Cottrell v. Atlanta Development Authority, D/B/A Invest Atlanta , 297 Ga. 1 ( 2015 )


Menu:
  • In the Supreme Court of Georgia
    Decided: March 16, 2015
    S14A1874. COTTRELL et al. v. ATLANTA DEVELOPMENT
    AUTHORITY d/b/a INVEST ATLANTA et al.
    MELTON, Justice.
    This case concerns the Superior Court of Fulton County’s validation of
    roughly $200 million in municipal bonds (the “2014 NSP Bonds”) to be issued
    by the Atlanta Development Authority d/b/a Invest Atlanta (“Invest Atlanta”).
    Invest Atlanta and the Geo. L. Smith II Georgia World Congress Center
    Authority (“Congress Center Authority”) (collectively, the “New Stadium
    Entities”) propose to have the 2014 NSP Bonds issued for the purpose of
    funding a portion of the cost of developing, constructing, and operating a new
    stadium facility in downtown Atlanta (the “New Stadium Project” or “NSP”) for
    the Atlanta Falcons professional football team. Additional funding for the NSP
    will be provided by the Atlanta Falcons Stadium Company, LLC (“StadCo”), a
    Georgia limited liability company associated with the Atlanta Falcons Football
    Club, LLC (the “Club”), as well as through the sale of personal seat licenses.
    The NSP is a successor facility to the over twenty-year-old Georgia Dome, and
    it will be owned by the Congress Center Authority, which also owns the Georgia
    Dome.
    Procedurally, on February 4, 2014, the State of Georgia filed a Petition for
    Bond Validation in the superior court to authorize the issuance of the 2014 NSP
    Bonds. A notice to the public was filed on that same day, as well as a Rule Nisi
    Order setting the bond validation hearing for February 17, 2014. Notice of the
    proceeding was published in the Fulton County Daily Report on February 7,
    2014 and February 14, 2014 as required by OCGA § 36-82-76. Rev. William L.
    Cottrell, Sr., Mamie Lee Moore, Tracy Y. Bates, John H. Lewis, III, and Joe
    Henry Beasley (hereinafter collectively “Cottrell”) moved to intervene in the
    proceedings to file objections to the bond validation, and the trial court allowed
    them to do so. Among other things, Cottrell contended that OCGA § 48-13-51
    (a) (5) (B), which allows for an extended time period in which a county or
    municipality may levy a Hotel/Motel tax for purposes of funding a “successor
    facility” to an existing “multipurpose domed stadium facility,” was an
    unconstitutional special law. See Georgia Constitution of 1983, Art. III, Sec. VI,
    Par. IV (a). The bond hearing was continued until April 10, 2014, and the trial
    2
    court entered a Consolidated Pre-Trial Order on April 8, 2014. Following the
    April 10, 2014 hearing, the trial court entered a May 8, 2014 Validation Order
    and Final Judgment validating the 2014 NSP Bonds and overruling all
    objections. Cottrell appeals from this ruling, and, for the reasons that follow, we
    affirm.
    By way of background, the Georgia Dome was, and the NSP is to be,
    funded in part by a Hotel/Motel tax levied under OCGA § 48-13-51 (a) (5).1
    1
    The statute states in relevant part that
    (i) . . . a county (within the territorial limits of the special district
    located within the county) or municipality is authorized to levy a
    tax under this Code section at a rate of 7 percent. A county or
    municipality levying a tax pursuant to this paragraph shall expend
    an amount equal to at least 51.4 percent of the total taxes collected
    prior to July 1, 1990, at the rate of 7 percent and an amount equal
    to at least 32.14 percent of the total taxes collected on or after July
    1, 1990, at the rate of 7 percent for the purpose of [among other
    things]: (I) promoting tourism, conventions, and trade shows.
