Howard Town Center Developer, LLC v. Howard University , 278 F. Supp. 3d 333 ( 2017 )


Menu:
  •                              UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    HOWARD TOWN CENTER
    DEVELOPER, LLC,
    Plaintiff-Counter Defendant,              Civil Action No. 13-1075 (BAH)
    v.                                Chief Judge Beryl A. Howell
    HOWARD UNIVERSITY,
    Defendant-Counter Plaintiff-
    Third Party Plaintiff
    v.
    CASTLEROCK PARTNERS, LLC,
    Third Party Defendant.
    MEMORANDUM OPINION SETTING FORTH
    FINDINGS OF FACT AND CONCLUSIONS OF LAW
    The plaintiff Howard Town Center Developer, LLC, (the “Developer”) instituted this
    lawsuit against the defendant, Howard University (the “University”), over four years ago, on July
    15, 2013. The parties’ dispute, over which this Court possesses diversity jurisdiction, centers on
    a parcel of land (the “Property”) located in the Shaw neighborhood of Washington, D.C., that
    was leased by the University to the Developer in January 2010, based on the Developer’s
    contractual obligation to construct improvements at a cost of over $140,000,000. Instead, the
    Property has remained dormant for nearly eight years. Pending before the Court are the
    Developer’s claim that the University breached its contract with the Developer and the
    University’s claims that the Developer and the third-party defendant, CastleRock Partners, LLC,
    are in breach of contract. See Pl.’s Amended Complaint, ECF No. 72; Def.’s Counterclaim and
    Third-Party Complaint, ECF No. 15. 1 During an eight-day-long bench trial, the Court heard
    evidence on the parties’ claims and counterclaims. For the reasons set forth below, the Court
    concludes that the University has sustained its burden of proof on its breach of contract claims,
    that judgment must be entered for the University, and that forfeiture is an appropriate remedy.
    I.      PROCEDURAL BACKGROUND
    The parties’ allegations, as well as significant issues raised and either resolved or
    deferred in pre-trial motions, are summarized below.
    A.       THE PARTIES’ CLAIMS
    The Developer’s operative complaint in this action, Pl.’s Amended Complaint, asserts
    two counts, amounting to a single claim for relief. Count I claims breach of contract because the
    Developer “has performed its duties and responsibilities under the agreements,” while the
    University “has breached the terms of the Ground Lease and the Development Agreement by
    issuing an improper notice of termination and purporting to terminate the Ground Lease” and
    “has breached the terms of the Term Sheet by refusing to negotiate in good faith over the Second
    Amendments to the Ground Lease and Development Agreement.” Pl.’s Amended Complaint
    ¶¶ 88–91. In Count II, the Developer seeks declaratory relief, declaring that the Developer “was
    not and is not in default under the Ground Lease and the Development Agreement,” “that no
    Event of Default occurred,” “that [the University’s] purported termination . . . of June 17, 2013,
    is null and void,” “that delays that result from the historic designation process constitutes an
    Unavoidable Delay under the Lease,” and “that the construction deadlines contemplated by the
    parties will be shifted by at least the amount of time these proceedings are pending.” 
    Id. ¶¶ 95–
    1
    The third-party defendant, CastleRock Partners, LLC, assigned its rights and obligations under the
    operative agreements to the Developer, as explained below, but has not been released from its obligations to the
    University. See Def.’s Counterclaim and Third-Party Complaint ¶¶ 16–17. Consequently, the third-party defendant
    generally will not be referenced separately when discussing the actions of the parties in this matter.
    2
    100. The Developer seeks relief in the form of specific performance of the Term Sheet and
    “damages, including the lost value of the Lease during the period during which [the University’s]
    actions interfered with [the Developer’s] rights,” or, alternatively, “damages for the period of the
    99-year Ground Lease remaining at the time of breach”; declaratory relief; payment of “all of
    [the Developer’s] costs and expenses, including attorney’s fees”; and pre- and post-judgment
    interest. 
    Id. at 100.
    The University’s operative counterclaim and third-party complaint in this action alleges
    one claim of breach of contract each against Howard Town Center Developer, LLC, and the
    third-party defendant, CastleRock Partners, LLC. As support, the University asserts that the
    Developer “breached the Ground Lease by failing to pay rent as and when due” and requests
    judgment in its favor “in the amount of $1,475,000, together with additional interest, attorneys’
    fees and costs recoverable under the applicable contracts.” Def.’s Counterclaim and Third-Party
    Complaint ¶¶ 44, 47, 51, 54.
    B.      LITIGATION HISTORY
    This case’s extensive litigation history includes two memorandum opinions by this Court,
    as well as a decision of the D.C. Circuit. Upon instituting this action on July 15, 2013, the
    Developer filed a motion for a temporary restraining order, which motion was denied. See Pl.’s
    Mot. Temp. Restraining Order, ECF No. 5; Order, dated July 16, 2013, ECF No. 7. The
    Developer also requested a preliminary injunction. See Pl.’s Mem. Supp. Mot. TRO and/or
    Prelim. Inj., ECF No. 6-1. With the consent of the University, the Developer requested an
    extended briefing schedule on its injunction motion, which request this Court granted. See Min.
    Order, dated July 30, 2013. The University then filed a counterclaim seeking $1,475,000 for the
    second rental payment, originally due under the lease agreement by March 15, 2011, and moved
    3
    for summary judgment on October 15, 2013, which motion this Court granted on December 19,
    2013, while denying the Developer’s motion for injunctive relief. See Order, ECF No. 38.
    Relevant here, the Court’s decision was based in part on (1) the parties’ representations that a
    Term Sheet executed by the parties was “immaterial,” an “agreement to agree and not
    enforceable,” Pl.’s & Third-Party Def.’s Mem. P. & A. Opp’n Def.’s Mot. Summ. J. at 7–8 &
    n.8, ECF No. 31; see Howard Town Ctr. Developer, LLC v. Howard Univ. (HTC I), 
    7 F. Supp. 3d
    64, 72–73 (D.D.C. 2013); (2) the conclusion that the parties had agreed that the overdue rental
    payment was to be made by May 30, 2013, or the parties’ relationship would terminate, see HTC
    I, 
    7 F. Supp. 3d
    at 73–74; and (3) a determination that the University properly terminated the
    parties’ agreements and the Developer’s deposit of $1,475,000 on June 19, 2013, in an account
    held by its third-party agent, Closeline Settlements, did not cure its default, see 
    id. at 80–83.
    The
    Court also concluded that in addition to the $1,475,000 payment due to the University, forfeiture
    of the Developer’s rights in the lease was an appropriate remedy. See 
    id. at 83–87.
    On appeal, the D.C. Circuit vacated the grant of summary judgment to the University,
    concluding “[t]here is a genuine dispute whether the Developer was required to pay the
    University $1,475,000 by May 30, 2013, and, therefore, whether the University was entitled to
    terminate the Ground Lease and to collect $1,475,000 in damages,” and remanded for the Court
    to determine “whether the Term Sheet is a legally enforceable contract under D.C. law and, if so,
    how the Term Sheet affects both the Developer’s claim . . . and the University’s counterclaim.”
    Howard Town Ctr. Developer, LLC v. Howard Univ. (HTC II), 
    788 F.3d 321
    , 329–30 (D.C. Cir.
    2015). The Circuit declined to address three other arguments raised by the Developer: (1)
    whether “it was impossible to make the $1,475,000 rental payment in accordance with the terms
    of the Ground Lease because the parties had terminated the escrow account designated to receive
    4
    the payment”; (2) whether “the Developer cured the alleged breach by depositing $1,475,000
    into an escrow account on June 19, 2013”; and (3) whether “the district court erred by allowing
    the University to terminate the lease in addition to requiring the Developer to pay rent.” 
    Id. On remand,
    the parties filed cross-motions for summary judgment, which motions were
    denied. See Order, dated Jan. 31, 2017, ECF No. 93. Concluding the Term Sheet was a binding
    preliminary agreement, requiring the parties to fulfill the terms contained in the Term Sheet and
    negotiate toward the amendments to the Ground Lease and Development Agreement in good
    faith, the motions nevertheless were denied because the parties’ good faith in negotiating
    presented questions of fact as to which there was a genuine dispute. See Howard Town Ctr.
    Developer, LLC v. Howard Univ. (HTC III), No. 13-1075 (BAH), 
    2017 WL 421909
    , at *8–9
    (D.D.C. Jan. 31, 2017). The Developer’s argument that payment of the $1,475,000 was
    impossible was also addressed and rejected as a matter of law. See 
    id. at *9–10.
    Finally, while
    dropping its contention that the deposit of funds with its own third-party agent cured any default,
    the Developer argued on remand that the University’s notices to the defendant were insufficient,
    relying upon the D.C. Circuit’s observation that “the Ground Lease provides the University must
    send two notices to the Developer before it may terminate the lease.” HTC 
    II, 788 F.3d at 328
    .
    Noting that “the Developer received multiple notices of default over the course of the parties’
    business relationship,” the merits of the Developer’s arguments regarding notice were left to be
    resolved following trial. HTC III, 
    2017 WL 421909
    , at *11.
    C.      BENCH TRIAL
    Over the course of the eight-day bench trial, the Developer presented the testimony of
    eight witnesses: Ronald Cohen, Manager of Howard Town Center Developer, LLC; Dr. Sidney
    Ribeau, Ph.D., former President of Howard University; Steven Callcott, Deputy Historic
    5
    Preservation Office for the District of Columbia; Robert Tarola, former Chief Financial Officer
    of Howard University; Eric Siegel, Vice Manager of Howard Town Center Developer, LLC;
    Kurt Schmoke, former General Counsel and Vice President of Governmental Affairs for Howard
    University; Fabrice Vasques, Managing Director of Phillips Realty Capital; and Dennis Duffy,
    Certified General Real Estate Appraiser, testifying as an expert on damages. The University also
    called eight witnesses, including five of the Developer’s witnesses: Ronald Cohen, Sidney
    Ribeau, Eric Siegel, Kurt Schmoke, and Fabrice Vasques. In addition, the University called
    Norman Jenkins, Trustee of Howard University; Bryan Dickson, Vice President at Citi
    Community Capital; and Alan Brangman, former Associate Vice President of Facilities and Real
    Estate and University Architect of Howard University. 2 During the bench trial, the Court
    received the following 272 exhibits into evidence: Joint Exhibits 1–72; Plaintiff’s Exhibits 6, 8,
    10, 12–14, 16, 21–22, 27, 33–35, 37, 40, 46–48, 50, 52–56, 58–59, 62, 64, 66, 68–69, 71–73, 75,
    78, 80–81, 85–90, 93–94, 96–97, 101–06, 108–09, 111–12, 114, 117, 119, 121–26, 128, 134–35,
    137–38, 143, 145–46, 148–51, 153–54, 160–66, 168, 170, 173, 175, 177, 184, 191, 197–98, 202–
    03, 209, 212, 215–18, 220, 223, 225, 228–30, 232, 234, 236, 256–59, 261, 276–77, and 296–97;
    and Defendant’s Exhibits 1–2, 9–11, 14–15, 17–19, 21, 23, 25–26, 29, 31–32, 34, 36, 42, 44, 49–
    63, 67–68, 70–71, 74, 80, 87, 93–95, 100, 104, 109–14, 116–18, 124–25, 129–33, 135–36, 140,
    142–45, 149–54, and 156.
    Following the bench trial, both parties submitted proposed findings of fact and
    conclusions of law. See Pl.’s Prop. Findings Fact Concls. Law, ECF No. 108; Def.’s Prop.
    2
    The transcript of the bench trial appears on the docket as follows: Day 1 AM, ECF No. 112; Day 1 PM,
    ECF No. 120; Day 2 AM, ECF No. 113; Day 2 PM, ECF No. 121; Day 3 AM, ECF No. 114; Day 3 PM, ECF No.
    122; Day 4 AM, ECF No. 115; Day 4 PM, ECF No. 123; Day 5 AM, ECF No. 116; Day 5 PM, ECF No. 124; Day 6
    AM, ECF No. 117; Day 6 PM, ECF No. 125; Day 7 AM, ECF No. 118; Day 8 AM, ECF No. 119. Citations to the
    transcript indicate, if not otherwise apparent from the context, the name of the witness testifying to the information
    referenced.
    6
    Findings Fact Concls. Law, ECF No. 111. The parties’ respective claims became ripe for
    consideration on June 30, 2017. 3 The parties’ post-trial submissions, along with the testimony
    and exhibits at trial, have been duly considered.
    II.      FINDINGS OF FACT
    Based upon the testimony presented and exhibits admitted at the trial, the Court makes
    the findings of fact set forth below and further states its conclusions of law. See FED. R. CIV. P.
    52(a)(1) (“In an action tried on the facts without a jury . . . the court must find the facts specially
    and state its conclusions of law separately. The findings and conclusions may be stated on the
    record after the close of the evidence or may appear in an opinion or a memorandum of decision
    filed by the court.”).
    The findings of fact are based on the ample record in this case, which includes nearly
    three hundred exhibits and thousands of pages of trial testimony. “Factfinding is the basic
    3
    After postponing a total of three scheduled trial days at the request of the Developer and the Developer’s
    counsel so that they could attend the graduations of family members, one of which days was objected to by the
    University’s counsel on the ground that the long-scheduled trial could proceed without the Developer’s
    representative present, see Pl.’s Mot. One-Day Continuance May 22, 2017 Trial Date, ECF No. 100, and postponing
    the parties’ deadlines for submission of their Findings of Fact and Conclusions of Law by four days, also at the
    Developer’s request, the Developer and its counsel objected to the University’s counsel’s two requests for
    extensions for filing post-trial briefing as a result of emergency eye surgery that precluded counsel from working
    during the period of his recovery. Def.’s Mot. Extension Time, ECF No. 106; Pl.’s Resp. Position Statement, ECF
    No. 107; Def.’s Mot. Extension Time, ECF No. 109; Pl.’s Resp., ECF No. 110. The University first requested an
    extension of one week for the Developer, to June 21, 2017, and two weeks for the University, to July 5, 2017, to
    accommodate the University’s counsel’s emergency eye surgery and anticipated recovery period. Def.’s Mot.
    Extension Time at 4, ECF No. 106. The Developer objected to that proposal, arguing that the University should
    have only until June 28, 2017, on the ground that the Developer and the University should have the same amount of
    time for their filings, and that the Developer “d[id] not understand the . . . extension to July 5, 2017 to be based on
    the health issues of counsel.” See Pl.’s Resp. Position Statement at 2. The Developer’s proposal, granting it an
    extension to June 21, 2017, and the University an extension only until June 28, 2017, was adopted. See Min. Order,
    dated June 12, 2017. Then, on June 23, 2017, the University requested a further extension of two days because
    counsel’s “recovery has proven to be more extended than initially expected.” Def.’s Mot. Extension Time at 3, ECF
    No. 109. The Developer this time objected to any extension whatsoever, again on the ground that the Developer
    was entitled to the same extensions granted the University—ignoring the medical necessity for the University’s
    requested extension and lack of any such necessity on the part of the Developer—and noting that the Developer had
    already submitted its post-trial briefing and thus could not reap the benefit of the extension to which it believed it
    would be entitled in the event the University received an extension. See Pl.’s Resp. at 2. The University’s requested
    two-day extension for a medical necessity was granted over the Developer’s objection. See Min. Order, dated June
    23, 2017. This sampling of the motion practice in this litigation consumed judicial attention and falls short of the
    civility generally expected of members of the bar of this Court. See LCvR 83.8(b)(6)(v).
    7
    responsibility of district courts, rather than appellate courts . . . .” Pullman-Standard v. Swint,
    
