Martin Marietta Materials v. Kansas DOT , 810 F.3d 1161 ( 2016 )


Menu:
  •                                                                                FILED
    United States Court of Appeals
    PUBLISH                               Tenth Circuit
    UNITED STATES COURT OF APPEALS                     January 13, 2016
    Elisabeth A. Shumaker
    FOR THE TENTH CIRCUIT                          Clerk of Court
    _________________________________
    MARTIN MARIETTA MATERIALS,
    INC.; HUNT MARTIN MATERIALS,
    LLC,
    Plaintiffs - Appellants,
    v.                                                       No. 13-3314
    KANSAS DEPARTMENT OF
    TRANSPORTATION; MIKE KING, in his
    individual and official capacity as Kansas
    Secretary of Transportation; JERRY
    YOUNGER, in his individual and official
    capacity as Deputy Secretary of
    Transportation and State Transportation
    Engineer,
    Defendants - Appellees.
    _________________________________
    Appeal from the United States District Court
    for the District of Kansas
    (D.C. No. 2:12-CV-02699-SAC-KGS)
    _________________________________
    H. Wayne Phears (Daniel L. Delnero, with him on the briefs), McGuireWoods LLP,
    Atlanta, Georgia, for Plaintiffs-Appellants.
    Lyndon W. Vix (Carmen D. Tucker Bakarich and Gelene D. Savage, Kansas Depatment
    of Transportation, Topeka, Kansas, and Charles E. Milsap, Fleeson, Gooing, Coulson &
    Kitch, L.L.C., Wichita, Kansas with him on the brief), Fleeson, Gooing, Coulson &
    Kitch, L.L.C., Wichita, Kansas, for Kansas Department of Transportation, Defendant-
    Appellee.
    _________________________________
    Before KELLY, PHILLIPS, and MORITZ, Circuit Judges.
    _________________________________
    PHILLIPS, Circuit Judge.
    _________________________________
    INTRODUCTION
    Martin Marietta Materials, Inc. appeals the district court’s dismissal of its due-
    process claims against the Kansas Department of Transportation (KDOT). After
    KDOT removed two Martin Marietta quarries from its preapproved lists of limestone-
    aggregate suppliers, Martin Marietta unsuccessfully sought pre- and post-deprivation
    hearings from KDOT. Among its many claims in its federal lawsuit—most
    abandoned on appeal—it asserted a property-right claim under the Fourteenth
    Amendment. Specifically, it claimed a property interest in keeping its two quarries on
    “the approved list” of aggregate suppliers,1 and a liberty interest in its reputation as a
    1
    The dissent says that we have “mischaracterized the nature of Martin
    Marietta’s asserted property interest” by “repeatedly and consistently stat[ing] that
    Martin Marietta asserts a property interest in actually supplying aggregate from its
    quarries to KDOT projects.” Dissent at 1, 4. Three responses. First, the quotations the
    dissent references from our opinion address the limitations of Martin Marietta’s legal
    theory—they explain why it isn’t entitled to relief. Second, the dissent itself admits
    that Martin Marietta’s Complaint claimed a property and liberty interest to supply
    limestone from its quarries, but says Martin no longer pursues this claim on appeal.
    Id. at 3 n.2. And, third, here’s a sample of Martin Marietta’s own characterization of
    its claim on appeal: “The Right to Supply Aggregate to KDOT-Funded Projects is
    Governed by Inclusion on the Approved List.” Appellant’s Br. at 3. In any event, as
    discussed in the opinion, Martin Marietta’s claim also fails because neither its Ottawa
    nor its Sunflower Quarry passed the 2013 testing standards, so neither qualifies for
    the 2013 prequalified list. Those failures to qualify defeat any property interest in
    being on the 2013 prequalified list. We see nothing in the dissent disputing this.
    2
    supplier of quality materials under the Fourteenth Amendment. The district court
    disagreed, dismissing these claims on the pleadings.
    Exercising jurisdiction under 
    28 U.S.C. § 1291
    , we affirm. We hold that Martin
    Marietta has not plausibly alleged a protected property interest, and thus that KDOT
    did not violate Martin Marietta’s procedural-due-process rights by failing to provide
    pre- or post-deprivation hearings. We also hold that Martin Marietta has no
    cognizable liberty interest, because KDOT did not make defamatory statements about
    Martin Marietta and because Martin Marietta failed to allege sufficiently significant
    harm to its business.
    I. BACKGROUND
    A. Factual Background
    Under Kansas law, KDOT has general supervisory power over all roads and
    bridges in the state. 
    Kan. Stat. Ann. § 68-404
    (a) (2014). In exercising this power,
    KDOT is obligated to “devise and adopt standard plans and specifications for
    road . . . construction and maintenance” and to “make tests, do research, to inspect
    and test all materials . . . used for state highway purposes or highway projects
    involving federal funds, and to develop methods and procedures for this purpose.” 
    Id.
    § 68-404(c), (h). The Kansas legislature has also directed KDOT “to adopt rules and
    regulations to carry out the provisions of this act.” Id. § 68-404(k).
    In accordance with these duties, KDOT has established, as part of its Standard
    Specifications, quality requirements for materials used in Kansas road-construction
    3
    projects. KDOT identifies quarries whose aggregate2 has passed KDOT’s tests set
    forth in its Standard Specifications and places them on a list of preapproved sources.3
    Upon a quarry’s meeting KDOT’s testing standards and qualifying for its
    preapproved list,4 KDOT preliminarily approves that quarry’s aggregate for use by
    contractors working on road projects funded by KDOT and the Federal Highway
    Administration (FHWA). At the same time, KDOT disallows the use of aggregate
    from quarries not on the preapproved list.
    As part of its business, Martin Marietta supplies limestone aggregate to
    contractors working on public and private projects. In fact, it is the second largest
    producer of aggregate in the country. All told, it operates more than 300 quarries in
    28 states and employs more than 5,000 people in its construction-aggregate
    production. For decades, some of its quarries have been on KDOT’s preapproved list
    to supply aggregate, and it has routinely supplied aggregate to contractors working
    on KDOT projects.
    2
    “Aggregate” refers to sand, gravel, slag, crushed stone, and like materials that
    are mixed with a cementing material to form concrete, cement, mortar, or asphalt.
    These materials are essential in the construction industry. Constr. Aggregate Transp.,
    Inc. v. Fla. Rock Indus., Inc., 
    710 F.2d 752
    , 757 n.4 (11th Cir. 1983).
    3
    For KDOT and federal projects, contractors may purchase only aggregate that
    has passed KDOT’s tests and has been placed on the preapproved list. But that does
    not preclude a supplier from selling other types of rock from its quarry for other
    purposes. But aggregate for on-grade concrete projects must pass KDOT’s various
    tests, which, as seen in this case, may change over time.
    4
    When we refer to KDOT’s list of preapproved sources generically (not from a
    specific time period), we will call it the “preapproved list.”
    4
    This appeal concerns two of Martin Marietta’s quarries, Ottawa and Sunflower.
    Because “the” preapproved list (as Martin Marietta calls it) is really three separate
    preapproved lists depending on the months and years in question, we must examine
    Martin Marietta’s two quarries individually during each of three time periods to
    consider Martin Marietta’s general claim.
    1. Pre-October 2010
    For decades, Martin Marietta supplied aggregate from the Ottawa Quarry for use
    in Kansas-roadway projects. It did the same with aggregate from its Sunflower
    Quarry. Before October 2010, quarries qualified to be on KDOT’s “Approved List”
    to supply aggregate for on-grade concrete projects by passing the ASTM c666 test of
    300-cycles at a 95% freeze-thaw durability factor. Both the Ottawa and Sunflower
    Quarries had passed the 300-cycle test and qualified for the Approved List. Because
    both quarries successfully sold aggregate until October 2010, we can eliminate from
    Martin Marietta’s claim any KDOT actions before then.
    2. October 2010–January 2013
    In the years leading up to 2010, KDOT began to notice D-cracking on Kansas
    roads. D-cracking refers to the deterioration of concrete in a D-shaped pattern. It
    results from damage to the concrete from the expanding and contracting of water
    during freeze-thaw cycles.
    On or before October 2010, based upon its study of the D-cracking problem on
    Kansas roads, KDOT adopted a policy (stop-gap measure) of removing from its
    Approved List any quarry when: (1) KDOT confirmed D-cracking at three separate
    5
    stretches of road, (2) the same quarry had supplied the aggregate for those roads, and
    (3) the road-construction projects for those stretches of road had been completed less
    than 20 years before KDOT confirmed the D-cracking on them.5 On October 29,
    2010, KDOT informed Martin Marietta that it had removed Ottawa Quarry from the
    Approved List for aggregate because Ottawa’s aggregate had failed the stop-gap
    measure. Martin Marietta requested a hearing to challenge the removal, but KDOT
    denied the request. In support of its request for a hearing, Martin Marietta argued that
    it could show that aggregate from the Ottawa Quarry had not in fact caused the D-
    cracking.
    We understand Martin Marietta to claim that it had a property interest in Ottawa
    Quarry’s remaining on the Approved List from October 2010 until January 2013
    (Stop-Gap Approved List) despite KDOT’s additional requirement imposed by the
    stop-gap measure. Martin Marietta alleges that because the stop-gap measure was not
    validly approved by FHWA, and thus not adopted into the Standard Specifications,
    KDOT could not remove quarries from “the Approved List” based on this test. We do
    not understand Martin Marietta to make this same claim for Sunflower Quarry, which
    remained on the Stop-Gap Approved List during this 27-month interval and
    continued to remain eligible to supply aggregate during that time.
    5
    After KDOT adopted this stop-gap measure, it removed nine quarries from the list
    based on their failure. The empirical condition was in place for 27 months until a new—
    and more stringent—scientific test was approved and adopted after studying the D-
    cracking problem further. For that reason, we refer to the 27-month period as a “stop-
    gap.”
    6
    3. January 2013 and Beyond
    In January 2013, KDOT changed the name of the preapproved list for aggregate to
    the “Prequalified List” to reflect newly adopted testing standards in the Standard
    Specifications. As mentioned, the new test imposed a more stringent standard for
    aggregate used in on-grade concrete projects: a 660-cycle freeze-thaw test with a
    95% durability factor. On January 11, 2013, KDOT informed Martin Marietta by
    letter that Sunflower Quarry’s aggregate had failed the 660-cycle test. Martin
    Marietta admits that Sunflower Quarry’s aggregate “allegedly failed” the more-
    stringent test “by a very narrow margin, while passing other criteria.” Appellant’s
    App. at 23. Because it failed, KDOT declined to place it on the Prequalified List.
    After it received KDOT’s letter, Martin Marietta requested pre- and post-deprivation
    hearings, but KDOT refused to provide either. In support of its request for a hearing,
    Martin Marietta argued that it could show that aggregate from Sunflower Quarry
    satisfied the Standard Specifications “in effect” at the time of removal. Appellant’s
    Opening Br. at 49. We assume Martin Marietta was referring to the 660-cycle test
    that KDOT imposed in January 2013.
    We see nothing in the record, in Martin Marietta’s Complaint, in its Amended
    Complaint, or in its briefing to us suggesting that KDOT ever tested Ottawa Quarry’s
    aggregate using the new 660-cycle test, or that Ottawa’s aggregate has ever passed
    this test. At oral argument, when questioned on this point, Martin Marietta said that it
    did not know whether KDOT had tested Ottawa Quarry’s aggregate under the new
    test.
    7
    We understand Martin Marietta to contend, somehow, that its Ottawa Quarry and
    Sunflower Quarry had a property interest in being on the new Prequalified List
    despite Ottawa’s aggregate not being tested under the 660-cycle test and Sunflower’s
    failing that test. Here, we express some frustration that Martin Marietta has not
    explained its claim satisfactorily either in its briefs or during pointed questioning at
    oral argument. As seen later, we painstakingly cover the field of Martin Marietta’s
    possible theories supporting its claim. Martin Marietta’s continued references to “the
    Approved List” are unhelpful when its claim covers an interval in which three
    different “approved lists” applied.
    Regardless, because neither Ottawa Quarry nor Sunflower Quarry qualified for the
    Prequalified List by passing KDOT’s new 660-cycle test, Martin Marietta can no
    longer supply aggregate from those quarries to KDOT- and FHWA-funded projects
    for on-grade concrete roadways.6 According to Martin Marietta, being on the
    Prequalified List is a “stamp of approval” in the industry, and private contractors also
    use it to select their suppliers. Appellant’s Opening Br. at 11; Appellant’s App. at
    20–21. Because KDOT determined that neither quarry qualified for its Prequalified
    List, Martin Marietta claims losses of millions of dollars.
    6
    Martin Marietta remains free to supply other material from those quarries to
    KDOT-funded projects for other purposes.
    8
    B. Procedural History
    On October 29, 2012, Martin Marietta sued KDOT in federal court. In its
    Complaint, it alleged that KDOT had erroneously determined that Ottawa Quarry’s
    aggregate caused D-cracking, and it claimed a right to a hearing to challenge
    KDOT’s conclusion. In all, it asserted 11 claims for relief.7 On January 17, 2013,
    KDOT filed a motion for judgment on the pleadings under Fed. R. Civ. P. 12(c).
