F.H. PASCHEN, S.N. NIELSEN & ASSOCIATES, LLC v. B & B SITE DEVELOPMENT, INC. ( 2021 )


Menu:
  •        DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA
    FOURTH DISTRICT
    F.H. PASCHEN, S.N. NIELSEN & ASSOCIATES LLC,
    a foreign corporation,
    Appellant,
    v.
    B&B SITE DEVELOPMENT, INC., a Florida corporation,
    Appellee.
    No. 4D19-3839
    [February 3, 2021]
    Appeal from the Circuit Court for the Nineteenth Judicial Circuit in and
    for Okeechobee, County; Laurie E. Buchanan, Judge; L.T. Case No.
    472016CA000326.
    Caryn L. Bellus and Barbara E. Fox of Kubicki Draper, P.A., Miami, for
    appellant.
    Kevin S. Hennessy of Lewis, Longman & Walker, P.A., St. Petersburg,
    and Christopher D. Johns of Lewis, Longman & Walker, P.A., West Palm
    Beach, for appellee.
    GROSS, J.
    A general contractor and a subcontractor disagree over the scope of
    work required by a subcontract. Litigation ensued and both parties moved
    for summary judgment. The circuit court denied the contractor’s motion
    and granted summary judgment in favor of the subcontractor. We affirm
    the finding of liability on two counts of implied contract, but reverse and
    remand for a determination of damages.
    Facts
    F.H. Paschen, S.N. Nielson & Associates (the “GC”) was the general
    contractor on a project for the United States Postal Service to perform
    construction work at various locations, including the main post office in
    Okeechobee, Florida. The master contract with the Postal Service required
    the GC to “verify all dimensions shown of existing work . . . by actual
    measurement of the existing work,” and to report any discrepancies to the
    Postal Service’s contracting office prior to submitting a price proposal for
    a particular project.
    The GC entered into a subcontract with B&B Site Development, Inc.
    (the “Sub”) that required the Sub to perform demolition and paving work
    for the parking lot of the Okeechobee post office.
    Various documents used to solicit bids from potential subcontractors
    interchangeably used the terms “pavement,” “cement concrete pavement,”
    “existing Portland cement concrete pavement,” and “existing PCC
    pavement” to describe what was to be demolished and removed. The GC
    and the Sub exchanged information prior to the execution of the
    subcontract.
    The eastern driveway was not laid with Portland cement but asphalt.
    The Sub’s principal examined the asphalt, which was only three years old,
    and found that it was in good condition and did not need replacing. The
    Sub’s measurements at the site showed 9,000 square yards of concrete,
    so the Sub submitted a lump-sum bid based on that measurement.
    The GC failed to perform a pre-bid site walk to verify the area of concrete
    to be demolished. The GC incorrectly assumed that the entire parking lot
    was concrete and relied upon this mistaken assumption when it submitted
    a price proposal to the Postal Service. That proposal quoted a price for
    concrete removal that included the total area of all the pavement in the
    parking lot, including the asphalt eastern driveway.
    The GC and the Sub entered into a subcontract in December 2014. The
    subcontract described the project as “USPS—Okeechobee FL MPO—
    Replace Pavement” and provided that the Sub would perform “the work
    described in Schedule A.” Schedule A described the scope of work as
    including demolition of “the existing concrete pavement.” The subcontract
    also stated that the terms of the subcontract constituted “the full and
    complete agreement between the parties,” with “[a]ll previous oral or
    written promises, negotiations, representations or agreements relating to
    the subject matter of [the subcontract being] hereby declared to be null
    and void.”
    Shortly after the parties executed the subcontract, the Sub provided
    the GC with a “job sequencing narrative” that described a sequence of
    tasks that did not include demolishing or repaving the asphalt on the
    eastern driveway. The GC responded with an email that identified the
    asphalt eastern driveway as “Phase B5,” but which did not indicate that
    any work was to be performed there.
    2
    A problem arose when the project neared completion. The GC
    maintained that removal and replacement of the asphalt on the Phase B5
    eastern driveway was within the scope of the subcontract, while the Sub
    disagreed, pointing to language in the subcontract that specified removal
    of concrete only.