    (ii) In addition to the amounts required to be expended under
    division (i) of this subparagraph, a county or municipality levying
    a tax pursuant to this paragraph shall further expend (in each fiscal
    year during which the tax is collected under this paragraph) an
    amount equal to 14.3 percent of the total taxes collected prior to
    July 1, 1990, at the rate of 7 percent and an amount equal to 39.3
    percent of the total taxes collected on or after July 1, 1990, at the
    rate of 7 percent toward funding a multipurpose domed stadium
    3
    Generally, Hotel/Motel taxes can only be levied at a rate of three percent or less.
    See OCGA § 48-13-51 (a) (1) (D) (“Except as provided in paragraphs (2.1),
    (2.2), (3), (3.1), (3.2), (3.3), (3.4), (3.5), (3.7), (4), (4.1), (4.2), (4.3), (4.4), (4.5),
    (4.6), (4.7), (5), (5.1), (5.2), and (5.3) of this subsection, no tax levied pursuant
    to this Code section shall be levied or collected at a rate exceeding 3 percent of
    the charge to the public for the furnishings”). However, OCGA § 48-13-51 (a)
    (5) (A) provides an exception to this three percent ceiling for Hotel/Motel taxes
    by allowing counties and municipalities to levy a seven percent Hotel/Motel tax
    as long as a designated portion of the collected tax proceeds is used to fund a
    multipurpose domed stadium facility. Before 2010, taxes imposed under
    Paragraph (a) (5) of OCGA § 48-13-51 were required to have a stated expiration
    date “not later than December 31, 2020.” OCGA § 48-13-51 (a) (5) (A) (ii).
    However, the General Assembly amended Paragraph (a) (5) in 2010 to add a
    new subsection (B), which allowed those taxing jurisdictions that had previously
    levied a tax under Paragraph (a) (5) to extend the stated expiration date to
    facility. . . . Any tax levied pursuant to this paragraph shall
    terminate not later than December 31, 2020.
    OCGA § 48-13-51 (a) (5) (A) (i) and (ii).
    4
    December 31, 2050, so long as the same portion of the proceeds that had been
    used to fund the original multipurpose domed facility was expended to fund a
    “successor facility” during the extended period. Pursuant to OCGA § 48-13-51
    (a) (5) (B):
    Notwithstanding the [December 31, 2020] termination date
    stated in division (ii) of subparagraph (A) of this paragraph
    . . . a tax levied under this paragraph may be extended by
    resolution of the levying county or municipality and continue
    to be collected through December 31, 2050, if a state
    authority certifies: (i) that the same portion of the proceeds
    will be used to fund a successor facility to the multipurpose
    domed facility as is currently required to fund the
    multipurpose domed facility under division (ii) of
    subparagraph (A) of this paragraph; (ii) that such successor
    facility will be located on property owned by the state
    authority; and (iii) that the state authority has entered into a
    contract with a national football league team for use of the
    successor facility by the national football league team through
    the end of the new extended period of the tax collection.
    In order to structure the deal and issue the 2014 NSP Bonds for the New
    Stadium Project, the New Stadium Entities created various agreements and took
    several steps:
    •        Based on the 2010 subsection (B) amendment to OCGA §
    48-13-51 (a) (5) allowing for an extended period to collect a
    Hotel/Motel tax as long as a certain percentage of the proceeds
    5
    collected during the extended period were expended to fund a
    “successor facility,” in March 2013, the City passed City Resolution
    13-R-0615, which authorized
    the Mayor to execute (1) a Hotel/Motel Tax Funding
    Agreement with [Invest Atlanta], as consideration for
    Invest Atlanta agreeing to provide for the development,
    construction, equipping, and funding of the publicly
    financed portion of the cost of a multi-purpose operable
    roof stadium through its issuance of revenue bonds
    necessary to provide such services and facilities and the
    [City] agreeing to make payments from certain
    Hotel/Motel Taxes collected under such agreement to
    be pledged as security for the [2014 NSP Bonds] (2) a
    Hotel/Motel Tax Operation and Maintenance
    Agreement [“O&M Agreement”] with [the] Congress
    Center Authority for the use of funds in excess of the
    amount necessary for payments due under the
    Hotel/Motel Tax Funding Agreement to provide for
    operation and maintenance services for the new
    stadium, all in accordance with OCGA [§] 48-13-51 (a)
    (5) [B]; and for other purposes.
