jesse-mcintosh-as-personal-representative-of-the-estate-of-james-mcintosh ( 2015 )


Menu:
  •           DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA
    FOURTH DISTRICT
    JESSE MCINTOSH, as Personal Representative of the Estate of JAMES
    MCINTOSH, deceased, on behalf of JESSE MCINTOSH and DYLAN
    MCINTOSH, JAMES MCINTOSH’s minor children,
    Appellants,
    v.
    PROGRESSIVE DESIGN AND ENGINEERING, INC., MASTEC NORTH
    AMERICA, INC., GBF ENGINEERING, INC., BROWARD COUNTY,
    STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION, TEI
    ENGINEERS & PLANNERS and/or HNTB CORPORATION, a successor
    corporation, and CITY OF PEMBROKE PINES, jointly and severally,
    Appellees.
    No. 4D12-2335
    [January 7, 2015]
    Appeal from the Circuit Court for the Seventeenth Judicial Circuit,
    Broward County; Jeffrey Levenson, Judge; L.T. Case No. 07-25039CACE.
    Bard D. Rockenbach of Burlington & Rockenbach, P.A., West Palm
    Beach, and Todd Middlebrooks of Middlebrooks & Middlebrooks, P.A., Fort
    Lauderdale, for appellant.
    Scott A. Cole, George R. Truit and Kristen A. Tajak of Cole, Scott &
    Kissane, P.A., Miami, for appellee.
    MAY, J.
    A tragic car accident resulted in the death of the plaintiff’s father. He
    now appeals an adverse jury verdict in a negligence action against a
    company that designed the traffic signals for the intersection. He argues:
    (1) the trial court erred in finding that the Slavin1 doctrine applied to the
    design company; (2) the evidence did not support the jury’s finding that
    the completed intersection had been “accepted” before the accident; and
    (3) the design defect was latent. We find no error and affirm.
    1 Slavin v. Kay, 
    108 So. 2d 462
     (Fla. 1959) (holding that a contractor is not liable
    for patent defects after acceptance of a construction project by the owner).
    The Accident
    The plaintiff’s father was exiting a mobile home park, traveling
    eastbound through an intersection, when he collided with a truck traveling
    southbound on the cross-street. The traffic signals at the intersection
    allowed a driver exiting the mobile home park to rely upon a traffic signal
    further out into the intersection meant for other traffic, while overlooking
    the traffic signal closest to him that was meant to control traffic exiting the
    mobile home park.
    Design and Construction of the Intersection Traffic Signals
    The City of Pembroke Pines asked the Florida Department of
    Transportation (“FDOT”) to install traffic signals at the intersection. FDOT
    hired TEI Engineers and Planners (“TEI”), who in turn, hired Progressive
    Design and Engineering, Inc. (“design company”) to design the traffic
    signals for the intersection. The design company’s scope of work included
    signal design and interconnect plans. The design plans were required to
    be in accordance with the Manual on Uniform Traffic Control Devices.
    The design company submitted the traffic signal design to FDOT, which
    provided it to Broward County Traffic Engineering (“Broward County”)2,
    the police department, and various FDOT departments associated with the
    project. The parties reviewed the plans and provided electronic comments
    to the design company’s engineer of record. The design company’s
    response had to be approved by FDOT and the original commenter.
    During the review process, an FDOT employee commented that a
    special signal might be necessary to make sure drivers did “not see the
    wrong indication from this quite large almost diamond like interchange
    design.” The design company responded to the comment; FDOT approved
    the response. A Broward County employee also participated in reviewing
    and commenting on the plans for signal installation and controls.
    According to the plaintiff’s expert, an engineer and former FDOT
    employee, FDOT probably spent a “couple of hours” reviewing the design
    plan, compared to the “hundreds of hours” the design company would
    have spent to design the traffic signals. He testified that it was impossible
    for FDOT to have the same knowledge as the design company. He also
    testified that the design drawings did not include a tree that was located
    2 Broward County was involved in the review process because it was ultimately
    responsible for maintaining the timing and phasing of the signalization for a fee.
    2
    in the median.