    456 U.S. 273
    , 291 (1982) (quoting DeMarco v. United States, 
    415 U.S. 449
    , 450 (1974)). “The
    ultimate test as to the adequacy of findings will always be whether they are sufficiently
    comprehensive and pertinent to the issues to provide a basis for decision, and whether they are
    supported by the evidence.” Schilling v. Schwitzer-Cummins Co., 
    142 F.2d 82
    , 84 (D.C. Cir.
    1944) (footnotes omitted). The findings must be “sufficient to allow [the appellate] court to
    conduct a meaningful review, which is the main point of the rule.” Caffey v. West, 1998 U.S.
    App. LEXIS 4689, *6–7 (D.C. Cir. Feb. 9, 1998); see also Lyles v. United States, 
    759 F.2d 941
    ,
    943–45 (D.C. Cir. 1985) (noting that “an appellate court requires some reasonable measure of
    detail and exactness in the trial court’s findings as a predicate for intelligent review”(internal
    quotation marks omitted)); Fasolino Foods Co. v. Banca Nazionale del Lavoro, 
    961 F.2d 1052
    ,
    1058 (2d Cir. 1992) (“All that is required by Rule 52(a) is that the trial court provide findings
    that are adequate to allow a clear understanding of its ruling.”). Accordingly, the court need not
    “address every factual contention and argumentative detail raised by the parties,” Mayaguez v.
    Corporacion Para El Desarrollo Del Oeste, 
    824 F. Supp. 2d 289
    , 295 (D.P.R. 2011), or “discuss
    all evidence presented at trial,” Wachovia Bank N.A., Nat’l Ass’n v. Tien, 598 F. App’x 613,
    617–18 (11th Cir. 2014). See also 
    Schilling, 142 F.2d at 84
    (“While counsel may be
    disappointed that findings do not discuss propositions sincerely contended for, that, alone, does
    not make them inadequate or suggest that such propositions were not understood by the court.”).
    Instead, as the Advisory Committee Notes on Rule 52 explain, a “judge need only make brief,
    definite, pertinent findings and conclusions upon the contested matters; there is no necessity for
    over-elaboration of detail or particularization of facts.” FED. R. CIV. P. 52(a) advisory
    committee’s note to 1946 amendment.
    8
    While “a district court’s opinion should not simply state conclusions where
    circumstances require more detail,” courts have “wide leeway . . . in determining what facts to
    include.” Thermo Electron Corp. v. Schiavone Constr. Co., 
    958 F.2d 1158
    , 1160–61 (1st Cir.
    1992) (Breyer, C.J.) (internal quotation marks omitted). In particular, the trial court is tasked
    with the “opportunity to judge the witnesses’ credibility,” FED R. CIV. P. 52(a)(6), and should
    make that assessment where probative of the legal conclusions. See Cooter & Gell v. Hartmarx
    Corp., 
    496 U.S. 384
    , 401–02 (1990) (“Issues involving credibility are normally considered
    factual matters.” (citing FED R. CIV. P. 52)); Noble v. Sombrotto, 
    525 F.3d 1230
    , 1237 (D.C. Cir.
    2008) (remanding where district court failed to discuss evidence of “bad faith” and advising
    court to “closely scrutinize self-serving” evidence).
    In this case, the evidence shows the parties on a collision course toward litigation at least
    as early as October 2010, when the Developer lost the opportunity to finance the project with a
    particular lender with which the Developer had been in discussions since before entering into the
    agreements with the University. After October 2010, the Developer abandoned any intention it
    may have had previously to take seriously the agreed-upon deadlines for fulfillment of its
    monetary and construction-related obligations to the University. While no provision of any
    agreement ever executed by the parties made the Developer’s performance of those obligations
    contingent on the Developer securing financing—indeed, the University entered into the
    agreement for the express purpose of delegating to an experienced real estate development
    professional the risks and rewards of developing the Property—the Developer simply refused to
    perform fully absent financing. At the same time, the Developer repeatedly persuaded the
    University to forbear from terminating the parties’ agreements with tactics that varied from
    agreeing to new deadlines to threatening litigation.
    9
    The Developer’s principals appear to have deeply internalized the view that the
    Developer was entitled to hold fast to the Property while failing to fulfill its performance
    obligations, operating in an alternate reality in which the flagrant breaching of binding contracts
    is “reasonable” if doing so is favorable, from a business perspective, to the Developer. At one
    point, one principal of the Developer, Ronald Cohen, even expressed his view that for the
    Developer to honor its contractual commitment to make a long overdue $1,475,000 rental
    payment to the University, when financing had not yet been secured, would be “STUPID and
    that we are not,” Def.’s Ex. 118, Email from Ron Cohen to Eric Siegel and Alan Cohen, dated
    May 29, 2013, at 1, despite the University’s certain termination of the agreements. As the
    following evidence illustrates, the Developer was dead wrong, at least with respect to its own
    conduct.
    A.      THE PARTIES
    1. The plaintiff, Howard Town Center Developer, LLC, is a limited liability corporation
    (“LLC”) created for the purpose of developing the Property. Cohen testified that, as an LLC,
    Howard Town Center Developer, LLC, is a “standalone entity,” capitalized only for the
    purpose of the Howard Town Center project through funding provided by Cohen, his son,
    Alan Cohen, and his son-in-law, Eric Siegel. Trial Tr. Day 1 AM at 64:14–15, 65:11. The
    three individuals use the “trade name” Cohen Companies. See 
    id. at 99:3–8.
    Cohen further
    testified that the LLC form is used to “limit[] certain exposures you have” as a result of the
    risks associated with real estate development. 
    Id. at 63:25–64:1.
    Siegel testified that
    Howard Town Center Developer, LLC, “has no money in its bank account as of today” and,
    consequently, in the “narrow” sense that the LLC is unable to pay any judgment rendered
    10
    against it, the instant litigation is “risk free” for the Developer. Trial Tr. Day 5 PM at 26:14–
    22, 27:1–16.
    2. The defendant, Howard University, is a private university located in the District of Columbia,
    “authorized by a charter of the thirty-ninth Congress of the United States in 1867.” Def.’s
    Counterclaim and Third-Party Complaint ¶ 1.
    3. The third-party defendant, CastleRock Partners, LLC, is also an LLC in the business of
    developing real estate, and is headed by Timothy Kissler. See 
    id. ¶ 3;
    Trial Tr. Day 1 AM at
    61:4–17 (Cohen).
    B.      2008 – 2009: THE 2008 DEVELOPMENT AGREEMENT AND THE
    DEVELOPER’S INITIAL EFFORTS
    4. The Property. In December 2008, CastleRock and the University agreed that the University
    would lease to CastleRock a parcel of land, located at 2112 and 2146 Georgia Avenue NW,
    which CastleRock would develop for mixed residential and commercial use. See generally
    Def.’s Ex. 1, 2008 Development Agreement. The University had acquired the parcel of land
    from the District of Columbia in an agreement dated February 19, 2008. See 
    id. at 5.
    Two
    buildings were already located on the site: the WRECO (“Washington Railway and Electric
    Company”) garage, which was “the first purpose built bus garage for the city’s transit
    system,” constructed in 1930, and the Bond Bread building, a large industrial bakery
    building, constructed in 1929. Trial Tr. Day 2 PM at 4:7–17 (Callcott).
    5. Pertinent Terms of the Declaration of Covenants with the District. Pursuant to the
    University’s land conveyance agreement with the District of Columbia, the parcel was
    subject to a “Declaration of Covenants . . . recorded in the land records of the District of
    Columbia” in 2008. 2008 Development Agreement at 3; see generally Def.’s Ex. 2,
    11
    Declaration of Covenants. The Declaration of Covenants required that the parcel be
    developed, specifying four salient terms for its development, described below.
    a)      The design of the development was to be consistent with the Development
    Framework for a Cultural Destination District within Washington, D.C.’s Greater
    Shaw/U Street adopted by the D.C. Council in 2005. Declaration of Covenants at
    2; see Pl.’s Ex. 261, Draft Development Framework for a Cultural Destination
    District within Washington, DC’s Greater Shaw/U Street (the “DUKE Plan”). 4
    Notably, the DUKE Plan contemplated the Howard Town Center development
    project and specified that the project “[p]reserve . . . all or some façade elements”
    of the WRECO garage. DUKE Plan at 30; see Trial Tr. Day 2 PM at 5:15–7:22
    (Callcott).
    b)      The development was required to include a grocery store of no less than 35,000
    square feet, unless the District approved a grocery store comprising fewer square
    feet. See Declaration of Covenants at 3.
    c)      Construction was to commence within twenty-four months of the execution of the
    Declaration of Covenants and be completed within thirty-six months of said
    execution. See 
    id. at 4.
    In other words, the development was to be completed in
    2011.
    d)      The Developer was to enter into a “CBE Agreement” with the District of
    Columbia Department of Small and Local Business Development “requiring that
    20% of the equity and development participation of the Developer be comprised
    4
    The DUKE Plan is named after Edward Kennedy “Duke” Ellington, a Washington, D.C., native. See
    DUKE Plan.
    12
    of CBEs,” which are “local, small, or disadvantaged business enterprise[s]”
    certified as such under D.C. law. 
    Id. at 5.
    6. While never made clear why CastleRock involved the Developer in the development of the
    Property, shortly after the 2008 Development Agreement was signed, the Developer took
    steps, at its own expense, toward developing the parcel in anticipation of the transfer of
    CastleRock’s rights and obligations under the 2008 Development Agreement to the
    Developer. See Trial Tr. Day 3 AM at 106:22–113:7. These steps included:
    a)     retaining Fabrice Vasques of Phillips Realty Capital to prepare a “pro forma
    document,” which “sets forth all of the construction costs associated with the
    project; all of the sources where these funds will be coming from to pay for those
    construction costs and the uses for those funds.” 
    Id. at 107:6–14.
    The “initial
    plan” for financing the project was to obtain funding from the U.S. Department of
    Housing and Urban Development (“HUD”), through HUD’s “conduit,” Wells
    Fargo. 
    Id. at 113:8–18.
    Siegel testified that “starting 2009 through 2010 the
    economy was in bad shape and conventional financing was very difficult to have,
    particularly given the size of this project,” so “HUD financing was really one of
    our only options we could pursue.” 
    Id. at 114:4–14;
    see Trial Tr. Day 6 PM at
    9:23–10:17, 13:15–18 (Vasques) (testifying that in 2009 and 2010, financing
    sources were “[v]ery limited, the finance world was frozen, . . . [s]o, [the
    Developer] applied to HUD”);
    b)     retaining an environmental consultant, which determined that the site needed
    extensive remediation. See Trial Tr. Day 3 AM at 107:16–24; Pl.’s Ex. 231,
    13
    Phase II Environmental Site Assessment, 2112 and 2146 Georgia Avenue, NW,
    Washington, DC;
    c)       retaining two retail brokers, beginning in “approximately April or May of 2009,”
    “to seek retail tenants for the project,” in accordance with the requirements of the
    Declaration of Covenants. Trial Tr. Day 3 AM at 110:20–111:21; and
    d)       retaining GTM Architects to do “concept drawings and feasibility studies of the
    entire site.” 
    Id. at 112:16–113:2.
    C.       JANUARY 22, 2010: GROUND LEASE AND DEVELOPMENT
    AGREEMENT AND FIRST AMENDMENTS
    7. On January 22, 2010, the University and CastleRock executed a Ground Lease Agreement
    and a second Development Agreement. See Joint Ex. 1, Ground Lease; Joint Ex. 2,
    Development Agreement. Effective that same day, the University, CastleRock, and the
    Developer executed an agreement assigning CastleRock’s rights and obligations under the
    Ground Lease and Development Agreement to the Developer. See Joint Ex. 5, Assignment
    and Assumption of Ground Lease and Development Agreement. 5 Siegel testified that
    CastleRock, not the Developer, was the signatory to the Ground Lease and Development
    Agreement because CastleRock “was the awardee of the request [for] proposals from
    Howard University” and, consequently, given the public nature of the request for proposal
    process, “the parties believed it best, from the optic standpoint, to have Castle[R]ock sign the
    original document and then assign it to the master developer.” Trial Tr. Day 3 AM at
    115:20–24.
    5
    While the Developer now identifies CastleRock only as a “minority partner” in the project, Pl.’s Prop.
    Findings Fact Concls. Law ¶ 30, the Developer has previously acknowledged that CastleRock’s “responsibilities as
    an assignor are identical to [the Developer’s],” Pl.’s Mem. P. & A. Supp. Pl. & Third-Party Def.’s Mot. Summ. J. at
    18 n.2, ECF No. 87.
    14
    8. Pertinent Terms of the Ground Lease. The Ground Lease provided for a lease term of
    ninety-nine years, see Ground Lease at 5, as well as a right of first offer to purchase the
    Property in the event of its sale, see 
    id. at 68,
    in exchange for which rent was to be paid to the
    University according to a specified schedule.
    a)     The rent payment schedule required the Developer to pay:
    i.      $525,000 on January 22, 2010, “which amount shall be deemed earned
    and is non-refundable notwithstanding any future termination of this Lease
    for any reason whatsoever,” 
    id. at 5;
    ii.     $1,475,000 upon “the earlier to occur of (i) the date on which [the
    Developer] shall make settlement upon a construction loan for the funding
    of the costs of constructing the Mandatory Project Improvements (as
    defined in the Development Agreement) to the extent such costs are not
    funded from [the Developer’s] own resources or other equity sources, or
    (ii) March 15, 2011,” 
    id. at 2,
    5; and
    iii.    monthly installments of rent thereafter, beginning no later than December
    31, 2014, the latest possible “Rent Commencement Date,” at a monthly
    rate of $95,016.25, subject to (1) a percentage reduction during any period
    prior to the Rent Commencement Date in which, pursuant to the Ground
    Lease, rent is due, if less than 100% of the improvements are occupied by
    tenants and (2) increases after the fifth year following the Rent
    Commencement Date based on the Consumer Price Index, 
    id. at 6.
    In sum, at the outset of the parties’ relationship, the Developer agreed to pay rent
    to the University of $525,000 on January 22, 2010; $1,475,000 by March 15,
    15
    2011; and monthly installments of about $95,016.25 no later than December 31,
    2014. Over the last seven years, the Developer made only the first payment.
    b)     The Ground Lease provided that, in the event that the Developer should “at any
    time be in default with respect to any rental payments or other charges . . . and
    should such default continue for a period of ten (10) days after written notice from
    [the University] to [the Developer]; or should [the Developer] be in default in the
    prompt and full performance of any other of its promises, covenants or
    agreements” in the Ground Lease or the Development Agreement, subject to
    defined cure period and notice requirements, including “written notice, . . .
    specifying in BOLD FACE CONSPICUOUS TYPE, that [the University] intends
    to terminate” the Ground Lease if the default is not cured, the University shall
    have the option to terminate the agreements or reenter the Property. 
    Id. at 49–50.
    c)     The Ground Lease further provided that the University could recover from the
    Developer in damages, inter alia, “the worth at the time of award of any unpaid
    rent . . . that had been earned and is outstanding at the time of such termination”
    and “the reasonable amount of any costs or expenses incurred by [the University]
    in enforcing its rights under this [Ground] Lease after such default.” 
    Id. at 51.
    9. Pertinent Terms of the Development Agreement. The 2010 Development Agreement “set
    forth [the parties’] agreements and understandings concerning the planning, development and
    construction of the Project Improvements.” Development Agreement at 1.
    a)     In particular, the Development Agreement imposed a number of requirements, in
    addition to those contained in the Declaration of Covenants, on the Developer,
    including that:
    16
    i.      the improvements on the parcel would be constructed at the Developer’s
    “sole expense,” 
    id. at 1;
    ii.    because the parcel “is an integral part of the University’s campus, . . . the
    University requires that the Project Improvements be approved by the
    University” and “[n]o Work on any of the Project Improvements shall be
    commenced that is not approved in accordance with [this Agreement],” 
    id. at 11;
    iii.   the Developer “shall develop with Contractor, and deliver to the
    University, a comprehensive, integrated project schedule . . . addressing
    and setting forth specific dates for the timeline and sequencing of each
    distinct portion, aspect or phase of the activities and tasks to be
    accomplished by the Developer with respect to the construction and
    completion” of the development, 
    id. at 15.
    b)   The 2010 Development Agreement further dictated the timetable for the
    development of the Property, specifying as follows:
    i.     the Developer shall commence construction as provided in the Declaration
    of Covenants, i.e., by December 17, 2010, and achieve completion by
    December 17, 2011, or, failing either, shall “pay to the University, upon
    demand, all penalties, damages and demands that the University may
    become obligated to pay to the District of Columbia,” except that the
    University authorizes the Developer to communicate with the District
    regarding extension of those two dates, as long as the Developer “keep[s]
    the University fully informed” of its discussions with the District, the
    17
    University “ha[s] the right to participate directly” in those discussions, and
    the Developer has no “right to commit the University as to any matter,”
    and the University “shall not object” to any extension “consistent with the
    schedule for performance of Developer’s obligations,” 
    id. at 17–18;
    ii.    if construction is not commenced by March 15, 2011, the University may
    “give written notice specifying IN BOLD FACE CONSPICUOUS TYPE”
    that the Development Agreement and Ground Lease will be terminated if
    construction does not begin within thirty days of receipt of notice, 
    id. at 17;
    and
    iii.   “the Developer shall achieve Substantial Completion of all of the
    Mandatory Project Improvements no later than March 15, 2013 . . . ,
    subject to extensions for additional periods of time equal to time actually
    lost on account of Unavoidable Delays,” 
    id. at 18,
    which category includes
    delays due to, inter alia, “unanticipated, unusual and extreme weather”
    and “other unanticipated events or circumstances beyond the affected
    Party’s control,” 
    id. at 7.
    Significantly for the parties’ future relationship,
    the Unavoidable Delays provisions expressly excluded delays due to
    “changes in market conditions” affecting costs, “governmental delays”
    unless not attributable to the Developer’s actions, or “unavailability to
    Developer of any debt or equity financing to provide construction or
    permanent funding for the Project.” 
    Id. In other
    words, if the Developer
    was unable to obtain financing or to do so on the timetable the University
    expected, as set out in the Development Agreement, the University had the
    18
    clear contractual right to terminate the agreements and find a developer up
    to the job.
    10. First Amendments. The same day as the execution of the Ground Lease and Development
    Agreement, the parties executed amendments to both agreements, effective January 22, 2010,
    addressing various matters, including environmental remediation of the site. See generally
    Joint Ex. 3, Ground Lease Amendment; Joint Ex. 4, Development Agreement Amendment.
    The Developer’s consultant had “determined in 2009 [the remediation cost] to be
    approximately $4 million,” and the University agreed through the Development Agreement
    Amendment to shift a substantial portion of those costs from the Developer to itself. Trial.
    Tr. Day 3 AM at 116:7–15 (Siegel). Specifically, the amendments provided that:
    a)       the University would, at its own cost, hire a consultant to prepare a remediation
    report and plan, in coordination with the Developer, and “endeavor to cause the
    Consultant to complete a draft [remediation plan] by approximately mid-March,
    2010,” Development Amendment Agreement at 2;
    b)      the Developer would be responsible for implementation of the remediation plan,
    see 
    id. at 2–3;
    c)      the Developer would be responsible for remediation costs up to $750,000, and the
    University would cover the costs in excess of that amount, see 
    id. at 4–6;
    and
    d)      as a means of facilitating the Developer’s reimbursement by the University for the
    environmental remediation expenses in excess of $750,000, “the University and
    the Developer shall establish an escrow account . . . with an escrow agent . . .
    reasonably acceptable to the University and Developer,” into which the Developer
    would deposit the first two rental payments “when due and payable under the
    19
    Lease.” 
    Id. at 4.
    The account was to bear interest, which interest would “be
    added to” and “included as a part of” the funds in the account. 
    Id. at 5.
    The funds
    in the escrow account would be disbursed by the escrow agent, upon receipt of
    specified documentation, to cover incurred remediation costs. 
    Id. The parties
    entered into an escrow agreement, effective January 25, 2010, to form the
    required escrow account. See Joint Ex. 6, Escrow Agreement.
    D.     SPRING 2010 – FEBRUARY 2011: THE DEVELOPER SEEKS
    MODIFICATION OF THE AGREEMENTS
    11. Following the signing of the agreements and amendments thereto, the Developer continued
    to pursue financing for the project. Siegel testified that “[a]round March or April of 2010,
    HUD representatives had a site tour” and, after a subsequent meeting, the Developer was
    given a “green light to file an application” to obtain HUD financing for the project. Trial Tr.
    Day 3 AM at 114:17–21.
    12. At the same time, the Developer sought to extend the deadlines for commencement and
    completion of construction contained in the Declaration of Covenants. Siegel testified that in
    his view those deadlines were “unrealistic” and “candidly ridiculous” at the time they were
    entered into two years earlier, in 2008, by the University and the District. 
    Id. at 105:9–19.
    Based on this view, “beginning in the spring of 2010, Ron Cohen and [Siegel] met with
    various council members” seeking revision of the schedule, and those council members
    “seemed very supportive of the approach” outlined by the Developer. 
    Id. at 130:9–19
    (Siegel). Siegel further testified that he would learn later, in October 2010, almost ten
    months after executing the Ground Lease and Development Agreement with the University,
    that changing the schedule “required an administrative change from [the deputy mayor’s]
    office, not from the council members.” 
    Id. at 131:5–11.
    20
    13. Meanwhile, the parties undertook to fulfill their obligations under the Development
    Agreement Amendment and applicable law regarding the environmental remediation of the
    Property site. Those efforts culminated in the filing with the District, of a remediation plan,
    known as the “Corrective Action Plan,” dated November 17, 2010, which was approved by
    the District’s Department of the Environment (“DDoE”) on December 4, 2010. Pl.’s Ex.
    234, Corrective Action Plan. Siegel testified that no construction could be done on the site
    prior to the District’s approval of a Corrective Action Plan. See Trial Tr. Day 3 AM at
    121:24–122:3.
    14. The Developer First Accuses the University of Delay. Just prior to the District’s approval of
    the Corrective Action Plan, in a letter dated December 2, 2010, the Developer expressed to
    the University its belief that the University had delayed the environmental remediation
    process. See Pl.’s Ex. 72, Letter from Ronald Cohen to Diane Branch, Assoc. Vice President
    of Real Estate Development and Asset Mgmt., Howard Univ., dated Dec. 2, 2010, at 2. First,
    citing a provision of yet another agreement between the parties “that the Developer is not to
    release the environmental reports to any governmental agency without the prior approval of
    Howard,” the Developer objected to the University’s forwarding of an environmental report
    to the DDoE. 
    Id. (emphasis added).
    The Developer’s letter ignored the plain language of the
    cited agreement, which imposes the nondisclosure obligation only on the Developer, not the
    University. In any event, according to the Developer, the University’s action resulted in the
    DDoE issuing directives requiring remediation of the site before any excavation permits
    could be granted, a result characterized by the Developer as “unnecessary bureaucratic
    delay[],” without acknowledging any other potential reasons for this requirement, such as the
    safety of the community or environment. 
    Id. Second, the
    Developer expressed its view that
    21
    the University had failed to comply with the Development Agreement Amendment’s
    provisions regarding the timing of the production of the remediation report and plan,
    asserting that the report was produced “a full six (6) months after it was required” under that
    amendment. 
    Id. In fact,
    the University was merely required to “endeavor to cause the
    Consultant to complete a draft [remediation plan] by approximately mid-March, 2010,”
    Development Agreement Amendment at 2, and, according to the Developer, produced the
    report in August of that year, see Pl.’s Ex. 72, Letter from Ronald Cohen to Diane Branch,
    dated Dec. 2, 2010, at 2.
    15. In the same letter, the Developer represented that “[u]ntil the [remediation plan] is approved,
    the Developer is unable to complete its excavation permit application because DDoE
    comments, qualifications and conditions to the [plan] will determine certain basic questions
    as to whether excavation beyond the garage levels will be necessary.” 
    Id. at 3.
    According to
    the Developer, in light of the status of the remediation plan, “the March 15, 2011 deadline to
    commence construction is not realistic, and has not been for some time, beyond the control of
    the Developer.” 
    Id. At the
    same time the Developer was shifting fault for delay on the
    University, the Developer had been unsuccessful in obtaining any financing for the project.
    16. The University responded to the Developer, stating the University’s view that the University
    “has proceeded appropriately and with diligence” with the work required for environmental
    remediation, and that “[a]lthough that process has not proceeded strictly in accordance with
    the schedule outlined in the Amendment, the deviations from that schedule were caused by a
    number of factors beyond Howard’s control.” Pl.’s Ex. 46, Letter from Troy Stovall to
    Ronald Cohen, dated Dec. 9, 2010, at 1. Contrary to the Developer’s proffer of the
    remediation plan as a justification for delay, the University further stated it did “not believe
    22
    that any delays in the implementation of the process outlined in the Amendment have
    materially impaired the Developer’s ability to proceed with any of the numerous other steps
    necessary to commence and complete the Project as and when contemplated in the
    Development Agreement.” 
    Id. at 1.
    Countering the Developer’s contention that disclosure
    of an environmental report to the DDoE was improper, the University expressed its belief
    that disclosure was permissible and, moreover, was “required under applicable law.” 
    Id. at 2.
    6
    17. The December 15, 2010 Meeting. On December 15, 2010, the Developer submitted to the
    University plans the Developer describes as “reflect[ing] conceptual design, building
    specifications and schematic design for the project.” Pl.’s Ex. 109, Letter from Developer to
    Diane Branch, dated Dec. 15, 2010; see also Pl.’s Ex. 236, Howard Town Center Feasibility
    Study by GTM Architects, dated Dec. 15, 2010. That same day, representatives for the
    Developer and the University met to discuss the project. See Trial Tr. Day 3 AM at 127:18–
    128:4 (Siegel). At that meeting, the Developer presented those plans to the University and
    also informed the University that the Developer had “lost the opportunity to finance the
    project with HUD” in October 2010. 
    Id. at 128:11–14,
    115:3–4. The Developer raised the
    “difficulty in getting conventional financing for an entire city block project and the need to
    potentially phase the project if [the Developer] could not secure financing for an entire city
    block.” 
    Id. at 128:14–17.
    7 Stovall responded by “suggest[ing] that the University might be
    6
    While the Developer presses the view that the University “mishandl[ed] [the] environmental issues”
    affecting the Property, Pl.’s Prop. Findings Fact Concls. Law at 1, the evidence hardly supports that characterization.
    The University did not comply strictly with the generally framed deadline in the amendment to the Development
    Agreement, but took appropriate actions to comply fully with applicable environmental and safety laws. Moreover,
    while the Developer is also critical of the fact that the University “submitted a report to the District without the
    Developer’s approval,” that criticism also seems misplaced given the lack of any evidence indicating the
    Developer’s approval was in fact required. 
    Id. ¶ 86.
    7
    The record is thin as to the reasons why the Developer lost the HUD financing. Siegel testified that “we
    received a letter from them, a formal letter, that upon communications with the District they felt that there were
    23
    open to the idea of master-leasing one of the [two planned] residential towers as a way to
    finance the entire project at once.” 
    Id. at 129:1–3.
    In such an arrangement, the University
    would have rented an entire tower from the Developer and handled the unit-by-unit rental
    agreements itself. See 
    id. at 129:4–15.
    18. Under the Development Agreement, the Developer was required to submit a conceptual
    design for the University’s approval before submitting building specifications or a schematic
    design, presumably to give the University ample time to review these designs separately and
    avoid the inefficiencies of moving forward on a conceptual design not approved by the
    University, but the Developer failed to follow this procedure. See Development Agreement
    at 12–13. The University did not respond to the Developer’s proposed plans within twenty
    days, the amount of time specified in the Development Agreement. See Trial Tr. Day 3 AM
    at 129:19–130:3; Development Agreement at 12. 8
    19. In a letter dated January 20, 2011, Stovall wrote to the Developer indicating that the
    University was “continuing to review [the submitted] documents in greater detail” but was
    “writing this preliminary response to identify certain discrepancies between” the Developer’s
    documents and “the program for development contemplated in the Ground Lease and
    Development Agreement.” Joint Ex. 7, Letter from Troy Stovall to Ronald J. Cohen, dated
    Jan. 20, 2011, at 1. Specifically, Stovall noted that “it appears from [the documents] that the
    other priorities they wanted to have HUD pursue” with available funding. Trial Tr. Day 3 AM at 115:3–9. Despite
    Siegel’s seeming placement of the blame for the loss of the HUD financing on the District, other evidence suggests
    that the Developer’s negotiation tactics may have played a role. A letter from Cohen to a Wells Fargo representative
    regarding the HUD financing, dated September 16, 2010, reveals that Cohen found certain terms of one of Wells
    Fargo’s proposed agreements to be “a deal breaker” and expressed the view that at Wells Fargo, “the right hand does
    not know what the left hand is doing,” further asserting that “Wells Fargo must convince [Cohen] that it has its act
    together, or [he is] going to sever [their] relationship.” Def,’s Ex. 11, Letter from Ronald Cohen to Catherine Pharls,
    Wells Fargo Multifamily Capital, dated Sept. 16, 2010, at 1–2.
    8
    In discussing a later instance in which the Developer sent the University documents in mid-December that
    invited a response, counsel for the Developer “recognize[d]” that the period during which the University did not
    respond was “the holidays.” Trial Tr. Day 1 AM at 19:7–9.
    24
    commencement of construction will occur approximately at the end of January, 2012, rather
    than by March 15, 2011, as required under the Development Agreement” and that “the area
    of the proposed grocery store . . . is significantly less than the minimum required by both the
    Development Agreement and the Covenant.” 
    Id. at 1–2.
    Stovall reminded the Developer
    that the District’s approval was needed for modifications to the schedule and grocery store
    requirements and, with respect to the former, the University’s approval as well. See 
    id. The letter
    further included a “reminder that the Ground Lease requires that the Developer tender
    $1,475,000 to the University, by March 15, 2010 [sic], in payment,” 
    id. at 2,
    which rental
    payment due date was only two months away. Finally, Stovall requested that the Developer
    “contact [him] at [the Developer’s] earliest opportunity to schedule a time for a detailed
    discussion of the concerns identified in this letter.” 
    Id. 9 20.
    The Developer responded to the University, expressing the view that the concerns outlined in
    the University’s letter reflected “a direct departure from the results of [their] meeting on
    December 15, 2010,” where a “detailed discussion of the revised project schedule” had
    occurred. Joint Ex. 8, Letter from Developer to Troy Stovall, dated Feb. 1, 2011, at 1.
    Notwithstanding the Developer’s execution of the Development Agreement along with a first
    amendment to that agreement that incorporated construction deadlines, the Developer now
    complained “that neither the District nor the University set forth realistic deadlines three
    years earlier.” 
    Id. With respect
    to the items for which the Developer needed District
    approval, the Developer represented that it had been “informed in December by . . . staff [at
    the deputy mayor’s office] that a representative of Howard University intervened in [the
    9
    While the Developer describes the University’s letter as “not[ing] only unspecified ‘discrepancies,’” Pl.’s
    Prop. Findings Fact Concls. Law ¶ 90, the above-cited evidence demonstrates that, to the contrary, the University
    provided details as to the identified discrepancies.
    25
    Developer’s] process and insisted that [the deputy mayor’s office] not communicate with the
    Developer on this matter at this time and that it should be taken up with the administration of
    Howard University,” and, thus, the Developer had “been stymied in [its] efforts to meet with
    the District to address” the issues requiring District approval. 
    Id. at 2.
    The Developer made
    this accusation without acknowledging that the Developer was required by the Development
    Agreement to “keep the University fully informed” of all communications with the District
    regarding the deadlines. Development Agreement at 18. 10 The Developer again for a second
    time raised the issue of building the project in two phases and the University “potentially
    master leasing a residential tower for student housing,” conveying that this potentiality “has a
    real impact on the progress of the designs.” Joint Ex. 8, Letter from Developer to Troy
    Stovall, dated Feb. 1, 2011, at 3.
    21. Toward the letter’s conclusion, the Developer alluded for the first time to litigation with the
    University, stating it “can only assume through reading between the lines . . . that the
    University is setting up the Developer to assert termination of the Ground Lease and that this
    venture is heading toward litigation” but that the Developer was “prepared to vigorously
    defend [its] actions and efforts to date.” 
    Id. The Developer
    also noted that it “feels that the
    Closing Date . . . needs to be renegotiated.” 
    Id. The Developer
    understood that the “Closing
    Date” was the date upon which the $1,475,000 payment was to be made. See Trial Tr. Day 3
    AM at 140:12–15 (Siegel). Despite the aggressive tone of this letter, the Developer still had
    not secured financing for the project, and, according to the Developer, would not have been
    prepared to make the rental payment or move forward without that financing in place. See,
    10
    The Developer now acknowledges this, but apparently begrudgingly, since it notes that the phrase “keep
    the University fully informed” should be understood to mean “the Developer was not required to include the
    University on all its communications.” Pl.’s Prop. Findings Fact Concls. Law ¶ 199 n.5.
    26
    e.g., Trial Tr. Day 1 PM at 100:5–12 (Cohen) (explaining “because we . . . did not secure our
    financing, . . . we just weren’t in a position to break ground” by December 17, 2010, as
    required by the agreements).
    22. The Historic Factories Blog Post. Later that month, on February 22, 2011, Branch, the
    Associate Vice President of Real Estate Development and Asset Management at the
    University, forwarded Cohen an email containing the text of a blog post entitled “Bread for
    the City: Shaw’s Historic Bakeries” discussing the historic nature of the Bond Bread building
    on the Property. Def.’s Ex. 14, Emails Between Ronald Cohen, Diane Branch, Maybelle
    Bennett, and Scott Roberts, dated Feb. 22, 2011. She asked Cohen, “Are we concerned that
    there will be an application to deem this property historic? What are your
    recommendations?” 
    Id. at 1.
    Cohen forwarded the email to Siegel and wrote, “??? FYI- we
    need to monitor this . . . .” 
    Id. Siegel testified
    that upon receiving this email, he “went back
    to the Duke Plan” and verified its requirement that “some portion of the corner of V and
    Georgia Avenue,” i.e., the WRECO garage, but not the Bond Bread building, be preserved.
    Trial Tr. Day 3 PM at 93:15–94:4.
    23. Siegel testified that between February 1, 2011, and the end of the month, Stovall “was
    essentially requesting information from [the Developer] so that he could evaluate th[e]
    master lease concept” and two-phase plan newly proposed by the Developer but conceded
    that the University did not agree to either alternative plan. Trial Tr. Day 3 AM at 143:7–
    144:10. With the March 15, 2011, deadline for payment of the $1,475,000 rent installment
    looming, on February 28, 2011, the Developer submitted to the University a memorandum
    setting out a schedule for the development, based on a two-phase project, and moving the
    Closing Date to “the earlier of settlement on a construction loan or February 15, 2012,” with
    27
    “excavation to begin December 8, 2011.” See Def.’s Ex. 15, Memorandum from Ronald J.
    Cohen to Troy Stovall, dated Feb. 28, 2011, at 1–3.
    E.      MARCH – AUGUST 2011: THE UNIVERSITY AGREES TO CERTAIN
    OF THE DEVELOPER’S PROPOSED MODIFICATIONS, BUT THE
    DEVELOPER SEEKS FURTHER MODIFICATION
    24. A month later, on March 31, 2011, Stovall represented that the University had undertaken “a
    considered review of the entire history of the Developer’s interaction with the University
    since the Project’s inception” and was “prepared to approve the revised schedule for the
    Project” provided by the Developer on February 28, 2011, which included a scheduled
    construction commencement date of December 8, 2011. Joint Ex. 9, Letter from Troy
    Stovall to Developer dated Mar. 31, 2011, at 1.
    25. At the same time, however, after consideration of the Developer’s proposals to change the
    development plan to, inter alia, “divide its development into two phases,” the University did
    “not believe [the Developer’s explanations for the proposals] warrant changes” to the
    development plan set out in the agreements. 
    Id. at 2.
    26. Notably, Stovall also highlighted the fact that the Developer “failed to pay the $1,475,000
    rental payment that became due under the Ground Lease on March 15, 2011,” and explained
    that the University did “not concur” with the Developer’s position that the failure was
    justified. 
    Id. at 2
    (emphasis in original). Nevertheless, having agreed to push back the date
    for commencement of construction, the University also agreed to “postpone the due date for
    that payment until December 8, 2011,” as requested by the Developer. 
    Id. (emphasis in
    original). Having rejected a two-phase project, however, the University did not grant the
    Developer’s request that “only half of the next ground lease payment” be paid at that time.
    28
    Def.’s Ex. 15, Memorandum from Ronald J. Cohen to Troy Stovall, dated Feb. 28, 2011, at
    2.
    27. Siegel testified that at the end of April 2011, the Developer met with the deputy mayor to
    brief him on the project. See Trial Tr. Day 3 PM at 9:7–13 (Siegel). According to Siegel, the
    Developer did not request revision of the covenant deadlines in that meeting, however,
    because, notwithstanding the University’s clear rejection of the Developer’s proposed change
    to the development plan to permit two phases, it “couldn’t ask for deadlines . . . unless [the
    Developer] knew whether [it] w[as] building all at one time or in two phases.” 
    Id. at 9:14–
    20. Notably, the Developer still had not secured financing at this point.
    28. Siegel further testified that during the months of May, June, and July, the Developer and the
    University discussed how they would proceed with the project, with the University
    explaining that master-leasing could be considered if the rental rate reflected a twenty
    percent discount off the market rate, which the Developer believed “wasn’t economically
    feasible.” 
    Id. at 3:24–25.
    29. By the summer of 2011, the Developer had still been unable to secure financing after the
    possibility of the HUD funding had evaporated. In good news on the financing front,
    however, in a “letter of intent” dated July 7, 2011, J.P. Morgan Investment Management,
    Inc., “set forth the general terms and conditions under which [it] would be prepared to enter
    into a [redacted] joint venture agreement” with the Developer regarding the development,
    “based upon the information [the Developer has] supplied . . . to date.” Pl.’s Ex. 212, Letter
    of Intent from J.P. Morgan Investment Management, Inc., to Ron Cohen, dated July 7, 2011,
    at 1. The letter of intent was “non-binding” and required the Developer to sign and return a
    29
    copy of the letter to J.P. Morgan “no later than July 15th, 2011” if the developer agree[d] to
    the terms and conditions described.” 
    Id. at 4.
    30. Siegel testified that he provided the letter of intent from J.P. Morgan to the University and
    continued discussions regarding the plan for the project, sending a further proposal for terms
    of the project to the University on July 28, 2011. See Trial Tr. Day 3 PM at 5:4–11, 7:6–14.
    In that proposal, the Developer “approach[ed] the [two-phase] idea from the expense side,”
    suggesting the University agree to “defer[]” the Developer’s rental payment obligations for
    the improvements made to the Property, i.e., accept late payments with interest, in exchange
    for the Developer building the project in a single phase, as provided in the Development
    Agreement, and as the University had consistently required. Trial Tr. Day 6 AM at 70:18–
    71:11.
    31. The District Expresses Concerns to the University. In a letter dated August 19, 2011, Stovall
    provided to the Developer a copy of a letter dated August 15, 2011, from the District
    regarding the Declaration of Covenants and requested that the Developer respond by August
    26, 2011, so that the University could, in turn, respond to the District. See Def.’s Ex. 19,
    Letter from Troy Stovall to Ronald J. Cohen, dated Aug. 19, 2011, at 1. The letter from the
    District stated that the University “was required to cause its selected developer to achieve
    Commencement of Construction . . . by December 17, 2010” and noted that “Howard ha[d]
    yet to achieve” that milestone. 
    Id. at 3.
    The District represented that it was “willing to
    consider extending the deadline for Commencement of Construction to October 1, 2012 if
    Howard” delivered, by September 16, 2011, (1) an updated schedule of performance; (2)
    additional security in the amount of $100,000; and (3) the “CBE Agreement executed by the
    Developer, as required under the Covenants.” 
    Id. 30 32.
    The Developer responded in a letter, dated August 22, 2011, repeating many of its previous
    assertions regarding the project, including that “neither the District nor the University set
    forth realistic deadlines three years earlier when the Declaration of Covenants was executed,”
    even though these were the terms to which the Developer had agreed in the Ground Lease
    and Development Agreement, and that “a representative of Howard University intervened in
    [the Developer’s] process” with the District, causing delays, even though the University was
    merely enforcing the term of the Development Agreement requiring that it be informed of the
    Developer’s communications and negotiations with the District. Joint Ex. 10, Letter from
    Developer to Troy Stovall, dated Aug. 22, 2011, at 1, 2. The Developer also informed the
    University of its position with respect to the three items requested by the District, asserting
    that the Developer would (1) not agree to a revised schedule with the District until “Howard
    and the Developer agree on terms to pursue the entire project or, alternatively, to develop it
    in phases”; (2) “not provide any additional money until Howard and [the Developer] reach an
    agreement on how to proceed; and (3) not sign the CBE Agreement until the University and
    the Developer “have an amended Ground Lease (and corresponding amended Development
    Agreement) in place.” 
    Id. at 2.
    With respect to the requested $100,000, in particular, Siegel
    testified that “the position we had in response was we’re not interested in posting security.”
    Trial Tr. Day 3 PM at 10:3–6. Again, the Developer was not open to investing additional
    money in the project when it had not obtained a funding commitment and did not know if the
    project was going to move forward.
    33. Also on August 22, 2011, Stovall responded to the Developer’s July 28, 2011, proposal,
    which reflected an expense-side version of the two-phase approach previously rejected by the
    31
    University, stating that the “proposal is not acceptable to Howard University.” Pl.’s Ex. 90,
    Emails Between Eric Siegel and Troy Stovall, dated Aug. 20, 21, 22, 2011, at 1.
    F.      AUGUST – SEPTEMBER 2011: WITH THE DISTRICT POSING
    QUESTIONS, THE UNIVERSITY DEMANDS ASSURANCE OF
    PERFORMANCE FROM THE DEVELOPER, WHICH INSTEAD OF
    PROVIDING SUCH ASSURANCE, ALLUDES TO LITIGATION
    34. In a letter dated August 30, 2011, Stovall responded to the Developer’s August 22, 2011,
    letter “to make clear” that “[t]he Developer’s proposed modifications to the Project are not
    acceptable; and the terms the Developer has proposed to us for the alteration of its
    obligations are likewise unacceptable.” Joint Ex. 11, Letter from Troy Stovall to Developer,
    dated Aug. 30, 2011, at 1. Referring to prior discussions and correspondence between the
    parties, Stovall noted that he had “made it abundantly clear . . . that (i) although the
    University was willing to listen to and consider [the Developer’s] proposed changes, and
    although the parties may engage in further discussions about them, [the Developer] should
    not assume that they are or will be approved; and (ii) our continuing discussions should not
    be construed to delay . . . efforts to carry out the Project as previously agreed.” 
    Id. at 1–2.
    35. Stovall also informed the Developer of the University’s position that under the governing
    agreements, the Developer alone is responsible for securing financing and that any delay in
    doing so does not warrant delay in execution of obligations under those agreements; and that
    the Developer’s “accusations concerning the University’s purported interference with [the
    Developer’s] communications with District representatives” were “responded to . . . many
    months ago” and “any misunderstanding on the part of the District as to [the Developer’s]
    authority to deal directly with the District was dispelled late last year.” 
    Id. After enumerating
    the Developer’s lapsed obligations under the agreements, Stovall expressed
    concern that the Developer had stated repeatedly that it was “unable or unwilling to proceed
    32
    with the construction and completion of the Project according to the single-phase program”
    specified in the agreements, unless “the University agree[d] to significant financial
    concessions.” 
    Id. at 3–4.
    36. Finally, Stovall’s letter demanded that the Developer provide assurances to the University by
    September 8, 2011, including, inter alia, (1) “unqualified ratification of [the Developer’s]
    obligations under the existing Project Documents and an unqualified statement that the
    Developer is ready, willing and able to timely comply with and perform” those obligations;
    (2) “[r]easonable evidence” of the Developer’s ability to obtain tenants, financing, and
    permits consistent with its obligations; and (3) “written affirmation of [the Developer’s]
    intent and ability . . . to timely pay to the University the rent payment in the amount of
    $1,475,000.00 due on December 8, 2011” and comply with the other milestone dates set out
    in the Developer’s February 28, 2011, memorandum and approved by the University on
    March 31, 2011. 
    Id. at 5–6.
    37. Having received no assurances from the Developer by September 8, 2011, in a letter dated
    September 9, 2011, the University wrote to the District, copying the Developer, among
    others, “to update [the District] on the status” of the Project, informing the District that while
    the University “requested substantiated assurances from the Developer of its ability and
    intent to fulfill its contractual obligations to the University and the District[,] . . .
    [u]nfortunately, as of this date [the University] ha[s] not received those assurances.” Def.’s
    Ex. 23, Letter from Troy Stovall to Senthil Sankaran, Director of Development, Office of the
    Deputy Mayor for Planning and Economic Development, dated Sept. 9, 2011, at 1.
    38. As noted, despite the District’s demand to the University setting a strict deadline, the
    Developer did not timely respond on September 8, 2011. Siegel explained that the Developer
    33
    did not timely respond because Siegel “was busy working on a chronology of events to make
    sure that the recitation of facts was precise and accurate.” Trial Tr. Day 3 PM at 13:9–16.
    The Developer responded to the University’s letters of August 30 and September 9, 2011, in
    a letter dated September 15, 2011, setting out the Developer’s perspective on the chronology
    of events, followed by a warning to the University: “Conduct yourselves accordingly.” See
    Joint Ex. 12, Letter from Developer to Troy Stovall, dated Sept. 15, 2011, at 1–7. Yet, rather
    than “conduct” itself in accordance with extant agreements or provide any of the assurances
    requested by the University and the District, the Developer continued to press its desired
    modifications to the agreements, expressing its “hope that we can put these issues behind us
    and continue” negotiating terms that “can realistically form the basis for a modified ground
    lease.” 
    Id. at 7.
    Reading between the lines, as the Developer was wont to do, see Joint Ex. 8,
    Letter from Developer to Troy Stovall, dated Feb. 1, 2011, at 3, the Developer appears to
    have been seizing an opportunity, leveraging the pressure exerted on the University by the
    District’s demand for assurances to, in turn, pressure the University to concede to terms more
    favorable to the Developer, which terms the University had resisted. Indeed, acknowledging
    the harm to the University of continued delay in the project, the Developer noted that “the
    University has foregone approximately $1,000,000 in potential lease revenue upon delivery
    of this project by failing in a timely manner to come to terms with the economic realities of
    the environment we currently operate in and by modifying [sic] ground lease terms
    accordingly so that we can break ground expeditiously.” Joint Ex. 12, Letter from Developer
    to Troy Stovall, dated Sept. 15, 2011, at 7. As the Developer put it, in a prescient, and not-
    so-oblique, threat of litigation, “[o]therwise, we will find ourselves mired in dispute, and the
    project will remain dormant for the foreseeable future.” 
    Id. At this
    point, the Developer still
    34
    had no funding secured and, as Cohen and Siegel made very clear in their testimony, moving
    forward with the project and any further investment of the Developer’s funds—even as
    relatively small an amount as the $100,000 demanded by the District—was not going to
    happen.
    G.      SEPTEMBER 2011: THE UNIVERSITY SENDS THE FIRST NOTICE OF
    DEFAULT TO THE DEVELOPER
    39. On September 26, 2011, the University sent the Developer a notice that the Developer “is in
    default under the Project Documents” for its failure to comply with the requirements of those
    documents in the time provided. Joint Ex. 13, Notice of Default, dated Sept. 26, 2011, at 1.
    The University also stated that “the Developer is in anticipatory breach of the Project
    Documents,” noting that “the Developer has evidenced repeatedly its inability and/or
    unwillingness to proceed with the construction and completion of the Project according to the
    program” set out in the governing agreements, most recently by failing to provide the
    assurances requested in the letter dated August 30, 2011. 
    Id. at 3–4.
    In other words, the
    University did not buckle to the pressure applied by the Developer to accede to further
    concessions, under the threat of litigation; the Developer’s bullying tactics did not work.
    40. Cohen feigned surprise at the University’s reaction to the Developer’s utter failure to provide
    assurances but only to threaten litigation, testifying that upon receiving this letter, he said to
    Siegel, “Let’s get to the bottom of this. . . . Where is this coming from? Something we
    messed up on? Something they’re posturing?” Trial Tr. Day 2 AM at 78:4–79:7. With the
    Developer’s bluff called, the Developer owned up to its inability to secure financing. In a
    letter dated September 29, 2011, the Developer responded to the September 26, 2011, Notice
    of Default, explaining its “great difficulty in securing conventional financing for the entire
    project” after losing the HUD financing and noting the “shortfall” of $1,500,000 “in
    35
    financing this $145,000,000 project.” Joint Ex. 14, Letter from Developer to Troy Stovall,
    dated Sept. 29, 2011, at 1. The Developer responded “to each of [the University’s] alleged
    defaults in turn so that [the University] can receive the positive assurances [it] seek[s] that,
    with the exception of this $1,500,000 shortfall, [the Developer] ha[s] not stopped [its]
    efforts.” 
    Id. at 2.
    The Developer’s responses focused on the “financing hurdle[s]” involved
    in the project and its continuing efforts to obtain financing; the Developer’s reasons for
    failing to comply with certain requirements, such as the requirement that it erect and
    maintain signage for the project so the community would be aware of the development
    planned for the site, characterizing its failures as “reasonable” or “prudent”; and the
    Developer’s progress in obtaining tenants, including a grocery store exceeding the square
    footage requirements of the Declaration of Covenants. 
    Id. at 1–5.
    In this September 2011
    exchange, the University simply refused to be bullied or threatened and the Developer finally
    responded substantively to the University and District’s request from a month earlier, in
    August 2011. The parties then tried to reset the working relationship.
    H.      OCTOBER – DECEMBER 2011: THE UNIVERSITY CONTINUES ITS
    RELATIONSHIP WITH THE DEVELOPER NOTWITHSTANDING THE
    DEVELOPER’S DEFAULTS
    41. The Proposed Memorandum of Understanding. While Stovall was primarily responsible for
    the project and had the authority to issue the Notice of Default and engage in other
    communications with the Developer, see Trial Tr. Day 1 PM at 16:12–16 (Ribeau), some
    within the University did not agree with Stovall’s approach. Dr. Hassan Minor, a Senior
    Vice President of the University in charge of governmental relations, had been responsible
    for the Howard Town Center development project at its inception, before the project was
    transferred to Stovall. See 
    id. at 3:18–4:15,
    35:7–14 (Ribeau). Dr. Ribeau testified that the
    36
    Howard Town Center project was “Dr. Minor’s baby” and reassigning it to Stovall had been
    “tough.” Trial Tr. Day 1 AM at 35:10–36:11. On October 21, 2011, Dr. Minor emailed Dr.
    Ribeau expressing his view that Stovall had employed a “‘default to litigation’ approach” to
    the project and his understanding that he (Dr. Minor) had been tasked with “see[ing] if it was
    possible to change the final destination of the [Howard Town Center development] train from
    injunctions, damages and years of litigation to building permits, construction, ribbon-cuttings
    and occupancy.” Pl.’s Ex. 6, Emails Between Dr. Hassan Minor and Dr. Sidney Ribeau,
    dated Oct. 21, 2011, and Nov. 2, 2011, at 2. Dr. Minor “enclosed a draft of a new
    [Memorandum of Understanding (“MOU”)] that ha[d] been developed in the last 3 days with
    the [Developer].” 
    Id. 42. Along
    with Dr. Minor, Norman Jenkins helped develop the MOU on the University’s behalf.
    See Joint Ex. 15, Email and Memorandum from Eric Siegel to Norman Jenkins, cc: Ron
    Cohen, dated Oct. 17, 2011. Jenkins is an alumnus of Howard University and has
    volunteered for the University for many years, now serving as a trustee. See Trial Tr. Day 7
    AM at 4:2–7, 4:24–5:10 (Jenkins). Jenkins “run[s] a company [that] develop[s] and
    acquire[s] all classes of real estate” and testified that Dr. Ribeau asked him to become
    involved in the Howard Town Center project because he “wanted someone with a
    development background to come in and also have a sympathetic ear and a different lens than
    the University might have, to see if we can get the project moving.” 
    Id. at 4:14–17,
    5:11–17.
    Both Cohen and Siegel used the same words to express their view that Jenkins was “a breath
    of fresh air.” Trial Tr. Day 1 AM at 92:12–19 (Cohen); Trial Tr. Day 3 PM at 26:14–15
    (Siegel).
    37
    43. The proposed MOU between the Developer and the University was reviewed by a consultant
    retained by the real estate committee of the Howard University Board of Trustees. See Pl.’s
    Ex. 50, Memorandum from Sumner Partners & S. Klebanoff to Josh Rales, Trustee of
    Howard University, cc: Sidney Ribeau, Troy Stovall, dated Nov. 14, 2011. In an eight-page
    memorandum relaying its assessment to a trustee of the University, the consultant noted its
    “previous and standing recommendations to terminate the transaction and re-market the
    property based on the default and actions of the [Developer]” and stated that the “‘take away’
    from [its] review of the [MOU] is that there is nothing new in [the Developer’s] proposal—in
    fact, it just continues the ‘free look’ that [the Developer] has been provided for calendar year
    2011.” 
    Id. at 1.
    Indeed, for the two years that the Developer had exclusive rights to the
    Property’s leasehold, the Developer had paid only the initial rental payment on the execution
    of the agreements in January 2010 and failed to make any other rental payment. 11
    44. Certain persons within the University appear to have been persuaded by the consultant’s
    standing recommendation. Robert Tarola, who at the time was the University’s Chief
    Financial Officer, took over responsibility for the project from Stovall at some point “late in
    2011.” Trial Tr. Day 2 PM at 44:24–45:2. Tarola testified that at the time he took over,
    “[t]here were a few people that had a view that [the Developer] would not be able to perform.
    And as a result a better deal could be obtained.” 
    Id. at 58:24–59:5.
    45. Others within the University continued to desire preservation of the University’s relationship
    with the Developer, if the University and the Developer could formulate “a deal equal to the
    11
    The Developer cherry picks from a document containing notes from a November 8, 2011, meeting with Dr.
    Ribeau to suggest that the motivating factor behind the consultant’s recommendation that the Developer be
    terminated and the Property remarketed was that the “[d]eal was done below current market,” Pl.’s Prop. Findings
    Fact Concls. Law ¶ 121 (quoting Pl.’s Ex. 53, Notes from Meeting with President Ribeau, dated Nov. 8, 2011, at 2),
    but viewed in its totality, that document, along with the consultant’s report and the entire record in this case,
    demonstrate that the Developer’s failure to perform was the precipitating factor for the consultant’s consideration of
    the consequences to the University of continuing with or terminating that relationship.
    38
    original.” Pl.’s Ex. 52, Emails Between Dr. Hassan Minor, Dr. Sidney Ribeau, and Robert
    Tarola, dated Dec. 11–12, 2011. As noted, Dr. Ribeau had asked Dr. Minor to develop the
    MOU and had brought in Jenkins for that purpose. 
    See supra
    Part II.H.41–42. Tarola
    testified that after Stovall’s departure from the University for personal reasons, see Trial Tr.
    Day 1 PM at 60:24–61:4 (Ribeau), Dr. Ribeau “asked [Tarola] to pick up the project and see
    if [he] c[ould] get it moving to a positive result.” Trial Tr. Day 2 PM at 59:6–12.
    I.     DECEMBER 2011 – MARCH 2012: DURING NEGOTIATIONS, THE
    DEVELOPER FURTHER DEFAULTS, AND THE UNIVERSITY SENDS
    TWO ADDITIONAL NOTICES OF DEFAULT
    46. The Developer failed to make the $1,475,000 second rental payment on December 8, 2011.
    Cohen testified that while the Developer “had the money to do whatever was necessary to get
    this project off the ground, including funding whatever equities was required, and any other
    obligations financially that it took to get this project up and running,” after “collective
    decision input from the attorney, from [his] son, from [his] son-in-law, Eric Siegel, and
    [him]self,” he decided not to make payment as required by the extended deadline proposed
    by the Developer and accepted by the University in March 2011. Trial Tr. Day 2 AM at
    103:2–104:14; see 
    also supra
    Part II.E.24.
    47. On December 28, 2011, Tarola transmitted to Cohen, via email, a “letter agreement that
    Howard University propose[d] [the parties] jointly execute to move the Town Center project
    forward.” Joint Ex. 16, Email from Robert Tarola to Ron Cohen, cc: Timothy Kissler and
    Dr. Hassan Minor, dated Dec. 28, 2011, at 1. The email further stated, “We are prepared to
    negotiate in good faith toward an immediate resolution of issues that have caused project
    delays.” 
    Id. The referenced
    letter agreement states that the parties “desire to engage in
    discussions . . . aris[ing] out of a pending dispute between the University and Developer
    39
    concerning Developer’s obligations.” 
    Id. at 2.
    Under the heading “Negotiations,” the letter
    agreement provides that “the parties . . . acknowledge that they are about to commence
    negotiations . . . concerning the obligations owed to the University by Developer . . . with a
    view to a settlement by the parties of their dispute” and further provides, inter alia, that “[n]o
    [w]aiver” of any rights under the existing agreements would occur as a result of the letter
    agreements and “while there may be many matters which the parties hope to discuss, no
    agreement reached with respect to any matter . . . shall have any effect whatsoever unless
    such agreement is reduced to writing.” 
    Id. at 2
    –3. The Developer executed this agreement,
    “with some minor changes,” on January 4, 2012. See Def.’s Ex. 34, Email from Eric Siegel
    to Robert Tarola, dated Jan. 4, 2012, at 1, 4.
    48. On January 12, 2012, Dr. Ribeau sent an email to Tarola, Dr. Minor, and Klebanoff
    designating them as the University’s “negotiating team for the current phase of project
    deliberations.” Pl.’s Ex. 55, Emails from Dr. Ribeau and Dr. Minor, dated Jan. 12, 2012, at
    2. In response to a question from Dr. Minor about Jenkins’s relationship to the negotiating
    team, Dr. Ribeau stated that Dr. Minor would “replace Norm on the team” but “[h]e should
    still be on call.” 
    Id. at 1.
    49. The Second Notice of Default. Notwithstanding the University’s commitment to negotiate
    toward a modified agreement with the Developer regarding the Howard Town Center project,
    on February 3, 2012, the University sent the Developer, for the second time, a notice of the
    Developer’s defaults, and in the same document gave the first notice of the University’s
    intent to terminate the agreements with the Developer. See Joint Ex. 17, Notice of Default
    and Notice of Intent to Terminate, dated Feb. 3, 2012. The notice states that “[t]he
    Developer has failed to perform a number of its important obligations and responsibilities
    40
    under the Project Documents, including those listed in the University’s letter to the
    Developer dated September 26, 2011, and subsequent correspondence” and that “[a]s a result
    of those prior notices to the Developer and the failure of the Developer to completely cure
    the defaults itemized in those notices within the applicable cure periods,” the Developer now
    has only one “further opportunity to cure” before “it may be terminated by the University.”
    