    Although the GC believed that replacement of the B5 asphalt fell
    withing the subcontract’s scope of work, it requested a price proposal from
    the Sub. The Sub provided a proposed work order to remove 561 square
    yards of asphalt pavement and to replace it “to match existing contracted
    work” at a price of $33,386.80.
    The parties came to no agreement about this extra work, with the GC
    maintaining that it was included in the Sub’s original contract price and
    the Sub insisting that it was extra work outside of the subcontract.
    Nonetheless, the Sub proceeded with the asphalt work to avoid delaying
    the project, insisting that it still expected to be paid for it. The GC
    responded that the project architect would review the costs and proposals
    to “ensure that this area was not already included” in the subcontract.
    The project architect reviewed the GC’s bidding documents and opined
    that the asphalt pavement area was included in the cost of the project.
    The Sub replaced the existing asphalt in the B5 area under protest and
    sought $33,386.80 in compensation. The GC denied the Sub’s request for
    additional compensation, maintaining its previous position.
    The Sub sued the GC in a three-count amended complaint for breach
    of contract, and two theories of implied contract—quantum meruit and
    unjust enrichment. The Sub sought damages of $33,386.80 or the
    reasonable value of the labor and materials it provided.
    Both parties moved for summary judgment. The circuit court granted
    the Sub’s motion for summary judgment on all three counts, denied the
    GC’s motion, and entered judgment for $33,386.80 plus interest. This
    appeal ensued.
    The Circuit Court Properly Determined that the Scope of the
    Subcontract was Limited to Concrete Removal
    The central issue in this case is whether the removal and replacement
    of the asphalt pavement on the eastern driveway fell within the scope of
    3
    the contract. The circuit court correctly ruled that the work at issue was
    not covered by the subcontract.
    “When the language of a contract is clear and unambiguous, courts
    must give effect to the contract as written and cannot engage in
    interpretation or construction as the plain language is the best evidence
    of the parties’ intent.” Talbott v. First Bank Fla., FSB, 
    59 So. 3d 243
    , 245
    (Fla. 4th DCA 2011). A court must interpret a contract “in a manner that
    accords with reason and probability,” endeavoring to “avoid an absurd
    construction.” Katz v. Katz, 
    666 So. 2d 1025
    , 1028 (Fla. 4th DCA 1996).
    A contract should be read as a whole. Discover Prop. & Cas. Ins. Co. v.
    Beach Cars of W. Palm, Inc., 
    929 So. 2d 729
    , 732 (Fla. 4th DCA 2006).
    Courts must give reasonable meaning to all provisions of a contract, rather
    than rendering part of the contract useless. Publix Super Mkts., Inc. v.
    Wilder Corp. of Del., 
    876 So. 2d 652
    , 654 (Fla. 2d DCA 2004). Specific
    provisions in a contract control over general provisions. Bridges v. City of
    Boynton Beach, 
    927 So. 2d 1061
    , 1063 (Fla. 4th DCA 2006). Furthermore,
    “the headings or subheadings of a document do not dictate the meaning
    of the entire agreement, especially where the literal language of the
    heading is contrary to the agreement’s overall scheme.” Hinely v. Fla.
    Motorcycle Training, Inc., 
    70 So. 3d 620
    , 624 (Fla. 1st DCA 2011). An
    ambiguous contractual provision must be construed against the drafter.
    City of Homestead v. Johnson, 
    760 So. 2d 80
    , 84 (Fla. 2000).
    Here, the only reasonable interpretation of the subcontract is that the
    scope of work did not include the removal and replacement of the asphalt
    eastern driveway of the parking lot. “Asphalt” and “concrete” are not
    synonymous terms. Nothing in the subcontract stated that the Sub was
    required to remove any asphalt from the parking lot. The subcontract did
    not say that the Sub was required to remove pavement from the “entire”
    parking lot. Nor did the subcontract describe the specific square footage
    of pavement that the Sub was to remove.
