Standing Rock Sioux Tribe v. United States Army Corps of Engineers ( 2020 )


Menu:
  •                             UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF COLUMBIA
    STANDING ROCK SIOUX TRIBE, et al.,
    Plaintiffs,
    and
    CHEYENNE RIVER SIOUX TRIBE, et al.,
    Plaintiff-Intervenors,
    v.                                        Civil Action No. 16-1534 (JEB)
    U.S. ARMY CORPS OF ENGINEERS,
    Defendant,
    and
    DAKOTA ACCESS, LLC,
    Defendant-Intervenor.
    MEMORANDUM OPINION
    Lake Oahe is a large reservoir lying behind a dam on the Missouri River and stretching
    between North and South Dakota. Fearing severe environmental consequences, American Indian
    Tribes on nearby reservations have sought for several years to invalidate federal permits
    allowing the Dakota Access Pipeline to carry oil under the lake. Today they finally achieve that
    goal — at least for the time being.
    Following multiple twists and turns in this long-running litigation, this Court recently
    found that Defendant U.S. Army Corps of Engineers had violated the National Environmental
    Policy Act when it granted an easement to Defendant-Intervenor Dakota Access, LLC to
    construct and operate a segment of that crude-oil pipeline running beneath the lake. This was
    1
    because the Corps had failed to produce an Environmental Impact Statement despite conditions
    that triggered such a requirement. The Court consequently remanded the case to the agency to
    prepare such an EIS, but it asked for separate briefing on the appropriate interim remedy. In
    other words, the Court asked the parties whether the easement should be vacated and the pipeline
    emptied during the remand process. Although mindful of the disruption such a shutdown will
    cause, the Court now concludes that the answer is yes. Clear precedent favoring vacatur during
    such a remand coupled with the seriousness of the Corps’ deficiencies outweighs the negative
    effects of halting the oil flow for the thirteen months that the Corps believes the creation of an
    EIS will take.
    I.     Background
    The Court recounts here only the background information necessary to set the stage for
    the remedy analysis. For the full history of this case, the interested reader can refer to the
    Court’s ten prior Opinions in this matter. See, e.g., Standing Rock Sioux Tribe v. U.S. Army
    Corps. of Eng’rs (Standing Rock III), 
    255 F. Supp. 3d 101
    , 114–16 (D.D.C. 2017); see also ECF
    Nos. 39, 158, 206, 239, 284, 304, 392, 418, 496. The Court begins with the relevant statute and
    then describes the procedural history of the litigation.
    A. Statutory Scheme
    The National Environmental Policy Act requires agencies to “consider every significant
    aspect of the environmental impact of a proposed action,” Balt. Gas & Elec. Co. v. NRDC, 
    462 U.S. 87
    , 97 (1983) (quoting Vt. Yankee Nuclear Power Corp v. NRDC, 
    435 U.S. 519
    , 553
    (1978)), so as to “inform the public that it has indeed considered environmental concerns in its
    decisionmaking process.”
    Id. (citing Weinberger
    v. Catholic Action of Haw., 
    454 U.S. 139
    , 143
    (1981)). In order to achieve these goals, NEPA imposes on agencies certain procedural
    2
    requirements, Citizens Against Burlington, Inc. v. Busey, 
    938 F.2d 190
    , 193–94 (D.C. Cir.
    1991), but it “does not mandate particular consequences.”
    Id. at 194.
    First, an agency must draft an Environmental Assessment, see 40 C.F.R. § 1501.4(b), that
    “[b]riefly provide[s] sufficient evidence and analysis for determining whether to prepare an
    environmental impact statement [EIS] or a finding of no significant impact [FONSI].”
    Id. § 1508.9(a).
    “If any ‘significant’ environmental impacts might result from the proposed agency
    action[,] then an EIS must be prepared before agency action is taken.” Grand Canyon Trust v.
    FAA, 
    290 F.3d 339
    , 340 (D.C. Cir. 2002) (quoting Sierra Club v. Peterson, 
    717 F.2d 1409
    , 1415
    (D.C. Cir. 1983)); see also 42 U.S.C. § 4332(2)(C) (requiring statement of environmental impact
    of any proposed action “significantly affecting the quality of the human environment”). If, on
    the other hand, the agency determines that no EIS is required, it must prepare either a FONSI or
    a Mitigated FONSI, depending on whether the lack of significant impact results from an
    agency’s commitment to mitigation measures. See 40 C.F.R. §§ 1501.4(e), 1508.13; Council on
    Environmental Quality, Appropriate Use of Mitigation and Monitoring and Clarifying the
    Appropriate Use of Mitigated Findings of No Significant Impact 2, 7 (2011), https://ceq.doe.gov/
    docs/ceq-regulations-and-guidance/Mitigation_and_Monitoring_Guidance_14Jan2011.pdf.
    In order to determine whether its actions may result in “significant” environmental
    impacts — and therefore whether it must prepare an EIS — an agency must examine both the
    “context” and the “intensity” of the action. See 40 C.F.R. § 1508.27. [I]n evaluating intensity,”
    the agency must consider ten factors,
    id. § 1508.27(b),
    only one of which is relevant here.
    “Implicating any one of the[se] factors may be sufficient to require development of an EIS.”
    Nat’l Parks Conservation Ass’n v. Semonite, 
    916 F.3d 1075
    , 1082 (D.C. Cir. 2019) (citing Grand
    Canyon 
    Trust, 290 F.3d at 347
    ). The decision here turned on the fourth of these factors — “[t]he
    3
    degree to which the effects on the quality of the human environment are likely to be highly
    controversial.” 40 C.F.R. § 1508.27(b)(4).
    Effects are “controversial” where “substantial dispute exists as to the size, nature, or
    effect of the major federal action rather than to the existence of opposition to a use.” Town of
    Cave Creek v. FAA, 
    325 F.3d 320
    , 331 (D.C. Cir. 2003) (emphasis omitted) (quoting Found. for
    N. Am. Wild Sheep v. USDA, 
    681 F.2d 1172
    , 1182 (9th Cir. 1982)). While “what constitutes
    the type of ‘controversy’ that requires a full EIS is not entirely clear,” Nat’l Parks Conservation
    Ass’n v. United States, 
    177 F. Supp. 3d 1
    , 33 (D.D.C. 2016) (quoting Nat’l Wildlife Fed’n v.
    Norton, 
    332 F. Supp. 2d 170
    , 184 (D.D.C. 2004)), “something more is required besides the fact
    that some people may be highly agitated and be willing to go to court over the matter.”
    Id. (quoting Fund
    for Animals v. Frizzell, 
    530 F.2d 982
    , 988 n.15 (D.C. Cir. 1975)).
    B. Procedural History
    This case involves efforts by several American Indian Tribes to enjoin Defendant United
    States Army Corps of Engineers from permitting Defendant-Intervenor Dakota Access, LLC to
    constructe and operate a segment of its oil pipeline under Lake Oahe, which lies on the Missouri
    River. In 2016, Plaintiff Standing Rock Sioux Tribe filed its Complaint in this Court, followed
    shortly by Plaintiff-Intervenor Cheyenne River Sioux Tribe and later by Plaintiffs Oglala and
    Yankton Sioux Tribes, the latter two in cases that have now been consolidated into the present
    one. Standing Rock Sioux Tribe v. U.S. Army Corps of Eng’rs (Standing Rock VI), No. 16-
    1534, 
    2020 WL 1441923
    , at *3 (D.D.C. Mar. 25, 2020). Early on, both Standing Rock and
    Cheyenne River were unsuccessful in seeking preliminary injunctions under the National
    Historic Preservation Act and the Religious Freedom Restoration Act. Standing Rock Sioux
    Tribe v. U.S. Army Corps of Eng’rs (Standing Rock II), 
    239 F. Supp. 3d 77
    , 100 (D.D.C. 2017);
    4
    Standing Rock Sioux Tribe v. U.S. Army Corps of Eng’rs (Standing Rock I), 
    205 F. Supp. 3d 4
    ,
    37 (D.D.C. 2016). In between these two Opinions, the Corps “announced that DAPL
    construction would be suspended pending the Corps’ reconsideration of its statutory obligations”
    under NEPA. Standing Rock VI, 
    2020 WL 1441923
    , at *3. A few months later, however,
    following the change of administration in January 2017 and a presidential memorandum urging
    acceleration of the project, the Corps again reconsidered and decided to move forward.
    Id. It granted
    the sought permit, construction was completed, and oil commenced flowing through the
    Dakota Access Pipeline. Standing Rock 
    III, 255 F. Supp. 3d at 120
    .
    Undeterred, later in 2017, Standing Rock and Cheyenne River switched focus and
    “sought summary judgment under [the National Environmental Policy Act], arguing that the
    Corps was required to prepare an [Environmental Impact Statement], and Defendants similarly
    cross-moved.” Standing Rock VI, 
    2020 WL 1441923
    , at *4. The Court found that the Corps’
    decision “not to issue an EIS largely complied with NEPA,” but three “substantial exceptions” to
    that compliance necessitated a remand. Standing Rock 
    III, 255 F. Supp. 3d at 147
    . Specifically,
    the Court “found wanting the Corps’ analysis of: (1) whether the project's effects were likely to
    be highly controversial; (2) the impact of an oil spill on the Tribe’s fishing and hunting rights
    under the Treaty of 1851; and (3) ‘whether,’ under a required environmental-justice analysis,
    ‘Standing Rock would be disproportionately harmed by a spill.’” Standing Rock VI, 
    2020 WL 1441923
    , at *5 (citations omitted) (quoting Standing Rock 
    III, 255 F. Supp. 3d at 140
    ). This
    raised the significant question of whether the permit should be vacated — and the oil flow
    arrested — during the remand. In a subsequent Opinion, the Court declined to so order, finding
    that there was a “‘serious possibility’ that the Corps w[ould] be able to substantiate its prior
    5
    conclusions.” Standing Rock Sioux Tribe v. U.S. Army Corps of Eng’rs (Standing Rock IV),
    