    KDOT argued that Martin Marietta had not plausibly alleged a property or liberty
    interest capable of supporting its constitutional claims and that immunity under the
    Eleventh Amendment barred the tort claims.
    7
    The eleven claims were as follows: Claim One: “Violation of K.A.R. § 36-31-2,”
    alleging KDOT did not comply with the debarment procedures required in this
    regulation; Claim Two: “Violation of Procedural Due Process,” because KDOT failed
    to provide a pre-deprivation hearing; Claim Three: “Violation of Procedural Due
    Process,” because KDOT failed to provide a post-deprivation hearing; Claim Four:
    “Intentional Interference with Business Relationships,” in the loss of contracts and
    business caused by KDOT’s removal of Ottawa Quarry from the Approved List and
    refusal to return it; Claim Five: “Negligent Interference with Business
    Relationships,” in the loss of contracts and business caused by KDOT’s removal of
    Ottawa Quarry from the Approved List and refusal to return it; Claim Six:
    “Defamation,” for falsely representing that Ottawa Quarry did not satisfy the
    requirements for the Approved List; Claim Seven: “Violation of Equal Protection,”
    for KDOT’s testing of quarries and decisions to prequalify some quarries but not
    Martin Marietta’s quarries; Claim Eight: “Violation of Substantive Due Process,” for
    KDOT’s arbitrary and irrational actions that denied Martin Marietta of its property
    and liberty interests; Claim Nine: “Violation of the Takings Clause” by the
    deprivation of Martin Marietta’s property interest to be on the Approved List; Claim
    Ten: “Request for Preliminary and Injunctive Relief” that would put Ottawa Quarry
    on the Approved List until the hearings were held and would require the
    prequalification and testing of all Martin Marietta quarries; and Claim Eleven:
    “Request for Declaratory Relief.” Appellant’s App. at 323–24.
    9
    On February 13, 2013, while KDOT’s motion was pending, Martin Marietta
    moved to amend its complaint to add similar claims based on KDOT’s decision not to
    place Sunflower Quarry on the Prequalified List after the quarry failed the new
    freeze-thaw test.8 In the meantime, the parties continued to file motions and also
    began discovery. As part of the initial discovery, KDOT designated Rick Kreider as
    its Fed. R. Civ. P. 30(b)(6) witness. Kreider testified about KDOT’s approval criteria
    used to determine which quarries qualified for KDOT’s preapproved lists.9 Kreider
    served as KDOT’s Chief of the Bureau of Materials and Research, the agency that
    creates and implements the Standard Specifications and oversees the preapproved
    lists. On March 15, 2013, Martin Marietta deposed Kreider about KDOT’s Standard
    Specifications, including the considerations used in setting testing criteria for
    aggregate and D-cracking.
    On May 21, 2013, the district court denied as futile Martin Marietta’s motion to
    amend its complaint and granted KDOT’s motion for judgment on the pleadings on
    several claims.10 Relevant to this appeal, the district court concluded that Martin
    8
    In its motion, Martin Marietta proposed adding a count for void-for-vagueness
    as an alternative claim for relief to counts one through three, seven, and eight.
    9
    When a government agency is deposed, the agency “must then designate one or
    more . . . persons who consent to testify on its behalf; and it may set out the matters
    on which each person designated will testify.” Fed. R. Civ. P. 30(b)(6).
    10
    The district court granted KDOT’s judgment on the pleadings for the following
    claims: Claim One (Violation of K.A.R. § 36-31-2), Claim Two (Violation of 
    42 U.S.C. § 1983
    : Procedural Due Process—Pre-Deprivation Notice and Hearing),
    Claim Three (Violation of 
    42 U.S.C. § 1983
    : Procedural Due Process—Post-
    10
    Marietta had not alleged a plausible claim supporting its claimed property interest in
    having its quarries on any of KDOT’s preapproved lists. As its basis, the district
    court concluded that a supplier’s being on a preapproved list does not guarantee the
    supplier any particular outcome (e.g., supplying construction aggregate). Under the
    Eleventh Amendment, the district court also dismissed KDOT as a party to the
    lawsuit. In response, Martin Marietta moved for reconsideration, contending that the
    district court had failed to consider Kreider’s testimony and failed to defer to his
    understanding and interpretation of KDOT’s rules. The district court denied the
    motion for reconsideration, stating that it had considered the proffered testimony and
    had found it consistent with KDOT’s position.
    On November 8, 2013, Martin Marietta filed its First Amended Complaint, which
    listed only the claims from its February 13, 2013 Proposed Amended Complaint that
    ____________________
    Deprivation Notice and Hearing), Claim Five (Negligent Interference with Business
    Relationships), Claim Six (Defamation), Claim Eight (Violation of 
    42 U.S.C. § 1983
    :
    Substantive Due Process), and Claim Nine (Ten in the February 13, 2013 Proposed
    Amended Complaint) (Violation of the Takings Clause).
    The district court further concluded that Claim Ten and Claim Eleven (Eleven and
    Twelve in the February 13, 2013 Proposed Amended Complaint) did not allege
    separate claims for relief but instead asked for injunctive and declaratory relief for
    the remaining claims: Claim Seven (Violation of 
    42 U.S.C. § 1983
    : Equal Protection)
    and Claim Nine (the February 13, 2013 Proposed Amended Complaint Alternative
    Count of Void of Vagueness).
    Finally, the district court denied KDOT’s motion for judgment on the pleadings,
    but granted Martin Marietta’s motion for leave to file its amended complaint, for
    Claim Four (Intentional Interference with Business Relationships), Claim Seven
    (Violation of 
    42 U.S.C. § 1983
    : Equal Protection), Claim Nine (the February 13,
    2013 Proposed Amended Complaint Alternative Claim for Void for Vagueness), and
    Claim Ten and Claim Eleven (Eleven and Twelve in the February 13, 2013 Proposed
    Amended Complaint) seeking injunctive and declaratory relief.
    11
    the district court had later allowed in the May 21, 2013 order. Before KDOT could
    respond to the First Amended Complaint, Martin Marietta moved to dismiss all its
    claims, both from the February 13, 2013 Proposed Amended Complaint and the First
    Amended Complaint, presumably so that it could appeal. In its motion, Martin
    Marietta explained that “[d]ismissal pursuant to this motion shall not affect in any
    manner the claims that were resolved by the Court in its [May 21, 2013 order] ruling
    on Defendant’s motion for judgment on the pleadings pursuant to Fed. R. Civ. P.
    12(c) . . . .” Appellee’s Suppl. App. at 209. It requested that the district court enter an
    order directing the “final judgment on those claims resolved by the Court in its [May
    21, 2013 order] and those claims for which [Martin Marietta] seek[s] dismissal in this
    motion.” 
    Id.
     The defendants consented to the proposed dismissal, the district court
    dismissed all claims, and the clerk of court entered a final judgment on all of Martin
    Marietta’s claims. Martin Marietta timely appealed.11
    On appeal, Martin Marietta does not challenge the district court’s dismissal of
    KDOT as a party. Instead, it proceeds forward solely on its claims against Mike
    King, the Secretary of Transportation, and Jerry Younger, the Deputy Secretary of
    Transportation and State Transportation Engineer, in their individual and official
    capacities. Addressing the official-capacity claims against the two men, the district
    11
    The district court’s grant of Martin Marietta’s motion to dismiss its claims
    ripened the case for appeal. See Niemi v. Lasshofer, 
    770 F.3d 1331
    , 1342 (10th Cir.
    2014) (“A dismissal of all claims with prejudice, even if voluntarily sought by the
    party who initiated the suit, is final for purposes of appellate jurisdiction, making
    [Fed. R. Civ. P.] 54(b) certification unnecessary.”).
    12
    court concluded that the Eleventh Amendment barred the claims. The district court
    permitted Martin Marietta to bring any prospective, federal claims against King and
    Younger, including procedural due process, equal protection, substantive due
    process, and void for vagueness. Addressing the individual-capacity claims against
    King and Younger, the court stated that the Eleventh Amendment offered no
    immunity. King challenged the claims involving the Ottawa Quarry because he did
    not become Secretary of Transportation until over a year after the Ottawa Quarry was
    removed from the Approved List. But the court noted that he had “refused to restore
    the Ottawa quarry to the [Approved List] or to grant them a due process hearing,”
    meaning that Martin Marietta had sufficiently alleged King’s personal involvement in
    the ongoing violation against Ottawa Quarry. Appellant’s. App. at 334. Thus, it
    appears from the district court’s order that Martin Marietta was free to bring any of
    its prospective federal claims against King and Younger in their official capacities
    and any of its claims—state or federal—against King and Younger in their individual
    capacities.
    In spite of the broad array of permitted claims, Martin Marietta raises on appeal
    only the procedural-due-process claim. Martin Marietta contends that King and
    Younger denied it due process under the Fourteenth Amendment by not providing it
    deprivation hearings before removing Ottawa Quarry from the Approved List
    (October 2010–January 2013) and before refusing Sunflower Quarry a place on the
    Prequalified List (post-January 2013).
    13
    II.   DISCUSSION
    This court reviews “a dismissal granted under Rule 12(c) ‘under the standard of
    review applicable to a Rule 12(b)(6) motion to dismiss.’” Nelson v. State Farm Mut.
    Auto. Ins. Co., 
    419 F.3d 1117
    , 1119 (10th Cir. 2005) (quoting McHenry v. Utah
    Valley Hosp., 
    927 F.2d 1125
    , 1126 (10th Cir. 1991)). Thus, we review de novo a
    district court’s dismissal under Rule 12(c). 
    Id.
     We must “accept all facts pleaded by
    the non-moving party as true and grant all reasonable inferences from the pleadings
    in that party’s favor.” Sanders v. Mountain Am. Fed. Credit Union, 
    689 F.3d 1138
    ,
    1141 (10th Cir. 2012) (quotation marks omitted). In reviewing a motion to dismiss,
    this court must look for “plausibility in th[e] complaint.” Alvarado v. KOB-TV,
    L.L.C., 
    493 F.3d 1210
    , 1215 (10th Cir. 2007) (alteration in original); see Bell Atl.
    Corp. v. Twombly, 
    550 U.S. 544
    , 556 (2007) (concluding that we do “not impose a
    probability requirement at the pleading stage; it simply calls for enough fact to raise a
    reasonable expectation that discovery will reveal evidence of” the alleged claim for
    relief).
    The Fourteenth Amendment prohibits any state from “depriv[ing] any person of
    life, liberty, or property, without due process of law.” U.S. Const. amend. XIV, § 1.
    To be entitled to procedural due process, Martin Marietta must prove it has either a
    protected property or liberty interest. See Bd. of Regents of State Colls. v. Roth, 
    408 U.S. 564
    , 569 (1972) (“The requirements of procedural due process apply only to the
    deprivation of interests encompassed by the Fourteenth Amendment’s protection of
    liberty    and   property.”).   A     procedural-due-process   claim   requires   (1)   a
    14
    constitutionally cognizable liberty or property interest, (2) a deprivation of this
    interest, and (3) a lack of constitutionally adequate notice and a hearing. 
    Id.
     at
    569–70.
    To determine whether a plaintiff has been deprived of procedural due process,
    courts ask two questions: (1) Did the plaintiff possess a protected property or liberty
    interest to which due process protections apply? And if so, (2) was the plaintiff
    afforded an appropriate level of process? Farthing v. City of Shawnee, 
    39 F.3d 1131
    ,
    1135 (10th Cir. 1994). Because we agree with the district court that Martin Marietta
    alleged no plausible protected property or liberty interest, we need address only the
    first question.
    A. Property Interest
    As support for its claim to a protected property interest, Martin Marietta contends
    that it has a right to be on “the Approved List.” Appellant’s Opening Br. at 21. But
    this hardly helps us understand its claim, because our case involves three—not one—
    preapproved lists: the Approved List (pre-October 2010), the Stop-Gap Approved
    List (October 2010 – January 2013), and the Prequalified List (post-January 2013).
    Nowhere has Martin Marietta explained what supports its view that it has a property
    interest in either of the two most recent preapproved lists (the first presumably is not
    in play since Martin Marietta sold aggregate from both quarries until October
    15
    2010).12 Based on its vague and ambiguous use of the term “the Approved List,” we
    understand Martin Marietta to be claiming that it had a property interest to supply
    aggregate from Ottawa Quarry to KDOT and FHWA projects from October 2010,
    when KDOT removed Ottawa Quarry from the Approved List, to January 2013, when
    the new testing was implemented, and perhaps even after that. And for Sunflower
    Quarry, we believe Martin Marietta is asserting that it had a property interest to
    supply aggregate to KDOT and FHWA projects from January 2013 until the present
    and beyond. Whatever Martin Marietta’s theory, which it has failed to explain, it
    must account for its admission that Sunflower Quarry “allegedly failed” the new 660-
    cycle test required in January 2013.
    Martin Marietta argues that the district court erred in concluding that it had not
    plausibly alleged a property interest as needed to state a due-process claim. “The
    Fourteenth Amendment’s procedural protection of property is a safeguard of the
    security of interests that a person has already acquired in specific benefits.” Roth,
    
