K. Miller Construction Compay, Inc. v. McGinnis ( 2010 )


Menu:
  •                         Docket No. 109156.
    IN THE
    SUPREME COURT
    OF
    THE STATE OF ILLINOIS
    K. MILLER CONSTRUCTION COMPANY, INC., Appellee, v.
    JOSEPH J. McGINNIS et al., Appellants.
    Opinion filed September 23, 2010.
    JUSTICE BURKE delivered the judgment of the court, with
    opinion.
    Chief Justice Fitzgerald and Justices Freeman, Thomas, Kilbride,
    Garman, and Karmeier concurred in the judgment and opinion.
    OPINION
    The Home Repair and Remodeling Act (815 ILCS 513/15 (West
    2006)) states that, “[p]rior to initiating home repair or remodeling
    work for over $1,000, a person engaged in the business of home
    repair or remodeling shall furnish to the customer for signature a
    written contract or work order.” At issue here is whether a home
    remodeling contractor who violates this provision and enters into an
    oral contract for home remodeling work over $1,000 may enforce the
    oral contract or seek recovery in quantum meruit against a
    homeowner who has refused to pay for a completed home remodeling
    project. The appellate court concluded that such a contractor may not
    enforce the oral contract but may seek recovery in quantum meruit.
    
    394 Ill. App. 3d 248
    . For the reasons that follow, we hold that
    recovery is available under both theories.
    Background
    The plaintiff, K. Miller Construction Company, Inc., filed a
    second-amended complaint in the circuit court of Cook County
    against the defendants, Joseph and Frances McGinnis. The complaint
    alleged the following.
    Plaintiff is an Illinois construction firm whose sole owner is Keith
    Miller. Defendant Joseph McGinnis is an Illinois real estate attorney
    who has been in practice since 1970 and been a division counsel for
    United General Title Insurance Company for 10 years. Defendant
    Frances McGinnis is Joseph McGinnis’s wife. Plaintiff has done
    remodeling work for defendants in the past and, prior to the initiation
    of this litigation, Joseph McGinnis and Miller were friends.
    In the spring of 2004, defendants purchased a three-flat apartment
    building in Chicago. Defendants intended to convert the building into
    a single-family residence by demolishing and rebuilding the interior
    of the building while retaining the building’s exterior structure.
    Architectural plans were drawn up and several discussions took place
    among defendants, the architect and Miller about the scope and
    details of the work to be performed. In the fall of 2004, plaintiff
    entered into an oral contract with defendants to undertake the
    remodeling project as general contractor for the sum of $187,000.
    In December 2004 and January 2005, defendants told Miller that
    they wanted to “vastly increase” the work to be performed on the
    building and that the architect would develop new plans and
    specifications for the expanded project. The new work included,
    among other things, lowering of the basement foundation and floor,
    installation of steel beams and framework to replace wood materials,
    replacement of plumbing, installation of additional heating,
    ventilation and air conditioning, and related changes. These
    modifications raised the total cost of the project to approximately
    $500,000.
    Defendants instructed Miller to assist them in obtaining a new
    building permit for the construction changes. The permit was issued
    by the City of Chicago in January 2005. Plaintiff proceeded to
    perform the construction ordered by defendants according to the
    -2-
    revised architectural plans and the new building permit.
    Defendants paid the first $65,000 of invoices issued by plaintiff
    from April 2005 to June 2005. In September 2005, plaintiff submitted
    an invoice to defendants for $58,000. Defendants refused to pay the
    invoice and told Miller they did not want to make any further
    payments until all construction work on the project was completed.
    Plaintiff was unable to finance the remainder of the construction on
    its own and, therefore, obtained a bank line of credit for $150,000 to
    complete the remodeling project.
    Defendants visited the construction site at least weekly in 2005
    and 2006 to review and give approval to construction work plaintiff
    had performed. In June and July of 2006, defendants conducted final
    walk-throughs of the property. Defendants approved all of the
    construction work with the exception of certain flooring that
    defendants estimated would cost $300 to repair. Plaintiff’s final day
    of construction on the project was July 10, 2006. Defendants made
    some additional payments to plaintiff but at the close of construction,
    the balance due to plaintiff for labor and materials furnished was over
    $300,000. Defendants refused to pay plaintiff any of this amount.
