A.P. Croll & Son, Inc. v. Clark's General Contractors, Inc. ( 2015 )


Menu:
  •         IN THE SUPERIOR COURT OF THE STATE OF DELAWARE
    IN AND FOR SUSSEX COUNTY
    A.P. Croll & Son, Inc.,                      :     C.A. No.: S13C–07–022 RFS
    Plaintiff                              :
    :
    v.                               :
    :
    Clark’s General Contractors, Inc.,           :
    Defendant                              :
    MEMORANDUM OPINION
    Final Decision and Order
    Date Submitted: January 6, 2015
    Date Decided: April 30, 2015
    Dean A. Campbell, Esquire, Law Office of Dean A. Campbell, LLC,
    Georgetown Professional Park, North Building, 20175 Office Circle, P.O. Box
    568, Georgetown, DE, 19947, Attorney for Plaintiff
    Jeffrey J. Clark, Esquire, Schmittinger & Rodriguez, P.A., 414 S. State
    Street, P.O. Box 497, Dover, DE, 19901, Attorney for Defendant
    STOKES, J.
    1
    Presently before the Court is a breach of contract action brought by
    subcontractor, A.P. Croll & Son, Inc., (“Croll”), against general contractor, Clark’s
    General Contractors, Inc. (“Clark”).            Croll seeks to recover losses sustained
    resulting from work related to site preparation and a paving subcontract related to
    the construction project for Royal Farms in Georgetown, Delaware. Croll alleges
    Clark failed to pay Croll for performance of its obligation in accordance with a
    written construction contract for the completion of highway reconstruction work.
    Croll seeks payment of $24,188.54, plus interest and reasonable attorney’s fees.
    Clark maintains Croll did not perform as contractually obligated and is not entitled
    to recover losses.
    Following the bench trial and upon review of the parties’ post-trial briefs,
    the Court finds Croll is entitled to recover losses sustained in the amount of
    $5,489.57, plus costs and present and past interest.1 This amount accounts for a
    deduction for back fill and top soil, affords set-offs for work performed on Gordy
    Street, the additional stone materials, and the difference between the interest paid
    and simple interest for payments made by Clark to a subcontractor on behalf of
    Croll.
    1
    Interest is to be calculated at the simple legal interest rate. See e.g., O'Riley v. Rogers, 
    2013 WL 4773076
    , at *1 (Del. Super. Sept. 4, 2013) (applying the legal interest rate); see also, David
    L. Finger & Louis J. Finger, Delaware Trial Handbook, § 28.10 (1994).
    2
    FACTS AND PROCEDURAL POSTURE
    In April 2012 Croll entered into a contract, prepared by Clark, in which
    Croll was to perform work related to highway reconstruction in and around Royal
    Farms located in Georgetown, Delaware. 2         The Royal Farms project required
    substantial highway reconstruction work at the intersection of US Route 113
    (“113”) and Route 404 (“404”).3 Along 113, 404, and Gordy Street is where most
    of the work related to the present dispute took place. 4
    Emory Hill was hired to oversee the project and Clark was hired as a general
    contractor to construct the new store. 5 Clark subcontracted with Croll to complete
    roadwork, including site work within the right-of-way as defined by Delaware
    Department of Transportation (“Del Dot”), for the agreed upon amount of
    $298,353.31. 6
    As work progressed, incremental payments were made by Clark to Croll. 7 A
    dispute arose after four applications were paid, totaling $192,880.73, leaving an
    alleged balance of $105,472.58 owed to Croll.8             In July 2013, Croll filed a
    Complaint alleging Clark had breached their contract by failing to pay Croll for
    2
    Pl’s Ex. E.
    3
    