    Id. at 1,
    3. The notice further cites the Developer’s failure to pay $1,475,000 by December 8,
    2011, as agreed by the parties in the letters between Stovall and the Developer, and warns
    that “if that failure is not cured . . . within ten (10) days after this notice, then such failure
    shall also constitute an event of default” for which, pursuant to the Ground Lease, the
    Developer would have one “further cure period [of] ten (10) days” before becoming subject
    to termination for that default. 
    Id. at 3
    (emphasis and capitalization omitted). The letter
    advises that “the University is not waiving any of the rights and remedies available to the
    University at law and in equity on account of the Developer’s failure to timely cure the
    Developer’s defaults” and, “specifically,” that “[n]o failure to exercise and no delay in
    exercising, on the part of the University, any right, remedy, power or privilege, shall operate
    as a waiver thereof.” 
    Id. at 4.
    50. This second notice was signed by Tarola. 
    Id. He testified
    that the decision to send the notice
    at this juncture was made not by him but the lawyers advising the University as to the
    project. Specifically, Tarola testified that with respect to this notice, he “was deferring to
    legal counsel to make sure that the legalities were as they wished.” Trial Tr. Day 2 PM at
    60:23–61:7; see also 
    id. at 61:15–62:4
    (plaintiff’s counsel reading Tarola’s deposition
    testimony stating the February 3, 2012 Notice of Default and Notice of Intent to Terminate
    “seemed to be counterproductive”).
    41
    51. Cohen testified that after receiving this notice, he consulted with Siegel and Michael
    Hollander, the Cohen Companies’ General Counsel, and considered the past interactions and
    present positon of the parties, including “what [Cohen] considered at some point some[]
    posturing on Howard’s part,” and notwithstanding the reference in the default notice to the
    Developer’s failure to make the second rental payment, “the decision was just not to make
    the payment.” Trial Tr. Day 2 AM at 112:6–22. Siegel testified that “it’s always been a
    surprise to [him] that the University had been pushing so hard for a rental payment that they
    could never use because it was always going to . . . make a clean site,” i.e., to cover
    environmental remediation costs in excess of $750,000, pursuant to the Development
    Agreement Amendment, and, thus, “the money would never be used by the University for
    their own purposes.” Trial Tr. Day 4 AM at 27:5–12.
    52. Rather than cure the default even in part by making the second rental payment, the
    Developer’s response to the February 3, 2012, Notice of Default and Notice of Intent to
    Terminate was a blunt threat of litigation. On February 7, 2012, the Developer emailed a
    letter to Tarola, which stated its purpose was “to ensure that the University is on notice that it
    should take all necessary steps to preserve the written and electronic records associated with
    the Howard University Town Center project.” Def.’s Ex. 36, Email from Eric Siegel to
    Robert Tarola, cc: Dr. Hassan Minor, Michael Hollander, Timothy Kissler, and
    mvahey@dccouncil.us, attaching Letter from Developer to Robert Tarola, dated Feb. 7,
    2012, at 2. The letter further stated, “Failure to preserve such documents shall subject the
    University to a claim for spoliation of evidence in the District of Columbia, in addition to
    legal pursuit of any other rights and remedies the Developer may have against the University.
    Conduct yourselves accordingly.” 
    Id. at 3.
    Siegel testified that he included that warning
    42
    because he “was concerned based upon . . . prior dealings with the University that while [the
    Developer] had [its] records, . . . records might be lost.” Trial Tr. Day 3 PM at 29:19–30:3.
    He further testified that while the letter anticipated litigation, he denied that he “perceive[d] it
    as a threat” but was “indicating . . . we may have a dispute here that’s going to rise to the
    level of litigation.” Trial Tr. Day 4 PM at 43:2–44:2.
    53. On February 15, 2012, following the February 3, 2012, Notice of Default and Notice of
    Intent to Terminate and the Developer’s response, the parties executed a letter agreement,
    substantially similar to the one sent via email to the Developer by Tarola almost two months
    earlier, on December 28, 2011, but including Kissler, principal of CastleRock, as a signatory
    and party to the negotiations and noting the February 3, 2012, Notice of Default as a basis for
    the contemplated discussions. See Joint Ex. 18, Re: Howard Town Center, dated Feb. 14,
    2012, at 1–2.
    54. The Third Notice of Default. On March 5, 2012, the University sent the third notice of
    default, and the second notice of intent to terminate, to the Developer. See Joint Ex. 20,
    Notice of Default and Notice of Intent to Terminate, dated Mar. 5, 2012. This notice
    reiterated the University’s intent to terminate, announced in the February 3, 2012, Notice of
    Default and Notice of Intent to Terminate, based on the defaults first noticed in the
    September 2011 Notice of Default. 
    Id. at 1.
    This notice further provided that the
    Developer’s failure to pay $1,475,000 “ha[d] not been cured within the required cure period
    . . . and now constitutes an Event of Default,” 
    id. at 2,
    and consequently that “the University
    intends to terminate the Ground Lease, the Development Agreement and the other project
    documents if this event of default is not cured within ten (10) days.” 
    Id. at 1–2
    (emphasis
    and capitalization omitted). Tarola testified that he believed this notice to be “[n]o more
    43
    productive” than the notice sent on February 3, 2012. Trial Tr. Day 2 PM at 63:10–12. Yet,
    in his testimony, Siegel conceded that in sending these notices, the University was “certainly
    well within [its] right to do so.” Trial Tr. Day 4 PM at 47:5–48:21.
    55. The evidence reflects that the Developer was unwilling to enter into the “settlement”
    resolving “the obligations owed to the University by Developer” contemplated by the
    February 14, 2012, letter agreement, see Joint Ex. 18, Re: Howard Town Center, dated Feb.
    14, 2012, at 1, until a financing commitment had been secured. For example, on April 3,
    2012, Kissler wrote an email to Tarola stating that “Ron is very close to agreeing to our deal.
    He would like to hear from JP Morgan, but they have not responded as of yet” and
    expressing his view that “a brief conversation between Norm and Ron would tip the scales in
    our favor.” Pl.’s Ex. 12, Emails Between Timothy Kissler, Robert Tarola, Norman Jenkins,
    Dr. Sidney Ribeau, dated Apr. 3, 4, 2012. Tarola forwarded this email to Jenkins and
    Ribeau, addressing Jenkins specifically in stating that “Kissler believes that Ron Cohen
    would commit to my proposal if he had some assurance from you that the new Howard team
    will be supportive of the project,” and providing a summary of the details of the proposal
    offered by Tarola. 
    Id. at 1.
    Tarola inexplicably stepped over the part of Kissler’s comments
    indicating that a financing commitment was really the hold up to the Developer moving
    forward, even though every document for the deal expressly excluded financing or the lack
    thereof as a reason for delay or non-performance. Jenkins recognized the Developer’s
    maneuvering, stating in response that he would prefer commencement of construction sooner
    but “suspect[ed] [the specified date] is driven by financing?” and concluding by opining that
    “if we can get this deal, we should take it.” 
    Id. In his
    response, Ribeau offered, “If we can
    get the right deal, it’s a home run for us.” 
    Id. 44 J.
        APRIL 2012: THE PARTIES SIGN A TERM SHEET
    56. On April 10, 2012, after nearly six months of negotiations and two letter agreements aimed at
    resolving their dispute, the parties executed a three-page “Term Sheet” designated as “For
    Settlement purposes.” Joint Ex. 21, Term Sheet, dated Apr. 6, 2012, at 1; see Trial Tr. Day 2
    AM at 135:24–136:8 (counsel for both parties stipulating that the Term Sheet was fully
    executed by April 10, 2012). This is the same Term Sheet that the Developer previously
    advised the Court was “immaterial,” see Pl.’s & Third-Party Def.’s Mem. P. & A. Opp’n
    Def.’s Mot. Summ. J. at 7–8, and, indeed, the Developer’s original complaint in this matter is
    conspicuously devoid of any reference whatsoever to the Term Sheet, see generally Pl.’s
    Compl., ECF No. 3. In an about-face on appeal, however, the Developer pushed this Term
    Sheet front and center as a reason for vacatur and remand of the grant of summary judgment
    against it. 
    See supra
    Part I.B (discussing this case’s litigation history).
    57. Provisions of the Term Sheet. In twelve simple paragraphs, the Term Sheet withdrew the
    University’s second and third notices of default, sent in February and March 2012,
    conditioned on “[t]he timetable for cure of the monetary default . . . defined herein.” Term
    Sheet at 1. Under this “timetable” for “RENT, SCHEDULE, AND OTHER ITEMS,” the
    following steps were expressly required:
    a)     execution of the Term Sheet itself;
    b)     execution of an amendment to the escrow agreement such that the $525,000 paid
    by the Developer thus far to the parties’ escrow account would be released to the
    University upon execution of the Term Sheet;
    c)     execution of amendments to the Ground Lease and the Development Agreement
    by April 30, 2012;
    45
    d)       commencement of construction by April 15, 2013, with phasing of the project
    permitted;
    e)       automatic termination of the lease if the “Developer fails to break ground by
    September 15, 2013,” at which point “both parties agree that all actions, by either
    party, prior to the execution of the Ground Lease Amendment shall not be
    grounds for litigation,” i.e., a walk away provision; and
    f)       “[p]ayment of past due ground rent in the amount of $1,475,000,” with $100,000
    to be paid “no later than ten (10) days after execution of th[e] Term Sheet” and
    “the balance of $1,375,000” to be paid “no later than ninety (90) days after the
    execution” of the amendments to the Ground Lease and the Development
    Agreement, 
    id. at 2.
    12
    58. With respect to the University’s withdrawal of the Developer’s defaults, Jenkins testified that
    “[t]he way [he] understood the term sheet to work is: Provided that all of the terms within the
    term sheet were agreed upon and complied with, then there would be a waiver.” Trial Tr.
    Day 7 AM at 27:17–22. 13
    59. Consistent with the original Ground Lease and Development Agreements, and first
    amendments thereto, no term of the Term Sheet made either party’s performance contingent
    on the securing of financing for the project. See generally 
    id. Tarola testified
    that even
    without financing having been secured by the Developer, he “understood that the Developer
    12
    The $100,000 initial installment requirement may have been driven in part by the District’s prior request
    for security in the amount of $100,000 to demonstrate the parties’ commitment to the Howard Town Center project.
    See Def.’s Ex. 19, Letter from Troy Stovall to Ronald J. Cohen, dated Aug. 19, 2011, at 3.
    13
    While the Developer summarizes Jenkins’s testimony as demonstrating “he understood the Term Sheet to
    ‘waive’ the defaults,” Pl.’s Prop. Findings Fact Concls. Law ¶ 143, and Siegel testified to his view that the
    Developer could walk away scot free from the deal following the signing of the Term Sheet, see Trial Tr. Day 3 PM
    at 34:4–8 (testifying that the default language was so the Developer “could have a playing field going forward” and
    “wouldn’t be held in a default posture, that it would be over”), the portion of Jenkins’ testimony cited in the text
    belies the Developer’s characterization of the Term Sheet’s intended effect.
    46
    had some substantial assets and should be able to pay what was due to the University; so [he]
    expected it to be paid and, indeed, . . . was looking for cash as a way of showing good faith to
    continue the project.” Trial Tr. Day 5 AM at 17:19–18:4. Tarola “felt that the Developer
    needed to show commitment to the project in the form of cash contributed toward moving
    that along . . . . [T]he cash was not important to Howard University, being a billion-dollar
    company, but it was important to make sure that we had the commitment to move forward
    with the project.” 
    Id. at 18:11–19.
    60. Siegel understood that pursuant to the Term Sheet, the money owed by the Developer would
    “be paid in two different installments, subject to the first one being within ten days and the
    second one would be subject to the second amendment documents being signed.” Trial Tr.
    Day 6 AM at 66:5–11.
    K.      APRIL – MAY 2012: THE INITIAL PROPOSALS FOR SECOND
    AMENDMENTS
    61. Siegel testified that “between the 10th and approximately the 19th of April,” i.e., “[a]fter the
    signing of the term sheet[,] we learned from J.P. Morgan that they were no longer interested
    in moving forward with the project.” Trial Tr. Day 4 PM at 86:14–87:3. Apparently, the
    Developer had no other possible financing options by then to move the project forward, more
    than two years after execution of the first amendments to the Ground Lease and Development
    Agreement.
    62. On April 19, 2012, Tarola briefed the Real Estate Committee of the Howard University
    Board of Trustees “on developments subsequent to the approval to commence ‘default
    proceedings’ at the January 26, 2012 meeting.” Pl.’s Ex. 8, Report of the Real Estate
    Committee, Howard University Board of Trustees, dated Apr. 19, 2012, at 4. The Committee
    Report summarizes the Term Sheet as providing for, on the Developer’s part, the release of
    47
    the $525,000, payment to the University of “past due ground rents,” and “release of litigation
    risk for past acts. In return, the Developer would receive a default waiver from Howard and
    a new construction start date and ground rent payment schedule.” 
    Id. Jenkins, at
    that time a
    trustee of the University and serving as Chair of the Real Estate Committee, relayed to the
    Committee that, according to the Developer, “facts have changed subsequent to the execution
    of the term sheet” in that “the financial backing [it] had from JP Morgan may no longer be
    viable” but that “the Developer appears motivated and willing to proceed with this project.”
    