    282 F. Supp. 3d 91
    , 109 (D.D.C. 2017).
    During the remand, which stretched on for well over a year, the D.C. Circuit “issued a
    significant opinion clarifying a court’s role in reviewing an agency’s finding that a project was
    not ‘highly controversial.’” Standing Rock VI, 
    2020 WL 1441923
    , at *7. In Semonite, that
    court held that it was not sufficient for an agency to simply “acknowledge and try to address
    concerns raised during the NEPA 
    process.” 916 F.3d at 1085
    (emphasis added). “The question
    is not whether the Corps attempted to resolve the controversy, but whether it succeeded.”
    Id. at 1085–86.
    Because the Corps in that case had failed to resolve the scientific controversy raised
    by expert and agency comments, the Semonite court found that it had been wrong to choose not
    to prepare an EIS and remanded for such action.
    Id. at 1087–88.
    After the remand in this case was completed, the parties again cross-moved for summary
    judgment. Realizing that Semonite guided both “the nature and scope of [this Court’s] review,”
    Standing Rock VI, 
    2020 WL 1441923
    , at *8; see
    id. at *6–8
    (detailing reasons for following
    Semonite), the Court conducted a detailed analysis of some of the many expert critiques of the
    environmental effects of the proposed project.
    Id. at *8–16
    (discussing leak-detection system,
    operator safety record, winter conditions, and worst-case discharge). Ultimately, “even this non-
    extensive selection suffice[d] to show the necessity of an EIS.”
    Id. at *9.
    The Court found that
    “the Corps ha[d] not ‘succeeded’ in ‘resolv[ing] the controversy’ created by ‘consistent and
    strenuous opposition, often in the form of concrete objections to the Corps’ analytical process
    and findings,’ by ‘organizations with subject-matter expertise.’”
    Id. at *16
    (second alteration in
    original) (quoting 
    Semonite, 916 F.3d at 1086
    ). As in Semonite, “[t]his demonstrate[d] the
    ‘something more’ needed to show that the ‘effects on the quality of the human environment are
    6
    likely to be highly controversial.’”
    Id. (first alteration
    in original) (quoting 
    Semonite, 916 F.3d at 1086
    ). “The Corps ha[d] thus violated NEPA by determining that an EIS was unnecessary
    even though one of the EIS-triggering factors was met.”
    Id. While there
    were two remaining NEPA topics — other than the “highly controversial”
    factor — that had formed the basis for the Court’s first remand, it found no need to reach them,
    since the remedy for any finding in the Tribes’ favor would be the same — viz., an EIS — and
    such EIS would require consideration of them in any case.
    Id. After disposing
    of a handful of
    other, non-NEPA issues,
    id. at *16–19,
    the Court again “remand[ed] to the agency for it to
    complete such EIS.”
    Id. at *16
    (citing 
    Semonite, 916 F.3d at 1082
    ; then citing Grand Canyon
    
