AVANT DESIGN GROUP, INC., etc. v. AQUASTAR HOLDINGS, LLC, etc. ( 2022 )


Menu:
  •       Third District Court of Appeal
    State of Florida
    Opinion filed October 12, 2022.
    Not final until disposition of timely filed motion for rehearing.
    ________________
    No. 3D21-53
    Lower Tribunal No. 18-22242
    ________________
    Avant Design Group, Inc., etc.,
    Appellant/Cross-Appellee,
    vs.
    Aquastar Holdings LLC, etc.,
    Appellee/Cross-Appellant.
    An Appeal from the Circuit Court for Miami-Dade County, Abby
    Cynamon and Charles Johnson, Judges.
    Peckar & Abramson, P.C., and Adam P. Handfinger, Freddy X. Muñoz
    and Anne-Solenne Rolland, for appellant/cross-appellee.
    The Law Offices of Kristin Vivo, and Kristin Vivo (Singer Island);
    Osherow, PLLC, and Mark R. Osherow (Boca Raton), for appellee/cross-
    appellant.
    Before SCALES, HENDON and GORDO, JJ.
    SCALES, J.
    Appellee/cross-appellant     Aquastar    Holdings,    LLC    (“Aquastar”)
    purchased a condominium unit in a building in Surfside, Florida. Aquastar
    hired appellant/cross-appellee Avant Design Group, Inc. (“Avant”) to
    administer the build-out of the unit. Toward the end of the project, Aquastar,
    concerned about the integrity of Avant’s billings, terminated its contract with
    Avant. Each party sued the other on multiple bases and Aquastar also sued
    the three owners of Avant individually. In a detailed final judgment,1 the trial
    court found in favor of Aquastar in its suit against Avant but declined to hold
    Avant’s three owners individually liable for Aquastar’s claims. Both parties
    appealed the Amended Final Judgment and Aquastar also appealed the trial
    court’s April 14, 2021 order denying its Florida Rule of Civil Procedure 1.530
    rehearing motion. For the reasons that follow, we affirm in part, reverse in
    part, and remand with instructions.
    I. Relevant Facts and Procedural History
    A. The Contract
    Aquastar is owned by Wilson De Lara, a Brazilian businessman.
    Aquastar used Brazilian architect Debora Aguiar to design the interior of the
    1
    During the pendency of the appeal, this Court relinquished jurisdiction to
    the trial court to correct the final judgment. On October 21, 2021, a successor
    judge entered a Final Judgment After Non-Jury Trial, nunc pro tunc to
    December 7, 2020 (the “Amended Final Judgment”).
    2
    unit. Because Aguiar is not licensed in the United States, she recommended
    Avant both to oversee the project’s construction and to obtain goods and
    services for the interior build-out. Aquastar purchased the unit and hired
    Avant in September 2016.
    Aquastar and Avant entered into a contract known as “Proposal 27.”
    Proposal 27 provided a schedule of construction items along with their
    anticipated costs. Although the trial court focused its attention on Proposal
    27 for its analysis of the terms and conditions to which the parties had
    agreed, the parties executed a total of ninety-two such proposals, each of
    which was on a form generated by Avant. These other proposals described
    the furnishings, goods and services to be purchased for each of the rooms
    in the unit. Proposal 27 and the additional proposals all followed the same
    format, and all contained the same contractual language. The proposals
    provided that Aquastar would pay the cost of the goods and services of the
    vendors, plus pay a “20% Interior Design & Administrative Fee” to Avant (the
    “20% Fee”). 2 The proposals contained no other contractual language
    regarding the amount or calculation of payment.
    2
    Other than item descriptions and related pricing, the only other contractual
    language in Proposal 27 reads as follows:
    The preliminary budget of the Client’s construction costs include
    [sic] anticipated costs for construction materials, labor and sales
    3
    B. Avant’s Billings
    For approximately eighteen months, the parties mutually performed
    under the proposals. Avant dealt with Aquastar’s architect, and with
    contractors, subcontractors and vendors; presented Aquastar with vendor
    proposals, which Aquastar either accepted or rejected; oversaw the delivery
    and installation of furnishings, many of which were custom-made; served as
    a liaison with the condominium association; and provided written updates to
    Aquastar and its architect.
