Keep Our Wells Clean v. Department of Natural Resources and Environmental Control ( 2020 )


Menu:
  • SUPERIOR COURT
    OF THE
    STATE OF DELAWARE
    E. SCOTT BRADLEY
    JUDGE
    Kenneth T. Kristl, Esquire
    Environmental & Natural Resources
    Law Clinic
    Widener University Delaware Law
    School
    4601 Concord Pike
    Wilmington, DE 19803
    1 The Circle, Suite 2
    GEORGETOWN, DE 19947
    March 19, 2020
    Devera B. Scott, Esquire
    Kayli H. Spialter, Esquire
    State of Delaware
    Department of Justice
    102 W. Water Street, Third Floor
    Dover, DE 19904
    R. Judson Scaggs, Jr., Esquire
    Barnaby Grzaslewicz, Esquire
    Morris, Nichols, Arsht & Tunnell LLP
    1201 North Market Street
    P.O. Box 1347
    Wilmington, DE 19899-1347
    Re: Keep Our Wells Clean, et al. v. Department of Natural
    Resources and Environmental Control, et al.
    Case No. S19A-07-002-ESB
    Dear Counsel:
    This is my decision on the appeal filed by Appellant Keep Our Wells Clean
    (“KOWC”)! of the Environmental Appeals Board’s decision affirming the decision
    by the Secretary of Appellee Department of Natural Resources and Environmental
    'Eight individuals are also Appellants.
    Control (““DNREC”) amending the construction permit issued by DNREC to
    Appellee Artesian Wastewater Management, Inc. (“Artesian”) on October 15,
    2017 for the construction of Phase 1 of the Artesian Northern Sussex Regional
    Wastewater Recharge Facility (“ANSRWRF”) northwest of Milton, Sussex
    County, Delaware.
    ANSRWRF was to be built in three phases and have a wastewater treatment
    plant, three lagoons to store wastewater, treat up to three million gallons of
    domestic wastewater per day, and spray the treated domestic wastewater on
    agricultural lands. ANSRWRF was approved by DNREC under regulations
    adopted by it in 1999 (the “1999 Regulations”). As part of the approval process,
    Artesian submitted hydrogeologic and soil investigation reports to DNREC.
    DNREC approved those reports under the 1999 Regulations. DNREC adopted
    new regulations in 2014 (the “2014 Regulations”). The 2014 Regulations
    continue to require hydrogeologic and soil investigation reports; however, the
    hydrogeologic report required by the 2014 Regulations would require more test
    wells to be drilled than Artesian drilled previously under the 1999 Regulations.
    The demand for domestic wastewater never materialized. Artesian filled the
    void by agreeing to take treated food processing wastewater from a chicken
    processing plant and spray it on the agricultural lands. Artesian filed an
    application on May 10, 2017 with DNREC to amend its construction permit to
    address the change from domestic to food processing wastewater, and to
    reconfigure and delay some aspects of ANSRWRF. The amended application did
    not include new hydrogeologic and soil investigation reports. The Secretary and
    the Environmental Appeals Board (“EAB”) approved the amendments to
    Artesian’s construction permit, concluding that the changes were not significant
    enough to require new hydrogeologic and soil investigation reports and to start the
    approval process from the beginning. I have concluded that the Secretary and
    EAB were correct because the applicable provisions of the 2014 Regulations do
    not require Artesian to obtain a new permit for two reasons. First, Artesian
    already has a permit. Second, the changes that Artesian wants to make to its
    permit are, as the Secretary and EAB found, not substantial enough to require new
    hydrogeologic and soil investigation reports.
    ANSRWRE
    ANSRWRYF, as originally approved by DNREC, would initially treat
    domestic wastewater from the Elizabethtown housing project located northwest of
    Milton and ultimately serve the wastewater needs of the surrounding area.
    ANSRWRF was to consist of a wastewater treatment plant and three lagoons with
    storage for 159 million gallons of wastewater on a 75 acre parcel of land, be
    capable of treating three million gallons of wastewater per day, and spraying the
    treated wastewater on agricultural lands totaling 1722 gross acres (actual spray
    area of 1326.5 acres). ANSRWRF was to be constructed in three phases. Phase 1
    would (1) have a wastewater treatment plant and two lagoons with storage for 67.5
    million gallons of wastewater; (2) process one million gallons of wastewater per
    day; and (3) spray the treated wastewater on 608.9 acres of agricultural lands.