    The City prepared a Hotel/Motel Tax Funding Agreement with
    Invest Atlanta and an O&M Agreement with the Congress Center
    Authority consistent with City Resolution 13-R-0615. The City
    currently levies a Hotel/Motel Tax, and 39.3 percent of the first
    seven percent of the tax will be paid to fund the NSP (the “NSP Tax
    6
    Proceeds”).
    •     Invest Atlanta is to issue the 2014 NSP Bonds, which Bonds
    will be secured by Invest Atlanta’s pledge and assignment of the
    NSP Tax Proceeds to a bond Trustee. The City will collect the tax
    and transfer the proceeds to Invest Atlanta, and Invest Atlanta will
    use the NSP Tax Proceeds to pay the debt service on the 2014 NSP
    Bonds.
    •     Pursuant to a “Bond Proceeds Funding and Development
    Agreement,” Invest Atlanta is to place the proceeds from the sale of
    the 2014 NSP Bonds into a Project Fund and instruct the Trustee to
    distribute money from the Project Fund to the Congress Center
    Authority. The Congress Center Authority will use the money to
    fund the New Stadium Project, and the Congress Center Authority
    will own the New Stadium Project. The Congress Center Authority
    will also raise money to fund a portion of the NSP by selling certain
    personal seat licenses. StadCo will provide all additional funds
    necessary for the NSP.
    7
    •     After paying the necessary NSP Tax Proceeds to Invest
    Atlanta to provide for the payment of the principal and interest on
    the 2014 NSP Bonds, the City will allocate the remaining NSP Tax
    Proceeds to the Congress Center Authority, consistent with the
    extended levy provision of OCGA § 48-13-51 (a) (5) (B). The
    Congress Center Authority, in turn, will use those proceeds to pay
    a portion of the NSP’s future capital upkeep, maintenance and
    operating expenses.
    •     StadCo and the Club are required to play Atlanta Falcons’
    regular-season and post-season home games at the New Stadium
    Project for at least 30 years.
    1. Cottrell contends that the 2010 subsection (B) amendment to OCGA §
    48-13-51 (a) (5) is an unconstitutional “special law” that violates the
    Uniformity Clause of the Georgia Constitution. See Ga. Const. of 1983
    Art. III, Sec. VI, Par. IV (a). We disagree.
    Pursuant to the Uniformity Clause, “[l]aws of a general nature shall have
    uniform operation throughout this state and no local or special law shall
    8
    be enacted in any case for which provision has been made by an existing
    general law.” 
    Id. In this
    regard, a statute would run afoul of the
    Constitution if it were “a general law which lack[ed] uniform operation
    throughout the state or a special law for which provision ha[d] been made
    by existing general law.” Lasseter v. Georgia Public Service Com’n., 
    253 Ga. 227
    , 229 (2) (319 SE2d 824) (1984). However,
    “‘[o]ur State Constitution only requires a law to have uniform
    operation; and that means that it shall apply to all persons, matters,
    or things which it is intended to affect. If it operates alike on all
    who come within the scope of its provisions, constitutional
    uniformity is secured. Uniformity does not mean universality. This
    constitutional provision is complied with when the law operates
    uniformly upon all persons who are brought within the relations and
    circumstances provided by it.' (Cits.) A law which operates
    uniformly upon all persons of a designated class is a general law
    within the meaning of the Constitution, provided that the
    classification thus made is not arbitrary or unreasonable.” [Cit.]