    Monica Souza, Avant’s Vice President, testified that Avant typically
    provides three types of work on a project like this one and charges separately
    for each distinct service: design services, construction administration
    services, and sales of construction materials and vendor products to be
    installed in the condominium unit. In this instance, because Aquastar had its
    own architect, Avant did not charge for design services. According to Souza,
    tax. Any other cost, including not limited to, freight, cartage,
    shipping, receiving, storage and delivery are not included in the
    preliminary budget and will be invoiced separately. All items,
    materials or supplies are custom and are non-cancelable, non-
    returnable, non-refundable. [Avant] does not guarantee fitness or
    merchantability of any items, materials or supplies and does not
    warranty or guarantee for any functionality, use, damage, defect,
    wear or fading, any items, materials, or supplies, purchased for
    Client’s Project, including but not limited to appliances, fixtures,
    fabrics and flooring items.
    4
    Avant did charge Aquastar both its 20% Fee and a profit mark-up for certain
    materials and services. Monica Souza testified that Avant’s determination
    whether to add a profit mark-up to a service, a vendor’s product or a product
    that Avant itself supplied was not a fixed decision but depended upon the
    “complexity” involved in Avant’s ability to deliver the specific order.
    By March 2018, as the project was nearing completion, Aquastar
    became concerned about mounting costs and requested that Avant provide
    Aquastar with copies of all vendor and contractor invoices reflecting
    wholesale costs of services and materials. Avant declined this request.
    Unable to verify actual vendor and contractor costs, Aquastar, on April 27,
    2018, terminated the contract with Avant. At that point, Avant’s records
    showed it had billed Aquastar a total of $1,208,899.87. These billings
    comprised all construction costs and all costs of vendor goods and services,
    plus Avant’s 20% Fee and profit mark-ups. As of the date Aquastar
    terminated the contract, Aquastar believed it had paid Avant $1,117,890.78.3
    Thus, according to Avant, Aquastar’s balance due at termination was
    $91,009.21. After Avant, on advice of counsel, made adjustments to this
    balance due, Avant, in May 2018, recorded a construction lien against the
    subject property in the amount of $66,909.21.
    3
    At trial this amount was adjusted to $1,117,250.63.
    5
    C. The Dueling Complaints
    In June 2018, Avant sued Aquastar. Avant’s operative amended
    complaint, filed in April 2019, contains four counts: breach of oral contract,
    open account, unjust enrichment, and foreclosure of its construction lien.
    Essentially, Avant sued Aquaster for the balance due, though it is not clear
    from Avant’s amended complaint whether Avant was seeking $91,009.12 or
    $66,909.21.
    A month after Avant filed its initial complaint, Aquastar sued Avant and
    Avant’s three owners individually (along with additional defendants who are
    not part of this appeal). Aquastar asserted against Avant counts for breach
    of contract, fraud in the inducement, breach of an implied covenant of good
    faith and fair dealing, conversion, fraudulent lien,4 violation of Florida’s
    Deceptive and Unfair Trade Practices Act (FDUTPA), and unjust enrichment;
    and, as against the individual owners of Avant in their individual capacities,
    counts for fraud in the inducement, conversion, FDUTPA violation, unjust
    enrichment, and fraud. 5 In its complaint, Aquastar alleged that Avant had
    4
    While Aquastar’s fraudulent lien count asserted a claim for punitive
    damages, see § 713.31(2)(c) (2018), Aquastar did not comply with the
    procedural requirements of section 768.72 of the Florida Statutes.
    5
    In the Amended Final Judgment, the trial court ruled against Aquastar on
    its claims for fraud in the inducement, conversion and unjust enrichment.
    Aquastar did not appeal these rulings.
    6
    overcharged Aquastar by (i) adding a profit mark-up to certain vendor goods
    and services over and above the 20% Fee that Aquastar asserted was
    inclusive of all profit, (ii) overbilling actual costs, and (iii) failing to complete
    billed work.
    The trial court consolidated the cases and, with the consent of the
    parties, treated Aquastar’s complaint as a counterclaim.
    D. Avant’s Accounting Procedures
    During the discovery phase of the litigation, Avant disclosed that it used
    a software program called Designer Logic for its project recordkeeping.
    Designer Logic, though, is a construction management program, not an
    accounting program. After Aquastar filed a motion to compel Avant to
    produce its QuickBooks ledgers, the trial court, on October 8, 2019, entered
    an order compelling Avant to provide Aquastar with access to all QuickBooks
    data pertaining to the Aquastar project. QuickBooks, unlike Designer Logic,
    has an audit trail feature that would give Aquastar a clearer picture of the
    history of Avant’s project invoices. Aquastar’s expert witness, Dana
    Kaufman, reviewed Avant’s Quickbooks entries, and Kaufman’s subsequent
    testimony at trial provided the principal support for the trial court’s rulings
    favorable to Aquastar.