    Id. 4 Id.
    5
    
    Id. 6 Id.
    7
    Pretrial Stipulation and Order at ¶ 3–4.
    8
    Id.; Compl. at ¶ 7.
    3
    work performed. 9 Before trial, most of the disputes raised in the Complaint were
    resolved.
    At this juncture, the parties’ contentions center on a handful of transactions.
    First, Emory Hill paid Croll directly for work related to the back fill and top-soil
    on 404 and 113 and subtracted the amount due, $8,884.50, to Clark. 10 Second,
    Clark paid $11,870 to an alternative contractor, Stanley’s Asphalt, to pave Gordy
    Street and $520.08 for additional stone material to complete work allegedly within
    Croll’s responsibility under the contract. 11 Lastly, Croll disputes the payment
    Clark paid to Shea Concrete, LTD (“Shea”), a party subcontracted by Croll.12
    Croll contends Shea was not entitled to interest in the first instance, and in the
    alternative argues to reduce the amount of interest paid from $2,914.96, calculated
    at a rate of twenty-four percent, to $339.35 in order to reflect interest calculated at
    the legal interest rate.13
    Croll maintains Clark has breached the contract by failing to pay for work
    performed. 14     Defendant Clark asserts Croll failed to perform the work as
    9
    See generally, Compl. (asserting a total sum due to Croll).
    10
    Pl.’s Post Trial Closing Reply Mem. at 1–2; Def.’s Closing Mem. at 2–3.
    11
    Pl.’s Post Trial Closing Reply Mem. at 4–5; Def.’s Closing Mem. at 3–4.
    12
    Pl.’s Post Trial Closing Reply Mem. at 4–5; Pretrial Stipulation and Order at ¶ 4 (alleging
    “Clark paid Shea Concrete $26,522.34 on behalf of Croll”).
    13
    Pl.’s Post Trial Closing Reply Mem. at 4–5.
    14
    See generally, Compl. (seeking damages for failure to pay for work performed); Pl.’s Post
    Trial Closing Reply Mem.
    4
    contractually obligated resulting in a breach of contract.15 As such, Clark asserts
    funds are not due to Croll, and in the alternative that set-offs are due to Clark.16
    Following a bench trial held on November 19, 2014 the Court reserved
    decision pending receipt of post-trial briefs.
    DISCUSSION
    Both parties in this matter have abundant experience; both parties are
    particularly knowledgeable about their chosen profession. Moreover, some of the
    parties involved in this dispute have a history; some parties even have a prior
    course of dealings. In fact, Croll and Clark were known to each other.
    Looking at the issue globally, both sides are not without fault in terms of
    how things fell apart. On Clark’s side of the ledger, an amount of $24,188.54 was
    owed.17 On the other hand, Croll, after making an initial payment failed to pay—
    even the principal amount—which escalated into the demand of interest by Shea at
    a rate of twenty-four percent. 18
    Moreover, with Croll’s knowledge as a subcontractor in this large project
    Croll was aware the bills were paid by Clark in order to obtain a release for the
    15
    Def.’s Closing Mem. at 5.
    16
    
    Id. 17 Pl.’s
    Opening Post Trial Closing Mem. at 2.
    18
    Pl.’s Post Trial Closing Reply Mem. at 4–5.
    5
    Royal Farms project. Although, Croll was not paid in full for the work performed,
    it is not tenable in the trade to fail to pay subcontractors, such as Shea in this case,
    based on the failure to receive all funds due under Delaware law. 19 The evidence
    does not reflect a finding of intent to make Clark’s payment to Croll a condition
    precedent of Croll’s payment to Shea.20 As such, some of the present controversy
    regarding Shea could have been avoided had Croll paid Shea when their right to
    payment matured.
    Turning to contract formation, the contract itself was finalized in April. 21 It
    is important to note Croll’s proposal was submitted one month before the contract
    was finalized.22 The proposal offered more details, including line items, compared
    to the scant contract developed in April by Clark.23 The bottom line of Croll’s
    work was $298,353.31; however, the proposal was not signed by Clark and the
    19
    See e.g.,Worthy Bros. Pipeline Corp. v. Acierno, 
    1996 WL 527347
    , at *2 (Del. Super. July 26,
    1996) aff'd, 
    693 A.2d 1066
    (Del. 1997) (resolving a dispute against a subcontractor raised by a
    paving company finding when a reasonable time expires the paving company’s right to payment
    matures notwithstanding receipt of payment from a general contractor in the absence of an
    unambiguous expression of the parties’ intent to make receipt of payment a condition precedent).
    20
    Pl’s Trial Ex. E; see e.g., Volair Contractors, Inc. v. Coastal Mechanical, Inc.,1986 WL
    13982, (Del. Dec. 1, 1986) at *1 (requiring an unambiguous expression of intent to establish a
    condition precedent).
    21
    Pretrial Stipulation and Order at ¶ 1.
    22
    Pl’s Trial Ex. C.
    23
    
