Stenstrom Petroleum Services Group, Inc. v. Mesch ( 2007 )


Menu:
  •                                            No. 2--07--0504               Filed: 9-7-07
    IN THE
    APPELLATE COURT OF ILLINOIS
    SECOND DISTRICT
    STENSTROM PETROLEUM SERVICES                       )   Appeal from the Circuit Court
    GROUP, INC.,                                       )   of Winnebago County.
    )
    Plaintiff-Appellant and                     )
    Cross-Appellee,                             )
    )
    v.                                                 )   No. 07--CH--366
    )
    ROBERT MESCH,                                      )
    )
    Defendant-Appellee and                      )
    Cross-Appellant                             )
    )   Honorable
    (Precision Petroleum Installation, Inc.,           )   Ronald L. Pirrello,
    Defendant-Appellee).                               )   Judge, Presiding.
    JUSTICE CALLUM delivered the opinion of the court:
    I. INTRODUCTION
    Plaintiff, Stenstrom Petroleum Services Group, Inc., sued defendants, Robert Mesch (its
    former employee) and Precision Petroleum Installation, Inc. (New PPI) (Mesch's current employer),
    alleging, inter alia, breach of a covenant not to compete, violations of the Illinois Trade Secrets Act
    (Trade Secrets Act or Act) (765 ILCS 1065/1 et seq. (West 2006)), and breach of fiduciary duty.
    Stenstrom sought an injunction and damages. The trial court granted Stenstrom a preliminary
    injunction to enforce the covenant not to compete and denied relief on the other grounds alleged in
    its complaint.    Stenstrom appeals, arguing that the trial court erred in determining the
    No. 2--07--0504
    commencement date of the preliminary injunction and in declining to enjoin Mesch and New PPI
    for breach of fiduciary duty and violations of the Act. Mesch cross-appeals, arguing that the
    covenant not to compete is unenforceable. We affirm.
    II. BACKGROUND
    Stenstrom filed its complaint on March 7, 2007. The trial court entered a temporary
    restraining order (TRO) on March 8, 2007. The court heard testimony on Stenstrom's petition for
    a preliminary injunction on March 16 and April 3, 2007. It entered the preliminary injunction on
    April 25, 2007. The following testimony was presented at the hearing on the preliminary injunction.
    A. Mesch
    Mesch began working in the petroleum industry in 1974, installing equipment such as
    underground storage tanks and petroleum piping systems. For subsequent employers, Mesch rebuilt
    damaged gasoline dispensers and pumps, maintained and repaired service station equipment, and
    worked as a warehouse manager and a purchasing manager. Mesch also performed outside sales
    and, starting in 1986, engaged in estimating and project management.
    Stenstrom installs and maintains equipment in the petroleum industry, including the
    installation and removal of petroleum tanks, pumps, and electronics. It also repairs such equipment.
    A separate Stenstrom company performs excavation work.
    On June 18, 2003, Stenstrom purchased Precision Petroleum, Inc. (Old PPI). Mesch had
    worked for Old PPI for about seven years. On the same day that it purchased Old PPI, Stenstrom
    hired Mesch, who signed a noncompete agreement and a confidentiality agreement. Mesch
    performed the same work for Stenstrom that he had for Old PPI, working as an estimator and project
    manager.
    -2-
    No. 2--07--0504
    The noncompete agreement, or restrictive covenant, Mesch signed appears in a document
    entitled "Petroleum Services Group Training Agreement," at paragraph 3. The covenant provides:
    "RESTRICTIVE COVENANT. Employee, as additional consideration for the training,
    classroom study and materials provided by the Company, shall not for a period of six (6)
    months from the date of termination of his employment with the Company, engage directly
    or indirectly in any capacity in the excavation or equipment repair field in the counties of
    Winnebago and Boone (which constitute the Company's trade area or areas), except with
    Company's written consent. In addition to any other rights or remedies available to the
    Company for breach of this Agreement, the Company shall be entitled to enforcement by
    preliminary restraining order and injunction. In the event the Company is forced to take legal
    action against Employee under this Agreement, all of the Company's costs and expenses of
    such action, including reasonable [attorney] fees, shall be paid by Employee." (Emphasis
    added.)
    Mesch worked for Stenstrom between June 2003 and December 2006. He estimated
    petroleum jobs, bid on the jobs, and managed successful bids. During his tenure with Stenstrom,
    Mesch bid on 378 jobs and managed 121 jobs.
    He acknowledged that, while at Stenstrom, he received training in the Timberline and Excel
    computer programs. The Timberline database limits employees' access to only those folders that
    they are granted permission to use. Mesch stated that he merely "dabbled" in using the program.
    He denied using Timberline to prepare bids in December 2006. He did access it, however, to retrieve
    job costs and reports.
    -3-
    No. 2--07--0504
    In calculating his bids, Mesch used an Excel spreadsheet and not the Timberline estimating
    program that other Stenstrom project managers used. Addressing the Excel spreadsheet, Mesch
    explained that it was first developed by someone at Old PPI. It began as a "crude spreadsheet, which
    was just quantities, list prices, some discounts, and the way the owner of the company put it, he
    wanted something that was better than just doing a bid off a napkin." Mesch continued to use the
    spreadsheet in estimating projects, with "great revisions and modifications" that he incorporated into
    it.
    Mesch described his spreadsheet calculations as follows. The material and labor worksheet
    contains part numbers, quantities, list prices, discounts off of list prices, and extended pricing. The
    spreadsheet also contains markups to net prices. Mesch manually entered quantities, subcontractor
    bids, labor hours, and markup percentages. The "bid" tab incorporates the material and labor data.
    Mesch manually revised entries concerning the scope of the work.
    On December 22, 2006, Mesch resigned from his job with Stenstrom. He last worked for
    Stenstrom on December 26, 2006. His salary at that time was $73,840. Mesch started copying
    Stenstrom files in early-to-mid 2006 for the purpose of working at home on Stenstrom's behalf.
    From this period through his termination date, he did not use any of the copied materials to prepare
    bids for any entity other than Stenstrom.
    After he left Stenstrom, Mesch commenced working for a newly formed entity--New PPI.
    Mesch testified that all of New PPI's customers are also Stenstrom customers and that New PPI has
    bid on jobs only for Stenstrom customers. He also stated that New PPI has discussed bids only with
    Stenstrom customers. New PPI's logo is similar to Old PPI's logo. Mesch conceded that he
    referenced a computer file of the Old PPI logo, which he copied from Stenstrom, in order to create
    -4-
    No. 2--07--0504
    the New PPI logo. Mesch agreed that he currently has an unwritten agreement with New PPI under
    which he will receive 20% of its net profits in addition to his salary. His job title is project manager/
    estimator. Mesch denied that he is an officer, director, or shareholder of New PPI.