    E. The Trial
    7
    The trial court conducted a six-day, non-jury trial in June 2020. The
    principal issue for the trial court’s adjudication was whether the parties’
    contract was, as Aquastar asserted, a cost-plus contract 6 or, as Avant
    argued, a fixed-price contract. 7 This threshold contract interpretation issue
    was intertwined with several factual issues arising from Aquastar’s
    allegations about Avant’s billing practices and accounting irregularities. Each
    party presented an accounting expert witness. The trial court found
    Kaufman’s testimony to be the more persuasive. In addition to testifying that
    Avant was not entitled to a profit mark-up on top of the 20% Fee, Kaufman
    also testified, based on his review of Avant’s QuickBooks ledger, that Avant
    had: (i) fabricated documents; (ii) backdated checks; (iii) greatly overcharged
    for the purchase of the unit’s tile, then received money back from the tile
    supplier; (iv) billed Aquastar for a purchase of goods intended for a different
    6
    As it argues on appeal, Aquastar asserted below that, pursuant to the
    proposals’ payment provision, it was obligated to pay Avant only for vendor
    services provided for, and materials incorporated into, the project, plus the
    20% Fee, i.e., a “cost-plus” contract.
    7
    As it argues on appeal, Avant asserted below that Aquastar was required
    to pay Avant’s invoices as they were submitted, and that Avant dynamically
    priced materials and services it acquired for the project based on the
    complexity of the item or service. Additionally, Avant asserted that, on those
    occasions when Aquastar acquired an item or service from a vendor not
    selected by Avant, Avant was entitled to – and invoiced Aquastar for – the
    20% Fee on that item. Avant characterized this invoice-based arrangement
    as its “fixed fee” contract.
    8
    Avant customer; and (v) entered charges into QuickBooks for which there
    were no corresponding purchase orders.
    F. The Amended Final Judgment
    In the detailed Amended Final Judgment, the trial court ruled primarily
    in favor of Aquastar and against Avant. The trial court entered judgment in
    favor of Aquastar on all four counts of Avant’s complaint and most of
    Aquastar’s counterclaim. 8 The trial court determined that the parties’ contract
    was a cost-plus contract. Additionally, based on Kaufman’s testimony, the
    trial court found that Avant not only breached the contract but acted in a
    fraudulent manner; that Avant’s $66,909.21 construction lien was fraudulent
    under section 713.31;9 and that Avant’s refusal to provide Aquastar with
    information about vendor costs was itself a deceptive practice prohibited by
    FDUTPA. The Amended Final Judgment’s damage award of $525,608.50
    8
    Aquastar prevailed on Avant’s breach of contract, open account, unjust
    enrichment, and lien foreclosure counts. Aquastar also prevailed on its own
    breach of contract, breach of implied covenant of good faith and fair dealing,
    and fraudulent lien counts, as well as its unpled fraud count against Avant
    (see section II.C., supra). As described in more detail in section II.D., supra,
    the Amended Final Judgment is internally inconsistent as to whether
    Aquastar prevailed on its FDUTPA claim against Avant.
    9
    Notwithstanding the trial court’s determination that Avant’s construction lien
    was fraudulent, the Amended Final Judgment did not discharge the lien (see
    section II, G. 2., infra).
    9
    for Aquastar, though, does not identify any separate and distinct damages
    occasioned by what the trial court characterized as Avant’s fraud, FDUTPA
    violation, or violation of the implied covenant of good faith and fair dealing.
    In the Amended Final Judgment, the trial court ruled in favor of Avant’s
    three owners whom Aquastar sought to hold personally liable for fraud in the
    inducement, conversion, unjust enrichment, and fraud; and declined to
    pierce the corporate veil to find them liable on Avant’s FDUTPA violation.
    Avant timely appealed the Amended Final Judgment and Aquastar
    cross-appealed.
    II. Analysis
    A. Introduction
    Avant challenges five rulings contained in the Amended Final
    Judgment that found Avant had (i) breached its contract with Aquastar, (ii)
    committed fraud, (iii) committed a FDUTPA violation, (iv) breached an
    implied covenant of good faith and fair dealing, and (v) filed a fraudulent
    construction lien. Avant also challenges the trial court’s damages calculation.
    Aquastar cross-appeals several rulings contained in the Amended Final
    Judgment: (i) that the three individual defendants bear no personal liability
    for Avant’s fraud and for Avant’s FDUTPA violation; (ii) that the trial court
    10
    erred by not discharging the fraudulent construction lien; and (iii) several trial
    court findings involving attorney’s fees, costs, and punitive damages.
