Department of Transportation v. Dalzell , 2018 IL App (2d) 1160911 ( 2018 )


Menu:
  •                                                                             Digitally signed by
    Reporter of Decisions
    Reason: I attest to the
    Illinois Official Reports                       accuracy and
    integrity of this
    document
    Appellate Court                          Date: 2018.03.14
    13:36:33 -05'00'
    Department of Transportation v. Dalzell, 
    2018 IL App (2d) 160911
    Appellate Court        THE DEPARTMENT OF TRANSPORTATION, Plaintiff and
    Caption                Counterdefendant-Appellant, v. DARLENE M. DALZELL, as
    Trustee Under Declaration of Trust Dated December 12, 1990;
    RONALD L. DALZELL, as Trustee Under Declaration of Trust
    Dated December 12, 1990; UNKNOWN OWNERS; and
    NONRECORD CLAIMANTS, Defendants (Ronald L. Dalzell, as
    Trustee Under Declaration of Trust Dated December 12, 1990,
    Defendant and Counterplaintiff-Appellee).
    District & No.         Second District
    Docket No. 2-16-0911
    Filed                  January 31, 2018
    Decision Under         Appeal from the Circuit Court of Du Page County, No. 10-ED-127;
    Review                 the Hon. Dorothy French Mallen, Judge, presiding.
    Judgment               Affirmed.
    Counsel on             Lisa Madigan, Attorney General (Nadine J. Wichern, Assistant
    Appeal                 Attorney General, of counsel), and Todd L. Lindquist, Special
    Assistant Attorney General, both of Chicago, for appellant.
    Bryan P. Lynch, of Law Office of Bryan P. Lynch, P.C., of Chicago,
    for appellees.
    Panel                     JUSTICE JORGENSEN delivered the judgment of the court, with
    opinion.
    Justices Zenoff and Birkett concurred in the judgment and opinion.
    OPINION
    ¶1          Plaintiff, the Illinois Department of Transportation (IDOT), brought a condemnation action
    under the Eminent Domain Act (Act) (735 ILCS 30/1-1-1 et seq. (West 2008)) and the Illinois
    Highway Code (605 ILCS 5/4-501 et seq. (West 2008)) to acquire property owned by
    defendants, Darlene M. and Ronald L. Dalzell, as trustees under a declaration of trust dated
    December 12, 1990.1 Dalzell filed a counterclaim seeking compensation for damage to the
    remainder (i.e., the part of his property not taken). After trial, the jury found that the just
    compensation due to Dalzell totaled $247,000, comprised of (1) $23,000 for the taking of
    parcel No. 1EA0014, (2) $220,000 for damage to the remainder, and (3) $4000 for damage to
    the property within and outside of a temporary-easement strip on parcel No. 1EA0014TE. The
    trial court denied IDOT’s motion for a new trial.
    ¶2          IDOT appeals, first raising issues concerning the court’s jurisdiction over certain claims
    for damages. Next, IDOT challenges numerous court rulings concerning the parties’ motions
    in limine as well as its decisions to permit or restrict certain testimony, limit cross-examination
    of a witness, and refuse certain jury instructions. Finally, IDOT asserts that Dalzell’s counsel’s
    opening and closing statements constituted plain error. IDOT requests a new trial. For the
    following reasons, we affirm.
    ¶3                                         I. BACKGROUND
    ¶4        Dalzell owns property on the northeast corner of North Avenue (also known as Route 64)
    and Powis Road in West Chicago. Since 1985, Dalzell has operated thereon a business, On Site
    Storage, for public rental of parking areas and storage of steel containers (ranging
    approximately 20 to 40 feet in length). Drivers could originally access Dalzell’s property via
    two driveways, one off North Avenue, which runs east-west, and the other off Powis Road,
    which runs north-south.
    ¶5        On December 14, 2010, to complete its public-works project of widening and resurfacing
    North Avenue, IDOT filed a complaint for condemnation of portions of Dalzell’s land.
    Specifically, IDOT wished to acquire two things:
    1. Fee-simple title to parcel No. 1EA0014. The parcel is roughly an L-shape, with
    the short arm near the southwest corner of the property (running parallel to North
    Avenue). The long arm extends along the west border of the property, on Powis Road.
    The area connecting the short arm to the long arm encompasses a triangular section of
    1
    Darlene passed away during the pendency of the litigation, and Ronald was substituted as the
    successor trustee of her trust. Accordingly, we refer to Dalzell, in the singular, in this opinion. In
    addition, we note that, on February 12, 2012, a default judgment was entered against any unknown
    owners and nonrecord claimants.
    -2-
    grass lawn. Included within the parcel taken, on the west border (or long arm), is a
    portion of the property’s Powis Road driveway.
    2. A temporary easement (for a period up to five years) on parcel No. 1EA0014TE.
    This easement is located directly east of the long arm of parcel No. 1EA0014, although
    it is shorter, and it includes a section of, and spans the width of, the Powis Road
    driveway.
    ¶6       Although slightly out of sequence chronologically, we note two additional aspects of the
    overall project to provide context for the issues and arguments. First, the project’s expansion of
    North Avenue elevated the stretch of highway directly in front of the property’s North Avenue
    driveway, and IDOT placed a concrete barrier there that closed that driveway. Second, a
    concrete median was ultimately placed in the middle of Powis Road such that the property’s
    Powis Road driveway became only a right-turn-in, right-turn-out access point. Collectively,
    the closure of the North Avenue driveway and the median barrier on Powis Road prevent
    drivers from exiting the property onto North Avenue; rather, drivers must exit onto Powis
    Road and drive 3.5 miles to return to North Avenue.
    ¶7                                        A. Quick-Take Hearing
    ¶8       Shortly after filing its complaint, in January 2011, IDOT moved for immediate possession
    and use of the two parcels, i.e., a “quick-take” motion under section 25-7-103.1 of the Act (735
    ILCS 30/25-7-103.1 (West 2010)), alleging that delay in acquiring the two parcels would set
    back the North Avenue improvement project. In response, Dalzell filed a “traverse and motion
    to dismiss,” arguing, in part, that IDOT did not have the requisite authority to acquire the
    property, the taking was not necessary, and the taking exceeded IDOT’s needs. An October 12,
    2011, order reflects, however, that, “in consideration of the parties’ agreement and the
    modification of the construction plans for Route 64, [Dalzell] withdraw[s] [his] Traverse and
    Motion to Dismiss.” Thereafter, on November 4, 2011, the parties entered into a stipulation
    that acknowledged both IDOT’s eminent-domain authority and the existence of reasonable
    necessity to take the property through “quick-take” proceedings. However, the parties agreed
    that their stipulation regarding the value of the two parcels would be “irrelevant to, separate
    from, independent of, and shall have no effect on, the issue of damages to the remainder due to
    the take.”
    ¶9       Therefore, at the quick-take hearing, testimony was received concerning the value of the
    remainder. Various appraisers testified, and notably, all acknowledged that the project would
    result in the closure of the North Avenue driveway. IDOT’s appraiser, Frances Lorenz, did not
    believe that the North Avenue driveway added value to the property and, thus, did not assess
    any reduction in value to the property from the driveway’s closure. Lorenz explained:
    “Q. You didn’t give any compensation for the North Avenue driveway; correct?
    A. That’s correct.
    Q. And why did you make reference to it in your report if you weren’t giving any
    compensation to Mr. Dalzell?
    A. I didn’t think it was appropriate to ignore it. It was a part of the taking, part of
    the improvement, and I thought that it was important to disclose in my report what’s
    going on.” (Emphasis added.)
    -3-
    Dalzell’s appraiser, Michael MaRous, did attribute the loss of the North Avenue driveway as
    an element of damages. He explained that the property would go from “two main driveways to
    one driveway that’s far inferior.” MaRous testified that, in the “before” state, both driveways
    were “absolutely” important to the property and that losing one driveway would be a material
    change to the site. MaRous testified that he knew of no appraisal practice that would ignore the
    closing of a driveway in a condemnation project. He explained that it is customary for any
    appraisal report to include the number of driveways or access points to the subject property.
    When asked why, in an appraisal concerning condemnation powers, he considers damages
    associated with closing a driveway, MaRous explained, “[b]ecause a driveway for most
    properties is a very important fact. It’s kind of like the main artery into a property, and it’s very
    critical and properties that have limited access generally have a direct reflection of a lower
    value.”
    ¶ 10        A few years later, on July 28, 2014, the parties entered into a three-part stipulation. First,
    they agreed that, as of the date of valuation in this case (i.e., December 14, 2010, when IDOT
    filed its condemnation complaint), the property had a right of access directly onto North
    Avenue. Second, they agreed that, as of the date of valuation, the “North Avenue driveway
    existed from North Avenue directly north to the subject property.” Third, and most relevant,
    they agreed that “[b]oth parties may present evidence at trial as to the subject property’s North
    Avenue driveway’s value based upon any issue of fact except as to the legality or illegality of
    the driveway.” (Emphases added.)
    ¶ 11        On December 3, 2014, Dalzell filed his counterclaim for damage to the remainder. The
    counterclaim noted that “the Remainder parcel is owned and used in common with the Part
    Taken and Easement Area” that IDOT acquired. It did not mention or specifically request
    damages for the closure of the North Avenue driveway.
    ¶ 12                   B. IDOT’s Motion In Limine No. 1: North Avenue Driveway
    ¶ 13        On March 4, 2016 (more than five years after the condemnation complaint was filed),
    IDOT filed numerous motions in limine, with motion No. 1 requesting that Dalzell’s appraisers
    be barred from considering the closure of the North Avenue driveway as an element of damage
    to the remainder. IDOT argued that such testimony would be improper because the closure was
    not a direct and proximate result of the taking and, therefore, any claim for damages based on
    that closure must be brought in the Illinois Court of Claims, which has exclusive jurisdiction
    over all claims against the State for damages in any case sounding in tort, if such a case would
    lie against a private person in a civil suit. 705 ILCS 505/8(d) (West 2008). IDOT noted that the
    taking itself did not physically touch the North Avenue driveway and that the property’s North
    Avenue access was instead altered by the overall construction project. IDOT argued that, “in
    order to claim damage to the remainder here as a result of the closure of the North Avenue
    access point in this circuit court action, the damage must be a direct and proximate result of the
    taking of parcel Nos. 1EA0014 and 1EA0014TE and not merely as a result of [IDOT’s] total
    construction plan and construction of North Avenue or of construction in [the] general area.”
    In sum, IDOT argued that the trial court lacked jurisdiction over damages claims concerning
    the North Avenue driveway, and it therefore asked that Dalzell’s appraisers be barred from
    considering the closure of the driveway in formulating their damage-to-the-remainder
    opinions.
    -4-
    ¶ 14       On March 18, 2016, after hearing oral argument, the court denied the motion. Noting that
    the constitution provides that private property may not be taken or damaged for public use
    without just compensation, the court framed the issue as follows: whether, when arriving at an
    opinion of the fair market value of the property after the taking occurred, an appraiser could
    consider the closure of access, even though the taking did not physically touch the closure and
    the closure resulted from the construction project. The court agreed with IDOT that, if the
    taking had nothing to do with the closure of the North Avenue driveway, any claims for
    damages concerning the closure would be exclusive to the court of claims:
    “But I think that the closing of the North Avenue driveway in this case does impact
    the value of the property, in light of the change in the access at Powis Road, which was
    the taking. So I agree with [Dalzell’s counsel] that this is interrelated, and the decrease
    in value in the after is directly related to the taking.
    And you―I don’t see how you can take out the closure of the North Avenue
    driveway, because if the North Avenue access point was still open, then the
    right-in/right-out of Powis Road wouldn’t matter. It wouldn’t decrease the value of the
    property at all, because you can get in and out North Avenue.
    But you can’t get in and out at North Avenue, and so the appraisers, I think, have to
    consider the impact of the taking as a whole, which would include the closing of North
    Avenue to arrive at a fair market value in the after.