    ANSRWRI was approved by DNREC under the 1999 Regulations.
    DNREC adopted the 2014 Regulations on January 11, 2014. The Elizabethtown
    housing project was apparently never built. However, Artesian located a new
    customer. Artesian and Allen Harim Foods, LLC (“Allen Harim”) entered into an
    agreement whereby treated food processing wastewater from Allen Harim’s
    Harbeson chicken processing plant would be sent via a pipeline to ANSRWRF.
    Artesian would store and then spray the already-treated wastewater on the existing
    agricultural lands that it had already leased. Allen Harim had previously been
    discharging its treated wastewater directly to “Beaverdam Creek,” a stream about
    three miles from Milton, Sussex County, Delaware.
    Artesian filed an application to amend its Phase 1 construction permit with
    DNREC on May 10, 2017. The application included an amended Design
    Development Report (“DDR”), which Artesian submitted to account for the
    changes in the anticipated influent flow characteristics and phasing of treatment
    and disposal capacity. The amendment sought to (1) move construction of the
    wastewater treatment plant from Phase | to Phase 2; (2) build one 92 million
    gallon storage lagoon in Phase | instead of two lagoons totaling 67.5 million
    gallons; (3) accept and dispose of 1.5 million gallons to 2.0 million gallons of
    already-treated food processing wastewater per day instead of accepting and
    treating 1.0 million gallons of domestic wastewater per day (but still less than the
    3.0 million gallons of discharge per day for all three phases); and, (4) dispose of
    the already-treated food processing wastewater, instead of the domestic
    wastewater, by spray irrigation on 961.1 gross acres (762.7 spray acres).
    The 2014 Regulations require a Hydrogeologic Suitability Report (“HSR”)
    and a Surface Water Assessment Report (“SWAR”). Artesian had, before
    obtaining the initial DNREC approval for ANSRWRF, submitted, among other
    things, (1) a Site Selection and Evaluation Report, dated January 10, 2007, that
    was reviewed and approved by DNREC, in which DNREC concluded that the
    proposed sites for spray irrigation met the current criteria for land treatment
    systems; and (2) a Design Development Report, dated June 19, 2002, which
    included a Soil Investigation Report prepared by Brickhouse Environmental and a
    Hydrogeologic Investigation Report and Preliminary Groundwater Mounding
    Analysis prepared by Artesian Utility Development, Inc. DNREC approved the
    DDR, which was amended with subsequent supporting documentation, on April
    29, 2010. Artesian submitted construction plans on October 27, 2011. DNREC
    issued the construction permit to Artesian on October 15, 2013.
    Artesian did not submit an HSR and SWAR with its application for an
    amended construction permit on May 10, 2017. The application went to
    DNREC’s Division of Water, Groundwater Discharge Section (“GWDS”), which
    determined that the application was administratively complete even though it did
    not include an HSR and SWAR. A public hearing was held on July 27, 2017.
    GWDS recommended approval of the application, reasoning, in part, that
    ANSRWRE would have the highest treatment level required for spray irrigation.
    The hearing officer, in a report dated October 5, 2017, recommended that the
    Secretary issue the amended construction permit for Phase 1. The Secretary issued
    an Order approving the amended application on November 2, 2017. The
    Secretary’s decision noted that Artesian must meet the public access criteria for
    spraying treated wastewater on the ground, which is the highest criteria for spray
    irrigation. The Secretary also addressed what he considered to be the application’s
    three most significant changes, concluding that an increase in the Phase | storage
    capacity from 62 to 90 million gallons, delaying construction of the wastewater
    treatment plant to Phase 2, and increasing the use of agricultural lands to reflect
    Allen Harim’s volume of already-treated food processing wastewater were
    reasonable and well-supported in the record. KOWC then filed an appeal of the
    Secretary’s decision with the EAB.
    The EAB Decision
    The EAB held public hearings on May 22, 2018 and March 12, 2019. The
    issue of whether DNREC should have required Artesian to file an HSR and
    SWAR before DNREC considered Artesian’s amended application was squarely
    before the Board. The Board heard from two witnesses, John G. Hayes, Jr. and
    Christopher P. Grobel, Ph.D. Hayes is DNREC’s Program Manager for the Large
    Systems Branch, Ground Water Discharge Section. Grobel is an expert in
    hydrology and hydrogeology.