    B. Breach of Contract
    1. The Contract’s Payment Terms
    At the threshold, we address Avant’s principal argument that the trial
    court erred by finding that the parties had entered into a cost-plus contract.
    While the trial court did not make a specific finding that the parties’ contract
    was ambiguous, the trial court, nevertheless, heard testimony from both
    parties’ experts regarding the parties’ contractual relationship, and, after
    weighing the testimony of the parties’ competing experts, ultimately
    concluded there was no credible testimony to support Avant’s position. 10
    10
    As noted, the trial court did not make a specific finding that the parties’
    contract was ambiguous. Generally, absent a finding of ambiguity, parol
    evidence is not admissible to assist the factfinder regarding the parties’
    intent. See Rivero v. Rivero, 
    963 So. 2d 934
    , 938 (Fla. 3d DCA 2007). Also,
    because questions of law are generally within the exclusive province of the
    trial court, an expert is normally not allowed to give opinion testimony on
    legal matters. See HSBC Bank USA, Nat’l Ass’n v. Buset, 
    241 So. 3d 882
    ,
    886 (Fla. 3d DCA 2018). In this case, though, both parties, without objection,
    elicited expert testimony regarding the nature of the parties’ contract.
    Ordinarily, we would review de novo a trial court’s contract interpretation.
    See Perez-Gurri Corp. v. McLeod, 
    238 So. 3d 347
    , 350 (Fla. 3d DCA 2017)
    (recognizing that the review of a trial court’s contract interpretation is de
    novo.). Instead, we review the record to determine whether the trial court’s
    finding in reliance on parol evidence is supported by competent, substantial
    evidence. Spancrete, Inc. v. Rinker Materials Corp., 
    623 So. 2d 760
    , 760
    (Fla. 3d DCA 1993); Laufer v. Norma Fashions, Inc., 
    418 So. 2d 437
    , 439
    (Fla. 3d DCA 1982).
    11
    Because the trial court and the parties treated the contract
    interpretation issue as a fact issue, we are compelled to affirm the trial court’s
    factual findings unless the record is devoid of competent, substantial
    evidence supporting the trial court’s findings. SG 2901, LLC v. Complimenti,
    Inc., 
    323 So. 3d 804
    , 806 (Fla. 3d DCA 2021). As ample record evidence
    supports the trial court’s finding that the parties entered into a cost-plus
    contract that limited Aquastar’s payment obligation to the 20% Fee, we affirm
    the trial court’s principal conclusion regarding the contract’s payment terms.
    2. Damages
    Avant next challenges the trial court’s damages calculation. The trial
    court calculated Aquastar’s damages by accepting the testimony of
    Aquastar’s expert witness Dana Kaufman that the full cost of the build-out of
    Aquastar’s condominium unit was $534,660.81. By adding Avant’s 20% Fee
    plus applicable sales tax to this amount, the trial court arrived at a total
    project cost of $656,511.70. By deducting this amount from Aquastar’s
    payment to Avant of $1,117,250.63, and including other damages to which
    Kaufman testified,11 the trial court calculated Aquastar’s damages at
    $525,608.50.
    11
    This damages amount includes $40,091.87 that Aquastar paid another
    contractor to complete the project and $24,777.70 to reimburse Aquastar for
    work for which Avant charged Aquastar but failed to perform.
    12
    The trial court relied heavily upon the testimony of Kaufman, a certified
    public accountant and certified fraud examiner. Kaufman conducted an
    exhaustive review of Avant’s financial records, including, significantly,
    Avant’s QuickBooks ledger. His testimony provided a detailed description of
    how Avant overcharged Aquastar. Kaufman’s testimony constituted
    competent, substantial evidence upon which the trial court was entitled to
    rely. See Coconut Grove Acquisition, LLC v. S & C Venture, 
    240 So. 3d 92
    ,
    95 (Fla. 3d DCA 2018). Because the trial court’s breach-of-contract damage
    findings are supported by competent, substantial evidence, we are
    compelled to affirm the Amended Final Judgment in this regard. See SG
    2901, LLC, 323 So. 3d at 806; Mars Int’l Corp. v. Pan Am. Trading Corp.,
    
    561 So. 2d 13
    , 13 (Fla. 3d DCA 1990) (“This court will not disturb the trial
    court’s findings and conclusions where such findings and conclusions are
    based upon competent substantial evidence.”); Pearce & Pearce, Inc. v.
    Kroh Bros. Dev. Co., 
    474 So. 2d 369
    , 371 (Fla. 1st DCA 1985) (“The general
    rule is that the extent of damages determined by a trial court is a question of
    fact which will be affirmed on appeal if supported by competent, substantial
    evidence.”).
