Diaz v. Legat Architects, Inc. - Corrected 12/23/09 ( 2009 )


Menu:
  •                                     FIRST DIVISION
    Date Filed: December 14, 2009
    Nos. 1-08-3622 & 1-08-3635 Cons.
    JOSE DIAZ and MARIA DIAZ,          )   Appeal from the
    )   Circuit Court of
    Plaintiffs-Appellees and   )   Cook County.
    Cross-Appellants,          )
    )
    v.                         )
    )   No. 04 L 2874
    LEGAT ARCHITECTS, INC., a          )
    Corporation, and THE DURANT        )
    COMPANY, a Corporation,            )
    )
    Defendants                 )
    )
    (Boller Construction Company,      )   Honorable Clare Elizabeth
    Inc., a Corporation,               )   McWilliams,
    )   Judge Presiding.
    Defendant-Appellant and    )
    Cross-Appellee and         )
    Third-Party Plaintiff-     )
    Appellant;                 )
    )
    Larmco Construction Company,       )
    )
    Third-Party Defendant-     )
    Appellee and Cross-        )
    Appellant).                )
    PRESIDING JUSTICE HALL delivered the opinion of the court:
    The plaintiffs, Jose Diaz, and his wife, Maria Diaz, filed
    a complaint against defendant Boller Construction Company, Inc.
    (Boller), for personal injuries he sustained while working on a
    construction site.   Boller filed a third-party complaint against
    Mr. Diaz's employer, Larmco Construction Company (Larmco),
    seeking contribution pursuant to the Joint Tortfeasor
    Contribution Act (740 ILCS 100/1 et seq. (West 2004)).     The jury
    Nos. 1-08-3622 & 3635 Cons.
    returned a verdict for the plaintiffs and against Boller.     The
    jury also returned a verdict for Boller and against Larmco in the
    third-party suit.     After reducing the award by the percentage of
    Mr. Diaz's negligence, the jury awarded Mr. Diaz $1,246,875 and
    awarded Mrs. Diaz $50,000 for loss of consortium.
    Following the filing of posttrial motions, the trial court
    ordered a remittitur of the jury award based on the improper
    admission at trial of future medical costs.     The trial court
    denied the plaintiffs' request to adjudicate Larmco's workers'
    compensation lien and granted Larmco's motion to dismiss Boller's
    third-party complaint for contribution.     After allowing other
    setoffs and credits, not at issue in this case, Mr. Diaz's award
    was reduced to $1,029,270.06, and Mrs. Diaz's award was reduced
    to $47,500, resulting in a total award of $1,076,770.06.
    Both Boller and the plaintiffs have appealed from the
    judgment in this case.     The plaintiffs and Larmco have also filed
    cross-appeals.     This court ordered the consolidation of the
    plaintiffs' and Boller's appeals and the cross-appeals for
    purposes of review and decision.1
    1
    In its cross-appeal, Larmco requested that the plaintiffs'
    appeal and cross-appeal and Boller's appeal be denied.     In the
    alternative, Larmco requested a judgment n.o.v. be entered in its
    favor on Boller's third-party complaint or that it be granted a
    2
    Nos. 1-08-3622 & 3635 Cons.
    Boller raises the following issues on appeal: (1) whether
    Boller's motion for a directed verdict should have been granted
    or a judgment n.o.v. entered; (2) whether the trial court erred
    in instructing the jury with the pattern construction negligence
    instructions; (3) whether trial court errors require a new trial,
    either individually or cumulatively; and (4) whether the trial
    court erred in granting Larmco's motion to dismiss Boller's
    third-party complaint.   In their appeal, the plaintiffs contend
    that the trial court erred in denying their motion to adjudicate
    Larmco's workers' compensation lien.       In their cross-appeal, the
    plaintiffs contend that the trial court erred in granting the
    remittitur.   Due to the length of the record in this case, we
    will limit our recitation of the facts to the trial testimony
    pertinent to the issues raised on appeal.
    BACKGROUND
    Boller performs general construction and concrete work.        It
    was one of 17 "prime" contractors hired to perform work on the
    Highland Park High School project (the project).      Thereafter,
    Boller entered into a contract with Larmco to perform the masonry
    work on the project.
    I. Trial Court Proceedings
    A. Liability Testimony
    new trial.
    3
    Nos. 1-08-3622 & 3635 Cons.
    In March 2002, Mr. Diaz was 53 years of age, and he was
    working on the project for Larmco as a laborer.       As part of his
    duties he would assist in the building of scaffolds.       Larmco used
    two kinds of scaffolds, either Non-Stops or Morgans.
    On March 19, 2002, Mr. Diaz and the other laborers were
    working on a Non-Stop scaffold.     A laborer named "Al"2 put an
    extension on the scaffold.     Mr. Diaz explained that, when an
    extension was added to a scaffold, it was necessary to put up two
    cross braces.     A second extension required two more cross braces
    and a straight brace at the top.       Al told Mr. Diaz that he was
    only using one cross brace because there was not a lot of
    material.
    In the afternoon, Mr. Diaz was working on the scaffolding
    with other laborers.     There were two types of planks on the
    scaffold; one for materials, such as bricks and mortar, and one
    used for walking.     While he was walking across the scaffold, a
    pile of bricks on the material plank broke open and fell on the
    bricklayers' plank.     Mr. Diaz went back to remove the bricks so
    that the bricklayers would not trip over them.       When he stepped
    on the material plank, it gave way, and he fell.        He briefly
    2
    "Al" was never identified, although it was suggested that
    Mr. Diaz was referring to Mr. Allen.       However, Mr. Allen was the
    foreman, not a laborer.
    4
    Nos. 1-08-3622 & 3635 Cons.
    lost consciousness.     After he regained consciousness, he was
    transported to the hospital.     He remained in the hospital over
    night and was released the next day.
    On cross-examination, Mr. Diaz denied complaining to Al that
    there was a problem with the scaffold.      However, he acknowledged
    that he felt there was something wrong when Al was putting up the
    extensions and told him he was going to put up only a single
    brace.     Mr. Diaz considered the scaffold safe.   Mr. Diaz took all
    of his instructions from Ed Allen from Larmco.      He did not take
    any instructions from anyone from Boller.      He did not hear any
    warning not to step on the plank.      He never complained to Mr.
    Allen about the scaffold.     He did not know whether the lack of
    the braces caused his accident.
    Miguel Diaz (Miguel)3 testified that he was employed by
    Larmco as a laborer and was working with Mr. Diaz on March 19,
    2002.     One of the material planks holding bricks fell.   "Maris,"
    one of the bricklayers, told them to be careful.      Mr. Diaz
    grabbed on to the tower portion of the scaffolding and stepped on
    the plank.     The plank fell with Mr. Diaz on top of it.
    According to Miguel, the laborers took their instructions
    for extending the scaffold and as to safety issues from Mr.
    Allen.     Miguel did not notice anything unusual about the scaffold
    3
    No relation to the plaintiffs.
    5
    Nos. 1-08-3622 & 3635 Cons.
    prior to the accident.    He did not pay any attention to the
    position of the planks.    Miguel and Mr. Diaz cranked the scaffold
    up to about 15 or 20 feet.
    Miroslaw Kundzicz testified that he was employed as a
    laborer by Larmco.   On March 19, 2002, just prior to Mr. Diaz's
    fall, Mr. Kundzicz was standing on one of the walking planks and
    noticed that one of the material planks was not completely on the
    angle iron where it normally rested.    About an inch of the plank
    was resting on the angle iron.    Mr. Kundzicz told the laborers
    nearby that the plank was not positioned correctly and warned
    them to be careful; he thought Miguel was behind him and would
    have heard the warning.    After turning back to his work, he heard
    the bricks fall to the walking platform.    He noticed that the
    Boller superintendent was always walking around the project.
    On cross-examination by Boller, Mr. Kundzicz testified that
    he took all of his orders from Mr. Allen.    He took no orders or
    directions from Boller.    The planks that fell were material
    planks.   Material planks are not intended for walking.   He was
    not sure what Mr. Diaz was walking on when he fell.    The only
    planks that moved prior to the fall were material planks.    He
    told the laborers that there was something wrong with the planks
    because it was their job to fix it.
    Francisco Gutierrez testified that he was employed as a
    6
    Nos. 1-08-3622 & 3635 Cons.
    machine operator by Larmco.   Prior to that, he had been a laborer
    and had assisted in assembling Non-Stop scaffolds and adding
    extensions to them.   On March 19, 2002, he was operating a crane,
    lifting up bricks to the scaffolding.      After he saw Mr. Diaz
    fall, he stopped the crane and went over to where Mr. Diaz was on
    the ground.   He observed a plank on the ground.     When he looked
    up at the scaffold, two planks were missing.      Based on his
    experience, a straight brace would be placed at the top of the
    scaffold.
    On cross-examination by Boller, Mr. Gutierrez testified that
    Mr. Allen directed how the scaffold was to be built.      Mr.
    Gutierrez had not been trained to assemble that type of scaffold,
    but he had assembled them.    He had also done pipe scaffolding but
    that was different from a Non-Stop scaffold.      Mr. Allen would be
    the appropriate person to decide where and when straight braces
    should be put on the scaffold.   Mr. Allen was his foreman; all
    the directions and orders came from him.      Mr. Gutierrez had no
    dealings with Boller.   Larmco employees were the only ones to
    erect and maintain the scaffold.       He did not know what caused the
    planks to fall or why Mr. Diaz fell.      After Mr. Diaz fell, Mr.
    Gutierrez looked up and saw the straight brace was missing.        On
    redirect examination, Mr. Gutierrez testified that, at the height
    of the scaffold in this case, when no cross braces are used, a
    7
    Nos. 1-08-3622 & 3635 Cons.
    straight brace is placed at the bottom and the top of the
    scaffold.
    Edward Allen, field superintendent for Larmco, testified as
    an adverse witness.     As a field superintendent, he was in charge
    of projects for Larmco.     He had taken an OSHA4 course in
    scaffolding.     At the time of Mr. Diaz's accident, he was a
    foreman but was still in charge of supervising the Larmco workers
    on the project.     OSHA required scaffolds to be built under the
    direction and supervision of a competent person.     According to
    Mr. Allen, he was considered a competent scaffold person.       There
    were scaffold builders but, as the foreman, he was responsible
    for making sure that the scaffolds were erected correctly.