    *** [T]he fair market value of this property in the after[,] in order to arrive at the
    figure[,] you cannot ignore the closing of the North Avenue access. It has to be part of
    the consideration. *** [I]t’s directly related to the taking and the change in the access
    at Powis Road.” (Emphases added.)
    ¶ 15       In response to questions from IDOT, the court explained that Dalzell could not request
    damages as a result of the closure of the North Avenue driveway. Rather, Dalzell could request
    that the jury consider the difference between the property’s value before and after the taking,
    and part of that difference might be based on the driveway’s closure. IDOT asked whether the
    jury would receive an instruction that it could not award damages for the closure, and the court
    responded that it was not going to instruct the jury on all things for which it could not award
    damages. Rather, the jury would be told what it could consider and that it would be tasked with
    awarding the difference between the fair market value before and after the taking. Further, the
    court reiterated that the appraisers would not be permitted to testify as to damages in a specific
    amount attributable to the closure but, instead, as to:
    “[T]heir opinion based on a reasonable degree of appraisal certainty that the before
    market value is X and the subsequent fair market value is Y. And then I base my
    opinion on these comparables, and I base my opinion on this situation and that
    situation, one of which is going to be the fact that you can only go right in and right out
    of the Powis driveway, which really wouldn’t have had much of an impact if they still
    had this North Avenue entrance.
    But since they don’t have the North Avenue entrance anymore, this has been a huge
    impact to the value of the property. There will be no amount assigned as damages for
    the closure of North Avenue.”
    ¶ 16       The court summarized its ruling:
    -5-
    “I actually agree with both of your positions, and I agree with [IDOT] that if they’re
    seeking damages for the closure of access to North Avenue they’ve got to go to the
    Court of Claims. If they’re seeking the fair compensation between the value of the
    property before and the value of the property in the after *** I just don’t see how an
    appraiser cannot include a factor that actually exists. I don’t know how they do that,
    and that’s why I say it’s interrelated. And the fair market value in the after is directly a
    result of the taking, and that’s why it can be considered by [the] appraisers.”
    ¶ 17        IDOT moved for reconsideration. IDOT first purported to provide a comprehensive review
    of eminent-domain precedent establishing that claims of impaired access belong in the court of
    claims and that, therefore, Dalzell could not seek damages in the trial court for the closure of
    the North Avenue driveway, which was not part of the taking. As to the court’s concern about
    how the appraisers could value the property after the taking without considering the closure,
    IDOT asserted, for the first time, that the appraisers must value the property after the taking as
    though the driveway remained open. Specifically, IDOT noted that the driveway was not
    physically closed until January 20, 2012. Therefore, on December 14, 2010, the date of
    valuation, the driveway remained open. Accordingly, IDOT argued, the “solution to the
    court’s concern becomes clear: the appraisers in this circuit court proceeding must consider
    that the North Avenue [d]riveway existed and provided access to North Avenue in the before
    and after conditions, but exclude any damages for the closure of the North Avenue
    [d]riveway.” IDOT urged that such an approach would not force the appraisers to consider a
    hypothetical, because, in fact, the North Avenue driveway was open on December 14, 2010,
    and that circumstance did not change as a result of the taking. Rather, the driveway did not
    close until months later.
    ¶ 18        In denying the motion, the court first questioned the strength of IDOT’s argument in light
    of the fact that it was being raised on the eve of trial when, if the law were as clear as IDOT
    propounded, it would have been raised at or near the time of the quick-take hearing and before
    significant taxpayer expenditures were incurred for discovery and numerous other motions
    concerning the North Avenue driveway. The court reiterated that damages arising from closing
    the North Avenue driveway would, if sought on their own, be properly sought only in the court
    of claims. However, the court noted that its jurisdiction of Dalzell’s claim was supported by
    Illinois Pattern Jury Instructions, Civil, No. 300.49 (2011) (hereinafter IPI Civil (2011) No.
    300.49), which provides that, in determining the fair market value of the remainder after a
    taking, the jury may consider any detriment (or benefit) from the proposed public use proved
    by the evidence that decreases (or increases) the fair market value of the remainder. The court
    did not find that instruction to be qualified, and it opined that, if the driveway’s closure had
    somehow benefited the property, IDOT likely would have used that benefit to argue for a
    reduction in damage to the remainder. Thus, the court noted, “I don’t see how the government
    can use that benefit and not let the property owner use a detriment.” The court stated that the
    driveway’s closure would be presented to the jury not as evidence of specific damages for
    cutting off the access but, rather, under IPI Civil (2011) No. 300.49.
    ¶ 19        The court next acknowledged that parties could not confer or waive subject-matter
    jurisdiction and, so, the issue could be raised at any time. However, the court noted that, if the
    issue were not jurisdictional, it would have found estoppel and waiver based on IDOT’s
    position at the quick-take hearing and throughout the litigation, as well as on its delay in
    -6-
    raising the issue and the resultant expense and time that went into arguments concerning the
    driveway.
    ¶ 20       Finally, as to IDOT’s argument concerning the date of valuation:
    “IDOT, really, is asking me to consider *** that the property is supposed to be
    valued as of the―a date that the eminent domain complaint was filed, which is
    absolutely true, that’s the part taken and the easement taken. But it cannot be the law
    that you cannot consider the benefit or detriment of the proposed public use because
    why would we indeed have this IPI instruction if that were true.
    So[,] I don’t think you can consider when the project was completed to the extent
    that it closed off the North Avenue driveway and say, you don’t get damages to [the]
    remainder because we didn’t complete this project until after the valuation date. And
    that’s essentially what IDOT is arguing, and I don’t think that that is correct law.”
    (Emphasis added.)
    ¶ 21                                C. Safety of North Avenue Driveway
    ¶ 22       In response to various motions in limine filed by Dalzell and as a discovery sanction, the
    court barred IDOT’s engineer and safety expert, Michael Ziegler, from testifying to any
    opinions concerning the safety of the North Avenue driveway that relied on design speed. In
    keeping with that ruling, the court also ruled that certain exhibits relating to design speed
    would not be permitted into evidence and that IDOT could not cross-examine Dalzell’s
    engineer and safety expert, Todd Abrams, concerning design speed. The court ruled, however,
    that the experts could testify to the safety of the driveway on bases not related to design speed.2
    ¶ 23       In a series of discovery requests between 2011 and 2013, Dalzell sought from IDOT any
    and all prior construction plans since 1995 for North Avenue or Powis Road that included the
    subject property. It is apparently undisputed that (1) there was only one prior project at this
    intersection, in 1995, and (2) the design speed for the North Avenue driveway would have
    been included within any such plan, even appearing on the cover sheet. It is also apparently
    undisputed that IDOT objected to the requests as burdensome and irrelevant and that, at one
    point, IDOT suggested that any such documents had been destroyed, providing to Dalzell its
    document-retention policy.
    ¶ 24       Ziegler issued reports in April and May 2013 and November 2014, opining that, for
    multiple reasons, in the “before” condition and on the date of valuation, the North Avenue
    driveway was unsafe, based in part on tests and equations applying a design speed of 50 miles
    per hour. In December 2014, Dalzell moved for leave to issue discovery specifically to obtain
    documents related to design speed. IDOT objected on the basis of untimeliness because
    discovery had already closed. On December 18, 2014, the court denied Dalzell’s motion,
    noting that anything not produced would not be introduced at trial by either side. However, the
    court extended, until August 2015, the time to disclose nonappraisal expert reports.
    ¶ 25       Abrams issued a report in January 2015, opining that the North Avenue driveway was safe,
    applying a design speed of 45 miles per hour. His deposition was taken on February 17, 2015.
    2
    We note that the parties’ stipulation (supra ¶ 10) allowed for consideration of the issue of the
    driveway’s value. The driveway’s safety related to its value as an access point on the date of valuation.
    In turn, its value, or lack thereof, was relevant to the extent to which its closure impacted damage to the
    remainder.
    -7-
    ¶ 26       On March 12, 2015, IDOT produced to Dalzell a rebuttal opinion from Ziegler (attaching,
    according to Dalzell, more than 1000 pages of documents), critiquing Abrams’s opinion, in
    part for relying on an incorrect design speed. Included within the attachments were documents
    showing that the design speed before the taking was 50 miles per hour (consistent with
    Ziegler’s opinion). In March 2016, Dalzell moved in limine to bar Ziegler’s testimony based
    on design speed, as the documents supporting that opinion were not previously disclosed.
    ¶ 27       In response to Dalzell’s motion, IDOT argued that Ziegler did not have the documents at
    issue until he prepared his report rebutting Abrams’s opinion. However, the court found that
    Dalzell’s general discovery requests, to which IDOT objected, would have encompassed
    documents that would have reflected the design speed. Moreover, the court found critical that,
    in December 2014, IDOT objected to Dalzell’s specific request for design-speed documents
    when it knew that Ziegler had testified to safety based on design speed, even if he had not used
    the documents at issue. Accordingly, although IDOT produced the documents in March 2015,
    the production was not until after Abrams rendered an opinion and was deposed. IDOT was
    then able to give Ziegler the documents to bolster his opinion and to critique Abrams’s opinion
    as based on incorrect information.
    ¶ 28       IDOT argued that, although Dalzell did not receive the documents until March 2015, he
    had until August 2015 to have Abrams amend his opinion but he did not do so; therefore, IDOT
    argued, Dalzell’s motion in limine simply reflected gamesmanship. The trial court disagreed. It
    granted Dalzell’s request to bar Ziegler from testifying to any opinion based upon the design
    speed before the taking, but it held that he could testify to his opinion to the extent that it was
    not based on design speed. The court similarly held that no other witnesses could rely on
    design speed or Ziegler’s analysis or conclusion relating to design speed. The court noted,
    apparently referencing Dalzell’s initial discovery requests for construction plans (which would
    have included design speed), that the spirit of discovery is full disclosure and that “if anything
    could remotely be within a notice to produce or an interrogatory, then it should be produced,
    especially when you have the government on one side and a private party on the other side.”
    Further, with respect to Dalzell’s specific request for design-speed information, the court
    concluded:
    “To object to [the request] on that basis that it’s too late, discovery is closed[,] is
    kind of like, in your face my expert is using this, but I’m not going to let you use it
    because you were too late. I think [it] is outrageous, really.
    To object to it, knowing your expert is going to be using the exact documents that
    they have been requesting all along and now come into court and try to denigrate Mr.
    [Abrams’s] testimony because he didn’t have the documents because you didn’t
    produce them and then allow the expert to render an opinion based upon documents
    that you objected to producing, I think is outrageous.”
    ¶ 29       The court denied IDOT’s motion to reconsider the ruling. IDOT asserted that the initial
    requests did not specify design-speed information and that it did not realize that design speed
    was an issue until after Abrams’s deposition. Therefore, when it objected to the request in
    December 2014, IDOT thought that the request was seeking to challenge what the design speed
    should be, not just to find out what it was. IDOT reiterated that Dalzell had time to have
    Abrams amend his opinion after the documents were produced. In response, Dalzell noted that
    none of IDOT’s arguments were proper for a motion to reconsider. Further, he argued that,
    although they did not specifically mention design speed, his early discovery requests would
    -8-
    have encompassed it and, clearly, IDOT’s objections that production was burdensome and
    irrelevant and that the documents had been destroyed proved untrue. In fact, the evidence
    reflected that IDOT’s counsel never requested the documents until February 20, 2015. In any
    event, Dalzell noted, he did not need to justify to IDOT his strategic purpose for wanting the
    documents, so its failure to produce the documents until it realized why he wanted them was
    inexcusable.
    ¶ 30       The trial court agreed with Dalzell. It again emphasized that the initial discovery requests
    would have included the design-speed information. Nevertheless, it explained, it was more
    concerned with IDOT’s objection to Dalzell’s December 2014 specific request for
    design-speed information. Even if Ziegler did not rely on the documents at issue for his initial
    opinions, he nevertheless, even then, opined on design speed. Dalzell wanted documents that
    related to that issue, upon which Abrams would also be expected to opine. IDOT objected to
    the request, and the court denied it:
    “And then, I’m sorry, [IDOT] had the audacity to then produce it to their expert,
    and it just happened to confirm his opinion that the design speed was 50 miles per hour.
