International Business Machines Corporation v. State of Indiana, acting on behalf of the Indiana Family & Social Services Administration ( 2018 )


Menu:
  •                                                                             FILED
    Sep 28 2018, 8:58 am
    CLERK
    Indiana Supreme Court
    Court of Appeals
    and Tax Court
    ATTORNEYS FOR APPELLANT                                    ATTORNEYS FOR APPELLEE
    Jay P. Lefkowitz                                           Peter J. Rusthoven
    Kirkland & Ellis, LLP                                      John R. Maley
    New York, New York                                         J. Curtis Greene
    Meredith Thornburgh White
    Paul D. Clement
    Barnes & Thornburg, LLP
    Kirkland & Ellis, LLP
    Indianapolis, Indiana
    Washington, D.C.
    Andrew W. Hull
    Laurie E. Martin
    Hoover Hull Turner, LLP
    Indianapolis, Indiana
    IN THE
    COURT OF APPEALS OF INDIANA
    International Business Machines                            September 28, 2018
    Corporation,                                               Court of Appeals Case No.
    Appellant/Cross Appellee-                                  49A02-1709-PL-2006
    Defendant/Plaintiff,                                       Appeal from the Marion Superior
    v.                                                  Court
    The Honorable Heather A. Welch,
    State of Indiana, acting on behalf                         Judge
    of the Indiana Family & Social                             Trial Court Cause No.
    Services Administration,                                   49D01-1005-PL-21451
    Appellee/Cross Appellant-
    Plaintiff/Defendant.
    Riley, Judge.
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018                   Page 1 of 32
    STATEMENT OF THE CASE
    [1]   Appellant/Cross-Appellee-Defendant/Plaintiff, International Business
    Machines Corporation (IBM), appeals the trial court’s calculation of damages
    after materially breaching the Master Services Agreement which IBM had
    entered into with Appellee/Cross-Appellant- Plaintiff/Defendant, the State of
    Indiana, Acting on Behalf of the Indiana Family & Social Services
    Administration (State). 1
    [2]   We affirm in part, reverse in part, and remand with instructions.
    ISSUES
    [3]   IBM raises three issues on appeal, which we restate as:
    (1) Whether the trial court, on remand for calculation of damages, erred in
    concluding that the findings of fact issued by the previous trial court,
    presided over by Judge Dreyer after a six-week bench trial, are not part of
    the law of the case and therefore not binding on the trial court;
    (2) Whether the trial court erred in awarding damages to the State that arose
    from the implementation of the Hybrid system, which was purported to
    be different from the system contracted for under the Master Services
    Agreement; and
    1
    We held oral argument on August 21, 2018, in the Supreme Court courtroom at Indianapolis, Indiana. We
    thank counsel for their eloquent oral advocacy and civil professionalism during the argument.
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018               Page 2 of 32
    (3) Whether IBM is entitled to post-judgment interest on its $49.5 million
    damages award.
    [4]   The State raises two issues on Cross-Appeal, which we restate as:
    (1) Whether the trial court correctly applied the direct damages cap specified
    in the Master Services Agreement; and
    (2) Whether the trial court properly rejected the State’s request to include the
    salaries for new state employees as part of its direct damages.
    FACTS AND PROCEDURAL HISTORY
    [5]   The latest installment in the seemingly never-ending saga between the State and
    IBM comes before us as an appeal from the trial court’s Order upon remand
    from the supreme court to calculate the parties’ damages. As this cause has an
    intricate factual matrix, we will rely extensively on the recitations issued in
    previous opinions in this matter.
    [6]   During his first term, Governor Mitch Daniels announced that Indiana’s
    welfare system was “broken” and “plagued by high error rates, fraud, wasted
    dollars, poor conditions for its employees, and very poor service to its clients.”
    State v. IBM, 
    51 N.E.3d 150
    , 153 (Ind. 2016). Governor Daniels called it
    “America’s worst welfare system.” 
    Id. The seeds
    of an overhaul and
    modernization of the system were sown shortly after Governor Daniels and
    senior officials began developing the concept of a welfare eligibility upgrade
    based on a remote eligibility model similar to the one previously instituted in
    Texas. This new system would allow Indiana citizens to apply for welfare
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 3 of 32
    benefits “via web and call center” without the need for face-to-face meetings
    with a case worker, and eligibility determinations would be done on a
    centralized, statewide basis rather than in local county welfare offices. 
    Id. [7] The
    State commenced the outsourcing process by publishing a Request for
    Information 6-C (RFI) in 2005, followed by a Request for Proposal 6-58 (RFP)
    in early 2006, seeking input and recommendations from vendors to improve the
    distribution of welfare resources. IBM submitted proposals as requested by the
    RFP, which designated IBM as the prime contractor while working with several
    subcontractors for operational and subject matter expertise, known as the IBM
    Coalition.
    [8]   On December 27, 2006, after months of negotiations, the State and IBM
    entered into a ten-year, $1.3 billion Master Services Agreement (MSA) in an
    effort to modernize and improve Indiana’s welfare eligibility system. The MSA
    is detailed, comprehensive, and contains more than 160 pages plus extensive
    attachments, including 10 exhibits, 24 schedules, and 10 appendices,
    encompassing all aspects of the parties’ working relationship. “[T]he MSA
    intended to establish centralized service and call centers for the processing of
    welfare applications, enable remote electronic access to the system, provide the
    State a paperless document system, create systems to combat fraud and improve
    Indiana’s poor welfare-to-work record and lower administrative costs.” 
    Id. To that
    end, the MSA set forth the various overarching “Policy Objectives” for the
    modernization effort, which include, in pertinent part:
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 4 of 32
    (i) to provide efficient, accurate and timely eligibility
    determinations for individuals and families who qualify for
    public assistance, (ii) to improve the availability, quality and
    reliability of the services being provided to Clients by expanding
    access to such services, decreasing inconvenience and improving
    response time, among other improvements, (iii) to assist and
    support Clients through programs that foster personal
    responsibility, independence and social and economic self-
    sufficiency, (iv) to assure compliance with all relevant Laws, (v)
    to assure the protection and integrity of Personal Information
    gathered in connection with eligibility determination, and (vi) to
    foster the development of policies and procedures that underscore
    the importance of accuracy in eligibility determinations, caseload
    integrity across all areas of public assistance and work and work-
    related experience for Clients in the Programs.