    Trust, 290 F.3d at 340
    ). It asked for separate briefing, however, on “the status of the
    easement — and, ultimately, the oil — in the meantime.”
    Id. at *19.
    Unsurprisingly, the Tribes
    have argued for vacatur of the permits, Defendants have opposed, and each side is joined by an
    army of amici. See ECF Nos. 504, 514–19, 521, 532–33, 537. With the benefit of this bountiful
    briefing, the Court is now prepared to rule as to vacatur.
    II.     Legal Standard
    “The ordinary practice is to vacate unlawful agency action.” United Steel v. Mine Safety
    & Health Admin., 
    925 F.3d 1279
    , 1287 (D.C. Cir. 2019) (citing 5 U.S.C. § 706(2)); accord FCC
    v. NextWave Personal Comms. Inc., 
    537 U.S. 293
    , 300 (2003) (“In all cases agency action must
    be set aside if the action . . . failed to meet statutory, procedural, or constitutional requirements.”)
    (quoting Citizens to Preserve Overton Park, Inc. v. Volpe, 
    401 U.S. 402
    , 413–14 (1971)).
    Vacatur is also the “standard remedy” in this Circuit for an “action promulgated in violation of
    NEPA.” Humane Soc’y of U.S. v. Johanns, 
    520 F. Supp. 2d 8
    , 37 (D.D.C. 2007) (citing Am.
    Bioscience, Inc. v. Thompson, 
    269 F.3d 1077
    , 1084 (D.C. Cir. 2001)); see Reed v. Salazar, 744
    
    7 F. Supp. 2d 98
    , 118–20 (D.D.C. 2010) (finding NEPA violation and ordering vacatur); Sierra
    Club v. Van Antwerp, 
    719 F. Supp. 2d 77
    , 78–80 (D.D.C. 2010) (finding NEPA violation and
    ordering remand with partial vacatur); Greater Yellowstone Coal. v. Kempthorne, 
    577 F. Supp. 2d
    183, 204–05, 210 (D.D.C. 2008) (finding NEPA violation and ordering vacatur); see also Pub.
    Emps. for Envtl. Responsibility v. U.S. Fish & Wildlife Serv., 
    189 F. Supp. 3d 1
    , 2 (D.D.C.
    2016) (surveying “cases in this district” and noting “the primacy of vacatur to remedy NEPA
    violations”).
    Although vacatur may be the “presumptively appropriate remedy,” Sierra Club, 719 F.
    Supp. 2d at 78, it is not the only option. Instead, as equity requires, the reviewing court has
    discretion to leave the agency action in place. See, e.g., Advocates for Highway & Auto Safety
    v. Fed. Motor Carrier Safety Admin., 
    429 F.3d 1136
    , 1151 (D.C. Cir. 2005) (declining to vacate
    vehicle-safety rule found arbitrary and capricious under APA); Int’l Union, United Mine
    Workers of Am. v. Fed. Mine Safety & Health Admin., 
    920 F.2d 960
    , 966–67 (D.C. Cir. 1990)
    (same for mine-safety rule). Indeed, that is precisely what this Court did last time around. See
    Standing Rock 
    IV, 282 F. Supp. 3d at 109
    .
    In Allied-Signal v. United States Nuclear Regulatory Commission, 
    988 F.2d 146
    (D.C.
    Cir. 1993), the court laid out the operative test for whether to vacate a deficient agency action
    during remand. First, a court must consider “the seriousness of the order’s deficiencies (and thus
    the extent of doubt whether the agency chose correctly).”
    Id. at 150
    (quoting Int’l 
    Union, 920 F.2d at 967
    ). Second, it analyzes “the disruptive consequences of an interim change that may
    itself be changed.”
    Id. at 150
    –51 (quoting Int’l 
    Union, 920 F.2d at 967
    ). “Because vacatur is the
    default remedy, . . . defendants bear the burden to prove that vacatur is unnecessary.” Nat’l
    Parks Conservation Ass’n v. Semonite, 
    422 F. Supp. 3d 92
    , 99 (D.D.C. 2019).
    8
    III.    Analysis
    The Court analyzes each prong of the Allied-Signal test separately, keeping in mind that
    “[t]here is no rule requiring either the proponent or opponent of vacatur to prevail on both
    factors.” Shands Jacksonville Med. Ctr. v. Burwell, 
    139 F. Supp. 3d 240
    , 270 (D.D.C. 2015). It
    ultimately concludes that shutting down the pipeline is warranted.
    A. Seriousness of Deficiencies
    Unlike the Court’s last Opinion on remedy in this case, the first Allied-Signal prong is
    quite straightforward here. The Court’s task in considering this first factor is to determine
    whether there is “a significant possibility that the [agency] may find an adequate explanation for
    its actions” on remand. Williston Basin Interstate Pipeline Co. v. FERC, 
    519 F.3d 497
    , 504
    (D.C. Cir. 2008) (citing 
    Allied-Signal, 988 F.2d at 150
    –51); accord Nat’l Parks Conservation
    Ass’n v. Jewell, 
    62 F. Supp. 3d 7
    , 20 (D.D.C. 2014) (“[R]emand without vacatur is appropriate
    where ‘there is at least a serious possibility that the [agency] will be able to substantiate its
    decision on remand.’”) (second alteration in original) (quoting 
    Allied-Signal, 988 F.2d at 151
    ).
    In its prior remedy Opinion, this Court went through the three topics to be covered on remand in
    significant detail, see Standing Rock 
    IV, 282 F. Supp. 3d at 97
    –103, finding in each case that the
    Corps was likely to be able to “substantiate its prior decision to issue an EA.”
    Id. at 100
    (fishing
    and hunting rights); see also
    id. at 99
    (highly controversial);
    id. at 102
    (environmental justice).
    Now, however, that decision has been weighed, it has been measured, and it has been
    found wanting. The Court’s March 2020 Opinion examined the first of the three remand
    topics — namely, whether the effects were highly controversial — and found definitively that,
    notwithstanding the Court’s earlier optimism, the Corps had not been able to substantiate its
    decision to publish only an EA and not an EIS:
    9
    As shown at great length in the preceding analysis, the Corps has
    not “succeeded” in “resolv[ing] the controversy” created by
    “consistent and strenuous opposition, often in the form of concrete
    objections to the Corps’ analytical process and findings,” by
    “organizations with subject-matter expertise.” As in Semonite,
    “[t]his demonstrates the ‘something more’ needed to show that the
    ‘effects on the quality of the human environment are likely to be
    highly controversial.’” The Corps has thus violated NEPA by
    determining that an EIS was unnecessary even though one of the
    EIS-triggering factors was met.
    Standing Rock VI, 
    2020 WL 1441923
    , at *16 (alterations in original) (citations omitted) (quoting
    