    Plaintiff thereafter filed a three-count, second-amended complaint
    against defendants. Count I sought to foreclose a mechanic’s lien.
    Count II alleged a breach of contract. Count III, which was pled in the
    alternative, sought recovery in quantum meruit for the reasonable
    value of plaintiff’s work.
    Defendants filed a motion to dismiss pursuant to section 2–615 of
    the Code of Civil Procedure (735 ILCS 5/2–615 (West 2006)). With
    respect to count II of plaintiff’s complaint, defendants maintained that
    the oral contract plaintiff entered into with defendants “violates
    Illinois law and is therefore not enforceable.” In support, defendants
    pointed to section 15 of the Home Repair and Remodeling Act (Act)
    (815 ILCS 513/15 (West 2006)), which states that persons “engaged
    in the business of home repair or remodeling” shall provide
    customers with “a written contract or work order” prior to beginning
    work on a project costing more than $1,000, and section 30 of the Act
    (815 ILCS 513/30 (West 2006)), which at the time plaintiff filed its
    complaint, stated that it is “unlawful” to engage in home remodeling
    “before obtaining a signed contract or work order over $1,000.”
    Defendants noted that plaintiff’s complaint alleged that the
    -3-
    remodeling contract was not in writing and that it was for work
    totaling more than $1,000. Based on these facts, defendants
    maintained that the contract violated the Act and was unenforceable
    and, therefore, that count II of plaintiff’s complaint should be
    stricken. Further, because a mechanic’s lien may be enforced only if
    there is a valid underlying contract, defendants contended that count
    I of plaintiff’s complaint should also be stricken.
    With respect to count III of plaintiff’s complaint, defendants cited
    to Smith v. Bogard, 
    377 Ill. App. 3d 842
    , 848 (2007), wherein the
    appellate court held that allowing a contractor to recover in quantum
    meruit when he has breached the writing requirement of the Act
    “would run afoul of the legislature’s intent of protecting consumers,
    would reward deceptive practices, and would be violative of public
    policy.” Relying on Bogard, defendants contended that count III of
    plaintiff’s complaint should be stricken and plaintiff’s action
    dismissed.
    The circuit court granted defendants’ motion and dismissed
    plaintiff’s cause of action with prejudice.
    The appellate court affirmed in part and reversed in part. 
    394 Ill. App. 3d 248
    . The appellate court unanimously agreed that plaintiff’s
    claims for breach of contract and foreclosure of mechanic’s lien could
    not go forward. The appellate court reasoned that because the Act
    imposes a writing requirement for remodeling work costing over
    $1,000, the Act necessarily “bars the enforcement of an oral
    contract.” 394 Ill. App. 3d at 254.
    However, on the question of whether plaintiff could recover in
    quantum meruit, the appellate court was divided. Justice Garcia,
    writing the lead opinion for the court, concluded that plaintiff could
    proceed with its quantum meruit claim because there was “no clear
    and plain intent in the Act to do away with quantum meruit, an
    equitable remedy that is a part of our common law going back to the
    times when Abraham Lincoln practiced in our courts.” 394 Ill. App.
    3d at 258. In reaching this conclusion, Justice Garcia expressly
    disagreed with the appellate court’s decision in Bogard. 394 Ill. App.
    3d at 258-61.
    Justice Robert Gordon agreed with the result reached by Justice
    Garcia, but not his reasoning. Justice Gordon pointed to the last
    -4-
    sentence of section 30 of the Act, which, at the time plaintiff’s
    complaint was filed, stated that the failure to obtain a written contract
    is “unlawful but is not exclusive nor meant to limit other kinds of
    methods, acts, or practices that may be unfair or deceptive” (815
    ILCS 513/30 (West 2006)). Justice Gordon concluded that this
    sentence “leaves the door open to equitable remedies, such as the
    quantum meruit claim in this case.” 394 Ill. App. 3d at 266 (Gordon,
    J., specially concurring).