    The day following Mr. Diaz's fall, Mr. Allen inspected the
    site of the accident in compliance with Larmco's safety manual.
    In his report of the accident, he noted that two material planks
    had fallen off the scaffold, one of which fell when Mr. Diaz
    stepped on it.     Mr. Allen acknowledged that there was no straight
    arm brace at the top of the scaffold but explained that the Non-
    Stop scaffold used here did not require it.     He acknowledged
    that, at his deposition, he stated that the straight arm brace
    was to be placed between the two cross braces.     During his
    inspection of the scaffold, he observed that five other straight
    4
    Occupational Safety and Health Act (
    29 U.S.C. §651
     (2000)).
    8
    Nos. 1-08-3622 & 3635 Cons.
    braces were missing.   While Mr. Allen stated that the height of
    the scaffold in this case did not require a straight brace at
    every interval where there was no cross brace, he acknowledged
    that, at his deposition, he had stated that the straight braces
    were required.
    Mr. Allen explained that, as part of his duties, he walked
    the jobsite every morning and checked the scaffolds to make sure
    they were safe.   They had to be checked every day due to changing
    conditions, such as the weather.       He had checked the scaffolding
    the morning of Mr. Diaz's accident.      Had he noticed the missing
    braces then, he would have ordered that they be installed.
    However, he explained that scaffold changes also took place
    during the day.   Mr. Allen was familiar with the tagging system;
    a scaffold would be tagged to indicate it was okay to use or had
    problems.   Boller did not require Larmco to use the tagging
    system.   It was his understanding that the straight arm braces
    were taken off when the extensions were added to the scaffold
    prior to the accident but were not put back on the scaffold.
    Mr. Allen identified Ben Chambers as Boller's job
    superintendent for the project.    While Larmco was responsible for
    the scaffolding, if Mr. Chambers noticed a problem, he would
    inform Mr. Allen, and the problem would have to be fixed.      Mr.
    Chambers was in charge of where and when Larmco did its work.
    9
    Nos. 1-08-3622 & 3635 Cons.
    Mr. Chambers had the right to stop work for safety reasons.     Mr.
    Chambers had the right to instruct Larmco personnel to implement
    safety procedures for scaffolding, but only if he knew what they
    were.
    On cross-examination by Boller's attorney, Mr. Allen
    explained that at the time of his deposition, he had confused the
    Non-Stop scaffold with the Morgan scaffold and had testified
    about the Morgan scaffold rather than the Non-Stop scaffold that
    Larmco used in the project.    The Non-Stop scaffold required
    bracing at a higher level, 36 feet, than did the Morgan scaffold.
    The scaffold in this case was not required to go to 36 feet.
    As part of his job, Mr. Allen oversaw the safety aspect of
    Larmco's work.   Larmco had safety training for its workers and
    laborers, including weekly safety meetings.    The bracing of the
    scaffold was Larmco's job.    There had been no complaints about
    the scaffolding.   Boller would not have any reason to believe
    that there was a problem with Larmco's scaffold.
    On redirect examination, Mr. Allen acknowledged, based on
    his investigation, it was possible Mr. Diaz's fall was due to the
    missing straight brace, which caused the scaffold to separate.
    On re-cross-examination by Boller, Mr. Allen stated that the
    measurements he took during his investigation indicated that the
    scaffold was in the same position it was in prior to the
    10
    Nos. 1-08-3622 & 3635 Cons.
    accident.
    Benjamin Chambers testified as an adverse witness.    Mr.
    Chambers worked for Boller as a construction superintendent and,
    as such, was the Boller person responsible for preventing
    accidents on the project.   Mr. Chambers would arrive on the
    project site at 6:30 a.m. and would spend 30 minutes inspecting
    the site.   He would look at the scaffolding every morning to make
    sure there were no safety deficiencies.    He also walked around
    the site at other times during the day looking for safety
    problems.   As the Boller construction superintendent, Mr.
    Chambers had the authority to stop the work if a subcontractor
    was using unsafe equipment or doing work in an unsafe manner.      On
    two occasions, he had stopped excavation work on the site.     While
    he had experience in excavation work, he had no experience in
    scaffolding.   He did not know when straight braces were required
    or the number of bricks that could be placed safely on the
    material planks.
    All of the subcontractors were required to give Mr. Chambers
    a copy of their safety manuals.    According to Larmco's safety
    manual, there was a checklist for tower scaffolding.    However,
    Mr. Chambers never collected the checklists to determine if
    Larmco was using and following them in its work on the project.
    He was not familiar with the tagging system.    He did not know
    11
    Nos. 1-08-3622 & 3635 Cons.
    what the qualifications were for someone like Mr. Allen to
    oversee the construction of the scaffold.
    On March 19, 2002, Mr. Chambers did not see anything wrong
    with the scaffold at 6:30 am.   Shortly after lunch on that day,
    he looked at the scaffold again but did not observe any problem
    with it.
    On cross-examination by Boller, Mr. Chambers described his
    safety responsibilities on the project: establishing entrances
    and exits, signage for the construction area, providing fire
    extinguishers, telephone access and emergency plans.    Boller had
    a safety program dealing with safety hazards that could arise on
    the project site.    Boller was the general contractor on the
    science building wing.   While there were 17 other prime
    contractors, eventually, Boller began to coordinate those
    contractors as well.
    Mr. Chambers acknowledged that he had no training in
    scaffolding, but for many years, he had watched them be
    constructed and knew "what is supposed to happen."    He relied on
    Mr. Allen to use the scaffold correctly.    There were no
    complaints about the scaffold, and Mr. Chambers observed nothing
    to indicate that Larmco was not competent in its use of its own
    scaffold.   He saw nothing on the morning of the accident to
    indicate that the scaffold was unsafe.   Mr. Chambers relied on
    12
    Nos. 1-08-3622 & 3635 Cons.
    Mr. Allen to make that decision whether a brace was required.
    William Hickey testified that he had been a part owner of
    Larmco and had been employed as a general superintendent.    He had
    been a bricklayer and had worked on a variety of scaffolds.   He
    had taken 10-hour and 40-hour OSHA courses.    At the time of Mr.
    Diaz's accident, Mr. Hickey was Larmco's general superintendent.
    He would spend at least one day a week on the project site.   He
    attended the job meetings and discussed scheduling, safety issues
    and problems with Mr. Allen.   He was not informed of any safety
    issues with the Non-Stop scaffolding.   Weekly safety meetings
    were held to discuss safety issues.   Larmco had its own safety
    manual, which covered scaffolding.
    Mr. Hickey testified further that he inspected the scaffold
    the day after the accident and found nothing wrong with it.   The
    scaffold appeared to be braced properly.   There were no straight
    braces missing from the top of the scaffold.   Straight bracing
    was used on a Non-Stop scaffold once it reached 36 feet in
    height.
    Mr. Hickey further testified that the general contractor did
    not tell Larmco laborers how to build the scaffolding.   He would
    not expect the general contractor to tell Larmco's foreman or
    laborers to put in a straight brace at 36 feet.   The contract
    between Larmco and Boller required Larmco to furnish a competent
    13
    Nos. 1-08-3622 & 3635 Cons.
    person as its representative on the site.     In this case, that
    person was Mr. Allen.   The laborers received on-the-job training
    with regard to the scaffold building and maintenance.     Mr. Diaz
    would have received such training.
    On cross-examination by the plaintiffs, Mr. Hickey
    acknowledged that he did not see the scaffolding prior to the
    accident.   He denied that when a scaffold is constructed, a
    straight brace was placed at the top.     He further denied that a
    straight brace was required on the scaffold for stability
    purposes.   He did not recall his deposition testimony in which he
    stated that there should be a straight brace at the top of the
    scaffold for stability and because "[i]t's the way the scaffold's
    built."
    On redirect examination, Mr. Hickey testified that the
    straight braces were not necessary because each tower worked
    individually.   He believed that the scaffold had been adequately
    braced.
    Frank L. Burg, the plaintiff's expert, testified that he was
    a certified safety professional.     He had worked for OSHA as a
    compliance officer and then as a training director.     He became
    head of the voluntary protection program, which required him to
    look at companies and determine the adequacy of their safety
    programs.   Mr. Burg participated in writing the standards at the
    14
    Nos. 1-08-3622 & 3635 Cons.
    American National Standards Institute (ANSI), especially for
    cranes, scaffolding and safety programs.
    Mr. Burg testified that he was familiar with the Non-Stop
    scaffold used in this case.   He stated that a straight brace was
    required at the bottom and at the top between the scaffolding
    towers to keep the towers from separating.   If the scaffolding
    was properly constructed, the material planks would not fall out.
    Mr. Burg opined that Boller had control and responsibility
    for the proper construction of the scaffolding based on its
    control of the safety of the project site.   Based on his
    experience, as part of its control of the project site, Boller
    would be expected to make sure that its subcontractors were
    competent, qualified and properly trained.   Mr. Burg opined that
    Boller did not meet its responsibilities regarding scaffold
    safety, explaining as follows:
    "They didn't make sure that the people that were doing the
    scaffolding were properly trained, that they were competent,
    that they were qualified, that they had a system of
    accountability for the scaffolding."
    Mr. Burg further opined that Mr. Allen was not a competent
    or qualified person under OSHA standards because he allowed an
    untrained worker to erect the scaffold and acknowledged in his
    deposition that he was unsure who had training and who did not.
    15
    Nos. 1-08-3622 & 3635 Cons.
    The tagging system was not used, an important factor given
    workers' lack of fluency in English.    Boller's duty was to make
    sure the masonry company it hired used trained personnel who
    followed procedures and that there was a system of
    accountability, i.e., records of the inspections.    In this case,
    Boller's written safety program consisted of one page.    It
    contained no specific safety rules for the erection of a Non-Stop
    scaffold.   In Mr. Burg's opinion, Boller's safety manual was not
    adequate to ensure safety at the project site.
    Mr. Burg testified further that, as project superintendent,
    Ben Chambers had responsibility for safety, both under the terms
    of the contract between Boller and the school district and his
    job description.    Mr. Burg noted that, in his deposition, Mr.
    Chambers acknowledged that he did not know anything about Non-
    Stop scaffolds.    Mr. Burg explained that, while the general
    contractor does not have to have complete knowledge of its
    subcontractors' work, Boller needed sufficient knowledge to
    assess whether its subcontractor is qualified and competent.