    (Appellant’s App. Vol. V, p. 21). The MSA also provides that when construing
    and interpreting contractual provisions and terms, “[i]n the event of any
    uncertainties” or in the event of any “ambiguity, vagueness, or inconsistency”
    the “provisions and terms shall be read in a manner consistent with the Policy
    Objectives.” (Appellant’s App. Vol. V, p. 24). However, the MSA cautions
    that:
    [n]otwithstanding the foregoing, in no event shall the Policy
    Objectives change or expand [IBM]’s obligations hereunder
    unless expressly agreed to by the Parties pursuant to a Change.
    (Appellant’s App. Vol. V, p. 25).
    [9]   Pursuant to the terms of the MSA, IBM’s first obligation was to assist the State
    in processing applications under the State’s existing procedures in all Indiana
    counties. Then, the Modernized system was to be rolled out in phases on a
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 5 of 32
    region-by-region basis according to a “preliminary,” “initial Transition
    Timeline.” (Appellant’s App. Vol. V, p. 29). Finally, once Modernization was
    in place in all counties, the project would reach the final stage, “Steady State.”
    
    IBM, 51 N.E.3d at 154
    . The MSA set forth various standards and
    measurements to assess IBM’s performance through the different project stages.
    Throughout Modernization, the State retained the right to make operational
    decisions and kept control over all policy-making authority.
    [10]   Once IBM began to roll out the Modernized version to the 12-county pilot area,
    the parties immediately noticed implementation issues. Despite these
    challenges, the State approved rolling out the project to additional Indiana
    counties. Other disasters also impacted the rollout of Modernization. First,
    after the rollout to the pilot region, Indiana was faced with the Great Recession,
    and the State unemployment rate more than doubled. Because of this, benefit
    applications increased dramatically. Second, Indiana was hit with a series of
    natural disasters beginning in 2008. As a result, the parties mutually agreed to
    suspend rollout of Modernization to accommodate disaster relief efforts. The
    State expanded the scope of IBM’s work 11 times during the course of the
    project. As such, in 2007, the State added a Healthy Indiana Plan (HIP) to
    provide insurance to uninsured Hoosiers below a certain income level. The
    volume of HIP applications far exceeded the State’s initial projections, causing
    IBM to fall further behind in application processing.
    [11]   Despite the State’s initial positive feedback of IBM’s implementation of
    Modernization, in March 2009, Family and Social Services Administration
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 6 of 32
    (FSSA) Secretary, Anne Murphy (Secretary Murphy), requested a formal
    corrective action plan from IBM to address 36 enumerated issues. After IBM
    conducted its own assessment, both parties agreed on a corrective action plan
    which included both short and long-term goals. Even though IBM made some
    improvements in technology and staffing requirements, the overall scope and
    services of Modernization did not improve. In September of 2009, the State
    decided to change its approach and adopted a Hybrid version to welfare
    Modernization, referred to as “Plan B.” 
    IBM, 51 N.E.3d at 157
    . Plan B called
    for a move away from the Centralized Call Center and brought eligibility
    determinations back to the local office, as well as an increase of face-to-face
    contact between clients and staff. While the State initially sought IBM’s
    services to implement Plan B, the parties did not reach an agreement regarding
    the price of the services and no change order was executed.
    [12]   On October 15, 2009, Secretary Murphy notified IBM that the State was
    terminating the MSA for cause, effective December 14, 2009, and asserted that
    IBM’s series of breaches were material considering the MSA as a whole and
    were not curable within 30 days. Following the termination, the State
    implemented the Hybrid approach that retained the majority of the Coalition’s
    subcontractors, but replaced IBM with the State as the general contractor.
    [13]   On May 13, 2010, the State filed a Complaint for damages and declaratory
    relief against IBM, seeking over $170 million in damages. The same day, IBM
    filed a Complaint against the State, demanding damages in excess of $52
    million. Although the two filings initially proceeded under different Cause
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 7 of 32
    Numbers, the trial court consolidated both Causes. After filing and deciding
    numerous motions for summary judgment, the matter proceeded to a six-week
    bench trial, Judge Dreyer presiding. In its 65-page findings of fact and
    conclusions thereon, the trial court determined, among other items, that the
    State had failed to prove that IBM materially breached the MSA and found that
    IBM had substantially performed the MSA. The trial court awarded $49.5
    million to IBM in past-due fees that the State was required to pay pursuant to
    the MSA. This award included $9.5 million in equipment fees for the IBM-
    owned computer equipment the State kept after terminating the MSA and $40
    million in subcontractor assignment fees, which were contractually required
    payments owed to IBM as a result of the State’s decision to purchase IBM’s
    interest in its contracts with certain IBM subcontractors.
    [14]   On appeal, this court’s majority opinion reversed the trial court on the material
    breach issue, finding that IBM had materially breached the MSA. See State ex
    rel. Indiana Family & Soc. Servs. Admin. v. Int’l Bus. Machines Corp., 
    4 N.E.3d 696
    ,
    702 (Ind. Ct. App. 2014), vacated in part. The appellate majority looked to the
    Policy Objectives to define the essence of the contract and found that the MSA
    intended “to provide and expand access to services for welfare recipients in a
    timely, reliable and efficient manner” while remaining within federal
    guidelines, reducing fraud and increasing work-participation rates. 
    Id. at 718.
    It concluded that IBM had failed to do so. 
    Id. at 728.
    However, the court of
    appeals unanimously affirmed the trial court’s award of $49.5 million to IBM
    for equipment fees and subcontractor assignment fees. 
    Id. at 747.