    C. Fraud
    13
    Citing to this Court’s opinion in Peebles v. Puig, 
    223 So. 3d 1065
    , 1068
    (Fla. 3d DCA 2017), Avant also challenges the trial court’s determination that
    it is liable to Aquastar in the amount of $525,608.50 (the same amount that
    the trial court awarded to Aquastar for Avant’s breach of contract) for Avant’s
    fraud. 12 In Peebles, the contracting parties consented to the entry of a
    judgment for breach of contract damages against Peebles’s corporate
    employer. The case went to trial against Peebles on Puig’s fraud claim in
    which Puig alleged that she had been duped into entering and performing
    the breached contract based on Peebles’s fraudulent misrepresentations. Id.
    at 1067. Puig prevailed at trial, with the jury awarding Puig the exact same
    damages that had been awarded against and occasioned by Peebles’s
    corporate employer’s breach of contract. Id. at 1068. We reversed the fraud
    judgment against Peebles, concluding that, irrespective of what may have
    been Peebles’s fraudulent conduct, “Florida does not allow a party damaged
    by a breach of contract to recover the exact same contract damages via a
    fraud claim.” Id. at 1069; see Ghodrati v. Miami Paneling Corp., 
    770 So. 2d 12
    Avant also asserts that the trial court erred in finding Avant liable for
    Aquastar’s fraud claim because only the three individual defendants, and not
    Avant, were named in Aquastar’s fraud count. Aquastar counters that its
    fraud claim against Avant was tried by consent. Because of our reversal of
    the fraud award against Avant on other grounds, we need not, and therefore
    do not, reach this argument.
    14
    181, 183 (Fla. 3d DCA 2000) (“A plaintiff . . . may not recover damages for
    fraud that duplicate damages awarded for breach of contract.”).
    While we do not blithely disregard Kaufman’s evidence that, post-
    litigation, Avant made bookkeeping alterations to justify overcharges, the
    crux of this case is – and Aquastar’s damages are occasioned by – Avant’s
    breach of its contractual arrangement with Aquastar. Aquastar presented no
    evidence of, and the trial court awarded no damages that were separate and
    distinct from, those damages it suffered as a result of Avant’s breach of
    contract. We therefore reverse the Amended Final Judgment’s award of
    damages for fraud against Avant. Peebles, 223 So. 3d at 1069.
    D. The FDUTPA Claim
    Avant next challenges what appears to be the trial court’s
    determination in the Amended Final Judgment that Avant is liable to
    Aquastar in an indeterminate amount for Avant’s violation of Florida’s
    Deceptive and Unfair Trade Practices Act. See § 501.201 et seq., Fla. Stat.
    (2018). 13 The problems with the Amended Final Judgment with regard to
    Aquastar’s FDUTPA claim are twofold: (i) the Amended Final Judgment is
    internally inconsistent as to whether a FDUTPA violation occurred; and (ii)
    13
    Aquastar’s FDUTPA claim was also brought against Monica Souza,
    Cristina Souza and Sonia Sun Yee Mak. See section II, F., infra.
    15
    the Amended Final Judgment does not quantify Aquastar’s “actual damages”
    occasioned by any FDUTPA violation.
    As for the internal inconsistency, in the body of the Amended Final
    Judgment, the trial court seems to find that a FDUTPA violation occurred
    when Avant refused to disclose its vendor wholesale prices to Aquastar,
    allegedly as a part of the scheme to overcharge Aquastar. Yet, in the portion
    of the Amended Final Judgment that purports to adjudicate the parties’
    various claims, the Amended Final Judgment reads: “9. The Court enters
    judgment in favor of Avant . . . on Count XI of Aquastar’s Counterclaim
    [alleging a FDUTPA violation].” These contrasting holdings are not
    reconcilable.
    Equally, if not more problematic, is that, to the extent it was the trial
    court’s intention to enter judgment against Avant on Aquastar’s FDUTPA
    claim, the Amended Final Judgment does not adjudicate any “actual
    damages” occasioned by Avant’s alleged FDUTPA violation. Aquastar’s
    FDUTPA claim against Avant is a statutory cause of action premised on
    section 501.211(2). This statute reads, in relevant part, as follows: “In any
    action brought by a person who has suffered a loss as a result of a violation
    of this part, such person may recover actual damages, plus attorney's fees
    16
    and court costs as provided in s. 501.2105.” (Emphasis added.)14 Despite
    such “actual damages” being an essential element of a FDUTPA claim
    brought pursuant to section 501.211(2), nowhere in the Amended Final
    Judgment does the trial court make a finding of any “actual damages”
    Aquastar suffered as a result of Avant’s alleged FDUTPA violation.