    Semonite, 916 F.3d at 1086
    ). There is no longer any question of the Corps being able to justify
    its choice.
    In such a circumstance, Circuit precedent overwhelmingly dictates that vacatur is
    appropriate. That court routinely vacates agency action when remanding for preparation of an
    EIS, and often without discussion. See, e.g., Sierra Club v. FERC, 
    867 F.3d 1357
    , 1379 (D.C.
    Cir. 2017) (vacating agency approval of interstate natural-gas pipelines); Am. Wild Horse
    Preservation Campaign v. Perdue, 
    873 F.3d 914
    , 932 (D.C. Cir. 2017) (vacating Forest Service
    decision to eliminate 23,000 acres of wild horse territory); see also Sierra Club v. U.S. Army
    Corps of Eng’rs, 
    803 F.3d 31
    , 43 (D.C. Cir. 2015) (“If the NEPA analysis were legally
    inadequate, ‘we could order that the [pipeline] be closed or impose restrictions on its use,’ at
    least on federally authorized segments, ‘until [the agencies] complied with NEPA.’”) (alterations
    in original) (quoting Airport Neighbors All., Inc. v. United States, 
    90 F.3d 426
    , 429 (10th Cir.
    1996)). When vacatur is discussed, the seriousness of a failure to produce an EIS under NEPA is
    emphasized. See, e.g., Oglala Sioux Tribe v. U.S. Nuclear Regulatory Comm’n, 
    896 F.3d 520
    ,
    536 (D.C. Cir. 2018) (“The seriousness of the NEPA deficiency is particularly clear here because
    the point of NEPA is to require an adequate EIS before a project goes forward . . . .”).
    10
    In fact, to the Court’s and the parties’ knowledge, only twice has a court (once the
    Circuit, once the district court here) not vacated agency action that violated NEPA because of a
    missing or defective EIS. Defendants attempt to hang their hat on these cases, but to no avail. In
    both, the second prong of the Allied-Signal test, but not the first, weighed in favor of remand
    without vacatur, leading those courts to find that the scales tipped toward the agency. See id.;
    
    Semonite, 422 F. Supp. 3d at 99
    –100 (“[T]he seriousness of the defect is significant. If the first
    Allied-Signal factor were the only consideration, the standard remedy [of vacatur] would likely
    apply.”);
    id. at 103
    (“For all of these reasons, the second Allied-Signal factor forces the Court to
    conclude that vacating the permit would be inappropriate.”). That second factor will be analyzed
    presently, see infra Section III.B, and the Court will revisit these two cases at that time. As to
    this first prong, however, both decisions strongly support the Court’s conclusion here.
    Defendants and Defendant-Intervenor next argue that, instead of focusing on the Corps’
    decision not to prepare an EIS, the Court should be analyzing whether “the Corps will likely
    substantiate its substantive easement decision.” ECF No. 507 (Corps Remedy Brief) at 7
    (emphasis added); see ECF No. 509-1 (DA Remedy Brief) at 14 (“The Corps’ key premises for
    granting the easement . . . remain intact, and they strongly suggest that the Corps will be able to
    reach the same top-line conclusion on remand.”). They maintain that focusing on the EIS
    decision “would render the first part of th[e Allied-Signal] test surplusage,” since it suggests that
    any agency action that is invalid for failure to produce an EIS will always flunk this first prong
    of the vacatur test. See ECF No. 536 (Corps Remedy Reply) at 5; see ECF No. 541 (DA
    Remedy Reply) at 9 (arguing that focusing on the EIS “alter[s] that prong such that it could
    never apply in NEPA cases like this”). Instead, they would have the Court evaluate their ability
    in an EIS to remedy the specific areas of concern stated in its prior Opinion. They thus spill
    11
    considerable ink rehashing the merits of the Court’s prior Opinions. See, e.g., DA Remedy Br. at
    19–31 (arguing in great detail why Corps will be able to “easily address the four discrete issues
    that this Court found ‘highly controversial,’”
    id. at 19);
    Corps Remedy Br. at 10–14 (arguing that
    pipeline’s Mineral Leasing Act easement is valid for the reasons argued in first round of
    summary judgment).
    To the extent that Defendants complain that the “seriousness” of an agency’s failure to
    produce an EIS under NEPA is a foregone conclusion, they are taking issue with the caselaw in
    this Circuit, as just explained. See also Dep’t of Transp. v. Pub. Citizen, 
    541 U.S. 752
    , 757
    (2004) (describing EIS as being “[a]t the heart of NEPA”). But the magnitude of those
    shortcomings is even clearer here, where the Court had the benefit of a second round of
    summary-judgment briefing to determine that the defects in the EA were, in fact, too serious to
    be ignored. See generally Standing Rock VI, 
    2020 WL 1441923
    . The Court determined in
    March of this year that these infirmities were so significant as to merit the preparation of an
    Environmental Impact Statement,
    id. at *16,
    and, as just explained, an EIS failure under NEPA is
    considered a very serious deficiency in this Circuit. The Court’s focus on the EIS, rather than on
    the entire easement decision, is in fact supported by one of the aforementioned two cases on
    which Defendants rely. See 
    Semonite, 422 F. Supp. 3d at 99
    (“Looking at the first Allied-Signal
    factor, the Court does not assess the deficiency of the ultimate decision itself — the choice to
    issue the permit — but rather the deficiency of the determination that an EIS was not
    warranted.”) (emphasis added).
    Defendants’ argument, moreover, betrays what appears to be a misunderstanding of their
    obligations going forward. The time for justifying the Environmental Assessment has passed —
    the Court has ordered an Environmental Impact Statement, and another limited remand analysis
    12
    will not fit the bill. Contra DA Remedy Br. at 14 (arguing that task on remand is to address only
    “four areas of criticism pertaining to one remand topic”). Indeed, the Court explicitly did not
    reach the other two remand topics because “the remedy for them would be the same,” and “‘[i]n
    preparing its EIS, the Corps [would] have to revisit’ those issues in any case.” Standing Rock
    VI, 
    2020 WL 1441923
    , at *16 (alterations in original) (quoting 
    Semonite, 916 F.3d at 1088
    ).
    Contra Corps Remedy Br. at 10 (“[T]he Court found no fault with the Corps’ consideration of
    environmental justice or of the impacts to the Tribes’ treaty hunting and fishing rights . . . .”).
    An EIS, it is important to remember, is a separate regulatory beast, with its own
    requirements. See, e.g, Taxpayers of Mich. Against Casinos v. Norton, 
    433 F.3d 852
    , 857 (D.C.
    Cir. 2006) (describing EIS as “detailed” and “comprehensive”). The fact that the Corps has
    submitted a detailed EA does not minimize its obligations when preparing that EIS. See
    Anderson v. Evans, 
    371 F.3d 475
    , 494 (9th Cir. 2004) (“No matter how thorough, an EA can
    never substitute for preparation of an EIS, if the proposed action could significantly affect the
    environment.”). Compare 40 C.F.R. § 1501.4 (laying out considerations for “whether to prepare
    an environmental impact statement”), with 40 C.F.R. §§ 1502.1–1502.24 (laying out
    requirements for environmental impact statement). Contra DA Remedy Br. at 10 (arguing that
    Corps can “continue to rely largely, if not exclusively, on its prior analysis”). The Corps must
    perform a full and complete EIS for the entire project, potentially subject to the full scope of
    judicial review normally applied to environmental impact statements. See, e.g., 40 C.F.R.
    § 1502.14 (comparison of environmental impacts of alternatives to proposed agency project “is
    the heart of the environmental impact statement”); Sierra 
    Club, 867 F.3d at 1371
    –72 (discussing
    agency’s duty in preparing EIS to consider indirect environmental effects of pipeline operations).
    13
    In sum, the first Allied-Signal factor weighs entirely in favor of vacatur. The Court has
    had ample opportunity to consider the serious deficiencies in the Corps’ decision not to prepare
    an EIS, see Standing Rock VI, 
    2020 WL 1441923
    , at *8–16, and it finds no “possibility that the
    [agency] may find an adequate explanation for its actions.” Williston Basin Interstate 
    Pipeline, 519 F.3d at 504
    ; see 
    Allied-Signal, 988 F.2d at 151
    .
    B. Disruptive Consequences
    The second Allied-Signal factor is less straightforward here than the first. At issue are
    “the disruptive consequences of 
    vacating,” 988 F.2d at 151
    , particularly those that threaten to
    “‘set back’ the Act’s objective[s].” Am. Bankers Ass’n v. Nat’l Credit Union Admin., 
    934 F.3d 649
    , 674 (D.C. Cir. 2019); accord Envtl. Def. Fund, Inc. v. EPA, 
    898 F.2d 183
    , 190 (D.C. Cir.
    1990) (remanding without vacatur when no party requested to vacate and doing so would defeat
    “the enhanced protection of the environmental values covered by the [Clean Air Act]”). Courts
    may choose “not [to] vacate regulations when doing so would risk significant harm to the public
    health or the environment.” Wisconsin v. EPA, 
    938 F.3d 303
    , 336 (D.C. Cir. 2019) (citing
    