    (Emphasis supplied.) State v. Martin, 
    266 Ga. 244
    , 246 (4) (466 SE2d 216)
    (1996). Indeed, “[t]he General Assembly may [properly] exclude certain
    persons or things from the application of a general law.” McAllister v.
    American National Red Cross, 
    240 Ga. 246
    (2) (240 SE2d 247) (1977).
    As explained more fully below, OCGA § 48-13-51 (a) (5) (B) is a proper
    exception to the general law of OCGA § 48-13-51 (a) (1) (D), which
    9
    imposes a three percent cap on Hotel/Motel taxes, in that the statute
    applies uniformly on all taxing authorities which come within the scope
    of its provisions, and because the classification made by the statute is not
    arbitrary or unreasonable.
    As an initial matter, this Court has previously determined that OCGA §
    48-13-51 (a) (5) (A), the statute most closely related to OCGA § 48-13-51
    (a) (5) (B), is a proper general law. See Youngblood v. State, 
    259 Ga. 864
    ,
    866 (2) (388 SE2d 671) (1990) (upholding constitutionality of § 48-13-51
    (a) (5) (A) under the similar Tax Uniformity Clause). In this connection,
    OCGA § 48-13-51 (a) (5) (A) provides a proper general law exception to
    OCGA § 48-13-51 (a) (1). More specifically, as mentioned previously,
    OCGA § 48-13-51 (a) (1) allows for the levy of a Hotel/Motel tax that
    may not “exceed[] 3 percent.” OCGA § 48-13-51 (a) (1) (D). There are
    several exceptions to this three percent cap on Hotel/Motel taxes, one of
    which, OCGA § 48-13-51 (a) (5) (A), allows for the levy of a seven
    percent Hotel/Motel tax for purposes of funding a multipurpose domed
    stadium facility through December 31, 2020. See OCGA § 48-13-51 (a)
    (5) (A) (ii). This exception to the three percent cap on Hotel/Motel taxes
    10
    is proper, in that it applies uniformly to any “county (within the territorial
    limits of the special district located within the county) or municipality” (
    OCGA § 48-13-51 (a) (5) (A) (i)) that has decided to levy such an
    increased tax, and in that it is reasonable, because allowing this class of
    taxing entities to collect an increased tax on “the provision of public
    accommodations. . . is not arbitrary[,] as the[] businesses [subject to the
    tax] will directly benefit from an increase in tourism and the provision of
    local government services within the district” in which the multipurpose
    domed stadium facility is being built. 
    Youngblood, supra
    , 
    259 Ga. 864
    ,
    866 (2) (388 SE2d 671) (1990).
    Like subsection (A) before it, OCGA § 48-13-51 (a) (5) (B) is also a
    constitutional general law exception to the three percent cap on
    Hotel/Motel taxes contained in OCGA § 48-13-51 (a) (1). It is of no
    consequence that subsection (B) happens to only impact the New Stadium
    Project at this time, as the other counties and municipalities covered under
    subsection (A) that could have collected a seven percent Hotel/Motel tax
    for purposes of funding their own multipurpose domed stadium facilities
    at the time that subsection (A) was passed had every opportunity to do so.
    11
    We reject the idea that the Legislature is now forbidden from enacting
    legislation that affects the class of taxing entities covered under
    subsection (A) simply because only one taxing entity chose to take
    advantage of implementing a seven percent Hotel/Motel tax for purposes
    of funding a multipurpose domed stadium facility over twenty years ago.
    To determine otherwise would mean that this class would be forever off
    limits for further legislation by the General Assembly simply because only
    one jurisdiction stepped into the previously open class. Indeed, even if the
    window has now closed for additional entities to begin funding their own
    multipurpose domed stadium facilities pursuant to subsection (A), that
    would not change the fact that the law itself is a general law that provided
    a proper class with reasonable taxing authority for funding a stadium
    facility if those class members chose to do so during the time frame in
    which they had an opportunity to do so. In this regard, like subsection (A),
    subsection (B) applies uniformly to all taxing authorities affected by it.