    To be sure, the subcontract contained general titles and headings such
    as “Replace Pavement” and “Replace Parking Area,” and set forth a general
    Summary of Work stating that “[t]he existing pavement should be
    demolished.” However, the specific provisions governing the subcontract’s
    scope of work control over the headings and other general language in the
    subcontract. In multiple places of the subcontract, the specific description
    of the scope of work called for the Sub to replace “the existing concrete
    pavement” or “the existing Portland cement concrete pavement.” The
    subcontract even specified the thickness of the concrete to be removed,
    but provided no similar specification for the existing asphalt.
    4
    While Schedule A stated that the work was “not limited to” the
    enumerated tasks, including disposal of the existing concrete pavement,
    the phrase “not limited to” modified the phrase “Sitework . . . necessary to
    complete the project in accordance with the contract plans and
    specifications.” Thus, although the phrase “not limited to” implies that
    there may be some unenumerated tasks that are necessary to complete
    the project, the phrase cannot be used to expand the required tasks
    beyond the “contract plans and specifications.”
    Documents used to prepare the bid and pre-contract communications
    do not change the interpretation of the subcontract. The subcontract
    required the Sub to rely on its own examination of the site, not on the
    opinions or representations of the GC or the Postal Service. The
    subcontract also contained a merger clause indicating that
    representations made previous to the contract were “null and void.” 1
    For these reasons, we agree with the trial court’s conclusion that the
    subcontract was “clear and unambiguous as to the work [the Sub] was
    required to perform. In very specific terms, the [subcontract] explains in
    multiple places what material was to be removed from the parking lot—
    Portland cement concrete—and what material was to be installed—
    asphalt.”
    The Dispute Resolution Clause of the Contract
    Cannot be Used to Rewrite Express Language in the Contract
    Concerning the Scope of Work
    The subcontract included this provision regarding “DISPUTES”:
    Should any dispute arise between the parties respecting the
    true construction or interpretation of the Plans, Specifications
    and/or the Contract Requirements, the decision of the Owner
    or the Owner’s designated representative as set forth in the
    General Contract shall be final.
    1 A pre-contract drawing that depicted the entire parking area does not alter our
    interpretation of the subcontract. The General Notes on the document stated
    that the drawing was “diagrammatic only” and that the subcontractor should
    “verify all dimensions.” Moreover, the Order of Preference provision in the Master
    Contract stated that “[i]n case of discrepancy or conflicts between drawings and
    specifications, the specifications will govern.” The specifications unambiguously
    call for the removal of concrete, not asphalt.
    5
    The law does not permit a party to use such a clause to rewrite the
    express language of a contract.
    “Construction projects frequently provide that, during the course of the
    project, disputes over the meaning of the contract documents, drawings
    and specifications will be decided by the architect.” James A. Cummings,
    Inc. v. Young, 
    589 So. 2d 950
    , 953 (Fla. 3d DCA 1991) (quoting 2
    Construction and Design Law § 11.7 (1984)). “As a general rule, the
    architect’s interpretation of the contract will be adopted by the court
    absent a showing of fraud, bad faith or gross mistake on the part of the
    architect.” Id. (quoting 2 Construction and Design Law § 11.7 (1984)).
    “When parties to a contract agree by its express terms to be bound to
    the determination made by an architect, that agreement is binding upon
    the parties.” Id. at 954 (citing Willcox v. Stephenson, 
    11 So. 659
     (Fla.
    1892)). “In the absence of fraud, or such mistake as would amount to
    fraud, the determination made by the architect shall be final.” 
    Id.
    The Florida Supreme Court has cautioned that “construction contracts
    cannot leave the arbitrary or fraudulent decision of an architect or
    engineer or the like to operate as a conclusive settlement of matters in
    controversy.” Duval Cnty. v. Charleston Eng’g & Contracting Co., 
    134 So. 509
    , 514 (Fla. 1931). As a Louisiana court has succinctly stated, “a
    contract clause providing the architect or engineer shall be the final arbiter
    of disputes is binding upon the parties unless the architect or engineer’s
    decision is manifestly arbitrary or rendered in bad faith.” J. H. Jenkins
    Contractor, Inc. v. City of Denham Springs, 
    216 So. 2d 549
    , 553 (La. Ct.
    App. 1968).