    I mean, what would happen if the design speed was something else?
    It was just lucky that it happened to confirm it.
    But here is the prejudice to [the] property owner. He already disclosed his expert.
    He already had his expert’s report disclosed. He already had presented his expert for
    deposition testimony. At which time the expert, Mr. Abrams, is utilizing an,
    apparently, incorrect design speed. So that all of his testimony with regard to the safety
    of this driveway now becomes imperil[ed].
    ***
    *** [W]e are not producing it to the defendant. Yet, we are going to have our own
    expert―have it produced for our own expert, and [it is] going to confirm his opinion
    that this was indeed the 50-mile-an-hour design speed.”
    ¶ 31       The court denied the motion to reconsider, reiterating that, as a sanction pursuant to Illinois
    Supreme Court Rule 219(c) (eff. July 1, 2002), it was barring Ziegler from testifying to any
    opinion based on the design speed, for IDOT’s (1) failure to produce the prior construction
    plans in response to Dalzell’s production requests and (2) objection to Dalzell’s specific
    request for design-speed information. The court noted that other witnesses would also be
    prohibited from testifying, to the extent that their opinions relied upon Ziegler’s design-speed
    analysis. Further, not even Abrams could testify to design speed because his testimony that the
    design speed was 45 miles per hour would open the door to IDOT’s cross-examination of him
    for using an incorrect design speed, an error resulting from IDOT’s failure to produce relevant
    information. “So anything that is based on the design speed is out of the case on both sides.”
    ¶ 32                              D. Dalzell’s Motion In Limine No. 14
    ¶ 33        As previously noted, the parties stipulated that the legality of the North Avenue driveway’s
    existence before the taking would not be an issue at trial. However, Dalzell believed that IDOT
    still wished to touch upon that issue through evidence concerning the existence, or lack
    thereof, of a permit for the driveway. As such, Dalzell deposed Thomas Gallenbach, IDOT’s
    permit engineer.
    -9-
    ¶ 34       At some point prior to trial, the trial court apparently agreed that no evidence would be
    received concerning the driveway’s permits. Therefore, Dalzell moved in limine to exclude
    Gallenbach’s testimony, partly on the basis that IDOT, after Gallenbach’s deposition, amended
    its disclosures for other expert witnesses, who had already opined and been deposed, as
    including “all matters disclosed and discussed” in Gallenbach’s deposition. Dalzell objected
    that IDOT’s other experts’ opinions could not possibly have been based on something that did
    not exist, i.e., Gallenbach’s testimony, when they rendered their conclusions.
    ¶ 35       The court granted the motion in part. It did not bar all evidence from Gallenbach. However,
    it agreed that IDOT should not be permitted to effectively supplement other witnesses’
    opinions with Gallenbach’s testimony. The court noted that the other witnesses did not need or
    have Gallenbach’s testimony when they issued their opinions. For them to now testify that they
    reviewed Gallenbach’s testimony and that it supported their opinions would unfairly buttress
    their testimony. The court therefore barred five of IDOT’s witnesses from discussing
    Gallenbach’s testimony. However, it also held that, on cross-examination of those witnesses,
    Dalzell could not assert or imply that they had failed to review Gallenbach’s testimony. The
    court stated that, with respect to the other witnesses, “[Gallenbach’s testimony is] not going to
    be mentioned in their testimony at all.”
    ¶ 36       At trial, IDOT made an offer of proof concerning Gallenbach’s testimony, specifically
    with respect to Dalzell’s objection to his testimony concerning motorists “coming over the
    crest of the bridge.” IDOT offered Gallenbach’s entire deposition transcript. It apparently did
    not, however, make an offer of proof as to what other witnesses would have testified with
    respect to Gallenbach’s opinion.
    ¶ 37                        E. Motions and Instructions Regarding Barrier Median
    ¶ 38        As previously noted, before the taking and the project, the property had direct access to
    North Avenue from the North Avenue driveway and indirect access to North Avenue by
    exiting left out of the Powis Road driveway. After the taking and during the project, direct
    access to North Avenue was removed when the North Avenue driveway was closed. The
    indirect access was not retained either, as IDOT installed a barrier median along Powis Road
    that prevents drivers from turning left either (1) onto Powis Road from the property to access
    North Avenue at the intersection or (2) off Powis Road to access the property. Therefore,
    although North Avenue is less than 100 feet from the Powis Road driveway, drivers can access
    it from the property only by turning right out of the Powis Road driveway and then proceeding
    in a 3.5-mile circular route. Further, the sole means of accessing the property is a right turn
    onto Powis Road from North Avenue and then a right turn onto the Powis Road driveway.
    Also, the Powis Road driveway was reduced in size by the taking.
    ¶ 39        Prior to trial, IDOT moved in limine to bar any damages flowing from the barrier median,
    on the basis that damages from a barrier median are not compensable. IDOT also moved
    in limine for a finding as a matter of law that there was no material impairment of access to the
    property (and Dalzell filed a motion in limine arguing the opposite position). IDOT submitted
    proposed jury instructions on the same bases. In sum, IDOT argued that not every limitation of
    access is compensable and that, because the installation of barrier medians is a valid exercise
    of a government’s police powers and Dalzell retained direct access to Powis Road’s lane of
    traffic that abuts the property, he was not entitled to compensation flowing from the median or
    the resulting 3.5-mile route.
    - 10 -
    ¶ 40       After hearing oral argument, the trial court distinguished the cases upon which IDOT
    relied, namely Department of Public Works & Buildings v. Wilson & Co., 
    62 Ill. 2d 131
     (1975),
    and Department of Public Works & Buildings v. Mabee, 
    22 Ill. 2d 202
     (1961), and denied
    IDOT’s motions in limine (thereby also granting Dalzell’s motion concerning material
    impairment of access). The court found that there existed both a taking and a material
    impairment of access to the property at the Powis Road driveway. “It’s not just because a
    barrier has been put there, it’s also because of the physical taking and the necessity of now
    having to drive further to try and get back to the point they could go back in the before.” As it
    found sufficient evidence to allow the jury to consider material impairment of access, the court
    determined that it was for the jury to decide whether there were any damages flowing from that
    impairment.
    ¶ 41       At the jury-instruction conference, the court rejected, without prejudice, a non-IPI
    instruction that IDOT offered, allegedly based on Department of Public Works & Buildings v.
    Greenwell, 
    45 Ill. App. 3d 159
    , 163 (1977), to prevent the jury from awarding damages based
    upon the 3.5-mile route. The proposed instruction stated, “The law does not permit an award of
    damages for circuity of travel.” The court found, based on its rulings in limine, that the trial
    would focus not on circuity of travel so much as material impairment of access. If, at trial, the
    evidence did not show material impairment, or if circuity of travel “leaked” into the case, then
    IDOT could reintroduce the instruction.
    ¶ 42       At trial, the court also rejected IDOT’s presentation of IPI Civil (2011) No. 300.51. That
    instruction provides, “The law does not permit an award of damages for the loss or reduction
    of traffic which may result from [the installation of a median or divider strip] [the
    establishment of a one-way traffic regulation], and you should not consider this factor in
    determining damages to the remainder.” (Emphasis added.) 
    Id.
     Further, the comment to the
    instruction states: “Diminution of traffic must, of course, be distinguished from deprivation of
    material impairment of access, which is compensable.” IPI Civil (2011) No. 300.51,
    Comment, at 589. As such, the court found that the instruction was meant to ensure that the
    jury did not compensate for any reduction in traffic flow, which was not an argument raised or
    an issue upon which evidence was received at trial. Further, it reiterated that diminution of
    traffic resulting from a barrier median must be distinguished from material impairment of
    access resulting from a barrier median, the latter being compensable. The court explained that
    there was evidence, separate from the barrier, that there had been material impairment of
    access because the Powis Road driveway had been reduced in size by the taking, resulting in a
    shorter turning radius. However, there had been no evidence regarding traffic flow, and
    therefore, the court found, the instruction would be confusing to the jury.
    ¶ 43       At trial, IDOT also moved to strike all testimony about the 3.5-mile route, arguing again
    that the barrier median was the sole cause of the 3.5-mile route. Dalzell argued that the
    3.5-mile route concerned impairment of access, both ingress and egress. “And that is the
    essence of material impairment of access. If you only had to go 20 extra yards, you’d never
    [have] had material impairment of access. This is probably the textbook case on material
    impairment of access.” The court agreed, and it denied the motion to strike.
    ¶ 44                              F. Opening and Closing Statements
    ¶ 45       During opening statements, Dalzell’s counsel informed the jury that the issues in the case
    included “access, responsibility and accountability.” He explained that the jurors should view
    - 11 -
    the evidence through the “prism” of responsibility and accountability. Counsel explained that
    the case did not concern Dalzell’s actions; rather, it concerned IDOT’s responsibility to pay
    just compensation for the ruined access for which it was accountable. Counsel noted that IDOT
    claimed that the North Avenue driveway was not safe before the taking and therefore lacked
    value and that its closure thus did not warrant compensation.
    ¶ 46       Similarly, in closing arguments, Dalzell’s counsel explained that the evidence showed that
    access to the property had been compromised and damaged as a result of IDOT’s project and
    the taking, responsibility for which lay with IDOT, not Dalzell, who had done nothing wrong.
    “He only happens to be the property owner, and that’s where the accountability comes in.
    IDOT has to be held accountable.” Counsel requested that the jury, recognizing IDOT’s
    responsibility, compensate Dalzell fairly and according to the law for the impaired access and
    the damage to his property. Counsel also noted that “[t]his is the only opportunity that Mr.
    Dalzell has to be made whole in this process, is through you, as a jury deliberating on the
    evidence that’s been presented.” Finally, counsel commented, “If you’re not paid just
    compensation, you violate the Fifth Amendment constitutional right to receive just
    compensation, and that’s why you have to consider the take and the project, because if you
    don’t, you are not properly awarding Mr. Dalzell the just compensation, what’s fair, the just
    compensation that he is due.”
    ¶ 47       IDOT concedes that it did not object at trial to Dalzell’s counsel’s opening and closing
    statements.
    ¶ 48                            G. Dale Kleszynski’s Valuation Testimony
    ¶ 49       One of Dalzell’s appraisers, Dale Kleszynski, testified that, to arrive at the value for the
    part taken, consideration of the whole property was required; “you consider its contributory
    value *** what does the part that is being taken contribute to the overall value of the real
    estate.” Further:
    “COUNSEL: Okay. And you don’t just value the part taken as just this
    independent, irregular-shaped taking of the property and say what is this part; you look
    at the value of this in relation to the whole, correct?
    KLESZYNSKI: That is correct, what does it contribute to the whole property, as
    well as the improvements that are on the property.”
    ¶ 50       Kleszynski discussed comparable properties and determined that the unit value for the
    subject property would fall between $4.71 and $11.35 per square foot. In Kleszynski’s opinion,
    after various adjustments, the value of the property as a whole, before the taking, was $6.75 per
    square foot. As to the value of the part taken, Kleszynski explained that it equated to $12 per
    square foot because the contributory value of that portion of the property, as it related to the
    whole property, was higher than other portions of the site. He stated, “the value of the part
    taken as part of the whole is an analysis of what the contributory value of the part taken is as it
    relates to the whole property taking into consideration the utility that is has, as well as the
    remainder parcel and the improvements that are on it.” Counsel asked Kleszynski why he had
    concluded that the part taken had a substantially higher value than the property overall, and
    Kleszynski commented, “[i]t’s the best part of the site,” explaining:
    “[i]t’s the most visible portion of the site that is located on North Avenue and Powis
    Road. And if you were to compare it to some of the back portions of the property, the
    - 12 -
    contributory value of that portion of the site would be higher when compared to just, by
    way of example, the back, the furthest eastern section of the property that is in the
    middle of the site.”