    408 U.S. at 576
    . The plaintiff “must have more than a unilateral expectation of it. He
    must, instead, have a legitimate claim of entitlement to it.” 
    Id. at 577
    . Such an
    12
    The dissent also ignores the reality that this case involves the three
    mentioned lists, simply joining Martin Marietta in ambiguously lumping them
    together as “the Approved List.” Dissent at 1, 3-5, 8, 10. In addition, the dissent
    leaves unexplained how Martin Marietta could establish a property right in having its
    Ottawa or Sunflower Quarries on each of the three distinct lists. For instance, it fails
    even to acknowledge that material from the Sunflower Quarry failed the 2013 testing
    standards and that material from the Ottawa Quarry wasn’t even tested. We don’t
    “chide” Martin Marietta for this failure. 
    Id.
     at 5 n.6. Instead, in resolving the case, we
    simply point out the deficiencies in its pleading and argument.
    16
    interest does not arise from the Due Process Clause itself, but is “defined by existing
    rules or understandings that stem from an independent source such as state law—
    rules or understandings that secure certain benefits and that support claims of
    entitlement to those benefits.” Driggins v. City of Okla. City, 
    954 F.2d 1511
    , 1513
    (10th Cir. 1992) (quoting Roth, 
    408 U.S. at 577
    ). Martin Marietta must demonstrate
    an “entitlement to a substantive right or benefit” supported by “rules or mutually
    explicit understandings . . . that support [its] claim of entitlement to the benefit and
    that [it] may invoke at a hearing.” Robbins v. U.S. Bureau of Land Mgmt., 
    438 F.3d 1074
    , 1085 (10th Cir. 2006).
    On two grounds, Martin Marietta alleges that it has a property interest:
    (1) KDOT’s discretion in determining which quarries are on the preapproved lists is
    limited by the Standard Specifications; and (2) KDOT has created a mutually explicit
    understanding with suppliers that it will approve aggregate meeting the Standard
    Specifications. Because Martin Marietta has failed to adequately explain its legal
    theory justifying the first ground, we take special care to consider its argument in
    three separate pieces: (1) pre-October 2010, (2) October 2010 through January 2013,
    and (3) January 2013 and beyond.
    1. Pre-October 2010
    As mentioned, before October 2010, KDOT tested aggregate based on the 300-
    cycle test at a 95% durability factor. Both Ottawa and Sunflower Quarries were on
    the Approved List and supplied aggregate to KDOT projects during this time.
    17
    Therefore, we do not understand Martin Marietta to assert any claim based on
    KDOT’s actions before October 2010.
    2. October 2010–January 2013
    In October 2010, after observing D-cracking on Kansas roads, KDOT refined its
    Approved List by requiring that quarries not have failed the stop-gap measure. Martin
    Marietta asserts that KDOT never submitted the stop-gap measure to the FHWA and
    that KDOT never adopted the test into the Standard Specifications. At this juncture,
    Sunflower Quarry remained on the Approved List and so we focus on Ottawa Quarry.
    Ottawa Quarry failed the new stop-gap measure because KDOT employees observed
    D-cracking in at least three such roadways built with Ottawa Quarry’s aggregate and
    the cracking occurring within 20 years of constructing the roadways. As such, KDOT
    removed it from the Approved List, together with eight other quarries.
    We understand Martin Marietta to contend that, because the FHWA did not
    approve the stop-gap measure, and thus it was not included in the Standard
    Specifications, KDOT did not have the authority to remove quarries from the
    Approved List based on a quarry’s failing this test. We do not have to address this
    argument’s relevance here because Martin Marietta did not raise it before the district
    court until its motion for reconsideration. We have held that a party’s attempt to raise
    a new argument in a motion for reconsideration is “not sufficient to preserve it for
    appeal.” Braswell v. Cincinnati Inc., 
    731 F.3d 1081
    , 1093 (10th Cir. 2013). “This
    rule, however, ‘is not inflexible and the matter of what questions may be taken up
    and resolved for the first time on appeal is one left primarily to the discretion of the
    18
    courts of appeals, to be exercised on the facts of individual cases.’” 
    Id.
     at 1092–93
    (quoting Forest Guardians v. U.S. Forest Serv., 
    495 F.3d 1162
    , 1170 n.7 (10th Cir.
    2007)).
    Martin Marietta touched on this argument only briefly in its motion for
    reconsideration. Its argument was so cursory that the district court did not even
    address it in its order denying the motion for reconsideration. Thus, we have no
    obligation to address it at all. See Braswell, 731 F.3d at 1093 (citing Anderson v.
    Unisys Corp., 
    52 F.3d 764
    , 765 (8th Cir. 1995) (declining to rule on an argument
    raised for the first time in a motion for reconsideration when the district court did not
    address the argument)).
    But even if Martin Marietta had raised this argument below, it would fail.13 The
    remaining defendants, King and Younger, contend that nothing in Kansas law
    constrains KDOT’s authority to adopt and change the Standard Specifications to
    fulfill its duties. See 
    Kan. Stat. Ann. § 68-404
    . They explain that just because the
    “amendments must be approved by the [FHWA] for KDOT to receive federal funding
    for certain projects does not create a property [interest] for a supplier such as Martin
    Marietta . . . .” Appellee’s Br. at 47 (emphasis in original). We understand the
    defendants to argue that KDOT might jeopardize federal funding by unilateral
    13
    We reiterate that Martin Marietta did not properly preserve this argument for
    appeal.
    19
    amendments to the Standard Specifications but that its doing so is of no concern to
    Martin Marietta.
    We agree with King and Younger. First, KDOT’s decision to strengthen its testing
    protocols to avoid D-cracking was hardly one likely to raise FHWA’s ire—by
    requiring better aggregate, KDOT would build more durable roads. Second, and
    relatedly, KDOT faced a D-cracking problem threatening public safety and taxpayer
    expenditures. If FHWA took offense to KDOT’s acting quickly on these concerns, it
    had authority to take any necessary actions. But Martin Marietta cannot assume
    FHWA’s authority. Third, KDOT considered and deliberated its potential actions
    before adopting the stop-gap measure from October 2010 to January 2013. Based on
    findings from its studious research on D-cracking,14 KDOT removed nine quarries
    from its Approved List (including Ottawa Quarry) based on demonstrated D-cracking
    associated with use of their aggregate. KDOT continued to remove quarries until
    January 2013 when it implemented its new 660-cycle test designed to ensure the
    14
    The study found that 523 lane-miles of on-grade pavement showed D-cracking
    less than 20 years after construction. Heather A. McLeod, D-Cracking Field
    Performance of Portland Cement Concrete Pavements Containing Limestone in
    Kansas: Phase 1 Report, Kan. Dep’t of Transp. 27 (May 2012),
    ntl.bts.gov/lib/45000/45200/45246/KS123_Final.pdf. The cost of reconstructing two-
    lane concrete pavement per lane-mile is between $800,000 and $1.15 million, while
    the shorter-term remedy of resurfacing costs between $300,000 and $500,000 per
    lane-mile. 
    Id. at 2
    . In addition to monetary considerations, KDOT also must account
    for its responsibility for public safety. Where a supplier is providing inferior
    aggregate, which creates dangerous conditions for drivers by increasing the amount
    of road damage, KDOT must have the flexibility to address the problem quickly. One
    mechanism for ensuring safer roads, thereby protecting the public, is for KDOT to
    heighten the quality-criteria standards for aggregate.
    20
    durability and safety of Kansas roadways.15 Fourth, KDOT’s actions may comport
    with the Standard Specifications. Section 102.18(a) provides that “[e]ven though a
    Contractor is qualified . . . the Prequalification Committee may determine a
    Contractor is otherwise non-responsible as lacking the skills, abilities, or integrity to
    perform the work.” See Bidding Requirements and Conditions, Kan. Dep’t of
    Transp.,     www.ksdot.org/Assets/wwwksdotorg/bureaus/burConsMain/specprov/2007/
    102.pdf. If KDOT is able to deny a benefit to a prequalified contractor based upon
    concerns about the contractor’s skills or abilities to perform the work, we cannot
    believe that KDOT is unable to take similar measures to ensure that materials from
    prequalified suppliers are of the character necessary to produce a quality road. We
    find support for our view in Trout v. Koss Construction Co., 
    727 P.2d 450
     (Kan.
    1986), where the Kansas Supreme Court stated that “it is clear from the Standard
    Specifications that . . . KDOT retains the ultimate authority to dictate safety measures
    to the contractor and to require compliance with such measures.” Trout, 727 P.2d at
    456. We think this applies with equal force to the construction suppliers.
    3. January 2013 and Beyond
    15
    Kreider testified that KDOT’s change to the 660-cycle test occurred because of
    damage KDOT observed on Kansas roads. KDOT began researching the problem (the
    D-cracking project) to understand its cause. During that process, it became apparent
    to KDOT that it needed to modify its Standard Specifications. Ultimately, this led to
    a study that proposed and recommended options. From these, KDOT chose and
    imposed the 660-cycle test.
    21
    For the reasons given, we conclude that in January 2013, KDOT acted within its
    authority under the Standard Specifications in implementing the 660-cycle test. See
    