    The GC argues that the “DISPUTES” provision of the subcontract
    makes the Postal Service the final arbiter of all disputes concerning the
    plans and specifications. But the law is more nuanced. The law does not
    allow a third party’s arbitrary decision concerning the scope of a contract’s
    specifications “to operate as a conclusive settlement of matters in
    controversy.” Duval Cnty., 
    134 So. at 514
    . The GC appears to argue for
    an interpretation of the subcontract that would preclude judicial scrutiny
    of even an arbitrary interpretation of the scope of the subcontract.
    Application of such a principle would unfairly allow the revision of the
    explicit scope of a subcontract after work has commenced, to the detriment
    of the subcontractor.
    6
    In this case, to the extent that the Postal Service’s architect determined
    the scope of the project specifications in the subcontract, the
    determination was a “gross mistake” and was manifestly arbitrary. As
    noted above, the only reasonable interpretation of the subcontract is that
    it did not encompass the removal of the existing asphalt on the parking
    lot.
    Importantly, the architect’s decision had little to do with the actual
    language of the subcontract. Rather, the architect reasoned that because
    the GC’s bid was based on the parking lot’s total area of 89,388 square
    feet, the asphalt pavement area was already considered in the cost. In
    other words, USPS ultimately denied any additional compensation (and,
    in fact, reduced the compensation to the GC) because the GC’s Price
    Proposal quoted a price for concrete removal that included the total area
    of all the pavement in the parking lot, including the existing asphalt
    portion. But the GC’s mistake—bidding the job to USPS on the erroneous
    assumption that the entire parking lot consisted of concrete—had nothing
    to do with the proper interpretation of the subcontract.
    The Trial Court Erroneously Entered Summary Judgment on the
    Breach of Contract Count Because the GC Did Not Breach any
    Provision of the Subcontract
    We agree with the GC that the trial court erred in granting summary
    judgment in favor of the Sub on the breach of contract claim, as the record
    does not show that the GC breached any provision of the subcontract.
    An essential element of a claim for breach of contract is the existence
    of a material breach of a contractual duty. Chetu, Inc. v. KO Gaming, Inc.,
    
    261 So. 3d 605
    , 606 (Fla. 4th DCA 2019). “[W]hen a contract is silent on
    a matter, the court cannot impose contractual rights and duties under the
    guise of construction.” Blok Builders, LLC v. Katryniok, 
    245 So. 3d 779
    ,
    784 (Fla. 4th DCA 2018).
    This case differs from W&J Construction Corp. v. Fanning/Howey
    Associates, 
    741 So. 2d 582
     (Fla. 5th DCA 1999), upon which the trial court
    relied below, because the contractual language in the two cases is
    different. In Fanning/Howey, the Fifth District addressed a dispute
    between a contractor and an owner concerning the scope of a fire
    protection system called for by the contract. The Fifth District reversed a
    summary judgment in favor of the owner, concluding that a factual issue
    remained as to whether the owner breached the contract by failing to issue
    a formal written change order as called for by the contract provisions:
    7
    In this case, the essence of this dispute is whether the
    original contract specifications and engineering requirements
    encompassed the work [which the contractor] claims was
    above and beyond that originally required by the contract. If
    it did, then [the contractor] is entitled to no additional
    compensation. If it did not, because the [owner] required [the
    contractor] to do the work yet failed to issue a change order
    as it should have done pursuant to the contract, [the
    contractor] may be entitled to compensation.
    
    Id. at 584
    . However, the contract in Fanning/Howey stated that a
    “[c]hange order shall be issued for the amounts of cost and time
    determined by the Owner and shall become binding upon the Contractor .
    . . .” 
    Id.
     at 583 n.4 (emphasis added).
    While this case bears some similarity to Fanning/Howey, the
    contractual language here at issue is different. The subcontract stated
    that the GC had the “right” to “make changes, additions and/or deletions
    in the Work, upon written order to Subcontractor.”          Further, the
    subcontract provided that the value of the work as changed “shall be
    stated in the written order, approved by Contractor, and the Subcontract
    Price shall be adjusted.” Should the parties be unable to agree on the
    value, the subcontract provided that “the determination of the amount of
    such addition or reduction by the Owner as provided in the General
    Contract shall be binding on the Subcontractor and the Contractor.”