    Allied-Signal, 988 F.2d at 150
    –51).
    1. Economic Disruption
    Dakota Access’s central and strongest argument as to the second Allied-Signal prong is
    that shutting down the pipeline would cause it, and the industries that rely on it, significant
    economic harm, including substantial job losses. See, e.g., DA Remedy Br. at 32 (stating that
    shutdown would “pose an existential threat to DAPL” due to “massive” revenue loss). It submits
    declarations stating that DAPL could lose as much as $643 million in the second half of 2020
    and $1.4 billion in 2021 if shut down pursuant to the Court’s order. See ECF No. 509-9
    (Declaration of Glenn Emery), ¶ 10. “All of these financial losses would be absorbed by the
    14
    owners of Dakota Access,” particularly Energy Transfer Partners, the current parent company of
    DAPL after a merger with Sunoco. See DA Remedy Br. at 33; Standing Rock VI, 
    2020 WL 1441923
    , at *10.
    In addition, both Dakota Access and many amici argue, shutting the pipeline down would
    have serious repercussions for the entire North Dakota oil industry. “There is no viable pipeline
    alternative for transporting the 570,000 barrels of Bakken crude that DAPL is capable of
    carrying each day,” Dakota Access states, and railroads do not have the capacity “to fill the
    breach.” DA Remedy Br. at 35–36; see ECF No. 504 (Amicus Brief of State of North Dakota) at
    11 (“An increase in crude by rail volumes sufficient to offset current pipeline deliveries by
    DAPL would take an unknown amount of time to assemble the required tank cars, engines, and
    crews, and to ensure market destinations would be prepared for a surge in rail volume.”).
    Several states also argue that their grain farmers would be harmed by having to pay a premium
    for railroad cars once oil, which is more valuable by volume, enters that market and drives up
    prices. See ECF No. 514 (Amicus Brief of IN, MT, AL, AR, IA, KS, KY, LA, NE, OH, SD, TX,
    UT, and WV) at 9–10. “[M]any North Dakota oil producers,” meanwhile, with no way to get
    their oil to market, “would have no choice but to respond by ‘shutting in’ some of their wells and
    ceasing production entirely,” with consequent effects on the workers at those wells. See DA
    Remedy Brief at 35 (citing ECF No. 509-11 (Declaration of Jeff D. Makholm), ¶ 17; then citing
    Emery Decl., ¶¶ 14, 18). Specifically, Dakota Access estimates, “producers would have to shut-
    in between 3,460 and 5,400 wells, stranding up to 34.5% of North Dakota crude production.”
    Id. at 36;
    see also, e.g., North Dakota Br. at 8 (estimating that “[e]ach of those wells represents 1.6
    full time jobs”) (citing ECF No. 504-2 (Declaration of Lynn Helms), ¶ 10). This would also
    have a reverberating effect on the state of North Dakota, whose economy derives a large part of
    15
    its revenue from oil and gas taxes, largely from the Williston Basin, which includes the Bakken
    fields that supply DAPL. See North Dakota Br. at 2–3; DA Remedy Br. at 4; see also North
    Dakota Br. at 2 (explaining that “despite the small overall size of North Dakota’s economy, [it] is
    a large producer of oil and natural gas”).
    The Tribes and other amici respond that these projected consequences are “wildly
    exaggerated” because, following “a precipitous collapse in oil prices, demand, and production”
    caused in part by the COVID-19 pandemic, “production in North Dakota has [already]
    plummeted.” ECF No. 527 (Tribes Remedy Brief) at 21–22; see also ECF No. 531 (Amicus
    Brief of Members of Congress) at 9 (“Since [the Court’s last remedy Opinion in this case in]
    2017, the price and demand for oil has plummeted due to factors well beyond the operation of
    this pipeline.”); ECF No. 519 (Amicus Brief of North Dakota Petroleum Council) at 8 (“In recent
    weeks, of course, the coronavirus pandemic has turned the nation’s economy and the oil industry
    upside down.”). They point out that North Dakota estimates that “as many as 5,000 wells may
    now be shut-in” because of “the current economic situation,” North Dakota Br. at 3 n.4, noting
    that this is more than the number of wells Dakota Access claimed would be affected by a DAPL
    shutdown. See Tribes Remedy Br. at 22–23; see also
    id. at 23
    (citing news articles reporting that
    North Dakota well shut-ins have now increased to 7,000). Other briefs allude to the pandemic,
    admitting some effect on the oil market but maintaining more optimism than realism. See, e.g.,
    N.D. Petroleum Council Br. at 8 (“In recent weeks, of course, the coronavirus pandemic has
    turned the nation’s economy and the oil industry upside down. Nevertheless, NDPC continues to
    hope and expect that our country’s economy and the industry will recover in coming months.”);
    North Dakota Br. at 12 (“[T]he potential impacts of the COVID-19 pandemic are impossible to
    quantify due to rapidly changing oil prices, employment numbers, and capital investment
    16
    plans . . . .”). The Tribes further claim that this drop in production may mean that there will be
    “little or no increase in rail transportation.” Tribes Remedy Br. at 25 (citing ECF No. 527-2
    (Declaration of Marie Fagan), ¶ 5). And to the extent that a DAPL shutdown causes crude-oil
    demand to drop even further or its transportation to switch to railroads, the Tribes argue that with
    “some participants in the North Dakota oil market [facing] increased costs,” “other participants,”
    such as railroads and other oil-producing states, would “benefit from the shift.” Tribes Remedy
    Br. at 26 (citing ECF No. 272-2 (Third Declaration of Richard Krupewicz), ¶ 30; then citing
    Fagan Decl., ¶ 7). Defendant-Intervenors, for their part, dismiss the Tribes’ take on the
    pandemic, calling their analysis of the continuing effects of a pandemic-depressed oil market
    “bearish” and “erroneous[].” DAPL Remedy Rep. at 17–18.
    The Court need not pick apart the various positions in these disputes, for it is clear that at
    least some immediate harm to the North Dakota oil industry should be expected from a DAPL
    shutdown, even if its effects are tempered by a decreased demand for oil. See DA Remedy Rep.
    at 18 (averring that “demand for [the pipeline]’s services has remained strong”). Indeed, the
    Court does not take lightly the serious effects that a DAPL shutdown could have for many states,
    companies, and workers. Losing jobs and revenue, particularly in a highly uncertain economic
    environment, is no small burden. Ultimately, however, these effects do not tip the scales
    decisively in favor of remanding without vacatur. This is so for several reasons.
    First, “the Corps anticipates the [EIS] process” for DAPL “will take approximately
    thirteen months,” Corps Remedy Br. at 5, whereas in general “the mean time from initiation to
    completion of an EIS is 3.6 years” across all federal agencies, and the Corps’ own average time