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 8 of 32
    [15]   The parties each filed cross-petitions to transfer on several issues, including
    whether IBM materially breached the MSA, whether IBM was entitled to
    deferred fees for costs incurred during the project, and whether IBM was
    entitled to assignment fees for the State assuming IBM’s subcontracts. The
    Indiana Supreme Court granted transfer on those petitions. Addressing the
    question of the material breach, our supreme court held that IBM materially
    breached the MSA. See 
    IBM, 51 N.E.3d at 158
    . However, like the court of
    appeals before it, the supreme court affirmed the trial court’s $49.5 million
    award to IBM. It then remanded to the trial court to determine the amount of
    fees IBM would be entitled to for Change Orders 119 and 133 and for
    calculation of the parties’ damages, including any appropriate offsets to the
    State as a result of IBM’s material breach of the MSA. See id at 168-69. Shortly
    thereafter, the State and IBM stipulated to the entry of a judgment on Change
    Orders 119 and 133 in favor of IBM and against the State in the amount of
    $311,096 with post-judgment interest to be determined by the trial court under
    Indiana law. The parties agreed that the amount of the Change Orders would
    be entered by the trial court at the time the court ruled on IBM’s request for
    post-judgment interest and the State’s claim for damages.
    [16]   Upon remand, the trial court, presided over by Judge Dreyer, considered the
    issue of the State’s claimed damages and, on May 6, 2016, found that the State
    was not entitled to any damages from IBM’s material breach. That same day,
    the State moved for a change of judge under Indiana Trial Rule 76(C)(3) and
    sought a writ with the supreme court, compelling the trial court to vacate all
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 9 of 32
    orders issued in the case since certification of the supreme court’s decision. On
    July 5, 2016, the supreme court ordered the trial court to grant the State’s
    petition for a new judge and “to vacate all orders issued in the underlying case
    on or after May 6, 2016.” State v. Marion Superior Court, 
    54 N.E.2d 995
    , 995
    (Ind. 2016).
    [17]   Revisiting the issue of damages, the trial court, presided over by Judge Welch,
    found that it was not bound by the prior trial court’s findings of fact and
    conclusions thereon issued after the six-week bench trial. After extensive
    review, a full-day hearing, and post-hearing submissions, the trial court entered
    its very detailed and extensive Order, covering 83 pages and including 387
    findings of fact and conclusions thereon. The trial court awarded the State $125
    million in direct damages on its breach of contract claim, based largely on the
    costs the State incurred by implementing Hybrid after terminating
    Modernization pursuant to the MSA, and $3 million in consequential damages.
    The court denied IBM’s request for post-judgment interest on its $49.5 million
    award. Offsetting the State’s pre-interest liability to IBM, the trial court entered
    a final judgment, ordering IBM to pay the State more than $78 million.
    DISCUSSION AND DECISION
    I. Law of the Case
    [18]   As a first and overarching procedural argument, IBM posits that the trial court,
    presided over by J. Welch, erred in setting aside the factual findings in Judge
    Dreyer’s extensive 65-page opinion in which Judge Dreyer found no material
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 10 of 32
    breach after the original six-week trial. IBM maintains that the supreme court
    accepted these findings and only held that the trial court had applied the wrong
    legal test to those facts. Accordingly, IBM contends that the supreme court’s
    holding, including its affirmance of the $49.5 million award to IBM, and its
    subsequent limited remand to calculate damages did not nullify Judge Dreyer’s
    factual findings that Modernization and Hybrid were materially different. As
    Judge Dreyer’s initial findings must stand, and the trial court could not set aside
    these factual findings, the entire damages award “requires vacatur.”
    (Appellant’s Br. p. 24).
    [19]   In support of its argument, IBM relies on Greater Clark Cty. Sch. Corp. v. Myers,
    
    493 N.E.2d 1267
    (Ind. Ct. App. 1986). In Greater Clark, the school board
    terminated Myer’s employment without first obtaining the statutorily required
    recommendation of the school superintendent. 
    Id. at 1268.
    On appeal, we
    concluded that Myers had been wrongfully terminated, reversed the trial court’s
    judgment, and remanded to the trial court for determination of damages. 
    Id. During the
    hearing on remand, Greater Clark argued that because the judgment
    was reversed on appeal, “the judgment was voided and the parties were
    returned to their original positions. Thus, Greater Clark opine[d], the merits of
    Myers’s termination were relevant to the issue of damages.” 
    Id. at 1270.
    The
    court of appeals disagreed. Noting that “[t]he reversal and remand for
    determination of Myers’s damages necessarily implied the entry of judgment in
    favor of Myers by the [c]ourt of [a]ppeals, an action within its inherent
    authority,” this court affirmed the trial court’s decision that the only issue
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 11 of 32
    before it on remand was the amount of damages. 
    Id. IBM asserts
    that Greater
    Clark stands for the proposition that “while a complete reversal typically
    nullifies the trial court’s opinion, a reversal coupled with a limited remand for
    calculation of damages implies that the reviewing court decided certain facts
    that bind the parties as law of the case.” (Appellant’s Br. p. 30). Accordingly,
    IBM maintains that because the supreme court embraced Judge Dreyer’s
    factual findings, the decision below must be vacated and remanded with
    instructions to adhere to the factual findings entered after the bench trial. We
    disagree.
    [20]   Facts determined at one stage of a proceeding, which were part of an issue on
    which judgment was entered and appeal taken, are unalterably and finally
    established as part of the law of the case and may not be relitigated at a
    subsequent stage. St. Margaret Mercy Healthcare Ctr., Inc. v. Ho, 
    663 N.E.2d 1220
    ,
    1222 (Ind. Ct. App. 1996). Even if the judgment is erroneous, it nevertheless
    becomes the law of the case and thereafter binds the parties unless successfully
    challenged on appeal. Certain Northeast Annexation Area Landowners v. City of Fort
    Wayne, 
    622 N.E.2d 548
    , 549 (Ind. Ct. App. 1993), reh’g denied, trans. denied. All
    issues decided directly or by implication in a prior decision are binding in all
    further portions of the same case. Am. Family Mut. Ins. Co. v. Federated Mut. Ins.