    FDOT hired EAC Consulting (“EAC”) to provide additional engineering
    review of the plans. EAC certified the plans to FDOT in February 2003.
    FDOT then decided the project was ready for the final engineering
    submittal. After the design plans were reviewed and almost complete, a
    meeting was held at the intersection to review the design in the field.
    FDOT, EAC, Broward County, GBF Engineering (“GBF”), and the design
    company attended this meeting.
    FDOT accepted the final comments in 2003. FDOT’s project manager
    was unaware of any further consultation with the design company. This
    was the last meeting the design company attended for the project; it had
    finished its work under the sub-contract with TEI. The design company
    did not receive any further change requests.
    The design company signed and sealed the design plans and sent them
    to TEI, which sent them to FDOT, which sent them to Tallahassee. In
    Tallahassee, the plans were reviewed to ensure compliance with the
    guidelines and sent out for contractor bidding. The project was generally
    built as designed, but the construction team had some ability to make
    modifications if needed.
    The selected contractor worked with GBF as the construction
    engineering inspector. GBF oversaw field operations to ensure the
    contractor’s compliance with the design plans. The completed project was
    inspected and initially approved on August 10, 2004. Broward County,
    the contractor, GBF, and FDOT, were at the inspection site.
    A Broward County employee testified that its acceptance was
    conditional, with final acceptance occurring after the burn-in period.
    Broward County did not object to the traffic signal sequencing and
    conditionally approved the intersection on August 10th. On that date, the
    signals became fully operational, using full color signals instead of flashing
    yellow signals.
    The design company’s engineer of record described the burn-in period
    as a contractor warranty period where the contractor maintained the
    traffic signals if something went wrong. FDOT was in control of the
    intersection and the only entity that could make changes. Broward
    County technicians inspected all aspects of the traffic signals. After the
    burn-in period, FDOT would transfer control of the intersection to Broward
    County for maintenance purposes. The accident occurred sixteen days
    into the burn-in period. Broward County did not take final control of the
    3
    intersection until January 2005.
    The plaintiff’s accident reconstruction expert testified the traffic signal
    design was the primary cause of the collision because the line of sight
    would give the driver the ability to focus on the second set of signals
    located farther out in the intersection, but not the first set of signals
    located just above the stop bar for people exiting the mobile home park. A
    mobile home park resident testified that a tree was located in the median
    at the mobile home park’s entrance. The tree also caused a problem
    because it blocked the view of the first set of traffic signals.
    The plaintiff moved for directed verdict based on the Slavin doctrine,
    arguing that Broward County had not “accepted” the project because the
    burn-in period had not ended. The trial court denied the motion. The
    design company also moved for directed verdict based on the Slavin
    doctrine, arguing the project was completed, accepted, and the defects
    known or reasonably discoverable by FDOT prior to the accident. The trial
    court also denied that motion finding that the issues were better left for
    the jury.
    Although the plaintiff’s counsel objected to Slavin’s use in the jury
    instructions, he helped draft the instruction without waiving his objection.
    Both parties agreed that if a Slavin instruction was included, it would
    discuss acceptance of the design.
    The trial court instructed the jury on Slavin and directed that “if you
    find that the design of the intersection . . . was accepted by [FDOT] before
    James McIntosh was injured, you must determine whether [FDOT] knew
    about the defects.” The trial court then instructed the jury, “[i]f you find
    that [FDOT] either knew of the defects or should have discovered the
    defects in conducting a reasonably careful inspection, then your verdict
    should be for [the design company].”
    The jury returned a verdict finding the design company negligent in its
    traffic signal design, which was the legal cause of the plaintiff’s father’s
    death. But, the jury found the negligent design was accepted and
    discoverable by FDOT with the exercise of reasonable care.
    The plaintiff moved for a new trial or judgment in accordance with his
    motion for directed verdict, arguing that Slavin did not apply to the claim
    because the evidence failed to show that Broward County accepted the
    project. The trial court denied the motions and entered final judgment in
    4
    favor of the design company.3 From the adverse judgment, the plaintiff
    now appeals.