    When the scaffold was altered by adding the extension, OSHA
    standards required that it be supervised by a competent person
    and then reinspected to ensure its safety.    In this case, no such
    inspection was performed.
    On cross-examination by Boller, Mr. Burg acknowledged, that
    16
    Nos. 1-08-3622 & 3635 Cons.
    with respect to the bracing, Boller or Larmco personnel would
    have thought that the scaffold conformed to the requirements of
    the Non-Stop manual.    While he understood that the wall the
    bricklayers were working on would not reach 36 feet and the
    manual did not call for bracing below 36 feet, Mr. Burg explained
    that the ground conditions could change or the scaffold might be
    affected by the weather, causing it to be unbalanced.    He did not
    know if the scaffold was in fact unbalanced.    He did acknowledge
    that the planks might have been cracked or might have been
    knocked out of place by the bricks.
    Mr. Burg testified further that OSHA standards provide the
    minimum requirements.    Following OSHA or ANSI standards would not
    ensure safety.   According to Mr. Burg, Mr. Allen was not
    competent, even though he was trained in scaffold use.      Mr. Burg
    opined that Boller did not do what was reasonable and normal for
    a general contractor to do as far as implementing a safety
    program; had they done so, Mr. Diaz's accident would not have
    occurred.   While the scaffold looked in perfect condition when
    Mr. Chambers viewed it, it should have been reinspected after the
    addition of the extension.    Had the planks been checked, the
    accident would not have happened.     Mr. Burg agreed that the Non-
    Stop manual stated that braces were not needed until the scaffold
    reached 36 feet.
    17
    Nos. 1-08-3622 & 3635 Cons.
    On redirect examination, Mr. Burg testified that a 2006 Non-
    Stop publication showed scaffolds at the same height as or
    shorter than the one from which Mr. Diaz fell; there were
    straight braces at the top of the scaffolds.    In his deposition
    testimony, Mr. Allen agreed with Mr. Burg that straight braces
    should have been provided on the scaffold in this case.    Mr. Burg
    opined that the Larmco safety manual was not implemented on this
    project.   Boller was required to make sure that its
    subcontractors had a safety program and that they were competent
    and qualified.   Had the straight brace been at the top, the plank
    would not have fallen out.
    Wendell Rust, Boller's expert, testified that he was
    employed as a safety professional.    Previously, he worked for
    OSHA as an inspector and a consultant.    While working for OSHA,
    he inspected many construction projects, including scaffolding.
    He was an authorized OSHA trainer and had taken training for
    scaffold construction and use.
    Mr. Rust testified that, under OSHA rules, Boller was the
    "controlling" employer and was not normally required to inspect
    for hazards or have the same level of knowledge of the applicable
    standards for the trades.    It was Larmco's responsibility to
    train its workers who utilized the scaffolds.    Mr. Rust opined
    that Boller did nothing to cause the accident in this case.      He
    18
    Nos. 1-08-3622 & 3635 Cons.
    found no evidence that would have indicated to Boller that Mr.
    Allen was not competent to oversee the scaffold.
    According to Mr. Rust, Boller met its responsibilities on
    the construction site by providing training for their management
    personnel, by using a safety consultant to do additional safety
    management and by having a safety director/superintendent (Mr.
    Chambers) who had the authority to stop the work if he saw
    something wrong.   Mr. Chambers had taken a 30-hour training
    course and checked the jobsite for unsafe conditions.   Had there
    been anything obviously wrong with the scaffolding, Mr. Chambers
    could order the work stopped and require the subcontractor and
    his employees to fix it.
    Mr. Rust testified that, based on OSHA regulations, the Non-
    Stop assembly instructions and the Larmco safety manual, there
    was no need to place a straight brace at the top of the scaffold.
    If one of the towers was not secure because of swaying, there
    would have been an obvious problem with the scaffold.
    On cross-examination by the plaintiffs, Mr. Rust
    acknowledged that the contract between Boller and the school
    district required Boller to be responsible for safety in
    performance of the contract and required it to provide a
    competent superintendent.   He agreed that the superintendent
    should be able to identify hazards or unsafe conditions in the
    19
    Nos. 1-08-3622 & 3635 Cons.
    scaffolding.   He was familiar with Mr. Chambers's statements in
    his deposition that he had no specific training in scaffolding
    and that he was not certified by OSHA to build scaffolding.
    B. Damages Testimony
    Dr. Ernest John Saliba, Jr., an emergency room physician at
    Evanston Hospital, examined Mr. Diaz following his fall from the
    scaffold.   The plaintiff had fallen from a height of 20 to 30
    feet; 50% of the people experiencing such a fall do not survive.
    Mr. Diaz exhibited swelling in his right forearm and a scalp
    laceration.    He had abrasions on his lower back and complained of
    pain in that area.   A CT scan of his head revealed no injury.   On
    cross-examination, Dr. Saliba testified that the CT scan of Mr.
    Diaz's neck was negative but did show degenerative changes.    The
    CT scan of his abdomen showed that there were no fractures or
    dislocations to his spine.
    Mr. Diaz testified that, for the first few days following
    his fall, he remained in bed; he felt very bruised and could not
    move.   He saw either Dr. Marcus or Dr. Vanderbilt and complained
    of pain throughout his body.   He was given pills and prescribed
    physical therapy.    Dr. Marcus performed surgery on his right knee
    after which he returned for more physical therapy.   In November
    2002, Mr. Diaz was examined by Dr. Shenker.    Mr. Diaz complained
    of pain in his neck, back and his eyes.
    20
    Nos. 1-08-3622 & 3635 Cons.
    Mr. Diaz was next examined by Dr. Skaletsky.       Mr. Diaz
    complained of constant headaches, dizziness and neck and shoulder
    pain.     He also complained of pain in his lower back radiating
    into his leg.5     Recently, Dr. Skaletsky referred him to Dr. Jain
    at PainNet.     Dr. Jain treated him with injections.    He still has
    pain in his neck and back.     He takes medication for the pain and
    wears a back brace.     He also has pain in his jaw; when he opens
    his mouth a lot, it cracks.
    Mr. Diaz explained that he felt very stressed from not being
    able to move or to work.     He has been unsuccessful at obtaining
    work in other industries and was not working at the time of
    trial.
    Ronald Agrigento, a physical therapist, testified that he
    examined Mr. Diaz on April 9, 2002.     The examination revealed
    that Mr. Diaz had a diminished range of motion and strength in
    his shoulder and his right knee; the knee was swollen, and he had
    a large bruise on his lower extremity.         Mr. Diaz rated his pain
    as very high.     He had three sessions of therapy after which he
    had surgery on his knee.     On June 4, 2002, he returned for more
    therapy, primarily on his knee.     He then began the work-hardening
    therapy program.     Mr. Diaz worked hard at his therapy.    An
    evaluation showed that he did not meet the requirements for heavy
    5
    Mr. Diaz did not specify which leg.
    21
    Nos. 1-08-3622 & 3635 Cons.
    work but was able to perform medium work.
    Mr. Agrigento testified further that, in March 2005, Mr.
    Diaz returned for an evaluation and treatment of his lower back
    pain.   Testing revealed that he had diminished range of motion in
    his lumbosacral spine and a diminished curve indicating some form
    of tightness or spasm in the spine.     By the end of April 2005, he
    showed improvement; his pain levels were reduced and his range of
    motion nearly doubled.   Mr. Diaz was still having problems and
    complained of experiencing a slight headache every morning.
    On cross-examination by Boller, Mr. Agrigento testified
    that, in May 2002, Mr. Diaz had undergone surgery to repair a
    meniscus tear in his right knee.     At the time of the first
    evaluation in June 2002, there was no mention of lower back pain.
    At the time of the second evaluation in July 2002, Mr. Diaz
    complained of headaches and that his right knee gave out
    occasionally.   He also experienced a sensation of "pins and
    needles" in his right knee except when walking.     There was no
    complaint of lower back pain at that time.
    Dr. Gary S. Skaletsky, a board-certified neurosurgeon,
    testified that he first examined Mr. Diaz on March 25, 2003.       Mr.
    Diaz complained of pain in his head and neck, and pain, as well
    as numbness and weakness, in his right arm.     His examination
    revealed a muscle spasm in the right trapezius muscle.     Given Mr.
    22
    Nos. 1-08-3622 & 3635 Cons.
    Diaz's history and his examination, Dr. Skaletsky concluded that
    Mr. Diaz's complaints were related to his fall.   The doctor
    ordered X-rays of Mr. Diaz's neck and an MRI of his spine.     The
    X-ray showed degenerative changes but no instability.     The MRI
    showed the degenerative changes expected in a man of Mr. Diaz's
    age but not a slipped disc.   The doctor explained that
    degenerative changes do not typically result in pain, but a
    traumatic event can cause the changes to produce pain.
    When Mr. Diaz returned to see Dr. Skaletsky in May 2003, his
    symptoms had not changed.   Dr. Skaletsky opined that Mr. Diaz's
    fall irritated the nerve root and resulted in loss of sensation
    and pain in his right arm. The doctor further opined that Mr.
    Diaz should not return to his work as a laborer; his pain and
    limited motion and the difficulty in using his right arm put him
    and people working with him at risk.   Dr. Skaletsky recommended
    physical therapy.   However, Mr. Diaz could not afford physical
    therapy at that time.
    On September 15, 2003, Dr. Skaletsky examined Mr. Diaz who,
    for the first time, complained of low back pain radiating into
    his right leg all the way to his ankle; the pain was worse with
    activity.   Mr. Diaz had a limited range of motion, and straight
    leg tests indicated he had an irritation of the sciatic nerve,
    the nerve stemming from the L5-S1 level.   The doctor recommended
    23
    Nos. 1-08-3622 & 3635 Cons.
    epidural steroid injections and that Mr. Diaz undergo a course of
    physical therapy to build and strengthen his muscles.    In the
    spring of 2005, Dr. Skaletsky referred Mr. Diaz for physical
    therapy, but he continued to complain of pain in his lower back.