    Mesch explained that New PPI purchases its equipment from a distributor. Stenstrom,
    however, purchases directly from manufacturers. According to Mesch, New PPI does not obtain the
    same prices from manufacturers as does Stenstrom. Stenstrom receives much deeper discounts than
    New PPI because it does not go through a distributor, which takes a markup. To calculate bids at
    New PPI, Mesch obtained a list of manufacturer discounts from Source North America and
    incorporated the data into the Excel spreadsheet, thus changing the discounts.
    Mesch stated that New PPI, unlike Stenstrom, does not perform any excavation work or
    equipment repair work. It relies instead on subcontractors. Mesch testified that Stenstrom does the
    majority of its own concrete work and excavation work. As to electrical contractors, Mesch has used
    at New PPI contractors that he used at Stenstrom and previously at Old PPI.
    According to Mesch, in September 2006, he copied a subdirectory entitled "Estimating" from
    Stenstrom's server onto his personal Dell Jukebox, a music player. He testified that he did so with
    his supervisor's knowledge. The directory contained folders that, in turn, contained subfolders for
    various jobs. Mesch testified that not all of the jobs involved clients, but included entities for which
    Stenstrom had prepared unsuccessful bids. In addition to the music player, Mesch conceded that he
    copied Stenstrom information onto a travel drive on December 1, 2006. Mesch copied the files from
    the music player and travel drive to his home computer and then onto two DVDs. He copied the
    information for the purpose of using it for New PPI and conceded that he did access the information
    while working for New PPI. He did not use the files from the music player at New PPI, but only the
    -5-
    No. 2--07--0504
    files from the travel drive. Mesch testified that many of the files were from Old PPI and that
    Stenstrom received them because he brought them to Stenstrom. He conceded that the files were on
    a computer that Stenstrom purchased. Mesch destroyed the DVDs before he left Stenstrom. Further,
    Mesch conceded that some of the data he copied from Stenstrom he used to prepare bids at New PPI.
    He did this on his own and not at New PPI's request.
    As of the hearing on the preliminary injunction, Mesch no longer possessed the computer
    files he copied from Stenstrom's computers. Within three days after the TRO was issued, Mesch
    turned over the Stenstrom data he had copied. Mesch further testified that he no longer had the
    spreadsheet available to him to prepare bids. However, he testified that he could reproduce it in two
    to three days because he developed the original. He would not have to rely upon any information
    from Stenstrom in order to recreate it. All of the information he requires "is readily available from
    manufacturers." Also, he knows from experience the discounts that Stenstrom obtains from its key
    suppliers. He can recite many of the discounts from memory.
    While working for Old PPI, Mesch prepared six bids for State Oil. State Oil was one of Old
    PPI's better customers. His contact at the company was Jim Peters. Mesch also prepared 12 bids
    for Road Ranger. His contact there was John Carabelli. Road Ranger was Old PPI's largest
    customer.
    Mesch further testified that Stenstrom's Road Ranger Hampshire computer file is in New
    PPI's Road Ranger Hampshire computer file. Mesch conceded that he bid on Road Ranger's
    Hampshire project while at Stenstrom and then bid on a larger version of that project while working
    at New PPI. Mesch also conceded that he successfully bid on a job for State Oil, the North Chicago
    -6-
    No. 2--07--0504
    project, for New PPI after having bid on the project for Stenstrom. Mesch testified that he used
    Stenstrom drawings to make the "CAD" drawings for New PPI to submit with its bid.
    New PPI's only successful bid as of the hearing date was the State Oil North Chicago project.
    Mesch bid on the project in September 2006 for Stenstrom. That bid was rejected. After he left
    Stenstrom, Mesch called Jim Peters and informed him that he had left Stenstrom. While working
    at New PPI, Mesch re-bid on the project, at Jim Peters' request. New PPI's bid was higher than
    Stenstrom's bid. At the time he left Stenstrom, State Oil had not yet rejected Stenstrom's bid for the
    North Chicago job. Comparing Stenstrom's unsuccessful bid with New PPI's successful bid, Mesch
    testified that the only differences are the names on the bids, the prices, and the payment terms.
    Mesch conceded that Stenstrom's name appears in several places in another bid he submitted
    on behalf of New PPI. Mesch also conceded that while working at New PPI he consulted Stenstrom
    bid information to obtain subcontractor electrical, canopy, and tank costs for bids. Mesch used the
    spreadsheet at New PPI with the new company's costs substituted in the place of Stenstrom's costs.
    B. David Sockness
    David Sockness, president of Stenstrom and of Stenstrom Excavation and Blacktop, testified
    on Stenstrom's behalf that both companies are owned by the same holding company. Sockness
    manages Stenstrom. He explained that the company, which has been in the petroleum business since
    1982, installs petroleum equipment, such as tanks, piping, dispensers, islands, point-of-sale devices,
    tank-monitoring equipment, submersible pumps, and manholes. It also services the equipment it
    installs and places concrete. Stenstrom operates within a 100-mile radius of Rockford. In some
    cases, the company performs work outside this area.
    -7-
    No. 2--07--0504
    Sockness acknowledged that Stenstrom uses a spreadsheet to create its bids and that the
    information therein is not contained in the final bids submitted to customers. This information is
    valuable to Stenstrom. It includes all of its pricing, including material, labor, and equipment, and
    includes manufacturer discounts, vendor discounts, and profit margins. It also contains labor hours
    for jobs and labor rates. The spreadsheet can be used to determine future Stenstrom bids. Two
    current bidders use the spreadsheet. Stenstrom purchased the spreadsheet when it purchased Old
    PPI. It also purchased the Old PPI logo. According to Sockness, New PPI's logo is the same as Old
    PPI's logo. Sockness is unaware if Stenstrom registered Old PPI's logo or trade name. Sockness
    further testified that Stenstrom is moving away from the Timberline program and toward using the
    spreadsheet to bid on jobs.
    Stenstrom's largest customers are Kelley Williamson, Road Ranger, and State Oil. They
    comprise about 40% of Stenstrom's petroleum installation business and 40% of its petroleum service
    business. Old PPI had a strong relationship with Road Ranger, and this is one of the reasons
    Stenstrom bought Old PPI. This was also the case with State Oil. Stenstrom's second tier of clients
    includes Vista Marketing and Combined Oil. They comprise about 10% of Stenstrom's installation
    business and 10% of its service business. Stenstrom has never lost a major client.
    Stenstrom handles all of Kelley Williamson's and Vista's petroleum installation business.
    It performs about 50% of Road Ranger's local petroleum installation business. According to
    Sockness, Stenstrom maintains its relationships with its customers via marketing campaigns,
    personal calls, personal visits, and business meetings. Its client entertainment budget is $20,000.
    Sockness conceded that Road Ranger and State Oil get competitive bids from other companies for
    installation work. Also, Stenstrom does not have any agreement with Kelley Williamson to be its
    -8-
    No. 2--07--0504
    exclusive provider of installation services. Further, when Stenstrom purchased Old PPI, there was
    no promise by Road Ranger that a certain percentage of its business would thereafter go to
    Stenstrom.