    On appeal, the plaintiff argues the trial court erred in applying Slavin,
    the evidence did not support a finding that Broward County accepted the
    completed intersection before the accident, and the design defects were
    latent. The design company responds that the evidence established the
    traffic signal design was accepted by FDOT before the accident. It also
    argues the design defect was patent, and that the jury verdict was
    supported by the evidence.
    We have de novo review of the trial court’s ruling on the motion for
    directed verdict. Meruelo v. Mark Andrew of Palm Beaches, Ltd., 
    12 So. 3d 247
    , 250 (Fla. 4th DCA 2009).
    The Slavin doctrine was born of the need to limit a contractor’s liability
    to third persons. “[A] contractor who performs work does not owe a duty
    to the whole world . . . else the extent of his responsibility would be difficult
    to measure and a sensible man would hardly engage in the occupation
    under such conditions.” Slavin v. Kay, 
    108 So. 2d 462
    , 464 (Fla. 1959).
    “The Slavin doctrine considers the respective liability of an owner and
    contractor, after the owner has resumed possession of the construction,
    for injuries to a third person for negligence of the contractor in the
    construction of the improvement.” Gonsalves v. Sears, Roebuck & Co., 
    859 So. 2d 1207
    , 1208 (Fla. 4th DCA 2003).
    Under Slavin, “the liability of a contractor is cut off after the owner has
    accepted the work performed, if the alleged defect is a patent defect which
    the owner could have discovered and remedied.” Fla. Dep’t of Transp. v.
    Capeletti Bros., Inc., 
    743 So. 2d 150
    , 152 (Fla. 3d DCA 1999). The
    contractor’s work must be “fully completed before the owner becomes
    liable and the contractor is exonerated.” Gonsalves, 859 So. 2d at 1209.
    The rationale is that “‘[b]y occupying and resuming possession of the work
    the owner deprives the contractor of all opportunity to rectify his wrong.’”
    Slavin, 
    108 So. 2d at 466
     (quoting Casey v. Hoover, 
    89 S.W. 330
    , 334 (Mo.
    Ct. App. 1905)).
    There are two requirements to be met before the Slavin doctrine will
    isolate a contractor from liability. First, the defect must be patent. Kala
    Invs., Inc. v. Sklar, 
    538 So. 2d 909
    , 913 (Fla. 3d DCA 1989) (citations
    omitted). “[T]he test for patency is not whether or not the condition was
    obvious to the owner, but whether or not the dangerousness of the
    3   Other defendants were dismissed after settling with the plaintiff.
    5
    condition was obvious had the owner exercised reasonable care.” Capeletti
    Bros., Inc., 743 So. 2d at 152 (citing Sklar, 
    538 So. 2d at 913
    ).
    The issue of whether a defect is patent or latent is usually a jury
    question. 
    Id.
     (citing Sklar, 
    538 So. 2d at 914
    ). The trial court recognized
    the factual nature of the patency issue and correctly submitted it to the
    jury.
    Here, an FDOT employee discovered the potential design defect long
    before the accident. As our supreme court has noted, FDOT is a “highly
    knowledgeable and sophisticated purchaser.” Chadbourne, Inc. v. Vaughn,
    
    491 So. 2d 551
    , 554 (Fla. 1986). It “has at least as much knowledge about
    road construction as” a road construction contractor, and certainly that of
    a design company. 
    Id. at 553
    . Even a mobile home park resident
    recognized that something was wrong with the traffic signals. The jury
    decided that the defect was patent. The evidence supported this finding.
    The second requirement is “acceptance” of the work. The reason for
    this requirement is that at some point the contractor loses control of the
    work, and concomitantly loses the ability to alter or change it. If the defect
    is patent, “the owner is charged with knowledge of it, and the contractor
    is relieved of liability because it is the owner’s intervening negligence in
    not correcting it which is the proximate cause of the injury.” Brady v.
    State Paving Corp., 
    693 So. 2d 612
    , 613 (Fla. 4th DCA 1997). That is the
    point of “acceptance.”
