Europlasma, S.A. v. Solena Group, Inc. , 604 F. Supp. 2d 66 ( 2009 )


Menu:
  • 604 F. Supp. 2d 66 (2009)

    EUROPLASMA, S.A., Plaintiff,
    v.
    SOLENA GROUP, INC., Defendant.

    Civil Action No. 08-01089 (HHK).

    United States District Court, District of Columbia.

    March 30, 2009.

    *67 Joanne L. Zimolzak, McKenna Long & Aldridge, LLP, Washington, DC, for Plaintiff.

    James M. Mesnard, Seyfarth Shaw, LLP, Washington, DC, for Defendant.

    MEMORANDUM OPINION

    HENRY H. KENNEDY, JR., District Judge.

    Plaintiff Europlasma S.A. ("Europlasma") brings this action to enforce the terms of a promissory note requiring Defendant Solena Group, Inc. ("Solena") to pay Europlasma the principal amount of 394,517, plus interest at an annual rate of 4%, in consideration for equipment that Solena purchased and received from Europlasma. Before the court is Solena's motion to dismiss or, in the alternative, to stay and compel arbitration [## 6, 7] and Europlasma's motion for summary judgment [# 9]. Upon consideration of the motions, the oppositions thereto, and the arguments of counsel at a hearing, the court concludes that Solena's motion to dismiss should be denied and Europlasma's summary judgment motion should be granted.

    I. BACKGROUND

    A. Promissory Note

    On or about October 3, 2006, Solena ordered a plasma torch from Europlasma and paid the shipping costs and part of the *68 purchase price. On September 14, 2007, the parties executed an unsecured promissory note ("Note") for the balance of €394,517 remaining on the torch purchase, plus interest at an annual rate of 4%. Compl. ¶¶ 6-7; Compl. Exh. 1 ("Note"). The Note provides that if Solena fails to meet its obligations under the Note, Europlasma is entitled to recover all costs, including reasonable attorney's fees, incurred in collecting or attempting to collect on the note, "whether or not a lawsuit is commenced." Note at 1. Solena did not make the required payment on the Note by its due date of January 10, 2008.

    B. Master Teaming Agreement

    On May 29, 2007, after the torch purchase and before the execution of the Note, the parties entered into the Master Teaming Agreement ("Agreement"). Mot. to Dismiss at 2 & Exh. 2 ("Master Teaming Agreement"). Among other things, the Agreement states that "Solena commits to treat Europlasma as its Preferred Provider of torch systems, and as such, Solena commits to purchase all of the plasma torch systems from Europlasma for Solena Projects utilizing Solena Technology from the date of this agreement." Agreement ¶ 1.2.1. In consideration for Europlasma serving as Solena's exclusive source, Europlasma agreed to provide Solena with discount pricing for the purchase of multiple torch systems. Id. ¶ 1.2.2. The parties agreed that the Agreement would have a term of three years "from the date first above written, which term may be renewed or extended by the parties." Id. ¶ 5.1.

    The Agreement includes an alternative dispute resolution clause that reads:

    6.2 If [sic] the event of a controversy, claim or dispute arising out of or relating to this Agreement, the representatives of the Parties shall meet and confer in good faith negotiations with the object of reaching mutual agreement and a settlement. If the Parties' representatives are unable to agree, such representatives shall promptly commence discussion with respect to resolving the dispute through non-binding alternative dispute resolution ("ADR") procedures fashioned by the representative themselves or with the assistance of persons or organizations experienced in ADR procedures such as the International Chamber of Commerce.
    6.3 Any controversy, claim or dispute arising out of or relating to this Agreement, or the breach thereof, that the Parties can not [sic] amicably resolve under the procedures in Article 6.2., shall be settled by arbitration administered by the International Chamber of Commerce under its Commercial Arbitration Rules using an arbitrator that both Parties consent to in writing, and judgment on the award rendered by the arbitrator(s) may be entered in any court having jurisdiction thereof. The place of arbitration shall be London, England and the arbitrator shall determine the matters in dispute in accordance with Applicable Law. The parties agree that the award of the arbitrator shall be binding and shall be the sole and exclusive remedy among them regarding claims, counterclaims, issues or accountings presented to the arbitrator.

    Id. ¶¶ 6.2, 6.3.

    Finally, the Agreement contains an integration clause, specifying that "[t]his Agreement constitutes the entire agreement between the Parties, relating to the *69 subject matter hereof, and supersedes any previous agreements or understandings between them, whether oral or written." Id. ¶ 10.1.

    II. ANALYSIS

    A. Because The Note Is Unambiguous, The Court Will Not Consider Extrinsic Evidence

    Europlasma's complaint raises a single claim: breach of promissory note. Solena moves to dismiss Europlasma's complaint on the grounds that the dispute over the Note is subject to the Master Teaming Agreement's mandatory arbitration clause. Europlasma responds that the Note contains no arbitration provision and because it is unambiguous on its face, the court should not consider any extrinsic evidence, such as the Master Teaming Agreement. The court agrees with Europlasma.