    Summary of Hayes’ Testimony
    Hayes (1) was familiar with ANSRWREF as originally approved and with the
    proposed amendments to the Phase 1 Construction Permit; (2) was familiar with
    the 2014 Regulations; (3) knew that no HSR and SWAR had been filed with the
    amended application; (4) believed that only a new application required a HSR and
    SWAR; (5) believed that an existing permit could be amended; (6) believed that
    the proposed changes to the construction permit were not significant enough to
    require a new application; (7) believed that the site was still suitable for the
    disposal of treated wastewater; (8) believed that Artesian had submitted
    everything that is was obligated to submit; (9) believed that the volume of the
    wastewater to be sprayed on the agricultural fields of 1.5 to 2.0 million gallons per
    day was less than the overall 6 to 7 million gallons per day that for which the site
    was suitable; (10) recognized that although domestic wastewater and the treated
    wastewater from Allen Harim contained different components, the differences
    were not significant enough to require a new permit; and (11) recognized that
    Allen Harim was treating its wastewater to a higher level than was required for
    spray irrigation because it was being stream discharged and that Allen Harim
    would continue to treat its wastewater to that higher level before it was sent to
    ANSRWREF.
    Summary of Grobbel’s Testimony
    Grobbel testified about some of the issues in the permitting process, but his
    testimony was stopped because the EAB concluded that the evidence presented to
    the EAB would be limited to proper site selection and design, and not operation of
    the wastewater treatment plant.
    The Board’s Summary of the Evidence
    On the issue of whether the 2014 Regulations required Artesian to submit a
    HSR and SWAR, the EAB noted the following testimony from Hayes:
    (1) Hayes was involved in DNREC’s issuance of the 2013 and 2017 permits
    and knew what they allowed;
    (2) Hayes knew that the regulations changed between the issuance of the
    2013 and 2017 permits and he was involved in the development of the new
    regulations;
    (3) Hayes stated that the site selection process was not part of the
    amendment to the 2013 permit and based on the proposed changes there was no
    need to apply all of the 2014 Regulations to the amended application;
    (4) Hayes reviewed the soil report submitted with the 2013 permit and
    concluded that no additional soil work was necessary;
    (5) Hayes said that the requirements for a HSR and SWAR apply to new
    applications, not existing ones;
    (6) Hayes said that subsections 6.3.1.1.14 and 6.5.3.3.1 of the 2014
    Regulations allow DNREC to amend a permit;
    (7) Hayes said the volume of water to be sprayed on the fields was within
    the scope of the investigations that were previously performed; and
    (8) Hayes said that DNREC had the functional equivalent of a HSR and
    SWAR even though they were not required for an amended permit.
    The EAB’s Legal Conclusions
    The EAB reached, in part, the following legal conclusions:
    The Board agrees with DNREC and Artesian’s
    contention that, as a matter of law, the 2014 regulations
    do not apply to the amendment to the existing
    construction permit. DNREC concluded that a permit
    amendment is subject to the regulations that were in
    effect at the time of the initial permit application unless
    the changes are significant. In this case DNREC
    determined the changes are not significant enough to
    require the application to submit a new permit
    application. DNREC’s determination is not
    unreasonable or clearly wrong.
    The Board agrees with Artesian’s contention, and
    finds as a matter of law, that it submitted the required
    plan, specifications and design engineer report
    contemplated by subsection 6.3.1.1.14. Lastly, the Board
    finds as a matter of fact that the Sussex County zoning
    approval allowed for a regional wastewater facility to
    serve multiple sources and that Sussex County was
    aware of the amended construction permit application
    and reaffirmed its conditional use approval. The Board
    finds as a matter of law that the Secretary had sufficient
    evidence to so conclude.
    10
    Standard of Review
    This Court’s review of administrative board decisions is limited to whether
    the decision is supported by “substantial evidence” and is “free from legal error.”
    “Substantial evidence is that which a reasonable mind might accept as adequate to
    support a conclusion.”? It is not the Court’s role to “weigh the evidence,
    determine questions of credibility or make its own factual findings.’ The Court
    “merely determines if the evidence is legally adequate to support the agency’s
    factual findings.”