    Kan. Stat. Ann. § 68-404
    (h) (KDOT has the power “to make tests, do research, to
    inspect and test all materials, supplies, equipment, and machinery used for state
    highway purposes or highway projects involving federal funds, and to develop
    methods and procedures for this purpose”). Sometime near then, KDOT tested
    aggregate from the Sunflower Quarry under its new test, and the aggregate failed to
    meet the new standard. Yet even acknowledging the “allegedly failed” test, Martin
    Marietta still maintains it somehow has a property interest in the Sunflower Quarry’s
    being on the Prequalified List. Appellant’s Opening Br. at 35; Appellant’s App. at
    23, 441. Seemingly, on appeal, Martin Marietta also contends that it has a property
    interest in the Ottawa Quarry’s being on the Prequalified List. Both in its briefing and
    at oral argument, it has failed to explain its supporting rationale. Because we are
    reviewing a dismissal on the pleadings, we broadly review Martin Marietta’s claims
    to see if it has alleged even a single plausible one. See Alvarado, 
    493 F.3d at 1215
    . In
    doing so, we recognize that Martin Marietta may not make some of the claims we
    credit it as making, but given its impreciseness we will err on the side of broadly
    construing its claims to avoid overlooking any.
    Regarding Ottawa Quarry, Martin Marietta never alleges that KDOT tested
    aggregate from the Ottawa Quarry after implementing the new 660-cycle test. To
    claim that Ottawa Quarry should be on the Prequalified List, Martin Marietta must at
    least allege that Ottawa’s aggregate had been tested under the new requirements.
    22
    Because Martin Marietta did not plausibly allege that Ottawa Quarry was tested
    under the 660-cycle test, it has not plausibly alleged entitlement to a place on the
    Prequalified List.
    In its opening brief, Martin Marietta asserts that “[a]gency discretion and
    judgment simply do not come into play; material either meets the detailed
    specifications or it does not.” Appellant’s Opening Br. at 16. Kreider’s deposition
    testimony supports this fact. See id. at 29 (“Mr. Kreider testified that inclusion on the
    [Preapproved List] is governed by the Standard Specifications, not agency
    discretion.” (citing Appellant’s App. at 158–59)). Martin Marietta argues, and we
    agree, that quarries whose aggregate passes the 660-cycle test are placed on the
    Prequalified List, and quarries whose aggregate fails the test are not placed on the
    Prequalified List. But we do not see how this helps Martin Marietta. Aggregate tested
    from the Sunflower Quarry failed the 660-cycle test. Therefore, according to Martin
    Marietta’s own argument, KDOT had no choice but to refuse Sunflower Quarry a
    place on the Prequalified List. This would end our analysis, except Martin Marietta
    may be alleging other theories requiring that Sunflower Quarry be on the Prequalified
    List. We now turn to those possibilities.
    First, we understand that Martin Marietta might be arguing that any quarry owner
    that independently tests its aggregate under the Standard Specifications’ criteria, and
    says its aggregate passes those tests, has a protected property interest. At oral
    argument, Martin Marietta’s counsel stated, “I think you have a property right if you
    meet the criteria.” Oral Arg. at 09:02–09:15. We also see Martin Marietta alluding to
    23
    this idea in its brief when it writes that if it had been granted a hearing, it “could have
    shown that both quarries met the Standard Specifications existing at the time of
    removal.” Appellant’s Opening Br. at 11. This argument must fail because it would
    result in a supplier’s being able to claim a constitutionally protected property interest
    in selling its aggregate to KDOT projects without KDOT’s having any ability to
    oversee the material quality. Under KDOT’s legislatively required supervisory role,
    KDOT must “make tests, do research, to inspect and test all materials” used for road
    construction involving federal funds. 
    Kan. Stat. Ann. § 68-404
    (h). Therefore, it must
    maintain oversight over a quarry’s aggregate quality to comply with state law.
    Second, we understand that Martin Marietta might be arguing that, even if a
    quarry’s aggregate fails KDOT’s test, the owner has a protected property interest if it
    contends that it would pass if given another chance at testing. In essence, Martin
    Marietta may be alleging a property interest in the right to re-test. We see an inherent
    problem in Martin Marietta’s asking for a post-deprivation hearing after its aggregate
    had already failed the 660-cycle test. A deprivation hearing’s purpose is to give an
    individual an opportunity to have a voice in the decision before he is deprived of a
    protected property interest. See Cleveland Bd. of Educ. v. Loudermill, 
    470 U.S. 532
    ,
    542 (1985). But once Sunflower Quarry’s aggregate failed KDOT’s new test, we see
    nothing KDOT could deprive from Martin Marietta.
    Third, we understand that Martin Marietta might be arguing that KDOT’s new test
    is too stringent and that KDOT could adequately protect against D-cracking with
    lower test standards. We take issue with this argument because it would require that
    24
    we supplant KDOT in establishing the appropriate tests. It should go without saying
    that KDOT, not a federal court, should decide what tests and standards to adopt to
    protect motorists from unsafe roadways. If KDOT wants to adopt a 1000-cycle, 99%
    durability factor test, we think it would be perfectly within its rights to do so, even if
    that test would exclude many quarries’ aggregate that in fact would not have caused
    D-cracking.
    But even ignoring everything above, Martin Marietta would still not succeed on
    its appeal, because it is not in privity with KDOT and because its being on any of the
    preapproved lists would not entitle it to any particular outcome. We explain below.
    4. Privity
    Because suppliers of construction materials are not in privity with KDOT and its
    contractors, we reject Martin Marietta’s contention that it has a property interest in
    being on any of KDOT’s preapproved lists. We look to the Standard Specifications
    themselves to determine whether they are for the suppliers’ benefit, and we conclude
    that they are not. The Definitions and Terms section of the Standard Specifications
    make clear that the Standard Specifications make up part of the contract between
    KDOT and the “Contractor.”16 Appellant’s App. at 376. In contrast, the Standard
    Specifications state that “[i]nspection, testing, and approval of Contractor-furnished
    16
    The “Contractor” is “[t]he individual partnership, corporation, other legal
    entity, or any acceptable combination thereof (joint venture) contracting with the
    Secretary to complete the contract.” Appellant’s App. at 376. The “Contract”
    between the Secretary of KDOT and the Contractor setting forth the parties’
    obligations “includes . . . [the] standard specifications . . . .” 
    Id.
    25
    sources of supply are for KDOT’s benefit . . . .” Id. at 367 (emphasis added). A
    “Supplier” is defined as “[a]n individual, partnership, corporation, other legal entity,
    or any combination thereof (joint venture) from which the Contractor obtains
    commodities needed to fulfill the contract. Suppliers are not a party to the contract
    between the Secretary and the Contractor.” Id. at 381 (emphasis added). Thus, we
    know that Martin Marietta is not a party to the contract (that includes the Standard
    Specifications) between KDOT and the contractor.
    We agree with King and Younger that, because Martin Marietta is not a party to
    the contract, it cannot claim a property interest arising out of that contract. In Biby v.
    Boards of Regents, 
    419 F.3d 845
     (8th Cir. 2005), the Eighth Circuit concluded that a
    non-party to the contract who gained from it an incidental benefit had no property
    interest entitling him to due process. Biby, 
    419 F.3d at 852
    ; see Machisa v. Columbus
    City Bd. of Educ., 563 F. App’x 458, 463 n.5 (6th Cir. 2014) (unpublished)
    (“[B]ecause [plaintiff] was not a party to the contract, he had no property interest in
    the contract and therefore cannot bring a procedural due process claim on this basis at
    all.”); Rooker v. Ouray Cty., 504 F. App’x 734, 738 (10th Cir. 2012) (unpublished)
    (concluding that a third-party beneficiary to a contract did not have a property
    interest arising out of the contract). While Martin Marietta may plausibly allege that
    it has an incidental benefit from the contract between KDOT and the contractor—
    eligibility to supply aggregate to state projects—it is not a party to the contract and
    so cannot claim a property interest arising from that contract. In Empire Transit Mix,
    Inc. v. Giuliani, 
    37 F. Supp. 2d 331
     (S.D.N.Y. 1999), the court concluded that a
    26
    construction supplier did not have a property interest in its supply contracts with
    contractors on city projects, because under Second Circuit precedent “involvement in
    publicly-financed projects does not rise to the level of a property interest.” Giuliani,
    
    37 F. Supp. 2d at 335
     (quoting Eastway Constr. Corp. v. City of N.Y., 
    762 F.2d 243
    ,
    250 (2d Cir. 1985), on remand, 
    637 F. Supp. 558
     (E.D.N.Y. 1986), modified, 
    821 F.2d 121
     (2d Cir. 1987)). Likewise here, Martin Marietta cannot claim a property
    interest arising from its involvement in publicly financed construction projects.
    Because KDOT’s Standard Specifications, and therefore the tests at issue, are for
    KDOT’s benefit and not the suppliers’, we conclude that Martin Marietta has no basis
    to claim a property interest arising out of the Standard Specifications. Martin
    Marietta emphasizes that the Standard Specifications “are not locked in a KDOT desk
    drawer accessible only by senior policy-making officials . . . . They are public
    documents KDOT publishes ‘so folks can figure out what specific criteria their
    material must meet.’” Appellant’s Opening Br. at 50 (quoting Appellant’s App. at
    154). But KDOT’s making the Standard Specifications available to the public has no
    bearing on their legal effect. In its very first section, the Standard Specifications state
    that “Suppliers are not a party to the contract,” which undermines Martin Marietta’s
    entire argument. Appellant’s App. at 365. KDOT’s making the Standard
    Specifications available to suppliers is an act done voluntarily and not by any legal
    duty, and therefore no legal obligation—such as providing a pre- or post-deprivation
    hearing—can arise from its having made the Standard Specifications available.
    27
    In addition, we point out that courts typically hesitate to second guess government
    procurement decisions in bidding cases. The Supreme Court has stated:
    Like private individuals and businesses, the Government enjoys the
    unrestricted power to produce its own supplies, to determine those with
    whom it will deal, and to fix the terms and conditions upon which it will
    make needed purchases. . . . Judicial restraint of those who administer
    the Government’s purchasing would constitute a break with settled
    judicial practice and a departure into fields hitherto wisely and happily
    apportioned by the genius of our polity to the administration of another
    branch of Government.
    Perkins v. Lukens Steel Co., 
    310 U.S. 113
    , 127–28 (1940) (footnote omitted); see
    Coyne-Delany Co. v. Capital Dev. Bd., 
    616 F.2d 341
    , 342 (7th Cir. 1980) (citing
    Perkins, 
    310 U.S. at 127
    ) (“[G]overnment enjoys a broad freedom to deal with whom
    it chooses on such terms as it chooses; no one has a ‘right’ to sell to the government
    that which the government does not wish to buy.”). We see wisdom in the caution
    against courts intruding into a state agency’s decision-making authority, particularly
    when it involves public-safety issues.
    5. Entitlement
    But even if Martin Marietta was a party to the contract and thus could assert a
    property interest arising from the Standard Specifications, it would still be unable to
    allege a property interest because being on the preapproved lists would not grant it
    any entitlement. In determining whether a state has created an entitlement in a
    benefit, we must remember that “a benefit is not a protected entitlement if
    government officials may grant or deny it in their discretion.” Town of Castle Rock v.
    Gonzales, 
    545 U.S. 748
    , 756 (2005). “A property interest exists if discretion is
    28
    limited by the procedures in question, that is, whether the procedures, if followed,
    require a particular outcome. However, where the governing body retains discretion
    and the outcome of the proceeding is not determined by the particular procedure at
    issue,” then no property interest exists. Crown Point I, LLC v. Intermountain Rural
    Elec. Ass’n, 
    319 F.3d 1211
    , 1217 (10th Cir. 2003) (citation omitted) (emphasis
    added) (citing Hyde Park Co. v. Santa Fe City Council, 
    226 F.3d 1207
    , 1210 (10th
    Cir. 2000)); see Glover v. Mabrey, 384 F. App’x 763, 777 (10th Cir. 2010)
    (unpublished) (“There is no protected property or liberty interest when the outcome
    of the process is within the government official’s complete discretion.” (citing
    Nichols v. Bd. of Cty. Comm’rs of the City of La Plata, 
    506 F.3d 962
    , 970 (10th Cir.
    2007))).
    Martin Marietta asserts that it has a constitutionally protected property interest in
    being on the preapproved list because the detailed, technical criteria set forth in
    KDOT’s Standard Specifications exclusively govern prequalified status.
    The district court dismissed Martin Marietta’s procedural-due-process claim,
    explaining that
    To assume that the detailed, technical and objective nature of the
    specifications and testing criteria reflects an effort to limit KDOT’s
    discretion in enforcing and applying these standards ignores the nature
    and function of KDOT’s highly technical work and its compelling
    public safety responsibility. . . . Owing to its breadth, this statutory
    mandate plainly and necessarily vests all such matters in the full
    discretion of KDOT to develop its own criteria, methods and procedures
    for this public safety purpose. The related regulations and specifications
    do not otherwise restrict or delimit the manner, the scope or content of
    that discretion to such an extent as to give rise to an entitlement.
    29
    Appellant’s App. at 343–44. It concluded that Martin Marietta had not plausibly
    alleged a property interest because KDOT retained discretion to inspect and judge, at
    the project site, whether the aggregate satisfies the requisite quality criteria, and to
    reject it if not. Therefore, a quarry’s prequalification status does not guarantee that its
    aggregate will be accepted and used on a project. Accordingly, the district court
    concluded that a quarry’s prequalified status guarantees no particular outcome.
    We conclude that the Standard Specifications support the district court’s view.
    For instance, section 1101.5 states that KDOT “reserves the right to re-sample, test
    and reject any previously accepted aggregate if the Engineer has reason to believe it
    no longer complies with the Contract Documents.”17 Appellant’s App. at 386. Similar
    17
    Because the Contract Documents are not in the record, Martin Marietta takes
    issue with the district court’s reliance on this provision that discusses the Contract
    Documents. In response, KDOT notes that the definition of Contract Documents is
    contained in the Standard Specifications:
    An all-encompassing term for all documents relating to the contract and
    hereby incorporated by reference into the contract. The Contract
    Documents include the proposal, exploratory work documents, addenda,
    amendments, contract form, contract bond, standard specifications,
    special provisions, project special provisions, general plans, detailed
    plans, the notice to proceed, material test methods, material test reports,
    material certifications, Part V of the KDOT Construction Manual,
    change orders, payment vouchers, guarantees, warranties, and other
    agreements, if any, that are required to complete the construction of the
    work timely and in an acceptable manner.
    Appellant’s App. at 376.
    We think that this definition adequately explains what the Contract Documents
    are. Based on this definition, we believe that Martin Marietta could not, as it states
    that it could, prove that compliance with the Contract Documents means compliance
    30
    provisions are found in section 106(b), which governs the source of supply, and
    which gives the Engineer or Inspector the authority to “reject materials at the project
    site even if the Engineer or Inspector previously approved the materials at the source
    of supply” and the authority to “reject the materials if, at any time, the Engineer
    determines the materials do not meet the Contract Documents.” Appellant’s App. at
    367. And Part V of the Construction Manual, incorporated under section 101.3, states
    that:
    The acceptance of . . . Aggregate is contingent upon production being
    from approved beds and in compliance with “Official Quality”
    requirements.
    ...
    (5) Continuation of Prequalified Status for [Aggregates]
    After a quarry has been prequalified to produce . . . [a]ggregate from a
    specific bed(s) the prequalified status will continue as long as no major
    changes are made in the production process or occur in the deposit
    characteristics. Changes in deposit characteristics may be discovered
    either visually or through test results performed on Production Samples.
    ...
    When any party feels that any change in the prequalified status of a
    quarry is warranted they should notify the DME [District Materials
    Engineer] responsible for quarry inspection who in turn will advise the
    Chief of Materials and Research. The Chief of Materials and Research
    will review all available information on the changed conditions and
    render a decision on any such changes. Official notification of any
    change in . . . [a]ggregate [p]roduction status for a quarry will be
    ____________________
    merely with the Standard Specifications. Thus, we find that Martin Marietta is not
    entitled to additional discovery on what it means to be in compliance with the
    Contract Documents.
    31
    provided by the DME to the quarry owner/operator and the appropriate
    contractors.
    Appellant’s App. at 368, 372.
    We agree with Martin Marietta that KDOT’s ability to retest the aggregate and
    reject it at the project site does not mean that a party’s qualifying for a preapproved
    list is governed by anything but the Standard Specifications. But KDOT’s ability to
    reject the aggregate for other reasons—project special provisions, material-test
    methods, material-test reports, or change orders—demonstrates that a supplier’s
    being on a preapproved list does not entitle it to sell its material or have that material
    actually accepted at the project site. Martin Marietta even concedes that KDOT can
    reject a supplier’s aggregate at the project site for reasons other than failure to meet
    the appropriate tests, including defects in specific material or because the material
    might fail the Standard Specifications for contamination or size. In addition, Martin
    Marietta points to no law, regulation, or Standard Specification provision that says
    that having prequalified status guarantees that a contractor will actually purchase and
    use its product.
    This matters because “[b]eing on the prequalified list is not a protected interest[]
    since it does not assure the particular outcome, that is, KDOT’s acceptance of the
    aggregate.” Appellant’s App. at 346. The district court concluded that just because “a
    source or supplier has been approved is not a guarantee that its product will be
    accepted and used on a project.” 
    Id.
     Because of KDOT’s ability to reject preapproved
    material for reasons other than passing or failing the Standard Specifications, the
    32
    district court reasoned that it was not examining a regulatory structure where the
    governing body’s “discretion is ‘constrained by particularized and comprehensive
    standards, criteria or conditions outlined by statute . . . .’” Appellant’s App. at 344
    (quoting Interior Contractors, Inc. v. Bd. of Trs. of Newman Mem’l Cty. Hosp., 
    185 F. Supp. 2d 1216
    , 1228 (D. Kan. 2002)).
    We agree with the district court’s ultimate conclusion and find informative this
    court’s discussion of property interests in Teigen v. Renfrow, 
    511 F.3d 1072
     (10th
    Cir. 2007). In Teigen, employees of the Colorado Department of Corrections (DOC)
    sued DOC officials under 
    42 U.S.C. § 1983
    , alleging that the officials had engaged in
    a policy of blacklisting employees in violation of the Due Process Clause. 
    511 F.3d at 1077
    . The employees contended that they possessed, and were deprived of, a
    protected property interest in the right to be considered for promotion and transfer
    according to the standards set forth in the state statutes. 
    Id. at 1080
    . The court wholly
    rejected this proposition, explaining that the “subtle distinction between the right to
    be selected for promotion and the right to take part in the promotion process is
    insufficient to salvage Plaintiffs’ due process claims.” 
    Id.
     at 1080–81. “This is
    because ‘[p]rocess is not an end in itself,’ but instead serves only ‘to protect a
    substantive interest to which the individual has a legitimate claim of entitlement.’”
    