    He further explained that, from an appraisal perspective, every piece of property has zones of
    value but not every portion contributes equally; for example, the back corner of a backyard is
    typically worth less than the front yard. After elements of damage were considered, Kleszynski
    valued the remainder (after the taking) at $4.60 per square foot.
    ¶ 51       IDOT did not object to the foregoing direct testimony. On cross-examination, IDOT asked
    Kleszynski whether, in valuing the part taken, he had considered the contributory value of the
    improvements contained in the remainder. He replied, “yes.”
    ¶ 52       At the conclusion of Kleszynski’s testimony, the trial court offered the jury the opportunity
    to submit questions for Kleszynski. The jury returned three questions, including: “Regarding
    the part taken, are you saying that a market purchaser would pay $12.00 per square foot for that
    part alone? Or would a buyer have to include the balance of the property in a purchase to
    validate the $12.00 [per] square foot for that parcel?” In response, Kleszynski explained:
    “KLESZYNSKI: What I am saying is that the $12.00 [per] square foot is reflective
    of the high profile nature of that portion of the property.
    So, in other words, if for example, and I am just using this as an example, if Mr.
    Dalzell had somebody who came to him and said I want to put a sign at this location
    because it’s high―
    IDOT: Objection, there was no [Rule] 213(f) [disclosure] on sign.
    THE COURT: Okay. The signage is not an issue in this case. This is a hypothetical
    to explain it. So the objection is overruled. You may proceed.
    KLESZYNSKI: And I am just using it. It’s best explained by example.
    So if, for example, somebody came to Mr. Dalzell and said I want to buy this
    portion of the property because I want to put a sign up on it *** Mr. Dalzell would
    be―it would be in his best interest to charge them the $12.00 [per] square foot for that
    property because it would be reflective of the high profile needs that that particular user
    would have.
    What I am saying in this particular instance is that the area that was marked [on an
    exhibit] in blue on the part taken is, in fact, the highest visibility and the location of the
    highest profile of the subject property, and so it has a higher contributory value.
    By contrast[,] if it were true that we were talking about the taking being at the back
    portion of the property near the rail tracks and it had very little visibility, that number
    would be significantly lower.” (Emphasis added.)
    ¶ 53       Dalzell’s counsel asked some follow-up questions, eliciting that evaluating a narrow strip
    of land in isolation, with no consideration of its relation to the remaining land, would actually
    lower the strip’s value. As such, counsel confirmed with Kleszynski that “you have to take into
    consideration the entire property because it’s *** an integrated piece of property, correct?”
    Kleszynski replied, “That is exactly correct. That is why the question is asked what is the value
    of the part taken as part of the whole. It has to be always considered as part of the whole
    property in the utility that it carries itself, as well as the utility that it adds to the overall piece of
    real estate including the improvements in the after condition.”
    - 13 -
    ¶ 54       Outside of the jury’s presence, IDOT moved to strike Kleszynski’s entire testimony. It
    argued that the jury’s question reflected that it was confused “as to what the value of a part
    taken is.” IDOT argued that Kleszynski had discussed the value of the part taken for putting up
    a sign, versus how that portion contributes to the actual storage use of this property. “They are
    looking at it now for a sign, and that is highly prejudicial and confusing to the jury. I think that
    the jury is absolutely confused at that now.” Dalzell disagreed, noting that Kleszynski made
    very clear that he was posing only a hypothetical.
    ¶ 55       The court overruled the motion to strike the testimony. Noting first that “this jury is,
    amazingly, on track, which is very gratifying,” the court found further that “he clarified it at the
    end that it has to be part of the whole part.” (Emphasis added.)
    ¶ 56                                    H. Dalzell Cross-Examination
    ¶ 57       Dalzell testified at trial that ingress to and egress from his property are now problematic.
    He testified that he continues to use the property as an outside storage yard, as he did prior to
    the taking. However, prior to the taking, 20-foot, 40-foot, and 45-foot trailers could come onto
    the property. Now, 45-foot trailers cannot get onto the property. A 40-foot trailer can access
    the property from the Powis Road driveway, but only “with difficulty” so “we don’t do it
    anymore.” When asked whether he is conducting essentially the same storage business, Dalzell
    replied, “It’s the same storage business, not the same equipment.” IDOT’s counsel then asked,
    “Now was your income from 2010 and 2014 pretty much the same?” The trial court sustained
    Dalzell’s counsel’s objection to the question as irrelevant.
    ¶ 58       IDOT requested a sidebar. There, IDOT presented Department of Transportation v. Shell
    Oil Co., 
    156 Ill. App. 3d 304
     (1987), as supporting its position that it could use a lack of
    decrease in income to show that access had not been impaired. Dalzell’s counsel noted that
    impairment of access to a gas station concerned flow of traffic and sales, different concepts
    from those at issue here, where the changes have impacted what vehicles can physically get in
    and out of the property. The trial court ultimately disagreed with IDOT, noting that, in Shell
    Oil, Shell’s expert testified that sales evidence was relevant to the issue of station access. In
    contrast, here, there had been “no discovery with regard to income before and income after.
    You’ve got no expert to testify to the income before and income after and how that might
    [a]ffect their valuation.”
    ¶ 59       The court concluded:
    “I’m going to sustain the objection. The reason I’m sustaining the objection is
    because I think that it has very little probative [value] and [is] highly prejudicial in that
    you’re trying to directly relate income to access to this property, and income can be
    dependent on a lot of things, especially when we’re going from 2010 to, I don’t even
    know what year. Are we doing 2016? I don’t know when the project was finished? Are
    we doing it from the time the project was finished to 2016? And since there was no
    discovery on this, there’s been no opportunity to explain why there’s *** less of an
    income. He’s 73 years old now. Maybe he’s not working as much now. [We are]
    [t]alking about the market value of the property itself. Not his income that he generates
    from that property. So for those reasons[,] I’m sustaining the objection.” (Emphasis
    added.)
    - 14 -
    ¶ 60                                       I. Abrams’s Remedy Plan
    ¶ 61       At trial, Abrams testified to a remedy plan for the Powis Road driveway, which would
    allow Dalzell to provide ingress and egress for trucks. Abrams testified that, in order to
    implement the remedy plan, Dalzell would have to get permission from his neighbor. IDOT
    objected that the testimony had not been disclosed and violated Illinois Supreme Court Rule
    213 (eff. Jan. 1, 2007). Dalzell’s counsel showed that the evidence was in Abrams’s exhibit,
    “as it relates to where the scope of the remedy plan is and the property lines.” Counsel asserted,
    “It’s a fact. It’s not an opinion.” The court agreed and overruled IDOT’s objection. Thereafter,
    counsel asked Abrams if “Mr. Dalzell would have to go to his neighbor and obtain permission
    to have an easement or some sort of use of his property in order to construct his driveway?”
    Abrams responded, “It’s an agreement usually between the parties [(i.e., Dalzell and his
    neighbor)].”
    ¶ 62       IDOT appeals.
    ¶ 63                                            II. ANALYSIS
    ¶ 64               A. IDOT’s Motion In Limine No. 1: North Avenue Driveway and Jurisdiction
    ¶ 65        IDOT argues first that the court erred as a matter of law when it denied IDOT’s motion in
    limine No. 1 wherein it sought to exclude, on the basis of the trial court’s lack of jurisdiction,
    testimony concerning damage to the remainder caused by the closure of the North Avenue
    driveway. Reiterating that it took only the two parcels and that the North Avenue driveway was
    not closed as a result of the taking, IDOT argues that, as a matter of law, any claims of damages
    to the remainder due to the closure of the North Avenue driveway are within the exclusive
    jurisdiction of the court of claims. IDOT notes that, to be recoverable in eminent-domain
    proceedings, all claimed damages must be the direct and proximate result of the taking.
    Therefore, IDOT argues, Dalzell cannot in this action claim damages as a result of the North
    Avenue driveway closure, where the damages were not a direct and proximate result of the
    taking, the obstruction to the driveway was not built upon land taken, and the closure resulted
    merely from IDOT’s overall construction plan for North Avenue.
    ¶ 66        Generally, a court’s ruling on a motion in limine is reviewed for an abuse of discretion.
    City of Quincy v. Diamond Construction Co., 
    327 Ill. App. 3d 338
    , 342-43 (2002). However, to
    the extent that this issue presents a question of law, we review it de novo, while the court’s
    findings of fact are reviewed under the manifest-weight-of-the-evidence standard. See, e.g.,
    Illinois State Toll Highway Authority v. South Barrington Office Center, 
    2016 IL App (1st) 150960
    , ¶¶ 31-33. Here, IDOT used its power of eminent domain to take certain property from
    Dalzell. Dalzell filed a counterclaim for compensation for damage to the remainder. IDOT
    disputed damages in the amount claimed. Accordingly, the jury here was tasked with deciding
    (1) the amount of just compensation IDOT must pay Dalzell for the property taken and (2) the
    amount that would reasonably and fairly compensate Dalzell for any damage to the remainder.
    See, e.g., IPI Civil (2011) No. 300.12. The issue presently before us implicates the second
    question, i.e., the evidence that the jury could consider in determining the amount that
    reasonably compensates Dalzell for damage to the remainder.
    ¶ 67        A circuit court claim for just compensation derives from the Illinois Constitution.
    Specifically, article I, section 15, of the Illinois Constitution provides that “[p]rivate property
    shall not be taken or damaged for public use without just compensation as provided by law.
    Such compensation shall be determined by a jury as provided by law.” Ill. Const. 1970, art. I,
    - 15 -
    § 15. This constitutional provision is codified in section 10-5-5 of the Act. 735 ILCS 30/10-5-5
    (West 2008). Accordingly, the object of a condemnation proceeding is to ascertain the just
    compensation to be paid. Illinois State Toll Highway Authority v. Dicke, 
    208 Ill. App. 3d 158
    ,
    171 (1991). Just compensation is the market value of the property adapted to its highest and
    best use on the date of the filing of the condemnation complaint (see, e.g., Department of
    Transportation v. White, 
    264 Ill. App. 3d 145
    , 149-50 (1994)), and market value, in turn, is the
    amount that a purchaser would pay to the owner to buy the property in a voluntary sale (735
    ILCS 30/10-5-60 (West 2008)).
    ¶ 68        As noted above, a property owner may claim, separate from the amount of just
    compensation for the land taken, that the remaining property was damaged by the taking. See,
    e.g., Oak Brook Park District v. Oak Brook Development Co., 
    170 Ill. App. 3d 221
    , 239 (1988)
    (the plaintiff exercised a taking through eminent-domain powers, and the defendant claimed
    damage to the remainder); Department of Public Works & Buildings v. Horejs, 
    78 Ill. App. 2d 284
    , 287 (1966) (the plaintiff filed petition to condemn, and the defendants claimed damage to
    the remainder); see also IPI Civil (2011) Nos. 300.11-300.15 (providing instructions in varying
    circumstances where counterclaims for damage to the remainder are filed or not filed, or
    amount is contested or not contested). The settled measure of damage to a remainder is the
    “ ‘depreciation in value of the land not taken which results from the taking, that is, the
    difference between the fair cash market value of the part not taken unaffected by the
    improvement and its fair cash market value as affected.’ ” Dicke, 208 Ill. App. 3d at 172
    (quoting Department of Public Works & Buildings v. Bloomer, 
    28 Ill. 2d 267
    , 270 (1963)). Not
    all factors bringing about a reduction in value represent recoverable damages relating to land
    not taken; the depreciation must be from a direct physical disturbance of a right the owner
    enjoys in connection with his or her property. Department of Transportation v. Rasmussen,
    
    108 Ill. App. 3d 615
    , 626 (1982).
