this point. Ambiguity cuts in FERC’s favor, for the Commission’s interpretation of
    ambiguous terms in the FPA is entitled to Chevron deference. See, e.g., Rhinelander Paper Co. v.
    FERC, 
    405 F.3d 1
    , 6 (D.C. Cir. 2005). FERC made its interpretation clear in Order 670, explaining
    that in its view “any entity” is a broadly inclusive term that should be read to encompass “any
    person or form of organization, regardless of its legal status, function or activities.” 114 FERC
    ¶ 61,047 at P 18. That is a reasonable reading of the statute to which the Court will defer. See
    Maxim Power, 
    2016 WL 4126378
    , at *15 (finding Chevron deference applicable to FERC’s
    interpretation of “entity”); Silkman, 
    2016 WL 1430009
    , at *21 (same).
    Tsingas pushes back, arguing that in this particular statute “entity” unambiguously
    excludes individuals. Tsingas says that in the rest of the EPAct, “the word ‘entity’ is used
    exclusively to describe groups and organizations,” and so cannot be read to include individuals
    here. Defs.’ Mem. at 34. But the Court does not find such clear uniformity throughout the EPAct.
    It is true that some instances of “entity” seem to refer primarily to non-individuals, and there is
    one instance of the disjunctive phrase “individual or entity,” suggesting that an individual is not
    an entity, see EPAct § 652, 119 Stat. at 810. As FERC explains, however, there are a number of
    instances in which it is not clear that “entity” must have this narrower sense and not apparent why
    individuals would logically be excluded. See Pl.’s Opp’n at 25–27. And countering the instance
    of “individual or entity” is an instance of the phrase “persons or other entities,” which again
    suggests that an individual person is a type of “entity.” See EPAct § 349(b)(2), 119 Stat. at 709.
    34
    The Court does not find the usage of “entity” throughout the EPAct so clear and consistent as to
    render Section 222 unambiguous on this score.
    Tsingas also argues that the use of “entity” rather than “person” makes unambiguous
    Congress’s intent that Section 222 not encompass individuals. “Person,” he notes, is specifically
    defined in the FPA to mean “an individual or a corporation,” 16 U.S.C. § 796(4), and so would
    have been the obvious word for Congress to choose if it wanted to include individuals. Moreover,
    he observes, “person” is the word Section 10(b) of the SEA uses; the switch to “entity” in Section
    222 must signify something, and the obvious answer is an intent to exclude individuals. In fact,
    however, there was a good reason for Congress not to have used the word “person” in Section 222.
    Congress specifically provided that Section 222’s prohibition applies to “an entity described in
    section 824(f) of this title.” Among the entities described in 16 U.S.C. § 824(f) is “any political
    subdivision [or agency] of a State.” But the word “person” in the FPA specifically excludes
    subdivisions and agencies of States. 16 U.S.C. § 796(3), (4), (7). As used in the FPA, then,
    “person” was not broad enough to capture the full range of potential manipulators that Congress
    wanted covered by Section 222. Cf. Order No. 670, 114 FERC ¶ 61,047 at P 75 (noting that, for
    the same reason, FERC changed the phrase “would operate as a fraud or deceit upon any person”
    in the proposed Anti-Manipulation Rule to “would operate as a fraud or deceit upon any entity” in
    the final Rule). Because “entity” was used, at least in this respect, for the sake of its breadth, it
    hardly demonstrates an unambiguous intent to exclude individuals.
    Tsingas’s final argument on this issue, which consists of less than a sentence in his reply
    brief, is that FERC’s interpretation deserves no Chevron deference because under FPA Section
    31(d)(3) Tsingas is “entitled to de novo review of the law and the facts.” Defs.’ Reply at 19.
    Section 31(d)(3) does indeed authorize this Court “to review de novo the law and the facts
    35
    involved,” 16 U.S.C. § 823b(d)(3), but that does not eliminate Chevron deference. “De novo
    proceedings presume a foundation of law,” and Chevron deference is properly applied as part of
    determining that foundation. United States v. Haggar Apparel Co., 
    526 U.S. 380
    , 391 (1999).
    “Deference can be given to . . . regulations without impairing the authority of the court to make
    factual determinations, and to apply those determinations to the law, de novo.” Id.; see also Ampe
    v. Johnson, Civ. No. 14-717 (RDM), 
    2016 WL 247562
    , at *5 (D.D.C. Jan. 20, 2016). Deference
    is appropriate here.
    Because FERC reasonably interpreted “any entity” in Section 222 to include individuals,
    the Court will not dismiss the Anti-Manipulation Rule claim against Tsingas in his individual
    capacity.
    VI. MARKET BEHAVIOR RULE 3
    As discussed earlier, FERC concluded that in addition to violating the Anti-Manipulation
    Rule, City Power also violated the Commission’s Market Behavior Rule 3. That rule states in
    relevant part:
    A Seller must provide accurate and factual information and not submit false
    or misleading information, or omit material information, in any
    communication with the Commission, [or various other entities], unless
    Seller exercises due diligence to prevent such occurrences.
    18 C.F.R. § 35.41(b). FERC concluded that City Power (which no one disputes is a “Seller”)
    violated this rule on various occasions during the course of FERC’s investigation when—through
    communications made by Tsingas on behalf of the firm—it did not reveal the existence of Jurco’s
    archived instant messages (IMs). Penalty Assessment Order at PP 216–23. City Power contends
    that this claim fails as a matter of law, arguing that all of the statements it allegedly made turn out
    to be true when examined closely. See Defs.’ Mem. at 36–39; Defs.’ Reply at 21–23. But this
    issue is not even close. Assuming the truth of FERC’s allegations and drawing all reasonable
    36
    inferences in its favor, City Power (through Tsingas) made misleading statements or omitted
    material information on a number of occasions. FERC has therefore stated a viable claim under
    Market Behavior Rule 3.
    Recall that on August 19, 2010, the day after City Power received a document retention
    directive from FERC, Tsingas and Jurco had an IM conversation in which Jurco revealed that he
    had archived IM conversations in which the men discussed the UTC trading under investigation.
    See supra pp. 12–13. Less than two months later, on October 8, 2010, Tsingas provided sworn
    testimony to FERC Enforcement staff. That testimony included the following exchange:
    Q [Enforcement staff]: Do you use instant messaging?
    A [Tsingas]: Yeah, there may have been instant messaging.
    Q: What instant messaging programs do you use at work?
    A: Just IM, AIM, whatever that thing is.
    Q: Do you know if City Power keeps records of those IMs?
    A: I don’t think we do.
    Staff Report at 56. Given that Tsingas was well aware that Jurco, a City Power partner, had in fact
    kept records of those IMs, this response appears false or misleading. City Power now argues that
    this was a question about City Power’s records-retention policy, and so Tsingas’s answer was
    accurate. That is a possibility the finder of fact should perhaps consider, but even so, one could
    still conclude that Tsingas omitted the plainly material fact that, whatever City Power’s policies,
    Jurco did in fact have copies of relevant IMs.
    During the same October 2010 testimony, this exchange also occurred:
    Q: Do you know if Mr. Jurco or your other colleagues have set up their
    accounts to where it retains instant messages?
    A: I don’t believe they do, you know, but I don’t know 100 percent for a fact.
    Q: You haven’t checked with them to find out?
    A: I don’t remember if I checked or not. My understanding is they don’t, but I
    can’t remember how I remember that.
    37
    Q: After receiving Staff’s documentation preservation letter, did you make
    any attempt to see if they have instant messages on their system?
    A: No. But I did share that with the partners, at least, that this was out there.
    