    Stenstrom usually uses Nicholson Electric as its electrician. Al Hoover owns the company.
    New PPI also uses Nicholson Electric. Mesch would have had contact with Hoover at Nicholson
    Electric while Mesch worked at Stenstrom and would have developed a relationship with him.
    Sockness conceded that he is not aware of any reason Mesch should not go to Nicholson Electric to
    have electrical work done for New PPI.
    C. Brian Cotti
    Brian Cotti is the information technology manager for the Stenstrom companies. He testified
    that Stenstrom takes several steps to keep its information confidential. They include utilizing a
    firewall at the perimeter of its computer network; "NTFS" permissions that are built into the
    Windows operating system to determine whether a user is allowed to modify, open, or delete
    documents; computer authentication; and user authentication, which requires that a user log in to the
    network with a valid identification and password. Cotti further explained that the Timberline
    database similarly limits employees' access to information. The server room at Stenstrom is
    accessible only by key, and the physical job files are accessible only by key or key code.
    Cotti further testified that he ran a log of Timberline access and that the log showed that
    Mesch attempted to run tasks on Timberline, some of which failed. The failures occurred because
    Mesch did not have appropriate permissions to complete the tasks. Mesch was attempting to print
    a certain report.
    D. Robert Rowald
    -9-
    No. 2--07--0504
    Robert Rowald is a systems administrator and forensic examiner at Trekk Design, where he
    is in charge of the computer systems, servers, work stations, and related equipment, as well as
    forensic examinations. He holds several certifications and teaches certification courses. Rowald
    testified that a forensic copy is a bit-for-bit copy of a computer file, unlike a CD or DVD, which will
    change the last access date and modified date and will not show slack space, the area where files
    have been deleted, or unallocated space. Rowald made forensic copies for Stenstrom of one of its
    hard drives, a home hard drive, an external drive, and two DVDs. He was unable to make a forensic
    copy of a Dell DJ MP3 player, but did make a standard copy of the information on that device.
    Rowald also utilized Beyond Compare software to compare the binary codes in software
    files. He testified that the industry standard above which a work is considered definitely derivative
    is 70%. Comparing a "dwg" file called "Ranger Hampshire - Line Repair," dated September 21,
    2005, from the Dell DJ, with "Ranger Hampshire - D-S-L Gas Island Config.," dated February 17,
    2007, from the business hard drive, revealed that well over 70% of the data lines (i.e., zeros and
    ones) matched. Rowald explained that one could not redraw a "CAD" drawing by hand and have
    it match as much as these files did. According to Rowald, the only way to get this many lines to
    match is to make a file from another file.
    Rowald also compared a file named "Ranger Hampshire - Line Repair," dated September 21,
    2005, from the Dell DJ, with a file called "Ranger Hampshire - Diesel Lane Conversion," dated
    February 15, 2007, from the business hard drive, and he testified that the match rate was significantly
    over 70%: 5,242 lines matched and 101 did not.
    Additional exhibits of "data compares" were admitted into evidence. The parties stipulated
    that one set of files came from Mesch's/New PPI's computers; that the comparisons compare Dell
    -10-
    No. 2--07--0504
    DJ documents with Stenstrom hard drive documents; and that they all have match rates above 85%.
    E. James Peters
    James Peters, State Oil Company's general manager, testified on defendants' behalf that State
    Oil is a petroleum distributor that owns gas stations, the majority of which are in the Chicago and
    Lake County areas. Some are also in Boone and Winnebago Counties. Peters testified that he has
    known Mesch for 20 years. He came to know Mesch because Mesch's father worked for a company
    owned by State Oil.
    Peters testified that State Oil did business with Old PPI. Peters developed a business
    relationship with Mesch as a result. They also developed a personal relationship, as they became
    friends. State Oil did business with Stenstrom after Stenstrom purchased Old PPI. According to
    Peters, Mesch's employment with Stenstrom after the Old PPI purchase was a factor in his decision
    to do business with Stenstrom. He explained that he had never done business with Stenstrom prior
    to this time and that, when he found out that Mesch would be working for Stenstrom, he knew that
    he would be dependable.
    Peters explained that, for each of its jobs, State Oil receives about three bids. Peters selects
    the winning bid on the grounds of price and familiarity of entities and people, even if the result is
    selecting a higher bid. Mesch is one person with whom Peters is comfortable working.
    In about November 2006, Mesch informed Peters that he was leaving Stenstrom to work at
    New PPI. He asked if State Oil "would support him in the bidding process." Since joining New PPI,
    Mesch submitted to State Oil a bid for the North Chicago project. Mesch submitted the bid at Peters'
    -11-
    No. 2--07--0504
    request. Peters currently sends his repair work almost exclusively to Stenstrom. According to
    Peters, Mesch has not attempted to secure service-related repair work for New PPI.
    F. John Carabelli
    John Carabelli, vice president of construction at Road Ranger, testified on defendants' behalf
    that he has known Mesch for nine years. They met when Mesch worked at Old PPI. Carabelli
    developed a degree of trust and confidence in the work Mesch performed for Road Ranger. Part of
    the basis for continuing to do business with Stenstrom was the fact that Mesch worked there.
    Between 2003 and 2006, Road Ranger did not exclusively use Stenstrom for installation work. For
    the last three to four years, most of Road Ranger's projects have been done on a bid basis as opposed
    to a cost-plus basis. In December 2006, Mesch informed Carabelli that he was leaving Stenstrom
    to work for New PPI. Since January 2007, Road Ranger has received bids from New PPI, at
    Carabelli's request. As to the Hampshire project bid, it has not been determined if New PPI will get
    the job. Carabelli further testified that he has provided Mesch with "AutoCAD" drawings for gas
    stations so that Mesch could submit bids to Carabelli.
    G. Trial Court's Order
    On April 9, 2007, the trial court issued a memorandum opinion granting in part and denying
    in part Stenstrom's petition for a preliminary injunction. Addressing the covenant not to compete,
    the court found that it was reasonable in scope and time and supported by adequate consideration.
    Accordingly, it found that Stenstrom was entitled to injunctive relief in Winnebago and Boone
    Counties, "for whatever time remains on the covenant." As to the remaining counts, the court found
    "either" that Stenstrom failed to show a likelihood of prevailing on the merits "or that there is ample
    -12-
    No. 2--07--0504
    legal remedy available for the cause of action examined." It denied Stenstrom relief against New
    PPI.
    On April 25, 2007, the court entered the injunction in conformance with its opinion. Finding
    that Stenstrom had met the requirements for a preliminary injunction for violations of the restrictive
    covenant, the trial court enjoined Mesch from "performing, directly or indirectly, in any capacity,
    petroleum excavation or equipment repair work in Boone and Winnebago Counties for a period of
    six (6) months from the date of the termination of his employment" with Stenstrom. As to
    Stenstrom's claims of breach of fiduciary duty and violations of the Act, the court found that
    Stenstrom failed to show a likelihood of prevailing on the merits "and/or" a lack of an adequate
    remedy at law. Finally, the court found that Stenstrom "failed to meet its burden" to obtain an
    injunction against New PPI. Stenstrom timely appealed, and Mesch timely cross-appealed.