    The plaintiff argues that acceptance did not occur because the ninety-
    day burn-in period to allow the contractor to correct any errors had not
    ended, and Broward County had not taken over maintenance of the
    intersection. The design company responds that its work had been
    completed and accepted by FDOT months before the accident. It had no
    control after FDOT accepted its work, and had no ability to alter the work
    of FDOT or its contractor. In essence, the design company argues that
    FDOT stood in the shoes of the proverbial owner in Slavin. We agree with
    the design company.
    The design company’s duty as a sub-contractor was to design the traffic
    signals. The design company completed its duty under the contract before
    the construction was completed. FDOT accepted the plans, and put the
    construction contract out to bid. The design company had no control of
    the project’s construction or when the completed project would become
    operational. Responsibility for the construction rested with the contractor.
    Going operational was a decision to be made by FDOT and Broward
    County.
    6
    Our supreme court has held “that a paving contractor could not be
    liable for injuries caused by defects in a road after the repaving work had
    been accepted by the Department of Transportation.” Easterday v. Masiello,
    
    518 So. 2d 260
    , 261 (Fla. 1988) (emphasis added) (citing Chadbourne, 
    491 So. 2d at 553
    ). Here, FDOT accepted the design company’s work, and the
    construction project was completed by August 10th, sixteen days before
    the accident.
    The real dispute here is whether acceptance of the design company’s
    work was to be by FDOT, which controlled the project and accepted the
    design company’s design, or by Broward County, which would ultimately
    maintain the intersection. To answer that question, we need only apply
    the underlying premise of the Slavin doctrine and subsequent caselaw.
    That premise is the responsibility for a patent defect rests with the entity
    in control and with the ability to correct it.
    “Acceptance” is the term applied for shifting the responsibility to correct
    patent defects to the party in control. In essence, acceptance will move
    along the timeline of a construction project, passing to each entity
    maintaining control of the work. This application makes perfect sense.
    Once an entity completes its work, and that work is accepted, the burden
    of correcting patent defects shifts to the entity in control. It is the
    controlling entity’s intervening negligence in not correcting a patent defect
    that proximately causes the injury. Brady, 
    693 So. 2d at 613
    .
    As between the parties to this construction project, FDOT was the entity
    to whom the design company owed its duty, because it controlled
    “acceptance” of the design company’s work. In turn, Broward County
    controlled acceptance of FDOT’s work. At each step along the timeline,
    the party in control bore the burden of correcting patent defects because
    its control prevented anyone else from doing so.
    Our supreme court has acknowledged and reaffirmed Slavin’s vitality.
    It has applied it to shield a design engineer and architects. See Easterday,
    
    518 So. 2d at 260
    ; Gustinger v. H.J.R., Inc., 
    573 So. 2d 1033
    , 1033–34 (Fla.
    3d DCA 1991). Other Florida courts have applied Slavin in road
    construction scenarios. See Chadbourne, 
    491 So. 2d at
    552–54 (applying
    Slavin to a contractor’s repaving of a road); Capeletti Bros., Inc., 743 So.
    2d at 151–52 (applying Slavin to a guardrail after road construction, but
    reversing a summary judgment due to a genuine issue of material fact).
    Slavin exists to limit the liability of contractors because “it would be
    unfair to continue to hold the contractor responsible for patent defects
    after the owner has accepted the improvement and undertaken its
    7
    maintenance and repair.” Easterday, 
    518 So. 2d at 261
    . We join in the
    acknowledgement that Slavin is necessary to place the burden of
    responsibility upon the entity that controls the environment.
    The trial court did not err in permitting the jury to determine whether
    the defect was patent and whether the project was accepted. It also did
    not err in its instructions to the jury. The factual disputes on these issues
    precluded the court from deciding them as a matter of law for either side.
    While the jury found the design company negligent, and the legal cause of
    the plaintiff’s father’s death, it also found the design was accepted and
    discoverable (or patent) by FDOT with the exercise of reasonable care. The
    trial court correctly declined to disturb these findings which were
    supported by the evidence. We therefore affirm.
    Affirmed.
    DAMOORGIAN, C.J., and GROSS, J., concur.
    *        *         *
    Not final until disposition of timely filed motion for rehearing.
    8