    Id. But according
    to FERC’s allegations, Tsingas did know that Jurco had set up his account to
    retain IMs, and Tsingas had confirmed, after receiving the preservation letter, that Jurco had the
    messages on his computer. City Power’s excuse for this exchange is even flimsier: it says Tsingas
    was expressing his genuine uncertainty about how his colleagues’ accounts were configured at the
    moment of his testimony. See Defs.’ Mem. at 38. But even if that were so, the factfinder could
    still easily conclude that his answers were misleading or, at minimum, again omitted the obviously
    material fact that Jurco had archived the IMs.
    For similar reasons, if FERC’s allegations are correct, City Power’s December 2010 and
    November 2011 responses to data requests by Enforcement staff were false, misleading, or omitted
    material information. Both data requests sought all communications, including IMs, regarding
    City Power’s UTC transactions. The second request focused on the issue of IMs in detail. See
    Staff Report at 59–60. Yet neither of City Power’s responses acknowledged the existence of the
    IMs. Among other questionable statements in the November 2011 response was this: “Mr. Jurco
    is no longer with City Power Marketing, but prior requests to Mr. Jurco to produce any responsive
    instant messages did not reveal any such instant messages.” 
    Id. at 63.
    A factfinder could readily
    conclude that saying this without also saying that Jurco had archived relevant IMs was misleading,
    or was at least a material omission.
    In contending that this claim fails, City Power seems to think that as long as its statements
    were not technically false, it did not violate Market Behavior Rule 3. See, e.g., Defs.’ Mem. at 37
    (“FERC has not actually, specifically, alleged that these statements were false (nor can it because
    all of City Power’s statements were literally true).”). Indeed, City Power repeatedly describes this
    38
    claim as the “false statements claim.” See, e.g., 
    id. at 3,
    39; Defs.’ Reply at 21, 23. But Market
    Behavior Rule 3 is not limited to false statements; it forbids a Seller to “submit false or misleading
    information, or omit material information.” Assuming the truth of FERC’s allegations, one could
    reasonably conclude that City Power’s answers, even if not false, were misleading or omitted
    material information. City Power will get the chance to dispute FERC’s portrayal of the facts in
    due course, but for now the claim under Market Behavior Rule 3 survives.
    VII. JOINT AND SEVERAL LIABILITY
    Raising one final argument in his individual capacity, Tsingas contends that, contrary to
    the Penalty Assessment Order’s conclusion, he cannot be held jointly and severally liable for any
    penalty imposed on City Power. See Defs.’ Mem. at 39–44; Defs.’ Reply at 23–25. No surprise,
    FERC thinks he can. Pl.’s Opp’n at 29–32; see also Penalty Assessment Order at P 257. But the
    Court will not resolve this disagreement here. Even if Tsingas were correct, that conclusion would
    not compel the dismissal of any of FERC’s claims. It would only impact the remedy the Court
    would order if it ultimately finds that City Power is liable—which of course it might not find. Like
    the question of City Power’s right to a jury trial, then, this is a bridge the Court might never need
    to cross. Judicial restraint therefore counsels against crossing it now.
    CONCLUSION
    For the foregoing reasons, City Power’s motion to dismiss is denied. A separate order will
    issue. Unless the parties propose a different course, the Court expects City Power to file an answer
    in accordance with Federal Rule of Civil Procedure 12.
    /s/
    JOHN D. BATES
    United States District Judge
    Dated: August 10, 2016
    39
    