    is even longer. See Tribes Remedy Br. at 16 n.4 (citing Council on Envtl. Quality,
    Environmental Impact Statement Timelines (2010–2017), at 1, 8, https://www.whitehouse.gov/
    17
    wp-content/uploads/2017/11/CEQ-EIS-Timelines-Report.pdf). This expedited process, if it
    proceeds on track, would cabin the economic disruption of a shutdown. See Standing Rock 
    IV, 282 F. Supp. 3d at 108
    (“[T]he Corps' assertions regarding the timing of the remand process are
    also relevant to analyzing the disruption in this case.”). Without vacatur, conversely, the Corps
    and Dakota Access would have little incentive to finish the EIS in a timely matter.
    Second, while economic disruption is a proper consideration for the second Allied-Signal
    prong, it may not necessarily be “determinative.” Standing Rock 
    IV, 282 F. Supp. 3d at 104
    ; see
    also Am. Water Works Ass’n v. EPA, 
    40 F.3d 1266
    , 1273 (D.C. Cir. 1994) (considering
    “disrupti[on] to the [affected] industries” in vacatur analysis). Courts more often cite “harm to
    the public health or the environment,” 
    Wisconsin, 938 F.3d at 336
    (citing 
    Allied-Signal, 988 F.2d at 150
    –51), and those that “‘set back’ the Act’s objective[s].” Am. Bankers 
    Ass’n, 934 F.3d at 674
    . The Court will discuss environmental disruption shortly. See infra Section III.B.2,.
    Third, accepting Dakota Access’s arguments wholesale would subvert the structure of
    NEPA, the “objective[s]” of which are an important touchstone when considering disruption.
    Am. Bankers 
    Ass’n, 934 F.3d at 674
    . NEPA’s “requirement that a detailed environmental
    impact statement be made for a ‘proposed’ action makes clear that agencies must take the
    required hard look before taking that action.” Oglala Sioux 
    Tribe, 896 F.3d at 532
    ; see also
    Robertson v. Methow Valley Citizens Council, 
    490 U.S. 332
    , 349 (1989) (“The statutory
    requirement that a federal agency contemplating a major action prepare such an environmental
    impact statement serves NEPA’s ‘action-forcing’ purpose . . . .”) (citing Baltimore Gas & Elec.
    Co. v. NRDC, 
    462 U.S. 87
    , 97 (1983); then citing Weinberger v. Catholic Action of Haw., 
    454 U.S. 139
    , 143 (1981)). When it comes to NEPA, it is better to ask for permission than
    18
    forgiveness: if you can build first and consider environmental consequences later, NEPA’s
    action-forcing purpose loses its bite.
    Dakota Access attempts the same workaround of this principle as was offered last time,
    and the Court again finds it unavailing. In 2017, Defendants “argue[d] that vacatur here would
    ‘have greater disruptive consequences than in the typical NEPA case’ because the pipeline has
    already been completed.” Standing Rock 
    IV, 282 F. Supp. 3d at 107
    (citing ECF No. 258 at 12);
    see DA Remedy Br. at 33–34 (“[H]owever one might have quantified what the ‘economic
    disruption’ risk was back then, the potential economic risk now is quantifiable and catastrophic.
    And after almost three years of operations and several court rulings, it has been reasonable for
    Dakota Access, the state of North Dakota, and all the other interested third parties to assume that
    the ‘risk’ of a shutdown would decrease significantly over time.”) The Court’s response to these
    arguments is the same now as then:
    [D]enying vacatur on the basis of alleged economic harm risks
    creating undesirable incentives for future agency actions. If
    projections of financial distress are sufficient to prevent vacatur, the
    Court fears that agencies and third parties may choose to devote as
    many resources as early as possible to a challenged project — and
    then claim disruption in light of such investments. Such a strategy
    is contrary to the purpose of NEPA, which seeks to ensure that the
    government “looks before it leaps.”
    Standing Rock 
    IV, 282 F. Supp. 3d at 106
    (quoting ECF No. 269-1).
    Fourth and finally, such “economic myopia,”
    id. at 105,
    causes Dakota Access to
    “address the ‘potentially disruptive effects of vacatur as if they occur in a vacuum,’ thus giving
    short shrift to the ‘potentially disruptive effects that could flow from remand without vacatur.’”
    Id. at 105
    (quoting Friends of Capital Crescent Trail v. Fed. Transit Admin., 
    218 F. Supp. 3d 53
    ,
    60 (D.D.C. 2016)). As before, “there is no doubt that allowing oil to flow through the pipeline
    during remand risks the potentially disruptive effect about which the Tribes are most
    19
    concerned — a spill under Lake Oahe.”
    Id. Indeed, even
    while “[t]he likelihood of any such
    rupture may be low,”
    id., the impact
    of such a spill has been one of the Court’s central concerns
    throughout the case. See Standing Rock 
    III, 255 F. Supp. 3d at 139
    (“As to the effects from a
    spill (as distinct from the risk of a spill occurring), the EA’s discussion is minimal . . . .”);
    Standing Rock 
    IV, 282 F. Supp. 3d at 105
    (“[T]he possible effects of an oil spill on the Tribes’
    treaty rights and communities were at the center of this Court’s prior Opinion.”). Indeed, while
    the most recent Opinion in this case did not have cause to reach the topic of the impact of a spill
    on tribal hunting and fishing rights, it did spend much time discussing the possibility that, in the
    unlikely event of a spill, systems may not be in place to prevent that spill from becoming
    disastrous. See, e.g., Standing Rock VI, 
    2020 WL 1441923
    , at *10 (discussing unaddressed
    possibility that DAPL’s leak-detection system was incapable of detecting leaks of less than 1%
    of its flow rate, meaning that “6,000 barrels per day” could leak without triggering an alarm);
    id. at *11
    (noting that 30% of spills on pipelines operated by DAPL’s operator occurred outside of
    operator property);
    id. at *11
    –12 (recounting expert concerns that wintertime spill would be
    difficult to contain and had not been sufficiently prepared for in EA). Even assuming the risk of
    a spill remains small, “pausing the operation of the pipeline would mitigate even this small risk.”
    Standing Rock 
    IV, 282 F. Supp. 3d at 105
    .
    One final word here so that the Court may make good on its earlier promise to address
    the two cases offered by Defendant-Intervenor as examples of courts’ declining to vacate when
    faced with an EIS failure. Recall that both cases based their decision not on the first Allied-
    Signal factor, which they found supported vacatur, but on the second. See Oglala Sioux 
    Tribe, 896 F.3d at 538
    ; 
    Semonite, 422 F. Supp. 3d at 99
    –100, 103. In Oglala Sioux Tribe, the D.C.
    Circuit held that this second factor disfavored vacatur simply because a “South Dakota
    20
    permitting requirement independently bar[red] it from moving forward with construction on the
    site until the [agency] complete[d] its compliance with 