    Id. 63. The
    Developer did not make the $100,000 payment as required by the Term Sheet. Cohen
    testified that, at some point, after “assessing where [the Developer] w[as] financially in this
    project, [he] immediately called [Jenkins]” and told him he was “just not in a position to pay
    this money” because the Developer was “almost $2 million out-of-pocket.” Trial Tr. Day 1
    AM at 103:4–9. Jenkins “was upset,” and Cohen “fully underst[oo]d” given that he “went
    back on a promise” to the University. 
    Id. at 103:9–10.
    The Developer continued to conduct
    itself as if the contract documents conditioned its responsibilities and obligations to the
    development project on securing financing, when the documents expressly provided the
    opposite.
    64. The University’s April 23, 2012, Drafts. On April 23, 2012, the University sent a first draft
    of the contemplated amendments to the Developer. See Def.’s Ex. 42, Email from Robert
    Tarola to Timothy Kissler, Ronald Cohen, and Eric Siegel, cc: Norman Jenkins, Bridget
    Sarikas, Odessa Jackson, and David Gifford, attaching three documents: (1) Termination of
    Escrow Agreement; (2) Second Amendment to Ground Lease; and (3) Second Amendment to
    Development Agreement, dated Apr. 23, 2012. The University’s proposed second
    48
    amendments were fully consistent with the Term Sheet’s outline of the parties’ intent,
    including the University’s concession to a two-phase project, a concept that the University
    had not originally agreed to and resisted for over two years. The salient terms of these
    documents are summarized below.
    a)      The proposed Termination of Escrow Account provided for the termination of the
    existing escrow account between the parties and release of the amounts currently
    in the account to the University. See 
    id. at 2–3.
    b)      The proposed Second Amendment to Ground Lease provided for payment of the
    $1,475,000 in two installments, one of $100,000 and one of $1,375,000, on “April
    __, 2012” and “July __, 2012,” respectively. See 
    id. at 6.
    c)      The proposed Second Amendment to Development Agreement took into account
    the termination of the escrow account, providing that environmental remediation
    costs in excess of $750,000 would be paid by the University directly to the
    Developer or any third-party contractor and that rental payments should be made
    directly to the University by the Developer; provided for mandatory submission
    dates for the design documents required of the Developer by the Development
    Agreement; provided for construction of the project in two phases; provided for
    construction of the project in two phases, as the Developer had requested; and, in
    accordance with the “walk away” provision of the Term Sheet, provided that “if
    for any reason (including due to any Unavoidable Delay and/or any action of
    inaction on the part of the University or the District, whether or not constituting a
    default or breach on the part of the University), the ‘commencement of
    construction,’ as defined in . . . the Development Agreement, has not occurred by
    49
    September 15, 2013, the Ground Lease and the Development Agreement shall
    terminate and be of no further force or effect.” 
    Id. at 12–14.
    65. The Developer’s May 2, 2012, Drafts. On May 2, 2012, nine days after the University
    transmitted its draft documents and two days after the date provided by the Term Sheet for
    execution of the amendments, the Developer responded to the University with its revisions.
    See Joint Ex. 23, Email from Eric Siegel to David Gifford, cc: Norman Jenkins, Bridget
    Sarikas, Odessa Jackson, Robert Tarola, Timothy Kissler, Ronald Cohen, and Michael
    Hollander, attaching (1) Termination of Escrow Agreement; (2) Second Amendment to
    Ground Lease; and (3) Second Amendment to Development Agreement, dated May 2, 2012.
    The Developer’s proposed changes shifted the fundamental financial risks of the project from
    the Developer to the University by making explicit that the Developer would not make
    further investments, even rent payments past due, until financing was secured. The
    Developer’s redlines reflect the following changes, inter alia:
    a)     to the proposed Termination of Escrow Agreement, the Developer inserted the
    precise amount currently in the parties’ escrow account for release to the
    University, but made no other changes, see 
    id. at 2;
    b)     to the proposed Second Amendment to Ground Lease, the Developer inserted a
    provision amending the definition of “Closing Date” to be contingent on
    financing, 
    id. at 23;
    deleted the University’s provisions requiring payment of the
    $1,475,000 in two installments on dates certain and replaced it with a provision
    making its payment contingent on financing, 
    id. at 24–25;
    inserted the terms for a
    rental payment schedule, contemplated by the University’s April 23, 2012, draft,
    that would defer the Developer’s obligations to pay rent, 
    id. at 25–26;
    inserted an
    50
    amendment making execution of a Memorandum of Lease, to be recorded with
    the District of Columbia, contingent on financing, 
    id. at 27;
    and deleted the phrase
    “(other than financial inability)” from the “force majeure” (i.e., excuse of
    performance in the event of an Act of God or the like) clause of the Ground
    Lease, id.; and
    c)     to the proposed Second Amendment to Development Agreement, the Developer
    deleted the portion of the definition of “Unavoidable Delay” providing that
    inability to obtain financing is not an unavoidable delay, 
    id. at 10;
    amended the
    definition of “Construction Commencement Deadline” to be contingent on
    financing, id.; and deleted the walk away provision, 
    id. at 13.
    Siegel testified that
    he deleted the walk away provision in its entirety, notwithstanding this key
    provision in the Term Sheet, because he “didn’t think it was reasonable.” Trial
    Tr. Day 3 PM at 52:7–24.
    66. The University’s May 4, 2012, Drafts. Two days later, on May 4, 2012, Tarola sent an email
    responding to the Developer’s redlines stating, “We have reviewed the documents you sent
    and note that they depart considerably from the Term Sheet. We also note that payments to
    Howard as agreed within the Term Sheet are already past due.” Joint Ex. 24, Emails
    Between Eric Siegel and Robert Tarola, attaching (1) Second Amendment to Ground Lease;
    (2) Second Amendment to Development Agreement, dated May 4, 2012. In the attached
    proposed amendments, the University continued to seek the $1,475,000 rental payment in
    two installments, one of $100,000 on May 10, 2012 and the balance on July 31, 2012, and
    reinserted the proposed walk away provision. See 
    id. at 7,
    17. The University accepted the
    Developer’s changes regarding recording of a Memorandum of Lease contingent on
    51
    financing and, in modified form, its proposed deferred rental payment schedule, but rejected
    the Developer’s other proposals to make its performance contingent on financing. See
    generally id.; see also Joint Ex. 25, Email from David Gifford to Eric Siegel, dated May 7,
    2012 (attaching blacklines of the University’s proposed documents). The entire purpose of
    the Development Agreement from the outset, as Dr. Ribeau and Tarola explained, was to
    outsource to a developer, with professional experience in the development arena and real
    estate community, the responsibilities and risks associated with the development project, for
    the benefit of the University and surrounding community. See Trial Tr. Day 1 PM at 43:17–
    44:7 (Ribeau) (explaining that the University’s motivation was not the profitability of the
    development project but the “value it added to the community” and the purpose of hiring a
    developer was “to do things that developers do that really wasn’t in our portfolio of things to
    do”); Trial Tr. Day 5 AM at 106:5–7 (Tarola) (explaining that from “the business
    perspective” the purpose of the relationship with the Developer was “improving the campus”
    with “other people’s money”).
    67. The Developer’s May 8, 2012, Drafts. The Developer responded on May 8, 2012, with
    proposed revisions to the University’s most recently transmitted proposed second
    amendments to the Ground Lease and Development Agreement. See Joint Ex. 26, Email
    from Eric Siegel to Robert Tarola, cc: David Gifford, Norman Jenkins, Bridget Sarikas, Tim
    Kissler, Ron Cohen, and Michael Hollander, attaching (1) Second Amendment to
    Development Agreement; (2) Second Amendment to Ground Lease, dated May 8, 2012. In
    these drafts, the Developer proposed, inter alia, modifying the Construction Commencement
    Deadline to be October 1, 2013, nearly six months later than the Term Sheet’s
    commencement date of April 15, 2013, see 
    id. at 7;
    deleting the University’s proposal for
    52
    mandatory submission dates for required design documents, see 
    id. at 8;
    reinserting a change
    to the definition of “Closing Date” to be the earlier of the date on which the Developer settles
    on a construction loan or September 30, 2013, 
    id. at 19;
    and inserting a provision requiring
    payment of the $1,475,000 only on the newly defined Closing Date, 
    id. at 21,
    which ignored
    the $100,000 partial payment of the second rental payment and effectively made the second
    rental payment due upon the Developer securing financing, or an outside date fifteen days
    after the Term Sheet’s walk away date of September 15, 2013, which the Developer proposed
    extending until October 1, 2013, 
    id. at 10–11.
    68. Execution of the Termination of Escrow Agreement. The parties executed the Termination of
    Escrow Agreement, effective May 10, 2012, releasing the funds in escrow to the University
    and dissolving the parties’ escrow account. See Joint Ex. 27, Termination of Escrow
    Agreement, dated May 10, 2012.
    69. On May 15, 2012, in a letter to “Members of the Finance and Executive Committees” of the
    Howard University Board of Trustees, Tarola relayed that “[l]ate last week [the University]
    received the first payment from the developer under the term sheet” and that “we are working
    with the developer to solidify new agreements that would move the project forward.” Pl.’s
    Ex. 13, Confidential Letter from Robert Tarola to Members of the Finance and Executive
    Committees, dated May 15, 2012, at 6. In that letter, Tarola also thanked Jenkins for
    “helping to negotiate to a satisfactory resolution.” 
    Id. L. MAY
    – DECEMBER 2012: THE UNIVERSITY FORBEARS FROM
    TERMINATING THE DEVELOPER WHILE ASSISTING THE
    DEVELOPER IN PURSUING FINANCING
    70. Following the Developer’s drafts transmitted on May 8, 2012, which reflected terms the
    University had explicitly rejected, for a period of time, the University neither accepted those
    53
    drafts nor proposed revisions to them. While consistently refusing to execute agreements
    that conditioned the Developer’s performance of any of its obligations on securing financing,
    the University recognized that for the relationship with this Developer to continue, obtaining
    financing was paramount and therefore the University took steps to assist the Developer in
    this regard.
    71. Jenkins testified that the University’s response to those drafts was to give the Developer an
    opportunity to secure financing for the project. See Trial Tr. Day 7 AM at 11:5–16. In fact,
    during that period, Jenkins assisted the Developer in its efforts to obtain financing. See 
    id. at 11:17–12:3;
    Def.’s Ex. 50, Email from Eric Siegel to Norman Jenkins, attaching clean draft
    amendment documents, dated May 23, 2012. Specifically, Jenkins “introduced the developer
    to some of [his] existing partners, [Quadrangle Development Corp.,] who were prominent
    Washington, D.C. developers, to see if they might be able to land on some sort of
    arrangement, because that group had a dedicated fund to do development in the Washington,
    D.C. market.” Trial Tr. Day 7 AM at 11:20–12:3.
    72. Siegel testified that he “was instructed by Robert Tarola to give regular updates on where we
    were with the financing, which we did” and expressed his view that “the university, Norman
    Jenkins, was very generous to putting [sic] us in touch with potential financing sources.”
    Trial Tr. Day 3 PM at 60:9–25; see also Pl.’s Ex. 161, Confidential Letter from Robert
    Tarola to Members of the Finance and Executive Committees, dated July 31, 2012, at 4 (“We
    have introduced the developer to two interested investors/lenders and are in regular contact
    about financing progress.”).
    73. In addition to financing, the University also assisted the Developer in pursuing a tax
    abatement for the project with the District. See Trial Tr. Day 3 PM at 60:9–18 (Siegel). On
    54
    November 12, 2012, Tarola sent a letter to the District expressing the University’s support
    for the tax abatement bill, noting that the University “has been working closely with the
    Developer and the District for some time to bring this project to reality” and “fully supports
    the Tax Abatement Act as a means to help the project come to fruition.” Joint Ex. 28, Email
    from Robert Tarola to Timothy Kissler and Eric Siegel, attaching Letter from Robert Tarola
    to the Council of the District of Columbia, dated Nov. 12, 2012, at 2.
    74. The Demolition Permit Applications. By November 2012, the second amendments to the
    Ground Lease and Development Agreement remained unsigned, with the parties’ differing
    provisions unreconciled and the Developer still without financing secured. Nevertheless, in
    early November 2012, Jenkins relayed to Tarola that the Developer was seeking the
    University’s signature for its applications to the District for permits allowing demolition on
    the Property. See Pl.’s Ex. 14, Emails Between Norman Jenkins, Robert Tarola, and Eric
    Siegel, dated Nov. 6, 2012. Jenkins explained that he told Siegel “we would not sign until
    we had certainty of funding.” 
    Id. at 1.
    Jenkins testified that he recommended that the
    University “not begin demolition of the building” because “we didn’t have a deal” and “the
    project wasn’t capitalized.” Trial Tr. Day 7 AM at 12:20–13:3.
    75. Early in 2012, the University had recruited a new University Architect, Alan Brangman, who
    became involved in the Howard Town Center project. See Trial Tr. Day 8 AM at 5:6–6:11.
    Brangman testified that he believed demolition before the second amendments were signed
    was inadvisable “because that would have been giving up control of the site, and that also
    would have put the University at risk with respect to activities taking place on the property
    before it was under the direct and true control of the developer.” 
    Id. at 9:19–10:2.
    Brangman
    further testified that the Developer was “asking to demolish various section of the buildings
    55
    that were on the site” notwithstanding the “historic nature of some of those properties.” 
    Id. at 10:4–7.
    76. The Citi Community Capital Term Sheet. On November 27, 2012, Siegel emailed Jenkins,
    stating the Developer was “working diligently on the tax abatement and finalizing the capital
    stack.” Joint Ex. 30, Emails from Eric Siegel to Norman Jenkins, dated Nov. 5, 27, 2012, at
    1. The email also attached a letter from Citi Community Capital “offer[ing] an opportunity
    to submit a preliminary application . . . for financing” and attaching a “Term Sheet dated
    November 21, 2012.” 
    Id. at 2.
    This bank Term Sheet set an estimated closing date of May
    30, 2013, for the loan, see 
    id. at 8,
    and listed the application fees, see 
    id. at 13–14.
    Vasques
    testified that in his view, by soliciting the application and related fees from the Developer,
    Citi demonstrated that “[t]hey were very serious about moving forward to try to get this
    done.” Trial Tr. Day 6 PM at 21:3–11.
    77. The following day, Tarola signed the demolition permit applications as requested by the
    Developer, though Jenkins’s and Brangman’s position remained not to begin demolition on
    the site until the project was capitalized. See Pl.’s Ex. 134, Application for Raze Permit,
    2146 Georgia Ave. NW, dated Dec. 3, 2012, at 4; Pl.’s Ex. 135, Application for Raze Permit,
    2112 Georgia Ave. NW, dated Dec. 3, 2012, at 4.
    78. On December 4, 2012, the Developer paid Citi Community Capital $176,750 in fees for an
    application for a loan. See Pl.’s Ex. 165, Email from Alex Diaz, Cohen Companies, to
    Fabrice Vasques, cc: Ron Cohen, Eric Siegel, Alan Cohen, and Michael Hollander, dated
    Dec. 4, 2012.
    79. One week later, Tarola sent a letter to the Developer advising that while the University
    “signed and authorized [the Developer] to submit an application for a [demolition] permit,” it
    56
    did so “notwithstanding the existence of unresolved disputes between the University and
    Developer.” Joint Ex. 31, Letter from Robert Tarola to Developer, dated Dec. 11, 2012, at 1.
    Tarola further explained that the Developer was “not authorized by the University to
    commence demolition under [the applied-for] permit without further approval by the
    University” given the failure of the parties yet to reach a “satisfactory resolution” to their
    disputes. 
    Id. at 1–2.
    The letter made clear that “the University is not waiving any defaults on
    the part of the Developer.” 
    Id. at 1.
    The record contains no response from the Developer to
    the University’s concerns expressed in this December 11, 2012, letter. 14
    80. Notwithstanding the University’s expressed concern about the status of the project, including
    the lack of executed second amendments to the Ground Lease and Development Agreement
    and lack of secured financing, the Developer sent a letter to the University on December 18,
    2012, advising that “the contractor will be mobilizing on Monday, January 7, 2013 to
    commence asbestos abatement and demolition” and to “[p]lease make sure any equipment,
    personal items and vehicles have been removed from the building prior to that date.” Joint
    Ex. 32, Letter from Developer to Howard University, dated Dec. 18, 2012.
    M.       DECEMBER 2012 – FEBRUARY 2013: THE PARTIES RESUME
    NEGOTIATIONS, AND THE UNIVERSITY SETS A FINAL DEADLINE
    FOR THE $1,475,000 RENTAL PAYMENT
    81. During late 2012, shortly after the Developer had positive news regarding potential financing
    from Citi Community Capital, which had authorized the Developer to submit a loan
    application on December 4, 2012, the Developer restarted its efforts to obtain the District’s
    14
    The Developer characterizes the University’s December 11, 2012, letter as a “reversal of its position to
    allow demolition to proceed,” Pl.’s Prop. Findings Fact Concls. Law ¶ 190, but no evidence supports the
    Developer’s implication that the University authorized the Developer to begin demolition, and, to the contrary, the
    evidence shows that the University was opposed to the Developer’s beginning demolition from the moment the
    Developer proposed demolition due to the unresolved second amendment issues and the Developer’s continuing
    default in failing to make either installment payment on the second rental payment as required by the parties’ Term
    Sheet.
    57
    approval to alter the construction deadlines in the Declaration of Covenants between the
    District and the University. Specifically, the Developer sent Andre Byers, a District official,
    emails on December 10 and 11 requesting new deadlines and representing that its suggested
    deadlines came from “the Second Amendment to the Ground Lease and Development
    Agreement that [the Developer has] negotiated with Howard University, who agrees to these
    deadlines.” Joint Ex. 33, Emails Between Eric Siegel, Andre Byers, Robert Tarola, and
    Norman Jenkins, dated Dec. 10, 11, 18, 19, 2012, at 3. On December 18, 2012, Byers
    forwarded the emails to Tarola inquiring whether he was “familiar with the request below,”
    