    ¶ 69        Accordingly, there is no question that, to the extent that Dalzell’s claim implicated just
    compensation and damage to the remainder as a result of the taking, the trial court was the
    proper forum. Indeed, IDOT never disputed this in a motion to dismiss the counterclaim for
    lack of jurisdiction. Instead, IDOT’s challenge is based on the concept that, for damages to be
    compensable in an eminent-domain proceeding, they must be a direct and proximate result of
    the taking (Dicke, 208 Ill. App. 3d at 172), and if the alleged damage is not a direct and
    proximate result of the taking or if the property damaged is not taken, the property owner’s
    remedy lies in the court of claims, which, again, has exclusive jurisdiction over all claims
    against the State for damages in any case sounding in tort, if such a case would lie against a
    private person in a civil suit. 705 ILCS 505/8(d) (West 2008); Patzner v. Baise, 
    133 Ill. 2d 540
    ,
    545 (1990). As such, IDOT frames the issue on appeal as the trial court’s lack of jurisdiction to
    consider testimony concerning Dalzell’s claim for damages relating to the North Avenue
    driveway’s closure, which, it argues, was not a direct and proximate result of the taking.
    ¶ 70        However, in denying IDOT’s motion in limine, the court clearly and correctly drew the
    proverbial “line in the sand” with respect to its jurisdiction. The court was aware that claims
    for damages against the State belong in the court of claims, and it expressly did not allow
    Dalzell to seek damages for the North Avenue driveway’s closure. Indeed, the court agreed
    with IDOT that, if Dalzell wished to seek damages for the driveway’s closure, he would have
    to proceed in the court of claims. However, the court also correctly recognized that the
    constitution and the Act contemplate that certain elements of claims regarding just
    - 16 -
    compensation and the corollary of damage to the remainder properly belong in the circuit
    court. The issue, therefore, is more nuanced than as framed by IDOT: namely, the issue is
    whether the court correctly determined that, although Dalzell could not elicit testimony
    concerning damages for the driveway’s closure, the impact of that closure could nevertheless
    still be considered by appraisal experts and the jury in assessing the remainder’s post-taking
    fair market value. Again, Dalzell’s counterclaim did not request damages pertaining to the
    driveway; rather, it alleged that, because the remainder was used in common with the parcels
    taken, IDOT’s condemnation actions decreased the overall value of the remainder. Therefore,
    the court found simply that the appraisers and the jury were not required to ignore that, because
    of the North Avenue driveway’s closure, the Powis Road driveway became the sole driveway
    on the property. For the following reasons, we reject IDOT’s argument that the court’s ruling
    was improper, addressing first its cited authority and then its ancillary arguments.
    ¶ 71        IDOT cites several cases to argue that the court’s ruling was improper, emphasizing that
    claimed damage to the remainder must be proximately caused by the taking. However, the
    cases upon which IDOT relies are unpersuasive because they either simply recount undisputed
    law or do not present analogous facts. For example, although certain claimed damages in some
    of the cases were denied because proximate cause between the taking and the alleged damages
    did not exist, the focus in those cases was on the fact that the damages sought were caused not
    by takings on the owners’ properties but, rather, by takings or other events that occurred on the
    properties of others. See, e.g., Dicke, 208 Ill. App. 3d at 171 (the owners were not entitled to
    damages for changed drainage on their property that resulted from the placement of dirt fill on
    another owner’s adjacent property); Department of Transportation v. Lake Ka-Ho, Inc., 
    98 Ill. App. 3d 1052
    , 1055 (1981) (damage from lake siltation was not compensable where the silt did
    not come from the property taken from the defendants but, rather, from improvements on the
    properties of others). Similarly, proximate cause did not exist where (1) the alleged damages
    were caused not by the taking on the owner’s property but, instead, by an improvement placed
    on property across the street from the owner and (2) the resulting depreciation was suffered in
    common by all properties in the vicinity of the improvement. See Horejs, 78 Ill. App. 2d at
    290-92 (although a portion of the defendants’ property was taken for a frontage road as part of
    an overall project, the defendants could not claim as damage to the remainder an alleged
    interference with view, light, and air that was actually caused by an embankment that was
    placed across the road from their property on land acquired by the plaintiff from other property
    owners; the damages were not a result of the taking for the frontage road, and they were
    “suffered in common by all lands in the vicinity”).3
    ¶ 72        Here, Dalzell is claiming damage, i.e., a loss in value, to the remainder based solely on
    events that occurred on his property, and the issues here do not concern depreciation factors
    that affect the public at large. Further, in the above-mentioned cases, it was relevant that the
    alleged damages would have occurred regardless of any takings on the defendants’ properties.
    Accordingly, the requirement that the damages be a direct and proximate result of a taking was
    not satisfied, because the damages were simply the result of construction in the general areas.
    3
    In Rasmussen, 108 Ill. App. 3d at 624-27, a case cited by Dalzell, the court similarly found that
    damage to the remainder could not include the decrease in fair market value resulting simply from an
    overpass being built next to the defendants’ property because that decrease would affect any land in the
    vicinity and the public at large.
    - 17 -
    Here, the counterclaim alleged damages and a reduction in value from the taking only on, and
    unique to, Dalzell’s property.
    ¶ 73        IDOT also relies upon Department of Transportation ex rel. People v. Interstate Brands
    Corp., 
    251 Ill. App. 3d 785
    , 788 (1993). There, the court answered in the negative the
    following certified question:
    “ ‘When an Eminent Domain proceeding brought by the State of Illinois involves the
    taking of a temporary easement, may the Defendant seek recovery by counterclaim for
    damages to the remainder based upon changes in access to the property, in a forum
    other than the Illinois Court of Claims?’ ” 
    Id.
    ¶ 74        The facts given in Interstate do not fully describe the physical alterations to the property,
    but it appears that IDOT acquired a temporary easement through condemnation proceedings
    and also relocated an access driveway as part of the project. The relocated access driveway
    required that semi-trucks be given more maneuvering room and, consequently, resulted in a
    loss of parking spaces to the property owner. The property owner counterclaimed for damages
    for the loss of parking spaces. The court noted that (1) the counterclaim did not seek damages
    to the remainder resulting from the taking of the temporary easement, (2) it was not alleged that
    the property subject to the temporary easement was the same property on which the new access
    driveway was built, and (3) the damages (lost parking) due to the location of the access
    driveway did not directly relate to the temporary easement. 
    Id.
     Therefore, the court concluded,
    the defendant could not “tag on” to an eminent-domain proceeding an action for damages that
    belonged in the court of claims. Id. at 789. The court reiterated that, where a loss does not
    involve the actual physical invasion of the property (i.e., a taking), it is compensable in a
    common-law action for damages in the court of claims, not in an eminent-domain proceeding.
    Id.
    ¶ 75        At first blush, the certified question in Interstate seemingly speaks to the issue before us.
    However, for three reasons, Interstate does not change our opinion that there is no
    jurisdictional issue here. First, we note that, although Interstate purported to answer a certified
    question of law, it improperly did so, in large part, by basing its answer on the particular facts
    of the case rather than answering a question of law. See, e.g., Razavi v. Walkuski, 
    2016 IL App (1st) 151435
    , ¶ 7 (“a Rule 308 [(Ill. S. Ct. R. 308 (eff. Jan. 1, 2016))] appeal is limited to
    answering a certified question of law and is not intended to address the application of the law
    to the facts of a particular case”). Second, to the extent that Interstate provided facts, they are
    distinguishable from those here. The court in Interstate apparently determined that there
    existed no relationship between the taking and the access issue that resulted in the claimed
    damages. Further, Interstate concerned a defendant property owner who was seeking
    compensable damages only for the condition that was not, apparently, related to the taking.
    Here, however, the trial court was not presented with a claim seeking damages for an access
    issue―i.e., the closure of the North Avenue driveway―unrelated to the taking. Rather, the
    trial court was faced with the reverse: a claim for damage caused by the taking to the remainder
    as impacted by the driveway’s closure. Therefore, and in part due to the procedural posture of
    Interstate, the court there was simply not presented with the question before us―i.e., whether
    the change in access could be considered to the extent that it impacted the damages
    proximately caused by the taking and thereby affected the post-taking remainder value, even if
    damages for that changed condition could not be claimed or awarded in their own right. Third,
    as summarized in the above case law, it is simply undisputed that, where there is no
    - 18 -
    relationship between a taking and an access issue or other damages, recovery must be sought in
    the court of claims. Accordingly, to the extent that the court in Interstate held something
    different―i.e., that there can never be a relationship between a taking and an access issue or
    that, if there is such a relationship, the access issue cannot impact damage to the remainder for
    purposes of an eminent-domain proceeding―we decline to follow it.
    ¶ 76       Accordingly, the aforementioned case law does not instruct that the trial court here erred,
    as a matter of law, when it allowed consideration of the driveway’s closure for purposes of
    assessing post-taking remainder value. While it is clear that not every diminution resulting
    from a project necessarily also results from a taking that is a component of that project, the
    facts of this case demonstrate that the closure is interrelated with the damage to the remainder
    caused by the taking. In this case, the closure meant that the taking caused, as testified, a
    greater diminution than it would have otherwise. As a result, the calculation of that diminution
    properly included the closure.
    ¶ 77       We also reject IDOT’s argument for other reasons. First, we reject its argument, raised for
    the first time in its motion to reconsider the denial of the motion in limine, that the appraisers
    must ignore the driveway’s closure in their valuations because, on the date of valuation (i.e.,
    the date of the complaint’s filing), the driveway remained open. While there is no dispute here
    that the date of the complaint’s filing constitutes the date of valuation, we may deem this
    particular argument forfeited, as it was improperly raised for the first time in a motion to
    reconsider before the trial court. See Evanston Insurance Co. v. Riseborough, 
    2014 IL 114271
    ,
    ¶ 36 (“Arguments raised for the first time in a motion for reconsideration in the circuit court
    are forfeited on appeal.”). In any event, IDOT’s argument takes an untenably narrow view of
    the idea that the post-taking valuation must be the value of the property as it existed
    “immediately” after the filing. We reject this idea, as did the trial court, in part based on IPI
    Civil (2011) No. 300.49, which provides:
    “In determining the fair cash market value of the remainder after the taking, you
    may consider [any] [benefits] [or] [detriments] from the proposed public use, proved
    by the evidence, which [increase] [or] [decrease] the fair cash market value of the
    remainder.” (Emphases added.).
    ¶ 78       In our view, the valuation cannot include only the property’s physical state immediately
    after the complaint’s filing, without any consideration of what the taking and the project will
    entail, as it is likely that little of the project will have been physically completed “immediately”
    (however that term is defined) after a condemnation complaint is filed. For one thing, such an
    approach would provide incentive to delay a project. Moreover, if IDOT’s argument were
    correct, IPI Civil (2011) No. 300.49 would not allow for consideration of the “proposed”
    public use.4 Further, one of the comments to the instruction provides: “It is also proper to
    4
    In fact, Kleszynski testified at trial that, regardless of when the North Avenue driveway was
    actually closed, he considered it closed as of the date of his valuation “because that is the way it’s done.
    It’s—the presumption is that on the date of value in the after condition the project is complete and the
    driveway would be closed. That is the technique that is applied.” We suspect that the concept of valuing
    property as of the date that a condemnation complaint is filed serves to account for possibly unrelated
    circumstances affecting property values (e.g., natural disasters, zoning changes, etc.) before the
    condemnation suit has proceeded to judgment, as opposed to creating a split-second snapshot for
    assessing value irrespective of any damages resulting from the proposed public use.
    - 19 -
    consider detriment to the remainder which is reasonably certain to result from the use to be
    made of the part taken.” (Emphases added.) IPI Civil (2011) No. 300.49, Comment, at 586. We
    also note that the comments to IPI Civil (2011) No. 300.45 reflect that, while not all factors
    bringing about depreciation represent recoverable damages relating to land not taken, some
    items that are not recoverable themselves may remain relevant as evidence of the depreciation.