    Co., 
    800 N.E.2d 1015
    , 1019 (Ind. Ct. App. 2004) (American Family II). The
    doctrine does not foreclose legitimate appeals of issues not previously decided,
    but is invoked in the interests of judicial economy and prompt dispensation of
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 12 of 32
    justice to preclude the promotion of potentially endless litigation and appeals.
    
    Id. at 1019.
    [21]   In Am. Family Mut. Ins. Co. v. Federated Mut. Ins. Co., 
    775 N.E.2d 1198
    , 1206
    (Ind. Ct. App. 2002) (American Family I), we specifically found that
    “Federated’s policy attempting to exclude the Browns from uninsured motorist
    coverage because they are not directors, officers, partners, and owners of the
    named insured is void[,]” and that “Federated failed to produce evidence that
    Allied expressly waived this statutory requirement in writing.” We also stated
    that failure to obtain written rejection of uninsured motorist coverage will
    require an insurer to provide uninsured motorist coverage equal to bodily injury
    liability limits, and there had been no written rejection of full-liability limits of
    uninsured motorist coverage by Allied. 
    Id. Therefore, we
    unequivocally
    ordered Federated to provide uninsured motorist coverage. 
    Id. at 1207.
    [22]   On remand, Federated filed an amended exhibit list, including a document
    which indicated that there had been a waiver. American Family 
    II, 800 N.E.2d at 1018
    . This document had not been included in the material on which
    Federated relied for summary judgment in the first appeal, but American
    Family had raised the lack of a written waiver as an issue in its cross-motion for
    summary judgment in the first appeal. 
    Id. at 1019.
    The trial court denied
    American Family’s motion to strike the exhibit and granted Federated’s motion
    for summary judgment. 
    Id. On appeal
    after remand, we distinguished
    decisions where we declined to invoke the law of the case doctrine when
    additional or new evidence was presented after remand “where the evidence
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 13 of 32
    after remand was in accordance with our instructions or did not alter a matter
    that had already been finally determined.” 
    Id. at 1021.
    Contrasting this case
    law with American Family I, we noted that “[o]ur multifaceted approach—on
    statutory, public policy, contract, and evidentiary grounds to the broad issue
    [of] whether Federated was required to provide uninsured motorist coverage for
    the Browns, left no gap to be filled by the presentation of additional evidence on
    remand.” 
    Id. Even if
    one aspect “was arguably wrongly decided due to
    Federated’s failure to present all the evidence on the issue, that issue was
    nonetheless finally determined on the merits.” 
    Id. Accordingly, as
    the issue
    had been “decided directly” on the merits, we reversed the trial court’s decision.
    
    Id. at 1022.
    [23]   Deciding whether the factual determination on Modernization and Hybrid are
    part of the law of the case and binding upon us, we note that although the
    supreme court mentioned and explained Modernization versus Hybrid in its
    Facts section, in its Discussion section, the supreme court was silent on Hybrid
    and merely analyzed how the problems with Modernization led to the
    termination of the MSA and to the determination of a material breach. See
    IBM, 
    51 N.E.2d 150
    . The court held in its Conclusion, in pertinent part, as
    follows:
    Because IBM failed to perform satisfactorily as determined by the
    State (and by its own admission), consistently failed to meet
    certain timeliness metrics, and failed to assist the State in
    achieving its Policy Objectives, we hold that IBM did materially
    breach the MSA through its collective breaches in light of the
    MSA as a whole. We therefore reverse the trial court’s finding
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 14 of 32
    that IBM did not materially breach the MSA. We summarily
    affirm the [c]ourt of [a]ppeals on all other issues including:
    affirming the trial court’s award of $40 million in assignment fees
    and $9,510,795 in equipment fees to IBM, affirming the trial
    court’s denial of deferred fees to IBM, and reversing the trial
    court’s award of $2,570,621 in early termination close out
    payments and $10,632,333 in prejudgment interest to IBM. We
    also remand the case to the trial court to determine the amount of
    fees IBM is entitled to for Change Orders 119 and 133, and for
    calculation of the parties’ damages consistent with this opinion,
    including any appropriate offsets to the State as a result of IBM’s
    material breach of the MSA.
    
    Id. at 168-69.
    Accordingly, as the supreme court ultimately and decidedly
    established the issue of material breach, it remanded for the calculation of the
    parties’ damages. In reaching its conclusion that IBM had breached the MSA,
    the supreme court did not touch on whether Hybrid was a continuance of
    Modernization or a completely different system. As such, a gap needed to be
    filled by the presentation of additional evidence on damages before the trial
    court on remand. See American Family 
    II, 800 N.E.2d at 1021
    . Because the
    evidence after remand was in accordance with the supreme court’s instructions
    and did not alter the issue of material breach that became quintessentially the
    law of the case, the parties were free to litigate the possible distinction between
    Modernization and Hybrid as it related to the calculation of the State’s
    damages. See 
    id. at 1021.
    II. Damages Resulting From Hybrid
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 15 of 32
    [24]   Acknowledging that the State is entitled to obtain damages for the benefit of its
    bargain under the MSA, IBM limits the State’s scope of damages to damages
    resulting from Modernization. However, as the overwhelming majority of
    damages awarded by the trial court were costs derived from the implementation
    of Hybrid, IBM maintains that those costs are not recoverable under the MSA
    because Hybrid differs in material and critical respects from the contracted-for
    Modernization.
    A. Standard of Review
    [25]   Our review of a damages reward is limited. Hooker v. Norbu, 
    899 N.E.2d 366
    ,
    658 (Ind. Ct. App. 2008). We neither reweigh the evidence nor judge the
    credibility of witnesses, and will reverse an award only when it is not within the
    scope of the evidence for the factfinder. 
    Id. We review
    questions of law de novo.
    
    Id. [26] Furthermore,
    the trial court issued findings of fact and conclusions of law
    pursuant to Indiana Trial Rule 52. Trial Rule 52(A) provides that on appeal of
    claims tried to the bench, “the court on appeal shall not set aside the findings or
    judgment unless clearly erroneous, and due regard shall be given to the
    opportunity of the trial court to judge the credibility of the witnesses.”
    Woodsmall v. Lost Creek Tp. Conservation Club, Inc., 
    933 N.E.2d 899
    , 902 (Ind. Ct.