    id. at 2,
    and that same day, Tarola forwarded the emails to Siegel asking him to “advise
    [Tarola] about this email trail and the reference to a ‘second amendment,’” 
    id. At this
    point,
    no second amendments had been finalized, an issue of such concern to the University that
    Tarola’s letter of December 11, 2012, had instructed the Developer that no demolition on site
    was authorized.
    82. The Developer Resends Its May 8, 2012, Drafts. On December 19, 2012, in response to
    Tarola’s email, the Developer emailed Tarola, copying Jenkins, transmitting the same draft
    amendment documents sent by the Developer on May 8, 2012, but noting in the email that
    the “two-phased construction schedule” conceded to by the University and contained in the
    transmitted drafts was “now moot because [the Developer is] building the entire project at
    one time,” and further advising that the “University’s formal request to the District via Andre
    Byers to revise [the Covenant] dates is all we need” to get “the paperwork . . . in order for
    our lender and equity’s due diligence to get to closing.” 
    Id. at 1;
    see Trial Tr. Day 4 PM at
    132:3–23.
    58
    83. On December 27, 2012, Tarola sent Byers a letter advising him that the “University has
    approved” the new deadlines for construction proposed by the Developer and assuring the
    District that the University “remains committed to the prompt and successful completion of
    this Project” notwithstanding that “a number of . . . issues remain unresolved” between the
    University and the Developer. Joint Ex. 34, Letter from Robert Tarola to Andre Byers, cc:
    Ronald Cohen, dated Dec. 27, 2012, at 1.
    84. The same day, Tarola sent the Developer a letter responding to the Developer’s December
    18, 2012, letter regarding its intent to begin demolition, reiterating the University’s position
    that “[a]lthough [the] continuing discussions have been productive, they have not yet yielded
    a complete settlement arrangement acceptable to Howard University,” and, consequently, the
    University “cannot at this time agree to the Developer’s possession of the Project property, or
    approve the commencement of any work (including demolition).” Joint Ex. 35, Letter from
    Robert Tarola to Developer dated Dec. 27, 2012.
    85. In an email to Siegel, Tarola explained that the parties “need to reach agreement on the
    ground lease amendment and term sheet payments before [the University] can give [the
    Developer] access to the property.” Joint Ex. 36, Emails Between Eric Siegel, Andre Byers,
    Robert Tarola, and Norman Jenkins, dated Dec. 10, 11, 18, 27, 2012, Jan. 1, 2013, at 2. In
    response, on January 1, 2013, the Developer promised to “reach out tomorrow morning . . .
    about the time frame for receiving the draft Second Amendments to the Ground Lease and
    Development Agreements for [the Developer’s] review” and provided that “the outside date
    to ‘true up’ on the initial ground lease payment of $1.425 million [sic] would be May 30,
    2013 (the date of closing on the financing with Citi Community Capital . . . ).” 
    Id. at 1.
    Again, the Developer was seeking to condition the required rental payments on the securing
    59
    of financing, contrary to any provision in the contract documents or in the parties’ Term
    Sheet.
    86. The University’s January 11, 2013, Drafts. On January 11, 2013, David Gifford, outside
    counsel for the University in the negotiations with the Developer, transmitted revised draft
    documents requiring, inter alia, payment of the $1,475,000 by May 10, 2013, as well as
    liquidated damages for failure to meet construction deadlines and evidence of financing. See
    Joint Ex. 37, Email from David Gifford to Eric Siegel, attaching (1) Second Amendment to
    Ground Lease; (2) Second Amendment to Development Agreement, dated Jan. 11, 2013, at
    3. 15 These drafts again reflected the University’s position, consistent with the original
    contract documents, that the financial risks rested on the Developer and the Developer’s
    failure to perform was not excused by financing difficulties. In its cover email, the
    University also reiterated its position that “[t]he submission of these drafts remains merely a
    part of the negotiations concerning the obligations owed to the University by Developer with
    a view to compromise and settlement by the parties of their dispute.” 
    Id. at 1.
    15
    The Developer asserts the University’s selection of May 10, 2013, for payment of the second rental
    payment was inconsistent with the Developer’s “discussions with Mr. Jenkins and Mr. Tarola that the payment
    would be tied to a closing date on or before October 1, 2013,” but cites no evidence in support of this proposition.
    Pl.’s Prop. Findings Fact Concls. Law ¶ 215. Nor does such evidence exist in the record, which reflects that while
    Jenkins and Tarola may have discussed a construction commencement date of October 1, 2013, with the Developer,
    they never discussed the long overdue rental payment being made that day. See Joint Ex. 34, Letter from Robert
    Tarola to Andre Byers, cc: Ronald Cohen, dated Dec. 27, 2012, at 1; Trial Tr. Day 5 AM at 109:17–110:22 (Siegel)
    (asserting that in May 2012 Jenkins agreed to a commencement-of-construction deadline of October 1, 2013, though
    acknowledging that “[t]he only document that memorializes that [discussion] would be [the Developer’s own] May
    8 draft”).
    While the record is unclear as to the University’s reasons for selecting the precise date of May 10, 2013,
    this date in May, but a year earlier, was the date set out in the University’s May 4, 2012, drafts of the second
    amendments as the deadline for payment of the $100,000 installment of the second rental payment and “May 10”
    may have been a vestige of those prior drafts. See Joint Ex. 24, Emails Between Eric Siegel and Robert Tarola,
    attaching (1) Second Amendment to Ground Lease; (2) Second Amendment to Development Agreement, dated May
    4, 2012. In any event, the May 10, 2013, date is generous given the Developer’s assertion that it would close on
    financing no later than May 30, 2013, and the fact that a commitment letter would be issued at any point “if the
    developer or any party to a transaction requested a commitment, and it was agreed that it was necessary.” Trial Tr.
    Day 7 AM at 45:5–11, 53:10–13 (Dickson).
    60
    87. Around December 2012, principal responsibility for heading the project had been shifted
    from Tarola to Kurt Schmoke, then General Counsel for the University, though Tarola
    nevertheless remained involved in the project. See Trial Tr. Day 5 AM at 57:9–18.
    88. On Friday, January 25, 2013, Tarola scheduled a meeting for the following Monday, January
    28, 2013, with Siegel and other members of the University’s team to discuss the draft
    amendment documents sent by the University on January 11, 2013. Pl.’s Ex. 22, Emails
    Between Eric Siegel and Robert Tarola, et al., dated Jan. 25, 2013. In an email confirming
    the meeting, Siegel expressed that he would “be there ready to work together to finalize the
    documents.” 
    Id. at 1.
    89. Shortly before the scheduled meeting, in response to an email from Siegel asking where the
    meeting would take place, Tarola sent Siegel an email, copying the University team, stating
    that “we have to postpone the meeting” and “are meeting internally first later today.” Joint
    Ex. 39, Emails Between Eric Siegel and Robert Tarola, cc: Odessa Jackson, Norman Jenkins,
    and Kurt Schmoke, dated Jan. 28, 2013, at 1. Siegel responded stating that he “await[s] next
    steps” and “advised” that “[t]his will further impact ‘construction commencement.’” 
    Id. 90. The
    University’s February 1, 2013, Email. On February 1, 2013, Kurt Schmoke emailed
    Siegel, copying, inter alia, Dr. Ribeau, noting that University “officials . . . met to assess our
    current position with respect to this development” in light of the University’s “concerns
    about the lack of progress being made” and advised that the “University will take no further
    action in support of the current developer” unless the Developer “has obtained sufficient
    financing from a reliable source,” the $1,475,000 rental payment “has been made to Howard
    University by May 30, 2013,” and “architectural drawings sufficient to obtain construction
    permits . . . are developed by [the Developer] and approved by Howard University.” Joint
    61
    Ex. 40, Emails Between Kurt Schmoke and Eric Siegel, dated Feb. 1, 2013, at 2. Siegel
    responded within two minutes asking Schmoke to call him immediately. See 
    id. at 1.
    Schmoke subsequently sent an email reflecting that a call had taken place and stating that he
    “appreciate[s] the fact that [they] agree that if the [Developer] does not obtain financing . . .
    by May 30, 2013, we . . . part company on this project. . . . [I]t is very clear that if the
    financing is not obtained the relationship between your company and the university is
    dissolved.” 
    Id. 16 91.
    In requesting certainty of financing, the University was responding to the Developer’s
    repeated efforts to make its project obligations contingent on its securing of financing.
    Schmoke testified that he viewed financing as “the number one issue” for the Developer and
    believed that if financing was secured, “everything else would fall into place.” Trial Tr. Day
    6 AM at 122:5–20.
    92. Tarola testified that, around this time, he “felt the lawyers . . . wanted to kill the deal” given
    the Developer’s intransigence, but, in his view, the February 1, 2013, email from Schmoke
    “should not have killed the deal” and was not “intended to kill the deal.” Trial Tr. Day 2 PM
    at 104:10–14; Trial Tr. Day 5 AM at 77:5–11.
    93. By this point in 2013, Brangman had taken on some of Tarola’s responsibilities with respect
    to the project, though Tarola still remained involved. See Trial Tr. Day 8 AM at 5:6–6:22.
    Brangman testified that he took “on those responsibilities at the direction of Dr. Ribeau,”
    16
    In a footnote, the Developer takes issue with the University’s statements during this litigation that the
    Developer agreed in the February 1, 2013, phone call between Schmoke and Siegel to make the second rental
    payment on May 30, 2013, asserting that “[t]he University’s representations both to this Court and to the D.C.
    Circuit are flatly contradicted by the testimony of both Mr. Schmoke and Mr. Siegel that the two men did not
    discuss the payment on their telephone call.” Pl.’s Prop. Findings Fact Concls. Law ¶ 234 & n.6. While the
    evidence does not show that the timing of the payment was discussed on that call, the University’s representation is
    hardly “baseless,” 
    id., given the
    Developer’s own representation in its original Complaint that at some point during
    discussions in 2013 the Developer and the University “agreed that [the Developer] would not be obligated to tender
    the Payment called for under the Amendment until May 30, 2013,” Pl.’s Compl. ¶ 23.
    62
    who “needed somebody to be involved in the project who had experience in real estate
    development,” and “that was not always something that Mr. Tarola was happy with.” 
    Id. at 6:7–11,
    6:20–22.
    N.      FEBRUARY – MAY 2013: THE HISTORIC NOMINATIONS ARE FILED,
    AND THE PARTIES CONTINUE TO NEGOTIATE
    94. The Historic Preservation Nominations Email. On February 7, 2013, Brangman forwarded
    to Siegel an email from Rebecca Miller, Executive Director of the DC Preservation League
    (“DCPL”). See Joint Ex. 41, Emails Between Rebecca Miller, Alan Brangman, and Eric
    Siegel, dated Feb. 7, 8, 2013. In her email, Miller notified Brangman that DCPL had
    nominated the Bond Bread building and WRECO garage for historic status, which
    nominations are considered by the DC Historic Preservation Review Board. See 
    id. at 2.
    Miller shared that she “understand[s] that Howard University has plans to raze these
    buildings” and “would like to propose a meeting to discuss [its] plans and to determine if
    there is a way to retain these buildings while still carrying out the goals of the University’s
    project.” 
    Id. In response
    to Brangman’s email, Siegel replied, “Someone must call me to
    discuss how we jointly address this immediately or this project will come to a screeching
    halt.” 
    Id. at 1.
    95. The DCPL action to nominate the buildings on the Property could not have been a surprise
    given those buildings’ historic nature, as indicated in the DUKE Plan, which had long
    required the preservation of at least the façade of the WRECO garage, and a blog post
    forwarded to the Developer in February 2011, which discussed the Bond Bread building. 17
    17
    Apparently as support for its position that the Developer was surprised by the designation of these
    buildings, the Developer suggests that the DUKE Plan routinely included landmark designations, but notably failed
    to for these two buildings, which instead referenced “only . . . the preservation of some” of the WRECO garage.
    Pl.’s Prop. Findings Fact Concls. Law ¶ 259 (“The DUKE Plan did not include a landmark designation for these
    buildings.”). The Developer has it exactly backward. Testimony at trial revealed that as a general matter the DUKE
    63
    Moreover, not long before DCPL filed the nominations, the Developer met with personnel at
    the District’s Historic Preservation Office, at Siegel’s request, “to share the project that was
    being proposed and to just be sure that the Office of Planning was aware of the project
    pending and that it was moving forward.” Trial Tr. Day 2 PM at 10:24–11:2, 11:12–14
    (Callcott). “At the initial meeting [with the Developer], . . . the Preservation Office identified
    . . . both [the WRECO garage and Bond Bread building] as potentially meeting the
    designation criteria, and that [the Office] wouldn’t be surprised if [DCPL] would be
    interested in having them designated.” 
    Id. at 11:3–11.
    96. Gifford transmitted a draft Second Amendment to the Development Agreement to Siegel on
    February 8, 2013. See Joint. Ex. 42, Email from David Gifford to Eric Siegel, attaching
    Second Amendment to Development Agreement, dated Feb. 8, 2013.
    97. On February 14, 2013, Siegel transmitted a letter to the University, providing in his cover
    email that “[t]he letter is not offered to be confrontational but simply to set forth the realities
    of the situation to date while we continue to work together to finalize the Second
    Amendment documents and keep to an expeditious schedule to move the project forward.”
    Joint Ex. 43, Emails Between Eric Siegel, Robert Tarola, and Kurt Schmoke, dated Feb. 1,
    14, 2013, attaching Letter from Developer to Robert Tarola, at 1. The letter asserted that “the
    Developer has experienced two Unavoidable Delays” precluding the Developer from
    “adhering to the precise Project Schedule that was submitted . . . on January 31, 2013, and
    meeting a Construction Commencement Date of October 1, 2013.” 
    Id. at 5.
    According to
    the Developer, the Unavoidable Delays were (1) delays by the University in executing
    Plan “wanted to leave it open-ended as to whether or not properties would be preserved” subject to review “under
    the city’s historic preservation law,” but deemed the WRECO garage so historic that, in an exception to that general
    rule, it directed that building be preserved. Trial Tr. Day 2 PM at 7:1–22 (Callcott); see DUKE Plan at 30.
    64
    various documents enabling the Developer to begin demolition on the Property, and (2) the
    “more troubling . . . recent filing of two historic preservation applications to deem buildings
    on the property ‘historic.’” 
    Id. at 7.
    At the time, the Developer still had not obtained
    financing for the project, but this fact was not referenced in the letter as a basis for
    Unavoidable Delay, since lack of financing was expressly excluded as a justification for
    Unavoidable Delay in the Development Agreement. See generally id.; Development
    Agreement at 7, 18. In blaming the University for delays in beginning demolition, the
    Developer fails to acknowledge that the parties had not resolved their second amendment
    disagreements and, in particular, the Developer’s proposed changes, which altered
    fundamentally its second rental payment obligation to make it contingent on financing.
    98. The parties exchanged further drafts of the amendment documents, without coming to final
    agreement on all terms of all documents. See Joint Ex. 45, Email from Timothy McCormack
    to Eric Siegel, attaching (1) Second Amendment to Ground Lease and (2) Second
    Amendment to Development Agreement, dated Feb. 20, 2013; Joint Ex. 46, Email from Eric
    Siegel to Timothy McCormack, attaching (1) Second Amendment to Ground Lease and (2)
    Second Amendment to Development Agreement, dated Feb. 21, 2013; Joint Ex. 47, Email
    from Timothy McCormack to Eric Siegel, attaching Second Amendment to Development
    Agreement. The University declined to accept the Developer’s persistent demand to
    condition payment on securing financing. In its draft dated February 21, 2013, the Developer
    finally dropped its proposed language making payment contingent on financing and agreed to
    a May 30, 2013, deadline for the $1,475,000 rental payment to “coincide with [the] closing
    date” for financing. See Joint Ex. 46, Email from Eric Siegel to Timothy McCormack,
    65
    attaching (1) Second Amendment to Ground Lease and (2) Second Amendment to
    Development Agreement, dated Feb. 21, 2013, at 6.
    99. The University’s March 6, 2013, Drafts. In an email on March 6, 2013, the University’s
    outside counsel noted that the University had accepted the last draft of the Second
    Amendment to Development Agreement submitted by the Developer and attached a
    blackline document reflecting only minor changes to the Second Amendment to Ground
    Lease. See Joint Ex. 48, Email from David Gifford to Eric Siegel, attaching (1) Second
    Amendment to Ground Lease and (2) Second Amendment to Development Agreement, dated
    Mar. 6, 2013, at 1–6. The University’s outside counsel also wrote, “I have been asked to
    confirm specifically the parties’ understanding that the timing for the payment of the
    $1,475,000 Additional Rent payment will not be affected by the outstanding historical
    preservation challenge, or any other circumstance, and time is of the essence for the payment
    of that sum.” 
    Id. Siegel testified
    that he did not believe the University’s position regarding
    the rental payment was reasonable “[b]ecause we were still dealing with the historic issues,”
    which impacted the Developer’s ability to close on financing. Trial Tr. Day 5 PM at 77:11–
    79:20. In other words, despite dropping its request for language making its rental payment
    obligations contingent on financing, and agreeing in its drafts transmitted on February 21,
    2013, to a date certain for the rental payment, the Developer continued to operate in
    accordance with an alternate reality in which its rental payment obligations were contingent
    on financing, regardless of the requirements of any contract document.
    100.   The following day, the University’s outside counsel sent Siegel “an updated version of
    the Second Amendment to Development Agreement” that incorporated several changes
    requested by, and favorable to, the Developer. Joint Ex. 51, Email from David Gifford to
    66
    Eric Siegel, attaching Second Amendment to Development Agreement, dated Mar. 7, 2013,
    at 1. Thus, by March 7, 2013, the parties appeared to be close to executing agreements,
    almost one year after execution of the April 2012 Term Sheet. The Developer threw a
    proverbial wrench in this progress, however, by demanding new concessions from the
    University.
    101.   The Developer’s Request for Further Changes. On March 12, 2013, Siegel sent
    Brangman “for [his] consideration . . . two changes to the Ground Lease,” one of which was
    “language to address the fact that the D.C. Preservation League has filed the historic
    preservation applications and the potential impact of historic designation on the Development
    Program and payment of the initial ground lease payment of $1,475,000.” Joint Ex. 52,
    Emails Between Alan Brangman and Eric Siegel, dated Mar. 12, 13, 2013, at 2. In reply,
    Brangman told the Developer that its proposal for “[r]eturn of payment” in the case of certain
    contingencies related to the historic applications was not “going to work” but provided that,
    instead, the University “might agree to placing the payment in escrow.” 
    Id. at 1.
    102.   On March 14, 2013, Siegel transmitted to Gifford a draft of the amendment to the Ground
    Lease reflecting the changes discussed with, but not approved by, Brangman. See Joint Ex.
    54, Email from Eric Siegel to David Gifford, dated Mar. 14, 2013. Brangman and Gifford in
    separate emails to Siegel informed the Developer that the proposed escrow arrangement for
    the $1,475,000 rental payment was not acceptable to the University. See Joint Ex. 55, Email
    from Alan Brangman to Eric Siegel, dated Mar. 22, 2013; Joint Ex. 56, Email from David
    Gifford to Eric Siegel, attaching draft documents, dated Mar. 27, 2013.
    103.   On April 1, 2013, “[u]pon returning from spring break,” Siegel responded to Gifford’s
    March 27, 2013, email and the attached drafts. Joint Ex. 57, Email from Eric Siegel to David
    67
    Gifford, dated Apr. 1, 2013, at 1. He expressed that several of the University’s proposed
    terms were unacceptable to the Developer. In particular, he conveyed that the Developer
    “cannot agree that the University is entitled to collect $1,475,000 should the Development
    Agreement and Ground Lease be terminated on May 30 for non-payment, particularly now
    that there is looming . . . two historic preservation applications that may materially negatively
    impact the project or, at worst, mark its end.” 
    Id. Siegel added,
    “[W]e have already
    expended over $1 million towards this project” and “[i]f May 30 comes and we fail to make
    payment as obligated to do so under this Second Amendment, the agreement automatically
    terminates, and we are out all of the money we have expended.” 
    Id. Thus, Siegel
    asserted
    that, as already “stated in [his] March 7 email,” the Developer’s proposed “changes are non-
    negotiable.” 
    Id. The Developer
    simply does not acknowledge that this possibility of losing
    “all of the money [it] ha[s] expended” was a risk assumed by the Developer in the original
    agreements.
    104.   Brangman sent an email expressing the University’s views as to the reasonableness of its
    March 27, 2013, proposed but rejected changes, and the parties decided to meet in person.
    See Def.’s Ex. 109, Emails Between Eric Siegel and Alan Brangman, dated Apr. 9, 2013.
    After that in-person meeting, the Developer sent a letter to the University, acknowledging
    that the Developer had been required to preserve the WRECO garage under the DUKE Plan
    applicable to its development program from its inception, but asserting that the preservation
    of the Bond Bread building was an unexpected requirement and, accordingly, “must be paid
    for by the University.” Def.’s Ex. 110, Letter from Developer to Alan Brangman, dated Apr.
    15, 2013, at 2. The Developer further advised that “the $1,475,000 ground lease payment to
    68
    be tendered on or before May 30, 2013 is now a potential issue because we do not know what
    we are building as a result of these historic applications.” 
    Id. 105. In
    a letter dated the following day, Brangman responded stating that “the University does
    not come to the same conclusions” as the Developer, noting that the governing agreements
    do not require the University to “absorb any costs associated with the development of this
    property other than as expressly stated in the project documents,” which costs are the
    Developer’s responsibility under those agreements. Def.’s Ex. 111, Letter from Alan
    Brangman to Ron Cohen, dated Apr. 16, 2013, at 1. With respect to the $1,475,000 payment,
    the letter provides that “the University views [that] upcoming payment as a commitment to
    continue with the redevelopment of the property and more importantly as a cure for the fact
    that a default condition currently exists with respect to the project,” asserting that the
    “University does not in any way see a linkage between your obligation to make that payment
    as scheduled and the actions of DCPL.” 
    Id. at 2.
    106.   The Developer’s Historic Preservation Efforts. Meanwhile, the Developer worked to
    account for the historic preservation requirements likely to affect the Property. In particular,
    the Developer consulted with its architects and historic preservation contractors to get an
    estimate of the added expense of historic preservation, which estimate was $7,000,000 to
    $8,500,000. See Pl.’s Ex. 117, Email from Eric Siegel to Alan Brangman, dated Apr. 11,
    2013, attaching Letter from Alan Cohen to Eric Siegel, dated Apr. 9, 2013, at 2.
    107.   Concerns Raised Regarding the Developer’s Plans. The Developer also communicated
    with multiple individuals regarding the proposals it intended to submit to DCPL in hopes of
    obtaining DCPL’s support before the District’s Historic Preservation Review Board. The
    Developer’s proposals included demolishing the entirety of the WRECO garage. See Def.’s
    69
    Ex. 112, Emails Between Eric Siegel, Sean Cahill, et al., dated Apr. 18, 23, 2013, at 2. In an
    email to Eric Siegel, Sean Cahill, an architect and member of the Board of DCPL, expressed
    his view that the Developer’s proposal “enter[ed] a very slippery slope” given its reliance on
    the need for environmental remediation in accordance with city requirements to justify
    minimal preservation of the historic buildings even though “[t]he contaminants can certainly
    be remediated with the building in place.” 
    Id. at 1.
    After “strongly suggest[ing] [the
    Developer] rethink this position,” Cahill advised that “[a]ll developers have to deal with
    these issues. Welcome to developing in the District.” 
    Id. at 1–2.
    He further expressed his
    view that the Developer “is starting a war here” and that the “lack of movement on this will
    be seen as disappointing at best.” 
    Id. at 2.
    While Cahill believed in a “solution where both
    sides are satisfied and supportive of the project” that could be accomplished in a “timely
    manner,” he thought such a solution was not possible “with the design submission attached.”
    
    Id. 108. Notwithstanding
    Cahill’s recommendation, the Developer submitted a plan that, in
    DCPL’s view, “lack[ed] . . . any retention of the WRECO garage” and, thus, was not agreed
    to by DCPL. Def.’s Ex. 114, Emails Between Eric Siegel and Rebecca Miller, dated May 3,
    2013, at 1. Responding to Miller’s email rejecting the Developer’s proposal, Siegel
    expressed his view that it was “a shame that this project may die if the financing goes away
    at this late hour.” 
    Id. 109. On
    May 23, 2013, the Historic Preservation Review Board held a hearing at which it
    considered DCPL’s nomination applications for the WRECO garage and Bond Bread
    building, as well as a proposal by the Developer, dated April 30, 2013, regarding the use of
    those buildings in its construction. See Trial Tr. Day 2 PM at 20:5–22:4 (Callcott). At that
    70
    hearing, the Board “designated the two [buildings] as landmarks” and “found that substantial
    revisions would be needed for [the Developer’s proposal] to be an acceptable preservation
    solution that was consistent with the preservation law.” 
    Id. at 2
    0:8–16 (Callcott). In the
    following weeks, the Developer or its architects met with personnel at the Historic
    Preservation Office several times to develop a new plan for construction on the site. See 
    id. at 21:2–22:4
    (Callcott). The Developer also “sought a path forward through” the so-called
    Mayor’s Agent process, Trial Tr. Day 4 AM at 26:15–17 (Siegel), which allows “projects of
    special merit . . . that may not be entirely consistent with the preservation law” to go forward
    despite “some amount of demolition,” if they serve some other public interest, such as
    “clean[ing] up a site” having “environmental remediation issues,” Trial Tr. Day 2 PM at
    16:12–17:11 (Callcott).
    O.     MAY 2013: THE DEVELOPER AGAIN REFUSES TO MAKE THE
    $1,475,000 RENTAL PAYMENT AS REQUIRED
    110.   Consistent with its “non-negotiable” position expressed in March and April 2012, two
    days before the May 30, 2013, deadline for payment of the overdue rent, the Developer
    transmitted a letter to Brangman communicating that “until the[] historic issues are
    resolved,” it did “not intend to make any further monetary payments to Howard University.”
    Def.’s Ex. 116, Email from Eric Siegel to Alan Brangman, Robert Tarola, and Norman
    Jenkins, cc: Alan Cohen, Ron Cohen, and Tim Kissler, dated May 28, 2013, attaching Letter
    from Developer to Alan Brangman, dated May 23, 2013, at 2. The Developer also warned
    that “[s]hould Howard University determine that it is not advisable to continue working with
    the Developer,” the Developer would nevertheless “hold firm to this property.” 
    Id. at 3.
    The
    Developer further stated that it was “too invested to walk away” from the project. 
    Id. 71 111.
      Having established a belligerent tone of non-negotiable terms and implicitly threatening
    litigation to “hold” onto the Property, 
    id., the Developer
    offered the University a path
    forward that the Developer was willing to pursue. Specifically, the Developer proposed,
    “[a]s an alternative, if the University is adamant about receiving a lease payment,” that the
    University “consider swapping the adjacent University parking lot for the land subject to the
    ground lease.” 
    Id. In this
    arrangement, the Developer contemplated that the University, not
    the Developer, would then be responsible for “pursu[ing] remedies with the District” for the
    “severely constrained site.” 
    Id. 112. Cohen’s
    May 29, 2013, Email to Siegel and Alan Cohen. On May 29, 2013, Cohen
    emailed Siegel and Alan Cohen to inform them that Jenkins was “not an advocate of
    swapping sites” but that Cohen “d[id]n’t know whether he [wa]s posturing.” Def.’s Ex. 118,
    Email from Ron Cohen to Eric Siegel and Alan Cohen, dated May 29, 2013. He advised the
    two that the University was “trying to schedule a meeting for this Thursday to discuss” and
    they “should both attend and offer no compromise.” 
    Id. He further
    advised them that “[t]he
    best word to describe the payment if we were to make it is STUPID and that we are not.” 
    Id. 113. That
    same day, Siegel emailed Jenkins to decline the meeting Cohen had mentioned,
    citing existing travel plans, and offered to meet instead on June 3, 2013. See Joint Ex. 60,
    Emails Between Norman Jenkins and Eric Siegel, cc: Alan Cohen, Ron Cohen, and Kurt
    Schmoke, dated May 29, 31, 2013. Jenkins replied clarifying that no meeting had been
    proposed by the University but that “the university owed [the Developer] a ‘thoughtful
    response’ to [its] letter” and “[p]reparation of that response is in process.” 
    Id. 72 P.
        JUNE – JULY 2013: THE FINAL NOTICES OF DEFAULT AND
    TERMINATION AND THE DEVELOPER’S RESPONSE
    114.   The Fourth Notice of Default. On June 3, 2013, having received no rental payment from
    the Developer on May 30, 2013, the University sent the Developer a fourth notice regarding
    its defaults. See Joint Ex. 61, Notice of Default and Notice of Intent to Terminate, dated June
    3, 2013, at 1. The reason cited for the notice was “that the Developer is in default of the
    Ground Lease by reason of its failure to pay to the University the sum of $1,475,000.00 due
    December 8, 2011, . . . which due date was extended by the University through May 30,
    2013.” 
    Id. As required
    by the Ground Lease, in bold face and all-capitalized type, the letter
    provided, “PLEASE BE ADVISED THAT THE UNIVERSITY INTENDS TO
    TERMINATE THE GROUND LEASE IF THAT FAILURE IS NOT CURED BY THE
    PAYMENT IN FULL OF THE SUM OF $1,475,000.00 BY THE DEVELOPER TO THE
    UNIVERSITY WITHIN TEN (10) DAYS AFTER THIS NOTICE.” 
    Id. (emphasis omitted).
    115.   The Developer responded to this notice the following day by requesting a meeting and
    again proposing conditions on the rental payment, including return to the Developer should it
    decide, within six months, to “walk away” from the property. Joint Ex. 63, Emails Between
    Alan Brangman and Eric Siegel, dated June 4, 5, 2013, at 2; see Joint Ex. 62, Emails
    Between Alan Brangman and Eric Siegel, dated June 4, 2013. The Developer’s proposed
    conditioned payment of the second rental payment was again rejected by the University. See
    Joint Ex. 63, Emails Between Alan Brangman and Eric Siegel, dated June 4, 5, 2013, at 1.
    116.   Not all of the Developer’s stakeholders were of the view that the Developer should
    continue to refuse to make the rental payment. In an email on June 7, 2013, the principal of
    CastleRock, which shared the Developer’s rights and obligations under its agreements with
    the University, expressed his opinion to Siegel that he did “not think that being in capital ‘D’
    73
    default is a position where we can stay” and adopting a view, expressed by Tarola, that “[t]he
    timing is bad, but the payment is required, to keep the purchase option alive. Unfortunately
    it is a nonrefundable payment, but then again, we have had the property under contract for
    quite some time.” Def.’s Ex. 124, Email from Tim Kissler to Eric Siegel, dated June 7, 2013.
    117.     In an email dated June 6, 2013, Tarola informed Siegel that the University “would be
    happy to talk after Howard receives the ground rent payment to cure the default. Please
    advise when that will occur.” Joint Ex. 64, Emails Between Robert Tarola and Eric Siegel,
    dated June 6, 2013. Rather than make the payment, the Developer sent Schmoke, on June
    10, 2013, a letter detailing the Developer’s progress so far on the Property and offering to
    place the payment funds into an escrow account “so that Howard University knows that the
    money is there to be paid upon conclusion of the Mayor’s Agent process.” See Joint Ex. 65,
    Letter from Developer to Kurt Schmoke, dated June 10, 2013 at 1–4. By this date, the
    Developer still had no firm commitment for financing. 18
    118.     The Notice of Termination. On June 14, 2013, the University sent the Developer a notice
    of election to terminate the ground lease and, three days later, the University terminated the
    development agreement. See Joint Ex. 66, Notice of Election to Terminate Ground Lease,
    dated June 14, 2013; Joint Ex. 67, Notice of Termination of Development Agreement and
    Supplemental Development Agreement, dated June 17, 2013.
    119.     As of June 19, 2013, the Developer expressed awareness that the University “has
    determined not to change its position regarding termination,” Joint Ex. 68, Emails Between
    Eric Siegel, Kurt Schmoke, and Alan Brangman, dated June 19, 2013, at 1, but, nevertheless,
    18
    In its original Complaint, the Developer represented that “[a]fter receipt of the [June 3, 2013] Default
    Notice and until June 13, 2013, [the Developer] repeatedly requested that [the University] execute the Second
    Amendment.” Complaint ¶ 36. No evidence in the trial record supports this representation.
    74
    on June 21, 2013, wrote a check payable to Closeline Settlements in the amount of
    $1,475,000, deposited in an interest bearing account for the benefit of the Developer. See
    Joint Ex. 71, Email from David Carmen to Ron Cohen, Alan Cohen, and Eric Siegel, dated
    June 22, 2013, reflecting email to Kurt Schmoke attaching letter from Closeline Settlements,
    dated June 21, 2013, at 2. 19
    120.     On June 22, 2013, the Developer engaged David Carmen, a “personal friend” of Cohen,
    Trial Tr. Day 3 AM at 73:17–18 (Cohen), to transmit via email versions of the amendment
    documents signed by the Developer, as well as proof of the Developer’s deposit with
    Closeline, see Joint Ex. 69, Email from David Carmen to Ron Cohen, Alan Cohen, and Eric
    Siegel, dated June 22, 2013, reflecting email to Kurt Schmoke attaching proposed Second
    Amendment to Development Agreement; Joint Ex. 70, Email from David Carmen to Ron
    Cohen, Alan Cohen, and Eric Siegel, dated June 22, 2013, reflecting email to Kurt Schmoke
    attaching proposed Second Amendment to Ground Lease; Joint Ex. 71, Email from David
    Carmen to Ron Cohen, Alan Cohen, and Eric Siegel, dated June 22, 2013, reflecting email to
    Kurt Schmoke attaching letter from Closeline Settlements, dated June 21, 2013.
    121.     Carmen “is a government relations specialist” and knew Schmoke from when Schmoke
    served as the mayor of Baltimore. Trial Tr. Day 6 AM at 136:23–137:5 (Schmoke). While
    Cohen testified that Carmen “never got any money” from the Developer, Trial Tr. Day 3 AM
    at 75:15–18, Siegel clarified, and the evidence shows, that Carmen was retained at a cost of
    at least $75,000, and as much as over $100,000, see Trial Tr. Day 4 AM at 36:16–21; Def.’s
    19
    The Developer characterized the Closeline account as an “escrow account” throughout much of this
    litigation, notwithstanding that the University was never a party to the account as required for a “true escrow,”
    Def.’s Ex. 133, Email from Elliot Liss, Closeline Settlements, to Eric Siegel, dated June 19, 2013, but has at last
    dropped that misleading contention. See, e.g., Pl.’s Mem. Supp. Mot. TRO and/or Prelim. Inj. at 10, ECF No. 6-1;
    Pl.’s Resp. Def.’s SMF ¶ 110, ECF No. 90.
    75
    Ex. 10, Grid Note, at 3 (reflecting two payments in 2013, totaling over $100,000, to the
    Carmen Group).
    122.   The draft documents transmitted by Carmen and signed by the Developer reflected
    additional changes to the versions of these documents approved by the University, including
    extending the date for payment of the $1,475,000 to June 24, 2013, extending the project
    deadlines, modifying the construction design, and providing for contingent performance
    based on the historic designation process, never agreed to by the University. See generally
    Pl.’s Ex. 296 (redline comparison with last draft of the Ground Lease sent by the University);
    Pl.’s Ex. 297 (same as to Development Agreement). Despite these significant changes to the
    drafts sent by the University, throughout this litigation the Developer and its counsel have
    repeatedly minimized these unilateral proposals and suggested that the Developer accepted
    the University’s proposed drafts wholesale. See, e.g., Trial Tr. Day 1 AM at 26:23–24:6
    (counsel for the Developer) (“On June 22nd, the developer sent second amendments to the
    University signed by the developer that accepted the last draft from the University, other than
    to have a provision that said that: To the extent the Mayor’s agent process requires a change
    in the deadlines, the parties would negotiate those changes but otherwise accepts the terms
    the University demanded . . . .”); Trial Tr. Day 1 AM at 125:17–126:4 (Cohen) (asserting
    that after the Developer signed the June 22, 2013, drafts, “everything was agreed to,” “that
    second amendment—we didn’t draft it, their attorney did,” and all the university had to do
    was “sign the agreement that’s been floating around between Mr. Gifford of Howard’s law
    firm and Eric”).
    123.   In any event, these documents executed by the Developer lasted less than a week before
    the Developer withdrew them. In a letter to the University dated June 27, 2013, the
    76
    Developer withdrew its signed proposed second amendment documents and asserted that it
    would “keep the $1,475,000 tendered” in the Closeline account. Def.’s Ex. 142, Letter from
    Developer to Kurt Schmoke, dated June 27, 2013. Nevertheless, the University agreed to a
    meeting with the Developer on July 2, 2013, but remained unsatisfied that the Developer
    would fulfill its obligations to the University, given the Developer’s continued refusal to
    make the long overdue rental payment and inability to provide proof of financing. See Trial
    Tr. Day 6 AM at 140:10–141:1 (Schmoke); Trial Tr. Day 6 AM at 62:1–63:11 (Siegel).
    Q.      JULY 2013 – JANUARY 2014: THE DEVELOPER FILES SUIT, LOSES,
    AND EVADES THIS COURT’S JUDGMENT
    124.     As 
    noted supra
    Part I.B, the Developer filed this lawsuit on July 15, 2013, against the
    University, and summary judgment was granted in favor of the University’s counterclaim
    and claim against CastleRock Partners on December 19, 2013.
    125.     After the Developer filed an appeal to the D.C. Circuit, the University filed an
    application, on January 3, 2014, for a writ of attachment for the $1,475,000 held by
    Closeline, to satisfy its judgment against the Developer. See Appl. Writ Attachment, ECF
    No. 46. The writ was issued by the Clerk of this Court on January 6, 2014, Writ Attachment
    J., ECF No. 48, and served on Closeline on January 8, 2014, see Aff. Service Writ, ECF No.
    50. The funds were unable to be attached to satisfy the judgment, however, because, at the
    Developer’s direction, Closeline returned the $1,475,000 to the Developer on January 6,
    2014, the same date the writ had been issued. See Def.’s Mot. Suppl. Rec. App., ECF No.
    64. 20
    20
    The University’s unsuccessful efforts to attach the Developer’s funds to pay the judgment award were
    discussed in the January 2017 decision in this litigation. See HTC III, 
    2017 WL 421909
    , at *4 n.6. In its response
    to the writ of attachment, Closeline included a copy of the check returning the $1,475,000 to the Developer, which
    showed that the check “had been deposited into the Developer’s account with Industrial Bank.” Def.’s Mot. Suppl.
    Rec. App. at 4. In a further attempt to attach the funds in satisfaction of the judgment in its favor, the University
    77
    R.        THE DEVELOPER’S ALLEGED DAMAGES
    126.    Through an expert witness, the Developer presented testimony that, assuming the
    Developer’s legal entitlement to damages for the alleged breach of contract, the values
    applicable to calculation of the Developer’s damages would be $14,400,000 for the
    leasehold, $4,100,000 for the cost of delay as of June 1, 2017, and $6,200,000 for the lost tax
    abatement. See Trial Tr. Day 6 PM at 60:18–65:10 (Duffy); Pl.’s Ex. 277, Retrospective
    Market Value Appraisal – Leasehold, prepared by Integra Realty Resources, dated Feb. 5,
    2016, at 5.
    S.        CREDIBILITY ASSESSMENT
    127.    Given this Court’s “opportunity to judge the witnesses’ credibility,” FED. R. CIV. P.
    52(a)(6), the witnesses’ demeanor at trial informs the factual findings set out above, as well
    as the conclusions of law that follow.
    128.    With two exceptions, the witnesses who testified at trial were credible. They testified in
    a straightforward, careful manner about their knowledge of the project and, for those with
    expert or industry knowledge, their understanding of practices and procedures relevant to the
    legal issues presented in this case, acknowledging the limitations of their knowledge as
    appropriate.
    129.    The two witnesses who lacked credibility as to many issues addressed in their testimony
    were Ronald Cohen and Eric Siegel. Cohen avoided answering questions that he reasonably
    would have had knowledge to answer. For example, when asked by the University’s counsel
    served a writ of attachment on Industrial Bank, which explained in response that the Developer had transferred those
    funds to Property Management Account Services, LLC (“PMAS”), “an affiliate of the Developer.” Id.; see Pl.’s
    Resp. Def.’s Mot. Suppl. Rec. App. at 9, ECF No. 65 (acknowledging that the check for $1,475,000 to Closeline
    was “clearly made out by ‘Property Mgmt Acct Svcs LLC,’ i.e., PMAS, not [the Developer]”). The University
    then deposed PMAS, and PMAS’s deponent—Eric Siegel—testified that “the funds on deposit with Closeline
    Settlements were the property of PMAS (not the Developer) and PMAS had never relinquished its ownership of
    those funds.” Def.’s Mot. Suppl. Rec. App. at 4.
    78
    whether the University’s assertion, on August 30, 2011, that the Developer had “failed to
    execute the CBE Agreement required by the covenants,” was correct, Cohen made counsel
    repeat the question before opining, “I don’t know whether or not it was or it was not sitting
    here. That wasn’t something I was overseeing.” Trial Tr. Day 2 AM at 38:7–14. When
    pressed by the Court as to whether he had “any reason to doubt that the statement in this
    letter is correct,” Cohen again demurred before ultimately testifying “[i]t appears to be
    correct.” 
    Id. at 3
    8:15–23. In another pointed example of evasion, when asked whether he
    recognized the handwriting on a letter to the Developer from the University as Siegel’s,
    Cohen said, “I have no idea, quite honestly,” defying reasonable belief, given the close
    working relationship between Cohen and Siegel, as well as Cohen’s repeated assertions that
    Siegel was the point person for the Developer on the project. Trial Tr. Day 2 AM at 13:5–7
    (testifying as to Joint Ex. 9). Indeed, Siegel later confirmed that the handwriting in question
    was his. See Trial Tr. Day 3 AM at 144:11–16 (Siegel testifying that the handwriting on
    Joint Exhibit 9 was his). At other points, Cohen provided inaccurate or misleading answers
    favorable to the Developer. For example, when asked whether Carmen had been
    compensated for his involvement with the project, Cohen testified assertively, “No, he never
    got any money. Never paid anything. He is a friend.” Trial Tr. Day 3 AM at 75:15–18. The
    evidence shows, however, that Carmen was retained at a cost of at least $75,000, and as
    much as over $100,000, see Trial Tr. Day 4 AM at 36:7–21 (Siegel testifying Carmen was
    paid $75,000); Def.’s Ex. 10, Grid Note, at 3 (reflecting two payments to the Carmen Group
    totaling over $100,000); see also Def.’s Ex. 9, Grid Note (reflecting advances from PMAS,
    another Cohen affiliate, 
    see supra
    note 20; Trial Tr. Day 1 PM at 102:23–25, to the
    Developer). Cohen’s failure to acknowledge these payments is particularly damaging to his
    79
    credibility given his involvement in managing the money associated with the various Cohen
    Companies affiliates under his control. See Trial Tr. Day 1 PM at 102:13–103:23 (testifying
    as to the “grid note” reflected in Def.’s Ex. 9 and describing it as “a constant running ledger
    entry so at all times, I could pick up the phone, we knew exactly how much each of our
    entities were owned by whom and what the interest rate was that was accruing”).
    130.   Siegel’s testimony was at times credible and other times not credible. While Siegel was
    generally responsive to questioning, he demonstrated a tendency to rationalize, split hairs, or
    feign ignorance in an effort to provide answers favorable to the Developer. For example,
    when asked on direct examination about the Developer’s response to the University’s
    February 3, 2012, notice, Siegel stated he warned the University to preserve its records
    because he “was concerned based upon our prior dealings with the university that . . . records
    might be lost.” Trial Tr. Day 3 PM at 29:19–30:3. Absolutely no evidence was presented,
    however, that the University ever lost records in connection with this project. In addition,
    when asked about the same communications on cross, Siegel first disclaimed familiarity with
    the term “litigation hold letter” used by the University’s counsel, testifying, “I don’t know
    what that means, that term, ‘litigation hold.’ I don’t know what that means, I really don’t.”
    Trial Tr. Day 4 PM at 42:22–43:1. While, in response to the University’s rephrased question,
    asking whether the Developer sent its response “to ensure the preservation of those
    documents in the event of future litigation,” Siegel testified “[t]hat’s correct,” in almost the
    same breath he again disclaimed raising the specter of litigation, testifying that he “didn’t
    perceive [the response] as a threat” of litigation but “was basically indicating to them that
    they should hold on to their materials because we may have a dispute here that’s going to rise
    to the level of litigation. I wasn’t threatening litigation.” 
    Id. at 43:10–44:2.
    These
    80
    conflicting assertions strain credulity, rendering much of Siegel’s testimony less than
    credible.
    III.      CONCLUSIONS OF LAW
    In reaching conclusions of law, the Court evaluates the evidence to determine whether the
    litigants have established each element of their respective claims by a preponderance of the
    evidence. See Concrete Pipe & Prods. Calif., Inc. v. Constr. Laborers Pension Trust S. Calif.,
    