    Regulatory Construction
    When interpreting the language of the 2014 Regulations, I have to engage in
    regulatory construction, the functional equivalent of statutory construction. “The
    primary goal of statutory construction is to ‘ascertain and give effect to the intent of
    the legislature.””® Intent is determined by the plain language of the statute, and absent
    *State v. Calder, 
    2019 WL 5381918
    , at *2 (Del. Super. Oct. 16, 2019).
    *Liberty Mut. Ins. Co. v. Silva-Garcia, 
    2013 WL 4507847
    , at *4 (Del. Super. Aug. 22, 2013).
    ‘Lewis v. State Dep’t of Agriculture, 
    2007 WL 315359
    , at *3 (Del. Super. Jan. 31, 2007).
    “Id.
    ° Acadia Brandywine Town Ctr., LLC v. New Castle Cty. 
    879 A.2d 923
    , 927 (Del. 2005) (citing
    Dir. Of Revenue v. CNA Holdings, Inc., 
    818 A.2d 953
    , 957 (Del. 2003)); see also Norman J.
    Singer, Sutherland Statues and Statutory Construction, §78:3 (7° ed. 2015) (“The key to
    interpreting a ... statute is to ascertain and effectuate legislative intent as expressed in the statute.
    The statute’s language is the best and most reliable index of the statute’s meaning ....”).
    11
    ambiguity, “there is no room for judicial interpretation and ‘the plain meaning of the
    statutory language controls.’””’ Indeed, “[i]Jn the absence of any ambiguity, the
    language of the statute must be viewed as conclusive of the legislative intent. The
    judicial role is then limited to an application of the literal meaning of the words.”®
    Absent ambiguity, the Court cannot look to legislative history to determine the
    meaning of the legislative enactment.’ There is one other rule of statutory
    construction that is applicable. The expression of one thing but not another is”
    interpreted to mean that omitted items were not meant to be included.'°
    Discussion
    The difficult task in this case is to determine if DNREC correctly processed
    amendments to a 2013 construction permit that was approved under the 1999
    Regulations where those amendments are now governed by - at least to some
    ” PHL Variable Ins. Co. v. Price Dawe 2006 Ins. Trust, ex rel. Christiana Bank and Trust Co. ;
    
    28 A.3d 1059
    , 1070 (Del. 2011); see also Norman J. Singer, Sutherland Statutes and Statutory
    Construction, §46:1 (7" ed. 2015) (“the rules of statutory construction favor according statutes
    with their plain and obvious meaning and courts assume the legislature knew the plain and
    ordinary meanings of the words it chose to include in a statute.”).
    * Grand Ventures, Inc. v. Whaley, 
    632 A.2d 63
    , 68 (Del. 1993) (internal citation omitted).
    ” Arnold v. Society for Sav. Bancorp., Inc., 
    650 A.2d 1270
    , 1287 (Del. 1994) (“A court should
    not resort to legislative history in interpreting a statute where statutory language provides
    unambiguously an answer to the question at hand.”); Pellicone v. New Castle Cty., 
    88 A.3d 670
    ,
    675, n.21 (Del. 2014).
    '° See, e.g., Walt v. State, 
    727 A.2d 836
    , 840 (Del. 1999), citing Hickman v. Workman, 
    450 A.2d 338
    , 391 (Del. 1982).
    12
    extent - the 2014 Regulations.'’! Artesian argues that it did not have to start the
    approval process for a wastewater treatment system from the beginning because
    (1) it already had a permit to construct a wastewater treatment system, and (2) the
    changes that it wanted to make to its already-approved wastewater treatment
    system were not significant enough to require any further hydrogeologic and soil
    evaluations. DNREC and the EAB agreed with Artesian. KOWAC argues that
    Artesian had to start the process over because the 2014 Regulations require it. The
    2014 Regulations do not, in my view, address this situation with the clarity that is
    required. The 2014 Regulations make great sense if you are starting the permitting
    process after they became effective, but that is not the case here. ANWRWREF was
    approved by DNREC under the 1999 Regulations. Artesian already has a
    construction permit that DNREC approved pursuant to those regulations.