Document Info

Docket Number: Civil Action No. 2015-1428

Citation Numbers: 199 F. Supp. 3d 218

Judges: Judge John D. Bates

Filed Date: 8/10/2016

Precedential Status: Precedential

Modified Date: 1/13/2023

Authorities (28)

Calvi v. Knox County , 470 F.3d 422 ( 2006 )

Ed Peters Jewelry Co. v. C & J Jewelry Co. , 215 F.3d 182 ( 2000 )

United States Securities & Exchange Commission v. Pirate ... , 580 F.3d 233 ( 2009 )

Kenneth Foss, Administrator of the Estate of Vincent P. ... , 394 F.3d 540 ( 2005 )

ATSI Communications, Inc. v. Shaar Fund, Ltd. , 493 F.3d 87 ( 2007 )

rosalie-m-arlinghaus-of-the-will-of-frank-h-arlinghaus-and-rosalie-m , 543 F.2d 461 ( 1976 )

United States of America Ex Rel. Joel D. Joseph, and Joel D.... , 642 F.2d 1373 ( 1981 )

Trudeau v. Federal Trade Commission , 456 F.3d 178 ( 2006 )

Graham v. Securities & Exchange Commission , 222 F.3d 994 ( 2000 )

Electric Power Supply Ass'n v. Federal Energy Regulatory ... , 391 F.3d 1255 ( 2004 )

Markowski v. Securities & Exchange Commission , 274 F.3d 525 ( 2001 )

Rhinelander Paper Co. v. Federal Energy Regulatory ... , 405 F.3d 1 ( 2005 )

General Electric Company v. United States Environmental ... , 53 F.3d 1324 ( 1995 )

American Dental Association v. Donna E. Shalala, Secretary, ... , 3 F.3d 445 ( 1993 )

PDK Laboratories Inc. v. United States Drug Enforcement ... , 362 F.3d 786 ( 2004 )

City Abilene TX v. FCC , 164 F.3d 49 ( 1999 )

Califano v. Yamasaki , 99 S. Ct. 2545 ( 1979 )

New Hampshire Fire Insurance v. Scanlon , 80 S. Ct. 843 ( 1960 )

Ernst & Ernst v. Hochfelder , 96 S. Ct. 1375 ( 1976 )

United States v. First City National Bank of Houston , 87 S. Ct. 1088 ( 1967 )

View All Authorities »