    Id. at 1081
     (alteration in original) (quoting Olim v. Wakinekona, 
    461 U.S. 238
    , 250
    (1983)).
    Likewise, Martin Marietta’s attempt to distinguish between the right to sell its
    aggregate to KDOT projects and the right to have the opportunity to sell its aggregate
    33
    to KDOT projects by being on a preapproved list cannot save its due process claim.
    In Teigen, the court said that “[e]ven assuming state law grants every state employee
    the right to be fairly considered for promotion, this right is not itself a substantive
    right, but rather a vehicle for arriving at the ultimate promotion decision.” 
    Id.
     Martin
    Marietta’s situation is one step removed because there is no assumption that every
    supplier is entitled to have its quarries on a preapproved list. Rather, KDOT
    explicitly requires, through the Standard Specifications, that each quarry pass the
    relevant criteria to be on a list. But even if Martin Marietta’s aggregate at the two
    quarries had passed the test and were on a preapproved list (which they were not), it
    could not plausibly allege a property interest in being on a list because the list is
    merely a “vehicle” for arriving at the ultimate decision of whether the aggregate will
    actually be purchased and used. See 
    id.
     This is because KDOT expressly has the
    discretion to reject aggregate if it has “reason to believe” that the aggregate does not
    comply with the Contract Documents, which include a variety of requirements
    beyond the Standard Specifications, and also because prequalified status does not
    guarantee that Martin Marietta will actually sell its aggregate. See Horsfield
    Materials Inc. v. City of Dyersville, 
    834 N.W.2d 444
    , 459 (Iowa 2013) (finding that a
    supplier of aggregate which, for control purposes, was not included on the City’s list
    of approved suppliers, had no valid due-process claim because it had “no protected
    liberty or property interest at stake, merely an unfulfilled desire to enter into
    contracts to supply materials for Dyersville public improvements”).
    34
    We also find instructive the reasoning in Ruby-Collins, Inc. v. Cobb County, 
    515 S.E.2d 187
     (Ga. Ct. App. 1999). In Ruby-Collins, a county sued a contractor for
    breach of contract, and the contractor counter-claimed under § 1983 asserting that the
    county violated its due-process rights by disallowing the contractor from bidding on
    future projects pending the outcome of the dispute. 
    515 S.E.2d at
    188–89. The
    contractor claimed a property interest in being on the list of pre-qualified bidders. 
    Id. at 189
    . Under Georgia law, the county could reject “some bids or any indefinite
    number of bids” for a project, which the court inferred to mean that no prospective
    bidder had a legitimate claim of entitlement to bid on future projects. 
    Id.
     at 189–90.
    Consequently, it held “that [the contractor] ha[d] no protected property interest in
    remaining on a list of potential bidders pre-qualified to bid on future public works
    contracts.” 
    Id. at 190
    .
    Similarly, Martin Marietta claims a property interest in being on the list of
    preapproved quarries, which in reality would qualify it only to be considered for
    KDOT projects. But KDOT is not bound under the Standard Specifications to ensure
    that aggregate from each quarry on a preapproved list is purchased and later accepted
    at the project site. See Hill v. Grp. Three Hous. Dev. Corp., 
    799 F.2d 385
    , 391 (8th
    Cir. 1986) (concluding that eligible applicants for section 8 housing are not “entitled
    to such benefits” because the private owner retains discretion to select the tenant
    from a pool of eligible applicants (emphasis omitted)); see also Eidson v. Pierce, 
    745 F.2d 453
    , 461 (7th Cir. 1984) (same). KDOT retains its discretion to inspect
    aggregate at any time, even from previously approved sources, and to reject it if the
    35
    Engineer determines it does not satisfy any requirements in the Contract Documents.
    See Nichols v. Bd. of Cty. Comm’rs, 
    506 F.3d 962
    , 970 (10th Cir. 2007) (“[W]here
    the governing body retains discretion and the outcome of the proceeding is not
    determined by the particular procedure at issue, no property interest is implicated.”
    (quoting Crown Point I, 
    319 F.3d at 1217
    )). In addition, KDOT may “reject any
    previously accepted aggregate if the Engineer has reason to believe it no longer
    complies with the Contract Documents.” Appellant’s App. at 386 (emphasis added).
    These provisions demonstrate that even if Martin Marietta’s quarries are granted
    prequalified status, such status does not lead to a particular outcome, because
    aggregate from Martin Marietta’s quarries may never be purchased for KDOT
    projects, and even if it is, it could be rejected at the site.
    The Supreme Court has clearly stated that “[p]rocess is not an end in itself. Its
    constitutional purpose is to protect a substantive interest to which the individual has a
    legitimate claim of entitlement.” Olim, 
    461 U.S. at 250
    . Getting its quarries on a
    preapproved list is the process by which Martin Marietta achieves its ultimate goal—
    supplying aggregate for KDOT and FHWA projects. Martin Marietta points to no law
    or regulation suggesting that it has a legitimate claim of entitlement to supply
    aggregate to KDOT projects. Therefore, Martin Marietta has not plausibly alleged a
    property interest.
    In addition, Martin Marietta relies heavily on a case decided after the district
    court’s order, Brown v. Eppler, 
    725 F.3d 1221
     (10th Cir. 2013). In that case, we held
    that an individual or entity may have a protected property interest if agency rules
    36
    compel particular relief, even when the agency has discretion to change those rules.
    Brown, 725 F.3d at 1126–27. Martin Marietta reads the district court’s order as
    dismissing its claim in large measure on KDOT’s retaining discretion under the
    Standard Specifications to change the tests and criteria for quarries to qualify for the
    preapproved list. But we read the district court’s order differently—not as saying that
    any discretion to change testing requirements per se defeats a property interest (as in
    Eppler, where we reversed the district court’s so concluding with rules governing
    who could ride the city buses), but instead as saying that because KDOT has
    discretion to reject aggregate at the project site, prequalified status does not
    guarantee a particular outcome, and thus there is no protected property interest.
    Martin Marietta also argues that Kreider’s deposition testimony establishes that
    inclusion on a preapproved list is governed by the criteria in the Standard
    Specifications. Although we do not question this point, we again note that the district
    court relied on KDOT’s discretion to reject aggregate at the project site, not its
    discretion or lack thereof in the process for determining which quarries’ aggregate
    receives prequalified status. And we rely not only on KDOT’s ability to reject
    aggregate at the project site but also on the basis that KDOT does not guarantee sales
    to any supplier simply because it is on a preapproved list. We can imagine many
    scenarios in which contractors choose not to purchase materials from certain
    suppliers.
    37
    Next, Martin Marietta argues that the district court erred in comparing “right-to-
    test procedures”18 and “right-to-bid cases.” Appellant’s Opening Br. at 40. We agree
    with the district court that the right-to-bid cases are instructive because part of their
    rationale defeating any property interests is the lack of any guaranteed outcome from
    a right to bid. As with contract bidders, prequalified status does not guarantee
    aggregate sellers any sales of aggregate or acceptance at the project site. See S.
    Disposal, Inc. v. Tex. Waste Mgmt., 
    161 F.3d 1259
    , 1265 (10th Cir. 1998) (“‘[A]
    disappointed bidder has no constitutionally protected property interest’ until it is
    actually awarded the contract.” (quoting Curtis Ambulance of Fla., Inc. v. Bd. of Cty.
    Comm’rs, 
    811 F.2d 1371
    , 1376–77 (10th Cir. 1987))); see also Interior Contractors,
    