    NEPA.” 896 F.3d at 538
    . In Semonite,
    however, there was significant disruption anticipated from vacatur: the district court was
    concerned by “the risk that hundreds of thousands of people will be left with an unreliable power
    source if the permit is 
    vacated.” 422 F. Supp. 3d at 103
    . It would be “unjust,” that court
    reasoned, “to force all of those people to bear the brunt of the harm when they are not
    responsible for its cause.”
    Id. at 102.
    Such is not the case here: the disruption Dakota Access
    focuses on is to its own interests and those of the industry, both of whom relied on the continued
    operation of the pipeline in the face of ongoing litigation as well as changes in the
    administration’s stance on the environmental propriety of the pipeline. The parties do not raise
    any possibility that hundreds of thousands of ordinary citizens will be deprived of a reliable
    source of oil if DAPL is shut down, and, in fact, as already discussed, oil wells are currently
    being closed given a low demand having nothing to do with the pipeline.
    The other reason that the district court in Semonite considered the disruption too weighty
    to ignore was that the removal of the agency project in question — which “would [have]
    involve[d] dismantling seventeen steel lattice towers and removing 37.8 miles of conductor, 8.4
    miles of fiber optic shield wire, 32 solar panels and solar lighting systems, and all associated
    hardware” would have posed a “risk of massive waste” should the Corps ultimately “reissue the
    permit after conducting an 
    EIS.” 422 F. Supp. 3d at 103
    . The Corps admittedly does raise a
    similar removal issue here, pointing out that the dismantling of the pipeline under Lake Oahe
    would lead to “waste of time, energy, and resources, as well as environmental impacts such as
    ground disturbance and increased emissions from heavy construction machinery.” Corps
    Remedy Br. at 17. But the Court is not ordering that such step be taken, and any decision to
    21
    remove is entirely within the Corps’ control. As the agency explains, once the Court vacates the
    easement, the pipeline is considered an “encroachment” on federal lands and can be dealt with in
    one of four ways at the Corps’ discretion. See
    id. at 6.
    Removal is indeed one of those options,
    but so is “outgrant or consent (for easements).”
    Id. (quoting one
    of the Corps’ engineering
    regulations). Removal is therefore not the remedy being considered by the Court today, and it
    may not be the remedy chosen by the Corps in the future. Accord Standing Rock IV, 282 F.
    Supp. 3d at 107 (“Plaintiffs are not asking for the pipeline itself, or for any existing
    infrastructure, to be dismantled.”).
    2. Environmental Disruption
    Dakota Access here attempts to resurrect an unsuccessful argument from the last round of
    remedy briefing. It argues that if DAPL is inoperative, the crude oil must be transported by rail,
    and rail transport has worse environmental consequences than any potential pipeline spill. In
    2017, however, the Court “reject[ed] th[e] argument” that “alternative modes of transport
    required by vacatur, if any, will necessarily increase the risk of an oil spill.”
    Id. at 107.
    Not much has changed this time around. DAPL once again frames the shift to rail
    transportation in speculative terms. Compare
    id. (“Defendants[] assert[]
    that vacatur ‘could
    result in at least some portion’ of the oil being moved via train . . . .”), with Corps Remedy Br. at
    21 (“The Corps cannot state definitively that a particular percentage of the oil currently being
    transported by pipeline would be switched to rail in the event the Pipeline’s easement is
    withdrawn.”). Even assuming that some more oil will be transported by rail than would have
    been without a shutdown, the only new evidence the Corps and DAPL point to is a recent study
    by the Pipeline and Hazardous Materials Safety Administration comparing modes of oil
    transport, which ultimately concluded that “[e]ach mode has its own unique safety risks, and
    22
    more factors or different methodologies need to be considered to comprehensively answer the
    question of which mode is the safest.” ECF No. 507-2 (PHMSA Report) at 9; see
    id. (“Significant knowledge
    gaps exist for the exposure, vulnerability, and consequences of crude oil
    transportation.”). The report did find that, subject to these warnings, pipelines appear to have
    lower spill occurrences and amounts than rail transport.
    Id. While this
    is certainly an
    improvement on the dearth of information provided in the last round of remedy briefing, the
    report’s self-stated limitations do not get Defendants and Defendant-Intervenor much farther
    than before.
    The Court cannot forget, moreover, its responsibility to consider the potential
    environmental disruption of not vacating the easement, which it has discussed at length in prior
    Opinions and recapped above. 
    See supra
    Section III.B.1. On balance, the inconclusive evidence
    of environmental harm from an unknown number of barrels being transferred to rail
    transportation does not move the needle toward remand without vacatur.
    ***
    Putting this all together, the Court finds that vacatur is the only appropriate remedy here.
    The first Allied-Signal prong weighs strongly in its favor, even if the second is a much closer
    call. The Court does not reach its decision with blithe disregard for the lives it will affect. It
    readily acknowledges that, even with the currently low demand for oil, shutting down the
    pipeline will cause significant disruption to DAPL, the North Dakota oil industry, and potentially
    other states. Yet, given the seriousness of the Corps’ NEPA error, the impossibility of a simple
    fix, the fact that Dakota Access did assume much of its economic risk knowingly, and the
    potential harm each day the pipeline operates, the Court is forced to conclude that the flow of oil
    must cease. Not wishing to micromanage the shutdown, it will not prescribe the method by
    which DAPL must achieve this. The Court will nonetheless require the oil to stop flowing and
    23
    the pipeline to be emptied within 30 days from the date of this Opinion and accompanying
    Order. This time period was proposed by the Tribes and should provide sufficient time for the
    pipeline to be shut down in a safe and efficient manner, which is undoubtedly in everyone’s
    interest.
    IV.     Conclusion
    For the foregoing reasons, the Court will vacate the Corps’ decision to grant Dakota
    Access an easement under the Mineral Leasing Act and order that the Dakota Access Pipeline be
    shut down within 30 days. A separate Order consistent with this Opinion shall issue this day.
    /s/ James E. Boasberg
    JAMES E. BOASBERG
    United States District Judge
    Date: July 6, 2020
    24
    