    Likewise, the classification of the taxing authorities affected by
    subsection (B) is reasonable, in that (1) there is nothing arbitrary or
    unreasonable about allowing the same taxing entities that already have
    12
    experience paying for a multipurpose domed stadium facility through the
    collection of a seven percent Hotel/Motel tax under OCGA § 48-13-51 (a)
    (5) (A) to collect such a tax in the future to fund a different stadium after
    the first tax has expired, and (2) the collection of a seven percent tax by
    these authorized entities on “the provision of public accommodations . .
    . is not arbitrary[,] as the[] businesses [subject to the tax] will directly
    benefit from an increase in tourism and the provision of local government
    services within the district” in which the new stadium facility is being
    built. 
    Youngblood, supra
    , 259 Ga. at 866 (2).
    Accordingly, we find that OCGA § 48-13-51 (a) (5) (B) is constitutional.
    2. Cottrell argues that the Hotel/Motel Tax Funding Agreement
    between the City and Invest Atlanta is illegal, and, by extension,
    unconstitutional,2 because OCGA § 48-13-51 (a) (5) (B) requires that tax
    proceeds collected to fund the successor stadium facility “shall be
    expended only through a contract with the certifying state authority,” and
    2
    Cottrell contends that the contract violates the Intergovernmental
    Contracts Clause of the Georgia Constitution. See Ga. Const. of 1983 Art. IX,
    Sec. III, Par. 1 (a).
    13
    the City’s contract with Invest Atlanta is not a contract with “the
    certifying state authority.”3 However, Cottrell ignores the fact that more
    than one contractual agreement exists to control the manner in which the
    NSP Tax Proceeds are ultimately expended by the Congress Center
    Authority to fund the NSP. Indeed, as explained more fully below, the
    Hotel/Motel Tax Funding Agreement works in conjunction with the Bond
    Proceeds Funding and Development Agreement to ensure that the NSP
    Tax Proceeds are expended in a manner consistent with the requirements
    of OCGA § 48-13-51 (a) (5) (B).
    OCGA § 48-13-51 (a) (5) (B) states in relevant part that
    [d]uring the extended period of [Hotel/Motel Tax] collection [through
    December 31, 2050], the county or municipality shall further expend (in
    each fiscal year during which the tax is collected during the extended
    period of collection) an amount equal to 39.3 percent of the total taxes
    collected at the rate of 7 percent toward funding the successor facility
    certified by the state authority. Amounts so expended shall be expended
    only through a contract with the certifying state authority.
    Pursuant to the Hotel/Motel Tax Funding Agreement, after Invest Atlanta
    issues the 2014 NSP Bonds, the City will pay the NSP Tax Proceeds to a
    3
    The Congress Center Authority is the certifying state authority.
    14
    bond trustee to whom the proceeds have been assigned by Invest Atlanta.
    The funds are used to pay the debt service on the bonds and are
    distributed from the bond trustee to the Congress Center Authority
    pursuant to a Bond Proceeds Funding and Development Agreement,
    which allows the Congress Center Authority, as the certifying state
    authority here, to expend the money to fund the New Stadium Project. In
    this manner, the City will meet its obligation to ensure that it “expend[s]
    [the NSP Tax Proceeds] toward the funding of a successor facility” while
    also making sure that the “[a]mounts so expended [to fund the New
    Stadium Project] shall be expended only through a contract with the
    certifying state authority.” This arrangement complies with the
    requirements of OCGA § 48-13-51 (a) (5) (B), and Cottrell’s argument to
    the contrary is without merit.