    However, the subcontract also stated that “[n]o extra work or changes
    from Plans and Specifications or from this Agreement will be recognized or
    paid for unless agreed to in writing before the extra work is started or the
    changes made.” Likewise, the subcontract stated that “any claims for
    extras demanded by the Subcontractor arising from omissions and/or
    discrepancies in the Plans or Specifications shall not be binding upon the
    Contractor or honored by the Contractor except to the extent previously
    approved and the extent actually paid for by the Owner.”
    Here, as the GC argues, it never executed the Sub’s work order and no
    contractual provision in the subcontract required it to do so. The GC
    consistently—albeit erroneously—maintained that the replacement of the
    asphalt in the B5 area was within the subcontract’s original scope of work.
    While the GC wanted the Sub to perform extra work, this conduct did not
    amend the subcontract. The GC did not approve the work order. It did
    not agree to the price stated on the work order. The Postal Service did not
    make a determination of the value of the extra work described in the work
    8
    order and it did not “actually pa[y] for” the extra work. For these reasons,
    we reverse the summary judgment as to the breach of contract count.
    The Trial Court Properly Entered Summary Judgment on Liability
    as to the Implied Contract Theories of Recovery—Unjust
    Enrichment and Quantum Meruit
    We affirm the summary judgment as to liability on the unjust
    enrichment and quantum meruit claims.
    The distinction between quantum meruit and unjust enrichment is
    often blurred “by the potential for both theories to apply to the same
    factual setting.” Commerce P’ship 8098 Ltd. P’ship v. Equity Contracting
    Co., Inc., 
    695 So. 2d 383
    , 387 (Fla. 4th DCA 1997). The doctrine of
    quantum meruit, also called a contract implied in fact, imposes liability,
    in the absence of an express agreement, “based on a tacit promise, one
    that is inferred in whole or in part from the parties’ conduct, not solely
    from their words.” 
    Id. at 385
    . As we explained in Commerce Partnership:
    Where an agreement is arrived at by words, oral or written,
    the contract is said to be “express.” A contract implied in fact
    is not put into promissory words with sufficient clarity, so a
    fact finder must examine and interpret the parties’ conduct to
    give definition to their unspoken agreement.
    
    Id.
     (internal citations omitted).
    To satisfy the elements of quantum meruit, the plaintiff must prove that
    “the plaintiff provided, and the defendant assented to and received, a
    benefit in the form of goods or services under circumstances where, in the
    ordinary course of common events, a reasonable person receiving such a
    benefit normally would expect to pay for it.” W.R. Townsend Contracting,
    Inc. v. Jensen Civil Constr., Inc., 
    728 So. 2d 297
    , 305 (Fla. 1st DCA 1999).
    An action for unjust enrichment (also called a contract implied in law
    or a quasi-contract), is not based upon the finding, by a process of
    implication from the facts, of an agreement between the parties. “A
    contract implied in law is a legal fiction, an obligation created by the law
    without regard to the parties’ expression of assent by their words or
    conduct.” Commerce P’ship, 
    695 So. 2d at 386
    . “The fiction was adopted
    to provide a remedy where one party was unjustly enriched, where that
    party received a benefit under circumstances that made it unjust to retain
    it without giving compensation.” 
    Id.
    9
    The elements of a cause of action for unjust enrichment are that: (1)
    the plaintiff has conferred a benefit on the defendant; (2) the defendant
    has knowledge of the benefit; (3) the defendant has accepted the benefit
    conferred; and (4) the circumstances are such that it would be inequitable
    for the defendant to retain the benefit without paying fair value for it. 
    Id.
    As a general principle, a plaintiff cannot pursue an implied contract
    theory, such as unjust enrichment or quantum meruit, if an express
    contract exists. See Fulton v. Brancato, 
    189 So. 3d 967
    , 969 (Fla. 4th DCA
    2016) (stating that a plaintiff cannot pursue unjust enrichment or
    quantum merit “if an express contract exists”); Daake v. Decks N Such
    Marine, Inc., 
    201 So. 3d 179
    , 181 (Fla. 1st DCA 2016) (“Quantum meruit
    is premised upon the absence of an express and enforceable agreement;
    accordingly, the existence of a valid, written contract between the parties
    necessarily precludes the doctrine’s application.”); Corn v. Greco, 
    694 So. 2d 833
    , 834 (Fla. 2d DCA 1997) (explaining that the legal fiction of
    quantum meruit cannot be maintained “when the rights of the parties are
    described in a written contract”).