    App. 2010), trans. denied.
    B. Hybrid vs Modernization
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 16 of 32
    [27]   IBM’s main substantive contention revolves around the trial court’s
    determination that the costs derived from Hybrid, which was implemented by
    the State after terminating the MSA, was not a fundamental departure from
    Modernization and thus could be recovered as direct damages.
    [28]   The measure of damages in a breach of contract case is the loss actually suffered
    by the breach. Dana Companies, LLC v. Chaffee Rentals, 
    1 N.E.3d 738
    , 748 (Ind.
    Ct. App. 2013), trans. denied. To recover under a breach of contract claim, the
    State must show that its damages flowed directly and naturally from the breach.
    See 
    id. Although no
    particular degree of certainty is required in awarding
    damages, the award must be within the scope of the evidence. 
    Id. Damages may
    not be awarded on guess or speculation, but must be ascertainable with
    reasonable certainty. 
    Id. “Consequential damages
    may be awarded on a
    breach of contract claim when the non-breaching party’s loss flows naturally
    and probably from the breach and was contemplated by the parties when the
    contract was made and are generally limited to reasonably foreseeable
    economic losses.” Berkel & Co. Contractors, Inc. v. Palm & Associates, Inc., 
    814 N.E.2d 649
    , 658-59 (Ind. Ct. App. 2004).
    [29]   In support of its argument that Modernization and Hybrid are two distinct
    systems, IBM focuses on what it characterizes as the three core features: (1)
    Hybrid moved away from the Central Call Center envisioned by Modernization
    and moved eligibility determinations back to the local office, while renewing
    the focus on face-to-face contact; (2) Hybrid abandoned the task-based
    processing of Modernization and returned to the case-based model; and (3) in
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 17 of 32
    its renegotiation with subcontractors, the State changed their scope of work to
    fit the scope of work required to implement Hybrid.
    [30]   When the State first sought to modernize its welfare services delivery system, it
    published in its RFI that the FSAA “is not specific how Respondents might
    propose to build and manage a solution to realize a vision. The process is
    designed to take best advantage of Respondent’s [sic] expertise in realizing
    similar visions in other states and related challenges in the commercial section.”
    (Appellant’s App. Vol. IV, p. 32). Accordingly, “while this RFI mentions
    potential solution components in several areas, none is offered as a
    requirement. FSSA is looking to Respondents to describe how they would
    provide the scope of services.” (Appellant’s App. Vol. IV, p. 31).
    [31]   What IBM now characterizes as unique, Hybrid features were promised from
    the outset in IBM’s Response to the State’s RFI. In both narrative form and
    diagram, IBM assured the State that face-to-face assistance for welfare
    applications was part of IBM’s proposed solution. IBM clarified that “[w]hile
    their frequency may decrease with these additional access venues, face-to-face
    contact is still an important need for some clients. Local offices provide a
    setting for those clients who simply want to sit down with someone for one-on-
    one guidance and support.” (Appellant’s App. Vol. III, p. 154). Prior to
    entering the MSA, the inter-agency Review Committee, appointed by the State
    to review IBM’s Response to the RFI, suggested some revisions to
    Modernization to foster its success. One of these revisions was the requirement
    that Modernization maintain at least one office in every county to “allow
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 18 of 32
    clients to apply for benefits in person as they have always done.” (Appellant’s
    App. Vol. IV, p. 89).
    [32]   Turning to the Policy Objectives of the MSA, we note that the contract fails to
    refer to the core features now relied upon by IBM. Instead, the Objectives
    require that IBM’s Modernization “improve the availability, quality, and
    reliability of the services being provided to Clients by expanding access to such
    services.” (Appellant’s App. III, p. 152). Schedule 3, incorporated into the
    MSA and detailing the Vendor Services Environment, confirms that the Hybrid
    features which IBM describes as a departure from Modernization were part of
    IBM’s initially defined obligation. Specifically, Schedule 3 included in IBM’s
    service delivery model “the use of face-to-face customer service with enabling
    technologies to allow the Client the freedom to choose the initial and
    continuing methods of access which best meets their needs.” (Appellant’s App.
    Vol. VI, p. 5). It elaborates that IBM will establish a “Help Center” in each
    county where Clients can meet directly with a service provider.” (Appellant’s
    App. Vol. VI, p. 6). Schedule 3 does not advance a Centralized Call Center as a
    Modernization requirement, but a different solution accomplishing the same
    objectives was not precluded by the Schedule.
    [33]   Based on the substantial evidence before us, IBM’s attempt to immunize itself
    from the consequences of its material breach by claiming a fundamental
    distinction between Modernization and Hybrid is unpersuasive. It is evident
    that face-to-face client services were envisioned from the inception of
    Modernization and have always been available from the beginning of the
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 19 of 32
    State’s modernization of its welfare services. Only after the system of in-person
    services was found to be inefficient during Modernization did the State request
    IBM to review and rework it for Hybrid. The State’s decision to eliminate the
    Centralized Call Center instituted during Modernization does not remove
    Hybrid from the scope and objectives of the MSA. Nowhere does Schedule 3
    mention that a Centralized Call Center was a Modernization requirement or
    that a different solution accomplishing the same objective is prohibited. Even
    though the Centralized Call Center as run by IBM was eliminated due to its
    inefficient performance, its original structure and purpose continue in Hybrid,
    and are now combined with a remote eligibility application process.
    Furthermore, evidence reflects that the State still processes applications through
    tasks, Hybrid just routes these tasks differently. Most telling is the testimony in
    the record of Deputy Director Roger Zimmerman, the State’s architect of
    Hybrid, during the six-week bench trial, reiterating that Hybrid “required going
    through [M]odernization to get there.” (Appellant’s App. Vol. III, p. 42).
    Accordingly, we conclude that Hybrid fits the scope, objectives, and
    requirements of the MSA and implements a working version of Modernization.
    Therefore, costs incurred to implement Hybrid are recoverable as damages due
    to IBM’s material breach of the MSA.