    In relevant part, the Note states that Solena promises to pay Europlasma the sum of 394,517, plus interest on the unpaid principal at the annual rate of 4% from the date of the Note, September 14, 2007. The Note provides that the unpaid principal and accrued interest shall be payable in full on January 10, 2008. The Note could not be clearer and is unambiguous. See Rhone-Poulenc Basic Chems. Co. v. American Motorists Ins. Co., 616 A.2d 1192, 1196 (Del.1992) ("[A] contract is ambiguous only when the provisions in controversy are reasonably or fairly susceptible of different interpretations or may have two or more different meanings.").[1] Under well-settled principles of contract law, "[u]nambiguous written agreements should be enforced according to their terms, without using extrinsic evidence `to interpret the intent of the parties, to vary the terms of the contract or to create an ambiguity.'" MBIA Ins. Corp. v. Royal Indem. Co., 426 F.3d 204, 210 (3rd Cir. 2005) (quoting Eagle Indus. v. DeVilbiss Health Care, 702 A.2d 1228, 1232 (Del. 1997)); Capital Mgmt. Co. v. Brown, 813 A.2d 1094, 1097 (Del.2002) ("If a contract is unambiguous, extrinsic evidence may not be used to interpret the intent of the parties, to vary the terms of the contract or to create ambiguity."). Solena argues that the Master Teaming Agreement requires arbitration of the dispute over non-payment of the Note. Because the Note is unambiguous, however, the court will not consider evidence de hors the Note, including the Master Teaming Agreement.

    B. Were The Court To Consider the Agreement, It Would Find That The Dispute Is Not Subject to Arbitration.

    Even if the court were to consider the Agreement, it would find the Agreement's arbitration provision does not "arise out of or relate to the Agreement" ¶ 6.2, and therefore does not require arbitration of the dispute regarding non-payment of the Note.[2]

    *70 When a contract contains a broad arbitration clause, as here,[3] to determine whether the dispute at issue is subject to arbitration, the court must ask whether the claim at issue would be assertable even if the contract containing the arbitration clause did not exist. Parfi Holding AB, 817 A.2d at 155. Where the purportedly arbitrable claim "would be independently and separately assertable" even if the arbitration clause contract did not exist, the claim is not "in connection with" the contract containing the arbitration clause. Id.

    Under this analysis, the court finds that Europlasma's claim based on Solena's nonpayment of the Note would exist even in the absence of the Agreement. The purpose of the Agreement was to establish Europlasma as Solena's exclusive torch provider and to guarantee Solena discounting pricing in consideration for that exclusive arrangement. The Agreement creates no rights or obligations necessary for Europlasma's claim for breach of a promissory note. Indeed, no provision in the Agreement creates an obligation upon which Europlasma could base a claim of breach of a promissory note. In contrast, the Note alone provides a basis for Europlasma's claim. Accordingly, even were the court to consider the Agreement, it would conclude that Europlasma's claim is not subject to arbitration.[4]

    C. Europlasma Is Entitled to Summary Judgment, As Well As Attorneys' Fees and Costs.

    Solena does not dispute that the Note contains no arbitration clause, that the Note obligated Solena to pay Europlasma by January 10, 2008, and that Solena has failed to do so. Because there is no genuine dispute of material fact, the court finds that Europlasma is entitled to summary judgment.

    The Note provides that if it is not paid when due, Solena is "obligated to pay all costs of collection, including reasonable attorney fees, whether or not a lawsuit is commenced." Note at 1. Europlasma initially requested attorneys' fees in the amount of $39,461.00 and costs of $737.35, totaling $40,198.35. In response to Solena's objections to this amount as unreasonable, Europlasma enumerated potential reductions of its claim to a total of $27,705.85 in fees and costs. Supplemental Affidavit *71 of Joanne L. Zimolzak.[5] [# 18] The court finds that the reduced amount is reasonable, and that Europlasma is therefore entitled to $27,705.85 in attorneys' fees and costs.

    III. CONCLUSION

    For the foregoing reasons, Solena's motion to dismiss, or in the alternative, to stay and to compel arbitration [## 6, 7] is DENIED and Europlasma's cross-motion for summary judgment is GRANTED [# 9]. An appropriate order accompanies this memorandum opinion.

    NOTES

    [1] Delaware law applies because both the Note and the Agreement specify that they should be governed and construed in accordance with Delaware law. Note at 1; Agreement ¶ 6.1.

    [2] The Supreme Court of Delaware has set forth the analysis a court should undertake when determining whether the claim before it is subject to arbitration. Parfi Holding AB v. Mirror Image Internet, Inc., 817 A.2d 149, 155 (Del.2002). First, the court must "determine whether the arbitration clause is broad or narrow in scope," then "apply the relevant scope of the provision to the asserted legal claim to determine whether the claim falls within the scope of the contractual provisions that require arbitration." Id. If the arbitration clause is narrow, the court "will ask if the cause of action pursued in court directly relates to a right in the contract." On the other hand, if the clause is broad, "the court will defer to arbitration on any issues that touch on contract rights or contract performance." Id.

    [3] Under Delaware law, the Agreement's arbitration clause—calling for arbitration of "a controversy, claim or dispute arising out of or relating to this Agreement"—is broad. Detroit Med. Ctr. v. Provider Healthnet Servs., 269 F. Supp. 2d 487, 492 (D.Del.2003) ("Courts that have considered similar language in arbitration clauses have found that the `arising out of or relating to this Agreement' language is indicative of a broad arbitration provision.") (citing cases).

    [4] The following factors also lead the court to conclude that the Agreement's arbitration clause does not require arbitration of the present dispute: (a) the Agreement's prospective language, coupled with the fact that the October 2006 purchase had already been completed when the Agreement was signed in May 2007; (b) the Agreement's lack of reference to the October 2006 purchase even though the Agreement was signed in May 2007; (c) the Note's lack of reference to the Agreement even though the Note was signed in September 2007; (d) the difference between the torch model that was the subject of the October 2006 purchase and those covered by the Agreement; (e) the Note's provision that if the obligation is not paid when due, Solena is "obligated to pay all costs of collection, including reasonable attorney fees, whether or not a lawsuit is commenced;" Note at 1 (emphasis added); and (f) the separate consideration supporting the Note and the Agreement.

    [5] At the oral argument on December 17, 2008, the court ordered Europlasma to submit an affidavit to address Solena's argument that the amount of fees Europlasma claimed were unreasonable.