    III. ANALYSIS
    A. Stenstrom's Appeal
    1. Breach of Restrictive Covenant Claim
    In its appeal, Stenstrom argues first that the trial court erred in enjoining Mesch, based upon
    the restrictive covenant, for six months from the date he left Stenstrom's employment. Stenstrom
    contends that the six months should have commenced as of the date Mesch ceased breaching the
    restrictive covenant--March 8, 2007, the date the TRO was entered. Stenstrom reasons that,
    otherwise, the injunction will apply to conduct that has already occurred. It argues that it is entitled
    to the full six-month period of noncompetition for which it bargained.
    Stenstrom relies on Prairie Eye Center, Ltd. v. Butler, 
    329 Ill. App. 3d 293
    (2002). In that
    case, the defendant entered into a two-year restrictive covenant. The trial court, upon finding the
    -13-
    No. 2--07--0504
    covenant valid and enforceable, entered a preliminary injunction in 1999, finding that the defendant
    repeatedly violated his covenant not to compete. Following trial, the court entered a permanent
    injunction in 2000, extending the covenant by two years. On appeal, the court affirmed the trial
    court's judgment.
    We find Prairie Eye Center distinguishable because the covenant in that case provided that,
    upon breach of the covenant, the noncompetition period would extend by a time equal to the period
    beginning when the violation commenced and ending when the activities constituting the violation
    terminated. As the court noted, "the agreement itself provides for an extension of the restriction
    upon proof of its breach." Prairie Eye 
    Center, 329 Ill. App. 3d at 305
    . Here, in contrast, the
    restrictive covenant provides that Mesch "shall not for a period of six (6) months from the date of
    termination of his employment with the Company" work in the excavation or repair field in
    Stenstrom's trade area. (Emphasis added.) There is no provision in the agreement for an extension
    of this period or any modification of the commencement date.
    We reject Stenstrom's argument that the Prairie Eye Center court's holding was an alternative
    one and not a necessary requirement for granting relief in that case. Our review of the decision does
    not lead us to conclude that the court intended such a reading. In explaining its holding, the court
    first contrasted the purpose of monetary damages as opposed to injunctive relief. Prairie Eye 
    Center, 329 Ill. App. 3d at 304
    . The court then elaborated that the injunction gave the employer the agreed-
    upon period of noncompetition. Prairie Eye 
    Center, 329 Ill. App. 3d at 304
    . Notwithstanding the
    use of the word "further" in the paragraph containing the holding upon which we rely, the Prairie Eye
    Center court clearly rejected the employee's argument that the trial court erred in awarding both
    monetary damages and injunctive relief for an additional two-year term based on the restrictive
    -14-
    No. 2--07--0504
    covenant. In addition to providing for an extension, the covenant in that case also contemplated the
    assessment of damages. Prairie Eye 
    Center, 329 Ill. App. 3d at 304
    . The court concluded its opinion
    by stating that "[t]he trial court simply enforced the parties' agreement." Prairie Eye Center, 329 Ill.
    App. 3d at 305.
    In summary, we reject Stenstrom's argument that the trial court erred in enjoining Mesch with
    the commencement date as his last day of employment with Stenstrom.
    2. Trade Secrets Act Claim Against Mesch
    Next, Stenstrom argues that the trial court erred in denying it a preliminary injunction against
    Mesch based on violations of the Trade Secrets Act. In its complaint, Stenstrom alleged that its
    confidential information constitutes trade secrets under the Act and that it has exercised reasonable
    efforts to maintain the secrecy and confidentiality of its information. It further alleged that this
    information is not generally known by its competitors and, if known, would confer an economic
    benefit to them. According to Stenstrom, Mesch knew that its confidential information constituted
    trade secrets and he disclosed, misappropriated, and misused the secrets for his own benefit, resulting
    in injury to Stenstrom. Stenstrom requested injunctive relief, as well as damages, attorney fees, and
    an order directing Mesch to return to it all confidential information in his possession or control.
    A preliminary injunction is a provisional remedy granted to preserve the status quo pending
    a hearing on the merits of a case. It is "an extraordinary remedy used only in situations where an
    extreme emergency exists and serious harm would result in the absence of an injunction." Audio
    Properties, Inc. v. Kovach, 
    275 Ill. App. 3d 145
    , 147 (1995). To obtain a preliminary injunction, a
    party must establish that: (1) the party possesses a clear right or interest needing protection, such as
    confidential information; (2) the party has no adequate remedy at law; (3) irreparable harm will result
    -15-
    No. 2--07--0504
    if the preliminary injunction is not granted; and (4) there is a reasonable likelihood of success on the
    merits. Hanchett Paper Co. v. Melchiorre, 
    341 Ill. App. 3d 345
    , 351 (2003); see also Appelbaum
    v. Appelbaum, 
    355 Ill. App. 3d 926
    , 933 (2005). "Because a preliminary injunction is designed to
    preserve the status quo pending a decision on the merits, the plaintiff need not carry the same burden
    of proof that is required to support the ultimate issue." LSBZ, Inc. v. Brokis, 
    237 Ill. App. 3d 415
    ,
    425 (1992); see also Shapiro v. Regent Printing Co., 
    192 Ill. App. 3d 1005
    , 1009-10 (1989)
    ("purpose of a preliminary injunction is to raise a fair question as to the existence of a right needing
    protection, not to decide controverted facts or the ultimate merits"). To satisfy the first and fourth
    requirements, "a plaintiff need only raise a fair question as to the existence of the right which [it]
    claims and lead the court to believe that [it] will probably be entitled to the relief requested if the
    proof sustains [its] allegations." 
    LSBZ, 237 Ill. App. 3d at 425
    . "On review, we will not disturb a
    trial court's decision to grant a preliminary injunction, absent an abuse of discretion." Hanchett
    
    Paper, 341 Ill. App. 3d at 351
    .
    The trial court found that Stenstrom failed to establish a likelihood of prevailing on the merits
    of its Trade Secrets Act claim against Mesch "and/or" that it failed to establish that there is no
    adequate legal remedy available.
    a. Protectable Interest and Likelihood of Success on the Merits
    We begin our analysis by examining whether Stentrom has a protectable interest. Under
    Illinois law, an employer's trade secrets are a protectable interest. See Liebert Corp. v. Mazur, 
    357 Ill. App. 3d 265
    , 276 (2005).