    This general principle has often been misapplied to all disputes arising
    out of an express contract. Reliance upon a theory of implied contract is
    barred only if an express contract concerns the same subject matter as
    the implied contract. See Atlantis Estate Acquisitions, Inc. v. DePierro, 
    125 So. 3d 889
    , 893 (Fla. 4th DCA 2013) (“Unjust enrichment cannot apply
    where an express contract exists which allows the recovery.”); Solutec
    Corp. v. Young & Lawrence Assocs., 
    243 So. 2d 605
    , 606 (Fla. 4th DCA
    1971) (“Any proof of an express agreement between the parties as to the
    compensation to be paid for the services rendered would defeat . . . an
    action based upon quantum meruit . . . .”); Diamond “S” Dev. Corp. v.
    Mercantile Bank, 
    989 So. 2d 696
    , 697 (Fla. 1st DCA 2008) (“[A] plaintiff
    cannot pursue a quasi-contract claim for unjust enrichment if an express
    contract exists concerning the same subject matter.”); Kovtan v.
    Frederiksen, 
    449 So. 2d 1
    , 1 (Fla. 2d DCA 1984) (“It is well settled that the
    law will not imply a contract where an express contract exists concerning
    the same subject matter.”).
    The proposition that “the law will not imply a contract where a valid
    express contract exists” has been described by Professor Corbin as
    “misleading.” S. Bell Tel. & Tel. Co. v. Acme Elec. Contractors, Inc., 
    418 So. 2d 1187
    , 1189 (Fla. 4th DCA 1982). The real meaning of this statement is
    the following:
    [W]here the parties have made an express contract, the court
    should not find a different one by “implication” concerning the
    10
    same subject matter if the evidence does not justify an
    inference that they intended to make one. . . . [T]he fact that
    an express contract has been made does not prevent the
    parties from making another one tacitly, concerning the same
    subject matter or a different one.
    
    Id.
     (quoting 3 A. L. Corbin, Corbin on Contracts § 564 (1960 ed.)).
    Florida has long recognized that an implied contract may arise out of
    an express contract where a contractor or subcontractor performs “extras”
    not covered by the original contract. In DeLotto v. Fennell, 
    56 So. 2d 518
    (Fla. 1951), the Florida Supreme Court wrote:
    When parties enter into an agreement or contract for
    construction work and during the progress thereof alterations
    or changes are requested in the form of extras and otherwise,
    then the law implies an obligation to pay the reasonable costs
    thereof in addition to the stipulated sum named by the parties
    in the original agreement.
    Id. at 520 (Fla. 1951); see also Forest Constr., Inc. v. Farrell-Cheek Steel
    Co., Fla. Diversified Props. Div., 
    484 So. 2d 40
    , 42 (Fla. 2d DCA 1986)
    (“[T]he law implies an obligation to pay a reasonable cost for the extras not
    provided for in a contract[.]”); Davis v. Dep’t of Health & Rehab. Servs., 
    461 So. 2d 210
    , 212 (Fla. 1st DCA 1984) (“[W]here a contract exists and
    changes or alterations are requested by the owner, the law does imply an
    obligation to ‘pay the reasonable costs thereof[.]’”); Broderick v. Overhead
    Door Co. of Fort Lauderdale, 
    117 So. 2d 240
    , 243 (Fla. 2d DCA 1959)
    (“When parties enter into an agreement for construction work and during
    the progress of the construction changes are requested and made in the
    form of extras, then the law implies an obligation to pay the reasonable
    cost thereof in addition to the stipulated sum named in the original
    agreement.”).
