Erosion Control Specialists, Inc. v. Hyetts Corner, LLC ( 2020 )


Menu:
  •      IN THE SUPERIOR COURT OF THE STATE OF DELAWARE
    EROSION CONTROL SPECIALISTS,              )
    INC.,                                     )
    )   C.A. No. N19L-06-082 MAA
    Plaintiff,               )
    )
    v.                            )
    )
    HYETTS CORNER, LLC,                       )
    )
    Defendant.               )
    Submitted: February 6, 2020
    Decided: March 6, 2020
    Upon Defendant Hyetts Corner, LLC’s Motion to Dismiss Mechanic’s Lien and
    Building Construction Payments Act Claims: Granted
    MEMORANDUM OPINION
    G. Kevin Fasic, Esquire, of OFFIT KURMAN, P.A., Wilmington, Delaware,
    Attorney for Plaintiff.
    Richard L. Abbott, Esquire, of ABBOTT LAW FIRM, LLC, Hockessin, Delaware,
    Attorney for Defendant.
    Adams, J.
    1
    This action involves the applicability of Delaware mechanic’s lien statute, 
    25 Del. C
    . § 2701 et seq. and the Building Construction Payments Act, 
    6 Del. C
    . § 3501
    et seq. (the “BCPA”). At the crux of this case is whether a mechanic’s lien should
    attach to seven open lots (the “Lots”), situated in the residential subdivision known
    as “Enclave at Hyetts Crossing” in Middletown, Delaware, based on work performed
    by Plaintiff Erosion Control Specialists (“ECS”) on open spaces within that
    development.
    Put simply, ECS argues that because it performed work on the open spaces,
    which benefitted the community generally, a mechanic’s lien should attach to the
    Lots. ECS also argues it is entitled to compensation under the BCPA. Defendant
    Hyetts Corner LLC (“Hyetts”) moves to dismiss the Complaint, in part, on the
    grounds that the mechanic’s lien statute and the BCPA do not apply to the facts
    alleged in the Complaint. For the reasons stated herein, the Court grants Hyetts’
    Motion to Dismiss Counts I-VII and Count X of the Complaint.1
    1
    While the Court’s decision was pending in this case, another Judge on this Court
    issued a decision with respect to nearly identical issues, involving the same attorneys
    and same defendant, in Pearce & Moretto, Inc. v. Hyetts Corner, LLC, 
    2020 WL 532748
    (Del. Super. Jan. 31, 2020) (“Pearce & Moretto”). Counsel for Defendant
    brought the decision to the Court’s attention on February 6, 2020. The result in this
    Opinion is consistent with the Court’s ruling in Pearce & Moretto.
    2
    FACTS AND PROCEDURAL BACKGROUND
    The following facts are drawn from the pleadings and the record currently
    before the Court, viewed in the light most favorable to ECS. 2 ECS filed its
    Complaint on June 25, 2019 against Hyetts seeking a mechanic’s lien on seven
    residential building lots situated in the residential subdivision known as “Enclave at
    Hyetts Crossing” (hereinafter “Enclave”).3 ECS’s Complaint also included claims
    for breach of contract, quantum meruit/unjust enrichment and a breach of the BCPA.
    According to the Complaint, ECS was hired to perform landscaping services
    for two separate housing developments: Windsor Commons at Hyetts Corner, and
    Windsor South at Hyetts Corner (now known as the Enclave). 4 During oral
    argument, ECS described the work it performed as “landscaping,”5 and admitted that
    the work was performed on open spaces in the development, and not on any of the
    Lots.
    2
    See GMG Capital Investments v. Athenian Venture Partners, 
    36 A.3d 776
    , 779
    (Del. 2012) (citing State Farm Mut. Auto. Ins. Co. v. Patterson, 
    7 A.3d 454
    , 456
    (Del. 2010)).
    3
    Counts I through VII of the Complaint represent the seven Lots at issue: Lot 40,
    Lot 42, Lot 46, Lot 47, Lot 48, Lot 49 and Lot 50. ECS seeks a lien in the amount
    of $1,196.14 for each lot. Hyetts tendered payment to discharge the lien against Lot
    40. See Def.’s Petition to Discharge Mechanics Lien Against Lot 40. (Transaction
    ID 64303726).
    4
    The development has 84 lots, 77 of which had either been sold to homeowners or
    had been transferred to other developers at the time of oral argument. The remaining
    Lots at issue are owned by Defendant.
    5
    Tr. at 23:4.