    The Act provides, in relevant part:
    -16-
    No. 2--07--0504
    " 'Trade secret' means information, including but not limited to, technical, or non-
    technical data, a formula, pattern, compilation, program, device, method, technique, drawing,
    process, financial data, or list of actual or potential customers or suppliers, that:
    (1) is sufficiently secret to derive economic value, actual or potential, from not being
    generally known to other persons who can obtain economic value from its disclosure or use;
    and
    (2) is the subject of efforts that are reasonable under the circumstances to maintain
    its
    secrecy or confidentiality." 765 ILCS 1065/2(d) (West 2004).
    Thus, a plaintiff must meet two requirements to show that its information is a trade secret under the
    Act. First, it must show that the information was sufficiently secret to give it a competitive
    advantage. 765 ILCS 1065/2(d)(1) (West 2004); 
    Liebert, 357 Ill. App. 3d at 276
    . Second, it must
    show that it took affirmative measures to prevent others from acquiring or using the information.
    765 ILCS 1065/2(d)(2) (West 2004); 
    Liebert, 357 Ill. App. 3d at 276
    .
    In addition to the Act's requirements, when determining whether a trade secret exists courts
    often consider six common-law factors derived from section 757 of the Restatement (First) of Torts.
    See, e.g., ILG Industries, Inc. v. Scott, 
    49 Ill. 2d 88
    , 93 (1971), citing Restatement (First) of Torts
    §757, Comment b, at 6 (1939); see also 
    Liebert, 357 Ill. App. 3d at 276
    -77. They include: (1) the
    extent to which the information is known outside the plaintiff's business; (2) the extent to which it
    is known by employees and others involved in the plaintiff's business; (3) the extent of measures
    taken by the plaintiff to guard the secrecy of the information; (4) the value of the information to the
    plaintiff and to the plaintiff's competitors; (5) the amount of effort or money expended by the
    -17-
    No. 2--07--0504
    plaintiff in developing the information; and (6) the ease or difficulty with which the information
    could be properly acquired or duplicated by others. 
    Liebert, 357 Ill. App. 3d at 277
    .
    The protection afforded trade secrets reflects a balancing of conflicting social and economic
    interests. ILG 
    Industries, 49 Ill. 2d at 93
    . Information that is generally known or understood within
    an industry, even if not known to the public at large, does not qualify as a trade secret. Learning
    Curve Toys, Inc. v. PlayWood Toys, Inc., 
    342 F.3d 714
    , 722 (7th Cir. 2003). Information that is
    derived from public sources but requires laborious accumulation, culling, and/or analysis of the
    public information can, however, still qualify as a trade secret. See United States Gypsum Co. v.
    LaFarge North America, Inc., No. 03--C--6027, slip op. at 14 (N.D. Ill. April 3, 2007). In other
    words, where an employer has invested substantial time, money, and effort to obtain a secret
    advantage, the secret should be protected from an employee who obtains it through improper means.
    Delta Medical Systems v. Mid-America Medical Systems, Inc., 
    331 Ill. App. 3d 777
    , 791 (2002).
    "Nevertheless, in a competitive market, an employee must be entitled to utilize the general
    knowledge and skills acquired through experience in pursuing his or her chosen occupation." Delta
    Medical 
    Systems, 331 Ill. App. 3d at 791
    . Where information can be readily duplicated without
    considerable time, effort, or expense, it is not a trade secret. Hamer Holding Group, Inc. v. Elmore,
    
    202 Ill. App. 3d 994
    , 1011-12 (1990); see also Delta 
    Medical, 331 Ill. App. 3d at 792
    .
    Stenstrom contends that the information within its Excel bid spreadsheets that Mesch copied
    qualifies as a trade secret because it reveals Stenstrom's material costs, labor costs, profit margin,
    and future bids. Stenstrom further contends that it has made a reasonable effort to keep its
    information secret. Stenstrom notes that the bid spreadsheet information is not disclosed to
    -18-
    No. 2--07--0504
    customers and, so, is sufficiently secret to give Stenstrom a competitive advantage.1 Also, it secures
    its computer network with passwords and authentications. Employees with passwords are limited
    as to which files they can access, and the area containing physical files cannot be entered except
    through a secured reception area. According to Stenstrom, the information is valuable. It also notes
    Sockness's testimony that the information would allow competitors to determine Stenstrom's future
    bids. It further asserts that it paid a significant sum to purchase Old PPI and paid its estimators,
    including Mesch, significant amounts to create bids and/or to maintain the spreadsheet. Stenstrom
    also argues that there is no evidence in the record as to how a competitor could determine
    Stenstrom's labor and equipment rental costs, subcontractors' bids, and the actual profit margin added
    to all of the costs. It concludes that the bidding detail and profit margin information contained in
    the spreadsheet are trade secrets. Stenstrom also notes that, even if the foregoing costs could be
    independently determined, their compilation would still qualify as a trade secret because such a task
    requires the significant expenditure of time, effort, and expense. See Abbott-Interfast Corp. v.
    Harkabus, 
    250 Ill. App. 3d 13
    , 22 (1993), quoting Reinhardt Printing Co. v. Feld, 
    142 Ill. App. 3d 9
    , 18 (1986) ("Items such as customer lists, pricing information, and business techniques can be trade
    secrets if the employer has developed the information 'over a number of years at great expense and
    kept [it] under tight security' ").
    As to the trial court's finding that Stenstrom failed to show a likelihood of prevailing on the
    merits, Stenstrom argues that the court erred because Stenstrom not only showed that its information
    was stolen--it notes that Mesch conceded as much--but also showed that Mesch actually used the
    stolen trade secrets to bid against Stenstrom for the same jobs.
    1
    Stenstrom does not contend in its appeal on this count that its customer list is a trade secret.
    -19-
    No. 2--07--0504
    Mesch challenges Stenstrom's assertion that the Excel spreadsheet is a trade secret. Mesch
    concedes that he acquired and used the spreadsheet on New PPI's behalf. However, Mesch disagrees
    with Stenstrom that it constitutes a trade secret.
    Mesch asserts that the Excel spreadsheet does not constitute a trade secret, because it is a
    computer program readily available from any electronics store. He explains that he exclusively made
    all of the revisions to the spreadsheet after Stenstrom acquired Old PPI. According to Mesch, the
    spreadsheet allows the user to input item quantities that the user believes are necessary for a
    particular job. The spreadsheet then applies the pricing information, as previously input by the user,
    along with the discount information, also as previously input by the user, and a profit margin, again,
    input by the user, to calculate a suggested bid. Mesch argues that the same result could be achieved
    using only a pad of paper and a pencil. In support of his argument that the spreadsheet can be easily
    reproduced, he notes his testimony at the hearing that he can reproduce the spreadsheet in two or
    three days and that he would not need any information from Stenstrom in order to reproduce it.
    Rather, the information is all available from manufacturers.
    Addressing certain information in the spreadsheet, such as costs of labor and materials and
    profit margins, Mesch contends that this data is well known. As to materials, the spreadsheet
    contains a manufacturer's list price in one column and Stenstrom's discount in another column.