    Justice Wolfson dissented. Justice Wolfson concluded that
    quantum meruit was unavailable to plaintiff, as there was no authority
    “supporting the proposition that an act declared unlawful by the
    legislature can be sanitized by filtering it through a court of equity.”
    394 Ill. App. 3d at 267 (Wolfson, J., dissenting).
    We allowed defendants’ petition for leave to appeal. 210 Ill. 2d
    R. 315.
    Analysis
    The circuit court granted defendants’ motion to dismiss brought
    pursuant to section 2–615 of the Code of Civil Procedure (735 ILCS
    5/2–615 (West 2006)). A section 2–615 motion to dismiss challenges
    the legal sufficiency of a complaint based on defects apparent on its
    face. Pooh-Bah Enterprises, Inc. v. County of Cook, 
    232 Ill. 2d 463
    ,
    473 (2009). In ruling on a section 2–615 motion, only those facts
    apparent from the face of the pleadings, matters of which the court
    can take judicial notice, and judicial admissions in the record may be
    considered. Pooh-Bah Enterprises, Inc., 
    232 Ill. 2d at 473
    . The court
    must also accept as true all well-pleaded facts in the complaint and all
    reasonable inferences that may be drawn from those facts. Pooh-Bah
    Enterprises, Inc., 
    232 Ill. 2d at 473
    . We review de novo an order
    granting a section 2–615 motion to dismiss. Pooh-Bah Enterprises,
    Inc., 
    232 Ill. 2d at 473
    .
    At the outset, plaintiff suggests that defendants’ motion to dismiss
    should have been brought under section 2–619(a)(9) of the Code of
    Civil Procedure (735 ILCS 5/2–619(a)(9) (West 2006)) because the
    motion raised an affirmative defense, i.e., that the oral contract
    between plaintiff and defendants violates the Act and, hence, is
    unenforceable as a matter of public policy. See 735 ILCS 5/2–613(d)
    -5-
    (West 2006) (listing illegality as an affirmative defense). However,
    section 2–619(a)(9) speaks in terms of affirmative matter, not
    affirmative defenses: “If the grounds do not appear on the face of the
    pleading attacked the motion shall be supported by affidavit: ***
    (9) That the claim asserted against defendant is barred by other
    affirmative matter avoiding the legal effect of or defeating the claim.”
    735 ILCS 5/2–619(a)(9) (West 2006). An affirmative defense may be
    raised in a section 2–615 motion where the defense is “established by
    the facts apparent on the face of the complaint” and no other facts
    alleged in the complaint negate the defense. 3 R. Michael, Illinois
    Practice §27.2, at 492 (1989). Here, the factual basis of defendants’
    affirmative defense is found in plaintiff’s own allegations that the
    remodeling contract was oral and was for work totaling more than
    $1,000.
    Turning to the merits, defendants contend that the appellate court
    erred when it concluded that plaintiff could pursue relief in quantum
    meruit and reversed the circuit court’s dismissal of count III of
    plaintiff’s complaint. According to defendants, it is inconsistent to
    hold, as the appellate court did, that plaintiff may not recover in
    contract for having violated the Act, but that it may recover in equity.
    Citing to Bogard, defendants further argue that to allow a contractor
    who fails to comply with the writing requirement of the Act to seek
    relief in quantum meruit would defeat the intent of the General
    Assembly and violate the public policy expressed in the Act.
    Plaintiff disputes defendants’ assertion that quantum meruit is
    unavailable and also challenges the appellate court’s holding that
    plaintiff’s claim for breach of contract in count II was properly
    stricken by the circuit court. We address the latter issue first. If there
    is no public policy that would prohibit plaintiff from recovering in
    contract, then there is no inconsistency in plaintiff pursuing relief in
    quantum meruit. Accordingly, our resolution of whether plaintiff may
    pursue its claim for breach of contract may also determine whether
    plaintiff may seek relief in quantum meruit.