    508 U.S. 602
    , 622 (1993); Clark v. Feder Semo & Bard, P.C., 
    895 F. Supp. 2d 7
    , 29 (D.D.C.
    2012) (“The Court reviews the evidence under the ‘default rule for civil cases,’ the
    ‘preponderance of the evidence’ standard.” (quoting Cigna Corp. v. Amara, 
    563 U.S. 421
    , 444
    (2011))); see also Ascom Hasler Mailing Systems, Inc. v. United States Postal Service, 885 F.
    Supp. 2d 156, 181 (D.D.C. 2012). “The burden of showing something by a ‘preponderance of
    the evidence,’ the most common standard in the civil law, ‘simply requires the trier of fact to
    believe that the existence of a fact is more probable than its nonexistence before he may find in
    favor of the party who has the burden to persuade the judge of the fact’s existence.’” Concrete
    Pipe & Prods. Calif., 
    Inc., 508 U.S. at 622
    (quoting In re Winship, 
    397 U.S. 358
    , 371–72 (1970)
    (Harlan, J., concurring)). “[T]he factfinder must evaluate the raw evidence, finding it to be
    sufficiently reliable and sufficiently probative to demonstrate the truth of the asserted proposition
    with the requisite degree of certainty.” 
    Id. A. LIABILITY
    FOR BREACH OF CONTRACT
    Under District of Columbia law, “[t]o prevail on a claim of breach of contract, a party
    must establish (1) a valid contract between the parties; (2) an obligation or duty arising out of the
    contract; (3) a breach of that duty; and (4) damages caused by breach.” Francis v. Rehman, 
    110 A.3d 615
    , 620 (D.C. 2015) (emphasis omitted) (quoting Tsintolas Realty Co. v. Mendez, 984
    
    81 A.2d 181
    , 187 (D.C. 2009)). “Breach is an unjustified failure to perform all or any part of what
    is promised in a contract entitling the injured party to damages.” Fowler v. A & A Co., 
    262 A.2d 344
    , 347 (D.C. 1970) (internal quotation marks omitted). For example, “a contract is breached if
    a party fails to perform when performance is due.” Eastbanc, Inc. v. Georgetown Park Assocs.
    II, L.P., 
    940 A.2d 996
    , 1004 (D.C. 2008). A breach is material, such that the non-breaching
    party is “able to elect the alternative rights and the remedies available to him,” when the non-
    breaching party receives “something substantially less or different from that for which he
    bargained.” 
    Fowler, 262 A.2d at 347
    (internal quotation marks omitted).
    With respect to the first and second elements, i.e., a valid contract between the parties
    giving rise to obligations, for the reasons stated previously, three such contracts exist: the
    Ground Lease, as amended, the Development Agreement, as amended, and the Term Sheet. See
    HTC III, 
    2017 WL 421909
    , at *6 (concluding the Term Sheet is a binding preliminary
    agreement); HTC I, 
    7 F. Supp. 3d
    at 67 & n.4 (identifying the uncontested Ground Lease,
    Development Agreement, and corresponding first amendments to those agreements). The
    questions whether and which party was in breach of any agreements, and the appropriate remedy,
    if any, are addressed seriatim in the discussion that follows.
    B.      THE DEVELOPER WAS IN DEFAULT ON THE GROUND LEASE AND
    DEVELOPMENT AGREEMENT AT THE TIME THE TERM SHEET
    WAS EXECUTED
    The Developer has never expressly conceded in this litigation that it was in default on the
    Ground Lease and Development Agreement, as alleged by the University in notices sent in
    September 2011 and February and March 2012, by, inter alia, failing to make the $1,475,000
    rental payment by March 15, 2011, as required by the agreements. Yet, the April 2012 Term
    Sheet speaks for itself on this issue. In signing the Term Sheet, both parties acknowledged that
    82
    the agreement was “For Settlement Purposes” with the intent to “cure . . . the monetary default”
    by the Developer. Term Sheet at 1. Thus, in its Proposed Findings of Fact and Conclusions of
    Law, the Developer acknowledges, as it must, the existence of “prior defaults” by the Developer.
    See Pl.’s Prop. Findings Fact Concls. Law ¶ 401.
    A plain reading of the operative agreements also supports the conclusion that the
    Developer was in default at the time the Term Sheet was executed. “D.C. courts ‘adhere to an
    objective law of contracts,’” such that “the written language embodying the terms of an
    agreement will govern the rights and liabilities of the parties regardless of the intent of the parties
    at the time they entered the contract, unless the written language is not susceptible of a clear and
    definite meaning.” Hensel Phelps Constr. Co. v. Cooper Carry Inc., 
    861 F.3d 267
    , 272 (D.C.
    Cir. 2017) (quoting Carlyle Inv. Mgmt. L.L.C. v. Ace Am. Ins. Co., 
    131 A.3d 886
    , 894–95 (D.C.
    2016)). Pursuant to the clear and definite language of the Ground Lease, the Developer was
    required to pay $1,475,000 by March 15, 2011, subject to no contingencies or limitations
    whatsoever. While the University agreed to extend the time of the payment to December 8,
    2011, no payment was forthcoming on that date, and the evidence shows that no further
    extension was given by the University prior to three notices of default in September 2011,
    February 2012, and March 2012. Consequently, the Court finds that the Developer was in
    breach of its agreements with the University prior to the signing of the Term Sheet.
    C.      THE DEVELOPER EXHIBITED BAD FAITH IN ITS NEGOTIATIONS
    WITH THE UNIVERSITY ALMOST IMMEDIATELY FOLLOWING
    EXECUTION OF THE TERM SHEET
    As explained previously, the Term Sheet constituted a binding preliminary agreement to
    negotiate in good faith toward amendments to the Ground Lease and Development Agreement,
    which amendments would constitute modifications to the original agreements such that the
    83
    Developer’s defaults would be cured. Accordingly, whether either or both parties breached their
    duty to negotiate in good faith was a critical question identified in the latest summary judgment
    decision and, given the fact-intensive nature of the question, left for trial. See HTC III, 
    2017 WL 421909
    , at *8–9.
    Under D.C. law, “[g]ood faith performance or enforcement of a contract emphasizes
    faithfulness to an agreed common purpose and consistency with the justified expectations of the
    other party; it excludes a variety of types of conduct characterized as involving ‘bad faith’
    because they violate standards of decency, fairness or reasonableness.” Allworth v. Howard
    Univ., 
    890 A.2d 194
    , 201–02 (D.C. 2006) (quoting Restatement (Second) of Contracts § 205
    cmt. a). “[B]ad faith may be overt or may consist of inaction,” involving “evasion of the spirit of
    the bargain, lack of diligence and slacking off, willful rendering of imperfect performance, abuse
    of a power to specify terms, and interference with or failure to cooperate in the other party’s
    performance.” 
    Id. (quoting Restatement
    (Second) of Contracts § 205 cmt. d). Yet, “[b]ad faith
    means more than mere negligence.” 
    Id. (quoting Gupta
    v. New Britain Gen. Hosp., 
    687 A.2d 111
    , 122 (Conn. 1996)).
    In the context of a binding preliminary agreement to negotiate in good faith, like the
    Term Sheet, while parties may in good faith disagree on open terms of the contract being
    negotiated, and, as a result, decide mutually to abandon the negotiation, the requisite good faith
    is lacking where “a party unilaterally renounc[es] the deal, abandon[s] the negotiations, or
    insist[s] on conditions that do not conform to the preliminary agreement.” Banneker Ventures,
    LLC v. Graham, 
    798 F.3d 1119
    , 1131 (D.C. Cir. 2015) (quoting Teachers Ins. & Annuity Ass’n
    of Am. v. Tribune Co., 
    670 F. Supp. 491
    , 498 (S.D.N.Y. 1987)). Applying this understanding of
    good and bad faith, the D.C. Circuit concluded in Banneker Ventures that a plaintiff had stated a
    84
    claim for breach of the duty to negotiate in good faith where the defendant “directed cessation of
    negotiations and interjected new terms and conditions that were not part of [the applicable] Term
    Sheet.” 
    Id. Similarly, in
    Teachers Insurance & Annuity Association of America v. Tribune
    Company, a party was found to have breached the duty to negotiate in good faith “by refusing to
    negotiate unless the lender agreed to modify the deal by accepting a new condition” not
    contained in the binding preliminary 
    agreement. 670 F. Supp. at 507
    .
    Here, each party argues that it acted in good faith, while the other acted in bad faith, in
    their negotiations over the second amendments to the Ground Lease and Development
    Agreement pursuant to the Term Sheet. The Developer, apparently conceding that its proposed
    terms conflicted with those contained in the Term Sheet, contends that it nevertheless acted in
    good faith, noting that “[t]he Second Amendment terms drafted by the Developer were proposed
    in response to real[i]ties on the ground and in an effort expeditiously to commence construction
    on the Project,” including “the unexpected loss of J.P. Morgan Financing.” Pl.’s Prop. Findings
    Fact Concls. Law ¶ 414. By contrast, according to the Developer, the University showed bad
    faith in its negotiations, including by proposing terms that diverged from those contained the
    Term Sheet. Skipping over the University’s proposed drafts of April 23, 2012, and May 4, 2012,
    
    see supra
    Part II.K.64, 66, the Developer points to the draft amendments circulated by the
    University on January, 11 2013, to assert that the University “sharply revis[ed] its own latest
    draft and insert[ed] provisions unfavorable to Developer and not contemplated by the Term
    Sheet, . . . show[ing] disregard for the reasonable expectations of the parties,” Pl.’s Prop.
    Findings Fact Concls. Law ¶ 426. The Developer also contends that the University exhibited bad
    faith in early 2013 by (1) “placing Mr. Brangman in charge” notwithstanding that Tarola had
    negotiated the Term Sheet, (2) making Schmoke the “final decision-maker with respect to the
    85
    June 3, 2013 notice of termination,” even though he “testified that he was ‘not even aware of the
    Term Sheet’”; and (3) “abrupt[ly] cancel[ing], at the behest of Mr. Schmoke, . . . the planned
    meeting with the Developer in late January 2013.” 
    Id. ¶¶ 426–31
    (emphasis in original).
    The University, on the other hand, contends that the Developer’s “bad faith is
    demonstrated by its response to the University’s April 23, 2012 drafts,” which response included,
    inter alia, (1) “[f]ail[ure] to pay the sum of $100,000 by April 20, 2012, as called for by the
    Term Sheet; (2) failing to “respond to the University’s drafts until after the April 30, 2012
    execution deadline contemplated by the Term Sheet”; (3) “not immediately sign[ing] the
    Termination of Escrow Agreement”; (4) proposing terms that conflicted with the Term Sheet,
    including numerous terms that predicated the Developer’s performance on its obtaining
    financing; and (5) deleting terms proposed by the University that were consistent with the Term
    Sheet, including the provision that the overdue rent would be paid in two installments and the
    walk-away provision contained in the Term Sheet. Def.’s Prop. Findings Fact Concls. Law
    ¶ 316.
    The evidence strongly supports the University’s view. Notably, the Developer does not
    contend that the University exhibited bad faith in the negotiations that immediately followed the
    execution of the Term Sheet, arguing instead that the Developer engaged in those negotiations in
    good faith and pointing only to later actions of the University as demonstrative of bad faith on
    the University’s part. The Developer’s position is untenable, however, in light of the evidence
    showing it acted in bad faith, by willfully failing to perform, evading the spirit of the deal, and
    abusing its power to specify terms, almost immediately after execution of the Term Sheet.
    Under the Term Sheet, the Developer was to pay the University, without contingency or
    limitation, $100,000 ten days after the execution of the Term Sheet. See Term Sheet at 2. The
    86
    Term Sheet was executed on April 10, 2012, see Trial Tr. Day 2 AM at 135:24–136:8 (counsel
    for both parties stipulating that the Term Sheet was fully executed by April 10, 2012), and, yet,
    the Developer never made the $100,000 payment, let alone by April 20, 2012, as required under
    the parties’ agreement. Cohen testified that he told Jenkins that he was “just not in a position to
    pay this money” because the Developer was “almost $2 million out-of-pocket,” and he “fully
    underst[oo]d” why Jenkins was “upset” given that Cohen “went back on a promise” to the
    University. Trial Tr. Day 1 AM at 103:4–10.
    Through his testimony, Siegel suggests that the Developer’s blatant failure to make the
    $100,000 payment is excused by the fact that “no one, neither Mr. Tarola nor anyone else from
    the university raised that issue” with him. Trial Tr. Day 3 PM at 37:25–38:5. In the first place,
    this testimony is misleading because someone from the University, Jenkins, communicated the
    University’s displeasure to the Developer through Cohen, see Trial Tr. Day 1 AM at 103:4–10
    (Cohen), and in its April 23, 2012, and May 4, 2012, proposed amendments, the University
    included provisions for the $100,000 payment, 
    see supra
    Part II.K.64, 66. More importantly, the
    Developer willfully breached a term of the Term Sheet regardless of whether the University
    attempted to hold the Developer immediately accountable for that breach. The Developer’s
    decision not to fulfill even this relatively minor obligation under the Term Sheet evidences a
    “willful rendering of imperfect performance” constituting bad faith. 
    Allworth, 890 A.2d at 201
    –
    02 (quoting Restatement (Second) of Contracts § 205 cmt. d).
    The Developer also appears to have willfully failed to comply with the Term Sheet’s
    imperative to “[e]xecute Ground Lease Amendment and Development Agreement Amendment
    by Monday, April 30, 2012,” Term Sheet at 2, responding to the University’s first drafts, sent on
    April 23, 2012—a Monday—nine days later, after the April 30, 2012, deadline, see Joint Ex. 23,
    87
    Email from Eric Siegel to David Gifford, cc: Norman Jenkins, Bridget Sarikas, Odessa Jackson,
    Robert Tarola, Timothy Kissler, Ronald Cohen, and Michael Hollander, attaching (1)
    Termination of Escrow Agreement; (2) Second Amendment to Ground Lease; and (3) Second
    Amendment to Development Agreement, dated May 2, 2012. No evidence was presented to
    explain the Developer’s failure to respond expeditiously, in accordance with the Developer’s
    own understanding of the Term Sheet’s intent, to the University’s drafts. See Trial Tr. Day 3 PM
    at 35:22–36:4 (Siegel) (“Q: What was your expectation as of time of the signing of the term
    sheet as to when the ground lease amendment and development agreement was going to be able
    to be executed? A: My expectation [was] it would be executed by the 30th. We were going to be
    expediting getting it done.”).
    The Developer further demonstrated bad faith by proposing terms that conflicted with the
    Term Sheet, thereby reflecting “evasion of the spirit of the bargain” and “abuse of a power to
    specify terms.” 
    Allworth, 890 A.2d at 201
    –02 (quoting Restatement (Second) of Contracts § 205
    cmt. d). No provision of the Term Sheet makes the Developer’s performance of any of its
    obligations contingent on financing. See generally Term Sheet. In this way, the Term Sheet was
    consistent with the underlying Ground Lease and Development Agreement, which also declined
    to predicate any party’s performance on the obtaining of financing and, in fact, specifically
    provided that the failure to obtain financing was not an “Unavoidable Delay” such that extension
    of existing performance deadlines could be sought. See Development Agreement at 7, 18.
    Tarola testified that while the University was aware of the Developer’s desire to obtain financing
    for the project, he “understood that the developer had some substantial assets and should be able
    to pay what was due to the University; so [he] expected it to be paid and, indeed, . . . was looking
    for cash as a way of showing good faith to continue the project.” Trial Tr. Day 5 AM at 17:19–
    88
    18:4. Indeed, Tarola “felt that the developer needed to show commitment to the project in the
    form of cash contributed toward moving that along . . . . [T]he cash was not important to
    Howard University, being a billion-dollar company, but it was important to make sure that we
    had the commitment to move forward with the project.” 
    Id. at 18:11–19.
    Plainly, the “spirit of
    the bargain” was that the University would receive rental payments from the Developer during
    the period that the Developer had exclusive rights to develop the Property, without those rental
    payments being tied to the Developer’s financing for the entire project.
    The Developer asserts, in essence, that its proposal making performance contingent on
    obtaining financing was reasonable in light of “real[i]ties on the ground,” such as the
    “unexpected loss of J.P. Morgan financing” sometime between April 10, 2012, and April 19,
    2012. Pl.’s Prop. Findings Fact Concls. Law ¶ 414. While the Developer’s approach may have
    seemed reasonable from its perspective as a real estate developer, this was not the bargain to
    which it had agreed and was entirely unreasonable in light of the Term Sheet and the underlying
    Ground Lease and Development Agreement. Although the Term Sheet does not specifically
    provide that the Developer would bear the risks of financing, the Ground Lease and
    Development Agreement do, disavowing failure to obtain financing as a reason for delay and
    explicitly providing for payment of the $1,475,000 rent on the earlier of settlement on a
    construction loan or March 15, 2011. To be sure, the Developer failed to secure the HUD
    funding it had hoped would finance the project only after the Ground Lease and Development
    Agreement were signed, and, in light of those difficulties, might understandably have asked to
    modify its agreements with the University to account for the obtaining of financing. Yet, despite
    the parties’ awareness of past issues related to financing, the Term Sheet reflects no such
    modification. Viewed in that context, the parties plainly struck a bargain in which the
    89
    Developer, and the Developer alone, bore the risks associated with seeking financing for the
    entire project. Given the parties’ bargain, the Developer’s proposals making its performance
    contingent on financing constitute bad faith.
    Bad faith is further shown by the Developer’s deletion of terms in the University’s April
    23, 2012, draft that were specified in the Term Sheet. Notably, the Developer mounts no excuse
    for its deletion of the term specifying that the $1,475,000 payment would be made in two
    installments. With respect to the walk away provision in the University’s April 23, 2012, drafts,
    Siegel testified to his view that it was “an overreach and so burdensome,” he “didn’t think it was
    reasonable, and no rational person would think it was reasonable.” Trial Tr. Day 3 PM at 52:7–
    24. He is incorrect. The University’s proposed provision merely elaborated upon a term
    assented to by both parties when they signed the Term Sheet. While reasonable push back
    against the University’s proposal was possible in light of the Term Sheet’s failure to specify all
    conditions of the contemplated walk away provision, the Developer’s wholesale deletion of any
    such provision from the amendment documents was unreasonable. Siegel testified to his view
    that a reasonable elaboration upon the Term Sheet’s walk away provision would have treated the
    specified walk away date of September 15, 2013, as subject to extension based upon the
    occurrence of Unavoidable Delay, as defined in the agreements. See Trial Tr. Day 6 AM at
    79:17–81:9. The dubiousness of his view notwithstanding, Siegel never proposed such a
    revision to the University.
    The evidence shows that the Developer did not want the deal agreed to in the underlying
    agreements or the Term Sheet. Yet, the Developer plainly wanted a deal with the University. 21
    21
    The deal desired by the Developer—namely, to avoid putting at risk any further funds, including the second
    rental payment, until financing for the entire project was secured—may be most readily apparent in its proposal to
    the University the day following its receipt of the June 3, 2013, notice of default. In an email, the Developer
    proposed several new conditions on the second rental payment, including return to the Developer should the
    90
    In that regard, this case is different from cases involving bad faith in which the bad faith is
    deployed in hopes of ending the relationship between the parties because, for example, a better
    deal could be found elsewhere. See, e.g., Stanford Hotels Corp. v. Potomac Creek Assocs., L.P.,
    