    3. Cottrell asserts that the proposed bond transaction violates Art. IX, Sec.
    VI, Par. I of the Georgia Constitution and OCGA § 36-82-66 of the
    Revenue Bond Law because Invest Atlanta will not own or operate the
    NSP. Specifically, Cottrell contends that, because Invest Atlanta would
    not “own or operate” the New Stadium Project, the “revenue” to be paid
    15
    to Invest Atlanta by the City would not actually be revenue “derived from
    the project.” See Georgia Constitution of 1983 Art. IX, Sec. VI, Par. I
    (“The obligation represented by revenue bonds shall be repayable only out
    of the revenue derived from the project”). See also OCGA § 36-82-66
    (“Revenue bonds . . . shall not be payable from or charged upon any funds
    other than the revenue pledged to the payment thereof”); OCGA § 36-82-
    61 (3) (“‘Revenue’ or ‘revenue of the undertaking’ means all revenues,
    income, and earnings arising out of or in connection with the operation or
    ownership of the undertaking”). We disagree.
    There is no requirement that Invest Atlanta own the New Stadium Project
    in order for it to issue revenue bonds to fund the project or for the tax
    proceeds paid to Invest Atlanta to be considered as part of the “revenue”
    to pay for the bonds.4 Indeed, pursuant to OCGA § 36-82-61 (3) of the
    Revenue Bond Law, “revenue” consists of “all revenues, income, and
    earnings arising out of or in connection with the operation or ownership
    4
    Cottrell does not dispute whether tax funds may properly be included as
    part of the “revenue” to repay a bond issue. He contends only that, because
    Invest Atlanta will not “own or operate” the NSP, the tax funds collected here
    will not constitute “lawful” revenue.
    16
    of the undertaking.” (Emphasis supplied.) Here, Invest Atlanta need not
    be the owner of the NSP, as the Hotel/Motel NSP Tax Proceeds are being
    collected “in connection with the [Congress Center Authority’s] operation
    or ownership of the [NSP].” In this manner, the NSP Tax Proceeds qualify
    as lawful revenue, and Invest Atlanta need not actually own the NSP for
    this to be the case.
    4. Cottrell further contends that the bond transaction here violates the
    Intergovernmental Contracts Clause (see Ga. Const. of 1983 Art. IX, Sec.
    III, Par. 1 (a)), in that the NSP is not an authorized “project” of Invest
    Atlanta. More specifically, Cottrell argues that, because the NSP is really
    a “project” of the Congress Center Authority, and not a project actually
    being developed by Invest Atlanta, the NSP is not eligible for bond
    financing under the Developmental Authorities Law. See OCGA §
    36-62-2 (6) (H) (i) (“Project’ includes . . . [t]he acquisition, construction,
    improvement, or modification of any property, real or personal, which
    shall be suitable for or used as or in connection with . . . [s]ports
    facilities”). Cottrell is incorrect.
    Just as there is no requirement that Invest Atlanta own the NSP, there is
    17
    also no requirement that Invest Atlanta actually construct the NSP in order
    to properly issue revenue bonds for the purpose of financing the project.
    Pursuant to the Developmental Authorities Law, Invest Atlanta has the
    power to “issue [ ] revenue bonds . . . and to use the proceeds thereof for
    the purpose of paying all or part of the cost of any project” (OCGA §
    36-62-6 (a) (13) (emphasis supplied)), not only those projects
    “constructed” or “developed” by the authority issuing the bonds. Nor is
    there any language in the Developmental Authorities Law that would
    otherwise prohibit Invest Atlanta from using bond proceeds to pay the
    costs of another government entity’s project that “promote[s] trade,
    commerce, industry, and employment opportunities for the public good
    and the general welfare.” OCGA § 36-62-9. See also 
    Youngblood, supra
    ,
    259 Ga. at 866 (2) (multipurpose stadium facility would benefit
    businesses subject to Hotel/Motel tax in that the facility would bring
    about “an increase in tourism”). This enumeration is without merit.