    C. Damages
    [34]   In addition to the overall statement that costs incurred as a result of Hybrid are
    not recoverable as damages under the MSA, IBM also contends that certain
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 20 of 32
    specific categories of Hybrid-related damages should not have been awarded to
    the State.
    [35]   The trial court characterized the State’s costs derived from the implementation
    of Hybrid as Reprocurement Costs (and thus direct damages) based on its
    definition in the MSA. Reprocurement Costs are recoverable under the MSA,
    when:
    In the event of a Termination pursuant to Section 16.3.1
    (Termination for Cause) . . ., reasonable costs and expenses
    incurred by the State to bring the applicable terminated Services
    in-house or to procure services similar to the applicable
    terminated Services from an alternate source to the extent such
    costs and expenses would not have otherwise been incurred by
    the State but for the Termination, including:
    (i)      The cost differential between the Fees paid under this
    Agreement and the replacement costs of such Services
    from another contractor,
    (ii)     Administrative costs and expenses reasonably necessary to
    replace the applicable terminated portion of this
    Agreement, including the costs and expenses of
    competitive bidding, mailing, advertising, applicable fees,
    charges, staff time costs and costs and expenses of external
    advisors, consultants and attorneys to assist with such
    procurement, and
    (iii)    Other reasonable costs necessary to such procurement or
    insourcing.
    (Appellant’s App. Vol. III, p. 137).
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 21 of 32
    [36]   Contending that the trial court erred by awarding the State over $103 million
    for the increased cost of subcontractors, IBM asserts that this damage award
    would place the State in a better position than before the breach because it is
    charging IBM for a different and more expensive system than the parties
    contracted for. First, we already determined that Modernization and Hybrid
    are essentially the same systems, albeit under a different name. The State
    contracted with IBM to build a Modernized welfare system, which it failed to
    do. The State stepped in, contracted with the same subcontractors IBM had
    previously entered into subcontracts with, and built its system in accordance
    with the Hybrid specifics. Because these costs “flowed directly and naturally”
    from IBM’s breach of the MSA, and the services procured by the State were
    similar to the applicable terminated services, IBM is responsible for this
    increased cost. See Dana Companies, 
    LLC, 1 N.E.3d at 748
    .
    [37]   In a similar vein, IBM disputes the trial court’s award of $22.5 million damages,
    including the $9.7 million for hardware and software maintenance costs, $4.1
    million in overtime pay, $3.7 million in new lease costs, and “millions more in
    consulting fees.” (Appellant’s Br. p. 47). IBM contends that these damages do
    not result from losses caused by its own conduct. Again, we disagree. The
    renewed attention on the face-to-face customer service in Hybrid caused the
    State to reallocate more resources to the local offices to alleviate the problems
    resulting from the previously understaffed local offices under Modernization.
    These numbers merely represent “reasonable costs associated with bringing a
    similar service in-house” and are included in the “administrative costs and
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 22 of 32
    expenses reasonably necessary to replace the applicable terminated portion of”
    the MSA. (Appellant’s App. Vol. III, p. 137). Consequently, we affirm the trial
    court’s damage award.
    III. Post-Judgment Interest
    [38]   In its final argument, IBM contends that the trial court erred by not awarding it
    post-judgment interest on its $49.5 million damages award entered by Judge
    Dreyer in its July 18, 2012 Order.
    [39]   The right to post-judgment interest arises as a matter of statutory law. Tincher v.
    Davidson, 
    784 N.E.2d 551
    , 553 (Ind. Ct. App. 2003). Under Indiana law, a
    person awarded a monetary judgment against the State is entitled to post-
    judgment interest that accrues until the judgment is paid. I.C. § 34-13-1-6.
    However, “an execution shall not issue but the judgment shall draw interest at
    an annual rate of six percent (6%) from the date of the adjournment of the next
    ensuing session of the general assembly until an appropriation is made by law
    for the payment and the judgment is paid.” I.C. § 34-13-1-6.
    [40]   “If a judgment is reversed on appeal and remanded to the trial court for the
    entry of a new judgment, post-judgment interest accrues from the date the trial
    court enters the new judgment.” 
    Beam, 765 N.E.2d at 534
    . In Beam, the parties
    stipulated at trial that the jury would assess liability for an automobile accident
    and determine the damages, while the trial court would calculate the propriety
    of setoffs that Beam received from other sources. 
    Id. at 527.
    After the jury
    returned its verdict, the trial court reduced the damages by the entire amount of
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 23 of 32
    Beam’s worker’s compensation benefits, even though he had only been assessed
    45% at fault. 
    Id. On appeal
    , our supreme court determined that the trial court
    should have only reduced the jury verdict by 55%, and not 100%, of the
    worker’s compensation benefits amount that Beam already received. 
    Id. at 533-
    34. In doing so, the supreme court determined that it was not reversing the trial
    court’s judgment but rather modifying the jury’s verdict. 
    Id. at 534.
    Citing I.C.
    § 24-4.6-1-101, our supreme court concluded that post-judgment interest on a
    modified award should run from the date of the original verdict and not from
    the date that the verdict was modified. 
    Id. at 534-35.
    The supreme court added
    that when a judgment has been reversed on appeal and remanded for entry of a
    new judgment, then the post-judgment interest on the new judgment would
    begin to accrue from the date the trial court enters the new judgment. 
    Id. at 534.
    [41]   Judge Dreyer’s first Order, issued on July 18, 2012, decided:
    148. Trial judgment entered for IBM and against the State on
    IBM’s Complaint in the amount of [$12,081,416]. Previous
    summary judgment is reiterated in the amount of [$40] million.
    Final judgment amount totals [$50,081,416] plus prejudgment
    interest and costs.
    149. Judgment entered for IBM and against the State on the
    State’s Complaint, and the State takes nothing.
    (Appellant’s App. Vol. III, p. 66).