    Mesch notes that he testified that he knew Stenstorm's discounts without reference to the
    spreadsheet and that he could recite many of them from memory. Mesch further argues that any
    allegedly proprietary information in the spreadsheet has little or no value to any of Stenstrom's
    competitors because, due to its size, Stenstrom purchases directly from manufacturers. New PPI,
    -20-
    No. 2--07--0504
    in contrast, must purchase its materials through a distributor and does not receive the same level of
    discounts as Stenstrom.
    Turning to his bid on the State Oil North Chicago job, Mesch contends that he used the
    spreadsheet in preparing New PPI's bid only after he had made modifications to the spreadsheet.
    Mesch modified the spreadsheet to reflect New PPI's discounts, and he input subcontractor prices.
    He points out that New PPI's bid was higher than Stenstrom's. Turning to Stenstrom's prior bids,
    Mesch asserts that they are not trade secrets because they are merely calculations of the costs of
    materials and labor, along with a profit margin. Stenstrom's materials' prices, according to Mesch,
    can be readily determined: they are a function of list price less a standard discount. Similarly, labor
    costs and subcontractor prices are readily available.
    To show that certain information constitutes a trade secret, a plaintiff must show: (1) that its
    information is sufficiently secret to give it a competitive advantage; and (2) that it takes affirmative
    measures to prevent others from acquiring or using the information. 765 ILCS 1065/2(d) (West
    2004). Examples of trade secrets include: customer lists, formulae, patterns, and blueprints. Central
    Specialties Co. v. Schaefer, 
    318 F. Supp. 855
    , 859 (N.D. Ill. 1970). Knowledge of a supplier's
    pricing policies, however, does not constitute a trade secret. Central 
    Specialties, 318 F. Supp. at 859
    .
    In our view, the trial court did not err in denying Stenstrom injunctive relief on this count, because
    we believe that Stenstrom failed to raise a fair question as to the first Trade Secrets Act requirement
    and the related Restatement factors.
    Stenstrom failed to raise a fair question that its spreadsheet information, including its profit
    margin, was sufficiently secret to give it a competitive advantage. Mesch's testimony that he could
    reproduce the spreadsheet in about two to three days and his assertion that he would not require
    -21-
    No. 2--07--0504
    information from Stenstrom to do so was unrebutted. In order to prove that a pricing formula
    constitutes a trade secret, a plaintiff must establish that the value of the pricing formula lies in the
    fact that it is not generally known to others who could benefit by using it or that it could not be
    acquired through general skills and knowledge. Delta 
    Medical, 331 Ill. App. 3d at 792
    . Stenstrom's
    spreadsheet contains information such as part numbers, quantities, list prices, discounts, markups,
    subcontractor bids, and labor hours. Mesch testified that all of the information necessary to recreate
    it "is readily available from manufacturers." In addition, he testified that he knows from memory
    certain of Stenstrom's discounts. He acquired this knowledge in the course of his job. We reject
    Stenstrom's argument that its profit margin is a trade secret. The mere knowledge of the profit
    desired by an employer does not constitute a trade secret. Springfield Rare Coin Galleries, Inc. v.
    Mileham, 
    250 Ill. App. 3d 922
    , 934 (1993).
    Analysis of the relevant Restatement factors, we believe, also leads to the conclusion that
    Stenstrom's information does not constitute a trade secret. As to the extent to which the information
    is known outside and within Stenstrom's business, Mesch testified, unrebutted, that all of the
    information he requires to recreate the spreadsheet is available from manufacturers. As to the value
    of the information to Stenstrom, it was not unreasonable for the trial court to discount Sockness's
    self-serving testimony that the information is valuable to Stenstrom, as he failed to provide further
    explanation. Although Mesch testified that he made "great revisions and modifications" to the
    original Old PPI spreadsheet, we do not believe that the effort and time expended here, alone,
    necessarily requires a different result. Next, as to the ease or difficulty with which the information
    can be acquired or duplicated by others, we noted above Mesch's testimony that he could reproduce
    the spreadsheet in two to three days. Also, the information is primarily public, as it either is
    -22-
    No. 2--07--0504
    published or can be acquired by a telephone call to a subcontractor, for example. In summary, other
    than the efforts taken by Stenstrom to guard the secrecy of the information and possibly the time
    expended to create and maintain the spreadsheet, we conclude that the trial court could have
    reasonably found that the remaining relevant Restatement factors weigh against a finding that
    Stenstrom's spreadsheet information constitutes a trade secret.
    Our conclusion finds support in case law. See Service Centers of Chicago, Inc. v. Minogue,
    
    180 Ill. App. 3d 447
    , 455 (1989) (reversing preliminary injunction, finding that employer's pricing
    formula, which consisted of a customer survey, certain rules of thumb, and the use of a linear foot
    measurement, did not constitute a trade secret); Central Building & Cleaning Co. v. Vodnansky, 
    84 Ill. App. 3d 586
    , 590 (1980) (denial of preliminary injunctive relief not an abuse of trial court's
    discretion where employer's estimating method involved estimating the time to complete a job, labor
    and materials costs, and variables such as architectural detail, brick types, and possible hindrances
    such as power lines). Moreover, other jurisdictions have similarly concluded that various methods
    of calculating bids or the constituent elements of bids are not trade secrets. See Fortna v. Martin,
    
    158 Cal. App. 2d 634
    , 640, 
    323 P.2d 146
    , 149 (1958) (although employer utilized a pricing/bidding
    system that considered its costs, "any successful business man must do the same"); Porter Industries,
    Inc. v. Higgins, 
    680 P.2d 1339
    , 1342 (Colo. App. 1984) (employer's pricing and bidding structure
    not a trade secret); Mo-Kan Central Recovery Co. v. Hedenkamp, 
    671 S.W.2d 396
    , 400 (Mo. App.
    1984) (mere existence of an undefined bidding structure did not establish a trade secret where there
    was no evidence presented that the structure was novel or complicated and could not be easily
    duplicated by others and where no security measures were taken to maintain necessary element of
    secrecy); Whitmyer Bros., Inc. v. Doyle, 
    58 N.J. 25
    , 36-37, 
    274 A.2d 577
    , 583 (1971); cf. Ovation
    -23-
    No. 2--07--0504
    Plumbing, Inc. v. Furton, 
    33 P.3d 1221
    , 1224 (Colo. App. 2001) (declining to adopt per se rule that
    a bid itself, as opposed to the procedure for calculating it or its constituent elements, cannot be a
    trade secret as a matter of law where the defendant actually took information on specific bids for
    purpose of bidding against the plaintiff).
    b. Inadequate Legal Remedy and Irreparable Harm
    Although we need not address the remaining requirements to obtain a preliminary injunction,
    we choose to do so because the issues are easily resolved. Thus, we provide the following alternative
    bases for rejecting Stenstrom's arguments concerning injunctive relief as to its Trade Secrets Act
    claim against Mesch.