    Because Aquastar, as the proponent of this FDUTPA claim, bore the
    burden of proof on the claim, we conclude that it was incumbent upon
    Aquastar to seek the appropriate post-judgment relief under rule 1.530 or
    otherwise to assure that the judgment entered on its FDUTPA claim
    accurately reflected the trial court’s rulings and contained the appropriate
    findings. While Aquastar did file a rule 1.530 motion directed toward other
    alleged errors and omissions of the Amended Final Judgment, and Aquastar
    has cross-appealed the trial court’s denial of its rehearing motion, Aquastar’s
    rehearing motion did not seek to correct or clarify the issues we have
    identified with regard to its FDUTPA claim against Avant, nor has Aquastar
    cross-appealed the Amended Final Judgment in this regard. Therefore, we
    14
    Section 501.211(1) provides for a statutory declaratory judgment, wherein
    a party may seek a declaration from a court that a particular activity or
    conduct is violative of FDUTPA. Aquastar’s counterclaim did not seek
    declaratory relief under section 501.211(1) but sought only damages under
    subsection (2).
    17
    reverse the Amended Final Judgment to the extent that it purported to enter
    judgment against Avant on Aquastar’s FDUTPA claim.
    E. Implied Covenant of Good Faith and Fair Dealing
    Avant also appeals the trial court’s finding that, by charging Aquastar
    in excess of the 20% Fee, Avant breached the contract’s implied covenant
    of good faith and fair dealing. Every Florida contract contains an implied
    covenant of good faith and fair dealing that protects parties’ reasonable
    expectations of honest conduct in their contractual obligations. Ins. Concepts
    & Design, Inc. v. Healthplan Servs., Inc., 
    785 So. 2d 1232
    , 1234 (Fla. 4th
    DCA 2001).
    The implied covenant, though, only “comes into play ‘when a question
    is not resolved by the terms of the contract or when one party has the power
    to make a discretionary decision without defined standards.’” Speedway
    SuperAmerica, LLC v. Tropic Enters., Inc., 
    966 So. 2d 1
    , 3 (Fla. 2d DCA
    2007) (quoting Publix Super Markets, Inc. v. Wilder Corp. of Del., 
    876 So. 2d 652
    , 654 (Fla. 2d DCA 2004)); see Cox v. CSX Intermodal, Inc., 
    732 So. 2d 1092
    , 1097-98 (Fla. 1st DCA 1999) (“[W]here the terms of the contract afford
    a party substantial discretion to promote the party’s self-interest, the duty to
    act in good faith nevertheless limits that party’s ability to act capriciously to
    contravene the reasonable contractual expectations of the other party.”). The
    18
    parties’ dispute centers on and is resolved by the meaning of the 20% Fee
    provision of the contract. When the trial court determined that, pursuant to
    the parties’ contract, Aquastar’s payment obligations were specifically
    defined and limited so that Aquastar was liable to Avant only for vendor
    services provided for, and materials incorporated into, the project, plus the
    20% Fee, any discretion retained by Avant in its billing was far too limited to
    implicate the covenant of good faith and fair dealing. Indeed, the 20% Fee
    locked in Aquastar’s contractual payment obligation and afforded Avant no
    discretion to charge Aquastar in excess of the 20% Fee.
    Accordingly, in this case, the trial court’s factual findings specifically
    defining and limiting Aquastar’s contractual payment obligations were
    inconsistent with its finding that Avant breached the implied covenant of good
    faith and fair dealing. We therefore reverse this part of the Amended Final
    Judgment.15 Our reversal on this point, though, is not outcome-determinative
    as to damages because the trial court did not assign an amount of damages
    to Avant’s alleged breach of the implied covenant.
    F. Liability of Individual Defendants
    15
    Nothing herein should be construed to mean that the implied covenant of
    good faith and fair dealing can never be implicated in a cost-plus contract.
    There certainly can be cost-plus contractual arrangements that contain the
    requisite discretion that would implicate the covenant. As per the trial court’s
    specific findings, though, these parties did not have such an arrangement.
    19
    In its cross-appeal, Aquastar challenges those portions of the
    Amended Final Judgment that found for the three individual defendants, the
    principals of Avant – Monica Souza, Cristina Souza and Sonia Sun Yee Mak.
    Aquastar’s counterclaim sought to hold the individual defendants personally
    liable for their conduct. In entering judgment for the individual defendants on
    all of Aquastar’s claims, the trial court found that the individuals had not
    engaged in any conduct that would render them personally liable for any of
    Aquastar’s claims.