    3
    Between April 2015 and November 2017, ECS invoiced all work to an entity
    known as CCM-Koelig II, LLC. ECS was then directed to break out invoicing for
    certain landscaping work and begin invoicing Hyetts Corner, LLC, but to continue
    to bill for work impacting both developments through the CCM entity. ECS
    continued to perform work at both developments but invoiced its work separately to
    the different entities at the direction of the owner. While ECS has received partial
    payments from Hyetts for its work at the Enclave, $100,490.14 remains unpaid as of
    the date of the filing of the Complaint.
    On August 9, 2019, Hyetts filed a Motion to Dismiss Counts I through VII
    and Count X of the Complaint on the grounds that ECS could not state a claim for
    mechanics’ liens or under the BCPA. Briefing on the Motion to Dismiss was
    complete on October 15, 2019. The Court heard oral argument on November 22,
    2019. On February 6, 2020, Hyetts filed its letter to the Court regarding the Pearce
    & Moretto decision.
    ANALYSIS
    When considering a motion to dismiss, the Court must read the complaint
    generously, accept all of the well-pleaded allegations contained therein as true, and
    draw all reasonable inferences in a light most favorable to the non-moving party.6
    6
    In re Gen. Motors (Hughes) S’holder Litig., 
    897 A.2d 162
    , 168 (Del. 2006);
    Lagrone v. Am. Mortell Corp., 
    2008 WL 4152677
    , at *4 (Del. Super. Sept. 4, 2008).
    4
    “Dismissal is inappropriate unless the ‘plaintiff would not be entitled to recover
    under any reasonably conceivable set of circumstances susceptible of proof.’”7 The
    motion will be denied when the plaintiff is able to prove facts entitling plaintiff to
    relief. 8 However, “[w]here allegations are merely conclusory ... (i.e., without
    specific allegations of fact to support them) they may be deemed insufficient to
    withstand a motion to dismiss.”9
    I.    ECS fails to state a claim for a mechanic’s lien.10
    The availability of a mechanic’s lien is governed by 
    25 Del. C
    . § 2702(a):
    It shall be lawful for any person having performed or furnished labor or
    material, or both, to an amount exceeding $25 in or for the erection,
    alteration or repair of any structure, in pursuance of any contract,
    express or implied, with the owners of such structure or with the agent
    of such owner or with any contractor who has contracted for the
    erection, alteration or repair of the same and for the furnishing of the
    whole or any part of the materials therefor, including any person who
    has performed or furnished labor or material, or both, for or at such
    structure under a contract with or order from any subcontractor to
    7
    In re Gen. Motors (Hughes) S’holder 
    Litig., 897 A.2d at 168
    (quoting Savor, Inc.
    v. FMR Corp., 
    812 A.2d 894
    , 896–97 (Del. 2002)). See also Cent. Mortgage Co. v.
    Morgan Stanley Mortgage Capital Holdings LLC, 
    27 A.3d 531
    , 535 (Del. 2011).
    8
    Spence v. Funk, 
    396 A.2d 967
    , 968 (Del. 1978) (citations omitted).
    9
    Lord v. Souder, 
    748 A.2d 393
    , 398 (Del. 2000).
    10
    ECS conceded during oral argument that it was proceeding only under Section
    2702(a) and that it cannot meet the requirements of Section 2703 (for improvements
    to the land alone) due to a lack of the proper metes and bounds description in Exhibit
    “A” of the Complaint. Therefore, Section 2703 does not apply. Tr. at 51:6- 51:20.
    5
    obtain a lien upon such structure and upon the ground upon which the
    same may be situated or erected.
    The right to a mechanic’s lien is a creation of statute and “being in derogation of the
    common law, it must be strictly construed....”11 “Strict compliance with the statute
    is required as powerful relief is afforded that was unavailable at common law.”12
    Section 2702(a) provides that anyone who has provided labor and/or materials for
    the erection, alteration or repair of any structure may seek a mechanic’s lien for non-
    payment.13
    This Court has emphasized its limited judicial role with respect to interpreting
    Section 2702(a):
    Both our inclination and conviction of duty, therefore, is not to extend
    the operation of the act by construction any further than the terms of it
    clearly require, and to leave it to the legislature to remedy whatever
    defect or deficiencies may be found to attend it when put into practical
    operation and effect. We are therefore not to stretch the act beyond the
    limit fixed by it.14
    This limitation is appropriate considering the nature of the remedy the mechanic’s
    lien statute provides: “Statutory provisions permitting the summary enforcement of
    11
    Wyoming Concrete Indus., Inc. v. Hickory Commons, LLC II, 
    2007 WL 53805
    , at
    *2 (Del. Super. Jan. 8, 2007) (citing Dep’t of Cmty. Affairs & Econ. Dev. V.M. Davis
    & Sons, Inc., 
    412 A.2d 939
    , 942 (Del. 1980)).