    5. Cottrell argues that the trial court erred in failing to hold that City
    Resolution 13-R-0615, which extends Atlanta’s existing Hotel/Motel tax
    to fund a portion of the construction and maintenance costs of the NSP,
    18
    is illegal. He contends, primarily, that City Resolution 13-R-0615 is void
    because the City enacted it in March 2013, over a year before the
    Congress Center Authority provided the City with a tax certification
    required by OCGA § 48-13-51(a) (5) (B) to allow for the City to pass
    such a resolution.5 Cottrell is mistaken.
    In this regard, OCGA § 48-13-51(a) (5) (B) provides in relevant part that
    a tax levied under this paragraph may be extended [past the
    December 31, 2020 termination date stated in OCGA §
    48-13-51(a) (5) (A) (ii)] by resolution of the levying county
    or municipality and continue to be collected through
    December 31, 2050, if a state authority certifies [among other
    things]: (i) that the same portion of the proceeds will be used
    to fund a successor facility to the multipurpose domed facility
    as is currently required to fund the multipurpose domed
    facility under division (ii) of subparagraph (A) of this
    paragraph.
    By its plain terms, OCGA § 48-13-51 (a) (5) (B) dictates that a seven
    percent Hotel/Motel tax may be “levied . . . and continue to be collected
    through December 31, 2050” to fund a successor facility if the appropriate
    certification is given by the state authority involved (in this case, the
    5
    It is undisputed that the Congress Center Authority provided the
    certification prior to the final bond validation hearing.
    19
    Congress Center Authority). (Emphasis supplied.) It does not say that a
    city resolution cannot be written or passed in anticipation of the required
    certification. Nor does it say that a resolution passed before the city
    receives the certification would be rendered void. To the contrary, the
    statute requires that both the certification be given and the resolution
    passed before the City continues to levy and collect the seven percent
    Hotel/Motel tax beyond the December 31, 2020 termination date of the
    tax being collected to fund an initial multipurpose domed stadium facility
    pursuant to OCGA § 48-13-51 (a) (5) (A). In other words, while
    subsection (B) can be fairly read to imply that the certification must be
    given before a resolution is passed, there is nothing in the statute to imply
    that strict adherence to this chronological order of events is necessary in
    order for a city to pass a valid resolution or that the failure to adhere to
    this chronological order would have the extreme result of rendering prior
    authorizing actions void. In any event, here, both requirements have been
    met, as the City has passed a proper resolution and it has received the
    20
    proper certification from the Congress Center Authority.6 Accordingly,
    City Resolution 13-R-0615 is not “void,” as Cottrell argues.
    6. Cottrell asserts that the trial court erred in adjudicating the validity of
    the O&M Agreement7 in this case, because the Agreement did not act as
    “security” for the 2014 NSP Bonds. In this regard, he contends that, by
    answering any question regarding the validity of the O&M Agreement,
    the trial court violated its own self imposed limits on its “subject matter”
    jurisdiction. In its final validation order, the trial court stated that “[t]he
    purpose of this proceeding is to determine whether as a matter of law the
    proceedings for the issuance of the [2014 NSP] Bonds were lawfully
    6
    To the extent that Cottrell argues that City Resolution 13-R-0615 is void
    because OCGA § 48-13-51 (a) (5) (B) is an unconstitutional special law, that
    argument fails in light of our holding in Division 1 that the statute is
    constitutional. In addition, we find no merit to Cottrell’s argument that the tax
    certification given by the Congress Authority in 2014 is allegedly defective, as
    the certification itself contains all of the information required by OCGA §
    48-13-51 (a) (5) (B) and tracks all of the necessary components of the ongoing
    deal between the New Stadium Entities and the relevant parties who will bring
    the entire deal to fruition.
    7
    Pursuant to this Agreement, the City will provide the Congress Center
    Authority with any portion of the NSP Tax Proceeds not required to pay the debt
    service (and related expenses) on the 2014 NSP Bonds, and the Congress Center
    Authority will apply any NSP Tax Proceeds it receives to operate and maintain
    the New Stadium Project.