    Addressing the trial court's finding that it failed to raise a fair question that there was no
    adequate remedy at law, Stenstrom argues that it showed that Mesch and New PPI have successfully
    used Stenstrom's stolen trade secrets to obtain work first bid on by Stenstrom and will continue to
    do so to compete unfairly against Stenstrom. According to Stenstrom, Mesch has not offered any
    explanation as to why the court should believe that he did not retain copies of the stolen Stenstrom
    information. Stenstrom contends that it is deserving of protection against the virtual certainty that
    Mesch has retained and will continue to use copies of the information that he stole. Alternatively,
    Stenstrom argues that, even if Mesch returned all of the stolen information, his actions prior to
    returning it damaged Stenstrom's reputation because, by using the information, Mesch eroded
    customers' loyalty to Stenstrom. Stenstrom notes that State Oil did leave Stenstrom for New PPI by
    virtue of accepting New PPI's higher bid for the North Chicago job. Stenstrom reasons that loss of
    competitive position is incapable of being measured and, therefore, there is an inadequate remedy
    at law. See A-Tech Computer Services, Inc. v. Soo Hoo, 
    254 Ill. App. 3d 392
    , 401 (1993).
    -24-
    No. 2--07--0504
    Mesch responds that his possession of Stenstrom's alleged trade secrets was not continuing,
    because he returned all such information to Stenstrom in accordance with the TRO on March 13,
    2007, which was less than three months after his termination date. Mesch further asserts that a
    remedy at law could be measured. He submitted a limited number of bids for New PPI and only one
    of those bids was accepted. Addressing the two bids Stenstrom offered as evidence, Mesch notes
    that New PPI overbid Stenstrom. Further, Mesch asserts that the allegedly proprietary information
    he possessed was not disclosed to any third party other than New PPI. He also notes that the only
    information potential customers receive are the bids themselves. Stenstrom's underlying price
    information is not disclosed. Thus, there is no mass dissemination of Stenstrom's information.
    Addressing the irreparable harm requirement, Mesch responds that there is no danger here of
    recurrent violations because neither he nor New PPI currently has access to Stenstrom's allegedly
    confidential information.
    "[P]rolonged interruptions in the continuity of business relationships can cause irremedial
    damages for which no compensation would be adequate." Wolf & Co. v. Waldron, 
    51 Ill. App. 3d 239
    , 243 (1977). Under the Act, "[a]ctual or threatened misappropriation may be enjoined." 765
    ILCS 1065/3 (West 2004). Using a theory of inevitable disclosure, "a plaintiff may prove a claim
    of trade secret misappropriation by demonstrating that defendant's new employment will inevitably
    lead him to rely on the plaintiff's trade secrets." Pepsico, Inc. v. Redmond, 
    54 F.3d 1262
    , 1269 (7th
    Cir. 1995). The fact that a former employee accepted a similar position with a competitor, without
    more, will not demonstrate inevitable disclosure. See 
    Liebert, 357 Ill. App. 3d at 284
    . Courts also
    consider the level of competition between the parties and the new employer's actions to prevent
    unlawful disclosure of trade secrets. 
    Liebert, 357 Ill. App. 3d at 284
    . That a complaint also seeks
    -25-
    No. 2--07--0504
    monetary damages does not foreclose injunctive relief. Continental Cablevision of Cook County,
    Inc. v. Miller, 
    238 Ill. App. 3d 774
    , 788 (1992). To show irreparable injury, the plaintiff is not
    required to show that the injury is beyond repair or compensation in damages, but need show only
    transgressions of a continuing nature. Continental 
    Cablevision, 238 Ill. App. 3d at 788
    .
    We reject Stenstrom's argument that it sufficiently showed that Mesch will continue to
    compete unfairly against Stenstrom because he will continue to use its allegedly confidential
    information. It was not unreasonable for the trial court to find that Stenstrom failed to raise a fair
    question as to an inadequate legal remedy or irreparable harm where Mesch returned all of the
    computer files that he copied from Stenstrom's computers, especially in the absence of evidence that
    he still retained any copies of those files. As to Stenstrom's assertion that it has lost its competitive
    position in the industry, we cannot conclude that the trial court erred in discounting this argument,
    in light of the fact that Stenstrom lost out on only one job against New PPI after Mesch began
    working for the new company. Furthermore, it is undisputed that State Oil collects several proposals
    for its projects. This weighs against a finding that Stenstrom has permanently lost State Oil as a
    customer. Finally, as Mesch notes, there could be no mass dissemination of Stenstrom's allegedly
    confidential information because the bids submitted to potential customers do not include all of the
    component information.
    In summary, we conclude that the trial court did not abuse its discretion in declining to enter
    a preliminary injunction against Mesch on the basis of his alleged violations of the Trade Secrets
    Act.
    3. Trade Secrets Act Claim Against New PPI
    -26-
    No. 2--07--0504
    Stenstrom next argues that the trial court erred in denying it injunctive relief against New PPI
    based upon New PPI's violations of the Trade Secrets Act. Stenstrom asserts that it has a protectable
    interest in its customer list and argues that Mesch will inevitably disclose Stenstrom's trade secrets
    to New PPI. It notes that the information has already been copied to New PPI's computers and used
    for New PPI by an employee--Mesch--who will receive 20% of New PPI's profits and who named
    the company.
    In its claim against New PPI, Stenstrom asserts that both the spreadsheet information and its
    customer list constitute trade secrets. Because we rejected above its argument that it established its
    right to injunctive relief based on the spreadsheet information, we need not address that issue again
    here in relation to New PPI. Thus, we proceed by examining only whether Stenstrom established
    a right to injunctive relief based on its argument that its customer list constitutes a trade secret. For
    the reasons we state below, we reject Stenstrom's argument. Accordingly, we do not reach its
    inevitable disclosure argument, which is premised on the existence of a trade secret. See 
    Pepsico, 54 F.3d at 1267-68
    (party seeking an injunction under the Act must prove both the existence of a
    trade secret and an actual or threatened misappropriation, and inevitable disclosure theory addresses
    threatened misappropriation, which, in turn, bears on the reasonable-likelihood-of-success
    requirement for a preliminary injunction).
    Turning to the first requirement for a preliminary injunction--a protectable interest (i.e., a
    trade secret)--the Act defines a trade secret to include a "list of actual or potential customers or
    suppliers." 765 ILCS 1065/2(d) (West 2004). Again, the statute requires that a plaintiff show: (1)
    that the information is sufficiently secret to give it a competitive advantage; and (2) that it takes
    affirmative measures to prevent others from acquiring or using the information. 765 ILCS 1065/2(d)
    -27-
    No. 2--07--0504
    (West 2004). In addition to the Act's requirements, courts consider the six Restatement factors we
    listed above. See, e.g., 
    Liebert, 357 Ill. App. 3d at 276
    -77. "In determining whether [a customer list]
    is a trade secret, the focus of both the common law and the [Trade Secrets Act] is on the secrecy of
    the information sought to be protected." Stampede Tool Warehouse, Inc. v. May, 
    272 Ill. App. 3d 580
    , 588 (1995).