    We affirm the trial court’s entry of judgment for the individual
    defendants, as the trial court’s findings are supported by competent,
    substantial evidence. See Miami-Dade Cnty. Expressway Auth. v. Elec.
    Transaction Consultants Corp., 
    300 So. 3d 291
    , 294 (Fla. 3d DCA 2020).
    G. Avant’s Construction Lien
    After Aquastar terminated the contract, Avant recorded a construction
    lien against the condominium unit, claiming it was owed $66,909.21 for work
    performed on Aquastar’s unit. Avant’s amended complaint sought to
    foreclose on this lien, and, both as an affirmative defense to Avant’s
    foreclosure claim and as a stand-alone claim in its counterclaim, Aquastar
    asserted the lien was fraudulent. Making extensive findings of fact – findings
    supported primarily by the testimony of Aquastar’s expert – the trial court
    20
    determined that, under section 713.31 of the Florida Statutes, 16 Avant’s
    construction lien was fraudulent: “The Court finds that based on these
    overcharges, the lien is either willfully exaggerated or at the very least,
    compiled with such willful or gross negligence so as to amount to a willful
    exaggeration.” This conclusion in the Amended Final Judgment, and the trial
    court’s subsequent order denying Aquastar’s rule 1.530 rehearing motion,
    spurred both Avant and Aquastar to raise several issues in the appeal and
    cross-appeal.
    1. Fraudulent Lien
    Avant argues that its lien was not fraudulent as it was not the
    consequence of willful exaggeration or willful inclusion of work not
    performed, but rather, that it was the product of Avant’s good faith belief that,
    pursuant to its contract with Aquastar, it was owed additional funds from
    16
    In relevant part, this statute reads as follows:
    Any lien asserted under this part in which the lienor has willfully
    exaggerated the amount for which such lien is claimed or in
    which the lienor has willfully included a claim for work not
    performed upon or materials not furnished for the property upon
    which he or she seeks to impress such lien or in which the lienor
    has compiled his or her claim with such willful and gross
    negligence as to amount to a willful exaggeration shall be
    deemed a fraudulent lien.
    § 713.31(2)(a), Fla. Stat. (2018).
    21
    Aquastar. Avant argues that a good faith contract dispute does not convert
    a lien arising from non-payment under the contract into a fraudulent lien
    under section 713.31(2) and relies heavily upon Vinci Development Co. v.
    Connell, 
    509 So. 2d 1128
    , 1132 (Fla. 2d DCA 1987) (“A subsequent dispute
    between the parties as to the amount of compensation due according to the
    contract plan of compensation or even a dispute as to the method of
    compensation provided in the contract does not convert such a good faith
    dispute into a fraudulent lien as provided in section 713.31.”).
    While Avant correctly identifies the general legal proposition
    underpinning Vinci Development, a careful reading of Vinci Development
    reveals that its holding is inapplicable in this case. After conducting a bench
    trial on the lien issue, the Vinci Development trial court made a specific
    factual finding that the contractor’s lien was “based upon a contract dispute
    of valid feelings on behalf of the plaintiff that he was entitled to it; a good-
    faith feeling he was entitled to.” 
    Id.
     In reversing the trial court’s “reluctant”
    finding that the subject lien had been exaggerated, the Vinci Development
    court concluded that a factual finding that a lien is based upon a good faith
    contractual dispute cannot co-exist with the statutory factual findings
    necessary to establish that the lien is fraudulent: i.e., willful exaggeration or
    willful inclusion of work not performed. 
    Id.
    22
    Unlike the trial court in Vinci Development, the trial court in this case
    never made a factual finding that the lien was the product of a good faith
    contractual dispute. By contrast, the trial court determined, based primarily
    on the testimony of Aquastar’s expert, that Avant willfully overcharged
    Aquastar and, therefore, willfully exaggerated the amount of the lien. These
    findings are supported by competent, substantial evidence. See Miami-Dade
    Cnty. Expressway Auth., 300 So. 3d at 294. Because “[i]t is inappropriate for
    this court to substitute its judgment for that of the trial court,” we are
    compelled to affirm the trial court’s determination in the Amended Final
    Judgment that Avant’s lien was fraudulent. Castiello v. Sweetwater Homes
    of Citrus, Inc., 
    843 So. 2d 1019
    , 1021 (Fla. 5th DCA 2003).
    2. Discharge of Lien
    In its cross-appeal, Aquastar maintains that the trial court erred by not
    discharging Avant’s construction lien after the trial court found it to be
    fraudulent. Post-appeal, Aquastar filed a motion requesting the trial court to
    enter an order discharging the lien, but the trial court declined to adjudicate
    the motion because of its belief that the pendency of this appeal deprived it
    of jurisdiction to entertain the motion.