    [42]   On February 13, 2014, this court
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 24 of 32
    Affirm[ed] the trial court’s award of $40 million in assignment
    fees and $9,510,795 in Equipment fees to IBM, affirm[ed] the
    trial court’s denial of Deferred Fees to IBM, reverse[d] the trial
    court’s award of $2,570,621 in Early Termination Close Out
    Payments and $10,632,333 in prejudgment interest to IBM, and
    remand[ed] the case to the trial court to determine the amount of
    fees IBM is entitled to for Change Orders 119 and 133 and to
    determine the State’s damages and offset any damages awarded
    to IBM as a result of IBM’s material breach of the contract.
    State v. IBM, 
    4 N.E.3d 696
    , 747 (Ind. Ct. App. 2014), vacated in part.
    [43]   After granting transfer, our supreme court concluded on March 22, 2016,
    We therefore reverse the trial court’s finding that IBM did not
    materially breach the MSA. We summarily affirm the [c]ourt of
    [a]ppeals on all other issues including: affirming the trial court’s
    award of $40 million in assignment fees and $9,510,795 in
    equipment fees to IBM, affirming the trial court’s denial of
    deferred fees to IBM, and reversing the trial court’s award of
    $2,570,621 in early termination close out payments and
    $10,632,333 in prejudgment interest to IBM. We also remand
    the case to the trial court to determine the amount of fees IBM is
    entitled to for Change Orders 119 and 133, and for calculation of
    the parties’ damages consistent with this opinion, including any
    appropriate offsets to the State as a result of IBM’s material
    breach of the MSA.
    State v. 
    IBM, 51 N.E.3d at 168-69
    .
    [44]   Judge Dreyer, upon remand from the supreme court, issued his “Order upon
    Remand Regarding State’s Damages,” on May 6, 2016, and ruled that “the
    evidence shows that all of the costs for which the State seeks reimbursement
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 25 of 32
    were not adequately proven and thus cannot be recovered as damages.”
    (Appellant’s App. Vol. III, p. 98) (footnotes omitted). The court held that “the
    State fail[ed] to prove damages to a reasonable certainty.” (Appellant’s App.
    Vol. III, p. 98). In response to Judge Dreyer’s damages award, the supreme
    court, on July 5, 2016, decided that “[t]he Respondents, the Marion Superior
    Court and [Judge Dreyer] are ordered to vacate all orders issued in the
    underlying case on or after May 6, 2016, and to grant the change of judge.”
    State v. Marion Superior Court, 
    54 N.E.3d 995
    (Ind. 2016). After that, the current
    trial court, presided over by Judge Welch, issued the contested Order which is
    now before us. In her order, Judge Welch ruled:
    384. In this case, the plain language of the prior trial court’s
    [order] stated that ‘judgment was entered for IBM and against the
    State.’ The Indiana Supreme Court reversed the trial court’s []
    judgment on the State’s breach of contract claim by holding that
    IBM materially breached the MSA. In conclusion, the [s]upreme
    [c]ourt ordered this [c]ourt to calculate the parties’ damages and
    any appropriate offsets which are contained in the MSA, which
    this [c]ourt takes to mean the equipment, assignment fees, and
    change order damages owed to IBM.
    385. Therefore, this [c]ourt finds that the trial court judgment in
    favor of IBM was reversed, and thus, under Indiana law, IBM is
    not entitled to post-judgment interest from the date of the prior
    trial court’s judgment entry for IBM in 2012 but rather is only
    entitled to post-judgment interest from the date of this judgment
    after this [c]ourt has conducted the offset as required by the MSA
    and as instructed by the Indiana Supreme Court.
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 26 of 32
    (Appellant’s App. Vol. III, p. 176). Judge Welch again awarded IBM $40
    million in assignment fees and $9,510,795 in equipment fees.
    [45]   This review of the convoluted proceedings clearly indicates that since Judge
    Dreyer’s first Order of July 18, 2012, the one constant in this case has been
    IBM’s award of assignment and equipment fees upon IBM’s Complaint 2 against
    the State. Although the State challenged those awards on appeal, both this
    court and the supreme court expressly affirmed that portion of the judgment on
    the combined Complaints. More specifically, unlike Judge Welch’s opinion
    that interpreted the supreme court’s opinion of March 22, 2016, as a complete
    reversal of the lower court, we find that the Indiana Supreme Court
    unequivocally “summarily affirmed the [c]ourt of [a]ppeals [on] the trial court’s
    award of $40 million in assignment fees and $9,510,795 in equipment fees to
    IBM.” 
    IBM, 51 N.E.3d at 168
    . Accordingly, as no appellate decision reversed
    IBM’s judgment on its Complaint, IBM is entitled to post-judgment interest
    “from the date of the original verdict.” See 
    Beam, 765 N.E.2d at 534
    . We
    therefore reverse the trial court and remand for calculation of the post-judgment
    interest award entered on July 18, 2012.
    CROSS-APPEAL
    2
    IBM’s Complaint originally proceeded under its own cause number and separate from the State’s
    Complaint. In its Complaint, IBM demanded damages in excess of $52 million, which included damages for
    assignment and equipment fees. Although the two filings initially proceeded under different Cause Numbers,
    the trial court consolidated both Causes and issued one single opinion, ruling on both the State’s and IBM’s
    Complaint.
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018                 Page 27 of 32
    I. Direct Damages Cap
    [46]   On Cross-Appeal, the State contends that the trial court incorrectly applied the
    direct damages cap of the MSA. In its Order, the trial court noted that “the
    MSA caps damages to the State at $125 million for direct damages and $3
    million for consequential damages.” (Appellant’s App. Vol. III, p. 170).
    [47]   Referencing the MSA, the State nevertheless contends that §17.4.1(2)(A)
    provides
    As to direct damages, which shall include Reprocurement Costs,
    an amount equal to the greater of (i) [$125,000,000] and (ii) the
    Fees paid by State to Vendor hereunder during the [12] months
    prior to the most recent Claim [], provided nothing herein shall
    relieve the State of its obligation to mitigate Reprocurement
    Costs[.]