    21
    conducted and the procedures were complied with, and whether as a
    matter of fact there is adequate security for the payment of the bonds.”
    Validation Order at 5 n.6. However, the trial court’s statement has nothing
    to do with and no control over a superior court’s jurisdiction “to hear and
    determine all questions of law and of fact in the [bond validation] case
    and [] render judgment” on those issues. (Emphasis supplied.) OCGA §
    36-82-77. See also 
    Berry, supra
    , 277 Ga. App. at 650 (1) (627 SE2d 391)
    (2006) (“In a bond validation hearing, the role of the trial court is to
    determine whether the bond proposal is sound, feasible, and reasonable”
    [Cit.]) (footnote and punctuation omitted). The validity of the O&M
    agreement was indeed placed in issue at the April 10, 2014 bond
    validation hearing, and the trial court committed no error in rendering a
    judgment on this issue. See OCGA § 36-82-77.
    7. Finally, Cottrell urges that the trial court erred in failing to find that the
    O&M Agreement violates the Intergovernmental Contracts Clause of the
    State Constitution, in that this Agreement between the City and the
    Congress Center Authority requires the City to reimburse StadCo, a
    private company, for certain expenses incurred from events and other
    22
    activities at the New Stadium Project. Again, we disagree.
    Pursuant to the Intergovernmental Contracts Clause:
    [t]he state, or any institution, department, or other agency
    thereof, and any county, municipality, school district, or other
    political subdivision of the state may contract for any period
    not exceeding 50 years with each other or with any other
    public agency, public corporation, or public authority for
    joint services, for the provision of services, or for the joint or
    separate use of facilities or equipment; but such contracts
    must deal with activities, services, or facilities which the
    contracting parties are authorized by law to undertake or
    provide.
    Ga. Const. of 1983 Art. IX, Sec. III, Par. I (a). Here, consistent with the
    Intergovernmental Contracts Clause, the O&M Agreement is solely
    between two governmental entities, the City and the Congress Center
    Authority; the period of the Agreement does not exceed fifty years; the
    Agreement “involve[s] the provision of services, or . . . the joint or
    separate use of facilities or equipment;” and it “deal[s] with activities,
    services, or facilities which the contracting parties are authorized by law
    to undertake or provide.” The fact that StadCo pays some of the
    operating expenses for the NSP and is then reimbursed by the Congress
    Authority from funds that are specifically earmarked for covering “costs
    23
    relating to the operation, maintenance and improvements for the New
    Stadium Project” does not somehow make the O&M Agreement invalid.
    The Congress Center Authority is simply using the necessary funds to pay
    for the NSP as it is required to do in a manner consistent with its
    ownership of the NSP.8
    Judgment affirmed. All the Justices concur.
    8
    Nor would Cottrell’s challenge to the individual clause of the O&M
    Agreement allowing for StadCo to approve any changes to the Agreement
    render the entire O&M Agreement invalid. See O&M Agreement § 7.4 (“This
    O&M Agreement may not be effectively amended, changed, modified, altered
    or terminated by the parties hereto without the concurring prior written consent
    of StadCo; provided StadCo shall not unreasonably withhold its consent”).
    Indeed, despite the existence of this clause, again, StadCo is not an actual party
    to the O&M Agreement, and the Agreement itself contains a severability clause
    that would leave the remainder of the Agreement intact even if this particular
    provision failed. See O&M Agreement § 7.3. Thus, even if we assume without
    deciding that the clause in question were invalid, our analysis regarding the
    overall validity and constitutionality of the O&M Agreement would remain
    unchanged.
    24
    

Document Info

Docket Number: S14A1874

Citation Numbers: 297 Ga. 1, 770 S.E.2d 616

Filed Date: 3/16/2015

Precedential Status: Precedential

Modified Date: 1/12/2023