    Id. 6 scope
    of work in the resulting contract was different. 24 Accordingly, the Court
    finds the proposal is a mere offer and is not a contract. 25
    After analyzing the record, it is clear the April agreement did not adopt the
    proposal, nor was the proposal incorporated by reference.26                    Consistent with
    Delaware law, the Court finds Croll’s proposal was an offer that was not accepted
    because the terms were not identical.27 Instead, Clark presented a counter-offer,
    the contract at issue, which became a contract when Croll accepted the terms as
    evidenced by their signed agreement.28               Under Delaware law, Croll accepted
    Clark’s counter-offer by manifesting intent to be bound by Croll’s terms in
    consideration for payment for work performed forming a valid contract. 29
    Prior to signing a binding contract, both parties ought to have been aware of
    the scope of work the contract entailed before electing to be bound by the terms.
    To a certain extent, the parties were cautious enough to include a modification
    24
    Compare Pl’s Trial Ex. C, with, Pl’s Trial Ex. E.
    25
    See e.g., Blakeley v. Scanlon, 
    604 A.2d 416
    (Del. 1991) (holding “[u]nder Delaware law, it is
    an elementary principle that an acceptance of an offer, in order to be effectual, must be identical
    with the offer and unconditional. One aspect of the principle is stated in Restatement, Contracts,
    § 60: “A reply to an offer, although purporting to accept it, which adds qualifications or requires
    performance of conditions, is not an acceptance but is a counter offer.” (internal citations
    removed) (emphasis removed)).
    26
    Compare Pl’s Trial Ex. C, with, Pl’s Trial Ex. E.
    27
    See generally, Friel v. Jones, 
    206 A.2d 232
    , 233 (Del. Ch. 1964); see also, 1 Arthur L. Corbin,
    Corbin on Contracts § 82 (1963).
    28
    Id.; see also, Pl’s Trial Ex. E.
    29
    
    Friel, 206 A.2d at 233
    .
    7
    clarifying their responsibilities with respect to the south side of 404; however, the
    parties failed to delineate the specifics for the remainder of the project. 30
    The modification itself does not define the sole limitation of Croll’s
    expected work performance. 31          As such, it is difficult at this latent stage to
    determine the total expected scope of work performance based on the four-corners
    of the contract alone. 32 The general idea seems to be Croll would do the outside
    work because Croll had the Del Dot experience, Clark would do the inside work,
    and Del Dot presumably would submit approvals along the way. 33
    To the extent the parties’ intent can be ascertained and aligned with the
    simple facts giving meaning to the contract, the contract will dictate the outcome
    of the controversy. 34 Where the contract is highly susceptible to different
    interpretations by a reasonable person in the parties’ position, the contract shall be
    interpreted against the drafter, Clark. 35
    30
    Pl’s Trial Ex. E. (containing the following handwritten script, “on south side of 404 only”
    under a diagonal dash from the work sidewalks followed by the capital letters “CT”).
    31
    
    Id. 32 Id.
    33
    Def.’s Closing Mem. at 2; Shea Dep. 28:17–19.
    34
    Holland v. Hannan, 
    456 A.2d 807
    , 815 (D.C. 1983) (adopting the principle “[a contract] is not
    ambiguous where the court can determine its meaning without any other guide than a knowledge
    of the simple facts on which, from the nature of language in general, its meaning depends”)
    (quoting Burbridge v. Howard Univ., 
    305 A.2d 245
    , 247 (D.C. 1973)).
    35
    Rhone-Poulenc Basic Chemicals Co. v. Am. Motorists Ins. Co., 
    616 A.2d 1192
    , 1196 (Del.
    1992) (explaining the doctrine of contra proferentum which requires ambiguous language to be
    construed against the drafter).
    8
    BACK FILL AND TOP SOIL
    Croll refused to do the work accounting for the back fill and top soil on 404
    and 113 without a separate payment. 36 As a result, Emory Hill paid Croll directly
    and thusly reduced the amount paid to Clark. 37 Back fill and top soil work was
    required between the curb and the sidewalk. 38 This work is not clearly spelled out
    in the contract, but this work is alluded to in the contract by the term “top soil and
    seeding” and as necessary components to the related work. 39 According to contra
    proferentem this portion of the contract would be interpreted against Clark,40
    however; Croll’s interpretation of the contract is not reasonable when looking at
    the simple facts. 41
    Under Delaware law, a court need not adopt an interpretation of a contract
    “contrary to both the plain meaning of the document and logic, and to reach an
    absurd, unfounded result.”42         After careful analysis of the record, Croll’s
    interpretation is unreasonable. The contract outlining Croll’s duty to perform
    states: “the highway reconstruction work within right away of U.S. 113, Route
    36
    Def.’s Closing Mem. at 2.
    37
    