    185 F. Supp. 2d at 1225
    . By the same token, a potential supplier has no entitlement to
    sell its material. See Coyne-Delany, 
    616 F.2d at 343
     (“[A] potential supplier to the
    state has no property interest in having its product purchased or specified.”).
    Therefore, regardless of the other differences between these types of cases, we agree
    with the district court’s general premise. Martin Marietta’s ability to distinguish the
    cases in other ways does not help it to undermine our ultimate conclusion.
    In supporting its argument, Martin Marietta also emphasizes the content of King
    and Younger’s fifth footnote, which reads as follows:
    It is accurate that KDOT adopted the 660 cycle test and received
    approval for doing so from [FHWA]. As a result, all quarries were
    18
    We note that Martin Marietta itself described its alleged property interest as a
    right-to-procedure interest. The Supreme Court has concluded that a party cannot
    claim a property interest in a procedure. Olim, 
    461 U.S. at 250
    .
    38
    essentially taken back to square one and required to meet that standard
    in order to be on the [Prequalified List]. From and after January 1, 2013,
    the presence or absence of Martin Marietta’s aggregate on the
    [Prequalified List] has been based simply upon whether the product can
    meet the new freeze/thaw criteria, rather than the field testing that
    caused the initial removal of the Ottawa Quarry.
    Appellee’s Br. at 10 n.5 (citation omitted). Martin Marietta contends that King and
    Younger concede three points here. “First, it confirms that testing under the old
    criteria led to KDOT’s removal of the Ottawa Quarry.” Appellant’s Reply Br. at 23.
    We have no reason to question this statement. “Second, it confirms that inclusion on
    the [Prequalified List] ‘from and after January 1, 2013’ is governed by the new
    criteria.” 
    Id.
     Again, we see no reason to contest this assertion. But Martin Marietta
    has not plausibly alleged that aggregate from Sunflower Quarry passed the new test
    or that aggregate from Ottawa Quarry was ever even tested. And even if it could, we
    still would reject its claim on our earlier stated bases. First, Martin Marietta cannot
    claim a property interest deriving from a contract to which it is not a party. And
    second, it cannot allege a property interest in being on a preapproved list because the
    list does not guarantee any particular outcome.
    Finally, Martin Marietta argues that the district court failed to apply the
    plausibility standard correctly in ruling on the motion for judgment on the pleadings.
    It contends that the court weighed the evidence and drew inferences against the
    plaintiff in violation of that standard. We disagree with how Martin Marietta
    characterizes the district court’s application of the standard. The court relied on the
    provisions of the Standard Specifications, which give KDOT discretion to reject any
    39
    material, even from a prequalified source, to conclude that prequalified status does
    not guarantee a particular outcome. The court did not draw inferences against Martin
    Marietta in coming to that conclusion. Therefore, we find no error in the court’s
    application of the plausibility standard.
    To conclude, we note that in our view Martin Marietta is essentially asking us to
    move outside of the judicial realm and become a super-KDOT. We decline to do so.
    We lack any scientific expertise to determine what aggregate builds safe roads, and
    we lack KDOT’s statutory responsibility for motorist or taxpayer safety. KDOT is in
    the best position to determine the level of error it will tolerate in D-cracking testing,
    and we refuse to question its decision.
    6. Mutually Explicit Understanding
    Martin Marietta also urges us to find that it has established a property interest
    based on a mutually explicit understanding fostered by KDOT—that material
    complying with the Standard Specifications will remain on the preapproved list.
    Although a claim of entitlement may be grounded on specific statutory or contractual
    provisions, it need not be. “A person’s interest in a benefit is a ‘property’ interest for
    due process purposes if there are . . . rules or mutually explicit understandings that
    support his claim of entitlement to the benefit and that he may invoke at a hearing.”
    Casias v. City of Raton, 
    738 F.2d 392
    , 394 (10th Cir. 1984) (quoting Perry v.
    Sindermann, 
    408 U.S. 593
    , 601 (1972)); see Perry, 
    408 U.S. at
    602–03 (holding for
    the first time that a protected property interest derived from a mutually explicit
    understanding rather than laws or regulations). In our view, KDOT has expressly
    40
    stated the requirements to win placement on its approved lists and, as explained,
    Martin Marietta cannot meet them.
    B. Liberty Interest
    Martin Marietta also argues that the district court erred in dismissing its due-
    process claim in which it asserts that it has a liberty interest in its reputation. It
    claims that the Constitution protects this right by guaranteeing Martin Marietta a
    procedure in which it can clear its name. The Fourteenth Amendment protects
    citizens from being deprived of “liberty” as well as “property” without “due
    process.” Gwinn v. Awmiller, 
    354 F.3d 1211
    , 1216 (10th Cir. 2004). Martin Marietta
    argues that it has a protected interest in its reputation, “including a right not to be
    defamed by government officials in a manner that harms its ability to earn a living or
    causes ‘damage [to] [its] standing and associations in [its] community.’” Appellant’s
    Opening Br. at 51 (second and third alterations in original) (quoting Roth, 408 U.S. at
    572–73).
    “‘Where a person’s good name, reputation, honor, or integrity is at stake because
    of what the government is doing to him,’ a protectable liberty interest may be
    implicated that requires procedural due process in the form of a hearing to clear his
    name.” Gwinn, 
    354 F.3d at 1216
     (quoting Jensen v. Redev. Agency of Sandy City, 
    998 F.2d 1550
    , 1558 (10th Cir. 1993)). Damage to reputation alone, however, is not
    sufficient. Id.; see Paul v. Davis, 
    424 U.S. 693
    , 711–12 (1976) (holding that damage
    to reputation alone was not sufficient to establish a protected liberty interest).
    41
    For a plaintiff to prevail on a claim that the government has violated the Due
    Process Clause by damaging its reputation, that plaintiff must satisfy the “stigma-
    plus” standard. That standard requires the plaintiff to demonstrate both
    “(1) governmental defamation and (2) an alteration in legal status.” Nixon v. City and
    Cty. of Denver, 
    784 F.3d 1364
    , 1368 (10th Cir. 2015) (quoting Guttman v. Khalsa,
    
    669 F.3d 1101
    , 1125 (10th Cir. 2012)).
    Martin Marietta claims that KDOT defamed it (1) when KDOT employees
    announced to the concrete and pavement industry that aggregate from Martin
    Marietta’s two quarries could not be trusted to make concrete meeting the Standard
    Specifications, and (2) when KDOT employees attended meetings with some of
    Martin Marietta’s customers and told them that Martin Marietta’s material was poor
    quality. Martin Marietta claims it will show, if permitted, that KDOT “published a
    document with Martin Marietta quarries listed as providing either ‘poor’ or
    ‘unacceptable’ performance.” Appellant’s Opening Br. at 52. Martin Marietta then
    alleges that purely private contractors refused to accept limestone from Martin
    Marietta’s quarries as a result of those statements.
    Assuming all of these allegations are true, we fail to see how they amount to
    defamation. In order to constitute a defamatory statement, the speaker must make a
    false statement. See Bundren v. Parriott, 245 F. App’x 822, 826 (10th Cir. 2007)
    (unpublished) (listing the elements of defamation under Kansas law to include “false
    . . . words” (quoting Hall v. Kan. Farm Bureau, 
    50 P.3d 495
    , 504 (Kan. 2002))).
    Here, KDOT performed tests on Martin Marietta’s two quarries, and it determined
    42
    that the quarries’ aggregate failed those tests. KDOT then disseminated this
    information to the public.
    KDOT did not make any false statements. In fact, Martin Marietta concedes that
    KDOT did not place Sunflower Quarry on the Prequalified List, because it
    determined that its aggregate had failed the new, more stringent freeze-thaw test.
    Because KDOT did not make a false statement regarding Sunflower Quarry, it did
    not defame Martin Marietta. And for Ottawa Quarry, Martin Marietta acknowledges
    that another entity operated Ottawa Quarry and provided the aggregate for pavement
    where a KDOT employee later observed D-cracking. We thus agree with the district
    court’s finding that KDOT’s removal of Ottawa Quarry does not implicate Martin
    Marietta’s business practices because it did not even own the quarry when the
    material in question for D-cracking was provided. Upon review, we find no evidence
    that KDOT made a defamatory statement against Martin Marietta.19
    But even if Martin Marietta could prove that the government had made
    defamatory statements regarding its materials, it could not satisfy the “plus” of the
    stigma-plus standard. First, it cannot argue that the loss of its property interest meets
    the second prong of the stigma-plus standard, see WMX Techs., Inc. v. Miller, 
    197 F.3d 367
    , 376 (9th Cir. 1999) (rejecting a stigma-plus claim because the alleged
    19
    If, however, KDOT had told members of the industry that they should not do
    business with Martin Marietta because it would cheat them, then we would consider a
    defamation claim. But merely sharing information that KDOT believes truthful about
    the quality of aggregate from the Ottawa and Sunflower Quarries does not constitute
    defamation.
    43
    damage to reputation did not amount to the deprivation of a protected property
    interest), because we hold above that Martin Marietta did not plausibly allege a
    property interest.
    Second, Martin Marietta contends that, even if we do not find a property interest,
    it can satisfy the “plus” prong because it has alleged significant harm to its business
    resulting from KDOT’s allegedly false statements. If true, this could satisfy the
    “plus” prong of the test. But we see no basis for this contention. Martin Marietta
    alleges that KDOT’s actions have caused it “financial and economic repercussions
    beyond [its] ability to supply material for KDOT projects,” Appellant’s App. at 21,
    and have “impact[ed] [its] ability to earn a living by selling construction aggregate,”
    id. at 27.
    Assuming these statements to be true, we believe that they fail to demonstrate the
    requisite harm to Martin Marietta’s business as needed to find a violation of its
    liberty interest. Martin Marietta must show more harm to its business than the mere
    fact that it “was no longer able to supply material for [KDOT-funded] jobs.”
    Appellant’s Opening Br. at 54; cf. Jensen, 
    998 F.2d at 1559
     (“Damage to prospective
    employment opportunities is too intangible to constitute deprivation of a liberty
    interest.”); Phelps v. Wichita Eagle-Beacon, 
    886 F.2d 1262
    , 1269 (10th Cir. 1989)
    (stating that mere injury to business reputation is insufficient); Perry v. Fed. Bureau
    of Investigation, 
    781 F.2d 1294
    , 1302 (7th Cir. 1986) (“[A] liberty interest is not
    implicated merely by a reduction in an individual’s attractiveness to potential
    employers.”); Allen v. Denver Pub. Sch. Bd., 
    928 F.2d 978
    , 982 (10th Cir. 1991)
    44
    (“Only where the stigmatization results in the inability to obtain other employment
    does [a liberty-interest] claim rise to a constitutional level.”), overruled on other
    grounds by Kendrick v. Penske Transp. Servs., Inc., 
    220 F.3d 1220
     (10th Cir. 2000).
    Numerous courts have declined to find a liberty interest when the plaintiff is
    denied government business but can still engage in private business. See, e.g.,
    Morley’s AutoBody, Inc. v. Hunter, 
    70 F.3d 1209
    , 1217 n.5 (11th Cir. 1995). Not
    only can Martin Marietta continue to sell aggregate from its Ottawa and Sunflower
    Quarries to contractors engaged in private projects, it can also supply other types of
    rock from the quarries to KDOT-funded projects. We agree with the district court
    that these factual allegations “do not plausibly support . . . a significant impairment
    to [Martin Marietta’s] operating business due to the quarries’ removal from [either
    list].” Appellant’s App. at 355–56.
    Martin Marietta has failed to allege that the defendants have significantly
    impaired its activities as the “second largest producer of construction aggregate used
    in the United States,” Appellee’s Suppl. App. at 1, by not approving Martin
    Marietta’s aggregate from Sunflower and Ottawa. As such, we hold that Martin
    Marietta has not plausibly alleged a liberty interest.
    III.   CONCLUSION
    In sum, we hold that Martin Marietta has failed to demonstrate either a
    constitutionally protected property or liberty interest. Therefore, we affirm the
    district court’s decision denying relief.
    45
    No. 13-3314, Martin Marietta Materials, Inc. v. Kansas Department of Transportation
    MORITZ, J., concurring in part and dissenting in part.
    Throughout its opinion, the majority repeatedly and consistently states that Martin
    Marietta asserts a property interest in actually supplying aggregate from its quarries to
    KDOT projects. Yet Martin Marietta challenges only the dismissal of its claim that it has
    a property interest in inclusion or retention on the Approved List—not in actually
    supplying aggregate.
    Applying a properly cabined due process analysis and considering only whether
    Martin Marietta has a property interest in inclusion or retention on the Approved List, I
    would hold that Martin Marietta has plausibly stated a legitimate claim to entitlement.
    Therefore, Martin Marietta’s removal from that list without notice or hearing violated its
    right to due process under the Fourteenth Amendment. Thus, I dissent from the
    majority’s decision affirming the district court’s dismissal of Martin Marietta’s
    procedural due process claim with respect to its asserted property interest.
    However, because Martin Marietta hasn’t challenged on appeal the district court’s
    conclusion that it wasn’t defamed, I concur in the majority’s decision to affirm the
    dismissal of its liberty interest claim.
    I.     Martin Marietta asserts a legitimate claim of entitlement to inclusion and
    retention on the Approved List.
    To possess a protected property interest, Martin Marietta must show that state
    statutes, established rules, or mutually explicit understandings give it a “legitimate claim
    of entitlement” to that interest. An “‘abstract need or desire for it’ or a ‘unilateral
    expectation’ is insufficient.” Curtis Ambulance of Fla., Inc. v. Bd. of Cty. Comm’rs, 
    811 F.2d 1371
    , 1375 (10th Cir. 1987) (quoting Bd. of Regents of State Colls. v. Roth, 
    408 U.S. 564
    , 577 (1972)).
    “A property interest exists if . . . the procedures in question, . . . if followed,
    require a particular outcome.” Crown Point I, LLC v. Intermountain Rural Elec. Ass’n,
    