    Nevertheless, the 2014 Regulations are what DNREC had to work with in
    processing the amendments to Artesian’s construction permit. The resolution to
    ''The EAB appeared to state that the 2014 Regulations did not apply to Artesian’s proposed
    amendments to its already-issued construction permit. Although the EAB decision is not a
    model of clarity, I find that the fairest view of the EAB’s ruling, when you consider the issues
    before it and its factual findings, is that the EAB found that the sections of the 2014 Regulations
    requiring a HSR and SWAR do not apply, that Artesian complied with Section 6.3.1.14.1, and
    that the changes that Artesian sought were not substantial enough to require further
    hydrogeologic and soil evaluations. (The EAB’s reference to Section 6.3.1.1.14 instead of
    6.3.1.14.1 appears to be a typographical error.)
    13
    the parties’ arguments turns on the language of three sections of the 2014
    Regulations: Sections 6.1, 6.5 and 6.3.1.14.1.
    Large System Approvals
    The 2014 Regulations govern Small Systems and Large Systems for treating
    and disposing of wastewater. ANSRWRF is a Large System. Large Systems are
    governed by Section 6.0, et seg. Section 6.1 states, in part, as follows:
    A permit must be obtained from the Department
    prior to the construction, operation, maintenance or
    repair of any on-site wastewater treatment and disposal
    systems with daily design flow rates of > 2,500 gallons.
    There are, of course, many things you would have to do in order to get a
    permit for a Large System. You would, if you were starting the process from the
    very beginning, have to submit to DNREC an HSR and aSWAR. An HSR anda
    SWAR are discussed in Sections 6.2.3 and 6.2.4, respectively, and are required by
    Section 6.5.
    HSR
    An HSR is defined by the 2014 Regulations and “means a report that
    characterizes the hydrogeologic properties present on a given site through direct
    observations.” Section 6.2.3 states that an HSR “must be submitted to the
    Department for review and approval for large on-site wastewater treatment and
    disposal systems.” Hydrogeologic or hydrogeology is an area of geology that
    deals with the movement and distribution of groundwater in the soil.
    SWAR
    SWAR is defined by the 2014 Regulations and “means a report that
    characterizes the potential nutrient impacts of a wastewater treatment system to a
    site from future development through background data and computer modeling.”
    Section 6.2.4 states that a SWAR “must be submitted to demonstrate that nutrient
    performance standards for wastewater are being met at the post treatment location
    of a large on-site system or through natural attenuation processes prior to reaching
    the closest receiving surface water body in order to comply with surface water
    quality standards.”
    The information that must be included in an HSR and a SWAR, as well as
    the manner in which that information must be collected, are discussed in detail in
    the appropriate sections of the 2014 Regulations. Although those two reports are
    apparently of great consequence, they were not discussed in much detail before the
    EAB. Indeed, the only notable difference between the Soil Investigation Report
    and Hydrogeologic Investigative Report submitted by Artesian in 2002 and what
    an HSR would require now involves the number of test borings done. Artesian
    previously did 13 test borings over 1652 acres. An HSR would require around
    15
    160 test borings. The test borings are required to gather data to assess the
    suitability of the agricultural lands for the disposal of wastewater. I understand, of
    course, that getting more information could conceivably change the analysis, but
    that is purely speculative at this point.
    The requirement to obtain an HSR and SWAR is found in Section
    6.5, which states as follows:
    In order to obtain a permit to construct and operate
    an on-site wastewater treatment and disposal systems
    with daily flow rates of > 2,500 gallons, a permit
    application must be submitted to the Department for
    review and approval. A permit application will not be
    reviewed by the Department until the SIR, HSR and
    SWAR have been reviewed and approved by the
    Department.
    The Applicability of Sections 6.1 and 6.5
    If Sections 6.1 and 6.5 apply to Artesian’s proposed amendments to its
    already-issued construction permit, then Artesian would have to provide an HSR
    and SWAR because they are clearly part of the application to obtain a permit for a
    Large System. However, Sections 6.1 and 6.5 do not nicely fit this case because
    Artesian already has a construction permit. Artesian argues that Sections 6.1 and
    6.5 do not apply because it already has “obtained” a construction permit and the
    changes it wants to make to its permit are not substantial enough to justify starting
    16
    the process over from the very beginning. Artesian also argues that Section 6.1
    and 6.5 instead only apply to applications for new permits. KOWAC argues that
    Sections 6.1 and 6.5 apply even though Artesian already has a construction permit.
    I conclude that Sections 6.1 and 6.5, by their clear language, do not apply.