    Id. 38 Id.;
    see also, Def.’s Ex. 1.
    39
    Pl’s Trial Ex. E.
    40
    Rhone-Poulenc Basic Chemicals 
    Co., 616 A.2d at 1196
    .
    41
    Pl.’s Post Trial Closing Reply Mem. at 2–3.
    42
    Osborn ex rel. Osborn v. Kemp, 
    991 A.2d 1153
    , 1160 (Del. 2010).
    9
    18/404 Gordy road necessary…top soil and seeding” [sic]. 43 The top soil and
    backfill work in dispute were necessary highway reconstruction work for this
    project located between the curb and the line of construction, thus within the right
    of way indicated in the contract. 44 Accordingly, performing back fill and top soil
    work appear to be within Croll’s duty to perform under this contract. 45
    Moreover, finding back fill and top soil work within Croll’s responsibility is
    consistent with the bulk of evidence provided in the record. The record provides
    testimony from Emory Hill, testimony from Del Dot representatives, e-mail
    correspondence between Emory Hill and Croll, and Croll’s own testimony that
    bolster the reasonableness of this interpretation. 46 As such, a reasonable person in
    the parties’ position would have interpreted the contract as defining the back fill
    and top soil work within Croll’s responsibility, as did “everyone on the project,
    with purportedly the exception of Croll.” 47 Thus, the Court finds set-off in the
    amount of $8,884.50 will be charged against Croll as Emory Hill back-charged the
    same amount to Clark.
    43
    Pl.’s Trial Ex. E.
    44
    Def.’s Ex. 1.
    45
    
    Id. 46 Def.’s
    Closing Mem. at 2–3 (providing a detailed description of the testimony at trial and
    quoting the following pertinent portion of the e-mail correspondence between an Emory Hill
    representative and Croll: “[i]n talking with the DelDOT inspector the area along RT 113 up to
    the LOC is perceived as the DelDot ROW and based on this AP Croll would own the top soil
    between the curb and the LOC line”).
    47
    Def.’s Closing Mem. at 3.
    10
    GORDY STREET
    Croll disputes whether there was a duty under the contract to perform the
    paving work on Gordy Street. 48 Essentially, Croll asserts Gordy Street is not a
    ‘highway,’ therefore work on Gordy Street could not be considered necessary
    highway reconstruction work.49
    Generally, “[c]ourts will not torture contractual terms to impart ambiguity
    where ordinary meaning leaves no room for uncertainty.” 50 Here, at issue is the
    term highway. The Delaware Court of Chancery held the word highway “is a
    “generic name for all kinds of public ways including country and township roads,
    streets, and alleys.” 51 The Court finds a reasonable person in the parties’ position
    would interpret the term highway to include Gordy Street. With this reading, Croll
    was under a contractual obligation to perform paving on Gordy Street.
    Additionally, the contract specifically refers to “Gordy Street” and “asphalt
    paving.”52    These references combined with the parties’ respective course of
    performance indicate Croll was under a duty to perform site work on Gordy
    48
    Pl.’s Post Trial Closing Repy Mem. at 3.
    49
    
    Id. 50 Zullo
    v. Smith, 
    427 A.2d 409
    , 412 (Conn. 1980).
    51
    Scureman v. Judge, 
    626 A.2d 5
    , 11 n.3 (Del. Ch. 1992) aff'd sub nom. Wilmington Trust Co. v.
    Judge, 
    628 A.2d 85
    (Del. 1993).
    52
    Pl.’s Trial Ex. E.
    11
    Street. 53 The work performed on the north and south side of Gordy Street in
    accordance with the state inspection also dovetails with the general intent of the
    parties who collaborated in order to capitalize on Croll’s expertise in working with
    Del Dot.54
    Croll did the preparatory work 55 for the road but failed to pave it.56 The
    proffered reason at trial—Croll did the work gratuitously—is not persuasive and
    inconsistent with the evidence on the record. 57 Moreover, Croll had the billings for
    this work yet did not object to the work itself, only the interest rate as to Shea.58
    As such, the contract, logic, course of performance, and trade norms demonstrate a
    reasonable mind would interpret Croll’s responsibilities under the contract as
    including paving and other necessary work on Gordy Street.
    Following this reasonable interpretation and the course of performance of
    the parties, Croll was under a duty to perform the work on Gordy Street and Clark
    is due a set-off of $11,870.
    53
    Id.; see also, Def.’s Closing Mem. at 3–4.
    54
    Def.’s Closing Mem. at 3; Shea Dep. 28:17–19 (demonstrating “[e]verybody just knew Croll
    was doing the state work and I [, Shea,] was doing the curb work for them”).
    55
    Shea Dep. 34:13–19 (attributing the following work to Croll: “demo[ing] the existing concrete,
    roto-mill[ing] the street to get the blacktop out of the way,” getting the “sub-base ready, put[ing]
    the stone in, which is required by the state under my work”).
    56
    Def.’s Closing Mem. at 3–4.
    57
    