    Upon a finding that a lien is fraudulent, section 713.31(2)(b) empowers
    the trial court to declare the lien unenforceable. On remand, the trial court
    23
    shall enter such a declaration. Additionally, irrespective of Aquastar’s claim
    – and the trial court’s finding – that Avant’s lien was fraudulent, Avant did not
    prevail on its claim seeking to enforce its lien, thereby entitling Aquastar,
    pursuant to 713.29 Florida Statutes, 17 to those reasonable attorney fees
    Aquastar incurred defending against Avant’s lien claim. On remand, the trial
    court shall conduct whatever proceedings the trial court deems appropriate
    to determine those reasonable attorney’s fees to which Aquastar is entitled
    pursuant to section 713.29.
    H. Aquastar’s Rule 1.530 Rehearing Motion
    Shortly after the trial court entered its initial final judgment, Aquastar
    filed a Florida Rule of Civil Procedure 1.530 rehearing motion requesting,
    among other things, that (i) the trial court revisit its determinations that the
    individual defendants were not liable for the claims asserted in Aquastar’s
    counterclaim, and (ii) consistent with the trial court’s fraudulent lien
    determination, the trial court award Aquastar section 713.31(2)(c) prevailing
    party attorney’s fees, costs and punitive damages. On April 14, 2021, the
    trial court entered an order denying Aquastar’s rule 1.530 rehearing motion.
    17
    This provision reads, in relevant part, as follows: “In any action brought to
    enforce a lien . . . under this part, the prevailing party is entitled to recover a
    reasonable fee for the services of her or his attorney for trial . . . in an amount
    to be determined by the court, which fee must be taxed as part of the
    prevailing party’s costs. . . .” § 713.29, Fla. Stat. (2018).
    24
    We affirm, without further elaboration, those portions of the trial
    court’s April 14, 2021 order denying Aquastar’s request to revisit its findings
    that the individual defendants have no liability for Aquastar’s claims (see
    section II.F., supra), and denying Aquastar’s claim for punitive damages.
    With regard to that portion of Aquastar’s rehearing motion arguing that
    the trial court erred by not awarding it reasonable attorney’s fees and costs
    pursuant to section 713.31(2)(c), to the extent that Aquastar seeks recovery
    of such fees that would not be duplicative of fees the trial court may award
    pursuant to section 713.29 (see section II.G.2., supra), on remand the trial
    court shall conduct whatever proceedings it deems necessary to determine
    whether, in light of the holdings contained in this opinion, Aquastar is the
    prevailing party on the significant issues in the case, and thus entitled to
    reasonable attorney’s fees and costs pursuant to section 713.31(2)(c). See
    Newman v. Guerra, 
    208 So. 3d 314
    , 319 (Fla. 4th DCA 2017).
    III. Conclusion
    We affirm the trial court’s determinations in the Amended Final
    Judgment that: (i) the parties entered into a cost-plus contract limiting
    Aquastar’s payment obligations as set forth therein; (ii) Avant breached the
    parties’ contract; and (iii) as a result, Aquastar is entitled to $525,608.50 in
    breach of contract damages from Avant. We also affirm the trial court’s
    25
    determination in the Amended Final Judgment that Avant’s construction lien
    was fraudulent, and remand to the trial court to: (i) enter an order discharging
    the lien; (ii) conduct those proceedings it deems necessary to determine
    those reasonable attorney’s fees to which Aquastar is entitled under section
    713.29; and (iii) to determine, in light of the holdings in this opinion, whether
    Aquastar is the substantially prevailing party entitled to reasonable fees and
    costs pursuant to section 713.31(2)(c), to the extent that these fees are not
    duplicative of section 713.29 fees.
    We reverse the Amended Final Judgment to the extent that it
    concluded that Avant committed a FDUTPA violation. We also reverse those
    portions of the Amended Final Judgment insofar as it determines Avant is
    liable to Aquastar for fraud and breach of the covenant of good faith and fair
    dealing.
    We affirm the trial court’s findings that Avant’s owners, Monica Souza,
    Cristina Souza and Sonia Sun Yee Mak, bear no individual personal liability
    to Aquastar and that Avant is not liable to Aquastar for punitive damages.
    After conducting the proceedings on remand, the trial court shall enter
    a Revised Final Judgment that reflects the result of those proceedings and
    that is consistent with this opinion’s holdings.
    26
    Affirmed in part, reversed in part, and remanded with instructions.
    27