    18 A.3d 725
    , 731, 736 (D.C. 2011) (upholding trial court’s determination that party acted in bad
    faith where “the parties did, in fact, come to agreement on all . . . terms” of the contemplated
    final agreement and, thus, it would have been signed “but for [the breaching party’s] bad faith
    refusal to do so once” a “more advantageous alternative” became available). Far from trying to
    extricate itself from the deal to develop the Property, the Developer’s apparent aim was to make
    it difficult for the University to walk away, such that the University would submit to the
    Developer’s desired terms notwithstanding prior signed agreements prescribing terms more
    favorable to the University.
    The Developer miscalculated here, since the University did not fold in the face of the
    Developer’s bullying threats of litigation and “non-negotiable” demands. Nevertheless, the
    Developer did succeed in delaying execution of the second amendment agreements, which under
    the Term Sheet would have triggered the payment and construction obligations the Developer
    sought to avoid until financing was secured. By failing to abide by even the simplest terms in
    the Term Sheet, such as making the $100,000 payment, and proposing terms to make the
    Developer’s performance contingent on securing financing, the Developer exploited the
    flexibility agreed to by the University in the Term Sheet to the Developer’s singular advantage.
    As the party owing money, the Developer wielded a modicum of power over the
    University in these negotiations. With respect to the rental payment, the University faced three
    possible courses of action: (1) pursue voluntary collection of the payment from the Developer;
    Developer decide, within six months, to “walk away” from the property. Joint Ex. 63, Emails Between Alan
    Brangman and Eric Siegel, dated June 4, 5, 2013, at 2.
    91
    (2) institute a legal action to recover the payment; or (3) forfeit the payment. Having just
    negotiated the Term Sheet, the Developer could have reasonably assumed that the University
    favored the first course of action. Indeed, the Developer knew, and the University likely
    surmised, that a lawsuit against the Developer would have been an exercise in futility, given that
    the Developer’s status as an LLC holding no funds to satisfy its $1,475,000 obligation to the
    University rendered it practically judgment-proof. 22 Accordingly, the Developer was in a
    position to “hold up” the University by refusing to make the payment except on its own terms.
    This “hold up” approach is traceable through the entirety of the Developer’s dealings
    with the University, both before and after the Term Sheet. Given the reflected intent of the
    parties to reset their relationship by executing the Term Sheet, the parties’ actions prior to the
    execution of that document, without more, are not a basis to excuse performance under the Term
    Sheet. Nevertheless, the Developer’s prior behavior provides useful context, shedding light on
    the Developer’s overarching strategy and the reasons for the University’s response.
    The primary tactic used by the Developer prior to the Term Sheet’s execution was
    threatening litigation against the University in the event that the University terminated the
    agreements, aware that the Developer’s inadequate capitalization put the University in a position
    of having, as far as the rental payment is concerned, nothing to gain and further delay to incur if
    litigation ensued.
    22
    The Developer’s status as an inadequately capitalized shell company is an ongoing demonstration of bad
    faith. LLCs are a legitimate corporate form, and the societal benefits of such entities are significant. Dickson
    testified that the use of such entities in transactions like this one is “typical[],” explaining that “single-asset entities
    are established as borrowers” so that “the borrower[] contains one asset,” the advantage from a “liability standpoint”
    being that “on a transaction of this size, the asset couldn’t be pulled into bankruptcy.” Trial Tr. Day 7 AM at 49:25–
    50:7. Yet, even a single-asset entity must be capitalized to the extent necessary to satisfy its obligations to the
    project it was created to support. See Lawlor v. District of Columbia, 
    758 A.2d 964
    , 975 (D.C. 2000) (noting
    inadequate capitalization as factor in determining whether a given entity’s corporate form should be respected).
    Consequently, abuse of the corporate form to render a company judgment-proof is impermissible and reflects bad
    faith.
    92
    The Developer first alluded to litigation at least as early as February 2011, in response to
    the University’s letter pointing out the Developer’s failure to meet the construction deadlines
    contained in the Declaration of Covenants. See Joint Ex. 8, Letter from Developer to Troy
    Stovall, dated Feb. 1, 2011, at 1. After asserting “that neither the District nor the University set
    forth realistic deadlines three years earlier,” accusing the University of improperly intervening in
    the Developer’s communications with the District, and requesting modifications to the project
    plans at considerable expense to the University, the Developer stated its assumption “that this
    venture is heading toward litigation” and averred that the Developer was “prepared to vigorously
    defend [its] actions and efforts to date.” 
    Id. Later that
    year, in response to a letter from the
    University requesting assurances from the Developer that it would perform pursuant to the
    parties’ first modification to the underlying agreements by, inter alia, tendering the $1,475,000
    payment on December 8, 2011, the Developer declined to give assurances, instead reciting the
    Developer’s version of events and advising the University to “[c]onduct [it]sel[f] accordingly.”
    Joint Ex. 12, Letter from Developer to Troy Stovall, dated Sept. 15, 2011, at 1–7.
    Likewise, in response to the University’s February 3, 2012 notice, the Developer sent a
    letter advising that the University is “on notice that it should take all necessary steps to preserve
    the written and electronic records associated with the Howard University Town Center project”
    and that “[f]ailure to preserve such documents shall subject the University to a claim for
    spoliation of evidence in the District of Columbia, in addition to legal pursuit of any other rights
    and remedies the Developer may have against the University,” and repeated the threat, “Conduct
    yourselves accordingly.” Def.’s Ex. 36, Email from Eric Siegel to Robert Tarola, cc: Dr. Hassan
    Minor, Michael Hollander, Timothy Kissler, and mvahey@dccouncil.us, attaching Letter from
    Developer to Robert Tarola, dated Feb. 7, 2012, at 2–3. At trial, Siegel testified that he “didn’t
    93
    perceive [the February 7 letter] as a threat” while acknowledging that he was “indicating . . . we
    may have a dispute here that’s going to rise to the level of litigation.” Trial Tr. Day 4 PM at
    43:2–44:2. The Developer’s characterization is nothing more than a distinction without a
    difference, and its practice of raising the specter of litigation against the University, with the
    concomitant threatened delays in developing the project, in response to valid demands of the
    University for the Developer’s performance, evidences bad faith. 23
    Another, similar, tactic used by the Developer in furtherance of its “hold up” strategy was
    to hint that it would cause the Property to lie dormant, rather than walk away from the Property
    and enabling the University to find a new Developer, if the University did not agree to the
    Developer’s proposals. After the University acquiesced to the Developer’s request for an
    extension of the second rental payment deadline to December 8, 2011, but three months before
    that deadline came to pass, the Developer requested further modification of the deal, warning the
    University that “[o]therwise,” the parties would “find [them]selves mired in dispute, and the
    project will remain dormant for the foreseeable future.” Joint Ex. 12, Letter from Developer to
    Troy Stovall, dated Sept. 15, 2011, at 7. The Developer also highlighted the monetary costs to
    the University of not acceding to the Developer’s demands, opining that “the University has
    foregone approximately $1,000,000 in potential lease revenue upon delivery of this project by
    failing in a timely manner to come to terms with the economic realities of the environment we
    currently operate in and by modifying ground lease terms accordingly so that we can break
    ground expeditiously.” 
    Id. These observations
    by the Developer were designed to bully the
    University into compliance with the Developer’s proposed contract terms, even though those
    23
    In his testimony at trial, Cohen manifested a callous indifference to the University’s concerns about the
    Developer’s failure to fulfill its obligations to the project, despite the obvious importance of that project to the
    University and surrounding community. See Trial Tr. Day 2 AM at 112:6–22 (Cohen) (describing the University’s
    notices of default as “posturing” not warranting payment of the funds due).
    94
    terms were either contrary to, or not covered in, any governing document, another sign of bad
    faith.
    A third tactic in furtherance of its “hold up” strategy, and one particularly pointed at
    teeing up litigation, was the Developer’s practice of blaming delays on the University, in writing,
    rather than acknowledging the Developer’s own failure to perform as required by the operative
    agreements. As noted, the bargain struck by the University and the Developer clearly provided
    for the Developer’s making the $1,475,000 payment with or without settlement on a construction
    loan. See Ground Lease at 2, 5. It also specifically defined a category of events constituting
    “Unavoidable Delays” that would extend the project deadlines, which category expressly
    excluded delay due to lack of financing. See Development Agreement at 7. Notwithstanding
    these provisions, the Developer sought modification of its original bargain with the University
    after losing the HUD funding, including extension of its deadline to make the $1,475,000
    payment to December 8, 2011. The Developer deployed a myriad of questionable, if not
    spurious, justifications for the modification, including that (1) the project deadlines were “not
    realistic” to begin with, despite executing the agreements incorporating those deadlines; (2) the
    time it took for the University and its consultant to developer an environmental remediation plan;
    and (3) the University’s action in sharing certain environmental documentation with a
    governmental entity, which action was permitted by the applicable agreement and the University
    believed was required by law. See Pl.’s Ex. 72, Letter from Ronald Cohen to Diane Branch,
    dated Dec. 2, 2010, at 2–3; Pl.’s Ex. 46, Letter from Troy Stovall to Ronald Cohen, dated Dec. 9,
    2010, at 1–2. The evidence, however, shows that the actual reason for the Developer’s
    modification request to delay the second rental payment was, at bottom, its inability to secure
    financing, see Trial Tr. Day 3 AM, 127:18–128:17 (Siegel) (testifying that in December 2010,
    95
    the Developer met with the University, apprised it of the unavailability of HUD financing, and
    raised the “difficulty in getting conventional financing for an entire city block project and the
    need to potentially phase the project if [the Developer] could not secure financing for an entire
    city block”); Trial Tr. Day 3 PM at 9:7–20 (Siegel) (testifying that in April 2011, the Developer
    was not ready to request formal modification by the District of the project deadlines because,
    notwithstanding the University’s rejection of a two-phase project proposal, the Developer still
    hoped to build the project in two phases).
    A party to a contract doubtless may uphold its obligation to act in good faith while
    simultaneously requesting modification of an agreement. Nevertheless, the Developer’s actions
    in (1) threatening litigation outright; (2) threatening to cause the Property to “remain dormant,”
    whether because of litigation or merely through delay on the Developer’s part, if the University
    did not accede to the Developer’s demands for modification; and (3) casting aspersions on the
    University to obscure the reason for its requested modification, i.e., an inability to obtain
    financing—which inability was specifically contemplated by the governing agreements and
    rejected as a reason for the delay sought by the Developer—cross the line between hard
    bargaining and bad faith.
    Viewed in the context of the Developer’s prior behavior, the Developer’s failure to abide
    by the Term Sheet is, unfortunately, unsurprising, and merely reflects more of the same. Equally
    unsurprising, the Developer continued to pursue its strategy of bullying the University into
    maintaining a relationship with the Developer, notwithstanding its defaults, after it breached the
    Term Sheet.
    The Developer adhered to its “hold up” strategy. In November 2012, while still pursuing
    financing, the Developer took the unusual step of undertaking to begin demolition on the
    96
    Property, even though the Developer was unwilling to enter into an agreement acceptable to the
    University or honor its existing commitments to the University, including making the $1,475,000
    payment. Jenkins testified that it would have been unusual for the Developer to begin demolition
    without a “deal” between the parties or financing. Trial Tr. Day 7 AM at 12:20–13:3. No
    special expertise in real estate development is required to see that allowing one party to begin
    work on a project absent a final agreement memorializing the parties’ respective obligations
    would make it more difficult for the other party to extricate itself from the relationship, even if
    legally entitled to do so. See 
    id. at 13:4–7
    (Jenkins) (“Q: . . . If the Developer had begun
    demolition without an agreement, did you feel that would put the University in a less
    advantageous position? A: Yes.”). The Developer also continued to threaten litigation. Just two
    days before the May 30, 2013, deadline for making the second rental payment, the Developer
    emailed the University to inform it that it would not make the rental payment but even so,
    “[s]hould Howard University determine that it is not advisable to continue working with the
    Developer,” the Developer would nevertheless “hold firm to this property.” Def.’s Ex. 116,
    Email from Eric Siegel to Alan Brangman, Robert Tarola, and Norman Jenkins, cc: Alan Cohen,
    Ron Cohen, and Tim Kissler, dated May 28, 2013, attaching Letter from Developer to Alan
    Brangman, dated May 23, 2013, at 3.
    In addition, the Developer continued to abuse its bargaining power, representing that it
    would show no flexibility regarding terms while refusing to walk away from the project. For
    example, the Developer asserted in March and April 2013 that its proposals were “non-
    negotiable,” Joint Ex. 57, Email from Eric Siegel to David Gifford, dated Apr. 1, 2013, at 1, later
    informing the University that while it would not make the payment required by May 30, 2013, it
    was “too invested to walk away,” Def.’s Ex. 116, Email from Eric Siegel to Alan Brangman,
    97
    Robert Tarola, and Norman Jenkins, cc: Alan Cohen, Ron Cohen, and Tim Kissler, dated May
    28, 2013, attaching Letter from Developer to Alan Brangman, dated May 23, 2013, at 3.
    Even after receiving the June 3, 2013, notice of default, the Developer clung to its “my
    way or no way” approach. The Developer’s action in signing versions of the second amendment
    documents, albeit not ones conforming to the reasonable expectation of the University,
    demonstrates its willingness to bully the University to the point of termination before acceding to
    any of the University’s terms, however reasonable those terms, or even if required by existing
    agreements. The Developer’s persistence in avoiding putting its funds at risk, even in the face of
    a court order, was on display when the Developer evaded this Court’s December 19, 2013,
    judgment in favor of the University by removing from the Closeline account the $1,475,000
    payment owed to the University. 
    See supra
    Part II.Q.
    The Developer’s bad faith is also apparent in its dealings with entities other than the
    University. The Developer proposed to DCPL an unreasonably limited preservation of the
    historic structures on the Property, including demolition of the WRECO garage, which had been
    marked for preservation pursuant to the DUKE Plan since before the Developer became involved
    with the Property. See Def.’s Ex. 114, Emails Between Eric Siegel and Rebecca Miller, dated
    May 3, 2013, at 1. When that proposal was rejected, the Developer made the self-serving
    assertion that it “approached these recently-file[d] applications with a sincere attempt to arrive at
    an appropriate architectural solution” and, in what amounts to a thinly veiled attempt to shift
    blame to DCPL, noted its view that “[it] is a shame that this project may die if the financing goes
    away at this late hour.” 
    Id. 24 24
            The instant litigation aside, the Cohen Companies have been found to act in bad faith in litigation brought
    by other parties who have attempted business dealings with the limited liability entities they operate. The Cohen
    Companies’ actions are well documented in decisions of both state and federal courts in Maryland, its primary place
    of business. For example, in January 2014, a jury found another Cohen Companies’ affiliate liable for breach of
    98
    Accordingly, the Court finds the Developer acted in bad faith in its negotiations pursuant
    to the Term Sheet, a finding bolstered by the Developer’s conduct throughout its involvement in
    the Howard Town Center development project.
    D.        THE DEVELOPER’S BAD FAITH CONSTITUTED A MATERIAL
    BREACH OF THE TERM SHEET, REINSTATING THE UNIVERSITY’S
    NOTICES OF DEFAULT AND RELEASING THE UNIVERSITY FROM
    ITS OBLIGATION TO NEGOTIATE PURSUANT TO THE TERM
    SHEET
    Having concluded that the Developer acted in bad faith in negotiating with the University
    in April and May 2012, the effect of that bad faith on the obligations and rights of the parties
    must be assessed.
    First, it must be determined whether the Developer’s failure to negotiate in good faith
    constitutes a material breach of the Term Sheet. If so, the University’s obligations under the
    Term Sheet would be discharged. See Ashcraft & Gerel v. Coady, 
    244 F.3d 948
    , 950 (D.C. Cir.
    contract and tortious interference with contractual relations, i.e., that its conduct forced the other party into litigation
    with a third party, warranting an award of punitive damages. 121 Assocs. Ltd. P’ship v. Tower Oaks Boulevard,
    LLC, No. 0906 Sept. Term 2014, 
    2015 WL 7076013
    , at *1 (Md. Ct. Spec. App. Nov. 12, 2015), cert. denied sub
    nom. Tower Oaks Blvd. v. Ronald Cohen Invs., 
    136 A.3d 818
    (Md. 2016). Finding that the Cohen Companies’
    affiliate had no assets as a result of its principals’ bad faith efforts to evade judgment, the trial judge permitted
    garnishment of other Cohen-related assets to satisfy the judgment. 
    Id. at *7
    (finding Cohen’s “hand off” of funds
    from the liable entity to another Cohen-related entity, PMAS—the same entity into which the Developer transferred
    the funds from Closeline upon the issuance of the writ of attachment of those funds by this Court, 
    see supra
    note
    20—“was a sham simply to avoid the coming judgments”).
    While the appellate court reversed the jury’s verdict on the tortious interference claim, finding the evidence
    insufficient, it affirmed the breach of contract claim. Moreover, while the appellate court disallowed garnishment of
    the targeted Cohen-related assets, noting the appellees had never named those assets as parties and could not
    “transform the proceeding into a direct cause of action” against them, the appellate court also opined that the
    appellees “may have had a valid claim against” the Cohen-related assets had they instituted an action against them.
    Id.at *13. Notably, none of the appellate court’s holdings disturb the trial court’s findings that, inter alia, (1) in
    structuring his companies, Cohen “elected to move the pieces around the board . . . to stiff the plaintiffs and not pay
    them”; (2) the Cohen Companies’ behavior “is beyond sharp elbowed business practices” but rather “borders on
    unlawful,” apparently meaning criminal; and (3) “the level of absolute ability to manipulate and to run the levers of
    power go beyond frankly anything that [the Judge had] seen in the civil courtroom in a long time.” Memorandum of
    Decision at 9, In re Ronald Cohen Mgmt. Co., Ch. 11 Case No. 14-23399, (Bankr. Md. Feb. 6, 2015), ECF No. 69
    (quoting Mot. Hearing Tr., Tower Oaks Boulevard, LLC., et al. v. CW Capital LLC et al., Case No. 368256, Aug.
    19, 2014). These “detailed findings” were deemed persuasive by the U.S. Bankruptcy Court considering a Cohen
    Companies’ affiliate’s petition for bankruptcy, leading that Court to “the conclusion that the Debtor and its
    principal[, Ronald Cohen,] are acting in bad faith” and “filed this case with [a] bad faith motive,” supporting its
    decision to dismiss the petition outright for bad faith filing. 
    Id. at 8,
    10.
    99
    2001) (“[A] party’s continuing obligations under a contract are conditioned on there being no
    ‘uncured material failure by the other party to render any such performance due at an earlier
    time.’” (quoting Restatement (Second) of Contracts § 237)); Kriesch v. Vilsack, 
    931 F. Supp. 2d 238
    , 253 (D.D.C. 2013) (where a party breaches an agreement intended to resolve an earlier
    breach, “only a material breach would permit rescission of the Settlement Agreement and
    reinstatement of [the non-breaching party’s] claims” (internal quotation marks omitted)). While
    neither party addresses the question whether such breach is material, the Developer emphasizes
    its “partial performance” under the Term Sheet, noting that “the Term Sheet . . . created new
    obligations, beyond simply an obligation to negotiate,” and that the Developer “released for the
    University’s immediate use, and the University accepted, the balance of the $525,000 payment
    that otherwise would have remained in escrow” and “took other actions and spent considerable
    sums in reliance on the parties’ agreement to move forward.” Pl.’s Prop. Findings Fact Concls.
    Law ¶¶ 399–400.
    Under District of Columbia law, the following factors are significant in determining
    whether a breach is material:
    a) the extent to which the injured party will be deprived of the benefit which he
    reasonably expected; (b) the extent to which the injured party can be adequately
    compensated for the part of that benefit of which he will be deprived; (c) the
    extent to which the party failing to perform or to offer to perform will suffer
    forfeiture; (d) the likelihood that the party failing to perform or to offer to perform
    will cure his failure, taking account of all the circumstances including any
    reasonable assurances; (e) the extent to which the behavior of the party failing to
    perform or to offer to perform comports with standards of good faith and fair
    dealing.
    Greyhound Lines, Inc. v. Bender, 
    595 F. Supp. 1209
    , 1224 (D.D.C. 1984) (quoting Restatement
    (Second) of Contracts § 241 (1981)) (applying District of Columbia law). In addition, “[t]he
    earlier the breach the more likely it will be regarded as material”; “[a] willful breach is more
    100
    likely to be regarded as material than a breach caused by negligence or by extraneous
    circumstances”; and “[a] quantitatively serious breach is more likely to be considered material.”
    
    Id. (quoting J.
    Calamari & J. Perillo, Contracts §§ 11–22 (2d ed. 1977)).
    Consideration of these factors leads inescapably to the conclusion that Developer’s
    breach of its obligation to negotiate in good faith toward amendments to the Ground Lease and
    Development Agreement easily qualifies as a material breach of that agreement. Bad faith was
    evident a mere ten days following execution of the Term Sheet, when the Developer willfully
    declined to make the $100,000 payment required, and again eleven days after that in the
    Developer’s first proposal for amendments to the Ground Lease and Development Agreement.
    The Developer’s bad faith completely deprived the University of the speedy, good faith
    negotiation of amendments to the Ground Lease and Development Agreement contemplated by
    the Term Sheet, not to mention payments owed the University as part of the “cure of the
    monetary default” provided for in the Term Sheet. Term Sheet at 1. Moreover, the Developer’s
    bad faith by definition fails to comport with standards of good faith and fair dealing.
    Consequently, the Developer’s bad faith constitutes a material breach of the Term Sheet.
    As a result of the Developer’s material breach of the Term Sheet, the University’s
    obligations under the Term Sheet are discharged, notwithstanding the Developer’s partial
    performance by acting to terminate the escrow account and release the funds therein to the
    University. Nonetheless, the Developer emphasizes the Term Sheet’s declaration that the “letters
    entitled ‘Notice of Default and Notice of Intent to Terminate,’ dated February 3, 2012, and again
    on March 6, 2012 are hereby withdrawn,” Pl.’s Prop. Findings Fact Concls. Law ¶ 143 (quoting
    Term Sheet at 1) (emphasis added by Developer), urging that this pronouncement of an abstract
    “withdrawal” constitutes an irrevocable erasure of the Developer’s myriad defaults and the
    101
    notice duly given of them, see 
    id. ¶ 401.
    These two words, “hereby withdrawn,” are a thin reed
    to support the outcome urged by the Developer in light of other language in the Term Sheet and
    extrinsic evidence contravening its position. The parties’ clear purpose behind including that
    language in the Term Sheet was to acknowledge that the University would waive the
    Developer’s defaults and the accompanying notices thereof in exchange for—i.e., contingent
    on—the Developer’s “cur[ing] of the monetary default” by payment of the overdue rent, as well
    as the signing of amendments to the underlying project documents. Term Sheet at 1. Since the
    Developer was in material breach of its obligations under the Term Sheet, the University was
    under no continuing obligation to deem the Developer’s defaults waived. Accordingly,
    following the Developer’s material breach of the Term Sheet, the Developer was returned to a
    status of actionable default under the project documents for, inter alia, its failure to make the
    $1,475,000 rental payment as required.
    This understanding of the effect of the Developer’s breach is prescribed by a recent
    decision of the D.C. Court of Appeals. In District of Columbia v. Young, that court explained
    that “[w]here . . . a settlement agreement provides for future payments in satisfaction of a claim,
    there is no accord and satisfaction until all the payments have been made,” explaining that until
    that point, “the agreement is a mere executory accord” such that “if the debtor breaches the
    executory accord by failing to make all the payments due, his part performance does not preclude
    the creditor from resurrecting the original claim that was to have been extinguished by the
    settlement.” 
    39 A.3d 36
    , 40 (D.C. 2012) (internal quotation marks omitted). Given the Term
    Sheet’s intent to cure the Developer’s monetary default, that agreement is comparable to an
    “accord and satisfaction,” for which failure to satisfy all the required conditions, notwithstanding
    partial performance, “resurrect[s] the original claim that was to have been extinguished.” 
    Id. As 102
    there, the Developer’s material breach of the Term Sheet reinstated the University’s claims
    against the Developer intended to be “cure[d]” by the Term Sheet.
    Another result of the Developer’s material breach of the Term Sheet is that the University
    was no longer bound to negotiate pursuant to the Term Sheet and in accordance with its terms.
    That is, unlike a party to a unbreached preliminary agreement to negotiate in good faith, the
    University was entitled to “insist[] on conditions that do not conform to the preliminary
    agreement.” Banneker 
    Ventures, 798 F.3d at 1131
    . Consequently, the Developer’s contention,
    even assumed to be true, that the University’s proposals in January and February 2013 contained
    “provisions unfavorable to Developer and not contemplated by the Term Sheet,” and that those
    proposals reflect bad faith, is unavailing. Pl.’s Prop. Findings Fact Concls. Law ¶ 426. Given
    the Developer’s material breach of the Term Sheet in April 2012, the University was not bound
    to negotiate pursuant to that agreement. Likewise, the Developer’s arguments that the University
    displayed bad faith by (1) placing Brangman, who had “no involvement in the Term Sheet,” in
    charge of negotiations, even though Tarola was available, and (2) designating Schmoke “the
    final-decisionmaker with respect to the June 3, 2013 notice,” since he “testified that he was not
    even aware of the Term Sheet,” also fail. 
    Id. ¶ 429
    (emphasis in original). In light of the
    irrelevance of the Term Sheet after the Developer’s rapid material breach of that agreement, the
    University did not “disregard . . . the parties’ contractual obligations in the course of ongoing
    negotiations” by reassigning responsibility for the project. 
    Id. ¶ 430.
    To the contrary, the
    University’s decision to do so makes good business sense in view of Tarola’s complete failure to
    secure good faith performance from the Developer even after extended negotiations and
    concessions on the part of the University.
    103
    Also unavailing is the Developer’s contention that the University demonstrated “bad faith
    behavior” through “its abrupt cancellation . . . of the planned meeting with the Developer in late
    January 2013 to meet face-to-face and bring resolution to the negotiation of the Second
    Amendment documents.” 
    Id. ¶ 431.
    As explained, following the Developer’s breach of the
    Term Sheet, the University was no longer bound by the Term Sheet to execute amendment
    documents. In addition, the evidence shows that the meeting had been scheduled on almost as
    short notice as it was canceled, and that the University instead met internally to discuss a way
    forward with the Developer, notwithstanding the latter’s multiple breaches and bad faith. See
    Joint Ex. 39, Emails Between Eric Siegel and Robert Tarola, cc: Odessa Jackson, Norman
    Jenkins, and Kurt Schmoke, dated Jan. 28, 2013, at 1; Joint Ex. 40, Emails Between Kurt
    Schmoke and Eric Siegel, dated Feb. 1, 2013, at 2. Consequently, none of the Developer’s
    arguments accusing the University of bad faith is supported by the evidence.
    E.      THE UNIVERSITY’S TERMINATION OF THE GROUND LEASE AND
    DEVELOPMENT AGREEMENT WAS PROPER
    The appropriateness of the University’s termination of the Developer in June 2013 is now
    addressed.
    The University did not immediately pursue its entitlement, in view of the Developer’s
    ongoing failure to cure its defaults, to terminate the Ground Lease and Development Agreement.
    Rather, while declining to accept the Developer’s proposals making much of its performance
    under the agreements contingent on the obtaining of financing, the University opted to give the
    Developer additional time to secure financing. See Trial Tr. Day 3 PM at 60:9–25 (Siegel)
    (testifying he “was instructed by Robert Tarola to give regular updates on where we were with
    the financing, which we did” and expressing his view that “the university, Norman Jenkins, was
    very generous [in] putting us in touch with potential financing sources”); see also Pl.’s Ex. 161,
    104
    Confidential Letter from Robert Tarola to Members of the Finance and Executive Committees,
    dated July 31, 2012, at 4 (“We have introduced the developer to two interested investors/lenders
    and are in regular contact about financing progress.”). By doing so, the University exercised its
    prerogative to, effectively, extend the period in which the Developer would have been able to
    cure its defaults, including the failure to make the $1,475,000 rental payment. At that time, the
    University officials involved in the project believed that if the Developer obtained financing, the
    Developer would honor its other commitments to the University. See Trial Tr. Day 6 AM at
    122:9–20 (Schmoke) (testifying he viewed financing as “the number one issue” for the
    Developer and believed if financing was secured, “everything else would fall into place”); Trial
    Tr. Day 7 AM at 23:17–24; 24:14–24 (Jenkins) (acknowledging that “financing was a challenge”
    for the Developer and that he recommended the University be “flexible” with respect to the dates
    for performance while the Developer sought financing); see also Def.’s Ex. 61, Emails Between
    Eric Siegel and Robert Tarola, dated Sept. 24, 2012 (Siegel stating “we are busily working
    toward completion of the capital stack so that we can honor o[u]r commitments”). 25
    Throughout the course of its dealings with the Developer, however, the University never
    agreed to condition the Developer’s performance on its obtaining financing, repeatedly
    emphasizing that, by continuing a working relationship with the Developer, it was “not waiving
    any defaults on the part of the Developer.” Joint Ex. 31, Letter from Robert Tarola to Developer,
    25
    Paradoxically, the Developer’s unwillingness to execute second amendment agreements without
    conditioning its rental payment obligations on secured financing likely made more difficult its pursuit of financing.
    Vasques testified that without an agreement setting forth firm deadlines, Citi Community Capital would not close on
    financing with the Developer. See Trial Tr. Day 6 PM at 24:6–11 (“Q: Based on your experience as a finance
    broker, if the operative documents setting forth the construction commencement date and the end of the construction
    completion date were not yet signed between the developer and the land owner under a ground lease, would Citi
    close a loan? A: No.”). Thus, the Developer’s representation to the University that the “University’s formal request
    to the District via Andre Byers to revise [the Covenant] dates is all [the Developer] need[s]” to get “the paperwork
    . . . in order for our lender and equity’s due diligence,” Joint Ex. 33, Emails Between Eric Siegel, Andre Byers,
    Robert Tarola, and Norman Jenkins, dated Dec. 10, 11, 18, 19, 2012, at 3, appears to be wishful thinking since the
    fully executed agreements were necessary to secure funding.
    105
    dated Dec. 11, 2012, at 1; see also Joint Ex. 17, Notice of Default and Notice of Intent to
    Terminate, dated Feb. 3, 2012, at 4 (providing “the University is not waiving any of the rights
    and remedies available to the University at law and in equity on account of the Developer’s
    failure to timely cure the Developer’s defaults” and “[n]o failure to exercise and no delay in
    exercising, on the part of the University, any right, remedy, power or privilege, shall operate as a
    waiver thereof”). The University’s refusal, in December 2012, to permit the Developer to begin
    demolition on the Property absent a “satisfactory resolution” to their dispute reflects its ongoing
    concern that the Developer be held to account for its defaults, notwithstanding the University’s
    generosity in assisting the Developer with various aspects of their efforts to move the project
    forward. Joint Ex. 31, Letter from Robert Tarola to Developer, dated Dec. 11, 2012, at 1–2;
    Joint Ex. 35, Letter from Robert Tarola to Developer, dated Dec. 27, 2012 (explaining
    “[a]lthough [the] continuing discussions have been productive, they have not yet yielded a
    complete settlement arrangement acceptable to Howard University,” and, consequently, the
    University “cannot at this time agree to the Developer’s possession of the Project property, or
    approve the commencement of any work (including demolition)”).
    The Developer asserts that “[t]he University lacked the right unilaterally to set the date
    for the $1.475 million payment under the Term Sheet” because “the University bargained away
    its rights to demand payment of $1.475 million as of pre-Term Sheet dates when it bound itself
    to the Term Sheet.” Pl.’s Prop. Findings Fact Concls. Law ¶ 450. Consequently, the Developer
    focuses its efforts on showing that “[t]here was never an agreement to make the payment on that
    date independent of executed Second Amendment documents.” 
    Id. ¶ 447.
    26 Yet, the
    26
    The Developer’s present efforts contradict its earlier representation that the parties agreed to the May 30,
    2013, deadline for the payment. 
    See supra
    note 16 (quoting the assertion in the Developer’s original Complaint that
    the parties “agreed that [the Developer] would not be obligated to tender the Payment called for under the
    Amendment until May 30, 2013,” Pl.’s Compl. ¶ 23).
    106
    Developer’s argument rests upon the premise that no material breach of the Term Sheet by the
    Developer had occurred at the time the University demanded payment. As explained above, that
    assumption is incorrect. Given the Developer’s breach of the Term Sheet, which was to cure its
    default under the Ground Lease and Development Agreement, the pertinent question is whether
    the University was entitled to set a deadline of May 30, 2013, for cure of the Developer’s default.
    While the Developer does not directly address the scenario in which it is found to have acted in
    bad faith, it suggests the University was required to obtain the Developer’s agreement to any
    such deadline, or wait indefinitely for the Developer to sign second amendments. See 
    id. ¶¶ 447–51.
    The law, in accordance with common sense, says otherwise.
    Case law from the District of Columbia discussing deadlines in land sale contracts offers
    clear instruction on this point. District of Columbia law recognizes that, in contracts requiring
    performance on a date certain, unless the contract provides that time is of the essence, failure by
    one party to comply precisely with a deadline will not necessarily excuse the other party’s
    performance. See Drazin v. American Oil Co., 
    395 A.2d 32
    , 34 (D.C. 1978) (quoting Soehnlein
    v. Pumphrey, 
    37 A.2d 843
    , 845 (Md. 1944) (“[E]quity treats [such deadlines] as formal rather
    than essential.”)). Yet, “time can become of the essence when not originally in the contract by a
    refusal of one party to grant a further extension after such extended date, or when one party
    serve(s) notice on the other fixing a reasonable time within which the deal must be closed.” 
    Id. (internal quotation
    marks and citations omitted). “Once time is unilaterally made of the essence
    by explicit notification of such intent to the other party, the notification must provide a
    reasonable time for that party to tender performance.” Id.; see also 3A Corbin, Contracts § 723,
    at 383 (1960) (“If a definite date for performance is specified in the agreement, but performance
    on time is not of the essence, either party has the power to make on that date or some subsequent
    107
    date, performance essential and a condition of his own duty by giving notice to that effect,
    provided that the notice leaves a reasonable time for rendering performance.”).
    In this case, the University in 2011 and 2012 provided multiple notices to the Developer
    that it would be or was in default by reason of missing the deadline for making the $1,475,000
    rental payment required by the Ground Lease to be paid no later than March 15, 2011, which due
    date was extended by agreement of the parties to December 8, 2011. While the operative
    agreements provided only a ten-day period in which the Developer could cure these defaults, the
    University extended the ten-day period by abstaining from further action to terminate the
    agreements. Yet, on February 1, 2013, by means of an email from Schmoke to the Developer,
    the University exercised its option to make time of the essence by unilaterally notifying the
    Developer that the default on the payment had to be cured by May 30, 2013. See Joint Ex. 40,
    Emails Between Kurt Schmoke and Eric Siegel, dated Feb. 1, 2013, at 2 (specifying that the
    “University will take no further action in support of the current developer” unless, inter alia, the
    $1,475,000 rental payment “has been made to Howard University by May 30, 2013”).
    The notice provided by the University was clear and provided a reasonable amount of
    time of four months for the Developer to cure. Under District of Columbia law, “[t]he specific
    words ‘of the essence’ or any like phrase, need not appear, but rather it is sufficient that the
    meaning behind those words becomes apparent to the other party.” See 
    Drazin, 395 A.2d at 35
    .
    Schmoke’s emails did not use the words “time is of the essence,” but advised the Developer of
    its obligation to cure its default by making the overdue payment on that date by providing that
    the “University will take no further action in support of the current developer” absent such
    payment. Joint Ex. 40, Emails Between Kurt Schmoke and Eric Siegel, dated Feb. 1, 2013, at 2.
    Moreover, nearly three months before the May 30, 2013, deadline for the second rental payment
    108
    of $1,475,000, on March 6, 2013, the University’s outside counsel followed up on Schmoke’s
    deadline and expressly advised the Developer that “time is of the essence for the payment of that
    sum.” Joint Ex. 48, Email from David Gifford to Eric Siegel, attaching (1) Second Amendment
    to Ground Lease and (2) Second Amendment to Development Agreement, dated Mar. 6, 2013, at
    1. Consequently, the notice provided by the University was sufficient, under District of
    Columbia law, to alert the Developer of the new deadline and that time was of the essence.
    In addition, the deadline set by the University provided a reasonable time for the
    Developer to cure its default: approximately four months. The new deadline must be considered
    not only reasonable, but downright solicitous of the Developer given that the Developer had
    represented that (1) its failure to make the payment was a result of its inability to obtain
    financing and (2) it would close on financing on May 30, 2013. See Joint Ex. 36, Emails
    Between Eric Siegel, Andre Byers, Robert Tarola, and Norman Jenkins, dated Dec. 10, 11, 18,
    27, 2012, Jan. 1, 2013, at 1 (Developer assuring the University that “the outside date to ‘true up’
    on the initial ground lease payment of $1.425 million [sic] would be May 30, 2013 (the date of
    closing on the financing with Citi Community Capital . . . )”). In view of the fact that lenders
    typically issue commitment letters locking in financing “a week or two away” from the closing
    date, the new deadline for the $1,475,000 set by the University reflects a good faith attempt by
    the University to give the Developer every advantage in curing its default. Trial Tr. Day 7 AM
    at 53:6–17 (Dickson).
    The Developer argues that even assuming the May 30, 2013, deadline was a valid one—it
    was, after all, the deadline the Developer’s original complaint in this case said was operative, see
    Pl.’s Compl. ¶ 23—the University was required to extend it in light of the historic designation
    applications filed in February 2013, which occurrence the Developer contends constitutes an
    109
    “Unavoidable Delay” extending the time for performance under the agreements. See Pl.’s Prop.
    Findings Fact Concls. Law ¶¶ 440–46. While doubtful that the historic designation applications
    amounted to an “Unavoidable Delay,” given, inter alia, the Developer’s awareness of the
    likelihood of the event occurring, see Def.’s Prop. Findings Fact Concls. Law ¶¶ 363–67, and
    unclear that the concept of Unavoidable Delay could be applied to an “existing breach” such as
    the already long overdue rental payment, see 
    id. ¶ 371,
    those questions need not be addressed
    because the Ground Lease does not recognize Unavoidable Delay as a reason to extend the
    $1,475,000 payment deadline, see 
    id. ¶¶ 368–70;
    see generally Ground Lease.
    Having concluded that the University was entitled unilaterally to set a deadline of May
    30, 2013, for the Developer to cure its monetary default, whether the notice provided in June
    2013 was adequate under the Ground Lease must be addressed. The D.C. Circuit set out its
    interpretation of the Ground Lease’s notice requirement in its decision in this case.
    Section 16.2 of the Ground Lease provides the University must send two notices
    to the Developer before it may terminate the lease. First, the University must
    issue a notice advising the Developer it is “in default with respect to” a rental
    payment. If the Developer does not cure the default within ten days, then the
    University may treat the default “as a breach of th[e] Lease” (i.e., an “Event of
    Default”). After an “Event of Default” occurs, the University may terminate the
    Ground Lease by issuing a second notice and waiting an additional ten days:
    [“][P]rior to exercising any right to terminate this Lease on account of any Event
    of Default, Landlord shall provide Tenant . . . with a written notice (in addition to
    any notice of default provided for in this Section 16.2 . . . ), specifying . . . that
    Landlord intends to terminate the Lease if the Event of Default is not cured within
    ten (10) days.[”]
    HTC 
    II, 788 F.3d at 328
    –29.
    Addressing the University’s argument that the Developer’s failure to pay $100,000 alone
    could form a basis for the University’s termination of the Ground Lease in June 2013, the D.C.
    Circuit concluded it could not. After outlining the above notice requirement, the D.C. Circuit
    concluded with respect to the Developer’s failure to pay the $100,000 that the University “did
    110
    not follow this two-step process when it purported to terminate the Ground Lease in June 2013”
    because it sent only “a combined ‘Notice of Default’ and ‘Notice of Intent to Terminate’ on June
    3 and then terminated the lease on June 14.” 
    Id. at 3
    29.
    The Developer urges that the same conclusion should be reached as to the $1,475,000
    payment, relying upon the D.C. Circuit’s description of the “notice regime” and application of
    that regime to the $100,000 payment, detailed above. Pl.’s Prop. Findings Fact Concls. Law
    ¶¶ 457–64. In doing so, the Developer treats the June 3, 2013 Notice of Default as the first
    notice of default as to the $1,475,000 payment, asserting no second notice was ever given and,
    thus, that no “failure to make a payment that continues for a period of ten (10) days after written
    notice from the University,” as required by the Ground Lease before termination, ever occurred.
    