    12
    J.O.B. Constr. Co. v. Jennings & Churella Servs., Inc., 
    2001 WL 985106
    (Del.
    Super.) (Del. Super. Aug. 9, 2001).
    13
    Wyoming Concrete Indus., 
    2007 WL 53805
    , at *2.
    14
    McCartney v. Buck, 
    12 A. 717
    , 719 (1887) (quoting Capelle v. Baker, Del. Super.,
    3 Houst. 344, 356 (1866)).
    6
    private charges, such as mechanics’ liens, on property without the consent of the
    owner or judicial sanction cannot be extended in their operation beyond the plain
    and fair sense of the terms in which they are expressed.”15
    The case law interpreting the mechanic’s lien statute makes clear that the
    statute permits a lien against a building and land for the value of the labor and
    materials that “actually” become part of the structure.16 A “structure” is defined
    under 
    25 Del. C
    . § 2701(3) as “a building or house.” The Supreme Court of
    Delaware clarified that this definition is narrow:
    Since the term “house, building, or structure” is now simply “structure,”
    we must give it the limited definitional meaning intended by the
    codifiers as it appears in the mechanic’s lien laws, not the broad
    dictionary meaning.... In normal day to day usage, structure is one of
    the broadest words in the English language, but here, under the statutory
    rule of strict construction we must apply it as it appears in the context
    of [ ] our mechanic[’s] lien laws.17
    Thus, integral to every claim for a mechanic’s lien is the identification of the
    “structure” against which the lien is sought.18
    15
    Heitz v. Sayers, 
    113 A. 901
    , 902 (Del. Super. 1921) (quoting Phillips on
    Mechanics’ Liens, § 18).
    16
    Girdler Corp. v. Delaware Compressed Gas Co., 
    183 A. 480
    , 482 (1936) (holding
    that claimant who performed engineering services was not entitled to a lien since the
    services performed did not “actually” become part of the building).
    17
    Pioneer Nat. Title Ins. Co. v. Exten Assocs., Inc., 
    403 A.2d 283
    , 285 (Del. 1979).
    18
    Kershaw Excavating Co. v. City Sys., Inc., 
    581 A.2d 1111
    , 1113 (Del. 1990).
    7
    ECS argues that, under the statute, site work on a parcel can be considered as
    benefiting individual structures to be constructed, so long as the value of the work is
    apportioned among the structures. ECS contends, citing Wilmington Tr. Co. v.
    Branmar, Inc.,19 that because the Lots in question are intended to have houses built
    upon them, a mechanic’s lien can be imposed on the Lots for the services ECS
    provided.
    Although not stated in the Complaint, ECS agrees that the labor at issue was
    completed on “open spaces” and not on the specific seven Lots in question.20 ECS
    provided landscaping services, such as hydroseeding and mowing, and materials,
    including various plants.21 According to ECS, the services performed by it on open
    spaces within the Enclave development benefitted all lots equally.22
    Hyetts argues that a mechanic’s lien is not available to ECS because the work
    performed on the open spaces lacks a nexus with a structure on any of the seven Lots
    at issue.23 Therefore, because there was no work performed on any of the seven
    Lots and none of the Lots have a structure on them, Section 2702 is not satisfied and
    ECS’s mechanic’s lien claim must be dismissed.
    19
    
    353 A.2d 212
    , 216 (Del. Super. 1976).
    20
    Tr. at 33:20 – 34:11.
    21
    Compl. ¶ 24.
    22
    Compl. ¶ 5.
    23
    Motion to Dismiss at 3-4.
    8
    The parties acknowledged at oral argument that no contract exists for the work
    that ECS performed, and therefore 
    25 Del. C
    . § 2703 (regarding improvements to
    the land alone) does not apply.24 Therefore, in order to fall within the scope of the
    mechanic’s lien statute, ECS must satisfy the requirements of 
    25 Del. C
    . § 2702(a)
    and show that the services were provided in relation to a “structure.”25
    Because of the similarity between the claims in the Pearce & Moretto
    complaint and the claims in this action, the Court’s recent ruling in Pearce &
    Moretto is instructive. 26    In that case, the plaintiff was hired “to perform
    infrastructure construction services” for two housing developments, Windsor
    Commons at Hyetts Corner and Windsor South at Hyetts Corner – the same
    developments at issue in this action.27 The plaintiff sought a mechanic’s lien for
    seven open lots in the Enclave (the same seven Lots at issue here) as well as a claim
    for an alleged violation of the BCPA, among others.28 The defendant argued that
    plaintiff failed to state a claim for a mechanic’s lien because the lots on which they
    sought liens were “vacant and undeveloped.”29 Therefore, any lien would need to
    24
    Tr. at 40:16-40:22.