    Section 6.1 states that “a permit must be obtained from the Department prior to the
    construction, operation, maintenance or repair of any on-site wastewater treatment
    and disposal system...” Section 6.5 states that “[i]n order to obtain a permit to
    construct and operate on-site wastewater treatment and disposal system” you must
    submit an HSR and a SWAR to the Department. Artesian had already “obtained”
    a construction permit for Phase 1, making it unnecessary for Artesian to start the
    process from the very beginning and obtain yet another construction permit. Since
    I have concluded that Sections 6.1 and 6.5 do not apply, then the obligations to
    submit an HSR and a SWAR do not apply either. Thus, the question becomes
    what regulatory and analytical steps one has to follow to process changes to an
    already-issued permit. Changes to construction permits are addressed in Section
    6.3.1.14.1.
    17
    Construction Permit Changes
    Section 6.3.1.14.1 states:
    A construction permit application, plans and
    specifications and design engineer report with applicable
    fees must be submitted to the Department if the
    construction permit has expired or changes have
    occurred.
    Artesian argues that it has complied with 6.3.1.14.1. Artesian’s 2013
    construction permit for Phase 1 has not expired. However, Artesian does want to
    make changes to its construction permit, and the 2014 Regulations permit a
    construction permit holder to make changes to the permit if “changes have
    occurred.” Artesian has submitted to DNREC an amended Design Engineer
    Report and plans and specifications and paid the applicable fees in connection
    with its application for an amended construction permit. KOWAC argues that
    Section 6.3.1.14.1 means that an applicant who has gotten a construction permit
    under Sections 6.1 and 6.5 and wants to make changes would have already
    submitted an HSR and a SWAR as part of its original application. Thus, KOWAC
    reasons, any hydrogeologic and soil studies that are needed would already have
    been done. KOWAC’s argument, of course, assumes that the original application
    was filed after the 2014 Regulations became effective, but that is not the case here.
    18
    I certainly understand KOWAC’s argument, but it describes a situation that is not
    before us. Artesian and DNREC are dealing with a wastewater system that crosses
    different regulations enacted at different times. I conclude that Section 6.3.1.14.1,
    by its clear language, allows Artesian to seek an amendment to its existing
    construction permit. Section 6.3.1.14.1 sets forth a process that must be followed
    if “changes have occurred.” Artesian’s situation has changed and it wants to
    process those changes by submitting the required documentation and having those
    changes evaluated by DNREC. Unfortunately, the 2014 Regulations do not define
    or address what a “change” either means or, more importantly, what Artesian has
    to do in order to obtain the necessary DNREC approval.
    Processing the Changes
    Faced with this, the Secretary, and ultimately the EAB, concluded that the
    2014 Regulations did not require Artesian to submit a HSR and SWAR with its
    application for an amended construction permit because the changes that Artesian
    wanted to make to ANSRWRF were not substantial enough to require Artesian to
    conduct additional hydrogeologic and soil studies. Put another way, the Secretary,
    based on the nature of Artesian’s proposed changes and the hydrogeologic and soil
    studies done in 2002, concluded that no further environmental work was
    necessary. The EAB agreed with the Secretary’s conclusion. I conclude that the
    19
    EAB’s decision is a correct statement of the applicable law and is supported by
    substantial evidence in the record. The following are the changes that Artesian
    sought, and the rationale followed by the Secretary, and ultimately the EAB, in
    approving them.
    The Wastewater Treatment Plant
    Artesian sought to move construction of the wastewater treatment plan from
    Phase | to Phase 2. It would still be built on the same 75 acre parcel, but would be
    built later. The only change was one of timing. The Secretary and EAB found
    that there would be no adverse environmental consequence for doing this. Indeed,
    the Secretary found that the delay in construction would reduce the impact of the
    effect of construction on the amount of the land disturbed by the construction.
    That conclusion is supported by the record. Artesian has approval to build a
    wastewater treatment plant. Whether it is built now or later is irrelevant from an
    environmental viewpoint.
    The Lagoons
    Artesian sought to build one 90 million gallon lagoon in Phase 1 instead of
    two lagoons totaling 67.5 million gallons. The larger lagoon was necessary to
    handle the increased flow of treated wastewater from Allen Harim. This lagoon
    would still be on the same 75 acre parcel of land and the 90 million gallon lagoon
    20
    would be less in size than the three lagoons totaling 159 million gallons for the
    entire project. The Secretary and the EAB found that there would be no adverse
    environmental consequence for doing this. The only effect was to increase the
    land disturbance related to the construction of the larger lagoon initially. That
    conclusion is supported by the record. The fact that Artesian is building more
    storage capacity sooner rather than later is irrelevant from an environmental
    viewpoint.