    Section 178 of the Restatement (Second) of Contracts (1981) sets
    forth the following rule regarding the unenforceability of a
    contractual term because of the violation of a statute or other public
    policy:
    Ҥ178 When a Term Is Unenforceable on Grounds of
    -6-
    Public Policy
    (1) A promise or other term of an agreement is
    unenforceable on grounds of public policy if legislation
    provides that it is unenforceable or the interest in its
    enforcement is clearly outweighed in the circumstances by a
    public policy against the enforcement of such terms.
    (2) In weighing the interest in the enforcement of a term,
    account is taken of
    (a) the parties’ justified expectations,
    (b) any forfeiture that would result if enforcement
    were denied, and
    (c) any special public interest in the enforcement of
    the particular term.
    (3) In weighing a public policy against enforcement of a
    term, account is taken of
    (a) the strength of that policy as manifested by
    legislation or judicial decisions,
    (b) the likelihood that a refusal to enforce the term
    will further that policy,
    (c) the seriousness of any misconduct involved and
    the extent to which it was deliberate, and
    (d) the directness of the connection between that
    misconduct and the term.” Restatement (Second) of
    Contracts §178 (1981).
    Pursuant to the Restatement, in considering whether a contractual
    term is unenforceable as against public policy because of a statutory
    violation, the first step is to examine the relevant statute itself. If the
    statute explicitly provides that a contractual term which violates the
    statute is unenforceable then, barring any constitutional objection, the
    term is unenforceable. Conversely, if it is clear that the legislature did
    not intend for a violation of the statute to render the contractual term
    unenforceable, and that the penalty for a violation of the statute lies
    elsewhere, then the contract may be enforced. But where the statute
    is silent, then the court must balance the public policy expressed in
    the statute against the countervailing policy in enforcing contractual
    agreements:
    -7-
    “Only infrequently does legislation, on grounds of public
    policy, provide that a term is unenforceable. When a court
    reaches that conclusion, it usually does so on the basis of a
    public policy derived either from its own perception of the
    need to protect some aspect of the public welfare or from
    legislation that is relevant to that policy although it says
    nothing explicitly about unenforceability. See §179. In some
    cases the contravention of public policy is so grave, as when
    an agreement involves a serious crime or tort, that
    unenforceability is plain. In other cases the contravention is
    so trivial as that it plainly does not preclude enforcement. In
    doubtful cases, however, a decision as to enforceability is
    reached only after a careful balancing, in the light of all the
    circumstances, of the interest in the enforcement of the
    particular promise against the policy against the enforcement
    of such terms. The most common factors in the balancing
    process are set out in Subsections (2) and (3). Enforcement
    will be denied only if the factors that argue against
    enforcement clearly outweigh the law’s traditional interest in
    protecting the expectations of the parties, its abhorrence of
    any unjust enrichment, and any public interest in the
    enforcement of the particular term.” Restatement (Second) of
    Contracts §178, Comment b, at 8 (1981).
    Importantly, the fact that there has been a statutory violation does
    not, in itself, automatically render a contract unenforceable:
    “The strength of the public policy involved is a critical
    factor in the balancing process. Even when the policy is one
    manifested by legislation, it may be too insubstantial to
    outweigh the interest in the enforcement of the term in
    question.” Restatement (Second) of Contracts §178,
    Comment c, at 8 (1981).
    See also 5 R. Lord, Williston on Contracts §12:4, at 995-96 (4th ed.
    2009) (“To assert, however, as some courts have, that all unlawful
    agreements are ipso facto void is opposed to many decisions and
    unfortunate in its consequences, for it may protect a guilty defendant
    from paying damages to an innocent plaintiff”); 15 Corbin on
    Contracts §89.1, at 614 (rev. ed. 2003) (“The decision of whether and
    how to enforce a contract involving a prohibited performance is and
    -8-
    must be based on policy choices and a balancing of relevant factors”).
    Illinois law is in accord with the Restatement. For example, in
    Pascal P. Paddock, Inc. v. Glennon, 
    32 Ill. 2d 51
     (1964), a contractor
    entered into a written agreement with certain property owners to
    construct a pool and bathhouse. After the owners refused to pay, the
    contractor brought suit to foreclose a mechanics’ lien. The property
    owners contended, however, that the underlying contract was
    unenforceable because the contractor had used unlicensed plumbers
    in the construction of the pool, in violation of the Illinois Plumbing
    License Law (Ill. Rev. Stat. 1961, ch. 111½ , par. 116.38). The
    appellate court agreed with the property owners, but this court
    reversed.