    See IPI Civil (2011) No. 300.45, Comment, at 586 (citing Bloomer, 
    28 Ill. 2d 267
    , for the
    proposition that “[t]he expenditures made and costs incurred by the landowner in adapting the
    remainder to use after the takings are relevant, if reasonable and economical, as evidence of the
    depreciation in value, but not as recoverable items in themselves” (emphases added)).
    Although we are not presented here with a “cost of cure” issue, we find that the foregoing
    supports the trial court’s position that an appraisal of value need not completely ignore relevant
    factors, even if those factors are not, themselves, recoverable as damages in the proceeding.
    ¶ 79       We also note that, at the quick-take hearing, both parties presented expert appraisal
    witnesses whose assessments of the fair market value of the property in fact considered the
    closure of the North Avenue driveway. Lorenz explained that, although he did not attribute a
    damages amount for the driveway’s closure, he “didn’t think it was appropriate to ignore it. It
    was a part of the taking, part of the improvement.” Similarly, MaRous testified that (1) he
    knew of no appraisal practice that would ignore the closing of a driveway in a condemnation
    project, (2) it is customary in any appraisal report to include the number of driveways or access
    points to the subject property, and (3) “a driveway for most properties is a very important fact.
    *** [P]roperties that have limited access generally have a direct reflection of a lower value.”5
    (Emphasis added.) Therefore, when the court ruled on IDOT’s motion in limine, its finding
    that the driveway’s closure was a relevant factor to post-taking valuation was supported by the
    evidence it had previously received.
    ¶ 80       In sum, we see no jurisdictional error here concerning the closure of the North Avenue
    driveway. We do not disagree with the general proposition that “the actual taking or the use of
    the part actually taken must be the direct physical cause of the damage to the remainder.”
    Horejs, 78 Ill. App. 2d at 291. Neither did the trial court, which did not find that Dalzell could
    seek here damages for the North Avenue driveway’s closure. However, the law (and the jury
    instructions) clearly anticipates that a common corollary to a circuit court eminent-domain
    action might be a counterclaim seeking compensation for damage to the remainder caused by
    the taking. Accordingly, here, the court considered that, after the taking, the Powis Road
    driveway was the sole means of ingress to and egress from the property. It properly found that,
    in resolving the question of compensation for damage to the remainder, the valuation evidence
    could include that pre-taking there were two driveways and post-taking there would be only
    one, which would be only a right-turn-in, right-turn-out access point. Under the facts of this
    5
    IDOT asserts that the quick-take evidence is irrelevant and should be disregarded. It correctly
    notes that section 20-5-10(d) of the Act provides that the preliminary finding of just compensation from
    the quick-take hearing shall not be evidence in further proceedings, nor shall the reports of appointed
    appraisers be evidence in further proceedings, although the appraisers may be called as witnesses. 735
    ILCS 30/20-5-10(d) (West 2014). However, our reference to testimony from the quick-take hearing
    does not concern admission of evidence or implicate estoppel to IDOT from its witness’s appraisal
    approach. Rather, we reference the testimony to the extent that the appraisers’ approach to valuation at
    the quick-take hearing informed the court in its consideration of the factors that the post-take property
    assessment should include.
    - 20 -
    case, where the closure was relevant to assessing damage to the remainder that resulted from
    the taking, the court did not err in denying IDOT’s motion in limine No. 1.
    ¶ 81                             B. Safety of the North Avenue Driveway
    ¶ 82       IDOT argues next that the trial court abused its discretion with respect to rulings involving
    the safety of the North Avenue driveway. Specifically, it contends that the court abused its
    discretion in granting Dalzell’s motions in limine to effectively bar Ziegler’s testimony related
    to design speed and any exhibits related thereto (Dalzell’s motions in limine Nos. 8, 9, and 10
    and IDOT’s exhibits Nos. 34, 35, 48, and 49), granting the motions as a Rule 219(c) sanction,
    and granting Dalzell’s oral motion to bar IDOT’s cross-examination of Abrams about design
    speed or tests based upon design speed. IDOT also asserts that the court should not have
    permitted Abrams to testify that the North Avenue driveway was safe, while limiting, on the
    basis that it would run afoul of the court’s ruling on design speed, Gallenbach’s testimony to
    the contrary. In sum, IDOT contends that it produced the design-speed information “once [it]
    understood that Mr. Abrams did not know and disputed the design speed in the before
    condition, [at which time] IDOT’s counsel asked IDOT for any documentation it could find
    related to what Mr. Abrams said he was looking for in his deposition.” IDOT then “voluntarily,
    without court order,” produced the documents to Dalzell “only nine days” (emphasis in
    original) after they were located and more than one year prior to trial. IDOT asserts that, upon
    receipt, Dalzell could have Abrams supplement his report and opinion with the correct design
    speed but, instead, Dazell moved to bar the information one year later, right before trial and, in
    doing so, engaged in gamesmanship.
    ¶ 83       We review for an abuse of discretion both a trial court’s ruling on a motion in limine and its
    decision to impose Rule 219(c) sanctions. County Line Nurseries & Landscaping, Inc. v.
    Glencoe Park District, 
    2015 IL App (1st) 143776
    , ¶ 42; Diamond Construction, 327 Ill. App.
    3d at 342-43. An abuse of discretion occurs where no reasonable person would adopt the trial
    court’s view. Santorini Cab Corp. v. Banco Popular North America, 
    2013 IL App (1st) 122070
    , ¶ 21. When imposing sanctions, the trial court must consider the surprise to the
    adverse party, the prejudicial effect of the witness’s testimony, the nature of the testimony, the
    diligence of the adverse party, the timeliness of the objection, and the good faith of the party
    seeking to offer the testimony. 
    Id.
     However, no one factor is determinative, and each case
    presents unique facts. 
    Id.
    ¶ 84       We find no abuse of discretion in the trial court’s rulings in limine or its imposition of
    sanctions. In 2011, 2012, and 2013, Dalzell issued discovery requests seeking from IDOT prior
    construction plans for North Avenue and Powis Road that included Dalzell’s property. It is
    apparently undisputed that, although those requests did not specifically mention design speed,
    production of the plans would have included the design-speed information. It is also apparently
    undisputed that IDOT did not produce those plans, objecting to the requests as burdensome and
    irrelevant and, at one point, representing that those documents had been destroyed. When
    Dalzell later made a specific request, after discovery closed, for design-speed information,
    IDOT objected. But in February 2015, after Abrams had issued his report and had been
    deposed, IDOT’s counsel requested from IDOT the very information that Dalzell had been
    seeking since 2011.
    ¶ 85       The trial court found outrageous that, in December 2014, IDOT objected to the request for
    the information as untimely but then, when it “understood” why Dalzell wanted the
    - 21 -
    information, IDOT finally requested it, easily obtained it, and produced it. The court found
    outrageous that IDOT intended to use the information both to support Ziegler’s opinion and to
    rebut and critique Abrams’s opinion as based on an incorrect design speed, when IDOT failed
    to earlier produce the information. The court questioned whether the information would have
    ever been produced had it not supported IDOT’s own witness. We agree. We submit that it is
    also outrageous that IDOT failed to produce the plans in response to Dalzell’s earlier, general
    discovery requests between 2011 and 2013. It matters not that IDOT did not then know that
    Dalzell wanted the plans for the design-speed information. Clearly, producing the plans would
    not have been burdensome, they were not irrelevant, and they had not been destroyed, as they
    were easily retrieved when IDOT’s counsel deigned to request them. If they had simply been
    produced between 2011 and 2013, Dalzell would not have needed to incur additional expense,
    pursuing discovery requests and filing motions to exclude. (Nor, frankly, would additional
    taxpayer money have been expended for IDOT to respond to those motions and to further
    pursue and resolve this issue.)
    ¶ 86       IDOT argues that, ultimately, Dalzell received the documents one year prior to trial and,
    therefore, cannot claim surprise or prejudice. It contends that a lesser sanction would have
    been appropriate. We disagree. First, we note that, according to Dalzell, although the
    design-speed information was produced with Ziegler’s rebuttal opinion in March 2015, the
    information was included within more than 1000 pages of attachments, not specifically
    identified, and Dalzell did not know that it had been produced until Ziegler mentioned it in his
    November 2015 deposition. Second, and more importantly, other witnesses had relied on
    Abrams’s opinion. Thus, even if Dalzell had pursued the additional expense of having Abrams
    revise his opinion to account for the information, which IDOT possessed but failed to
    previously disclose, Dalzell would have had to pursue the additional expense of having the
    other witnesses modify their opinions that were based on Abrams’s previous opinion.
    Presumably, IDOT would then have requested an opportunity to rebut all the revised opinions.
    The far more just (and certainly reasonable) decision, we agree, was for the trial court to
    simply exclude the testimony from both experts that relied upon design speed.6
    ¶ 87       Critically, testimony concerning the North Avenue driveway’s safety was still permitted;
    the experts were allowed to opine on its safety to the extent that their conclusions were based
    on factors other than design speed. Under these unique facts, it is clear that the safety of the
    driveway was relevant only to the extent that it impacted the property’s value and, in turn, the
    extent to which the remainder was damaged when Powis Road’s driveway became the sole
    access point on the property. We disagree, therefore, with IDOT’s contention that the
    discovery sanction deprived it of a full trial on the merits. The jury was not deprived of
    information with respect to the driveway’s safety; instead, the experts were allowed to opine
    on safety, excluding design speed. Accordingly, we cannot conclude that no reasonable person
    would agree with the trial court’s rulings, and we reject IDOT’s challenge to the court’s
    decision to bar design-speed testimony and its resulting decisions consistent therewith.
    ¶ 88       IDOT also asserts that the trial court abandoned its role as gatekeeper when it announced
    that Abrams could testify that his safety opinion was based on “a yellow duck.” Again, we
    disagree. IDOT takes the court’s comment out of context. IDOT challenged at trial the bases
    6
    Incredibly, IDOT asserts that it “should be allowed at a new trial to cross examine Mr. Abrams on
    his admitted incorrect opinion of the design speed of North Avenue in the before condition.”
    - 22 -
    for Abrams’s safety opinion, arguing that they were not adequately disclosed. After Dalzell
    produced Abrams’s previous reports and testimony, Dalzell and IDOT agreed that Abrams had
    disclosed and could testify to three bases for safety that did not include design speed. IDOT’s
    counsel represented that, as long as Abrams testified to those three things, counsel would not
    further object. Thereafter, however, IDOT’s counsel asserted that one of the bases might be
    irrelevant, simply due to the passage of time. The court responded, “That is cross-examination.
    No, it doesn’t matter. No. That is the bas[i]s.” IDOT’s counsel replied, “I got you.” The court
    continued, “He could say that I looked at this yellow duck and then I came to this opinion. You
    may think it’s ridiculous that that would be a basis for his opinion. So that is a matter of
    cross-examination.” Accordingly, in context, it is clear that the court was simply informing
    IDOT that, since the basis had been disclosed, the alleged inadequacy of the basis was subject
    to cross-examination, not exclusion. Abrams did not, in fact, base his opinion on looking at a
    yellow duck. The court’s comment was simply rhetorical, and it did not abandon its gatekeeper
    role. Further, we are, at this point, discussing minutiae. Again, the safety of the North Avenue
    driveway was relevant only to the extent that it impacted its value as related to the remainder.
    The point of Abrams’s testimony was simply that he viewed the driveway as safe, and IDOT
    agreed that three bases for that opinion were disclosed. We must, therefore, reject IDOT’s
    argument that it was denied a fair trial by this isolated comment relating to a single basis for a
    safety opinion that was of marginal relevance to this case.