    319 F.3d 1211
    , 1217 (10th Cir. 2003). State laws, rules, and regulations don’t create
    property interests if “the governing body retains discretion” to confer or deny a benefit.
    
    Id.
     In determining “whether a plaintiff presents a legitimate claim of entitlement,” the
    court “focus[es] on the degree of discretion given the decisionmaker and not on the
    probability of the decision’s favorable outcome,” Jacobs, Visconsi & Jacobs, Co. v. City
    of Lawrence, 
    927 F.2d 1111
    , 1116 (10th Cir. 1991), or on whether the laws, rules,
    regulations, and procedures in question can be changed, see Brown v. Eppler, 
    725 F.3d 1221
    , 1226-27 (10th Cir. 2013).
    The majority’s analysis goes awry early on when it misstates or miscomprehends
    the interest to which Martin Marietta claims it has a “legitimate claim of entitlement.”
    Specifically, the majority consistently and repeatedly mischaracterizes Martin Marietta’s
    asserted property interest as an interest in actually supplying aggregate from its quarries
    to KDOT projects.1
    1
    See, e.g., Maj. Op. 15 (“[W]e understand Martin Marietta to be claiming that it
    had a property interest to supply aggregate from Ottawa Quarry to KDOT and FHWA
    projects.” (emphasis added)); 
    id. at 15-16
     ((“[F]or Sunflower Quarry, we believe Martin
    Marietta is asserting that it had a property interest to supply aggregate to KDOT and
    FHWA projects.” (emphasis added)); 
    id. at 31
     (“Martin Marietta points to no law,
    regulation, or Standard Specification provision that says that having prequalified status
    2
    Admittedly, Martin Marietta’s pleadings contain some conflicting language
    regarding the scope of the interest it asserts.2 And the district court may have conflated
    those two possible interests in dismissing this case.3 But on appeal, Martin Marietta
    clearly challenges only the district court’s conclusion that it had no property interest in
    remaining on the Approved List, and it concedes its property interest isn’t contingent on
    actually supplying material to KDOT projects. See Aplt. Reply Br. 25 (“Being on the
    Approved List is . . . a right to sell,” which doesn’t “guarantee sales.” (emphasis added));
    cf. Ripley v. Wyo. Med. Ctr., Inc., 
    559 F.3d 1119
    , 1124-25 (10th Cir. 2009) (discussing
    alternative property interests—one in receiving hospital privileges and another in
    exercising those privileges).4 Moreover, KDOT recognizes that Martin Marietta argues it
    ______________________
    guarantees that a contractor will actually purchase and use its product.” (emphasis
    added)); id. at 35-36 (“Martin Marietta points to no law or regulation suggesting that it
    has a legitimate claim of entitlement to supply aggregate to KDOT projects.” (emphasis
    added)).
    2
    See, e.g., Compl., Doc. 1, ¶ 45, at 12 (“Martin Marietta has a liberty and property
    interest in being on the A-Listing and in supplying limestone from its Ottawa Quarry to
    KDOT projects . . . .” (emphasis added)); Proposed First Am. Compl., Doc. 31-1, ¶ 52, at
    13 (“Martin Marietta has a liberty and property interest in being on the A-Listing/PQL
    and in supplying limestone from its Ottawa and Sunflower Quarries to KDOT
    projects . . . . (emphasis added)).
    3
    See Mem. & Order, Doc. 59, at 29 (“[P]laintiffs are unable to allege a plausible
    claim of a protected property interest in remaining on the A-Listing/PQL or in supplying
    aggregate for concrete in KDOT’s on-grade pavement projects.” (emphasis added)).
    4
    Further, in response to questioning at oral argument, Martin Marietta explicitly
    confirmed that its due process claim is based solely on remaining on KDOT’s Approved
    List of aggregate suppliers. See Oral Arg. Trans. at 11:04-11:12 (responding to the
    question, “Are you saying there [are] two different property interests, there’s one
    combined property interest, what is your position?,” with, “Our property interest is being
    on the Approved List.”).
    3
    has a property interest in having “aggregate from its quarries on KDOT’s Approved List
    for use in on-grade pavement.” Aplee. Br. 16-17.
    Martin Marietta clearly asserts a property interest in its inclusion and retention on
    the Approved List, and I would consider only that asserted interest in determining
    whether Martin Marietta has plausibly alleged a violation of procedural due process.
    II.    KDOT lacks discretion to include or remove a qualified quarry from its
    Approved List if that quarry meets the Standard Specifications.
    Having mischaracterized the nature of the asserted property interest, the majority
    compounds its error by applying the degree-of-discretion test to KDOT’s discretion to
    oversee the quality of the aggregate actually used by suppliers.5 But again, Martin
    Marietta doesn’t claim an interest in ultimately supplying aggregate, or in contracting
    with any particular contractor. Nor does Martin Marietta contend that KDOT lacks
    discretion to oversee the quality of aggregate actually used by contractors. I would
    restrict application of the degree-of-discretion test to the property interest alleged, and
    5
    See, e.g., Maj. Op. 23 (“[Martin Marietta’s] argument must fail because it would
    result in a supplier being able to claim a constitutionally protected property interest in
    selling its aggregate to KDOT projects without KDOT having any ability to oversee the
    material quality.” (emphasis added)); id. at 31 (“But KDOT’s ability to reject the
    aggregate for other reasons—project special provisions, material-test methods, material-
    test reports, or change orders—demonstrates that a supplier’s being on a preapproved list
    does not entitle it to sell its material or have that material actually accepted at the project
    site.” (emphasis added)); id. at 33 (“[P]requalified status does not guarantee that Martin
    Marietta will actually sell its aggregate.” (emphasis added)); id. at 36-37 (“And we rely
    not only on KDOT’s ability to reject aggregate at the project site but also on the basis that
    KDOT does not guarantee sales to any supplier simply because it is on a preapproved
    list.” (emphasis added)).
    4
    consider whether KDOT has discretion to include or remove suppliers from its Approved
    List.6
    A.    KDOT’s procedure for including a quarry on the Approved List
    Kansas’ Secretary of Transportation has broad supervisory authority over the
    “construction and maintenance of all roads . . . throughout the state,” with certain
    exceptions not relevant here. 
    Kan. Stat. Ann. § 68-404
    (a). This includes authority “to
    make tests, do research, to inspect and test all materials, supplies, equipment, and
    machinery used for state highway purposes, and to develop methods and procedures for
    this purpose.” 
    Id.
     § 68-404(h). The Secretary may exercise this authority by “adopt[ing]
    rules and regulations,” id. § 68-404(k), and performing “such other acts and duties,” id.
    § 68-404(j), necessary to carry out the State’s transportation-related laws.
    The Secretary has exercised this authority by adopting the Standard Specifications
    for State Road and Bridge Construction (2007), as amended by the Special Provisions to
    the Standard Specifications. Division 1100 of the Standard Specifications “covers the
    6
    The majority chides Martin Marietta for failing to distinguish between the
    Ottawa quarry’s inclusion on the Approved List prior to 2013 and the Sunflower quarry’s
    inclusion on what the majority refers to as a “new” list after 2013. I find the majority’s
    insistence on referring to distinct lists confusing at best, since none of the parties have
    asserted such a distinction. In any event, the majority’s distinction appears to be based on
    KDOT’s ability to change its specifications and create a new list with new specifications,
    which the majority suggests KDOT did in 2013. But as discussed infra, Martin Marietta
    doesn’t dispute KDOT’s ability to change its specifications or even to create a new list
    with new specifications. See Aplt. Br. 23-24. Instead, it simply argues that KDOT not
    only lacks discretion to remove suppliers from the existing Approved List, but also lacks
    discretion to exclude suppliers from the Approved List in the first instance if the supplier
    meets the specifications. See Aplt. Br. 5-10. Thus, even assuming KDOT created an
    entirely new list in 2013, if KDOT lacked discretion to exclude a qualified supplier from
    that list, then the supplier has a property interest in inclusion on that list.
    5
    basis of approval, certification and acceptance of aggregates,” Std. Specs. § 1101.1, and
    incorporates the sampling and testing requirements contained in Part V of KDOT’s
    Construction Manual,7 id. § 1101.2(b)(2). Part V, in turn, provides a specific procedure
    and substantive requirements for sources to prequalify. These procedures and
    requirements are significant because KDOT will reject any aggregates “produced from
    deposits, ledges, or beds that have not been previously approved for quality.” Id.
    § 1101.2(b)(4).
    Inclusion on the Approved List, however, doesn’t guarantee a source will be used
    to supply a KDOT project because contractors choose which source or sources to use. See
    id. § 101, at 9 (defining “suppliers” as entities “from which the Contractor obtains
    commodities needed to fulfill the contract”).
    Part V of KDOT’s Construction Manual provides the process for prequalifying to
    supply aggregate. In general,
    [a]dditional testing is performed on concrete produced with Class I and
    Class II Aggregates to determine if acceptable levels of concrete
    freeze/thaw resistance are provided. The freeze/thaw testing is intended to
    reduce the risk of the occurrence of premature “D-Cracking.” . . .
    Prequalification to produce Class I and Class II Aggregate is granted to a
    quarry on a bed by bed basis for each distinct bed in the quarry face.
    “Official Quality” sampling and testing is also required. The acceptance of
    Class I and Class II Aggregate is contingent upon production being from
    approved beds and in compliance with “Official Quality” requirements.
    Part V § 5.02(c)(1).
    7
    Citations to Part V are to the 2007 version of the Manual, which is located at
    Doc. No. 59-4 of the district court docket.
    6
    Specifically, for inclusion on the Approved List, a quarry operator contacts the
    District Materials Engineer (DME), who is responsible for initiating KDOT’s
    prequalification process. Id. § 5.02(c)(2)a. The Chief Geologist then arranges for a quarry
    inventory and sample collection. Id. § 5.02(c)(2)b. “The quarry inventory and sampling
    procedures will be conducted in accordance with written guidelines maintained by the
    Chief Geologist.” Id. (emphasis added). Then,
    [t]he Engineer of Tests will process and test the . . . samples to determine if
    each bed is in compliance with the specified requirements for Class I and
    Class II Aggregate. . . . The Engineer of Tests will prepare and distribute a
    listing showing the approved Class I and Class II beds for each quarry. . . .
    Inclusion on the approved listing requires 2 consecutive passing
    Production Samples representing current production from beds meeting the
    Class I or Class II requirement. . . . Exception to this process will require
    approval of the Chief of Materials and Research.
    Id. § 5.02(c)(2)c (emphasis added).
    In light of these provisions, it’s clear that inclusion of a quarry bed on the
    Approved List isn’t left to KDOT’s discretion.8 After all, the Standard Specifications
    speak in terms of procedures that “will be conducted in accordance with written
    guidelines,” id. § 5.02(c)(2)b (emphasis added), and require testing to determine
    “compliance with the specified requirements,” id. § 5.02(c)(2)c (emphasis added). By
    adopting these Specifications, KDOT has severely limited its broad statutory discretion;