    In so doing, we noted that a statutory violation does not
    automatically render a contract unenforceable: “the mere fact that [a
    contract] was performed in violation of law will not invalidate the
    resulting lien if not seriously injurious to the public order.” Paddock,
    
    32 Ill. 2d at 53-54
    . Applying this rule, we then examined the facts and
    concluded that the contract could be enforced because any violation
    of the licensing statute which may have occurred was not “seriously
    injurious to the public order.” Paddock, 
    32 Ill. 2d at 54
    . See also, e.g.,
    Federal Land Bank of St. Louis v. Walker, 
    212 Ill. App. 3d 420
    , 422
    (1991) (“Merely because a contract may violate some law or some
    regulation does not necessarily make that contract unenforceable”);
    Duncan v. Cannon, 
    204 Ill. App. 3d 160
    , 169-70 (1990) (party’s
    failure to strictly abide by a municipal ordinance did not operate as a
    bar to recovery for breach of contract); South Center Plumbing &
    Heating Supply Co. v. Charles, 
    90 Ill. App. 2d 15
    , 18 (1968) (“not all
    violations of law brought about in the performance of a contract are
    considered serious enough to prevent recovery on the contract by the
    party who violates the law”).
    With the foregoing principles in mind, we turn to the case at hand.
    In holding the oral contract at issue here unenforceable, the appellate
    court relied on sections 15 and 30 of the Act. Section 15 provides:
    Ҥ15. Written contract; costs enumerated requirements;
    contents. Prior to initiating home repair or remodeling work
    for over $1,000, a person engaged in the business of home
    repair or remodeling shall furnish to the customer for
    signature a written contract or work order that states the total
    -9-
    cost, including parts and materials listed with reasonable
    particularity and any charge for an estimate. In addition, the
    contract shall state the business name and address of the
    person engaged in the business of home repair or remodeling.
    If the person engaged in the business of home repair or
    remodeling uses a post office box or mail receiving service or
    agent to receive home repair or remodeling business
    correspondence, the contract also shall state the residence
    address of the person engaged in the business of home repair
    or remodeling.” 815 ILCS 513/15 (West 2006).
    Section 30, at the time plaintiff’s complaint was filed, stated:
    Ҥ30. Unlawful acts. It is unlawful for any person engaged
    in the business of home repairs and remodeling to remodel or
    make repairs or charge for remodeling or repair work before
    obtaining a signed contract or work order over $1,000 and
    before notifying and securing the signed acceptance or
    rejection, by the consumer, of the binding arbitration clause
    and the jury trial waiver clause as required in Section 15 and
    Section 15.1 of this Act. This conduct is unlawful but is not
    exclusive nor meant to limit other kinds of methods, acts, or
    practices that may be unfair or deceptive.” 815 ILCS 513/30
    (West 2006).
    Based on these provisions, the appellate court reasoned:
    “When the Miller construction company began home
    remodeling work for the McGinnises without obtaining a
    signed contract or work order, it violated the terms of the
    Home Repair Act and, therefore, was precluded from proving
    up an oral contract, as the Act declares such contracts
    ‘unlawful.’ ” 394 Ill. App. 3d at 265.
    In other words, according to the appellate court, because there was a
    statutory violation or “unlawful” act, the contract was, ipso facto,
    unenforceable. This was error. The General Assembly is capable of
    stating when a contractual term that violates a statute is
    unenforceable. See, e.g., 720 ILCS 5/28–7 (West 2008) (gambling
    contracts are “null and void”); 50 ILCS 105/3 (West 2008) (contracts
    in which a public official has a financial interest and may be called to
    vote upon are “void”); 625 ILCS 5/18c–4105 (West Supp. 2009)
    -10-
    (indemnity agreements in motor carrier transportation contracts are
    “void and unenforceable”). The General Assembly did not do so here.