    ¶ 89       Similarly, we reject IDOT’s argument that the court was biased and erred where, based on
    its design-speed rulings, it sustained an objection to Gallenbach’s testimony concerning
    motorists “coming over the crest of the bridge” but allowed Abrams to testify that the driveway
    was safe where he “considered, you know, basically the distance, you know, from the top of
    the hill to the driveways.” Again, IDOT takes Gallenbach’s testimony and the court’s ruling
    out of context, as it does not present Gallenbach’s entire statement. Specifically, Gallenbach
    testified that he based his safety opinion partly on “what kind of reaction time would a motorist
    have looking to the east to make a decision to go eastbound or if the vehicles coming over the
    crest curve of the bridge would they have to slow down below ten miles an hour, really hit the
    brakes.” Dalzell objected that the “stopping site distance” was based on site-distance analysis,
    a test that relied on design speed. The court sustained the objection. Given the full context of
    the quotation, we cannot find that the court’s decision was an abuse of discretion.
    ¶ 90                              C. Dalzell’s Motion In Limine No. 14
    ¶ 91        IDOT argues next that the trial court abused its discretion when it granted Dalzell’s motion
    in limine No. 14. Specifically, IDOT argues that the court should not have barred other
    witnesses from discussing Gallenbach’s opinion. IDOT asserts that Gallenbach was timely
    disclosed, Dalzell moved to depose him, and IDOT was granted leave to supplement its
    disclosures based on Gallenbach’s testimony. IDOT contends, “It is hardly fair to limit
    testimony that a party sought and obtained via a court order on a motion to compel simply
    because it is unfavorable to that party.” IDOT argues further that the other witnesses could not
    buttress Gallenbach because they were not permit engineers and, therefore, had different
    perspectives. For the following reasons, we reject IDOT’s argument.
    ¶ 92        First, we address forfeiture. Dalzell notes that IDOT objected to his motion but did not
    further preserve the claim for appeal. Indeed, in civil cases, when the court rules before trial
    concerning the admission of evidence, a contemporaneous trial objection or offer of proof
    - 23 -
    must be made to preserve a claim of error for appeal. See Ill. R. Evid. 103(b)(3) (eff. Oct. 1,
    2015); People v. Denson, 
    2014 IL 116231
    , ¶ 23. IDOT did not make offers of proof at trial
    addressing the barred testimony, namely, what the other witnesses would have said about
    Gallenbach’s opinion had they been allowed to do so. This claim is, therefore, forfeited.
    ¶ 93       Second, in any event, we would not find that the court abused its broad discretion in
    determining that IDOT’s other witnesses could not incorporate Gallenbach’s opinion into their
    own, when his opinion did not even exist when their opinions were formulated. The ruling
    limited the extent to which other witnesses could claim to have relied on that opinion.
    Therefore, the issue was not other witnesses buttressing Gallenbach; rather, the court
    determined that it would be inappropriate to buttress the other witnesses by allowing them to
    claim that Gallenbach’s opinion supported their own. We cannot find that this decision
    constituted an abuse of discretion.
    ¶ 94                       D. Motions and Instructions Regarding Barrier Median
    ¶ 95        IDOT argues next that the court erred as a matter of law when it denied IDOT’s motions
    concerning the barrier median, circuity of travel, and material impairment of access (and, in
    turn, when it granted Dalzell’s motion in limine concerning material impairment of access),
    and, further, that the court abused its discretion when it refused jury instructions about the
    barrier median and circuity of travel. IDOT argues that, pursuant to Wilson, 
    62 Ill. 2d 131
    , and
    Mabee, 
    22 Ill. 2d 202
    , Dalzell is not entitled to compensation because his free and direct access
    to the lane of traffic abutting his property on Powis Road has not been taken or impaired;
    rather, the installation of a barrier median simply controls the direction of travel. We disagree.
    ¶ 96        We note first that Dalzell asserts that IDOT forfeited these issues by failing to
    contemporaneously object at trial and IDOT does not directly reply to that assertion. However,
    given the interrelated nature of the issues presented by the motions in limine and the jury
    instructions, we choose to consider the issues to have been arguably (and tenuously) preserved
    at trial by (1) IDOT’s oral motion to strike any testimony concerning the 3.5-mile route and
    (2) its pursuit of IPI Civil (2011) No. 300.51 concerning the barrier median.
    ¶ 97        We review for an abuse of discretion a trial court’s ruling on a motion in limine. Diamond
    Construction, 327 Ill. App. 3d at 342-43. However, the question whether there has been a
    taking or material impairment of access that entitles the property owner to compensation is a
    question of law for the trial court to determine in the first instance. Wilson, 
    62 Ill. 2d at 141
    .
    The jury must then decide the extent of the resulting damages. 
    Id. at 142
    .
    ¶ 98        Here, the trial court did not err in determining that there had been a taking and material
    impairment of access at the Powis Road driveway. First, there was, undisputedly, a taking.
    Second, the court properly found that the reduced driveway size, coupled with the
    insurmountable median and resulting 3.5-mile route, materially impaired access. The extent of
    the damages resulting from the taking and impairment was a matter properly left to the jury.
    ¶ 99        We agree with the trial court’s determination that IDOT’s cited cases do not speak to the
    combination of factors present here. In Wilson, the court reviewed compensable and
    noncompensable actions affecting access and determined that “the rule is that[,] if there has
    been a taking or material impairment of access, then it is appropriate for the jury to consider
    that fact in determining the extent of damages to the remainder in an eminent domain
    proceeding.” Wilson, 
    62 Ill. 2d at 144
    . The court held, on the facts before it, that the trial court
    had not erred in determining that a partial taking, which eliminated direct access to a major
    - 24 -
    road but replaced it with a frontage road, was a material impairment and that the extent of
    damages was a consideration for the jury. 
    Id. at 145
    .
    ¶ 100       Likewise, IDOT’s heavy reliance upon Mabee is misplaced. First, in Mabee, unlike here,
    there was no taking. Second, the property owner in Mabee operated a gas station and argued
    that the construction of an insurmountable median on the portion of highway abutting one side
    of the property limited access to a one-direction traffic flow, reducing the volume of business
    and, to an extent, the value of the property. The court found first that the property owner was
    not entitled to an optimal flow of traffic and that inconveniences from the median, which ran
    the length of a roadway, were the same as those shared by the public generally. Mabee, 
    22 Ill. 2d at 204
    . The court next found that the property owner’s right of access had not been damaged
    because he maintained free and direct access to the lane of traffic abutting his property, which
    had not been “taken or impaired.” 
    Id.
     Here, however, Dalzell makes no argument concerning
    damages due to the changed flow of traffic. Further, here a taking touched the access point on
    Powis Road that connects to the lane abutting Dalzell’s property. Finally, Dalzell’s property is
    the only property affected by the barrier median and the reduced driveway size; the median
    does not extend down the length of the roadway such that the inconvenience is shared by the
    public generally.
    ¶ 101       Mabee was also distinguished in Rasmussen, 108 Ill. App. 3d at 621, and Illinois State Toll
    Highway Authority v. Humphrey Estate, 
    62 Ill. App. 3d 316
    , 322-23 (1978), in which courts
    recognized, on facts more similar to the facts presented here, that the situations involved more
    than a mere regulation of traffic pursuant to the State’s police power. In Rasmussen, before
    construction, vehicles exiting the property could drive directly onto a major road and proceed
    in a certain direction; after construction, they were forced to travel in a certain direction to one
    road, turn and drive one block in another direction, turn again onto a connecting street, and
    then drive another block in the other direction to access the major road. The court rejected the
    argument that the construction resulted in mere circuity of travel, shared by the public
    generally, and that the decrease in property value was, therefore, not compensable. Rasmussen,
    108 Ill. App. 3d at 621. The court found particularly significant that the physical effects of the
    construction on the property paralleled the effects of erecting barricades along the road in a
    manner that materially impaired the ingress to and egress from the property. Id. at 622-24.
    Similarly, in Humphrey, among other things, the property owner’s access rights to abutting
    roads were limited and/or taken, and one road was converted to a dead-end road. As a result, to
    gain access to the largest quadrant of the owner’s land, drivers were forced to travel along one
    road to another and then proceed for at least 120 feet. Humphrey, 62 Ill. App. 3d at 318-19. The
    court held that there was “no question” that the owner’s access rights had been “materially
    impaired.” Id. at 323. Therefore, we agree with the trial court here that, where Dalzell and his
    customers must travel 3.5 miles (more than 18,000 feet) to access abutting North Avenue, the
    circumstances involve more than simply an exercise of State police power resulting in a
    circuitous route that affects the public generally. The court did not err in finding a taking and
    material impairment of access.
    ¶ 102       Accordingly, IDOT’s arguments concerning the jury instructions must also be rejected.
    Whether to provide a certain jury instruction lies within the trial court’s sound discretion.
    Webber v. Wight & Co., 
    368 Ill. App. 3d 1007
    , 1020 (2006). It is for the trial court to evaluate
    whether a jury instruction is applicable, is supported by record evidence, and accurately states
    the law. Id. at 1021. Ultimately, the court’s jury-instruction rulings do not reflect an abuse of
    - 25 -
    discretion if the instructions given at trial, taken as a whole, fairly and fully apprised the jury of
    the relevant legal principles. Id. “A new trial will be granted based on the court’s refusal to
    give a proposed instruction only when that refusal has caused serious prejudice to a litigant’s
    right to a fair trial.” Id.
    ¶ 103       As to IDOT’s submission of IPI Civil (2011) No. 300.51, which, again, states that “[t]he
    law does not permit an award of damages for the loss or reduction of traffic which may result
    from [the installation of a median or divider strip] [the establishment of a one-way traffic
    regulation], and you should not consider this factor in determining damages to the remainder”
    (emphasis added), the court did not abuse its discretion in finding that the instruction concerns
    damages from flow of traffic, an argument not raised by Dalzell and not based on the evidence
    before it and therefore would potentially confuse the jury.
    ¶ 104       The court also did not err in rejecting IDOT’s non-IPI instruction that “[t]he law does not
    permit an award of damages for circuity of travel.” A court’s decision to refuse a non-IPI
    instruction should not be disturbed absent an abuse of discretion. Parikh v. Gilchrist, 
    2017 IL App (1st) 160532
    , ¶ 33. Illinois Supreme Court Rule 239(a) (eff. Apr. 8, 2013) provides that
    applicable IPI instructions shall be given; non-IPI instructions may be given if the IPI
    instructions do not accurately state the law or if they do not cover a subject upon which the jury
    should receive instruction. The court did not abuse its discretion in determining that the jury
    did not require this instruction, which, as seen from the foregoing case discussion, reflects an
    oversimplification of the law (as well as an oversimplification of Greenwell, 
    45 Ill. App. 3d 159
    ), and that the instructions provided to the jury accurately reflected the relevant legal
    principles.
    ¶ 105                                E. Opening and Closing Statements
    ¶ 106       IDOT argues next that Dalzell’s counsel, in opening and closing statements,
    inappropriately invited the jury to render its verdict based on prejudice and sympathy.
    Specifically, IDOT asserts that counsel improperly touched on issues, such as responsibility
    and accountability, that fell outside the sole issue to be decided, i.e., just compensation. It
    asserts that the comments also improperly dwelt at length upon the jury’s duty to award just
    compensation, lest it violate Dalzell’s constitutional rights; invited the jury to award damages
    for the closure of the North Avenue driveway; and violated the court’s instruction that the jury
    afford both sides fair consideration. IDOT concedes that it offered no objection at trial to
    counsel’s arguments. However, IDOT asserts that we should review the issue for plain error
    because the comments deprived it of a fair trial and substantially impaired the integrity of the
    judicial process.
    ¶ 107       The plain-error doctrine may be applied in civil cases, but it finds much greater application
    in criminal cases. See Arient v. Shaik, 
    2015 IL App (1st) 133969
    , ¶ 37. Indeed,
    “application of the plain[-]error doctrine to civil cases should be exceedingly rare.” 
    Id.
     The
    doctrine may be applied in civil cases only where there exists a prejudicial error so egregious
    that it deprived the complaining party of a fair trial and substantially impaired the integrity of
    the judicial process. 
    Id.