    if a quarry has two consecutive passing samples meeting the technical substantive
    8
    Indeed, the majority appears to concede that inclusion on the list is governed
    solely by objective criteria, not KDOT’s discretion. See Maj. Op. 31 (“We agree with
    Martin Marietta that KDOT’s ability to retest the aggregate and reject it at the project site
    does not mean that a party’s qualifying for a preapproved list is governed by anything but
    the Standard Specifications.” (emphasis added)).
    7
    requirements in the Standard Specifications, KDOT must include the quarry on the
    Approved List. See id.
    B.     KDOT’s procedure for removing a quarry from the Approved List
    Just as KDOT has adopted rules and specifications limiting its discretion with
    respect to inclusion of a quarry on the Approved List, it has adopted rules and
    specifications similarly limiting its discretion to remove a quarry from the list once that
    quarry has been prequalified. Specifically, Part V provides that “[a]fter a quarry has been
    prequalified . . . the prequalified status will continue as long as no major changes are
    made in the production process or occur in the deposit characteristics.” Id. § 5.02(c)(5)
    (emphasis added); see also Std. Specs. § 1101.4 (“Approved sources remain approved
    only if there are no major changes in the production methods or deposit characteristics.”).
    “Changes in deposit characteristics may be discovered either visually or through test
    results performed on Production Samples.” Part V § 5.02(c)(5).
    Importantly, the meaning of the term “major changes” is not left to KDOT’s
    discretion. Rather, a “major change” occurs if (1) a mining operation moves a
    “significant distance from where the last inventory inspection was made”; (2) “significant
    changes are observed in the deposit characteristics”; (3) it has been two years since an
    active quarry was last reinventoried; or (4) “a production sample fails.” Id.
    Only one provision, Part V § 5.02(c)(5), arguably stands in tension with these non-
    discretionary provisions. It states, “When any party feels that any change in the
    prequalified status of a quarry is warranted they should notify the DME responsible for
    quarry inspection who in turn will advise the Chief of Materials and Research,” who will
    8
    then “review all available information on the changed conditions and render a decision
    on any such changes.” Id. (emphasis added). Both KDOT and the majority rely, at least
    to some extent, on Part V § 5.02(c)(5) to conclude that KDOT’s discretion is sufficient to
    destroy Martin Marietta’s property interest. For the reasons discussed below, § 5.02(c)(5)
    just isn’t capable of that kind of heavy lifting.
    First, KDOT suggests that § 5.02(c)(5) gives it discretion to remove from the
    Approved List any quarry that, “in its judgment, does not produce a product of sufficient
    quality.” See Aplee. Br. 38-39. But interpreting Part V § 5.02(c)(5) to allow KDOT to
    remove a supplier from the list for any reason whatsoever is inconsistent with the
    provisions discussed above, which specifically provide that a quarry’s “prequalified
    status will continue as long as no major changes”—which are specified in Part V and
    which do not apply here—“are made in the production process or occur in the deposit
    characteristics.” Part V § 5.02(c)(5) (emphasis added).
    The majority, on the other hand, concludes Part V § 5.02(c)(5) gives KDOT
    “discretion to reject aggregate if it has ‘reason to believe’ that the aggregate does not
    comply with the Contract documents, which include a variety of requirements beyond the
    Standard Specifications.” Maj. Op. 33 (emphasis added). Even assuming the majority is
    correct, this interpretation renders § 5.02(c)(5) irrelevant to our discussion. The question
    here is whether KDOT retains discretion to remove a supplier from the list—not whether
    it retains discretion to reject aggregate.
    Instead, the most natural and reasonable interpretation of the Part V § 5.02(c)(5)
    is that it permits “any party” to request that the Chief of Materials and Research verify
    9
    that a quarry, once on the Approved List, continues to meet the requirements for
    inclusion on that list as spelled out in the Standard Specifications. Thus, Part V
    § 5.02(c)(5)’s reference to “any change” refers back to the “major changes” specified in
    that section, which provides, “After a quarry has been prequalified . . . the prequalified
    status will continue as long as no major changes are made in the production process or
    occur in the deposit characteristics.” Id. (emphasis added); see also Std. Specs. § 1101.4
    (“Approved sources remain approved only if there are no major changes in the
    production methods or deposit characteristics.” (emphasis added)). This interpretation is
    not only internally consistent but avoids rendering the “major changes” provisions of Part
    V § 5.02(c)(5) and § 1101.4 of the Standard Specifications meaningless.
    Thus, I would hold that KDOT has adopted rules and specifications which limit its
    discretion to remove a preapproved supplier from the Approved List.9
    C.     KDOT’s regulations governing the bidding and supply process don’t
    apply to Martin Marietta’s asserted property right
    Finally, I can’t accept the majority’s attempt to liken Martin Marietta’s asserted
    property interest to that of a “disappointed bidder” or an incidental third-party
    beneficiary, both of which generally lack a property interest in a government contract.
    See Maj. Op. 25-26, 37. Neither analogy is apt. The disappointed-bidder cases the
    9
    KDOT suggests that it “could not perform its legislatively-mandated duties if
    [its] use of technical specifications was construed to prevent it from exercising discretion
    to remove materials that do not perform as required.” Aplee. Br. 56-57. Once again, this
    dire prediction misconstrues the issue and misstates the remedy sought. Nothing prevents
    KDOT from removing a supplier’s quarry from the Approved List if the quarry’s
    aggregate no longer meets the criteria in the Standard Specifications, so long as the
    supplier is afforded due process (e.g., notice and a pre- or post-deprivation hearing) to
    contest the allegations.
    10
    majority cites turn on an examination of the particular regulations governing the bidding
    process, all of which implicitly or explicitly gave the government broad discretion in
    selecting the winning bid.10 As discussed, that is not the case here. Similarly, any analogy
    to third-party beneficiaries of government contracts is also unpersuasive because it
    assumes Martin Marietta claims a property interest as a result of a provision in a contract
    between KDOT and a contractor. But Martin Marietta’s property interest claim doesn’t
    rely on the existence of a contract; it relies on the requirements detailed in the Standard
    Specifications. Privity isn’t a requirement in this circumstance.
    Because KDOT has retained no discretion to exclude or remove a quarry from the
    Approved List so long as that quarry satisfies the Standard Specifications, I would hold
    that Martin Marietta has properly asserted a property interest protected by the Due
    Process Clause of the Fourteenth Amendment.
    10
    See, e.g., Glover v. Mabrey, 384 F. App’x 763, 777 (10th Cir. 2010)
    (unpublished) (holding no property or liberty interest in being prequalified bidder
    because prequalified bidder determination is subject to department of transportation’s
    sole discretion); S. Disposal, Inc. v. Tex. Waste Mgmt., a Div. of Waste Mgmt. of Tex.,
    Inc., 
    161 F.3d 1259
    , 1265 (10th Cir. 1998) (holding plaintiff had no property interest as a
    bidder to waste disposal contract because it was never guaranteed the contract); Curtis
    Ambulance of Fla., 
    811 F.2d at 1383
     (holding plaintiff lacked property interest in contract
    for ambulance services when procedures provided that defendant “may” enter into a
    contract for professional services by competitive bidding); Interior Contractors, Inc. v.
    Bd. of Trs. of Newman Mem’l Cty. Hosp., 
    185 F. Supp. 2d 1216
    , 1228 (D. Kan. 2002)
    (holding Kansas competitive bidding statute requiring certain contracts to go to “lowest
    and best bid” doesn’t confer property right to bidders because standard leaves broad
    discretion to decisionmaker).
    11
    III.   Martin Marietta hasn’t plausibly stated a liberty interest because it hasn’t
    challenged the district court’s defamation holding.
    Martin Marietta also claims a liberty interest in its reputation, specifically a right
    not to be defamed by government officials in a manner that harms its ability to earn a
    living or damages its standing in the community. It alleges that by removing its quarries
    from the Approved List, KDOT announced to the industry that the Ottawa and Sunflower
    quarries could not be trusted to produce acceptable concrete. The district court dismissed
    Martin Marietta’s liberty interest claim, at least in part, because it held that Martin
    Marietta couldn’t establish a property interest.
    The majority affirms the district court’s dismissal of Martin Marietta’s liberty
    interest claim on substantive grounds. But as KDOT points out, Martin Marietta hasn’t
    appealed the district court’s judgment with respect to the state law defamation claim. See
    Mem. & Order, Doc. 59, at 44-47 (dismissing Martin Marietta’s defamation claim for
    failure to state a claim because Kansas doesn’t recognize the tort of product
    disparagement); Aplee. Br. 51 (noting that “Martin Marietta has not appealed the district
    court’s determination that it does not have a valid defamation claim and that
    determination is now the law of the case.”).11 Thus, because Martin Marietta hasn’t
    alleged an actionable defamation claim that could give rise to a protected liberty interest,
    I concur with that portion of the majority’s decision affirming the dismissal of Martin
    Marietta’s procedural due process claim based on an asserted liberty interest.
    11
    In its reply, Martin Marietta doesn’t challenge KDOT’s assertion that the district
    court’s defamation holding is now the law of the case. Rather, Martin Marietta simply
    reiterates its argument that it plausibly alleged defamation in its complaint. See Aplt.
    Reply Br. 11-13.
    12
    

Document Info

Docket Number: 13-3314

Citation Numbers: 810 F.3d 1161

Filed Date: 1/13/2016

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (43)

Forest Guardians v. United States Forest Service , 495 F.3d 1162 ( 2007 )

No. 89-3082 , 927 F.2d 1111 ( 1991 )

Kendrick v. Penske Transportation Services, Inc. , 220 F.3d 1220 ( 2000 )

Crown Point I, LLC v. Intermountain Rural Electric Ass'n , 319 F.3d 1211 ( 2003 )

Curtis Ambulance of Florida, Inc. v. Board of County ... , 811 F.2d 1371 ( 1987 )

Nelson v. State Farm Mutual Automobile Insurance , 419 F.3d 1117 ( 2005 )

Alvarado v. KOB-TV, L.L.C. , 493 F.3d 1210 ( 2007 )

Teigen v. Renfrow , 511 F.3d 1072 ( 2007 )

Nichols v. BD. OF COUNTY COM'RS OF LA PLATA, COLO. , 506 F.3d 962 ( 2007 )

Hyde Park Co. v. Santa Fe City Council , 226 F.3d 1207 ( 2000 )

Robbins v. United States Bureau of Land Management , 438 F.3d 1074 ( 2006 )

James R. Farthing v. City of Shawnee, Kansas , 39 F.3d 1131 ( 1994 )

peter-casias-jr-v-city-of-raton-raton-council-on-alcoholism-inc-james , 738 F.2d 392 ( 1984 )

fred-w-phelps-sr-and-cross-appellee-v-the-wichita-eagle-beacon-steve , 886 F.2d 1262 ( 1989 )

isabella-e-allen-v-denver-public-school-board-robert-baker-individually , 928 F.2d 978 ( 1991 )

Gwinn v. Awmiller , 354 F.3d 1211 ( 2004 )

Kenneth McHenry v. Utah Valley Hospital, a Division of ... , 927 F.2d 1125 ( 1991 )

Sylvia Driggins v. City of Oklahoma City, Oklahoma , 954 F.2d 1511 ( 1992 )

No. 92-4084 , 998 F.2d 1550 ( 1993 )

Southern Disposal, Inc. v. Texas Waste Management , 161 F.3d 1259 ( 1998 )

View All Authorities »