    See Fandel v. Allen, 
    398 Ill. App. 3d 177
    , 192 (2010) (Schmidt, J.,
    specially concurring) (“it was not the legislature that said any
    violation of the Home Repair Act, ipso facto, renders the contract
    unenforceable; it was some judges”); Universal Structures, Ltd. v.
    Buchman, __ Ill. App. 3d __, __ (2010) (“the Act is void of any
    language which serves to invalidate the parties’ agreement when the
    contractor fails to secure a signed written contract or work order”);
    see also Restatement (Second) of Contracts §179, Comment b, at 16
    (1981) (“legislators seldom address themselves explicitly to the
    problems of contract law that may arise in connection with
    [proscribed] conduct. *** Usually they do not even have these
    problems in mind and say nothing as to the enforceability of terms”).
    Sections 15 and 30 of the Act make plain that an oral contract for
    home remodeling over $1,000 is a statutory violation. However, the
    Act left it an open question as to whether a statutory violation
    rendered an oral contract unenforceable. Accordingly, the appellate
    court should have conducted a balancing analysis and considered the
    relevant facts and public policies before concluding that plaintiff
    could not pursue relief for breach of contract.
    Having determined that the appellate court erred, we ordinarily
    would either remand to the appellate court to perform the required
    balancing analysis or conduct the analysis ourselves. See, e.g.,
    Asdourian v. Araj, 
    38 Cal. 3d 276
    , 289-94, 
    696 P.2d 95
    , 104-07, 
    211 Cal. Rptr. 703
    , 711-15 (1985) (conducting a balancing analysis and
    concluding that an oral contract for remodeling was enforceable,
    notwithstanding a statute which required that remodeling contracts in
    excess of $500 be in writing and which made violations of the statute
    a misdemeanor offense). However, we need not do so here.
    Legislation which was enacted after the appellate court rendered its
    decision in the case at bar has clarified that the General Assembly did
    not intend for violations of the writing requirement under the Act to
    render oral contracts unenforceable.
    Public Act 96–1023, effective July 12, 2010, has entirely
    rewritten section 30 of the Act, removing all references to the word
    “unlawful” and indicating that the remedy for violations of the Act is
    to be had under the Consumer Fraud and Deceptive Business
    -11-
    Practices Act (815 ILCS 505/10(a) (West 2008)). The section now
    reads:
    “Sec. 30. Action for actual damages. Any person who
    suffers actual damage as a result of a violation of this Act may
    bring an action pursuant to Section 10a of the Consumer
    Fraud and Deceptive Business Practices Act.” Public Act
    96–1023, eff. July 12, 2010.
    “A subsequent amendment to a statute may be an appropriate source
    for discerning legislative intent.” In re Detention of Lieberman, 
    201 Ill. 2d 300
    , 320-21 (2002) (citing People v. Parker, 
    123 Ill. 2d 204
    ,
    211 (1988), and Carey v. Elrod, 
    49 Ill. 2d 464
    , 472 (1971)). As we
    have explained, while an amendatory change in the language of a
    statute creates a presumption that it was intended to change the law
    as it previously existed, “ ‘the presumption is not controlling
    [citations] and may be overcome by other considerations.’ ” Parker,
    
    123 Ill. 2d at 211
    , quoting People v. Nunn, 
    77 Ill. 2d 243
    , 248 (1979).
    “The circumstances surrounding the amendment should be considered
    and: ‘If they indicate that the legislature intended only to interpret the
    original act, the presumption of an intention to change the law is
    rebutted.’ ” Parker, 
    123 Ill. 2d at 211
    , quoting People v. Youngbey,
    
    82 Ill. 2d 556
    , 563 (1980). A number of factors may indicate whether
    an amendment is merely a clarification rather than a substantive
    change in the law: “whether the enacting body declared that it was
    clarifying a prior enactment; whether a conflict or ambiguity existed
    prior to the amendment; and whether the amendment is consistent
    with a reasonable interpretation of the prior enactment and its
    legislative history.” Middleton v. City of Chicago, 
    578 F.3d 655
    , 663-
    64 (7th Cir. 2009); see also 1A N. Singer, Sutherland on Statutory
    Construction §22.30, at 366, 374-75 (6th ed. 2002 rev.) (“Although
    generally, a statutory amendment is presumed to have been intended
    to change the law, the legislative history may indicate that the
    amendment was intended instead as a clarification. *** [In addition,
    the] time and circumstances surrounding the enactment of the
    amendment may indicate that the change wrought by the amendment
    was formal only-that the legislature intended merely to interpret the
    original act”).