    Dr. Skaletsky referred Mr. Diaz to Dr. Jain at PainNet.      On
    March 20, 2008, Dr. Jain performed a nucleoplasty to reduce the
    irritation on the disc.    It was necessary to wait 6 to 12 weeks
    to determine the success of the procedure.    If the nucleoplasty
    were unsuccessful, the next step would be for Mr. Diaz to undergo
    an MRI to determine the general state of the nerves.    If the MRI
    showed nerve root compression, decompression surgery at the L5-S1
    level would be an option.    Dr. Skaletsky estimated the attendant
    costs to be $100,000 for the surgery and $75,000 for
    hospitalization.   Postoperative physical therapy would take about
    6 months, at three times a week for $1,000 per week.
    Prior to trial in this case, on April 4, 2008, Dr. Skaletsky
    examined Mr. Diaz, who still complained of pain in his lower
    back.   He also complained of neck pain, greater on the left side;
    the pain extended into his right shoulder and forearm.    The pain
    was worse with repetitive movements and prolonged positioning.
    He also had pain in the back of his head radiating from his neck.
    The doctor noted that these were the same symptoms Mr. Diaz had
    complained of in 2003.    The doctor further noted that Mr. Diaz
    24
    Nos. 1-08-3622 & 3635 Cons.
    had a limited range of motion in turning his neck to the left; he
    had tenderness at the back of the neck and the trapezius muscle.
    He had diminished strength and sensation in his upper right arm.
    Dr. Skaletsky reviewed the multiple MRIs of Mr. Diaz's low
    back. Using the 2006 MRI, the doctor explained that Mr. Diaz had
    a condition known as spondylolisthesis at the L5-S1 level.      Such
    a condition made him more susceptible to a nerve injury due to
    trauma.
    Dr. Skaletsky opined that Mr. Diaz's lower back pain was
    related to his fall from the scaffold.   Prior to the fall, he had
    no symptoms of lower back pain or dysfunction.   Following the
    fall, he experienced a rapid onset of symptoms, initially noted
    in his knee but also in his lower back. Dr. Skaletsky opined that
    Mr. Diaz's fall aggravated his preexisting condition of
    spondylolisthesis.
    Dr. Skaletsky then testified that, in late 2007 or the
    beginning of 2008, he received information that Mr. Diaz was
    having difficulties with his memory and attention span and that
    he was very irritable.   At his April 4, 2008, visit, Mr. Diaz
    acknowledged those symptoms to the doctor.   Because Mr. Diaz
    reported a loss of consciousness at the time of the accident, the
    doctor ordered a CT scan, but the results were normal.    Dr.
    Skaletsky explained that some damaged connections were too small
    25
    Nos. 1-08-3622 & 3635 Cons.
    to be seen on a CT scan.   The fact that there was a delay in
    reporting the symptoms could be attributed to Mr. Diaz's failure
    to recognize the symptoms as a medical problem.   Dr. Skaletsky
    opined that Mr. Diaz's symptoms of irritability, memory loss and
    confusion were causally connected to his fall.    He further opined
    that Mr. Diaz's conditions are permanent.
    On cross-examination by Boller, Dr. Skaletsky acknowledged
    that Mr. Diaz did not complain of lower back pain until September
    2005, and that prior to September 2005, none of the other doctors
    had treated Mr. Diaz for back pain.   He further acknowledged that
    at the time of his deposition in January 2005, he testified that,
    in his opinion, Mr. Diaz's back pain was not related to his fall.
    However, at his deposition, he had qualified that opinion by
    stating that it was based on the information he had at the time.
    At his deposition in January 2007, he was shown the Evanston
    Hospital emergency room records; these records formed the basis
    of his opinion of causality: Mr. Diaz's fall aggravated existing
    conditions in his neck and back.
    Dr. Skaletsky testified that, except for a complaint at his
    initial examination in 2003, Mr. Diaz made no complaints relative
    to his head until his April 4, 2008, examination.   The doctor
    acknowledged that the emergency room records showed that Mr. Diaz
    did not lose consciousness.   Dr. Skaletsky acknowledged that it
    26
    Nos. 1-08-3622 & 3635 Cons.
    was impossible to say within a reasonable degree of medical
    certainty whether or not Mr. Diaz would require surgery in the
    future.
    Dr. Daniel Fortuna, a chiropractic physician, testified that
    he examined Mr. Diaz on January 3, 2004.      Mr. Diaz complained of
    experiencing headaches, dizziness and lower back and neck pain
    since he had fallen off a scaffold in 2002.      The doctor's
    examination revealed tenderness in his neck, the trapezius muscle
    and the right-side muscles from his mid to lower back.      Tests
    showed an irritation of the nerve.      Dr. Fortuna opined that these
    symptoms were related Mr. Diaz's fall because he had no
    complaints prior to the fall.   He ordered an MRI; the results
    indicated spondylolisthesis.    The doctor ordered muscle relaxing
    treatments, stabilization and strengthening exercises.
    Dr. Fortuna further testified that, in March 2004, he
    reassessed Mr. Diaz's condition.      While Mr. Diaz had made
    progress in muscle strength, he still had tension and pain in the
    nerves.   Since Mr. Diaz was not recovering as the doctor had
    expected, the doctor referred him to an orthopedic surgeon.      In
    April 2004, Dr. Fortuna examined Mr. Diaz.      While he was feeling
    better, Mr. Diaz complained of headaches, three or four times a
    week.   He had constant lower back pain but of a milder intensity.
    The pain increased with sitting.
    27
    Nos. 1-08-3622 & 3635 Cons.
    Dr. Fortuna testified further that he examined Mr. Diaz in
    October 2006.   Mr. Diaz filled out a questionnaire to provide
    information as to his pain level and the effect it was having on
    his life.   Mr. Diaz indicated that his pain level was very
    intense and did not vary.   The pain affected his sleeping, his
    ability to sit and even his ability to wash and dress himself.
    He could lift only very light weights.    The pain restricted his
    social life and his ability to walk and to travel.    Mr. Diaz
    indicated that the pain extended from his low back up to his neck
    and the back of his head; the sides of his head hurt.    He had
    continuous jaw pain; it was hard to chew and to swallow.    He had
    numbness and a tingling sensation from his right knee down.      The
    right knee felt like it had no strength, and he felt as if he
    would fall.   Mr. Diaz felt angry and depressed and believed that
    his personality had changed.    His mood change began about two
    years after the accident.   He experienced right shoulder pain
    intermittently.   Dr. Fortuna opined that, given his condition,
    Mr. Diaz could not work.
    Testimony from family members and a friend confirmed Mr.
    Diaz's personality change and memory problems.    There was expert
    testimony from Charles Linke, an economist, establishing that the
    average life expectancy for Mr. Diaz was 21 years.
    ANALYSIS
    28
    Nos. 1-08-3622 & 3635 Cons.
    I. Boller's Appeal
    A.   Directed Verdict/Judgment N.O.V.
    Boller contends that it was entitled to a directed verdict
    or a judgment n.o.v. because there was no evidence of its
    liability pursuant to section 414 of the Restatement (Second) of
    Torts (Restatement (Second) of Torts §414 (1965)).     Section 414
    recognizes two theories of liability under which an injured
    worker may seek to hold a general contractor liable: vicarious
    and direct liability.   In its opening brief, Boller argued that
    the plaintiffs failed to present evidence to establish its
    vicarious liability for the plaintiff's injury.     However, the
    plaintiffs maintain that their suit was premised on Boller's
    direct liability.   Therefore, we will confine our discussion to
    whether the evidence established Boller's direct liability under
    section 414 for Mr. Diaz's accident.
    1. Directed Verdict
    a. Standard of Review
    The court applies the de novo standard of review to the
    denial of a motion for a directed verdict.      Jones v. DHR
    Cambridge Homes, Inc., 
    381 Ill. App. 3d 18
    , 28, 
    885 N.E.2d 330
    (2008).   "'A directed verdict is appropriate where the plaintiff
    has failed to establish a prima facie case.'"      Jones, 381 Ill.
    App. 3d at 28, quoting Kim v. Mercedes-Benz, U.S.A., Inc., 353
    29
    Nos. 1-08-3622 & 3635 Cons.
    Ill. App. 3d 444, 460, 
    818 N.E.2d 713
     (2004).    "'A directed
    verdict is granted improperly where "there is any evidence,
    together with reasonable inferences to be drawn therefrom,
    demonstrating a substantial factual dispute, or where the
    assessment of credibility of the witnesses or the determination
    regarding conflicting evidence is decisive to the outcome."'"
    Jones, 381 Ill. App. 3d at 28, quoting Kim, 381 Ill. App. 3d at
    460, quoting Maple v. Gustafson, 
    151 Ill. 2d 445
    , 454, 
    603 N.E.2d 508
     (1992).
    b. Discussion
    A cause of action for common law negligence under section
    414 requires that the plaintiff allege a duty on the part of the
    defendant, a breach of that duty and a compensable injury
    resulting from the breach.     Bokodi v. Foster Wheeler Robbins,
    Inc., 
    312 Ill. App. 3d 1051
    , 1059, 
    728 N.E.2d 726
     (2000).
    Boller contends that it did not owe a duty to the plaintiff
    because it did not retain any contractual control over Larmco's
    work on the project.
    i. Existence of Duty
    "As a general rule, one who entrusts work to an independent
    contractor will not be liable for the acts or omissions of that
    independent contractor."     Calderon v. Residential Homes of
    America, Inc., 
    381 Ill. App. 3d 333
    , 340, 
    885 N.E.2d 1138
     (2008).
    30
    Nos. 1-08-3622 & 3635 Cons.
    The "retained control exception" to this rule is set forth in
    section 414 of the Restatement (Second) of Torts (Restatement
    (Second) of Torts §414 (1965)).    Section 414 provides as follows:
    "One who entrusts work to an independent contractor,
    but who retains the control of any part of the work, is
    subject to liability for physical harm to others for whose
    safety the employer owes a duty to exercise reasonable care,
    which is caused by his failure to exercise his control with
    reasonable care."   Restatement (Second) of Torts §414, at
    387 (1965).
    Comment a to section 414 explains the distinction between
    "vicarious" liability and "direct" liability, which is at issue
    in this case, as follows:
    "If the employer of an independent contractor retains
    control over the operative detail of doing any part of the
    work, he is subject to liability for the negligence of the
    employees of the contractor engaged therein, under the rules
    of that part of the law of Agency which deals with the
    relation of master and servant.   The employer may, however,
    retain a control less than that which is necessary to
    subject him to liability as master.   He may retain only the
    power to direct the order in which the work shall be done,
    or to forbid its being done in a manner likely to be
    31
    Nos. 1-08-3622 & 3635 Cons.
    dangerous to himself or others.   Such a supervisory control
    may not subject him to liability under the principles of
    Agency, but he may be liable under the rule stated in this
    Section unless he exercises his supervisory control with
    reasonable care so as to prevent the work which he has
    ordered to be done from causing injury to others."