    The Allen Harim Wastewater
    Artesian sought to accept up to 1.5 to 2.0 million gallons per day of already-
    treated food processing wastewater from Allen Harim instead of 1.0 million
    gallons of untreated domestic wastewater. The Secretary and EAB concluded that
    Allen Harim’s already-treated wastewater would not contaminate the groundwater
    used for the drinking supply because of DNREC’s public access standard, which is
    the highest standard that one must meet in order to spray treated wastewater on
    agricultural land. Put another way, in order to spray Allen Harim’s already-treated
    wastewater on agricultural land, Artesian and Allen Harim would have to meet the
    appropriate standard for doing so. Moreover, the treated wastewater would be
    sprayed on lands that DNREC long ago deemed suitable for spray irrigation. The
    volume from Allen Harim is still less than the contemplated treatment and disposal
    21
    of 3.0 million gallons of treated wastewater for a site that was, according to Hayes,
    suitable for the disposal of 6 to 7 million gallons of wastewater per day.
    Moreover, also according to Hayes, Allen Harim would continue to treat its
    wastewater to a standard higher than is required for spray irrigation on agricultural
    fields. As I noted before, Allen Harim treats its wastewater to a level high enough
    to allow it to be discharged directly into a waterway. The Secretary increased the
    total spray acres from 608.9 to 762.7 acres, presumably to allow for the increase in
    wastewater.'* Hayes was well aware of the characteristics of the site and he knew
    that Allen Harim’s food processing wastewater had different components than
    domestic wastewater, but did not feel that the differences were significant enough
    to require a new permit. The Secretary’s conclusions are supported by the
    testimony of Hayes and there does not appear to be any evidence in the record to
    contradict the Secretary’s conclusions. The Secretary found that there would be
    no adverse environmental consequence for the changes sought by Artesian in this
    regard. Indeed, the fact that Allen-Harim’s wastewater is to be disposed of on
    agricultural lands instead of directly into a waterway is arguably better because the
    land further “treats” the wastewater.
    One of the fields - Field D, consisting of 90.7 acres - may not be used until it is approved by
    Sussex County as a conditional use.
    22
    Conclusion
    I find that the Secretary and EAB were correct when they found that the
    2014 Regulations do not require Artesian to start the process from the beginning
    because it already had “obtained” a construction permit for Phase 1 of
    ANSRWRI. I further find that the Secretary and EAB were correct when they
    concluded that the changes Artesian sought to make to its already-issued
    construction permit were not substantial enough to require further hydrogeologic
    and soil studies. The changes involving the timing of the construction of the
    wastewater treatment plant, sizing of the lagoons, and spraying of treated food-
    processing wastewater were all well within the previously-approved parameters
    for ANWRWRE. The evidence in the record supports the conclusions by the
    Secretary and EAB that the proposed changes would have no effect on the
    drinking water. KOWAC’s argument that Artesian’s proposed changes to its
    construction permit require it to start the process from the beginning, even though
    Artesian already has a construction permit, ignores the plain language of the 2014
    Regulations and the evidence in the record indicating that the proposed changes
    would have no effect on the drinking water in the area. There are certainly some
    changes to an existing construction permit that would justify additional testing.
    For example, an increase in disposal of wastewater beyond what the agricultural
    23
    lands had been approved for would arguably require more analysis. However, that
    is not the case here. The agricultural lands to be used in this case have been
    extensively studied and found suitable for spray irrigation. Quite simply, the
    poultry industry has been in Sussex County for a long time, and so has the
    spraying of treated food processing wastewater from a poultry plant on
    agricultural lands. The record in this case supports the findings and decisions by
    the Secretary and EAB. There is little to nothing in the record to support
    KOWAC’s arguments. Accordingly, I affirm the Environmental Appeals Board’s
    decision.
    IT IS SO ORDERED.
    Very truly yours,
    pa
    E. Scott Bradley
    ESB/tl
    cc: Prothonotary
    _7
    7 os
    = ah
    => ¢m
    = ae?
    S on
    = ria
    — tO
    9 mi
    “oO
    U Sz
    as
    i