    25 Pearce & Moretto, 
    2020 WL 532748
    , at *2.
    26
    
    Id. at *1.
    27
    Compl. ¶ 4. The Windsor South development is now known as the Enclave at
    Hyetts Crossing, and is referred to in this decision as the “Enclave.”
    28
    Again, the claims in the Pearce & Moretto action are virtually identical to those
    in this action.
    29
    Pearce & Moretto, 
    2020 WL 532748
    , at *1.
    9
    be based on improvements to the land alone, requiring a contract in conformity with
    
    25 Del. C
    . § 2703.
    The Court began its analysis by first determining whether the services
    provided by the plaintiff were to the land alone or whether they were provided in
    relation to any structure (i.e., the future houses that may be built on the vacant lots).
    After reviewing the scant case law interpreting the term “structure” under the
    mechanic’s lien statute, the Court concluded that the work the plaintiff performed
    there “must be considered an improvement to land, rather than an improvement to
    structure.”30 The Court also held that its “decision cannot be based on what may
    occur in the future, but what was occurring at the time the work was performed.” 31
    The Court then dismissed plaintiff’s mechanic’s lien claims because the contract at
    issue did not include a description of the metes and bounds, and therefore did not
    meet the requirements of Section 2703.
    Consistent with the decision in Pearce & Moretto, this Court finds that ECS
    has not alleged any relationship between the landscaping work performed and an
    existing structure.32 ECS’s argument is as follows: ECS performed landscaping
    work to the common area of the Enclave, and because the common area benefits all
    30
    
    Id. at *3.
    31 
    Id. at *3.
    32
    For purposes of clarity, and because some of the arguments made at oral argument
    differ slightly from this argument, the Court will address those issues in this Opinion.
    10
    lots within the Enclave equally, a mechanic’s lien can attach to each of the Lots at
    issue because they will one day have a house (i.e. a structure) built upon them.
    ECS’s claim for a mechanic’s lien under these circumstances is even more
    attenuated than in Pearce & Moretto. The Enclave is comprised of multiple lots,
    without any presently built homes or townhouses on the seven Lots at issue. Cases
    analyzing the term “structure” in the context of a mechanic’s lien have interpreted
    this term to include only houses and other buildings permanently situated or erected
    upon the land. 33   The lien obtainable upon the structure “may be extended, but
    limited to, labor and materials furnished in connection with those items specifically
    set forth in 
    25 Del. C
    . § 2702(b), as being necessary to or a component part of the
    house or building.”34
    33
    Earl D. Smith, Inc. v. Carter, 
    1998 WL 283379
    , at *1 (Del. Super. Feb. 17, 1998)
    (The claims were dismissed for failure to apportion the cost among the relevant
    structures, noting plaintiff did not plead a contract in conformity with section 2703
    and thus dismissed any additional claims based on improvements to land alone);
    C&J Paving, Inc. v. Hickory Commons, LLC, 
    2006 WL 3898268
    , at *1-2 (Del.
    Super. Oct. 6, 2006) (a mechanic’s lien based on paving and curbing of the streets
    within a vacant development must be considered an improvement solely to the land
    because no houses, buildings, or other structures had been built in the development
    and therefore section 2703 would apply, requiring a contract); Jones v. Julian, 
    195 A.2d 388
    , 390, 
    56 Del. 587
    (Del. 1963) (services performed by a subcontractor in
    “paving around a motel” were not considered improvements to the land alone
    because the work related to the general contractor’s construction of improvements
    to the motel, indicating contract requirements for mechanic’s lien based on
    improvements to land alone are not applicable).
    34
    Pioneer Nat. Title Ins. Co. v. Exten Assocs., Inc., 
    403 A.2d 283
    , 286 (Del. 1979).
    11
    ECS fails to show that the labor and materials used on the open spaces were
    necessary or component parts of any existing structure. ECS admits that the work
    was performed only on open spaces at the Enclave and that the Lots at issue did not
    have completed structures (i.e. houses) at the time services were rendered.35 The
    mechanic’s lien statute – which must be construed strictly – cannot be so flexible as
    to pertain to landscaping services performed on “open spaces” within a residential
    development and such a decision would stretch the statute “beyond the plain and fair
    sense of the terms” in the statute. 36     Therefore, the statute cannot apply to
    landscaping services on open spaces not connected to the Lots, especially when the
    Lots sit empty and undeveloped.37 Therefore, ECS’s mechanic’s lien claims are
    dismissed.