    Restatement (Second) of Torts §414, Comment a, at 387
    (1965).
    As this court noted in Cochran v. George Sollitt Construction
    Co., 
    358 Ill. App. 3d 865
    , 
    832 N.E.2d 355
     (2005), comment a
    clarifies that "the general contractor, by retaining control over
    the operative details of its subcontractor's work, may become
    vicariously liable for the subcontractor's negligence;
    alternatively, even in the absence of such control, the general
    contractor may be directly liable for not exercising his
    supervisory control with reasonable care."    Cochran, 
    358 Ill. App. 3d at 874
    .
    Comment b to section 414 explains the theory of direct
    liability described in comment a of section 414.    Comment b
    provides:
    "The rule stated in this Section is usually, though not
    exclusively, applicable when a principal contractor entrusts
    a part of the work to subcontractors, but himself or through
    32
    Nos. 1-08-3622 & 3635 Cons.
    a foreman superintends the entire job.   In such a situation,
    the principal contractor is subject to liability if he fails
    to prevent the subcontractors from doing even the details of
    the work in a way unreasonably dangerous to others, if he
    knows or by the exercise of reasonable care should know that
    the subcontractors' work is being so done, and has the
    opportunity to prevent it by exercising the power of control
    which he has retained in himself.   So too, he is subject to
    liability if he knows or should know that the subcontractors
    have carelessly done their work in such a way as to create a
    dangerous condition, and fails to exercise reasonable care
    either to remedy it himself or by the exercise of his
    control cause the subcontractor to do so."   Restatement
    (Second) of Torts §414, Comment b, at 387-88 (1965).
    Comment c to Section 414 explains that for the "retained"
    control exception to apply:
    "[T]he employer must have retained at least some degree
    of control over the manner in which the work is done.    It is
    not enough that he has merely a general right to order the
    work stopped or resumed, to inspect its progress or to
    receive reports, to make suggestions or recommendations
    which need not necessarily be followed, or to prescribe
    alterations and deviations.    Such a general right is usually
    33
    Nos. 1-08-3622 & 3635 Cons.
    reserved to employers, but it does not mean that the
    contractor is controlled as to his methods of work, or as to
    operative detail.   There must be such a retention of a right
    of supervision that the contractor is not entirely free to
    do the work in his own way."    Restatement (Second) of Torts
    §414, Comment c, at 388 (1965).
    The determination of whether Boller owed a duty of care to
    the plaintiff depends on whether Boller controlled the work in
    such a manner that it should be held liable.    Bokodi, 
    312 Ill. App. 3d at 1059
    .   The following portions of the contract between
    Boller, the school district and the architect were entered into
    evidence at trial:
    "The contractor shall take reasonable precautions for
    the safety of and shall provide reasonable protection to
    prevent damage, injury or loss to: One, employees who work
    or other persons who may be affected thereby.
    * * *
    The contractor shall designate a responsible member of
    contractor's organization at the site whose duty shall be
    the prevention of accidents.
    * * *
    The contractor shall be responsible for initiating,
    maintaining and supervising all safety precautions and
    34
    Nos. 1-08-3622 & 3635 Cons.
    programs in connection with the performance of the contract.
    * * *
    The contractor shall employ a competent superintendent
    and necessary assistants who shall be in attendance at the
    project site during the performance of the work.
    * * *
    The contractor shall supervise and direct the
    performance of the work using his best skill and attention.
    The contractor shall be solely responsible for all
    construction means, methods, techniques, sequences and
    procedures and for coordinating all portions of the work
    under the contract."
    An employer need only retain control over any part of the
    work in order to be subject to liability for a failure to
    exercise his control with reasonable care.    Brooks v. Midwest
    Grain Products of Illinois, Inc., 
    311 Ill. App. 3d 871
    , 
    726 N.E.2d 153
     (2000).    "[A] general right to ensure that safety
    precautions are observed and that work is done in a safe manner
    will not impose liability on the general contractor unless the
    evidence shows that the general contractor retained control over
    the means and methods of the independent contractor's work."
    Ross v. Dae Julie, Inc., 
    341 Ill. App. 3d 1065
    , 1071, 
    793 N.E.2d 68
     (2003).    "In determining whether that level of control has
    35
    Nos. 1-08-3622 & 3635 Cons.
    been retained, Illinois courts ask whether the principal merely
    retained general oversight of work progress and safety or
    actually engaged in detailed supervision and/or control of the
    subcontractors' methods and means of performing work."    Aguirre
    v. Turner Construction Co., 
    501 F.3d 825
    , 830 (7th Cir. 2007).
    Whether a contractor has retained sufficient control to trigger
    liability under section 414 is generally a question of fact.
    Wilkerson v. Paul H. Schwendener, Inc., 
    379 Ill. App. 3d 491
    , 
    884 N.E.2d 208
     (2008)
    Boller argues that it did not retain any contractual control
    over Larmco because the language giving it control over
    construction means, methods and techniques was stricken from the
    contract.   However, controlling the operative details of the
    subcontractors' work is necessary for vicarious liability; direct
    liability stems from the failure to exercise general supervisory
    control.    Pestka v. Town of Fort Sheridan Co., 
    371 Ill. App. 3d 286
    , 300, 
    862 N.E.2d 1044
     (2007).
    In the present case, the plaintiffs presented sufficient
    evidence to establish a prima facie case that Boller retained
    sufficient control over the safety of the project to trigger its
    liability for the plaintiff's injuries.   The provisions of the
    contract between Boller, the school district and the architect
    placed the responsibility for the safety of the project site with
    36
    Nos. 1-08-3622 & 3635 Cons.
    Boller.   Under the contract, Boller was responsible for
    preventing injuries on the project site.      It was required to
    initiate, maintain and supervise all of the safety precautions
    and programs in the performance of its contract.      It also was
    required to designate a person responsible for the prevention of
    accidents and to employ a "competent" superintendent.      Boller was
    solely responsible for "all construction means, methods,
    techniques, sequences and procedures and for coordinating all
    portions of the work under the contract."      Under the contract
    between Boller and Larmco, Larmco was responsible for the safety
    and training of its employees.   However, that contract also
    required Larmco to follow all of Boller's safety directions and,
    in emergency situations, Boller could implement the safety
    measures and require Larmco to pay for them.
    The testimony at trial confirmed the extent of Boller's
    control of safety of the project site.      Mr. Rust, Boller's expert
    witness, testified that the contract between Boller and the
    school district required Boller to be responsible for safety in
    the performance of the contract.      In meeting those
    responsibilities, Mr. Rust pointed out that Boller provided
    training for its management personnel, provided a safety
    consultant to do additional safety management and gave its
    superintendent the authority to stop work if he observed a
    37
    Nos. 1-08-3622 & 3635 Cons.
    problem.   Mr. Hickey testified that weekly safety meetings were
    held to discuss safety issues.   Mr. Chamberlain, Boller's
    superintendent, testified that it was his job to prevent
    accidents.   He had the authority to stop the work of a
    subcontractor if the contractor was using unsafe equipment or
    doing the work in an unsafe manner.   On two occasions, he had
    stopped an excavation on the project site.   See Wilkerson, 379
    Ill. App. 3d at 497 (the assertion of the general contractor's
    discretionary authority was the best evidence of the retention of
    more than a general right of supervision).   The subcontractors
    were required to give Mr. Chambers a copy of their safety
    manuals.   He walked the project site to check for safety
    deficiencies.   Mr. Allen testified that, if Mr. Chambers observed
    a problem with Lamarco's work, Mr. Chambers had the authority to
    stop the work and order the problem fixed.   According to Mr.
    Allen, provided he knew what safety measures were required, Mr.
    Chambers had the right to instruct Larmco personnel to implement
    those safety procedures for the scaffolding,
    Boller also argues that the responsibility for the
    prevention of accidents was passed on to Larmco under the terms
    of its contract with Larmco.   Under the Boller/Larmco contract,
    Larmco assumed the same duties toward Boller which Boller assumed
    toward the school district.    However, given the evidence in this
    38
    Nos. 1-08-3622 & 3635 Cons.
    case, whether Boller actually passed on the ultimate
    responsibility for the safety of the project site to Larmco was a
    question for the jury to resolve.
    ii. Notice
    The general contractor's knowledge, actual or constructive,
    of unsafe work methods or a dangerous condition is a precondition
    to direct liability.    Cochran, 
    358 Ill. App. 3d at 879-80
    .   In
    Cochran, the court upheld summary judgment for the general
    contractor where the evidence showed that the unsafe ladder setup
    was in existence for only an hour prior to the plaintiff's
    injury.   The court noted that none of the contractor's
    "'competent persons'" had observed the unsafe setup during that
    short period of time.   Cochran, 
    358 Ill. App. 3d at 880
    .
    Boller maintains that, because Mr. Chambers acknowledged he
    was unfamiliar with the Non-Stop scaffold and would not have
    known that the failure to place a straight brace at the top was a
    potential safety hazard, it cannot be held to have had actual or
    constructive knowledge of any safety hazard.   We disagree.
    Under the contract, Boller was required to furnish a
    "competent superintendent."    According to the plaintiff's expert,
    Mr. Burg, Mr. Chambers was not competent because he admitted that
    he was unfamiliar with the Non-Stop scaffold used by Larmco.    Mr.
    Burg explained that, while the general contractor was not
    39
    Nos. 1-08-3622 & 3635 Cons.
    expected to have substantive knowledge about every
    subcontractor's trade, to be competent, its superintendent needed
    to be able to ask the right questions to make sure the
    subcontractor was qualified and competent.   Mr. Rust, Boller's
    expert, agreed that the superintendent should be able to identify
    hazards or unsafe conditions in the scaffolding.
    On the morning of the accident, Mr. Chambers checked the
    scaffold around 6:30 a.m. and observed nothing wrong with it.