    Here, the parties confuse the foregoing tests with the near-permanent-relationship test that
    applies in cases involving restrictive covenants. See, e.g., 
    LSBZ, 237 Ill. App. 3d at 426
    . The near-
    permanent-relationship test focuses on the strength of an employer's relationship to its clients and
    not on the secrecy of its customer list. We caution the parties that the near-permanent-relationship
    test does not apply to a claim brought under the Trade Secrets Act. See Stampede Tool 
    Warehouse, 272 Ill. App. 3d at 586
    . Because Stenstrom does not address the correct legal standard, we do not
    address its argument concerning its Trade Secrets Act claim against New PPI. See Groenings v. City
    of St. Charles, 
    215 Ill. App. 3d 295
    , 306 (1991) (reviewing court may deem waived those issues that
    have not been sufficiently or properly presented, including with relevant authority cited); 210 Ill. 2d
    R. 341(h)(7).
    4. Breach of Fiduciary Duty Claims Against Mesch and New PPI
    Next, Stenstrom argues that the trial court erred in denying it preliminary injunctive relief
    against Mesch and New PPI based on Mesch's breach of his fiduciary duty to Stenstrom. Stenstrom
    notes that it seeks this relief against Mesch to prevent him from soliciting its customers. According
    to Stenstrom, Mesch was working for New PPI's benefit when he took and failed to return
    Stenstrom's trade secrets. As to its breach of fiduciary duty claim against New PPI, Stenstrom argues
    that New PPI is liable for Mesch's actions because Mesch acted as its agent when he copied
    -28-
    No. 2--07--0504
    Stenstrom's secret information for the benefit of New PPI, for the purpose of using the information
    at New PPI. It further contends that, as a New PPI employee, Mesch actually used the information
    for his new employer. According to Stenstrom, Mesch will receive 20% of New PPI's profits in
    addition to his salary, and Stenstrom notes that he named New PPI.
    We do not address these arguments at length because, although Stenstrom acknowledges that
    its breach of fiduciary duty claims are independent of its Trade Secrets Act claims, it repeatedly
    asserts in this portion of its brief that Mesch stole its trade secrets, thus premising its fiduciary duty
    claims on the adequacy of its showing that its information constitutes a trade secret, an argument we
    rejected above. It is well settled that "[a] reviewing court is entitled to have issues clearly defined
    with pertinent authority cited and cohesive arguments presented ([210 Ill. 2d R. 341(h)(7)]), and it
    is not a repository into which an appellant may foist the burden of argument and research." Obert
    v. Saville, 
    253 Ill. App. 3d 677
    , 682 (1993). We deem Stenstrom's breach of fiduciary duty
    arguments waived.
    Waiver aside, we note that Stenstrom again argues that it adequately asserted a lack of an
    adequate remedy at law. According to Stenstrom, Mesch and New PPI will continue to use its trade
    secrets to compete unfairly against it. We again reject this argument for the reasons we stated above
    in relation to Stenstrom's Trade Secrets Act claim against Mesch.
    B. Motion Taken with the Case and Mesch's Cross-Appeal
    In his cross-appeal, Mesch argues that the trial court erred in entering the preliminary
    injunction. He argues that the covenant not to compete is not valid and enforceable because it lacks
    consideration. Alternatively, Mesch asserts that, even if the covenant was supported by adequate
    -29-
    No. 2--07--0504
    consideration, Stenstrom does not have a protectable interest, such as near-permanent customer
    relationships or confidential information, sufficient to enforce the agreement.
    In a motion we ordered taken with the case, Stenstrom moves to dismiss Mesch's cross-
    appeal as moot. It argues that the preliminary injunction expired on June 26, 2007, and, therefore,
    the cross-appeal is now moot because it involves no actual controversy. It contends that, only if we
    accept its first argument concerning the commencement of the injunction would we need to reach
    the arguments Mesch raises in his cross-appeal.
    Mesch responds that Mohanty v. St. John Heart Clinic, S.C., 
    225 Ill. 2d 52
    (2006), instructs
    that his cross-appeal is not moot. In that case, two physicians sued their employer and its owner
    seeking a declaratory judgment that the restrictive covenants in their employment contracts were
    void as against public policy and unenforceable. The employer and its owner counterclaimed for
    declaratory, injunctive, and other relief to restrain the physicians from violating the restrictive
    covenants. The defendants also raised misappropriation and unjust enrichment claims and sought
    a declaration concerning the employer's responsibility for providing certain malpractice coverage.
    The trial court denied the defendants' request for a preliminary injunction, but the appellate court
    reversed. The supreme court held that the appeal was not moot as to a physician whose restrictive
    covenant period had lapsed.        
    Mohanty, 225 Ill. 2d at 92
    .         It noted that the defendants'
    countercomplaint sought damages for harm allegedly incurred and revenues allegedly lost as a result
    of the physicians' violations of the restrictive covenants. 
    Mohanty, 225 Ill. 2d at 92
    . It reasoned that
    a decision concerning the enforceability of the restrictive covenants "could have a direct impact on
    [the one physician's] rights and obligations in these matters." 
    Mohanty, 225 Ill. 2d at 64
    .
    -30-
    No. 2--07--0504
    We believe that Mesch's reliance on Mohanty is misplaced because, in that case, the
    counterclaims were based on violations of the restrictive covenants. Here, we reject Mesch's
    contention that a decision on the enforceability of the restrictive covenant will have a direct impact
    on Mesch's rights and obligations as to the other claims in Stenstrom's complaint. Stenstrom's Trade
    Secrets Act and breach of fiduciary duty claims are independent of the restrictive covenant claim.
    Given our resolution of Stenstrom's argument concerning the preliminary injunction's
    commencement date, the preliminary injunction expired on June 26, 2007. "An issue is moot when
    its resolution could not have any practical effect on the existing controversy." La Salle National
    Bank, N.A. v. City of Lake Forest, 
    297 Ill. App. 3d 36
    , 43 (1998). Moreover, a court cannot dissolve
    an injunction that has expired. Multiut Corp. v. Draiman, 
    359 Ill. App. 3d 527
    , 543 (2005) (appeal
    dismissed); see also The Agency, Inc. v. Grove, 
    362 Ill. App. 3d 206
    , 209 (2005) (enforceability of
    noncompetition provision was a moot issue where noncompetition period had expired). We agree
    with Stenstrom that the restrictive covenant's enforceability is mooted by the expiration of the
    preliminary injunction. Accordingly, we dismiss Mesch's cross-appeal and do not address the
    enforceability of the restrictive covenant.
    IV. CONCLUSION
    For the foregoing reasons, the judgment of the circuit court of Winnebago County is
    affirmed.
    Affirmed.
    GROMETER, P.J., and HUTCHINSON, J., concur.
    -31-