    35
    ECS admits that the Complaint specifically states “open spaces” without including
    the seven Lots themselves as the area that was allegedly serviced. Tr. at 34:7. ECS
    points to the invoice of services attached to the Complaint as Exhibit “C;” however,
    the invoices merely show the services rendered, not where the work was performed
    on the actual Lots at issue. See also Compl. ¶¶ 15, 26, 38, 50, 62, 74, 86.
    36
    
    Heitz, 113 A. at 902
    . Because the parties acknowledged at oral argument that no
    such contract existed, the Court need not reach any arguments made regarding
    Section 2702(b) and 2703. The decision in Pearce & Moretto makes clear that a
    contract is required under Section 2703, and because ECS admits that no such
    contract exists, ECS’s complaint can be dismissed on this ground as well.
    37
    Pearce & Moretto, 
    2020 WL 532748
    , at *2 (“[T]he Court believes the decision
    cannot be based on what may occur in the future, but what was occurring at the time
    the work was performed.”).
    12
    II.    ECS fails to state a claim under the Building Construction Payments Act.
    The pertinent part of the BCPA states:
    All moneys or funds received by a contractor in connection with a
    contract for the erection, construction, completion, alteration or repair
    of any building or for additions to a building and all moneys or funds
    received by a contractor in connection with a contract for the sale of
    land and the erection, construction, completion, alteration or repair of
    any building or addition thereon, shall be trust funds in the hands of the
    contractor. 38
    The arguments made here regarding the applicability of the BCPA are identical to
    those made in Pearce & Moretto. 39 Hyetts argues that ECS does not meet the
    definition of “contractor” under the BCPA because ECS did not perform the work
    on any building or structure on the Lots.40 ECS counters that it meets the definition
    of contractor under the BCPA because their services related to individual structures
    that will be built in the future.41
    The Court is not persuaded by ECS’s arguments. As this Court recently held,
    there are two possible ways to meet the definition of contractor under the BCPA:
    “(1) to furnish labor and/or materials in connection with the erection, construction,
    38
    
    6 Del. C
    . § 3502.
    39
    Pearce & Moretto, 
    2020 WL 532748
    , at *4-5.
    40
    Tr. at 18:6- 18:17.
    41
    Tr. at 27:19 – 27:21; Pl.’s Resp. in Opp’n to Def.’s Mot. to Dismiss ¶ 11, citing
    Earl D. Smith, Inc. v. Carter, 
    1998 WL 283379
    , at *1 (Del. Super. Feb. 17, 1998).
    13
    completion, alteration or repair of any building or for additions to a building; or (2)
    for the sale to such other person of any lands and premises upon which such
    contractor undertakes to erect, construct, complete, alter or repair any building or
    addition to a building.”42
    The BCPA “is unambiguous and its plain language states that the statute only
    applies to the construction of buildings.”43 The United States District Court for the
    District of Delaware addressed this same question in VSI Sales, LLC v. Griffin Sign,
    Inc., stating that the legislature consistently used the terminology building and
    construction throughout the Act “thereby reinforcing the fact that the law only
    applies to building construction work.” 44 This same position was reinforced in
    Pearce & Moretto, where the Court held that the BCPA does not apply to services
    rendered solely to the improvement of land.45
    Therefore, the Court will grant Hyetts’ Motion to Dismiss Count X of the
    Complaint. It is clear that the BCPA pertains to contracts for the sale of land and
    the work performed in relation to the any buildings thereon. There is no building
    situated on any of the seven Lots or in the open spaces alleged in the Complaint.
    Therefore, the statute does not apply under the facts asserted here.
    42
    Pearce & Moretto, 
    2020 WL 532748
    , at *4 (citing 
    6 Del. C
    . § 3501(2)).
    43
    VSI Sales, LLC v. Griffin Sign, Inc., 
    2014 WL 1653271
    , at *2 (D. Del. Apr. 25,
    2014).
    44
    
    Id. 45 Pearce
    & Moretto, 
    2020 WL 532748
    , at *4-5.
    14
    CONCLUSION
    For the reasons stated herein, Defendant’s Motion to Dismiss Counts I-VII
    and Count X of the Complaint is GRANTED. IT IS SO ORDERED.
    15