    Although he was in charge of safety and preventing accidents at
    the project site, Mr. Chambers lacked the training and experience
    to recognize a problem with the scaffold.    Sometime thereafter,
    the scaffold was extended without placing the straight brace at
    the top.   Around 1 p.m., Mr. Chambers again looked at the
    scaffolding, but he failed to observe that the scaffold had been
    extended and did not check to see if a reinspection of the
    scaffold had been made after the extension had been added.   The
    plaintiff's accident happened about an hour later.   Thus, there
    was evidence that Boller should have known that the scaffold
    presented a safety hazard.
    We conclude that the plaintiffs presented sufficient
    evidence to establish a prima facie case as to Boller's notice of
    a dangerous condition.   Therefore, the trial court did not err in
    denying Boller's motion for a directed verdict.
    40
    Nos. 1-08-3622 & 3635 Cons.
    2. Judgment n.o.v.
    a. Standard of Review
    "A trial court should enter a judgment non obstante
    veredicto (judgment n.o.v.) only if all the evidence, viewed in
    the light most favorable to the nonmoving party, so
    overwhelmingly favors the moving party that no contrary verdict
    could ever stand."   Check v. Clifford Chrysler-Plymouth of
    Buffalo Grove, Inc., 
    342 Ill. App. 3d 150
    , 156, 
    794 N.E.2d 829
    (2003).   This court reviews whether the trial court met that
    standard de novo.    Check, 
    342 Ill. App. 3d at 156
    .
    b. Discussion
    Our supreme court has held that "a judgment n.o.v. may not
    be granted merely because a verdict is against the manifest
    weight of the evidence."     Maple, 
    151 Ill. 2d at 453
    .   In ruling
    on a motion for a judgment n.o.v., the trial court "does not
    weigh the evidence, nor is it concerned with the credibility of
    the witnesses; rather it may only consider the evidence, and any
    inferences therefrom, in the light most favorable to the party
    resisting the motion."     Maple, 
    151 Ill. 2d at 453
    .   "[I]f there
    is any evidence, together with reasonable inferences to be drawn
    therefrom, demonstrating a substantial factual dispute, or where
    the assessment of credibility of the witnesses or the
    determination regarding conflicting evidence is decisive to the
    41
    Nos. 1-08-3622 & 3635 Cons.
    outcome," the trial court has no right to enter a judgment n.o.v.
    Maple, 
    151 Ill. 2d at 454
    .
    In this case, the jury heard conflicting testimony relating
    to the necessity of straight braces at the top of the scaffold.
    The expert witnesses for the plaintiffs and Boller presented
    conflicting testimony as to the control exercised by Boller over
    the project and as to the competency of Mr. Chambers and Mr.
    Allen.   The verdict as to liability in this case was based on the
    jury's resolution of these conflicts in the evidence.   Therefore,
    the trial court did not err in denying Boller's motion for a
    judgment n.o.v.
    3. Section 343 Liability
    Because we have determined that Boller was liable under
    section 414 of the Restatement (Second) of Torts, we need not
    address its liability under section 343 of the Restatement
    (Second) of Torts.
    B. Jury Instructions
    Boller contends that it is entitled to a new trial because
    the IPI construction negligence instructions given to the jury
    did not set forth an accurate statement of the law.   It argues
    that the trial court erred by rejecting the non-IPI instructions
    it tendered.
    1. Standard of Review
    42
    Nos. 1-08-3622 & 3635 Cons.
    In Barth v. State Farm Fire & Casualty Co., 
    228 Ill. 2d 163
    ,
    
    886 N.E.2d 976
     (2008), our supreme court held that when the issue
    is whether jury instructions accurately reflect the applicable
    law, the court's review is de novo.     Barth, 
    228 Ill. 2d at 170
    .
    2. Discussion
    Boller proposed to modify Illinois Pattern Jury
    Instructions, Civil, No. 55.01 (2006) (hereafter IPI Civil (2006)
    No. 55.01) as follows:
    "One who entrusts work to an independent contractor but
    who retained some control over the manner in which the work
    is done owes a duty to exercise reasonable care with respect
    to its retained control.
    One who retained some control over the manner in which
    the work is done can be liable for injuries resulting from
    the work if the injuries were proximately caused by the
    failure to exercise that control with ordinary care."
    The trial court rejected the modified instruction, and the jury
    was instructed as follows:
    "A contractor who entrusts work to a subcontractor can
    be liable for injuries resulting from the work if the
    contractor retained some control over the safety of the work
    and the injuries were proximately caused by the contractor's
    failure to exercise that control with ordinary care."    IPI
    43
    Nos. 1-08-3622 & 3635 Cons.
    Civil (2006) No. 55.01.
    Boller tendered a modified IPI Civil (2006) No. 55.02, which
    read as follows:
    "A party who retained some control over the manner in
    which the work is done, has a duty to exercise that control
    with ordinary care.
    When I use the words, 'retained control' the party
    must have retained at least some degree of control over the
    manner in which the work is done.    To be liable, a party
    must have more than a general right to order the work
    stopped or resumed, to inspect its progress or to receive
    reports, to make suggestions or recommendations which need
    not necessarily be followed, or to prescribe alterations and
    deviations.   There must be such a retention of a right of
    supervision that the contractor is not entirely free to do
    the work his own way."
    The trial court refused Boller's modified IPI Civil (2006)
    No. 55.02 instruction.     The court did modify the first sentence
    of the IPI instruction.    The instruction the jury received read
    as follows:
    "A party who retained some control over the safety
    and/or the manner in which the work is done has a duty to
    exercise that control with ordinary care."
    44
    Nos. 1-08-3622 & 3635 Cons.
    The trial court rejected Boller's proposed issues
    instruction.    Over its objection, the jury received IPI Civil
    (2006) No. 55.03, which in pertinent part stated as follows:
    "Plaintiffs Jose and Maria Diaz seek to recover damages
    from the Defendant Boller Construction Co.    In order for
    Jose and Maria Diaz to recover, they have the burden of
    proving:
    1. Defendant Boller Construction Co., retained some
    control over the safety of the work ***."
    Finally, over Boller's objection, the jury received IPI
    Civil (2006) No. 55.04, which read as follows:
    "One or more persons may have some control over the
    safety of the work.    Which person or persons had some
    control over the work under the particular facts of this
    case is for you to decide."
    Boller maintains that the IPI construction negligence
    instructions did not accurately state the law because they failed
    to qualify the term "some control over the work."    This court
    rejected the same argument in Jones.
    In Jones, the contractor tendered modified IPI construction
    negligence instructions similar to the ones tendered by Boller in
    this case.    The trial court refused to instruct the jury with the
    modified instructions.     On appeal, the contractor argued that the
    45
    Nos. 1-08-3622 & 3635 Cons.
    patterned instructions did not accurately reflect the law based
    on the decision in Martens v. MCL Construction Corp., 
    347 Ill. App. 3d 303
    , 
    807 N.E.2d 480
     (2004).    In Martens, this court
    rejected the holding in Moss v. Rowe Construction Co., 
    344 Ill. App. 3d 772
    , 
    801 N.E.2d 612
     (2003), that the central issue was
    the contractor's ability to control the safety of the project.
    Instead, the court in Martens held that "'[t]he central issue is
    retained control of the independent contractors's work, whether
    contractual, supervisory, operational, or some mix thereof.     The
    party who retains control is the logical party upon whom to
    impose the duty to ensure worker safety.'"    Jones, 381 Ill. App.
    3d at 37, quoting Martens, 
    347 Ill. App. 3d at 318
    .
    In Jones, this court pointed out that, despite its holding,
    the court in Martens referred to IPI Civil (2005) No. 55.02
    without criticism.   In Martens, there was no evidence that the
    mere existence of the safety program   affected the contractor's
    means and methods of doing his work.   However, in Jones, the
    general contractor could require compliance with its safety
    standards and stop the work if the subcontractor's employees were
    violating its safety rules.   Jones, 381 Ill. App. 3d at 38.
    While maintaining a general right to safety would not be
    sufficient under Martens, in this case, as in Jones, Boller had
    the right to stop the work if Larmco was doing work in an unsafe
    46
    Nos. 1-08-3622 & 3635 Cons.
    manner.
    We conclude that the IPI construction negligence
    instructions continue to reflect an accurate statement of the
    law.    Moreover, Boller's proposed instructions were premised on
    vicarious liability.    The jury found Boller directly liable.    As
    the jury was properly instructed, Boller is not entitled to a new
    trial.
    C. Trial Court Errors
    Boller contends that trial court errors, either individually
    or cumulatively, require that it receive a new trial.
    1. Standard of Review
    The trial court's evidentiary rulings are reviewed under the
    abuse of discretion standard.    Jones, 381 Ill. App. 3d at 34.
    2. Discussion
    a. Failure to Allow Cross-examination as an Adverse Witness
    Boller contends that the trial court erred when it refused
    to allow it to cross-examine as adverse witnesses, William
    Hickey, Edward Allen, Miroslaw Kundzicz, Francesco Gutierrez and
    Miguel Diaz.
    With the exception of Mr. Hickey's testimony, Boller failed
    to provide citations to the record where it was denied the
    opportunity to cross-examine the above witnesses and failed to
    provide argument on the issue.    Boller merely states that it was
    47
    Nos. 1-08-3622 & 3635 Cons.
    prejudiced.   Supreme Court Rule 341(h)(7) requires citation to
    the pages of the record where the denial took place, as well as
    argument in support of the issue.     210 Ill. 2d R. 341(h)(7).
    Failure to comply with our supreme court rules is grounds for
    disregarding the argument on appeal.     Burmac Metal Finishing Co.
    v. West Bend Mutual Insurance Co., 
    356 Ill. App. 3d 471
    , 
    825 N.E.2d 1246
     (2005).
    Boller does argue that it should have been permitted to
    cross-examine Mr. Hickey as an adverse witness pursuant to
    section 2-1102 of the Code of Civil Procedure.     735 ILCS 5/2-1102
    (West 2008) (allowing officers, directors, managing agents or
    foreman of any party to the action to be cross-examined).     While
    Mr. Hickey had been an employee and part owner of Larmco, at the
    time of trial, he had been retired for three years.     See Bassett
    v. Burlington Northern R.R. Co., 
    131 Ill. App. 3d 807
    , 
    476 N.E.2d 31
     (1985) (section 2-1101 requires that the witness be in a
    supervisory position with the opposing party at the time the
    witness is called to testify).