    This case falls squarely under the rule of DeLotto. 2 The GC and the
    Sub entered into a construction contract. While the Sub performed under
    the contract, the GC requested and accepted a change to the scope of work,
    an extra that the GC erroneously claimed was included within the work
    described in the subcontract. Under these circumstances, “the law implies
    an obligation to pay the reasonable costs thereof in addition to the
    2 Although DeLotto involved an oral express contract rather than a written
    agreement, the principle of DeLotto still applies here.
    11
    stipulated sum named by the parties in the original agreement.” DeLotto,
    56 So. 2d at 520.
    The GC is also liable under a theory of unjust enrichment. The Sub
    conferred a benefit on the GC in the form of asphalt removal and
    replacement that was required under the master contract but not the
    subcontract. The GC accepted the benefit and the circumstances are such
    that it would be inequitable for the GC to retain the benefit without paying
    fair value for it. As the trial court ruled, “it would be both inequitable and
    unjust to allow [the GC] to retain the benefit without paying [the Sub] fair
    value for it, because it was [the GC’s] unilateral mistake and breach of the
    General Contract that created the problem.”
    The existence of the subcontract did not defeat recovery under either
    implied contract theory of recovery, as the subcontract did not cover
    removal and replacement of the existing asphalt.
    The Trial Court Erred in Granting Summary Judgment
    on the Issue of Damages
    We reverse the award of damages because issues of fact remain on that
    issue.
    The measure of damages in a quantum meruit action is the reasonable
    value of the labor performed and the market value of the materials
    furnished. Dean v. Blank, 
    267 So. 2d 670
    , 671 (Fla. 4th DCA 1972).
    Damages in an action for unjust enrichment “may be valued based on
    either (1) the market value of the services; or (2) the value of the services
    to the party unjustly enriched.” Merle Wood & Assocs., Inc. v. Frazer, 45
    Fla. L. Weekly D2635, 
    2020 WL 6937855
    , at *2 (Fla. 4th DCA Nov. 25,
    2020) (quoting Alvarez v. All Star Boxing, Inc., 
    258 So. 3d 508
    , 512 (Fla. 3d
    DCA 2018)). The measure of damages for unjust enrichment is the value
    of the benefit conferred, not the amount the plaintiff hoped to receive or
    the cost to the plaintiff. See Am. Safety Ins. Serv., Inc. v. Griggs, 
    959 So. 2d 322
    , 332 (Fla. 5th DCA 2007) (holding that an award of damages for
    unjust enrichment was not supported by competent, substantial evidence
    where the plaintiffs “only presented evidence of the money they hoped to
    receive” and did not present evidence of the value of the benefit conferred);
    Levine v. Fieni McFarlane, Inc., 
    690 So. 2d 712
    , 713 (Fla. 4th DCA 1997)
    (explaining that it is the “the benefit to the owner, not the cost to the
    improver,” which is the basis for an award for unjust enrichment).
    12
    Here, the Sub failed to meet its burden of proving that there were no
    genuine issues of material fact as to damages on its claims for quantum
    meruit and unjust enrichment. On the issue of damages, the Sub
    presented only (1) a proposed change order showing the $33,386.80 price
    the Sub wanted to charge for the asphalt removal and replacement and (2)
    a separate document showing a breakdown of costs for the proposed
    change order. While such evidence would have been sufficient had the
    Sub prevailed on its express contract count, it did not meet what was
    required under either implied contract theory.
    The Sub presented no evidence of the reasonable value of the labor and
    materials it provided on the B5 phase of the project. There was no opinion
    evidence as to the market value of the services performed on the B5
    asphalt phase of the project. Nor does the record contain any evidence as
    to the number of man-hours spent on this phase of the project, the
    reasonable hourly rate for labor or equipment used, or the market value
    of materials furnished.
    The record contains no evidence establishing the amount of the Sub’s
    damages under either quantum meruit or unjust enrichment.
    Conclusion
    We affirm the summary judgment as to liability under the quantum
    meruit and unjust enrichment counts, reverse the summary judgment on
    the breach of contract count, and remand for further proceedings on the
    issue of damages under the implied contract theories of recovery.
    Affirmed in part, reversed in part, and remanded.
    LEVINE, C.J., and CONNER, J., concur.
    *        *        *
    Not final until disposition of timely filed motion for rehearing.
    13