    At the time the General Assembly was considering Senate Bill
    2540 (the bill which would become Public Act 96–1023), there was
    -12-
    disagreement in our appellate court as to the effect a violation of the
    Act had on the legal claims that could be pursued by a contractor. For
    example, as noted previously, the appellate court in Smith v. Bogard,
    
    377 Ill. App. 3d 842
     (2007), had concluded that a contractor who
    violated the writing requirement of the Act could not recover in
    quantum meruit, while the appellate court in the case at bar had
    concluded the opposite. Further, while the appellate court in both this
    case and others had concluded that recovery in contract was per se
    unavailable, the appellate court in Fandel v. Allen, 
    398 Ill. App. 3d 177
    , 186 (2010), had concluded that a violation of the Act “does not
    act to automatically invalidate the agreement between the parties.”
    The doctrine of substantial compliance had also been invoked by our
    appellate court in addressing violations of the Act. See Behl v.
    Gingerich, 
    396 Ill. App. 3d 1078
     (2009).
    The existence of these conflicting appellate decisions negates the
    presumption that the legislature’s removal of the word “unlawful”
    from section 30 was a change in the law. Because of the differing
    views in the appellate court, there was no clear interpretation of the
    law to be changed. It follows, therefore, that Public Act 96–1023 was
    meant to clarify the previous law and make clear that a violation of
    the Act does not render oral contracts unenforceable or relief in
    quantum meruit unavailable and that, instead, the remedy for
    violations of the Act lies elsewhere.
    Legislative history supports this conclusion. During the debate on
    Senate Bill 2540, Senator Wilhelmi, the Senate sponsor of the bill,
    stated:
    “Senate Bill 2540 does two things. First, it resolves confusion
    as to the proper remedy for the courts to apply by providing
    that any person who suffers actual damages as a result of a
    violation of the Home Repair and Remodeling Act may bring
    an action under the Consumer Fraud and Deceptive Business
    Practices Act. Secondly, the Home Repair and Remodeling
    Act requires a contractor to give a pamphlet to his–his–his
    customer, as well as to have a signed contract with that
    customer. However, what the courts have found is that some
    of these consumers are using the Act to get out of paying the
    balance due on a home repair or remodeling contract. So the
    courts are asking for a clarification of this. I think what we are
    -13-
    doing through this bill is saying that, unless there’s actual
    damages, a consumer cannot get out of paying the balance due
    to a home repair or remodeling company by using these two
    technical provisions in the Act of requiring a pamphlet to be
    given and requiring a written contract before work on the
    project.” 96th Ill. Gen. Assem., Senate Proceedings, March 9,
    2010, at 68 (statements of Senator Wilhelmi).
    In light of the foregoing, we conclude that Public Act 96–1023 is
    a clarification of the prior statute and must be accepted as a legislative
    declaration of the meaning of the original Act. There is, therefore, no
    public policy requiring that oral contracts for home remodeling over
    $1,000 be held unenforceable or that relief in quantum meruit be
    denied. Accordingly, the appellate court erred in upholding the circuit
    court’s dismissal of counts I and II of plaintiff’s complaint, but
    properly reversed the dismissal of count III of plaintiff’s complaint.
    Conclusion
    For the foregoing reasons, we reverse that part of the appellate
    court’s judgment which affirmed the circuit court’s dismissal of
    counts I and II. We affirm that part of the appellate court’s judgment
    which reversed the circuit court’s dismissal of count III. The
    judgment of the circuit court is reversed, and the cause is remanded
    to that court for further proceedings.
    Appellate court judgment affirmed in part
    and reversed in part;
    circuit court judgment reversed;
    cause remanded.
    -14-