    Fornoff v. Parke Davis & Co., 
    105 Ill. App. 3d 681
    , 
    434 N.E.2d 793
     (1982), relied on by Boller, is distinguishable.       In
    that case, the reviewing court held that no showing of adversity
    was required before a codefendant could examine another
    codefendant as an adverse witness.     The fact that it was to each
    48
    Nos. 1-08-3622 & 3635 Cons.
    codefendant's advantage to shift the liability was considered
    sufficient adversity by the court to allow one codefendant to
    call and cross-examine another codefendant.    Fornoff, 
    105 Ill. App. 3d at 690
    .   In this case, Mr. Hickey was not a codefendant.
    We conclude that the trial court did not abuse its
    discretion when it denied Boller's request to examine Mr. Hickey
    as an adverse witness.   We further conclude that the issue is
    waived as to the remaining witnesses specified by Boller.
    b. Mention of Workers' Compensation/Insurance
    During direct examination, Mr. Diaz was questioned as follows:
    "When you were going to the clinic, did Larmco have a
    nurse who was following - -"
    Larmco's attorney objected based on a motion in limine barring
    reference to Mr. Diaz's workers' compensation case.   The objection
    was sustained. The trial court advised the plaintiffs' attorney to
    instruct Mr. Diaz not to refer to workers' compensation.
    Later during direct examination, Mr. Diaz was questioned about
    his November 2002, examination by Dr. Shenker.    When asked if the
    doctor prescribed any treatment, the plaintiff testified:
    "No.    The only thing he said at that time was that he
    didn't know that he would give a report to the company or the
    insurance.   I don't know.   But that's all he told me."
    The trial court denied Larmco's attorney's request to be heard but
    49
    Nos. 1-08-3622 & 3635 Cons.
    instructed the jury to disregard the last portion of Mr. Diaz's
    response and ordered the questioning to continue.
    During a break in Mr. Diaz's testimony, Larmco moved for a
    mistrial based on Mr. Diaz's references to insurance and workers'
    compensation.   The trial court found that the reference was
    unintentional and denied the motion.
    Not every mention of insurance in a personal injury trial
    requires the court to declare a mistrial.     Neyzelman v. Treitman,
    
    273 Ill. App. 3d 511
    , 515, 
    652 N.E.2d 1300
     (1995).   "A reference to
    insurance is only prejudicial if it directly indicates that the
    defendant is insured [citation] or if it is the product of conduct
    by counsel intended to influence or prejudice the jury [citation]."
    Neyzelman, 
    273 Ill. App. 3d at 515
    .    Neither of those instances is
    present in this case.   Moreover, the trial court instructed the
    jury to disregard the reference to insurance.        In general, the
    prejudicial impact of a remark may be cured if the trial court
    sustains the objection and instructs the jury to disregard the
    objectionable testimony.   See Nickon v. City of Princeton, 
    376 Ill. App. 3d 1095
    , 
    877 N.E.2d 776
     (2007).
    We conclude that Boller was not prejudiced by the reference to
    workers' compensation and insurance.
    c. Closing Argument
    50
    Nos. 1-08-3622 & 3635 Cons.
    Boller contends that the following remark by the plaintiffs'
    attorney during closing argument required that the trial court
    declare a mistrial.
    During closing argument, the plaintiff's attorney stated as
    follows:
    "I would also like to suggest to you in using your common
    sense and ordinary experience in the affairs of life that when
    Mr. Daley [Boller's attorney] cross-examined Mr. Allen and
    then Mr. Gutierrez, I think your common sense should tell you
    and probably does tell you that this is a team effort."
    The trial court sustained Boller's objection.
    At the conclusion of the plaintiffs' closing argument, Boller
    made a motion for a mistrial; Larmco joined in the motion.    While
    the trial court agreed the remark was improper, it found no
    prejudice and denied the motion.
    In his rebuttal argument, the plaintiffs' attorney stated:
    "It's Boller who brought Larmco into this case, not the Diaz'.
    But you could never tell that from what's happened in this
    courtroom over the last two weeks because there's a love fest
    between those two."
    The trial court sustained Larmco's objection.
    Improper comments at closing do not constitute reversible
    error unless they result in substantial prejudice to the party.
    51
    Nos. 1-08-3622 & 3635 Cons.
    Tierney v. Community Memorial General Hospital, 
    268 Ill. App. 3d 1050
    , 1061,   
    645 N.E.2d 284
       (1994).   Counsel    is   allowed   broad
    latitude in drawing reasonable inferences and conclusions from the
    evidence.   Tierney, 268 Ill. App. 3d at 1061.          The trial court's
    ruling on whether counsel has stayed within the bounds of proper
    argument will not be reversed absent a clear abuse of discretion.
    Tierney, 268 Ill. App. 3d at 1061; but see People v. Wheeler, 
    226 Ill. 2d 92
    , 
    871 N.E.2d 728
     (2007) (court now applies de novo review
    to whether remarks in closing argument require a new trial for a
    criminal defendant).
    While discussing Mr. Allen's testimony with the parties'
    attorneys, the trial court expressed concern that the jury might be
    confused. The court stated to Boller's and Larmco's attorneys that
    "it really looks like you're bootstrapping each other's cases and
    it's two on one in there."     Therefore, the plaintiffs' attorney's
    argument could be construed as reasonable comments on how Boller
    and Larmco were conducting their respective defenses in this case.
    Even if the remarks were error, a new trial will not be
    granted unless the remarks are clearly improper, prejudicial and
    denied the party a fair trial when the trial is viewed in its
    entirety.   Tierney, 268 Ill. App. 3d at 1061.         While Boller claims
    it was prejudiced, there is no indication that the jury's verdict
    against Boller was in any way influenced by the two comments by the
    52
    Nos. 1-08-3622 & 3635 Cons.
    plaintiffs' attorney.    The trial court did sustain the objection,
    and the jury was properly instructed as to the purpose of closing
    arguments.   We conclude that the denial of Boller's motion for a
    mistrial was not an abuse of discretion.
    Finally, Boller maintains that the cumulative effect of these
    errors require that it receive a new trial.       Boller's reliance on
    Christou v. Arlington Park-Washington Park Race Tracks Corp., 
    104 Ill. App. 3d 257
    , 
    432 N.E.2d 920
     (1982) is misplaced.         In that
    case, the reviewing court held that cumulative effect of trial
    court errors and the introduction of improper evidence of damages
    amounted to prejudicial error requiring a new trial. Christou, 
    104 Ill. App. 3d at 260-61
    .      In the present case, there was no error
    with regard to the denial of cross-examination.       As to the other
    alleged errors, Boller suffered no prejudice from the mention of
    workers' compensation, insurance or from the plaintiffs' closing
    argument. Therefore, whether these errors are considered singly or
    cumulatively,   Boller was not denied a fair trial.
    D. Dismissal of Third Party Complaint
    1.   Standard of Review
    The court reviews the granting of a section 2-619 motion to
    dismiss de novo.     Westmeyer v. Flynn, 
    382 Ill. App. 3d 952
    , 
    889 N.E.2d 671
     (2008).
    2. Discussion
    53
    Nos. 1-08-3622 & 3635 Cons.
    Boller contends that the trial court erred in dismissing its
    third-party   complaint   for   contribution   against   Larmco.   Boller
    points out that the dismissal of its complaint against Larmco for
    contribution renders it responsible for the entire judgment amount
    of $1,076,270.06.   That amount exceeds the $1 million amount of
    insurance coverage Larmco was required to provide Boller under the
    terms of their contract.        Larmco responds that by agreeing that
    Larmco would provide insurance for Boller, the parties intended
    that they would look only to the insurance and not impose
    liability on each other.        Larmco relies on the rule stated in
    Briseno v. Chicago Union Station Co., 
    197 Ill. App. 3d 902
    , 
    557 N.E.2d 196
     (1990), that where the parties agree that insurance will
    be provided as part of their contract, the contract must be
    interpreted as providing mutual exculpation to the bargaining
    parties.   Briseno, 
    197 Ill. App. 3d at 905
    .
    Briseno is distinguishable from the present case.        There,
    the reviewing court ruled that the third-party contribution action
    was properly dismissed where the parties' liability had been
    determined and satisfied from the proceeds of the insurance policy.
    Briseno, 
    197 Ill. App. 3d at 906
    .        The dispositive issue in cases
    involving the purchase of insurance in the context of contractor
    indemnification is the status of the underlying suit: "whether a
    settlement or judgment within the policy's limits was reached
    54
    Nos. 1-08-3622 & 3635 Cons.
    and fully funded by the insurer."      Kehoe v. Commonwealth Edison
    Co., 
    296 Ill. App. 3d 584
    , 588, 
    694 N.E.2d 1119
     (1998).
    In Kirincich v. Jimi Construction Co., 
    267 Ill. App. 3d 51
    ,
    
    640 N.E.2d 958
     (1994), the reviewing court held that the contractor
    could pursue its contribution action against the subcontractor for
    the amount that was not covered by insurance.    Kirincich, 
    267 Ill. App. 3d at 55
    .      The court noted that the cases holding that
    contribution was barred by the rule of mutual exculpation arose in
    a factual context where the parties' joint insurance had absorbed
    the entire liability of the party seeking contribution. "Where the
    joint insurance policy has not fully protected one of the parties
    against liability, contribution should be allowed to the extent of
    the party's actual loss."     Kirincich, 
    267 Ill. App. 3d at 55
    .
    Under the Boller/Larmco contract, Lamarco was required to
    "indemnify and hold harmless [Boller] from and against all claims,
    damages, loss, and expenses" in connection with the performance
    of Larmco's work.   Larmco provided $1 million in initial coverage
    to Boller.   Following the granting of the remittitur and other
    credits, the verdict for the plaintiffs totaled $1,076,770.06.
    Since the insurance funds did not completely indemnify Boller,
    the trial court erred in granting the dismissal of the contribution
    action.
    II. Plaintiffs' Appeal and Cross-Appeal
    55
    Nos. 1-08-3622 & 3635 Cons.
    The plaintiffs originally appealed from the denial of their
    motion to adjudicate Larmco's workers' compensation lien.           After
    Boller filed its appeal, the plaintiffs filed a cross-appeal from
    the grant of the remittitur.     If the   trial court erred in granting
    the remittitur, we need not address the issue of the adjudication
    of the workers' compensation lien.        Therefore, we will address
    first the cross-appeal issue of the granting of the remittitur.