     Our supreme court has stated that, in a civil case, the forfeiture doctrine
    will be strictly applied unless the “prejudicial error involves flagrant misconduct or behavior
    so inflammatory that the jury verdict is a product of biased passion, rather than an impartial
    consideration of the evidence.” Gillespie v. Chrysler Motor Corp., 
    135 Ill. 2d 363
    , 375-76
    (1990).
    - 26 -
    ¶ 108       Here, Dalzell argues that IDOT’s arguments must fail. He asserts that IDOT’s failure to
    object at trial to any of the “selective” comments with which it takes issue on appeal reflects
    that the comments were simply not so egregious that IDOT was deprived of a fair trial or that
    the integrity of the judicial process was impaired. Dalzell notes that the terms “responsibility”
    and “accountability” are particularly innocuous in eminent-domain settings because IDOT is,
    in fact, undisputedly “accountable” for any damages and “responsible” for paying just
    compensation. Dalzell asserts that, in a case such as this, referencing a property owner’s
    constitutional right to just compensation from a condemnor who is, in fact, accountable for
    damages it caused cannot be considered an appeal to a jury’s “base emotions of prejudice and
    sympathy.” We agree.
    ¶ 109       We are not convinced that any of the comments that IDOT highlights necessarily constitute
    error, let alone prejudicial error or flagrant misconduct so egregious that IDOT was deprived of
    a fair trial, the integrity of the judicial process was impaired, and there is a likelihood that the
    jury’s verdict resulted from biased passion. In contrast, for example, the plain-error doctrine
    was applied and a new trial awarded for the first time in a civil case by the supreme court in
    Belfield v. Coop, 
    8 Ill. 2d 293
    , 312-13 (1956), where the plaintiff’s counsel referred to the
    defendants as “thieves,” “usurpers,” and “defrauders,” suggested that defense counsel was
    disreputable, and further suggested that the jury should find for the plaintiff because he was a
    former judge. Dalzell’s mere references to responsibility and accountability are markedly
    different from the implications of immorality found flagrantly improper in Belfield. Further,
    this case is markedly different from Zoerner v. Iwan, 
    250 Ill. App. 3d 576
    , 585-86 (1993),
    another case cited by IDOT. In Zoerner, a panel of this court, despite forfeiture, concluded that
    a closing statement deprived the plaintiff of a fair trial where, although the jury’s sole task was
    determining proximate cause, the defense attorney emphasized that drinking and driving was
    wrong and then impressed upon the jury’s sense of moral outrage by asking it to reach a certain
    verdict because it would send a message against drunk driving and punish the plaintiff for
    antisocial behavior. Here, IDOT’s accountability for the taking and damages and its
    responsibility to pay just compensation are simply not controversial themes. Therefore,
    referencing those concepts did not unfairly impugn IDOT’s “character” or inflame the jurors’
    passions and sympathies. The subject of the North Avenue driveway was controversial, but the
    parties’ stipulation permitted discussion concerning its value and, ultimately, safety, which
    IDOT also raised through its evidence and in argument. Further, the jury was instructed that
    (1) opening and closing statements are summaries and should be disregarded if not based on
    the evidence or supported by the law, (2) it should not consider IDOT’s right to take the
    property, (3) fair consideration should be given to both parties, and (4) it should not be swayed
    by prejudice or sympathy. As such, the instructions safeguarded against any prejudice that
    might theoretically have arisen from the challenged comments.
    ¶ 110       In sum, for the foregoing reasons, this civil case does not present the “exceedingly rare”
    scenario warranting application of the plain-error doctrine. IDOT’s challenges to the opening
    and closing statements are forfeited.
    ¶ 111                            F. Kleszynski’s Valuation Testimony
    ¶ 112       IDOT argues that the trial court abused its discretion when it denied the motion to strike
    Kleszynski’s valuation testimony. Specifically, IDOT argues that Kleszynski improperly
    responded to the jury’s question with an example that did not follow proper valuation
    - 27 -
    methodology for a partial taking because he valued the part taken as a tract of land separate and
    distinct from the whole. See Department of Transportation v. Kelley, 
    352 Ill. App. 3d 278
    , 281
    (2004) (the part taken must not be valued as a separate tract from the whole). IDOT asserts that
    Kleszynski’s testimony was inconsistent and lacked veracity because he assigned the part
    taken a higher value per square foot than the property as a whole but then testified that, if one
    considers a strip of land completely divorced from the whole, its value would decrease. IDOT
    contends that the testimony relied on improper valuation methodology and should have been
    stricken and that it should be granted a new trial. We disagree.
    ¶ 113        First, we note that IDOT’s trial objection to this testimony concerned disclosure of the
    testimony, the example of signage, and alleged juror confusion. IDOT did not object on the
    basis that the testimony reflected improper valuation methodology. As such, we may deem this
    argument forfeited. K&K Iron Works, Inc. v. Marc Realty, LLC, 
    2014 IL App (1st) 133688
    ,
    ¶ 25 (arguments not raised before the trial court are forfeited and cannot be raised for the first
    time on appeal).
    ¶ 114        Second, even if not forfeited, the argument fails. We review for an abuse of discretion a
    trial court’s decision to strike an expert’s testimony. See, e.g., In re Marriage of Hunter, 
    223 Ill. App. 3d 947
    , 955 (1992) (trial court did not abuse its discretion where it refused to strike an
    expert’s testimony as based upon hearsay).
    ¶ 115        Here, IDOT’s argument regarding improper valuation methodology relies upon a mistaken
    premise, i.e., that Kleszynski valued the part taken separate from the whole, thereby
    misrepresenting the value of the part taken. As acknowledged by the trial court, Kleszynski
    made clear (on multiple occasions) that he assessed the value of the part taken in terms of its
    contributory value to the property as a whole. He explained that various parts of a property
    have different contributory values to the whole and that the part taken here had a higher
    contributory value to the whole than would a different portion of the property. We do not find
    this concept inconsistent with Kleszynski’s testimony that valuing a small strip of land in total
    isolation would result in a lower value for that strip of land. Therefore, the court did not abuse
    its discretion in denying IDOT’s motion to strike the testimony.
    ¶ 116                                   G. Dalzell Cross-Examination
    ¶ 117       IDOT next argues that the trial court abused its discretion when it sustained Dalzell’s
    objection to cross-examination concerning his income. IDOT contends that its reliance on
    Shell Oil was sound and that it should have been allowed to pursue this line of questioning to
    discredit Dalzell and “destroy” his direct testimony that ingress and egress were worse after the
    taking. “IDOT was prejudiced because the jury could have found Mr. Dalzell’s testimony
    regarding ingress/egress not credible because his income largely remained the same.” IDOT
    asserts that it should be granted a new trial.
    ¶ 118       Evidentiary issues, including determining the scope of a witness’s cross-examination, fall
    within the trial court’s sound discretion. Sekerez v. Rush University Medical Center, 
    2011 IL App (1st) 090889
    , ¶ 70.
    ¶ 119       The court did not abuse its discretion in finding that this case concerned the market value of
    the property itself, not Dalzell’s income that he generates from the property. The court found
    that there was no discovery concerning Dalzell’s income before and after the taking. Dalzell
    was not claiming damages due to loss of income. Rather, he was claiming that physical
    alterations to the property affected ingress and egress. Therefore, where the evidence
    - 28 -
    concerned only the valuation of the property itself, not Dalzell’s business income, the court did
    not abuse its discretion in sustaining Dalzell’s objection to IDOT’s income question.
    ¶ 120       We note that IDOT’s reliance on Shell Oil is misplaced. There, the property had the same
    number of entrances before and after the taking, but the driveways were made smaller, and
    vehicles needed to make sharper turns in order to enter. Shell Oil, 156 Ill. App. 3d at 306.
    IDOT’s motion in limine to exclude testimony relating to the volume of sales was denied.
    Shell, therefore, presented evidence that, after the taking, an average of 34,000 gallons of
    gasoline were shipped each month to the station, whereas, before the taking, an average of
    55,300 gallons had been shipped each month. Further, Shell presented a witness who testified
    to the value of the property taken as well as the value of the remainder, noting that “he took the
    decreased sales into account, but he viewed the decreased sales only as an indication that the
    taking substantially impaired access to the station. He testified that ease of ingress is of
    primary importance in determining the value of a service station.” Id. The court held that the
    evidence was properly admitted, noting that the witness relied on sales figures solely as
    substantiation of Shell’s claim that access to the station was worsened by the taking. Id. at 308.
    ¶ 121       Therefore, in Shell Oil, where the same number of entrances to the property existed after
    the taking and no barrier median or other impediment was at issue, Shell could substantiate its
    claim to a material impairment of access only by showing decreased sales. Further, Shell’s
    witness had relied upon decreased sales in his valuation opinion, and he testified, without
    objection, that ease of ingress is of primary importance for determining the value of a service
    station. Id. at 306. In contrast, here, the access issues were clearly established without any need
    to resort to income. Further, no expert here relied on income or sales to derive a valuation
    opinion. Again, the valuation at issue here was of the property, not the business. Therefore, had
    the cross-examination been allowed, the jury would have been forced to reconcile on its own
    whether any changes in income (or lack thereof) impacted the valuation opinions that it had
    received. Further, the court properly noted that changes in income could relate to many factors
    other than access and that, therefore, such testimony could cause unfair prejudice not
    outweighed by any probative value. In sum, the court’s decision to sustain the objection was
    not an abuse of discretion.
    ¶ 122                                   H. Abrams’s Remedy Plan
    ¶ 123       IDOT argues that the trial court abused its discretion when it allowed Abrams to testify to
    his remedy plan because Abrams’s opinion that Dalzell would need to obtain permission from
    his neighbor in order to implement the remedy plan was not disclosed pursuant to Rule
    213(f)(3). IDOT asserts that the only thing Dalzell pointed to in support of disclosure was a
    demonstrative exhibit. IDOT finally asserts that the court’s ruling was unfair in that it allowed
    Dalzell to sabotage his own remedy plan by suggesting that it could not be implemented.
    ¶ 124       We cannot find an abuse of discretion in the court’s decision to allow Abrams’s
    remedy-plan testimony. Apparently, the remedy plan contemplated Dalzell’s use of his
    neighbor’s property. That the use of the neighbor’s property would require some form of
    permission is, as counsel noted, more akin to fact than opinion. We reject IDOT’s feeble
    argument that the ruling was unfair in that it allowed Dalzell to sabotage his own remedy plan.
    Pointing out the steps that would need to be taken to implement the plan does not equate to an
    assertion that those steps could not be completed. In sum, we cannot find unreasonable the
    court’s decision that the testimony reflected a common-sense implication of a demonstrative
    - 29 -
    drawing disclosing a remedy plan.
    ¶ 125                                          I. Cumulative Error
    ¶ 126        In its reply brief, IDOT raises for the first time an argument that cumulative errors warrant
    a new trial. As this argument was improperly raised in the reply brief, we need not address it.
    An appellant’s arguments must be made in its opening brief and cannot be raised for the first
    time in the reply brief. See Ill. S. Ct. R. 341(h)(7) (eff. July 1, 2008) (“Points not argued are
    waived and shall not be raised in the reply brief, in oral argument, or on petition for
    rehearing.”); see also In re Marriage of Winter, 
    2013 IL App (1st) 112836
    , ¶ 29.
    ¶ 127        In any event, while no litigant is assured a perfect trial, the litigant must not be denied a fair
    trial. Andes v. Lauer, 
    80 Ill. App. 3d 411
    , 416 (1980). As such, while individual errors standing
    alone might not be sufficient to require a new trial, cumulative errors can be so prejudicial as to
    justify a new trial. 
    Id.
     However, “[a]s we find no error, we necessarily find no cumulative
    error.” In re Estate of Mankowski, 
    2014 IL App (2d) 140154
    , ¶ 63.
    ¶ 128                                       III. CONCLUSION
    ¶ 129       For the reasons stated, we affirm the judgment of the circuit court of Du Page County.
    ¶ 130       Affirmed.
    - 30 -