    Id. ¶ 460.
    The Developer’s invocation of the D.C. Circuit decision vacating this Court’s prior
    judgment against it is misplaced, however, since the Developer’s application of that precedent to
    the issue at hand approaches the inane. The Developer’s argument hinges on the position that
    the June 3, 2013 notice of default was the first notice of the Developer’s default as to the
    $1,475,000. That position is unsupportable. As the Developer acknowledges, the University
    sent two notices of default in 2012. See 
    id. ¶ 439.
    27 While the Developer argues that both those
    notices were irrevocably withdrawn and their accompanying defaults waived by the Term Sheet,
    that argument has been rejected. 
    See supra
    Part III.D. Since the Developer breached the Term
    Sheet, the University was no longer required to deem the Developer’s defaults, and the notices
    accompanying them, waived or “withdrawn.” The Developer’s contrary position reflects an
    27
    The Developer also sent a notice of default in September 2011, but that notice did not include as an existing
    default the Developer’s failure to make the $1,475,000 rental payment, as the December 8, 2011, deadline, extended
    from March 15, 2011, at the Developer’s request, had not yet come to pass. See Joint Ex. 13, Notice of Default,
    dated Sept. 26, 2011, at 3–4 (asserting the Developer “is in anticipatory breach,” though not default, of its obligation
    to pay $1,475,000 by December 8, 2011).
    111
    unreasonable reading of the Term Sheet, which referred to the notices of default as “withdrawn”
    as a way of expressing, perhaps inartfully, waiver of those defaults in the case of complete cure
    by the defaulting party.
    The Developer’s interpretation would import to the two cherry-picked words “hereby
    withdrawn” a power to cause the notices to evaporate, regardless of whether the agreement in
    which they appear is honored. In other words, through the lens of the Developer’s alternate
    reality, the effect of the Term Sheet is that University would waive its notices of default, even if
    denied the benefit of the bargain for such waiver by the Developer’s bad faith failure to perform
    its obligations under the Term Sheet. As explained, this interpretation is simply incorrect.
    Assuming, however, that the Developer were correct, and the Term Sheet caused the
    February and March 2012 notices of default no longer to be effective for purposes of termination
    of the Ground Lease, even in the face of the Developer’s bad faith and material breach of the
    Term Sheet, its notice argument would nevertheless fail. District of Columbia law eschews
    overly formalistic application of notice requirements to prevent an injured party to a contract
    from extricating itself from that contract, so long as sufficient notice to the breaching party has
    been given. See, e.g., Sun Secured Financing LLC v. ARCS Commercial Mortg. Co., 730 F.
    Supp. 2d 132, 138 (D.D.C. 2010) (citing Mason v. Curro, 
    41 A.2d 164
    , 165 (D.C. 1945))
    (“District of Columbia courts have shown some willingness to excuse purely technical
    deficiencies in notice.”). Thus, even if the University did not technically comply with every
    requirement of the two-step notice regime, substantial compliance would nevertheless suffice. 28
    28
    The Developer appears to acknowledge that as long as the University substantially provided “two-step
    notice,” such that the Developer was given “two distinct notices and cure periods,” any technical deficiencies should
    be excused, arguing only that the University “fail[ed] to provide two-step notice” which, according to the Developer,
    is “not a ‘purely technical deficiency in notice,’ which courts have found occasion to excuse.” Pl.’s Prop. Findings
    Fact Concls. Law ¶ 463–64 (quoting Sun Secured 
    Financing, 730 F. Supp. 2d at 138
    ).
    112
    Here, the Developer was made aware numerous times after the signing of the Term Sheet
    that the University considered the Developer in default, and thus, that it was then occupying the
    first cure period contemplated by the Ground Lease’s notice requirement. See, e.g., Joint Ex. 31,
    Letter from Robert Tarola to Developer, dated Dec. 11, 2012, at 1; Def.’s Ex. 111, Letter from
    Alan Brangman to Ron Cohen, dated Apr. 16, 2013, at 2 (“[T]he University views [the
    Developer’s] upcoming payment as a commitment to continue with the redevelopment of the
    property and more importantly as a cure for the fact that a default condition currently exists with
    respect to the project.”). Notice of this need to cure was unequivocally given on February 1,
    2013, when the University informed the Developer of the May 30, 2013, deadline for the second
    rental payment. See Joint Ex. 40, Emails Between Kurt Schmoke and Eric Siegel, dated Feb. 1,
    2013, at 1. These numerous notices were more than sufficient to alert the Developer to its
    precarious position of needing to cure its default or be subject to one final “Notice of Default and
    Notice of Intent to Terminate” and ten-day cure period before termination. 29
    29
    The multiple formal, written communications putting the Developer on notice of its ongoing status of
    default and impending final opportunity to cure leave no doubt as to the lack of viability of the Developer’s notice
    argument. Even considering a scenario in which the notice given by the University did not substantially comply
    with the “two-step process” described by the D.C. Circuit, however, the Developer has not shown an entitlement to
    the relief it seeks on that ground. District of Columbia law recognizes that a contract’s notice requirements may
    “merely impose[] a duty,” as opposed to a “condition precedent” to termination, such that an “alleged failure to
    comply at most entitles the plaintiffs to recover damages for the lack of notice.” Sun Secured Financing, 730 F.
    Supp. 2d at 139. In other words, a termination without required notice may nevertheless be effective. Under
    District of Columbia law, “there is a presumption in favor of construing doubtful language in a contract as language
    of promise rather than as language of condition,” which presumption avoids “the consequence that a slight failure to
    perform wholly destroys all rights under the contract.” Wash. Props., Inc. v. Chin, Inc., 
    760 A.2d 546
    , 549 (D.C.
    2000) (citing New York Bronze Powder Co. v. Benjamin Acquisition Corp., 
    716 A.2d 230
    , 234 (Md. 1998);
    Williston on Contracts § 38.13 (4th ed. 2000)). “[T]he question of whether a provision in a contract constitutes a
    condition precedent is one of construction dependent on the intent of the parties as revealed by the contract itself
    and, if necessary, by extrinsic evidence.” Sun Secured 
    Financing, 730 F. Supp. 2d at 139
    (quoting Wash. Props.,
    
    Inc., 760 A.2d at 550
    ). One consideration courts take into account when deciding whether to construe a provision of
    a contract as a condition precedent is whether doing so would further “fairness and justice.” Wash. Props., 
    Inc., 760 A.2d at 550
    (citing Calamari & Perillo, The Law of Contracts § 11.8 (4th ed. 1998); Catherine M.A. McCauliff,
    Corbin on Contracts § 32.1 (1999)). For the reasons enumerated and expounded upon at length in this opinion,
    fairness and justice would not be served by treating the purported non-compliance on the part of the University with
    the Ground Lease’s notice requirements, which the Developer acknowledges were “detailed,” Pl.’s Prop. Findings
    Fact Concls. Law ¶ 464, as a condition precedent warranting voiding of its termination of the Developer.
    113
    Consequently, the Developer had been in the first “cure” period required by the Ground
    Lease for many months by the time the June 3, 2013, notice was sent, which notice triggered the
    second cure period of ten days. The University appeared to understand the June 3, 2013, notice
    as the penultimate notice of default required, titling the notice a “Notice of Default and Notice of
    Intent to Terminate,” Joint Ex. 61, Notice of Default and Notice of Intent to Terminate, dated
    June 3, 2013, rather than simply a “Notice of Default,” as it had entitled its very first notice of
    default in September 2011, Joint Ex. 13, Notice of Default, dated Sept. 26, 2011, at 1, and
    referring to the failure to make the $1,475,000 payment as an “EVENT OF DEFAULT,” as
    would be appropriate only in a second notice of default, according to the D.C. Circuit’s
    description of the Ground Lease’s notice regime, Joint Ex. 61, Notice of Default and Notice of
    Intent to Terminate, dated June 3, 2013, at 2 (emphasis omitted). 30 The University waited the
    requisite ten days before terminating the Ground Lease and Development Agreement. See Joint
    Ex. 66, Notice of Election to Terminate Ground Lease, dated June 14, 2013; Joint Ex. 67, Notice
    of Termination of Development Agreement and Supplemental Development Agreement, dated
    June 17, 2013. Accordingly, the University’s termination complied with the requirements of the
    operative agreements and is, thus, unquestionably valid. 31
    30
    The Developer cites the June 3, 2013, notice’s statement that the December 8, 2011, “due date” for the
    rental payment “was extended by the University through May 30, 2013,” as support for its argument that the
    University “did not claim that there existed an ‘Event of Default’ under the Ground Lease” as of May 30, 2013.
    Pl.’s Def.’s Prop. Findings Fact Concls. Law ¶ 460. The Developer’s knack for cherry picking two-word phrases to
    support the Developer’s position when construed in utter isolation, in contravention of overwhelming evidence
    supporting the University’s position, as the Developer did with its focus on the word “withdrawn” in the Term
    Sheet, again gets the Developer nowhere, given other language in the very same notice, discussed above, including
    the language cited in the text informing the Developer verbatim of an “Event of Default,” the prior notices of
    default, and the University’s repeated warnings to the Developer that the Developer remained in default and thus
    within a cure period extended only at the University’s pleasure.
    31
    The University suggests that the D.C. Circuit’s interpretation of the Ground Lease’s notice requirement is
    incorrect, asserting that the second notice of default applies only in the event of a “leasehold mortgagee.” Def.’s
    Prop. Findings Fact Concls. Law ¶¶ 339–40. Given that the University’s notice complied with the D.C. Circuit’s
    more stringent interpretation of the notice required under the Ground Lease, the thorny question of whether this
    Court would be bound by an incorrect determination of the D.C. Circuit on the notice required by a contract
    governed by D.C. local law need not be addressed.
    114
    F.      THE DEVELOPER NEVER ATTEMPTED TO CURE ITS DEFAULT,
    NOR IS IT EXCUSED FROM DOING SO
    The Developer argues it “attempt[ed] to cure its purported default” and was “precluded
    by the University” from doing so. Pl.’s Prop. Findings Fact Concls. Law ¶ 465. According to
    the Developer, the governing agreements required that the rental payment be made into an
    escrow account, and “had the University cooperated” by “enter[ing] into a new escrow
    agreement,” the Developer could have cured. 
    Id. ¶ 472.
    The Developer’s arguments must be
    rejected.
    First, to the extent the Developer argues its failure to cure is excused by impossibility, see
    Pl.’s Prop. Findings Fact Concls. Law ¶ 471, that argument is rejected as explained in this
    Court’s January 31, 2017, memorandum opinion, see HTC III, 
    2017 WL 421909
    , at *9–10. By
    dissolving the existing escrow account pursuant to the Term Sheet, the parties manifested and
    operationalized their understanding that the $1,475,000 payment would be made directly to the
    University. Consequently, the Developer’s protestations that it had no means to cure its
    monetary default are entirely disingenuous. Notably, the Developer has never argued it was
    impossible for the Developer to make the $100,000 payment required by the Term Sheet, even
    though, pursuant to the Term Sheet, the payment should have been made following the
    dissolution of the parties’ escrow account. See Term Sheet at 1–2.
    Second, the Developer, quite simply, made no attempt to set up an escrow account with
    the University for the purpose of curing its failure to make the $1,475,000 payment on May 30,
    2013. Rather, the Developer suggested the creation of a new escrow account, in contravention of
    the parties’ intent manifested in the Term Sheet, for the Developer’s own benefit. The
    Developer had proposed in March 2013 that the University agree to a new escrow account into
    which the $1,475,000 would be placed, “pending and subject to further negotiations,” in the
    115
    event that any portion of the Property were designated historic. See Joint Ex. 54, Email from
    Eric Siegel to David Gifford, dated Mar. 14, 2013, at 6. The University rejected that proposal as
    contrary to the understanding of the parties reflected in the Term Sheet. See Joint Ex. 55, Email
    from Alan Brangman to Eric Siegel, dated Mar. 22, 2013; Joint Ex. 56, Email from David
    Gifford to Eric Siegel, attaching draft documents, dated Mar. 27, 2013. On June 10, 2013, the
    Developer repeated its offer, rejected at least once already, to set up an escrow account into
    which to place the $1,475,000 payment. See Joint Ex. 65, Letter from Developer to Kurt
    Schmoke, dated June 10, 2013 (“We are happy to post the ground lease payment in escrow so
    that Howard University knows that the money is there to be paid upon conclusion of the Mayor’s
    Agent process.”). While at trial Siegel testified that, by this letter, he “offered to place the
    money in escrow pursuant to the contract documents that required us to do so,” the Developer’s
    letter nowhere cited any such contract requirement as a reason for the University to set up a new
    escrow account with the Developer. Trial Tr. Day 6 AM at 20:3–10. Nor would invocation of
    an escrow requirement have been reasonable at that time, given that the parties already
    manifested their understanding that, going forward, rental payments were to be made directly to
    the University by terminating the escrow account between the parties. Thus, by suggesting that
    an escrow account be created on June 10, 2013, the Developer sought a new condition on the
    rental payment, not to cure unequivocally its monetary default.
    The Developer did set up an account with Closeline on June 21, 2013. It only did so,
    however, after the applicable cure period had expired, and, as explained in prior opinions, the
    Developer’s payment into that account constituted neither a payment into an “escrow account”
    with the University nor a payment directly to the University. Yet again, the Developer’s action
    in opening the Closeline account reflects a desire to avoid putting its funds, including the second
    116
    rental payment, at risk without first securing financing for the project and a refusal to comply
    with agreed-to terms not desirable to the Developer. Consequently, the Developer never
    attempted to cure, let alone actually cured, its default.
    G.      APPROPRIATE REMEDY
    In light of the Developer’s breach of contract, the University is entitled to the damages it
    requests: the $1,475,000 rental payment and its attorney’s fees, in an amount to be determined
    following the submission of further evidence regarding those fees. See Def.’s Prop. Findings
    Fact Concls. Law ¶¶ 399–402. Given the Developer’s breach of the Term Sheet’s obligation to
    negotiate in good faith, the University would also have been entitled to recoupment of its
    investment of “time, money, and effort in negotiating” with the Developer over the amendments.
    Stanford 
    Hotels, 18 A.3d at 740
    . The University never requested or provided evidence of any
    such damages, however, so they will not be awarded.
    The University also requests forfeiture of the lease. See Def.’s Prop. Findings Fact
    Concls. Law ¶¶ 373–84. The Developer again presses its argument, rejected in this Court’s
    December 2013 memorandum opinion, that forfeiture of the Ground Lease is not an appropriate
    remedy. See Pl.’s Prop. Findings Fact Concls. Law ¶¶ 474–88; HTC I, 
    7 F. Supp. 3d
    at 83–87.
    For the reasons stated in the December 2013 memorandum opinion, the Developer’s argument is
    again rejected. In fact, the evidence presented at trial offers additional support for the remedy of
    forfeiture. Before imposing forfeiture, the following factors are considered: whether the breach
    was willful; whether the lessee acted in good faith; whether one of the parties violated
    fundamental principles of fair dealing; whether the landlord has given adequate notice to the
    tenant of the default and reasonable time to comply; and whether prejudice has accrued to the
    landlord by reason of the breach. See Entrepreneur, Ltd. v. Yasuna, 
    498 A.2d 1151
    , 1160–61
    117
    (D.C. 1985). As has been discussed, the Developer demonstrated willfulness and bad faith in its
    breaching of the parties’ various agreements; the University gave the Developer more than
    sufficient notice and time to cure; and, as the Developer itself has represented, the University
    experienced significant monetary prejudice, see Joint Ex. 12, Letter from Developer to Troy
    Stovall, dated Sept. 15, 2011, at 1–7 (asserting $1,000,000 as the loss to the University in lease
    revenue as of the date of the letter), as well as prejudice to its ability to carry out its mission of
    serving the University and surrounding community, as a result of the Developer’s breach. On
    the present record, forfeiture is unquestionably appropriate.
    H.      PIERCING THE CORPORATE VEIL
    During trial, the parties were directed to discuss in their conclusions of law whether, in
    the event the Developer were found liable, the corporate veil should be pierced to satisfy the
    judgment against it. See Trial Tr. Day 6 AM at 37:5–8.
    “Normally the corporation is an insulator from liability . . . [b]ut there are occasions when
    the limited liability sought to be obtained through the corporation will be qualified or denied.”
    Anderson v. Abbott, 
    321 U.S. 349
    , 361–62 (1944). “[C]ourts may look past a corporation’s
    formal existence to hold shareholders or other controlling individuals liable” in the event that
    “the incentive value of limited liability is outweighed by the competing value of basic fairness to
    parties dealing with the corporation.” Labadie Coal Co. v. Black, 
    672 F.2d 92
    , 96 (D.C. Cir.
    1982). In the District of Columbia, “[a] ‘party seeking to disregard the corporate entity must
    prove by affirmative evidence that there is (1) unity of ownership and interest, and (2) use of the
    corporate form to perpetuate fraud or wrong.’” Lawlor v. District of Columbia, 
    758 A.2d 964
    ,
    975 (D.C. 2000) (quoting Vuitch v. Furr, 
    482 A.2d 811
    , 815 (D.C. 1984)). “Although no single
    factor controls, courts generally inquire, inter alia, whether corporate formalities have been
    118
    observed; whether there has been commingling of corporate and shareholder funds, staff and
    property; whether a single shareholder dominates the corporation; whether the corporation is
    adequately capitalized; and, especially, whether the corporate form has been used to effectuate a
    fraud.” 
    Id. The Developer
    contends that the University “chose not to pursue” relief against any
    Cohen Companies asset or individual, as would require consideration of whether the corporate
    veil should be pierced, and “is thus not entitled to this relief.” Pl.’s Prop. Findings Fact Concls.
    Law ¶ 519. As support for this contention, the Developer cites Simon v. Circle Assocs., Inc., in
    which the District of Columbia Court of Appeals opined that “[d]ue process considerations
    would ordinarily require [in a suit against a corporation] that [an] alleged alter ego be joined in
    the action.” 
    753 A.2d 1006
    , 1010 n.4 (D.C. 2000). The Developer further argues that “on the
    merits, the University has failed to carry its burden of proof at trial as to any veil-piercing,” Pl.’s
    Prop. Findings Fact Concls. Law ¶ 520, noting the lack of evidence respecting the factors
    relevant to a veil-piercing determination. The University does not address whether its failure to
    bring a claim against any individual during this lawsuit precludes veil-piercing relief, arguing
    only that, on the merits, the evidence adduced thus far supports veil-piercing and “[b]ased on
    th[o]se facts, the University is entitled to discovery in support of its claim that this Court should
    disregard the separate forms of the Developer and its affiliates.” See Def.’s Prop. Findings Fact
    Concls. Law ¶¶ 403–07.
    While the substantive legal analysis for veil-piercing “is actually remarkably uniform
    across jurisdictions,” the procedures required before a Court may pierce the corporate veil differ.
    See Sam F. Halabi, Veil-Piercing’s Procedure, 67 Rutgers U. L. Rev. 1001, 1001, 1010 (2015)
    (arguing the “procedural fluidity” of veil-piercing, rather than substantive differences, explain
    119
    the “‘incoherence’ of veil-piercing law”). For example, courts differ as to (1) whether “plaintiffs
    [must] bring an independent cause of action for piercing the corporate veil” or request it as “a
    remedy for an underlying action” and (2) whether veil-piercing claims are waived “if not
    specifically pled before trial.” 
    Id. at 1008.
    Neither of these questions has been addressed in
    District of Columbia law, and a dearth of authority delineating the acceptable procedures for
    piercing the corporate veil exists more generally.
    “[W]hen necessary for the disposition of a case brought to it for decision,” a federal court
    must decide questions of state law. Meredith v. City of Winter Haven, 
    320 U.S. 228
    , 237 (1943)
    (imposing this requirement notwithstanding that “the highest court of the state had not answered
    [the state law questions], the answers were difficult, and the character of the answers which the
    highest state courts might ultimately give remained uncertain”). With respect to whether the veil
    may be pierced in this case, Simon is persuasive, if not dispositive, authority for the proposition
    that under District of Columbia law, a targeted asset or individual must be named before veil-
    piercing may be considered. Accordingly, veil-piercing is not appropriate in this case given its
    current procedural posture, wherein no other Cohen Companies asset or individual has been
    made a party to the University’s counterclaims.
    The University should not lament, nor the Developer celebrate, that conclusion, however,
    on the erroneous assumption that the University has waived its right to veil-piercing in this
    matter. As noted by a federal district court in a different jurisdiction, a procedural rule that
    “would force [litigants] to join parties and present ve[i]l-piercing claims, and courts to adjudicate
    them, in any case where a [litigant] has an inkling that piercing may be appropriate” would raise
    “concerns for judicial efficiency and economy.” Careccia v. Macrae, No. 05CV1628ARR, 
    2005 WL 1711156
    , at *5 (E.D.N.Y. July 19, 2005); but see 
    Halabi, supra, at 1019
    –20 (“The general
    120
    set of sanctions rules of civil procedure impose for failure to reasonably bring as many claims
    and parties together in the same dispute should counsel toward a requirement that veil-piercing
    be pleaded early in litigation.”). These concerns are significant.
    While District of Columbia law is silent on the specific issue, it has spoken loudly on the
    purpose of veil-piercing doctrine, repeating throughout the pertinent case law its core
    “considerations of justice and equity.” 
    Lawlor, 758 A.2d at 975
    ; Bingham v. Goldberg.
    Marchesano. Kohlman. Inc., 
    637 A.2d 81
    , 93 (D.C. 1994); 
    Vuitch, 482 A.2d at 815
    ; see also
    
    Labadie, 672 F.2d at 96
    (inquiring whether “if the acts are treated as those of the corporation
    alone . . . an inequitable result [will] follow”). Justice and equity demand a procedural rule that
    preserves the University’s right to its judgment, without wasting resources or punishing a failure
    to predict the need for veil-piercing. In light of Simon’s requirement that veil-piercing subjects
    be named as parties to a suit, and in the absence of controlling precedent, the Court holds that
    under District of Columbia law, a judgment-winner, unable to satisfy its judgment against a
    corporate adversary, may initiate a fresh action seeking veil-piercing against the adversary’s
    shareholders or purported alter egos. Consequently, in the event the University is unable to
    satisfy its judgment through attachment of assets belonging to the Developer or CastleRock, it
    may file a separate action requesting veil-piercing. Any such action will be fairly
    straightforward given the instant decision, including the Court’s observations regarding the
    inadequacy of the Developer’s capitalization, 
    see supra
    note 22, and the University may then be
    entitled to the additional discovery it presently seeks.
    This case highlights the injustice that may flow from a rule barring veil-piercing for
    litigants that fail to join parties and raise veil-piercing at the outset of an action to recover against
    a corporation. To the extent the University failed to predict a need for veil-piercing, the
    121
    Developer is to blame. The Developer touted, to the University and to this Court, the funds in
    the Closeline account as a reason for the University to continue its relationship with the
    Developer, prior to its decision to hand off those funds to PMAS, as it has done in other cases.
    
    See supra
    notes 20, 24. The University reasonably could have assumed that a party acting in
    good faith and under the microscope of litigation would not have acted so blatantly to evade a
    judgment against it. Under the rule announced in this case, the cost of the University’s
    reasonable but erroneous assumption as to the Developer’s honesty and integrity is justly laid at
    the feet of the Developer.
    IV.    CONCLUSION
    For the aforementioned reasons, the Developer is not entitled to judgment on its claim,
    the University is entitled to judgment on its counterclaim and third-party complaint, and
    judgment is, for the second time in this litigation, entered in favor of the University on the
    ground that its termination of the Ground Lease and the Development Agreement was effective
    and is a permissible forfeiture of all rights of the Developer, and that the University is entitled to
    damages in the amount of $1,475,000, along with interest and fees in an amount to be
    determined after the submission by the University, as requested, see Def.’s Prop. Findings Fact
    Concls. Law ¶ 423, of evidence supporting that award by September 5, 2017.
    An appropriate Order accompanies this Memorandum Opinion Setting Forth Findings of
    Fact and Conclusions of Law.
    Date: August 14, 2017
    __________________________
    BERYL A. HOWELL
    Chief Judge
    122