Document Info

Docket Number: Civil Action No. 2016-1534

Judges: Judge James E. Boasberg

Filed Date: 7/6/2020

Precedential Status: Precedential

Modified Date: 7/6/2020

Authorities (25)

airport-neighbors-alliance-inc-a-new-mexico-corporation-v-united-states , 90 F.3d 426 ( 1996 )

foundation-for-north-american-wild-sheep-a-corporation-society-for-the , 681 F.2d 1172 ( 1982 )

TOMAC v. Norton, Gale A. , 433 F.3d 852 ( 2006 )

citizens-against-burlington-inc-v-james-b-busey-iv-administrator , 938 F.2d 190 ( 1991 )

Grand Canyon Trust v. Federal Aviation Administration , 290 F.3d 339 ( 2002 )

will-anderson-fund-for-animals-humane-society-of-the-united-states , 371 F.3d 475 ( 2004 )

Amer Bioscience Inc v. Thompson, Tommy G. , 269 F.3d 1077 ( 2001 )

Town of Cave Creek v. Federal Aviation Administration , 325 F.3d 320 ( 2003 )

Advoc Hwy Auto Sfty v. FMCSA , 429 F.3d 1136 ( 2005 )

Williston Basin Interstate Pipeline Co. v. Federal Energy ... , 519 F.3d 497 ( 2008 )

american-water-works-association-v-environmental-protection-agency , 40 F.3d 1266 ( 1994 )

Sierra Club v. R. Max Peterson, in His Official Capacity as ... , 717 F.2d 1409 ( 1983 )

allied-signal-inc-v-us-nuclear-regulatory-commission-and-the-united , 988 F.2d 146 ( 1993 )

international-union-united-mine-workers-of-america-v-federal-mine-safety , 920 F.2d 960 ( 1990 )

environmental-defense-fund-inc-v-administrator-of-the-united-states , 898 F.2d 183 ( 1990 )

Department of Transportation v. Public Citizen , 124 S. Ct. 2204 ( 2004 )

Weinberger v. Catholic Action of Hawaii/Peace Education ... , 102 S. Ct. 197 ( 1981 )

Humane Soc. of US v. Johanns , 520 F. Supp. 2d 8 ( 2007 )

Sierra Club v. Van Antwerp , 719 F. Supp. 2d 77 ( 2010 )

National Wildlife Federation v. Norton , 332 F. Supp. 2d 170 ( 2004 )

View All Authorities »