    Id. 58 Id.
                                                    12
    ADDITIONAL MATERIAL REQUIRED TO FILL RIGHT-OF-WAY
    With respect to the additional materials, the 22 tons of stones, Clark will also
    be afforded a set-off in the amount of $520.08. 59                     This amount has been
    unchallenged by Croll and the stones were an anticipated expense related to the
    project.60
    INTEREST PAYMENT TO SHEA
    It is undisputed that Clark paid money owed to a subcontractor, Shea, on
    behalf of Croll.61 Ultimately, at issue before the Court is the past-due interest paid
    by Clark to Shea totaling $2,914.96.62 Croll contends there was not a specified
    contractual term which entitled Shea to a payment of interest. 63 Thusly, Croll
    maintains Clark wrongfully paid Shea interest because he was not entitled to any
    interest per their contractual arrangement. 64             Croll disputes the entire interest
    payment made to Shea, and in the alternative seeks a set-off utilizing an alternative
    59
    
    Id. at 4–5.
    60
    
    Id. 61 Pl.’s
    Post Trial Closing Br. at 4–5; Pretrial Stipulation and Order at ¶ 4 (alleging “Clark paid
    Shea Concrete $26,522.34 on behalf of Croll”).
    62
    Pl.’s Post Trial Closing Reply Mem. at 4–5.
    63
    
    Id. 64 Id.
                                                     13
    interest rate. 65   The interest payment was calculated at a rate of twenty-four
    percent. 66 Croll suggests employing the legal interest rate of 5.75 percent. 67
    Generally, “[i]nterest is money awarded to a successful plaintiff in a civil
    action beyond the amount of the judgment to compensate the plaintiff for
    additional losses resulting from being deprived of the use of the money during the
    period between the injury and payment.” 68 Here, Shea, although not a party to this
    case, ordinarily would be entitled to interest for being deprived of the use of money
    while awaiting payment.69
    After establishing that interest was due to Shea in the ordinary course of
    business, the question remaining is what interest rate should be applied. 70 This
    Court has held interest should be calculated using the same rate when possible.71
    As interest is due to Croll at the legal interest rate, the interest rate for this dispute
    shall be calculated at the same rate. 72 As such, the Court finds Croll is responsible
    65
    
    Id. 66 Id.
    67
    Id.; see also, O'Riley, 
    2013 WL 4773076
    , at *1 (explaining “[t]he rate of interest allowed in
    actions at law generally is equated to the ‘legal rate’ of interest described in 
    6 Del. C
    . § 2301
    (quoting David L. Finger & Louis J. Finger, Delaware Trial Handbook, § 28.10 (1994))).
    68
    O'Riley, 
    2013 WL 4773076
    , at *1.
    69
    
    Id. 70 Id.
    71
    
    Id. (holding interest
    should be calculated using the same rate rather than two separate rates
    referring to pre-judgment and post-judgment interest).
    72
    
    Id. 14 for
    past-due interest calculated at the legal interest rate.73 Utilizing the legal
    interest rate would reduce the interest amount from $2,914.96 to $339.35.74 As
    such, a set-off for will be afforded to Croll in the amount of $2,575.61.
    CONCLUSION
    For the foregoing reasons, an award of $5,489.57, accounting for the above-
    mentioned set-offs, plus costs and present and past interest calculated at the legal
    interest rate is to be entered for Plaintiff, Croll.
    IT IS SO ORDERED
    /s/ Richard F. Stokes
    ________________________
    Richard F. Stokes, Judge
    cc: Prothonotary
    73
    
    Id. 74 Pl.’s
    Post Trial Closing Reply Memo. at 4–5.
    15