    (Appellant’s App. Vol. V, p. 162). ‘Claim’ is contractually defined as a “claim,
    demand, cause of action, debt or liability of any kind, including a claim for
    expenses and attorney fees.” (Appellant’s App. Vol. VI, p. 38). Equating
    ‘Claim’ to the date of terminating the MSA, the State asserts that evidence was
    submitted indicating that during the 12-months preceding the October 15, 2009
    termination of the MSA, the State paid IBM at least $158 million. Accordingly,
    focusing on the second prong of §17.4.1(2)(A), the State requests us to increase
    the applicable direct damages cap to $158 million.
    [48]   At the time of termination of the MSA, the State notified IBM that its series of
    breaches would be considered material under the contract and stopped IBM’s
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 28 of 32
    services under the MSA. The State failed to submit any evidence supporting
    that a “demand, cause of action, [or] debt or liability of any kind” was made at
    that point in time. (Appellant’s App. Vol. VI, p. 38). Rather, the evidence
    supports that the earliest demand for damages was made on May 13, 2010,
    when the State filed its cause of action against IBM. Accordingly, as the State
    does not dispute that the fees paid to IBM in the 12-months preceding the date
    of termination were substantially less than $125 million, the trial court properly
    limited the direct damages cap at the greater number of $125 million.
    II. Salaries for New State Employees
    [49]   As part of its damages request, the State demanded an additional $36.5 million
    to cover the salaries of 48 new State eligibility consultants and 50 new
    management personnel. Denying the State’s request, the trial court concluded,
    in pertinent part:
    268. This presents an issue of whether these damages are
    consistent and arising from the breach. The State’s position is
    that had Modernization worked properly, then the staffing
    reduction would not have caused problems. Because
    Modernization did not work properly, the State suffered damages
    by having to rehire Staff.
    269. This [c]ourt finds that such an award would be putting the
    State in a better position than it was prior to the MSA. The State
    would essentially receive a windfall from IBM by being paid to
    return to pre-MSA staffing levels.
    270. While the State was insourcing the program, hiring forty-
    five new managers falls outside of “reasonable costs associated
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 29 of 32
    with bringing a similar service in-house,” and because they are
    new staff, their costs cannot be considered Reprocurement Costs
    as the additional hires do not support that the State was installing
    a new regime “similar to the applicable terminated Services.”
    271. These workers do not constitute a differential in between
    the fees paid under the previous Modernization regime and those
    now under Hybrid because these workers were not around under
    Modernization.
    272. These worker expenses are not reasonable costs to replace a
    terminated portion of the MSA, and they are not external
    advisors, consultants, or attorneys assisting with the
    Reprocurement. While their efforts can loosely be attributed to
    MSA § 15 “staff time costs,” hiring forty-eight full-time
    employees and additional managers goes well beyond the aims of
    in-sourcing a program previously provided by IBM and instead
    constitutes putting the State in a better position than it was prior
    to the MSA.
    (Appellant’s App. Vol. III, p. 157).
    [50]   The State contends that to make the State whole, it did not have to return to the
    system prior to Modernization; rather, it meant giving “the State the benefit of
    the MSA bargain—i.e., a Modernized system that worked[.]” (Appellee’s Br. p.
    48). Claiming to be entitled to be placed in a better position than it was prior to
    the MSA, the State maintains that this better position was the reason it entered
    into the MSA; it did not seek a windfall, merely it sought the cost of post-MSA
    staff required to make Modernization work.
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 30 of 32
    [51]   Generally, the computation of damages for a breach of contract is a matter
    within the sound discretion of the trial court. City of Jeffersonville v. Envtl. Mgmt.
    Corp., 
    954 N.E.2d 1000
    , 1015 (Ind. Ct. App. 2011). We will not reverse a
    damage award upon appeal unless it is based on insufficient evidence or is
    contrary to law. 
    Id. In determining
    whether an award is within the scope of the
    evidence, we may not reweigh the evidence or judge the credibility of witnesses.
    
    Id. However, we
    recognize that the appropriate measure of damages in a
    breach of contract case is the loss actually suffered as a result of the breach. 
    Id. The non-breaching
    party is not entitled to be placed in a better position than it
    would have been if the contract had not been broken. 
    Id. [52] The
    record contains evidence that the 48 new eligibility employees were hired
    in the spring of 2009, prior to the termination of the MSA. This additional staff
    was retained to serve Hoosiers in need in local offices in an effort to make
    Modernization work and to salvage the project. The State failed to submit any
    evidence that these costs were incurred due to IBM’s breach.
    [53]   Unlike the eligibility personnel, the 50 new management positions were created
    and filled after the termination of the MSA. The State’s damages expert
    explained that the purpose of this hire was to satisfy the State’s intent to place
    “more focus at the local county level, which required more people.” (Suppl.
    App. Vol. II, pp. 7-8). However, the goal of both Modernization and Hybrid
    was a move away from an increasing face-to face contact by the
    implementation of technology. While the State recognized that a more efficient
    level of personal contact between clients and staff had to be retained in its
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 31 of 32
    Hybrid system, the trial court found that—and we agree—the 50 new
    management positions essentially returned the State to “pre-MSA staffing
    levels.” (Appellant’s App. Vol. III, p. 157). As these new positions did not
    exist under Modernization, their costs cannot constitute a “differential”
    between the fees paid under the MSA and the replacement cost. (Appellant’s
    App. Vol. III, p. 137). Therefore, the costs of these new positions do not fall
    within the scope of Reprocurement Costs because they never constituted a
    “terminated Service[]” that the State needed to substitute from an alternative
    source after termination of the MSA. (Appellant’s App. Vol. III, p. 137).
    Accordingly, as the State is not entitled to be placed in a better position than it
    would have been if the MSA had not been breached, we affirm the trial court’s
    conclusion that the salaries for these new State employees cannot be attributed
    to IBM’s breach.
    CONCLUSION
    [54]   Based on the foregoing, we hold that the trial court did not err in its award of
    the State’s damages. However, we conclude that IBM is entitled to post-
    judgment interest on its $49.5 million damages award, and we remand to the
    trial court for calculation of the post-judgment interest.
    [55]   Affirmed in part, reversed in part, and remanded.
    [56]   May, J. and Altice, J. concur
    Court of Appeals of Indiana | Opinion 49A02-1709-PL-2006 | September 28, 2018   Page 32 of 32