    A. Grant of the Remittitur
    The plaintiffs contend that the trial court erred in granting
    the remittitur.      The trial court granted Boller's motion for a
    remittitur, stating as follows:
    "After reviewing the testimony of Dr. Skeletsky, it is
    the   court's    position   that   this   testimony   was   based   on
    speculation, relative to the potential future surgery, and
    further, that the court erred in allowing sanctity [sic]
    presented to the jury.
    The calculations of $100,000 for future surgery,
    [illegible] for potential future hospitalization, and $26,000
    for potential physical therapy costs were inappropriately
    allowed to present it to the jury.        This total is $201,000."
    After allowing other setoffs and credits, the court offered the
    plaintiffs the choice of a new trial or a reduction in the judgment
    by $217,604.94.      The plaintiffs accepted the remittitur.
    56
    Nos. 1-08-3622 & 3635 Cons.
    1.     Procedural Bar to the Plaintiffs' Appeal
    Supreme Court Rule 366 provides in pertinent part that
    "[c]onsenting to a remittitur as a condition to the denial of a new
    trial does not preclude the consenting party from asserting on
    appeal that the amount of the verdict was proper.      No cross-appeal
    is required."    155 Ill. 2d R. 366(b)(2)(ii).    However, "a party who
    consents to a remittitur is bound thereby and is precluded from
    appealing the entry of the remittitur unless the opposing party
    appeals from the judgment."     Haid v. Tingle, 
    219 Ill. App. 3d 406
    ,
    415, 
    579 N.E.2d 913
     (1991), citing Anderson v. Greyhound Lines,
    Inc., 
    34 Ill. App. 3d 643
    , 
    339 N.E.2d 465
     (1975).
    Boller maintains that the plaintiffs are procedurally barred
    from raising the remittitur issue because they filed a notice of
    appeal from the judgment.     The plaintiffs' appeal raised only the
    adjudication of Larmco's workers' compensation lien.       It was
    only after Boller filed its notice of appeal from the judgment that
    the plaintiffs' filed a cross-appeal raising the issue of the
    remittitur.    Therefore, the plaintiffs are not procedurally barred
    from raising the issue of granting of the remittitur on appeal.
    2.   Standard of Review
    A ruling on a motion for a remittitur is reviewed for an abuse
    of discretion.    See Kindernay v. Hillsboro Area Hospital, 
    366 Ill. App. 3d 559
    , 572, 
    851 N.E.2d 866
     (2006).
    57
    Nos. 1-08-3622 & 3635 Cons.
    3. Discussion
    The trial court granted the remittitur after it ruled that Dr.
    Skaletsky's     testimony     as    to     future    medical       costs   had    been
    improperly admitted into evidence.                We first address whether the
    trial court abused its discretion when it ruled Dr. Skaletsky's
    testimony    was     inadmissible.        Jones,    381     Ill.   App.    3d    at    34
    (evidentiary rulings are reviewed for an abuse of discretion).
    a. Striking of Dr. Skaletsky's Testimony
    The plaintiffs contend that the trial court erred in striking
    Dr. Skaletsky's testimony as to the costs of Mr. Diaz's future
    treatment.      Boller responds that striking of this testimony was
    proper because Dr. Skaletsky could not testify within a reasonable
    degree of     certainty    that     Mr.    Diaz     would    require    surgery       and
    physical therapy in the future.
    Possible future damages are not recoverable by the plaintiff
    unless   they    are    reasonably       certain     to     follow.    Terracina       v.
    Castelli, 
    80 Ill. App. 3d 475
    , 480, 
    400 N.E.2d 27
     (1979).                   Evidence
    as to damages which is speculative, remote or based upon mere
    probability is improper.             Terracina, 
    80 Ill. App. 3d at 480
    .
    "'Expert testimony is admissible or required as evidence of the
    certainty of the need and as to the reasonable value of the
    services to     be     rendered.'"    Biehler       v.    White    Metal   Rolling      &
    Stamping Corp., 
    30 Ill. App. 3d 435
    , 445, 
    333 N.E.2d 716
     (1975),
    58
    Nos. 1-08-3622 & 3635 Cons.
    quoting 22 Am. Jur. 2d Damages §312 (1965).
    In Terracina, the reviewing court upheld the striking of a
    doctor's testimony that further surgery for the plaintiff was
    possible. Noting that future consequences must be reasonably
    certain to follow, the court stated as follows:
    "Here, the question did not call for an opinion based upon a
    reasonable degree of medical certainty nor did the answer
    indicate that future surgery was reasonably certain to follow.
    Rather, in response to the question, '[I]n your opinion based
    on the hypothetical question previously asked of you, do you
    believe that Mr. Terracina is a candidate for future surgery?'
    Dr. Moody replied, 'It's possible.'        Accordingly, we believe
    that   the   court   properly   struck   this   testimony   as   being
    speculative."    Terracina, 
    80 Ill. App. 3d at 480
    .
    The plaintiffs rely on Jeffers v. Weinger, 
    132 Ill. App. 3d 877
    , 
    477 N.E.2d 1270
     (1985).     In Jeffers, the doctor testified
    that it was possible the plaintiff might lose her foot as a
    result of the defendant's malpractice.        On cross-examination,
    the doctor testified that the possibility that the plaintiff
    might lose her foot was less than 1%.         The reviewing court found
    that the doctor's testimony should be considered by the jury
    because, regardless of the percentage number, the possibility
    remained that the plaintiff would suffer the loss of her foot.
    59
    Nos. 1-08-3622 & 3635 Cons.
    Jeffers, 
    132 Ill. App. 3d at 884
    .
    In the present case, Dr. Skaletsky was not testifying as to a
    possible consequence flowing from the negligence in this case based
    on his expertise.   Instead, he was asked to predict what treatment
    course Mr. Diaz would follow, which was dependant on future test
    results and Mr. Diaz's own decisions as to the treatment.        Dr.
    Skaletsky's testimony did not rise to the "strong possibility" for
    the need of future treatment testified to by the doctor in Zitzmann
    v. Miller, 
    194 Ill. App. 3d 477
    , 484, 
    551 N.E.2d 707
     (1990).
    The plaintiff also relies on Kamp v. Preis, 
    332 Ill. App. 3d 1115
    , 
    774 N.E.2d 865
     (2002).   In that case, the court held that as
    long as the increased risk of future injury is proven within a
    reasonable degree of medical certainty, evidence of future
    damages is not speculative.    Kamp, 
    332 Ill. App. 3d at 1121
    .
    While Dr. Skaletsky did testify that Mr. Diaz was subject to the
    risk of future injury, his testimony as to the costs of future
    surgery and physical therapy was not related to the risk of
    future injury.
    We conclude that Dr. Skaletsky's testimony as to the costs
    for surgery, hospitalization and physical therapy Mr. Diaz might
    undergo in future was properly stricken as speculative.
    b. Evidence of Mr. Diaz's Need for Future Medical Care
    Even without Dr. Skaletsky's testimony, the plaintiffs
    60
    Nos. 1-08-3622 & 3635 Cons.
    maintain that other evidence supported the jury's award of future
    medical expenses.       Our supreme court has observed that "[w]hen
    reviewing an award of compensatory damages for a nonfatal injury,
    a court may consider, among other things, the permanency of the
    plaintiff's condition, the possibility of future deterioration,
    the extent of the plaintiff's medical expenses, and the
    restrictions imposed on the plaintiff by the injuries."
    Richardson v. Chapman, 
    175 Ill. 2d 98
    , 113-14, 
    676 N.E.2d 621
    (1997).
    Even without the evidence as to the costs of future
    treatments,   the   medical   evidence   established   that   Mr.   Diaz's
    condition was permanent and that he was at risk for further injury.
    While the evidence showed that none of the treatments he had
    undergone so far had been successful, the evidence did not indicate
    that there was nothing further the doctors could do for him.         Apart
    from   the   stricken   portion   regarding   costs,   Dr.    Skaletsky's
    testimony indicated that there was an ongoing treatment plan for
    Mr. Diaz.
    As our supreme court observed in Richardson, "[t]he
    determination of damages is a question reserved to the trier of
    fact, and a reviewing court will not lightly substitute its
    opinion for the judgment rendered in the trial court."
    Richardson, 
    175 Ill. 2d at 113
    .     "A verdict will not be set aside
    61
    Nos. 1-08-3622 & 3635 Cons.
    by a court unless it is so excessive that it indicates that the
    jury was moved by passion or prejudice or unless it exceeds the
    necessarily flexible limits of fair and reasonable compensation or
    is so large that it shocks the judicial conscience."    Kindernay,
    366 Ill. App. 3d at 572.   A remittitur should not be granted if
    the jury's award falls within the flexible range of conclusions
    reasonably supported by the evidence.   Kindernay, 366 Ill. App.
    3d at 572.
    We conclude that the trial court abused its discretion in
    granting a remittitur in the amount of costs for future treatment
    testified to by Dr. Skaletsky.   The evidence established that Mr.
    Diaz's condition was permanent and that he remained at risk for
    future injury.   The evidence further established that he continued
    to experience pain and loss of strength and that there were further
    treatments available to give him some relief.   It was, therefore,
    reasonable inference from the evidence that Mr. Diaz will
    continue to incur medical and medically-related expenses for pain
    relief and to help him cope with the restrictions imposed on him
    as a result of his injuries.   Given that his past medical bills
    were $132,000 for the 6 years between his accident and the trial
    in this case and that his life expectancy was 21 years, an award
    of $201,000 for future medical expenses was supported by the
    evidence.
    62
    Nos. 1-08-3622 & 3635 Cons.
    B. Adjudication of Workers' Compensation Lien
    In their appeal, the plaintiffs contend that the trial court
    erred when it denied their motion to reduce Larmco's workers'
    compensation   lien   rights   to   zero   based   on   granting   of   the
    remittitur.    As we have determined that the granting of the
    remittitur was error, we need not address this issue.
    III. Conclusion
    The jury's verdict as to liability is affirmed.         The
    dismissal of Boller's third-party complaint is reversed, and the
    cause is remanded for further proceedings.         On remand, the trial
    court is directed to vacate $201,000 of the remittitur and enter
    judgment in favor of the plaintiffs in the amount awarded by the
    jury, minus the reductions not contested in this appeal.
    Affirmed in part and reversed in part; cause remanded with
    directions.
    GARCIA and LAMPKIN, JJ., concur.
    63